ER27-513-000 · 2026-11-16 · Pacific Gas and Electric Company

Exhibit No. PGE-0002 - Study Process Nedrud

PDF page 1

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Pacific Gas and Electric Company

Docket No. ER27-XXX-000
PREPARED DIRECT TESTIMONY OF
JENS NEDRUD
TCLL INTERCONNECTION STUDY PROCESSES
ON BEHALF OF
PACIFIC GAS AND ELECTRIC COMPANY
NOVEMBER 16, 2026

PDF page 2

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 1 of 37

PACIFIC GAS AND ELECTRIC COMPANY
1
EXHIBIT PGE-0002
2
TCLL INTERCONNECTION STUDY PROCESSES
3
I. Introduction
4
Q.
Please state your name, title, and business address.
5
A. My name is Jens Nedrud and I am Director, Electric Transmission Planning 6

with Pacific Gas and Electric Company (“PG&E”).  My business address is 7

300 Lakeside Drive, Oakland, California.
8
Q.
Please briefly describe your current responsibilities at PG&E. 9

A. I oversee the interconnection of wholesale and retail load to PG&E’s electric 10

transmission grid.  I also oversee the transmission planning for PG&E’s 11

transmission grid enhancements to meet future growth on the system to support 12

the California Independent System Operator Corporation (“CAISO”) 13

Transmission Planning Process (“TPP”) and comply with federal planning 14

criteria.
15
Q.
Please summarize your educational and professional background. 16

A. I earned a Bachelor of Science in Electrical Engineering from the University of 17

Washington in 2004 and a Master of Science in Electrical Engineering from 18

the same university in 2006.  I am a licensed professional engineer in 19

Washington with 20 years of utility experience, leading engineering functions 20

such as substation design, distribution and transmission planning, and asset 21

PDF page 3

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 2 of 37

health planning.  I have extensive experience planning transmission system 1

projects across the Northwest and California.
2
Q.
What is the purpose of your testimony?
3
A. The purpose of my testimony is to describe PG&E’s current process for 4

studying Wholesale Load Interconnections and to identify and explain the new 5

study processes PG&E is proposing to adopt to accommodate requests for 6

wholesale interconnection service by entities that PG&E’s Transmission 7

Owner Tariff (“TO Tariff”) identifies as “Transmission Customers for Large 8

Load” or “TCLLs.”  In particular, I will explain how the proposed changes to 9

the TO Tariff address the concerns reflected in the Order to Show Cause 10

(“OSC”) issued by the Federal Energy Regulatory Commission (“FERC” or 11

“Commission”) regarding study procedures for TCLLs.
12
II. Concerns Expressed in the OSC Regarding Study Processes
13
Q.
Can you summarize your understanding of the Commission’s concerns that 14

are relevant to your testimony and area of expertise?
15
A. The Commission generally expressed concern that the CAISO and TO Tariffs 16

lack provisions that address “with sufficient clarity and consistency” how the 17

CAISO and/or the Participating Transmission Owners (“Participating TO”) 18

will timely study the provision of transmission service to Eligible Customers 19

on behalf of Large Loads.  The Commission observed that the CAISO does not 20

appear to conduct studies to determine the necessary network upgrades needed 21

PDF page 4

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 3 of 37

for the provision of transmission service outside of its TPP.1  FERC thus 1

directed the CAISO and
 to explain whether their tariffs
2
remain just and reasonable without, among other things, study procedures that 3

address the unique characteristics and challenges of providing transmission 4

service or to amend their tariffs to do so.2
5
Q.
How do the CAISO and the Participating TOs study the provision of 6

transmission service to Eligible Customers as contemplated under the OSC? 7

A. Mr. Virani’s testimony provides a more fulsome explanation, but I also will 8

touch on this issue.  The CAISO does not have a specific process for entities to 9

apply for transmission service like other regions.  Similarly, the CAISO region 10

does not have a process for studying specific requests for transmission service 11

like the traditional process contemplated by the Commission’s pro forma Open 12

Access Transmission Tariff (“OATT”).  Rather, the CAISO engages in 13

transmission planning holistically for the entire Balancing Authority Area 14

(“BAA”) and the Participating TOs engage in their own planning in 15

coordination with the CAISO to ensure delivery is possible over their 16

transmission facilities.  My understanding is that the CAISO is not intending to 17

change this process.
18
The Commission indicated in the OSC that to the extent the CAISO or 19

1  OSC at P 39.
2  Id. at P 40.

PDF page 5

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 4 of 37

the Participating TOs already have procedures and conduct “such studies,” 1

(i.e., transmission service request studies) but those processes are not included 2

in their tariffs, that the CAISO and Participating TOs could amend their tariffs 3

so that the study process was clearer.3  To address this concern, PG&E 4

proposes to create a new interconnection process to study TCLL 5

Interconnections.  Specifically, in paragraph 25 of the OSC, FERC mentions 6

that the TO Tariff (Wholesale Load) interconnection process “does not grant 7

transmission service; rather, the applicant must retain the services of a 8

Scheduling Coordinator to access transmission service over the CAISO- 9

controlled grid.”  The Commission is correct that the existing Wholesale Load 10

interconnection process (retitled “Wholesale Load Interconnection” process) 11

does not “grant transmission service.”  However, it serves a similar purpose 12

because once the facilities found to be required for Wholesale Load 13

Interconnection service are planned in coordination with the CAISO and then 14

constructed, Wholesale Customers’ Scheduling Coordinators need not request 15

or be studied further to schedule power on a firm basis.
16
Q.
Does the TO Tariff address Wholesale Load Interconnections to a particular 17

