SCE TO Tariff Revisions-New LLIP_Sect205-OSC LL_CLEAN
Text extracted from the eLibrary original (SHA-256 0150523b07b5f9bd…). Download the original from the official source.
Contents · 92 sections
- ATTACHMENT A
- A. Site drawing showing Large Load location and Point of Interconnection
- B. Single-line diagram showing applicable equipment such as large load
- A. Rated total MW consumption and power factor of the Large Load, including
- B. Percentage of the total MW consumption of the Large Load for each of the
- C. If the Large Loadhas some form of forced cooling system, indicate what it is
- D. Motor-driven components of the cooling systems are driven by (check all
- E. Voltage sag levels and durations below which the components within the
- F. Voltage swell levels and durations above which the components within the
- G. Frequency thresholds above and below which any computing/server load
- H. Reconnection of load after voltage and frequency recover (check all that
- I. Emergency generation and battery energy storage:
- A. Arrangement and operating mode:
- B. Technology and ratings (aggregate nameplate MVA and MW for each
- C. Gross and net withdrawal and requested service:
- D. Non-export controls (for non-exporting co-located generation):
- E. Ride-through, protection, and disturbance behavior:
- F. Models and data:
- G. NERC registration:
- A. Total Generating Facility rated output (MW):
- B. Generating Facility auxiliary load (MW): _______________
- C. Net Generating Facility capacity at generator/inverter terminals (MW):
- D. Collector system losses (MW): _______________ (insert “n/a” if not
- E. Main step-up transformer losses (MW): _______________ (insert “n/a” if
- F. Net Generating Facility capacity at high-side of main step-up transformer
- G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert
- H. Net Generating Facility capacity at Point of Interconnection (MW):
- I. Standby Load when Generating Facility is off-line (MW):
- A. Rated Generator speed (rpm): ____________
- B. Rated MVA: _______________
- C. Rated Generator Power Factor: ____________
- D. Generator Efficiency at Rated Load (%): ____________
- E. Moment of Inertia (including prime mover): ____________
- F. Inertia Time Constant (on machine base) H: ____________ sec or
- G. SCR (Short-Circuit Ratio - the ratio of the field current required for
- H. Please attach generator reactive capability curves.
- I. Rated Hydrogen Cooling Pressure in psig (Steam Units only):
- A. Indicate the Manufacturer ____________________ and Type
- B. Attach a copy of the block diagram of the excitation system from its
- C. Excitation system response ratio (ASA): ______________
- D. Full load rated exciter output voltage: ___________
- E. Maximum exciter output voltage (ceiling voltage): ___________
- F. Other comments regarding the excitation system?
- A. Manufacturer:
- B. Is the PSS digital or analog?
- C. Note the input signal source for the PSS?
- D. Please attach a copy of a block diagram of the PSS from the PSS
- E. Other comments regarding the PSS?
- A. Steam, gas or combined-cycle turbines:
- B. Hydro turbines:
- C. Complete this section for each machine, independent of the turbine
- A. Motoring Power (kW): ______________
- B. I22t or K (Heating Time Constant): ______________
- C. Rotor Resistance, Rr: ______________
- D. Stator Resistance, Rs: ______________
- E. Stator Reactance, Xs: ______________
- F. Rotor Reactance, Xr: ______________
- G. Magnetizing Reactance, Xm: ______________
- H. Short Circuit Reactance, Xd'': ______________
- I. Exciting Current: ______________
- A. Number of generators to be interconnected pursuant to this
- B. Average Site Elevation: ______ Single Phase _____ Three Phase_____
- C. Field Volts: _________________
- D. Field Amperes: ______________
- E. Motoring Power (MW): _______
- F. Neutral Grounding Resistor (If Applicable): ____________
- G. I22t or K (Heating Time Constant): ____________
- H. Rotor Resistance: ____________
- I. Stator Resistance: ____________
- A. Inverter Manufacturer and Model: _________________________
- B. Number of Inverters: ___________________
- C. Nameplate Rating (AC, each inverter): _______/_______ kW
- D. Nameplate Voltage Rating (AC): _______ kV
- E. Maximum AC line current: _______ Amps
- F. Nameplate Power Factor Rating (AC): _______
- G. Please attach capability curve describing reactive power or power factor
- H. Inverter control mode (e.g. voltage, power factor, reactive power): _____
- I. Short Circuit Characteristics: Applicant to provide technical data related to
- A. Number of individual shunt capacitor banks: _____________
- B. Individual shunt capacitor bank rated voltage (kV): _____________
- C. Individual shunt capacitor bank size (kVAR at rated voltage):
- D. Planned dynamic reactive control devices (SVC, STATCOM):
- E. Control range: _____________ kVAR (lead) _____________ kVAR (lag)
