ER27-513-000 · 2026-11-16 · Pacific Gas and Electric Company
TO: Response to Large Load Order to Show Cause in EL26-71-000
PDF page 1
Mailing Address
P.O. Box 1018
Oakland, CA 94612-3534
501-551-4036
John.Perkins@pge.com
John Perkins III
Chief Counsel
November 16, 2026
The Honorable Debbie-Anne A. Reese, Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
RE: Tariff Amendments in Response to FERC Order to Show Cause in Docket No. EL26-71-000
Filing Code: 10
Dear Secretary Reese:
Pursuant to section 205 of the Federal Power Act (“FPA”), Pacific Gas and Electric Company (“PG&E”) submits amendments to its Transmission Owners Tariff, FERC Electric Tariff Volume No. 5 (“TO Tariff”), to address the issues identified by the Federal Energy Regulatory Commission (“Commission” or “FERC”) as potentially unjust and unreasonable in its Order to Show Cause (“OSC”) issued in Docket No. EL26-71-000.1 Specifically, PG&E proposes changes to its TO Tariff to implement a process that will enable Transmission Customers for Large Load (“TCLLs”) to interconnect “Large Load End Users” to the PG&E transmission system. The process will ensure that the necessary transmission facilities are in place to provide the interconnection and transmission service required for the TCLLs to serve those customers.2 PG&E’s proposed TO Tariff amendments and this filing are submitted in response to and answer the OSC pursuant to section 206 of the FPA, 16 U.S.C. § 824e, Rule 213 of the Commission’s Rules of Practice and Procedure, and Ordering Paragraph B of the OSC. PG&E requests that the Commission find the proposed changes to the TO Tariff just and reasonable and that the changes address the issues raised in the OSC. PG&E notes that the CAISO is proposing amendments to the CAISO Open Access Transmission Tariff (“CAISO Tariff”) to address the issues raised in the OSC regarding the CAISO Tariff. PG&E requests that the Commission accept the proposed changes effective February 16, 2027, the same day that the
1 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (“OSC”).
2 The TO Tariff defines a TCLL as a “[Utility Distribution Company (“UDC”) or [Metered Subsystem (“MSS”] that provides service to Large Load End User(s); a UDC or MSS procures transmission service from the ISO based on its Gross Load in order to deliver power to End Users.” TCLLs are referred to in other regions and the OSC as “Eligible Customers” (i.e., customers that take transmission service on behalf of Loads, including Large Loads, in the CAISO’s Balancing Authority Area (“BAA”)).
PDF page 2
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 2
CAISO requests that its proposed changes become effective. PG&E also requests that the Commission, through its acceptance of PG&E’s proposed TO Tariff changes, terminate the show cause proceeding as to PG&E.
I. INTRODUCTION
The California Energy Commission (“CEC”) forecasts that data center load in the CAISO BAA will increase by 1.8 gigawatts (“GW”) by 2030 and 4.9 GW by 2040.3 In recent years, PG&E has received substantially more applications from large load customers seeking transmission-level interconnections.4 The OSC arises from this increase in large load. On June 18, 2026, the Commission issued the OSC in Docket No. EL26-71 as one of six- region specific orders to show cause addressing the unprecedented growth of large loads.5 The Commission instituted this proceeding to address the “urgent challenges associated with providing the transmission service needed to serve the ongoing influx of large loads while maintaining reliability and affordability,” including concerns that large loads are not efficiently integrated onto the transmission system, that they pose unique reliability challenges, and that the rates, terms, and conditions of transmission service may not remain just and reasonable as large loads are added.6 The OSC preliminarily finds that the CAISO Tariff and the TO Tariffs may lack the provisions needed to provide transmission service to TCLLs reliably, affordably, and without shifting costs to other transmission customers.7 The OSC’s preliminary findings reflect four related policy objectives.
The first is reliability. The OSC finds that large loads can be more energy-intensive and geographically concentrated than other load growth and can affect the transmission system in
3 CAISO, Large Load Considerations Issue Paper at 3, 8-9 (Jan. 30, 2026) (“CAISO Issue Paper”), https://www.caiso.com/documents/issue-paper-large-load-consideration-jan-20-2026.pdf (citing CEC data center forecast assumptions: https://www.energy.ca.gov/sites/default/files/2025-11- 2025_IEPR_Preliminary_Data_Center_Forecast_ada.pfg).
4 OSC at P 8 (citing PG&E November ANOPR Comments at 3). See generally Application of Pac. Gas & Elec. Co. for Approval of Elec. Rule No. 30, A.24-11-007, Decision Partly Granting and Partly Denying PG&E’s Motion for Interim Implementation of Electric Rule No. 30, at 15 & Finding of Fact 7 (Cal. P.U.C. [July 24, 2025]) (“Rule 30 Interim Decision”).5 PJM Interconnection, LLC, 195 FERC ¶ 61,211 (2026); Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026); N.Y. Indep. System Operator, Inc., 195 FERC ¶ 61,216 (2026); Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026); ISO New England Inc., 195 FERC ¶ 61,215 (2026). See also PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (PJM Show Cause Order); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (PJM Co-Location Order); Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (SPP HILL Order); Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026) (SPP CHILLS Order); see also, e.g., Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025); Commonwealth Edison Co., 194 FERC ¶ 61,181 (2026).6 OSC PP 1-2.7 OSC at PP 1-5; See also Interconnection of Large Loads to the Interstate Transmission System, Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (Oct. 23, 2025) (ANOPR).
