ER27-508-000 · 2026-11-16 · Southern California Edison Company

SCE TO Tariff Revisions-New LLIP_Sect205-OSC LL_CLEAN

Text extracted from the eLibrary original (SHA-256 0150523b07b5f9bd…). Download the original from the official source.

Contents · 92 sections
  1. ATTACHMENT A p. 1
  2. A. Site drawing showing Large Load location and Point of Interconnection p. 98
  3. B. Single-line diagram showing applicable equipment such as large load p. 98
  4. A. Rated total MW consumption and power factor of the Large Load, including p. 98
  5. B. Percentage of the total MW consumption of the Large Load for each of the p. 98
  6. C. If the Large Loadhas some form of forced cooling system, indicate what it is p. 99
  7. D. Motor-driven components of the cooling systems are driven by (check all p. 99
  8. E. Voltage sag levels and durations below which the components within the p. 99
  9. F. Voltage swell levels and durations above which the components within the p. 99
  10. G. Frequency thresholds above and below which any computing/server load p. 99
  11. H. Reconnection of load after voltage and frequency recover (check all that p. 99
  12. I. Emergency generation and battery energy storage: p. 100
  13. A. Arrangement and operating mode: p. 100
  14. B. Technology and ratings (aggregate nameplate MVA and MW for each p. 101
  15. C. Gross and net withdrawal and requested service: p. 101
  16. D. Non-export controls (for non-exporting co-located generation): p. 101
  17. E. Ride-through, protection, and disturbance behavior: p. 101
  18. F. Models and data: p. 102
  19. G. NERC registration: p. 102
  20. A. Total Generating Facility rated output (MW): p. 102
  21. B. Generating Facility auxiliary load (MW): _______________ p. 102
  22. C. Net Generating Facility capacity at generator/inverter terminals (MW): p. 102
  23. D. Collector system losses (MW): _______________ (insert “n/a” if not p. 102
  24. E. Main step-up transformer losses (MW): _______________ (insert “n/a” if p. 103
  25. F. Net Generating Facility capacity at high-side of main step-up transformer p. 103
  26. G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert p. 103
  27. H. Net Generating Facility capacity at Point of Interconnection (MW): p. 103
  28. I. Standby Load when Generating Facility is off-line (MW): p. 103
  29. A. Rated Generator speed (rpm): ____________ p. 103
  30. B. Rated MVA: _______________ p. 103
  31. C. Rated Generator Power Factor: ____________ p. 103
  32. D. Generator Efficiency at Rated Load (%): ____________ p. 103
  33. E. Moment of Inertia (including prime mover): ____________ p. 103
  34. F. Inertia Time Constant (on machine base) H: ____________ sec or p. 103
  35. G. SCR (Short-Circuit Ratio - the ratio of the field current required for p. 103
  36. H. Please attach generator reactive capability curves. p. 104
  37. I. Rated Hydrogen Cooling Pressure in psig (Steam Units only): p. 104
  38. A. Indicate the Manufacturer ____________________ and Type p. 104
  39. B. Attach a copy of the block diagram of the excitation system from its p. 104
  40. C. Excitation system response ratio (ASA): ______________ p. 105
  41. D. Full load rated exciter output voltage: ___________ p. 105
  42. E. Maximum exciter output voltage (ceiling voltage): ___________ p. 105
  43. F. Other comments regarding the excitation system? p. 105
  44. A. Manufacturer: p. 105
  45. B. Is the PSS digital or analog? p. 105
  46. C. Note the input signal source for the PSS? p. 105
  47. D. Please attach a copy of a block diagram of the PSS from the PSS p. 105
  48. E. Other comments regarding the PSS? p. 105
  49. A. Steam, gas or combined-cycle turbines: p. 105
  50. B. Hydro turbines: p. 106
  51. C. Complete this section for each machine, independent of the turbine p. 106
  52. A. Motoring Power (kW): ______________ p. 107
  53. B. I22t or K (Heating Time Constant): ______________ p. 107
  54. C. Rotor Resistance, Rr: ______________ p. 107
  55. D. Stator Resistance, Rs: ______________ p. 107
  56. E. Stator Reactance, Xs: ______________ p. 107
  57. F. Rotor Reactance, Xr: ______________ p. 107
  58. G. Magnetizing Reactance, Xm: ______________ p. 107
  59. H. Short Circuit Reactance, Xd'': ______________ p. 107
  60. I. Exciting Current: ______________ p. 107
  61. A. Number of generators to be interconnected pursuant to this p. 107
  62. B. Average Site Elevation: ______ Single Phase _____ Three Phase_____ p. 107
  63. C. Field Volts: _________________ p. 107
  64. D. Field Amperes: ______________ p. 107
  65. E. Motoring Power (MW): _______ p. 107
  66. F. Neutral Grounding Resistor (If Applicable): ____________ p. 107
  67. G. I22t or K (Heating Time Constant): ____________ p. 107
  68. H. Rotor Resistance: ____________ p. 108
  69. I. Stator Resistance: ____________ p. 108
  70. A. Inverter Manufacturer and Model: _________________________ p. 108
  71. B. Number of Inverters: ___________________ p. 108
  72. C. Nameplate Rating (AC, each inverter): _______/_______ kW p. 108
  73. D. Nameplate Voltage Rating (AC): _______ kV p. 108
  74. E. Maximum AC line current: _______ Amps p. 108
  75. F. Nameplate Power Factor Rating (AC): _______ p. 108
  76. G. Please attach capability curve describing reactive power or power factor p. 108
  77. H. Inverter control mode (e.g. voltage, power factor, reactive power): _____ p. 108
  78. I. Short Circuit Characteristics: Applicant to provide technical data related to p. 108
  79. A. Number of individual shunt capacitor banks: _____________ p. 112
  80. B. Individual shunt capacitor bank rated voltage (kV): _____________ p. 112
  81. C. Individual shunt capacitor bank size (kVAR at rated voltage): p. 112
  82. D. Planned dynamic reactive control devices (SVC, STATCOM): p. 112
  83. E. Control range: _____________ kVAR (lead) _____________ kVAR (lag) p. 112
  84. F. Control mode (e.g. voltage, power factor, reactive power): p. 112
  85. G. Please provide the overall plant reactive power control strategy p. 112
  86. A. Manufacturer and model: ____________________________________ p. 112
  87. B. Source Functions p. 112
  88. C. Charging Functions p. 112
  89. D. Primary frequency response operating range for electric storage resources p. 113
  90. A. Provide load flow model for the generating plant and its interconnection p. 113
  91. B. For each generator, governor, exciter, power system stabilizer, WTG, or p. 113
  92. C. For Large Loads, the Large Load Interconnection Customer shall provide a p. 113

