Exhibit No. PGE-0002 - Study Process Nedrud
Text extracted from the eLibrary original (SHA-256 13643e5fe968c862…). Download the original from the official source.
Contents · 57 sections
- I. Introduction
- A. My name is Jens Nedrud and I am Director, Electric Transmission Planning
- A. The purpose of my testimony is to describe PG&E’s current process for
- II. Concerns Expressed in the OSC Regarding Study Processes
- A. The Commission generally expressed concern that the CAISO and TO Tariffs
- A. Mr. Virani’s testimony provides a more fulsome explanation, but I also will
- A. Yes, all the Participating TOs’ existing Wholesale Load Interconnection
- A. The changes being proposed are based on the existing roles and
- A. The specific concerns about studies include
- III. PG&E’s Existing Wholesale Load Interconnection study process
- A. When a new Wholesale Load customer seeks to interconnect to PG&E’s
- A. Mr. Virani’s testimony describes the application process and the nature of the
- A. PG&E’s existing TO Tariff outlines the study process for Wholesale Load in
- A. Section 10.6 indicates the Company will use “due diligence” to complete the
- A. If the System Impact Study shows that the request can be accommodated
- A. Yes. Some applicants would rather move forward quickly than wait for a
- A. The upgrades are grouped into three categories, Direct Assignment Facilities,
- A. As already discussed, Participating TOs such as PG&E are responsible for
- A. Yes. As part of the study process, to the extent that upgrades are required to
- IV. The TCLL Interconnection Study Processes
- A. PG&E is proposing to add a new section (Section 10A) to its TO Tariff to
- A. Within 15 Business Days of PG&E deeming an application complete, the
- A. As indicated in the proposed TO Tariff definition, an Electrically Independent
- A. To determine whether a Large Load End User is electrically independent,
- A. Because an Electrically Independent Large Load interconnection does not
- A. PG&E will hold a scoping meeting with the TCLL within 5 Business Days of
- V. Serial Study Process
- A. If a System Impact Study Agreement is required, the Participating TO will
- A. Within 15 Business Days of completion of the System Impact Study, the TCLL
- A. Within 15 Business Days of receipt of the completed Facilities Study, the
- A. The parties then negotiate and execute the TCLL Agreement, Facilities
- A. Generally, the study process identifies all facilities and equipment needed to
- A. Cluster Study Process
- A. It has been my experience that a request to interconnect a significant amount of
- A. PG&E will run one Cluster Study each year. Each year has a closing date of
- A. The Cluster Study Process has two distinct phases. In Phase 1, PG&E will
- A. Within 20 Business Days of providing the final Phase 1 Study report, PG&E
- A. The Phase 2 Study will (i) update, as necessary, analyses performed in the
- A. PG&E will hold a second results meeting to review the Phase 2 results,
- A. One of the Commission’s concerns in the OSC was avoiding disputes over how
- A. Yes, the Company has been performing cluster studies for loads greater than
- A. The Company has found that studying Large Loads collectively as part of a
- A. Each phase of the Cluster Study is targeted for completion within 120 Business
- A. Studying Electrically Dependent Large Loads together produces more accurate
- VI. Interim Interconnection Services
- A. The two services, FILLI Interconnection Service and/or Interim Standard
- VII. TCLL Interconnections associated with Co-Located Large Load End
- A. Yes. These requests are always studied in the Cluster Study Process. To the
- VIII. Interaction of PG&E Study Processes and TPP.
- A. As discussed earlier, PG&E’s study process can identify transmission upgrades
- IX. Other Issues
- A. Yes. PG&E will perform an electromagnetic transient study for a Large Load
- A. The new NERC Computational Load standards and pending updates to the
- A. During Phase 1 and Phase 2 of the Large Load Cluster Study Process, once the
- A. Mr. Virani addresses the readiness requirements that apply when a TCLL
- X. Conclusion
- A. Yes, it does.
