Eversheds Sutherland (US) LLP
700 Sixth Street, NW, Suite 700
Washington, DC 20001-3980
T: 202.383.0915
joehall@eversheds-sutherland.com
Eversheds Sutherland (US) LLP is part of a global legal practice, operating through various separate and distinct legal entities, under Eversheds Sutherland. For a full description of the structure and a list of offices, please visit www.eversheds-sutherland.com.
November 16, 2026
VIA E-TARIFF
Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
Re:
DCR Transmission, L.L.C., Docket No. ER27-____-000
Proposed Transmission Owner Tariff Revisions to Implement Large Load
Interconnection Process and Agreements
Dear Secretary Reese:
Pursuant to Section 205 of the Federal Power Act (“FPA”)1 and sections 35.3 and 35.13 of
the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) regulations,2 and in
compliance with the Commission’s June 18, 2026, order to show cause (“OSC Order”) issued to the California Independent System Operator Corporation (“CAISO”) and the CAISO Participating Transmission Owners (“PTOs”),3 DCR Transmission, L.L.C. (“DCRT”) hereby submits proposed
revisions to its Transmission Owner Tariff (“TO Tariff”)4 to address issues regarding large loads identified by the Commission’s OSC Order (“Large Loads”).5 As explained herein, DCRT’s
proposed TO Tariff revisions are just and reasonable and comply with the OSC Order. DCRT respectfully requests that the Commission accept the proposed Tariff revisions, to be effective February 15, 2027.6
1 16 U.S.C. § 824d.2 18 C.F.R. §§ 35.3, 35.13 (2026).3 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (“OSC Order”).4 DCR Transmission, L.L.C., Transmission Owner Tariff, available in FERC eTariff (“DCRT TO Tariff”).5 See OSC Order, at PP 6, 31. 6 See 18 C.F.R. § 35.3(a)(1). From DCRT’s understanding, the CAISO plans to request that its tariff provisions submitted in compliance with the OSC Order be subject to a ninety (90) day notice period, so that the CAISO’s tariff revisions go into effect on February 15, 2027. DCRT is requesting the same notice period for this filing, so that DCRT’s proposed Tariff revisions go into effect on the same date as the CAISO’s proposed Tariff revisions. This
PDF page 2
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 2
I. BACKGROUND
A. DCRT
DCRT owns and operates the 125-mile, 500 kilovolt Ten West Link Transmission Line (“Ten West Link”), which runs from Arizona Public Service Company’s (“APS”) Delaney Substation, in Maricopa County, Arizona, to Southern California Edison Company’s (“SCE”) Colorado River Substation, in Riverside County, California. DCRT has transferred operational control of Ten West Link to the CAISO pursuant to the CAISO’s Transmission Control Agreement and is a PTO subject to that agreement.7 DCRT also maintains its own TO Tariff.8 Ten West Link entered commercial operation on June 12, 2024, and is currently one of the few transmission interconnections between Arizona and Southern California. Approximately 100 miles of Ten West Link are in Arizona.
B. Commission’s Show Cause Order
On June 18, 2026, the Commission issued orders to each of the six Independent System Operators (“ISOs”) and Regional Transmission Organizations (“RTOs”) over which it exercises jurisdiction and the PTOs within those ISOs and RTOs.9 These orders addressed potential deficiencies identified by the Commission regarding the integration of Large Loads onto the bulk power system.10 One such order was directed at the CAISO and the CAISO PTOs. DCRT is one such PTO within the CAISO and, therefore, subject to the Commission’s OSC Order.11 In the OSC Order, the Commission directed the CAISO and the CAISO PTOs, as
applicable, to address the requirements for Large Load interconnections, either through proposed tariff revisions or an explanation for why such revisions to existing tariffs are not needed.12 The Commission requested that the CAISO address the following:
• Rates, terms, and conditions of service that apply to interconnection customers serving co- located Large Load to address:
• The scope of the analyses the CAISO performs as part of its existing study process to evaluate the impacts of co-location arrangements, which may need to account for any potential dynamic impacts of co-located Large Loads and any potential
facilitates consistency between DCRT’s proposed Large Load Tariff revisions and related tariff revisions submitted by the CAISO.
7 See Letter Order accepting revisions to CAISO Transmission Control Agreement adding DCRT as signatory, Cal. Indep. Sys. Operator Corp., 187 FERC ¶ 61,134 (2024).8 See DCRT TO Tariff. 9 See OSC Order, at P 2 n.2. (Chairman Swett Concurrence).10 See OSC Order, at PP 1–3.11 See OSC Order, at P 2 n.9.12 See OSC Order, at PP 6, 31, 39–105.
PDF page 3
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 3
impacts of requests to modify an existing generating facility’s interconnection service level to serve co-located Large Loads on transmission system reliability;
• The potential that Eligible Customers,13 on behalf of Large Load, may not be required to pay for wholesale transmission services that they receive, as required by the cost causation principle;
• Netting Behind-the-Meter Generation (“BTMG”) against its Large Load for purposes of calculating Regional Access Charges;
• Generator interconnection service(s) that reflects the operational dynamics of serving either an electrically proximate Large Load or a co-located load that has a high peak load; and
• Transmission services that reflect that an Eligible Customer taking transmission service on behalf of Large Load is willing and able to limit its energy withdrawals from the transmission system under certain conditions, such as:
o An interim non-firm network transmission service while Network Upgrades are being constructed (i.e., interim Network Integration Transmission Service (“NITS”)); and
o Permanent firm and non-firm contract demand transmission services (transmission service up to a specified megawatt (“MW”) quantity, i.e., the contract level, on a firm or non-firm basis).14
The Commission requested that the CAISO and the CAISO PTOs address the following:
•
A definition of Large Load sufficient to capture loads that present the unique challenges described in the OSC Order;
•
The application process for requesting transmission service to Eligible Customers on behalf of Large Loads;
•
Procedures for studying the provision of transmission service to Large Loads that: o Identify which party will be responsible for conducting such studies; o Consider the unique characteristics and impacts of Large Loads on the transmission system, including Large Loads that are able to limit their energy withdrawals under certain conditions, which may thereby lessen or potentially avoid the need for certain Network Upgrades;
13 See OSC Order, at P 3 n.12.14 See OSC Order, at P 105.
PDF page 4
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 4
o Deter speculative or duplicative requests for transmission service by Eligible Customers on behalf of Large Loads;
o Are timely completed within 60–90 days;
o Require the evaluation of Alternative Transmission Technologies (“ATTs”) in studies for the provision of transmission service, using models that are capable of evaluating the transmission system to accurately account for ATTs, in all instances, without the need for a request from the Eligible Customer seeking transmission service on behalf of a Large Load; and o If traditional Network Upgrades are selected instead of ATTs, inclusion in the relevant study report to the Eligible Customer seeking transmission service on behalf of a Large Load of a sufficiently clear demonstration of why ATTs are not feasible (i.e., would not resolve reliability violations identified or meet the relevant planning criteria) or would not result in lower costs or a faster timeline for accommodating the transmission service request;
•
Ongoing operational requirements for transmission customers serving Large Loads necessary to ensure reliable operation of the transmission system;
•
Pro forma provisions in transmission service agreements, or other applicable agreements, to memorialize the procedures listed above;
•
Mechanisms to mitigate the risk of cost-shifting among transmission customers, which may result in unjust and unreasonable rates for transmission;
•
Provision of data on the CAISO’s website in a single location, and in an easily accessible format that is searchable and allows users to filter the data, on transmission service provided to Eligible Customers on behalf of Large Loads, for Network Upgrades evaluated in the local transmission planning process that are needed to accommodate transmission service to Eligible Customers on behalf of those Large Loads, and the costs for those Network Upgrades.15
The Commission recommended that the CAISO and the CAISO PTOs coordinate amongst each other in the development of the relevant Tariff provisions for compliance with the OSC Order’s directives.1615 See OSC Order, at P 66.16 See OSC Order, at P 37.
PDF page 5
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 5
C. DRCT’s Understanding of the CAISO’s Position
Based on the OSC Order, DCRT participated in the CAISO’s stakeholder process for the CAISO PTOs to coordinate the CAISO’s and the CAISO PTO’s compliance filing in response to the OSC Order. As recommended by the Commission,17 the CAISO and the CAISO PTOs coordinated the development of their respective tariff revisions.18 The CAISO and the CAISO PTOs held weekly coordination meetings where the CAISO PTOs and the CAISO could apply shared technical expertise to the Commission’s identified issues and revise internal draft proposals before dissemination to the public for comments via the CAISO’s stakeholder process. The CAISO PTOs also held regular meetings amongst themselves to apply shared expertise and jointly address CAISO PTO-specific issues where possible. The CAISO utilized its existing stakeholder processes to develop its proposed tariff revisions.
Through participation in the CAISO’s coordination process and standard stakeholder process, DCRT understands the CAISO’s position with respect to the OSC Order to be that:
•
The CAISO will define Large Loads as those that are 50 MW or greater and interconnected with the CAISO Controlled Grid, which definition DCRT will adopt;
•
The CAISO PTOs will address load interconnection procedures (including for Large Loads), including for co-located Large Loads, as is the current practice within the CAISO;
•
The CAISO will address interconnection of generators that export power to the CAISO Controlled Grid, including for co-located generation, as is the current practice within the CAISO;
•
The CAISO PTOs will address the risk of cost-shifting among Eligible Customers;
•
The CAISO and the CAISO PTOs will jointly address ongoing operational
requirements for Large Loads;
•
The CAISO and the CAISO PTOs will jointly address the provision of interim non- firm interconnection service through the Flexible Interim Load Interconnection (“FILI”) Service;
•
Large Load developers have not expressed interest in permanent non-firm
transmission service to any of the CAISO PTOs; therefore, such a transmission service is not warranted at this time;
17 See OSC Order, at P 37.18 Publicly available information about the CAISO Large Load Initiative stakeholder proceedings may be found at the following link to the CAISO internet website: https://stakeholdercenter.caiso.com/StakeholderInitiatives/Large-loads.
PDF page 6
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 6
•
The CAISO and the CAISO PTOs will jointly address provision of data on the
CAISO’s website in a single location, and in an easily accessible format that is searchable and allows users to filter the data, on transmission service provided to Eligible Customers on behalf of Large Loads, for Network Upgrades evaluated in the local transmission planning process that are needed to accommodate
transmission service to Eligible Customers on behalf of those Large Loads, and the costs for those Network Upgrades; and
•
Specific study procedures for generator interconnection regarding electrically proximate Large Loads are not necessary because the CAISO is not capacity-
constrained.
The CAISO’s and the CAISO PTO’s coordination processes were dynamic, with many opinions and perspectives shared and vigorous debates among the parties. DCRT understands the opinions of the other parties but tailored its proposed tariff revisions to its unique situation as a single-asset PTO whose transmission line traverses the California-Arizona border. DCRT’s filing reflects DCRT’s understanding of how the CAISO envisions the split of responsibilities between the CAISO and the CAISO PTOs for purposes of Large Load interconnection based on the OSC Order.
From DCRT’s understanding, the CAISO will not revise its offering of transmission products for Large Load interconnection.19 DCRT, as a PTO, cannot independently offer specific transmission products under the DCRT TO Tariff that may be inconsistent with services provided by the CAISO. Therefore, DCRT has not proposed additional or revised transmission services in this filing.20
II. DCRT’S PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE
AND COMPLY WITH THE DIRECTIVES OF THE OSC ORDER
A. The Interconnection Study Process Proposed in DCRT’s TO Tariff, Appendix IV and Large Load Interconnection Agreement Satisfies the Directives of the OSC
Order
In the OSC Order, the Commission preliminarily found that the CAISO Tariff and/or the TO Tariffs appear to be unjust and unreasonable because they lack sufficiently clear and consistent provisions establishing the application process and study procedures that will be used to evaluate the provision of transmission service to Eligible Customers on behalf of Large Loads.21 The Commission explained its concern that, absent such provisions, existing processes may not be
19 See CAISO Draft Final Proposal, Large Load Enhancements, September 24, 2026 at 67, available at https://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load-Enhancements-Sep-24- 26.pdf (“The CAISO does not propose to create new ‘transmission services’ or more responsibilities around eligible customers, which would require redesigning transmission and interconnection service entirely. The CAISO does not believe such a redesign is warranted.”).20 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 4.4.21 See OSC Order, at PP 49-53, 58.
PDF page 7
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 7
described with the clarity and specificity necessary to mitigate the operational risks of serving Large Loads, avoid disputes regarding how Large Load-related studies are conducted, deter speculative or duplicative requests for transmission service, and help avoid excessive and unnecessary Network Upgrades.22
DCRT proposes to add a new Appendix IV to its TO Tariff to directly respond to each of these concerns, as described below.23 The new Appendix IV includes a new Large Load Interconnection Process (“LLIP”) which details the interconnection process required for Large Loads to interconnect to Ten West Link for purposes of taking transmission service over the CAISO system, and includes a new pro forma Large Load Interconnection Agreement (“LLIA”). The combination of DCRT’s new LLIP and LLIA provide the level of transparency and detail sought in the OSC Order for the Large Loads, so transmission-related services are provided in a just, reasonable and not unduly discriminatory manner.
1. Clear Assignment of Study Responsibility
In the OSC Order, the Commission expressed concern that the CAISO Tariff and/or the TO Tariffs may not clearly specify which entity will be responsible for studying the provision of transmission service to Eligible Customers on behalf of Large Loads.24 DCRT will not be administrating transmission service to Large Load Interconnection Customers. The CAISO will be providing that service. DCRT will be providing interconnection to Large Loads. DCRT’s proposed Tariff revisions clearly assign responsibilities for the LLIP and state that DCRT will process Large Load interconnections. DCRT TO Tariff, proposed Appendix IV, Section 2 obligates DCRT to perform the two studies that frame Large Load interconnections: the Large Load System Impact Study, and the Large Load Facilities Study.25 By memorializing this obligation in its TO Tariff, DCRT provides Large Load Interconnection Customers with certainty as to which entity is accountable for each phase of the Large Load study process.
2. Rolling Application Process
In the OSC Order, the Commission directed the CAISO and the PTOs to explain whether their tariffs remain just and reasonable without, among other things, an application process that accepts Eligible Customers’ applications for transmission service on behalf of Large Loads on a rolling basis.26 DCRT’s proposed Tariff revisions establish a rolling application process for Large Load interconnections. DCRT TO Tariff, new Appendix IV, Section 1.2 provides that DCRT will
22 See OSC Order, at P 49.23 DCRT notes that, as stated above, its transmission facilities interconnect with the SCE and APS transmission systems. Appendix A of DCRT’s LLIA expressly states that DCRT will coordinate with the Large Load Interconnection Customers to ensure that all local state utility franchise rules and regulations are adhered to through, among other things, arrangements that provide for station service directly from the local franchised public utility. Appendix A also provides that DCRT will coordinate with the Large Load Interconnection Customer to facilitate any necessary pseudo-tie or similar arrangement for the delivery of power into the CAISO BAA.24 See OSC Order, at P 51.25 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 2.26 See OSC Order, at P 58.
PDF page 8
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 8
time-stamp each application upon receipt to establish study priority.27 This approach permits Large Load Interconnection Customers to submit applications whenever their projects are ready, rather than awaiting a periodic window, while providing an objective, transparent, and non- discriminatory basis for determining the order in which requests will be studied.
3. Non-Refundable Application and Study Fees
In the OSC Order, the Commission identified a non-refundable application fee as one tool to deter duplicative or speculative requests for transmission service on behalf of Large Loads.28 DCRT’s proposed Tariff revisions include meaningful non-refundable fees for Large Load interconnections. DCRT TO Tariff, proposed Appendix IV, Section 1.4.2 provides for a non- refundable application fee of two-hundred-thousand dollars ($200,000) that also covers the Large Load System Impact Study fees, and Section 2.3.2 establishes a non-refundable study fee of two- hundred-thousand dollars ($200,000) for the Large Load Facilities Study. For both studies, the Large Load Interconnection Customer is obligated to reimburse DCRT for any study costs in excess of the default fee.29 Moreover, by requiring the Large Load Interconnection Customer to bear study costs in excess of the fee, the proposed revisions ensure that the cost of studying a Large Load request is borne by the requesting party rather than by DCRT’s other customers.
4. Readiness Requirements
In the OSC Order, the Commission preliminarily found that sufficient readiness requirements that escalate at distinct phases of the study process (e.g., meaningful milestones and/or financial commitments) may be necessary to deter duplicative or speculative requests for transmission service.30 DCRT’s proposed Tariff revisions establish readiness requirements that escalate as an application progresses through the study process for Large Load interconnections. DCRT TO Tariff, proposed Appendix IV provides several readiness tools, including: (1) evidence of site control; (2) an attestation by an officer of the Large Load Interconnection Customer; (3) a deadline by which the Large Load Interconnection Customer must elect to proceed following the completion of each study phase, failing which the application will be deemed withdrawn; and (4) a limit of one amendment to the application.31
DCRT also has proposed requiring detailed dynamic models as part of the Large Load Interconnection Customer’s initial application and an initial sufficiency review of applications.32 Such models require meaningful effort and expertise to create, helping filter out speculative requests. Lastly, DCRT is proposing that Large Load Interconnection Customers be required to
27 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 1.2.28 See OSC Order, at P 58.29 See DCRT TO Tariff, proposed Appendix IV, LLIP, at §§ 2.2.1, 2.3.2.30 See OSC Order, at PP 55, 58.31 See DCRT TO Tariff, proposed Appendix IV, LLIP, at §§ 1.4(x)(q)–(r), 1.4.3, 2.2.2, 2.3.1, 2.5.1.32 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 1.4(x)(o)–(p).
PDF page 9
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 9
post financial security at three specific milestones or the application will be withdrawn. The details of these security postings are addressed in proposed Appendix IV, Attachment 4. Together, these readiness requirements ensure that only those interconnection requests that are genuinely viable, and that the Large Load Interconnection Customer is prepared to pursue, continue to consume study resources. This protects the integrity of the study queue for all Large Load Interconnection Customers and reduces the risk that Network Upgrades are planned for Large Loads that never materialize.
5. Evaluation of ATTs
In the OSC Order, the Commission preliminarily found that the CAISO Tariff and/or the TO Tariffs appear to be unjust and unreasonable because they lack clear and consistent provisions requiring the evaluation of ATTs as potential solutions to accommodate an Eligible Customer’s request for transmission service on behalf of a Large Load.33 Specifically, the Commission directed the CAISO and the CAISO PTOs to explain whether their tariffs remain just and reasonable without provisions that: (1) require the evaluation of ATTs in studies for the provision of transmission service, using models that are capable of evaluating the transmission system to accurately account for advanced transmission technologies, in all instances, without the need for a request from the Eligible Customer seeking transmission service on behalf of a Large Load; and
(2) if traditional Network Upgrades are selected instead of ATTs, require inclusion in the study report to the Eligible Customer of a sufficiently clear demonstration as to why ATTs are not feasible (i.e., would not resolve reliability violations identified or meet the relevant planning criteria) or would not result in lower costs or a faster timeline for accommodating the transmission service request.34 In so doing, the Commission explained that ATTs can add capacity on existing transmission lines quickly, often within one to three years, which may be more preferable for Large Loads.35
For purposes of the OSC Order, the Commission defined ATTs to include static
synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, tower lifting, and dynamic line ratings, and noted that the Commission has also referred to these technologies as Grid Enhancing Technologies.36 DCRT’s proposed Tariff revisions address the Commission’s directives regarding the evaluation of ATTs. DCRT’s proposed Tariff revisions include study procedures that will evaluate whether such technologies can resolve identified reliability needs when evaluating the transmission upgrades necessary to interconnect a new Large Load, and set forth the decision-making process for determining when to utilize an ATT rather than a traditional transmission upgrade.
33 See OSC Order, at P 60.34 See OSC Order, at PP 61, 126.35 See OSC Order, at P 60.36 See OSC Order, at P 60 n.154.
PDF page 10
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 10
Importantly, the Commission emphasized that it is not mandating the use of ATTs.37 Rather, the Commission’s directive is that ATTs be evaluated and, where they are not selected, that the basis for that determination be transparently explained to the Eligible Customer.38 To comply with the Commission’s directives regarding ATTs, DCRT’s proposed Tariff revisions explicitly state that ATTs, as defined in the OSC Order, will be considered, as applicable, during the Large Load System Impact Study and the Large Load Facilities Study when evaluating necessary transmission upgrades.39 DCRT’s revisions also explain the decision-making process for when to utilize an ATT versus a traditional transmission upgrade to ensure reliability while interconnecting a new Large Load.40 Specifically, if a traditional Network Upgrade solution is selected instead of ATTs, the study report will explain why ATTs are not feasible, ensuring that ATTs are appropriately considered during the study process.41 DCRT’s proposal will ensure that ATTs receive a meaningful evaluation in every Large Load study, while preserving DCRT’s engineering judgment to select the solution that will reliably and cost-effectively accommodate the requested service on DCRT’s single-line system.
6. Study Timelines
The OSC Order preliminarily found that the CAISO’s Tariff and/or the TO Tariffs appear to be unjust and unreasonable because they lack provisions that address, with sufficient clarity and consistency, how the CAISO and/or the CAISO PTOs will timely study (i.e., within 60–90 days of receiving the request) the provision of transmission service to Eligible Customers on behalf of Large Loads.42 DCRT’s proposed Tariff revisions address the OSC Order’s directives for purposes of Large Load interconnection study timelines.
DCRT’s proposed Tariff revisions meet the 90-day study deadline directed by the OSC Order by specifying the following benchmarks for the application and study process: (1) sufficiency review of the initial application to take five (5) business days, averaging 7 calendar days; (2) if deficiencies are identified, three (3) business days for the Large Load Interconnection Customer to cure the deficiencies; (3) five (5) calendar days to review any re-submitted application; (4) seven (7) calendar days for DCRT to execute the Large Load System Impact Study Agreement and conduct an initial scoping meeting with the Large Load Interconnection Customer;
(5) concurrently with step 4, thirty (30) days to conduct the Large Load System Impact Study and submit a study report; (6) seven (7) days for the Large Load Interconnection Customer to review the Large Load System Impact Study report and execute a Large Load Facilities Study Agreement; and (7) thirty (30) days for DCRT to conduct the Large Load Facilities Study and submit a report.43
37 See OSC Order, at P 61.
38 Id.39 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 2.4.40 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 2.4.41 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 2.4.42 See OSC Order, at P 38.43 See DCRT TO Tariff, proposed Appendix IV, LLIP, at §§ 2.1, 2.1.1, 2.1.2, 2.2, 2.2.2, 2.3.1.
PDF page 11
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 11
In total, these steps will average roughly 85 calendar days from start to finish, meeting the OSC Order’s target of 60–90 days.
B. Overview of DCRT’s Pro Forma Large Load Interconnection Agreement
DCRT TO Tariff, proposed Appendix IV, Attachment 3, includes DCRT’s proposed pro forma LLIA, generally modeled on the CAISO’s pro forma Large Generator Interconnection Agreement (“LGIA”), set forth in the CAISO Tariff, Appendix EE, which has been accepted by the Commission.44 In developing its proposed LLIA, DCRT began with the CAISO LGIA and removed those provisions that are specific to the interconnection and operation of generating facilities and have no application to a Large Load—for example, provisions addressing power system stabilizers, generator reactive power and primary frequency response obligations (replaced with a composite power factor requirement for the Large Load Facility), the Merchant Option, data requirements for Variable Energy Resources, and the interconnection requirements for Asynchronous Generating Facilities.45 At the same time, DCRT retained the interconnection and Network Upgrade concepts of the CAISO pro forma LGIA that apply equally to the interconnection of a Large Load, including the provisions governing Interconnection Facilities, Network Upgrades, and Distribution Upgrades; the engineering, procurement, and construction of such facilities; the Scoping Meeting; coordination with, and agreements involving, Affected Systems; milestones and financial security; and the provision of construction status reports to the CAISO. DCRT took this approach deliberately, so that the terminology, structure, and allocation of responsibilities among the CAISO, DCRT, and the Large Load Interconnection Customer in the LLIA remain consistent with those in the Commission-accepted CAISO LGIA. Doing so promotes clarity and consistency across the CAISO footprint, allows Large Load Interconnection Customers, the CAISO, and other market participants to rely on familiar and well-understood contractual terms, and minimizes the risk of disputes regarding the meaning of defined terms— consistent with the Commission’s emphasis in the OSC Order on clear and consistent tariff provisions.46 The DCRT proposed LLIA is different from the CAISO pro forma LGIA in certain provisions that reflect DCRT’s unique circumstances, most notably that DCRT’s single transmission line interconnects the CAISO Controlled Grid with the APS franchised service territory in Arizona.
Beyond the study, application, cost-responsibility, and FILI provisions addressed elsewhere in this transmittal letter and in the DCRT TO Tariff, the LLIA contains a number of key regulatory provisions, each carried over from, and consistent with, the corresponding provisions of the Commission-accepted CAISO LGIA. First, the proposed DCRT LLIA becomes effective upon execution by all Parties subject to acceptance by the Commission or, if filed unexecuted, on the date specified by the Commission, and DCRT will file the LLIA and any amendments with the
44 Cal. Indep. Sys. Operator Corp., Docket Nos. ER23-1977-000, et al., Letter Order (issued July 20, 2023) (accepting revisions to CAISO Open Access Transmission Tariff, Appendix EE (“CAISO pro forma LGIA”)). The CAISO Tariff is available in FERC eTariff.45 The sections of the CAISO pro forma LGIA that DCRT did not use in its proposal are CAISO Tariff, App. EE, at §§ 4.6, 5.1.5, 5.4, 8.4, 9.6, 11.4.1.4, and App. H.46 See OSC Order, at PP 49, 54.
PDF page 12
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 12
Commission as required.47 Second, and importantly in light of the CAISO’s unique transmission service framework, the LLIA makes clear that its execution does not constitute a request for, or the provision of, any transmission service under the CAISO Tariff and does not convey any right to receive electricity at any specific point of delivery; transmission service remains available only through the CAISO’s existing processes.48 Third, the proposed DCRT LLIA requires each Party to perform its obligations in accordance with Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility Practice, and to comply with the Emergency Condition procedures of the CAISO, the North American Electric Reliability Corporation (“NERC”), and the applicable Regional Reliability Council, while preserving the authority of DCRT to take actions necessary to preserve the reliability of the DCRT Transmission System during an Emergency Condition, including reduction or disconnection of the interconnection.49 Fourth, the proposed DCRT LLIA preserves the Parties’ respective rights to make unilateral filings under FPA sections 205 and 206.50 Collectively, these provisions ensure that the rights and obligations of the Parties under the LLIA are transparent, enforceable, and subject to the Commission’s continuing oversight.
In addition to these regulatory provisions, DCRT’s proposed LLIA contains the standard commercial provisions found in the Commission-accepted CAISO LGIA, adapted only as necessary to apply to a Large Load rather than a generating facility. These include: (1) invoicing, payment, and billing-dispute procedures, including the requirement that a Party continue performance during a billing dispute so long as undisputed amounts are paid and disputed amounts are paid or placed in escrow, with interest calculated under the Commission’s regulations;51 (2) termination procedures and the Large Load Interconnection Customer’s responsibility for termination costs, including costs incurred or irrevocably committed for the construction of DCRT’s Interconnection Facilities and Network Upgrades;52 (3) default and cure provisions affording a Breaching Party thirty (30) Calendar Days, or up to ninety (90) Calendar Days for a breach not capable of earlier cure, to remedy a Breach before the non-breaching Party may terminate;53 (4) force majeure;54 (5) mutual indemnification, a mutual waiver of special, indirect,
47 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Arts. 2.1, 3.1; CAISO Tariff, App. EE, LGIA, at §§ 2.1, 3.1.48 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 4.4; CAISO Tariff, App. EE, LGIA, at § 4.4; see also OSC Order, at PP 19, 25.49 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Arts. 4.3, 13.2, 13.5.2; CAISO Tariff, App. EE, LGIA, at §§ 4.3, 13.2, 13.5. 50 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 30.11; CAISO Tariff, App. EE, LGIA, at § 30.11.51 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Arts. 12.1-12.4; CAISO Tariff, App. EE, LGIA, at §§ 12.1-12.4.52 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Arts. 2.3-2.4; CAISO Tariff, Appendix EE, LGIA, at Arts. 2.3-2.4.53 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 17; CAISO Tariff, App. EE, LGIA, at §
17. 54 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 16; CAISO Tariff, App. EE, LGIA, at § 16.
PDF page 13
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 13
incidental, consequential, and punitive damages, and minimum insurance requirements, including workers’ compensation, commercial general liability, business automobile liability, and excess liability coverage, with provision for self-insurance by qualifying Parties;55 (6) restrictions on assignment without consent, subject to customary exceptions for assignment to creditworthy Affiliates and for collateral security purposes to facilitate project financing;56 (7) confidentiality obligations;57 (8) information access and audit rights;58 (9) responsibility for subcontractors;59 (10) informal dispute resolution and optional arbitration, with any arbitration decision affecting jurisdictional rates, terms, and conditions filed with the Commission;60 (11) customary representations and warranties regarding good standing, authority, absence of conflict, and regulatory approvals;61 and (12) miscellaneous provisions addressing, among other things, severability, binding effect, rules of interpretation, entire agreement, no third-party beneficiaries, waiver, amendment, and the absence of any partnership among the Parties.62
As proposed in DCRT’s LLIP, DCRT will evaluate the specific operating requirements for co-located load and generation to ensure reliability, including for BTMG.63 DCRT is aligned with the CAISO on the requirement that all generation exporting to the CAISO-controlled grid must undergo the CAISO’s Generator Interconnection and Deliverability Allocation Procedures (“GIDAP”) process.64 DCRT’s LLIA accommodates co-located generation and BTMG through
its Appendix H, as explained below. DCRT’s LLIA can be revised to accommodate the CAISO as a party to the extent there is co-location and BTMG facilities that inject power to the CAISO- controlled grid and that injection of power must be coordinated with the relevant Large Load Interconnection Customers.
55 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Arts. 18.1-18.3; CAISO Tariff, App. EE, LGIA, at §§ 18.1-18.3.56 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 19; CAISO Tariff, App. EE, LGIA, at §
19. 57 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 22; CAISO Tariff, App. EE, LGIA, at §
22. 58 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 25; CAISO Tariff, App. EE, LGIA, at §
25. 59 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 26; CAISO Tariff, App. EE, LGIA, at §
26. 60 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 27; CAISO Tariff, App. EE, LGIA, at §
27. 61 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Art. 28; CAISO Tariff, App. EE, LGIA, at §
28. 62 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Arts. 20, 30; CAISO Tariff, App. EE, LGIA, at §§ 20, 30.
63 BTMG, which is defined to be purely non-exporting generation, will be studied by DCRT during the LLIP. See DCRT TO Tariff, proposed Appendix IV, LLIP and Timeline. Specific provisions for BTMG are described in Appendix H to DCRT’s proposed LLIA. See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Appendix H, at §§ H.1, H.3, H.8; see also DCRT TO Tariff, proposed Appendix IV, at § 1.4(xi).64 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 3.2.
PDF page 14
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 14
C. DCRT’s Large Load Interconnection Process is Designed to Operate in Close Coordination with the CAISO, Including with Respect to Co-Located
Generation and BTMG
DCRT emphasizes that the central focus of its proposed TO Tariff revisions is to establish a just and reasonable, transparent, and clearly delineated process through which a Large Load Interconnection Customer may interconnect a Large Load to DCRT’s facilities, consistent with the requirements of the OSC Order. DCRT recognizes, however, that the interconnection of a Large Load to its system does not occur in isolation. Because DCRT’s facilities are under the operational control of the CAISO, and because the CAISO remains responsible for the interconnection of generating facilities—including co-located generation—to the CAISO Controlled Grid, DCRT’s proposed LLIP have been designed to operate in close coordination with the CAISO to ensure the reliability of both DCRT’s facilities and the CAISO-controlled transmission system.65 Accordingly, upon Commission acceptance of DCRT’s LLIP, DCRT will coordinate and collaborate with the CAISO regarding both the interconnection of Large Loads and, as explained below, the co-location of generation and BTMG with such Large Loads, as further memorialized in an Appendix H to the LLIA. To that end, DCRT’s proposed LLIA establishes several specific mechanisms through which DCRT will keep the CAISO informed throughout the load interconnection process, as described below.
1. Information-Sharing with the CAISO
DCRT will provide the CAISO with notice of any delays in DCRT’s construction of Interconnection Facilities, Network Upgrades, or Distribution Upgrades.66 This notice requirement is reasonable because the CAISO, as the entity responsible for the reliable operation of the CAISO- controlled transmission system and for transmission planning, must be aware of changes in the anticipated in-service dates of facilities that will be integrated into the transmission system over which the CAISO exercises operational control, so that the CAISO may account for such changes in its operational and planning activities.
DCRT will provide the CAISO with the specifications for the Large Load Interconnection Customer’s Interconnection Facilities and Large Load Facility, as well as “as-built” drawings, information, and documents for DCRT’s Interconnection Facilities, including appropriate drawings and relay diagrams.67 Providing this information ensures that the CAISO has an accurate and complete understanding of the physical and protection characteristics of the facilities being connected to the CAISO-controlled transmission system, which is essential to the CAISO’s ability to model the transmission system accurately and to maintain reliability.
To the extent applicable, DCRT will provide the CAISO with monthly construction status reports regarding the construction and installation of DCRT’s Interconnection Facilities and
65 See OSC Order, at PP 26, 37, 86 n.189.66 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 5.1.1.67 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Arts. 5.9.1-5.9.3, 5.10.
PDF page 15
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 15
Network Upgrades.68 These reports will include, but are not limited to: (1) progress to date; (2) a description of the activities undertaken since the last report; (3) a description of the action items for the next reporting period; and (4) the delivery status of equipment ordered.69 Regular, structured reporting of this nature will afford the CAISO ongoing visibility into the status of the facilities necessary to serve new Large Loads, consistent with the Commission’s expectation in the OSC Order that the CAISO and the CAISO PTOs will coordinate with each other, as appropriate, to address the concerns the Commission identified.70
2. Coordination with Affected Systems
In addition to coordination with the CAISO, DCRT’s proposed LLIP and LLIA recognize that the interconnection of a Large Load may affect systems other than DCRT’s own and, therefore, includes requirements for coordination with, and the provision of certain information to, Affected Systems.71 Specifically, DCRT will conduct a Scoping Meeting with the Large Load Interconnection Customer, other Affected Systems, and, as applicable, the CAISO.72 The purpose of the Scoping Meeting is to discuss alternative interconnection options; to exchange information, including any transmission data and earlier study evaluations that would reasonably be expected to impact such interconnection options; and to analyze such information.73 Convening all relevant parties at the earliest stage of the LLIP will help to identify potential issues before significant study resources are expended, promote the efficient selection of Points of Interconnection, and reduce the likelihood of later disputes regarding study assumptions—a concern the Commission specifically identified in the OSC Order.74
Further, under DCRT’s proposed LLIP, the Large Load Interconnection Customer will be obligated to enter into a construction and reimbursement agreement with the owner of any Affected System and/or other affected owners of portions of the CAISO Controlled Grid that govern facilities built on the relevant Affected System.75 Those agreements will govern the construction of facilities on Affected Systems and address the payments to be made by the Large Load Interconnection Customer to the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid, as well as any repayment by such owners.7668 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 24.2.69 Id.70 See OSC Order, at P 37.71 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 4.4.72 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 1 (definition of “Scoping Meeting”); see also DCRT TO Tariff, proposed Appendix IV, LLIP, at § 2.2.73 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 1 (definition of “Scoping Meeting”).74 See OSC Order, at P 54.75 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 4.4.76 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 11.3.3; OSC Order, at PP 65, 78.
PDF page 16
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 16
3. Treatment of Co-Located Generation and BTMG
DCRT’s proposed LLIA addresses the treatment of co-located generation and BTMG. Consistent with the CAISO’s existing practice, and with DCRT’s understanding of the CAISO’s position, described above, co-located generation will continue to interconnect through the CAISO’s GIDAP process pursuant to a Commission-approved Large Generator Interconnection Agreement.77 Facility-specific guidelines and procedures governing any net generation delivered to the grid from co-located generation will be addressed in Appendix H of the LLIA.78 DCRT’s proposal treats a Large Load that is co-located with generation, or that is served in part by BTMG, as a Large Load for purposes of the LLIP, while leaving the interconnection of the associated generating facility to the CAISO, to the extent that the generation exports power to the CAISO Controlled Grid. A Large Load Interconnection Customer must disclose in its Large Load Interconnection Application whether co-located generation is present and, if so, whether the generation resource will be fully behind-the-meter or may export to the CAISO Controlled Grid, the resource type, nameplate capacity, minimum and maximum operating levels, market participation status, and associated resource identifiers, together with all information required by DCRT and, as applicable, the CAISO in the Large Generator Interconnection Application.79 DCRT’s Large Load Interconnection studies will then evaluate the specific operating requirements of the combined load and generation configuration, including BTMG, to ensure that the interconnection can be accommodated reliably.80 Any generating facility that will export energy to the CAISO Controlled Grid, however, must interconnect through the CAISO’s GIDAP and execute a Commission-accepted LGIA, consistent with the CAISO’s existing practice and with the Commission’s recognition that the CAISO Tariff governs the generator interconnection process.81 This division of labor ensures that the Large Load interconnection and the generator interconnection are each studied under the procedures designed for them, without duplicating the CAISO’s generator interconnection function or creating inconsistent study results. To ensure that the two processes operate in tandem, DCRT will coordinate with the CAISO at each stage of the DCRT LLIP: DCRT will provide to the CAISO a copy of the Large Load Interconnection Application, the CAISO may participate with DCRT in designing any FILI constraints necessary to maintain reliability, and DCRT will coordinate with the CAISO on testing and commissioning of the Large Load and associated interconnection facilities.82 In addition, DCRT will coordinate with the CAISO to the extent the interconnection of a Large Load may impact the reliability of the CAISO Controlled Grid, and any potential injection of power from a Large Load, including from co-located generation, will require such coordination to ensure
77 See OSC Order, at P 26.78 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Appendix H, at §§ H.4, H.5.79 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 1.4(xi).80 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 2.2–2.4.81 See OSC Order, at P 86 n.189.82 See DCRT TO Tariff, proposed Appendix IV, LLIP, at §§ 1.2, 2.2.2, 3.1, 4.3.
PDF page 17
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 17
compliance with the CAISO Tariff.83 The CAISO’s role further will be memorialized in the DCRT LLIA, to which the CAISO will be a party, as stated above, if there is an injection of power to the CAISO-controlled grid. Finally, as noted above, the treatment of any net generation delivered to the transmission system from co-located generation or BTMG will be addressed on a project- specific basis in an appendix to the DCRT LLIA,84 ensuring that each such arrangement is subject to clear, enforceable terms that account for its particular operating characteristics. DCRT’s proposed approach respects the existing allocation of responsibilities between the CAISO, which administers generator interconnection, and the CAISO PTOs, which administer load interconnection, while ensuring that the unique operational characteristics of each co-location arrangement are captured on a project-specific basis. Indeed, the Commission expressly recognized in the OSC Order that the CAISO PTOs’ role in conducting load studies may stem from how the CAISO and the CAISO PTOs allocated rights and responsibilities in the governing documents establishing the CAISO and stated that it does not seek to alter that allocation.85
D. DCRT’s Proposed Flexible Interim Load Interconnection Service
As discussed above, DCRT understands that the CAISO has declined to propose a new transmission service at this time in light of the CAISO’s day-ahead scheduling process for allocating transmission capacity,86 and DCRT defers to the CAISO on this issue. As the Commission itself recognized in the OSC Order, the framework under which the CAISO provides transmission service is unique among the RTOs/ISOs: the CAISO does not offer traditional Order No. 888 network and point-to-point transmission services, offers no firm, long-term transmission reservations of capacity, and instead offers a single “daily” transmission service that is available to all Eligible Customers on a day-to-day basis.87
Rather than proposing a new transmission service, and as envisioned for CAISO PTO’s through the CAISO coordination process, DCRT is proposing a new FILI Service that will be available when a Large Load’s full requested capacity cannot immediately be provided on a firm basis.88 In alignment with DCRT’s understanding of the CAISO’s conception of the FILI Service, DCRT’s proposed revisions address: (1) the allocation of responsibility among the relevant parties;
(2) information-sharing with the CAISO; (3) operational requirements, including curtailment mechanisms and data reporting; (4) cost-responsibility provisions; and (5) the transition to firm
83 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 4.3.84 See OSC Order, at P 51; DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Appendix H.85 See OSC Order, at PP 51, 86 n.189.86 See CAISO Draft Final Proposal, Large Load Enhancements, September 24, 2026 at 67, available at https://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load-Enhancements-Sep-24- 26.pdf (“The CAISO does not propose to create new ‘transmission services’ or more responsibilities around eligible customers, which would require redesigning transmission and interconnection service entirely. The CAISO does not believe such a redesign is warranted.”).87 See OSC Order, at PP 19, 104.88 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 3.
PDF page 18
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 18
service upon completion of the necessary Network Upgrades. Each of these elements is discussed further below.
1. DCRT’s Proposed FILI Service Responds to the Commission’s
Directives Regarding Flexible Large Loads
In the OSC Order, the Commission preliminarily found that the CAISO Tariff appears to be unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking transmission service on behalf of flexible Large Loads that are willing and able to limit their use of the transmission system under certain conditions.89 The Commission directed the CAISO to explain whether its Tariff remains just and reasonable without: (1) an interim non- firm network transmission service while Network Upgrades are being constructed; and (2) permanent firm and non-firm contract demand transmission services.90 In the alternative, the Commission provided that the CAISO may explain whether, given that the CAISO does not offer the transmission services required by Order No. 888, its existing transmission service framework addresses the Commission’s concerns, or explain what specific changes to that framework would effectively provide comparable transmission service options for flexible Large Loads as in the PJM Interconnection, LLC Co-Location Order.91 The Commission further noted that it has found it just and reasonable that, in order to take such interim or contract demand transmission services, an Eligible Customer must have necessary control technologies and/or protection systems, which may include a special protection scheme, to limit its energy withdrawals to its approved level.92 In reaching these preliminary findings, the Commission recognized that load flexibility can avoid inefficient and costly transmission system build-out and can help timely interconnect flexible Large Loads.93 Although these particular directives were addressed to the CAISO, DCRT’s proposed FILI Service provides a mechanism for Large Load interconnection to DCRT’s system that is consistent with the interim, flexible service the Commission contemplated.
2. Terms and Conditions of FILI Service
Under Section 3.1 of DCRT’s proposed LLIP, DCRT may offer FILI Service if the System Impact Study shows that the Large Load “cannot be reliably served at its full requested demand until certain Network Upgrades are completed.”94 In that instance, the Large Load Interconnection Customer may request that DCRT offer FILI Service, and DCRT “may propose a customized plan . . . based on the type of constraints required to maintain Transmission System reliability.”95 The Large Load Interconnection Customer “may participate in the design of the FILI Service
89 See OSC Order, at P 104.90 See OSC Order, at P 105.91 See OSC Order, at PP 104-05 (citing PJM Interconnection, LLC, 193 FERC ¶ 61,217, PP 201, 205).92 See OSC Order, at PP 102, 105.93 See OSC Order, at P 104.94 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 3.1.95 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 3.1.
PDF page 19
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 19
constraints.”96 Once the necessary upgrades are complete, the Large Load Interconnection Customer “may elect to receive firm service.”97 This provision serves as the operative trigger for FILI Service and provides the pathway for transition to firm service that the OSC Order contemplates.98 By allowing the specific constraints of FILI Service to be tailored, with the participation of the Large Load Interconnection Customer, to the reliability needs identified in the System Impact Study, this approach ensures that FILI Service reasonably limits a Large Load’s use of the system only to the extent necessary to maintain reliability on DCRT’s single-line system and the CAISO Controlled Grid.
Under Section A-2 of Appendix A to the LLIA, a Large Load Interconnection Customer may elect to take FILI Service until the Network Upgrades identified in Appendix A have achieved Commercial Operation.99 This structure tracks the Commission’s description of an interim service available “while network upgrades are being constructed.”100 As with the interim service the Commission described, DCRT’s proposed FILI Service will allow a flexible Large Load to obtain interconnection service more quickly than it otherwise could, in exchange for its willingness to accept limitations on its use of the system until the necessary upgrades are complete.101 Section A-2 of Appendix A to the LLIA, items 2(a)–(g), detail what should be included in a project-specific FILI addendum to a LLIA that implements the following concepts, in furtherance of the Commission’s directives: (i) study methods revised “to recognize the unique operational characteristics of flexible large loads”; (ii) “curtailment implementation mechanisms and data reporting”; (iii) financial security “during the conditional service period”; (iv) “automatic conversion to firm service upon Network Upgrade completion”; (v) coordination with the study process; and (vi) provisions governing longer-duration curtailments “in coordination with, as applicable, the CAISO.”102
Memorializing these terms in an addendum to the LLIA will ensure that the terms and conditions of FILI Service are transparent, are applied on a consistent and non-discriminatory basis to all similarly situated customers, and are enforceable.103 The curtailment implementation mechanisms, in particular, serve the same function as the control technologies and/or protection systems that the Commission has found necessary to limit an Eligible Customer’s energy withdrawals to its approved level.10496 See DCRT TO Tariff, proposed Appendix IV, LLIP, at § 3.1.97 Id.98 See OSC Order, at PP 105, 110.99 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Appendix A at § A-2.100 See OSC Order, at P 105.101 See OSC Order, at P 104 n.227.102 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, Appendix A at § A-2, items 2(a)-2(g).103 See OSC Order, at P 64.104 See OSC Order, at P 105.
PDF page 20
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 20
E. Cost Responsibility for Network Upgrades
DCRT understands the concerns about fair and equitable cost responsibility for Large Loads and has proposed a mechanism that DCRT believes balances its obligations under the FPA and the OSC Order, given that DCRT is a single-asset Transco and does not have a traditional integrated transmission system. Specifically, with respect to cost responsibility, Article 11.3.1 of the LLIA provides that Large Load Facilities will be reimbursed for Reimbursable Network Upgrades costing more than $10 million if the Large Load Facility reaches commercial operation.105 DCRT has provided a mechanism pursuant to which DCRT can seek a return of any amounts paid to the Large Load Interconnection Customer, to the extent that DCRT is not able to recover amounts paid for Reimbursable Network Upgrades in its transmission revenue requirement. The claw back period is five (5) years.
DCRT has proposed this mechanism because of concerns that Network Upgrades required for the interconnection of Large Load Facilities may be of a similar scope and size as those required under the CAISO generator interconnection process and it may be unduly discriminatory for DCRT to maintain different reimbursement procedures for the similar Network Upgrades, particularly for a single-asset Transco where the upgrades may be at or near each other. Reimbursement of Network Upgrades was a debated issue in the CAISO stakeholder process and DCRT understands that its reimbursement policies may be subject to additional discussion as part of the CAISO stakeholder process.
F. CAISO Data Exchange
The Commission directed the CAISO and the PTOs to jointly address provision of data on the CAISO’s website in a single location, and in an easily accessible format that is searchable and allows users to filter the data, on transmission service provided to Eligible Customers on behalf of Large Loads, for Network Upgrades evaluated in the local transmission planning process that are needed to accommodate transmission service to Eligible Customers on behalf of those Large Loads, and the costs for those Network Upgrades.106 DCRT will coordinate with the CAISO and provide all data requested by the CAISO to support the CAISO’s provision of this information in the manner directed by the OSC.107105 See DCRT TO Tariff, proposed Appendix IV, Attachment 3, LLIA, at Art. 11.3.1.106 See OSC Order, at P 66.107 DCRT will coordinate with CAISO concerning CAISO’s and DCRT’s data exchange and posting obligations and will incorporate the details of this process in DCRT’s Large Load interconnection business practices.
PDF page 21
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 21
III. CORRESPONDENCE
DCRT respectfully request that the following individuals be included on the official service list in this proceeding and for receipt of any communications regarding this filing:108 Ali Amirali
Jason Crew
DCR Transmission, L.L.C.
c/o Lotus Infrastructure, LLC
5 Greenwich Office Park - 2nd floor
Greenwich, CT 06831
aamirali@lotuspartners.com
jcrew@lotuspartners.com
Joseph C. Hall
Anthony Danti
Shenghao Wang
Kelly A. Cuthbertson
Eversheds Sutherland (US), LLP
700 Sixth Street NW, Suite 700
Washington, DC 20001
Tel: (202) 383-0915
joehall@eversheds-sutherland.com
anthonydanti@eversheds-sutherland.com
shenghaowang@eversheds-sutherland.com
kellycuthbertson@eversheds-sutherland.com
IV. REQUESTED EFFECTIVE DATE
DCRT respectfully requests that the Commission accept the proposed DCRT TO Tariff revisions submitted herewith to be effective on February 15, 2027.
V. DOCUMENTS ENCLOSED
This filing consists of the following:
•
A revised version of the DCRT TO Tariff, main body;
•
A new Appendix IV, Large Load Interconnection Process and Timeline, to the DCRT TO Tariff, and the following attachments thereto:
o Attachment 1, Large Load System Impact Study Agreement;
o Attachment 2, Large Load Facilities Study Agreement;
o Attachment 3, Large Load Interconnection Agreement;
o Attachment 4, Interconnection Financial Security;
•
A redline reflecting all revisions to the main body of the DCRT TO Tariff and the new Appendix IV, including all new attachments.
108 DCRT respectfully requests that the Commission grant waiver of Rule 2010(k)(1) of the Commission’s Rules of Practice and Procedure to permit DCRT to include more than two representatives on the official service list in this proceeding. See 18 C.F.R. § 385.2010(k)(1).
PDF page 22
The Honorable Debbie Anne A. Reese
November 16, 2026
Page 22
VI. SERVICE
A copy of this filing has been served upon the CAISO.
VII. CONCLUSION
Based on the foregoing, DCRT respectfully requests that the Commission accept and approve the revisions to its TO Tariff to be effective on February 15, 2027. Respectfully submitted,
/s/ Joseph C. Hall
Joseph C. Hall
Anthony Danti
Shenghao Wang
Kelly A. Cuthbertson
Eversheds Sutherland (US), LLP
700 Sixth Street, NW, Suite 700
Washington, D.C. 20001
joehall@eversheds-sutherland.com
anthonydanti@eversheds-sutherland.com
shenghaowang@eversheds-sutherland.com
kellycuthbertson@eversheds-sutherland.com
Counsel for DCR Transmission, L.L.C.
TABLE OF CONTENTS
Page No.
1. Preamble … 4
2. Effective Date … 4
3. TO Definitions … 4 3.1.
Access Charge … 4 3.2.
Alternative Transmission Technologies … 4 3.3.
Base Transmission Revenue Requirement (“Base TRR”) … 4
3.4.
CAISO ADR Procedures … 4 3.5.
CAISO Controlled Grid … 4 3.6.
CAISO Tariff … 4 3.7.
Completed Application Date … 5 3.8.
Completed Interconnection Application … 5 3.9.
Direct Assignment Facilities … 5 3.10. DCR Transmission, L.L.C. (“DCRT”) … 5 3.11. Existing Contracts … 5 3.12. Expedited Interconnection Agreement … 5 3.13. Flexible Interim Load Interconnection Service (“FILI Service”) … 5
3.14. Interconnection Application … 5 3.15. Large Load … 5 3.16. Large Load Facilities Study … 6 3.17. Large Load Facilities Study Agreement … 6 3.18. Large Load Interconnection Agreement … 6 3.19. Large Load Interconnection Application … 6 3.20. Large Load Interconnection Customer … 6 3.21. Large Load Interconnection Facilities … 6 3.22. Large Load Interconnection Process (“LLIP”) … 6 3.23. Large Load Interconnection Service … 6 3.24
Large Load System Impact Study … 6 3.25. Large Load System Impact Study Agreement … 7 3.26. Net FTR Revenue … 7 3.27. Participation Agreement … 7 3.28. Project Proponent … 7 3.29. Regional Transmission Group (“RTG”) … 7 3.30. Regulatory Authority … 7 3.31. Reliability Upgrade … 7 3.32. Requests for Expedited Interconnection Procedures … 8 3.33. System Impact Study … 8 3.34. System Impact Study Agreement … 8 3.35. TO Tariff … 8 3.36. Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 8
PDF page 27
3.37. Participating TO’s Transmission System … 8
4. Eligibility … 8
5. Access Charges … 8 5.1.
Transmission Revenue Requirement (“TRR”) … 8 5.2.
Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 8
6. Ancillary Services--Applicability and Charges … 9
7. Billing and Payment … 9 7.1.
Payment … 9 7.2.
Billing … 9
8. Obligation to Interconnect or Construct Transmission Expansions and Facility
Upgrades … 9 8.1.
Participating TO Obligation to Interconnect … 9 8.1.1. Interconnection to Transmission System … 10 8.1.1.1.
Letter Agreement … 10
8.1.2. Costs Associated with Interconnection … 11 8.1.3. Interconnection Agreement … 12 8.1.4. Due Diligence to Construct … 13 8.1.5. Energization … 13 8.1.6. Coordination with the CAISO on Interconnection Requests … 13
8.2.
Participating TO Obligation to Construct Transmission Expansions or
Facility Upgrades … 13 8.2.1. Obligation to Construct … 13 8.3.
Request for FERC Deference Regarding Need Determination … 14
9. Expansion Process … 14 9.1.
Determination of Facilities … 14 9.1.1. Payment of Facilities Study Costs … 14 9.1.1.1.
Market Participant to Pay for Facilities Study … 14
9.1.1.2.
Project Sponsor or Project Proponent to Pay for
Facilities Study … 14
9.1.1.3.
Principal Beneficiaries to Pay for Facilities Study … 14
9.1.2. Payment Procedure … 15 9.1.3. Facilities Study Procedures … 15 9.2.
Obligation to Build … 15 9.2.1. Due Diligence to Construct … 15 9.2.2. Delay in Construction or Expansion … 16 9.2.2.1.
Alternatives to the Original Facility Additions … 16
9.2.2.2.
Refund Obligation for Unfinished Facility Additions … 16
9.3.
Provisions Relating To Transmission Construction on the Systems of Other
TOs … 16 9.3.1. Responsibility for Third Party Additions … 16 9.3.2. Coordination of Third-Party System Additions … 17
PDF page 28
10. Interconnection Process … 17 10.1. Applicability … 17 10.2. Applications … 17 10.3. Interconnection Application … 17 10.3.1. Amendment to Completed Interconnection Application … 18
10.4. Review of Completed Interconnection Application … 19
10.5. Notice of Need for System Impact Study … 19 10.6. System Impact Study Cost Reimbursement and Agreement … 20
10.6.1. Cost Reimbursement … 20 10.6.2. Multiple Parties … 20 10.7. System Impact Study Procedures … 20 10.7.1. Procedures Upon Completion of System Impact Study … 21
10.8. Notice of Need for Facilities Study … 21 10.9. Facilities Study Procedures … 22 10.9.1. Execution of Interconnection Agreement … 22
10.10. Partial Interim Service … 23 10.11. Expedited Procedures for New Facilities … 23
11. Uncontrollable Forces and Indemnification … 23 11.1. Procedures to Follow if Uncontrollable Force Occurs … 23
11.2. Indemnification … 24
12. Regulatory Filings … 24
13. Miscellaneous … 24 13.1. Notices … 24 13.2. Waiver … 24 13.3. Confidentiality … 25 13.3.1. Maintaining Confidentiality if Not for Public Disclosure … 25
13.3.2. Disclosure of Confidential Information … 25
13.4. Titles … 25 13.5. Severability … 25 13.6. Preservation of Obligations … 26 13.7. Governing Law … 26 13.8. Appendices Incorporated … 26 13.9. Consistency with CAISO Tariff … 26 13.10. Disputes … 26
4. Eligibility … 7
5. Access Charges … 7 5.1.
Transmission Revenue Requirement (“TRR”) … 7
5.2.
Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 7
6. Ancillary Services--Applicability and Charges … 7
7. Billing and Payment … 7
PDF page 29
7.1.
Payment … 7 7.2.
Billing … 8
8. Obligation to Interconnect or Construct Transmission Expansions and Facility
Upgrades … 8 8.1.
Participating TO Obligation to Interconnect … 8 8.1.1. Interconnection to Transmission System … 8 8.1.2. Costs Associated with Interconnection … 10 8.1.3. Interconnection Agreement … 10 8.1.4. Due Diligence to Construct … 11 8.1.5. Energization … 11 8.1.6. Coordination with the CAISO on Interconnection Requests … 12
8.2.
Participating TO Obligation to Construct Transmission Expansions or
Facility Upgrades … 12 8.2.1. Obligation to Construct … 12 8.3.
Request for FERC Deference Regarding Need Determination … 12
9. Expansion Process … 12 9.1.
Determination of Facilities … 12 9.1.1. Payment of Facilities Study Costs … 12 9.1.1.1.
Market Participant to Pay for Facilities Study … 12
9.1.1.2.
Project Sponsor or Project Proponent to Pay for
Facilities Study … 12
9.1.1.3.
Principal Beneficiaries to Pay for Facilities Study … 13
9.1.2. Payment Procedure … 13 9.1.3. Facilities Study Procedures … 13 9.2.
Obligation to Build … 14 9.2.1. Due Diligence to Construct … 14 9.2.2. Delay in Construction or Expansion … 15 9.2.2.1.
Alternatives to the Original Facility Additions … 15
9.2.2.2.
Refund Obligation for Unfinished Facility Additions … 15
9.3.
Provisions Relating To Transmission Construction on the Systems of Other
TOs … 16 9.3.1. Responsibility for Third Party Additions … 16 9.3.2. Coordination of Third-Party System Additions … 16
10. Interconnection Process … 16 10.1. Applicability … 16 10.2. Applications … 17 10.3. Interconnection Application … 17 10.3.1. Amendment to Completed Interconnection Application … 18
10.4. Review of Completed Interconnection Application … 18 10.5. Notice of Need for System Impact Study … 19 10.6. System Impact Study Cost Reimbursement and Agreement … 19
10.6.1. Cost Reimbursement … 20 10.6.2. Multiple Parties … 20 10.7. System Impact Study Procedures … 20
PDF page 30
10.7.1. Procedures Upon Completion of System Impact Study … 20
10.8. Notice of Need for Facilities Study … 21 10.9. Facilities Study Procedures … 22 10.9.1. Execution of Interconnection Agreement … 22
10.10. Partial Interim Service … 22 10.11. Expedited Procedures for New Facilities … 22
11. Uncontrollable Forces and Indemnification … 23 11.1. Procedures to Follow if Uncontrollable Force Occurs … 23
11.2. Indemnification … 23
12. Regulatory Filings … 23
13. Miscellaneous … 23 13.1. Notices … 24 13.2. Waiver … 24 13.3. Confidentiality … 24 13.3.1. Maintaining Confidentiality if Not for Public Disclosure … 24
13.3.2. Disclosure of Confidential Information … 24
13.4. Titles … 25 13.5. Severability … 25 13.6. Preservation of Obligations … 25 13.7. Governing Law … 25 13.8. Appendices Incorporated … 25 13.9. Consistency with CAISO Tariff … 25 13.10. Disputes … 25
APPENDIX I TRANSMISSION REVENUE REQUIREMENT AND TRBAA
APPENDIX II NOTICE
APPENDIX III PRO FORMA LETTER AGREEMENT
APPENDIX IV – LARGE LOAD INTERCONNECTION PROCESS AND TIMELINE
PDF page 31
1. Preamble. DCR Transmission, L.L.C.’s (“DCRT” or “Participating TO”) Transmission Revenue Requirement (“TRR”) for its Regional Transmission Facilities placed under the California Independent System Operator Corporation’s (“CAISO”) Operational Control, and certain terms and conditions relating to transmission expansion of and interconnection with DCRT’s Regional Transmission Facilities placed under the CAISO’s Operational Control, are set forth in this Transmission Owner (“TO”) Tariff.
2. Effective Date. This TO Tariff is effective on the date on which DCRT became a Participating TO, and shall continue to be effective so long as DCRT is a party to the Transmission Control Agreement (“TCA”).
3. TO Definitions. Certain capitalized terms used in this TO Tariff that are set out immediately below shall have the meanings set out below unless otherwise stated or the context otherwise requires. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the CAISO Open Access Transmission Tariff (“Tariff”), as it may be amended from time to time.
3.1.
Access Charge. A charge paid by all Utility Distribution Companies, Small Utility Distribution Companies, and Metered Sub System (“MSS”) Operators with Gross Load in a Participating Transmission Owner (“PTO” or “Participating TO”) Service Territory, as set forth in CAISO Tariff, Article II. The Access Charge includes the Regional Access Charge and the Local Access Charge, as applicable. The Access Charge will recover the Participating TO’s TRR in accordance with CAISO Tariff, Appendix F, Schedule 3.
3.2
Alternative Transmission Technologies. Any transmission technology other than Network Upgrades that can be used to improve the Participating TO’s Transmission System facilitate the interconnection of a Customer or a Large Load Interconnection Customer, which may include but is not limited to, static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, unified power flow controller, and tower lifting. 3.3.
Base Transmission Revenue Requirement (“Base TRR”). The TRR before reflecting TRBAA and Standby Transmission Revenues. The Base TRR is shown in Appendix I to this TO Tariff.
3.4.
CAISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13 of the CAISO Tariff, as amended from time to time.
3.5.
CAISO-Controlled Grid. The system of transmission lines and associated facilities of the Participating TOs that have been placed under the CAISO’s Operational Control.
3.6.
CAISO Tariff. The currently effective CAISO Agreement and Tariff, as it is on file with FERC and as may be modified from time to time.
PDF page 32
3.7.
Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed Interconnection Application.
3.8.
Completed Interconnection Application. An Interconnection Application that satisfies all of the information and other requirements of Section 10.3 of this TO Tariff and, if applicable, the information requirements as specified by the CAISO and posted on the CAISO Home Page.
3.9.
Direct Assignment Facilities. Facilities or portions of facilities that are owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting interconnection under this TO Tariff to the CAISO Controlled Grid at the point of interconnection. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval.
3.10. DCR Transmission, L.L.C. (“DCRT”). The Delaware limited liability corporation that is the Participating TO under this TO Tariff.
3.11. Existing Contracts. Those transmission service agreements or other contracts which grant transmission service rights in existence on the CAISO Operations Date (including any contracts entered into pursuant to such contracts) as may be amended in accordance with their terms or by agreement between the parties thereto from time to time.
3.12. Expedited Interconnection Agreement. A contract between a party which has submitted a Request for Expedited Interconnection Procedures and the Participating TO under which the Participating TO agrees to process, on an expedited basis, the Completed Interconnection Application of such party and which sets forth the terms, conditions, and cost responsibilities for such Interconnection.
3.13 Flexible Interim Load Interconnection Service (“FILI Service”). An interconnection service that may be offered by Participating TO at its sole discretion, that interconnects a Large Load Facility that cannot be reliably served at its full requested capacity without the construction of Network Upgrades or Alternative Transmission Technologies, subject to operational constraints on the Large Load Facility to ensure Transmission System reliability, as memorialized in a Large Load Interconnection Agreement.
3.14. Interconnection Application. An application that requests Interconnection to the CAISO Controlled Grid, other than a Large Load Interconnection Application. 3.15 Large Load. An End User located at a single site whose Point(s) of Interconnection is/are to the CAISO-Controlled Grid, and that has a peak load of 50 MW or greater.
PDF page 33
3.16. Large Load Facilities Study. The second study conducted as part of the LLIP as described in Appendix IV to this TO Tariff, used to create the detailed design of the interconnection facilities used to interconnect the Large Load to the Participating TO’s facilities, based on the findings of the Large Load System Impact Study.
3.17. Large Load Facilities Study Agreement. The prerequisite agreement before DCRT will conduct, or cause to be conducted, the Large Load Interconnection Facilities Study, a pro forma version of which constitutes Attachment 2 to Appendix IV of this TO Tariff.
3.18. Large Load Interconnection Agreement. The required agreement between DCRT and a Large Load Interconnection Customer prior to construction of Large Load Interconnection Facilities, a pro forma version of which constitutes Attachment 3 of Appendix IV of this TO Tariff.
3.19. Large Load Interconnection Application. The required application for a Large Load Interconnection Customer seeking interconnection with DCRT’s Transmission System, as described in Appendix IV to this TO Tariff. 3.20. Large Load Interconnection Customer. Any entity that proposes to interconnect a Large Load, or modify its existing interconnection, with the DCRT Transmission System.
3.21. Large Load Interconnection Facilities. All facilities and equipment between the Large Load and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Large Load to the transmission system. Interconnection Facilities are sole-use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades.
3.22. Large Load Interconnection Process (“LLIP”). The process by which Large Loads may be interconnected to DCRT’s Transmission System, as described in Appendix IV to this TO Tariff.
3.23. Large Load Interconnection Service. The service provided by the Participating TO associated with interconnecting the Large Load Interconnection Customer’s Generating Facility to the CAISO-Controlled Grid and enabling it to receive electric energy and capacity from the CAISO-Controlled Grid at the Point of Interconnection, pursuant to the terms of the Large Load Interconnection Agreement, the Participating TO’s TO Tariff, and the CAISO Tariff. 3.24. Large Load System Impact Study. The initial study conducted as part of the LLIP as described in Appendix IV to this TO Tariff, consisting of short circuit analysis, a stability analysis, a power flow analysis, and any other studies that are deemed necessary.
3.25 Large Load System Impact Study Agreement. The prerequisite agreement
PDF page 34
before DCRT will conduct, or cause to be conducted, the Large Load System Impact Study, a pro forma version of which constitutes Attachment 1 to Appendix IV of this TO Tariff.
3.26. Net FTR Revenue. The sum of: 1) The revenue received by the Participating TO from the sale, auction, or other transfer of the Financial Transmission Rights (“FTR”) provided to it pursuant to Section 9.4.3 FTR, or any substantively identical successor provision, of the CAISO Tariff; and 2) For each hour: a) the Usage Charge revenue received by the Participating TO associated with its Section 9.4.3 FTRs; minus b) Usage Charges that are: i) incurred by the Scheduling Coordinator for the Participating TO under CAISO Tariff Section 7.3.1.4, ii) associated with the Participating TO’s Section 9.4.3 FTRs, and iii) incurred by the Participating TO for its energy transactions but not incurred as a result of the use of the transmission by a third-party and minus c) the charges paid by the Participating TO pursuant to Section 7.3.1.7, to the extent such charges are incurred by the Scheduling Coordinator of the Participating TO on Congested Inter-zonal Interfaces that are associated with the Section 9.4.3 FTRs provided to the Participating TO. The component of Net FTR Revenue represented by item 2) immediately above shall not be less than zero for any hour.