Participating TO?
18
A. Yes, all the Participating TOs’ existing Wholesale Load Interconnection 19

processes are limited to Wholesale Customers in light of FERC’s jurisdiction. 20

3  OSC at P 62.

PDF page 6

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 5 of 37

The “retail service” request process, just like the Wholesale Load 1

Interconnection process, results in the studies being performed that, when 2

coupled with the TPP, mean that the Scheduling Coordinators for retail load 3

likewise need not request or be studied further to schedule power on a firm 4

basis.  In short, the Participating TOs and the CAISO share responsibility for 5

conducting studies that ensure that all Load ultimately is served.  Today, a 6

Large Load End User in PG&E’s service area would request retail service and 7

a PG&E study process would commence.  If the Large Load End User were 8

not in PG&E’s service area, Participating TO studies would occur under the 9

respective Participating TO’s TO Tariff.  In both cases, the CAISO TPP would 10

ultimately determine what facilities need to be constructed to ensure that a 11

Scheduling Coordinator could schedule firm power to the Large Load End 12

User.
13
Q.
How are you proposing to change the existing processes to satisfy the OSC? 14

A. The changes being proposed are based on the existing roles and 15

responsibilities.  As my colleague Mr. Virani explains, it is the TO Tariff 16

interconnection process, coupled with the CAISO’s TPP, that will continue to 17

be the means of ensuring that Scheduling Coordinators can schedule to 18

particular Loads, including Large Load End Users.  However, a new process is 19

being created to study Large Load End Users whose TCLL interconnects to, or 20

seeks to interconnect to, PG&E’s transmission system.  Under this process, all 21

PDF page 7

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 6 of 37

Large Load End Users whose TCLLs connect or seek to connect to PG&E’s 1

facilities, including those who seek service from PG&E as a TCLL, will be 2

studied under a single tariff, regardless of their retail transmission provider. 3

And, that process will interact with the CAISO TPP much in the same manner 4

as the other existing retail and wholesale study processes.
5
Q.
Can you provide more detail as to what concerns were identified by the OSC 6

as relates to the performance of studies for Large Load End Users? 7

A. The specific concerns about studies include
study process that
8
considered the unique characteristics and impacts of large loads, such as 9

studies that evaluate the transmission system’s ability to withstand risks 10

observed from analyzed large load behavior.4  FERC noted that accurate 11

models using electromagnetic transient studies might help to ensure that 12

transmission service needed on behalf of large loads can be provided without 13

compromising reliability.5  It also noted the absence of clear and consistent 14

provisions requiring the evaluation of alternative transmission technologies 15

that can meet transmission needs more efficiently or cost-effectively than 16

traditional network upgrades.6  The Commission noted that, “based on the 17

record, it appears reasonable that such study processes, culminating in a report 18

to the [TCLL] with the results of the studies, including any Direct Assignment 19

4  OSC at P 48.
5  OSC at P 59.
6  Id. at P 60.

PDF page 8

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 7 of 37

Facilities and network upgrades necessary to accommodate the transmission 1

service request as well as a non-binding good-faith estimate of the cost and the 2

time to construct such facilities, should take no more than 60-90 calendar days 3

to complete.”7
4
As I describe below, PG&E proposes to address those concerns through 5

a new TCLL Interconnection process.  However, before discussing that 6

process, I think it would be helpful to provide some background on how PG&E 7

currently studies Wholesale Load Interconnections under its TO Tariff. 8

III. PG&E’s Existing Wholesale Load Interconnection study process 9

Q.
What is the purpose of PG&E’s existing Wholesale Load study process? 10

A. When a new Wholesale Load customer seeks to interconnect to PG&E’s 11

transmission system or an existing Wholesale Load customer seeks to modify 12

or expand an existing Wholesale Load Interconnection, PG&E must study the 13

request to determine the impacts on its transmission system.  Specifically, a 14

study is necessary to identify whether there is adequate transmission capacity 15

to safely and reliably interconnect new or incremental Wholesale Load to 16

PG&E’s electrical system.  The process analyzes the impacts of 17

interconnecting the Load and identifies any upgrades that will be required to 18

accommodate the Load on the transmission system.
19

7  Id. at P 62.

PDF page 9

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 8 of 37

Q.
Under PG&E’s existing process, how does the Company process applications 1

seeking to interconnect Wholesale Load?
2
A. Mr. Virani’s testimony describes the application process and the nature of the 3

customers seeking what is now called a “Wholesale Load Interconnection.” 4

After determining that an application is complete, in a typical situation, the 5

Company tenders a System Impact Study Agreement within 20 Business Days 6

of receipt of a Completed Wholesale Load Interconnection Application.  The 7

System Impact Study Agreement defines, among other things, the scope, 8

content, and assumptions of the study to be completed by the Participating TO, 9

and the estimated time required to complete it.  At the time of execution, the 10

applicant is also required to pay the reasonable estimated cost of performing 11

the study.  Sections 10.3 and 10.4 set out the timelines for each of these steps. 12

If a System Impact Study indicates that additions or upgrades to the ISO 13

Controlled Grid are needed to satisfy an applicant’s request for 14

Interconnection, the final step is a Facilities Study under Sections 10.7 and 15

10.8.
16
Q.
Please describe the existing Wholesale Load study process.
17
A. PG&E’s existing TO Tariff outlines the study process for Wholesale Load in 18

Sections 10.4 through 10.8.  As I explained above, PG&E uses two separate 19

studies to analyze Wholesale Loads:  a System Impact Study and, if needed, a 20

Facilities Study.  First, as outlined in Section 10.6 of the TO Tariff, in a typical 21

situation, PG&E completes a System Impact Study.  The System Impact Study 22

PDF page 10

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 9 of 37

identifies and analyzes any transmission additions or upgrades that are 1

necessary to interconnect and serve the Wholesale Load.  The System Impact 2

Study will also identify any adverse impact on Encumbrances.
3
Q.
How long does the Company have to complete the System Impact Study? 4

A. Section 10.6 indicates the Company will use “due diligence” to complete the 5

System Impact Study within 60 calendar days.  In PG&E’s experience, 6

generally, the System Impact Study process takes the full 60 days to complete 7

and can require more time, especially when multiple applications are in the 8

study process.
9
Q.
What happens after the System Impact Study?
10
A. If the System Impact Study shows that the request can be accommodated 11

without Direct Assignment Facilities, Reliability Upgrades, or implementing 12

operating procedures, the applicant must request and execute a Wholesale 13

Load Interconnection Agreement that will allow them to interconnect to the 14

PG&E transmission system or modify their existing Wholesale Load 15

Interconnection Agreement.  If the study shows that such facilities or upgrades 16

are likely needed, the next step is generally a Facilities Study, as provided in 17