PDF page 3
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 3
ways comparable to large generators, and therefore, require study processes and ongoing operational requirements tailored to their characteristics.8 The second is timely and efficient integration. The OSC seeks application study processes with defined timelines and readiness requirements that deter speculative or duplicative requests, which can delay studies, distort load forecasts, and lead to unnecessary network upgrades, and it directs the evaluation of alternative transmission technologies that can add capacity more quickly and at lower cost.9 The third is protection of transmission customers. The Commission seeks transparency regarding the network upgrades and costs needed to serve large loads, and a cost recovery agreement to ensure that transmission customers serving large loads bear their fair share of the costs to provide transmission service to those loads.10 The fourth is flexibility. The OSC notes that “load flexibility can avoid inefficient and costly transmission system build-out.”11 Accordingly, the Commission seeks tariff provisions that offer transmission services, with regional variation as appropriate, that reflect “the use of the transmission system by Eligible Customers on behalf of flexible large load, on both an interim and permanent basis.”12 In ordering these directives to be met, however, the OSC acknowledges that the CAISO framework “is unique among the RTOs/ISOs” and that certain responsibilities fall to the Participating Transmission Owners (“PTOs” or “Participating TOs”), and the Commission does not seek to alter the allocation of responsibilities between the CAISO and the PTOs.13
PG&E’s proposal responds to each of these concerns within the CAISO’s existing structure and provides a clear, standardized framework that the growth of large loads in PG&E’s service territory and the CAISO more broadly requires. Because the CAISO does not offer traditional stand-alone transmission service, PG&E proposes to implement the OSC’s directives primarily through a new Section 10A of its TO Tariff that governs the interconnection of TCLLs to the transmission system on behalf of their Large Load End Users. PG&E also proposes to implement four new pro forma agreements, which can be found in Appendix XI of PG&E’s TO Tariff.14 Specifically, PG&E proposes: (1) an application process with readiness requirements, and separate Serial and Cluster Study processes for Electrically Independent and Electrically Dependent Large Loads; (2) an Agreement to Interconnect Transmission Customer for Large Load (“TCLL Agreement”) memorializing the TCLL Interconnection; (3) a Facilities Agreement governing construction and the cost responsibility framework for Direct Assignment and TCLL Interconnection Network Upgrades and expansions; (4) a Cost Assurance Agreement that protects other transmission customers from cost shifting associated with TCLL Reliability Network Upgrades; and (5) a voluntary Interim Service Agreement that allows a TCLL to permit Large Load End Users to begin taking Flexible Interim Large Load Interconnection Service
8 Id. at PP 51-52, 57, 62.9 Id. at PP 54-55, 60.10 Id. at PP 65-66, 80.11 Id. at P 104.12 Id. at 104-105. 13 Id. at P 37.14 These changes triggered other TO Tariff changes that are addressed herein.
PDF page 4
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 4
(“FILLI Interconnection Service”), subject to curtailment, while the facilities needed for traditional Standard Interconnection Service are completed.
In developing these proposals, PG&E coordinated with the other Participating TOs in the CAISO footprint. PG&E and Southern California Edison Company (“SCE”) reached broad consensus on the cost responsibility and flexible service frameworks adopted in their respective proposals. PG&E is also aligned with San Diego Gas & Electric Company (“SDG&E”) and LS Power Grid California, LLC (“LS Power”) on requiring a financial mechanism to protect against the risk of cost shifting due to speculative or departing loads. PG&E’s proposed changes provide the clarity, consistency, and protection the OSC seeks. They also preserve the CAISO’s Transmission Planning Process (“TPP”) as the primary means by which the CAISO plans the system to serve aggregate Load growth, including Large Loads, and preserve the coordinated roles of the CAISO and the Participating TOs.
For these reasons and the reasons set forth below, PG&E requests that the Commission find the proposed changes to the TO Tariff just and reasonable and that the changes address the issues raised in the OSC.
II. BACKGROUND
A. CAISO Is a Unique Transmission Market That Does Not Operate in
the Same Manner as Other RTOs.
The OSC recognizes that “the framework under which CAISO provides transmission service is unique among the RTOs/ISOs and that certain responsibilities fall to the Participating Transmission Owners.”15 Most other regions operate under the traditional framework established in Order No. 888. There, the Commission required all public utilities that own, operate, or control interstate transmission facilities to offer network and point-to-point transmission services to all Eligible Customers under a pro forma open access transmission tariff, and established “rules for discounting practices, provisions governing priority of service and curtailment, and a right of first refusal for all firm transmission customers.”16 That framework is based on advance reservations of transmission capacity by transmission customers. A transmission customer, including the transmission provider, may reserve existing capacity for native and network load growth, and the customer may secure firm transmission service ahead of
15 OSC at P 37.16 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996), order on reh'g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, order on reh'g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh'g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff'd in relevant part sub nom. Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002).
PDF page 5
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 5
its need.17 Those transmission reservation requests are made through a formal application process set forth in the transmission provider’s Tariff.18
As the OSC recognizes, the CAISO’s framework differs from this traditional framework in several key ways. The CAISO’s transmission service model has no formal application process for transmission service, and wholesale transmission customers do not reserve transmission capacity in advance.19 Instead, Scheduling Coordinators—entities certified by the CAISO to submit balanced schedules on behalf of customers20—submit bids or self-schedules for supply and demand into the CAISO day-ahead and real-time markets, with equal access to all available transmission capacity each day. If available transmission capacity is insufficient, losing bidders cannot schedule service. If in real-time all accepted schedules cannot be met, due to unexpected or unplanned events, the CAISO curtails schedules based on tariff-defined scheduling priorities.21
Unlike a traditional network customer, the Scheduling Coordinator does not reserve, or pay for, transmission service on behalf of a specific Load. Nor does the Scheduling Coordinator pay an access charge for scheduling and settling Load on behalf of Eligible Customers. Rather, the CAISO Tariff assesses Regional and Local Access Charges on each UDC or MSS, as Eligible Customers, represented by a Scheduling Coordinator to serve Load. As a result, the functions of a single network customer requesting service in other RTOs are divided among, and coordinated between, the PTOs, Scheduling Coordinators, and UDCs and MSSs.
