ER27-508-000 · 2026-11-16 · Southern California Edison Company

SCE OSC - Large Load, TOT Revisions

Southern California Edison files tariff revisions under section 205 on November 16, 2026, in ER27-508-000, answering the CAISO show cause order. A new Appendix XV sets large load interconnection procedures, with a study deposit, a 15-year minimum revenue obligation backed by security, exit fees and a curtailable interim service. More than 250 pages of tariff sheets follow the letter.

Asks FERC to: Accept the revisions as filed, effective February 16, 2027, and rescind the show cause order as to SCE's tariff.

Filed under section 205 to answer the E-10 show cause order for SCE's own transmission owner tariff. SCE says it covers the application, cost shifting and flexible service items and expects other owners' tariffs to differ.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62)

Key points

  1. SCE takes CAISO's 50 MW definition into its tariff.
    SCE proposes to incorporate the CAISO’s definition of “Large Load” into its TO Tariff PDF p. 7
  2. A new appendix holds the large load interconnection procedures.
    SCE proposes to create a new Appendix titled the Large Load Interconnection Procedures (“LLIP”) to augment existing TO Tariff interconnection and cost responsibility sections PDF p. 5
  3. A request needs a $250,000 study deposit and a readiness deposit of twice that.
    an Interconnection Study Deposit of $250,000, a Commercial Readiness Deposit equal to two times the study deposit PDF p. 10
  4. The same transmission rules apply to SCE's own retail large load customers.
    SCE’s LLIP thus applies the same transmission-related requirements to SCE’s own Large Load retail transmission customers as it does to Eligible Customers seeking to interconnect on behalf of Large Loads PDF p. 9
  5. A 15-year minimum revenue obligation backed by five years of security protects against stranded network upgrade costs.
    a 15-year minimum transmission revenue obligation backed by 5 years of security PDF p. 22
  6. Early termination after service starts costs the customer all remaining required security.
    early termination triggers an Exit Fee equal to all remaining required security, including the MARO security, due within 30 Business Days PDF p. 24
  7. Curtailment terms for the interim service sit in an appendix to the security and reliability agreement.
    the conditions and limitations applicable to FILI service, including curtailments, are specified in Appendix E to the TSRA PDF p. 17
  8. SCE says the California owners should not be expected to file uniform tariffs.
    SCE believes uniformity in the PTOs’ tariffs should not be expected PDF p. 3

Text extracted from the eLibrary original (SHA-256 f5d7ac378d4dff75…). Download the original from the official source.

