TO: Response to Large Load Order to Show Cause in EL26-71-000
Pacific Gas and Electric files tariff amendments under section 205 on November 16, 2026, in ER27-513-000, answering the CAISO show cause order. A new Section 10A sets an application and study process for utilities that serve large loads, with four pro forma agreements covering facilities, cost assurance and optional curtailable interim service.
Asks FERC to: Accept the amendments effective February 16, 2027, find them just and reasonable, and terminate the show cause proceeding as to PG&E.
Filed under section 205 to answer the E-10 show cause order for PG&E's own transmission owner tariff. PG&E says it covers the application, cost recovery and flexible service items, and leaves electrically proximate generation to CAISO.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)
Key points
- PG&E builds the response around a new tariff section for the utilities that buy transmission service for large loads.
primarily through a new Section 10A of its TO Tariff that governs the interconnection of TCLLs to the transmission system on behalf of their Large Load End Users PDF p. 3
- PG&E adopts CAISO's definition of large load.
PG&E proposes to amend its TO Tariff to adopt the CAISO’s proposed definition of Large Load PDF p. 10
- Each application needs a cash study deposit plus per-megawatt security.
The study deposit requirement includes a $500,000 cash deposit and financial security in the amount of $1,000 per MW of requested maximum load PDF p. 13
- Independent loads are studied one at a time. Dependent loads are studied in an annual cluster.
PG&E proposes a Serial Study Process for Electrically Independent Large Loads and a Cluster Study Process for Electrically Dependent Large Loads PDF p. 16
- A cost assurance agreement sets a minimum annual revenue obligation backed by five years of security.
the Cost Assurance Agreement establishes a Minimum Annual Revenue Obligation payable by the TCLL/Large Load End User and a Financial Security requirement equal to five (5) times the Minimum Annual Revenue Obligation PDF p. 31
- Leaving early triggers an exit fee equal to the required security.
the Cost Assurance Agreement provides for an Exit Fee equal to the value of the required Financial Security on the date of termination PDF p. 34
- The interim service is curtailable at all times and only available within limits.
FILLI Interconnection Service is subject to curtailment at all times, and is available only where the Participating TO determines service may be provided within limitations in certain periods under normal operating conditions PDF p. 39
- PG&E says it and SCE agreed on how cost responsibility and flexible service should work.
PG&E and Southern California Edison Company (“SCE”) reached broad consensus on the cost responsibility and flexible service frameworks adopted in their respective proposals PDF p. 4
Text extracted from the eLibrary original (SHA-256 26f1e93cfbb843d2…). Download the original from the official source.
Contents · 38 sections
- I. INTRODUCTION
- II. BACKGROUND
- A. CAISO Is a Unique Transmission Market That Does Not Operate in
- B. CAISO and the PTOs Each Perform Unique and Coordinated
- C. PG&E and the Other Founding Transmission Owning Members of
- D. The OSC Preliminarily Found the CAISO and TO Tariffs to Be Unjust
- III. PG&E SUPPORTS THE CAISO’S PROPOSED DEFINITION OF LARGE LOAD
- A. The OSC Requires a Definition of Large Load Sufficient to Capture
- B. PG&E Supports and Adopts CAISO’s Proposed Definition of Large
- IV. PG&E PROPOSES JUST AND REASONABLE CHANGES TO ITS TARIFF TO
- A. PG&E Proposes a Just and Reasonable Process for a TCLL to Apply
- B. PG&E Proposes a Just and Reasonable Study Process for Evaluating
- V. PG&E PROPOSES A SET OF PRO FORMA AGREEMENTS TO MEET THE
- A. PG&E Proposes a Just and Reasonable Set of Agreements to Address
- B. PG&E Proposes to Address the Operational and General Pro Forma
- C. PG&E Proposes to Address the Cost Assurance Requirements of the
- D. PG&E Proposes Changes to the TO Tariff That Provide a Just and
- VI. PG&E PROPOSES CHANGES TO THE TO TARIFF THAT PROVIDE A JUST
- A. The CAISO and the Participating TOs Propose to Maintain the
- B. PG&E Proposes to Include a New Process for Addressing the TCLL
- C. Electrically Proximate Load