3.27. Participation Agreement. An agreement between a Participating TO and a Project Sponsor that specifies the terms and conditions under which the Participating TO will construct a transmission addition or upgrade on behalf of the Project Sponsor.
3.28. Project Proponent. A Market Participant or group of Market Participants that:
(i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition and upgrade and thus is not a Project Sponsor; and (iii) initiates proceedings under the CAISO ADR Procedures to determine the need for the proposed transmission addition or upgrade. 3.29. Regional Transmission Group (“RTG”). A voluntary organization approved by FERC and composed of transmission owners, transmission users, and other entities, organized to efficiently coordinate the planning, expansion, and use of transmission on a regional and inter-regional basis.
3.30. Regulatory Authority. The Federal Energy Regulatory Commission (“FERC”), or successor agency.
3.31. Reliability Upgrade. The transmission facilities other than Direct Assignment Facilities beyond the first point of Interconnection necessary to interconnect a New Facility or wholesale Load safely and reliably to the CAISO Controlled Grid, which would not have been necessary but for the Interconnection of a New Facility or wholesale Load, including network upgrades necessary to remedy short circuit or stability problems resulting from the Interconnection of the new Facility or wholesale Load to the CAISO Controlled Grid. Reliability Upgrades also include, consistent with WECC practice, the facilities necessary to mitigate
PDF page 35
any adverse impact a New Facility’s or wholesale Load’s Interconnection may have on a path’s WECC path rating. Reliability Upgrades shall be specified in the Interconnection Agreement that governs Interconnection service and shall be subject to FERC approval.
3.32. Requests for Expedited Interconnection Procedures. A written request by which an applicant for Interconnection can request expedited processing of its Interconnection Application.
3.33. System Impact Study. An engineering study conducted by a Participating TO to determine whether a request for Interconnection to the Participating TO’s transmission system would require new transmission additions, upgrades or other mitigating measures.
3.34. System Impact Study Agreement. An agreement between a Participating TO and an entity that has requested Interconnection to the Participating TO’s transmission system pursuant to which the entity requesting Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a System Impact Study.
3.35. TO Tariff. This Transmission Owner Tariff, as it may be amended or superseded.
3.36. Transmission Revenue Balancing Account Adjustment (“TRBAA”). A mechanism established by the Participating TO which will ensure that all Transmission Revenue Credits and other credits specified in Sections 6 and 8 of CAISO Tariff, Appendix F, Schedule 3 flow through to CAISO Tariff and TO Tariff transmission customers.
3.37. Participating TO’s Transmission System. The transmission facilities owned by DCRT.
4. Eligibility. Transmission service over DCRT’s Regional Transmission Facilities and Entitlements placed under the CAISO’s Operational Control shall be provided only to Eligible Customers as defined by the CAISO Tariff. Any dispute as to whether a customer is eligible for wholesale transmission service shall be resolved by FERC.
5. Access Charges. The applicable Access Charges are provided in the CAISO Tariff. 5.1.
Transmission Revenue Requirement (“TRR”). As set forth in the CAISO Tariff, the TRR for each Participating TO is used to develop the Access Charges set forth in the CAISO Tariff, and is used by the CAISO to calculate the disbursement of wheeling revenues among Participating TOs pursuant to Section 26.1.4.3 of the CAISO Tariff. DCRT’s TRR is set forth in Appendix I. 5.2.
TRBAA. The Participating TO shall maintain a Transmission Revenue Balancing Account (“TRBA”) that will ensure that all Transmission Revenue Credits and the refunds, specified in Sections 6 and 8 of Appendix F, Schedule 3
PDF page 36
of the CAISO Tariff, flow through to transmission customers. The TRBAA shall be equal to: TRBAA = TRCF + TRCT + I.
TRCT =
The balance representing the prior period difference
between the projected Transmission Revenue Credits
and the actual credits.
TRCF =
The forecast of Transmission Revenue Credits for
the following calendar year.
I
=
The interest balance for the TRBA, which shall be
calculated using the interest rate pursuant to Section
35.19(a) of FERC’s regulations under the Federal Power
Act (18 CFR Section 35.19(a)). Interest shall be calculated
based on the average TRBA principal balance each month,
compounded quarterly.
The DCRT estimated TRBAA, calculated in accordance with the CAISO Tariff, is stated in Appendix I.
6. Ancillary Services--Applicability and Charges. If any Ancillary Services are required, DCRT will not provide such services, but transmission customers will be required to meet any such requirement in accordance with the CAISO Tariff.
7. Billing and Payment.
7.1.
Payment. The CAISO, in accordance with the CAISO Tariff, shall pay the Participating TO, among other things, Wheeling, Usage, Access Charge revenues, and FTR auction proceeds (excluding Usage Charge revenues payable to FTR Holders) in accordance with the CAISO Tariff.
7.2.
Billing. Users of DCRT’s Regional Transmission Facilities and Entitlements placed under the CAISO’s Operational Control shall pay to the CAISO all applicable charges in accordance with the CAISO Tariff.
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades.
8.1.
Participating TO Obligation to Interconnect. The Participating TO shall, at the request of a third party pursuant to Section 10, interconnect its system to the wholesale generation or load of such third party, or modify an existing wholesale Interconnection. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the FPA. Interconnections requested by entities or individuals that are not so eligible shall be governed by the Local Regulatory Authority. The procedures for Interconnection of wholesale generation to the CAISO Controlled Grid shall be governed by the CAISO Tariff.
PDF page 37
8.1.1. Interconnection to Transmission System. Interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, and CAISO reliability criteria for the CAISO Controlled Grid. The Participating TO will not accommodate the Interconnection if doing so would impair systems reliability or would otherwise impair the ability of the Participating TO to honor its Encumbrances existing as of the time an entity submits its Interconnection Application. The Participating TO shall identify any such adverse effect on its Encumbrances in the System Impact Study performed pursuant to Section 10.7. To the extent the Participating TO determines that the Interconnection will have an adverse effect on Encumbrances, the party requesting Interconnection shall mitigate such adverse effect.
8.1.1.1 Letter Agreement. Pursuant to Section 12 of Appendix DD of the ISO Tariff, prior to executing an Interconnection Agreement, a party seeking Interconnection may, in order to advance the implementation of its Interconnection, request, and the Participating TO shall offer the party, a Letter Agreement, a pro forma version of which is set forth in Appendix III to the TO Tariff, that authorizes the Participating TO to begin engineering, design, and procurement of long lead-time items, or construction necessary for the establishment of the Interconnection. However, Participating TO shall not be obligated to offer a Letter Agreement if the party seeking Interconnection is in Dispute Resolution as a result of an allegation that the party seeking Interconnection has failed to meet any milestones or comply with any prerequisites specified in the ISO Tariff. The Letter Agreement is an optional procedure. The Letter Agreement shall provide for the party seeking Interconnection to pay the cost of all activities authorized by the party and to make advance payments or provide other satisfactory security for such costs. Following a party seeking Interconnection’s request for a Letter Agreement, the Participating TO shall prepare and tender to the party seeking Interconnection a draft Letter Agreement in the form of the Participating TO’s FERC-approved Letter Agreement as set forth in Appendix III to the TO Tariff, including draft exhibits that include the proposed scope of work, estimated costs, payments, financial security and milestones, as applicable. The party seeking Interconnection shall provide written comments, or notification of no comments, to the draft exhibits within thirty (30) Calendar Days. The Participating TO and the party seeking Interconnection shall negotiate concerning any disputed provisions of the exhibits to the draft Letter Agreement for not more than ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Interconnection. If the party seeking Interconnection determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the draft Letter Agreement and request submission of the unexecuted Letter
PDF page 38
Agreement with FERC or initiate dispute resolution procedures pursuant to Section 13.10 of this TO Tariff. If the party seeking Interconnection requests termination of the negotiations, but within ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Interconnection, fails to request either the filing of the unexecuted Letter Agreement or initiate dispute resolution procedures, it shall be deemed to have withdrawn its request for a Letter Agreement and the Participating TO shall have no further obligation to enter into a Letter Agreement, unless an extension is mutually agreed to by the parties. The Participating TO shall provide to the party seeking Interconnection a final Letter Agreement within fifteen (15) Business Days after the completion of the negotiation process.
Following submission of the final Letter Agreement to the party seeking Interconnection, the party shall either: (i) execute two originals of the tendered Letter Agreement and return them to the Participating TO; or (ii) request in writing that the Participating TO file with FERC a Letter Agreement in unexecuted form. As soon as practicable, but not later than ten (10) Business Days after receiving either the two executed originals of the tendered Letter Agreement (if it does not conform with a FERC- approved Letter Agreement) or the request to file an unexecuted Letter Agreement, the Participating TO shall file the Letter Agreement with FERC, together with its explanation of any matters as to which the party seeking Interconnection and the Participating TO disagree and support for the costs that the Participating TO proposes to charge to the party seeking Interconnection under the Letter Agreement. An unexecuted Letter Agreement should contain terms and conditions deemed appropriate by the Participating TO for the Interconnection request.
If the party seeking Interconnection executes the final Letter Agreement, the Participating TO and the party seeking Interconnection shall perform their respective obligations in accordance with the terms of the Letter Agreement, subject to modification by FERC. Upon submission of an unexecuted Letter Agreement, the party seeking Interconnection and the Participating TO shall promptly comply with the unexecuted Letter Agreement, subject to modification by FERC.
8.1.2. Costs Associated with Interconnection. Each party requesting Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities and, if applicable, any Reliability Upgrades required to provide the requested Interconnection. In addition, such party shall implement all existing operating procedures necessary to safely and reliability interconnect such party’s generation or wholesale load to the facilities of the Participating TO and to ensure the CAISO Controlled Grid’s conformance with the CAISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with
PDF page 39
accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the CAISO Tariff for transmission expansions or upgrades.
8.1.3. Interconnection Agreement. Pursuant to Section 10.4, 10.7.1, or 10.9.1, a party requesting an Interconnection shall request in writing that the Participating TO tender to such part an Interconnection Agreement that will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement will include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, and construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, any Delivery Upgrades, if applicable, and for any other mitigation measures. For an Interconnection request to remain a Completed Interconnection Application, the party requesting the Interconnection shall execute the Interconnection Agreement and return it to the Participating TO within thirty (30) Business Days of receipt. Alternatively, if an Eligible Customer requesting the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the CAISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the CAISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted interconnection Agreement or commence construction of the Interconnection facilities or incur other costs under the Interconnection Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed Interconnection Agreement shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by any System Impact Study Agreement or Facilities Study Agreement. To maintain its queue position, the applicant must timely comply with the Interconnection requirements of Section 5.76 of the CAISO Tariff and Sections 8.1 and 10 of this TO Tariff. If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application or because its queue position has been
PDF page 40
modified pursuant to the queuing provisions in Section 25 of the CAISO Tariff.
8.1.4. Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Reliability Upgrades that it is obligated to construct pursuant to this TO Tariff and Section 24 of the CAISO Tariff. The Participating TO’s obligation to build will be subject to: (1) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (2) the presence of a cost recovery mechanism with cost responsibility assigned to accordance with the CAISO Tariff or applicable FERC precedent; and (3) a signed Interconnection Agreement or a signed Expedited Interconnection Agreement, or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection Agreement.
8.1.5. Energization. The Participating TO shall not be obligated to energize, nor shall the applicant or wholesale load be entitled to have its interconnection to the CAISO-Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3; or a Large Load Interconnection Agreement has been executed, or filed at FERC pursuant to Appendix IV, Section 2.5.1; and such agreement become effective and such applicant or wholesale load has demonstrated to the CAISO’s reasonable satisfaction that it has complied with all of the requirements of the CAISO Tariff and the requirements of this TO Tariff.
8.1.6. Coordination with CAISO on Interconnection Requests. The Participating TO shall coordinate with the CAISO and Affected TOs, if any, pursuant to the provisions of the TCA, in developing interconnection standards and guidelines for processing interconnection request under this TO Tariff.
8.2.
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to: (1) perform System Impact or Facility Studies where the Project Sponsor or the CAISO agrees to pay the study cost and specifies the project objectives to be achieved, and (2) build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations under Section 24 of the CAISO Tariff and this TO Tariff. 8.2.1. Obligation to Construct. Participating TO shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.2.1 hereof have been satisfied. 8.3.
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the CAISO,
PDF page 41
(including the CAISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated planning processes as to the need for or construction of a facility, the need for full cost recovery, and the allocation of costs.
9. Expansion Process.
9.1.
Determination of Facilities. A Participating TO shall perform a Facilities Study in accordance with this Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 of the CAISO Tariff and this TO Tariff; (2) a Market Participant agrees to pay the costs of the Facilities Study and specifies the project objectives to be achieved in terms of increased capacity or reduced congestion; or (3) the Participating TO is required to perform a Facilities Study pursuant to the CAISO Tariff. 9.1.1. Payment of Facilities Study Costs.
9.1.1.1. Market Participant to Pay for Facilities Study. Where a Market Participant requests a Facilities Study and the need for the transmission addition or upgrade has not yet been
established in accordance with the procedures established
herein and the CAISO Tariff, the Market Participant shall pay the cost of the Facilities Study.
9.1.1.2. Project Sponsor or Project Proponent to Pay for Facilities Study. Where the facilities to be added or upgraded have
been determined to be needed in accordance with the
procedures established herein and the CAISO Tariff, the
Project Sponsor, Project Proponent, or the CAISO requesting the study shall pay the reasonable cost of the Facilities Study. When the Participating TO is the Project Sponsor in
accordance with the CAISO Tariff, the costs of the Facilities Study shall be recovered through its Access Charges and
transmission rates.
9.1.1.3. Principal Beneficiaries to Pay for Facilities Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the CAISO or CAISO ADR Procedures in accordance with
the CAISO Tariff, the Project Sponsor and the identified
principal beneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as may be agreed, or, failing agreement, as determined in accordance with the
CAISO ADR Procedures.
9.1.2. Payment Procedure. Where a Facilities Study is being conducted pursuant to this TO Tariff, the Participating TO shall, within thirty (30) days of the receipt of all reasonably required information, tender to the
PDF page 42
Market Participant, Project Sponsor, Project Proponent, CAISO, or identified principal beneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Market Participant, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Facilities Study. If the Market Participant, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Facilities Study Agreement, they shall execute the Facilities Study Agreement and return it to the Participating TO within ten
(10) Business Days. Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Facilities Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the CAISO ADR
Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study, and the parties shall submit the disputed terms for resolution under the CAISO’s ADR Procedures. 9.1.3. Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or alternative request to proceed as provided for in Section 9.1.2, a copy of which has been provided to the CAISO by the party requesting the Facilities Study, the Participating TO will use due diligence to complete the required Facilities Study within a sixty (60) day period. If the Participating TO is unable to complete the Facilities Study in the allotted time period, the Participating TO shall notify the party requesting the Facilities Study and provide an estimate of the time needed to reach a final determination along with an explanation of the reasons that additional time is required to complete the Facilities Study. If additional time is required, the Participating TO will use best efforts to complete the Facilities Study within ten (10) months, provided adequate information is provided by all the parties.
9.2.
Obligation to Build.
9.2.1. Due Diligence to Construct. Subject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the CAISO Tariff and this TO Tariff. Alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the CAISO ADR Procedures, including any
determination by FERC or on appeal of a FERC determination in
PDF page 43
accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the CAISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement or alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the CAISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the CAISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement, commence construction of the additions or upgrades or incur other costs under the Participation Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Participation Agreement has been issued by the applicable court or regulatory authority. The Participating TO’s obligation to build will be subject to: 1) its ability, after making a good faith effort, to obtain the necessary approvals and property rights under applicable federal, state, and local laws; 2) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the CAISO Tariff; and 3) a signed Participation Agreement. The Participating TO will not construct or expand its existing or planned transmission system if doing so would impair system reliability as determined through systems analysis based on the Applicable Reliability Criteria.
9.2.2. Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify: (1) the Project Sponsor with regard to facilities determined to be needed; (2) the Parties to the Participation Agreement with regard to facilities determined to be needed pursuant to the CAISO Tariff where principal beneficiaries were identified; and (3) the CAISO. In such circumstances, the Participating TO shall, within thirty (30) days of notifying such Project Sponsor, Parties to the Participation Agreement, and the CAISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Participation Agreement, and the CAISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the CAISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives.
PDF page 44
9.2.2.1. Alternatives to the Original Facility Additions. If the review process of Section 9.2.2 determines that one or more alternatives exist to the originally planned construction project, the Participating TO shall present such alternatives for consideration to the Project Sponsor, Parties to the
Participation Agreement, and the CAISO, as the case may be. If upon review of any alternatives, such Project Sponsor, the CAISO, or Parties to the Participation Agreement wish to evaluate or to proceed with one of the alternative additions or upgrades, such Project Sponsor, the CAISO, or Parties to the Participation Agreement may request that the Participating TO prepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO Tariff. In the event the
Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Participation Agreement or the CAISO disagree, the dispute shall be resolved pursuant to the CAISO ADR Procedure
9.2.2.2. Refund Obligation for Unfinished Facility Additions. If the Participating TO and the Project Sponsor, the CAISO, or Parties to the Participation Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Regulation 35.19(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.
9.3.
Provisions Relating To Transmission Construction on the Systems of Other TOs.
9.3.1. Responsibility for Third Party Additions. Participating TO shall not be responsible for making arrangements for any engineering, permitting, and construction of any transmission or distribution facilities on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO will undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice. 9.3.2. Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the CAISO Tariff require additions or upgrades on other systems, to the extent consistent with this
PDF page 45
TO Tariff, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the CAISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Participation Agreement, and the CAISO, in writing of the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or resume construction of the new facilities. Within forty (40) Business Days of receiving written notification by the Participating TO of its intent to defer construction pursuant to this section, such Project Sponsor, Parties to the Participation Agreement, or the CAISO may challenge the decision in accordance with the CAISO ADR Procedure.
10. Interconnection Process.
10.1. Applicability. All requests for Interconnection directly to the CAISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the provisions of this Section 10, except for requests for Interconnection from Large Loads. Large Load requests for Interconnection shall be processed pursuant to Appendix IV to this Tariff. All requests for Interconnection of wholesale generation directly to the CAISO Controlled Grid shall be processed pursuant to the provisions of the CAISO Tariff.
10.2. Applications. Except as provided in Section 10.1, a party requesting Interconnection shall submit written Interconnection Application which provides the information required in Section 10.3 to the Participating TO and shall send a copy of the application to the CAISO. The Participating TO shall time-stamp the application to establish study priority.
10.3. Interconnection Application. An Interconnection Application shall provide all of the information listed in 18 C.F.R. § 2.20, including, but not limited to, the following:
(i) The identity, address, telephone number, and facsimile number of the entity requesting Interconnection;
(ii) The Interconnection point(s) to the CAISO Controlled Grid contemplated by the applicant;
(iii) The resultant (or new) maximum amount of Interconnection capacity contemplated by the applicant;
(iv) The proposed date for energizing the Interconnection and the term of Interconnection service; and
PDF page 46
(v) Such other information as the Participating TO reasonably requires to process the application.
In addition to the information specified above, the following information may also be provided in order to properly evaluate system conditions:
(vi) If the applicant is a Load, the electrical location of the source of the power (if known) to be transmitted pursuant to the applicant’s request for Interconnection. If the source of the power is not known, a system purchase will be assumed.;
(vii) The electrical location of the ultimate load (if known). If the location of the load is not known, a system sale will be assumed.;
(viii) If an applicant proposes to perform or cause a third party to perform any required System Impact Study or any required Facilities Study, it shall so indicate in its Interconnection Application. The results of any study or studies performed by an applicant or its designated third party must be approved by both the CAISO and the Participating TO.
Within ten (10) Business Days after receipt of an Interconnection Application, the Participating TO and the CAISO, if applicable, shall determine whether the application is complete (“Completed Interconnection Agreement”). Whenever possible, the Participating TO will attempt to remedy deficiencies in the Interconnection Application through informal communications with the applicant. If such efforts are unsuccessful, the Participating TO shall return the Interconnection Application to the applicant. The Participating TO will treat the information in the Interconnection Agreement, including the applicant’s identity, as confidential at the request of the applicant except to the extent that disclosure of the information is required by this TO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or CAISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations.
10.3.1. Amendment to Completed Interconnection Application. An
applicant shall only be limited to amending its Completed
Interconnection Application once. Additional amendments will be at the Participating TO’s discretion, to be permitted on a not unduly discriminatory basis and without undue preference or advantage, and the Participating TO’s agreement for applicant to make additional
amendment shall not be unreasonably withheld. Such amendment shall occur on or before ten (10) Business Days following the date the Participating TO tenders any Facilities Study Agreement. Specifically, an applicant may submit an amendment to its Completed
Interconnection Application to reflect a revised configuration for its New Facility. The amended Completed Interconnection Application
shall be treated in accordance with Section 25 of the CAISO Tariff and
PDF page 47
Section 10.5 of this TO Tariff; the applicant’s Completed
Interconnection Application shall be deemed withdrawn; and the
applicant shall maintain its existing queue position, if (a) the amended Completed Interconnection Application is received by the Participating TO within ten (10) Business Days of the Participating TO’s tender of a Facilities Study Agreement; and (b) the applicant has not submitted a previous amendment to the Completed Interconnection Application. In the event an applicant amends its Completed Interconnection
Application, it will be responsible for any additional study costs that result from that amendment, including costs associated with revisions to studies for other applicants holding later queue positions.
10.4. Review of Completed Interconnection Application. After receiving a Completed Interconnection Application, the Participating TO and the CAISO, if applicable, will determine on a non-discriminatory basis whether a System Impact Study is required. Whenever the Participating TO, and the CAISO, if applicable, determines that a System Impact Study is not required and that neither Reliability Upgrades nor changes in existing operating procedures are required, the Participating TO shall notify the applicant within fifteen (15) Business Days of the Completed Application Date. If the Interconnection can be accommodated without any Direct Assignment Facilities, then within thirty (30) Business Days of such notice from the Participating TO, the applicant shall request the Participating TO to tender to the applicant an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. If the Participating TO determines upon review of the Completed Interconnection Application, that Direct Assignment Facilities are required, the Participating TO shall tender to the applicant a Facilities Study Agreement within twenty (20) Business Days of the Completed Application Date and continue the Interconnection process pursuant to Section 10.8
10.5. Notice of Need for System Impact Study. If the Participating TO, and the CAISO if applicable, determines that a System Impact Study is necessary to accommodate the requested Interconnection, the Participating TO shall so inform the applicant as soon as practicable. In such cases, the Participating TO shall within twenty (20) Business Days of receipt of a Completed Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO, the estimated time required to complete it, and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of performing the required System Impact Study. A description of the Participating TO’s transmission assessment practices for completing a System Impact Study shall be provided in the Participating TO’s FERC Form 715. Alternatively, if the applicant will perform the System Impact Study, the Participating TO shall within twenty (20) Business Days of receipt of a Completed Interconnection Application, tender a System Impact Study Agreement that defines the scope, content,
PDF page 48
assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of reviewing the required System Impact Study. For an Interconnection request to remain a Completed Interconnection Application, the applicant shall execute the System Impact Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated cost of performing the System Impact Study or reviewing the applicant’s System Impact Study. Alternatively, if the applicant request the Participating TO to proceed with the System Impact Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the CAISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the System Impact Study provided that such request is accompanied by payment of the reasonable estimated cost of the System Impact Study, and the parties shall submit the disputed terms for resolution under the CAISO’s ADR Procedures. If the applicant elects not to execute a System Impact Study Agreement, and does not request that the Participating TO proceed with the System Impact Study or review thereof, its application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO and the CAISO all costs reasonably incurred in processing the application. 10.6. System Impact Study Cost Reimbursement and Agreement.
10.6.1. Cost Reimbursement. The System Impact Study Agreement shall clearly specify the charge for the System Impact Study, based on the Participating TO’s estimate of the cost and time for completion of the System Impact Study. The charge shall not exceed the reasonable cost of the study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any modifications to existing planning studies that are reasonably necessary to evaluate the impact of the applicant’s request.
10.6.2. Multiple Parties. If multiple parties request Interconnection at the same location, the Participating TO may conduct a single System Impact Study. The costs of that study shall be pro-rated among the parties requesting Interconnection.
10.7. System Impact Study Procedures. Upon receipt of an executed System Impact Study Agreement or initiation of the CAISO ADR Procedures and receipt of payment for estimated study costs, the Participating TO will use due diligence to
(a) complete the required System Impact Study within a sixty (60) calendar day period or (b) complete its review of an applicant’s System Impact Study within
PDF page 49
thirty (30) calendar days of its receipt of the completed study. The System Impact Study will identify whether any Direct Assignment Facilities or Reliability Upgrades are necessary to deliver a New Facility’s full output over the CAISO Controlled Grid, or any transmission additions or upgrades are necessary to serve a wholesale load. The System Impact Study will also identify any adverse impact on Encumbrances existing as of the applicant’s Completed Application Date. In the event that the Participating TO is unable to complete the required System Impact Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed System Impact Study and related work papers shall be made available to the applicant and the CAISO. The Participating TO shall notify the applicant and the CAISO immediately upon completion of the System Impact Study.
10.7.1. Procedures Upon Completion of System Impact Study. Within fifteen (15) Business Days of completion of the System Impact Study or review and approval of an applicant’s System Impact Study, the
Participating TO shall notify the applicant whether the transmission system will be adequate to accommodate all of a request for
Interconnection. If no costs are likely to be incurred for any Direct Assignment Facilities, any Reliability Upgrades, or implementing any operating procedures, then within thirty (30) Business Days of receipt of written approval of the applicant’s System Impact Study from the Participating TO and the CAISO the applicant shall request the
Participating TO to tender an Interconnection Agreement within thirty
(30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. If costs are likely to be incurred to accommodate a request for
Interconnection, the Participating TO shall tender to the applicant a Facilities Study Agreement pursuant to Section 10.8.
10.8. Notice of Need for Facilities Study. If a System Impact Study indicates that additions or upgrades to the CAISO Controlled Grid are needed to satisfy an applicant’s request for interconnection, the Participating TO shall, within fifteen
(15) Business Days of the date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study by the Participating TO, tender to the applicant a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete the required study; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of performing the required Facilities Study. Alternatively, if the applicant will perform the Facilities Study, the Participating TO shall within fifteen (15) Business Days of the completion date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study, tender a Facilities Study Agreement that defines the scope, content, assumptions
PDF page 50
and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete the required review; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of reviewing the required Facilities study. For an Interconnection request to remain a Completed Interconnection Application, the applicant shall execute the Facility Studies Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated costs of performing the Facilities Study or reviewing the applicant’s Facilities Study. Alternatively, if the applicant request the Participating TO to proceed with the Facilities Study to review thereof and commits to abide by terms, conditions, and cost assignments ultimately determined under the CAISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study provided that such request is accompanied by payment for the reasonable estimated cost of the Facilities Study, and the parties shall submit the disputed terms for resolution under the CAISO ADR Procedures. If the applicant elects not to execute a Facilities Study Agreement and does not request that the Participating TO proceed with the Facilities Study or review thereof, its application shall be deemed withdrawn and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by the System Impact Study Agreement.
10.9. Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or initiation of the CAISO ADR Procedures and receipt of payment for the estimated study costs, the Participating TO will use due diligence to either (a) complete the required Facilities Study within a sixty (60) calendar day period or
(b) complete its review of an applicant’s Facilities Study within thirty (30) calendar days of its receipt of the Completed Study. In the event that Participating TO is unable to complete the required Facilities Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed Facilities Study shall be made available to the applicant.
10.9.1. Execution of Interconnection Agreement. Within thirty (30) Business Days of receipt of the completed Facilities Study performed by the Participating TO or receipt of written approval of the applicant’s Facilities Study from the Participating TO, the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty
(30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. 10.10. Partial Interim Service. If the Participating TO determines that there will not be adequate transmission capability to satisfy the full amount requested in a Completed Interconnection Application, the Participating TO nonetheless shall be obligated to offer and provide the portion of the requested Interconnection that
PDF page 51
can be accommodated without any additional Direct Assignment Facilities or Reliability Upgrades. However, the Participating TO shall not be obligated to provide the incremental amount of requested Interconnection that requires such additional facilities or upgrades until such facilities or upgrades have been placed in service.
10.11. Expedited Procedures for New Facilities. In lieu of the procedures set forth above, the applicant shall have the option to expedite the processing of its Completed Interconnection Application. In order to exercise this option, the applicant shall submit in writing a Request for Expedited Interconnection Procedures to the Participating TO within ten (10) Business Days after receiving a copy of the System Impact Study for the proposed Interconnection. Within ten
(10) Business Days after receiving a Request for Expedited Procedures, the Participating TO shall tender an Expedited Interconnection Agreement that requires the applicant to compensate the Participating TO for all costs reasonably incurred pursuant to the terms of this TO Tariff for processing the Completed Interconnection Application and providing the requested Interconnection. While the Participating TO agrees to provide the applicant with its best estimate of the costs of any needed Direct Assignment Facilities and, if applicable, Reliability Upgrades, and such other charges that may be incurred, unless otherwise agreed by the parties, such estimate shall not be binding and the applicant must agree in writing to compensate the Participating TO for all actual Interconnection costs reasonably incurred pursuant to the provisions of this TO Tariff. The applicant shall execute and return such Expedited Service Agreement within ten (10) Business Days of its receipt or the applicant’s request for Interconnection will cease to be a Completed Interconnection Application and will be deemed terminated and withdrawn, In that event, the applicant shall reimburse the Participating TO for all costs reasonably incurred in processing the application not covered by the terms of the System Impact Study Agreement.
11. Uncontrollable Forces and Indemnification.
11.1. Procedures to Follow if Uncontrollable Force Occurs. In the event of the occurrence of an Uncontrollable Force which prevents a Party from performing any of its obligations under this TO Tariff, such Party shall (i) immediately notify the other Parties in writing of the occurrence of such Uncontrollable Force, (ii) not be entitled to suspend performance in any greater scope or longer duration than is required by the Uncontrollable Force, (iii) use its best efforts to mitigate the effects of such Uncontrollable Force, remedy its inability to perform, and resume full performance hereunder, (iv) keep the other Parties apprised of such efforts on a continual basis and (v) provide written notice of the resumption of performance hereunder. Notwithstanding any of the foregoing, the settlement of any strike, lockout, or labor dispute constituting an Uncontrollable Force shall be within the sole discretion of the Party to this TO Tariff involved in such strike, lockout, or labor dispute and the requirement that a Party must use its best efforts
PDF page 52
to remedy the cause of the Uncontrollable Force and mitigate its effects and resume full performance hereunder shall not apply to strikes, lockouts, or labor disputes. No Party will be considered in default as to any obligation under this TO Tariff if prevented from fulfilling the obligation due to the occurrence of an Uncontrollable Force.
11.2. Indemnification. A Market Participant shall at all times indemnify, defend, and save the Participating TO harmless from any and all damages, losses, claims, (including claims and actions relating to injury or to death of any person or damage to property), demands, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the Participating TO's performance of its obligations under this TO Tariff on behalf of a Market Participant, except in cases of negligence or intentional wrongdoing by the Participating TO.
12. Regulatory Filings. Nothing contained herein shall be construed as affecting, in any way, the right of DCRT to unilaterally make application to FERC as it deems necessary and appropriate to recover its TRR, or for a change in its terms and conditions, including changes in rate methodology, or for a change in designation of transmission Entitlements to be placed under the CAISO’s control, pursuant to the applicable FERC rules, regulations, policies, and governing statutes.
13. Miscellaneous.
13.1. Notices. Any notices, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person,
(ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return electronic facsimile if sent by facsimile, or (iv) upon delivery if delivered by prepaid commercial courier service, in each case addressed to a Party at the address set forth in Appendix II. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix II to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.
13.2. Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver.
13.3. Confidentiality.
PDF page 53
13.3.1. Maintaining Confidentiality if Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the documents, data, and information provided to it by any other Party that such Party may designate as confidential, provided, however, that the information will not be held confidential by the receiving Party if (1) the designating Party is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory requirements, or (2) the information becomes available to the Public on a non-confidential basis (other than from the receiving Party).
13.3.2. Disclosure of Confidential Information. Notwithstanding anything in this Section 11.3.2 to the contrary, if any Party is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to this Section 11.3.2, the Party may disclose such information; provided, however, that as soon as such Party learns of the disclosure requirement and prior to making such disclosure, such Party shall notify the affected Party or Parties of the requirement and the terms thereof. The affected Party or Parties may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Party shall cooperate with such affected Party or Parties to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Party shall cooperate with the affected Parties to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure.
13.4. Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.
13.5. Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.
13.6. Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of each Party shall be preserved until satisfied.
PDF page 54
13.7. Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California. 13.8. Appendices Incorporated. The appendices to this TO Tariff are attached to this TO Tariff and are incorporated by reference as if fully set forth herein. 13.9. Consistency with CAISO Tariff. This TO Tariff is intended to be consistent with the CAISO Tariff, and, if necessary, shall be amended to conform with any changes authorized or required in any final order in a FERC proceeding mandating such changes in the CAISO Tariff.
13.10. Disputes. Except as limited by law, the CAISO ADR Procedures shall apply to all disputes between parties which arise under this TO Tariff or under or in respect of the proposed terms and conditions of a Facilities Study Agreement, System Impact Study Agreement or Expedited Service Agreement. The CAISO ADR Procedures set forth in Section 13 of the CAISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.
PDF page 55
APPENDIX IV
Large Load Interconnection Process and Timeline
PDF page 56
2
Appendix IV
to the DCRT TO Tariff
Large Load Interconnection Process and Timeline
1.1
Applicability. This Appendix IV shall govern all requests for Interconnection submitted by Large Load Interconnection Customers seeking to interconnect a Large Load directly to the Participating TO’s Transmission System. Participating TO shall coordinate with the CAISO to implement the interconnection of a Large Load as needed pursuant to Section 4.3 to this Appendix IV. Coordination with the CAISO pursuant to Section 4.3 of this Appendix IV may require that Participating TO, Large Load Interconnection Customer and the CAISO negotiate revised deadlines for the processing of the Large Load Interconnection Customer’s interconnection request. Such revised deadlines will be included in the Large Load Interconnection Customer’s Large Load System Impact Study Agreement and Large Load Facilities Study Agreement included with these procedures as Attachments 1 and 2 to this Appendix IV, respectively.
1.2
Application Required. A Large Load Interconnection Customer shall submit a written Large Load Interconnection Application that provides the information required in Section 1.4 to this Appendix IV. The Participating TO shall time-stamp the application to establish study priority and send a copy to any other transmission providers whose transmission facilities potentially may be impacted by the interconnection of the Large Load Interconnection Customer’s Large Load based on Participating TO’s review of the application. Participating TO will also provide the Large Load Interconnection Customer’s application to the CAISO pursuant to Section 4.3.
1.3
Process Overview. Participating TO’s processing of a Large Load Interconnection Application will proceed in four stages: (1) Sufficiency Review of the Large Load Interconnection Application; (2) Large Load System Impact Study; (3), Large Load Facilities Study; and (4) negotiation of a Large Load Interconnection Agreement based on the pro forma agreement provided as Attachment 3 to this Appendix IV. In the first stage, Participating TO will review the Large Load Interconnection Application for completeness and sufficiency of the provided information, verify the submitted information, and provide an opportunity to cure any deficiencies found. In the second phase, Participating TO will execute the Large Load System Impact Study Agreement included as Attachment 1 to this Appendix IV with the Large Load Interconnection Customer; perform the Large Load System Impact Study; submit the study results to the Large Load Interconnection Customer; and conduct a study review meeting with the Large Load Interconnection Customer. In the third phase, Participating TO will execute the Large Load Facilities Study Agreement included as Attachment 2 to this Appendix IV and Participating TO will perform the Large Load Facilities Study to address detailed engineering design; submit the study results to the Large Load Interconnection Customer; and conduct a final study review meeting with the Large Load Interconnection Customer. In the fourth phase, Participating TO will negotiate and execute a Large Load Interconnection Agreement with the Large Load
PDF page 57
3
Interconnection Customer. Participating TO will coordinate with the Large Load Interconnection Customer to facilitate any studies required to determine the impact of the Large Load Interconnection Application on Affected Systems. 1.4
Interconnection Application Contents. A Large Load Interconnection Application from a Large Load Interconnection Customer shall provide the following:
(i) The identity, address, telephone number, and email address for the contacts for the entity requesting Interconnection for the relevant Large Load;
(ii) A signed copy of a Large Load System Impact Study Agreement, ready for execution by Participating TO;
(iii) At least three (3) dates/times the Large Load Interconnection Customer is available to meet with Participating TO within one (1) week of the Large Load Interconnection Application’s submission;
(iv) The Point(s) of Interconnection to the Participating TO’s system contemplated by the applicant;
(v) The resultant (or new) maximum amount of Interconnection capacity contemplated by the Large Load Interconnection Customer;
(vi) The proposed date for energizing the Large Load and the term of Large Load Interconnection Service;
(vii) The electrical location of the source of the power (if known) to be transmitted pursuant to the Large Load Interconnection Customer’s request for Interconnection. If the source of the power is not known, a system purchase will be assumed;
(viii) The electrical location of the ultimate load (if known). If the location of the load is not known, a system sale will be assumed;
(ix) Energization plans and expected in-service dates;
(x) The following physical characteristics of the prospective Large Load, sufficient to characterize expected load behavior, including: a. Load type
b. Variable or flat load designation
c. Expected hourly operating profile
d. Location of service
e. Point of delivery
PDF page 58
4
f. Connected capacity
g. Any market participation status or expected participation in demand response programs
h. Maximum operating demand
i. Minimum operating demand
j. Curtailment capability
k. Expected hourly flexibility capability
l. Ramp-up capability
m. Ramp-down capability
n. Preliminary site layout
o. Modelling inputs for steady-state and transient studies p. Location, size, and connection of every transformer and large motor q. Evidence of site control
r. Attestation by officer of accuracy of submitted Large Load Interconnection Application
(xi) Co-located resource information, if applicable:
a. Presence of co-located generation
b. Whether the resource will be fully Behind-the-Meter or may export to the CAISO Controlled Grid
c. Resource type
d. Nameplate capacity
e. Minimum and maximum operating levels
f. Market participation status
g. Associated status resource identifiers
h. All information required by the Participating TO and, as applicable, the CAISO in the Large Generator Interconnection Application
PDF page 59
5
(xii) Such other information as the Participating TO reasonably requires to process the Large Load Interconnection Application.
1.4.2 Large Load Interconnection Application Fee. A Large Load Interconnection Customer shall submit a non-refundable application fee of two-hundred- thousand dollars ($200,000).
1.4.3 Amendment to Completed Large Load Interconnection Application. A Large Load Interconnection Customer shall be limited to only amending its Large Load Interconnection Application once. Additional amendments will be at Participating TO’s discretion, to be permitted on a not unduly discriminatory basis and without undue preference or advantage, and Participating TO’s agreement for Large Load Interconnection Customer to make additional amendment shall not be unreasonably withheld. Such amendment shall occur no later than ten (10) Business Days after the date the Participating TO tenders the Large Load System Impact Study report. Specifically, a Large Load Interconnection Customer may submit an amendment to its Interconnection Application to reflect a revised configuration for its Large Load. In the event a Large Load Interconnection Customer amends its Large Load Interconnection Application, it will be responsible for any additional study costs that result from that amendment.
1.5
Withdrawal of Large Load Interconnection Application. A Large Load Interconnection Customer may withdraw its Large Load Interconnection Application at any time by providing notice to Participating TO in writing. A withdrawal shall not result in the refund of any previously paid application fees.
2. Application Processing and Timeline. The Large Load Interconnection Application will be processed under the procedures and timeline described below:
2.1
Sufficiency Review. Within five (5) Business Days of receipt of a Large Load Interconnection Application and application fee, Participating TO will complete its sufficiency review of the Large Load Interconnection Application and provide the Large Load Interconnection Customer with either a notice of sufficiency or a deficiency letter for the Large Load Interconnection Application, via email. A deficiency letter will specify the necessary changes to meet the Large Load Interconnection Application requirements.
2.1.1 Cure of Deficiency. If a Large Load Interconnection Customer receives a deficiency letter, it will have three (3) Business Days to re-submit a revised Large Load Interconnection Application curing the deficiencies identified in the deficiency letter.
2.1.2 Review of Resubmitted Large Load Interconnection Application. If the Large Load Interconnection Customer receives a deficiency letter and timely re-submits a revised Large Load Interconnection Application, within five (5) calendar days, Participating TO will conduct another sufficiency review of the
PDF page 60
6
resubmitted application and notify the Large Load Interconnection Customer of the sufficiency or deficiency of the resubmitted application. A second finding of deficiency will result in the application being deemed withdrawn. 2.2
Large Load System Impact Study. Within seven (7) calendar days of approving a completed Large Load Interconnection Application, Participating TO and Large Load Interconnection Customer shall execute the Large Load System Impact Study Agreement included in the initial Large Load Interconnection Application and conduct an initial Scoping Meeting. The system impact study will consist of a short circuit analysis, a stability analysis, a power flow analysis, and any other studies that are deemed necessary. The system impact study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested Large Load Interconnection Service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the Interconnection. The Large Load System Impact Study shall provide a list of Large Load Interconnection Facilities and Network Upgrades that are required to interconnect the relevant Large Load and provide a non-binding good faith estimate of cost responsibility and the amount of construction time required. The Large Load System Impact Study shall also identify any Affected Systems that Participating TO must coordinate with in order to interconnect the Large Load Interconnection Customer. 2.2.1 Large Load System Impact Study Fee. If the Large Load System Impact Study costs exceed the Large Load Interconnection Application Fee, the Large Load Interconnection Customer shall reimburse the Participating TO for the actual study costs that exceed the initial application fee of two-hundred- thousand dollars ($200,000).
2.2.2 Large Load System Impact Study Timeline. Within thirty (30) calendar days of execution of the Large Load System Impact Study Agreement, Participating TO, using reasonable efforts, will perform the Large Load System Impact Study, prepare and submit a study report to the Large Load Interconnection Customer, and provide the Large Load Interconnection Customer with an initial draft Large Load Interconnection Agreement reflecting the results of the Large Load System Impact Study. This draft Large Load Interconnection Agreement will be revised based on the Large Load Facilities Study described in Section 2.3. Within seven calendar (7) days of submitting the Large Load System Impact Study report to the Large Load Interconnection Customer, using reasonable efforts, Participating TO will schedule a meeting with the Large Load Interconnection Customer and the CAISO, as applicable pursuant to Section 4.3, to review the results of the Large Load System Impact Study. 2.3
Large Load Facilities Study. The Large Load Facilities Study will be used to create the detailed design of the interconnection facilities used to interconnect the Large Load to the Participating TO’s facilities, based on the findings of the Large Load System Impact Study.
PDF page 61
7
2.3.1 Large Load Facilities Study Timeline. The Large Load Interconnection Customer will have seven (7) calendar days after receiving the Large Load System Impact Study results to execute a Large Load Facilities Study Agreement with Participating TO or its Large Load Interconnection Application will be deemed withdrawn. Within thirty (30) calendar days of execution of the Large Load Facilities Study Agreement, using reasonable efforts, Participating TO will conduct the Large Load Facilities Study and submit the study report to the Large Load Interconnection Customer.
2.3.2 Large Load Facilities Study Fee. The Large Load Interconnection Customer shall submit a non-refundable study fee of two-hundred thousand dollars ($200,000) upon execution of the Large Load Facilities Study Agreement. If the Large Load Facilities Study costs exceed the study fee, the Large Load Interconnection Customer shall promptly reimburse the Participating TO for the actual study costs that exceed the default study fee.
2.4
Consideration of Alternative Transmission Technologies. The Large Load System Impact Study and Large Load Facilities Study will consider both traditional Network Upgrades and Alternative Transmission Technologies when evaluating options for reliably interconnecting the Large Load. Alternative Transmission Technologies to be studied will include, as applicable, static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, and tower lifting. The Participating TO’s studies, will select the best available transmission solution to interconnect Large Load. If a traditional Network Upgrade solution is selected instead of Alternative Transmission Technologies, the Participating TO will explain why Alternative Transmission Technologies are not feasible (i.e., would not resolve reliability violations identified or meet the relevant planning criteria) or would not result in lower costs or a faster timeline for accommodating the interconnection of the Large Load.
2.5
Large Load Interconnection Agreement.
2.5.1 Large Load Interconnection Agreement Timeline. Within sixty (60) calendar days of receipt of the Large Load Facilities Study report, Large Load Interconnection Customer shall execute a Large Load Interconnection Agreement with Participating TO or request that an unexecuted Large Load Interconnection Agreement be filed with FERC for resolution of any dispute over the terms of the Large Load Interconnection Agreement, or the Large Load Interconnection Application will be deemed withdrawn.
2.5.2 Large Load Interconnection Agreement Signatories and Terms. The Large Load Interconnection Agreement will be negotiated between the Large Load Interconnection Customer and Participating TO, with, the CAISO also signing, as applicable pursuant to Section 4.3. The Large Load Interconnection Agreement will obligate the Large Load Interconnection Customer to pay the cost of interconnecting the Large Load to the Participating TO’s system,
PDF page 62
8
including procurement, construction, and commissioning of the interconnection facilities based on the terms within the Large Load Interconnection Agreement. Participating TO will not perform any procurement or construction associated with interconnecting the Large Load until the Large Load Interconnection Agreement is executed and all funding identified in the Large Load Interconnection Agreement is received. The Large Load Interconnection Agreement will address reimbursement to the Large Load Interconnection Customer for any Network Upgrades.
2.5.3 Construction of Interconnection Facilities. Based on the designs produced by the Large Load Facilities Study, Participating TO will procure necessary equipment, and construct the interconnection facilities required to interconnect the Large Load to the Participating TO’s system.
2.6
Interconnection Financial Security Agreements. A Large Load Interconnection Customer intending to proceed with interconnection shall post financial security according to the timelines identified in Attachment 4 to this Appendix IV, or its application will be deemed withdrawn.
2.6.1 Initial Postings. Within ninety (90) calendar days of receipt of the Facilities Study report, a Large Load Interconnection Customer shall execute separate Interconnection Financial Security Agreements and post financial security for each of: 1) its assigned Network Upgrades; and 2) its Interconnection Facilities. 2.6.2 Second Postings. Second postings and amended Interconnection Financial Security Agreements are required no later than thirty (30) calendar days prior to the date on which the Facilities Study report provides that such amounts will be needed to fund long lead time equipment procurement as part of the Construction Activities (as defined in Attachment 4) for the Network Upgrades (as defined in Attachment 3) or the Participating TO’s Interconnection Facilities, whichever is earlier.
2.6.3 Third Postings. No later than thirty (30) calendar days after the date on which the Participating TO provides notice that Participating TO is obligated to provide security needed to fund any additional obligations for Network Upgrades (as defined in Attachment 3) or Participating TO’s Interconnection Facilities on behalf of the Large Load Interconnection Customer, whichever is earlier, the Large Load Interconnection Customer shall modify the two separate Interconnection Financial Security instruments.
3. Flexible Interim Load Interconnection Service.
3.1
Availability of Flexible Interim Load Interconnection Service. If a Large Load System Impact Study conducted for a Large Load Interconnection Customer shows that the Large Load cannot be reliably served at its full requested demand until certain Network Upgrades are completed, Participating TO may, at the Large Load Interconnection Customer’s request offer FILI Service. Based on the study results,
PDF page 63
9
Participating TO, and, as applicable, the CAISO pursuant to Section 4.3, may propose a customized plan for the Large Load Interconnection Customer based on the type of constraints required to maintain Transmission System reliability. Such constraints may require flexibility in demand by the Large Load or any other conditions that Participating TO and, as applicable, the CAISO determine are necessary to maintain reliability. The Large Load Interconnection Customer may participate in the design of the FILI Service constraints. Once the required Network Upgrades necessary to serve the Large Load at its full requested demand are complete, the Large Load Interconnection Customer may elect to receive firm service. The scope of any FILI offered to the Large Load Interconnection Customer will be memorialized in the Large Load Interconnection Agreement.
4. Participating TO Obligation to Provide Interconnection Service.
4.1
Interconnection to Transmission System. Interconnection Services for Large Loads must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, the Participating TO’s reliability criteria and, as applicable, the CAISO reliability criteria for the CAISO Controlled Grid. The Participating TO will not provide Large Load Interconnection Services to the Large Load Interconnection Customer if doing so would impair reliability. 4.2
Energization. The Participating TO shall not be obligated to energize, nor shall the Large Load Interconnection Customer be entitled to have its interconnection to the Participating TO’s system energized, unless and until a Large Load Interconnection Agreement has been executed, or filed at FERC pursuant to Section 2.5.1 and becomes effective and such Large Load Interconnection Customer has demonstrated to the Participating TO’s reasonable satisfaction that it has complied with all of the requirements of the of the Participating TO’s Tariff, and, as applicable, the CAISO Tariff.
4.3
Coordination with the CAISO on Interconnection Requests. Participating TO reserves the right to coordinate with the CAISO to the extent that the interconnection of a Large Load may impact the reliability of the CAISO controlled transmission system. The potential injection of any power from a Large Load to the Participating TO’s Transmission System, including but not limited to the injection of power to the Participating TO’s Transmission System resulting from the colocation of generation with the Large Load facility, shall require that the Participating TO coordinate with the CAISO to ensure that the Large Load’s interconnection complies with the CAISO Tariff.
4.4
Coordination with Affected Systems. Participating TO will coordinate with the Large Load Interconnection Customer to facilitate any studies required to determine the impact of the Large Load Interconnection Application on Affected Systems. Participating TO may provide a copy of the Large Load System Impact Study and Large Load Facilities Study results to an Affected System Operator and the Western Electricity Coordinating Council. Requests for review and input from Affected System Operators or the Western Electricity Coordinating Council may arrive at any time prior
PDF page 64
10
to interconnection. If interconnecting the Large Load Interconnection Customer requires upgrades to any Affected Systems, Large Load Interconnection Customer must enter into a construction and reimbursement agreement with the owner of any Affected System and/or other affected owners of portions of the CAISO Controlled Grid that govern facilities built on the relevant Affected System, pursuant to the tariff or procedures of the Affected System owner.
PDF page 65
Appendix IV
Attachment 1
Large Load System Impact Study Agreement
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 66
2
Attachment 1
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
LARGE LOAD SYSTEM IMPACT STUDY AGREEMENT
[LARGE LOAD INTERCONNECTION CUSTOMER]
AND
DCR TRANSMISSION, L.L.C.
THIS AGREEMENT is made and entered into this day of ___________, 20__ by and between ___________, a ___________ organized and existing under the laws of the State/Commonwealth of___________, (“Large Load Interconnection Customer”) and DCR Transmission, L.L.C., a limited liability company, organized and existing under the laws of the State of Delaware, (“DCRT” or “Participating TO”). The Large Load Interconnection Customer and DCRT each may be referred to as a “Party,” or collectively as the “Parties.” RECITALS
WHEREAS, Large Load Interconnection Customer is proposing to develop a Large Load Facility or Large Load Facility expansion to an existing Large Load Facility consistent with the Large Load Interconnection Application submitted by the Large Load Interconnection Customer dated
; and
WHEREAS, the Large Load Interconnection Customer desires to interconnect the Large Load Facility with the California Independent System Operator Corporation (“CAISO”) Controlled Grid pursuant to the Large Load Interconnection Process; and
WHEREAS, the Large Load Interconnection Customer has requested DCRT to conduct or cause to be performed a Large Load System Impact Study to assess the system impact of interconnecting the Large Load Facility to the CAISO Controlled Grid and to specify and estimate the cost of the equipment, engineering, procurement and construction work needed on the Participating TO’s electric system in accordance with Good Utility Practice to physically and electrically connect the Large Load Facility to the CAISO Controlled Grid; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agree as follows:
1.0
When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in DCRT’s Federal Energy Regulatory Commission (“FERC”)-approved Large Load Interconnection Process in the DCRT Tariff, or the Master Definitions Supplement, Appendix A to the CAISO Tariff, as
applicable.
PDF page 67
3
2.0
The Large Load Interconnection Customer elects and DCRT shall conduct or cause to be performed a Large Load System Impact Study in accordance with the DCRT Tariff, Appendix IV.
3.0
The scope of the applicable Large Load System Impact Study shall be subject to the assumptions set forth in Appendices A and B to this Agreement. 4.0
The Large Load System Impact Study will be based upon the technical information provided by the Large Load Interconnection Customer in the Large Load Interconnection Application, as may be modified as the result of the Scoping Meeting, subject to any modifications in accordance with Section 1.4.2 of the DCRT Tariff, Appendix IV and modifications to the proposed Commercial Operation Date of the Large Load Facility permitted by the Large Load Interconnection Process. DCRT reserves the right to request additional technical information from the Large Load Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the Large Load System Impact Study. If the Large Load Interconnection Customer modifies its designated Point of Interconnection, Large Load Interconnection Application, or the technical information provided therein is modified, the Large Load System Impact Study may be modified as specified in the DCRT Tariff, Appendix IV.
5.0
The Large Load System Impact Study report shall provide the information specified in the Large Load Interconnection Process.
6.0
The Large Load Interconnection Customer shall provide a Large Load Interconnection Application fee for the performance of the Large Load System Impact Study in accordance with the provisions of Section 1.4.1 of the Large Load Interconnection Process.
7.0
Pursuant to Section 4.4 of the Large Load Interconnection Process, DCRT will coordinate with the Large Load Interconnection Customer to facilitate any studies required to determine the impact of the Large Load Interconnection Application on Affected Systems. DCRT may provide a copy of the system impact and facilities study results to an Affected System Operator and the Western Electricity Coordinating Council. Requests for review and input from Affected System Operators or the Western Electricity Coordinating Council may arrive at any time prior to interconnection.
8.0
Substantial portions of technical data and assumptions used to perform the Large Load System Impact Study, such as system conditions, existing and planned generation, and unit modeling, may change after DCRT provides the Large Load System Impact Study results to the Large Load Interconnection Customer. Large Load System Impact Study results will reflect available data at the time DCRT provides the system impact and facilities study report to the Large Load Interconnection Customer. DCRT shall not be responsible for any additional costs, including, without limitation, costs of new or additional facilities, system upgrades,
PDF page 68
4
or schedule changes, that may be incurred by the Large Load Interconnection Customer as a result of changes in such data and assumptions.
9.0
DCRT shall maintain records and accounts of all costs incurred in performing the Large Load System Impact Study in sufficient detail to allow verification of all costs incurred, including associated overheads. The Large Load Interconnection Customer shall have the right, upon reasonable notice, within a reasonable time at DCRT’s offices and at its own expense, to audit DCRT’s records as necessary and as appropriate in order to verify costs incurred by DCRT. Any audit requested by the Large Load Interconnection Customer shall be completed, and written notice of any audit dispute provided to DCRT representative, within one hundred eighty (180) calendar days following receipt by the Large Load Interconnection Customer of DCRT’s notification of the final costs of the Interconnection Study. 10.0 In accordance with Section 1.5 of the Large Load Interconnection Process, the Large Load Interconnection Customer may withdraw its Large Load
Interconnection Application at any time by written notice to DCRT. Within ninety (90) days of receiving the withdrawal notice of the Large Load Interconnection Application, DCRT will refund the unused amount of the Large Load Interconnection Study Application fee to the Large Load Interconnection Customer.
11.0 This Agreement shall become effective upon the date the fully executed Agreement is submitted to the Large Load Interconnection Customer by DCRT.
12.0
Miscellaneous.
12.1
Dispute Resolution. Any dispute, or assertion of a claim, arising out of or in connection with this Agreement, shall be resolved in accordance with Section 13.10 of the DCRT Tariff.
12.2
Confidentiality. Confidential Information shall be treated in accordance with Section 13.3 of the DCRT Tariff.
12.3
Binding Effect. This Agreement and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto.
12.4
Conflicts. In the event of a conflict between the body of this Agreement and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this Agreement shall prevail and be deemed the final intent of the Parties. 12.5
Rules of Interpretation. This Agreement, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person’s successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this Agreement, and reference to a person in a particular
PDF page 69
5
capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this Agreement), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof; (4) reference to any applicable laws and regulations means such applicable laws and regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article or Section of this Agreement or such Appendix to this Agreement, as the case may be; (6) “hereunder”, “hereof”, “herein”, “hereto” and words of similar import shall be deemed references to this Agreement as a whole and not to any particular Article, Section, or other provision hereof or thereof; (7) “including” (and with correlative meaning “include”) means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, “from” means “from and including”, “to” means “to but excluding” and “through” means “through and including”.
12.6
Entire Agreement. This Agreement, including all Appendices and Schedules attached hereto, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, any Party’ s compliance with its obligations under this Agreement.
12.7
No Third-Party Beneficiaries. This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.
12.8
Waiver. The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party. Any waiver at any time by either Party of its rights with respect to this Agreement shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this Agreement. Termination or default of this Agreement for any reason by the Large Load Interconnection Customer shall not constitute a waiver of the Large Load Interconnection Customer’s legal rights to obtain an interconnection from the Participating TO. Any waiver of this Agreement shall, if requested, be provided in writing. Any waivers at any time by any Party of its rights with respect to any default under this Agreement, or with respect to any other matter arising in connection with this
PDF page 70
6
Agreement, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this Agreement. Any delay, short of the statutory period of limitations, in asserting or enforcing any right under this Agreement shall not constitute or be deemed a waiver of such right. 12.9
Headings. The descriptive headings of the various Articles and Sections of this Agreement have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this Agreement. 12.10 Multiple Counterparts. This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.
12.11 Amendment. The Parties may by mutual agreement amend this Agreement by a written instrument duly executed by both of the Parties.
12.12 Modification by the Parties. The Parties may by mutual agreement amend the Appendices to this Agreement by a written instrument duly executed by both of the Parties. Such amendment shall become effective and a part of this Agreement upon satisfaction of all applicable laws and regulations.
12.13 Reservation of Rights. DCRT shall have the right to make a unilateral filing with FERC to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under section 205 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder, and Large Load Interconnection Customer shall have the right to make a unilateral filing with FERC to modify this Agreement pursuant to section 206 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by another Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this Agreement shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.
12.14 No Partnership. This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon any Party. No Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, another Party.
12.15 Assignment. This Agreement may be assigned by a Party only with the written consent of the other Party; provided that a Party may assign this Agreement without the consent of the other Party to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement; and provided further
PDF page 71
7
that the Large Load Interconnection Customer shall have the right to assign this Agreement, without the consent of the other Party, for collateral security purposes to aid in providing financing for the Large Load Facility, provided that the Large Load Interconnection Customer will require any secured party, trustee or mortgagee to notify the other Party of any such assignment. Any financing arrangement entered into by the Large Load Interconnection Customer pursuant to this Section will provide that prior to or upon the exercise of the secured party’s, trustee’s or mortgagee’s assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify the other Party of the date and particulars of any such exercise of assignment right(s). Any attempted assignment that violates this Section is void and ineffective. Any assignment under this Agreement shall not relieve a Party of its obligations, nor shall a Party’s obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. DCR Transmission, L.L.C.
By:
Printed Name:
Title:
Date:
[Insert name of the Large Load Interconnection Customer]
By:
Printed Name:
Title:
Date:
PDF page 72
Appendix A
ASSUMPTIONS USED IN CONDUCTING THE
SYSTEM IMPACT STUDY
The system impact and facilities study will be based upon the information set forth in the Large Load Interconnection Application and agreed upon in the Scoping Meeting held on __________, subject to any modifications in accordance with Section 1.4.2 of the Large Load Interconnection Process, and the following assumptions:
Designation of Point of Interconnection and configuration to be studied.
[Fill out with application requirements from Appendix IV]
PDF page 73
Appendix B
Data Form, Pre-System Impact
DATA FORM TO BE PROVIDED BY THE LARGE LOAD IS APPLICANT
PRIOR TO COMMENCEMENT OF THE LARGE LOAD SYSTEM IMPACT STUDY
Large Load Facility size (MW):
Provide two (2) copies of this completed form and other required plans and diagrams in accordance with Section 1.2 of the Large Load Interconnection Process.
Provide location plan and one-line diagram of the plant and station facilities. For staged projects, please indicate future facility plans, transmission circuits, etc.
One set of metering is required for each generation connection to the new bus or existing CAISO Controlled Grid station. Number of grid connections:
On the one line indicate the demand attached at each metering location. (Maximum load on CT/PT) On the one-line indicate the location of auxiliary power. (Minimum load on CT/PT) Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes No Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant load?
Yes
No
(Please indicate on one-line).
What type of control system or PLC will be located at the Large Load Interconnection Customer’s Large Load Facility?
What protocol does the control system or PLC use?
Please provide a 7.5-minute quadrangle of the site. Sketch the facility, station, transmission line, and property line.
Physical dimensions of the proposed interconnection station:
Bus length from load to interconnection station:
Line length from interconnection station to the Participating TO’s transmission line. Tower number observed in the field. (Painted on tower leg)*:
Number of third-party easements required for transmission lines*:
PDF page 74
* To be completed in coordination with the Participating TO or the CAISO. Local service provider for auxiliary and other power:
Please provide proposed schedule dates:
Environmental survey start:
Environmental impact report submittal:
Procurement of project equipment:
Begin Construction Date:
In-Service Date:
Trial Operation Date:
Commercial Operation Date:
Requested Level of Interconnection Service: Choose one of the following:
Firm Service Only
Flexible Interim Load Interconnection (FILI) Service, as applicable Please provide any additional modification request pursuant to Section 1.4.2 of Appendix IV of the DCRT Tariff.
PDF page 75
Appendix IV
Attachment 2
Large Load Facilities Study Agreement
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 76
2
Attachment 2
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
LARGE LOAD FACILITIES STUDY AGREEMENT AND DATA FORM TO BE
PROVIDED BY THE LARGE LOAD INTERCONNECTION STUDY APPLICANT
PRIOR TO COMMENCEMENT OF THE INTERCONNECTION FACILITIES STUDY
[LARGE LOAD INTERCONNECTION CUSTOMER]
AND
DCR TRANSMISSION, L.L.C.
THIS AGREEMENT is made and entered into this day of ___________, 20__ by and between ___________, a ___________ organized and existing under the laws of the State/Commonwealth of___________, (“Large Load Interconnection Customer”) and DCR Transmission, L.L.C., a limited liability company, organized and existing under the laws of the State of Delaware, (“DCRT”, or “Participating TO”). The Large Load Interconnection Customer and DCRT each may be referred to as a “Party,” or collectively as the “Parties.” RECITALS
WHEREAS, Large Load Interconnection Customer is proposing to develop a Large Load Facility or Large Load Facility expansion to an existing Large Load Facility consistent with the Large Load Interconnection Application submitted by the Large Load Interconnection Customer dated
; and
WHEREAS, the Large Load Interconnection Customer desires to interconnect the Large Load Facility with the CAISO Controlled Grid pursuant to the Large Load Interconnection Process; and
WHEREAS, the Large Load Interconnection Customer has requested DCRT to conduct or cause to be performed a Large Load Facilities Study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed on the Participating TO’s electric system in accordance with Good Utility Practice to physically and electrically connect the Large Load Facility to the CAISO Controlled Grid;
NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agree as follows:
1.0
When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in DCRT’s Federal Energy Regulatory Commission (“FERC”)- approved Large Load Interconnection Process in DCRT Tariff, Appendix IV thereto, or the Master Definitions Supplement, Appendix A to the CAISO Tariff, as applicable.
2.0
The Large Load Interconnection Customer elects and DCRT shall conduct or cause to be performed a Large Load Facilities Study in accordance with the DCRT Tariff, Appendix IV.
PDF page 77
3
3.0
The scope of the Large Load Facilities Study will be subject to the assumptions set forth in and the data provided with this Agreement.
4.0
The Large Load Facilities Study Report: (i) will provide a description, estimated cost of (consistent with Attachment A), schedule for required facilities to interconnect the Large Load Facility to the CAISO Controlled Grid; (ii) will address the issues identified in the voltage, short circuit, stability, and power flow studied conducted as a part of the Large Load System Impact Study; and (iii) will reflect the evaluation of alternative transmission technologies in accordance with Section 2.4 of the DCRT Tariff, Appendix IV, including, if traditional Network Upgrades are selected instead of alternative transmission technologies, an explanation of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline.
5.0
Large Load Interconnection Customer will provide a Large Load Facilities Study fee for the performance of the Large Load Facilities Study in accordance with the provisions of Section 2.3.2 of the Large Load Interconnection Process. The time for completion of the Large Load Facilities Study is specified in the Large Load Interconnection Process in DCRT Tariff, Appendix IV.
6.0
Miscellaneous.
6.1
Dispute Resolution. Any dispute, or assertion of a claim, arising out of or in connection with this Agreement, shall be resolved in accordance with Section 13.10 of the DCRT Tariff.
6.2
Confidentiality. Confidential Information shall be treated in accordance with
Section 13.3 of the DCRT Tariff.
6.3
Binding Effect. This Agreement and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto. 6.4
Conflicts. In the event of a conflict between the body of this Agreement and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this Agreement shall prevail and be deemed the final intent of the Parties.
6.5
Rules of Interpretation. This Agreement, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person’s successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this Agreement, and reference to a person in a particular capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this Agreement), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof;
(4) reference to any applicable laws and regulations means such applicable laws and regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article or Section of this Agreement or such Appendix to this Agreement, as the case may be; (6) “hereunder”, “hereof”,
PDF page 78
4
“herein”, “hereto” and words of similar import shall be deemed references to this Agreement as a whole and not to any particular Article, Section, or other provision hereof or thereof; (7) “including” (and with correlative meaning “include”) means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, “from” means “from and including”, “to” means “to but excluding” and “through” means “through and including”.