Under this unique framework, the CAISO does not refer to wholesale transmission customers as “Eligible Customers” in the same way as the OSC.22 Rather, in the CAISO, an “Eligible Customer” is the UDC or MSS that procures transmission service and provides service to Large Load End Users.23 PG&E is therefore proposing terminology tailored to how transmission service is provided to the same wholesale transmission customers referenced in the
17 Order No. 888-B, 81 FERC ¶ 61,248 (1997) (addressing the provider’s ability to reserve existing capacity for native and network load growth, and a firm point-to-point customer’s options to elect network service, extend its contract term, or reassign capacity).18 See pro forma Tariff §§ 17, 29. See also, Open Access Same-Time Information System (formerly Real- Time Information Networks) and Standards of Conduct, Order No. 889 (establishing the OASIS through which requests for service under the pro forma tariff are made).19 Virani Testimony at 2-3; Nedrud Testimony at 2-5; OSC at P 39. 20 Cal. Indep. Sys. Operator Corp., 87 FERC ¶ 61,143 (1999) (describing Scheduling Coordinators as entities certified by the ISO to submit balanced schedules under the ISO Tariff).21 See generally CAISO Tariff § 7.22 Virani Testimony at 2-3.23 See generally CAISO Tariff § 4.4 (Relationship Between CAISO and UDCs).
PDF page 6
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 6
OSC.24 For these reasons, PG&E refers to the entities that receive transmission service on behalf of Large Loads as TCLLs, not Eligible Customers.25
B. CAISO and the PTOs Each Perform Unique and Coordinated
Functions with Respect to Requests to Interconnect to the
Transmission System
Participating TOs are responsible for studying requests from customers with Wholesale Load to interconnect to the CAISO-controlled transmission system (“CAISO Controlled Grid”) or increase or modify the nature or number of delivery points to serve such Load as it grows under the TO Tariff.26 PG&E’s Wholesale Load Interconnection service is coordinated with the CAISO, which provides Market Access and Generation (i.e., resource) interconnection service to such Wholesale Load.27 This coordinated framework supports the respective tariff responsibilities of the Participating TOs and the CAISO under the Transmission Control Agreement and ensures that Wholesale Load Interconnections are studied, planned, and implemented consistent with transmission reliability requirements and long-term transmission plans.28 Applicants seeking wholesale generation interconnection to the CAISO Controlled Grid submit their requests to the CAISO, while applicants seeking Wholesale Load Interconnection submit their requests to the relevant Participating TO.29
The CAISO reviews the impacts of all new Load interconnections and increases in Load growth using two related processes. The first is the annual TPP conducted under Section 24 of the CAISO Tariff. The TPP is the process the CAISO uses to plan the transmission system and approve transmission solutions, including constructing new transmission facilities and network upgrades, to serve load growth within the CAISO footprint.30 The TPP integrates the CEC statewide long-term energy demand forecast and the CPUC’s integrated resource planning information, both of which consider and account for large loads.31 The second is the CAISO’s “concurrence” process, which allows the Participating TOs to propose transmission solutions and
24 See CAISO, Proposed Appendix A (definition of "Large Load"), Second Revised Draft Tariff Language
– Large Loads Order to Show Cause at 17 (Oct. 30, 2026),
https://stakeholdercenter.caiso.com/InitiativeDocuments/Second-Revised-Draft-Tariff-Language-Large- Loads-Order-to-Show-Cause-Oct-30-2026.docx. (“CAISO Tariff, Proposed”).
25 Virani Testimony at 2-3, 5-6.26 Wholesale loads connecting to the Distribution System of PG&E interconnect under its Wholesale Distribution Tariff (“WDT”).27 Generator interconnections to the Distribution System of PG&E also are subject to the WDT.28 Virani Testimony at 3-6; Nedrud Testimony at 3-5.29 See TO Tariff, § 10.30 CAISO Tariff § 24.1; OSC at PP 21-22 & n.79; Memorandum of Understanding Between the CPUC, the CEC, and the CAISO Regarding Transmission and Resource Planning and Implementation (Dec. 2022).31 CAISO, Large Load Considerations Issue Paper at 8-10 (Jan. 30, 2026).
PDF page 7
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 7
network upgrades in the TPP when Load seeks to interconnect after the demand forecast and resource portfolios have been developed.32 Under this process, the Participating TO studies the proposed Load interconnection and identifies any Reliability and network upgrades.33 The Participating TO may then submit the Load interconnection study results to the CAISO for review and concurrence that the Load meets applicable transmission reliability and long-term transmission planning requirements.34 The CAISO reviews the interconnection studies, together with other Load growth, in the TPP to determine whether additional upgrades are necessary.35 The CAISO, however, does not conduct studies to determine the necessary network upgrades for the provision of transmission service outside the TPP.36
C. PG&E and the Other Founding Transmission Owning Members of
CAISO Have Unique and Specific Roles.
PG&E is one of the three Original Participating Transmission Owners (“Original
Participating TOs”) that transferred Operational Control of their transmission facilities to the CAISO while retaining ownership, physical operation, and maintenance responsibilities of those facilities. The Original Participating TOs have a distinct position within the CAISO market structure.