- VII. PG&E PROPOSES A TRANSITION PERIOD CONSISTENT WITH THE
- VIII. OTHER CHANGES TO THE TO TARIFF
- IX. RESPONSES TO THE OSC BRIEFING QUESTIONS
- A. Protection of Existing Commercial Arrangements
- B. Impacts of New FILLI Interconnection Service on Transmission
- C. Structure of Cost Recovery Agreements and Minimum Cost Recovery
- D. Evaluation of Alternative Transmission Technologies
- E. Generating Facilities Serving Electrically Proximate Large Load or
- X. ETARIFF CHANGES
- XI. EFFECTIVE DATE
- XII. CORRESPONDENCE AND COMMUNICATIONS
- XIII. ADDITIONAL INFORMATION REQUIRED BY REGULATION 35.13(b)
- A. Contents of Filing
- B. Service
- C. Description of and Reason for Changes
- D. Request for Waivers
- XIV. CONCLUSION
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
EL26-71-000.1 Specifically, PG&E proposes changes to its TO Tariff to implement a process that will enable Transmission Customers for Large Load (“TCLLs”) to interconnect “Large Load End Users” to the PG&E transmission system.Read this passage
I. INTRODUCTION
printed heading · Topic match: Connecting load and generation
The OSC seeks application study processes with defined timelines and readiness requirements that deter speculative or duplicative requests, which can delay studies, distort load forecasts, and lead to unnecessary network upgrades, and it directs the evaluation of alternative transmission…Read this passage
II. BACKGROUND
printed heading
II.Read this passage
A. CAISO Is a Unique Transmission Market That Does Not Operate in
printed heading · Topic match: Reliability and curtailment
Reese, Secretary November 16, 2026 Page 5 its need.17 Those transmission reservation requests are made through a formal application process set forth in the transmission provider’s Tariff.18 As the OSC recognizes, the CAISO’s framework differs from this traditional framework in several key ways.Read this passage
B. CAISO and the PTOs Each Perform Unique and Coordinated
printed heading · Topic match: Connecting load and generation
CAISO and the PTOs Each Perform Unique and Coordinated Functions with Respect to Requests to Interconnect to the Transmission System Participating TOs are responsible for studying requests from customers with Wholesale Load to interconnect to the CAISO-controlled transmission system (“CAISO…Read this passage
C. PG&E and the Other Founding Transmission Owning Members of
printed heading · Topic match: Connecting load and generation
These retail tariffs govern the study costs, retail rates, and potential cost recovery for retail Load interconnections.37 However, when the MSS or UDC is not a PTO, the MSS or UDC must seek Wholesale Load Interconnection service through the Participating TO Tariff to provide transmission service…Read this passage
D. The OSC Preliminarily Found the CAISO and TO Tariffs to Be Unjust
printed heading · Topic match: Cost allocation
The Commission directed its findings to “CAISO’s Tariff and/or the TO Tariffs” and expected the CAISO and the Participating TOs to “coordinate with each other, as appropriate, to develop responses to this order.”42 Consistent with that direction, the CAISO 38 See Order No. 888-A, FERC Stats. &…Read this passage
III. PG&E SUPPORTS THE CAISO’S PROPOSED DEFINITION OF LARGE LOAD
printed heading
PG&E SUPPORTS THE CAISO’S PROPOSED DEFINITION OF LARGE LOAD AS BEING JUST AND REASONABLE.Read this passage
A. The OSC Requires a Definition of Large Load Sufficient to Capture
printed heading
The OSC Requires a Definition of Large Load Sufficient to Capture the Loads That Present the Unique Challenges to the Transmission System Identified in the OSC.Read this passage
B. PG&E Supports and Adopts CAISO’s Proposed Definition of Large
printed heading
In response to the OSC, PG&E proposes to amend its TO Tariff to adopt the CAISO’s proposed definition of Large Load.Read this passage
IV. PG&E PROPOSES JUST AND REASONABLE CHANGES TO ITS TARIFF TO
printed heading · Topic match: Connecting load and generation
PG&E PROPOSES JUST AND REASONABLE CHANGES TO ITS TARIFF TO IMPLEMENT A NEW APPLICATION AND STUDY PROCESS FOR TCLLS INTERCONNECTING LARGE LOAD END USERS TO THE PG&E TRANSMISSION SYSTEM.Read this passage
A. PG&E Proposes a Just and Reasonable Process for a TCLL to Apply
printed heading · Topic match: Connecting load and generation