6.6
Entire Agreement. This Agreement, including all Appendices and Schedules
attached hereto, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, any Party’s compliance with its obligations under this Agreement.
6.7
No Third-Party Beneficiaries. This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns. 6.8
Waiver. The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.
Any waiver at any time by either Party of its rights with respect to this Agreement shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this Agreement. Termination or default of this Agreement for any reason by the Large Load Interconnection Customer shall not constitute a waiver of the Large Load Interconnection Customer’s legal rights to obtain an interconnection from the Participating TO. Any waiver of this Agreement shall, if requested, be provided in writing.
Any waivers at any time by any Party of its rights with respect to any default under this Agreement, or with respect to any other matter arising in connection with this Agreement, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this Agreement. Any delay, short of the statutory period of limitations, in asserting or enforcing any right under this Agreement shall not constitute or be deemed a waiver of such right. 6.9
Headings. The descriptive headings of the various Articles and Sections of this Agreement have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this Agreement.
6.10
Multiple Counterparts. This Agreement may be executed in two (2) or more
counterparts, each of which is deemed an original but all constitute one and the same instrument. 6.11
Amendment. The Parties may by mutual agreement amend this Agreement by a
written instrument duly executed by both of the Parties.
PDF page 79
5
6.12
Modification by the Parties. The Parties may by mutual agreement amend the
Appendices to this Agreement by a written instrument duly executed by both of the Parties. Such amendment shall become effective and a part of this Agreement upon satisfaction of all applicable laws and regulations.
6.13
Reservation of Rights. DCRT shall have the right to make a unilateral filing with FERC to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under section 205 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder, and Large Load Interconnection Customer shall have the right to make a unilateral filing with FERC to modify this Agreement pursuant to section 206 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by another Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this Agreement shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.
6.14
No Partnership. This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon any Party. No Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, another Party.
6.15
Assignment. This Agreement may be assigned by a Party only with the written
consent of the other Party; provided that a Party may assign this Agreement without the consent of the other Party to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement; and provided further that the Large Load Interconnection Customer shall have the right to assign this Agreement, without the consent of the other Party, for collateral security purposes to aid in providing financing for the Large Load Facility, provided that the Large Load Interconnection Customer will require any secured party, trustee or mortgagee to notify the other Party of any such assignment. Any financing arrangement entered into by the Large Load Interconnection Customer pursuant to this Section will provide that prior to or upon the exercise of the secured party’s, trustee’s or mortgagee’s assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify the other Party of the date and particulars of any such exercise of assignment right(s). Any attempted assignment that violates this Section is void and ineffective. Any assignment under this Agreement shall not relieve a Party of its obligations, nor shall a Party’s obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.
PDF page 80
6
IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. DCR Transmission, L.L.C.
By:
Title:
Date:
Large Load Interconnection Customer
By:
Title:
Date:
PDF page 81
Appendix IV
Attachment 3
Large Load Interconnection Agreement
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 82
i
TABLE OF CONTENTS
Page
ARTICLE 1. DEFINITIONS … 2 ARTICLE 2. EFFECTIVE DATE, TERM AND TERMINATION … 8
2.1
Effective Date … 8 2.2
Term of Agreement … 8 2.3
Termination Procedures … 8 2.3.1
Written Notice … 8 2.3.2
Default … 8 2.3.3
Suspension of Work … 8 2.4
Termination Costs … 8 2.5
Disconnection … 10 2.6
Survival … 10 ARTICLE 3. REGULATORY FILINGS AND CAISO TARIFF COMPLIANCE … 10
3.1
Filing … 10 3.2
Agreement Subject to CAISO Tariff … 10 ARTICLE 4. SCOPE OF SERVICE … 10 4.1
Large Load Interconnection Service … 10 4.2
Provision of Service … 11 4.3
Performance Standards … 11 4.4
No Transmission Service … 11 ARTICLE 5. LARGE LOAD INTERCONNECT CUSTOMER’S INTERCONNECTION
FACILITIES ENGINEERING, PROCUREMENT, AND CONSTRUCTION … 11
5.1
Design Requirements … 11 5.1.1
Standard Option … 11 5.2
Liquidated Damages … 12 5.3
Reserved … 12 5.4
Equipment Procurement … 13 5.5
Construction Commencement … 13 5.6
Work Progress … 13 5.7
Information Exchange … 13 5.8
Limited Operation … 14 5.9
Large Load Interconnection Customer’s Interconnection Facilities … 14
5.9.1
Large Load Facility and Large Load Interconnection Customer’s
Interconnection Facilities Specifications … 14
5.9.2
Participating TO’s Review … 14 5.9.3
Large Load Interconnection Customer’s Interconnection Facilities
Construction … 15 5.10
Participating TO’s Interconnection Facilities Construction … 15 5.11
Access Rights … 15
PDF page 83
ii
5.12
Lands of Other Property Owners … 16 5.13
Permits … 16 5.14
Suspension … 16 5.15
Taxes … 16 5.15.1
Large Load Interconnection Customer Payments Not Taxable … 16
5.15.2
Representations And Covenants … 17 5.15.3
Indemnification for the Cost Consequence of Current Tax Liability Imposed
Upon the Participating TO … 17 5.15.4
Tax Gross-Up Amount … 18 5.15.5
Private Letter Ruling or Change or Clarification of Law … 18
5.15.6
Subsequent Taxable Events … 19 5.15.7
Contests … 19 5.15.8
Refund … 20 5.15.9
Taxes Other Than Income Taxes … 21 5.16
Tax Status … 22 ARTICLE 6. LARGE LOAD INTERCONNECTION TESTING AND INSPECTION … 22
6.1
Pre-Commercial Operation Date Testing and Modifications … 22 6.2
Post-Commercial Operation Date Testing and Modifications … 22 6.3
Right to Observe Testing … 22 6.4
Right to Inspect … 22 ARTICLE 7. METERING … 23 7.1
General … 23 7.2
Check Meters … 23 7.3
Participating TO Retail Metering … 23 ARTICLE 8. COMMUNICATIONS … 23 8.1
Large Load Interconnection Customer Obligations … 23 8.2
Remote Terminal Unit … 24 8.3
No Annexation … 24 ARTICLE 9. LARGE LOAD INTERCONNECTION CUSTOMER OPERATIONS … 24
9.1
General … 24 9.2
Participating TO Obligations … 24 9.3
Large Load Interconnection Customer Obligations … 24 9.4
Reactive Power and Primary Frequency Response … 25 9.5
Disconnection from the Grid … 25 9.6
Outages and Interruptions … 25 9.6.1
Outages … 25 9.6.1.1
Outage Authority and Coordination … 25
9.6.1.2
Outage Schedules … 25
9.6.1.3
Outage Restoration … 25
9.6.2
Interruption of Service … 26 9.6.3
Under-Frequency and Over-Frequency Conditions … 26
9.6.4
System Protection and Other Control Requirements … 27
9.6.4.1
System Protection Facilities … 27
PDF page 84
iii
9.6.5
Requirements for Protection … 28 9.6.6
Power Quality … 28 9.7
Switching and Tagging Rules … 28 9.8
Use of Interconnection Facilities by Third Parties … 29 9.8.1
Purpose of Interconnection Facilities … 29
9.8.2
Third Party Users … 29 9.9
Disturbance Analysis Data Exchange … 29 ARTICLE 10. MAINTENANCE … 29 10.1
Participating TO Obligations … 29 10.2
Large Load Interconnection Customer Obligations … 29 10.3
Coordination … 30 10.4
Secondary Systems … 30 10.5
Operating and Maintenance Expenses … 30 ARTICLE 11. PERFORMANCE OBLIGATION … 30 11.1
Large Load Interconnection Customer’s Interconnection Facilities … 30
11.2
Participating TO’s Interconnection Facilities … 30 11.3
Network Upgrades and Distribution Upgrades … 30 11.3.1
Reimbursement for Network Upgrades … 31
11.3.2
Repayment of Amounts Advanced for Network Upgrades … 31
11.3.2.1
Repayment Schedule … 31
11.3.2.2
Interest Payments and Assignment Rights … 31
11.3.2.3
Failure to Achieve Commercial Operation … 32
11.3.2.4
Accelerated Reimbursement Against Reimbursement Security … 32
11.3.3
Special Provisions for Affected Systems … 33
11.4
Provision of Interconnection Financial Security … 34 ARTICLE 12. INVOICE … 34 12.1
General … 34 12.2
Final Invoice … 34 12.3
Payment … 35 12.4
Disputes … 35 ARTICLE 13. EMERGENCIES … 36 13.1
[Reserved] … 36 13.2
Obligations … 36 13.3
Notice … 36 13.4
Immediate Action … 36 13.5
Participating TO Authority … 36 13.5.1
General … 36 13.5.2
Reduction and Disconnection … 37 13.6
Large Load Interconnection Customer Authority … 37 13.7
Limited Liability … 37 ARTICLE 14. REGULATORY REQUIREMENTS AND GOVERNING LAWS … 37
14.1
Regulatory Requirements … 37
PDF page 85
iv
14.2
Governing Law … 38 ARTICLE 15. NOTICES … 38 15.1
General … 38 15.2
Billings and Payments … 38 15.3
Alternative Forms of Notice … 38 15.4
Operations and Maintenance Notice … 38 ARTICLE 16. FORCE MAJEURE … 39 16.1
Force Majeure … 39 ARTICLE 17. DEFAULT … 39 17.1
Default … 39 17.1.1
General … 39 17.1.2
Right to Terminate … 39 ARTICLE 18. INDEMNITY, CONSEQUENTIAL DAMAGES, AND INSURANCE … 40
18.1
Indemnity … 40 18.1.1
Indemnified Party … 40 18.1.2
Indemnifying Party … 40 18.1.3
Indemnity Procedures … 40 18.2
Consequential Damages … 41 18.3
Insurance … 41 18.3.1
Workers’ Compensation Insurance and Employers’ Liability … 41
18.3.2
Commercial General Liability Insurance … 41
18.3.3
Business Automobile Liability Insurance … 42
18.3.4
Excess Liability Insurance … 42 18.3.8
[Not Used.] … 43 ARTICLE 19. ASSIGNMENT … 44 19.1
Assignment … 44 ARTICLE 20. SEVERABILITY … 44 20.1
Severability … 44 ARTICLE 21. COMPARABILITY … 44 21.1
Comparability … 44 ARTICLE 22. CONFIDENTIALITY … 45 22.1
Confidentiality … 45 22.1.1
Term … 45 22.1.2
Scope … 45 22.1.3
Release of Confidential Information … 45
22.1.4
Rights … 46 22.1.5
No Warranties … 46 22.1.6
Standard of Care … 46 22.1.7
Order of Disclosure … 46 22.1.8
Termination of Agreement … 46
PDF page 86
v
22.1.9
Remedies … 46 22.1.10
Disclosure to FERC, its Staff, or a State … 47
ARTICLE 23. ENVIRONMENTAL RELEASES … 48
ARTICLE 24. INFORMATION REQUIREMENTS … 48
24.1
Information Acquisition … 48 24.2
Information Submission by Participating TO … 48 ARTICLE 25. INFORMATION ACCESS AND AUDIT RIGHTS … 48
25.1
Information Access … 48 25.2
Reporting of Non-Force Majeure Events … 49 25.3
Audit Rights … 49 25.4
Audit Rights Periods … 49 25.4.1
Audit Rights Period for Construction-Related Accounts and Records … 49
25.4.2
Audit Rights Period for All Other Accounts and Records … 49
25.5
Audit Results … 50 ARTICLE 26. SUBCONTRACTORS … 50 26.1
General … 50 26.2
Responsibility of Principal … 50 26.3
No Limitation by Insurance … 50 ARTICLE 27. DISPUTES … 50 27.1
Submission … 50 27.2
External Arbitration Procedures … 51 27.3
Arbitration Decisions … 51 27.4
Costs … 51 ARTICLE 28. REPRESENTATIONS, WARRANTIES AND COVENANTS … 51
28.1
General … 51 28.1.1
Good Standing … 51 28.1.2
Authority … 52 28.1.3
No Conflict … 52 28.1.4
Consent and Approval … 52 ARTICLE 29. [RESERVED] … 52 ARTICLE 30. MISCELLANEOUS … 52 30.1
Binding Effect … 52 30.2
Conflicts … 52 30.3
Rules of Interpretation … 52 30.4
Entire Agreement … 53 30.5
No Third-Party Beneficiaries … 53 30.6
Waiver … 53 30.7
Headings … 53 30.8
Multiple Counterparts … 53 30.9
Amendment … 53
PDF page 87
vi
30.10 Modification by the Parties … 53 30.11 Reservation of Rights … 54 30.12 No Partnership … 54 30.13 Joint and Several Obligations … 54
Appendices
Appendix A Interconnection Facilities, Network Upgrades and Distribution Upgrades
Appendix B Milestones
Appendix C Interconnection Details
Appendix D Security Arrangements Details
Appendix E Commercial Operation Date
Appendix F Addresses for Delivery of Notices and Billings
Appendix G Large Load Interconnection Customer’s Share of Costs of Network Upgrades
for Applicable Project Group
Appendix H Co-Location and Behind-the-Meter Generation Provisions
PDF page 88
1
Attachment 3
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
LARGE LOAD INTERCONNECTION AGREEMENT
[LARGE LOAD INTERCONNECTION CUSTOMER]
AND
DCR TRANSMISSION, L.L.C.
THIS LARGE LOAD INTERCONNECTION AGREEMENT (“LLIA”) is made and
entered into this ______ day of ________________ 20___, by and among _________________, a ________________, organized and existing under the laws of the State/Commonwealth of ___________ (“Large Load Interconnection Customer” with a Large Load Facility), and DCR Transmission, L.L.C., a limited liability company, organized and existing under the laws of the State of Delaware (“DCRT” or “Participating TO”). Large Load Interconnection Customer, and Participating TO each may be referred to as a “Party” or collectively as the “Parties.”1 RECITALS
WHEREAS, the California Independent System Operator Corporation (“CAISO”) exercises Operational Control over the CAISO Controlled Grid; and
WHEREAS, the Participating TO owns, operates, and maintains the Participating TO’s Transmission System; and
WHEREAS, Large Load Interconnection Customer intends to own, lease and/or control and operate the Large Load Facility identified as a Large Load Facility in Appendices A and C to this LLIA; and
WHEREAS, Large Load Interconnection Customer, Participating TO, and, as applicable, CAISO have agreed to enter into this LLIA for the purpose of interconnecting the Large Load Facility with the Participating TO’s Transmission System; and
WHEREAS, to the extent applicable, Appendix H sets forth the applicable provisions relating to impacts (financial, operational, regulatory and otherwise) on the Large Load Interconnection Customer arising out of or related to co-located or Behind-the-Meter Generation utilizing the Large Load Interconnection Customer’s Interconnection Facilities that may necessitate CAISO becoming a signatory to this LLIA;
NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein, it is agreed:
1 The California Independent System Operator Corporation will be added as a party to this LLIA as may be required pursuant to Appendix H.
PDF page 89
2
When used in this LLIA, terms with initial capitalization that are not defined in Article 1 shall have the meanings specified in the Article in which they are used. Further, terms with initial capitalization which are used but not defined in the LLIA shall have the meaning given them in the Appendices.
Article 1. Definitions
1.1
Capitalized terms used herein that are not defined in this Article 1 are defined in the Participating TO Tariff.
Access Party shall have the meaning set forth in Article 5.11.
Affected System shall mean an electric system other than the Participating Transmission Owners Transmission System that may be affected by the proposed interconnection. Affiliate shall mean, with respect to a corporation, partnership or other entity, each such other corporation, partnership or other entity that directly or indirectly, through one or more intermediaries, controls, is controlled by, or is under common control with, such corporation, partnership or other entity.
Alternative Transmission Technologies shall mean any transmission technology other than Network Upgrades that can be used to improve the Participating TO’s Transmission System to interconnect an Interconnection Customer or Large Load Interconnection Customer, which may include static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, and tower lifting.
Applicable Laws and Regulations shall mean all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any Governmental Authority.
Applicable Reliability Council shall mean the Western Electricity Coordinating Council or its successor.
Applicable Reliability Standards shall mean the requirements and guidelines of NERC, the Applicable Reliability Council, and the Balancing Authority Area of the Participating TO’s Transmission System to which the Large Load Facility is directly connected, including requirements adopted pursuant to section 215 of the Federal Power Act.
Balancing Authority shall mean the responsible entity that integrates resource plans ahead of time, maintains load-interchange-generation balance within a Balancing Authority Area, and supports Interconnection frequency in real time.
Balancing Authority Area shall mean the collection of generation, transmission, and loads within the metered boundaries of the Balancing Authority. The Balancing Authority maintains load-resource balance within this area.
PDF page 90
3
Behind-the-Meter Generation shall mean generating facility that delivers energy to load without using the transmission system or any distribution facilities.
Breach shall mean the failure of a Party to perform or observe any material term or condition of this LLIA.
Breaching Party shall mean a Party that is in Breach of this LLIA.
Business Day shall mean Monday through Friday, excluding federal holidays and the day after Thanksgiving Day.
CAISO Controlled Grid shall mean the system of transmission lines and associated facilities of the parties to the Transmission Control Agreement that have been placed under the CAISO’s Operational Control.
CAISO Tariff shall mean the CAISO’s tariff, as filed with FERC, and as amended or supplemented from time to time, or any successor tariff.
Calendar Day shall mean any day including Saturday, Sunday or a federal holiday. Co-located Facilities shall mean both the load and generation facilities in a configuration where end-use customer load is physically connected to the facilities of an existing or planned generating facility on the generator interconnection customer’s side of the point of interconnection to the Participating TO’s Transmission System.
Commercial Operation shall mean the status of a (i) Large Load Facility or project phase at a Large Load Facility that has commenced demand for electricity, excluding electricity used during the construction of the Large Load Facility or (ii) Network Upgrade, when such upgrade is fully and finally constructed and can fully operate as intended. Commercial Operation Date of a Large Load Facility or project phase shall mean the date on which the Large Load Facility or project phase at the Large Load Facility commences Commercial Operation as agreed to by the applicable Participating TO, as applicable, the CAISO, and the Large Load Interconnection Customer pursuant to Appendices E and H to this LLIA, and in accordance with any implementation plan agreed to by the Participating TO and the CAISO for multiple individual Large Load Facilities or project phases at a Large Load Facility where a Large Load Interconnection Customer intends to establish separate Commercial Operation Dates for those Large Load Facilities or project phases.
Confidential Information shall mean any confidential, proprietary or trade secret information of a plan, specification, pattern, procedure, design, device, list, concept, policy or compilation relating to the present or planned business of a Party, which is designated as confidential by the Party supplying the information, whether conveyed orally, electronically, in writing, through inspection, or otherwise, subject to Article 22.1.2.
Default shall mean the failure of a Breaching Party to cure its Breach in accordance with Article 17 of this LLIA.
PDF page 91
4
Distribution System shall mean those non-CAISO-controlled transmission and
distribution facilities owned by the Participating TO.
Distribution Upgrades shall mean the additions, modifications, and upgrades to the Participating TO’s Distribution System. Distribution Upgrades do not include Interconnection Facilities.
Effective Date shall mean the date on which this LLIA becomes effective upon
execution by all Parties subject to acceptance by FERC, or if filed unexecuted, upon the date specified by FERC.
Emergency Condition shall mean a condition or situation, that in the judgment of the Party making the claim, is imminently likely: (1) to endanger life or property; (2) is imminently likely to cause a material adverse effect on the security of, or damage to, the Participating TO’s Transmission System, Participating TO’s Interconnection Facilities, Distribution System, or the electric systems of others to which the Participating TO’s electric system is directly connected; or (3) to cause a material adverse effect on the security of, or damage to, the Large Load Facility or Large Load Interconnection Customer’s Interconnection Facilities.
Environmental Law shall mean Applicable Laws and Regulations relating to pollution or protection of the environment or natural resources.
Federal Power Act shall mean the Federal Power Act, as amended, 16 U.S.C. §§ 791a et seq.
FERC shall mean the Federal Energy Regulatory Commission or its successor.
Flexible Interim Load Interconnection Service (FILI) shall mean the interim
interconnection service that the Participating TO may offer pursuant to Section 4.1 of the LLIP where the Large Load Facility cannot be reliably served at its full requested demand until certain Network Upgrades are completed, as further described in Section A-2 of Appendix A to this LLIA.
Force Majeure shall mean any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party’s control. A Force Majeure event does not include acts of negligence or intentional wrongdoing by the Party claiming Force Majeure.
Good Utility Practice shall mean any of the practices, methods and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be any one of a number of the optimum practices, methods, or acts to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.
PDF page 92
5
Governmental Authority shall mean any federal, state, local or other governmental, regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided, however, that such term does not include the Large Load Interconnection Customer, CAISO, Participating TO, or any Affiliate thereof. Granting Party shall have the meaning set forth in Article 5.11.
Hazardous Substances shall mean any chemicals, materials or substances defined as or included in the definition of “hazardous substances,” “hazardous wastes,” “hazardous materials,” “hazardous constituents,” “restricted hazardous materials,” “extremely hazardous substances,” “toxic substances,” “radioactive substances,” “contaminants,” “pollutants,” “toxic pollutants” or words of similar meaning and regulatory effect under any applicable Environmental Law, or any other chemical, material or substance, exposure to which is prohibited, limited or regulated by any applicable Environmental Law.
In-Service Date shall mean the date upon which the Large Load Interconnection Customer reasonably expects it will be ready to begin use of the Participating TO’s Interconnection Facilities to draw energy from the Participating Transmission Owner Transmission System.
Interconnection Facilities shall mean the Participating TO’s Interconnection Facilities and the Large Load Interconnection Customer’s Interconnection Facilities. Collectively, Interconnection Facilities include all facilities and equipment between the Large Load Facility and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Large Load Facility to the Participating TO’s Transmission System. Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, or Network Upgrades.
Interconnection Financial Security (IFS) shall mean any of the financial instruments listed in Attachment 4 to the LLIP that are posted by Large Load Interconnection Customer to finance the construction of facilities or Network Upgrades.
Interconnection Service shall mean the service provided by the Participating TO and, as applicable, CAISO associated with interconnecting the Large Load Interconnection Customer’s Interconnection Facilities to the Participating TO’s Transmission System and enabling the CAISO Controlled Grid to transmit electric energy and capacity from the CAISO Controlled Grid to the Large Load Facility at the Point of Interconnection, pursuant to the terms of this LLIA, the Participating TO’s Transmission Owner Tariff, and, as applicable, the CAISO Tariff. IRS shall mean the Internal Revenue Service.
LLIP means the process for studying load interconnection as set forth in Appendix IV of the Participating TO Tariff.
PDF page 93
6
Large Load Facility means a facility whose Point(s) of Interconnection connect to the Participating TO’s Transmission System and has a peak load of 50 megawatts (MW) or greater. Large Load Facility Point of Change of Ownership shall mean the point, as set forth in Appendix A to this LLIA, where the Large Load Interconnection Customer’s Interconnection Facilities connect to the Participating TO’s Interconnection Facilities.
Large Load Interconnection Agreement (LLIA) shall have the meaning set forth in the Preamble.
Large Load Interconnection Application shall mean an application for interconnection, in the form of Section 1.4 to the LLIP.
Large Load Interconnection Customer shall have the meaning set forth in the Preamble.
Large Load Interconnection Customer’s Interconnection Facilities shall mean all facilities and equipment, as identified in Appendix A of this LLIA, that are located between the Large Load Facility and the Participating TO’s Interconnection Facilities, including any modification, addition, or upgrades to such facilities and equipment necessary to physically and electrically interconnect the Large Load Facility to the Participating TO’s Transmission System. Large Load Interconnection Customer’s Interconnection Facilities are sole use facilities. Large Load Interconnection Studies shall mean studies performed pursuant to Appendix IV of the Participating TO Tariff, including the Large Load System Impact Study and the Large Load Facilities Study.
Loss shall mean any and all damages, losses, and claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties. Metering Equipment shall mean all metering equipment installed or to be installed for measuring the power flows to the Large Load Facility pursuant to this LLIA at the metering points, including but not limited to instrument transformers, Megawatt-hour-meters, data acquisition equipment, transducers, remote terminal unit, communications equipment, phone lines, and fiber optics.
NERC shall mean the North American Electric Reliability Corporation or its successor organization.
Network Upgrades shall be the mean the additions, modifications, and upgrades to the Participating TO’s Transmission System at or beyond the Point of Interconnection, identified in the Large Load Interconnection Studies, as identified in Appendix A and, as applicable Appendix H, to relieve constraints on the Participating TO’s Transmission System. Alternative Transmission Technologies shall be included in the definition of Network Upgrades. Operational Control shall mean the rights of the CAISO under the Transmission Control Agreement and the CAISO Tariff to direct the parties to the Transmission Control
PDF page 94
7
Agreement how to operate their transmission lines and facilities and other electric plant affecting the reliability of those lines and facilities for the purpose of affording comparable non- discriminatory transmission access and meeting applicable reliability criteria. Participating TO’s Interconnection Facilities shall mean all facilities and equipment owned, controlled or operated by the Participating TO from the Large Load Facility Point of Change of Ownership to the Point of Interconnection as identified in Appendix A to this LLIA, including any modifications, additions or upgrades to such facilities and equipment. Participating TO’s Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, or Network Upgrades.
Participating TO’s Interconnection Handbook shall mean the Participating TO’s business practice for prospective Large Load Interconnection Customers seeking interconnection under the Large Load Interconnection Process described in Appendix IV to the Participating TO’s Tariff.
Participating TO’s Tariff shall mean the currently effective tariff of DCR Transmission, L.L.C., Transmission Owner Tariff on file with FERC, as may be amended or superseded from time to time upon further filing with and acceptance by FERC.
Participating TO’s Transmission System shall mean the facilities owned and operated by the Participating TO and that have been placed under the CAISO’s Operational Control, which facilities form part of the CAISO Controlled Grid.
Party or Parties shall mean the Participating TO, CAISO, Large Load Interconnection Customer or the applicable combination of the above.
Point of Interconnection shall mean the point, as set forth in Appendix A to this LLIA, where the Interconnection Facilities connect to the Participating TO’s Transmission System. Reasonable Efforts shall mean, with respect to an action required to be attempted or taken by a Party under this LLIA, efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.
Scoping Meeting shall mean the meeting among representatives of the Large Load Interconnection Customer, the Participating TO(s), and, as applicable the CAISO and other Affected Systems, conducted for the purpose of discussing alternative interconnection options, to exchange information including any transmission data and earlier study evaluations that would be reasonably expected to impact such interconnection options, to analyze such information, and to determine the potential feasible Points of Interconnection.
System Protection Facilities shall mean the equipment, including necessary protection signal communications equipment, that protects: (1) the Participating TO’s Transmission System, Participating TO’s Interconnection Facilities, CAISO Controlled Grid, and Affected Systems from faults or other electrical disturbances occurring at the Large Load Interconnection Customer’s Interconnection Facilities; and (2) the Large Load Facility from faults or other electrical system disturbances occurring on the CAISO Controlled Grid, Participating TO’s
PDF page 95
8
Interconnection Facilities, and Affected Systems or on other delivery systems or other generating systems to which the CAISO Controlled Grid is directly connected.
Transmission Control Agreement shall mean CAISO FERC Electric Tariff No. 7. Trial Operation shall mean the period during which the Large Load Interconnection Customer is engaged in on-site test operations and commissioning of the Large Load Facility prior to Commercial Operation.
Article 2. Effective Date, Term and Termination
2.1
Effective Date. This LLIA shall become effective upon execution by all Parties subject to acceptance by FERC (if applicable), or if filed unexecuted, upon the date specified by FERC. The Participating TO shall promptly file this LLIA with FERC upon execution in accordance with Article 3.1, if required.
2.2
Term of Agreement. Subject to the provisions of Article 2.3, this LLIA shall remain in effect for a period of ten (10) years from the Effective Date (Term Specified in individual agreements to be ten (10) years or such other longer period as the Large Load Interconnection Customer may request) and shall be automatically renewed for each successive one-year period thereafter.
2.3
Termination Procedures.
2.3.1 Written Notice. This LLIA may be terminated by the Large Load Interconnection Customer after giving the Participating TO and, as applicable CAISO, ninety (90) Calendar Days advance written notice, or by the Participating TO notifying FERC after the Large Load Facility permanently ceases Commercial Operation. 2.3.2 Default. A Party may terminate this LLIA in accordance with Article 17. 2.3.3 Suspension of Work. This LLIA may be deemed terminated in accordance with Article 5.14, if applicable.
2.3.4 Notwithstanding Articles 2.3.1, 2.3.2, and 2.3.3, no termination shall become effective until the Parties have complied with all Applicable Laws and Regulations applicable to such termination, including the filing with FERC of a notice of termination of this LLIA (if applicable), which notice has been accepted for filing by FERC, and the Large Load Interconnection Customer has fulfilled its termination cost obligations under Article 2.4.
2.4
Termination Costs. Immediately upon the other Parties’ receipt of a notice of the termination of this LLIA pursuant to Article 2.3 above, the Participating TO will determine the total cost responsibility of the Large Load Interconnection Customer. If, as of the date of the other Parties’ receipt of the notice of termination, the Large Load Interconnection Customer has not already paid its share of Network Upgrade costs, as set forth in Appendix G to this LLIA, the Participating TO will liquidate the Large Load Interconnection Customer’s Interconnection Financial Security associated with its cost
PDF page 96
9
responsibility for Network Upgrades, in accordance with Appendix IV, Attachment 4 of the Participating TO’s tariff.
The Large Load Interconnection Customer will also be responsible for all costs incurred or irrevocably committed to be incurred in association with the construction of the Participating TO’s Interconnection Facilities (including any cancellation costs relating to orders or contracts for Interconnection Facilities and equipment) and other such expenses, including any Distribution Upgrades for which the Participating TO has incurred expenses or has irrevocably committed to incur expenses and has not been reimbursed by the Large Load Interconnection Customer, as of the date of the other Parties’ receipt of the notice of termination, subject to the limitations set forth in this Article 2.4. Nothing in this Article 2.4 shall limit the Parties’ rights under Article 17. If, as of the date of the other Parties’ receipt of the notice of termination, the Large Load Interconnection Customer has not already reimbursed the Participating TO for costs incurred to construct the Participating TO’s Interconnection Facilities, the Participating TO will liquidate the Large Load Interconnection Customer’s Interconnection Financial Security associated with the construction of the Participating TO’s Interconnection Facilities. If the amount of the Interconnection Financial Security liquidated by the Participating TO under this Article 2.4 is insufficient to compensate the Participating TO for actual costs associated with the construction of the Participating TO’s Interconnection Facilities contemplated in this Article, any additional amounts will be the responsibility of the Large Load Interconnection Customer. Any such additional amounts due from the Large Load Interconnection Customer beyond the amounts covered by its Interconnection Financial Security will be due to the Participating TO immediately upon termination of this LLIA. If the amount of the Interconnection Financial Security exceeds the Interconnection Customer’s cost responsibility under this LLIA, any excess amount will be released to the Interconnection Customer.
2.4.1 Large Load Interconnection. Notwithstanding the foregoing, in the event of termination by a Party, all Parties shall use commercially Reasonable Efforts to mitigate the costs, damages, and charges arising as a consequence of termination. With respect to any portion of the Participating TO’s Interconnection Facilities that have not yet been constructed or installed, the Participating TO shall to the extent possible, and with the Large Load Interconnection Customer’s authorization, cancel any pending orders of, or return, any materials or equipment for, or contracts for construction of, such facilities; provided that in the event the Large Load Interconnection Customer elects not to authorize such cancellation, the Large Load Interconnection Customer shall assume all payment obligations with respect to such materials, equipment, and contracts, and the Participating TO shall deliver such material and equipment, and, if necessary, assign such contracts, to the Large Load Interconnection Customer as soon as practicable, at the Large Load Interconnection Customer’s expense. To the extent that the Large Load Interconnection Customer has already paid the Participating TO for any or all such costs of materials or equipment not taken by the Large Load Interconnection Customer, the Participating TO shall promptly refund such amounts to the Large Load Interconnection
PDF page 97
10
Customer, less any costs, including penalties, incurred by the Participating TO to cancel any pending orders of, or return such materials, equipment, or contracts. 2.4.2 The Participating TO may, at its option, retain any portion of such materials, equipment, or facilities that the Large Load Interconnection Customer chooses not to accept delivery of, in which case the Participating TO shall be responsible for all costs associated with procuring such materials, equipment, or facilities. 2.4.3 With respect to any portion of the Interconnection Facilities, and any other facilities already installed or constructed pursuant to the terms of this LLIA, Large Load Interconnection Customer shall be responsible for all costs associated with the removal, relocation or other disposition or retirement of such materials, equipment, or facilities.
2.5
Disconnection. Upon termination of this LLIA, the Parties will take all appropriate steps to disconnect the Large Load Facility from the Participating TO’s Transmission System. All costs required to effectuate such disconnection shall be borne by the terminating Party, unless such termination resulted from the non-terminating Party’s Default of this LLIA or such non-terminating Party otherwise is responsible for these costs under this LLIA.
2.6
Survival. This LLIA shall continue in effect after termination to the extent necessary to provide for final billings and payments and for costs incurred hereunder, including billings and payments pursuant to this LLIA; to permit the determination and enforcement of liability and indemnification obligations arising from acts or events that occurred while this LLIA was in effect; and to permit each Party to have access to the lands of the other Parties pursuant to this LLIA or other applicable agreements, to disconnect, remove or salvage its own facilities and equipment.
Article 3. Regulatory Filings and CAISO Tariff Compliance
3.1
Filing. The Participating TO shall file this LLIA (and any amendment hereto) with the appropriate Governmental Authority(ies), if required. The Large Load Interconnection Customer may request that any information provided be subject to the confidentiality provisions of Article 22. If the Large Load Interconnection Customer has executed this LLIA, or any amendment thereto, the Large Load Interconnection Customer shall reasonably cooperate with the Participating TO and, as applicable, CAISO with respect to such filing and to provide any information reasonably requested by the Participating TO or CAISO as needed to comply with applicable regulatory requirements. 3.2
Agreement Subject to CAISO Tariff. The Large Load Interconnection Customer will comply with all applicable provisions of the CAISO Tariff, including the GIDAP as may be required pursuant to Appendix H for co-located or Behind-the-Meter Generation. Article 4. Scope of Service
4.1
Large Load Interconnection Service. Large Load Interconnection Service allows the Large Load Interconnection Customer to connect the Large Load Facility to the
PDF page 98
11
Participating TO’s Transmission System and be eligible to receive energy from the CAISO Controlled Grid. To the extent the Large Load Interconnection Customer wants to receive Large Load Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct.
4.2
Provision of Service. The Participating TO shall provide Interconnection Service for the Large Load Facility. Any Interconnection Service subject to Appendix H shall be negotiated between the Participating TO, Large Load Interconnection Customer and the CAISO.
4.3
Performance Standards. Each Party shall perform all of its obligations under this LLIA in accordance with Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility Practice, and to the extent a Party is required or prevented or limited in taking any action by such regulations and standards, such Party shall not be deemed to be in Breach of this LLIA for its compliance therewith. If such Party is the Participating TO, then that Party shall amend the LLIA and submit the amendment to FERC for approval. 4.4
No Transmission Service. The execution of this LLIA does not constitute a request for, nor the provision of, any transmission service over the Participating TO’s Transmission System, and does not convey any right to deliver electricity to, or receive electricity from, any specific point of delivery. Large Load Interconnection Customer must request transmission service from CAISO, including through a Scheduling Coordinator, in accordance with the CAISO Tariff.
Article 5. Large Load Interconnect Customer’s Interconnection Facilities Engineering, Procurement, And Construction
5.1
Design Requirements. Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO from the Large Load Interconnection Customer associated with interconnecting the Large Load Facility.
5.1.1 Standard Option. The Participating TO shall design, procure, and construct the Participating TO’s Interconnection Facilities, Network Upgrades using Reasonable Efforts to complete the Participating TO’s Interconnection Facilities and Network Upgrades by the dates set forth in Appendix B, Milestones. The Participating TO shall not be required to undertake any action which is inconsistent with its standard safety practices, its material and equipment specifications, its design criteria and construction procedures, its labor agreements, and Applicable Laws and Regulations. In the event the Participating TO reasonably expects that it will not be able to complete the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades by the specified dates, the Participating TO shall promptly provide written notice to the Large Load Interconnection Customer
PDF page 99
12
and, as applicable, the CAISO and the Participating TO shall undertake Reasonable Efforts to meet the earliest dates thereafter.
5.2
Liquidated Damages. The actual damages to the Large Load Interconnection Customer, in the event the Participating TO’s Interconnection Facilities or Network Upgrades are not completed by the dates designated by the Large Load Interconnection Customer and accepted by the Participating TO, may include Large Load Interconnection Customer’s fixed operation and maintenance costs and lost opportunity costs. Such actual damages are uncertain and impossible to determine at this time. Because of such uncertainty, any liquidated damages paid by the Participating TO the Large Load Interconnection Customer in the event that the Participating TO does not complete any portion of the Participating TO’s Interconnection Facilities or Network Upgrades by the applicable dates, shall be an amount equal to one half of one percent (½ of 1%) per day of the actual cost of the Participating TO’s Interconnection Facilities and Network Upgrades, in the aggregate, for which the Participating TO has assumed responsibility to design, procure and construct.
However, in no event shall the total liquidated damages exceed twenty percent (20%) of the actual cost of the Participating TO’s Interconnection Facilities and Network Upgrades for which the Participating TO has assumed responsibility to design, procure, and construct. The foregoing payments will be made by the Participating TO the Large Load Interconnection Customer as just compensation for the damages caused to the Large Load Interconnection Customer, which actual damages are uncertain and impossible to determine at this time, and as reasonable liquidated damages, but not as a penalty or a method to secure performance of this LLIA. Liquidated damages, when the Parties agree to them, are the exclusive remedy for the Participating TO’s failure to meet its schedule. No liquidated damages shall be paid to the Large Load Interconnection Customer if: (1) the Large Load Interconnection Customer is not ready to commence use of the Participating TO’s Interconnection Facilities or Network Upgrades to take the delivery of power for the Large Load Facility’s Trial Operation, unless the Large Load Interconnection Customer would have been able to commence use of the Participating TO’s Interconnection Facilities or Network Upgrades to take the delivery of power for Large Load Facility’s Trial Operation, but for the Participating TO’s delay; and (2) the Participating TO’s failure to meet the specified dates is the result of the action or inaction of the Large Load Interconnection Customer or any other interconnection customer who has entered into an interconnection agreement with the Participating TO and/or CAISO, action or inaction by the CAISO, or any cause beyond the Participating TO’s reasonable control or reasonable ability to cure.
In no event shall the Participating TO have any responsibility or liability to the Large Load Interconnection Customer for liquidated damages pursuant to the provisions of this Article 5.2.
5.3
Reserved.
PDF page 100
13
5.4
Equipment Procurement. Participating TO shall commence design of the Participating TO’s Interconnection Facilities or Network Upgrades and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:
5.4.1 The Participating TO has received written authorization to proceed with design and procurement from the Large Load Interconnection Customer by the date specified in Appendix B, Milestones; and
5.4.2 The Large Load Interconnection Customer has provided security to the Participating TO in accordance with Article 11.3 by the dates specified in Appendix B, Milestones.
5.5
Construction Commencement. The Participating TO shall commence construction of the Participating TO’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied: 5.5.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.5.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of the Participating TO’s Interconnection Facilities and Network Upgrades;
5.5.3 The Participating TO has received written authorization to proceed with construction from the Large Load Interconnection Customer by the date specified in Appendix B, Milestones; and
5.5.4 The Large Load Interconnection Customer has provided payment and security to the Participating TO in accordance with Article 11.3 by the dates specified in Appendix B, Milestones.
5.6
Work Progress. The Parties will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Any Party may, at any time, request a progress report from another Party. If, at any time, the Large Load Interconnection Customer determines that the completion of the Participating TO’s Interconnection Facilities will not be required until after the specified In-Service Date, the Large Load Interconnection Customer will provide written notice to the Participating TO and, as applicable, CAISO of such later date upon which the completion of the Participating TO’s Interconnection Facilities will be required.
5.7
Information Exchange. As soon as reasonably practicable after the Effective Date, the Parties shall exchange information regarding the design and compatibility of the Large Load Interconnection Customer’s Interconnection Facilities and Participating TO’s Interconnection Facilities and compatibility of the Interconnection Facilities with the Participating TO’s Transmission System, and shall work diligently and in good faith to make any necessary design changes.
PDF page 101
14
5.8
Limited Operation. If any of the Participating TO’s Interconnection Facilities or Network Upgrades are not reasonably expected to be completed prior to the Commercial Operation Date of the Large Load Facility, the Participating TO shall, upon the request and at the expense of the Large Load Interconnection Customer, perform operating studies on a timely basis to determine the extent to which the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities may operate prior to the completion of the Participating TO’s Interconnection Facilities or Network Upgrades consistent with Applicable Laws and Regulations, Applicable Reliability Standards, Good Utility Practice, and this LLIA. The Participating TO shall permit the Large Load Interconnection Customer to operate the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities in accordance with the results of such studies.
5.9
Large Load Interconnection Customer’s Interconnection Facilities. The Large Load Interconnection Customer shall, at its expense, design, procure, construct, own, and install the Large Load Interconnection Customer’s Interconnection Facilities, as set forth in Appendices A and H, as applicable.
5.9.1 Large Load Facility and Large Load Interconnection Customer’s
Interconnection Facilities Specifications. In addition to the Large Load Interconnection Customer’s responsibility to submit technical data with its Large Load Interconnection Application, Large Load Interconnection Customer shall submit all remaining necessary specifications for the Large Load Interconnection Customer’s Interconnection Facilities and Large Load Facility, including System Protection Facilities, to the Participating TO (who shall provide such information to the CAISO) at least one hundred eighty (180) Calendar Days prior to the Commercial Operation Date. The Participating TO shall review such specifications pursuant to this LLIA and the LLIP to ensure that the Large Load Interconnection Customer’s Interconnection Facilities and Large Load Facility are compatible with the technical specifications, operational control, safety requirements, and any other applicable requirements of the Participating TO and comment on such
specifications within thirty (30) Calendar Days of the Large Load Interconnection Customer’s submission. All specifications provided hereunder shall be deemed confidential.
5.9.2 Participating TO’s Review. The Participating TO’s review of the Large Load Interconnection Customer’s final specifications shall not be construed as confirming, endorsing, or providing a warranty as to the design, fitness, safety, durability or reliability of the Large Load Facility, or the Large Load Interconnection Customer’s Interconnection Facilities. Large Load Interconnection Customer shall make such changes to the Large Load Interconnection Customer’s Interconnection Facilities as may reasonably be required by the Participating TO, in accordance with Good Utility Practice, to ensure that the Large Load Interconnection Customer’s Interconnection Facilities are compatible with the technical specifications, Operational Control, and safety requirements of the Participating TO.
PDF page 102
15
5.9.3 Large Load Interconnection Customer’s Interconnection Facilities Construction. The Large Load Interconnection Customer’s Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Large Load Interconnection Customer agree on another mutually acceptable deadline, the Large Load Interconnection Customer shall deliver to the Participating TO “as-built” drawings, information and documents for the Large Load Interconnection Customer’s Interconnection Facilities and the Large Load Facility(s), such as: a one-line diagram, a site plan showing the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities, plan and elevation drawings showing the layout of the Large Load Interconnection Customer’s Interconnection Facilities, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Large Load Interconnection Customer’s step-up transformers, the facilities connecting the Large Load Facility to the step-up transformers and the Large Load Interconnection Customer’s Interconnection Facilities, and the impedances (determined by factory tests) for the associated step-up transformers and the Large Load Facilities. The Large Load Interconnection Customer shall provide the Participating TO specifications for the automatic voltage regulator, Large Load Facility control and protection settings, transformer tap settings, and communications, if applicable. Any deviations from the relay settings, machine specifications, and other specifications originally submitted by the Large Load Interconnection Customer shall be assessed by the Participating TO pursuant to the appropriate provisions of this LLIA and the LLIP.
5.10
Participating TO’s Interconnection Facilities Construction. The Participating TO’s Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Large Load Interconnection Customer agree on another mutually acceptable deadline, the Participating TO shall deliver to the Large Load Interconnection Customer and the CAISO the following: “as- built” drawings, information and documents for the Participating TO’s Interconnection Facilities, including appropriate drawings and relay diagrams.
The Participating TO will obtain control for operating and maintenance purposes of the Participating TO’s Interconnection Facilities upon completion of such facilities. 5.11
Access Rights. Upon reasonable notice and supervision by a Party, and subject to any required or necessary regulatory approvals, a Party (“Granting Party”) shall furnish at no cost to the other Party (“Access Party”) any rights of use, licenses, rights of way and easements with respect to lands owned or controlled by the Granting Party, its agents (if allowed under the applicable agency agreement), or any Affiliate, that are necessary to enable the Access Party to obtain ingress and egress to construct, operate, maintain, repair, test (or witness testing), inspect, replace or remove facilities and equipment to: (i) interconnect the Large Load Facility with the Participating TO’s Transmission System;
(ii) operate and maintain the Large Load Facility, the Interconnection Facilities and the
PDF page 103
16
Participating TO’s Transmission System; and (iii) disconnect or remove the Access Party’s facilities and equipment upon termination of this LLIA. In exercising such rights of use, licenses, rights of way and easements, the Access Party shall not unreasonably disrupt or interfere with normal operation of the Granting Party’s business and shall adhere to the safety rules and procedures established in advance, as may be changed from time to time, by the Granting Party and provided to the Access Party.
5.12
Lands of Other Property Owners. If any part of the Participating TO’s Interconnection Facilities and/or Network Upgrades are to be installed on property owned by persons other than the Large Load Interconnection Customer or Participating TO, the Participating TO shall at the Large Load Interconnection Customer’s expense use efforts, similar in nature and extent to those that it typically undertakes on its own behalf or on behalf of its Affiliates, including use of its eminent domain authority, and to the extent consistent with state law, to procure from such persons any rights of use, licenses, rights of way and easements that are necessary to construct, operate, maintain, test, inspect, replace or remove the Participating TO’s Interconnection Facilities and/or Network Upgrades upon such property.
5.13
Permits. Participating TO and Large Load Interconnection Customer shall cooperate with each other in good faith in obtaining all permits, licenses and authorizations that are necessary to accomplish the interconnection in compliance with Applicable Laws and Regulations. With respect to this paragraph, the Participating TO shall provide permitting assistance to the Large Load Interconnection Customer comparable to that provided to the Participating TO’s own, or an Affiliate’s generation.
5.14
Suspension. The Large Load Interconnection Customer may request to suspend at any time all work associated with the construction and installation of the Participating TO’s Interconnection Facilities, Network Upgrades, and/or Distribution Upgrades required under this LLIA, other than Network Upgrades or Alternative Transmission Technologies solutions identified in the Large Load Interconnection Studies that are not subject to suspension. Large Load Interconnection Customers seeking to suspend construction will provide the Participating TO a request to suspend. The Participating TO shall evaluate a request to suspend work submitted pursuant to this Article 5.14 and may approve suspension requests where the Participating TO’s Transmission System can be left in a safe and reliable condition in accordance with Good Utility Practice, the Participating TO’s safety and reliability criteria, and Applicable Reliability Standards and Participating TO will not be subject to financial harm.
5.15
Taxes.
5.15.1 Large Load Interconnection Customer Payments Not Taxable. The Parties intend that all payments or property transfers made by the Large Load
Interconnection Customer to the Participating TO for the installation of the Participating TO’s Interconnection Facilities and the Network Upgrades shall be non-taxable, either as contributions to capital, or as a refundable advance, in accordance with the Internal Revenue Code and any applicable state income tax
PDF page 104
17
laws and shall not be taxable as contributions in aid of construction or otherwise under the Internal Revenue Code and any applicable state income tax laws. 5.15.2 Representations And Covenants. In accordance with IRS Notice 2001-82 and IRS Notice 88-129, the Large Load Interconnection Customer represents and covenants that: (i) for income tax purposes, the amount of any payments and the cost of any property transferred to the Participating TO for the Participating TO’s Interconnection Facilities will be capitalized by the Large Load Interconnection Customer as an intangible asset and recovered using the straight-line method over a useful life of twenty (20) years; and (ii) any portion of the Participating TO’s Interconnection Facilities that is a “dual-use intertie,” within the meaning of IRS Notice 88-129, is reasonably expected to carry only a de minimis amount of electricity away from the Large Load Facility. For this purpose, “de minimis amount” means no more than 5 percent of the total power flows in both directions, calculated in accordance with the “5 percent test” set forth in IRS Notice 88-129. This is not intended to be an exclusive list of the relevant conditions that must be met to conform to IRS requirements for non-taxable treatment.
At the Participating TO’s request, the Large Load Interconnection Customer shall provide the Participating TO with a report from an independent engineer confirming its representation in clause (iii), above. The Participating TO represents and covenants that the cost of the Participating TO’s Interconnection Facilities paid for by the Large Load Interconnection Customer without the possibility of refund or credit will have no net effect on the base upon which rates are determined.
5.15.3 Indemnification for the Cost Consequence of Current Tax Liability Imposed Upon the Participating TO. Notwithstanding Article 5.15.1, the Large Load Interconnection Customer shall protect, indemnify and hold harmless the Participating TO from the cost consequences of any current tax liability imposed against the Participating TO as the result of payments or property transfers made by the Large Load Interconnection Customer to the Participating TO under this LLIA for Interconnection Facilities, as well as any interest and penalties, other than interest and penalties attributable to any delay caused by the Participating TO. The Participating TO shall not include a gross-up for the cost consequences of any current tax liability in the amounts it charges the Large Load Interconnection Customer under this LLIA unless (i) the Participating TO has determined, in good faith, that the payments or property transfers made by the Large Load Interconnection Customer to the Participating TO should be reported as income subject to taxation or (ii) any Governmental Authority directs the Participating TO to report payments or property as income subject to taxation; provided, however, that the Participating TO may require the Large Load Interconnection Customer to provide security for Interconnection Facilities, in a form reasonably acceptable to the Participating TO (such as a parental guarantee or a letter of credit), in an amount equal to the cost consequences of any current tax liability under this Article 5.15. The Large Load Interconnection Customer shall reimburse the Participating TO for such costs on a fully grossed-up basis, in accordance with Article 5.15.4, within
PDF page 105
18
thirty (30) Calendar Days of receiving written notification from the Participating TO of the amount due, including detail about how the amount was calculated. The indemnification obligation shall terminate at the earlier of (1) the expiration of the ten year testing period and the applicable statute of limitation, as it may be extended by the Participating TO upon request of the IRS, to keep these years open for audit or adjustment, or (2) the occurrence of a subsequent taxable event and the payment of any related indemnification obligations as contemplated by this Article 5.15.
5.15.4 Tax Gross-Up Amount. The Large Load Interconnection Customer’s liability for the cost consequences of any current tax liability under this Article 5.15 shall be calculated on a fully grossed-up basis. Except as may otherwise be agreed to by the Parties, this means that the Large Load Interconnection Customer will pay the Participating TO, in addition to the amount paid for the Interconnection Facilities and Network Upgrades, an amount equal to (1) the current taxes imposed on the Participating TO (“Current Taxes”) on the excess of (a) the gross income realized by the Participating TO as a result of payments or property transfers made by the Large Load Interconnection Customer to the Participating TO under this LLIA (without regard to any payments under this Article 5.15) (the “Gross Income Amount”) over (b) the present value of future tax deductions for depreciation that will be available as a result of such payments or property transfers (the “Present Value Depreciation Amount”), plus (2) an additional amount sufficient to permit the Participating TO to receive and retain, after the payment of all Current Taxes, an amount equal to the net amount described in clause (1).
For this purpose, (i) Current Taxes shall be computed based on the Participating TO’s composite federal and state tax rates at the time the payments or property transfers are received and the Participating TO will be treated as being subject to tax at the highest marginal rates in effect at that time (the “Current Tax Rate”), and (ii) the Present Value Depreciation Amount shall be computed by discounting the Participating TO’s anticipated tax depreciation deductions as a result of such payments or property transfers by the Participating TO’s current weighted average cost of capital. Thus, the formula for calculating the Large Load Interconnection Customer’s liability to the Participating TO pursuant to this Article 5.15.4 can be expressed as follows: (Current Tax Rate x (Gross Income Amount – Present Value of Tax Depreciation))/(1-Current Tax Rate). Large Load Interconnection Customer’s estimated tax liability in the event taxes are imposed shall be stated in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades.
5.15.5 Private Letter Ruling or Change or Clarification of Law. At the Large Load Interconnection Customer’s request and expense, the Participating TO shall file with the IRS a request for a private letter ruling as to whether any property transferred or sums paid, or to be paid, by the Large Load Interconnection Customer to the Participating TO under this LLIA are subject to federal income taxation. The Large Load Interconnection Customer will prepare the initial draft of the request for
PDF page 106
19
a private letter ruling, and will certify under penalties of perjury that all facts represented in such request are true and accurate to the best of the Large Load Interconnection Customer’s knowledge. The Participating TO and Large Load Interconnection Customer shall cooperate in good faith with respect to the submission of such request, provided, however, the Large Load Interconnection Customer and the Participating TO explicitly acknowledge (and nothing herein is intended to alter) Participating TO’s obligation under law to certify that the facts presented in the ruling request are true, correct and complete.
The Participating TO shall keep the Large Load Interconnection Customer fully informed of the status of such request for a private letter ruling and shall execute either a privacy act waiver or a limited power of attorney, in a form acceptable to the IRS, that authorizes the Large Load Interconnection Customer to participate in all discussions with the IRS regarding such request for a private letter ruling. The Participating TO shall allow the Large Load Interconnection Customer to attend all meetings with IRS officials about the request and shall permit the Large Load Interconnection Customer to prepare the initial drafts of any follow-up letters in connection with the request.
5.15.6 Subsequent Taxable Events. If, within ten (10) years from the date on which the relevant Participating TO’s Interconnection Facilities are placed in service, (i) the Large Load Interconnection Customer Breaches the covenants contained in Article 5.15.2, (ii) a “disqualification event” occurs within the meaning of IRS Notice 88- 129, or (iii) this LLIA terminates and the Participating TO retains ownership of the Interconnection Facilities and Network Upgrades, the Large Load Interconnection Customer shall pay a tax gross-up for the cost consequences of any current tax liability imposed on the Participating TO, calculated using the methodology described in Article 5.15.4 and in accordance with IRS Notice 9060. 5.15.7 Contests. In the event any Governmental Authority determines that the Participating TO’s receipt of payments or property constitutes income that is subject to taxation, the Participating TO shall notify the Large Load Interconnection Customer, in writing, within thirty (30) Calendar Days of receiving notification of such determination by a Governmental Authority. Upon the timely written request by the Large Load Interconnection Customer and at the Large Load Interconnection Customer’s sole expense, the Participating TO may appeal, protest, seek abatement of, or otherwise oppose such determination. Upon the Large Load Interconnection Customer’s written request and sole expense, the Participating TO may file a claim for refund with respect to any taxes paid under this Article 5.15, whether or not it has received such a determination. The Participating TO reserves the right to make all decisions with regard to the prosecution of such appeal, protest, abatement or other contest, including the selection of counsel and compromise or settlement of the claim, but the Participating TO shall keep the Large Load Interconnection Customer informed, shall consider in good faith suggestions from the Large Load Interconnection Customer about the conduct of the contest, and shall reasonably permit the Large Load Interconnection Customer or an Large Load Interconnection Customer representative to attend contest proceedings.
PDF page 107
20
The Large Load Interconnection Customer shall pay to the Participating TO on a periodic basis, as invoiced by the Participating TO, the Participating TO’s documented reasonable costs of prosecuting such appeal, protest, abatement or other contest, including any costs associated with obtaining the opinion of independent tax counsel described in this Article 5.15.7. The Participating TO may abandon any contest if the Large Load Interconnection Customer fails to provide payment to the Participating TO within thirty (30) Calendar Days of receiving such invoice.
At any time during the contest, the Participating TO may agree to a settlement either with the Large Load Interconnection Customer’s consent or, if such consent is refused, after obtaining written advice from independent nationally-recognized tax counsel, selected by the Participating TO, but reasonably acceptable to the Large Load Interconnection Customer, that the proposed settlement represents a reasonable settlement given the hazards of litigation. The Large Load Interconnection Customer’s obligation shall be based on the amount of the settlement agreed to by the Large Load Interconnection Customer, or if a higher amount, so much of the settlement that is supported by the written advice from nationally-recognized tax counsel selected under the terms of the preceding paragraph. The settlement amount shall be calculated on a fully grossed-up basis to cover any related cost consequences of the current tax liability. The Participating TO may also settle any tax controversy without receiving the Large Load Interconnection Customer’s consent or any such written advice; however, any such settlement will relieve the Large Load Interconnection Customer from any obligation to indemnify the Participating TO for the tax at issue in the contest (unless the failure to obtain written advice is attributable to the Large Load Interconnection Customer’s unreasonable refusal to the appointment of independent tax counsel).
5.15.8 Refund. In the event that: (a) a private letter ruling is issued to the Participating TO which holds that any amount paid or the value of any property transferred by the Large Load Interconnection Customer to the Participating TO under the terms of this LLIA is not subject to federal income taxation; (b) any legislative change or administrative announcement, notice, ruling or other determination makes it reasonably clear to the Participating TO in good faith that any amount paid or the value of any property transferred by the Large Load Interconnection Customer to the Participating TO under the terms of this LLIA is not taxable to the Participating TO; (c) any abatement, appeal, protest, or other contest results in a determination that any payments or transfers made by the Large Load Interconnection Customer to the Participating TO are not subject to federal income tax; or (d) if the Participating TO receives a refund from any taxing authority for any overpayment of tax attributable to any payment or property transfer made by the Large Load Interconnection Customer to the Participating TO pursuant to this LLIA, the Participating TO shall promptly refund to the Large Load Interconnection Customer the following:
PDF page 108
21
(i) any payment made by Large Load Interconnection Customer under this Article 5.15 for taxes that is attributable to the amount determined to be non-taxable, together with interest thereon,
(ii) interest on any amounts paid by the Large Load Interconnection Customer to the Participating TO for such taxes which the Participating TO did not submit to the taxing authority, calculated in accordance with the methodology set forth in FERC’s regulations at 18 C.F.R.
§35.19a(a)(2)(iii) from the date payment was made by the Large Load Interconnection Customer to the date the Participating TO refunds such payment to the Large Load Interconnection Customer, and
(iii) with respect to any such taxes paid by the Participating TO, any refund or credit the Participating TO receives or to which it may be entitled from any Governmental Authority, interest (or that portion thereof attributable to the payment described in clause (i), above) owed to the Participating TO for such overpayment of taxes (including any reduction in interest otherwise payable by the Participating TO to any Governmental Authority resulting from an offset or credit); provided, however, that the Participating TO will remit such amount promptly to the Large Load Interconnection Customer only after and to the extent that the Participating TO has received a tax refund, credit or offset from any Governmental Authority for any applicable overpayment of income tax related to the Participating TO’s Interconnection Facilities.
The intent of this provision is to leave the Parties, to the extent practicable, in the event that no taxes are due with respect to any payment for Interconnection Facilities and Network Upgrades hereunder, in the same position they would have been in had no such tax payments been made.
5.15.9 Taxes Other Than Income Taxes. Upon the timely request by the Large Load Interconnection Customer, and at the Large Load Interconnection Customer’s sole expense, the Participating TO may appeal, protest, seek abatement of, or otherwise contest any tax (other than federal or state income tax) asserted or assessed against the Participating TO for which the Large Load Interconnection Customer may be required to reimburse the Participating TO under the terms of this LLIA. The Large Load Interconnection Customer shall pay to the Participating TO on a periodic basis, as invoiced by the Participating TO, the Participating TO’s documented reasonable costs of prosecuting such appeal, protest, abatement, or other contest. The Large Load Interconnection Customer and the Participating TO shall cooperate in good faith with respect to any such contest. Unless the payment of such taxes is a prerequisite to an appeal or abatement or cannot be deferred, no amount shall be payable by the Large Load Interconnection Customer to the Participating TO for such taxes until they are assessed by a final, non-appealable order by any court or agency of competent jurisdiction. In the event that a tax payment is withheld and ultimately due and payable after appeal, the Large Load Interconnection Customer
PDF page 109
22
will be responsible for all taxes, interest and penalties, other than penalties attributable to any delay caused by the Participating TO.
5.16
Tax Status. Each Party shall cooperate with the others to maintain the other Parties’ tax status.
Article 6. Large Load Interconnection Testing and Inspection
6.1
Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Large Load Interconnection Customer shall test the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. The Large Load Interconnection Customer shall bear the cost of all such testing and modifications.
6.2
Post-Commercial Operation Date Testing and Modifications. Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Load Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice. 6.3
Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days in advance of its performance of tests of its Interconnection Facilities or Large Load Facility. The other Parties have the right, at their own expense, to observe such testing.
6.4
Right to Inspect. Each Party shall have the right, but shall have no obligation to: (i) observe another Party’s tests and/or inspection of any of its System Protection Facilities and other protective equipment; (ii) review the settings of another Party’s System Protection Facilities and other protective equipment; and (iii) review another Party’s maintenance records relative to the Interconnection Facilities, the System Protection Facilities and other protective equipment. A Party may exercise these rights from time to time as it deems necessary upon reasonable notice to the other Party. The exercise or non- exercise by a Party of any such rights shall not be construed as an endorsement or confirmation of any element or condition of the Interconnection Facilities or the System Protection Facilities or other protective equipment or the operation thereof, or as a warranty as to the fitness, safety, desirability, or reliability of same. Any information that a Party obtains through the exercise of any of its rights under this Article 6.4 shall be deemed to be Confidential Information and treated pursuant to Article 22 of this LLIA.
PDF page 110
23
Article 7. Metering
7.1
General. Each Party shall comply with any Applicable Reliability Standards and the Applicable Reliability Council requirements. Unless otherwise agreed by the Participating TO and the Large Load Interconnection Customer, the Participating TO may install additional Metering Equipment at the Point of Interconnection of the Large Load Facility, and shall own, operate, test and maintain such Metering Equipment. Power flows to the Large Load Facility shall be measured at or, at the Participating TO’s option for its respective Metering Equipment, compensated to, the Point of Interconnection. The Large Load Interconnection Customer shall also install meters at each load block and at each individual generation source to accurately capture the demand/generation and power factor of these facilities. The Large Load Interconnection Customer shall bear all reasonable documented costs associated with the purchase, installation, operation, testing and maintenance of the Metering Equipment.
7.2
Check Meters. The Large Load Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LLIA, except in the case that no other means are available on a temporary basis at the option of the Participating TO. The check meters shall be subject at all reasonable times to inspection and examination by the Participating TO or their designees. The installation, operation and maintenance thereof shall be performed entirely by the Large Load Interconnection Customer in accordance with Good Utility Practice.
7.3
Participating TO Retail Metering. The Participating TO may install retail revenue quality meters and associated equipment, pursuant to the Participating TO’s applicable retail tariffs.
Article 8. Communications
8.1
Large Load Interconnection Customer Obligations. The Large Load Interconnection Customer shall maintain satisfactory operating communications with the Participating TO and, as applicable, the CAISO in accordance with the provisions of the CAISO Tariff and with the Participating TO’s dispatcher or representative designated by the Participating TO. The Large Load Interconnection Customer shall provide standard voice line, dedicated voice line and facsimile communications at its Large Load Facility control room or central dispatch facility through use of either the public telephone system, or a voice communications system that does not rely on the public telephone system. The Large Load Interconnection Customer shall also provide two (2) independent dedicated data circuit(s) necessary to provide Large Load Interconnection Customer data to the Participating TO and, as applicable, the CAISO pursuant to the CAISO Tariff. The data circuit(s) shall extend from the Large Load Facility to the location(s) specified by the Participating TO and, as applicable, the CAISO. Any required maintenance of such communications equipment shall be performed by the Large Load Interconnection Customer. Operational communications shall be activated and maintained under, but not
PDF page 111
24
limited to, the following events: system paralleling or separation, scheduled and unscheduled shutdowns, equipment clearances, and hourly and daily load data. 8.2
Remote Terminal Unit. Prior to the interconnection of a Large Load Facility, a remote terminal unit, or equivalent data collection and transfer equipment acceptable to the Parties, shall be installed by the Large Load Interconnection Customer, or by the Participating TO at the Large Load Interconnection Customer’s expense, to gather accumulated and instantaneous data to be telemetered to the location(s) designated by the Participating TO and, as applicable, the CAISO through use of a dedicated point-to-point data circuit(s) as indicated in Article 8.1.
For telemetry to the Participating TO, the communication protocol for the data circuit(s) shall be specified by the Participating TO. Telemetry to the CAISO shall be provided in accordance with the CAISO’s technical standards for direct telemetry. Instantaneous bi- directional real power and reactive power flow and any other required information must be telemetered directly to the location(s) specified by the Participating TO. Each Party will promptly advise the other Parties if it detects or otherwise learns of any metering, telemetry or communications equipment errors or malfunctions that require the attention and/or correction by another Party. The Party owning such equipment shall correct such error or malfunction as soon as reasonably feasible.
8.3
No Annexation. Any and all equipment placed on the premises of a Party shall be and remain the property of the Party providing such equipment regardless of the mode and manner of annexation or attachment to real property, unless otherwise mutually agreed by the Parties.
Article 9. Large Load Interconnection Customer Operations
9.1
General. Each Party shall comply with Applicable Reliability Standards and the Applicable Reliability Council requirements. Each Party shall provide to the other Party all information that may reasonably be required by the other Party to comply with Applicable Laws and Regulations and Applicable Reliability Standards.
9.2
Participating TO Obligations. The Participating TO at the Large Load Interconnection Customer’s expense shall cause the Participating TO’s Interconnection Facilities to be operated, maintained and controlled in a safe and reliable manner and in accordance with this LLIA. The Participating TO may provide operating instructions to the Large Load Interconnection Customer consistent with this LLIA and Participating TO operating protocols and procedures as they may change from time to time. The Participating TO will consider changes to their operating protocols and procedures proposed by the Large Load Interconnection Customer.