Like the other Original Participating TOs, PG&E must purchase transmission service for all retail customers within its service territory. Most retail customers located in the CAISO BAA interconnect to distribution facilities owned by a UDC or MSS under retail tariffs approved by the Local Regulatory Authority, or the California Public Utilities Commission (“CPUC”), if the utility is investor-owned. These retail tariffs govern the study costs, retail rates, and potential cost recovery for retail Load interconnections.37 However, when the MSS or UDC is not a PTO, the MSS or UDC must seek Wholesale Load Interconnection service through the Participating TO Tariff to provide transmission service to those retail customers. As an Original Participating TO, PG&E is not a wholesale transmission customer on its transmission system and is not
32 Nedrud Testimony at 10-11.33 Id.34 Id.; Virani at 4-5.35 Nedrud at 10-11.36 OSC at P 39.37 The few retail customers that seek to interconnect directly to a Participating TO’s Transmission System also obtain service through a UDC or MSS (i.e., the Eligible Customer) rather than seeking service directly from the CAISO. Such retail customers can only obtain transmission service from their UDC or MSS but may be permitted by their Local Regulatory Authority to choose another load-serving entity (“LSE”) to provide them “generation service” (i.e., energy and capacity).
PDF page 8
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 8
required to seek Wholesale Load Interconnection service to serve retail customers connecting to its Distribution System.38
Participating TOs recover their just and reasonable regional transmission costs through Regional Transmission Revenue Requirements (“RTRRs”) approved by the Commission. Non- Load Serving Entity (“LSE”) Participating TOs bear different obligations within the CAISO framework; they generally joined the CAISO after its formation by constructing transmission facilities selected through the competitive solicitation process the Commission established in Order No. 1000. Order No. 1000 directed transmission providers to remove federal rights of first refusal for facilities selected in a regional transmission plan for purposes of cost allocation and to adopt qualification criteria and protocols for evaluating competing, non-incumbent proposals.39 Such entities do not have Participating TO Service Territories and do not have an obligation to serve retail Load.40 Because Non-LSE Participating TOs do not sell retail services, Participating TOs with Participating TO Service Territories41 will bear primary responsibility for processing Large Load applications from TCLLs, conducting Wholesale Load Interconnection studies, coordinating with Affected Systems with regard to changes in Load, and managing the cost responsibility and cost recovery.
D. The OSC Preliminarily Found the CAISO and TO Tariffs to Be Unjust
and Unreasonable as They Pertain to Eligible Customers Serving
Large Loads.
In the OSC, the Commission preliminarily found that the CAISO’s Tariff and/or the TO Tariffs appear to be unjust, unreasonable, or unduly discriminatory or preferential on the five bases summarized above. The Commission directed its findings to “CAISO’s Tariff and/or the TO Tariffs” and expected the CAISO and the Participating TOs to “coordinate with each other, as appropriate, to develop responses to this order.”42 Consistent with that direction, the CAISO
38 See Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (clarifying that "retail customers taking unbundled service pursuant to a state requirement (i.e., direct retail service) are eligible for such service only from those transmission providers that the state orders to provide service.").39 Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051, at PP 6, 9, 13, 558, 690 (2011), order on reh'g, Order No. 1000-A, 139 FERC ¶ 61,132, order on reh'g & clarification, Order No. 1000-B, 141 FERC ¶ 61,044 (2012), aff'd sub nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014).40 In collecting their RTRRs from the CAISO, there is no netting of the TRR entitlement and payment for transmission service.41 A Participating TO Service Territory is “[t]he area in which an IOU, a Local Public Owned Electric Utility, or federal power marketing authority that has turned over its transmission facilities and/or Entitlements to CAISO Operational Control is obligated to provide electric service to Load. A Participating TO Service Territory may be comprised of the Service Areas of more than one Local Publicly Owned Electric Utility, if they are operating under an agreement with the CAISO for aggregation of their MSS and their MSS Operator is designated as the Participating TO.” Appendix A to CAISO Tariff (defining Participating TO Service Territory).42 OSC at P 37.
PDF page 9
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 9
and the Participating TOs have divided their responses along the lines that govern their respective roles. The CAISO is addressing the matters that implicate the CAISO Tariff and the functions for which it is responsible—market access, the generator interconnection process, and the CAISO’s responsibility “for access to and the provision of transmission service, including transmission and ancillary services, to all Eligible Customers, and the reliability of that transmission service.”43 PG&E and the other Participating TOs are addressing the matters that implicate their TO Tariffs—the application process, study procedures, related requirements for evaluating and effectuating the TCLL’s request to interconnect Large Loads, and the provision of cost responsibility for a TCLL providing transmission service on behalf of a Large Load End User. PG&E submits the proposed TO Tariff revisions described below pursuant to its rights under section 205 of the FPA, as the Commission encouraged.44 As explained below, those changes are just and reasonable and address the issues in the OSC.
III. PG&E SUPPORTS THE CAISO’S PROPOSED DEFINITION OF LARGE LOAD
AS BEING JUST AND REASONABLE.
A. The OSC Requires a Definition of Large Load Sufficient to Capture
the Loads That Present the Unique Challenges to the Transmission
System Identified in the OSC.
The OSC preliminarily found that the CAISO Tariff and/or the TO Tariffs appear to be unjust and unreasonable because they lack “a definition of large load, as a new category of load.”45 As the Commission explained, integrating large loads poses specific challenges because, although large loads are retail customers, they can impact reliability on the transmission system in ways comparable to large wholesale generators.46 The OSC therefore directs that an appropriate definition, including load size, be adopted. The OSC also notes that the definition should be based on the characteristics of CAISO’s transmission system.47
Importantly, the OSC did not mandate a particular definition. Rather, the Commission identified, based on the record in the Large Load Advanced Notice of Proposed Rulemaking proceeding, a definition that it preliminarily found would be reasonable:
a new commercial or industrial customer, located at a single site
behind one or more points of interconnection, that has a peak load
of 50 MW or greater, interconnects to the transmission system at a
43 Id. at P 39.44 16 U.S.C. § 824d; OSC at P 34.45 OSC at P 57; see also id. at P 56 (identifying the absence of "a definition of large load sufficient to capture loads that present the unique challenges described herein").46 Id. at P 57.47 Id.