- F. Control mode (e.g. voltage, power factor, reactive power):
- G. Please provide the overall plant reactive power control strategy
- A. Manufacturer and model: ____________________________________
- B. Source Functions
- C. Charging Functions
- D. Primary frequency response operating range for electric storage resources
- A. Provide load flow model for the generating plant and its interconnection
- B. For each generator, governor, exciter, power system stabilizer, WTG, or
- C. For Large Loads, the Large Load Interconnection Customer shall provide a
Topics in the text: Registry access · Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
ATTACHMENT A
printed heading
ATTACHMENT A Clean TO Tariff Sheets Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6Read this passage
TABLE OF CONTENTS
printed heading · Topic match: Connecting load and generation
Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval. 3.19 Dispatch.Read this passage
TABLE OF CONTENTS
printed heading · Topic match: Registry access
Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.Read this passage
A. Site drawing showing Large Load location and Point of Interconnection
printed heading
Site drawing showing Large Load location and Point of Interconnection with the Participating TO’s Transmission System.Read this passage
B. Single-line diagram showing applicable equipment such as large load
printed heading
This one-line drawing must be signed and stamped by a licensed Professional Engineer. 2.Read this passage
A. Rated total MW consumption and power factor of the Large Load, including
printed heading
Rated total MW consumption and power factor of the Large Load, including IT equipment, power distribution, and cooling: Total MW: _______________ Power factor: _______________Read this passage
B. Percentage of the total MW consumption of the Large Load for each of the
printed heading
Percentage of the total MW consumption of the Large Load for each of the following load components: Computing/server load: _____ % Lighting load: _____ % Power distribution losses: _____ % Cooling: _____ % Other: _____ % (describe if applicable): _______________ Does the percentage change during…Read this passage
C. If the Large Loadhas some form of forced cooling system, indicate what it is
printed heading
If the Large Loadhas some form of forced cooling system, indicate what it is comprised of (check all that apply and add details if needed): ___ Computer Room Air Conditioners (CRACs) with internal compressors: _______________ ___ Computer Room Air Handlers (CRAHs) supplied with chilled water:…Read this passage
D. Motor-driven components of the cooling systems are driven by (check all
printed heading
Motor-driven components of the cooling systems are driven by (check all that apply and add details if needed): ___ Single-speed motors operated across the line (motors connected directly to the AC supply): _______________ ___ Motors controlled by variable/adjustable speed drives or electronically…Read this passage
E. Voltage sag levels and durations below which the components within the
printed heading
Voltage sag levels and durations below which the components within the data center disconnect from the grid: (1) Computing/server load: _______________ (2) Cooling load: _______________ (3) Are voltage sags sensed per phase or on a three-phase basis for the disconnection action? _______________ (4)…Read this passage
F. Voltage swell levels and durations above which the components within the
printed heading
Voltage swell levels and durations above which the components within the data center disconnect from the grid: (1) Computing/server load: _______________ (2) Cooling load: _______________ (3) Are voltage swells sensed per phase or on a three-phase basis for the disconnection action? _______________…Read this passage
G. Frequency thresholds above and below which any computing/server load
printed heading
Frequency thresholds above and below which any computing/server load may disconnect from the grid: Above: _______________ Below: _______________Read this passage
H. Reconnection of load after voltage and frequency recover (check all that
printed heading
Reconnection of load after voltage and frequency recover (check all that apply and specify): ___ Reconnects immediately; voltage and frequency levels: _______________ Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 ___ Reconnects after a time delay; voltage and…Read this passage
I. Emergency generation and battery energy storage:
printed heading
Details of existing protection and control schemes that affect the response of the facility: _______________________________________________ K.Read this passage
A. Arrangement and operating mode:
printed heading