9.3
Large Load Interconnection Customer Obligations. The Large Load Interconnection Customer shall at its own expense operate, maintain, and control the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LLIA. The Large Load Interconnection Customer shall operate the Large Load Facility and the Large Load Interconnection
PDF page 112
25
Customer’s Interconnection Facilities in accordance with all applicable requirements of the Balancing Authority Area of which it is part, if any, including such requirements as set forth in Appendix C, Interconnection Details, of this LLIA. Appendix C, Interconnection Details, will be modified to reflect changes to the requirements as they may change from time to time. A Party may request that another Party provide copies of the requirements set forth in Appendix C, Interconnection Details, of this LLIA. 9.4
Reactive Power and Primary Frequency Response. Large Load Interconnection Customer will design the Large Load Facility and Behind-the-Meter facility to maintain a composite power factor within the range of 0.99 leading to 0.97 lagging at the Point of Interconnection, unless the Participating TO established a different requirement that applies to all Large Loads connected to its system or the CAISO has establishes different requirements that apply to all Large Loads in the CAISO Balancing Authority Area on a comparable basis.
9.5
Disconnection from the Grid: The Participating TO will have the right to remotely disconnect the Large Load Facility under conditions specific operation conditions identified in the Large Load System Impact Study or under conditions where disconnecting the Large Load Facility is required to maintain transmission system reliability and stability.
9.6
Outages and Interruptions.
9.6.1 Outages.
9.6.1.1 Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties remove from service any of its respective Interconnection Facilities or Network Upgrades that may impact another Party’s facilities as necessary to
perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a removal of such
facility(ies) from service will use Reasonable Efforts to schedule such removal on a date and time mutually acceptable to all Parties. In all circumstances any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Parties of such removal.
9.6.1.2 Outage Schedules. The Large Load Interconnection Customer Shall submit its planned facility maintenance schedules no less than thirty (30) days in advance of the event.
9.6.1.3 Outage Restoration. If an outage on a Party’s Interconnection Facilities or Network Upgrades adversely affects another Party’s operations or
facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide
PDF page 113
26
the other Parties, to the extent such information is known, information on the nature of the Emergency Condition, if the outage is caused by an Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage, if requested by a Party, which may be provided by e-mail or facsimile. 9.6.2 Interruption of Service. If required by Good Utility Practice to do so, the Participating TO may require the Large Load Interconnection Customer to interrupt or reduce its receipt of deliveries of electricity if such receipt of electricity could adversely affect the Participating TO’s ability to perform such activities as are necessary to safely and reliably operate and maintain the Participating TO’s electric system. The following provisions shall apply to any interruption or reduction permitted under this Article 9.6.2:
9.6.2.1 The interruption or reduction shall continue only for so long as reasonably necessary under Good Utility Practice;
9.6.2.2 Any such interruption or reduction shall be made on an equitable, non- discriminatory basis with respect to all load directly connected to the Participating TO, subject to any conditions specified in this LLIA; 9.6.2.3 When the interruption or reduction must be made under circumstances which do not allow for advance notice, the Participating TO shall notify the Large Load Interconnection Customer by telephone as soon as practicable of the reasons for the curtailment, interruption, or reduction, and, if known, its expected duration. Telephone notification shall be followed by written notification, if requested by the Large Load Interconnection Customer, as soon as practicable;
9.6.2.4 Except during the existence of an Emergency Condition, the Participating TO shall notify the Large Load Interconnection Customer in advance regarding the timing of such interruption or reduction and further notify the Large Load Interconnection Customer of the expected duration. The Participating TO shall coordinate with the Large Load Interconnection Customer using Good Utility Practice to schedule the interruption or reduction during periods of least impact to the Large Load Interconnection Customer, the CAISO, and the Participating TO;
9.6.2.5 The Parties shall cooperate and coordinate with each other to the extent necessary in order to restore the Large Load Facility, Interconnection Facilities, the Participating TO’s Transmission System, and the CAISO Controlled Grid to their normal operating state, consistent with system conditions and Good Utility Practice.
9.6.3 Under-Frequency and Over-Frequency Conditions. The Large Load Interconnection Customer shall implement under-frequency and over-frequency
PDF page 114
27
protection set points for the Large Load Facility as required by Applicable Reliability Standards and the Applicable Reliability Council to ensure “ride through” capability. Large Load Facility response to frequency deviations of pre- determined magnitudes, both under-frequency and over-frequency deviations, shall be studied and coordinated with the Participating TO and the CAISO in accordance with Good Utility Practice. The term “ride through” as used herein shall mean the ability of a Generating Facility to stay connected to and synchronized with the CAISO Controlled Grid during system disturbances within a range of under- frequency and over-frequency conditions, in accordance with Good Utility Practice. The Large Load Interconnection Customer is required to satisfy all current and future frequency ride through requirement established by Western Electricity Coordinating Council or NERC.
9.6.4 System Protection and Other Control Requirements.
9.6.4.1 System Protection Facilities. The Large Load Interconnection Customer shall, at its expense, install, operate, and maintain System Protection Facilities as a part of the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities. The Participating TO shall install at the Large Load Interconnection Customer’s expense any System Protection Facilities that may be required on the Participating TO’s Interconnection Facilities or the Participating TO’s Transmission System as a result of the interconnection of the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities. 9.6.4.2 The Participating TO’s and Large Load Interconnection Customer’s protection facilities shall be designed and coordinated with other systems in accordance with Applicable Reliability Standards, Applicable Reliability Council criteria, and Good Utility Practice.
9.6.4.3 The Participating TO and Large Load Interconnection Customer shall each be responsible for protection of its facilities consistent with Good Utility Practice.
9.6.4.4 The Participating TO’s and Large Load Interconnection Customer’s protective relay design shall incorporate the necessary test switches to perform the tests required in Article 6. The required test switches will be placed such that they allow operation of lockout relays while preventing breaker failure schemes from operating and causing unnecessary breaker operations and/or the tripping of the Large Load Interconnection Customer’s Large Load Facilities.
9.6.4.5 The Participating TO and Large Load Interconnection Customer will test, operate and maintain System Protection Facilities in accordance with Good Utility Practice.
PDF page 115
28
9.6.4.6 Prior to the In-Service Date, and again prior to the Commercial Operation Date, the Participating TO and Large Load Interconnection Customer or their agents shall perform a complete calibration test and functional trip test of the System Protection Facilities. At intervals suggested by Good Utility Practice, the standards and procedures of the Participating TO, including, if applicable, the requirements of the Participating TO’s Interconnection Handbook, and following any apparent malfunction of the System Protection Facilities, each Party shall perform both calibration and functional trip tests of its System Protection Facilities. These tests do, however, require that all protective relays and lockout contacts be activated.
9.6.5 Requirements for Protection. In compliance with Good Utility Practice and, the Large Load Interconnection Customer shall provide, install, own, and maintain relays, circuit breakers and all other devices necessary to remove any fault contribution of the Large Load Facility to any short circuit occurring on the Participating TO’s Transmission System not otherwise isolated by the Participating TO’s equipment, such that the removal of the fault contribution shall be coordinated with the protective requirements of the Participating TO’s Transmission System. Such protective equipment shall include, without limitation, a disconnecting device with fault current-interrupting capability located between the Large Load Facility and the Participating TO’s Transmission System at a site selected upon mutual agreement (not to be unreasonably withheld, conditioned or delayed) of the Parties. The Large Load Interconnection Customer shall be responsible for protection of the Large Load Facility and the Large Load Interconnection Customer’s other equipment from such conditions as negative sequence currents, over- or under- frequency, sudden load rejection, over- or under-voltage, and generator loss-of- field. The Large Load Interconnection Customer shall be solely responsible to disconnect the Large Load Facility and the Large Load Interconnection Customer’s other equipment if conditions on the CAISO Controlled Grid could adversely affect the Large Load Facility.
9.6.6 Power Quality. Large Load Interconnection Customer’s facilities shall not cause excessive voltage flicker nor introduce excessive voltage and harmonic distortion to the sinusoidal voltage or current waves as defined by ANSI Standard C84.1-1989, in accordance with IEEE Standard 519, any applicable superseding electric industry standard, or any alternative Applicable Reliability Standard or Applicable Reliability Council standard. In the event of a conflict among ANSI Standard C84.1-1989, any applicable superseding electric industry standard, or any alternative Applicable Reliability Standard or Applicable Reliability Council standard, the alternative Applicable Reliability Standard or Applicable Reliability Council standard shall control.
9.7
Switching and Tagging Rules. Each Party shall provide the other Parties a copy of its switching and tagging rules that are applicable to the other Parties’ activities. Such switching and tagging rules shall be developed on a non-discriminatory basis. The Parties
PDF page 116
29
shall comply with applicable switching and tagging rules, as amended from time to time, in obtaining clearances for work or for switching operations on equipment. 9.8
Use of Interconnection Facilities by Third Parties.
9.8.1 Purpose of Interconnection Facilities. Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Load Facility to the Participating TO’s Transmission System and shall be used for no other purpose.
9.8.2 Third Party Users. If required by Applicable Laws and Regulations or if the Parties mutually agree, such agreement not to be unreasonably withheld, to allow one or more third parties to use the Participating TO’s Interconnection Facilities, or any part thereof, the Large Load Interconnection Customer will be entitled to compensation for the capital expenses it incurred in connection with the Interconnection Facilities based upon the pro rata use of the Interconnection Facilities by the Participating TO, all third party users, and the Large Load Interconnection Customer, in accordance with Applicable Laws and Regulations or upon some other mutually-agreed upon methodology. In addition, cost
responsibility for ongoing costs, including operation and maintenance costs associated with the Interconnection Facilities, will be allocated between the Large Load Interconnection Customer and any third party users based upon the pro rata use of the Interconnection Facilities by the Participating TO, all third party users, and the Large Load Interconnection Customer, in accordance with Applicable Laws and Regulations or upon some other mutually agreed upon methodology. If the issue of such compensation or allocation cannot be resolved through such negotiations, it shall be submitted to FERC for resolution.
9.9
Disturbance Analysis Data Exchange. The Parties will cooperate with one another in the analysis of disturbances to either the Large Load Facility or the Participating TO Transmission System by gathering and providing access to any information relating to any disturbance, including information from oscillography, protective relay targets, breaker operations and sequence of events records, and any disturbance information required by Good Utility Practice.
Article 10. Maintenance
10.1
Participating TO Obligations. The Participating TO shall maintain the Participating TO’s Transmission System and the Participating TO’s Interconnection Facilities in a safe and reliable manner and in accordance with this LLIA.
10.2
Large Load Interconnection Customer Obligations. The Large Load Interconnection Customer shall maintain the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LLIA.
PDF page 117
30
10.3
Coordination. The Parties shall confer regularly to coordinate the planning, scheduling and performance of preventive and corrective maintenance on the Large Load Facility and the Interconnection Facilities.
10.4
Secondary Systems. The Participating TO and Large Load Interconnection Customer shall cooperate with the other Parties in the inspection, maintenance, and testing of control or power circuits that operate below 600 volts, AC or DC, including, but not limited to, any hardware, control or protective devices, cables, conductors, electric raceways, secondary equipment panels, transducers, batteries, chargers, and voltage and current transformers that directly affect the operation of a Party’s facilities and equipment which may reasonably be expected to impact the other Parties. Each Party shall provide advance notice to the other Parties before undertaking any work on such circuits, especially on electrical circuits involving circuit breaker trip and close contacts, current transformers, or potential transformers.
10.5
Operating and Maintenance Expenses. Subject to the provisions herein addressing the use of facilities by others, and except for operations and maintenance expenses associated with modifications made for providing interconnection or transmission service to a third party and such third party pays for such expenses, the Large Load Interconnection Customer shall be responsible for all reasonable expenses including overheads, associated with: (1) owning, operating, maintaining, repairing, and replacing the Large Load Interconnection Customer’s Interconnection Facilities; and (2) operation, maintenance, repair, and replacement of the Participating TO’s Interconnection Facilities. Article 11. Performance Obligation
11.1
Large Load Interconnection Customer’s Interconnection Facilities. The Large Load Interconnection Customer shall design, procure, construct, install, own and/or control the Large Load Interconnection Customer’s Interconnection Facilities described in Appendix A and Appendix H at its sole expense.
11.2
Participating TO’s Interconnection Facilities. The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendices A and H at the sole expense of the Large Load Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Large Load Interconnection Customer.
11.3
Network Upgrades and Distribution Upgrades. The Participating TO shall design, procure, construct, install, and own the Network Upgrades and Distribution Upgrades described in Appendix A and Appendix H. The Large Load Interconnection Customer shall be responsible for all costs related to Distribution Upgrades. Network Upgrades shall be funded by the Large Load Interconnection Customer, and the Large Load Interconnection Customer shall bear the risk of, and be ultimately responsible for, the costs incurred to provide the Interconnection Service requested, including the costs of Network Upgrades, in accordance with this Article 11.3.
PDF page 118
31
11.3.1 Reimbursement for Network Upgrades. The Large Load Interconnection Customer shall be reimbursed in accordance with this Article 11.3.1 for amounts paid to the Participating TO for any Network Upgrade identified in Appendix A that has a cost of $10,000,000 or more (each, a “Reimbursable Network Upgrade”). Reimbursement for Reimbursable Network Upgrades placed in service on or before the Commercial Operation Date of the Large Load Facility shall commence upon the Commercial Operation Date. Reimbursement for each Reimbursable Network Upgrade placed in service after the Commercial Operation Date shall commence no later ninety (90) Calendar Days after such Network Upgrade is placed in service (as applicable, the “Reimbursement Commencement Date”). Subject to this Article 11.3, a reimbursement amount shall become fully and finally payable to the Large Load Interconnection Customer only when (x) such Network Upgrades have achieved Commercial Operation, (y) the Large Load Facility has achieved Commercial Operation and (z) the Large Load Interconnection Customer is not in Default under this LLIA (collectively, the “Final Payment Conditions”). Participating TO shall collect the cost of these facilities through its Transmission Revenue Requirement.
11.3.2 Repayment of Amounts Advanced for Network Upgrades.
11.3.2.1
Repayment Schedule. Any repayment amount provided pursuant
to Article 11.3.1 shall include any tax gross-up or other tax-related payments associated with Network Upgrades not refunded to the Large Load Interconnection Customer pursuant to Article 5 or otherwise, and shall be paid to the Large Load Interconnection Customer by the Participating TO on a dollar-for-dollar basis either through: (1) direct payments made on a levelized basis over a period of years, which shall be not less than five (5) years nor more than twenty (20) years, commencing on the applicable
Reimbursement Commencement Date (the “Repayment Period”);
or (2) any alternative payment schedule that is mutually agreeable to the Large Load Interconnection Customer and Participating TO, provided that such amount is paid within the Repayment Period, in each case subject to Article 11.3.2.4. The unpaid balance of any repayment amount outstanding from time to time shall accrue
interest at the rate calculated in accordance with the methodology set forth in FERC’s regulations at 18 C.F.R. §35.19a(a)(2)(iii), and such interest shall be paid together with each installment.
Notwithstanding the foregoing, if this LLIA terminates before the end of the applicable Repayment Period, the Participating TO’s obligation to pay refunds to the Large Load Interconnection
Customer shall cease as of the date of termination.
11.3.2.2
Interest Payments and Assignment Rights. Any repayment shall include interest calculated in accordance with the methodology set forth in FERC’s regulations at 18 C.F.R. §35.19a(a)(2)(iii) from the date of any payment for Network Upgrades through the date on
PDF page 119
32
which the Large Load Interconnection Customer receives a repayment of such payment. Interest shall continue to accrue on the repayment obligation so long as this LLIA is in effect. The Large Load Interconnection Customer may assign such repayment rights to any entity.
11.3.2.3
Failure to Achieve Commercial Operation. If the Large Load Facility fails to achieve Commercial Operation, but it or another Large Load Facility is later constructed, achieves Commercial Operation and makes use of the Network Upgrades, the Participating TO shall at that time reimburse Large Load Interconnection Customer for the amounts advanced for the Network Upgrades, provided that, notwithstanding Article 11.3.2.2, interest on such reimbursement shall not incur interest from the time the Large Load Facility that paid for the Network Upgrades fails to achieve Commercial Operation and, in the Participating TO’s reasonable discretion, will not be able to achieve Commercial Operation until the later Large Load Facility achieves Commercial Operation. Before any such reimbursement can occur, the Large Load Interconnection Customer, or the entity that ultimately constructs the Large Load Facility, if different, is responsible for identifying and demonstrating to the Participating TO the appropriate entity to which reimbursement must be made in order to implement the intent of this reimbursement obligation. 11.3.2.4
Accelerated Reimbursement Against Reimbursement Security. As a condition precedent to receiving any Reimbursement, the Large Load Interconnection Customer shall provide, and thereafter maintain until released under this Article 11.3.2.4, credit support in a form acceptable to Participating TO and from an issuer reasonably acceptable to the Participating TO (the
“Reimbursement Security”) in an amount equal to: (i) initially, an amount equal to the anticipated first Reimbursement payment (based on the amount of the Network Upgrades divided by the years in the Repayment Period); and (ii) thereafter, the aggregate amount of all Reimbursements received by the Large Load Interconnection Customer plus the amounts for the operation and maintenance of the Network Upgrades to date, for a period of five
(5) years from the Participating TO’s receipt of such Reimbursement Security. The Reimbursement Security shall secure the Large Load Interconnection Customer’s obligation to pay the Participating TO, within thirty (30) Calendar Days of invoice, any amount by which Participating TO is not able to collect relating to the full cost of a Reimbursable Network Upgrade in Participating TO’s Transmission Revenue Requirement
PDF page 120
33
In addition, the Large Load Interconnection Customer may elect, by written notice to the Participating TO, to receive reimbursement amounts for Reimbursable Network Upgrades for which it has made payment before such amounts have become fully and finally payable under Article 11.3.1 and Article 11.3.2.1 (each such payment, an “Accelerated Reimbursement”). In order to receive such Accelerated Reimbursement, the Large Load Interconnection Customer shall post Reimbursement Security. Prior to receipt of each additional Accelerated Reimbursement before the
Commercial Operation Date, the Large Load Interconnection Customer shall increase the Reimbursement Security by the amount of such additional Accelerated Reimbursement, such that the Reimbursement Security at all times through the Commercial Operation Date is not less than the cumulative Accelerated Reimbursements received.
The Participating TO shall pay each Reimbursement and Accelerated Reimbursement, as applicable, within thirty (30) Calendar Days after its receipt of the required Reimbursement Security, and no interest shall accrue under Article 11.3.2.1 or Article 11.3.2.2 on any amount from and after the date it is paid. If (a) the Final Payment Conditions are not satisfied with respect to any portion of an Accelerated Reimbursement, or (b) this LLIA terminates before any portion of an Accelerated Reimbursement has become fully and finally payable, the Large Load
Interconnection Customer shall repay such portion to the Participating TO, together with interest calculated in accordance with 18 C.F.R. §35.19a(a)(2)(iii) from the date of the Accelerated Reimbursement, within thirty (30) Calendar Days of invoice. If the Large Load Interconnection Customer fails to timely make any such repayment, or fails to renew or replace the Reimbursement Security at least thirty (30) Calendar Days before its expiration or to replenish it within five (5) Business Days after any draw, the Participating TO may draw upon the Reimbursement Security in the amount of the unpaid repayment obligation or, in the case of a failure to renew, replace, or replenish, in the full amount of the then-outstanding Reimbursements, and hold any cash proceeds as security for such obligation. Any portion of an Accelerated Reimbursement repaid or recovered by the Participating TO shall remain eligible for reimbursement in accordance with this Article 11.3 when it becomes fully and finally payable.
11.3.3 Special Provisions for Affected Systems. The Large Load Interconnection Customer shall enter into an agreement with the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid, as applicable, in accordance with this Article 11.3.3. Such agreement shall specify the
PDF page 121
34
terms governing payments to be made by the Large Load Interconnection Customer to the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid as well as the repayment by the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid. In no event shall the Participating TO be responsible for the repayment for any facilities that are not part of the Participating TO’s Transmission System. In the event the Participating TO is a joint owner with an Affected System or with any other co-owner of a facility affected by the Large Load Facility, the Participating TO’s obligation to reimburse the Large Load Interconnection Customer for payments made to address the impacts of the Large Load Facility on the system shall not exceed the proportionate amount of the cost of any upgrades attributable to the proportion of the jointly-owned facility owned by the Participating TO. 11.4
Provision of Interconnection Financial Security. The Large Load Interconnection Customer is obligated to provide all necessary Interconnection Financial Security required under Attachment 4 to the LLIP in a manner acceptable under Attachment 4. Failure by the Large Load Interconnection Customer to timely satisfy the terms and conditions set forth in Attachment 4 to the LLIP for the provision of Interconnection Financial Security shall be deemed a Breach of this Agreement and a condition of Default of this Agreement.
11.4.1 Notwithstanding any other provision of this Agreement for notice of Default and opportunity to cure such Default, the Participating TO shall provide the Large Load Interconnection Customer with written notice of any Default due to timely failure to post Interconnection Financial Security, and the Large Load Interconnection Customer shall have five (5) Business Days from the date of such notice to cure such Default by posting the required Interconnection Financial Security. If the Large Load Interconnection Customer fails to cure the Default, then this Agreement shall be deemed terminated.
Article 12. Invoice
12.1
General. The Participating TO shall submit to the Large Load Interconnection Customer, on a monthly basis, invoices of amounts due pursuant to this LLIA for the preceding month. Each invoice shall state the month to which the invoice applies and fully describe the services and equipment provided. The Parties may discharge mutual debts and payment obligations due and owing to each other on the same date through netting, in which case all amounts a Party owes to the other Party under this LLIA, including interest payments or credits, shall be netted so that only the net amount remaining due shall be paid by the owing Party.
12.2
Final Invoice. As soon as reasonably practicable, but within twelve (12) months after completion of the construction of the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades, the Participating TO shall provide an invoice of the final cost of the construction of the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades, and shall set forth such costs in sufficient detail to enable the Large Load Interconnection Customer to compare the actual
PDF page 122
35
costs with the estimates and to ascertain deviations, if any, from the cost estimates. With respect to costs associated with the Participating TO’s Interconnection Facilities and Distribution Upgrades, the Participating TO shall refund to the Large Load Interconnection Customer any amount by which the actual payment by the Large Load Interconnection Customer for estimated costs exceeds the actual costs of construction within thirty (30) Calendar Days of the issuance of such final construction invoice; or, in the event the actual costs of construction exceed the Large Load Interconnection Customer’s actual payment for estimated costs, then the Large Load Interconnection Customer shall pay to the Participating TO any amount by which the actual costs of construction exceed the actual payment by the Large Load Interconnection Customer for estimated costs within thirty (30) Calendar Days of the issuance of such final construction invoice. With respect to costs associated with Network Upgrades, the Participating TO shall refund to the Large Load Interconnection Customer any amount by which the actual payment by the Large Load Interconnection Customer for estimated costs exceeds the actual costs of construction multiplied by the Large Load Interconnection Customer’s percentage share of those costs, as set forth in Appendix G to this LLIA within thirty (30) Calendar Days of the issuance of such final construction invoice. In the event the actual costs of construction multiplied by the Large Load Interconnection Customer’s percentage share of those costs exceed the Large Load Interconnection Customer’s actual payment for estimated costs, then the Participating TO shall recover such difference through its transmission service rates. 12.3
Payment. Invoices shall be rendered to the Large Load Interconnection Customer at the address specified in Appendix F. The Large Load Interconnection Customer shall pay, or Participating TO shall refund, the amounts due within thirty (30) Calendar Days of the Large Load Interconnection Customer’s receipt of the invoice. All payments shall be made in immediately available funds payable to the Large Load Interconnection Customer or Participating TO, or by wire transfer to a bank named and account designated by the invoicing Large Load Interconnection Customer or Participating TO. Payment of invoices by any Party will not constitute a waiver of any rights or claims any Party may have under this LLIA.
12.4
Disputes. In the event of a billing dispute between the Large Load Interconnection Customer and the Participating TO, the Participating TO shall continue to provide Interconnection Service under this LLIA as long as the Large Load Interconnection Customer: (i) continues to make all payments not in dispute; and (ii) pays to the Participating TO or into an independent escrow account the portion of the invoice in dispute, pending resolution of such dispute. If the Large Load Interconnection Customer fails to meet these two requirements for continuation of service, then the Participating TO may provide notice to the Large Load Interconnection Customer of a Default pursuant to Article 17. Within thirty (30) Calendar Days after the resolution of the dispute, the Party that owes money to the other Party shall pay the amount due with interest calculated in accordance with the methodology set forth in FERC’s Regulations at 18 C.F.R. § 35.19a(a)(2)(iii).
PDF page 123
36
Article 13. Emergencies
13.1
[Reserved]
13.2
Obligations. Each Party shall comply with the Emergency Condition procedures of the CAISO, NERC, the Applicable Reliability Council, Applicable Reliability Standards, Applicable Laws and Regulations, Applicable Reliability Coordinators requirements, and any emergency procedures set forth in this LLIA or provided by the Participating TO. 13.3
Notice. The Participating TO shall notify the Large Load Interconnection Customer promptly when it becomes aware of an Emergency Condition that affects the Participating TO’s Interconnection Facilities or Distribution System or the CAISO Controlled Grid, respectively, that may reasonably be expected to affect the Large Load Interconnection Customer’s operation of the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities. The Large Load Interconnection Customer shall notify the Participating TO and, as applicable, the CAISO promptly when it becomes aware of an Emergency Condition that affects the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities that may reasonably be expected to affect the CAISO Controlled Grid or the Participating TO’s Interconnection Facilities. To the extent information is known, the notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of the Large Load Interconnection Customer’s or Participating TO’s facilities and operations, its anticipated duration and the corrective action taken and/or to be taken. The initial notice shall be followed as soon as practicable with written notice, if requested by a Party, which may be provided by electronic mail or facsimile.
13.4
Immediate Action. Unless, in the Large Load Interconnection Customer’s reasonable judgment, immediate action is required, the Large Load Interconnection Customer shall obtain the consent of the Participating TO, such consent to not be unreasonably withheld, prior to performing any manual switching operations at the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities in response to an Emergency Condition declared by the Participating TO in response to any other emergency condition.
13.5
Participating TO Authority.
13.5.1 General. The Participating TO may take whatever actions or inactions, including issuance of dispatch instructions, with regard to Participating TO’s Interconnection Facilities or Distribution System they deem necessary during an Emergency Condition in order to: (i) preserve public health and safety; (ii) preserve the reliability of the Participating TO’s Transmission System and/or the Participating TO’s Interconnection Facilities or Distribution System; (iii) limit or prevent damage; and (iv) expedite restoration of service.
The Participating TO shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities. The Participating TO may, on the basis of
PDF page 124
37
technical considerations, require the Large Load Facility to mitigate an Emergency Condition by taking actions necessary and limited in scope to remedy the Emergency Condition, including, but not limited to, directing the Large Load Interconnection Customer to shut-down, implementing a reduction or
disconnection pursuant to Article 13.5.2; or altering the outage schedules of the Large Load Facility and the Large Load Interconnection Customer’s
Interconnection Facilities.
13.5.2 Reduction and Disconnection. The Participating TO may reduce Interconnection Service or disconnect the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities when such reduction or disconnection is necessary under Good Utility Practice due to Emergency Conditions and/or under certain abnormal operating conditions to maintain the reliability of the transmission network. When the Participating TO can schedule the reduction or disconnection in advance, the Participating TO shall notify the Large Load Interconnection Customer of the reasons, timing and expected duration of the reduction or disconnection. The Participating TO shall coordinate with the Large Load Interconnection Customer using Good Utility Practice to schedule the reduction or disconnection during periods of least impact to the Large Load Interconnection Customer and the Participating TO. Any reduction or disconnection shall continue only for so long as reasonably necessary under Good Utility Practice. The Parties shall cooperate with each other to restore the Large Load Facility, the Interconnection Facilities, and the Participating TO’s Transmission System to their normal operating state as soon as practicable consistent with Good Utility Practice.
13.6
Large Load Interconnection Customer Authority. Consistent with Good Utility Practice and this LLIA, the Large Load Interconnection Customer may take actions or inactions with regard to the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities during an Emergency Condition in order to: (i) preserve public health and safety; (ii) preserve the reliability of the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities; (iii) limit or prevent damage; and (iv) expedite restoration of service. Large Load Interconnection Customer shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Participating TO’s Transmission System and the Participating TO’s Interconnection Facilities. The Participating TO shall use Reasonable Efforts to assist Large Load Interconnection Customer in such actions.
13.7
Limited Liability. Except as otherwise provided in this LLIA, no Party shall be liable to any other Party for any action it takes in responding to an Emergency Condition so long as such action is made in good faith and is consistent with Good Utility Practice. Article 14. Regulatory Requirements and Governing Laws
14.1
Regulatory Requirements. Each Party’s obligations under this LLIA shall be subject to its receipt of any required approval or certificate from one or more Governmental Authorities in the form and substance satisfactory to the applying Party, or the Party making any required filings with, or providing notice to, such Governmental Authority,
PDF page 125
38
and the expiration of any time period associated therewith. Each Party shall in good faith seek and use its Reasonable Efforts to obtain such other approvals. Nothing in this LLIA shall require the Large Load Interconnection Customer to take any action that could result in its inability to obtain, or its loss of, status or exemption under the Federal Power Act or the Public Utility Holding Company Act of 1935, as amended, or the Public Utility Regulatory Policies Act of 1978, or the Energy Policy Act of 2005. 14.2
Governing Law.
14.2.1 The validity, interpretation and performance of this LLIA and each of its provisions shall be governed by the laws of the state where the Point of Interconnection is located, without regard to its conflicts of law principles.
14.2.2 This LLIA is subject to all Applicable Laws and Regulations.
14.2.3 Each Party expressly reserves the right to seek changes in, appeal, or otherwise contest any laws, orders, rules, or regulations of a Governmental Authority. Article 15. Notices
15.1
General. Unless otherwise provided in this LLIA, any notice, demand or request required or permitted to be given by a Party to another and any instrument required or permitted to be tendered or delivered by a Party in writing to another shall be effective when delivered and may be so given, tendered or delivered, by recognized national courier, conveyed by e-mail, or by depositing the same with the United States Postal Service with postage prepaid, for delivery by certified or registered mail, addressed to the Party, or personally delivered to the Party, at the address set out in Appendix F, Addresses for Delivery of Notices and Billings.
A Party must update the information in Appendix F as information changes. A Party may change the notice information in this LLIA by giving five (5) Business Days written notice prior to the effective date of the change. Such changes shall not constitute an amendment to this LLIA.
15.2
Billings and Payments. Billings and payments shall be sent to the addresses set out in Appendix F.
15.3
Alternative Forms of Notice. Any notice or request required or permitted to be given by a Party to another and not required by this LLIA to be given as provided in Article 15.1 may be so given by telephone, or e-mail to the telephone numbers and e-mail addresses set out in Appendix F.
15.4
Operations and Maintenance Notice. Each Party shall notify the other Parties in writing of the identity of the person(s) that it designates as the point(s) of contact with respect to the implementation of Articles 9 and 10.
PDF page 126
39
Article 16. Force Majeure
16.1
Force Majeure.
16.1.1 Economic hardship is not considered a Force Majeure event.
16.1.2 No Party shall be considered to be in Default with respect to any obligation hereunder, (including obligations under Article 4), other than the obligation to pay money when due, if prevented from fulfilling such obligation by Force Majeure. A Party unable to fulfill any obligation hereunder (other than an obligation to pay money when due) by reason of Force Majeure shall give notice and the full particulars of such Force Majeure to the other Party in writing or by telephone as soon as reasonably possible after the occurrence of the cause relied upon. Telephone notices given pursuant to this Article shall be confirmed in writing as soon as reasonably possible and shall specifically state full particulars of the Force Majeure, the time and date when the Force Majeure occurred and when the Force Majeure is reasonably expected to cease. The Party affected shall exercise due diligence to remove such disability with reasonable dispatch, but shall not be required to accede or agree to any provision not satisfactory to it to settle and terminate a strike or other labor disturbance.
Article 17. Default
17.1
Default.
17.1.1 General. No Default shall exist where such failure to discharge an obligation (other than the payment of money) is the result of Force Majeure as defined in this LLIA or the result of an act or omission of the other Party. Upon a Breach, the affected non-Breaching Party(ies) shall give written notice of such Breach to the Breaching Party. Except as otherwise provided herein, the Breaching Party shall have thirty
(30) Calendar Days from receipt of the Default notice within which to cure such Breach; provided however, if such Breach is not capable of cure within thirty (30) Calendar Days, the Breaching Party shall commence such cure within thirty (30) Calendar Days after notice and continuously and diligently complete such cure within ninety (90) Calendar Days from receipt of the Default notice; and, if cured within such time, the Breach specified in such notice shall cease to exist. 17.1.2 Right to Terminate. If a Breach is not cured as provided in this Article, or if a Breach is not capable of being cured within the period provided for herein, the affected non-Breaching Party(ies) shall have the right to declare a Default and terminate this LLIA by written notice at any time until cure occurs, and be relieved of any further obligation hereunder and, whether or not such Party(ies) terminates this LLIA, to recover from the Breaching Party all amounts due hereunder, plus all other damages and remedies to which it is entitled at law or in equity. The provisions of this Article will survive termination of this LLIA.
PDF page 127
40
Article 18. Indemnity, Consequential Damages, and Insurance
18.1
Indemnity. Each Party (the “Indemnifying Party”) shall at all times indemnify, defend, and hold the other Parties (“Indemnified Party”) harmless from, any and all Losses arising out of or resulting from another Party’s action or inactions of its obligations under this LLIA on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the Indemnified Party.
18.1.1 Indemnified Party. If an Indemnified Party is entitled to indemnification under this Article 18 as a result of a claim by a third party, and the Indemnifying Party fails, after notice and reasonable opportunity to proceed under Article 18.1, to assume the defense of such claim, such Indemnified Party may at the expense of the Indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.
18.1.2 Indemnifying Party. If an Indemnifying Party is obligated to indemnify and hold any Indemnified Party harmless under this Article 18, the amount owing to the Indemnified Party shall be the amount of such Indemnified Party’s actual Loss, net of any insurance or other recovery.
18.1.3 Indemnity Procedures. Promptly after receipt by an Indemnified Party of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in Article 18.1 may apply, the Indemnified Party shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect a Party’s indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying Party.
The Indemnifying Party shall have the right to assume the defense thereof with counsel designated by such Indemnifying Party and reasonably satisfactory to the Indemnified Party. If the defendants in any such action include one or more Indemnified Parties and the Indemnifying Party and if the Indemnified Party reasonably concludes that there may be legal defenses available to it and/or other Indemnified Parties which are different from or additional to those available to the Indemnifying Party, the Indemnified Party shall have the right to select separate counsel to assert such legal defenses and to otherwise participate in the defense of such action on its own behalf. In such instances, the Indemnifying Party shall only be required to pay the fees and expenses of one additional attorney to represent an Indemnified Party or Indemnified Parties having such differing or additional legal defenses.
The Indemnified Party shall be entitled, at its expense, to participate in any such action, suit or proceeding, the defense of which has been assumed by the Indemnifying Party. Notwithstanding the foregoing, the Indemnifying Party: (i) shall not be entitled to assume and control the defense of any such action, suit or proceedings if and to the extent that, in the opinion of the Indemnified Party and its counsel, such action, suit or proceeding involves the potential imposition of
PDF page 128
41
criminal liability on the Indemnified Party, or there exists a conflict or adversity of interest between the Indemnified Party and the Indemnifying Party, in such event the Indemnifying Party shall pay the reasonable expenses of the Indemnified Party; and (ii) shall not settle or consent to the entry of any judgment in any action, suit or proceeding without the consent of the Indemnified Party, which shall not be unreasonably withheld, conditioned or delayed.
18.2
Consequential Damages. Other than the liquidated damages heretofore described in Article 5.2, in no event shall any Party be liable under any provision of this LLIA for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided, however, that damages for which a Party may be liable to another Party under another agreement will not be considered to be special, indirect, incidental, or consequential damages hereunder.
18.3
Insurance. As indicated below, the designated Party shall, at its own expense, maintain in force throughout the periods noted in this LLIA, and until released by the other Parties, the following minimum insurance coverages, with insurers rated no less than A- (with a minimum size rating of VII) by Bests’ Insurance Guide and Key Ratings and authorized to do business in the state where the Point of Interconnection is located, except in the case of any insurance required to be carried by the CAISO, the State of California: 18.3.1 Workers’ Compensation Insurance and Employers’ Liability. The Participating TO and the Large Load Interconnection Customer shall maintain such coverage from the commencement of any construction activities providing statutory benefits for Workers Compensation coverage and coverage amounts of no less than One Million Dollars ($1,000,000) for employer’s liability for each employee for bodily injury by accident and One Million Dollars ($1,000,000) for each employee for bodily injury by disease in accordance with the laws and regulations of the state in which the Point of Interconnection is located. The Participating TO shall provide the Large Load Interconnection Customer with evidence of such insurance coverage within thirty (30) Calendar Days of any request by the Large Load Interconnection Customer. The Large Load Interconnection Customer shall provide evidence of such insurance thirty (30) Calendar Days prior to entry by any employee or contractor or other person acting on the Large Load Interconnection Customer’s behalf onto any construction site to perform any work related to the Interconnection Facilities or Large Load Facility.
18.3.2 Commercial General Liability Insurance. The Participating TO and the Large Load Interconnection Customer shall maintain commercial general liability insurance coverage commencing within thirty (30) Calendar Days of the Effective Date of this LLIA, including coverage for premises and operations, bodily injury (including death), personal injury, property damage, products and completed operations coverage, coverage for explosion, collapse and underground hazards, independent contractors coverage, and (i) liability of Participating TO and the Large
PDF page 129
42
Load Interconnection Customer that would be imposed without the LLIA, or (ii) liability assumed by the Participating TO and the Large Load Interconnection Customer in a contract or agreement that is an “insured contract” under commercial general liability insurance policy. Such insurance shall include no cross-liability exclusions or separation of insured clause endorsement exclusions, with minimum limits of One Million Dollars ($1,000,000) per occurrence/One Million Dollars ($1,000,000) aggregate. If the activities of the Large Load Interconnection Customer are being conducted through the actions of an Affiliate, then the Large Load Interconnection Customer may satisfy the insurance requirements of this Article 18.3.2 by providing evidence of insurance coverage carried by such Affiliate and showing the Participating TO and, as applicable, the CAISO as an additional insured only with respect to the LLIA, together with the Large Load Interconnection Customer’s written representation to the Participating TO and, as applicable, the CAISO that the insured Affiliate is conducting all of the necessary pre-construction work. Within thirty (30) Calendar Days prior to the entry of any person on behalf of the Large Load Interconnection Customer onto any construction site to perform work related to the Interconnection Facilities or Large Load Facility, the Large Load Interconnection Customer shall replace any evidence of affiliate insurance with evidence of such insurance carried by the Large Load Interconnection Customer, naming the Participating TO and, as applicable, the CAISO as additional insured only with respect to the LLIA.
18.3.3 Business Automobile Liability Insurance. Prior to the entry of any such vehicles on any construction site in connection with work done by or on behalf of the Large Load Interconnection Customer, the Large Load Interconnection Customer shall provide evidence of coverage of owned and non-owned and hired vehicles, trailers or semi-trailers designed for travel on public roads, with a minimum, combined single limit of One Million Dollars ($1,000,000) per occurrence for bodily injury, including death, and property damage. The Large Load Interconnection Customer shall include the Participating TO and, as applicable, the CAISO as additional insured with respect to the LLIA on any such policies.
18.3.4 Excess Liability Insurance. Commencing at the time of entry of any person on its behalf upon any construction site for the Network Upgrades, Interconnection Facilities, or Large Load Facility, the Participating TO and the Large Load Interconnection Customer shall maintain Excess Liability insurance over and above the Employer’s Liability Commercial General Liability and Business Automobile Liability Insurance coverage, with a minimum limit of Twenty Million Dollars ($20,000,000) per occurrence/Twenty Million Dollars ($20,000,000) aggregate. Such insurance carried by the Participating TO shall include the Large Load Interconnection Customer and, as applicable, the CAISO as additional insured with respect to the LLIA, and such insurance carried by the Large Load Interconnection Customer shall include the Participating TO and, as applicable, the CAISO as an additional insured with respect to the LLIA. The requirements of Articles 18.3.2 and 18.3.4 may be met by any combination of general and excess liability insurance.
PDF page 130
43
18.3.5 The Commercial General Liability Insurance, Business Automobile Liability Insurance and Excess Liability Insurance policies shall include the other Parties identified in the articles above, their parents, their subsidiaries, respective directors, officers, agents, servants and employees (“Other Party Group”) and, as applicable, the CAISO as additional insured. All policies shall contain provisions whereby the insurers waive all rights of subrogation in accordance with the provisions of this LLIA against the Other Party Group. If any Party can reasonably demonstrate that coverage policies containing provisions for insurer waiver of subrogation rights, or advance notice are not commercially available, then the Parties shall meet and confer and mutually determine to: (i) establish replacement or equivalent terms in lieu of subrogation or notice; or (ii) waive the requirements that coverage(s) include such subrogation provision or require advance written notice from such insurers. 18.3.6 The Commercial General Liability Insurance, Business Automobile Liability Insurance and Excess Liability Insurance policies shall contain provisions that specify that the policies are primary and non-contributory. Each Party shall be responsible for its respective deductibles or self-insured retentions. 18.3.7 The Commercial General Liability Insurance, Business Automobile Liability Insurance and Excess Liability Insurance policies, if written on a claims first made basis, shall be maintained in full force and effect for two (2) years after termination of this LLIA, which coverage may be in the form of extended reporting period coverage if agreed by the Parties.
18.3.8 [Not Used.]
18.3.9 Thirty (30) Calendar Days prior to the start of any work at the construction site related to Interconnection Facilities or Large Load Facility under this LLIA, and as soon as practicable after the end of each fiscal year or at the renewal of the insurance policy and in any event within ninety (90) Calendar Days thereafter, the Participating TO and the Large Load Interconnection Customer shall provide a certificate of insurance for all insurance required in this LLIA, executed by each insurer or by an authorized representative of each insurer.
18.3.10 Notwithstanding the foregoing, each Party may self-insure:
(a) to meet the minimum insurance requirements of Article 18.3.1, to the extent that it maintains a self-insurance program that is a qualified self-insurer within the state in which the Point of Interconnection is located, under the laws and regulations of such state; and
(b) to meet the minimum insurance requirements of Articles 18.3.2 through 18.3.8 to the extent it maintains a self-insurance program; provided that, such Party’s senior unsecured debt or issuer rating is BBB-, or better, as rated by Standard & Poor’s and that its self-insurance program meets the minimum insurance requirements of Articles 18.3.2 through 18.3.8. For any period of time that a Party’s senior unsecured debt rating and issuer rating are both unrated by Standard & Poor’s or
PDF page 131
44
are both rated at less than BBB- by Standard & Poor’s, such Party shall comply with the insurance requirements applicable to it under Articles 18.3.2 through 18.3.9.
(c) in the event that a Party is permitted to self-insure pursuant to this Article 18.3.10, it shall notify the other Parties that it meets the requirements to self-insure and that its self-insurance program meets the minimum insurance requirements in a manner consistent with that specified in Article 18.3.9.
18.3.11The Parties agree to report to each other in writing as soon as practical all accidents or occurrences resulting in injuries to any person, including death, and any property damage greater than $25,000, including within the scope of coverage of such insurance whether or not such coverage is sought.
Article 19. Assignment
19.1
Assignment. This LLIA may be assigned by a Party only with the written consent of the other Parties; provided that a Party may assign this LLIA without the consent of the other Parties to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this LLIA; and provided further that the Large Load Interconnection Customer shall have the right to assign this LLIA, without the consent of the Participating TO for collateral security purposes to aid in providing financing for the Large Load Facility, provided that the Large Load Interconnection Customer will promptly notify the Participating TO of any such assignment. Any financing arrangement entered into by the Large Load Interconnection Customer pursuant to this Article will provide that prior to or upon the exercise of the secured party’s, trustee’s or mortgagee’s assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify the Participating TO of the date and particulars of any such exercise of assignment right(s), including providing the Participating TO, with proof that it meets the requirements of Articles 11.3 and 18.3. Any attempted assignment that violates this Article is void and ineffective. Any assignment under this LLIA shall not relieve a Party of its obligations, nor shall a Party’s obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.
Article 20. Severability
20.1
Severability. If any provision in this LLIA is finally determined to be invalid, void or unenforceable by any court or other Governmental Authority having jurisdiction, such determination shall not invalidate, void or make unenforceable any other provision, agreement or covenant of this LLIA.
Article 21. Comparability
21.1
Comparability. The Parties will comply with all applicable comparability and code of conduct laws, rules and regulations, as amended from time to time.
PDF page 132
45
Article 22. Confidentiality
22.1
Confidentiality. Confidential Information shall include, without limitation, all information relating to a Party’s technology, research and development, business affairs, and pricing, and any information supplied by any of the Parties to the other Parties prior to the execution of this LLIA.
Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Parties receiving the information that the information is confidential.
If requested by any Party, the other Parties shall provide in writing the basis for asserting that the information referred to in this Article 22 warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority. Each Party shall be responsible for the costs associated with affording confidential treatment to its information.
22.1.1 Term. During the term of this LLIA, and for a period of three (3) years after the expiration or termination of this LLIA, except as otherwise provided in this Article 22, each Party shall hold in confidence and shall not disclose to any person Confidential Information.
22.1.2 Scope. Confidential Information shall not include information that the receiving Party can demonstrate: (1) is generally available to the public other than as a result of a disclosure by the receiving Party; (2) was in the lawful possession of the receiving Party on a non-confidential basis before receiving it from the disclosing Party; (3) was supplied to the receiving Party without restriction by a third party, who, to the knowledge of the receiving Party after due inquiry, was under no obligation to the disclosing Party to keep such information confidential; (4) was independently developed by the receiving Party without reference to Confidential Information of the disclosing Party; (5) is, or becomes, publicly known, through no wrongful act or omission of the receiving Party or Breach of this LLIA; or (6) is required, in accordance with Article 22.1.7 of this LLIA, Order of Disclosure, to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena, or is necessary in any legal proceeding establishing rights and obligations under this LLIA. Information designated as Confidential Information will no longer be deemed confidential if the Party that designated the information as confidential notifies the other Parties that it no longer is confidential. 22.1.3 Release of Confidential Information. No Party shall release or disclose Confidential Information to any other person, except to its employees, consultants, Affiliates (limited by the Standards of Conduct requirements set forth in Part 358 of FERC’s Regulations, 18 C.F.R. 358), subcontractors, or to parties who may be or considering providing financing to or equity participation with the Large Load Interconnection Customer, or to potential purchasers or assignees of the Large Load Interconnection Customer, on a need-to-know basis in connection with this LLIA,
PDF page 133
46
unless such person has first been advised of the confidentiality provisions of this Article 22 and has agreed to comply with such provisions. Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible for any release of Confidential Information in contravention of this Article 22.
22.1.4 Rights. Each Party retains all rights, title, and interest in the Confidential Information that each Party discloses to the other Parties. The disclosure by each Party to the other Parties of Confidential Information shall not be deemed a waiver by a Party or any other person or entity of the right to protect the Confidential Information from public disclosure.
22.1.5 No Warranties. The mere fact that a Party has provided Confidential Information does not constitute a warranty or representation as to its accuracy or completeness. In addition, by supplying Confidential Information, no Party obligates itself to provide any particular information or Confidential Information to the other Parties nor to enter into any further agreements or proceed with any other relationship or joint venture.
22.1.6 Standard of Care. Each Party shall use at least the same standard of care to protect Confidential Information it receives as it uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination. Each Party may use Confidential Information solely to fulfill its obligations to the other Parties under this LLIA or its regulatory requirements.
22.1.7 Order of Disclosure. If a court or a Governmental Authority or entity with the right, power, and apparent authority to do so requests or requires any Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the other Parties with prompt notice of such request(s) or requirement(s) so that the other Parties may seek an appropriate protective order or waive compliance with the terms of this LLIA. Notwithstanding the absence of a protective order or waiver, the Party may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose. Each Party will use Reasonable Efforts to obtain reliable assurance that confidential treatment will be accorded any Confidential Information so furnished. 22.1.8 Termination of Agreement. Upon termination of this LLIA for any reason, each Party shall, within ten (10) Calendar Days of receipt of a written request from another Party, use Reasonable Efforts to destroy, erase, or delete (with such destruction, erasure, and deletion certified in writing to the other Party) or return to the other Party, without retaining copies thereof, any and all written or electronic Confidential Information received from the other Party.
22.1.9 Remedies. The Parties agree that monetary damages would be inadequate to compensate a Party for another Party’s Breach of its obligations under this Article
22. Each Party accordingly agrees that the other Parties shall be entitled to equitable
PDF page 134
47
relief, by way of injunction or otherwise, if the first Party Breaches or threatens to Breach its obligations under this Article 22, which equitable relief shall be granted without bond or proof of damages, and the receiving Party shall not plead in defense that there would be an adequate remedy at law. Such remedy shall not be deemed an exclusive remedy for the Breach of this Article 22 but shall be in addition to all other remedies available at law or in equity. The Parties further acknowledge and agree that the covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope. No Party, however, shall be liable for indirect, incidental, or consequential or punitive damages of any nature or kind resulting from or arising in connection with this Article 22.
22.1.10 Disclosure to FERC, its Staff, or a State. Notwithstanding anything in this Article 22 to the contrary, and pursuant to 18 C.F.R. section 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence pursuant to this LLIA, the Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information. In providing the information to FERC or its staff, the Party must, consistent with 18 C.F.R. section 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Parties to this LLIA prior to the release of the Confidential Information to FERC or its staff. The Party shall notify the other Parties to the LLIA when it is notified by FERC or its staff that a request to release Confidential Information has been received by FERC, at which time any of the Parties may respond before such information would be made public, pursuant to 18 C.F.R. section 388.112. Requests from a state regulatory body conducting a confidential investigation shall be treated in a similar manner if consistent with the applicable state rules and regulations.
22.1.11 Subject to the exception in Article 22.1.10, Confidential Information shall not be disclosed by the other Parties to any person not employed or retained by the other Parties, except to the extent disclosure is: (i) required by law; (ii) reasonably deemed by the disclosing Party to be required to be disclosed in connection with a dispute between or among the Parties, or the defense of litigation or dispute; (iii) otherwise permitted by consent of the other Parties, such consent not to be unreasonably withheld; or (iv) necessary to fulfill its obligations under this LLIA or as a transmission service provider or a Balancing Authority including disclosing the Confidential Information to a Regional Transmission Organization or Independent System Operator or to a regional or national reliability organization. The Party asserting confidentiality shall notify the other Parties in writing of the information it claims is confidential. Prior to any disclosures of another Party’s Confidential Information under this subparagraph, or if any third party or Governmental Authority makes any request or demand for any of the information described in this subparagraph, the disclosing Party agrees to promptly notify the other Party in writing and agrees to assert confidentiality and cooperate with the other Party in
PDF page 135
48
seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order or other reasonable measures. Article 23. Environmental Releases
23.1
Each Party shall notify the other Parties, first orally and then in writing, of the release of any Hazardous Substances, any asbestos or lead abatement activities, or any type of remediation activities related to the Large Load Facility or the Interconnection Facilities, each of which may reasonably be expected to affect the other Parties. The notifying Party shall: (i) provide the notice as soon as practicable, provided such Party makes a good faith effort to provide the notice no later than twenty-four (24) hours after such Party becomes aware of the occurrence; and (ii) promptly furnish to the other Parties copies of any publicly available reports filed with any Governmental Authorities addressing such events.
Article 24. Information Requirements
24.1
Information Acquisition. The Participating TO and the Large Load Interconnection Customer shall submit specific information regarding the electrical characteristics of their respective facilities to each other as described below and in accordance with Applicable Reliability Standards.
24.2
Information Submission by Participating TO. The initial information submission by the Participating TO shall occur no later than one hundred eighty (180) Calendar Days prior to Trial Operation and shall include the Participating TO’s Transmission System information necessary to allow the Large Load Interconnection Customer to select equipment and meet any system protection and stability requirements, unless otherwise agreed to by the Participating TO and the Large Load Interconnection Customer. On a monthly basis the Participating TO shall provide the Large Load Interconnection Customer and, as applicable, the CAISO a status report on the construction and installation of the Participating TO’s Interconnection Facilities and Network Upgrades, including, but not limited to, the following information: (1) progress to date; (2) a description of the activities since the last report; (3) a description of the action items for the next period; and (4) the delivery status of equipment ordered.
Article 25. Information Access and Audit Rights
25.1
Information Access. Each Party (the “disclosing Party”) shall make available to the other Party information that is in the possession of the disclosing Party and is necessary in order for the other Party to: (i) verify the costs incurred by the disclosing Party for which the other Party is responsible under this LLIA; and (ii) carry out its obligations and responsibilities under this LLIA. The Parties shall not use such information for purposes other than those set forth in this Article 25.1 and to enforce their rights under this LLIA. Nothing in this Article 25 shall obligate the Participating TO to make available to a Party any third-party information in its possession or control. if making such third-party information available would violate Participating TO’s obligations the use or disclosure of such third-party information.
PDF page 136
49
25.2
Reporting of Non-Force Majeure Events. Each Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this LLIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this LLIA.
25.3
Audit Rights. Subject to the requirements of confidentiality under Article 22 of this LLIA, the Parties’ audit rights shall include audits of a Party’s costs pertaining to such Party’s performance or satisfaction of obligations owed to the other Party under this LLIA, calculation of invoiced amounts and each such Party’s actions in an Emergency Condition. The Large Load Interconnection Customer and the Participating TO shall each have the right, during normal business hours, and upon prior reasonable notice to the other Party, to audit at its own expense the other Party’s accounts and records pertaining to either such Party’s performance or either such Party’s satisfaction of obligations owed to the other Party under this LLIA. Any audit authorized by this Article shall be performed at the offices where such accounts and records are maintained and shall be limited to those portions of such accounts and records that relate to each such Party’s performance and satisfaction of obligations under this LLIA. Each such Party shall keep such accounts and records for a period equivalent to the audit rights periods described in Article 25.4.
25.4
Audit Rights Periods.
25.4.1 Audit Rights Period for Construction-Related Accounts and Records. Accounts and records related to the design, engineering, procurement, and construction of Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades constructed by the Participating TO shall be subject to audit for a period of twenty-four (24) months following the Participating TO’s issuance of a final invoice in accordance with Article 12.2. Accounts and records related to the design, engineering, procurement, and construction of Participating TO’s Interconnection Facilities constructed by the Large Load Interconnection Customer shall be subject to audit and verification by the Participating TO for a period of twenty-four (24) months following the Large Load Interconnection Customer’s issuance of a final invoice.
25.4.2 Audit Rights Period for All Other Accounts and Records. Accounts and records related to a Party’s performance or satisfaction of all obligations under this LLIA other than those described in Article 25.4.1 shall be subject to audit as follows: (i) for an audit relating to cost obligations, the applicable audit rights period shall be twenty-four (24) months after the auditing Party’s receipt of an invoice giving rise to such cost obligations; and (ii) for an audit relating to all other obligations, the applicable audit rights period shall be twenty-four (24) months after the event for which the audit is sought.
PDF page 137
50
25.5
Audit Results. If an audit by the Large Load Interconnection Customer or the Participating TO determines that an overpayment or an underpayment has occurred with respect to the other Party, a notice of such overpayment or underpayment shall be given to the other Party together with those records from the audit which supports such determination. The Party that is owed payment shall render an invoice to the other Party and such invoice shall be paid pursuant to Article 12 hereof.
Article 26. Subcontractors
26.1
General. Nothing in this LLIA shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this LLIA; provided, however, that each Party shall require its subcontractors to comply with all applicable terms and conditions of this LLIA in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor. 26.2
Responsibility of Principal. The creation of any subcontract relationship shall not relieve the hiring Party of any of its obligations under this LLIA. The hiring Party shall be fully responsible to the other Parties for the acts or omissions of any subcontractor the hiring Party hires as if no subcontract had been made; provided, however, that in no event shall the Participating TO, or, as applicable, the CAISO be liable for the actions or inactions of the Large Load Interconnection Customer or its subcontractors with respect to obligations of the Large Load Interconnection Customer under Article 5 of this LLIA. Any applicable obligation imposed by this LLIA upon the hiring Party shall be equally binding upon, and shall be construed as having application to, any subcontractor of such Party.
26.3
No Limitation by Insurance. The obligations under this Article 26 will not be limited in any way by any limitation of subcontractor’s insurance.
Article 27. Disputes
All disputes arising out of or in connection with this LLIA shall be settled in accordance with this Article 27.
27.1
Submission. In the event either Party has a dispute, or asserts a claim, that arises out of or in connection with this LLIA or its performance, such Party (the “disputing Party”) shall provide the other Party with written notice of the dispute or claim (“Notice of Dispute”). Such dispute or claim shall be referred to a designated senior representative of each Party for resolution on an informal basis as promptly as practicable after receipt of the Notice of Dispute by the other Party. In the event the designated representatives are unable to resolve the claim or dispute through unassisted or assisted negotiations within thirty (30) Calendar Days of the other Party’s receipt of the Notice of Dispute, such claim or dispute may, upon mutual agreement of the Parties, be submitted to arbitration and resolved in accordance with the arbitration procedures set forth below. In the event the Parties do not agree to submit such claim or dispute to arbitration, each Party may exercise whatever rights and remedies it may have in equity or at law consistent with the terms of this LLIA.
PDF page 138
51
27.2
External Arbitration Procedures. Any arbitration initiated under this LLIA shall be conducted before a single neutral arbitrator appointed by the Parties. If the Parties fail to agree upon a single arbitrator within ten (10) Calendar Days of the submission of the dispute to arbitration, each Party shall choose one arbitrator who shall sit on a three (3)- member arbitration panel. The two arbitrators so chosen shall within twenty (20) Calendar Days select a third arbitrator to chair the arbitration panel. In either case, the arbitrators shall be knowledgeable in electric utility matters, including electric transmission and bulk power issues, and shall not have any current or past substantial business or financial relationships with any party to the arbitration (except prior arbitration). The arbitrator(s) shall provide each of the Parties an opportunity to be heard and, except as otherwise provided herein, shall conduct the arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association (“Arbitration Rules”) and any applicable FERC regulations; provided, however, in the event of a conflict between the Arbitration Rules and the terms of this Article 27, the terms of this Article 27 shall prevail.
27.3
Arbitration Decisions. Unless otherwise agreed by the Parties, the arbitrator(s) shall render a decision within ninety (90) Calendar Days of appointment and shall notify the Parties in writing of such decision and the reasons therefor. The arbitrator(s) shall be authorized only to interpret and apply the provisions of this LLIA and shall have no power to modify or change any provision of this LLIA in any manner. The decision of the arbitrator(s) shall be final and binding upon the Parties, and judgment on the award may be entered in any court having jurisdiction. The decision of the arbitrator(s) may be appealed solely on the grounds that the conduct of the arbitrator(s), or the decision itself, violated the standards set forth in the Federal Arbitration Act or the Administrative Dispute Resolution Act. The final decision of the arbitrator(s) must also be filed with FERC if it affects jurisdictional rates, terms and conditions of service, Interconnection Facilities, or Network Upgrades.
27.4
Costs. Each Party shall be responsible for its own costs incurred during the arbitration process and for the following costs, if applicable: (1) the cost of the arbitrator chosen by the Party to sit on the three (3) member panel and one half of the cost of the third arbitrator chosen; or (2) one half (1/2) the cost of the single arbitrator jointly chosen by the Parties.
Article 28. Representations, Warranties and Covenants
28.1
General. Each Party makes the following representations, warranties and covenants: 28.1.1 Good Standing. Such Party is duly organized, validly existing and in good standing under the laws of the state in which it is organized, formed, or incorporated, as applicable; that it is qualified to do business in the state or states in which the Large Load Facility, Interconnection Facilities and Network Upgrades owned by such Party, as applicable, are located; and that it has the corporate power and authority to own its properties, to carry on its business as now being conducted and to enter into this LLIA and carry out the transactions contemplated hereby and perform and
PDF page 139
52
carry out all covenants and obligations on its part to be performed under and pursuant to this LLIA.
28.1.2 Authority. Such Party has the right, power and authority to enter into this LLIA, to become a Party hereto and to perform its obligations hereunder. This LLIA is a legal, valid and binding obligation of such Party, enforceable against such Party in accordance with its terms, except as the enforceability thereof may be limited by applicable bankruptcy, insolvency, reorganization or other similar laws affecting creditors’ rights generally and by general equitable principles (regardless of whether enforceability is sought in a proceeding in equity or at law). 28.1.3 No Conflict. The execution, delivery and performance of this LLIA does not violate or conflict with the organizational or formation documents, or bylaws or operating agreement, of such Party, or any judgment, license, permit, order, material agreement or instrument applicable to or binding upon such Party or any of its assets.
28.1.4 Consent and Approval. Such Party has sought or obtained, or, in accordance with this LLIA will seek or obtain, each consent, approval, authorization, order, or acceptance by any Governmental Authority in connection with the execution, delivery and performance of this LLIA, and it will provide to any Governmental Authority notice of any actions under this LLIA that are required by Applicable Laws and Regulations.
Article 29. [Reserved]
Article 30. Miscellaneous
30.1
Binding Effect. This LLIA and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto. 30.2
Conflicts. In the event of a conflict between the body of this LLIA and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this LLIA shall prevail and be deemed the final intent of the Parties.
30.3
Rules of Interpretation. This LLIA, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person’s successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this LLIA, and reference to a person in a particular capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this LLIA), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof; (4) reference to any Applicable Laws and Regulations means such Applicable Laws and Regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article of this LLIA or such
PDF page 140
53
Appendix to this LLIA, or such Section to the LLIP or such Appendix to the LLIP, as the case may be; (6) “hereunder”, “hereof”, “herein”, “hereto” and words of similar import shall be deemed references to this LLIA as a whole and not to any particular Article or other provision hereof or thereof; (7) “including” (and with correlative meaning “include”) means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, “from” means “from and including”, “to” means “to but excluding” and “through” means “through and including”.
30.4
Entire Agreement. This LLIA, including all Appendices and Schedules attached hereto, constitutes the entire agreement among the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between or among the Parties with respect to the subject matter of this LLIA. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, any Party’s compliance with its obligations under this LLIA.
30.5
No Third-Party Beneficiaries. This LLIA is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.
30.6
Waiver. The failure of a Party to this LLIA to insist, on any occasion, upon strict performance of any provision of this LLIA will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.
Any waiver at any time by either Party of its rights with respect to this LLIA shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this LLIA. Termination or Default of this LLIA for any reason by the Large Load Interconnection Customer shall not constitute a waiver of the Large Load Interconnection Customer’s legal rights to obtain an interconnection from the Participating TO. Any waiver of this LLIA shall, if requested, be provided in writing. 30.7
Headings. The descriptive headings of the various Articles of this LLIA have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this LLIA.
30.8
Multiple Counterparts. This LLIA may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument. 30.9
Amendment. The Parties may by mutual agreement amend this LLIA by a written instrument duly executed by all of the Parties. Such amendment shall become effective and a part of this LLIA upon satisfaction of all Applicable Laws and Regulations. 30.10 Modification by the Parties. The Parties may by mutual agreement amend the Appendices to this LLIA by a written instrument duly executed by all of the Parties. Such
PDF page 141
54
amendment shall become effective and a part of this LLIA upon satisfaction of all Applicable Laws and Regulations.
30.11 Reservation of Rights. The Large Load Interconnection Customer and the Participating TO shall have the right to make a unilateral filing with FERC to modify this LLIA pursuant to sections 205 and 206 of the Federal Power Act or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by another Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this LLIA shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.
30.12 No Partnership. This LLIA shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership among the Parties or to impose any partnership obligation or partnership liability upon any Party. No Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, another Party. 30.13 Joint and Several Obligations. Except as otherwise provided in this LLIA, the obligations of the CAISO, the Participating TO, and the Large Load Interconnection Customer are several, and are neither joint nor joint and several.
PDF page 142
IN WITNESS WHEREOF, the Parties have executed this LLIA in multiple originals, each of which shall constitute and be an original effective agreement among the Parties. [Insert name of Large Load Interconnection Customer]
By: _________________________
Name: ______________________
Title: _______________________
Date: _______________________
[Insert name of Participating TO]
By: _________________________
Name: ______________________
Title: _______________________
Date: _______________________
PDF page 143
Appendices to LLIA
Appendix A Interconnection Facilities, Network Upgrades and Distribution Upgrades Appendix B Milestones
Appendix C Interconnection Details
Appendix D Security Arrangements Details
Appendix E Commercial Operation Date
Appendix F Addresses for Delivery of Notices and Billings
Appendix G Large Load Interconnection Customer’s Share of Costs of Network Upgrades for Applicable Project Group
Appendix H Co-Location and Behind-the-Meter Generation Provisions
PDF page 144
Appendix A
Appendix A
Interconnection Facilities, Network Upgrades and Distribution Upgrades
A-1: Facilities and Upgrades
Participating TO will coordinate with the Large Load Interconnection Customer to ensure that all local state utility franchise rules and regulations are adhered to through, among other things, arrangements that provide for station service directly from the local franchised public utility. Participating TO will coordinate with the Large Load Interconnection Customer to facilitate any necessary pseudo-tie or similar arrangement for the delivery of power into the CAISO BAA.
1. Interconnection Facilities:
(a) [insert Large Load Interconnection Customer’s Interconnection Facilities]:
(b) [insert Participating TO’s Interconnection Facilities]:
2. Network Upgrades:
(c) [insert Other Network Upgrades]:
(i)
(ii) [insert Participating TO’s Network Upgrades]
3. Distribution Upgrades:
A-2: FILI
1. Large Load Interconnection Customer has elected to take FILI until the Network Upgrades identified in this Appendix A have reached Commercial Operation.