Sections 10.7 and 10.8.
18
The Facilities Study is a more refined analysis of the impact of interconnecting 19

the Wholesale Load to the PG&E transmission system as compared to the 20

System Impact Study.  The results of the Facilities Study will refine the cost of 21

PDF page 11

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 10 of 37

the equipment, engineering, procurement and construction work (including 1

overheads) needed to interconnect to the PG&E system.  This gives the 2

applicant a firmer understanding of its cost responsibility before it signs a 3

Wholesale Load Interconnection Agreement.
4
Q.
Does Section 10 offer any alternative to that sequence?
5
A. Yes.  Some applicants would rather move forward quickly than wait for a 6

Facilities Study to refine the cost estimate.  Section 10.12 allows an applicant, 7

after it receives the System Impact Study for the proposed Wholesale Load 8

Interconnection, to request an Expedited Wholesale Load Interconnection 9

Agreement.  Under the expedited process, the applicant proceeds based on 10

PG&E’s best estimate of costs of any needed Direct Assignment Facilities and, 11

if applicable, Reliability Upgrades, rather than a refined estimate, and agrees to 12

pay the actual costs PG&E reasonably incurs.
13
Q.
What types of facilities are identified in these studies?
14
A. The upgrades are grouped into three categories, Direct Assignment Facilities, 15

Reliability Upgrades, and transmission network upgrades.
16
Q.
How does PG&E’s study process interact with CAISO’s study and planning 17

process?
18
A. As already discussed, Participating TOs such as PG&E are responsible for 19

studying Wholesale Load Interconnections, and the CAISO is responsible for 20

transmission planning generally through the TPP as well as Generation 21

PDF page 12

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 11 of 37

Interconnections to the CAISO Controlled Grid.  The results of PG&E’s 1

Wholesale Load studies (wholesale and retail) impact the CAISO planning 2

process in two distinct ways.  First, when PG&E submits the Wholesale Load 3

Interconnection study results to the CAISO for review in their load 4

concurrence process, both the Reliability Upgrades and the transmission 5

network upgrades are submitted to the CAISO for their review and 6

concurrence for inclusion in the TPP.  In addition, the Load identified in 7

Wholesale Load Interconnection studies, along with other retail load growth is 8

considered in the TPP process and can trigger upgrades.  As a result of these 9

two steps, both the upgrades needed to interconnect Wholesale Loads and the 10

Load itself are integrated into the CAISO’s transmission planning process. 11

Q.
Can a Wholesale Load customer interconnect to PG&E’s electrical system if 12

there is not sufficient transmission capability to accommodate its full load? 13

A. Yes.  As part of the study process, to the extent that upgrades are required to 14

serve the full Load, PG&E will identify the portion of the requested Load that 15

can be accommodated without any Direct Assignment Facilities or Reliability 16

Upgrades.  To the extent the applicant is interested, Section 10.11 allows them 17

to elect partial interim service up to the level of identified partial interim 18

service capability until the required facilities or upgrades are placed in service. 19

PDF page 13

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 12 of 37

IV. The TCLL Interconnection Study Processes
1
Q.
How is PG&E proposing to change its TO Tariff to address the requirements 2

of the OSC for studying Large Loads?
3
A. PG&E is proposing to add a new section (Section 10A) to its TO Tariff to 4

address TCLL Interconnections.  PG&E proposes using a Serial Study Process 5

for TCLL requests that do not impact other customers on the transmission 6

system.  In addition, PG&E proposes using a new Cluster Study Process for 7

TCLL requests that impact other customers.  I will discuss both processes in 8

turn.
9
Q.
What is the first step after a TCLL Interconnection Application is deemed 10

complete?
11
A. Within 15 Business Days of PG&E deeming an application complete, the 12

Company will perform an Electrical Independence Test to determine if the 13

Large Load End User associated with the TCLL’s Interconnection request 14

qualifies as an Electrically Independent Large Load.  The one exception is a 15

request associated with a Co-Located Large Load End User, which is always 16

studied in the Cluster Study Process, as I discuss later in my testimony. 17

PDF page 14

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 13 of 37

Q.
What is an Electrically Independent Large Load?
1
A. As indicated in the proposed TO Tariff definition, an Electrically Independent 2

Large Load is one where its interconnection impacts are not materially affected 3

by one or more other projects.  In these instances, the interconnecting Large 4

Load End User and corresponding upgrade facilities would not impact other 5

Load interconnections.  For example, additional Load in an unconstrained 6

portion of the PG&E system (e.g., which does not depend on pre-identified 7

transmission upgrades to meet the aggregate Load), and where the incremental 8

Load does not affect other planned projects or would not be expected to impact 9

other interconnections would be considered electrically independent.  As a 10

result, PG&E can study this Large Load End User without needing to assume 11

the status, timing, or configuration of other queued projects. 12

Q.
How do you determine if the Large Load End User is electrically 13

independent?
14
A. To determine whether a Large Load End User is electrically independent, 15