Arrangement and operating mode: (1) Arrangement (check one): ___ Co-located generation serving the Large Load on the generator side of the Point of Interconnection ___ Behind-the-meter generation at the Large Load’s retail meter ___ Other (describe): _______________ Southern California Edison…Read this passage
B. Technology and ratings (aggregate nameplate MVA and MW for each
printed heading
Technology and ratings (aggregate nameplate MVA and MW for each technology): ____ Combustion turbine or reciprocating engine: ____MVA / ____MW Fuel: __________ ____ Solar photovoltaic: _____ MVA / _____ MW ____ Battery energy storage: _____ MVA / _____ MW / ____ MWh Charges from the ISO Controlled…Read this passage
C. Gross and net withdrawal and requested service:
printed heading
Gross and net withdrawal and requested service: (1) Gross Large Load (MW) and gross co-located generation (MW), reported separately: _______ / _______ (2) Maximum net withdrawal from the ISO Controlled Grid with co- located generation online (MW): _______________ (3) Largest single co-located…Read this passage
D. Non-export controls (for non-exporting co-located generation):
printed heading
Non-export controls (for non-exporting co-located generation): (1) Method used to prevent export (e.g., reverse-power relay, export-limiting controls, power control system): _______________ _____________________________________________________Read this passage
E. Ride-through, protection, and disturbance behavior:
printed heading
E.Read this passage
F. Models and data:
printed heading
Models and data: (1) Power flow and dynamic models of the co-located generation and an electromagnetic transient (EMT) model if required. (2) Evidence of model verification (e.g., manufacturer attestation, test data, or commissioning measurements), with as-built model updates provided before the…Read this passage
G. NERC registration:
printed heading
NERC registration: (1) Co-located generation (check one): ___ Bulk Electric System generation (BES Inclusion I2, I3, or I4): Category 1 Generator Owner / Generator Operator ___ Non-BES inverter-based resources with aggregate nameplate capacity of 20 MVA or more connected at 60 kV or above: Category…Read this passage
A. Total Generating Facility rated output (MW):
printed heading
Total Generating Facility rated output (MW): _______________ A1.Read this passage
B. Generating Facility auxiliary load (MW): _______________
printed heading
Generating Facility auxiliary load (MW): _______________Read this passage
C. Net Generating Facility capacity at generator/inverter terminals (MW):
printed heading
Net Generating Facility capacity at generator/inverter terminals (MW): _______________ (A-B) or (A1-B)Read this passage
D. Collector system losses (MW): _______________ (insert “n/a” if not
printed heading
Collector system losses (MW): _______________ (insert “n/a” if not applicable or negligible) Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6Read this passage
E. Main step-up transformer losses (MW): _______________ (insert “n/a” if
printed heading
Main step-up transformer losses (MW): _______________ (insert “n/a” if not applicable or negligible)Read this passage
F. Net Generating Facility capacity at high-side of main step-up transformer
printed heading
Net Generating Facility capacity at high-side of main step-up transformer (MW): _______________ (C-D-E)Read this passage
G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert
printed heading
Gen-tie loss to Point of Interconnection (MW): _______________ (insert “n/a” if not applicable or negligible)Read this passage
H. Net Generating Facility capacity at Point of Interconnection (MW):
printed heading
Net Generating Facility capacity at Point of Interconnection (MW): _______________ (F-G) H1.Read this passage
I. Standby Load when Generating Facility is off-line (MW):
printed heading
Standby Load when Generating Facility is off-line (MW): _______________ J.Read this passage
A. Rated Generator speed (rpm): ____________
printed heading
A.Read this passage
B. Rated MVA: _______________
printed heading
B.Read this passage
C. Rated Generator Power Factor: ____________
printed heading
C.Read this passage
D. Generator Efficiency at Rated Load (%): ____________
printed heading
Generator Efficiency at Rated Load (%): ____________Read this passage
E. Moment of Inertia (including prime mover): ____________
printed heading
Moment of Inertia (including prime mover): ____________Read this passage
F. Inertia Time Constant (on machine base) H: ____________ sec or
printed heading
Inertia Time Constant (on machine base) H: ____________ sec or MJ/MVARead this passage
G. SCR (Short-Circuit Ratio - the ratio of the field current required for
printed heading
SCR (Short-Circuit Ratio - the ratio of the field current required for Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 rated open-circuit voltage to the field current required for rated short-circuit current): ___________________________________________Read this passage