PDF page 10
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 10
voltage level of greater than 69 kV, and is not part of a co-location
arrangement.48
The Commission directed the CAISO and the Participating TOs either to explain whether their tariffs remain just and reasonable without such a definition or to propose tariff revisions establishing their own definition of large load.49
B. PG&E Supports and Adopts CAISO’s Proposed Definition of Large
Load Because it Meets the Requirements of the OSC While
Maintaining the Unique Aspects of the CAISO Transmission System.
In response to the OSC, PG&E proposes to amend its TO Tariff to adopt the CAISO’s proposed definition of Large Load. CAISO proposes to define Large Load as “an End User located at a single site or behind one or more point(s) of interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater.”50 This definition satisfies the OSC’s requirements. It adopts the 50 MW peak-load threshold and includes Large Loads that are interconnecting behind the CAISO Controlled Grid and that have a Point of Withdrawal on the CAISO Controlled Grid for taking transmission service.51
The CAISO’s proposed definition appropriately captures the transmission-service relationship at issue in the OSC, while avoiding an artificial requirement that the end user connect directly to the grid.52 The vast majority of Large Loads in the CAISO do not connect directly to the CAISO-Controlled Grid. Rather, Large Loads typically connect to the Distribution Systems of their TCLL. However, those Large Loads have an impact on the transmission system when the TCLL seeks interconnection and transmission service to serve the Large Load End User. The proposed definition encompasses the Large Load that the OSC intended to reach and therefore appropriately addresses the Commission’s concerns. The
48 OSC at P 57.49 Id.50 CAISO, Proposed Appendix A (definition of "Large Load").51 OSC at P 57. PG&E proposes accommodating changes in its TO Tariff to add a definition of “Large Load End User” to define a specific Large Load as a retail transmission customer that purchases energy behind one or more points of interconnection to the ISO Controlled Grid or to the Distribution System. For Large Load End Users with multiple “Point(s) of Withdrawal,” the definition is clear that for a Large Load End User the Point of Withdrawal is “where a non-transmission facility that is used to withdraw Energy from the ISO Controlled Grid to serve a Large Load End User connects to the ISO Controlled Grid.”52 OSC at P 57.
PDF page 11
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 11
CAISO’s proposed definition is also consistent with the definition of large load proposed in the OSC53 and definitions adopted by other regions that have been approved by the Commission.54 For these reasons, PG&E concludes that the CAISO’s proposed definition is just and reasonable and should be used consistently in the CAISO Tariff and the TO Tariffs. Thus, PG&E proposes to include the CAISO proposed definition for Large Load in its TO Tariff.
IV. PG&E PROPOSES JUST AND REASONABLE CHANGES TO ITS TARIFF TO
IMPLEMENT A NEW APPLICATION AND STUDY PROCESS FOR TCLLS
INTERCONNECTING LARGE LOAD END USERS TO THE PG&E
TRANSMISSION SYSTEM.
As discussed in Section II, the CAISO does not offer Order No. 888 network or point-to- point transmission service, does not accept advance reservations of transmission capacity, and has no formal application process for transmission service.55 Identifying the necessary transmission facilities needed to accommodate new Loads interconnecting to the transmission system through UDCs and MSSs is conducted through either the TO Tariff or the CAISO TPP Process. The CAISO conducts the TPP pursuant to Section 24 of the CAISO Tariff to identify transmission solutions needed for the CAISO system, including maintaining system reliability and reducing congestion.56 Participating TOs study interconnection requests under the TO Tariff and, where reliability network upgrades and network upgrades are implicated, either seek the CAISO’s concurrence that the project is a transmission facility that should be included in the CAISO Controlled Grid, that transmission cost recovery is appropriate, and that the project is consistent with the CAISO’s operational and planning requirements, or the need is addressed through the TPP.57
Consistent with this existing framework for addressing interconnection service requests, PG&E proposes to address the OSC’s directives concerning the provision of transmission service to Eligible Customers on behalf of Large Loads (referred to by PG&E as TCLL’s) through its
53 OSC at P 57.
54 See e.g., PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, at PP 16, 27-32 (2026) (approving PJM’s definition of large load as an end-use customer “…behind one or more points of interconnection….”). See also, NERC, Characteristics and Risks of Emerging Large Loads (July 2025), https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics-and- risks-of-emerging-large-loads.pdf (NERC Characteristics and Risks of Large Loads).55 OSC at P 19; see Cal. Indep. Sys. Operator Corp., 87 FERC ¶ 61,143 (1999) (the ISO Tariff “differs from the pro forma tariff in that it does not delineate transmission services into firm and nonfirm categories,” and the Access Charge provides “general access to the ISO grid, but without any commitment as to what specific transactions … will be accommodated”).56 CAISO Tariff § 24.1.57 Nedrud Testimony at 10-11, 32; OSC at PP 23, 25, 39; see Pac. Gas & Elec. Co., 81 FERC ¶ 61,122 (1997) (addressing the ISO’s “transmission expansion and planning process”).
PDF page 12
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 12
TO Tariff interconnection process, coordinated with the CAISO’s TPP and concurrence processes, as described below.
A. PG&E Proposes a Just and Reasonable Process for a TCLL to Apply
for Large Load Interconnection Service That Meets the Requirements
of the OSC.