Read the parent filing

Topics in the text: Registry access · Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

ATTACHMENT A

printed heading

ATTACHMENT A Clean TO Tariff Sheets Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Connecting load and generation

Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval. 3.19 Dispatch.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.
Read this passage

A. Site drawing showing Large Load location and Point of Interconnection

printed heading

Site drawing showing Large Load location and Point of Interconnection with the Participating TO’s Transmission System.
Read this passage

B. Single-line diagram showing applicable equipment such as large load

printed heading

This one-line drawing must be signed and stamped by a licensed Professional Engineer. 2.
Read this passage

A. Rated total MW consumption and power factor of the Large Load, including

printed heading

Rated total MW consumption and power factor of the Large Load, including IT equipment, power distribution, and cooling: Total MW: _______________ Power factor: _______________
Read this passage

B. Percentage of the total MW consumption of the Large Load for each of the

printed heading

Percentage of the total MW consumption of the Large Load for each of the following load components: Computing/server load: _____ % Lighting load: _____ % Power distribution losses: _____ % Cooling: _____ % Other: _____ % (describe if applicable): _______________ Does the percentage change during…
Read this passage

C. If the Large Loadhas some form of forced cooling system, indicate what it is

printed heading

If the Large Loadhas some form of forced cooling system, indicate what it is comprised of (check all that apply and add details if needed): ___ Computer Room Air Conditioners (CRACs) with internal compressors: _______________ ___ Computer Room Air Handlers (CRAHs) supplied with chilled water:…
Read this passage

D. Motor-driven components of the cooling systems are driven by (check all

printed heading

Motor-driven components of the cooling systems are driven by (check all that apply and add details if needed): ___ Single-speed motors operated across the line (motors connected directly to the AC supply): _______________ ___ Motors controlled by variable/adjustable speed drives or electronically…
Read this passage

E. Voltage sag levels and durations below which the components within the

printed heading

Voltage sag levels and durations below which the components within the data center disconnect from the grid: (1) Computing/server load: _______________ (2) Cooling load: _______________ (3) Are voltage sags sensed per phase or on a three-phase basis for the disconnection action? _______________ (4)…
Read this passage

F. Voltage swell levels and durations above which the components within the

printed heading

Voltage swell levels and durations above which the components within the data center disconnect from the grid: (1) Computing/server load: _______________ (2) Cooling load: _______________ (3) Are voltage swells sensed per phase or on a three-phase basis for the disconnection action? _______________…
Read this passage

