ER27-500-000 · 2026-11-16 · Citizens Sycamore-Penasquitos Transmission LLC

Tariff Revisions to Address Commission's ER26-71 Order to Show Cause

Citizens Sycamore-Penasquitos Transmission LLC files tariff revisions under section 205 on November 16, 2026, in ER27-500-000, answering the CAISO show cause order. It leases part of an SDG&E line, so its revisions say SDG&E's tariff governs study, interconnection and expansion requests. The operative text matches the Citizens Sunrise filing; only the project facts differ.

Asks FERC to: Accept the revisions effective January 15, 2027, and find that Citizens Sycamore has satisfied the concerns in the show cause order.

Filed under section 205 to answer the E-10 show cause order for CAISO and its transmission owners. It sends large load study and interconnection matters to SDG&E's tariff rather than setting up a process of its own.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25)

Key points

  1. Citizens Sycamore owns none of the line. SDG&E keeps ownership, operation and maintenance.
    Citizens Sycamore does not own any of the actual facilities. SDG&E retains ownership and operation and maintenance responsibilities. PDF p. 2
  2. Its interest is a lease of under 13 percent of one segment of the project.
    Citizens Sycamore has a limited, less than 13% leasehold interest in a single segment of the overall Sycamore Project transmission line PDF p. 3
  3. It is a non-load-serving transmission owner with no end-use customers.
    Non-Load- Serving Participating TO and has no End-Use Customers PDF p. 2
  4. Study, planning, interconnection and expansion requests would be governed by SDG&E's tariff.
    any study, planning, interconnection or expansion requests related to Citizens Sycamore’s interest in the Sycamore Project will be governed by the relevant provisions of the SDG&E TO Tariff PDF p. 3
  5. New language in Sections 8, 9 and 10 repeats the point, one section at a time.
    Added new language to Section 10, Interconnection Process, to confirm that all conduct that falls under Section 10 will be governed by SDG&E’s TO Tariff PDF p. 4
  6. Definitions are revised to say SDG&E's tariff provisions govern.
    each to clarify that SDG&E’s TO Tariff provisions will govern PDF p. 4
  7. It commits to a compliance filing if CAISO or SDG&E changes its tariff in a way that affects these revisions.
    Citizens Sycamore commits to making a compliance filing to ensure its TO Tariff remains consistent PDF p. 5
  8. It asks for an effective date 60 days after filing.
    accept these TO Tariff revisions to become effective January 15, 2027, which is sixty (60) days from the date of this filing PDF p. 1

Text extracted from the eLibrary original (SHA-256 a1e051552cf64261…). Download the original from the official source.

Contents · 6 sections
  1. I. BACKGROUND ON CITIZENS SYCAMORE p. 2
  2. II. RESPONSE TO SHOW CAUSE ORDER p. 2
  3. A. Relevant Existing TO Tariff Provisions p. 3
  4. B. Proposed TO Tariff Provision Revisions p. 4
  5. III. REQUESTED EFFECTIVE DATE p. 5
  6. VIII. CONCLUSION p. 5

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Citizens Sycamore respectfully requests that the Commission accept these TO Tariff revisions to become effective January 15, 2027, which is sixty (60) days from the date of this filing. 1 CAISO et al., 195 FERC ¶61,214 (2026).
Read this passage

I. BACKGROUND ON CITIZENS SYCAMORE

printed heading

BACKGROUND ON CITIZENS SYCAMORE Citizens Sycamore is a wholly owned subsidiary of Citizens Energy Corporation, a non-profit organization dedicated to making life’s basic needs more affordable through successful business ventures.
Read this passage

II. RESPONSE TO SHOW CAUSE ORDER

printed heading

For these reasons, Citizens Sycamore proposes revisions to its TO Tariff to make clear that any study, planning, interconnection or expansion requests related to Citizens Sycamore’s interest in the Sycamore Project will be governed by the relevant provisions of the SDG&E TO Tariff.
Read this passage

A. Relevant Existing TO Tariff Provisions

printed heading

Relevant Existing TO Tariff Provisions Citizens Sycamore’s current TO Tariff recognizes the limited nature of its interest in the Sycamore Project.
Read this passage

B. Proposed TO Tariff Provision Revisions

printed heading

To the extent that the CAISO or SDG&E propose TO Tariff revisions that impact the revisions Citizens Sycamore proposes in this filing, Citizens Sycamore commits to making a compliance filing to ensure its TO Tariff remains consistent.
Read this passage

III. REQUESTED EFFECTIVE DATE

printed heading

REQUESTED EFFECTIVE DATE Citizens Sycamore requests an effective date for the revised TO Tariff of January 15, 2027.
Read this passage

VIII. CONCLUSION

printed heading

CONCLUSION Citizens Sycamore respectfully requests that the Commission accept these proposed tariff revisions effective as of January 15, 2027, and determine that Citizens Sycamore has satisfied the concerns the Commission identified in its Show Cause Order.