The OSC found that PG&E’s TO Tariff may be unjust and unreasonable because it lacks “sufficiently clear and consistent provisions establishing the application process . . . that will be used when CAISO and/or the [PTO] evaluate the provision of transmission service to Eligible Customers on behalf of Large Loads.”58 Specifically, the OSC identifies three elements the TO Tariff appears to lack: (1) an application process that accepts Eligible Customers’ applications for transmission service on behalf of large loads on a rolling basis; (2) a non-refundable application fee and sufficient readiness requirements that escalate at distinct phases of the study process to deter duplicative or speculative requests for transmission service, such as meaningful milestones and/or financial commitments; and (3) information and data requirements that Eligible Customers must submit to the CAISO and/or the Participating TOs regarding the characteristics of the large load, including disclosure to the CAISO of any substantially similar pending transmission service requests on behalf of the same Large Load End User.59 PG&E proposes to address this directive through a structured application process in a new Section 10A.2 of its TO Tariff under which a TCLL applies for interconnection service to serve a Large Load End User.60 PG&E’s proposed Section 10A.2 is modeled on the existing Section 10 wholesale-load process but with specific attributes targeted at addressing the deficiencies in the OSC, including readiness, data, and coordination requirements needed for TCLL Interconnection Applications.61 Under this process, PG&E intends to review TCLL Interconnection Applications for completion on a rolling basis, with the request then being studied under a Serial Study Process (§ 10A.4) or a Cluster Study Process (§ 10A.5) after an electrical-independence determination.62
Proposed Section 10A.2.1 requires a TCLL requesting interconnection service to submit a TCLL Interconnection Application electronically to PG&E in the manner and format prescribed through PG&E’s Open Access Same-Time Information System (“OASIS”) and provide a copy of the application to the CAISO. Proposed Section 10A.2.1 also requires that a TCLL Interconnection Application include information that describes the characteristics of the
58 OSC at P 58.59 Id. .60 To avoid any appearance of discrimination, PG&E will treat itself as a TCLL when the “Large Load End User” is in its service area. PG&E provides retail transmission service in its service area regardless of the identity of the LSE or Scheduling Coordinator for the Large Load End User.61 Virani Testimony at 10-11.62 An exception being that TCLL Interconnections associated with a Co-Located Large Load End User will always be studied under the Cluster Study Process. Id. at 18, 19.
PDF page 13
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 13
Large Load End User, including: (i) the Point of Withdrawal; (ii) a proposed Large Load End User fifteen-year load ramp schedule identifying anticipated Load additions over time and its maximum Load; (iii) a single-line electrical diagram; (iv) the electrical location of the source of the power (if known) to be transmitted pursuant to the TCLL’s request for TCLL Interconnection; and (v) a completed PG&E Large Load Technical Data Request Workbook in the form provided on PG&E’s public website.63 The TCLL Interconnection Application also requires information demonstrating that the request is not speculative and is capable of moving forward, such as: (i) a site plan; and (ii) an attestation from the TCLL that the Large Load End User has Site Control. The TCLL Interconnection Application also requires the TCLL to disclose TCLL Interconnection requests in the TCLL’s footprint that are for the same Large Load End User or any of its affiliate(s). In addition, if the TCLL Interconnection Application requests Interim Standard Interconnection Service and/or FILLI Interconnection Service, the TCLL must so indicate and, if FILLI Interconnection Service is requested, the FILLI Interconnection Service addendum to the TCLL Interconnection Application must be completed. Finally, the TCLL Interconnection Application requires that the TCLL provide information concerning all relevant co-located generating facilities if the Large Load End User will be a Co- Located Large Load End User. Thus, consistent with the OSC directives, PG&E proposes an application process that requires the TCLL to submit information necessary for PG&E and the CAISO to understand the characteristics of the Large Load End User and to demonstrate that the application is not speculative through a site plan and attestations of clear Site Control.64 Proposed Section 10A.2.2 establishes a nonrefundable application fee of $25,000 to be submitted by the TCLL with its TCLL Interconnection Application. The fee is designed to cover PG&E’s costs to review the application for completeness.65 It also will assist in ensuring that applications are not speculative. As outlined in the OSC, the nonrefundable application fee when combined with the study deposit requirements proposed below will help deter speculative requests.66
Proposed Section 10A.2.3 sets forth the study deposit requirements for a TCLL submitting a TCLL Interconnection Application. The study deposit requirement includes a $500,000 cash deposit and financial security in the amount of $1,000 per MW of requested maximum load.67 The deposit and security will cover the Participating TOs’ actual costs incurred to perform the Electrical Independence Test and specific required studies,68 including any analysis for FILLI Interconnection Service and/or Interim Standard Interconnection Service.
63 See Virani Testimony at 20.64 OSC at P 58.65 Virani Testimony at 17-18.66 OSC at P 58.67 Virani Testimony at 17-18.68 Id. As detailed below, a second deposit is required for Electrically Dependent Large Load to proceed through the Phase 2 Cluster Study.
PDF page 14
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 14
Proposed Section 10A.2.4 establishes a process for reviewing and processing TCLL Interconnection Applications. Within ten (10) Business Days of receipt of a TCLL Interconnection Application, PG&E shall determine whether the application is complete. Thus, consistent with the OSC requirements, PG&E will process the TCLL Interconnection Applications for completeness on a rolling 10-day basis.69 The proposed provisions also require PG&E to treat all information provided in the TCLL Interconnection Application as confidential except to the extent that disclosure of this information is required by the TO Tariff, the CAISO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, for Affected Systems purposes pursuant to other Interconnection Agreements, or pursuant to RTO or ISO transmission information sharing agreements.