Contents · 106 sections
  1. I. BACKGROUND p. 2
  2. II. RESPONSE TO SHOW CAUSE ORDER p. 4
  3. A. APPLICATION PROCESS, STUDY PROCEDURES, AND ONGOING p. 6
  4. B. COST SHIFTING MITIGATION p. 19
  5. C. FLEXIBLE SERVICE p. 26
  6. D. PROXIMATE LARGE LOAD AND CO-LOCATED LOAD p. 28
  7. E. SUMMARY OF OTHER PROPOSED TARIFF CHANGES p. 33
  8. III. EFFECTIVE DATE p. 34
  9. IV. CONTENTS OF FILING p. 34
  10. V. OTHER FILING REQUIREMENTS p. 34
  11. VI. CORRESPONDENCE p. 35
  12. VII. NOTICE p. 35
  13. VIII. CONCLUSION p. 36
  14. ATTACHMENT A p. 37
  15. A. Site drawing showing Large Load location and Point of Interconnection p. 134
  16. B. Single-line diagram showing applicable equipment such as large load p. 134
  17. A. Rated total MW consumption and power factor of the Large Load, including p. 134
  18. B. Percentage of the total MW consumption of the Large Load for each of the p. 134
  19. C. If the Large Loadhas some form of forced cooling system, indicate what it is p. 135
  20. D. Motor-driven components of the cooling systems are driven by (check all p. 135
  21. E. Voltage sag levels and durations below which the components within the p. 135
  22. F. Voltage swell levels and durations above which the components within the p. 135
  23. G. Frequency thresholds above and below which any computing/server load p. 135
  24. H. Reconnection of load after voltage and frequency recover (check all that p. 135
  25. I. Emergency generation and battery energy storage: p. 136
  26. A. Arrangement and operating mode: p. 136
  27. B. Technology and ratings (aggregate nameplate MVA and MW for each p. 137
  28. C. Gross and net withdrawal and requested service: p. 137
  29. D. Non-export controls (for non-exporting co-located generation): p. 137
  30. E. Ride-through, protection, and disturbance behavior: p. 137
  31. F. Models and data: p. 138
  32. G. NERC registration: p. 138
  33. A. Total Generating Facility rated output (MW): p. 138
  34. B. Generating Facility auxiliary load (MW): _______________ p. 138
  35. C. Net Generating Facility capacity at generator/inverter terminals (MW): p. 138
  36. D. Collector system losses (MW): _______________ (insert “n/a” if not p. 138
  37. E. Main step-up transformer losses (MW): _______________ (insert “n/a” if p. 139
  38. F. Net Generating Facility capacity at high-side of main step-up transformer p. 139
  39. G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert p. 139
  40. H. Net Generating Facility capacity at Point of Interconnection (MW): p. 139
  41. I. Standby Load when Generating Facility is off-line (MW): p. 139
  42. A. Rated Generator speed (rpm): ____________ p. 139
  43. B. Rated MVA: _______________ p. 139
  44. C. Rated Generator Power Factor: ____________ p. 139
  45. D. Generator Efficiency at Rated Load (%): ____________ p. 139
  46. E. Moment of Inertia (including prime mover): ____________ p. 139
  47. F. Inertia Time Constant (on machine base) H: ____________ sec or p. 139
  48. G. SCR (Short-Circuit Ratio - the ratio of the field current required for p. 139
  49. H. Please attach generator reactive capability curves. p. 140
  50. I. Rated Hydrogen Cooling Pressure in psig (Steam Units only): p. 140
  51. A. Indicate the Manufacturer ____________________ and Type p. 140
  52. B. Attach a copy of the block diagram of the excitation system from its p. 140
  53. C. Excitation system response ratio (ASA): ______________ p. 141
  54. D. Full load rated exciter output voltage: ___________ p. 141
  55. E. Maximum exciter output voltage (ceiling voltage): ___________ p. 141
  56. F. Other comments regarding the excitation system? p. 141
  57. A. Manufacturer: p. 141
  58. B. Is the PSS digital or analog? p. 141
  59. C. Note the input signal source for the PSS? p. 141
  60. D. Please attach a copy of a block diagram of the PSS from the PSS p. 141
  61. E. Other comments regarding the PSS? p. 141
  62. A. Steam, gas or combined-cycle turbines: p. 141
  63. B. Hydro turbines: p. 142
  64. C. Complete this section for each machine, independent of the turbine p. 142
  65. A. Motoring Power (kW): ______________ p. 143
  66. B. I22t or K (Heating Time Constant): ______________ p. 143
  67. C. Rotor Resistance, Rr: ______________ p. 143
  68. D. Stator Resistance, Rs: ______________ p. 143
  69. E. Stator Reactance, Xs: ______________ p. 143
  70. F. Rotor Reactance, Xr: ______________ p. 143
  71. G. Magnetizing Reactance, Xm: ______________ p. 143
  72. H. Short Circuit Reactance, Xd'': ______________ p. 143
  73. I. Exciting Current: ______________ p. 143
  74. A. Number of generators to be interconnected pursuant to this p. 143
  75. B. Average Site Elevation: ______ Single Phase _____ Three Phase_____ p. 143
  76. C. Field Volts: _________________ p. 143
  77. D. Field Amperes: ______________ p. 143
  78. E. Motoring Power (MW): _______ p. 143
  79. F. Neutral Grounding Resistor (If Applicable): ____________ p. 143
  80. G. I22t or K (Heating Time Constant): ____________ p. 143
  81. H. Rotor Resistance: ____________ p. 144
  82. I. Stator Resistance: ____________ p. 144
  83. A. Inverter Manufacturer and Model: _________________________ p. 144
  84. B. Number of Inverters: ___________________ p. 144
  85. C. Nameplate Rating (AC, each inverter): _______/_______ kW p. 144
  86. D. Nameplate Voltage Rating (AC): _______ kV p. 144
  87. E. Maximum AC line current: _______ Amps p. 144
  88. F. Nameplate Power Factor Rating (AC): _______ p. 144
  89. G. Please attach capability curve describing reactive power or power factor p. 144
  90. H. Inverter control mode (e.g. voltage, power factor, reactive power): _____ p. 144
  91. I. Short Circuit Characteristics: Applicant to provide technical data related to p. 144
  92. A. Number of individual shunt capacitor banks: _____________ p. 148
  93. B. Individual shunt capacitor bank rated voltage (kV): _____________ p. 148
  94. C. Individual shunt capacitor bank size (kVAR at rated voltage): p. 148
  95. D. Planned dynamic reactive control devices (SVC, STATCOM): p. 148
  96. E. Control range: _____________ kVAR (lead) _____________ kVAR (lag) p. 148
  97. F. Control mode (e.g. voltage, power factor, reactive power): p. 148
  98. G. Please provide the overall plant reactive power control strategy p. 148
  99. A. Manufacturer and model: ____________________________________ p. 148
  100. B. Source Functions p. 148
  101. C. Charging Functions p. 148
  102. D. Primary frequency response operating range for electric storage resources p. 149
  103. A. Provide load flow model for the generating plant and its interconnection p. 149
  104. B. For each generator, governor, exciter, power system stabilizer, WTG, or p. 149
  105. C. For Large Loads, the Large Load Interconnection Customer shall provide a p. 149
  106. ATTACHMENT B p. 236