Topics in the text: Connecting load and generation · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
ER27-XXXX-000 EXHIBIT PGE-0002 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Pacific Gas and Electric Company Docket No.Read this passage
I. Introduction
printed heading
Please state your name, title, and business address. 5Read this passage
A. My name is Jens Nedrud and I am Director, Electric Transmission Planning
printed heading
My name is Jens Nedrud and I am Director, Electric Transmission Planning 6 with Pacific Gas and Electric Company (“PG&E”).Read this passage
A. The purpose of my testimony is to describe PG&E’s current process for
printed heading · Topic match: Connecting load and generation
The purpose of my testimony is to describe PG&E’s current process for 4 studying Wholesale Load Interconnections and to identify and explain the new 5 study processes PG&E is proposing to adopt to accommodate requests for 6 wholesale interconnection service by entities that PG&E’s Transmission 7…Read this passage
II. Concerns Expressed in the OSC Regarding Study Processes
printed heading
Concerns Expressed in the OSC Regarding Study Processes 13 Q.Read this passage
A. The Commission generally expressed concern that the CAISO and TO Tariffs
printed heading
The Commission generally expressed concern that the CAISO and TO Tariffs 16 lack provisions that address “with sufficient clarity and consistency” how the 17 CAISO and/or the Participating Transmission Owners (“Participating TO”) 18 will timely study the provision of transmission service to…Read this passage
A. Mr. Virani’s testimony provides a more fulsome explanation, but I also will
printed heading · Topic match: Connecting load and generation
Similarly, the CAISO region 10 does not have a process for studying specific requests for transmission service 11 like the traditional process contemplated by the Commission’s pro forma Open 12 Access Transmission Tariff (“OATT”).Read this passage
A. Yes, all the Participating TOs’ existing Wholesale Load Interconnection
printed heading · Topic match: Retail and wholesale authority
ER27-XXXX-000 EXHIBIT PGE-0002 Page 5 of 37 The “retail service” request process, just like the Wholesale Load 1 Interconnection process, results in the studies being performed that, when 2 coupled with the TPP, mean that the Scheduling Coordinators for retail load 3 likewise need not request or be…Read this passage
A. The changes being proposed are based on the existing roles and
printed heading
The changes being proposed are based on the existing roles and 15 responsibilities.Read this passage
A. The specific concerns about studies include
printed heading
ER27-XXXX-000 EXHIBIT PGE-0002 Page 7 of 37 Facilities and network upgrades necessary to accommodate the transmission 1 service request as well as a non-binding good-faith estimate of the cost and the 2 time to construct such facilities, should take no more than 60-90 calendar days 3 to complete.”7…Read this passage
III. PG&E’s Existing Wholesale Load Interconnection study process
printed heading
PG&E’s Existing Wholesale Load Interconnection study process 9 Q.Read this passage
A. When a new Wholesale Load customer seeks to interconnect to PG&E’s
printed heading
When a new Wholesale Load customer seeks to interconnect to PG&E’s 11 transmission system or an existing Wholesale Load customer seeks to modify 12 or expand an existing Wholesale Load Interconnection, PG&E must study the 13 request to determine the impacts on its transmission system.Read this passage
A. Mr. Virani’s testimony describes the application process and the nature of the
printed heading
Virani’s testimony describes the application process and the nature of the 3 customers seeking what is now called a “Wholesale Load Interconnection.” 4 After determining that an application is complete, in a typical situation, the 5 Company tenders a System Impact Study Agreement within 20 Business…Read this passage
A. PG&E’s existing TO Tariff outlines the study process for Wholesale Load in
printed heading
PG&E’s existing TO Tariff outlines the study process for Wholesale Load in 18 Sections 10.4 through 10.8.Read this passage
A. Section 10.6 indicates the Company will use “due diligence” to complete the
printed heading
Section 10.6 indicates the Company will use “due diligence” to complete the 5 System Impact Study within 60 calendar days.Read this passage
A. If the System Impact Study shows that the request can be accommodated
printed heading
If the System Impact Study shows that the request can be accommodated 11 without Direct Assignment Facilities, Reliability Upgrades, or implementing 12 operating procedures, the applicant must request and execute a Wholesale 13 Load Interconnection Agreement that will allow them to interconnect to…Read this passage
A. Yes. Some applicants would rather move forward quickly than wait for a
printed heading
Some applicants would rather move forward quickly than wait for a 6 Facilities Study to refine the cost estimate.Read this passage
A. The upgrades are grouped into three categories, Direct Assignment Facilities,
printed heading
The upgrades are grouped into three categories, Direct Assignment Facilities, 15 Reliability Upgrades, and transmission network upgrades. 16 Q.Read this passage
A. As already discussed, Participating TOs such as PG&E are responsible for
printed heading
As already discussed, Participating TOs such as PG&E are responsible for 19 studying Wholesale Load Interconnections, and the CAISO is responsible for 20 transmission planning generally through the TPP as well as Generation 21 Docket No.Read this passage
A. Yes. As part of the study process, to the extent that upgrades are required to
printed heading
