ER27-512-000 · 2026-11-16 · DCR Transmission, L.L.C.

Proposed TO Tariff Revisions

DCR Transmission, L.L.C. files tariff revisions under section 205 on November 16, 2026, in ER27-512-000, answering the CAISO show cause order. It owns the Ten West Link, a 125-mile 500 kV line, and adds a new Appendix IV with large load interconnection procedures, a pro forma agreement modeled on CAISO's generator agreement, and an interim service. It adds no new transmission service.

Asks FERC to: Accept the revisions effective February 15, 2027.

Filed under section 205 to answer the E-10 show cause order. It adds a study process, an interconnection agreement and an interim service, handles cost responsibility through reimbursement terms, and leaves new transmission services to CAISO.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)

Key points

  1. DCR is a single-asset owner whose line crosses the California-Arizona border.
    DCRT owns and operates the 125-mile, 500 kilovolt Ten West Link Transmission Line PDF p. 2
  2. It notes the other parties held other views but tailors its filing to its position as a single-asset owner.
    tailored its proposed tariff revisions to its unique situation as a single-asset PTO whose transmission line traverses the California-Arizona border PDF p. 6
  3. It proposes no new transmission service, deferring to CAISO.
    DCRT has not proposed additional or revised transmission services in this filing PDF p. 6
  4. Its study steps average about 85 days, within the 60 to 90 day range FERC set.
    these steps will average roughly 85 calendar days from start to finish, meeting the OSC Order’s target of 60–90 days PDF p. 11
  5. Its pro forma large load interconnection agreement is modeled on CAISO's generator agreement.
    generally modeled on the CAISO’s pro forma Large Generator Interconnection Agreement (“LGIA”) PDF p. 11
  6. Co-located generation that exports must still go through CAISO's generator process.
    Any generating facility that will export energy to the CAISO Controlled Grid, however, must interconnect through the CAISO’s GIDAP and execute a Commission-accepted LGIA PDF p. 16
  7. The interim service lasts until the identified upgrades reach commercial operation.
    a Large Load Interconnection Customer may elect to take FILI Service until the Network Upgrades identified in Appendix A have achieved Commercial Operation PDF p. 19
  8. Large load facilities are reimbursed for upgrades over $10 million once they reach commercial operation.
    Large Load Facilities will be reimbursed for Reimbursable Network Upgrades costing more than $10 million if the Large Load Facility reaches commercial operation PDF p. 20

Text extracted from the eLibrary original (SHA-256 b116947ffb903613…). Download the original from the official source.

Contents · 16 sections
  1. I. BACKGROUND p. 2
  2. A. DCRT p. 2
  3. B. Commission’s Show Cause Order p. 2
  4. C. DRCT’s Understanding of the CAISO’s Position p. 5
  5. II. DCRT’S PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE p. 6
  6. A. The Interconnection Study Process Proposed in DCRT’s TO Tariff, Appendix IV p. 6
  7. B. Overview of DCRT’s Pro Forma Large Load Interconnection Agreement p. 11
  8. C. DCRT’s Large Load Interconnection Process is Designed to Operate in Close p. 14
  9. D. DCRT’s Proposed Flexible Interim Load Interconnection Service p. 17
  10. E. Cost Responsibility for Network Upgrades p. 20
  11. F. CAISO Data Exchange p. 20
  12. III. CORRESPONDENCE p. 21
  13. IV. REQUESTED EFFECTIVE DATE p. 21
  14. V. DOCUMENTS ENCLOSED p. 21
  15. VI. SERVICE p. 22
  16. VII. CONCLUSION p. 22

Topics in the text: Connecting load and generation · Registry access · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

DCRT respectfully requests that the Commission accept the proposed Tariff revisions, to be effective February 15, 2027.6 1 16 U.S.C. § 824d. 2 18 C.F.R. §§ 35.3, 35.13 (2026). 3 Cal.
Read this passage

I. BACKGROUND

printed heading

I.
Read this passage

A. DCRT

printed heading

DCRT DCRT owns and operates the 125-mile, 500 kilovolt Ten West Link Transmission Line (“Ten West Link”), which runs from Arizona Public Service Company’s (“APS”) Delaney Substation, in Maricopa County, Arizona, to Southern California Edison Company’s (“SCE”) Colorado River Substation, in Riverside…
Read this passage

B. Commission’s Show Cause Order

printed heading · Topic match: Connecting load and generation

Reese November 16, 2026 Page 3 impacts of requests to modify an existing generating facility’s interconnection service level to serve co-located Large Loads on transmission system reliability; • The potential that Eligible Customers,13 on behalf of Large Load, may not be required to pay for…
Read this passage