Topics in the text: Registry access · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Jeffrey Nelson Director, FERC Rates & Market Integration P.O.
Read this passage

I. BACKGROUND

printed heading · Topic match: Cost allocation

SCE appreciates that the ISOs/RTOs have significant regional differences that must be recognized.
Read this passage

II. RESPONSE TO SHOW CAUSE ORDER

printed heading · Topic match: Cost allocation

Reese, Secretary Federal Energy Regulatory Commission Page 5 November 16, 2026 5 (e) the rates, terms, and conditions of service applicable to interconnection customers serving electrically proximate large load or co-located load[.] In this filing, SCE proposes revisions to its TO Tariff in…
Read this passage

A. APPLICATION PROCESS, STUDY PROCEDURES, AND ONGOING

printed heading · Topic match: Cost allocation

Within 30 Calendar Days after receiving the final study report, the customer must increase its Commercial Readiness Deposit to 20% of its Large Load Network Upgrade cost assignment identified in the study, or its Interconnection Request will be deemed withdrawn (LLIP Section 4.6.1.4).
Read this passage

B. COST SHIFTING MITIGATION

printed heading · Topic match: Cost allocation

COST SHIFTING MITIGATION Order Section B (“Cost Shifting Risk Among Transmission Customers”) preliminarily found that CAISO’s Tariff and/or the TO Tariffs appear to be unjust and unreasonable because they lack adequate mechanisms to mitigate the risk of cost shifting among transmission Ms.
Read this passage

C. FLEXIBLE SERVICE

printed heading · Topic match: Connecting load and generation

Tariff Changes to Implement New Flexible Interim Interconnection Service SCE proposes tariff changes to implement FILI, which the LLIP defines as curtailable, interim transmission interconnection service for a Large Load, provided by the CAISO and the Participating TO, that enables the Large Load…
Read this passage

D. PROXIMATE LARGE LOAD AND CO-LOCATED LOAD

printed heading · Topic match: Connecting load and generation

PROXIMATE LARGE LOAD AND CO-LOCATED LOAD In Section E (“Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load”), the Order found that that the CAISO tariff appears to be unjust and unreasonable because it does not contain provisions allowing an interconnection…
Read this passage

E. SUMMARY OF OTHER PROPOSED TARIFF CHANGES

printed heading

Section 10.1 has been revised to indicate that requests for interconnection on behalf of Large Loads are governed by Appendix XV rather than the existing wholesale load procedures. ix.
Read this passage

III. EFFECTIVE DATE

printed heading

EFFECTIVE DATE SCE requests that the Commission accept the tariff revisions submitted in this compliance filing effective as of February 16, 2027, 92 days after the date of this filing.
Read this passage

IV. CONTENTS OF FILING

printed heading

CONTENTS OF FILING Besides this transmittal letter, this filing includes these attachments: Att.
Read this passage

V. OTHER FILING REQUIREMENTS

printed heading

SCE believes that the data contained in this letter and the attachments provide sufficient information upon which to approve this filing; however, to the extent necessary, SCE further requests that the Commission waive its filing requirements contained in Sections 35.5 and 35.13 of the Commission’s…
Read this passage