2. The following documents and process shall be executed, undertaken and provided for FILI Interconnection Service applicants:
a. A pro forma Flexible Interconnection Service Addendum to the pro forma Large Load Interconnection Agreement (or, alternatively, a standalone pro forma Flexible Interconnection Agreement) that identifies the roles and responsibilities for impacted parties that will identify customer- and site-specific equipment and systems necessary to operationalize FILI service;
b. Study methodologies will be revised to recognize the unique operational characteristics of flexible large loads;
PDF page 145
Appendix A
c. Operational requirements for FILI service will be revised, including curtailment implementation mechanisms and data reporting;
d. Cost responsibility provisions will be revised, including any financial security during the conditional service period;
e. Procedures for the transition-to-firm Interconnection Service provisions for FILI will be implemented that specify the automatic conversion to firm service upon Network Upgrade completion;
f. Coordination mechanisms shall be promulgated that address coordination between FILI Service and the Participating TO study process; and
g. Operational requirements shall be revised to address the management of longer- duration curtailments in coordination with, as applicable, the CAISO.
3. Further, the following considerations will be addressed in the FILI application process: a. Curtailment triggers and operating conditions and the process for establishing curtailment parameters;
b. Deployment priorities between FILI and non-FILI applicants;
c. Scheduling treatment between FILI and non-FILI Large Load Facilities; d. The relationship between operational restrictions and study assumptions; e. Potential interactions with scheduling, dispatch, and price formation; and f. How the FILI Interconnection Service may apply to co-located load arrangements [and existing generation resources], particularly where load flexibility can reduce transmission impacts or support continued wholesale market participation.
PDF page 146
Appendix B
Appendix B
Milestones
PDF page 147
Appendix C
Appendix C
Interconnection Details
PDF page 148
Appendix D
Appendix D
Security Arrangements Details
Infrastructure security of CAISO Controlled Grid equipment and operations and control hardware and software is essential to ensure day-to-day CAISO Controlled Grid reliability and operational security. FERC will expect the Participating TOs, CAISO, market participants, and Large Load Interconnection Customers interconnected to the CAISO Controlled Grid to comply with Applicable Reliability Criteria. All public utilities will be expected to meet basic standards for system infrastructure and operational security, including physical, operational, and cyber- security practices.
PDF page 149
Appendix E
Appendix E
[This Appendix E sets forth a form of letter to be provided by the Large Load Interconnection Customer to the CAISO and Participating TO to provide formal notice of the Commercial Operation of a Large Load Facility.]
[Date]
[CAISO Address]
[Participating TO Address]
Re:
__________ Large Load Facility
Dear ____________:
On [Date] [Large Load Interconnection Customer] has completed Trial Operation of Unit No. ___. This letter confirms that [Large Load Interconnection Customer] commenced Commercial Operation of Unit No. ___ at the Large Load Facility, effective as of [Date plus one day] and that [Large Load Interconnection Customer] provided the CAISO’s operations personnel advance notice of its intended Commercial Operation Date no less than five (5) Business Days prior to that date.
Thank you.
[Signature]
[Large Load Interconnection Customer Representative]
PDF page 150
Appendix F
Appendix F
Addresses for Delivery of Notices and Billings
Notices:
Participating TO:
[To be supplied.]
Large Load Interconnection Customer:
[To be supplied.]
CAISO:
[To be supplied.]
Billings and Payments:
Participating TO:
[To be supplied.]
Large Load Interconnection Customer:
[To be supplied.]
CAISO:
[To be supplied.]
Alternative Forms of Delivery of Notices (telephone, facsimile or e-mail): Participating TO:
[To be supplied.]
Large Load Interconnection Customer:
PDF page 151
Appendix F
[To be supplied.]
CAISO:
[To be supplied.]
PDF page 152
Appendix G
Appendix G
Large Load Interconnection Customer’s Share of Costs of Network Upgrades for Applicable Project Group
PDF page 153
Appendix H
Appendix H Co-Location and Behind-the-Meter Generation Provisions
H.1
Purpose and Scope. This Appendix H sets forth the terms that apply where the Large Load Facility is, or will be: (a) physically connected to the facilities of an existing or planned generating facility on the generator interconnection customer’s side of the Point of Interconnection (“Co- Located Generation”); or (b) served by a generating facility or energy storage device that delivers energy to the Large Load Facility without using the transmission system or any distribution facilities (“Behind-the-Meter Generation”). The Participating TO’s Tariff governs the interconnection of the Large Load Facility, and the CAISO Tariff governs the interconnection of any generating facility that injects, or may inject, energy into the CAISO Controlled Grid. This Appendix H memorializes the procedures by which the Participating TO, the CAISO, and the Large Load Interconnection Customer will coordinate those processes. Station power load, and generation that exclusively serves station power load, are excluded from this Appendix H. H.2
Description of Co-Located Generation and Behind-the-Meter Generation. The Co- Located Generation and/or Behind-the-Meter Generation serving the Large Load Facility, if any, is described as follows: [Identify facility name, owner/operator, technology type, nameplate capacity (MW), storage capacity (MW/MWh), metering configuration, and whether the facility is:
(i) back-up generation used only during outages or islanding; (ii) non-exporting Behind-the-Meter Generation; or (iii) generation that may export energy to the CAISO Controlled Grid.] H.3
Non-Exporting Configurations. Back-up generation used only during outages or islanding, and non-exporting Behind-the-Meter Generation, do not require a CAISO generator interconnection request and may be accommodated under the Participating TO’s Tariff, provided that the Large Load Interconnection Customer installs and maintains control technologies and/or protection systems sufficient to ensure that no energy is injected into the CAISO Controlled Grid and that such facilities do not adversely affect the CAISO Controlled Grid. The Large Load Interconnection Customer shall provide the Participating TO with all generation characteristics of such facilities, and the Participating TO shall provide that information to the CAISO in accordance with Article H.6.
H.4
Power Injection Triggers CAISO Generator Interconnection Process. Any injection, or proposed capability to inject, energy from Co-Located Generation or Behind-the-Meter Generation into the CAISO Controlled Grid shall require the generating facility to submit an interconnection request and be studied under the CAISO Tariff, including screening and participation in the applicable cluster study, and to execute a generator interconnection agreement with the CAISO and the Participating TO (or a non-conforming agreement or bridging agreement where appropriate) before any such injection occurs. Scoring, financial requirements, and study results shall be based on the interconnection capacity requested, which may be less than the generating facility’s maximum output. The generating facility may exercise all rights available under the CAISO Tariff, including surplus interconnection service, grid enhancing technologies, and phasing. Any participating generator shall also complete the CAISO new resource implementation process and execute a CAISO Participating Generator Agreement. No injection into the CAISO Controlled Grid is authorized under this LLIA, and any unauthorized injection shall be a Breach of this LLIA.
PDF page 154
Appendix H
H.5
Coordination Procedures. Where Article H.4 applies, the Parties shall coordinate as follows: (a) the Large Load Interconnection Customer shall submit comprehensive information on both the Large Load Facility and the generating facility in the CAISO resource interconnection process and the Participating TO load interconnection process; (b) the Participating TO and the CAISO shall exchange and compare information to ensure that the load and generation studies are consistent with the requested mode of operation and type of service, and shall seek to align load and generation study timing so that studies may proceed concurrently; (c) the generation study shall commence with the Large Load Facility assumptions and reflect the combined impact of the Large Load Facility and the generating facility as requested; (d) a request to remove or add a co- located load after commencement of studies shall be made under the Participating TO’s tariff and evaluated by the Participating TO and the CAISO Tariff.
H.6
Information Requirements. In addition to the information required under the CAISO resource interconnection process and the operational requirements of this LLIA, the Large Load Interconnection Customer shall provide to the Participating TO (which shall provide it to the CAISO) and, where Article H.4 applies, to the CAISO: (a) the expected presence and range of energy consumption characteristics of the Large Load Facility; (b) minimum and maximum generator operating capabilities; (c) generator operating characteristics when the Large Load Facility is at its minimum level; (d) market participation status, if any; (e) any load services requested when the generator is offline; and (f) for non-exporting or non-participating generation, all generation characteristics. The Large Load Interconnection Customer shall notify the Participating TO and the CAISO of any material change to such information, and forecasts submitted by the applicable Scheduling Coordinator shall reflect Co-Located Generation and Behind-the-Meter Generation impacts on the load forecast.
H.7
Metering, Storage, and Settlement. The Participating TO shall require the Large Load Facility to be sub-metered independent of any Co-Located Generation or Behind-the-Meter Generation, and the applicable Scheduling Coordinator shall report such meter values separately so that regulation and black start services are assessed on a gross load basis. Any wholesale energy storage resource shall remain operationally separate from, and separately metered and settled from, the Large Load Facility, and its energy shall not be commingled with the Large Load Facility. Station power load shall be metered separately consistent with Local Regulatory Authority requirements.
H.8
Full Load Exposure. The Interconnection Service provided under this LLIA shall be studied and provided on the basis of the full Demand of the Large Load Facility, without reduction for Co-Located Generation or Behind-the-Meter Generation, unless the Large Load Interconnection Customer has elected a flexible interconnection service with enforceable control technologies and/or protection systems that limit withdrawals from the CAISO Controlled Grid. H.9
CAISO Role; Order of Precedence. The CAISO’s obligations under this LLIA with respect to the Large Load Facility are limited to those expressly set forth in this Appendix H and in the generator interconnection agreement, Participating Generator Agreement, or other CAISO agreement applicable to any Co-Located Generation, and the CAISO shall have no responsibility for the financing or construction of facilities required solely for the Large Load Facility.
PDF page 155
Appendix IV
Attachment 4
Interconnection Financial Security
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 156
2
Attachment 4
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
INTERCONNECTION FINANCIAL SECURITY
Defined Terms:
Construction Activities shall mean any activities related to the construction of the Network Upgrades, including but not limited to equipment procurement, engineering, construction and associated activities.
Current Cost Responsibility shall mean the Large Load Interconnection Customer’s current allocated costs for Network Upgrades, not to exceed the Maximum Cost Responsibility, in each case pursuant to Section 4 of the Facilities Study Agreement. This cost is used to calculate the Large Load Interconnection Customer’s Interconnection Financial Security requirement.
Maximum Cost Responsibility (MCR) shall mean, pursuant to this Attachment 4 and the Facilities Study Agreement, the full cost of: (1) assigned Network Upgrades and (2) Participating Transmission Operator’s (TO) Interconnection Facilities.
1. Types of Interconnection Financial Security.
The Interconnection Financial Security posted by a Large Load Interconnection Customer may be any combination of the following types of Interconnection Financial Security provided in favor of the Participating TO:
(a) an irrevocable and unconditional letter of credit issued by a bank or financial institution that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s;
(b) an irrevocable and unconditional surety bond issued by an insurance company that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s;
(c) an unconditional and irrevocable guaranty issued by a company that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s;
(d) a cash deposit standing to the credit of the Participating TO in an interest- bearing escrow account maintained at a bank or financial institution that is reasonably acceptable to the Participating TO;
(e) a certificate of deposit in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s; or
PDF page 157
3
(f) a payment bond certificate in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s.
Interconnection Financial Security instruments as listed above shall be in such form as the Participating TO may reasonably require from time to time by notice to Large Load Interconnection Customers or in such other form as has been evaluated and approved as reasonably acceptable by the Participating TO.
The Participating TO shall publish and maintain standardized forms related to the types of Interconnection Financial Security listed above which shall be accessible on the Participating TO’S Website. The Participating TO shall require the use of standardized forms of Interconnection Financial Security to the greatest extent possible. If at any time the guarantor of the Interconnection Financial Security fails to maintain the credit rating required by this Section 1, the Large Load Interconnection Customer shall provide to the Participating TO replacement Interconnection Financial Security meeting the requirements of this Section 1 within five (5) Business Days of the change in credit rating.
Interest on a cash deposit standing to the credit of the Participating TO in an interest- bearing escrow account under Section 1(d) will accrue to the account of the Large Load Interconnection Customer.
2. Interconnection Financial Security-Initial Posting for Large Load Interconnection Customers.
2.1 Each Large Load Interconnection Customer shall post, with notice to the Participating TO, two (2) separate Interconnection Financial Security instruments:
(i) a posting relating to the applicable Network Upgrades; and (ii) a posting relating to the Participating TO’s Interconnection Facilities.
2.2 Timing of Postings. The postings set forth in this Section 2 shall be made any time after the issuance of the Facilities Study report but no later than ninety (90) calendar days after issuance of the Facilities Study report for Large Load Interconnection.
2.3 Revised Study Reports. If the Participating TO revises a Facilities Study, the initial postings will be due from the Large Load Interconnection Customer by the later of ninety (90) calendar days after issuance of the original Facilities Study Report or forty (40) calendar days after issuance of the revised Facilities Study report.
PDF page 158
4
2.4 Posting Amount for Network Upgrades.
2.4.1 Large Load Interconnection Customers. Each Large Load
Interconnection Customer for a Large Load Facility shall post an Interconnection Financial Security instrument relating to the Network Upgrades assigned to such Large Load Interconnection Customer pursuant to the Facilities Study.
The posting amount for such Network Upgrades shall equal the lesser of:
(i) fifteen percent (15%) of the Current Cost Responsibility assigned to the Large Load Interconnection Customer in the Facilities Study for Network Upgrades; (ii) $20,000 per megawatt of electrical load of the Large Load Facility or the amount of megawatt increase in the load of each existing Large Load Facility as listed by the Large Load Interconnection Customer in its Large Load Interconnection Application, including any requested modifications thereto; or (iii) $7,500,000, but in no event less than $500,000.
2.5 Posting Amount for Participating TO Interconnection Facilities. 2.5.1 Large Load Interconnection Customers. Each Large Load
Interconnection Customer for a Large Load Facility shall post an Interconnection Financial Security instrument in an amount equal to the lesser of: (i) fifteen percent (15%) of the Current Cost Responsibility assigned to the Large Load Interconnection Customer in the Facilities Study for Participating TO’s Interconnection Facilities; (ii) $20,000 per megawatt of electrical load of the Large Load Facility or the amount of megawatt increase in the load of each existing Large Load Facility as listed by the Large Load Interconnection Customer in its Large Load Interconnection Application including any requested modifications thereto; or (iii) $7,500,000, but in no event less than $500,000. 2.6 Cost Estimates Less than Minimum Posting Amounts. If (1) the Current Cost Responsibility of the assigned Network Upgrades, (2) the allocated costs of the Participating TO Interconnection Facilities, or (3) both are less than the respective minimum posting amounts that would apply under Sections 2.3.1 or 2.4.1, then the posting amount required will equal the Current Cost Responsibility of the Assigned Network Upgrades or the allocated costs for Participating TO Interconnection Facilities, as applicable.
2.7 Consequences for Failure to Post. The failure by a Large Load Interconnection Customer to timely post the Interconnection Financial Security required by this Attachment 4 shall result in the Large Load Interconnection Application being deemed withdrawn. The Large Load Interconnection Customer shall provide the Participating TO and the Participating TO with written notice that it has posted the required Interconnection Financial Security no later than the applicable final day for posting. The failure by a Large Load Interconnection Customer to timely
PDF page 159
5
post the Interconnection Financial Security required by this Section 2 shall result in the Large Load Interconnection Application being deemed withdrawn. The Large Load Interconnection Customer shall provide the Participating TO with written notice that it has posted the required Interconnection Financial Security no later than the applicable final day for posting.
2.8 Re-calculation of Initial Posting Requirement. If withdrawals, modifications, or system changes occur after the completion of the Facilities Study, and the Participating TO, is able to reasonably determine, prior to the date for initial posting of Interconnection Financial Security, that as a result of such decrease (solely or in combination with other modifications made by Large Load Interconnection Customers) some of the Network Upgrades and/or Participating TO Interconnection Facilities identified in the Facilities Study will no longer be required, then the calculation of the initial posting of Interconnection Financial Security will not include those Network Upgrades and/or Participating TO Interconnection Facilities. Such determination will be made based on the Participating TO’s best engineering judgment and will not include any re-studies.
3. Interconnection Financial Security –Second and Third Postings for Large Load Interconnection Customers.
3.1 Second Posting for Large Load Interconnection Customers.
3.1.1 Each Large Load Interconnection Customer shall make second postings, with notice to the Participating TO, of two separate Interconnection Financial Security instruments: (i) a second posting relating to the Network Upgrades; and (ii) a second posting relating to the Participating TO’s Interconnection Facilities. The Current Cost Responsibility for calculating the second and third Interconnection Financial Security postings for Large Load Interconnection Customers shall be set forth in the Facilities Study report.
3.1.2 The postings set forth in this Section 3 for second postings for Large Load Interconnection Customers shall be made any time after issuance of the Facilities Study report but no later than thirty (30) calendar days prior to the date on which the Facilities Study report provides that such amounts will be needed to fund long lead time equipment procurement as part of the Construction Activities for the Network Upgrades or the Participating TO’s Interconnection Facilities, whichever is earlier.
3.2 Third Posting for Large Load Interconnection Customers.
3.2.1 After the second posting for a Large Load Interconnection Customer has been made but no later than thirty (30) calendar days after the date on which the Participating TO provides notice that Participating TO is obligated to provide security needed to fund any additional obligations for
PDF page 160
6
Network Upgrades or Participating TO’s Interconnection Facilities on behalf of the Large Load Interconnection Customer, whichever is earlier, the Large Load Interconnection Customer shall modify the two (2) separate Interconnection Financial Security instruments posted pursuant to Section 3.1.
3.3 Determining Refundable Portion of the Interconnection Financial Security for Network Upgrades.
3.3.1 Withdrawal Between the First Posting and the Deadline for the Second Posting. If the Large Load Interconnection Customer either withdraws its Large Load Interconnection Application or terminates its Large Load Interconnection Agreement (LLIA) at any time between the initial posting and the deadline for the second posting of the Interconnection Financial Security for applicable Network Upgrades, then the Participating TO shall liquidate the Interconnection Financial Security for the applicable Network Upgrades and reimburse the Large Load Interconnection Customer the lesser of:
a. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) less (all costs and expenses incurred or irrevocably committed to finance Pre- Construction Activities for Network Upgrades on behalf of the Large Load Interconnection Customer); or
b. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) minus the lesser of fifty percent (50%) of the value of the posted
Interconnection Financial Security for Network Upgrades or $10,000 per requested and approved, pre-downsized megawatt of the Large Load Facility load.
3.3.2 Withdrawal Between the Second Posting and the Commencement of Construction Activities. If the Large Load Interconnection Customer either withdraws or terminates its LLIA at any time after the second posting of the Interconnection Financial Security for applicable Network Upgrades and the Commencement of Construction Activities for such Network Upgrades, then the Participating TO shall liquidate the Interconnection Financial Security for the applicable Network Upgrades and reimburse the Large Load Interconnection Customer the lesser of:
a. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) less (all costs and expenses incurred or irrevocably committed to finance Pre- Construction Activities for Network Upgrades on behalf of the Large Load Interconnection Customer) and less (any posting
PDF page 161
7
reduction due to the Large Load Interconnection Customer’s election to self-build Stand Alone Network Upgrades); or b. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) minus the lesser of fifty percent (50%) of the value of the posted
Interconnection Financial Security for Network Upgrades or $20,000 per requested and approved, pre-downsized megawatt of the Large Load Facility load.
3.3.3 Special Treatment Based on Failure to Obtain Necessary Permit or Authorization from Governmental Authority. If, at any time after the second posting requirement, the Large Load Interconnection Customer withdraws the Large Load Interconnection Application or terminates the LLIA, as applicable, because the Large Load Interconnection Customer received a final denial from the primary issuing Governmental Authority for authorization necessary for the construction or operation of the Large Load Facility, and the Network Upgrades to be financed by the Large Load Interconnection Customer are also to be financed by one or more other Large Load Interconnection Customers, then the provisions of Section 3.3.2 apply, except that the Large Load Interconnection Customer shall not be reimbursed for its share of any actual costs incurred or irrevocably committed by the Participating TO for Construction Activities.
3.3.4 After Commencement of Construction Activities. Once Construction Activities on Network Upgrades on behalf of the Large Load Interconnection Customer commence, any withdrawal of the Large Load Interconnection Application or termination of the LLIA by the Large Load Interconnection Customer will be treated as follows:
The Participating TO shall liquidate the Interconnection Financial Security, or balance thereof, posted by the Large Load Interconnection Customer for Network Upgrades at the time of withdrawal.
To the extent the amount of the liquidated Interconnection Financial Security plus capital, if any, separately provided by the Large Load Interconnection Customer to satisfy its obligation to finance Network Upgrades exceeds the total cost responsibility for Network Upgrades assigned to the Large Load Interconnection Customer, the Participating TO shall remit to the Large Load Interconnection Customer the excess amount.
Withdrawal of a Large Load Interconnection Application or termination of a LLIA shall result in the release to the Large Load Interconnection Customer of any Interconnection Financial Security posted by the Large Load Interconnection Customer for Participating TO Interconnection Facilities, except with respect to any amounts necessary to pay for costs
PDF page 162
8
incurred or irrevocably committed by the Participating TO on behalf of the Large Load Interconnection Customer for the Participating TO’s Interconnection Facilities and for which the Participating TO has not been reimbursed in accordance with this Attachment 4. Withdrawal of a Large Load Interconnection Application or termination of a LLIA shall result in the release to the Large Load Interconnection Customer of any Interconnection Financial Security posted by the Large Load Interconnection Customer for Participating TO Interconnection Facilities, except with respect to any amounts necessary to pay for costs incurred or irrevocably committed by the Participating TO on behalf of the Large Load Interconnection Customer for the Participating TO’s Interconnection Facilities and for which the Participating TO has not been reimbursed in accordance with this Section 3.3.4.
3.3.5 Accounting by The Participating TO. Within twenty (20) calendar days of any liquidating event, the Participating TO shall provide the Participating TO and Large Load Interconnection Customer with an accounting of the disposition of the proceeds of the liquidated Interconnection Financial Security and remit to the Participating TO all proceeds not otherwise reimbursed to the Large Load Interconnection Customer or applied to costs incurred or irrevocably committed by the Participating TO on behalf of the Large Load Interconnection Customer in accordance with this Attachment 4.
PDF page 163
REVISED DCRT TO TARIFF (REDLINE)
PDF page 164
DCR Transmission, L.L.C.
Transmission Owner Tariff
Version 2.0.0
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
8. Obligation to Interconnect or Construct Transmission Expansions and Facility
Upgrades … 8 8.1.
Participating TO Obligation to Interconnect … 8 8.1.1. Interconnection to Transmission System … 8 8.1.2. Costs Associated with Interconnection … 10 8.1.3. Interconnection Agreement … 10 8.1.4. Due Diligence to Construct … 11 8.1.5. Energization … 11 8.1.6. Coordination with the CAISO on Interconnection Requests … 12
8.2.
Participating TO Obligation to Construct Transmission Expansions or
Facility Upgrades … 12 8.2.1. Obligation to Construct … 12 8.3.
Request for FERC Deference Regarding Need Determination … 12
9. Expansion Process … 12 9.1.
Determination of Facilities … 12 9.1.1. Payment of Facilities Study Costs … 12 9.1.1.1.
Market Participant to Pay for Facilities Study … 12
9.1.1.2.
Project Sponsor or Project Proponent to Pay for
Facilities Study … 12
9.1.1.3.
Principal Beneficiaries to Pay for Facilities Study … 13
9.1.2. Payment Procedure … 13 9.1.3. Facilities Study Procedures … 13 9.2.
Obligation to Build … 14 9.2.1. Due Diligence to Construct … 14 9.2.2. Delay in Construction or Expansion … 15 9.2.2.1.
Alternatives to the Original Facility Additions … 15
9.2.2.2.
Refund Obligation for Unfinished Facility Additions … 15
9.3.
Provisions Relating To Transmission Construction on the Systems of Other
TOs … 16 9.3.1. Responsibility for Third Party Additions … 16 9.3.2. Coordination of Third-Party System Additions … 16
10. Interconnection Process … 16 10.1. Applicability … 16 10.2. Applications … 17 10.3. Interconnection Application … 17 10.3.1. Amendment to Completed Interconnection Application … 18
10.4. Review of Completed Interconnection Application … 18 10.5. Notice of Need for System Impact Study … 19 10.6. System Impact Study Cost Reimbursement and Agreement … 19
10.6.1. Cost Reimbursement … 20 10.6.2. Multiple Parties … 20 10.7. System Impact Study Procedures … 20 10.7.1. Procedures Upon Completion of System Impact Study … 20
PDF page 168
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
10.8. Notice of Need for Facilities Study … 21 10.9. Facilities Study Procedures … 22 10.9.1. Execution of Interconnection Agreement … 22
10.10. Partial Interim Service … 22 10.11. Expedited Procedures for New Facilities … 22
11. Uncontrollable Forces and Indemnification … 23 11.1. Procedures to Follow if Uncontrollable Force Occurs … 23
11.2. Indemnification … 23
12. Regulatory Filings … 23
13. Miscellaneous … 23 13.1. Notices … 24 13.2. Waiver … 24 13.3. Confidentiality … 24 13.3.1. Maintaining Confidentiality if Not for Public Disclosure … 24
13.3.2. Disclosure of Confidential Information … 24
13.4. Titles … 25 13.5. Severability … 25 13.6. Preservation of Obligations … 25 13.7. Governing Law … 25 13.8. Appendices Incorporated … 25 13.9. Consistency with CAISO Tariff … 25 13.10. Disputes … 25
1. Preamble … 4
2. Effective Date … 4
3. TO Definitions … 4 3.1.
Access Charge … 4 3.2.
Alternative Transmission Technologies … 4
3.3.
Base Transmission Revenue Requirement (“Base TRR”) … 4
3.4.
CAISO ADR Procedures … 4 3.5.
CAISO Controlled Grid … 4 3.6.
CAISO Tariff … 4 3.7.
Completed Application Date … 5 3.8.
Completed Interconnection Application … 5
3.9.
Direct Assignment Facilities … 5 3.10. DCR Transmission, L.L.C. (“DCRT”) … 5 3.11. Existing Contracts … 5 3.12. Expedited Interconnection Agreement … 5 3.13. Flexible Interim Load Interconnection Service (“FILI Service”)_ … 5
3.14. Interconnection Application … 5 3.15. Large Load … 5
PDF page 169
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
3.16. Large Load Facilities Study … 6 3.17. Large Load Facilities Study Agreement … 6 3.18. Large Load Interconnection Agreement … 6 3.19. Large Load Interconnection Application … 6 3.20. Large Load Interconnection Customer … 6 3.21. Large Load Interconnection Facilities … 6 3.22. Large Load Interconnection Process (“LLIP”) … 6 3.23. Large Load Interconnection Service … 6 3.24
Large Load System Impact Study … 6 3.25. Large Load System Impact Study Agreement … 7 3.26. Net FTR Revenue … 7 3.27. Participation Agreement … 7 3.28. Project Proponent … 7 3.29. Regional Transmission Group (“RTG”) … 7 3.30. Regulatory Authority … 7 3.31. Reliability Upgrade … 7 3.32. Requests for Expedited Interconnection Procedures … 8 3.33. System Impact Study … 8 3.34. System Impact Study Agreement … 8 3.35. TO Tariff … 8 3.36. Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 8
3.37. Participating TO’s Transmission System … 8
4. Eligibility … 8
5. Access Charges … 8 5.1.
Transmission Revenue Requirement (“TRR”) … 8
5.2.
Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 8
6. Ancillary Services--Applicability and Charges … 9
7. Billing and Payment … 9 7.1.
Payment … 9 7.2.
Billing … 9
8. Obligation to Interconnect or Construct Transmission Expansions and Facility
Upgrades … 9 8.1.
Participating TO Obligation to Interconnect … 9 8.1.1. Interconnection to Transmission System … 10
8.1.1.1.
Letter Agreement … 10
8.1.2. Costs Associated with Interconnection … 11
8.1.3. Interconnection Agreement … 12 8.1.4. Due Diligence to Construct … 13 8.1.5. Energization … 13 8.1.6. Coordination with the CAISO on Interconnection Requests … 13
PDF page 170
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
8.2.
Participating TO Obligation to Construct Transmission Expansions or
Facility Upgrades … 13 8.2.1. Obligation to Construct … 13 8.3.
Request for FERC Deference Regarding Need Determination … 14
9. Expansion Process … 14 9.1.
Determination of Facilities … 14 9.1.1. Payment of Facilities Study Costs … 14 9.1.1.1.
Market Participant to Pay for Facilities Study … 14
9.1.1.2.
Project Sponsor or Project Proponent to Pay for
Facilities Study … 14
9.1.1.3.
Principal Beneficiaries to Pay for Facilities Study … 14
9.1.2. Payment Procedure … 15 9.1.3. Facilities Study Procedures … 15 9.2.
Obligation to Build … 15 9.2.1. Due Diligence to Construct … 15 9.2.2. Delay in Construction or Expansion … 16 9.2.2.1.
Alternatives to the Original Facility Additions … 16
9.2.2.2.
Refund Obligation for Unfinished Facility Additions … 16
9.3.
Provisions Relating To Transmission Construction on the Systems of Other
TOs … 16 9.3.1. Responsibility for Third Party Additions … 16 9.3.2. Coordination of Third-Party System Additions … 17
10. Interconnection Process … 17 10.1. Applicability … 17 10.2. Applications … 17 10.3. Interconnection Application … 17 10.3.1. Amendment to Completed Interconnection Application … 18
10.4. Review of Completed Interconnection Application … 19 10.5. Notice of Need for System Impact Study … 19 10.6. System Impact Study Cost Reimbursement and Agreement … 20
10.6.1. Cost Reimbursement … 20 10.6.2. Multiple Parties … 20 10.7. System Impact Study Procedures … 20 10.7.1. Procedures Upon Completion of System Impact Study … 21
10.8. Notice of Need for Facilities Study … 21 10.9. Facilities Study Procedures … 22 10.9.1. Execution of Interconnection Agreement … 22 10.10. Partial Interim Service … 23 10.11. Expedited Procedures for New Facilities … 23
11. Uncontrollable Forces and Indemnification … 23 11.1. Procedures to Follow if Uncontrollable Force Occurs … 23 11.2. Indemnification … 24
PDF page 171
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
12. Regulatory Filings … 24
13. Miscellaneous … 24 13.1. Notices … 24 13.2. Waiver … 24 13.3. Confidentiality … 25 13.3.1. Maintaining Confidentiality if Not for Public Disclosure … 25
13.3.2. Disclosure of Confidential Information … 25
13.4. Titles … 25 13.5. Severability … 25 13.6. Preservation of Obligations … 26 13.7. Governing Law … 26 13.8. Appendices Incorporated … 26 13.9. Consistency with CAISO Tariff … 26 13.10. Disputes … 26
4. Eligibility … 7
5. Access Charges … 7 5.1.
Transmission Revenue Requirement (“TRR”) … 7
5.2.
Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 7
6. Ancillary Services--Applicability and Charges … 7
7. Billing and Payment … 7 7.1.
Payment … 7 7.2.
Billing … 8
8. Obligation to Interconnect or Construct Transmission Expansions and Facility
Upgrades … 8 8.1.
Participating TO Obligation to Interconnect … 8
8.1.1. Interconnection to Transmission System … 8
8.1.2. Costs Associated with Interconnection … 10
8.1.3. Interconnection Agreement … 10 8.1.4. Due Diligence to Construct … 11 8.1.5. Energization … 11 8.1.6. Coordination with the CAISO on Interconnection Requests … 12
8.2.
Participating TO Obligation to Construct Transmission Expansions or
Facility Upgrades … 12 8.2.1. Obligation to Construct … 12 8.3.
Request for FERC Deference Regarding Need Determination … 12
9. Expansion Process … 12 9.1.
Determination of Facilities … 12 9.1.1. Payment of Facilities Study Costs … 12
9.1.1.1.
Market Participant to Pay for Facilities Study … 12
PDF page 172
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
9.1.1.2.
Project Sponsor or Project Proponent to Pay for
Facilities Study … 12
9.1.1.3.
Principal Beneficiaries to Pay for Facilities Study … 13
9.1.2. Payment Procedure … 13 9.1.3. Facilities Study Procedures … 13 9.2.
Obligation to Build … 14 9.2.1. Due Diligence to Construct … 14 9.2.2. Delay in Construction or Expansion … 15
9.2.2.1.
Alternatives to the Original Facility Additions … 15
9.2.2.2.
Refund Obligation for Unfinished Facility Additions … 15
9.3.
Provisions Relating To Transmission Construction on the Systems of Other
TOs … 16 9.3.1. Responsibility for Third Party Additions … 16
9.3.2. Coordination of Third-Party System Additions … 16
10. Interconnection Process … 16 10.1. Applicability … 16 10.2. Applications … 17 10.3. Interconnection Application … 17 10.3.1. Amendment to Completed Interconnection Application … 18
10.4. Review of Completed Interconnection Application … 18
10.5. Notice of Need for System Impact Study … 19 10.6. System Impact Study Cost Reimbursement and Agreement … 19
10.6.1. Cost Reimbursement … 20 10.6.2. Multiple Parties … 20 10.7. System Impact Study Procedures … 20 10.7.1. Procedures Upon Completion of System Impact Study … 20
10.8. Notice of Need for Facilities Study … 21 10.9. Facilities Study Procedures … 22 10.9.1. Execution of Interconnection Agreement … 22
10.10. Partial Interim Service … 22 10.11. Expedited Procedures for New Facilities … 22
11. Uncontrollable Forces and Indemnification … 23 11.1. Procedures to Follow if Uncontrollable Force Occurs … 23
11.2. Indemnification … 23
12. Regulatory Filings … 23
13. Miscellaneous … 23 13.1. Notices … 24 13.2. Waiver … 24 13.3. Confidentiality … 24 13.3.1. Maintaining Confidentiality if Not for Public Disclosure … 24
13.3.2. Disclosure of Confidential Information … 24
13.4. Titles … 25
PDF page 173
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
13.5. Severability … 25 13.6. Preservation of Obligations … 25 13.7. Governing Law … 25 13.8. Appendices Incorporated … 25 13.9. Consistency with CAISO Tariff … 25 13.10. Disputes … 25
APPENDIX I TRANSMISSION REVENUE REQUIREMENT AND TRBAA
APPENDIX II NOTICE
APPENDIX III PRO FORMA LETTER AGREEMENT
PDF page 174
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
APPENDIX IV – LARGE LOAD INTERCONNECTION PROCESS AND TIMELINE
PDF page 175
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
1. Preamble. DCR Transmission, L.L.C.’s (“DCRT” or “Participating TO”) Transmission Revenue Requirement (“TRR”) for its Regional Transmission Facilities placed under the California Independent System Operator Corporation’s (“CAISO”) Operational Control, and certain terms and conditions relating to transmission expansion of and interconnection with DCRT’s Regional Transmission Facilities placed under the CAISO’s Operational Control, are set forth in this Transmission Owner (“TO”) Tariff.
2. Effective Date. This TO Tariff is effective on the date on which DCRT became a Participating TO, and shall continue to be effective so long as DCRT is a party to the Transmission Control Agreement (“TCA”).
3. TO Definitions. Certain capitalized terms used in this TO Tariff that are set out immediately below shall have the meanings set out below unless otherwise stated or the context otherwise requires. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the CAISO Open Access Transmission Tariff (“Tariff”), as it may be amended from time to time.
3.1.
Access Charge. A charge paid by all Utility Distribution Companies, Small Utility Distribution Companies, and Metered Sub System (“MSS”) Operators with Gross Load in a Participating Transmission Owner (“PTO” or “Participating TO”) Service Territory, as set forth in CAISO Tariff, Article II. The Access Charge includes the Regional Access Charge and the Local Access Charge, as applicable. The Access Charge will recover the Participating TO’s TRR in accordance with CAISO Tariff, Appendix F, Schedule 3.
3.2
Alternative Transmission Technologies. Any transmission technology other than Network Upgrades that can be used to improve the Participating TO’s Transmission System facilitate the interconnection of a Customer or a Large Load Interconnection Customer, which may include but is not limited to, static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, unified power flow controller, and tower lifting. 3.3.
Base Transmission Revenue Requirement (“Base TRR”). The TRR before reflecting TRBAA and Standby Transmission Revenues. The Base TRR is shown in Appendix I to this TO Tariff.
3.4.
CAISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13 of the CAISO Tariff, as amended from time to time.
3.5.
CAISO-Controlled Grid. The system of transmission lines and associated facilities of the Participating TOs that have been placed under the CAISO’s Operational Control.
3.6.
CAISO Tariff. The currently effective CAISO Agreement and Tariff, as it is on
PDF page 176
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
file with FERC and as may be modified from time to time.
3.7.
Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed Interconnection Application.
3.8.
Completed Interconnection Application. An Interconnection Application that satisfies all of the information and other requirements of Section 10.3 of this TO Tariff and, if applicable, the information requirements as specified by the CAISO and posted on the CAISO Home Page.
3.9.
Direct Assignment Facilities. Facilities or portions of facilities that are owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting interconnection under this TO Tariff to the CAISO Controlled Grid at the point of interconnection. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval.
3.10. DCR Transmission, L.L.C. (“DCRT”). The Delaware limited liability corporation that is the Participating TO under this TO Tariff.
3.11. Existing Contracts. Those transmission service agreements or other contracts which grant transmission service rights in existence on the CAISO Operations Date (including any contracts entered into pursuant to such contracts) as may be amended in accordance with their terms or by agreement between the parties thereto from time to time.
3.12. Expedited Interconnection Agreement. A contract between a party which has submitted a Request for Expedited Interconnection Procedures and the Participating TO under which the Participating TO agrees to process, on an expedited basis, the Completed Interconnection Application of such party and which sets forth the terms, conditions, and cost responsibilities for such Interconnection.
CAISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13 of the CAISO Tariff, as amended from time to time. CAISO Controlled Grid. The system of transmission lines and associated facilities of the Participating TOs that have been placed under the CAISO’s Operational Control.
CAISO Tariff. The currently effective CAISO Agreement and Tariff, as it is on file with FERC and as may be modified from time to time.
3.13 Flexible Interim Load Interconnection Service (“FILI Service”). An interconnection service that may be offered by Participating TO at its sole discretion, that interconnects a Large Load Facility that cannot be reliably served at its full requested capacity without the construction of Network Upgrades or
PDF page 177
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
Alternative Transmission Technologies, subject to operational constraints on the Large Load Facility to ensure Transmission System reliability, as memorialized in a Large Load Interconnection Agreement.
3.14. Interconnection Application. An application that requests Interconnection to the CAISO Controlled Grid., other than a Large Load Interconnection Application.
3.15 Large Load. An End User located at a single site whose Point(s) of Interconnection is/are to the CAISO-Controlled Grid, and that has a peak load of 50 MW or greater.
3.16. Large Load Facilities Study. The second study conducted as part of the LLIP as described in Appendix IV to this TO Tariff, used to create the detailed design of the interconnection facilities used to interconnect the Large Load to the Participating TO’s facilities, based on the findings of the Large Load System Impact Study.
3.17. Large Load Facilities Study Agreement. The prerequisite agreement before DCRT will conduct, or cause to be conducted, the Large Load Interconnection Facilities Study, a pro forma version of which constitutes Attachment 2 to Appendix IV of this TO Tariff.
3.18. Large Load Interconnection Agreement. The required agreement between DCRT and a Large Load Interconnection Customer prior to construction of Large Load Interconnection Facilities, a pro forma version of which constitutes Attachment 3 of Appendix IV of this TO Tariff.
3.19. Large Load Interconnection Application. The required application for a Large Load Interconnection Customer seeking interconnection with DCRT’s Transmission System, as described in Appendix IV to this TO Tariff. 3.20. Large Load Interconnection Customer. Any entity that proposes to interconnect a Large Load, or modify its existing interconnection, with the DCRT Transmission System.
3.21. Large Load Interconnection Facilities. All facilities and equipment between the Large Load and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Large Load to the transmission system. Interconnection Facilities are sole-use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades.
3.22. Large Load Interconnection Process (“LLIP”). The process by which Large Loads may be interconnected to DCRT’s Transmission System, as described in Appendix IV to this TO Tariff.
PDF page 178
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
3.23. Large Load Interconnection Service. The service provided by the Participating TO associated with interconnecting the Large Load Interconnection Customer’s Generating Facility to the CAISO-Controlled Grid and enabling it to receive electric energy and capacity from the CAISO-Controlled Grid at the Point of Interconnection, pursuant to the terms of the Large Load Interconnection Agreement, the Participating TO’s TO Tariff, and the CAISO Tariff. 3.24. Large Load System Impact Study. The initial study conducted as part of the LLIP as described in Appendix IV to this TO Tariff, consisting of short circuit analysis, a stability analysis, a power flow analysis, and any other studies that are deemed necessary.
3.25 Large Load System Impact Study Agreement. The prerequisite agreement before DCRT will conduct, or cause to be conducted, the Large Load System Impact Study, a pro forma version of which constitutes Attachment 1 to Appendix IV of this TO Tariff.
3.26. Net FTR Revenue. The sum of: 1) The revenue received by the Participating TO from the sale, auction, or other transfer of the Financial Transmission Rights (“FTR”) provided to it pursuant to Section 9.4.3 FTR, or any substantively identical successor provision, of the CAISO Tariff; and 2) For each hour: a) the Usage Charge revenue received by the Participating TO associated with its Section 9.4.3 FTRs; minus b) Usage Charges that are: i) incurred by the Scheduling Coordinator for the Participating TO under CAISO Tariff Section 7.3.1.4, ii) associated with the Participating TO’s Section 9.4.3 FTRs, and iii) incurred by the Participating TO for its energy transactions but not incurred as a result of the use of the transmission by a third-party and minus c) the charges paid by the Participating TO pursuant to Section 7.3.1.7, to the extent such charges are incurred by the Scheduling Coordinator of the Participating TO on Congested Inter-zonal Interfaces that are associated with the Section 9.4.3 FTRs provided to the Participating TO. The component of Net FTR Revenue represented by item 2) immediately above shall not be less than zero for any hour.
3.27. Participation Agreement. An agreement between a Participating TO and a Project Sponsor that specifies the terms and conditions under which the Participating TO will construct a transmission addition or upgrade on behalf of the Project Sponsor.
3.28. Project Proponent. A Market Participant or group of Market Participants that:
(i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition and upgrade, and thus is not a Project Sponsor; and (iii) initiates proceedings under the CAISO ADR Procedures to determine the need for the proposed transmission addition or upgrade. 3.29. Regional Transmission Group (“RTG”). A voluntary organization approved by FERC and composed of transmission owners, transmission users, and other
PDF page 179
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
entities, organized to efficiently coordinate the planning, expansion, and use of transmission on a regional and inter-regional basis.
3.30. Regulatory Authority. The Federal Energy Regulatory Commission (“FERC”), or successor agency.
3.31. Reliability Upgrade. The transmission facilities other than Direct Assignment Facilities beyond the first point of Interconnection necessary to interconnect a New Facility or wholesale Load safely and reliably to the CAISO Controlled Grid, which would not have been necessary but for the Interconnection of a New Facility or wholesale Load, including network upgrades necessary to remedy short circuit or stability problems resulting from the Interconnection of the new Facility or wholesale Load to the CAISO Controlled Grid. Reliability Upgrades also include, consistent with WECC practice, the facilities necessary to mitigate any adverse impact a New Facility’s or wholesale Load’s Interconnection may have on a path’s WECC path rating. Reliability Upgrades shall be specified in the Interconnection Agreement that governs Interconnection service and shall be subject to FERC approval.
3.32. Requests for Expedited Interconnection Procedures. A written request by which an applicant for Interconnection can request expedited processing of its Interconnection Application.
3.33. System Impact Study. An engineering study conducted by a Participating TO to determine whether a request for Interconnection to the Participating TO’s transmission system would require new transmission additions, upgrades or other mitigating measures.
3.34. System Impact Study Agreement. An agreement between a Participating TO and an entity that has requested Interconnection to the Participating TO’s transmission system pursuant to which the entity requesting Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a System Impact Study.
3.35. TO Tariff. This Transmission Owner Tariff, as it may be amended or superseded.
3.36. Transmission Revenue Balancing Account Adjustment (“TRBAA”). A mechanism established by the Participating TO which will ensure that all Transmission Revenue Credits and other credits specified in Sections 6 and 8 of CAISO Tariff, Appendix F, Schedule 3 flow through to CAISO Tariff and TO Tariff transmission customers.
3.37. Participating TO’s Transmission System. The transmission facilities owned by DCRT.
PDF page 180
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
4. Eligibility. Transmission service over DCRT’s Regional Transmission Facilities and Entitlements placed under the CAISO’s Operational Control shall be provided only to Eligible Customers as defined by the CAISO Tariff. Any dispute as to whether a customer is eligible for wholesale transmission service shall be resolved by FERC.
5. Access Charges. The applicable Access Charges are provided in the CAISO Tariff. 5.1.
Transmission Revenue Requirement (“TRR”). As set forth in the CAISO Tariff, the TRR for each Participating TO is used to develop the Access Charges set forth in the CAISO Tariff, and is used by the CAISO to calculate the disbursement of wheeling revenues among Participating TOs pursuant to Section 26.1.4.3 of the CAISO Tariff. DCRT’s TRR is set forth in Appendix I. 5.2.
TRBAA. The Participating TO shall maintain a Transmission Revenue Balancing Account (“TRBA”) that will ensure that all Transmission Revenue Credits and the refunds, specified in Sections 6 and 8 of Appendix F, Schedule 3 of the CAISO Tariff, flow through to transmission customers. The TRBAA shall be equal to: TRBAA = TRCF + TRCT + I.
TRCT =
The balance representing the prior period difference
between the projected Transmission Revenue Credits
and the actual credits.
TRCF =
The forecast of Transmission Revenue Credits for
the following calendar year.
I
=
The interest balance for the TRBA, which shall be
calculated using the interest rate pursuant to Section
35.19(a) of FERC’s regulations under the Federal Power
Act (18 CFR Section 35.19(a)). Interest shall be calculated
based on the average TRBA principal balance each month,
compounded quarterly.
The DCRT estimated TRBAA, calculated in accordance with the CAISO Tariff, is stated in Appendix I.
6. Ancillary Services--Applicability and Charges. If any Ancillary Services are required, DCRT will not provide such services, but transmission customers will be required to meet any such requirement in accordance with the CAISO Tariff.
7. Billing and Payment.
7.1.
Payment. The CAISO, in accordance with the CAISO Tariff, shall pay the Participating TO, among other things, Wheeling, Usage, Access Charge revenues, and FTR auction proceeds (excluding Usage Charge revenues payable to FTR Holders) in accordance with the CAISO Tariff.
PDF page 181
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
7.2.
Billing. Users of DCRT’s Regional Transmission Facilities and Entitlements placed under the CAISO’s Operational Control shall pay to the CAISO all applicable charges in accordance with the CAISO Tariff.
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades.
8.1.
Participating TO Obligation to Interconnect. The Participating TO shall, at the request of a third party pursuant to Section 10, interconnect its system to the wholesale generation or load of such third party, or modify an existing wholesale Interconnection. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the FPA. Interconnections requested by entities or individuals that are not so eligible shall be governed by the Local Regulatory Authority. The procedures for Interconnection of wholesale generation to the CAISO Controlled Grid shall be governed by the CAISO Tariff.
8.1.1. Interconnection to Transmission System. Interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, and CAISO reliability criteria for the CAISO Controlled Grid. The Participating TO will not accommodate the Interconnection if doing so would impair systems reliability, or would otherwise impair the ability of the Participating TO to honor its Encumbrances existing as of the time an entity submits its Interconnection Application. The Participating TO shall identify any such adverse effect on its Encumbrances in the System Impact Study performed pursuant to Section 10.7. To the extent the Participating TO determines that the Interconnection will have an adverse effect on Encumbrances, the party requesting Interconnection shall mitigate such adverse effect.
8.1.1.1 Letter Agreement. Pursuant to Section 12 of Appendix DD of the ISO Tariff, prior to executing an Interconnection Agreement, a party seeking Interconnection may, in order to advance the implementation of its Interconnection, request, and the Participating TO shall offer the party, a Letter Agreement, a pro forma version of which is set forth in Appendix III to the TO Tariff, that authorizes the Participating TO to begin engineering, design, and procurement of long lead-time items, or construction necessary for the establishment of the Interconnection. However, Participating TO shall not be obligated to offer a Letter Agreement if the party seeking Interconnection is in Dispute Resolution as a result of an allegation that the party seeking Interconnection has failed to meet any milestones or comply with any prerequisites specified in the ISO Tariff. The Letter Agreement is an optional procedure. The Letter Agreement shall provide for the party seeking Interconnection to pay the
PDF page 182
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
cost of all activities authorized by the party and to make advance payments or provide other satisfactory security for such costs. Following a party seeking Interconnection’s request for a Letter Agreement, the Participating TO shall prepare and tender to the party seeking Interconnection a draft Letter Agreement in the form of the Participating TO’s FERC-approved Letter Agreement as set forth in Appendix III to the TO Tariff, including draft exhibits that include the proposed scope of work, estimated costs, payments, financial security and milestones, as applicable. The party seeking Interconnection shall provide written comments, or notification of no comments, to the draft exhibits within thirty (30) Calendar Days. The Participating TO and the party seeking Interconnection shall negotiate concerning any disputed provisions of the exhibits to the draft Letter Agreement for not more than ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Interconnection. If the party seeking Interconnection determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the draft Letter Agreement and request submission of the unexecuted Letter Agreement with FERC or initiate dispute resolution procedures pursuant to Section 13.10 of this TO Tariff. If the party seeking Interconnection requests termination of the negotiations, but within ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Interconnection, fails to request either the filing of the unexecuted Letter Agreement or initiate dispute resolution procedures, it shall be deemed to have withdrawn its request for a Letter Agreement and the Participating TO shall have no further obligation to enter into a Letter Agreement, unless an extension is mutually agreed to by the parties. The Participating TO shall provide to the party seeking Interconnection a final Letter Agreement within fifteen (15) Business Days after the completion of the negotiation process.
Following submission of the final Letter Agreement to the party seeking Interconnection, the party shall either: (i) execute two originals of the tendered Letter Agreement and return them to the Participating TO; or (ii) request in writing that the Participating TO file with FERC a Letter Agreement in unexecuted form. As soon as practicable, but not later than ten (10) Business Days after receiving either the two executed originals of the tendered Letter Agreement (if it does not conform with a FERC- approved Letter Agreement) or the request to file an unexecuted Letter Agreement, the Participating TO shall file the Letter Agreement with FERC, together with its explanation of any matters as to which the party seeking Interconnection and the Participating TO disagree and support for the costs that the Participating TO proposes to charge to the party seeking Interconnection under the Letter Agreement. An unexecuted Letter
PDF page 183
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
Agreement should contain terms and conditions deemed appropriate by the Participating TO for the Interconnection request.
If the party seeking Interconnection executes the final Letter Agreement, the Participating TO and the party seeking Interconnection shall perform their respective obligations in accordance with the terms of the Letter Agreement, subject to modification by FERC. Upon submission of an unexecuted Letter Agreement, the party seeking Interconnection and the Participating TO shall promptly comply with the unexecuted Letter Agreement, subject to modification by FERC.
8.1.2. Costs Associated with Interconnection. Each party requesting Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities and, if applicable, any Reliability Upgrades required to provide the requested Interconnection. In addition, such party shall implement all existing operating procedures necessary to safely and reliability interconnect such party’s generation or wholesale load to the facilities of the Participating TO and to ensure the CAISO Controlled Grid’s conformance with the CAISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the CAISO Tariff for transmission expansions or upgrades.
8.1.3. Interconnection Agreement. Pursuant to Section 10.4, 10.7.1, or 10.9.1, a party requesting an Interconnection shall request in writing that the Participating TO tender to such part an Interconnection Agreement that will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement will include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, and construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, any Delivery Upgrades, if applicable, and for any other mitigation measures. For an Interconnection request to remain a Completed Interconnection Application, the party requesting the Interconnection shall execute the Interconnection Agreement and return it to the Participating TO within thirty (30) Business Days of receipt. Alternatively, if an Eligible Customer requesting the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the CAISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the CAISO ADR Procedures concerns whether the
PDF page 184
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted interconnection Agreement or commence construction of the Interconnection facilities or incur other costs under the Interconnection Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed Interconnection Agreement shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by any System Impact Study Agreement or Facilities Study Agreement. To maintain its queue position, the applicant must timely comply with the Interconnection requirements of Section 5.76 of the CAISO Tariff and Sections 8.1 and 10 of this TO Tariff. If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application or because its queue position has been modified pursuant to the queuing provisions in Section 25 of the CAISO Tariff.
8.1.4. Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Reliability Upgrades that it is obligated to construct pursuant to this TO Tariff and Section 24 of the CAISO Tariff. The Participating TO’s obligation to build will be subject to: (1) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (2) the presence of a cost recovery mechanism with cost responsibility assigned to accordance with the CAISO Tariff or applicable FERC precedent; and (3) a signed Interconnection Agreement or a signed Expedited Interconnection Agreement, or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection Agreement.
8.1.5. Energization. The Participating TO shall not be obligated to energize, nor shall the applicant or wholesale load be entitled to have its interconnection to the CAISO -Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3, and; or a Large Load Interconnection Agreement has been executed, or filed at FERC pursuant to Appendix IV, Section 2.5.1; and such agreement become effective and such applicant or wholesale load has demonstrated to the CAISO’s reasonable satisfaction
PDF page 185
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
that it has complied with all of the requirements of the CAISO Tariff and the requirements of this TO Tariff.
8.1.6. Coordination with CAISO on Interconnection Requests. The Participating TO shall coordinate with the CAISO and Affected TOs, if any, pursuant to the provisions of the TCA, in developing interconnection standards and guidelines for processing interconnection request under this TO Tariff.
8.2.
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to: (1) perform System Impact or Facility Studies where the Project Sponsor or the CAISO agrees to pay the study cost and specifies the project objectives to be achieved, and (2) build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations under Section 24 of the CAISO Tariff and this TO Tariff. 8.2.1. Obligation to Construct. A Participating TO shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.2.1 hereof have been satisfied. 8.3.
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the CAISO, (including the CAISO’s ADR Procedures), the CPUC, WECC, or RTG
coordinated planning processes as to the need for or construction of a facility, the need for full cost recovery, and the allocation of costs.
9. Expansion Process.
9.1.
Determination of Facilities. A Participating TO shall perform a Facilities Study in accordance with this Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 of the CAISO Tariff and this TO Tariff; (2) a Market Participant agrees to pay the costs of the Facilities Study and specifies the project objectives to be achieved in terms of increased capacity or reduced congestion; or (3) the Participating TO is required to perform a Facilities Study pursuant to the CAISO Tariff.
9.1.1. Payment of Facilities Study Costs.
9.1.1.1. Market Participant to Pay for Facilities Study. Where a Market Participant requests a Facilities Study and the need for
the transmission addition or upgrade has not yet been
established in accordance with the procedures established
herein and the CAISO Tariff, the Market Participant shall pay
the cost of the Facilities Study.
PDF page 186
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
9.1.1.2. Project Sponsor or Project Proponent to Pay for Facilities Study. Where the facilities to be added or upgraded have
been determined to be needed in accordance with the
procedures established herein and the CAISO Tariff, the
Project Sponsor, Project Proponent, or the CAISO requesting the study shall pay the reasonable cost of the Facilities Study. When the Participating TO is the Project Sponsor in
accordance with the CAISO Tariff, the costs of the Facilities Study shall be recovered through its Access Charges and
transmission rates.
9.1.1.3. Principal Beneficiaries to Pay for Facilities Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the CAISO or CAISO ADR Procedures in accordance with
the CAISO Tariff, the Project Sponsor and the identified
principal beneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as may be agreed, or, failing agreement, as determined in accordance with the
CAISO ADR Procedures.
9.1.2. Payment Procedure. Where a Facilities Study is being conducted pursuant to this TO Tariff, the Participating TO shall, within thirty (30) days of the receipt of all reasonably required information, tender to the Market Participant, Project Sponsor, Project Proponent, CAISO, or identified principal beneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Market Participant, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Facilities Study. If the Market Participant, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Facilities Study Agreement, they shall execute the Facilities Study Agreement and return it to the Participating TO within ten
(10) Business Days. Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Facilities Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the CAISO ADR
Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study, and the parties shall submit the disputed terms for resolution under the CAISO’s ADR Procedures.
PDF page 187
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
9.1.3. Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or alternative request to proceed as provided for in Section 9.1.2, a copy of which has been provided to the CAISO by the party requesting the Facilities Study, the Participating TO will use due diligence to complete the required Facilities Study within a sixty (60) day period. If the Participating TO is unable to complete the Facilities Study in the allotted time period, the Participating TO shall notify the party requesting the Facilities Study and provide an estimate of the time needed to reach a final determination along with an explanation of the reasons that additional time is required to complete the Facilities Study. If additional time is required, the Participating TO will use best efforts to complete the Facilities Study within ten (10) months, provided adequate information is provided by all the parties.
9.2.
Obligation to Build.
9.2.1. Due Diligence to Construct. Subject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the CAISO Tariff and this TO Tariff. Alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the CAISO ADR Procedures, including any
determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the CAISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement or alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the CAISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the CAISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement, commence construction of the additions or upgrades or incur other costs under the Participation Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Participation Agreement has been issued by the applicable court or regulatory authority. The Participating TO’s obligation to build will be subject to: 1) its ability, after making a good faith effort, to obtain the
PDF page 188
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
necessary approvals and property rights under applicable federal, state, and local laws; 2) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the CAISO Tariff; and 3) a signed Participation Agreement. The Participating TO will not construct or expand its existing or planned transmission system if doing so would impair system reliability as determined through systems analysis based on the Applicable Reliability Criteria.
9.2.2. Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify: (1) the Project Sponsor with regard to facilities determined to be needed; (2) the Parties to the Participation Agreement with regard to facilities determined to be needed pursuant to the CAISO Tariff where principal beneficiaries were identified; and (3) the CAISO. In such circumstances, the Participating TO shall, within thirty (30) days of notifying such Project Sponsor, Parties to the Participation Agreement, and the CAISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Participation Agreement, and the CAISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the CAISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives.
9.2.2.1. Alternatives to the Original Facility Additions. If the review process of Section 9.2.2 determines that one or more alternatives exist to the originally planned construction
project, the Participating TO shall present such alternatives for consideration to the Project Sponsor, Parties to the
Participation Agreement, and the CAISO, as the case may be. If upon review of any alternatives, such Project Sponsor, the CAISO, or Parties to the Participation Agreement wish to
evaluate or to proceed with one of the alternative additions or upgrades, such Project Sponsor, the CAISO, or Parties to the Participation Agreement may request that the Participating TO prepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO Tariff. In the event the
Participating TO concludes that no reasonable alternative
exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Participation Agreement or the CAISO disagree, the dispute shall be resolved pursuant to the CAISO ADR Procedure
PDF page 189
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
9.2.2.2. Refund Obligation for Unfinished Facility Additions. If the Participating TO and the Project Sponsor, the CAISO, or Parties to the Participation Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Regulation 35.19(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.
9.3.
Provisions Relating To Transmission Construction on the Systems of Other TOs.
9.3.1. Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any engineering, permitting, and construction of any transmission or distribution facilities on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO will undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice.
9.3.2. Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the CAISO Tariff require additions or upgrades on other systems, to the extent consistent with this TO Tariff, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the CAISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Participation Agreement, and the CAISO, in writing of the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or resume construction of the new facilities. Within forty (40) Business Days of receiving written notification by the Participating TO of its intent to defer construction pursuant to this section, such Project Sponsor, Parties to the Participation Agreement, or the CAISO may challenge the decision in accordance with the CAISO ADR Procedure.
10. Interconnection Process.
PDF page 190
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
10.1. Applicability. All requests for Interconnection directly to the CAISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the provisions of this Section 10., except for requests for Interconnection from Large Loads. Large Load requests for Interconnection shall be processed pursuant to Appendix IV to this Tariff. All requests for Interconnection of wholesale generation directly to the CAISO Controlled Grid shall be processed pursuant to the provisions of the CAISO Tariff.
10.2. Applications. Except as provided in Section 10.1, a party requesting Interconnection shall submit written Interconnection Application which provides the information required in Section 10.3 to the Participating TO and shall send a copy of the application to the CAISO. The Participating TO shall time-stamp the application to establish study priority.
10.3. Interconnection Application. An Interconnection Application shall provide all of the information listed in 18 C.F.R. § 2.20, including, but not limited to, the following:
(i) The identity, address, telephone number, and facsimile number of the entity requesting Interconnection;
(ii) The Interconnection point(s) to the CAISO Controlled Grid contemplated by the applicant;
(iii) The resultant (or new) maximum amount of Interconnection capacity contemplated by the applicant;
(iv) The proposed date for energizing the Interconnection and the term of Interconnection service; and
(v) Such other information as the Participating TO reasonably requires to process the application.
In addition to the information specified above, the following information may also be provided in order to properly evaluate system conditions:
(vi) If the applicant is a Load, the electrical location of the source of the power (if known) to be transmitted pursuant to the applicant’s request for Interconnection. If the source of the power is not known, a system purchase will be assumed.;
(vii) The electrical location of the ultimate load (if known). If the location of the load is not known, a system sale will be assumed.;
(viii) If an applicant proposes to perform or cause a third party to perform any required System Impact Study or any required Facilities Study, it shall so indicate in its Interconnection Application. The results of any study or
PDF page 191
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
studies performed by an applicant or its designated third party must be approved by both the CAISO and the Participating TO.
Within ten (10) Business Days after receipt of an Interconnection Application, the Participating TO and the CAISO, if applicable, shall determine whether the application is complete (“Completed Interconnection Agreement”). Whenever possible, the Participating TO will attempt to remedy deficiencies in the Interconnection Application through informal communications with the applicant. If such efforts are unsuccessful, the Participating TO shall return the Interconnection Application to the applicant. The Participating TO will treat the information in the Interconnection Agreement, including the applicant’s identity, as confidential at the request of the applicant except to the extent that disclosure of the information is required by this TO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or CAISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations.
10.3.1. Amendment to Completed Interconnection Application. An applicant shall only be limited to amending its Completed
Interconnection Application once. Additional amendments will be at the Participating TO’s discretion, to be permitted on a not unduly discriminatory basis and without undue preference or advantage, and the Participating TO’s agreement for applicant to make additional
amendment shall not be unreasonably withheld. Such amendment shall occur on or before ten (10) Business Days following the date the Participating TO tenders any Facilities Study Agreement. Specifically, an applicant may submit an amendment to its Completed
Interconnection Application to reflect a revised configuration for its New Facility. The amended Completed Interconnection Application shall be treated in accordance with Section 25 of the CAISO Tariff and Section 10.5 of this TO Tariff; the applicant’s Completed
Interconnection Application shall be deemed withdrawn; and the applicant shall maintain its existing queue position, if (a) the amended Completed Interconnection Application is received by the Participating TO within ten (10) Business Days of the Participating TO’s tender of a Facilities Study Agreement; and (b) the applicant has not submitted a previous amendment to the Completed Interconnection Application. In the event an applicant amends its Completed Interconnection
Application, it will be responsible for any additional study costs that result from that amendment, including costs associated with revisions to studies for other applicants holding later queue positions.
10.4. Review of Completed Interconnection Application. After receiving a Completed Interconnection Application, the Participating TO and the CAISO, if applicable, will determine on a non-discriminatory basis whether a System Impact
PDF page 192
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
Study is required. Whenever the Participating TO, and the CAISO, if applicable, determines that a System impactImpact Study is not required and that neither Reliability Upgrades nor changes in existing operating procedures are required, the Participating TO shall notify the applicant within fifteen (15) Business Days of the Completed Application Date. If the Interconnection can be accommodated without any Direct Assignment Facilities, then within thirty (30) Business Days of such notice from the Participating TO, the applicant shall request the Participating TO to tender to the applicant an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. If the Participating TO determines upon review of the Completed Interconnection Application, that Direct Assignment Facilities are required, the Participating TO shall tender to the applicant a Facilities Study Agreement within twenty (20) Business Days of the Completed Application Date and continue the Interconnection process pursuant to Section 10.8
10.5. Notice of Need for System Impact Study. If the Participating TO, and the CAISO if applicable, determines that a System Impact Study is necessary to accommodate the requested Interconnection, the Participating TO shall so inform the applicant as soon as practicable. In such cases, the Participating TO shall within twenty (20) Business Days of receipt of a Completed Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO, the estimated time required to complete it, and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of performing the required System Impact Study. A description of the Participating TO’s transmission assessment practices for completing a System Impact Study shall be provided in the Participating TO’s FERC Form 715. Alternatively, if the applicant will perform the System Impact Study, the Participating TO shall within twenty (20) Business Days of receipt of a Completed Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of reviewing the required System Impact Study. For an Interconnection request to remain a Completed Interconnection Application, the applicant shall execute the System Impact Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated cost of performing the System Impact Study or reviewing the applicant’s System Impact Study. Alternatively, if the applicant request the Participating TO to proceed with the System Impact Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the CAISO ADR Procedures, including any determination by FERC or appeal of a
PDF page 193
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
FERC determination in accordance with that process, the Participating TO shall promptly proceed with the System Impact Study provided that such request is accompanied by payment of the reasonable estimated cost of the System Impact Study, and the parties shall submit the disputed terms for resolution under the CAISO’s ADR Procedures. If the applicant elects not to execute a System Impact Study Agreement, and does not request that the Participating TO proceed with the System Impact Study or review thereof, its application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO and the CAISO all costs reasonably incurred in processing the application. 10.6. System Impact Study Cost Reimbursement and Agreement.
10.6.1. Cost Reimbursement. The System Impact Study Agreement shall clearly specify the charge for the System Impact Study, based on the Participating TO’s estimate of the cost and time for completion of the System Impact Study. The charge shall not exceed the reasonable cost of the study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any modifications to existing planning studies that are reasonably necessary to evaluate the impact of the applicant’s request.
10.6.2. Multiple Parties. If multiple parties request Interconnection at the same location, the Participating TO may conduct a single System Impact Study. The costs of that study shall be pro-rated among the parties requesting Interconnection.