PG&E will conduct an Electrical Independence Test under proposed Section 16

10A.3.1.  This test requires PG&E to perform the incremental power flow and 17

aggregate power flow tests, which look at whether the request, on its own and 18

together with other requests, would cause issues on the CAISO Controlled 19

Grid.  If the TCLL Interconnection request does not pass the CAISO 20

Controlled Grid incremental power flow and aggregate power flow tests, then 21

it fails the evaluation of electrical independence for the CAISO Controlled 22

PDF page 15

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 14 of 37

Grid, and the request must be studied with the other electrically dependent 1

requests in the Cluster Study Process under proposed Section 10A.5 or 2

withdraw.  If it passes, the Large Load End User qualifies as an Electrically 3

Independent Load, and the request proceeds under the Serial Study Process 4

pursuant to proposed Section 10A.4.
5
Q.
Why does that matter?
6
A. Because an Electrically Independent Large Load interconnection does not 7

impact other interconnection applications, it can be studied independent of 8

other interconnection requests and therefore can be completed using the Serial 9

Study Process which can be completed in the timeframe the Commission 10

envisions in the OSC, if the TCLL opts out of a Facilities Study.  A TCLL that 11

requests Interim Standard Interconnection Service and/or Flexible Interim 12

Large Load Interconnection Service, however, will need a Facilities Study, 13

because that is where PG&E identifies and estimates the cost of the TCLL 14

FILLI Facilities. Note that consistent with the TO Tariff, I refer to Flexible 15

Interim Large Load Interconnection Service as FILLI Interconnection Service. 16

And when discussing both Interim Standard Interconnection Service and FILLI 17

Interconnection Service together, I refer to it as Interim Service. 18

Q.
What happens after the Electrical Independence Test?
19
A. PG&E will hold a scoping meeting with the TCLL within 5 Business Days of 20

completing the Electrical Independence Test.  The purpose of the meeting is to 21

PDF page 16

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 15 of 37

address the preliminary interconnection scope, discuss the Point of 1

Withdrawal, present preliminary planning assumptions, and assess available 2

system capacity.   Within 15 Business Days after the meeting, the TCLL must 3

elect to proceed under the applicable Serial Study Process or withdraw its 4

TCLL Interconnection Application.  If it withdraws at this point, it receives 5

back the unspent portion of its study deposit.  If the Large Load End User is 6

electrically dependent, it will proceed under the Cluster Study Process in 7

proposed section 10A.5.
8
V. Serial Study Process
9
Q.
Describe the Serial Study Process that applies to Electrically Independent 10

Large Loads.
11
A. If a System Impact Study Agreement is required, the Participating TO will 12

present it to the TCLL at the scoping meeting.  The TCLL then is expected to 13

notify the Participating TO within 15 Business Days whether it elects to 14

proceed with preparation of a System Impact Study Agreement or withdraw its 15

TCLL Interconnection Application.  The TCLL then must execute the System 16

Impact Study Agreement and return it to the Participating TO within 15 17

Business Days upon receipt.  If the TCLL does not sign, its application is 18

deemed withdrawn and any unused deposit and security are returned after 19

PG&E’s reasonably incurred costs are covered.  If the TCLL disputes the 20

agreement and asks that it be filed unexecuted, the study is put on hold until 21

FERC acts.  Upon receipt of an executed System Impact Study Agreement, the 22

PDF page 17

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 16 of 37

Participating TO will use due diligence to complete the required System 1

Impact Study within a 60 Business Day period.  The System Impact Study will 2

identify whether any Direct Assignment Facilities and TCLL Interconnection 3

Network Upgrades are required and provide an estimated cost for such 4

facilities.  These terms are all defined in the TO Tariff, and I will discuss them 5

further below.  The System Impact Study will also identify any adverse impact 6

on Encumbrances existing as of the TCLL’s Completed Application Date.  The 7

Participating TO will consider alternative transmission technologies in the 8

System Impact Study process.  If traditional network upgrades are selected 9

instead of alternative transmission technologies, the Participating TO will 10

provide a demonstration of why alternative transmission technologies are not 11

feasible or would not result in lower costs or a faster timeline for 12

accommodating the TCLL Interconnection.
13
Q.
What happens after the System Impact Study is complete?
14
A. Within 15 Business Days of completion of the System Impact Study, the TCLL 15

decides how it wants to proceed.  If it is satisfied with the results, it may 16

request that the Participating TO tender a TCLL Agreement, Facilities 17

Agreement, and Cost Assurance Agreement in accordance with Section 18

10A.4.8.  If it wants a more refined cost estimate, or if it is seeking Interim 19

Standard Interconnection Service and/or FILLI Interconnection Service, it 20

must request that the Participating TO tender a Facilities Study Agreement 21

PDF page 18

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 17 of 37

pursuant to Section 10A.4.5.  Alternatively, the TCLL may withdraw its 1

application.  If a TCLL requests a Facilities Study Agreement, the Participating 2

TO will provide a Facilities Study Agreement within 15 Business Days that 3

defines the scope, content, assumptions and terms of reference for such study; 4

the estimated time required to complete the required study; and such other 5

provisions as the parties may reasonably require.  The TCLL shall execute the 6

Facilities Study Agreement and return it to the Participating TO within 15 7

Business Days.  Upon receipt of an executed Facilities Study Agreement, the 8

Participating TO will use due diligence to complete the required Facilities 9

Study within a 60-Business Day period.  The Facilities Study refines the cost 10

estimates from the System Impact Study and identifies any TCLL FILLI 11

Facilities, if applicable.
12
Q.
What happens after the Facilities Study is complete?
13
A. Within 15 Business Days of receipt of the completed Facilities Study, the 14

TCLL shall request the Participating TO to tender a TCLL Agreement, 15

Facilities Agreement, Cost Assurance Agreement, and the optional Interim 16

Service Agreement in accordance with Section 10A.4.8 or withdraw its 17

application.
18
Q.
What happens once PG&E tenders those agreements?
19
A. The parties then negotiate and execute the TCLL Agreement, Facilities 20