In addition, if the TCLL Interconnection Application requests Interim Standard Interconnection Service and/or FILLI Interconnection Service, the TCLL must so indicate and, if FILLI Interconnection Service is requested, the FILLI Interconnection Service addendum to the TCLL Interconnection…Read this passage
B. PG&E Proposes a Just and Reasonable Study Process for Evaluating
printed heading · Topic match: Connecting load and generation
PG&E’s proposed study procedure will also account for the dynamic behavior of Large Load End Users at the Point of Withdrawal on the CAISO system, consistent with the OSC directives.90 In addition, in accordance with the OSC, PG&E will assess alternative transmission technologies and where…Read this passage
V. PG&E PROPOSES A SET OF PRO FORMA AGREEMENTS TO MEET THE
printed heading
PG&E PROPOSES A SET OF PRO FORMA AGREEMENTS TO MEET THE VARIOUS REQUIREMENTS OF THE OSCRead this passage
A. PG&E Proposes a Just and Reasonable Set of Agreements to Address
printed heading · Topic match: Connecting load and generation
The TCLL and Associated Agreements will be executed after the study process is complete and after the facilities needed for Standard Interconnection Service have been identified and, optionally, the facilities needed for FILLI Service and Interim Standard Interconnection Service.104 101 Id. at 27.…Read this passage
B. PG&E Proposes to Address the Operational and General Pro Forma
printed heading · Topic match: Connecting load and generation
Instead, it expressly permitted those requirements to be memorialized in a transmission service agreement “or other applicable agreement.”108 To address these general requirements for interconnection service, PG&E proposes a new pro forma TCLL Agreement.Read this passage
C. PG&E Proposes to Address the Cost Assurance Requirements of the
printed heading · Topic match: Connecting load and generation
PG&E will require studying load under both N-1-1 and N-1 conditions to determine how much, if any, FILLI Interconnection Service can be offered while upgrades are being constructed to enable Standard Interconnection Service for the entire load request.153 The study will identify capacity (in MW) of…Read this passage
D. PG&E Proposes Changes to the TO Tariff That Provide a Just and
printed heading
PG&E Proposes Changes to the TO Tariff That Provide a Just and Reasonable Process for Affected Systems The OSC does not separately address affected systems.Read this passage
VI. PG&E PROPOSES CHANGES TO THE TO TARIFF THAT PROVIDE A JUST
printed heading · Topic match: Connecting load and generation
PG&E PROPOSES CHANGES TO THE TO TARIFF THAT PROVIDE A JUST AND REASONABLE PROCESS FOR LARGE LOADS THAT SEEK TO CO- LOCATE WITH GENERATION PROJECTS In the OSC, the Commission preliminarily found that the CAISO Tariff appears to be unjust and unreasonable because it does not contain provisions…Read this passage
A. The CAISO and the Participating TOs Propose to Maintain the
printed heading · Topic match: Connecting load and generation
The Commission recognized that co-location concerns “mostly implicate the CAISO Tariff,” because only the CAISO Tariff governs the generator interconnection process.166 Accordingly, the OSC directs the CAISO to clarify how interconnection customers may use the generator interconnection process to…Read this passage
B. PG&E Proposes to Include a New Process for Addressing the TCLL
printed heading
PG&E Proposes to Include a New Process for Addressing the TCLL Portion of the Co-Located Large Load End User Interconnection Process that will Ensure Coordination with the CAISO’s Generator Interconnection Process.Read this passage
C. Electrically Proximate Load
printed heading · Topic match: Connecting load and generation
Electrically Proximate Load In the OSC, the Commission preliminarily finds that the CAISO Tariff appears to be unjust and unreasonable because it lacks a generator interconnection study process and/or generator interconnection service to reflect an interconnection customer’s commitment to limit the…Read this passage
VII. PG&E PROPOSES A TRANSITION PERIOD CONSISTENT WITH THE
printed heading · Topic match: Cost allocation
PG&E PROPOSES A TRANSITION PERIOD CONSISTENT WITH THE REQUIREMENTS OF THE OSC.Read this passage
VIII. OTHER CHANGES TO THE TO TARIFF
printed heading