10.7. System Impact Study Procedures. Upon receipt of an executed System Impact Study Agreement or initiation of the CAISO ADR Procedures and receipt of payment for estimated study costs, the Participating TO will use due diligence to
(a) complete the required System Impact Study within a sixty (60) calendar day period or (b) complete its review of an applicant’s System Impact Study within thirty (30) calendar days of its receipt of the completed study. The System Impact Study will identify whether any Direct Assignment Facilities or Reliability Upgrades are necessary to deliver a New Facility’s full output over the CAISO Controlled Grid, or any transmission additions or upgrades are necessary to serve a wholesale load. The System Impact Study will also identify any adverse impact on Encumbrances existing as of the applicant’s Completed Application Date. In the event that the Participating TO is unable to complete the required System Impact Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed System Impact Study and related work papers shall be made available to the applicant and the CAISO. The Participating TO shall notify the
PDF page 194
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
applicant and the CAISO immediately upon completion of the System Impact Study.
10.7.1. Procedures Upon Completion of System Impact Study. Within fifteen (15) Business Days of completion of the System Impact Study or review and approval of an applicant’s System Impact Study, the
Participating TO shall notify the applicant whether the transmission system will be adequate to accommodate all of a request for
Interconnection. If no costs are likely to be incurred for any Direct Assignment Facilities, any Reliability Upgrades, or implementing any operating procedures, then within thirty (30) Business Days of receipt of written approval of the applicant’s System Impact Study from the Participating TO and the CAISO the applicant shall request the
Participating TO to tender an Interconnection Agreement within thirty
(30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. If costs are likely to be incurred to accommodate a request for
Interconnection, the Participating TO shall tender to the applicant a Facilities Study Agreement pursuant to Section 10.8.
10.8. Notice of Need for Facilities Study. If a System Impact Study indicates that additions or upgrades to the CAISO Controlled Grid are needed to satisfy an applicant’s request for interconnection, the Participating TO shall, within fifteen
(15) Business Days of the date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study by the Participating TO, tender to the applicant a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete the required study; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of performing the required Facilities Study. Alternatively, if the applicant will perform the Facilities Study, the Participating TO shall within fifteen (15) Business Days of the completion date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study, tender a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete the required review; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of reviewing the required Facilities study. For an Interconnection request to remain a Completed Interconnection Application, the applicant shall execute the Facility Studies Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated costs of performing the Facilities Study or reviewing the applicant’s Facilities Study. Alternatively, if the applicant request the Participating TO to proceed with the
PDF page 195
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
Facilities Study to review thereof and commits to abide by terms, conditions, and cost assignments ultimately determined under the CAISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study provided that such request is accompanied by payment for the reasonable estimated cost of the Facilities Study, and the parties shall submit the disputed terms for resolution under the CAISO ADR Procedures. If the applicant elects not to execute a Facilities Study Agreement and does not request that the Participating TO proceed with the Facilities Study or review thereof, its application shall be deemed withdrawn and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by the System Impact Study Agreement.
10.9. Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or initiation of the CAISO ADR Procedures and receipt of payment for the estimated study costs, the Participating TO will use due diligence to either (a) complete the required Facilities Study within a sixty (60) calendar day period or
(b) complete its review of an applicant’s Facilities Study within thirty (30) calendar days of its receipt of the Completed Study. In the event that Participating TO is unable to complete the required Facilities Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed Facilities Study shall be made available to the applicant.
10.9.1. Execution of Interconnection Agreement. Within thirty (30) Business Days of receipt of the completed Facilities Study performed by the Participating TO or receipt of written approval of the applicant’s Facilities Study from the Participating TO, the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty
(30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. 10.10. Partial Interim Service. If the Participating TO determines that there will not be adequate transmission capability to satisfy the full amount requested in a Completed Interconnection Application, the Participating TO nonetheless shall be obligated to offer and provide the portion of the requested Interconnection that can be accommodated without any additional Direct Assignment Facilities or Reliability Upgrades. However, the Participating TO shall not be obligated to provide the incremental amount of requested Interconnection that requires such additional facilities or upgrades until such facilities or upgrades have been placed in service.
10.11. Expedited Procedures for New Facilities. In lieu of the procedures set forth above, the applicant shall have the option to expedite the processing of its Completed Interconnection Application. In order to exercise this option, the
PDF page 196
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
applicant shall submit in writing a Request for Expedited Interconnection Procedures to the Participating TO within ten (10) Business Days after receiving a copy of the System Impact Study for the proposed Interconnection. Within ten
(10) Business Days after receiving a Request for Expedited Procedures, the Participating TO shall tender an Expedited Interconnection Agreement that requires the applicant to compensate the Participating TO for all costs reasonably incurred pursuant to the terms of this TO Tariff for processing the Completed Interconnection Application and providing the requested Interconnection. While the Participating TO agrees to provide the applicant with its best estimate of the costs of any needed Direct Assignment Facilities and, if applicable, Reliability Upgrades, and such other charges that may be incurred, unless otherwise agreed by the parties, such estimate shall not be binding and the applicant must agree in writing to compensate the Participating TO for all actual Interconnection costs reasonably incurred pursuant to the provisions of this TO Tariff. The applicant shall execute and return such Expedited Service Agreement within ten (10) Business Days of its receipt or the applicant’s request for Interconnection will cease to be a Completed Interconnection Application and will be deemed terminated and withdrawn, In that event, the applicant shall reimburse the Participating TO for all costs reasonably incurred in processing the application not covered by the terms of the System Impact Study Agreement.
11. Uncontrollable Forces and Indemnification.
11.1. Procedures to Follow if Uncontrollable Force Occurs. In the event of the occurrence of an Uncontrollable Force which prevents a Party from performing any of its obligations under this TO Tariff, such Party shall (i) immediately notify the other Parties in writing of the occurrence of such Uncontrollable Force, (ii) not be entitled to suspend performance in any greater scope or longer duration than is required by the Uncontrollable Force, (iii) use its best efforts to mitigate the effects of such Uncontrollable Force, remedy its inability to perform, and resume full performance hereunder, (iv) keep the other Parties apprised of such efforts on a continual basis and (v) provide written notice of the resumption of performance hereunder. Notwithstanding any of the foregoing, the settlement of any strike, lockout, or labor dispute constituting an Uncontrollable Force shall be within the sole discretion of the Party to this TO Tariff involved in such strike, lockout, or labor dispute and the requirement that a Party must use its best efforts to remedy the cause of the Uncontrollable Force and mitigate its effects and resume full performance hereunder shall not apply to strikes, lockouts, or labor disputes. No Party will be considered in default as to any obligation under this TO Tariff if prevented from fulfilling the obligation due to the occurrence of an Uncontrollable Force.
11.2. Indemnification. A Market Participant shall at all times indemnify, defend, and save the Participating TO harmless from any and all damages, losses, claims,
PDF page 197
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
(including claims and actions relating to injury or to death of any person or damage to property), demands, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the Participating TO's performance of its obligations under this TO Tariff on behalf of a Market Participant, except in cases of negligence or intentional wrongdoing by the Participating TO.
12. Regulatory Filings. Nothing contained herein shall be construed as affecting, in any way, the right of DCRT to unilaterally make application to FERC as it deems necessary and appropriate to recover its TRR, or for a change in its terms and conditions, including changes in rate methodology, or for a change in designation of transmission Entitlements to be placed under the CAISO’s control, pursuant to the applicable FERC rules, regulations, policies, and governing statutes.
13. Miscellaneous.
13.1. Notices. Any notices, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person,
(ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return electronic facsimile if sent by facsimile, or (iv) upon delivery if delivered by prepaid commercial courier service, in each case addressed to a Party at the address set forth in Appendix II. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix II to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.
13.2. Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver.
13.3. Confidentiality.
13.3.1. Maintaining Confidentiality if Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the
documents, data, and information provided to it by any other Party that such Party may designate as confidential, provided, however, that the information will not be held confidential by the receiving Party if (1) the designating Party is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory
PDF page 198
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
requirements, or (2) the information becomes available to the Public on a non-confidential basis (other than from the receiving Party).
13.3.2. Disclosure of Confidential Information. Notwithstanding anything in this Section 11.3.2 to the contrary, if any Party is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to this Section 11.3.2, the Party may disclose such information; provided, however, that as soon as such Party learns of the disclosure requirement and prior to making such disclosure, such Party shall notify the affected Party or Parties of the requirement and the terms thereof. The affected Party or Parties may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Party shall cooperate with such affected Party or Parties to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Party shall cooperate with the affected Parties to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure.
13.4. Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.
13.5. Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.
13.6. Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of each Party shall be preserved until satisfied.
13.7. Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.
PDF page 199
DCR Transmission, L.L.C.
FERC FPA Transmission Tariff 2.0.0
Effective: 12/31/9998
13.8. Appendices Incorporated. The appendices to this TO Tariff are attached to this TO Tariff and are incorporated by reference as if fully set forth herein. 13.9. Consistency with CAISO Tariff. This TO Tariff is intended to be consistent with the CAISO Tariff, and, if necessary, shall be amended to conform with any changes authorized or required in any final order in a FERC proceeding mandating such changes in the CAISO Tariff.
13.10. Disputes. Except as limited by law, the CAISO ADR Procedures shall apply to all disputes between parties which arise under this TO Tariff or under or in respect of the proposed terms and conditions of a Facilities Study Agreement, System Impact Study Agreement or Expedited Service Agreement. The CAISO ADR Procedures set forth in Section 13 of the CAISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.
PDF page 200
APPENDIX IV
Large Load Interconnection Process and Timeline
PDF page 201
2
Appendix IV
to the DCRT TO Tariff
Large Load Interconnection Process and Timeline
1.1
Applicability. This Appendix IV shall govern all requests for Interconnection submitted by Large Load Interconnection Customers seeking to interconnect a Large Load directly to the Participating TO’s Transmission System. Participating TO shall coordinate with the CAISO to implement the interconnection of a Large Load as needed pursuant to Section 4.3 to this Appendix IV. Coordination with the CAISO pursuant to Section 4.3 of this Appendix IV may require that Participating TO, Large Load Interconnection Customer and the CAISO negotiate revised deadlines for the processing of the Large Load Interconnection Customer’s interconnection request. Such revised deadlines will be included in the Large Load Interconnection Customer’s Large Load System Impact Study Agreement and Large Load Facilities Study Agreement included with these procedures as Attachments 1 and 2 to this Appendix IV, respectively.
1.2
Application Required. A Large Load Interconnection Customer shall submit a written Large Load Interconnection Application that provides the information required in Section 1.4 to this Appendix IV. The Participating TO shall time-stamp the application to establish study priority and send a copy to any other transmission providers whose transmission facilities potentially may be impacted by the interconnection of the Large Load Interconnection Customer’s Large Load based on Participating TO’s review of the application. Participating TO will also provide the Large Load Interconnection Customer’s application to the CAISO pursuant to Section 4.3.
1.3
Process Overview. Participating TO’s processing of a Large Load Interconnection Application will proceed in four stages: (1) Sufficiency Review of the Large Load Interconnection Application; (2) Large Load System Impact Study; (3), Large Load Facilities Study; and (4) negotiation of a Large Load Interconnection Agreement based on the pro forma agreement provided as Attachment 3 to this Appendix IV. In the first stage, Participating TO will review the Large Load Interconnection Application for completeness and sufficiency of the provided information, verify the submitted information, and provide an opportunity to cure any deficiencies found. In the second phase, Participating TO will execute the Large Load System Impact Study Agreement included as Attachment 1 to this Appendix IV with the Large Load Interconnection Customer; perform the Large Load System Impact Study; submit the study results to the Large Load Interconnection Customer; and conduct a study review meeting with the Large Load Interconnection Customer. In the third phase, Participating TO will execute the Large Load Facilities Study Agreement included as Attachment 2 to this Appendix IV and Participating TO will perform the Large Load Facilities Study to address detailed engineering design; submit the study results to the Large Load Interconnection Customer; and conduct a final study review meeting with the Large Load Interconnection Customer. In the fourth phase, Participating TO will negotiate and execute a Large Load Interconnection Agreement with the Large Load
PDF page 202
3
Interconnection Customer. Participating TO will coordinate with the Large Load Interconnection Customer to facilitate any studies required to determine the impact of the Large Load Interconnection Application on Affected Systems. 1.4
Interconnection Application Contents. A Large Load Interconnection Application from a Large Load Interconnection Customer shall provide the following:
(i) The identity, address, telephone number, and email address for the contacts for the entity requesting Interconnection for the relevant Large Load;
(ii) A signed copy of a Large Load System Impact Study Agreement, ready for execution by Participating TO;
(iii) At least three (3) dates/times the Large Load Interconnection Customer is available to meet with Participating TO within one (1) week of the Large Load Interconnection Application’s submission;
(iv) The Point(s) of Interconnection to the Participating TO’s system contemplated by the applicant;
(v) The resultant (or new) maximum amount of Interconnection capacity contemplated by the Large Load Interconnection Customer;
(vi) The proposed date for energizing the Large Load and the term of Large Load Interconnection Service;
(vii) The electrical location of the source of the power (if known) to be transmitted pursuant to the Large Load Interconnection Customer’s request for Interconnection. If the source of the power is not known, a system purchase will be assumed;
(viii) The electrical location of the ultimate load (if known). If the location of the load is not known, a system sale will be assumed;
(ix) Energization plans and expected in-service dates;
(x) The following physical characteristics of the prospective Large Load, sufficient to characterize expected load behavior, including: a. Load type
b. Variable or flat load designation
c. Expected hourly operating profile
d. Location of service
e. Point of delivery
PDF page 203
4
f. Connected capacity
g. Any market participation status or expected participation in demand response programs
h. Maximum operating demand
i. Minimum operating demand
j. Curtailment capability
k. Expected hourly flexibility capability
l. Ramp-up capability
m. Ramp-down capability
n. Preliminary site layout
o. Modelling inputs for steady-state and transient studies p. Location, size, and connection of every transformer and large motor q. Evidence of site control
r. Attestation by officer of accuracy of submitted Large Load Interconnection Application
(xi) Co-located resource information, if applicable:
a. Presence of co-located generation
b. Whether the resource will be fully Behind-the-Meter or may export to the CAISO Controlled Grid
c. Resource type
d. Nameplate capacity
e. Minimum and maximum operating levels
f. Market participation status
g. Associated status resource identifiers
h. All information required by the Participating TO and, as applicable, the CAISO in the Large Generator Interconnection Application
PDF page 204
5
(xii) Such other information as the Participating TO reasonably requires to process the Large Load Interconnection Application.
1.4.2 Large Load Interconnection Application Fee. A Large Load Interconnection Customer shall submit a non-refundable application fee of two-hundred- thousand dollars ($200,000).
1.4.3 Amendment to Completed Large Load Interconnection Application. A Large Load Interconnection Customer shall be limited to only amending its Large Load Interconnection Application once. Additional amendments will be at Participating TO’s discretion, to be permitted on a not unduly discriminatory basis and without undue preference or advantage, and Participating TO’s agreement for Large Load Interconnection Customer to make additional amendment shall not be unreasonably withheld. Such amendment shall occur no later than ten (10) Business Days after the date the Participating TO tenders the Large Load System Impact Study report. Specifically, a Large Load Interconnection Customer may submit an amendment to its Interconnection Application to reflect a revised configuration for its Large Load. In the event a Large Load Interconnection Customer amends its Large Load Interconnection Application, it will be responsible for any additional study costs that result from that amendment.
1.5
Withdrawal of Large Load Interconnection Application. A Large Load Interconnection Customer may withdraw its Large Load Interconnection Application at any time by providing notice to Participating TO in writing. A withdrawal shall not result in the refund of any previously paid application fees.
2. Application Processing and Timeline. The Large Load Interconnection Application will be processed under the procedures and timeline described below:
2.1
Sufficiency Review. Within five (5) Business Days of receipt of a Large Load Interconnection Application and application fee, Participating TO will complete its sufficiency review of the Large Load Interconnection Application and provide the Large Load Interconnection Customer with either a notice of sufficiency or a deficiency letter for the Large Load Interconnection Application, via email. A deficiency letter will specify the necessary changes to meet the Large Load Interconnection Application requirements.
2.1.1 Cure of Deficiency. If a Large Load Interconnection Customer receives a deficiency letter, it will have three (3) Business Days to re-submit a revised Large Load Interconnection Application curing the deficiencies identified in the deficiency letter.
2.1.2 Review of Resubmitted Large Load Interconnection Application. If the Large Load Interconnection Customer receives a deficiency letter and timely re-submits a revised Large Load Interconnection Application, within five (5) calendar days, Participating TO will conduct another sufficiency review of the
PDF page 205
6
resubmitted application and notify the Large Load Interconnection Customer of the sufficiency or deficiency of the resubmitted application. A second finding of deficiency will result in the application being deemed withdrawn. 2.2
Large Load System Impact Study. Within seven (7) calendar days of approving a completed Large Load Interconnection Application, Participating TO and Large Load Interconnection Customer shall execute the Large Load System Impact Study Agreement included in the initial Large Load Interconnection Application and conduct an initial Scoping Meeting. The system impact study will consist of a short circuit analysis, a stability analysis, a power flow analysis, and any other studies that are deemed necessary. The system impact study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested Large Load Interconnection Service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the Interconnection. The Large Load System Impact Study shall provide a list of Large Load Interconnection Facilities and Network Upgrades that are required to interconnect the relevant Large Load and provide a non-binding good faith estimate of cost responsibility and the amount of construction time required. The Large Load System Impact Study shall also identify any Affected Systems that Participating TO must coordinate with in order to interconnect the Large Load Interconnection Customer. 2.2.1 Large Load System Impact Study Fee. If the Large Load System Impact Study costs exceed the Large Load Interconnection Application Fee, the Large Load Interconnection Customer shall reimburse the Participating TO for the actual study costs that exceed the initial application fee of two-hundred- thousand dollars ($200,000).
2.2.2 Large Load System Impact Study Timeline. Within thirty (30) calendar days of execution of the Large Load System Impact Study Agreement, Participating TO, using reasonable efforts, will perform the Large Load System Impact Study, prepare and submit a study report to the Large Load Interconnection Customer, and provide the Large Load Interconnection Customer with an initial draft Large Load Interconnection Agreement reflecting the results of the Large Load System Impact Study. This draft Large Load Interconnection Agreement will be revised based on the Large Load Facilities Study described in Section 2.3. Within seven calendar (7) days of submitting the Large Load System Impact Study report to the Large Load Interconnection Customer, using reasonable efforts, Participating TO will schedule a meeting with the Large Load Interconnection Customer and the CAISO, as applicable pursuant to Section 4.3, to review the results of the Large Load System Impact Study. 2.3
Large Load Facilities Study. The Large Load Facilities Study will be used to create the detailed design of the interconnection facilities used to interconnect the Large Load to the Participating TO’s facilities, based on the findings of the Large Load System Impact Study.
PDF page 206
7
2.3.1 Large Load Facilities Study Timeline. The Large Load Interconnection Customer will have seven (7) calendar days after receiving the Large Load System Impact Study results to execute a Large Load Facilities Study Agreement with Participating TO or its Large Load Interconnection Application will be deemed withdrawn. Within thirty (30) calendar days of execution of the Large Load Facilities Study Agreement, using reasonable efforts, Participating TO will conduct the Large Load Facilities Study and submit the study report to the Large Load Interconnection Customer.
2.3.2 Large Load Facilities Study Fee. The Large Load Interconnection Customer shall submit a non-refundable study fee of two-hundred thousand dollars ($200,000) upon execution of the Large Load Facilities Study Agreement. If the Large Load Facilities Study costs exceed the study fee, the Large Load Interconnection Customer shall promptly reimburse the Participating TO for the actual study costs that exceed the default study fee.
2.4
Consideration of Alternative Transmission Technologies. The Large Load System Impact Study and Large Load Facilities Study will consider both traditional Network Upgrades and Alternative Transmission Technologies when evaluating options for reliably interconnecting the Large Load. Alternative Transmission Technologies to be studied will include, as applicable, static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, and tower lifting. The Participating TO’s studies, will select the best available transmission solution to interconnect Large Load. If a traditional Network Upgrade solution is selected instead of Alternative Transmission Technologies, the Participating TO will explain why Alternative Transmission Technologies are not feasible (i.e., would not resolve reliability violations identified or meet the relevant planning criteria) or would not result in lower costs or a faster timeline for accommodating the interconnection of the Large Load.
2.5
Large Load Interconnection Agreement.
2.5.1 Large Load Interconnection Agreement Timeline. Within sixty (60) calendar days of receipt of the Large Load Facilities Study report, Large Load Interconnection Customer shall execute a Large Load Interconnection Agreement with Participating TO or request that an unexecuted Large Load Interconnection Agreement be filed with FERC for resolution of any dispute over the terms of the Large Load Interconnection Agreement, or the Large Load Interconnection Application will be deemed withdrawn.
2.5.2 Large Load Interconnection Agreement Signatories and Terms. The Large Load Interconnection Agreement will be negotiated between the Large Load Interconnection Customer and Participating TO, with, the CAISO also signing, as applicable pursuant to Section 4.3. The Large Load Interconnection Agreement will obligate the Large Load Interconnection Customer to pay the cost of interconnecting the Large Load to the Participating TO’s system,
PDF page 207
8
including procurement, construction, and commissioning of the interconnection facilities based on the terms within the Large Load Interconnection Agreement. Participating TO will not perform any procurement or construction associated with interconnecting the Large Load until the Large Load Interconnection Agreement is executed and all funding identified in the Large Load Interconnection Agreement is received. The Large Load Interconnection Agreement will address reimbursement to the Large Load Interconnection Customer for any Network Upgrades.
2.5.3 Construction of Interconnection Facilities. Based on the designs produced by the Large Load Facilities Study, Participating TO will procure necessary equipment, and construct the interconnection facilities required to interconnect the Large Load to the Participating TO’s system.
2.6
Interconnection Financial Security Agreements. A Large Load Interconnection Customer intending to proceed with interconnection shall post financial security according to the timelines identified in Attachment 4 to this Appendix IV, or its application will be deemed withdrawn.
2.6.1 Initial Postings. Within ninety (90) calendar days of receipt of the Facilities Study report, a Large Load Interconnection Customer shall execute separate Interconnection Financial Security Agreements and post financial security for each of: 1) its assigned Network Upgrades; and 2) its Interconnection Facilities. 2.6.2 Second Postings. Second postings and amended Interconnection Financial Security Agreements are required no later than thirty (30) calendar days prior to the date on which the Facilities Study report provides that such amounts will be needed to fund long lead time equipment procurement as part of the Construction Activities (as defined in Attachment 4) for the Network Upgrades (as defined in Attachment 3) or the Participating TO’s Interconnection Facilities, whichever is earlier.
2.6.3 Third Postings. No later than thirty (30) calendar days after the date on which the Participating TO provides notice that Participating TO is obligated to provide security needed to fund any additional obligations for Network Upgrades (as defined in Attachment 3) or Participating TO’s Interconnection Facilities on behalf of the Large Load Interconnection Customer, whichever is earlier, the Large Load Interconnection Customer shall modify the two separate Interconnection Financial Security instruments.
3. Flexible Interim Load Interconnection Service.
3.1
Availability of Flexible Interim Load Interconnection Service. If a Large Load System Impact Study conducted for a Large Load Interconnection Customer shows that the Large Load cannot be reliably served at its full requested demand until certain Network Upgrades are completed, Participating TO will, at the Large Load Interconnection Customer’s request offer FILI Service. Based on the study results,
PDF page 208
9
Participating TO, and, as applicable, the CAISO pursuant to Section 4.3, may propose a customized plan for the Large Load Interconnection Customer based on the type of constraints required to maintain Transmission System reliability. Such constraints may require flexibility in demand by the Large Load or any other conditions that Participating TO and, as applicable, the CAISO determine are necessary to maintain reliability. The Large Load Interconnection Customer may participate in the design of the FILI Service constraints. Once the required Network Upgrades necessary to serve the Large Load at its full requested demand are complete, the Large Load Interconnection Customer may elect to receive firm service. The scope of any FILI offered to the Large Load Interconnection Customer will be memorialized in the Large Load Interconnection Agreement.
4. Participating TO Obligation to Provide Interconnection Service.
4.1
Interconnection to Transmission System. Interconnection Services for Large Loads must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, the Participating TO’s reliability criteria and, as applicable, the CAISO reliability criteria for the CAISO Controlled Grid. The Participating TO will not provide Large Load Interconnection Services to the Large Load Interconnection Customer if doing so would impair reliability. 4.2
Energization. The Participating TO shall not be obligated to energize, nor shall the Large Load Interconnection Customer be entitled to have its interconnection to the Participating TO’s system energized, unless and until a Large Load Interconnection Agreement has been executed, or filed at FERC pursuant to Section 2.5.1 and becomes effective and such Large Load Interconnection Customer has demonstrated to the Participating TO’s reasonable satisfaction that it has complied with all of the requirements of the of the Participating TO’s Tariff, and, as applicable, the CAISO Tariff.
4.3
Coordination with the CAISO on Interconnection Requests. Participating TO reserves the right to coordinate with the CAISO to the extent that the interconnection of a Large Load may impact the reliability of the CAISO controlled transmission system. The potential injection of any power from a Large Load to the Participating TO’s Transmission System, including but not limited to the injection of power to the Participating TO’s Transmission System resulting from the colocation of generation with the Large Load facility, shall require that the Participating TO coordinate with the CAISO to ensure that the Large Load’s interconnection complies with the CAISO Tariff.
4.4
Coordination with Affected Systems. Participating TO will coordinate with the Large Load Interconnection Customer to facilitate any studies required to determine the impact of the Large Load Interconnection Application on Affected Systems. Participating TO may provide a copy of the Large Load System Impact Study and Large Load Facilities Study results to an Affected System Operator and the Western Electricity Coordinating Council. Requests for review and input from Affected System Operators or the Western Electricity Coordinating Council may arrive at any time prior
PDF page 209
10
to interconnection. If interconnecting the Large Load Interconnection Customer requires upgrades to any Affected Systems, Large Load Interconnection Customer must enter into a construction and reimbursement agreement with the owner of any Affected System and/or other affected owners of portions of the CAISO Controlled Grid that govern facilities built on the relevant Affected System, pursuant to the tariff or procedures of the Affected System owner.
PDF page 210
Appendix IV
Attachment 1
Large Load System Impact Study Agreement
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 211
2
Attachment 1
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
LARGE LOAD SYSTEM IMPACT STUDY AGREEMENT
[LARGE LOAD INTERCONNECTION CUSTOMER]
AND
DCR TRANSMISSION, L.L.C.
THIS AGREEMENT is made and entered into this day of ___________, 20__ by and between ___________, a ___________ organized and existing under the laws of the State/Commonwealth of___________, (“Large Load Interconnection Customer”) and DCR Transmission, L.L.C., a limited liability company, organized and existing under the laws of the State of Delaware, (“DCRT” or “Participating TO”). The Large Load Interconnection Customer and DCRT each may be referred to as a “Party,” or collectively as the “Parties.” RECITALS
WHEREAS, Large Load Interconnection Customer is proposing to develop a Large Load Facility or Large Load Facility expansion to an existing Large Load Facility consistent with the Large Load Interconnection Application submitted by the Large Load Interconnection Customer dated
; and
WHEREAS, the Large Load Interconnection Customer desires to interconnect the Large Load Facility with the California Independent System Operator Corporation (“CAISO”) Controlled Grid pursuant to the Large Load Interconnection Process; and
WHEREAS, the Large Load Interconnection Customer has requested DCRT to conduct or cause to be performed a Large Load System Impact Study to assess the system impact of interconnecting the Large Load Facility to the CAISO Controlled Grid and to specify and estimate the cost of the equipment, engineering, procurement and construction work needed on the Participating TO’s electric system in accordance with Good Utility Practice to physically and electrically connect the Large Load Facility to the CAISO Controlled Grid; NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agree as follows:
1.0
When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in DCRT’s Federal Energy Regulatory Commission (“FERC”)-approved Large Load Interconnection Process in the DCRT Tariff, or the Master Definitions Supplement, Appendix A to the CAISO Tariff, as
applicable.
PDF page 212
3
2.0
The Large Load Interconnection Customer elects and DCRT shall conduct or cause to be performed a Large Load System Impact Study in accordance with the DCRT Tariff, Appendix IV.
3.0
The scope of the applicable Large Load System Impact Study shall be subject to the assumptions set forth in Appendices A and B to this Agreement. 4.0
The Large Load System Impact Study will be based upon the technical information provided by the Large Load Interconnection Customer in the Large Load Interconnection Application, as may be modified as the result of the Scoping Meeting, subject to any modifications in accordance with Section 1.4.2 of the DCRT Tariff, Appendix IV and modifications to the proposed Commercial Operation Date of the Large Load Facility permitted by the Large Load Interconnection Process. DCRT reserves the right to request additional technical information from the Large Load Interconnection Customer as may reasonably become necessary consistent with Good Utility Practice during the course of the Large Load System Impact Study. If the Large Load Interconnection Customer modifies its designated Point of Interconnection, Large Load Interconnection Application, or the technical information provided therein is modified, the Large Load System Impact Study may be modified as specified in the DCRT Tariff, Appendix IV.
5.0
The Large Load System Impact Study report shall provide the information specified in the Large Load Interconnection Process.
6.0
The Large Load Interconnection Customer shall provide a Large Load Interconnection Application fee for the performance of the Large Load System Impact Study in accordance with the provisions of Section 1.4.1 of the Large Load Interconnection Process.
7.0
Pursuant to Section 4.4 of the Large Load Interconnection Process, DCRT will coordinate with the Large Load Interconnection Customer to facilitate any studies required to determine the impact of the Large Load Interconnection Application on Affected Systems. DCRT may provide a copy of the system impact and facilities study results to an Affected System Operator and the Western Electricity Coordinating Council. Requests for review and input from Affected System Operators or the Western Electricity Coordinating Council may arrive at any time prior to interconnection.
8.0
Substantial portions of technical data and assumptions used to perform the Large Load System Impact Study, such as system conditions, existing and planned generation, and unit modeling, may change after DCRT provides the Large Load System Impact Study results to the Large Load Interconnection Customer. Large Load System Impact Study results will reflect available data at the time DCRT provides the system impact and facilities study report to the Large Load Interconnection Customer. DCRT shall not be responsible for any additional costs, including, without limitation, costs of new or additional facilities, system upgrades,
PDF page 213
4
or schedule changes, that may be incurred by the Large Load Interconnection Customer as a result of changes in such data and assumptions.
9.0
DCRT shall maintain records and accounts of all costs incurred in performing the Large Load System Impact Study in sufficient detail to allow verification of all costs incurred, including associated overheads. The Large Load Interconnection Customer shall have the right, upon reasonable notice, within a reasonable time at DCRT’s offices and at its own expense, to audit DCRT’s records as necessary and as appropriate in order to verify costs incurred by DCRT. Any audit requested by the Large Load Interconnection Customer shall be completed, and written notice of any audit dispute provided to DCRT representative, within one hundred eighty (180) calendar days following receipt by the Large Load Interconnection Customer of DCRT’s notification of the final costs of the Interconnection Study. 10.0 In accordance with Section 1.5 of the Large Load Interconnection Process, the Large Load Interconnection Customer may withdraw its Large Load
Interconnection Application at any time by written notice to DCRT. Within ninety (90) days of receiving the withdrawal notice of the Large Load Interconnection Application, DCRT will refund the unused amount of the Large Load Interconnection Study Application fee to the Large Load Interconnection Customer.
11.0 This Agreement shall become effective upon the date the fully executed Agreement is submitted to the Large Load Interconnection Customer by DCRT.
12.0
Miscellaneous.
12.1
Dispute Resolution. Any dispute, or assertion of a claim, arising out of or in connection with this Agreement, shall be resolved in accordance with Section 13.10 of the DCRT Tariff.
12.2
Confidentiality. Confidential Information shall be treated in accordance with Section 13.3 of the DCRT Tariff.
12.3
Binding Effect. This Agreement and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto.
12.4
Conflicts. In the event of a conflict between the body of this Agreement and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this Agreement shall prevail and be deemed the final intent of the Parties. 12.5
Rules of Interpretation. This Agreement, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person’s successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this Agreement, and reference to a person in a particular
PDF page 214
5
capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this Agreement), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof; (4) reference to any applicable laws and regulations means such applicable laws and regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article or Section of this Agreement or such Appendix to this Agreement, as the case may be; (6) “hereunder”, “hereof”, “herein”, “hereto” and words of similar import shall be deemed references to this Agreement as a whole and not to any particular Article, Section, or other provision hereof or thereof; (7) “including” (and with correlative meaning “include”) means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, “from” means “from and including”, “to” means “to but excluding” and “through” means “through and including”.
12.6
Entire Agreement. This Agreement, including all Appendices and Schedules attached hereto, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, any Party’ s compliance with its obligations under this Agreement.
12.7
No Third-Party Beneficiaries. This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.
12.8
Waiver. The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party. Any waiver at any time by either Party of its rights with respect to this Agreement shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this Agreement. Termination or default of this Agreement for any reason by the Large Load Interconnection Customer shall not constitute a waiver of the Large Load Interconnection Customer’s legal rights to obtain an interconnection from the Participating TO. Any waiver of this Agreement shall, if requested, be provided in writing. Any waivers at any time by any Party of its rights with respect to any default under this Agreement, or with respect to any other matter arising in connection with this
PDF page 215
6
Agreement, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this Agreement. Any delay, short of the statutory period of limitations, in asserting or enforcing any right under this Agreement shall not constitute or be deemed a waiver of such right. 12.9
Headings. The descriptive headings of the various Articles and Sections of this Agreement have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this Agreement. 12.10 Multiple Counterparts. This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.
12.11 Amendment. The Parties may by mutual agreement amend this Agreement by a written instrument duly executed by both of the Parties.
12.12 Modification by the Parties. The Parties may by mutual agreement amend the Appendices to this Agreement by a written instrument duly executed by both of the Parties. Such amendment shall become effective and a part of this Agreement upon satisfaction of all applicable laws and regulations.
12.13 Reservation of Rights. DCRT shall have the right to make a unilateral filing with FERC to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under section 205 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder, and Large Load Interconnection Customer shall have the right to make a unilateral filing with FERC to modify this Agreement pursuant to section 206 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by another Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this Agreement shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.
12.14 No Partnership. This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon any Party. No Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, another Party.
12.15 Assignment. This Agreement may be assigned by a Party only with the written consent of the other Party; provided that a Party may assign this Agreement without the consent of the other Party to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement; and provided further
PDF page 216
7
that the Large Load Interconnection Customer shall have the right to assign this Agreement, without the consent of the other Party, for collateral security purposes to aid in providing financing for the Large Load Facility, provided that the Large Load Interconnection Customer will require any secured party, trustee or mortgagee to notify the other Party of any such assignment. Any financing arrangement entered into by the Large Load Interconnection Customer pursuant to this Section will provide that prior to or upon the exercise of the secured party’s, trustee’s or mortgagee’s assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify the other Party of the date and particulars of any such exercise of assignment right(s). Any attempted assignment that violates this Section is void and ineffective. Any assignment under this Agreement shall not relieve a Party of its obligations, nor shall a Party’s obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed. IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. DCR Transmission, L.L.C.
By:
Printed Name:
Title:
Date:
[Insert name of the Large Load Interconnection Customer]
By:
Printed Name:
Title:
Date:
PDF page 217
Appendix A
ASSUMPTIONS USED IN CONDUCTING THE
SYSTEM IMPACT STUDY
The system impact and facilities study will be based upon the information set forth in the Large Load Interconnection Application and agreed upon in the Scoping Meeting held on __________, subject to any modifications in accordance with Section 1.4.2 of the Large Load Interconnection Process, and the following assumptions:
Designation of Point of Interconnection and configuration to be studied. [Fill out with application requirements from Appendix IV]
PDF page 218
Appendix B
Data Form, Pre-System Impact
DATA FORM TO BE PROVIDED BY THE LARGE LOAD IS APPLICANT
PRIOR TO COMMENCEMENT OF THE LARGE LOAD SYSTEM IMPACT STUDY
Large Load Facility size (MW):
Provide two (2) copies of this completed form and other required plans and diagrams in accordance with Section 1.2 of the Large Load Interconnection Process.
Provide location plan and one-line diagram of the plant and station facilities. For staged projects, please indicate future facility plans, transmission circuits, etc.
One set of metering is required for each generation connection to the new bus or existing CAISO Controlled Grid station. Number of grid connections:
On the one line indicate the demand attached at each metering location. (Maximum load on CT/PT) On the one-line indicate the location of auxiliary power. (Minimum load on CT/PT) Will an alternate source of auxiliary power be available during CT/PT maintenance? Yes No Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant load?
Yes
No
(Please indicate on one-line).
What type of control system or PLC will be located at the Large Load Interconnection Customer’s Large Load Facility?
What protocol does the control system or PLC use?
Please provide a 7.5-minute quadrangle of the site. Sketch the facility, station, transmission line, and property line.
Physical dimensions of the proposed interconnection station:
Bus length from load to interconnection station:
Line length from interconnection station to the Participating TO’s transmission line. Tower number observed in the field. (Painted on tower leg)*:
Number of third-party easements required for transmission lines*:
PDF page 219
* To be completed in coordination with the Participating TO or the CAISO. Local service provider for auxiliary and other power:
Please provide proposed schedule dates:
Environmental survey start:
Environmental impact report submittal:
Procurement of project equipment:
Begin Construction Date:
In-Service Date:
Trial Operation Date:
Commercial Operation Date:
Requested Level of Interconnection Service: Choose one of the following:
Firm Service Only
Flexible Interim Load Interconnection (FILI) Service, as applicable Please provide any additional modification request pursuant to Section 1.4.2 of Appendix IV of the DCRT Tariff.
PDF page 220
Appendix IV
Attachment 2
Large Load Facilities Study Agreement
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 221
2
Attachment 2
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
LARGE LOAD FACILITIES STUDY AGREEMENT AND DATA FORM TO BE
PROVIDED BY THE LARGE LOAD INTERCONNECTION STUDY APPLICANT
PRIOR TO COMMENCEMENT OF THE INTERCONNECTION FACILITIES STUDY
[LARGE LOAD INTERCONNECTION CUSTOMER]
AND
DCR TRANSMISSION, L.L.C.
THIS AGREEMENT is made and entered into this day of ___________, 20__ by and between ___________, a ___________ organized and existing under the laws of the State/Commonwealth of___________, (“Large Load Interconnection Customer”) and DCR Transmission, L.L.C., a limited liability company, organized and existing under the laws of the State of Delaware, (“DCRT”, or “Participating TO”). The Large Load Interconnection Customer and DCRT each may be referred to as a “Party,” or collectively as the “Parties.” RECITALS
WHEREAS, Large Load Interconnection Customer is proposing to develop a Large Load Facility or Large Load Facility expansion to an existing Large Load Facility consistent with the Large Load Interconnection Application submitted by the Large Load Interconnection Customer dated
; and
WHEREAS, the Large Load Interconnection Customer desires to interconnect the Large Load Facility with the CAISO Controlled Grid pursuant to the Large Load Interconnection Process; and
WHEREAS, the Large Load Interconnection Customer has requested DCRT to conduct or cause to be performed a Large Load Facilities Study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed on the Participating TO’s electric system in accordance with Good Utility Practice to physically and electrically connect the Large Load Facility to the CAISO Controlled Grid;
NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein the Parties agree as follows:
1.0
When used in this Agreement, with initial capitalization, the terms specified shall have the meanings indicated in DCRT’s Federal Energy Regulatory Commission (“FERC”)- approved Large Load Interconnection Process in DCRT Tariff, Appendix IV thereto, or the Master Definitions Supplement, Appendix A to the CAISO Tariff, as applicable.
2.0
The Large Load Interconnection Customer elects and DCRT shall conduct or cause to be performed a Large Load Facilities Study in accordance with the DCRT Tariff, Appendix IV.
PDF page 222
3
3.0
The scope of the Large Load Facilities Study will be subject to the assumptions set forth in and the data provided with this Agreement.
4.0
The Large Load Facilities Study Report: (i) will provide a description, estimated cost of (consistent with Attachment A), schedule for required facilities to interconnect the Large Load Facility to the CAISO Controlled Grid; (ii) will address the issues identified in the voltage, short circuit, stability, and power flow studied conducted as a part of the Large Load System Impact Study; and (iii) will reflect the evaluation of alternative transmission technologies in accordance with Section 2.4 of the DCRT Tariff, Appendix IV, including, if traditional Network Upgrades are selected instead of alternative transmission technologies, an explanation of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline.
5.0
Large Load Interconnection Customer will provide a Large Load Facilities Study fee for the performance of the Large Load Facilities Study in accordance with the provisions of Section 2.3.2 of the Large Load Interconnection Process. The time for completion of the Large Load Facilities Study is specified in the Large Load Interconnection Process in DCRT Tariff, Appendix IV.
6.0
Miscellaneous.
6.1
Dispute Resolution. Any dispute, or assertion of a claim, arising out of or in connection with this Agreement, shall be resolved in accordance with Section 13.10 of the DCRT Tariff.
6.2
Confidentiality. Confidential Information shall be treated in accordance with
Section 13.3 of the DCRT Tariff.
6.3
Binding Effect. This Agreement and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto. 6.4
Conflicts. In the event of a conflict between the body of this Agreement and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this Agreement shall prevail and be deemed the final intent of the Parties.
6.5
Rules of Interpretation. This Agreement, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person’s successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this Agreement, and reference to a person in a particular capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this Agreement), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof;
(4) reference to any applicable laws and regulations means such applicable laws and regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article or Section of this Agreement or such Appendix to this Agreement, as the case may be; (6) “hereunder”, “hereof”,
PDF page 223
4
“herein”, “hereto” and words of similar import shall be deemed references to this Agreement as a whole and not to any particular Article, Section, or other provision hereof or thereof; (7) “including” (and with correlative meaning “include”) means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, “from” means “from and including”, “to” means “to but excluding” and “through” means “through and including”.
6.6
Entire Agreement. This Agreement, including all Appendices and Schedules
attached hereto, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, any Party’s compliance with its obligations under this Agreement.
6.7
No Third-Party Beneficiaries. This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns. 6.8
Waiver. The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.
Any waiver at any time by either Party of its rights with respect to this Agreement shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this Agreement. Termination or default of this Agreement for any reason by the Large Load Interconnection Customer shall not constitute a waiver of the Large Load Interconnection Customer’s legal rights to obtain an interconnection from the Participating TO. Any waiver of this Agreement shall, if requested, be provided in writing.
Any waivers at any time by any Party of its rights with respect to any default under this Agreement, or with respect to any other matter arising in connection with this Agreement, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this Agreement. Any delay, short of the statutory period of limitations, in asserting or enforcing any right under this Agreement shall not constitute or be deemed a waiver of such right. 6.9
Headings. The descriptive headings of the various Articles and Sections of this Agreement have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this Agreement.
6.10
Multiple Counterparts. This Agreement may be executed in two (2) or more
counterparts, each of which is deemed an original but all constitute one and the same instrument. 6.11
Amendment. The Parties may by mutual agreement amend this Agreement by a
written instrument duly executed by both of the Parties.
PDF page 224
5
6.12
Modification by the Parties. The Parties may by mutual agreement amend the
Appendices to this Agreement by a written instrument duly executed by both of the Parties. Such amendment shall become effective and a part of this Agreement upon satisfaction of all applicable laws and regulations.
6.13
Reservation of Rights. DCRT shall have the right to make a unilateral filing with FERC to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under section 205 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder, and Large Load Interconnection Customer shall have the right to make a unilateral filing with FERC to modify this Agreement pursuant to section 206 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by another Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this Agreement shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.
6.14
No Partnership. This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon any Party. No Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, another Party.
6.15
Assignment. This Agreement may be assigned by a Party only with the written
consent of the other Party; provided that a Party may assign this Agreement without the consent of the other Party to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement; and provided further that the Large Load Interconnection Customer shall have the right to assign this Agreement, without the consent of the other Party, for collateral security purposes to aid in providing financing for the Large Load Facility, provided that the Large Load Interconnection Customer will require any secured party, trustee or mortgagee to notify the other Party of any such assignment. Any financing arrangement entered into by the Large Load Interconnection Customer pursuant to this Section will provide that prior to or upon the exercise of the secured party’s, trustee’s or mortgagee’s assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify the other Party of the date and particulars of any such exercise of assignment right(s). Any attempted assignment that violates this Section is void and ineffective. Any assignment under this Agreement shall not relieve a Party of its obligations, nor shall a Party’s obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.
PDF page 225
6
IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers or agents on the day and year first above written. DCR Transmission, L.L.C.
By:
Title:
Date:
Large Load Interconnection Customer
By:
Title:
Date:
PDF page 226
Appendix IV
Attachment 3
Large Load Interconnection Agreement
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 227
i
TABLE OF CONTENTS
Page
ARTICLE 1. DEFINITIONS … 2 ARTICLE 2. EFFECTIVE DATE, TERM AND TERMINATION … 8
2.1
Effective Date … 8 2.2
Term of Agreement … 8 2.3
Termination Procedures … 8 2.3.1
Written Notice … 8 2.3.2
Default … 8 2.3.3
Suspension of Work … 8 2.4
Termination Costs … 8 2.5
Disconnection … 10 2.6
Survival … 10 ARTICLE 3. REGULATORY FILINGS AND CAISO TARIFF COMPLIANCE … 10
3.1
Filing … 10 3.2
Agreement Subject to CAISO Tariff … 10 ARTICLE 4. SCOPE OF SERVICE … 10 4.1
Large Load Interconnection Service … 10 4.2
Provision of Service … 11 4.3
Performance Standards … 11 4.4
No Transmission Service … 11 ARTICLE 5. LARGE LOAD INTERCONNECT CUSTOMER’S INTERCONNECTION
FACILITIES ENGINEERING, PROCUREMENT, AND CONSTRUCTION … 11
5.1
Design Requirements … 11 5.1.1
Standard Option … 11 5.2
Liquidated Damages … 12 5.3
Reserved … 12 5.4
Equipment Procurement … 13 5.5
Construction Commencement … 13 5.6
Work Progress … 13 5.7
Information Exchange … 13 5.8
Limited Operation … 14 5.9
Large Load Interconnection Customer’s Interconnection Facilities … 14
5.9.1
Large Load Facility and Large Load Interconnection Customer’s
Interconnection Facilities Specifications … 14
5.9.2
Participating TO’s Review … 14 5.9.3
Large Load Interconnection Customer’s Interconnection Facilities
Construction … 15 5.10
Participating TO’s Interconnection Facilities Construction … 15 5.11
Access Rights … 15
PDF page 228
ii
5.12
Lands of Other Property Owners … 16 5.13
Permits … 16 5.14
Suspension … 16 5.15
Taxes … 16 5.15.1
Large Load Interconnection Customer Payments Not Taxable … 16
5.15.2
Representations And Covenants … 17 5.15.3
Indemnification for the Cost Consequence of Current Tax Liability Imposed
Upon the Participating TO … 17 5.15.4
Tax Gross-Up Amount … 18 5.15.5
Private Letter Ruling or Change or Clarification of Law … 18
5.15.6
Subsequent Taxable Events … 19 5.15.7
Contests … 19 5.15.8
Refund … 20 5.15.9
Taxes Other Than Income Taxes … 21 5.16
Tax Status … 22 ARTICLE 6. LARGE LOAD INTERCONNECTION TESTING AND INSPECTION … 22
6.1
Pre-Commercial Operation Date Testing and Modifications … 22 6.2
Post-Commercial Operation Date Testing and Modifications … 22 6.3
Right to Observe Testing … 22 6.4
Right to Inspect … 22 ARTICLE 7. METERING … 23 7.1
General … 23 7.2
Check Meters … 23 7.3
Participating TO Retail Metering … 23 ARTICLE 8. COMMUNICATIONS … 23 8.1
Large Load Interconnection Customer Obligations … 23 8.2
Remote Terminal Unit … 24 8.3
No Annexation … 24 ARTICLE 9. LARGE LOAD INTERCONNECTION CUSTOMER OPERATIONS … 24
9.1
General … 24 9.2
Participating TO Obligations … 24 9.3
Large Load Interconnection Customer Obligations … 24 9.4
Reactive Power and Primary Frequency Response … 25 9.5
Disconnection from the Grid … 25 9.6
Outages and Interruptions … 25 9.6.1
Outages … 25 9.6.1.1
Outage Authority and Coordination … 25
9.6.1.2
Outage Schedules … 25
9.6.1.3
Outage Restoration … 25
9.6.2
Interruption of Service … 26 9.6.3
Under-Frequency and Over-Frequency Conditions … 26
9.6.4
System Protection and Other Control Requirements … 27
9.6.4.1
System Protection Facilities … 27
PDF page 229
iii
9.6.5
Requirements for Protection … 28 9.6.6
Power Quality … 28 9.7
Switching and Tagging Rules … 28 9.8
Use of Interconnection Facilities by Third Parties … 29 9.8.1
Purpose of Interconnection Facilities … 29
9.8.2
Third Party Users … 29 9.9
Disturbance Analysis Data Exchange … 29 ARTICLE 10. MAINTENANCE … 29 10.1
Participating TO Obligations … 29 10.2
Large Load Interconnection Customer Obligations … 29 10.3
Coordination … 30 10.4
Secondary Systems … 30 10.5
Operating and Maintenance Expenses … 30 ARTICLE 11. PERFORMANCE OBLIGATION … 30 11.1
Large Load Interconnection Customer’s Interconnection Facilities … 30
11.2
Participating TO’s Interconnection Facilities … 30 11.3
Network Upgrades and Distribution Upgrades … 30 11.3.1
Reimbursement for Network Upgrades … 31
11.3.2
Repayment of Amounts Advanced for Network Upgrades … 31
11.3.2.1
Repayment Schedule … 31
11.3.2.2
Interest Payments and Assignment Rights … 31
11.3.2.3
Failure to Achieve Commercial Operation … 32
11.3.2.4
Accelerated Reimbursement Against Reimbursement Security … 32
11.3.3
Special Provisions for Affected Systems … 33
11.4
Provision of Interconnection Financial Security … 34 ARTICLE 12. INVOICE … 34 12.1
General … 34 12.2
Final Invoice … 34 12.3
Payment … 35 12.4
Disputes … 35 ARTICLE 13. EMERGENCIES … 36 13.1
[Reserved] … 36 13.2
Obligations … 36 13.3
Notice … 36 13.4
Immediate Action … 36 13.5
Participating TO Authority … 36 13.5.1
General … 36 13.5.2
Reduction and Disconnection … 37 13.6
Large Load Interconnection Customer Authority … 37 13.7
Limited Liability … 37 ARTICLE 14. REGULATORY REQUIREMENTS AND GOVERNING LAWS … 37
14.1
Regulatory Requirements … 37
PDF page 230
iv
14.2
Governing Law … 38 ARTICLE 15. NOTICES … 38 15.1
General … 38 15.2
Billings and Payments … 38 15.3
Alternative Forms of Notice … 38 15.4
Operations and Maintenance Notice … 38 ARTICLE 16. FORCE MAJEURE … 39 16.1
Force Majeure … 39 ARTICLE 17. DEFAULT … 39 17.1
Default … 39 17.1.1
General … 39 17.1.2
Right to Terminate … 39 ARTICLE 18. INDEMNITY, CONSEQUENTIAL DAMAGES, AND INSURANCE … 40
18.1
Indemnity … 40 18.1.1
Indemnified Party … 40 18.1.2
Indemnifying Party … 40 18.1.3
Indemnity Procedures … 40 18.2
Consequential Damages … 41 18.3
Insurance … 41 18.3.1
Workers’ Compensation Insurance and Employers’ Liability … 41
18.3.2
Commercial General Liability Insurance … 41
18.3.3
Business Automobile Liability Insurance … 42
18.3.4
Excess Liability Insurance … 42 18.3.8
[Not Used.] … 43 ARTICLE 19. ASSIGNMENT … 44 19.1
Assignment … 44 ARTICLE 20. SEVERABILITY … 44 20.1
Severability … 44 ARTICLE 21. COMPARABILITY … 44 21.1
Comparability … 44 ARTICLE 22. CONFIDENTIALITY … 45 22.1
Confidentiality … 45 22.1.1
Term … 45 22.1.2
Scope … 45 22.1.3
Release of Confidential Information … 45
22.1.4
Rights … 46 22.1.5
No Warranties … 46 22.1.6
Standard of Care … 46 22.1.7
Order of Disclosure … 46 22.1.8
Termination of Agreement … 46
PDF page 231
v
22.1.9
Remedies … 46 22.1.10
Disclosure to FERC, its Staff, or a State … 47
ARTICLE 23. ENVIRONMENTAL RELEASES … 48
ARTICLE 24. INFORMATION REQUIREMENTS … 48
24.1
Information Acquisition … 48 24.2
Information Submission by Participating TO … 48 ARTICLE 25. INFORMATION ACCESS AND AUDIT RIGHTS … 48
25.1
Information Access … 48 25.2
Reporting of Non-Force Majeure Events … 49 25.3
Audit Rights … 49 25.4
Audit Rights Periods … 49 25.4.1
Audit Rights Period for Construction-Related Accounts and Records … 49
25.4.2
Audit Rights Period for All Other Accounts and Records … 49
25.5
Audit Results … 50 ARTICLE 26. SUBCONTRACTORS … 50 26.1
General … 50 26.2
Responsibility of Principal … 50 26.3
No Limitation by Insurance … 50 ARTICLE 27. DISPUTES … 50 27.1
Submission … 50 27.2
External Arbitration Procedures … 51 27.3
Arbitration Decisions … 51 27.4
Costs … 51 ARTICLE 28. REPRESENTATIONS, WARRANTIES AND COVENANTS … 51
28.1
General … 51 28.1.1
Good Standing … 51 28.1.2
Authority … 52 28.1.3
No Conflict … 52 28.1.4
Consent and Approval … 52 ARTICLE 29. [RESERVED] … 52 ARTICLE 30. MISCELLANEOUS … 52 30.1
Binding Effect … 52 30.2
Conflicts … 52 30.3
Rules of Interpretation … 52 30.4
Entire Agreement … 53 30.5
No Third-Party Beneficiaries … 53 30.6
Waiver … 53 30.7
Headings … 53 30.8
Multiple Counterparts … 53 30.9
Amendment … 53
PDF page 232
vi
30.10 Modification by the Parties … 53 30.11 Reservation of Rights … 54 30.12 No Partnership … 54 30.13 Joint and Several Obligations … 54
Appendices
Appendix A Interconnection Facilities, Network Upgrades and Distribution Upgrades
Appendix B Milestones
Appendix C Interconnection Details
Appendix D Security Arrangements Details
Appendix E Commercial Operation Date
Appendix F Addresses for Delivery of Notices and Billings
Appendix G Large Load Interconnection Customer’s Share of Costs of Network Upgrades
for Applicable Project Group
Appendix H Co-Location and Behind-the-Meter Generation Provisions
PDF page 233
1
Attachment 3
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
LARGE LOAD INTERCONNECTION AGREEMENT
[LARGE LOAD INTERCONNECTION CUSTOMER]
AND
DCR TRANSMISSION, L.L.C.
THIS LARGE LOAD INTERCONNECTION AGREEMENT (“LLIA”) is made and
entered into this ______ day of ________________ 20___, by and among _________________, a ________________, organized and existing under the laws of the State/Commonwealth of ___________ (“Large Load Interconnection Customer” with a Large Load Facility), and DCR Transmission, L.L.C., a limited liability company, organized and existing under the laws of the State of Delaware (“DCRT” or “Participating TO”). Large Load Interconnection Customer, and Participating TO each may be referred to as a “Party” or collectively as the “Parties.”1 RECITALS
WHEREAS, the California Independent System Operator Corporation (“CAISO”) exercises Operational Control over the CAISO Controlled Grid; and
WHEREAS, the Participating TO owns, operates, and maintains the Participating TO’s Transmission System; and
WHEREAS, Large Load Interconnection Customer intends to own, lease and/or control and operate the Large Load Facility identified as a Large Load Facility in Appendices A and C to this LLIA; and
WHEREAS, Large Load Interconnection Customer, Participating TO, and, as applicable, CAISO have agreed to enter into this LLIA for the purpose of interconnecting the Large Load Facility with the Participating TO’s Transmission System; and
WHEREAS, to the extent applicable, Appendix H sets forth the applicable provisions relating to impacts (financial, operational, regulatory and otherwise) on the Large Load Interconnection Customer arising out of or related to co-located or Behind-the-Meter Generation utilizing the Large Load Interconnection Customer’s Interconnection Facilities that may necessitate CAISO becoming a signatory to this LLIA;
NOW, THEREFORE, in consideration of and subject to the mutual covenants contained herein, it is agreed:
1 The California Independent System Operator Corporation will be added as a party to this LLIA as may be required pursuant to Appendix H.
PDF page 234
2
When used in this LLIA, terms with initial capitalization that are not defined in Article 1 shall have the meanings specified in the Article in which they are used. Further, terms with initial capitalization which are used but not defined in the LLIA shall have the meaning given them in the Appendices.
Article 1. Definitions
1.1
Capitalized terms used herein that are not defined in this Article 1 are defined in the Participating TO Tariff.
Access Party shall have the meaning set forth in Article 5.11.
Affected System shall mean an electric system other than the Participating Transmission Owners Transmission System that may be affected by the proposed interconnection. Affiliate shall mean, with respect to a corporation, partnership or other entity, each such other corporation, partnership or other entity that directly or indirectly, through one or more intermediaries, controls, is controlled by, or is under common control with, such corporation, partnership or other entity.
Alternative Transmission Technologies shall mean any transmission technology other than Network Upgrades that can be used to improve the Participating TO’s Transmission System to interconnect an Interconnection Customer or Large Load Interconnection Customer, which may include static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, and tower lifting.
Applicable Laws and Regulations shall mean all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any Governmental Authority.
Applicable Reliability Council shall mean the Western Electricity Coordinating Council or its successor.
Applicable Reliability Standards shall mean the requirements and guidelines of NERC, the Applicable Reliability Council, and the Balancing Authority Area of the Participating TO’s Transmission System to which the Large Load Facility is directly connected, including requirements adopted pursuant to section 215 of the Federal Power Act.
Balancing Authority shall mean the responsible entity that integrates resource plans ahead of time, maintains load-interchange-generation balance within a Balancing Authority Area, and supports Interconnection frequency in real time.
Balancing Authority Area shall mean the collection of generation, transmission, and loads within the metered boundaries of the Balancing Authority. The Balancing Authority maintains load-resource balance within this area.
PDF page 235
3
Behind-the-Meter Generation shall mean generating facility that delivers energy to load without using the transmission system or any distribution facilities.
Breach shall mean the failure of a Party to perform or observe any material term or condition of this LLIA.
Breaching Party shall mean a Party that is in Breach of this LLIA.
Business Day shall mean Monday through Friday, excluding federal holidays and the day after Thanksgiving Day.
CAISO Controlled Grid shall mean the system of transmission lines and associated facilities of the parties to the Transmission Control Agreement that have been placed under the CAISO’s Operational Control.
CAISO Tariff shall mean the CAISO’s tariff, as filed with FERC, and as amended or supplemented from time to time, or any successor tariff.
Calendar Day shall mean any day including Saturday, Sunday or a federal holiday. Co-located Facilities shall mean both the load and generation facilities in a configuration where end-use customer load is physically connected to the facilities of an existing or planned generating facility on the generator interconnection customer’s side of the point of interconnection to the Participating TO’s Transmission System.
Commercial Operation shall mean the status of a (i) Large Load Facility or project phase at a Large Load Facility that has commenced demand for electricity, excluding electricity used during the construction of the Large Load Facility or (ii) Network Upgrade, when such upgrade is fully and finally constructed and can fully operate as intended. Commercial Operation Date of a Large Load Facility or project phase shall mean the date on which the Large Load Facility or project phase at the Large Load Facility commences Commercial Operation as agreed to by the applicable Participating TO, as applicable, the CAISO, and the Large Load Interconnection Customer pursuant to Appendices E and H to this LLIA, and in accordance with any implementation plan agreed to by the Participating TO and the CAISO for multiple individual Large Load Facilities or project phases at a Large Load Facility where a Large Load Interconnection Customer intends to establish separate Commercial Operation Dates for those Large Load Facilities or project phases.
Confidential Information shall mean any confidential, proprietary or trade secret information of a plan, specification, pattern, procedure, design, device, list, concept, policy or compilation relating to the present or planned business of a Party, which is designated as confidential by the Party supplying the information, whether conveyed orally, electronically, in writing, through inspection, or otherwise, subject to Article 22.1.2.
Default shall mean the failure of a Breaching Party to cure its Breach in accordance with Article 17 of this LLIA.
PDF page 236
4
Distribution System shall mean those non-CAISO-controlled transmission and
distribution facilities owned by the Participating TO.
Distribution Upgrades shall mean the additions, modifications, and upgrades to the Participating TO’s Distribution System. Distribution Upgrades do not include Interconnection Facilities.
Effective Date shall mean the date on which this LLIA becomes effective upon
execution by all Parties subject to acceptance by FERC, or if filed unexecuted, upon the date specified by FERC.
Emergency Condition shall mean a condition or situation, that in the judgment of the Party making the claim, is imminently likely: (1) to endanger life or property; (2) is imminently likely to cause a material adverse effect on the security of, or damage to, the Participating TO’s Transmission System, Participating TO’s Interconnection Facilities, Distribution System, or the electric systems of others to which the Participating TO’s electric system is directly connected; or (3) to cause a material adverse effect on the security of, or damage to, the Large Load Facility or Large Load Interconnection Customer’s Interconnection Facilities.
Environmental Law shall mean Applicable Laws and Regulations relating to pollution or protection of the environment or natural resources.
Federal Power Act shall mean the Federal Power Act, as amended, 16 U.S.C. §§ 791a et seq.
FERC shall mean the Federal Energy Regulatory Commission or its successor.
Flexible Interim Load Interconnection Service (FILI) shall mean the interim
interconnection service that the Participating TO may offer pursuant to Section 4.1 of the LLIP where the Large Load Facility cannot be reliably served at its full requested demand until certain Network Upgrades are completed, as further described in Section A-2 of Appendix A to this LLIA.
Force Majeure shall mean any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party’s control. A Force Majeure event does not include acts of negligence or intentional wrongdoing by the Party claiming Force Majeure.
Good Utility Practice shall mean any of the practices, methods and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be any one of a number of the optimum practices, methods, or acts to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.
PDF page 237
5
Governmental Authority shall mean any federal, state, local or other governmental, regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided, however, that such term does not include the Large Load Interconnection Customer, CAISO, Participating TO, or any Affiliate thereof. Granting Party shall have the meaning set forth in Article 5.11.
Hazardous Substances shall mean any chemicals, materials or substances defined as or included in the definition of “hazardous substances,” “hazardous wastes,” “hazardous materials,” “hazardous constituents,” “restricted hazardous materials,” “extremely hazardous substances,” “toxic substances,” “radioactive substances,” “contaminants,” “pollutants,” “toxic pollutants” or words of similar meaning and regulatory effect under any applicable Environmental Law, or any other chemical, material or substance, exposure to which is prohibited, limited or regulated by any applicable Environmental Law.
In-Service Date shall mean the date upon which the Large Load Interconnection Customer reasonably expects it will be ready to begin use of the Participating TO’s Interconnection Facilities to draw energy from the Participating Transmission Owner Transmission System.
Interconnection Facilities shall mean the Participating TO’s Interconnection Facilities and the Large Load Interconnection Customer’s Interconnection Facilities. Collectively, Interconnection Facilities include all facilities and equipment between the Large Load Facility and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Large Load Facility to the Participating TO’s Transmission System. Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, or Network Upgrades.
Interconnection Financial Security (IFS) shall mean any of the financial instruments listed in Attachment 4 to the LLIP that are posted by Large Load Interconnection Customer to finance the construction of facilities or Network Upgrades.
Interconnection Service shall mean the service provided by the Participating TO and, as applicable, CAISO associated with interconnecting the Large Load Interconnection Customer’s Interconnection Facilities to the Participating TO’s Transmission System and enabling the CAISO Controlled Grid to transmit electric energy and capacity from the CAISO Controlled Grid to the Large Load Facility at the Point of Interconnection, pursuant to the terms of this LLIA, the Participating TO’s Transmission Owner Tariff, and, as applicable, the CAISO Tariff. IRS shall mean the Internal Revenue Service.
LLIP means the process for studying load interconnection as set forth in Appendix IV of the Participating TO Tariff.
PDF page 238
6
Large Load Facility means a facility whose Point(s) of Interconnection connect to the Participating TO’s Transmission System and has a peak load of 50 megawatts (MW) or greater. Large Load Facility Point of Change of Ownership shall mean the point, as set forth in Appendix A to this LLIA, where the Large Load Interconnection Customer’s Interconnection Facilities connect to the Participating TO’s Interconnection Facilities.
Large Load Interconnection Agreement (LLIA) shall have the meaning set forth in the Preamble.
Large Load Interconnection Application shall mean an application for interconnection, in the form of Section 1.4 to the LLIP.
Large Load Interconnection Customer shall have the meaning set forth in the Preamble.
Large Load Interconnection Customer’s Interconnection Facilities shall mean all facilities and equipment, as identified in Appendix A of this LLIA, that are located between the Large Load Facility and the Participating TO’s Interconnection Facilities, including any modification, addition, or upgrades to such facilities and equipment necessary to physically and electrically interconnect the Large Load Facility to the Participating TO’s Transmission System. Large Load Interconnection Customer’s Interconnection Facilities are sole use facilities. Large Load Interconnection Studies shall mean studies performed pursuant to Appendix IV of the Participating TO Tariff, including the Large Load System Impact Study and the Large Load Facilities Study.
Loss shall mean any and all damages, losses, and claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties. Metering Equipment shall mean all metering equipment installed or to be installed for measuring the power flows to the Large Load Facility pursuant to this LLIA at the metering points, including but not limited to instrument transformers, Megawatt-hour-meters, data acquisition equipment, transducers, remote terminal unit, communications equipment, phone lines, and fiber optics.
NERC shall mean the North American Electric Reliability Corporation or its successor organization.