Agreement, Cost Assurance Agreement, and, if applicable, the Interim Service 21

PDF page 19

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 18 of 37

Agreement.  The TO Tariff gives the parties 60 Business Days, which can be 1

extended if negotiations are progressing, to negotiate and execute the 2

agreements and ensure the relevant agreements, if any, are executed by the 3

Large Load End User.  If the parties cannot reach agreement, the TCLL can 4

ask that the agreements be filed unexecuted so that FERC can resolve the 5

dispute.  If the TCLL withdraws its application, the TCLL shall reimburse the 6

Participating TO for the costs reasonably incurred in processing the 7

application, after which its remaining security will be released. 8

Q.
Can you explain how the Direct Assignment Facilities, TCLL
9
Interconnection Network Upgrades, and/or TCLL FILLI Facilities are 10

identified?
11
A. Generally, the study process identifies all facilities and equipment needed to 12

safely and reliably interconnect the proposed Large Load End User.  Of that 13

equipment, the Direct Assignment Facilities are those that are owned by the 14

Participating TO that are necessary to physically and electrically interconnect 15

the TCLL to the ISO Controlled Grid at the point of interconnection.  Although 16

this equipment will be at a transmission voltage, it is not part of the ISO 17

controlled transmission system.  In contrast, TCLL Interconnection Network 18

Upgrades are the additional facilities needed to expand the transmission system 19

from the ISO Controlled Grid to the point of interconnection of the TCLL. 20

TCLL FILLI Facilities are analogous to the Direct Assignment Facilities in 21

that they are used exclusively by a Large Load End User taking FILLI 22

PDF page 20

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 19 of 37

Interconnection Service and are required to provide the flexible non-firm 1

interim service until the Participating TO and TCLL have completed 2

installation and commissioning of all equipment necessary for Standard 3

Interconnection Service.
4
A. Cluster Study Process
5
Q.
Why does the Serial Study Process not work for all TCLL Interconnections? 6

A. It has been my experience that a request to interconnect a significant amount of 7

load, such as a request associated with a Large Load End User, can have 8

electrical impacts on other customers.  The ability of PG&E to interconnect a 9

Large Load may be dependent on other requests from Large Load End Users 10

on PG&E’s transmission system that are being analyzed at the same time.  As a 11

result, if PG&E were to study such Electrically Dependent Large Loads 12

sequentially, the Company would have to complete each study, and the 13

applicant would need to decide on whether to proceed, before finalizing the 14

evaluation of additional interconnection requests.  This would be time 15

consuming and could result in a number of restudies as applicants drop out of 16

the interconnection queue or change their Load configurations based on study 17

results.  PG&E already studies all retail service requests for large customers 18

(those > 20 MW) using a cluster study process because it is more cost effective 19

and efficient for the customers.  PG&E proposes to use this cluster study 20

process as the basis for the proposed Cluster Study for TCLLs (who will now 21

PDF page 21

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 20 of 37

seek interconnection service on behalf of Large Load End Users).  PG&E will 1

continue to use the retail cluster study process for those larger customers (e.g., 2

20 MW to 49.99 MW loads) that are not Large Load End Users.
3
Q.
When does the Cluster Study Process begin, and which applications are 4

included?
5
A. PG&E will run one Cluster Study each year.  Each year has a closing date of 6

the last day of February, by which an application must be complete and found 7

to be Electrically Dependent, or involve a Co-Located Large Load End User, to 8

be included in that year’s cluster.  The Cluster Study Process will begin on the 9

first day of April, or the next Business Day, each year.  A fixed annual 10

schedule allows us to study all of the Electrically Dependent Large Load 11

requests together using the same assumptions and gives TCLLs and their Large 12

Load End Users certainty about when their requests will be studied.  Because 13

the new process will only just be taking effect, the TO Tariff also recognizes 14

that if no Completed TCLL Interconnection Applications have been found to 15

be electrically dependent by the last day of February in 2027, there will be no 16

Cluster Study Process beginning on April 1, 2027.  Shortly after the closing 17

date, each TCLL signs a Cluster Study Process Agreement.  Where it makes 18

sense, PG&E may also divide the Cluster into smaller study groups of requests 19

that electrically affect one another, so that each request is studied together with 20

the requests that actually matter to it.
21

PDF page 22

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 21 of 37

Q.
How does the Company propose to conduct the Cluster Study?
1
A. The Cluster Study Process has two distinct phases.  In Phase 1, PG&E will 2

evaluate all projects in the Cluster using studies that include, but are not 3

limited to, a short circuit and steady state (thermal and voltage) analysis.  The 4

Phase 1 and Phase 2 Study will identify Participating TO’s required facilities to 5

mitigate thermal overloads and voltage violations, and address short circuit, 6

stability, and other reliability issues associated with the requested service.  The 7

Phase 1 Study shall (i) evaluate the impact of all TCLL Interconnection 8

requests in the cluster; (ii) preliminarily identify for each TCLL 9

Interconnection request the required Direct Assignment Facilities, TCLL 10

Interconnection Network Upgrades, and TCLL FILLI Facilities; (iii) assess the 11

Point of Withdrawal selected by each TCLL and potential alternatives to 12

evaluate potential efficiencies in overall system upgrade costs; and (iv) provide 13

a good faith estimate of the cost of the Direct Assignment Facilities, TCLL 14

Interconnection Network Upgrades, and TCLL FILLI Facilities for each TCLL 15

Interconnection request.  We coordinate the Phase 1 Study with the CAISO, 16

including the development of Base Cases, so that the impacts on the CAISO 17

Controlled Grid are modeled accurately.
18
Q.
What happens after completion of Phase 1 Study?
19
A. Within 20 Business Days of providing the final Phase 1 Study report, PG&E 20

will schedule a Results Meeting with the TCLLs, the CAISO, and any Affected 21

PDF page 23

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 22 of 37

System Operators to review the Phase 1 Study results, including each TCLL’s 1

estimated cost responsibility.  Based on the information presented in the 2

meeting, the TCLLs have 60 Business Days to decide to withdraw their 3

application or to proceed to the next study phase (Phase 2).  I would expect that 4

the TCLLs will be consulting with their Large Load End Users, just as they 5

would throughout the Serial Study Process.  A TCLL that decides to proceed to 6

Phase 2 must sign a Phase 2 Cluster Study Process Agreement, under which it 7

agrees to post refundable security equal to 15 percent of the Phase 1 Study’s 8

estimated cost of its Direct Assignment Facilities and TCLL Interconnection 9

Network Upgrades.  That security first pays for PG&E’s actual costs of 10

performing and administering the Phase 2 Study, so having a signed agreement 11

in place before Phase 2 begins gives PG&E a clear commitment from the 12

TCLL to cover the costs of that phase.  The security also serves two broader 13

purposes.  First, it asks TCLLs to demonstrate a meaningful financial 14

commitment at the point where the study results become more concrete, which 15

helps ensure that Phase 2 is performed for requests that are likely to move 16

forward.  Second, PG&E may also use those funds for engineering, design, and 17

procurement of the Direct Assignment Facilities and TCLL Interconnection 18

Network Upgrades identified in the Phase 1 Study, together with the associated 19