H. Please attach generator reactive capability curves.
printed heading
Please attach generator reactive capability curves.Read this passage
I. Rated Hydrogen Cooling Pressure in psig (Steam Units only):
printed heading
Rated Hydrogen Cooling Pressure in psig (Steam Units only): ________________________________________________ J.Read this passage
A. Indicate the Manufacturer ____________________ and Type
printed heading
Indicate the Manufacturer ____________________ and Type _____________of excitation system used for the generator.Read this passage
B. Attach a copy of the block diagram of the excitation system from its
printed heading
Attach a copy of the block diagram of the excitation system from its instruction manual.Read this passage
C. Excitation system response ratio (ASA): ______________
printed heading
Excitation system response ratio (ASA): ______________Read this passage
D. Full load rated exciter output voltage: ___________
printed heading
Full load rated exciter output voltage: ___________Read this passage
E. Maximum exciter output voltage (ceiling voltage): ___________
printed heading
Maximum exciter output voltage (ceiling voltage): ___________Read this passage
F. Other comments regarding the excitation system?
printed heading
Other comments regarding the excitation system? _____________________________________________________ _____________________________________________________ 5C Power System Stabilizer (“PSS”) Information: (Please repeat the following for each generator model.Read this passage
A. Manufacturer:
printed heading
Manufacturer: _____________________________________________Read this passage
B. Is the PSS digital or analog?
printed heading
Is the PSS digital or analog? __________________________________Read this passage
C. Note the input signal source for the PSS?
printed heading
Note the input signal source for the PSS? _____ Bus frequency _____ Shaft speed _____ Bus Voltage _____________________ Other (specify source)Read this passage
D. Please attach a copy of a block diagram of the PSS from the PSS
printed heading
Please attach a copy of a block diagram of the PSS from the PSS Instruction Manual and the correspondence between dial settings and the time constants or PSS gain.Read this passage
E. Other comments regarding the PSS?
printed heading
Other comments regarding the PSS? _____________________________________________________ _____________________________________________________ _____________________________________________________ 5D Turbine-Governor Information: (Please repeat the following for each generator model.) Please…Read this passage
A. Steam, gas or combined-cycle turbines:
printed heading
A.Read this passage
B. Hydro turbines:
printed heading
Hydro turbines: (1) Turbine efficiency at rated load: _______% (2) Length of penstock: ______ft (3) Average cross-sectional area of the penstock: _______ft2 (4) Typical maximum head (vertical distance from the bottom of the penstock, at the gate, to the water level): ______ft (5) Is the water…Read this passage
C. Complete this section for each machine, independent of the turbine
printed heading
Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 • X”d – Direct Axis Subtransient Reactance: _____ p.u. • X2 – Negative Sequence Reactance: _____ p.u. • X0 – Zero Sequence Reactance: _____ p.u.Read this passage
A. Motoring Power (kW): ______________
printed heading
A.Read this passage
B. I22t or K (Heating Time Constant): ______________
printed heading
I22t or K (Heating Time Constant): ______________Read this passage
C. Rotor Resistance, Rr: ______________
printed heading
C.Read this passage
D. Stator Resistance, Rs: ______________
printed heading
D.Read this passage
E. Stator Reactance, Xs: ______________
printed heading
E.Read this passage
F. Rotor Reactance, Xr: ______________
printed heading
F.Read this passage
G. Magnetizing Reactance, Xm: ______________
printed heading
G.Read this passage
H. Short Circuit Reactance, Xd'': ______________
printed heading
H.Read this passage
I. Exciting Current: ______________
printed heading
Reactive Power Required In Vars (No Load): ______________ N.Read this passage
A. Number of generators to be interconnected pursuant to this
printed heading
Number of generators to be interconnected pursuant to this Interconnection Request: _____Read this passage
B. Average Site Elevation: ______ Single Phase _____ Three Phase_____
printed heading
Average Site Elevation: ______ Single Phase _____ Three Phase_____Read this passage
C. Field Volts: _________________
printed heading
C.Read this passage
D. Field Amperes: ______________
printed heading
D.Read this passage
E. Motoring Power (MW): _______
printed heading
E.Read this passage
F. Neutral Grounding Resistor (If Applicable): ____________
printed heading
Neutral Grounding Resistor (If Applicable): ____________Read this passage
G. I22t or K (Heating Time Constant): ____________