VI. CORRESPONDENCE

printed heading

CORRESPONDENCE Pursuant to Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, SCE requests that all correspondence, pleadings, and other communications regarding the filing should be directed to the following: Ellen Kenney Senior Attorney Southern California Edison Company P.O.
Read this passage

VII. NOTICE

printed heading

NOTICE In addition to serving the California Public Utilities Commission, SCE is serving notice of these proposed tariff revisions on all parties to EL26-71-000 and SCE’s TO Tariff customers.
Read this passage

VIII. CONCLUSION

printed heading

CONCLUSION For the reasons set forth above, SCE respectfully requests that the Commission accept SCE’s proposed tariff revisions as filed, and rescind the Order to Show Cause as to SCE’s TO Tariff.
Read this passage

ATTACHMENT A

printed heading

ATTACHMENT A Clean TO Tariff Sheets Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Connecting load and generation

Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval. 3.19 Dispatch.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.
Read this passage

A. Site drawing showing Large Load location and Point of Interconnection

printed heading

Site drawing showing Large Load location and Point of Interconnection with the Participating TO’s Transmission System.
Read this passage

B. Single-line diagram showing applicable equipment such as large load

printed heading

This one-line drawing must be signed and stamped by a licensed Professional Engineer. 2.
Read this passage

A. Rated total MW consumption and power factor of the Large Load, including

printed heading

Rated total MW consumption and power factor of the Large Load, including IT equipment, power distribution, and cooling: Total MW: _______________ Power factor: _______________
Read this passage

B. Percentage of the total MW consumption of the Large Load for each of the

printed heading

Percentage of the total MW consumption of the Large Load for each of the following load components: Computing/server load: _____ % Lighting load: _____ % Power distribution losses: _____ % Cooling: _____ % Other: _____ % (describe if applicable): _______________ Does the percentage change during…
Read this passage

C. If the Large Loadhas some form of forced cooling system, indicate what it is

printed heading

If the Large Loadhas some form of forced cooling system, indicate what it is comprised of (check all that apply and add details if needed): ___ Computer Room Air Conditioners (CRACs) with internal compressors: _______________ ___ Computer Room Air Handlers (CRAHs) supplied with chilled water:…
Read this passage

D. Motor-driven components of the cooling systems are driven by (check all

printed heading

Motor-driven components of the cooling systems are driven by (check all that apply and add details if needed): ___ Single-speed motors operated across the line (motors connected directly to the AC supply): _______________ ___ Motors controlled by variable/adjustable speed drives or electronically…
Read this passage

E. Voltage sag levels and durations below which the components within the

printed heading

Voltage sag levels and durations below which the components within the data center disconnect from the grid: (1) Computing/server load: _______________ (2) Cooling load: _______________ (3) Are voltage sags sensed per phase or on a three-phase basis for the disconnection action? _______________ (4)…
Read this passage

F. Voltage swell levels and durations above which the components within the

printed heading

Voltage swell levels and durations above which the components within the data center disconnect from the grid: (1) Computing/server load: _______________ (2) Cooling load: _______________ (3) Are voltage swells sensed per phase or on a three-phase basis for the disconnection action? _______________…
Read this passage

G. Frequency thresholds above and below which any computing/server load

printed heading

Frequency thresholds above and below which any computing/server load may disconnect from the grid: Above: _______________ Below: _______________
Read this passage

H. Reconnection of load after voltage and frequency recover (check all that

printed heading

Reconnection of load after voltage and frequency recover (check all that apply and specify): ___ Reconnects immediately; voltage and frequency levels: _______________ Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 ___ Reconnects after a time delay; voltage and…
Read this passage

I. Emergency generation and battery energy storage:

printed heading

Details of existing protection and control schemes that affect the response of the facility: _______________________________________________ K.
Read this passage

A. Arrangement and operating mode:

printed heading

Arrangement and operating mode: (1) Arrangement (check one): ___ Co-located generation serving the Large Load on the generator side of the Point of Interconnection ___ Behind-the-meter generation at the Large Load’s retail meter ___ Other (describe): _______________ Southern California Edison…
Read this passage