labor, materials, contractor charges, and overhead, including any applicable 20

income tax component of contribution.  That allows work on long lead-time 21

PDF page 24

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 23 of 37

equipment to begin earlier, which can shorten the time to energization.  The 1

security is refundable, and if it is posted in cash, PG&E pays interest on any 2

amount it returns at the commercial paper rate, from the date the security was 3

paid until the date it is refunded.
4
Q.
What occurs in the Phase 2 Cluster Study process?
5
A. The Phase 2 Study will (i) update, as necessary, analyses performed in the 6

Phase 1 Study to account for the withdrawal of requests after the Phase 1 Study 7

process, (ii) identify Direct Assignment Facilities, TCLL Interconnection 8

Network Upgrades, and TCLL FILLI Facilities, (iii) assign cost responsibility 9

for Direct Assignment Facilities, TCLL Interconnection Network Upgrades, 10

and TCLL FILLI Facilities needed for the TCLL’s interconnection request, (iv) 11

allocate estimated cost responsibility for financing the identified TCLL 12

Interconnection Network Upgrades, and (v) identify for each TCLL 13

Interconnection request a final Point of Withdrawal, and preliminarily identify 14

any TCLL Reliability Network Upgrades.  Phase 2 also includes a transient 15

stability study and as needed, a voltage stability analysis, which are more 16

detailed analyses that are most useful once the cluster has been narrowed to the 17

requests that are moving forward.  When the study identifies system violations, 18

PG&E will first evaluate whether alternative transmission technologies can 19

mitigate them before turning to traditional network upgrades.  If traditional 20

network upgrades are selected instead of alternative transmission technologies, 21

PDF page 25

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 24 of 37

PG&E will provide a demonstration of why alternative transmission 1

technologies are not feasible or would not result in lower costs or a faster 2

timeline for accommodating the TCLL Interconnection.
3
Q.
What happens after the Phase 2 Study is complete?
4
A. PG&E will hold a second results meeting to review the Phase 2 results, 5

including each TCLL’s assigned cost responsibility.  At that point the TCLL 6

has the information it needs to decide whether to move forward.  If it does, it 7

requests the TCLL Agreement, Facilities Agreement, Cost Assurance 8

Agreement, and, if applicable, the Interim Service Agreement, and the parties 9

negotiate and execute those agreements, including with the Large Load End 10

User where required.  If it does not, it withdraws its application.  If a TCLL 11

withdraws after Phase 2, PG&E will refund the amounts posted for Phase 2 12

less the costs it has incurred, including any engineering, design, and 13

procurement already performed for the TCLL’s request.  If the TCLL moves 14

forward, the parties may agree to apply the remaining Phase 2 financial 15

security toward the TCLL’s upfront payment under the Facilities Agreement, 16

so that the funds the TCLL has already committed go toward the facilities 17

needed to serve its load and PG&E can order long lead-time equipment and 18

begin work earlier, which can shorten the time to energization. 19

PDF page 26

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 25 of 37

Q.
How will TCLLs be able to understand and verify the results of PG&E’s 1

studies?
2
A. One of the Commission’s concerns in the OSC was avoiding disputes over how 3

studies are conducted, and I believe transparency is the best way to address 4

that.  Under both Phase 1 and Phase 2, the completed Cluster Study reports are 5

provided to the TCLL, Participating TO, the CAISO, and any Affected System 6

Operators, if applicable. TCLLs also can request supporting documentation 7

and work papers, including the relevant power flow, short circuit, and stability 8

databases, subject to appropriate confidentiality arrangements.  That allows a 9

TCLL and its consultants to see the assumptions we used and test our 10

conclusions.  We also commit to keeping TCLLs informed of the schedule.  If 11

it becomes clear that we will not complete a study within the target timeframe, 12

whether because of the number of requests, study complexity, coordination 13

with the CAISO, or the availability of contractors, we will notify the TCLLs, 14

explain why, and provide an estimated completion date.  Finally, the results 15

meetings after each phase of the Cluster Study, and the scoping meeting in the 16

Serial Study Process, give TCLLs a direct opportunity to ask questions and 17

raise concerns with PG&E and the CAISO before they decide whether to 18

proceed.
19
Q.
Does the Company have experience performing cluster studies for Large 20

Loads?
21
A. Yes, the Company has been performing cluster studies for loads greater than 22

PDF page 27

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 26 of 37

20 MW for several years.
1
Q.
What has been the Company’s experience to date with these CPUC- 2

jurisdictional Large Load interconnection requests?
3
A. The Company has found that studying Large Loads collectively as part of a 4

cluster has been an effective way to identify needs and plan the solutions 5

required to interconnect these customers.  In PG&E’s experience, studying 6

Electrically Dependent Large Load requests on a serial basis is extremely 7

inefficient.  Each study must be finished, and each applicant must decide 8

whether to proceed, before the next request can be studied with confidence, 9

and any change or withdrawal by an earlier request can require later requests to 10

be restudied.  PG&E has performed 3 Large Load cluster studies thus far, 11

involving 93 separate applications, with over 25 GW of Load.  If PG&E had 12

only used a serial study process, it would have required multiple years to 13

evaluate the applications, significantly delaying their interconnection.  By 14

using a two-step cluster process, PG&E was able to get phase 1 study results 15

back to the applicants in approximately 9 months, giving them actionable 16

information to make their business decisions.
17
Q.
What is the anticipated timeline for these Cluster Studies?
18
A. Each phase of the Cluster Study is targeted for completion within 120 Business 19