printed heading
I22t or K (Heating Time Constant): ____________ Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6Read this passage
H. Rotor Resistance: ____________
printed heading
H.Read this passage
I. Stator Resistance: ____________
printed heading
Total Rotating Inertia, H: ________ Per Unit on 100 MVA Base Note: A completed General Electric Company Power Systems Load Flow (PSLF) data sheet must be supplied with the Interconnection Request.Read this passage
A. Inverter Manufacturer and Model: _________________________
printed heading
Inverter Manufacturer and Model: _________________________Read this passage
B. Number of Inverters: ___________________
printed heading
B.Read this passage
C. Nameplate Rating (AC, each inverter): _______/_______ kW
printed heading
Nameplate Rating (AC, each inverter): _______/_______ kWRead this passage
D. Nameplate Voltage Rating (AC): _______ kV
printed heading
D.Read this passage
E. Maximum AC line current: _______ Amps
printed heading
E.Read this passage
F. Nameplate Power Factor Rating (AC): _______
printed heading
F.Read this passage
G. Please attach capability curve describing reactive power or power factor
printed heading
Please attach capability curve describing reactive power or power factor range from no output to full rated outputRead this passage
H. Inverter control mode (e.g. voltage, power factor, reactive power): _____
printed heading
Inverter control mode (e.g. voltage, power factor, reactive power): _____Read this passage
I. Short Circuit Characteristics: Applicant to provide technical data related to
printed heading
Short Circuit Characteristics: Applicant to provide technical data related to the short circuit characteristics of proposed inverter based generation systems.Read this passage
A. Number of individual shunt capacitor banks: _____________
printed heading
Number of individual shunt capacitor banks: _____________Read this passage
B. Individual shunt capacitor bank rated voltage (kV): _____________
printed heading
Individual shunt capacitor bank rated voltage (kV): _____________Read this passage
C. Individual shunt capacitor bank size (kVAR at rated voltage):
printed heading
Individual shunt capacitor bank size (kVAR at rated voltage): _____________Read this passage
D. Planned dynamic reactive control devices (SVC, STATCOM):
printed heading
Planned dynamic reactive control devices (SVC, STATCOM): _____________Read this passage
E. Control range: _____________ kVAR (lead) _____________ kVAR (lag)
printed heading
Control range: _____________ kVAR (lead) _____________ kVAR (lag)Read this passage
F. Control mode (e.g. voltage, power factor, reactive power):
printed heading
Control mode (e.g. voltage, power factor, reactive power): _____________Read this passage
G. Please provide the overall plant reactive power control strategy
printed heading
Please provide the overall plant reactive power control strategy 13.Read this passage
A. Manufacturer and model: ____________________________________
printed heading
Manufacturer and model: ____________________________________Read this passage
B. Source Functions
printed heading
Source Functions (1) Total storage capability: ___________________ MWh (2) Rated storage discharging power: ___________________ MW (3) Maximum storage discharging power: ________________ MW If the maximum storage discharging power is less than the rated storage discharging power, specify the…Read this passage
C. Charging Functions
printed heading
C.Read this passage
D. Primary frequency response operating range for electric storage resources
printed heading
Each Large Load shall provide the load flow and dynamic model data specified in Item C of this section, in addition to the information in Items A and B for any co-located generation.Read this passage
A. Provide load flow model for the generating plant and its interconnection
printed heading
Provide load flow model for the generating plant and its interconnection facilities in GE PSLF *.epc format, including new buses, generators, transformers, interconnection facilities.Read this passage
B. For each generator, governor, exciter, power system stabilizer, WTG, or
printed heading
For each generator, governor, exciter, power system stabilizer, WTG, or inverter based generator, select the appropriate dynamic models from the General Electric PSLF Program Manual and provide the required input data.Read this passage
C. For Large Loads, the Large Load Interconnection Customer shall provide a
printed heading · Topic match: Credit and exit
Confidential Information shall be treated in accordance with LLIP Section 7.1. 13.3 Binding Effect.Read this passage
TABLE OF CONTENTS
printed heading · Topic match: Registry access
Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 for any release of Confidential Information in contravention of this Article 22. 22.1.4…Read this passage