OTHER CHANGES TO THE TO TARIFF In addition to adding a new Section 10A, as well as replacing the currently unused Appendix XI, the new Large Load processes had a ripple effect on other TO Tariff sections, including, most importantly, the Definitions, where many new terms were added.Read this passage
IX. RESPONSES TO THE OSC BRIEFING QUESTIONS
printed heading
RESPONSES TO THE OSC BRIEFING QUESTIONS Section IV of the OSC directs further briefing on five sets of questions.Read this passage
A. Protection of Existing Commercial Arrangements
printed heading · Topic match: Retail and wholesale authority
Requests completed before the effective date will continue to be processed under PG&E’s existing Section 10 process for Wholesale Load Interconnection Applications.Read this passage
B. Impacts of New FILLI Interconnection Service on Transmission
printed heading · Topic match: Connecting load and generation
Impacts of New FILLI Interconnection Service on Transmission Planning The OSC also asks what potential impacts on regional and local transmission planning would arise from the introduction of new transmission services for flexible Large Loads, including how providers and planners would account for…Read this passage
C. Structure of Cost Recovery Agreements and Minimum Cost Recovery
printed heading · Topic match: Cost allocation
Structure of Cost Recovery Agreements and Minimum Cost Recovery and Financial Security The OSC directs respondents to provide information on potential structures for agreements between the transmission owner or provider and an Eligible Customer to prevent unjust and unreasonable cost shifts related…Read this passage
D. Evaluation of Alternative Transmission Technologies
printed heading
D.Read this passage
E. Generating Facilities Serving Electrically Proximate Large Load or
printed heading · Topic match: Connecting load and generation
Generating Facilities Serving Electrically Proximate Large Load or Large Co-Located Load The OSC asks (a) to what extent the CAISO would allow an interconnection customer’s generating facility serving electrically proximate large load or large co-located load to participate in the CAISO’s energy…Read this passage
X. ETARIFF CHANGES
printed heading
ETARIFF CHANGES When PG&E initially sectionalized its TO Tariff, it sectionalized the tariff to a greater degree than required (i.e., three levels).Read this passage
XI. EFFECTIVE DATE
printed heading
EFFECTIVE DATE PG&E requests that the Commission accept the proposed amendment to the TO Tariff without hearing, modification, or condition effective Tuesday, February 16, 2027.Read this passage
XII. CORRESPONDENCE AND COMMUNICATIONS
printed heading
CORRESPONDENCE AND COMMUNICATIONS PG&E requests that all correspondence, pleadings, and other communications concerning this filing be served upon the following: Tara Kaushik John P.Read this passage
XIII. ADDITIONAL INFORMATION REQUIRED BY REGULATION 35.13(b)
printed heading
ADDITIONAL INFORMATION REQUIRED BY REGULATION 35.13(b)Read this passage
A. Contents of Filing
printed heading
Contents of Filing This filing consists of the following documents in addition to the Tariff Records: • The instant Transmittal Letter; • Clean Tariff Attachment; • Marked Tariff Attachment;182 182 The Marked Tariff Attachment does not include Section 10A and Appendix XI, which are entirely new.Read this passage
B. Service
printed heading
Service Copies of this filing have been served upon the CPUC and the CAISO.Read this passage
C. Description of and Reason for Changes
printed heading
Description of and Reason for Changes A detailed description of the changes are included above.Read this passage
D. Request for Waivers
printed heading
To the extent necessary, PG&E requests waiver of the requirement to submit cost-of-service data required by 18 C.F.R. § 35.13.Read this passage
XIV. CONCLUSION
printed heading
CONCLUSION PG&E requests that the Commission find the proposed changes to the TO Tariff detailed herein just and reasonable and that the changes address the issues raised in the OSC.Read this passage
CERTIFICATE OF SERVICE
printed heading
Hammond Assistant General Counsel California Public Utilities Commission 505 Van Ness Avenue San Francisco, CA 94102 Christine.hammond@cpuc.ca.gov Anthony Ivancovich Deputy General Counsel California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 aivancovich@caiso.com…Read this passage