Days and the entire process, including meetings to discuss results, is estimated 20

to take over a year.  However, the Company proposes to conduct one Cluster 21

PDF page 28

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 27 of 37

Study Process annually by allowing for some overlap in each Cluster Study 1

Process.
2
Q.
Why do you believe a Cluster Study can be a timelier approach? 3

A. Studying Electrically Dependent Large Loads together produces more accurate 4

results and avoids serial restudies.  In addition, studying a group of interrelated 5

projects collectively is more efficient than studying those same projects 6

sequentially.
7
Q.
You previously mentioned the FERC suggestion in the OSC that studies 8

should be completed in 60-90 days, are you concerned that the Cluster Study 9

Process is outside those bounds?
10
A. I am aware of FERC’s recommendation, but studying each request serially 11

under a 90-day time frame will result in numerous restudies and will likely 12

take far longer to ultimately complete.  For requests that are electrically 13

independent and do not seek an optional Facilities Study, our proposed TO 14

Tariff language targets completion of the System Impact Study process within 15

90 Business Days.
16
PG&E has been studying “electrically dependent” Large Loads for 17

several years under a cluster study process and its experience is that such 18

studies will likely take significantly longer than 90 days.  However, while the 19

process may take longer than the 90 days contemplated in the OSC, it still 20

remains, in my opinion, the most efficient way to conduct studies of the 21

impacts of Large Load End Users on the transmission system.  The 22

PDF page 29

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 28 of 37

Commission highlights the reliability impacts of Large Loads on the 1

transmission system.  This concern is valid and thus, transmission owners, like 2

PG&E must thoughtfully consider what facilities are needed for the safe and 3

reliable interconnection of Large Load End Users.  When such Loads impact 4

more than one customer and are coming online under similar time periods, it is 5

simply not possible or reliably sound to study them in isolation over such a 6

short time period.  Although PG&E understands the urgency of the needs of 7

technology companies, particularly given its location, those needs cannot be 8

placed above the safety of the community and PG&E employees.
9
Q.
How do the study processes address impacts on neighboring transmission 10

systems?
11
A. A Large Load End User can affect transmission systems owned by others, such 12

as neighboring utilities interconnected with PG&E.  When our studies indicate 13

that another system may be affected, PG&E will notify that system’s operator, 14

the TCLL, and the CAISO, and coordinate any studies needed to assess the 15

impacts.  PG&E will include the Affected System Operator in meetings with 16

the TCLL.  Any upgrades needed on the Affected System are the TCLL’s cost 17

responsibility, because the TCLL’s request is what creates the need for them, 18

and those costs will be reflected in the Facilities Agreement.  To keep this 19

coordination from delaying the process, an Affected System Operator that 20

takes service under PG&E’s TO Tariff must tell us within 40 Business Days 21

whether it intends to study the TCLL Interconnection Application.  If it does 22

PDF page 30

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 29 of 37

not respond, it cannot later bring claims against PG&E regarding impacts from 1

that interconnection.
2
VI. Interim Interconnection Services
3
Q.
Can you describe the new FILLI Interconnection Service and Interim 4

Standard Interconnection Service and how you will study them?
5
A. The two services, FILLI Interconnection Service and/or Interim Standard 6

Interconnection Service, build on the existing partial interim service offered to 7

traditional Wholesale Loads under Section 10.  A study may show that Interim 8

Standard Interconnection Service can be provided to some portion of the total 9

amount of Load requested by a TCLL, after certain facilities are built.  As for 10

the remaining Load, or all the Load if no Interim Standard Interconnection 11

Service is available, FILLI Interconnection Service is an optional 12

interconnection service that PG&E and the CAISO are proposing to offer. 13

PG&E’s study process for FILLI Interconnection Service will investigate the 14

conditions during which Large Load End Users would need to limit their 15

Energy withdrawals under certain conditions during the period that network 16

upgrades are being constructed.  The analysis would also consider what 17

facilities may be needed and what procedures may need to be adopted to allow 18

for FILLI Interconnection Service, which is an as-available service. 19

In order to assess how much, if any, Interim Standard Interconnection Service 20

and FILLI Interconnection Service can be offered, PG&E will study the Load 21

under NERC Transmission System Planning Performance Requirement 22

PDF page 31

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 30 of 37

Conditions to determine how much firm service can be offered while upgrades 1

are being constructed to enable firm service for entire Load request.  This 2

analysis is performed as part of the otherwise applicable study process, rather 3

than as a separate process.  As part of that analysis, we will complete a 4

flexibility needs analysis to quantify when and how FILLI customers may need 5

to reduce consumption, including the expected magnitude, duration, and 6

likelihood of those reductions.  That information will allow customers to 7

understand and plan for potential operating limitations while supporting 8

reliable interconnection to the transmission system. As part of the FILLI 9

Interconnection Service evaluation, the Company will evaluate the annual load 10

ramp of each applicant and identify the expected facilities needed to 11

accommodate their interim flexible service.
12
VII. TCLL Interconnections associated with Co-Located Large Load End 13

Users
14
Q.
Are there any special conditions associated with studying requests from 15

TCLLs when the associated Large Load is co-located with, and at least 16

partially supplied by that co-located generation?
17
A. Yes.  These requests are always studied in the Cluster Study Process.  To the 18

extent that a TCLL request indicates that a Co-Located Large Load End User 19

commits to using on-site generation to reduce a portion or all of its demand, 20

PG&E will study upgrades needed to support the requested level of service. 21

That approach only works if we can rely on the Co-Located Large Load End 22

User staying at or below the level of service requested in the TCLL 23

PDF page 32

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 31 of 37

Interconnection Application, so our studies will take into account the 1

mechanisms the Co-Located Large Load End User proposes to ensure it does 2

not withdraw more Energy from the grid than it has requested.  If PG&E and 3

the CAISO are not satisfied that those mechanisms are adequate, the Large 4

Load must be restudied at the higher level.  In instances where the facility 5

wishes to export power onto the transmission system, the Generating Units co- 6

locating with Large Load End Users are studied under the CAISO Tariff, and 7

PG&E and the CAISO will produce study results that reflect the combined 8

presence of the Generating Units and Large Loads.  I would expect the CAISO, 9

as BAA, would be the entity that determines what equipment and protocols are 10

needed to ensure that no more than a pre-determined amount of generation 11

would appear on its system unexpectedly.
12
Q.
Why are requests associated with Co-Located Large Load End Users always 13

studied in the Cluster Study Process?
14
A. A Co-Located Large Load End User raises questions that a standalone load 15

does not.  Because the Co-Located Large Load End User is relying on on-site 16

generation to serve part of its demand, we have to understand what happens 17

when that Generation is unavailable and the Co-Located Large Load End Users 18

turns to the grid instead.  That means we need to evaluate the protective 19

mechanisms, such as relays, controls, and operating limits, that will keep the 20