B. Technology and ratings (aggregate nameplate MVA and MW for each

printed heading

Technology and ratings (aggregate nameplate MVA and MW for each technology): ____ Combustion turbine or reciprocating engine: ____MVA / ____MW Fuel: __________ ____ Solar photovoltaic: _____ MVA / _____ MW ____ Battery energy storage: _____ MVA / _____ MW / ____ MWh Charges from the ISO Controlled…
Read this passage

C. Gross and net withdrawal and requested service:

printed heading

Gross and net withdrawal and requested service: (1) Gross Large Load (MW) and gross co-located generation (MW), reported separately: _______ / _______ (2) Maximum net withdrawal from the ISO Controlled Grid with co- located generation online (MW): _______________ (3) Largest single co-located…
Read this passage

D. Non-export controls (for non-exporting co-located generation):

printed heading

Non-export controls (for non-exporting co-located generation): (1) Method used to prevent export (e.g., reverse-power relay, export-limiting controls, power control system): _______________ _____________________________________________________
Read this passage

E. Ride-through, protection, and disturbance behavior:

printed heading

E.
Read this passage

F. Models and data:

printed heading

Models and data: (1) Power flow and dynamic models of the co-located generation and an electromagnetic transient (EMT) model if required. (2) Evidence of model verification (e.g., manufacturer attestation, test data, or commissioning measurements), with as-built model updates provided before the…
Read this passage

G. NERC registration:

printed heading

NERC registration: (1) Co-located generation (check one): ___ Bulk Electric System generation (BES Inclusion I2, I3, or I4): Category 1 Generator Owner / Generator Operator ___ Non-BES inverter-based resources with aggregate nameplate capacity of 20 MVA or more connected at 60 kV or above: Category…
Read this passage

A. Total Generating Facility rated output (MW):

printed heading

Total Generating Facility rated output (MW): _______________ A1.
Read this passage

B. Generating Facility auxiliary load (MW): _______________

printed heading

Generating Facility auxiliary load (MW): _______________
Read this passage

C. Net Generating Facility capacity at generator/inverter terminals (MW):

printed heading

Net Generating Facility capacity at generator/inverter terminals (MW): _______________ (A-B) or (A1-B)
Read this passage

D. Collector system losses (MW): _______________ (insert “n/a” if not

printed heading

Collector system losses (MW): _______________ (insert “n/a” if not applicable or negligible) Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

E. Main step-up transformer losses (MW): _______________ (insert “n/a” if

printed heading

Main step-up transformer losses (MW): _______________ (insert “n/a” if not applicable or negligible)
Read this passage

F. Net Generating Facility capacity at high-side of main step-up transformer

printed heading

Net Generating Facility capacity at high-side of main step-up transformer (MW): _______________ (C-D-E)
Read this passage

G. Gen-tie loss to Point of Interconnection (MW): _______________ (insert

printed heading

Gen-tie loss to Point of Interconnection (MW): _______________ (insert “n/a” if not applicable or negligible)
Read this passage

H. Net Generating Facility capacity at Point of Interconnection (MW):

printed heading

Net Generating Facility capacity at Point of Interconnection (MW): _______________ (F-G) H1.
Read this passage

I. Standby Load when Generating Facility is off-line (MW):

printed heading

Standby Load when Generating Facility is off-line (MW): _______________ J.
Read this passage

A. Rated Generator speed (rpm): ____________

printed heading

A.
Read this passage

B. Rated MVA: _______________

printed heading

B.
Read this passage

C. Rated Generator Power Factor: ____________

printed heading

C.
Read this passage

D. Generator Efficiency at Rated Load (%): ____________

printed heading

Generator Efficiency at Rated Load (%): ____________
Read this passage

E. Moment of Inertia (including prime mover): ____________

printed heading

Moment of Inertia (including prime mover): ____________
Read this passage

F. Inertia Time Constant (on machine base) H: ____________ sec or

printed heading

Inertia Time Constant (on machine base) H: ____________ sec or MJ/MVA
Read this passage

G. SCR (Short-Circuit Ratio - the ratio of the field current required for

printed heading

SCR (Short-Circuit Ratio - the ratio of the field current required for Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 rated open-circuit voltage to the field current required for rated short-circuit current): ___________________________________________
Read this passage

H. Please attach generator reactive capability curves.

printed heading

Please attach generator reactive capability curves.
Read this passage

I. Rated Hydrogen Cooling Pressure in psig (Steam Units only):

printed heading

Rated Hydrogen Cooling Pressure in psig (Steam Units only): ________________________________________________ J.
Read this passage