Within fifteen (15) Business Days after the TCLL Interconnection Application is deemed complete, PG&E shall perform the Electrical Independence Test pursuant to proposed Section 10A.3.1.70 The Electrical Independence Test determines whether the Large Load End User being interconnected by the TCLL qualifies as an Electrically Independent Large Load or an Electrically Dependent Large Load.71 The Electrical Independence Test will include an incremental power flow test and aggregate power flow tests.72 These tests will analyze whether a TCLL Interconnection Application materially affects, or does not affect, other projects, and the results of that analysis will determine how the TCLL Interconnection Application is studied.73 Within five (5) Business Days of completion of the Electrical Independence Test, PG&E will hold a scoping meeting for Electrically Independent Large Load to address the preliminary interconnection scope, discuss the Point of Withdrawal, present preliminary planning assumptions and known system limitations, and available system capacity.74
Within fifteen (15) Business Days after the meeting, the TCLL must elect to proceed under the applicable Serial Study Process or withdraw its TCLL Interconnection Application. If withdrawn, the Participating TO shall calculate its costs spent on the application and return the unspent portion of the $500,000 study deposit and financial security and release any remaining portion of the financial security. Electrically Dependent Large Load proceeds under the Cluster Study Process in proposed section 10A.5 detailed below.
69 OSC at P 58. 70 Nedrud Testimony at 12.71 Id. at 13-14.72 Id. See also CAISO Tariff, Proposed § 25.7.73 Nedrud Testimony at 13-14; TO Tariff, Proposed § 10A.3.74 Nedrud Testimony at 14-15.
PDF page 15
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 15
B. PG&E Proposes a Just and Reasonable Study Process for Evaluating
the Provision of Transmission Service to TCLLs on Behalf of Large
Loads That Meets the Requirements of the OSC.
The OSC found that PG&E’s TO Tariff may be unjust and unreasonable because it lacks “sufficiently clear and consistent provisions establishing a study process for evaluating the provision of transmission service to Eligible Customers on behalf of large loads that considers the unique characteristics and impacts of large loads on the transmission system.”75 Specifically, the OSC requires PG&E to establish a study process that evaluates the transmission system’s ability to withstand the risks observed from analyzed large load behavior, together with any other supplemental studies necessary to evaluate the impact of providing such transmission service.76 The study-process provisions must also recognize the unique operational characteristics of large loads that are willing and able to limit their energy withdrawals under certain conditions that may lessen or avoid the need for certain network upgrades.77 The OSC indicates that it appears reasonable for such study processes — culminating in a report to the Eligible Customer with the study results, including any Direct Assignment Facilities and network upgrades necessary to accommodate the request and a non-binding good-faith estimate of the cost and time to construct such facilities — to take no more than 60-90 calendar days to complete.78 Finally, the OSC requires PG&E to evaluate alternative transmission technologies as potential solutions to accommodate an Eligible Customer’s request for transmission service on behalf of a large load.79 To address the issues identified in the OSC, PG&E proposes to amend its TO Tariff to incorporate a process to study TCLL requests in Section 10A, which accommodates two distinct study processes: a Serial Study Process in Section 10A.4 to govern Electrically Independent Large Loads and a Cluster Study Process in Section 10A.5 to govern Electrically Dependent Large Loads.
PG&E proposes two separate study processes for TCLLs based on the type of Load being studied to ensure that each Large Load End User is properly studied based on its technical characteristics and potential impact on the transmission system. Based on its experience studying Large Load requests to interconnect to date, Electrically Dependent Large Loads and Electrically Independent Large Loads have different impacts on the transmission system and thus must be studied differently.80 An Electrically Independent Large Load’s interconnection impacts are not materially affected by other projects.81 As a result, an Electrically Independent Large Loads can be studied on a rolling, serial basis without assuming the status, timing, or
75 OSC at P 59.76 Id.77 Id. at P 59.78 Id. at P 62.79 Id.80 Nedrud Testimony at 13-14.81 Id.
PDF page 16
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 16
configuration of other queued projects and can be studied within the timeframe contemplated by the OSC.82
In contrast, an Electrically Dependent Large Load’s interconnection impacts are materially affected by other projects or arise when multiple projects collectively affect the same grid facilities.83 Studying such requests sequentially would require repeated restudies as applicants withdraw or change their configurations and would delay later applicants.84 Instead, in PG&E’s experience, studying Electrically Dependent Large Loads together produces more accurate results, identifies interactions among projects, and avoids serial restudies.85 Within the last few years, PG&E has performed three (3) cluster studies, involving ninety-three (93) separate applications, for Large Load End Users greater than 20 MW seeking CPUC- jurisdictional interconnections and has found that the collective approach effectively and efficiently identifies needs and plans solutions.86 In light of the differences in the types of Large Load and PG&E’s experiences, PG&E proposes a Serial Study Process for Electrically Independent Large Loads and a Cluster Study Process for Electrically Dependent Large Loads.
1. PG&E Proposes a Serial Study Process for Electrically Independent
Large Loads that Mirrors the Serial Process for Other Wholesale
Interconnections in Section 10 Of the TO Tariff
Proposed Section 10A.4 establishes a serial study process for Electrically Independent Large Loads consistent with the existing process used for Wholesale Load Interconnections in Section 10. The proposed serial process starts with a System Impact Study. Under Section 10A.4.2, within sixty (60) Business Days of receipt of an executed System Impact Study Agreement, PG&E will use due diligence to complete the required System Impact Study. The System Impact Study will identify: (i) whether any Direct Assignment Facilities and TCLL Interconnection Network Upgrades are required; and (ii) any adverse impact on existing Encumbrances. In addition, PG&E will consider alternative transmission technologies, and if traditional network upgrades are selected instead of alternative transmission technologies, PG&E will provide a demonstration of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline for accommodating the TCLL Interconnection. The System Impact Study will also provide an estimated cost for the Direct Assignment Facilities and TCLL Interconnection Network Upgrades.87 To the extent reasonably practicable, PG&E shall rely on existing transmission planning studies.