Co-Located Large Load End User from drawing more from the CAISO 21

Controlled Grid than it has requested, and we need to coordinate that 22

PDF page 33

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 32 of 37

evaluation with the CAISO’s study of the Generating Units co-locating with 1

the Large Load End User.  That work takes time, and it cannot reliably be 2

completed within the timeframe of the Serial Study Process.  The Cluster 3

Study Process, with its two phases and its coordination with the CAISO, gives 4

PG&E the time to study those protective mechanisms properly.  It also gives us 5

the time to consider, if a Co-Located Large Load End User were to exceed its 6

requested capacity, what the consequences should be, including whether 7

penalties for exceeding that capacity are appropriate, similar to the approach 8

PJM has taken for co-located load.
9
VIII. Interaction of PG&E Study Processes and TPP.
10
Q.
How will the PG&E study processes interact with the CAISO’s TPP? 11

A. As discussed earlier, PG&E’s study process can identify transmission upgrades 12

that would be triggered by the Large Load End User.  These study results are 13

submitted to the CAISO for review in their concurrence process.  In addition, 14

the load identified in PG&E’s interconnection studies, together with other load 15

growth, is also considered in the CAISO’s TPP which can also identify if 16

additional upgrades are required to serve the aggregate load.
17
IX. Other Issues
18
Q.
FERC mentioned electromagnetic transient studies in the OSC, does PG&E 19

include such analysis in its study processes?
20
A. Yes.  PG&E will perform an electromagnetic transient study for a Large Load 21

End User approximately one year before the Load is scheduled to be energized. 22

PDF page 34

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 33 of 37

The timing matters.  An electromagnetic transient study is only as good as the 1

models and assumptions that go into it, including the specific equipment, 2

inverters, and control settings the Large Load End User will install and the 3

condition of the surrounding system when the load comes online.  Early in the 4

interconnection process, much of that information is not yet final, so a study 5

performed at that stage would rest on assumptions that are likely to change and 6

would produce results that are not reliable.  The CAISO faces a similar issue 7

on the generation side, where detailed transient analysis is generally performed 8

later, once equipment and controls are known.  By performing the study about 9

a year ahead of energization, PG&E can use actual equipment data and current 10

system conditions, which allows the study to identify issues on the system 11

more accurately.  A year also leaves enough time to act on the results, such as 12

adjusting control settings or adding protective equipment, before the load is 13

energized.  In short, performing the study at that point makes it a realistic and 14

actionable study rather than a theoretical one.
15
Q.
How do the various study processes consider the unique characteristics and 16

impacts of Large Loads, such as evaluating the transmission system’s ability 17

to withstand risks observed from analyzed Large Load behavior?
18
A. The new NERC Computational Load standards and pending updates to the 19

Company’s Transmission Interconnection Handbook will help define a number 20

of technical requirements specific to Large Load End Users, including detailed 21

operating requirements such as ramp rate limits.  These requirements coupled 22

PDF page 35

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 34 of 37

with detailed stability requirements as proposed in our interconnection study 1

process and active monitoring equipment will enable our operators to manage 2

these loads to maintain reliability.
3
Q.
Can you explain in more detail how you will examine alternative 4

transmission technologies in the study processes?
5
A. During Phase 1 and Phase 2 of the Large Load Cluster Study Process, once the 6

system violations are identified, the transmission planning team will first 7

evaluate whether any alternative transmission technology solutions can apply 8

to mitigate the violations.  If no alternative transmission technology solution 9

applies, transmission planning will proceed with proposals using conventional 10

mitigation solutions
11
Q.
The OSC also indicates that study procedures could include readiness 12

requirements (i.e., meaningful milestones and/or financial commitments) to 13

ensure Large Loads are viable and likely to materialize, does the process 14

proposed include such requirements?
15
A. Mr. Virani addresses the readiness requirements that apply when a TCLL 16

submits its application, which is outside the scope of my expertise.  From a 17

study perspective, however, the process is structured so that a TCLL must 18

affirmatively decide to move forward at each stage, after the scoping meeting, 19

after each study, and after each results meeting, or its request is withdrawn. 20

That keeps requests that are not progressing from occupying study resources or 21

affecting the results for other customers.  In addition, as I noted earlier, a 22

TCLL that proceeds to Phase 2 of the Cluster Study must post Phase 2 23

PDF page 36

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002
Page 35 of 37

Security, which is a meaningful financial commitment at the point where the 1

study results become more concrete.
2
X. Conclusion
3
Q.
Does this conclude your Prepared Direct testimony?
4
A. Yes, it does.
5

PDF page 37

Docket No. ER27-XXXX-000
EXHIBIT PGE-0002

Pacific Gas and Electric Company

Docket No. ER27-XXX-000

DECLARATION
I, Jens Nedrud, identified in the foregoing Prepared Direct testimony, do hereby declare under penalty of perjury, that I prepared or caused such testimony to be prepared; that the answers appearing therein are true to the best of my knowledge and belief; and that if asked the questions appearing therein, my answers would, under oath, be the same.

Executed on November 16, 2026, at Oakland, California.

/s/ Jens Nedrud

Jens Nedrud