Network Upgrades shall be the mean the additions, modifications, and upgrades to the Participating TO’s Transmission System at or beyond the Point of Interconnection, identified in the Large Load Interconnection Studies, as identified in Appendix A and, as applicable Appendix H, to relieve constraints on the Participating TO’s Transmission System. Alternative Transmission Technologies shall be included in the definition of Network Upgrades. Operational Control shall mean the rights of the CAISO under the Transmission Control Agreement and the CAISO Tariff to direct the parties to the Transmission Control
PDF page 239
7
Agreement how to operate their transmission lines and facilities and other electric plant affecting the reliability of those lines and facilities for the purpose of affording comparable non- discriminatory transmission access and meeting applicable reliability criteria. Participating TO’s Interconnection Facilities shall mean all facilities and equipment owned, controlled or operated by the Participating TO from the Large Load Facility Point of Change of Ownership to the Point of Interconnection as identified in Appendix A to this LLIA, including any modifications, additions or upgrades to such facilities and equipment. Participating TO’s Interconnection Facilities are sole use facilities and shall not include Distribution Upgrades, or Network Upgrades.
Participating TO’s Interconnection Handbook shall mean the Participating TO’s business practice for prospective Large Load Interconnection Customers seeking interconnection under the Large Load Interconnection Process described in Appendix IV to the Participating TO’s Tariff.
Participating TO’s Tariff shall mean the currently effective tariff of DCR Transmission, L.L.C., Transmission Owner Tariff on file with FERC, as may be amended or superseded from time to time upon further filing with and acceptance by FERC.
Participating TO’s Transmission System shall mean the facilities owned and operated by the Participating TO and that have been placed under the CAISO’s Operational Control, which facilities form part of the CAISO Controlled Grid.
Party or Parties shall mean the Participating TO, CAISO, Large Load Interconnection Customer or the applicable combination of the above.
Point of Interconnection shall mean the point, as set forth in Appendix A to this LLIA, where the Interconnection Facilities connect to the Participating TO’s Transmission System. Reasonable Efforts shall mean, with respect to an action required to be attempted or taken by a Party under this LLIA, efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.
Scoping Meeting shall mean the meeting among representatives of the Large Load Interconnection Customer, the Participating TO(s), and, as applicable the CAISO and other Affected Systems, conducted for the purpose of discussing alternative interconnection options, to exchange information including any transmission data and earlier study evaluations that would be reasonably expected to impact such interconnection options, to analyze such information, and to determine the potential feasible Points of Interconnection.
System Protection Facilities shall mean the equipment, including necessary protection signal communications equipment, that protects: (1) the Participating TO’s Transmission System, Participating TO’s Interconnection Facilities, CAISO Controlled Grid, and Affected Systems from faults or other electrical disturbances occurring at the Large Load Interconnection Customer’s Interconnection Facilities; and (2) the Large Load Facility from faults or other electrical system disturbances occurring on the CAISO Controlled Grid, Participating TO’s
PDF page 240
8
Interconnection Facilities, and Affected Systems or on other delivery systems or other generating systems to which the CAISO Controlled Grid is directly connected.
Transmission Control Agreement shall mean CAISO FERC Electric Tariff No. 7. Trial Operation shall mean the period during which the Large Load Interconnection Customer is engaged in on-site test operations and commissioning of the Large Load Facility prior to Commercial Operation.
Article 2. Effective Date, Term and Termination
2.1
Effective Date. This LLIA shall become effective upon execution by all Parties subject to acceptance by FERC (if applicable), or if filed unexecuted, upon the date specified by FERC. The Participating TO shall promptly file this LLIA with FERC upon execution in accordance with Article 3.1, if required.
2.2
Term of Agreement. Subject to the provisions of Article 2.3, this LLIA shall remain in effect for a period of ten (10) years from the Effective Date (Term Specified in individual agreements to be ten (10) years or such other longer period as the Large Load Interconnection Customer may request) and shall be automatically renewed for each successive one-year period thereafter.
2.3
Termination Procedures.
2.3.1 Written Notice. This LLIA may be terminated by the Large Load Interconnection Customer after giving the Participating TO and, as applicable CAISO, ninety (90) Calendar Days advance written notice, or by the Participating TO notifying FERC after the Large Load Facility permanently ceases Commercial Operation. 2.3.2 Default. A Party may terminate this LLIA in accordance with Article 17. 2.3.3 Suspension of Work. This LLIA may be deemed terminated in accordance with Article 5.14, if applicable.
2.3.4 Notwithstanding Articles 2.3.1, 2.3.2, and 2.3.3, no termination shall become effective until the Parties have complied with all Applicable Laws and Regulations applicable to such termination, including the filing with FERC of a notice of termination of this LLIA (if applicable), which notice has been accepted for filing by FERC, and the Large Load Interconnection Customer has fulfilled its termination cost obligations under Article 2.4.
2.4
Termination Costs. Immediately upon the other Parties’ receipt of a notice of the termination of this LLIA pursuant to Article 2.3 above, the Participating TO will determine the total cost responsibility of the Large Load Interconnection Customer. If, as of the date of the other Parties’ receipt of the notice of termination, the Large Load Interconnection Customer has not already paid its share of Network Upgrade costs, as set forth in Appendix G to this LLIA, the Participating TO will liquidate the Large Load Interconnection Customer’s Interconnection Financial Security associated with its cost
PDF page 241
9
responsibility for Network Upgrades, in accordance with Appendix IV, Attachment 4 of the Participating TO’s tariff.
The Large Load Interconnection Customer will also be responsible for all costs incurred or irrevocably committed to be incurred in association with the construction of the Participating TO’s Interconnection Facilities (including any cancellation costs relating to orders or contracts for Interconnection Facilities and equipment) and other such expenses, including any Distribution Upgrades for which the Participating TO has incurred expenses or has irrevocably committed to incur expenses and has not been reimbursed by the Large Load Interconnection Customer, as of the date of the other Parties’ receipt of the notice of termination, subject to the limitations set forth in this Article 2.4. Nothing in this Article 2.4 shall limit the Parties’ rights under Article 17. If, as of the date of the other Parties’ receipt of the notice of termination, the Large Load Interconnection Customer has not already reimbursed the Participating TO for costs incurred to construct the Participating TO’s Interconnection Facilities, the Participating TO will liquidate the Large Load Interconnection Customer’s Interconnection Financial Security associated with the construction of the Participating TO’s Interconnection Facilities. If the amount of the Interconnection Financial Security liquidated by the Participating TO under this Article 2.4 is insufficient to compensate the Participating TO for actual costs associated with the construction of the Participating TO’s Interconnection Facilities contemplated in this Article, any additional amounts will be the responsibility of the Large Load Interconnection Customer. Any such additional amounts due from the Large Load Interconnection Customer beyond the amounts covered by its Interconnection Financial Security will be due to the Participating TO immediately upon termination of this LLIA. If the amount of the Interconnection Financial Security exceeds the Interconnection Customer’s cost responsibility under this LLIA, any excess amount will be released to the Interconnection Customer.
2.4.1 Large Load Interconnection. Notwithstanding the foregoing, in the event of termination by a Party, all Parties shall use commercially Reasonable Efforts to mitigate the costs, damages, and charges arising as a consequence of termination. With respect to any portion of the Participating TO’s Interconnection Facilities that have not yet been constructed or installed, the Participating TO shall to the extent possible, and with the Large Load Interconnection Customer’s authorization, cancel any pending orders of, or return, any materials or equipment for, or contracts for construction of, such facilities; provided that in the event the Large Load Interconnection Customer elects not to authorize such cancellation, the Large Load Interconnection Customer shall assume all payment obligations with respect to such materials, equipment, and contracts, and the Participating TO shall deliver such material and equipment, and, if necessary, assign such contracts, to the Large Load Interconnection Customer as soon as practicable, at the Large Load Interconnection Customer’s expense. To the extent that the Large Load Interconnection Customer has already paid the Participating TO for any or all such costs of materials or equipment not taken by the Large Load Interconnection Customer, the Participating TO shall promptly refund such amounts to the Large Load Interconnection
PDF page 242
10
Customer, less any costs, including penalties, incurred by the Participating TO to cancel any pending orders of, or return such materials, equipment, or contracts. 2.4.2 The Participating TO may, at its option, retain any portion of such materials, equipment, or facilities that the Large Load Interconnection Customer chooses not to accept delivery of, in which case the Participating TO shall be responsible for all costs associated with procuring such materials, equipment, or facilities. 2.4.3 With respect to any portion of the Interconnection Facilities, and any other facilities already installed or constructed pursuant to the terms of this LLIA, Large Load Interconnection Customer shall be responsible for all costs associated with the removal, relocation or other disposition or retirement of such materials, equipment, or facilities.
2.5
Disconnection. Upon termination of this LLIA, the Parties will take all appropriate steps to disconnect the Large Load Facility from the Participating TO’s Transmission System. All costs required to effectuate such disconnection shall be borne by the terminating Party, unless such termination resulted from the non-terminating Party’s Default of this LLIA or such non-terminating Party otherwise is responsible for these costs under this LLIA.
2.6
Survival. This LLIA shall continue in effect after termination to the extent necessary to provide for final billings and payments and for costs incurred hereunder, including billings and payments pursuant to this LLIA; to permit the determination and enforcement of liability and indemnification obligations arising from acts or events that occurred while this LLIA was in effect; and to permit each Party to have access to the lands of the other Parties pursuant to this LLIA or other applicable agreements, to disconnect, remove or salvage its own facilities and equipment.
Article 3. Regulatory Filings and CAISO Tariff Compliance
3.1
Filing. The Participating TO shall file this LLIA (and any amendment hereto) with the appropriate Governmental Authority(ies), if required. The Large Load Interconnection Customer may request that any information provided be subject to the confidentiality provisions of Article 22. If the Large Load Interconnection Customer has executed this LLIA, or any amendment thereto, the Large Load Interconnection Customer shall reasonably cooperate with the Participating TO and, as applicable, CAISO with respect to such filing and to provide any information reasonably requested by the Participating TO or CAISO as needed to comply with applicable regulatory requirements. 3.2
Agreement Subject to CAISO Tariff. The Large Load Interconnection Customer will comply with all applicable provisions of the CAISO Tariff, including the GIDAP as may be required pursuant to Appendix H for co-located or Behind-the-Meter Generation. Article 4. Scope of Service
4.1
Large Load Interconnection Service. Large Load Interconnection Service allows the Large Load Interconnection Customer to connect the Large Load Facility to the
PDF page 243
11
Participating TO’s Transmission System and be eligible to receive energy from the CAISO Controlled Grid. To the extent the Large Load Interconnection Customer wants to receive Large Load Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct.
4.2
Provision of Service. The Participating TO shall provide Interconnection Service for the Large Load Facility. Any Interconnection Service subject to Appendix H shall be negotiated between the Participating TO, Large Load Interconnection Customer and the CAISO.
4.3
Performance Standards. Each Party shall perform all of its obligations under this LLIA in accordance with Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility Practice, and to the extent a Party is required or prevented or limited in taking any action by such regulations and standards, such Party shall not be deemed to be in Breach of this LLIA for its compliance therewith. If such Party is the Participating TO, then that Party shall amend the LLIA and submit the amendment to FERC for approval. 4.4
No Transmission Service. The execution of this LLIA does not constitute a request for, nor the provision of, any transmission service over the Participating TO’s Transmission System, and does not convey any right to deliver electricity to, or receive electricity from, any specific point of delivery. Large Load Interconnection Customer must request transmission service from CAISO, including through a Scheduling Coordinator, in accordance with the CAISO Tariff.
Article 5. Large Load Interconnect Customer’s Interconnection Facilities Engineering, Procurement, And Construction
5.1
Design Requirements. Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO from the Large Load Interconnection Customer associated with interconnecting the Large Load Facility.
5.1.1 Standard Option. The Participating TO shall design, procure, and construct the Participating TO’s Interconnection Facilities, Network Upgrades using Reasonable Efforts to complete the Participating TO’s Interconnection Facilities and Network Upgrades by the dates set forth in Appendix B, Milestones. The Participating TO shall not be required to undertake any action which is inconsistent with its standard safety practices, its material and equipment specifications, its design criteria and construction procedures, its labor agreements, and Applicable Laws and Regulations. In the event the Participating TO reasonably expects that it will not be able to complete the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades by the specified dates, the Participating TO shall promptly provide written notice to the Large Load Interconnection Customer
PDF page 244
12
and, as applicable, the CAISO and the Participating TO shall undertake Reasonable Efforts to meet the earliest dates thereafter.
5.2
Liquidated Damages. The actual damages to the Large Load Interconnection Customer, in the event the Participating TO’s Interconnection Facilities or Network Upgrades are not completed by the dates designated by the Large Load Interconnection Customer and accepted by the Participating TO, may include Large Load Interconnection Customer’s fixed operation and maintenance costs and lost opportunity costs. Such actual damages are uncertain and impossible to determine at this time. Because of such uncertainty, any liquidated damages paid by the Participating TO the Large Load Interconnection Customer in the event that the Participating TO does not complete any portion of the Participating TO’s Interconnection Facilities or Network Upgrades by the applicable dates, shall be an amount equal to one half of one percent (½ of 1%) per day of the actual cost of the Participating TO’s Interconnection Facilities and Network Upgrades, in the aggregate, for which the Participating TO has assumed responsibility to design, procure and construct.
However, in no event shall the total liquidated damages exceed twenty percent (20%) of the actual cost of the Participating TO’s Interconnection Facilities and Network Upgrades for which the Participating TO has assumed responsibility to design, procure, and construct. The foregoing payments will be made by the Participating TO the Large Load Interconnection Customer as just compensation for the damages caused to the Large Load Interconnection Customer, which actual damages are uncertain and impossible to determine at this time, and as reasonable liquidated damages, but not as a penalty or a method to secure performance of this LLIA. Liquidated damages, when the Parties agree to them, are the exclusive remedy for the Participating TO’s failure to meet its schedule. No liquidated damages shall be paid to the Large Load Interconnection Customer if: (1) the Large Load Interconnection Customer is not ready to commence use of the Participating TO’s Interconnection Facilities or Network Upgrades to take the delivery of power for the Large Load Facility’s Trial Operation, unless the Large Load Interconnection Customer would have been able to commence use of the Participating TO’s Interconnection Facilities or Network Upgrades to take the delivery of power for Large Load Facility’s Trial Operation, but for the Participating TO’s delay; and (2) the Participating TO’s failure to meet the specified dates is the result of the action or inaction of the Large Load Interconnection Customer or any other interconnection customer who has entered into an interconnection agreement with the Participating TO and/or CAISO, action or inaction by the CAISO, or any cause beyond the Participating TO’s reasonable control or reasonable ability to cure.
In no event shall the Participating TO have any responsibility or liability to the Large Load Interconnection Customer for liquidated damages pursuant to the provisions of this Article 5.2.
5.3
Reserved.
PDF page 245
13
5.4
Equipment Procurement. Participating TO shall commence design of the Participating TO’s Interconnection Facilities or Network Upgrades and procure necessary equipment as soon as practicable after all of the following conditions are satisfied, unless the Parties otherwise agree in writing:
5.4.1 The Participating TO has received written authorization to proceed with design and procurement from the Large Load Interconnection Customer by the date specified in Appendix B, Milestones; and
5.4.2 The Large Load Interconnection Customer has provided security to the Participating TO in accordance with Article 11.3 by the dates specified in Appendix B, Milestones.
5.5
Construction Commencement. The Participating TO shall commence construction of the Participating TO’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied: 5.5.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.5.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of the Participating TO’s Interconnection Facilities and Network Upgrades;
5.5.3 The Participating TO has received written authorization to proceed with construction from the Large Load Interconnection Customer by the date specified in Appendix B, Milestones; and
5.5.4 The Large Load Interconnection Customer has provided payment and security to the Participating TO in accordance with Article 11.3 by the dates specified in Appendix B, Milestones.
5.6
Work Progress. The Parties will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Any Party may, at any time, request a progress report from another Party. If, at any time, the Large Load Interconnection Customer determines that the completion of the Participating TO’s Interconnection Facilities will not be required until after the specified In-Service Date, the Large Load Interconnection Customer will provide written notice to the Participating TO and, as applicable, CAISO of such later date upon which the completion of the Participating TO’s Interconnection Facilities will be required.
5.7
Information Exchange. As soon as reasonably practicable after the Effective Date, the Parties shall exchange information regarding the design and compatibility of the Large Load Interconnection Customer’s Interconnection Facilities and Participating TO’s Interconnection Facilities and compatibility of the Interconnection Facilities with the Participating TO’s Transmission System, and shall work diligently and in good faith to make any necessary design changes.
PDF page 246
14
5.8
Limited Operation. If any of the Participating TO’s Interconnection Facilities or Network Upgrades are not reasonably expected to be completed prior to the Commercial Operation Date of the Large Load Facility, the Participating TO shall, upon the request and at the expense of the Large Load Interconnection Customer, perform operating studies on a timely basis to determine the extent to which the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities may operate prior to the completion of the Participating TO’s Interconnection Facilities or Network Upgrades consistent with Applicable Laws and Regulations, Applicable Reliability Standards, Good Utility Practice, and this LLIA. The Participating TO shall permit the Large Load Interconnection Customer to operate the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities in accordance with the results of such studies.
5.9
Large Load Interconnection Customer’s Interconnection Facilities. The Large Load Interconnection Customer shall, at its expense, design, procure, construct, own, and install the Large Load Interconnection Customer’s Interconnection Facilities, as set forth in Appendices A and H, as applicable.
5.9.1 Large Load Facility and Large Load Interconnection Customer’s
Interconnection Facilities Specifications. In addition to the Large Load Interconnection Customer’s responsibility to submit technical data with its Large Load Interconnection Application, Large Load Interconnection Customer shall submit all remaining necessary specifications for the Large Load Interconnection Customer’s Interconnection Facilities and Large Load Facility, including System Protection Facilities, to the Participating TO (who shall provide such information to the CAISO) at least one hundred eighty (180) Calendar Days prior to the Commercial Operation Date. The Participating TO shall review such specifications pursuant to this LLIA and the LLIP to ensure that the Large Load Interconnection Customer’s Interconnection Facilities and Large Load Facility are compatible with the technical specifications, operational control, safety requirements, and any other applicable requirements of the Participating TO and comment on such
specifications within thirty (30) Calendar Days of the Large Load Interconnection Customer’s submission. All specifications provided hereunder shall be deemed confidential.
5.9.2 Participating TO’s Review. The Participating TO’s review of the Large Load Interconnection Customer’s final specifications shall not be construed as confirming, endorsing, or providing a warranty as to the design, fitness, safety, durability or reliability of the Large Load Facility, or the Large Load Interconnection Customer’s Interconnection Facilities. Large Load Interconnection Customer shall make such changes to the Large Load Interconnection Customer’s Interconnection Facilities as may reasonably be required by the Participating TO, in accordance with Good Utility Practice, to ensure that the Large Load Interconnection Customer’s Interconnection Facilities are compatible with the technical specifications, Operational Control, and safety requirements of the Participating TO.
PDF page 247
15
5.9.3 Large Load Interconnection Customer’s Interconnection Facilities Construction. The Large Load Interconnection Customer’s Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Large Load Interconnection Customer agree on another mutually acceptable deadline, the Large Load Interconnection Customer shall deliver to the Participating TO “as-built” drawings, information and documents for the Large Load Interconnection Customer’s Interconnection Facilities and the Large Load Facility(s), such as: a one-line diagram, a site plan showing the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities, plan and elevation drawings showing the layout of the Large Load Interconnection Customer’s Interconnection Facilities, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Large Load Interconnection Customer’s step-up transformers, the facilities connecting the Large Load Facility to the step-up transformers and the Large Load Interconnection Customer’s Interconnection Facilities, and the impedances (determined by factory tests) for the associated step-up transformers and the Large Load Facilities. The Large Load Interconnection Customer shall provide the Participating TO specifications for the automatic voltage regulator, Large Load Facility control and protection settings, transformer tap settings, and communications, if applicable. Any deviations from the relay settings, machine specifications, and other specifications originally submitted by the Large Load Interconnection Customer shall be assessed by the Participating TO pursuant to the appropriate provisions of this LLIA and the LLIP.
5.10
Participating TO’s Interconnection Facilities Construction. The Participating TO’s Interconnection Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Participating TO and Large Load Interconnection Customer agree on another mutually acceptable deadline, the Participating TO shall deliver to the Large Load Interconnection Customer and the CAISO the following: “as- built” drawings, information and documents for the Participating TO’s Interconnection Facilities, including appropriate drawings and relay diagrams.
The Participating TO will obtain control for operating and maintenance purposes of the Participating TO’s Interconnection Facilities upon completion of such facilities. 5.11
Access Rights. Upon reasonable notice and supervision by a Party, and subject to any required or necessary regulatory approvals, a Party (“Granting Party”) shall furnish at no cost to the other Party (“Access Party”) any rights of use, licenses, rights of way and easements with respect to lands owned or controlled by the Granting Party, its agents (if allowed under the applicable agency agreement), or any Affiliate, that are necessary to enable the Access Party to obtain ingress and egress to construct, operate, maintain, repair, test (or witness testing), inspect, replace or remove facilities and equipment to: (i) interconnect the Large Load Facility with the Participating TO’s Transmission System;
(ii) operate and maintain the Large Load Facility, the Interconnection Facilities and the
PDF page 248
16
Participating TO’s Transmission System; and (iii) disconnect or remove the Access Party’s facilities and equipment upon termination of this LLIA. In exercising such rights of use, licenses, rights of way and easements, the Access Party shall not unreasonably disrupt or interfere with normal operation of the Granting Party’s business and shall adhere to the safety rules and procedures established in advance, as may be changed from time to time, by the Granting Party and provided to the Access Party.
5.12
Lands of Other Property Owners. If any part of the Participating TO’s Interconnection Facilities and/or Network Upgrades are to be installed on property owned by persons other than the Large Load Interconnection Customer or Participating TO, the Participating TO shall at the Large Load Interconnection Customer’s expense use efforts, similar in nature and extent to those that it typically undertakes on its own behalf or on behalf of its Affiliates, including use of its eminent domain authority, and to the extent consistent with state law, to procure from such persons any rights of use, licenses, rights of way and easements that are necessary to construct, operate, maintain, test, inspect, replace or remove the Participating TO’s Interconnection Facilities and/or Network Upgrades upon such property.
5.13
Permits. Participating TO and Large Load Interconnection Customer shall cooperate with each other in good faith in obtaining all permits, licenses and authorizations that are necessary to accomplish the interconnection in compliance with Applicable Laws and Regulations. With respect to this paragraph, the Participating TO shall provide permitting assistance to the Large Load Interconnection Customer comparable to that provided to the Participating TO’s own, or an Affiliate’s generation.
5.14
Suspension. The Large Load Interconnection Customer may request to suspend at any time all work associated with the construction and installation of the Participating TO’s Interconnection Facilities, Network Upgrades, and/or Distribution Upgrades required under this LLIA, other than Network Upgrades or Alternative Transmission Technologies solutions identified in the Large Load Interconnection Studies that are not subject to suspension. Large Load Interconnection Customers seeking to suspend construction will provide the Participating TO a request to suspend. The Participating TO shall evaluate a request to suspend work submitted pursuant to this Article 5.14 and may approve suspension requests where the Participating TO’s Transmission System can be left in a safe and reliable condition in accordance with Good Utility Practice, the Participating TO’s safety and reliability criteria, and Applicable Reliability Standards and Participating TO will not be subject to financial harm.
5.15
Taxes.
5.15.1 Large Load Interconnection Customer Payments Not Taxable. The Parties intend that all payments or property transfers made by the Large Load
Interconnection Customer to the Participating TO for the installation of the Participating TO’s Interconnection Facilities and the Network Upgrades shall be non-taxable, either as contributions to capital, or as a refundable advance, in accordance with the Internal Revenue Code and any applicable state income tax
PDF page 249
17
laws and shall not be taxable as contributions in aid of construction or otherwise under the Internal Revenue Code and any applicable state income tax laws. 5.15.2 Representations And Covenants. In accordance with IRS Notice 2001-82 and IRS Notice 88-129, the Large Load Interconnection Customer represents and covenants that: (i) for income tax purposes, the amount of any payments and the cost of any property transferred to the Participating TO for the Participating TO’s Interconnection Facilities will be capitalized by the Large Load Interconnection Customer as an intangible asset and recovered using the straight-line method over a useful life of twenty (20) years; and (ii) any portion of the Participating TO’s Interconnection Facilities that is a “dual-use intertie,” within the meaning of IRS Notice 88-129, is reasonably expected to carry only a de minimis amount of electricity away from the Large Load Facility. For this purpose, “de minimis amount” means no more than 5 percent of the total power flows in both directions, calculated in accordance with the “5 percent test” set forth in IRS Notice 88-129. This is not intended to be an exclusive list of the relevant conditions that must be met to conform to IRS requirements for non-taxable treatment.
At the Participating TO’s request, the Large Load Interconnection Customer shall provide the Participating TO with a report from an independent engineer confirming its representation in clause (iii), above. The Participating TO represents and covenants that the cost of the Participating TO’s Interconnection Facilities paid for by the Large Load Interconnection Customer without the possibility of refund or credit will have no net effect on the base upon which rates are determined.
5.15.3 Indemnification for the Cost Consequence of Current Tax Liability Imposed Upon the Participating TO. Notwithstanding Article 5.15.1, the Large Load Interconnection Customer shall protect, indemnify and hold harmless the Participating TO from the cost consequences of any current tax liability imposed against the Participating TO as the result of payments or property transfers made by the Large Load Interconnection Customer to the Participating TO under this LLIA for Interconnection Facilities, as well as any interest and penalties, other than interest and penalties attributable to any delay caused by the Participating TO. The Participating TO shall not include a gross-up for the cost consequences of any current tax liability in the amounts it charges the Large Load Interconnection Customer under this LLIA unless (i) the Participating TO has determined, in good faith, that the payments or property transfers made by the Large Load Interconnection Customer to the Participating TO should be reported as income subject to taxation or (ii) any Governmental Authority directs the Participating TO to report payments or property as income subject to taxation; provided, however, that the Participating TO may require the Large Load Interconnection Customer to provide security for Interconnection Facilities, in a form reasonably acceptable to the Participating TO (such as a parental guarantee or a letter of credit), in an amount equal to the cost consequences of any current tax liability under this Article 5.15. The Large Load Interconnection Customer shall reimburse the Participating TO for such costs on a fully grossed-up basis, in accordance with Article 5.15.4, within
PDF page 250
18
thirty (30) Calendar Days of receiving written notification from the Participating TO of the amount due, including detail about how the amount was calculated. The indemnification obligation shall terminate at the earlier of (1) the expiration of the ten year testing period and the applicable statute of limitation, as it may be extended by the Participating TO upon request of the IRS, to keep these years open for audit or adjustment, or (2) the occurrence of a subsequent taxable event and the payment of any related indemnification obligations as contemplated by this Article 5.15.
5.15.4 Tax Gross-Up Amount. The Large Load Interconnection Customer’s liability for the cost consequences of any current tax liability under this Article 5.15 shall be calculated on a fully grossed-up basis. Except as may otherwise be agreed to by the Parties, this means that the Large Load Interconnection Customer will pay the Participating TO, in addition to the amount paid for the Interconnection Facilities and Network Upgrades, an amount equal to (1) the current taxes imposed on the Participating TO (“Current Taxes”) on the excess of (a) the gross income realized by the Participating TO as a result of payments or property transfers made by the Large Load Interconnection Customer to the Participating TO under this LLIA (without regard to any payments under this Article 5.15) (the “Gross Income Amount”) over (b) the present value of future tax deductions for depreciation that will be available as a result of such payments or property transfers (the “Present Value Depreciation Amount”), plus (2) an additional amount sufficient to permit the Participating TO to receive and retain, after the payment of all Current Taxes, an amount equal to the net amount described in clause (1).
For this purpose, (i) Current Taxes shall be computed based on the Participating TO’s composite federal and state tax rates at the time the payments or property transfers are received and the Participating TO will be treated as being subject to tax at the highest marginal rates in effect at that time (the “Current Tax Rate”), and (ii) the Present Value Depreciation Amount shall be computed by discounting the Participating TO’s anticipated tax depreciation deductions as a result of such payments or property transfers by the Participating TO’s current weighted average cost of capital. Thus, the formula for calculating the Large Load Interconnection Customer’s liability to the Participating TO pursuant to this Article 5.15.4 can be expressed as follows: (Current Tax Rate x (Gross Income Amount – Present Value of Tax Depreciation))/(1-Current Tax Rate). Large Load Interconnection Customer’s estimated tax liability in the event taxes are imposed shall be stated in Appendix A, Interconnection Facilities, Network Upgrades and Distribution Upgrades.
5.15.5 Private Letter Ruling or Change or Clarification of Law. At the Large Load Interconnection Customer’s request and expense, the Participating TO shall file with the IRS a request for a private letter ruling as to whether any property transferred or sums paid, or to be paid, by the Large Load Interconnection Customer to the Participating TO under this LLIA are subject to federal income taxation. The Large Load Interconnection Customer will prepare the initial draft of the request for
PDF page 251
19
a private letter ruling, and will certify under penalties of perjury that all facts represented in such request are true and accurate to the best of the Large Load Interconnection Customer’s knowledge. The Participating TO and Large Load Interconnection Customer shall cooperate in good faith with respect to the submission of such request, provided, however, the Large Load Interconnection Customer and the Participating TO explicitly acknowledge (and nothing herein is intended to alter) Participating TO’s obligation under law to certify that the facts presented in the ruling request are true, correct and complete.
The Participating TO shall keep the Large Load Interconnection Customer fully informed of the status of such request for a private letter ruling and shall execute either a privacy act waiver or a limited power of attorney, in a form acceptable to the IRS, that authorizes the Large Load Interconnection Customer to participate in all discussions with the IRS regarding such request for a private letter ruling. The Participating TO shall allow the Large Load Interconnection Customer to attend all meetings with IRS officials about the request and shall permit the Large Load Interconnection Customer to prepare the initial drafts of any follow-up letters in connection with the request.
5.15.6 Subsequent Taxable Events. If, within ten (10) years from the date on which the relevant Participating TO’s Interconnection Facilities are placed in service, (i) the Large Load Interconnection Customer Breaches the covenants contained in Article 5.15.2, (ii) a “disqualification event” occurs within the meaning of IRS Notice 88- 129, or (iii) this LLIA terminates and the Participating TO retains ownership of the Interconnection Facilities and Network Upgrades, the Large Load Interconnection Customer shall pay a tax gross-up for the cost consequences of any current tax liability imposed on the Participating TO, calculated using the methodology described in Article 5.15.4 and in accordance with IRS Notice 9060. 5.15.7 Contests. In the event any Governmental Authority determines that the Participating TO’s receipt of payments or property constitutes income that is subject to taxation, the Participating TO shall notify the Large Load Interconnection Customer, in writing, within thirty (30) Calendar Days of receiving notification of such determination by a Governmental Authority. Upon the timely written request by the Large Load Interconnection Customer and at the Large Load Interconnection Customer’s sole expense, the Participating TO may appeal, protest, seek abatement of, or otherwise oppose such determination. Upon the Large Load Interconnection Customer’s written request and sole expense, the Participating TO may file a claim for refund with respect to any taxes paid under this Article 5.15, whether or not it has received such a determination. The Participating TO reserves the right to make all decisions with regard to the prosecution of such appeal, protest, abatement or other contest, including the selection of counsel and compromise or settlement of the claim, but the Participating TO shall keep the Large Load Interconnection Customer informed, shall consider in good faith suggestions from the Large Load Interconnection Customer about the conduct of the contest, and shall reasonably permit the Large Load Interconnection Customer or an Large Load Interconnection Customer representative to attend contest proceedings.
PDF page 252
20
The Large Load Interconnection Customer shall pay to the Participating TO on a periodic basis, as invoiced by the Participating TO, the Participating TO’s documented reasonable costs of prosecuting such appeal, protest, abatement or other contest, including any costs associated with obtaining the opinion of independent tax counsel described in this Article 5.15.7. The Participating TO may abandon any contest if the Large Load Interconnection Customer fails to provide payment to the Participating TO within thirty (30) Calendar Days of receiving such invoice.
At any time during the contest, the Participating TO may agree to a settlement either with the Large Load Interconnection Customer’s consent or, if such consent is refused, after obtaining written advice from independent nationally-recognized tax counsel, selected by the Participating TO, but reasonably acceptable to the Large Load Interconnection Customer, that the proposed settlement represents a reasonable settlement given the hazards of litigation. The Large Load Interconnection Customer’s obligation shall be based on the amount of the settlement agreed to by the Large Load Interconnection Customer, or if a higher amount, so much of the settlement that is supported by the written advice from nationally-recognized tax counsel selected under the terms of the preceding paragraph. The settlement amount shall be calculated on a fully grossed-up basis to cover any related cost consequences of the current tax liability. The Participating TO may also settle any tax controversy without receiving the Large Load Interconnection Customer’s consent or any such written advice; however, any such settlement will relieve the Large Load Interconnection Customer from any obligation to indemnify the Participating TO for the tax at issue in the contest (unless the failure to obtain written advice is attributable to the Large Load Interconnection Customer’s unreasonable refusal to the appointment of independent tax counsel).
5.15.8 Refund. In the event that: (a) a private letter ruling is issued to the Participating TO which holds that any amount paid or the value of any property transferred by the Large Load Interconnection Customer to the Participating TO under the terms of this LLIA is not subject to federal income taxation; (b) any legislative change or administrative announcement, notice, ruling or other determination makes it reasonably clear to the Participating TO in good faith that any amount paid or the value of any property transferred by the Large Load Interconnection Customer to the Participating TO under the terms of this LLIA is not taxable to the Participating TO; (c) any abatement, appeal, protest, or other contest results in a determination that any payments or transfers made by the Large Load Interconnection Customer to the Participating TO are not subject to federal income tax; or (d) if the Participating TO receives a refund from any taxing authority for any overpayment of tax attributable to any payment or property transfer made by the Large Load Interconnection Customer to the Participating TO pursuant to this LLIA, the Participating TO shall promptly refund to the Large Load Interconnection Customer the following:
PDF page 253
21
(i) any payment made by Large Load Interconnection Customer under this Article 5.15 for taxes that is attributable to the amount determined to be non-taxable, together with interest thereon,
(ii) interest on any amounts paid by the Large Load Interconnection Customer to the Participating TO for such taxes which the Participating TO did not submit to the taxing authority, calculated in accordance with the methodology set forth in FERC’s regulations at 18 C.F.R.
§35.19a(a)(2)(iii) from the date payment was made by the Large Load Interconnection Customer to the date the Participating TO refunds such payment to the Large Load Interconnection Customer, and
(iii) with respect to any such taxes paid by the Participating TO, any refund or credit the Participating TO receives or to which it may be entitled from any Governmental Authority, interest (or that portion thereof attributable to the payment described in clause (i), above) owed to the Participating TO for such overpayment of taxes (including any reduction in interest otherwise payable by the Participating TO to any Governmental Authority resulting from an offset or credit); provided, however, that the Participating TO will remit such amount promptly to the Large Load Interconnection Customer only after and to the extent that the Participating TO has received a tax refund, credit or offset from any Governmental Authority for any applicable overpayment of income tax related to the Participating TO’s Interconnection Facilities.
The intent of this provision is to leave the Parties, to the extent practicable, in the event that no taxes are due with respect to any payment for Interconnection Facilities and Network Upgrades hereunder, in the same position they would have been in had no such tax payments been made.
5.15.9 Taxes Other Than Income Taxes. Upon the timely request by the Large Load Interconnection Customer, and at the Large Load Interconnection Customer’s sole expense, the Participating TO may appeal, protest, seek abatement of, or otherwise contest any tax (other than federal or state income tax) asserted or assessed against the Participating TO for which the Large Load Interconnection Customer may be required to reimburse the Participating TO under the terms of this LLIA. The Large Load Interconnection Customer shall pay to the Participating TO on a periodic basis, as invoiced by the Participating TO, the Participating TO’s documented reasonable costs of prosecuting such appeal, protest, abatement, or other contest. The Large Load Interconnection Customer and the Participating TO shall cooperate in good faith with respect to any such contest. Unless the payment of such taxes is a prerequisite to an appeal or abatement or cannot be deferred, no amount shall be payable by the Large Load Interconnection Customer to the Participating TO for such taxes until they are assessed by a final, non-appealable order by any court or agency of competent jurisdiction. In the event that a tax payment is withheld and ultimately due and payable after appeal, the Large Load Interconnection Customer
PDF page 254
22
will be responsible for all taxes, interest and penalties, other than penalties attributable to any delay caused by the Participating TO.
5.16
Tax Status. Each Party shall cooperate with the others to maintain the other Parties’ tax status.
Article 6. Large Load Interconnection Testing and Inspection
6.1
Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Large Load Interconnection Customer shall test the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each Party shall make any modifications to its facilities that are found to be necessary as a result of such testing. The Large Load Interconnection Customer shall bear the cost of all such testing and modifications.
6.2
Post-Commercial Operation Date Testing and Modifications. Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Load Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice. 6.3
Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days in advance of its performance of tests of its Interconnection Facilities or Large Load Facility. The other Parties have the right, at their own expense, to observe such testing.
6.4
Right to Inspect. Each Party shall have the right, but shall have no obligation to: (i) observe another Party’s tests and/or inspection of any of its System Protection Facilities and other protective equipment; (ii) review the settings of another Party’s System Protection Facilities and other protective equipment; and (iii) review another Party’s maintenance records relative to the Interconnection Facilities, the System Protection Facilities and other protective equipment. A Party may exercise these rights from time to time as it deems necessary upon reasonable notice to the other Party. The exercise or non- exercise by a Party of any such rights shall not be construed as an endorsement or confirmation of any element or condition of the Interconnection Facilities or the System Protection Facilities or other protective equipment or the operation thereof, or as a warranty as to the fitness, safety, desirability, or reliability of same. Any information that a Party obtains through the exercise of any of its rights under this Article 6.4 shall be deemed to be Confidential Information and treated pursuant to Article 22 of this LLIA.
PDF page 255
23
Article 7. Metering
7.1
General. Each Party shall comply with any Applicable Reliability Standards and the Applicable Reliability Council requirements. Unless otherwise agreed by the Participating TO and the Large Load Interconnection Customer, the Participating TO may install additional Metering Equipment at the Point of Interconnection of the Large Load Facility, and shall own, operate, test and maintain such Metering Equipment. Power flows to the Large Load Facility shall be measured at or, at the Participating TO’s option for its respective Metering Equipment, compensated to, the Point of Interconnection. The Large Load Interconnection Customer shall also install meters at each load block and at each individual generation source to accurately capture the demand/generation and power factor of these facilities. The Large Load Interconnection Customer shall bear all reasonable documented costs associated with the purchase, installation, operation, testing and maintenance of the Metering Equipment.
7.2
Check Meters. The Large Load Interconnection Customer, at its option and expense, may install and operate, on its premises and on its side of the Point of Interconnection, one or more check meters to check the Participating TO’s meters. Such check meters shall be for check purposes only and shall not be used for the measurement of power flows for purposes of this LLIA, except in the case that no other means are available on a temporary basis at the option of the Participating TO. The check meters shall be subject at all reasonable times to inspection and examination by the Participating TO or their designees. The installation, operation and maintenance thereof shall be performed entirely by the Large Load Interconnection Customer in accordance with Good Utility Practice.
7.3
Participating TO Retail Metering. The Participating TO may install retail revenue quality meters and associated equipment, pursuant to the Participating TO’s applicable retail tariffs.
Article 8. Communications
8.1
Large Load Interconnection Customer Obligations. The Large Load Interconnection Customer shall maintain satisfactory operating communications with the Participating TO and, as applicable, the CAISO in accordance with the provisions of the CAISO Tariff and with the Participating TO’s dispatcher or representative designated by the Participating TO. The Large Load Interconnection Customer shall provide standard voice line, dedicated voice line and facsimile communications at its Large Load Facility control room or central dispatch facility through use of either the public telephone system, or a voice communications system that does not rely on the public telephone system. The Large Load Interconnection Customer shall also provide two (2) independent dedicated data circuit(s) necessary to provide Large Load Interconnection Customer data to the Participating TO and, as applicable, the CAISO pursuant to the CAISO Tariff. The data circuit(s) shall extend from the Large Load Facility to the location(s) specified by the Participating TO and, as applicable, the CAISO. Any required maintenance of such communications equipment shall be performed by the Large Load Interconnection Customer. Operational communications shall be activated and maintained under, but not
PDF page 256
24
limited to, the following events: system paralleling or separation, scheduled and unscheduled shutdowns, equipment clearances, and hourly and daily load data. 8.2
Remote Terminal Unit. Prior to the interconnection of a Large Load Facility, a remote terminal unit, or equivalent data collection and transfer equipment acceptable to the Parties, shall be installed by the Large Load Interconnection Customer, or by the Participating TO at the Large Load Interconnection Customer’s expense, to gather accumulated and instantaneous data to be telemetered to the location(s) designated by the Participating TO and, as applicable, the CAISO through use of a dedicated point-to-point data circuit(s) as indicated in Article 8.1.
For telemetry to the Participating TO, the communication protocol for the data circuit(s) shall be specified by the Participating TO. Telemetry to the CAISO shall be provided in accordance with the CAISO’s technical standards for direct telemetry. Instantaneous bi- directional real power and reactive power flow and any other required information must be telemetered directly to the location(s) specified by the Participating TO. Each Party will promptly advise the other Parties if it detects or otherwise learns of any metering, telemetry or communications equipment errors or malfunctions that require the attention and/or correction by another Party. The Party owning such equipment shall correct such error or malfunction as soon as reasonably feasible.
8.3
No Annexation. Any and all equipment placed on the premises of a Party shall be and remain the property of the Party providing such equipment regardless of the mode and manner of annexation or attachment to real property, unless otherwise mutually agreed by the Parties.
Article 9. Large Load Interconnection Customer Operations
9.1
General. Each Party shall comply with Applicable Reliability Standards and the Applicable Reliability Council requirements. Each Party shall provide to the other Party all information that may reasonably be required by the other Party to comply with Applicable Laws and Regulations and Applicable Reliability Standards.
9.2
Participating TO Obligations. The Participating TO at the Large Load Interconnection Customer’s expense shall cause the Participating TO’s Interconnection Facilities to be operated, maintained and controlled in a safe and reliable manner and in accordance with this LLIA. The Participating TO may provide operating instructions to the Large Load Interconnection Customer consistent with this LLIA and Participating TO operating protocols and procedures as they may change from time to time. The Participating TO will consider changes to their operating protocols and procedures proposed by the Large Load Interconnection Customer.
9.3
Large Load Interconnection Customer Obligations. The Large Load Interconnection Customer shall at its own expense operate, maintain, and control the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LLIA. The Large Load Interconnection Customer shall operate the Large Load Facility and the Large Load Interconnection
PDF page 257
25
Customer’s Interconnection Facilities in accordance with all applicable requirements of the Balancing Authority Area of which it is part, if any, including such requirements as set forth in Appendix C, Interconnection Details, of this LLIA. Appendix C, Interconnection Details, will be modified to reflect changes to the requirements as they may change from time to time. A Party may request that another Party provide copies of the requirements set forth in Appendix C, Interconnection Details, of this LLIA. 9.4
Reactive Power and Primary Frequency Response. Large Load Interconnection Customer will design the Large Load Facility and Behind-the-Meter facility to maintain a composite power factor within the range of 0.99 leading to 0.97 lagging at the Point of Interconnection, unless the Participating TO established a different requirement that applies to all Large Loads connected to its system or the CAISO has establishes different requirements that apply to all Large Loads in the CAISO Balancing Authority Area on a comparable basis.
9.5
Disconnection from the Grid: The Participating TO will have the right to remotely disconnect the Large Load Facility under conditions specific operation conditions identified in the Large Load System Impact Study or under conditions where disconnecting the Large Load Facility is required to maintain transmission system reliability and stability.
9.6
Outages and Interruptions.
9.6.1 Outages.
9.6.1.1 Outage Authority and Coordination. Each Party may in accordance with Good Utility Practice in coordination with the other Parties remove from service any of its respective Interconnection Facilities or Network Upgrades that may impact another Party’s facilities as necessary to
perform maintenance or testing or to install or replace equipment. Absent an Emergency Condition, the Party scheduling a removal of such
facility(ies) from service will use Reasonable Efforts to schedule such removal on a date and time mutually acceptable to all Parties. In all circumstances any Party planning to remove such facility(ies) from service shall use Reasonable Efforts to minimize the effect on the other Parties of such removal.
9.6.1.2 Outage Schedules. The Large Load Interconnection Customer Shall submit its planned facility maintenance schedules no less than thirty (30) days in advance of the event.
9.6.1.3 Outage Restoration. If an outage on a Party’s Interconnection Facilities or Network Upgrades adversely affects another Party’s operations or
facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide
PDF page 258
26
the other Parties, to the extent such information is known, information on the nature of the Emergency Condition, if the outage is caused by an Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage, if requested by a Party, which may be provided by e-mail or facsimile. 9.6.2 Interruption of Service. If required by Good Utility Practice to do so, the Participating TO may require the Large Load Interconnection Customer to interrupt or reduce its receipt of deliveries of electricity if such receipt of electricity could adversely affect the Participating TO’s ability to perform such activities as are necessary to safely and reliably operate and maintain the Participating TO’s electric system. The following provisions shall apply to any interruption or reduction permitted under this Article 9.6.2:
9.6.2.1 The interruption or reduction shall continue only for so long as reasonably necessary under Good Utility Practice;
9.6.2.2 Any such interruption or reduction shall be made on an equitable, non- discriminatory basis with respect to all load directly connected to the Participating TO, subject to any conditions specified in this LLIA; 9.6.2.3 When the interruption or reduction must be made under circumstances which do not allow for advance notice, the Participating TO shall notify the Large Load Interconnection Customer by telephone as soon as practicable of the reasons for the curtailment, interruption, or reduction, and, if known, its expected duration. Telephone notification shall be followed by written notification, if requested by the Large Load Interconnection Customer, as soon as practicable;
9.6.2.4 Except during the existence of an Emergency Condition, the Participating TO shall notify the Large Load Interconnection Customer in advance regarding the timing of such interruption or reduction and further notify the Large Load Interconnection Customer of the expected duration. The Participating TO shall coordinate with the Large Load Interconnection Customer using Good Utility Practice to schedule the interruption or reduction during periods of least impact to the Large Load Interconnection Customer, the CAISO, and the Participating TO;
9.6.2.5 The Parties shall cooperate and coordinate with each other to the extent necessary in order to restore the Large Load Facility, Interconnection Facilities, the Participating TO’s Transmission System, and the CAISO Controlled Grid to their normal operating state, consistent with system conditions and Good Utility Practice.
9.6.3 Under-Frequency and Over-Frequency Conditions. The Large Load Interconnection Customer shall implement under-frequency and over-frequency
PDF page 259
27
protection set points for the Large Load Facility as required by Applicable Reliability Standards and the Applicable Reliability Council to ensure “ride through” capability. Large Load Facility response to frequency deviations of pre- determined magnitudes, both under-frequency and over-frequency deviations, shall be studied and coordinated with the Participating TO and the CAISO in accordance with Good Utility Practice. The term “ride through” as used herein shall mean the ability of a Generating Facility to stay connected to and synchronized with the CAISO Controlled Grid during system disturbances within a range of under- frequency and over-frequency conditions, in accordance with Good Utility Practice. The Large Load Interconnection Customer is required to satisfy all current and future frequency ride through requirement established by Western Electricity Coordinating Council or NERC.
9.6.4 System Protection and Other Control Requirements.
9.6.4.1 System Protection Facilities. The Large Load Interconnection Customer shall, at its expense, install, operate, and maintain System Protection Facilities as a part of the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities. The Participating TO shall install at the Large Load Interconnection Customer’s expense any System Protection Facilities that may be required on the Participating TO’s Interconnection Facilities or the Participating TO’s Transmission System as a result of the interconnection of the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities. 9.6.4.2 The Participating TO’s and Large Load Interconnection Customer’s protection facilities shall be designed and coordinated with other systems in accordance with Applicable Reliability Standards, Applicable Reliability Council criteria, and Good Utility Practice.
9.6.4.3 The Participating TO and Large Load Interconnection Customer shall each be responsible for protection of its facilities consistent with Good Utility Practice.
9.6.4.4 The Participating TO’s and Large Load Interconnection Customer’s protective relay design shall incorporate the necessary test switches to perform the tests required in Article 6. The required test switches will be placed such that they allow operation of lockout relays while preventing breaker failure schemes from operating and causing unnecessary breaker operations and/or the tripping of the Large Load Interconnection Customer’s Large Load Facilities.
9.6.4.5 The Participating TO and Large Load Interconnection Customer will test, operate and maintain System Protection Facilities in accordance with Good Utility Practice.
PDF page 260
28
9.6.4.6 Prior to the In-Service Date, and again prior to the Commercial Operation Date, the Participating TO and Large Load Interconnection Customer or their agents shall perform a complete calibration test and functional trip test of the System Protection Facilities. At intervals suggested by Good Utility Practice, the standards and procedures of the Participating TO, including, if applicable, the requirements of the Participating TO’s Interconnection Handbook, and following any apparent malfunction of the System Protection Facilities, each Party shall perform both calibration and functional trip tests of its System Protection Facilities. These tests do, however, require that all protective relays and lockout contacts be activated.
9.6.5 Requirements for Protection. In compliance with Good Utility Practice and, the Large Load Interconnection Customer shall provide, install, own, and maintain relays, circuit breakers and all other devices necessary to remove any fault contribution of the Large Load Facility to any short circuit occurring on the Participating TO’s Transmission System not otherwise isolated by the Participating TO’s equipment, such that the removal of the fault contribution shall be coordinated with the protective requirements of the Participating TO’s Transmission System. Such protective equipment shall include, without limitation, a disconnecting device with fault current-interrupting capability located between the Large Load Facility and the Participating TO’s Transmission System at a site selected upon mutual agreement (not to be unreasonably withheld, conditioned or delayed) of the Parties. The Large Load Interconnection Customer shall be responsible for protection of the Large Load Facility and the Large Load Interconnection Customer’s other equipment from such conditions as negative sequence currents, over- or under- frequency, sudden load rejection, over- or under-voltage, and generator loss-of- field. The Large Load Interconnection Customer shall be solely responsible to disconnect the Large Load Facility and the Large Load Interconnection Customer’s other equipment if conditions on the CAISO Controlled Grid could adversely affect the Large Load Facility.
9.6.6 Power Quality. Large Load Interconnection Customer’s facilities shall not cause excessive voltage flicker nor introduce excessive voltage and harmonic distortion to the sinusoidal voltage or current waves as defined by ANSI Standard C84.1-1989, in accordance with IEEE Standard 519, any applicable superseding electric industry standard, or any alternative Applicable Reliability Standard or Applicable Reliability Council standard. In the event of a conflict among ANSI Standard C84.1-1989, any applicable superseding electric industry standard, or any alternative Applicable Reliability Standard or Applicable Reliability Council standard, the alternative Applicable Reliability Standard or Applicable Reliability Council standard shall control.
9.7
Switching and Tagging Rules. Each Party shall provide the other Parties a copy of its switching and tagging rules that are applicable to the other Parties’ activities. Such switching and tagging rules shall be developed on a non-discriminatory basis. The Parties
PDF page 261
29
shall comply with applicable switching and tagging rules, as amended from time to time, in obtaining clearances for work or for switching operations on equipment. 9.8
Use of Interconnection Facilities by Third Parties.
9.8.1 Purpose of Interconnection Facilities. Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Load Facility to the Participating TO’s Transmission System and shall be used for no other purpose.
9.8.2 Third Party Users. If required by Applicable Laws and Regulations or if the Parties mutually agree, such agreement not to be unreasonably withheld, to allow one or more third parties to use the Participating TO’s Interconnection Facilities, or any part thereof, the Large Load Interconnection Customer will be entitled to compensation for the capital expenses it incurred in connection with the Interconnection Facilities based upon the pro rata use of the Interconnection Facilities by the Participating TO, all third party users, and the Large Load Interconnection Customer, in accordance with Applicable Laws and Regulations or upon some other mutually-agreed upon methodology. In addition, cost
responsibility for ongoing costs, including operation and maintenance costs associated with the Interconnection Facilities, will be allocated between the Large Load Interconnection Customer and any third party users based upon the pro rata use of the Interconnection Facilities by the Participating TO, all third party users, and the Large Load Interconnection Customer, in accordance with Applicable Laws and Regulations or upon some other mutually agreed upon methodology. If the issue of such compensation or allocation cannot be resolved through such negotiations, it shall be submitted to FERC for resolution.
9.9
Disturbance Analysis Data Exchange. The Parties will cooperate with one another in the analysis of disturbances to either the Large Load Facility or the Participating TO Transmission System by gathering and providing access to any information relating to any disturbance, including information from oscillography, protective relay targets, breaker operations and sequence of events records, and any disturbance information required by Good Utility Practice.
Article 10. Maintenance
10.1
Participating TO Obligations. The Participating TO shall maintain the Participating TO’s Transmission System and the Participating TO’s Interconnection Facilities in a safe and reliable manner and in accordance with this LLIA.
10.2
Large Load Interconnection Customer Obligations. The Large Load Interconnection Customer shall maintain the Large Load Facility and the Large Load Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LLIA.
PDF page 262
30
10.3
Coordination. The Parties shall confer regularly to coordinate the planning, scheduling and performance of preventive and corrective maintenance on the Large Load Facility and the Interconnection Facilities.
10.4
Secondary Systems. The Participating TO and Large Load Interconnection Customer shall cooperate with the other Parties in the inspection, maintenance, and testing of control or power circuits that operate below 600 volts, AC or DC, including, but not limited to, any hardware, control or protective devices, cables, conductors, electric raceways, secondary equipment panels, transducers, batteries, chargers, and voltage and current transformers that directly affect the operation of a Party’s facilities and equipment which may reasonably be expected to impact the other Parties. Each Party shall provide advance notice to the other Parties before undertaking any work on such circuits, especially on electrical circuits involving circuit breaker trip and close contacts, current transformers, or potential transformers.
10.5
Operating and Maintenance Expenses. Subject to the provisions herein addressing the use of facilities by others, and except for operations and maintenance expenses associated with modifications made for providing interconnection or transmission service to a third party and such third party pays for such expenses, the Large Load Interconnection Customer shall be responsible for all reasonable expenses including overheads, associated with: (1) owning, operating, maintaining, repairing, and replacing the Large Load Interconnection Customer’s Interconnection Facilities; and (2) operation, maintenance, repair, and replacement of the Participating TO’s Interconnection Facilities. Article 11. Performance Obligation
11.1
Large Load Interconnection Customer’s Interconnection Facilities. The Large Load Interconnection Customer shall design, procure, construct, install, own and/or control the Large Load Interconnection Customer’s Interconnection Facilities described in Appendix A and Appendix H at its sole expense.
11.2
Participating TO’s Interconnection Facilities. The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendices A and H at the sole expense of the Large Load Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Large Load Interconnection Customer.
11.3
Network Upgrades and Distribution Upgrades. The Participating TO shall design, procure, construct, install, and own the Network Upgrades and Distribution Upgrades described in Appendix A and Appendix H. The Large Load Interconnection Customer shall be responsible for all costs related to Distribution Upgrades. Network Upgrades shall be funded by the Large Load Interconnection Customer, and the Large Load Interconnection Customer shall bear the risk of, and be ultimately responsible for, the costs incurred to provide the Interconnection Service requested, including the costs of Network Upgrades, in accordance with this Article 11.3.
PDF page 263
31
11.3.1 Reimbursement for Network Upgrades. The Large Load Interconnection Customer shall be reimbursed in accordance with this Article 11.3.1 for amounts paid to the Participating TO for any Network Upgrade identified in Appendix A that has a cost of $10,000,000 or more (each, a “Reimbursable Network Upgrade”). Reimbursement for Reimbursable Network Upgrades placed in service on or before the Commercial Operation Date of the Large Load Facility shall commence upon the Commercial Operation Date. Reimbursement for each Reimbursable Network Upgrade placed in service after the Commercial Operation Date shall commence no later ninety (90) Calendar Days after such Network Upgrade is placed in service (as applicable, the “Reimbursement Commencement Date”). Subject to this Article 11.3, a reimbursement amount shall become fully and finally payable to the Large Load Interconnection Customer only when (x) such Network Upgrades have achieved Commercial Operation, (y) the Large Load Facility has achieved Commercial Operation and (z) the Large Load Interconnection Customer is not in Default under this LLIA (collectively, the “Final Payment Conditions”). Participating TO shall collect the cost of these facilities through its Transmission Revenue Requirement.
11.3.2 Repayment of Amounts Advanced for Network Upgrades.
11.3.2.1
Repayment Schedule. Any repayment amount provided pursuant
to Article 11.3.1 shall include any tax gross-up or other tax-related payments associated with Network Upgrades not refunded to the Large Load Interconnection Customer pursuant to Article 5 or otherwise, and shall be paid to the Large Load Interconnection Customer by the Participating TO on a dollar-for-dollar basis either through: (1) direct payments made on a levelized basis over a period of years, which shall be not less than five (5) years nor more than twenty (20) years, commencing on the applicable
Reimbursement Commencement Date (the “Repayment Period”);
or (2) any alternative payment schedule that is mutually agreeable to the Large Load Interconnection Customer and Participating TO, provided that such amount is paid within the Repayment Period, in each case subject to Article 11.3.2.4. The unpaid balance of any repayment amount outstanding from time to time shall accrue
interest at the rate calculated in accordance with the methodology set forth in FERC’s regulations at 18 C.F.R. §35.19a(a)(2)(iii), and such interest shall be paid together with each installment.
Notwithstanding the foregoing, if this LLIA terminates before the end of the applicable Repayment Period, the Participating TO’s obligation to pay refunds to the Large Load Interconnection
Customer shall cease as of the date of termination.
11.3.2.2
Interest Payments and Assignment Rights. Any repayment shall include interest calculated in accordance with the methodology set forth in FERC’s regulations at 18 C.F.R. §35.19a(a)(2)(iii) from the date of any payment for Network Upgrades through the date on
PDF page 264
32
which the Large Load Interconnection Customer receives a repayment of such payment. Interest shall continue to accrue on the repayment obligation so long as this LLIA is in effect. The Large Load Interconnection Customer may assign such repayment rights to any entity.
11.3.2.3
Failure to Achieve Commercial Operation. If the Large Load Facility fails to achieve Commercial Operation, but it or another Large Load Facility is later constructed, achieves Commercial Operation and makes use of the Network Upgrades, the Participating TO shall at that time reimburse Large Load Interconnection Customer for the amounts advanced for the Network Upgrades, provided that, notwithstanding Article 11.3.2.2, interest on such reimbursement shall not incur interest from the time the Large Load Facility that paid for the Network Upgrades fails to achieve Commercial Operation and, in the Participating TO’s reasonable discretion, will not be able to achieve Commercial Operation until the later Large Load Facility achieves Commercial Operation. Before any such reimbursement can occur, the Large Load Interconnection Customer, or the entity that ultimately constructs the Large Load Facility, if different, is responsible for identifying and demonstrating to the Participating TO the appropriate entity to which reimbursement must be made in order to implement the intent of this reimbursement obligation. 11.3.2.4
Accelerated Reimbursement Against Reimbursement Security. As a condition precedent to receiving any Reimbursement, the Large Load Interconnection Customer shall provide, and thereafter maintain until released under this Article 11.3.2.4, credit support in a form acceptable to Participating TO and from an issuer reasonably acceptable to the Participating TO (the
“Reimbursement Security”) in an amount equal to: (i) initially, an amount equal to the anticipated first Reimbursement payment (based on the amount of the Network Upgrades divided by the years in the Repayment Period); and (ii) thereafter, the aggregate amount of all Reimbursements received by the Large Load Interconnection Customer plus the amounts for the operation and maintenance of the Network Upgrades to date, for a period of five
(5) years from the Participating TO’s receipt of such Reimbursement Security. The Reimbursement Security shall secure the Large Load Interconnection Customer’s obligation to pay the Participating TO, within thirty (30) Calendar Days of invoice, any amount by which Participating TO is not able to collect relating to the full cost of a Reimbursable Network Upgrade in Participating TO’s Transmission Revenue Requirement
PDF page 265
33
In addition, the Large Load Interconnection Customer may elect, by written notice to the Participating TO, to receive reimbursement amounts for Reimbursable Network Upgrades for which it has made payment before such amounts have become fully and finally payable under Article 11.3.1 and Article 11.3.2.1 (each such payment, an “Accelerated Reimbursement”). In order to receive such Accelerated Reimbursement, the Large Load Interconnection Customer shall post Reimbursement Security. Prior to receipt of each additional Accelerated Reimbursement before the
Commercial Operation Date, the Large Load Interconnection Customer shall increase the Reimbursement Security by the amount of such additional Accelerated Reimbursement, such that the Reimbursement Security at all times through the Commercial Operation Date is not less than the cumulative Accelerated Reimbursements received.
The Participating TO shall pay each Reimbursement and Accelerated Reimbursement, as applicable, within thirty (30) Calendar Days after its receipt of the required Reimbursement Security, and no interest shall accrue under Article 11.3.2.1 or Article 11.3.2.2 on any amount from and after the date it is paid. If (a) the Final Payment Conditions are not satisfied with respect to any portion of an Accelerated Reimbursement, or (b) this LLIA terminates before any portion of an Accelerated Reimbursement has become fully and finally payable, the Large Load
Interconnection Customer shall repay such portion to the Participating TO, together with interest calculated in accordance with 18 C.F.R. §35.19a(a)(2)(iii) from the date of the Accelerated Reimbursement, within thirty (30) Calendar Days of invoice. If the Large Load Interconnection Customer fails to timely make any such repayment, or fails to renew or replace the Reimbursement Security at least thirty (30) Calendar Days before its expiration or to replenish it within five (5) Business Days after any draw, the Participating TO may draw upon the Reimbursement Security in the amount of the unpaid repayment obligation or, in the case of a failure to renew, replace, or replenish, in the full amount of the then-outstanding Reimbursements, and hold any cash proceeds as security for such obligation. Any portion of an Accelerated Reimbursement repaid or recovered by the Participating TO shall remain eligible for reimbursement in accordance with this Article 11.3 when it becomes fully and finally payable.
11.3.3 Special Provisions for Affected Systems. The Large Load Interconnection Customer shall enter into an agreement with the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid, as applicable, in accordance with this Article 11.3.3. Such agreement shall specify the
PDF page 266
34
terms governing payments to be made by the Large Load Interconnection Customer to the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid as well as the repayment by the owner of the Affected System and/or other affected owners of portions of the CAISO Controlled Grid. In no event shall the Participating TO be responsible for the repayment for any facilities that are not part of the Participating TO’s Transmission System. In the event the Participating TO is a joint owner with an Affected System or with any other co-owner of a facility affected by the Large Load Facility, the Participating TO’s obligation to reimburse the Large Load Interconnection Customer for payments made to address the impacts of the Large Load Facility on the system shall not exceed the proportionate amount of the cost of any upgrades attributable to the proportion of the jointly-owned facility owned by the Participating TO. 11.4
Provision of Interconnection Financial Security. The Large Load Interconnection Customer is obligated to provide all necessary Interconnection Financial Security required under Attachment 4 to the LLIP in a manner acceptable under Attachment 4. Failure by the Large Load Interconnection Customer to timely satisfy the terms and conditions set forth in Attachment 4 to the LLIP for the provision of Interconnection Financial Security shall be deemed a Breach of this Agreement and a condition of Default of this Agreement.
11.4.1 Notwithstanding any other provision of this Agreement for notice of Default and opportunity to cure such Default, the Participating TO shall provide the Large Load Interconnection Customer with written notice of any Default due to timely failure to post Interconnection Financial Security, and the Large Load Interconnection Customer shall have five (5) Business Days from the date of such notice to cure such Default by posting the required Interconnection Financial Security. If the Large Load Interconnection Customer fails to cure the Default, then this Agreement shall be deemed terminated.
Article 12. Invoice
12.1
General. The Participating TO shall submit to the Large Load Interconnection Customer, on a monthly basis, invoices of amounts due pursuant to this LLIA for the preceding month. Each invoice shall state the month to which the invoice applies and fully describe the services and equipment provided. The Parties may discharge mutual debts and payment obligations due and owing to each other on the same date through netting, in which case all amounts a Party owes to the other Party under this LLIA, including interest payments or credits, shall be netted so that only the net amount remaining due shall be paid by the owing Party.
12.2
Final Invoice. As soon as reasonably practicable, but within twelve (12) months after completion of the construction of the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades, the Participating TO shall provide an invoice of the final cost of the construction of the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades, and shall set forth such costs in sufficient detail to enable the Large Load Interconnection Customer to compare the actual
PDF page 267
35
costs with the estimates and to ascertain deviations, if any, from the cost estimates. With respect to costs associated with the Participating TO’s Interconnection Facilities and Distribution Upgrades, the Participating TO shall refund to the Large Load Interconnection Customer any amount by which the actual payment by the Large Load Interconnection Customer for estimated costs exceeds the actual costs of construction within thirty (30) Calendar Days of the issuance of such final construction invoice; or, in the event the actual costs of construction exceed the Large Load Interconnection Customer’s actual payment for estimated costs, then the Large Load Interconnection Customer shall pay to the Participating TO any amount by which the actual costs of construction exceed the actual payment by the Large Load Interconnection Customer for estimated costs within thirty (30) Calendar Days of the issuance of such final construction invoice. With respect to costs associated with Network Upgrades, the Participating TO shall refund to the Large Load Interconnection Customer any amount by which the actual payment by the Large Load Interconnection Customer for estimated costs exceeds the actual costs of construction multiplied by the Large Load Interconnection Customer’s percentage share of those costs, as set forth in Appendix G to this LLIA within thirty (30) Calendar Days of the issuance of such final construction invoice. In the event the actual costs of construction multiplied by the Large Load Interconnection Customer’s percentage share of those costs exceed the Large Load Interconnection Customer’s actual payment for estimated costs, then the Participating TO shall recover such difference through its transmission service rates. 12.3
Payment. Invoices shall be rendered to the Large Load Interconnection Customer at the address specified in Appendix F. The Large Load Interconnection Customer shall pay, or Participating TO shall refund, the amounts due within thirty (30) Calendar Days of the Large Load Interconnection Customer’s receipt of the invoice. All payments shall be made in immediately available funds payable to the Large Load Interconnection Customer or Participating TO, or by wire transfer to a bank named and account designated by the invoicing Large Load Interconnection Customer or Participating TO. Payment of invoices by any Party will not constitute a waiver of any rights or claims any Party may have under this LLIA.