G. Frequency thresholds above and below which any computing/server load

printed heading

Frequency thresholds above and below which any computing/server load may disconnect from the grid: Above: _______________ Below: _______________
Read this passage

H. Reconnection of load after voltage and frequency recover (check all that

printed heading

Reconnection of load after voltage and frequency recover (check all that apply and specify): ___ Reconnects immediately; voltage and frequency levels: _______________ Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 ___ Reconnects after a time delay; voltage and…
Read this passage

I. Emergency generation and battery energy storage:

printed heading

Details of existing protection and control schemes that affect the response of the facility: _______________________________________________ K.
Read this passage

A. Arrangement and operating mode:

printed heading

Arrangement and operating mode: (1) Arrangement (check one): ___ Co-located generation serving the Large Load on the generator side of the Point of Interconnection ___ Behind-the-meter generation at the Large Load’s retail meter ___ Other (describe): _______________ Southern California Edison…
Read this passage

B. Technology and ratings (aggregate nameplate MVA and MW for each

printed heading

Technology and ratings (aggregate nameplate MVA and MW for each technology): ____ Combustion turbine or reciprocating engine: ____MVA / ____MW Fuel: __________ ____ Solar photovoltaic: _____ MVA / _____ MW ____ Battery energy storage: _____ MVA / _____ MW / ____ MWh Charges from the ISO Controlled…
Read this passage

C. Gross and net withdrawal and requested service:

printed heading

Gross and net withdrawal and requested service: (1) Gross Large Load (MW) and gross co-located generation (MW), reported separately: _______ / _______ (2) Maximum net withdrawal from the ISO Controlled Grid with co- located generation online (MW): _______________ (3) Largest single co-located…
Read this passage

D. Non-export controls (for non-exporting co-located generation):

printed heading

Non-export controls (for non-exporting co-located generation): (1) Method used to prevent export (e.g., reverse-power relay, export-limiting controls, power control system): _______________ _____________________________________________________
Read this passage

E. Ride-through, protection, and disturbance behavior:

printed heading

E.
Read this passage

F. Models and data:

printed heading

Models and data: (1) Power flow and dynamic models of the co-located generation and an electromagnetic transient (EMT) model if required. (2) Evidence of model verification (e.g., manufacturer attestation, test data, or commissioning measurements), with as-built model updates provided before the…
Read this passage

G. NERC registration:

printed heading

NERC registration: (1) Co-located generation (check one): ___ Bulk Electric System generation (BES Inclusion I2, I3, or I4): Category 1 Generator Owner / Generator Operator ___ Non-BES inverter-based resources with aggregate nameplate capacity of 20 MVA or more connected at 60 kV or above: Category…
Read this passage

A. Total Generating Facility rated output (MW):

printed heading

Total Generating Facility rated output (MW): _______________ A1.
Read this passage

B. Generating Facility auxiliary load (MW): _______________

printed heading

Generating Facility auxiliary load (MW): _______________
Read this passage

C. Net Generating Facility capacity at generator/inverter terminals (MW):

printed heading

Net Generating Facility capacity at generator/inverter terminals (MW): _______________ (A-B) or (A1-B)
Read this passage

D. Collector system losses (MW): _______________ (insert “n/a” if not

printed heading

Collector system losses (MW): _______________ (insert “n/a” if not applicable or negligible) Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

E. Main step-up transformer losses (MW): _______________ (insert “n/a” if

printed heading

Main step-up transformer losses (MW): _______________ (insert “n/a” if not applicable or negligible)
Read this passage

F. Net Generating Facility capacity at high-side of main step-up transformer

printed heading

Net Generating Facility capacity at high-side of main step-up transformer (MW): _______________ (C-D-E)
Read this passage

G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert

printed heading

Gen-tie loss to Point of Interconnection (MW): _______________ (insert “n/a” if not applicable or negligible)
Read this passage

H. Net Generating Facility capacity at Point of Interconnection (MW):

printed heading

Net Generating Facility capacity at Point of Interconnection (MW): _______________ (F-G) H1.
Read this passage

I. Standby Load when Generating Facility is off-line (MW):

printed heading

Standby Load when Generating Facility is off-line (MW): _______________ J.
Read this passage