As part of the study process, to the extent that upgrades are required to 14 serve the full Load, PG&E will identify the portion of the requested Load that 15 can be accommodated without any Direct Assignment Facilities or Reliability 16 Upgrades.Read this passage
IV. The TCLL Interconnection Study Processes
printed heading
How is PG&E proposing to change its TO Tariff to address the requirements 2 of the OSC for studying Large Loads? 3Read this passage
A. PG&E is proposing to add a new section (Section 10A) to its TO Tariff to
printed heading
PG&E proposes using a Serial Study Process 5 for TCLL requests that do not impact other customers on the transmission 6 system.Read this passage
A. Within 15 Business Days of PG&E deeming an application complete, the
printed heading
Within 15 Business Days of PG&E deeming an application complete, the 12 Company will perform an Electrical Independence Test to determine if the 13 Large Load End User associated with the TCLL’s Interconnection request 14 qualifies as an Electrically Independent Large Load.Read this passage
A. As indicated in the proposed TO Tariff definition, an Electrically Independent
printed heading
As indicated in the proposed TO Tariff definition, an Electrically Independent 2 Large Load is one where its interconnection impacts are not materially affected 3 by one or more other projects.Read this passage
A. To determine whether a Large Load End User is electrically independent,
printed heading
This test requires PG&E to perform the incremental power flow and 17 aggregate power flow tests, which look at whether the request, on its own and 18 together with other requests, would cause issues on the CAISO Controlled 19 Grid.Read this passage
A. Because an Electrically Independent Large Load interconnection does not
printed heading · Topic match: Connecting load and generation
A TCLL that 11 requests Interim Standard Interconnection Service and/or Flexible Interim 12 Large Load Interconnection Service, however, will need a Facilities Study, 13 because that is where PG&E identifies and estimates the cost of the TCLL 14 FILLI Facilities.Read this passage
A. PG&E will hold a scoping meeting with the TCLL within 5 Business Days of
printed heading
Within 15 Business Days after the meeting, the TCLL must 3 elect to proceed under the applicable Serial Study Process or withdraw its 4 TCLL Interconnection Application.Read this passage
V. Serial Study Process
printed heading
Describe the Serial Study Process that applies to Electrically Independent 10 Large Loads. 11Read this passage
A. If a System Impact Study Agreement is required, the Participating TO will
printed heading
The TCLL then must execute the System 16 Impact Study Agreement and return it to the Participating TO within 15 17 Business Days upon receipt.Read this passage
A. Within 15 Business Days of completion of the System Impact Study, the TCLL
printed heading · Topic match: Connecting load and generation
If it wants a more refined cost estimate, or if it is seeking Interim 19 Standard Interconnection Service and/or FILLI Interconnection Service, it 20 must request that the Participating TO tender a Facilities Study Agreement 21 Docket No.Read this passage
A. Within 15 Business Days of receipt of the completed Facilities Study, the
printed heading
Within 15 Business Days of receipt of the completed Facilities Study, the 14 TCLL shall request the Participating TO to tender a TCLL Agreement, 15 Facilities Agreement, Cost Assurance Agreement, and the optional Interim 16 Service Agreement in accordance with Section 10A.4.8 or withdraw its 17…Read this passage
A. The parties then negotiate and execute the TCLL Agreement, Facilities
printed heading
If the TCLL withdraws its application, the TCLL shall reimburse the 6 Participating TO for the costs reasonably incurred in processing the 7 application, after which its remaining security will be released. 8 Q.Read this passage
A. Generally, the study process identifies all facilities and equipment needed to
printed heading · Topic match: Connecting load and generation
ER27-XXXX-000 EXHIBIT PGE-0002 Page 19 of 37 Interconnection Service and are required to provide the flexible non-firm 1 interim service until the Participating TO and TCLL have completed 2 installation and commissioning of all equipment necessary for Standard 3 Interconnection Service. 4Read this passage
A. Cluster Study Process
printed heading
Why does the Serial Study Process not work for all TCLL Interconnections? 6Read this passage
A. It has been my experience that a request to interconnect a significant amount of
printed heading · Topic match: Connecting load and generation
PG&E already studies all retail service requests for large customers 18 (those > 20 MW) using a cluster study process because it is more cost effective 19 and efficient for the customers.Read this passage
A. PG&E will run one Cluster Study each year. Each year has a closing date of
printed heading
Each year has a closing date of 6 the last day of February, by which an application must be complete and found 7 to be Electrically Dependent, or involve a Co-Located Large Load End User, to 8 be included in that year’s cluster.Read this passage
A. The Cluster Study Process has two distinct phases. In Phase 1, PG&E will
printed heading
The 7 Phase 1 Study shall (i) evaluate the impact of all TCLL Interconnection 8 requests in the cluster; (ii) preliminarily identify for each TCLL 9 Interconnection request the required Direct Assignment Facilities, TCLL 10 Interconnection Network Upgrades, and TCLL FILLI Facilities; (iii) assess…Read this passage
A. Within 20 Business Days of providing the final Phase 1 Study report, PG&E
printed heading