12.4
Disputes. In the event of a billing dispute between the Large Load Interconnection Customer and the Participating TO, the Participating TO shall continue to provide Interconnection Service under this LLIA as long as the Large Load Interconnection Customer: (i) continues to make all payments not in dispute; and (ii) pays to the Participating TO or into an independent escrow account the portion of the invoice in dispute, pending resolution of such dispute. If the Large Load Interconnection Customer fails to meet these two requirements for continuation of service, then the Participating TO may provide notice to the Large Load Interconnection Customer of a Default pursuant to Article 17. Within thirty (30) Calendar Days after the resolution of the dispute, the Party that owes money to the other Party shall pay the amount due with interest calculated in accordance with the methodology set forth in FERC’s Regulations at 18 C.F.R. § 35.19a(a)(2)(iii).
PDF page 268
36
Article 13. Emergencies
13.1
[Reserved]
13.2
Obligations. Each Party shall comply with the Emergency Condition procedures of the CAISO, NERC, the Applicable Reliability Council, Applicable Reliability Standards, Applicable Laws and Regulations, Applicable Reliability Coordinators requirements, and any emergency procedures set forth in this LLIA or provided by the Participating TO. 13.3
Notice. The Participating TO shall notify the Large Load Interconnection Customer promptly when it becomes aware of an Emergency Condition that affects the Participating TO’s Interconnection Facilities or Distribution System or the CAISO Controlled Grid, respectively, that may reasonably be expected to affect the Large Load Interconnection Customer’s operation of the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities. The Large Load Interconnection Customer shall notify the Participating TO and, as applicable, the CAISO promptly when it becomes aware of an Emergency Condition that affects the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities that may reasonably be expected to affect the CAISO Controlled Grid or the Participating TO’s Interconnection Facilities. To the extent information is known, the notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of the Large Load Interconnection Customer’s or Participating TO’s facilities and operations, its anticipated duration and the corrective action taken and/or to be taken. The initial notice shall be followed as soon as practicable with written notice, if requested by a Party, which may be provided by electronic mail or facsimile.
13.4
Immediate Action. Unless, in the Large Load Interconnection Customer’s reasonable judgment, immediate action is required, the Large Load Interconnection Customer shall obtain the consent of the Participating TO, such consent to not be unreasonably withheld, prior to performing any manual switching operations at the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities in response to an Emergency Condition declared by the Participating TO in response to any other emergency condition.
13.5
Participating TO Authority.
13.5.1 General. The Participating TO may take whatever actions or inactions, including issuance of dispatch instructions, with regard to Participating TO’s Interconnection Facilities or Distribution System they deem necessary during an Emergency Condition in order to: (i) preserve public health and safety; (ii) preserve the reliability of the Participating TO’s Transmission System and/or the Participating TO’s Interconnection Facilities or Distribution System; (iii) limit or prevent damage; and (iv) expedite restoration of service.
The Participating TO shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities. The Participating TO may, on the basis of
PDF page 269
37
technical considerations, require the Large Load Facility to mitigate an Emergency Condition by taking actions necessary and limited in scope to remedy the Emergency Condition, including, but not limited to, directing the Large Load Interconnection Customer to shut-down, implementing a reduction or
disconnection pursuant to Article 13.5.2; or altering the outage schedules of the Large Load Facility and the Large Load Interconnection Customer’s
Interconnection Facilities.
13.5.2 Reduction and Disconnection. The Participating TO may reduce Interconnection Service or disconnect the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities when such reduction or disconnection is necessary under Good Utility Practice due to Emergency Conditions and/or under certain abnormal operating conditions to maintain the reliability of the transmission network. When the Participating TO can schedule the reduction or disconnection in advance, the Participating TO shall notify the Large Load Interconnection Customer of the reasons, timing and expected duration of the reduction or disconnection. The Participating TO shall coordinate with the Large Load Interconnection Customer using Good Utility Practice to schedule the reduction or disconnection during periods of least impact to the Large Load Interconnection Customer and the Participating TO. Any reduction or disconnection shall continue only for so long as reasonably necessary under Good Utility Practice. The Parties shall cooperate with each other to restore the Large Load Facility, the Interconnection Facilities, and the Participating TO’s Transmission System to their normal operating state as soon as practicable consistent with Good Utility Practice.
13.6
Large Load Interconnection Customer Authority. Consistent with Good Utility Practice and this LLIA, the Large Load Interconnection Customer may take actions or inactions with regard to the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities during an Emergency Condition in order to: (i) preserve public health and safety; (ii) preserve the reliability of the Large Load Facility or the Large Load Interconnection Customer’s Interconnection Facilities; (iii) limit or prevent damage; and (iv) expedite restoration of service. Large Load Interconnection Customer shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Participating TO’s Transmission System and the Participating TO’s Interconnection Facilities. The Participating TO shall use Reasonable Efforts to assist Large Load Interconnection Customer in such actions.
13.7
Limited Liability. Except as otherwise provided in this LLIA, no Party shall be liable to any other Party for any action it takes in responding to an Emergency Condition so long as such action is made in good faith and is consistent with Good Utility Practice. Article 14. Regulatory Requirements and Governing Laws
14.1
Regulatory Requirements. Each Party’s obligations under this LLIA shall be subject to its receipt of any required approval or certificate from one or more Governmental Authorities in the form and substance satisfactory to the applying Party, or the Party making any required filings with, or providing notice to, such Governmental Authority,
PDF page 270
38
and the expiration of any time period associated therewith. Each Party shall in good faith seek and use its Reasonable Efforts to obtain such other approvals. Nothing in this LLIA shall require the Large Load Interconnection Customer to take any action that could result in its inability to obtain, or its loss of, status or exemption under the Federal Power Act or the Public Utility Holding Company Act of 1935, as amended, or the Public Utility Regulatory Policies Act of 1978, or the Energy Policy Act of 2005. 14.2
Governing Law.
14.2.1 The validity, interpretation and performance of this LLIA and each of its provisions shall be governed by the laws of the state where the Point of Interconnection is located, without regard to its conflicts of law principles.
14.2.2 This LLIA is subject to all Applicable Laws and Regulations.
14.2.3 Each Party expressly reserves the right to seek changes in, appeal, or otherwise contest any laws, orders, rules, or regulations of a Governmental Authority. Article 15. Notices
15.1
General. Unless otherwise provided in this LLIA, any notice, demand or request required or permitted to be given by a Party to another and any instrument required or permitted to be tendered or delivered by a Party in writing to another shall be effective when delivered and may be so given, tendered or delivered, by recognized national courier, conveyed by e-mail, or by depositing the same with the United States Postal Service with postage prepaid, for delivery by certified or registered mail, addressed to the Party, or personally delivered to the Party, at the address set out in Appendix F, Addresses for Delivery of Notices and Billings.
A Party must update the information in Appendix F as information changes. A Party may change the notice information in this LLIA by giving five (5) Business Days written notice prior to the effective date of the change. Such changes shall not constitute an amendment to this LLIA.
15.2
Billings and Payments. Billings and payments shall be sent to the addresses set out in Appendix F.
15.3
Alternative Forms of Notice. Any notice or request required or permitted to be given by a Party to another and not required by this LLIA to be given as provided in Article 15.1 may be so given by telephone, or e-mail to the telephone numbers and e-mail addresses set out in Appendix F.
15.4
Operations and Maintenance Notice. Each Party shall notify the other Parties in writing of the identity of the person(s) that it designates as the point(s) of contact with respect to the implementation of Articles 9 and 10.
PDF page 271
39
Article 16. Force Majeure
16.1
Force Majeure.
16.1.1 Economic hardship is not considered a Force Majeure event.
16.1.2 No Party shall be considered to be in Default with respect to any obligation hereunder, (including obligations under Article 4), other than the obligation to pay money when due, if prevented from fulfilling such obligation by Force Majeure. A Party unable to fulfill any obligation hereunder (other than an obligation to pay money when due) by reason of Force Majeure shall give notice and the full particulars of such Force Majeure to the other Party in writing or by telephone as soon as reasonably possible after the occurrence of the cause relied upon. Telephone notices given pursuant to this Article shall be confirmed in writing as soon as reasonably possible and shall specifically state full particulars of the Force Majeure, the time and date when the Force Majeure occurred and when the Force Majeure is reasonably expected to cease. The Party affected shall exercise due diligence to remove such disability with reasonable dispatch, but shall not be required to accede or agree to any provision not satisfactory to it to settle and terminate a strike or other labor disturbance.
Article 17. Default
17.1
Default.
17.1.1 General. No Default shall exist where such failure to discharge an obligation (other than the payment of money) is the result of Force Majeure as defined in this LLIA or the result of an act or omission of the other Party. Upon a Breach, the affected non-Breaching Party(ies) shall give written notice of such Breach to the Breaching Party. Except as otherwise provided herein, the Breaching Party shall have thirty
(30) Calendar Days from receipt of the Default notice within which to cure such Breach; provided however, if such Breach is not capable of cure within thirty (30) Calendar Days, the Breaching Party shall commence such cure within thirty (30) Calendar Days after notice and continuously and diligently complete such cure within ninety (90) Calendar Days from receipt of the Default notice; and, if cured within such time, the Breach specified in such notice shall cease to exist. 17.1.2 Right to Terminate. If a Breach is not cured as provided in this Article, or if a Breach is not capable of being cured within the period provided for herein, the affected non-Breaching Party(ies) shall have the right to declare a Default and terminate this LLIA by written notice at any time until cure occurs, and be relieved of any further obligation hereunder and, whether or not such Party(ies) terminates this LLIA, to recover from the Breaching Party all amounts due hereunder, plus all other damages and remedies to which it is entitled at law or in equity. The provisions of this Article will survive termination of this LLIA.
PDF page 272
40
Article 18. Indemnity, Consequential Damages, and Insurance
18.1
Indemnity. Each Party (the “Indemnifying Party”) shall at all times indemnify, defend, and hold the other Parties (“Indemnified Party”) harmless from, any and all Losses arising out of or resulting from another Party’s action or inactions of its obligations under this LLIA on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the Indemnified Party.
18.1.1 Indemnified Party. If an Indemnified Party is entitled to indemnification under this Article 18 as a result of a claim by a third party, and the Indemnifying Party fails, after notice and reasonable opportunity to proceed under Article 18.1, to assume the defense of such claim, such Indemnified Party may at the expense of the Indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.
18.1.2 Indemnifying Party. If an Indemnifying Party is obligated to indemnify and hold any Indemnified Party harmless under this Article 18, the amount owing to the Indemnified Party shall be the amount of such Indemnified Party’s actual Loss, net of any insurance or other recovery.
18.1.3 Indemnity Procedures. Promptly after receipt by an Indemnified Party of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in Article 18.1 may apply, the Indemnified Party shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect a Party’s indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying Party.
The Indemnifying Party shall have the right to assume the defense thereof with counsel designated by such Indemnifying Party and reasonably satisfactory to the Indemnified Party. If the defendants in any such action include one or more Indemnified Parties and the Indemnifying Party and if the Indemnified Party reasonably concludes that there may be legal defenses available to it and/or other Indemnified Parties which are different from or additional to those available to the Indemnifying Party, the Indemnified Party shall have the right to select separate counsel to assert such legal defenses and to otherwise participate in the defense of such action on its own behalf. In such instances, the Indemnifying Party shall only be required to pay the fees and expenses of one additional attorney to represent an Indemnified Party or Indemnified Parties having such differing or additional legal defenses.
The Indemnified Party shall be entitled, at its expense, to participate in any such action, suit or proceeding, the defense of which has been assumed by the Indemnifying Party. Notwithstanding the foregoing, the Indemnifying Party: (i) shall not be entitled to assume and control the defense of any such action, suit or proceedings if and to the extent that, in the opinion of the Indemnified Party and its counsel, such action, suit or proceeding involves the potential imposition of
PDF page 273
41
criminal liability on the Indemnified Party, or there exists a conflict or adversity of interest between the Indemnified Party and the Indemnifying Party, in such event the Indemnifying Party shall pay the reasonable expenses of the Indemnified Party; and (ii) shall not settle or consent to the entry of any judgment in any action, suit or proceeding without the consent of the Indemnified Party, which shall not be unreasonably withheld, conditioned or delayed.
18.2
Consequential Damages. Other than the liquidated damages heretofore described in Article 5.2, in no event shall any Party be liable under any provision of this LLIA for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided, however, that damages for which a Party may be liable to another Party under another agreement will not be considered to be special, indirect, incidental, or consequential damages hereunder.
18.3
Insurance. As indicated below, the designated Party shall, at its own expense, maintain in force throughout the periods noted in this LLIA, and until released by the other Parties, the following minimum insurance coverages, with insurers rated no less than A- (with a minimum size rating of VII) by Bests’ Insurance Guide and Key Ratings and authorized to do business in the state where the Point of Interconnection is located, except in the case of any insurance required to be carried by the CAISO, the State of California: 18.3.1 Workers’ Compensation Insurance and Employers’ Liability. The Participating TO and the Large Load Interconnection Customer shall maintain such coverage from the commencement of any construction activities providing statutory benefits for Workers Compensation coverage and coverage amounts of no less than One Million Dollars ($1,000,000) for employer’s liability for each employee for bodily injury by accident and One Million Dollars ($1,000,000) for each employee for bodily injury by disease in accordance with the laws and regulations of the state in which the Point of Interconnection is located. The Participating TO shall provide the Large Load Interconnection Customer with evidence of such insurance coverage within thirty (30) Calendar Days of any request by the Large Load Interconnection Customer. The Large Load Interconnection Customer shall provide evidence of such insurance thirty (30) Calendar Days prior to entry by any employee or contractor or other person acting on the Large Load Interconnection Customer’s behalf onto any construction site to perform any work related to the Interconnection Facilities or Large Load Facility.
18.3.2 Commercial General Liability Insurance. The Participating TO and the Large Load Interconnection Customer shall maintain commercial general liability insurance coverage commencing within thirty (30) Calendar Days of the Effective Date of this LLIA, including coverage for premises and operations, bodily injury (including death), personal injury, property damage, products and completed operations coverage, coverage for explosion, collapse and underground hazards, independent contractors coverage, and (i) liability of Participating TO and the Large
PDF page 274
42
Load Interconnection Customer that would be imposed without the LLIA, or (ii) liability assumed by the Participating TO and the Large Load Interconnection Customer in a contract or agreement that is an “insured contract” under commercial general liability insurance policy. Such insurance shall include no cross-liability exclusions or separation of insured clause endorsement exclusions, with minimum limits of One Million Dollars ($1,000,000) per occurrence/One Million Dollars ($1,000,000) aggregate. If the activities of the Large Load Interconnection Customer are being conducted through the actions of an Affiliate, then the Large Load Interconnection Customer may satisfy the insurance requirements of this Article 18.3.2 by providing evidence of insurance coverage carried by such Affiliate and showing the Participating TO and, as applicable, the CAISO as an additional insured only with respect to the LLIA, together with the Large Load Interconnection Customer’s written representation to the Participating TO and, as applicable, the CAISO that the insured Affiliate is conducting all of the necessary pre-construction work. Within thirty (30) Calendar Days prior to the entry of any person on behalf of the Large Load Interconnection Customer onto any construction site to perform work related to the Interconnection Facilities or Large Load Facility, the Large Load Interconnection Customer shall replace any evidence of affiliate insurance with evidence of such insurance carried by the Large Load Interconnection Customer, naming the Participating TO and, as applicable, the CAISO as additional insured only with respect to the LLIA.
18.3.3 Business Automobile Liability Insurance. Prior to the entry of any such vehicles on any construction site in connection with work done by or on behalf of the Large Load Interconnection Customer, the Large Load Interconnection Customer shall provide evidence of coverage of owned and non-owned and hired vehicles, trailers or semi-trailers designed for travel on public roads, with a minimum, combined single limit of One Million Dollars ($1,000,000) per occurrence for bodily injury, including death, and property damage. The Large Load Interconnection Customer shall include the Participating TO and, as applicable, the CAISO as additional insured with respect to the LLIA on any such policies.
18.3.4 Excess Liability Insurance. Commencing at the time of entry of any person on its behalf upon any construction site for the Network Upgrades, Interconnection Facilities, or Large Load Facility, the Participating TO and the Large Load Interconnection Customer shall maintain Excess Liability insurance over and above the Employer’s Liability Commercial General Liability and Business Automobile Liability Insurance coverage, with a minimum limit of Twenty Million Dollars ($20,000,000) per occurrence/Twenty Million Dollars ($20,000,000) aggregate. Such insurance carried by the Participating TO shall include the Large Load Interconnection Customer and, as applicable, the CAISO as additional insured with respect to the LLIA, and such insurance carried by the Large Load Interconnection Customer shall include the Participating TO and, as applicable, the CAISO as an additional insured with respect to the LLIA. The requirements of Articles 18.3.2 and 18.3.4 may be met by any combination of general and excess liability insurance.
PDF page 275
43
18.3.5 The Commercial General Liability Insurance, Business Automobile Liability Insurance and Excess Liability Insurance policies shall include the other Parties identified in the articles above, their parents, their subsidiaries, respective directors, officers, agents, servants and employees (“Other Party Group”) and, as applicable, the CAISO as additional insured. All policies shall contain provisions whereby the insurers waive all rights of subrogation in accordance with the provisions of this LLIA against the Other Party Group. If any Party can reasonably demonstrate that coverage policies containing provisions for insurer waiver of subrogation rights, or advance notice are not commercially available, then the Parties shall meet and confer and mutually determine to: (i) establish replacement or equivalent terms in lieu of subrogation or notice; or (ii) waive the requirements that coverage(s) include such subrogation provision or require advance written notice from such insurers. 18.3.6 The Commercial General Liability Insurance, Business Automobile Liability Insurance and Excess Liability Insurance policies shall contain provisions that specify that the policies are primary and non-contributory. Each Party shall be responsible for its respective deductibles or self-insured retentions. 18.3.7 The Commercial General Liability Insurance, Business Automobile Liability Insurance and Excess Liability Insurance policies, if written on a claims first made basis, shall be maintained in full force and effect for two (2) years after termination of this LLIA, which coverage may be in the form of extended reporting period coverage if agreed by the Parties.
18.3.8 [Not Used.]
18.3.9 Thirty (30) Calendar Days prior to the start of any work at the construction site related to Interconnection Facilities or Large Load Facility under this LLIA, and as soon as practicable after the end of each fiscal year or at the renewal of the insurance policy and in any event within ninety (90) Calendar Days thereafter, the Participating TO and the Large Load Interconnection Customer shall provide a certificate of insurance for all insurance required in this LLIA, executed by each insurer or by an authorized representative of each insurer.
18.3.10 Notwithstanding the foregoing, each Party may self-insure:
(a) to meet the minimum insurance requirements of Article 18.3.1, to the extent that it maintains a self-insurance program that is a qualified self-insurer within the state in which the Point of Interconnection is located, under the laws and regulations of such state; and
(b) to meet the minimum insurance requirements of Articles 18.3.2 through 18.3.8 to the extent it maintains a self-insurance program; provided that, such Party’s senior unsecured debt or issuer rating is BBB-, or better, as rated by Standard & Poor’s and that its self-insurance program meets the minimum insurance requirements of Articles 18.3.2 through 18.3.8. For any period of time that a Party’s senior unsecured debt rating and issuer rating are both unrated by Standard & Poor’s or
PDF page 276
44
are both rated at less than BBB- by Standard & Poor’s, such Party shall comply with the insurance requirements applicable to it under Articles 18.3.2 through 18.3.9.
(c) in the event that a Party is permitted to self-insure pursuant to this Article 18.3.10, it shall notify the other Parties that it meets the requirements to self-insure and that its self-insurance program meets the minimum insurance requirements in a manner consistent with that specified in Article 18.3.9.
18.3.11The Parties agree to report to each other in writing as soon as practical all accidents or occurrences resulting in injuries to any person, including death, and any property damage greater than $25,000, including within the scope of coverage of such insurance whether or not such coverage is sought.
Article 19. Assignment
19.1
Assignment. This LLIA may be assigned by a Party only with the written consent of the other Parties; provided that a Party may assign this LLIA without the consent of the other Parties to any Affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this LLIA; and provided further that the Large Load Interconnection Customer shall have the right to assign this LLIA, without the consent of the Participating TO for collateral security purposes to aid in providing financing for the Large Load Facility, provided that the Large Load Interconnection Customer will promptly notify the Participating TO of any such assignment. Any financing arrangement entered into by the Large Load Interconnection Customer pursuant to this Article will provide that prior to or upon the exercise of the secured party’s, trustee’s or mortgagee’s assignment rights pursuant to said arrangement, the secured creditor, the trustee or mortgagee will notify the Participating TO of the date and particulars of any such exercise of assignment right(s), including providing the Participating TO, with proof that it meets the requirements of Articles 11.3 and 18.3. Any attempted assignment that violates this Article is void and ineffective. Any assignment under this LLIA shall not relieve a Party of its obligations, nor shall a Party’s obligations be enlarged, in whole or in part, by reason thereof. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.
Article 20. Severability
20.1
Severability. If any provision in this LLIA is finally determined to be invalid, void or unenforceable by any court or other Governmental Authority having jurisdiction, such determination shall not invalidate, void or make unenforceable any other provision, agreement or covenant of this LLIA.
Article 21. Comparability
21.1
Comparability. The Parties will comply with all applicable comparability and code of conduct laws, rules and regulations, as amended from time to time.
PDF page 277
45
Article 22. Confidentiality
22.1
Confidentiality. Confidential Information shall include, without limitation, all information relating to a Party’s technology, research and development, business affairs, and pricing, and any information supplied by any of the Parties to the other Parties prior to the execution of this LLIA.
Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Parties receiving the information that the information is confidential.
If requested by any Party, the other Parties shall provide in writing the basis for asserting that the information referred to in this Article 22 warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority. Each Party shall be responsible for the costs associated with affording confidential treatment to its information.
22.1.1 Term. During the term of this LLIA, and for a period of three (3) years after the expiration or termination of this LLIA, except as otherwise provided in this Article 22, each Party shall hold in confidence and shall not disclose to any person Confidential Information.
22.1.2 Scope. Confidential Information shall not include information that the receiving Party can demonstrate: (1) is generally available to the public other than as a result of a disclosure by the receiving Party; (2) was in the lawful possession of the receiving Party on a non-confidential basis before receiving it from the disclosing Party; (3) was supplied to the receiving Party without restriction by a third party, who, to the knowledge of the receiving Party after due inquiry, was under no obligation to the disclosing Party to keep such information confidential; (4) was independently developed by the receiving Party without reference to Confidential Information of the disclosing Party; (5) is, or becomes, publicly known, through no wrongful act or omission of the receiving Party or Breach of this LLIA; or (6) is required, in accordance with Article 22.1.7 of this LLIA, Order of Disclosure, to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena, or is necessary in any legal proceeding establishing rights and obligations under this LLIA. Information designated as Confidential Information will no longer be deemed confidential if the Party that designated the information as confidential notifies the other Parties that it no longer is confidential. 22.1.3 Release of Confidential Information. No Party shall release or disclose Confidential Information to any other person, except to its employees, consultants, Affiliates (limited by the Standards of Conduct requirements set forth in Part 358 of FERC’s Regulations, 18 C.F.R. 358), subcontractors, or to parties who may be or considering providing financing to or equity participation with the Large Load Interconnection Customer, or to potential purchasers or assignees of the Large Load Interconnection Customer, on a need-to-know basis in connection with this LLIA,
PDF page 278
46
unless such person has first been advised of the confidentiality provisions of this Article 22 and has agreed to comply with such provisions. Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible for any release of Confidential Information in contravention of this Article 22.
22.1.4 Rights. Each Party retains all rights, title, and interest in the Confidential Information that each Party discloses to the other Parties. The disclosure by each Party to the other Parties of Confidential Information shall not be deemed a waiver by a Party or any other person or entity of the right to protect the Confidential Information from public disclosure.
22.1.5 No Warranties. The mere fact that a Party has provided Confidential Information does not constitute a warranty or representation as to its accuracy or completeness. In addition, by supplying Confidential Information, no Party obligates itself to provide any particular information or Confidential Information to the other Parties nor to enter into any further agreements or proceed with any other relationship or joint venture.
22.1.6 Standard of Care. Each Party shall use at least the same standard of care to protect Confidential Information it receives as it uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination. Each Party may use Confidential Information solely to fulfill its obligations to the other Parties under this LLIA or its regulatory requirements.
22.1.7 Order of Disclosure. If a court or a Governmental Authority or entity with the right, power, and apparent authority to do so requests or requires any Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the other Parties with prompt notice of such request(s) or requirement(s) so that the other Parties may seek an appropriate protective order or waive compliance with the terms of this LLIA. Notwithstanding the absence of a protective order or waiver, the Party may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose. Each Party will use Reasonable Efforts to obtain reliable assurance that confidential treatment will be accorded any Confidential Information so furnished. 22.1.8 Termination of Agreement. Upon termination of this LLIA for any reason, each Party shall, within ten (10) Calendar Days of receipt of a written request from another Party, use Reasonable Efforts to destroy, erase, or delete (with such destruction, erasure, and deletion certified in writing to the other Party) or return to the other Party, without retaining copies thereof, any and all written or electronic Confidential Information received from the other Party.
22.1.9 Remedies. The Parties agree that monetary damages would be inadequate to compensate a Party for another Party’s Breach of its obligations under this Article
22. Each Party accordingly agrees that the other Parties shall be entitled to equitable
PDF page 279
47
relief, by way of injunction or otherwise, if the first Party Breaches or threatens to Breach its obligations under this Article 22, which equitable relief shall be granted without bond or proof of damages, and the receiving Party shall not plead in defense that there would be an adequate remedy at law. Such remedy shall not be deemed an exclusive remedy for the Breach of this Article 22 but shall be in addition to all other remedies available at law or in equity. The Parties further acknowledge and agree that the covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope. No Party, however, shall be liable for indirect, incidental, or consequential or punitive damages of any nature or kind resulting from or arising in connection with this Article 22.
22.1.10 Disclosure to FERC, its Staff, or a State. Notwithstanding anything in this Article 22 to the contrary, and pursuant to 18 C.F.R. section 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence pursuant to this LLIA, the Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information. In providing the information to FERC or its staff, the Party must, consistent with 18 C.F.R. section 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Parties to this LLIA prior to the release of the Confidential Information to FERC or its staff. The Party shall notify the other Parties to the LLIA when it is notified by FERC or its staff that a request to release Confidential Information has been received by FERC, at which time any of the Parties may respond before such information would be made public, pursuant to 18 C.F.R. section 388.112. Requests from a state regulatory body conducting a confidential investigation shall be treated in a similar manner if consistent with the applicable state rules and regulations.
22.1.11 Subject to the exception in Article 22.1.10, Confidential Information shall not be disclosed by the other Parties to any person not employed or retained by the other Parties, except to the extent disclosure is: (i) required by law; (ii) reasonably deemed by the disclosing Party to be required to be disclosed in connection with a dispute between or among the Parties, or the defense of litigation or dispute; (iii) otherwise permitted by consent of the other Parties, such consent not to be unreasonably withheld; or (iv) necessary to fulfill its obligations under this LLIA or as a transmission service provider or a Balancing Authority including disclosing the Confidential Information to a Regional Transmission Organization or Independent System Operator or to a regional or national reliability organization. The Party asserting confidentiality shall notify the other Parties in writing of the information it claims is confidential. Prior to any disclosures of another Party’s Confidential Information under this subparagraph, or if any third party or Governmental Authority makes any request or demand for any of the information described in this subparagraph, the disclosing Party agrees to promptly notify the other Party in writing and agrees to assert confidentiality and cooperate with the other Party in
PDF page 280
48
seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order or other reasonable measures. Article 23. Environmental Releases
23.1
Each Party shall notify the other Parties, first orally and then in writing, of the release of any Hazardous Substances, any asbestos or lead abatement activities, or any type of remediation activities related to the Large Load Facility or the Interconnection Facilities, each of which may reasonably be expected to affect the other Parties. The notifying Party shall: (i) provide the notice as soon as practicable, provided such Party makes a good faith effort to provide the notice no later than twenty-four (24) hours after such Party becomes aware of the occurrence; and (ii) promptly furnish to the other Parties copies of any publicly available reports filed with any Governmental Authorities addressing such events.
Article 24. Information Requirements
24.1
Information Acquisition. The Participating TO and the Large Load Interconnection Customer shall submit specific information regarding the electrical characteristics of their respective facilities to each other as described below and in accordance with Applicable Reliability Standards.
24.2
Information Submission by Participating TO. The initial information submission by the Participating TO shall occur no later than one hundred eighty (180) Calendar Days prior to Trial Operation and shall include the Participating TO’s Transmission System information necessary to allow the Large Load Interconnection Customer to select equipment and meet any system protection and stability requirements, unless otherwise agreed to by the Participating TO and the Large Load Interconnection Customer. On a monthly basis the Participating TO shall provide the Large Load Interconnection Customer and, as applicable, the CAISO a status report on the construction and installation of the Participating TO’s Interconnection Facilities and Network Upgrades, including, but not limited to, the following information: (1) progress to date; (2) a description of the activities since the last report; (3) a description of the action items for the next period; and (4) the delivery status of equipment ordered.
Article 25. Information Access and Audit Rights
25.1
Information Access. Each Party (the “disclosing Party”) shall make available to the other Party information that is in the possession of the disclosing Party and is necessary in order for the other Party to: (i) verify the costs incurred by the disclosing Party for which the other Party is responsible under this LLIA; and (ii) carry out its obligations and responsibilities under this LLIA. The Parties shall not use such information for purposes other than those set forth in this Article 25.1 and to enforce their rights under this LLIA. Nothing in this Article 25 shall obligate the Participating TO to make available to a Party any third-party information in its possession or control. if making such third-party information available would violate Participating TO’s obligations the use or disclosure of such third-party information.
PDF page 281
49
25.2
Reporting of Non-Force Majeure Events. Each Party (the “notifying Party”) shall notify the other Parties when the notifying Party becomes aware of its inability to comply with the provisions of this LLIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this LLIA.
25.3
Audit Rights. Subject to the requirements of confidentiality under Article 22 of this LLIA, the Parties’ audit rights shall include audits of a Party’s costs pertaining to such Party’s performance or satisfaction of obligations owed to the other Party under this LLIA, calculation of invoiced amounts and each such Party’s actions in an Emergency Condition. The Large Load Interconnection Customer and the Participating TO shall each have the right, during normal business hours, and upon prior reasonable notice to the other Party, to audit at its own expense the other Party’s accounts and records pertaining to either such Party’s performance or either such Party’s satisfaction of obligations owed to the other Party under this LLIA. Any audit authorized by this Article shall be performed at the offices where such accounts and records are maintained and shall be limited to those portions of such accounts and records that relate to each such Party’s performance and satisfaction of obligations under this LLIA. Each such Party shall keep such accounts and records for a period equivalent to the audit rights periods described in Article 25.4.
25.4
Audit Rights Periods.
25.4.1 Audit Rights Period for Construction-Related Accounts and Records. Accounts and records related to the design, engineering, procurement, and construction of Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades constructed by the Participating TO shall be subject to audit for a period of twenty-four (24) months following the Participating TO’s issuance of a final invoice in accordance with Article 12.2. Accounts and records related to the design, engineering, procurement, and construction of Participating TO’s Interconnection Facilities constructed by the Large Load Interconnection Customer shall be subject to audit and verification by the Participating TO for a period of twenty-four (24) months following the Large Load Interconnection Customer’s issuance of a final invoice.
25.4.2 Audit Rights Period for All Other Accounts and Records. Accounts and records related to a Party’s performance or satisfaction of all obligations under this LLIA other than those described in Article 25.4.1 shall be subject to audit as follows: (i) for an audit relating to cost obligations, the applicable audit rights period shall be twenty-four (24) months after the auditing Party’s receipt of an invoice giving rise to such cost obligations; and (ii) for an audit relating to all other obligations, the applicable audit rights period shall be twenty-four (24) months after the event for which the audit is sought.
PDF page 282
50
25.5
Audit Results. If an audit by the Large Load Interconnection Customer or the Participating TO determines that an overpayment or an underpayment has occurred with respect to the other Party, a notice of such overpayment or underpayment shall be given to the other Party together with those records from the audit which supports such determination. The Party that is owed payment shall render an invoice to the other Party and such invoice shall be paid pursuant to Article 12 hereof.
Article 26. Subcontractors
26.1
General. Nothing in this LLIA shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this LLIA; provided, however, that each Party shall require its subcontractors to comply with all applicable terms and conditions of this LLIA in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor. 26.2
Responsibility of Principal. The creation of any subcontract relationship shall not relieve the hiring Party of any of its obligations under this LLIA. The hiring Party shall be fully responsible to the other Parties for the acts or omissions of any subcontractor the hiring Party hires as if no subcontract had been made; provided, however, that in no event shall the Participating TO, or, as applicable, the CAISO be liable for the actions or inactions of the Large Load Interconnection Customer or its subcontractors with respect to obligations of the Large Load Interconnection Customer under Article 5 of this LLIA. Any applicable obligation imposed by this LLIA upon the hiring Party shall be equally binding upon, and shall be construed as having application to, any subcontractor of such Party.
26.3
No Limitation by Insurance. The obligations under this Article 26 will not be limited in any way by any limitation of subcontractor’s insurance.
Article 27. Disputes
All disputes arising out of or in connection with this LLIA shall be settled in accordance with this Article 27.
27.1
Submission. In the event either Party has a dispute, or asserts a claim, that arises out of or in connection with this LLIA or its performance, such Party (the “disputing Party”) shall provide the other Party with written notice of the dispute or claim (“Notice of Dispute”). Such dispute or claim shall be referred to a designated senior representative of each Party for resolution on an informal basis as promptly as practicable after receipt of the Notice of Dispute by the other Party. In the event the designated representatives are unable to resolve the claim or dispute through unassisted or assisted negotiations within thirty (30) Calendar Days of the other Party’s receipt of the Notice of Dispute, such claim or dispute may, upon mutual agreement of the Parties, be submitted to arbitration and resolved in accordance with the arbitration procedures set forth below. In the event the Parties do not agree to submit such claim or dispute to arbitration, each Party may exercise whatever rights and remedies it may have in equity or at law consistent with the terms of this LLIA.
PDF page 283
51
27.2
External Arbitration Procedures. Any arbitration initiated under this LLIA shall be conducted before a single neutral arbitrator appointed by the Parties. If the Parties fail to agree upon a single arbitrator within ten (10) Calendar Days of the submission of the dispute to arbitration, each Party shall choose one arbitrator who shall sit on a three (3)- member arbitration panel. The two arbitrators so chosen shall within twenty (20) Calendar Days select a third arbitrator to chair the arbitration panel. In either case, the arbitrators shall be knowledgeable in electric utility matters, including electric transmission and bulk power issues, and shall not have any current or past substantial business or financial relationships with any party to the arbitration (except prior arbitration). The arbitrator(s) shall provide each of the Parties an opportunity to be heard and, except as otherwise provided herein, shall conduct the arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association (“Arbitration Rules”) and any applicable FERC regulations; provided, however, in the event of a conflict between the Arbitration Rules and the terms of this Article 27, the terms of this Article 27 shall prevail.
27.3
Arbitration Decisions. Unless otherwise agreed by the Parties, the arbitrator(s) shall render a decision within ninety (90) Calendar Days of appointment and shall notify the Parties in writing of such decision and the reasons therefor. The arbitrator(s) shall be authorized only to interpret and apply the provisions of this LLIA and shall have no power to modify or change any provision of this LLIA in any manner. The decision of the arbitrator(s) shall be final and binding upon the Parties, and judgment on the award may be entered in any court having jurisdiction. The decision of the arbitrator(s) may be appealed solely on the grounds that the conduct of the arbitrator(s), or the decision itself, violated the standards set forth in the Federal Arbitration Act or the Administrative Dispute Resolution Act. The final decision of the arbitrator(s) must also be filed with FERC if it affects jurisdictional rates, terms and conditions of service, Interconnection Facilities, or Network Upgrades.
27.4
Costs. Each Party shall be responsible for its own costs incurred during the arbitration process and for the following costs, if applicable: (1) the cost of the arbitrator chosen by the Party to sit on the three (3) member panel and one half of the cost of the third arbitrator chosen; or (2) one half (1/2) the cost of the single arbitrator jointly chosen by the Parties.
Article 28. Representations, Warranties and Covenants
28.1
General. Each Party makes the following representations, warranties and covenants: 28.1.1 Good Standing. Such Party is duly organized, validly existing and in good standing under the laws of the state in which it is organized, formed, or incorporated, as applicable; that it is qualified to do business in the state or states in which the Large Load Facility, Interconnection Facilities and Network Upgrades owned by such Party, as applicable, are located; and that it has the corporate power and authority to own its properties, to carry on its business as now being conducted and to enter into this LLIA and carry out the transactions contemplated hereby and perform and
PDF page 284
52
carry out all covenants and obligations on its part to be performed under and pursuant to this LLIA.
28.1.2 Authority. Such Party has the right, power and authority to enter into this LLIA, to become a Party hereto and to perform its obligations hereunder. This LLIA is a legal, valid and binding obligation of such Party, enforceable against such Party in accordance with its terms, except as the enforceability thereof may be limited by applicable bankruptcy, insolvency, reorganization or other similar laws affecting creditors’ rights generally and by general equitable principles (regardless of whether enforceability is sought in a proceeding in equity or at law). 28.1.3 No Conflict. The execution, delivery and performance of this LLIA does not violate or conflict with the organizational or formation documents, or bylaws or operating agreement, of such Party, or any judgment, license, permit, order, material agreement or instrument applicable to or binding upon such Party or any of its assets.
28.1.4 Consent and Approval. Such Party has sought or obtained, or, in accordance with this LLIA will seek or obtain, each consent, approval, authorization, order, or acceptance by any Governmental Authority in connection with the execution, delivery and performance of this LLIA, and it will provide to any Governmental Authority notice of any actions under this LLIA that are required by Applicable Laws and Regulations.
Article 29. [Reserved]
Article 30. Miscellaneous
30.1
Binding Effect. This LLIA and the rights and obligations hereof, shall be binding upon and shall inure to the benefit of the successors and assigns of the Parties hereto. 30.2
Conflicts. In the event of a conflict between the body of this LLIA and any attachment, appendices or exhibits hereto, the terms and provisions of the body of this LLIA shall prevail and be deemed the final intent of the Parties.
30.3
Rules of Interpretation. This LLIA, unless a clear contrary intention appears, shall be construed and interpreted as follows: (1) the singular number includes the plural number and vice versa; (2) reference to any person includes such person’s successors and assigns but, in the case of a Party, only if such successors and assigns are permitted by this LLIA, and reference to a person in a particular capacity excludes such person in any other capacity or individually; (3) reference to any agreement (including this LLIA), document, instrument or tariff means such agreement, document, instrument, or tariff as amended or modified and in effect from time to time in accordance with the terms thereof and, if applicable, the terms hereof; (4) reference to any Applicable Laws and Regulations means such Applicable Laws and Regulations as amended, modified, codified, or reenacted, in whole or in part, and in effect from time to time, including, if applicable, rules and regulations promulgated thereunder; (5) unless expressly stated otherwise, reference to any Article, Section or Appendix means such Article of this LLIA or such
PDF page 285
53
Appendix to this LLIA, or such Section to the LLIP or such Appendix to the LLIP, as the case may be; (6) “hereunder”, “hereof”, “herein”, “hereto” and words of similar import shall be deemed references to this LLIA as a whole and not to any particular Article or other provision hereof or thereof; (7) “including” (and with correlative meaning “include”) means including without limiting the generality of any description preceding such term; and (8) relative to the determination of any period of time, “from” means “from and including”, “to” means “to but excluding” and “through” means “through and including”.
30.4
Entire Agreement. This LLIA, including all Appendices and Schedules attached hereto, constitutes the entire agreement among the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between or among the Parties with respect to the subject matter of this LLIA. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, any Party’s compliance with its obligations under this LLIA.
30.5
No Third-Party Beneficiaries. This LLIA is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.
30.6
Waiver. The failure of a Party to this LLIA to insist, on any occasion, upon strict performance of any provision of this LLIA will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.
Any waiver at any time by either Party of its rights with respect to this LLIA shall not be deemed a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, duty of this LLIA. Termination or Default of this LLIA for any reason by the Large Load Interconnection Customer shall not constitute a waiver of the Large Load Interconnection Customer’s legal rights to obtain an interconnection from the Participating TO. Any waiver of this LLIA shall, if requested, be provided in writing. 30.7
Headings. The descriptive headings of the various Articles of this LLIA have been inserted for convenience of reference only and are of no significance in the interpretation or construction of this LLIA.
30.8
Multiple Counterparts. This LLIA may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument. 30.9
Amendment. The Parties may by mutual agreement amend this LLIA by a written instrument duly executed by all of the Parties. Such amendment shall become effective and a part of this LLIA upon satisfaction of all Applicable Laws and Regulations. 30.10 Modification by the Parties. The Parties may by mutual agreement amend the Appendices to this LLIA by a written instrument duly executed by all of the Parties. Such
PDF page 286
54
amendment shall become effective and a part of this LLIA upon satisfaction of all Applicable Laws and Regulations.
30.11 Reservation of Rights. The Large Load Interconnection Customer and the Participating TO shall have the right to make a unilateral filing with FERC to modify this LLIA pursuant to sections 205 and 206 of the Federal Power Act or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder; provided that each Party shall have the right to protest any such filing by another Party and to participate fully in any proceeding before FERC in which such modifications may be considered. Nothing in this LLIA shall limit the rights of the Parties or of FERC under sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations thereunder, except to the extent that the Parties otherwise mutually agree as provided herein.
30.12 No Partnership. This LLIA shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership among the Parties or to impose any partnership obligation or partnership liability upon any Party. No Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, another Party. 30.13 Joint and Several Obligations. Except as otherwise provided in this LLIA, the obligations of the CAISO, the Participating TO, and the Large Load Interconnection Customer are several, and are neither joint nor joint and several.
PDF page 287
IN WITNESS WHEREOF, the Parties have executed this LLIA in multiple originals, each of which shall constitute and be an original effective agreement among the Parties. [Insert name of Large Load Interconnection Customer]
By: _________________________
Name: ______________________
Title: _______________________
Date: _______________________
[Insert name of Participating TO]
By: _________________________
Name: ______________________
Title: _______________________
Date: _______________________
PDF page 288
Appendices to LLIA
Appendix A Interconnection Facilities, Network Upgrades and Distribution Upgrades Appendix B Milestones
Appendix C Interconnection Details
Appendix D Security Arrangements Details
Appendix E Commercial Operation Date
Appendix F Addresses for Delivery of Notices and Billings
Appendix G Large Load Interconnection Customer’s Share of Costs of Network Upgrades for Applicable Project Group
Appendix H Co-Location and Behind-the-Meter Generation Provisions
PDF page 289
Appendix A
Appendix A
Interconnection Facilities, Network Upgrades and Distribution Upgrades
A-1: Facilities and Upgrades
Participating TO will coordinate with the Large Load Interconnection Customer to ensure that all local state utility franchise rules and regulations are adhered to through, among other things, arrangements that provide for station service directly from the local franchised public utility. Participating TO will coordinate with the Large Load Interconnection Customer to facilitate any necessary pseudo-tie or similar arrangement for the delivery of power into the CAISO BAA.
1. Interconnection Facilities:
(a) [insert Large Load Interconnection Customer’s Interconnection Facilities]:
(b) [insert Participating TO’s Interconnection Facilities]:
2. Network Upgrades:
(c) [insert Other Network Upgrades]:
(i)
(ii) [insert Participating TO’s Network Upgrades]
3. Distribution Upgrades:
A-2: FILI
1. Large Load Interconnection Customer has elected to take FILI until the Network Upgrades identified in this Appendix A have reached Commercial Operation.
2. The following documents and process shall be executed, undertaken and provided for FILI Interconnection Service applicants:
a. A pro forma Flexible Interconnection Service Addendum to the pro forma Large Load Interconnection Agreement (or, alternatively, a standalone pro forma Flexible Interconnection Agreement) that identifies the roles and responsibilities for impacted parties that will identify customer- and site-specific equipment and systems necessary to operationalize FILI service;
b. Study methodologies will be revised to recognize the unique operational characteristics of flexible large loads;
PDF page 290
Appendix A
c. Operational requirements for FILI service will be revised, including curtailment implementation mechanisms and data reporting;
d. Cost responsibility provisions will be revised, including any financial security during the conditional service period;
e. Procedures for the transition-to-firm Interconnection Service provisions for FILI will be implemented that specify the automatic conversion to firm service upon Network Upgrade completion;
f. Coordination mechanisms shall be promulgated that address coordination between FILI Service and the Participating TO study process; and
g. Operational requirements shall be revised to address the management of longer- duration curtailments in coordination with, as applicable, the CAISO.
3. Further, the following considerations will be addressed in the FILI application process: a. Curtailment triggers and operating conditions and the process for establishing curtailment parameters;
b. Deployment priorities between FILI and non-FILI applicants;
c. Scheduling treatment between FILI and non-FILI Large Load Facilities; d. The relationship between operational restrictions and study assumptions; e. Potential interactions with scheduling, dispatch, and price formation; and f. How the FILI Interconnection Service may apply to co-located load arrangements [and existing generation resources], particularly where load flexibility can reduce transmission impacts or support continued wholesale market participation.
PDF page 291
Appendix B
Appendix B
Milestones
PDF page 292
Appendix C
Appendix C
Interconnection Details
PDF page 293
Appendix D
Appendix D
Security Arrangements Details
Infrastructure security of CAISO Controlled Grid equipment and operations and control hardware and software is essential to ensure day-to-day CAISO Controlled Grid reliability and operational security. FERC will expect the Participating TOs, CAISO, market participants, and Large Load Interconnection Customers interconnected to the CAISO Controlled Grid to comply with Applicable Reliability Criteria. All public utilities will be expected to meet basic standards for system infrastructure and operational security, including physical, operational, and cyber- security practices.
PDF page 294
Appendix E
Appendix E
[This Appendix E sets forth a form of letter to be provided by the Large Load Interconnection Customer to the CAISO and Participating TO to provide formal notice of the Commercial Operation of a Large Load Facility.]
[Date]
[CAISO Address]
[Participating TO Address]
Re:
__________ Large Load Facility
Dear ____________:
On [Date] [Large Load Interconnection Customer] has completed Trial Operation of Unit No. ___. This letter confirms that [Large Load Interconnection Customer] commenced Commercial Operation of Unit No. ___ at the Large Load Facility, effective as of [Date plus one day] and that [Large Load Interconnection Customer] provided the CAISO’s operations personnel advance notice of its intended Commercial Operation Date no less than five (5) Business Days prior to that date.
Thank you.
[Signature]
[Large Load Interconnection Customer Representative]
PDF page 295
Appendix F
Appendix F
Addresses for Delivery of Notices and Billings
Notices:
Participating TO:
[To be supplied.]
Large Load Interconnection Customer:
[To be supplied.]
CAISO:
[To be supplied.]
Billings and Payments:
Participating TO:
[To be supplied.]
Large Load Interconnection Customer:
[To be supplied.]
CAISO:
[To be supplied.]
Alternative Forms of Delivery of Notices (telephone, facsimile or e-mail): Participating TO:
[To be supplied.]
Large Load Interconnection Customer:
PDF page 296
Appendix F
[To be supplied.]
CAISO:
[To be supplied.]
PDF page 297
Appendix G
Appendix G
Large Load Interconnection Customer’s Share of Costs of Network Upgrades for Applicable Project Group
PDF page 298
Appendix H
Appendix H Co-Location and Behind-the-Meter Generation Provisions
H.1
Purpose and Scope. This Appendix H sets forth the terms that apply where the Large Load Facility is, or will be: (a) physically connected to the facilities of an existing or planned generating facility on the generator interconnection customer’s side of the Point of Interconnection (“Co- Located Generation”); or (b) served by a generating facility or energy storage device that delivers energy to the Large Load Facility without using the transmission system or any distribution facilities (“Behind-the-Meter Generation”). The Participating TO’s Tariff governs the interconnection of the Large Load Facility, and the CAISO Tariff governs the interconnection of any generating facility that injects, or may inject, energy into the CAISO Controlled Grid. This Appendix H memorializes the procedures by which the Participating TO, the CAISO, and the Large Load Interconnection Customer will coordinate those processes. Station power load, and generation that exclusively serves station power load, are excluded from this Appendix H. H.2
Description of Co-Located Generation and Behind-the-Meter Generation. The Co- Located Generation and/or Behind-the-Meter Generation serving the Large Load Facility, if any, is described as follows: [Identify facility name, owner/operator, technology type, nameplate capacity (MW), storage capacity (MW/MWh), metering configuration, and whether the facility is:
(i) back-up generation used only during outages or islanding; (ii) non-exporting Behind-the-Meter Generation; or (iii) generation that may export energy to the CAISO Controlled Grid.] H.3
Non-Exporting Configurations. Back-up generation used only during outages or islanding, and non-exporting Behind-the-Meter Generation, do not require a CAISO generator interconnection request and may be accommodated under the Participating TO’s Tariff, provided that the Large Load Interconnection Customer installs and maintains control technologies and/or protection systems sufficient to ensure that no energy is injected into the CAISO Controlled Grid and that such facilities do not adversely affect the CAISO Controlled Grid. The Large Load Interconnection Customer shall provide the Participating TO with all generation characteristics of such facilities, and the Participating TO shall provide that information to the CAISO in accordance with Article H.6.
H.4
Power Injection Triggers CAISO Generator Interconnection Process. Any injection, or proposed capability to inject, energy from Co-Located Generation or Behind-the-Meter Generation into the CAISO Controlled Grid shall require the generating facility to submit an interconnection request and be studied under the CAISO Tariff, including screening and participation in the applicable cluster study, and to execute a generator interconnection agreement with the CAISO and the Participating TO (or a non-conforming agreement or bridging agreement where appropriate) before any such injection occurs. Scoring, financial requirements, and study results shall be based on the interconnection capacity requested, which may be less than the generating facility’s maximum output. The generating facility may exercise all rights available under the CAISO Tariff, including surplus interconnection service, grid enhancing technologies, and phasing. Any participating generator shall also complete the CAISO new resource implementation process and execute a CAISO Participating Generator Agreement. No injection into the CAISO Controlled Grid is authorized under this LLIA, and any unauthorized injection shall be a Breach of this LLIA.
PDF page 299
Appendix H
H.5
Coordination Procedures. Where Article H.4 applies, the Parties shall coordinate as follows: (a) the Large Load Interconnection Customer shall submit comprehensive information on both the Large Load Facility and the generating facility in the CAISO resource interconnection process and the Participating TO load interconnection process; (b) the Participating TO and the CAISO shall exchange and compare information to ensure that the load and generation studies are consistent with the requested mode of operation and type of service, and shall seek to align load and generation study timing so that studies may proceed concurrently; (c) the generation study shall commence with the Large Load Facility assumptions and reflect the combined impact of the Large Load Facility and the generating facility as requested; (d) a request to remove or add a co- located load after commencement of studies shall be made under the Participating TO’s tariff and evaluated by the Participating TO and the CAISO Tariff.
H.6
Information Requirements. In addition to the information required under the CAISO resource interconnection process and the operational requirements of this LLIA, the Large Load Interconnection Customer shall provide to the Participating TO (which shall provide it to the CAISO) and, where Article H.4 applies, to the CAISO: (a) the expected presence and range of energy consumption characteristics of the Large Load Facility; (b) minimum and maximum generator operating capabilities; (c) generator operating characteristics when the Large Load Facility is at its minimum level; (d) market participation status, if any; (e) any load services requested when the generator is offline; and (f) for non-exporting or non-participating generation, all generation characteristics. The Large Load Interconnection Customer shall notify the Participating TO and the CAISO of any material change to such information, and forecasts submitted by the applicable Scheduling Coordinator shall reflect Co-Located Generation and Behind-the-Meter Generation impacts on the load forecast.
H.7
Metering, Storage, and Settlement. The Participating TO shall require the Large Load Facility to be sub-metered independent of any Co-Located Generation or Behind-the-Meter Generation, and the applicable Scheduling Coordinator shall report such meter values separately so that regulation and black start services are assessed on a gross load basis. Any wholesale energy storage resource shall remain operationally separate from, and separately metered and settled from, the Large Load Facility, and its energy shall not be commingled with the Large Load Facility. Station power load shall be metered separately consistent with Local Regulatory Authority requirements.
H.8
Full Load Exposure. The Interconnection Service provided under this LLIA shall be studied and provided on the basis of the full Demand of the Large Load Facility, without reduction for Co-Located Generation or Behind-the-Meter Generation, unless the Large Load Interconnection Customer has elected a flexible interconnection service with enforceable control technologies and/or protection systems that limit withdrawals from the CAISO Controlled Grid. H.9
CAISO Role; Order of Precedence. The CAISO’s obligations under this LLIA with respect to the Large Load Facility are limited to those expressly set forth in this Appendix H and in the generator interconnection agreement, Participating Generator Agreement, or other CAISO agreement applicable to any Co-Located Generation, and the CAISO shall have no responsibility for the financing or construction of facilities required solely for the Large Load Facility.
PDF page 300
Appendix IV
Attachment 4
Interconnection Financial Security
for Interconnection Requests Processed under the Large Load Interconnection Process and Timeline
PDF page 301
2
Attachment 4
to the DCRT Large Load Interconnection Process and Timeline
DCRT TO Tariff, Appendix IV
INTERCONNECTION FINANCIAL SECURITY
Defined Terms:
Construction Activities shall mean any activities related to the construction of the Network Upgrades, including but not limited to equipment procurement, engineering, construction and associated activities.
Current Cost Responsibility shall mean the Large Load Interconnection Customer’s current allocated costs for Network Upgrades, not to exceed the Maximum Cost Responsibility, in each case pursuant to Section 4 of the Facilities Study Agreement. This cost is used to calculate the Large Load Interconnection Customer’s Interconnection Financial Security requirement.
Maximum Cost Responsibility (MCR) shall mean, pursuant to this Attachment 4 and the Facilities Study Agreement, the full cost of: (1) assigned Network Upgrades and (2) Participating Transmission Operator’s (TO) Interconnection Facilities.
1. Types of Interconnection Financial Security.
The Interconnection Financial Security posted by a Large Load Interconnection Customer may be any combination of the following types of Interconnection Financial Security provided in favor of the Participating TO:
(a) an irrevocable and unconditional letter of credit issued by a bank or financial institution that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s;
(b) an irrevocable and unconditional surety bond issued by an insurance company that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s;
(c) an unconditional and irrevocable guaranty issued by a company that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s;
(d) a cash deposit standing to the credit of the Participating TO in an interest- bearing escrow account maintained at a bank or financial institution that is reasonably acceptable to the Participating TO;
(e) a certificate of deposit in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s; or
PDF page 302
3
(f) a payment bond certificate in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poors or A2 or better by Moody’s.
Interconnection Financial Security instruments as listed above shall be in such form as the Participating TO may reasonably require from time to time by notice to Large Load Interconnection Customers or in such other form as has been evaluated and approved as reasonably acceptable by the Participating TO.
The Participating TO shall publish and maintain standardized forms related to the types of Interconnection Financial Security listed above which shall be accessible on the Participating TO’S Website. The Participating TO shall require the use of standardized forms of Interconnection Financial Security to the greatest extent possible. If at any time the guarantor of the Interconnection Financial Security fails to maintain the credit rating required by this Section 1, the Large Load Interconnection Customer shall provide to the Participating TO replacement Interconnection Financial Security meeting the requirements of this Section 1 within five (5) Business Days of the change in credit rating.
Interest on a cash deposit standing to the credit of the Participating TO in an interest- bearing escrow account under Section 1(d) will accrue to the account of the Large Load Interconnection Customer.
2. Interconnection Financial Security-Initial Posting for Large Load Interconnection Customers.
2.1 Each Large Load Interconnection Customer shall post, with notice to the Participating TO, two (2) separate Interconnection Financial Security instruments:
(i) a posting relating to the applicable Network Upgrades; and (ii) a posting relating to the Participating TO’s Interconnection Facilities.
2.2 Timing of Postings. The postings set forth in this Section 2 shall be made any time after the issuance of the Facilities Study report but no later than ninety (90) calendar days after issuance of the Facilities Study report for Large Load Interconnection.
2.3 Revised Study Reports. If the Participating TO revises a Facilities Study, the initial postings will be due from the Large Load Interconnection Customer by the later of ninety (90) calendar days after issuance of the original Facilities Study Report or forty (40) calendar days after issuance of the revised Facilities Study report.
PDF page 303
4
2.4 Posting Amount for Network Upgrades.
2.4.1 Large Load Interconnection Customers. Each Large Load
Interconnection Customer for a Large Load Facility shall post an Interconnection Financial Security instrument relating to the Network Upgrades assigned to such Large Load Interconnection Customer pursuant to the Facilities Study.
The posting amount for such Network Upgrades shall equal the lesser of:
(i) fifteen percent (15%) of the Current Cost Responsibility assigned to the Large Load Interconnection Customer in the Facilities Study for Network Upgrades; (ii) $20,000 per megawatt of electrical load of the Large Load Facility or the amount of megawatt increase in the load of each existing Large Load Facility as listed by the Large Load Interconnection Customer in its Large Load Interconnection Application, including any requested modifications thereto; or (iii) $7,500,000, but in no event less than $500,000.
2.5 Posting Amount for Participating TO Interconnection Facilities. 2.5.1 Large Load Interconnection Customers. Each Large Load
Interconnection Customer for a Large Load Facility shall post an Interconnection Financial Security instrument in an amount equal to the lesser of: (i) fifteen percent (15%) of the Current Cost Responsibility assigned to the Large Load Interconnection Customer in the Facilities Study for Participating TO’s Interconnection Facilities; (ii) $20,000 per megawatt of electrical load of the Large Load Facility or the amount of megawatt increase in the load of each existing Large Load Facility as listed by the Large Load Interconnection Customer in its Large Load Interconnection Application including any requested modifications thereto; or (iii) $7,500,000, but in no event less than $500,000. 2.6 Cost Estimates Less than Minimum Posting Amounts. If (1) the Current Cost Responsibility of the assigned Network Upgrades, (2) the allocated costs of the Participating TO Interconnection Facilities, or (3) both are less than the respective minimum posting amounts that would apply under Sections 2.3.1 or 2.4.1, then the posting amount required will equal the Current Cost Responsibility of the Assigned Network Upgrades or the allocated costs for Participating TO Interconnection Facilities, as applicable.
2.7 Consequences for Failure to Post. The failure by a Large Load Interconnection Customer to timely post the Interconnection Financial Security required by this Attachment 4 shall result in the Large Load Interconnection Application being deemed withdrawn. The Large Load Interconnection Customer shall provide the Participating TO and the Participating TO with written notice that it has posted the required Interconnection Financial Security no later than the applicable final day for posting. The failure by a Large Load Interconnection Customer to timely
PDF page 304
5
post the Interconnection Financial Security required by this Section 2 shall result in the Large Load Interconnection Application being deemed withdrawn. The Large Load Interconnection Customer shall provide the Participating TO with written notice that it has posted the required Interconnection Financial Security no later than the applicable final day for posting.
2.8 Re-calculation of Initial Posting Requirement. If withdrawals, modifications, or system changes occur after the completion of the Facilities Study, and the Participating TO, is able to reasonably determine, prior to the date for initial posting of Interconnection Financial Security, that as a result of such decrease (solely or in combination with other modifications made by Large Load Interconnection Customers) some of the Network Upgrades and/or Participating TO Interconnection Facilities identified in the Facilities Study will no longer be required, then the calculation of the initial posting of Interconnection Financial Security will not include those Network Upgrades and/or Participating TO Interconnection Facilities. Such determination will be made based on the Participating TO’s best engineering judgment and will not include any re-studies.
3. Interconnection Financial Security –Second and Third Postings for Large Load Interconnection Customers.
3.1 Second Posting for Large Load Interconnection Customers.
3.1.1 Each Large Load Interconnection Customer shall make second postings, with notice to the Participating TO, of two separate Interconnection Financial Security instruments: (i) a second posting relating to the Network Upgrades; and (ii) a second posting relating to the Participating TO’s Interconnection Facilities. The Current Cost Responsibility for calculating the second and third Interconnection Financial Security postings for Large Load Interconnection Customers shall be set forth in the Facilities Study report.
3.1.2 The postings set forth in this Section 3 for second postings for Large Load Interconnection Customers shall be made any time after issuance of the Facilities Study report but no later than thirty (30) calendar days prior to the date on which the Facilities Study report provides that such amounts will be needed to fund long lead time equipment procurement as part of the Construction Activities for the Network Upgrades or the Participating TO’s Interconnection Facilities, whichever is earlier.
3.2 Third Posting for Large Load Interconnection Customers.
3.2.1 After the second posting for a Large Load Interconnection Customer has been made but no later than thirty (30) calendar days after the date on which the Participating TO provides notice that Participating TO is obligated to provide security needed to fund any additional obligations for
PDF page 305
6
Network Upgrades or Participating TO’s Interconnection Facilities on behalf of the Large Load Interconnection Customer, whichever is earlier, the Large Load Interconnection Customer shall modify the two (2) separate Interconnection Financial Security instruments posted pursuant to Section 3.1.
3.3 Determining Refundable Portion of the Interconnection Financial Security for Network Upgrades.
3.3.1 Withdrawal Between the First Posting and the Deadline for the Second Posting. If the Large Load Interconnection Customer either withdraws its Large Load Interconnection Application or terminates its Large Load Interconnection Agreement (LLIA) at any time between the initial posting and the deadline for the second posting of the Interconnection Financial Security for applicable Network Upgrades, then the Participating TO shall liquidate the Interconnection Financial Security for the applicable Network Upgrades and reimburse the Large Load Interconnection Customer the lesser of:
a. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) less (all costs and expenses incurred or irrevocably committed to finance Pre- Construction Activities for Network Upgrades on behalf of the Large Load Interconnection Customer); or
b. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) minus the lesser of fifty percent (50%) of the value of the posted
Interconnection Financial Security for Network Upgrades or $10,000 per requested and approved, pre-downsized megawatt of the Large Load Facility load.
3.3.2 Withdrawal Between the Second Posting and the Commencement of Construction Activities. If the Large Load Interconnection Customer either withdraws or terminates its LLIA at any time after the second posting of the Interconnection Financial Security for applicable Network Upgrades and the Commencement of Construction Activities for such Network Upgrades, then the Participating TO shall liquidate the Interconnection Financial Security for the applicable Network Upgrades and reimburse the Large Load Interconnection Customer the lesser of:
a. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) less (all costs and expenses incurred or irrevocably committed to finance Pre- Construction Activities for Network Upgrades on behalf of the Large Load Interconnection Customer) and less (any posting
PDF page 306
7
reduction due to the Large Load Interconnection Customer’s election to self-build Stand Alone Network Upgrades); or b. the Interconnection Financial Security plus (any other provided security plus any separately provided capital) minus the lesser of fifty percent (50%) of the value of the posted
Interconnection Financial Security for Network Upgrades or $20,000 per requested and approved, pre-downsized megawatt of the Large Load Facility load.
3.3.3 Special Treatment Based on Failure to Obtain Necessary Permit or Authorization from Governmental Authority. If, at any time after the second posting requirement, the Large Load Interconnection Customer withdraws the Large Load Interconnection Application or terminates the LLIA, as applicable, because the Large Load Interconnection Customer received a final denial from the primary issuing Governmental Authority for authorization necessary for the construction or operation of the Large Load Facility, and the Network Upgrades to be financed by the Large Load Interconnection Customer are also to be financed by one or more other Large Load Interconnection Customers, then the provisions of Section 3.3.2 apply, except that the Large Load Interconnection Customer shall not be reimbursed for its share of any actual costs incurred or irrevocably committed by the Participating TO for Construction Activities.
3.3.4 After Commencement of Construction Activities. Once Construction Activities on Network Upgrades on behalf of the Large Load Interconnection Customer commence, any withdrawal of the Large Load Interconnection Application or termination of the LLIA by the Large Load Interconnection Customer will be treated as follows:
The Participating TO shall liquidate the Interconnection Financial Security, or balance thereof, posted by the Large Load Interconnection Customer for Network Upgrades at the time of withdrawal.
To the extent the amount of the liquidated Interconnection Financial Security plus capital, if any, separately provided by the Large Load Interconnection Customer to satisfy its obligation to finance Network Upgrades exceeds the total cost responsibility for Network Upgrades assigned to the Large Load Interconnection Customer, the Participating TO shall remit to the Large Load Interconnection Customer the excess amount.
Withdrawal of a Large Load Interconnection Application or termination of a LLIA shall result in the release to the Large Load Interconnection Customer of any Interconnection Financial Security posted by the Large Load Interconnection Customer for Participating TO Interconnection Facilities, except with respect to any amounts necessary to pay for costs
PDF page 307
8
incurred or irrevocably committed by the Participating TO on behalf of the Large Load Interconnection Customer for the Participating TO’s Interconnection Facilities and for which the Participating TO has not been reimbursed in accordance with this Attachment 4. Withdrawal of a Large Load Interconnection Application or termination of a LLIA shall result in the release to the Large Load Interconnection Customer of any Interconnection Financial Security posted by the Large Load Interconnection Customer for Participating TO Interconnection Facilities, except with respect to any amounts necessary to pay for costs incurred or irrevocably committed by the Participating TO on behalf of the Large Load Interconnection Customer for the Participating TO’s Interconnection Facilities and for which the Participating TO has not been reimbursed in accordance with this Section 3.3.4.
3.3.5 Accounting by The Participating TO. Within twenty (20) calendar days of any liquidating event, the Participating TO shall provide the Participating TO and Large Load Interconnection Customer with an accounting of the disposition of the proceeds of the liquidated Interconnection Financial Security and remit to the Participating TO all proceeds not otherwise reimbursed to the Large Load Interconnection Customer or applied to costs incurred or irrevocably committed by the Participating TO on behalf of the Large Load Interconnection Customer in accordance with this Attachment 4.