A. Indicate the Manufacturer ____________________ and Type

printed heading

Indicate the Manufacturer ____________________ and Type _____________of excitation system used for the generator.
Read this passage

B. Attach a copy of the block diagram of the excitation system from its

printed heading

Attach a copy of the block diagram of the excitation system from its instruction manual.
Read this passage

C. Excitation system response ratio (ASA): ______________

printed heading

Excitation system response ratio (ASA): ______________
Read this passage

D. Full load rated exciter output voltage: ___________

printed heading

Full load rated exciter output voltage: ___________
Read this passage

E. Maximum exciter output voltage (ceiling voltage): ___________

printed heading

Maximum exciter output voltage (ceiling voltage): ___________
Read this passage

F. Other comments regarding the excitation system?

printed heading

Other comments regarding the excitation system? _____________________________________________________ _____________________________________________________ 5C Power System Stabilizer (“PSS”) Information: (Please repeat the following for each generator model.
Read this passage

A. Manufacturer:

printed heading

Manufacturer: _____________________________________________
Read this passage

B. Is the PSS digital or analog?

printed heading

Is the PSS digital or analog? __________________________________
Read this passage

C. Note the input signal source for the PSS?

printed heading

Note the input signal source for the PSS? _____ Bus frequency _____ Shaft speed _____ Bus Voltage _____________________ Other (specify source)
Read this passage

D. Please attach a copy of a block diagram of the PSS from the PSS

printed heading

Please attach a copy of a block diagram of the PSS from the PSS Instruction Manual and the correspondence between dial settings and the time constants or PSS gain.
Read this passage

E. Other comments regarding the PSS?

printed heading

Other comments regarding the PSS? _____________________________________________________ _____________________________________________________ _____________________________________________________ 5D Turbine-Governor Information: (Please repeat the following for each generator model.) Please…
Read this passage

A. Steam, gas or combined-cycle turbines:

printed heading

A.
Read this passage

B. Hydro turbines:

printed heading

Hydro turbines: (1) Turbine efficiency at rated load: _______% (2) Length of penstock: ______ft (3) Average cross-sectional area of the penstock: _______ft2 (4) Typical maximum head (vertical distance from the bottom of the penstock, at the gate, to the water level): ______ft (5) Is the water…
Read this passage

C. Complete this section for each machine, independent of the turbine

printed heading

Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 • X”d – Direct Axis Subtransient Reactance: _____ p.u. • X2 – Negative Sequence Reactance: _____ p.u. • X0 – Zero Sequence Reactance: _____ p.u.
Read this passage

A. Motoring Power (kW): ______________

printed heading

A.
Read this passage

B. I22t or K (Heating Time Constant): ______________

printed heading

I22t or K (Heating Time Constant): ______________
Read this passage

C. Rotor Resistance, Rr: ______________

printed heading

C.
Read this passage

D. Stator Resistance, Rs: ______________

printed heading

D.
Read this passage

E. Stator Reactance, Xs: ______________

printed heading

E.
Read this passage

F. Rotor Reactance, Xr: ______________

printed heading

F.
Read this passage

G. Magnetizing Reactance, Xm: ______________

printed heading

G.
Read this passage

H. Short Circuit Reactance, Xd'': ______________

printed heading

H.
Read this passage

I. Exciting Current: ______________

printed heading

Reactive Power Required In Vars (No Load): ______________ N.
Read this passage

A. Number of generators to be interconnected pursuant to this

printed heading

Number of generators to be interconnected pursuant to this Interconnection Request: _____
Read this passage

B. Average Site Elevation: ______ Single Phase _____ Three Phase_____

printed heading

Average Site Elevation: ______ Single Phase _____ Three Phase_____
Read this passage

C. Field Volts: _________________

printed heading

C.
Read this passage

D. Field Amperes: ______________

printed heading

D.
Read this passage

E. Motoring Power (MW): _______

printed heading

E.
Read this passage

F. Neutral Grounding Resistor (If Applicable): ____________

printed heading

Neutral Grounding Resistor (If Applicable): ____________
Read this passage

G. I22t or K (Heating Time Constant): ____________

printed heading

I22t or K (Heating Time Constant): ____________ Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