C. DRCT’s Understanding of the CAISO’s Position

printed heading · Topic match: Connecting load and generation

DRCT’s Understanding of the CAISO’s Position Based on the OSC Order, DCRT participated in the CAISO’s stakeholder process for the CAISO PTOs to coordinate the CAISO’s and the CAISO PTO’s compliance filing in response to the OSC Order.
Read this passage

II. DCRT’S PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE

printed heading

DCRT’S PROPOSED TARIFF REVISIONS ARE JUST AND REASONABLE AND COMPLY WITH THE DIRECTIVES OF THE OSC ORDER
Read this passage

A. The Interconnection Study Process Proposed in DCRT’s TO Tariff, Appendix IV

printed heading · Topic match: Connecting load and generation

Reese November 16, 2026 Page 8 time-stamp each application upon receipt to establish study priority.27 This approach permits Large Load Interconnection Customers to submit applications whenever their projects are ready, rather than awaiting a periodic window, while providing an objective,…
Read this passage

B. Overview of DCRT’s Pro Forma Large Load Interconnection Agreement

printed heading · Topic match: Credit and exit

DCRT’s LLIA can be revised to accommodate the CAISO as a party to the extent there is co-location and BTMG facilities that inject power to the CAISO- controlled grid and that injection of power must be coordinated with the relevant Large Load Interconnection Customers. 55 See DCRT TO Tariff,…
Read this passage

C. DCRT’s Large Load Interconnection Process is Designed to Operate in Close

printed heading

Information-Sharing with the CAISO DCRT will provide the CAISO with notice of any delays in DCRT’s construction of Interconnection Facilities, Network Upgrades, or Distribution Upgrades.66 This notice requirement is reasonable because the CAISO, as the entity responsible for the reliable operation…
Read this passage

D. DCRT’s Proposed Flexible Interim Load Interconnection Service

printed heading · Topic match: Connecting load and generation

DCRT’s Proposed Flexible Interim Load Interconnection Service As discussed above, DCRT understands that the CAISO has declined to propose a new transmission service at this time in light of the CAISO’s day-ahead scheduling process for allocating transmission capacity,86 and DCRT defers to the CAISO…
Read this passage

E. Cost Responsibility for Network Upgrades

printed heading

Cost Responsibility for Network Upgrades DCRT understands the concerns about fair and equitable cost responsibility for Large Loads and has proposed a mechanism that DCRT believes balances its obligations under the FPA and the OSC Order, given that DCRT is a single-asset Transco and does not have a…
Read this passage

F. CAISO Data Exchange

printed heading

F.
Read this passage

III. CORRESPONDENCE

printed heading

CORRESPONDENCE DCRT respectfully request that the following individuals be included on the official service list in this proceeding and for receipt of any communications regarding this filing:108 Ali Amirali Jason Crew DCR Transmission, L.L.C. c/o Lotus Infrastructure, LLC 5 Greenwich Office Park -…
Read this passage

IV. REQUESTED EFFECTIVE DATE

printed heading

REQUESTED EFFECTIVE DATE DCRT respectfully requests that the Commission accept the proposed DCRT TO Tariff revisions submitted herewith to be effective on February 15, 2027.
Read this passage

V. DOCUMENTS ENCLOSED

printed heading

DOCUMENTS ENCLOSED This filing consists of the following: • A revised version of the DCRT TO Tariff, main body; • A new Appendix IV, Large Load Interconnection Process and Timeline, to the DCRT TO Tariff, and the following attachments thereto: o Attachment 1, Large Load System Impact Study…
Read this passage

VI. SERVICE

printed heading

SERVICE A copy of this filing has been served upon the CAISO.
Read this passage

VII. CONCLUSION

printed heading

CONCLUSION Based on the foregoing, DCRT respectfully requests that the Commission accept and approve the revisions to its TO Tariff to be effective on February 15, 2027.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Connecting load and generation

If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application…
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Flexible Interim Load Interconnection Service (FILI) shall mean the interim interconnection service that the Participating TO may offer pursuant to Section 4.1 of the LLIP where the Large Load Facility cannot be reliably served at its full requested demand until certain Network Upgrades are…
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Connecting load and generation

If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application…
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Flexible Interim Load Interconnection Service (FILI) shall mean the interim interconnection service that the Participating TO may offer pursuant to Section 4.1 of the LLIP where the Large Load Facility cannot be reliably served at its full requested demand until certain Network Upgrades are…
Read this passage