A. Rated Generator speed (rpm): ____________

printed heading

A.
Read this passage

B. Rated MVA: _______________

printed heading

B.
Read this passage

C. Rated Generator Power Factor: ____________

printed heading

C.
Read this passage

D. Generator Efficiency at Rated Load (%): ____________

printed heading

Generator Efficiency at Rated Load (%): ____________
Read this passage

E. Moment of Inertia (including prime mover): ____________

printed heading

Moment of Inertia (including prime mover): ____________
Read this passage

F. Inertia Time Constant (on machine base) H: ____________ sec or

printed heading

Inertia Time Constant (on machine base) H: ____________ sec or MJ/MVA
Read this passage

G. SCR (Short-Circuit Ratio - the ratio of the field current required for

printed heading

SCR (Short-Circuit Ratio - the ratio of the field current required for Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 rated open-circuit voltage to the field current required for rated short-circuit current): ___________________________________________
Read this passage

H. Please attach generator reactive capability curves.

printed heading

Please attach generator reactive capability curves.
Read this passage

I. Rated Hydrogen Cooling Pressure in psig (Steam Units only):

printed heading

Rated Hydrogen Cooling Pressure in psig (Steam Units only): ________________________________________________ J.
Read this passage

A. Indicate the Manufacturer ____________________ and Type

printed heading

Indicate the Manufacturer ____________________ and Type _____________of excitation system used for the generator.
Read this passage

B. Attach a copy of the block diagram of the excitation system from its

printed heading

Attach a copy of the block diagram of the excitation system from its instruction manual.
Read this passage

C. Excitation system response ratio (ASA): ______________

printed heading

Excitation system response ratio (ASA): ______________
Read this passage

D. Full load rated exciter output voltage: ___________

printed heading

Full load rated exciter output voltage: ___________
Read this passage

E. Maximum exciter output voltage (ceiling voltage): ___________

printed heading

Maximum exciter output voltage (ceiling voltage): ___________
Read this passage

F. Other comments regarding the excitation system?

printed heading

Other comments regarding the excitation system? _____________________________________________________ _____________________________________________________ 5C Power System Stabilizer (“PSS”) Information: (Please repeat the following for each generator model.
Read this passage

A. Manufacturer:

printed heading

Manufacturer: _____________________________________________
Read this passage

B. Is the PSS digital or analog?

printed heading

Is the PSS digital or analog? __________________________________
Read this passage

C. Note the input signal source for the PSS?

printed heading

Note the input signal source for the PSS? _____ Bus frequency _____ Shaft speed _____ Bus Voltage _____________________ Other (specify source)
Read this passage

D. Please attach a copy of a block diagram of the PSS from the PSS

printed heading

Please attach a copy of a block diagram of the PSS from the PSS Instruction Manual and the correspondence between dial settings and the time constants or PSS gain.
Read this passage

E. Other comments regarding the PSS?

printed heading

Other comments regarding the PSS? _____________________________________________________ _____________________________________________________ _____________________________________________________ 5D Turbine-Governor Information: (Please repeat the following for each generator model.) Please…
Read this passage

A. Steam, gas or combined-cycle turbines:

printed heading

A.
Read this passage

B. Hydro turbines:

printed heading

Hydro turbines: (1) Turbine efficiency at rated load: _______% (2) Length of penstock: ______ft (3) Average cross-sectional area of the penstock: _______ft2 (4) Typical maximum head (vertical distance from the bottom of the penstock, at the gate, to the water level): ______ft (5) Is the water…
Read this passage

C. Complete this section for each machine, independent of the turbine

printed heading

Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 • X”d – Direct Axis Subtransient Reactance: _____ p.u. • X2 – Negative Sequence Reactance: _____ p.u. • X0 – Zero Sequence Reactance: _____ p.u.
Read this passage

A. Motoring Power (kW): ______________

printed heading

A.
Read this passage

B. I22t or K (Heating Time Constant): ______________

printed heading

I22t or K (Heating Time Constant): ______________
Read this passage

C. Rotor Resistance, Rr: ______________

printed heading

C.
Read this passage

D. Stator Resistance, Rs: ______________

printed heading

D.
Read this passage

E. Stator Reactance, Xs: ______________

printed heading

E.
Read this passage

F. Rotor Reactance, Xr: ______________

printed heading

F.
Read this passage

G. Magnetizing Reactance, Xm: ______________

printed heading

G.
Read this passage

H. Short Circuit Reactance, Xd'': ______________

printed heading

H.
Read this passage

I. Exciting Current: ______________

printed heading

Reactive Power Required In Vars (No Load): ______________ N.
Read this passage

A. Number of generators to be interconnected pursuant to this

printed heading

Number of generators to be interconnected pursuant to this Interconnection Request: _____
Read this passage

B. Average Site Elevation: ______ Single Phase _____ Three Phase_____

printed heading

Average Site Elevation: ______ Single Phase _____ Three Phase_____
Read this passage