H. Rotor Resistance: ____________

printed heading

H.
Read this passage

I. Stator Resistance: ____________

printed heading

Total Rotating Inertia, H: ________ Per Unit on 100 MVA Base Note: A completed General Electric Company Power Systems Load Flow (PSLF) data sheet must be supplied with the Interconnection Request.
Read this passage

A. Inverter Manufacturer and Model: _________________________

printed heading

Inverter Manufacturer and Model: _________________________
Read this passage

B. Number of Inverters: ___________________

printed heading

B.
Read this passage

C. Nameplate Rating (AC, each inverter): _______/_______ kW

printed heading

Nameplate Rating (AC, each inverter): _______/_______ kW
Read this passage

D. Nameplate Voltage Rating (AC): _______ kV

printed heading

D.
Read this passage

E. Maximum AC line current: _______ Amps

printed heading

E.
Read this passage

F. Nameplate Power Factor Rating (AC): _______

printed heading

F.
Read this passage

G. Please attach capability curve describing reactive power or power factor

printed heading

Please attach capability curve describing reactive power or power factor range from no output to full rated output
Read this passage

H. Inverter control mode (e.g. voltage, power factor, reactive power): _____

printed heading

Inverter control mode (e.g. voltage, power factor, reactive power): _____
Read this passage

I. Short Circuit Characteristics: Applicant to provide technical data related to

printed heading

Short Circuit Characteristics: Applicant to provide technical data related to the short circuit characteristics of proposed inverter based generation systems.
Read this passage

A. Number of individual shunt capacitor banks: _____________

printed heading

Number of individual shunt capacitor banks: _____________
Read this passage

B. Individual shunt capacitor bank rated voltage (kV): _____________

printed heading

Individual shunt capacitor bank rated voltage (kV): _____________
Read this passage

C. Individual shunt capacitor bank size (kVAR at rated voltage):

printed heading

Individual shunt capacitor bank size (kVAR at rated voltage): _____________
Read this passage

D. Planned dynamic reactive control devices (SVC, STATCOM):

printed heading

Planned dynamic reactive control devices (SVC, STATCOM): _____________
Read this passage

E. Control range: _____________ kVAR (lead) _____________ kVAR (lag)

printed heading

Control range: _____________ kVAR (lead) _____________ kVAR (lag)
Read this passage

F. Control mode (e.g. voltage, power factor, reactive power):

printed heading

Control mode (e.g. voltage, power factor, reactive power): _____________
Read this passage

G. Please provide the overall plant reactive power control strategy

printed heading

Please provide the overall plant reactive power control strategy 13.
Read this passage

A. Manufacturer and model: ____________________________________

printed heading

Manufacturer and model: ____________________________________
Read this passage

B. Source Functions

printed heading

Source Functions (1) Total storage capability: ___________________ MWh (2) Rated storage discharging power: ___________________ MW (3) Maximum storage discharging power: ________________ MW If the maximum storage discharging power is less than the rated storage discharging power, specify the…
Read this passage

C. Charging Functions

printed heading

C.
Read this passage

D. Primary frequency response operating range for electric storage resources

printed heading

Each Large Load shall provide the load flow and dynamic model data specified in Item C of this section, in addition to the information in Items A and B for any co-located generation.
Read this passage

A. Provide load flow model for the generating plant and its interconnection

printed heading

Provide load flow model for the generating plant and its interconnection facilities in GE PSLF *.epc format, including new buses, generators, transformers, interconnection facilities.
Read this passage

B. For each generator, governor, exciter, power system stabilizer, WTG, or

printed heading

For each generator, governor, exciter, power system stabilizer, WTG, or inverter based generator, select the appropriate dynamic models from the General Electric PSLF Program Manual and provide the required input data.
Read this passage

C. For Large Loads, the Large Load Interconnection Customer shall provide a

printed heading · Topic match: Credit and exit

Confidential Information shall be treated in accordance with LLIP Section 7.1. 13.3 Binding Effect.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6 for any release of Confidential Information in contravention of this Article 22. 22.1.4…
Read this passage

ATTACHMENT B

printed heading

ATTACHMENT B Redlined TO Tariff Sheets Sections 1, 3, 4, 7-10, and 13 Southern California Edison Company FERC Electric Tariff, Third Revised Volume No. 6
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Connecting load and generation

Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval. 3.19 Dispatch.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Service was effected by transmitting copies via email to all parties who have provided an e-mail address.
Read this passage