A TCLL that decides to proceed to 6 Phase 2 must sign a Phase 2 Cluster Study Process Agreement, under which it 7 agrees to post refundable security equal to 15 percent of the Phase 1 Study’s 8 estimated cost of its Direct Assignment Facilities and TCLL Interconnection 9 Network Upgrades.Read this passage
A. The Phase 2 Study will (i) update, as necessary, analyses performed in the
printed heading
Phase 2 also includes a transient 15 stability study and as needed, a voltage stability analysis, which are more 16 detailed analyses that are most useful once the cluster has been narrowed to the 17 requests that are moving forward.Read this passage
A. PG&E will hold a second results meeting to review the Phase 2 results,
printed heading
If it does, it 7 requests the TCLL Agreement, Facilities Agreement, Cost Assurance 8 Agreement, and, if applicable, the Interim Service Agreement, and the parties 9 negotiate and execute those agreements, including with the Large Load End 10 User where required.Read this passage
A. One of the Commission’s concerns in the OSC was avoiding disputes over how
printed heading
If 11 it becomes clear that we will not complete a study within the target timeframe, 12 whether because of the number of requests, study complexity, coordination 13 with the CAISO, or the availability of contractors, we will notify the TCLLs, 14 explain why, and provide an estimated completion…Read this passage
A. Yes, the Company has been performing cluster studies for loads greater than
printed heading
What has been the Company’s experience to date with these CPUC- 2 jurisdictional Large Load interconnection requests? 3Read this passage
A. The Company has found that studying Large Loads collectively as part of a
printed heading
In PG&E’s experience, studying 6 Electrically Dependent Large Load requests on a serial basis is extremely 7 inefficient.Read this passage
A. Each phase of the Cluster Study is targeted for completion within 120 Business
printed heading
However, the Company proposes to conduct one Cluster 21 Docket No.Read this passage
A. Studying Electrically Dependent Large Loads together produces more accurate
printed heading
For requests that are electrically 13 independent and do not seek an optional Facilities Study, our proposed TO 14 Tariff language targets completion of the System Impact Study process within 15 90 Business Days. 16 PG&E has been studying “electrically dependent” Large Loads for 17 several years…Read this passage
VI. Interim Interconnection Services
printed heading · Topic match: Connecting load and generation
Can you describe the new FILLI Interconnection Service and Interim 4 Standard Interconnection Service and how you will study them? 5Read this passage
A. The two services, FILLI Interconnection Service and/or Interim Standard
printed heading · Topic match: Connecting load and generation
As for 10 the remaining Load, or all the Load if no Interim Standard Interconnection 11 Service is available, FILLI Interconnection Service is an optional 12 interconnection service that PG&E and the CAISO are proposing to offer. 13 PG&E’s study process for FILLI Interconnection Service will…Read this passage
VII. TCLL Interconnections associated with Co-Located Large Load End
printed heading
Are there any special conditions associated with studying requests from 15 TCLLs when the associated Large Load is co-located with, and at least 16 partially supplied by that co-located generation? 17Read this passage
A. Yes. These requests are always studied in the Cluster Study Process. To the
printed heading · Topic match: Connecting load and generation
These requests are always studied in the Cluster Study Process.Read this passage
VIII. Interaction of PG&E Study Processes and TPP.
printed heading
Interaction of PG&E Study Processes and TPP. 10 Q.Read this passage
A. As discussed earlier, PG&E’s study process can identify transmission upgrades
printed heading
As discussed earlier, PG&E’s study process can identify transmission upgrades 12 that would be triggered by the Large Load End User.Read this passage
IX. Other Issues
printed heading
FERC mentioned electromagnetic transient studies in the OSC, does PG&E 19 include such analysis in its study processes? 20Read this passage
A. Yes. PG&E will perform an electromagnetic transient study for a Large Load
printed heading
PG&E will perform an electromagnetic transient study for a Large Load 21 End User approximately one year before the Load is scheduled to be energized. 22 Docket No.Read this passage
A. The new NERC Computational Load standards and pending updates to the
printed heading
The new NERC Computational Load standards and pending updates to the 19 Company’s Transmission Interconnection Handbook will help define a number 20 of technical requirements specific to Large Load End Users, including detailed 21 operating requirements such as ramp rate limits.Read this passage
A. During Phase 1 and Phase 2 of the Large Load Cluster Study Process, once the
printed heading
During Phase 1 and Phase 2 of the Large Load Cluster Study Process, once the 6 system violations are identified, the transmission planning team will first 7 evaluate whether any alternative transmission technology solutions can apply 8 to mitigate the violations.Read this passage
A. Mr. Virani addresses the readiness requirements that apply when a TCLL
printed heading
From a 17 study perspective, however, the process is structured so that a TCLL must 18 affirmatively decide to move forward at each stage, after the scoping meeting, 19 after each study, and after each results meeting, or its request is withdrawn. 20 That keeps requests that are not progressing…Read this passage
X. Conclusion
printed heading
Does this conclude your Prepared Direct testimony? 4Read this passage
A. Yes, it does.
printed heading
ER27-XXXX-000 EXHIBIT PGE-0002 Pacific Gas and Electric Company Docket No.Read this passage