C. Field Volts: _________________

printed heading

C.
Read this passage

D. Field Amperes: ______________

printed heading

D.
Read this passage

E. Motoring Power (MW): _______

printed heading

E.
Read this passage

F. Neutral Grounding Resistor (If Applicable): ____________

printed heading

Neutral Grounding Resistor (If Applicable): ____________
Read this passage

G. I22t or K (Heating Time Constant): ____________

printed heading

I22t or K (Heating Time Constant): ____________ Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

H. Rotor Resistance: ____________

printed heading

H.
Read this passage

I. Stator Resistance: ____________

printed heading

Total Rotating Inertia, H: ________ Per Unit on 100 MVA Base Note: A completed General Electric Company Power Systems Load Flow (PSLF) data sheet must be supplied with the Interconnection Request.
Read this passage

A. Inverter Manufacturer and Model: _________________________

printed heading

Inverter Manufacturer and Model: _________________________
Read this passage

B. Number of Inverters: ___________________

printed heading

B.
Read this passage

C. Nameplate Rating (AC, each inverter): _______/_______ kW

printed heading

Nameplate Rating (AC, each inverter): _______/_______ kW
Read this passage

D. Nameplate Voltage Rating (AC): _______ kV

printed heading

D.
Read this passage

E. Maximum AC line current: _______ Amps

printed heading

E.
Read this passage

F. Nameplate Power Factor Rating (AC): _______

printed heading

F.
Read this passage

G. Please attach capability curve describing reactive power or power factor

printed heading

Please attach capability curve describing reactive power or power factor range from no output to full rated output
Read this passage

H. Inverter control mode (e.g. voltage, power factor, reactive power): _____

printed heading

Inverter control mode (e.g. voltage, power factor, reactive power): _____
Read this passage

I. Short Circuit Characteristics: Applicant to provide technical data related to

printed heading

Short Circuit Characteristics: Applicant to provide technical data related to the short circuit characteristics of proposed inverter based generation systems.
Read this passage

A. Number of individual shunt capacitor banks: _____________

printed heading

Number of individual shunt capacitor banks: _____________
Read this passage

B. Individual shunt capacitor bank rated voltage (kV): _____________

printed heading

Individual shunt capacitor bank rated voltage (kV): _____________
Read this passage

C. Individual shunt capacitor bank size (kVAR at rated voltage):

printed heading

Individual shunt capacitor bank size (kVAR at rated voltage): _____________
Read this passage

D. Planned dynamic reactive control devices (SVC, STATCOM):

printed heading

Planned dynamic reactive control devices (SVC, STATCOM): _____________
Read this passage

E. Control range: _____________ kVAR (lead) _____________ kVAR (lag)

printed heading

Control range: _____________ kVAR (lead) _____________ kVAR (lag)
Read this passage

F. Control mode (e.g. voltage, power factor, reactive power):

printed heading

Control mode (e.g. voltage, power factor, reactive power): _____________
Read this passage

G. Please provide the overall plant reactive power control strategy

printed heading

Please provide the overall plant reactive power control strategy 13.
Read this passage

A. Manufacturer and model: ____________________________________

printed heading

Manufacturer and model: ____________________________________
Read this passage

B. Source Functions

printed heading

Source Functions (1) Total storage capability: ___________________ MWh (2) Rated storage discharging power: ___________________ MW (3) Maximum storage discharging power: ________________ MW If the maximum storage discharging power is less than the rated storage discharging power, specify the…
Read this passage

C. Charging Functions

printed heading

C.
Read this passage

D. Primary frequency response operating range for electric storage resources

printed heading

Each Large Load shall provide the load flow and dynamic model data specified in Item C of this section, in addition to the information in Items A and B for any co-located generation.
Read this passage

A. Provide load flow model for the generating plant and its interconnection

printed heading

Provide load flow model for the generating plant and its interconnection facilities in GE PSLF *.epc format, including new buses, generators, transformers, interconnection facilities.
Read this passage

B. For each generator, governor, exciter, power system stabilizer, WTG, or

printed heading

For each generator, governor, exciter, power system stabilizer, WTG, or inverter based generator, select the appropriate dynamic models from the General Electric PSLF Program Manual and provide the required input data.
Read this passage

C. For Large Loads, the Large Load Interconnection Customer shall provide a

printed heading · Topic match: Credit and exit

Confidential Information shall be treated in accordance with LLIP Section 7.1. 13.3 Binding Effect.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 for any release of Confidential Information in contravention of this Article 22. 22.1.4…
Read this passage