82 Nedrud Testimony at 14.83 Nedrud Testimony at 19-20.84 Id. at 19, 26-27.85 Id.86 Id. at 26.87 Each of these facility types is discussed in more detail below.
PDF page 17
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 17
Proposed Sections 10A.4.4 and 10A.4.5 then set the conditions for moving from the completed System Impact Study to a Facilities Study, if a Facilities Study is elected or required. The TCLL can also choose to move forward with the requisite agreements rather than have a Facilities Study that will provide more detail as to required upgrades and their costs, with the exception that a TCLL seeking Interim Interconnection Service88 is required to undergo a Facilities Study. When the customer elects Interim Interconnection Service, the more detailed Facilities Study is required to assess those more dynamic and flexible interconnections. If no Facilities Study is requested or required, the TCLL proceeds to proposed Section 10A.4.8, and the Participating TO will tender the Facilities Study Agreement within fifteen (15) Business Days. The Facilities Study Agreement will, among other things, define the scope, terms, and estimated completion time of the Facilities Study. The TCLL shall execute the Facilities Study Agreement within fifteen (15) Business Days, or ask that it be filed unexecuted at FERC, or the application shall be deemed withdrawn. If an unexecuted filing is requested, the Serial Study Process will be paused until the Facilities Study Agreement is made effective by FERC.
Proposed Section 10A.4.6 describes the Facilities Study procedures and provides that within sixty (60) Business Days of receipt of an executed Facilities Study Agreement, PG&E will use due diligence to complete the Facilities Study. The Facilities Study will provide a revised cost estimate of Direct Assignment Facilities and TCLL Interconnection Network Upgrades, as well as identify and provide a cost estimate of any TCLL FILLI Facilities, if applicable. Proposed Section 10A.4.7 sets forth the timeline for tendering the TCLL Agreement and related agreements. If the TCLL seeks to move forward, Section 10A.4.8 would be the next step, which provides sixty (60) Business Days to negotiate and execute the various required interconnection agreements: the TCLL Agreement, the Facilities Agreement, the Cost Assurance Agreement, and if applicable, the Interim Service Agreement.
The deadlines collectively reflect a Serial Study Process of approximately 80 to 95 Business Days, depending on how long the applicant takes to execute the System Impact Study Agreement, from the application being complete to having System Impact Study results, consistent with the OSC’s 90-day target for Electrically Independent Large Loads.89 It also reflects that a decision to go through the Facilities Study process is optional (with the exception of a TCLL seeking Interim Standard Interconnection Service) and that negotiating and drafting the TCLL Agreement and associated agreements may take additional time.
PG&E’s proposed study procedure will also account for the dynamic behavior of Large Load End Users at the Point of Withdrawal on the CAISO system, consistent with the OSC directives.90 In addition, in accordance with the OSC, PG&E will assess alternative transmission technologies and where traditional network upgrades are selected, PG&E will demonstrate why
88 The use of the term Interim Interconnection Service in this document refers to both Interim Standard Interconnection Service and FILLI Interconnection Service.89 Nedrud Testimony at 27; OSC at P 38.90 OSC at P 38.
PDF page 18
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 18
alternative transmission technologies were not selected.91 Finally, if Interim Standard Interconnection Service or FILLI Interconnection Service is requested, the Facilities Study will address such request.
2. PG&E Proposes a Cluster Study Process for Electrically Dependent
Large Loads
Section 10A.5 proposes a Cluster Study Process for Electrically Dependent Large Loads, under which PG&E will batch the Electrically Dependent Large Load requests submitted by TCLLs into a single Cluster Study conducted annually.92 PG&E will accept applications on a rolling basis throughout the year, but Electrically Dependent Large Loads will be studied together as a cluster annually.93 All applications of Electrically Dependent Large Loads and Co- Located Large Load End Users required to participate in the Cluster Study Process with completed applications by the last day of February each year will be included in that year’s Cluster Study Process, which will begin April 1st of each year. To the extent these proposed tariff modifications are approved by the requested effective date and completed applications are received by the end of February 2027, there will be a Cluster Study Process for Large Load End Users in 2027. Otherwise, the first Cluster Study Process for Large Load End Users under this proposed tariff will be in 2028.
The Cluster Study will have two phases. In Phase 1 (utilizing the initial study deposit), PG&E will evaluate all projects in the cluster using a steady state power flow and short circuit analysis.94 Phase 1 will produce a list of the Direct Assignment Facilities, TCLL Interconnection Network Upgrades, and TCLL FILLI Facilities, if applicable, preliminarily identified as required, along with their estimated costs and each applicant’s share of cost responsibility.95 PG&E will use reasonable efforts to complete this study within one hundred twenty (120) Business Days after the annual commencement of the Phase 1 Study. Within twenty (20) Business Days after providing the final Phase 1 study report, PG&E will hold a results meeting with each TCLL, the CAISO, and any Affected System Operators, if applicable, to review the results, after which the TCLL may withdraw its application or proceed to Phase 2.96 If the TCLL decides to proceed to Phase 2, it must enter a second Cluster Study Process Agreement, wherein it commits to provide an additional refundable security equal to 15 percent of the Phase 1 Study’s estimated costs of the Direct Assignment Facilities and TCLL Interconnection Network Upgrades.97 The security will be used to pay for actual costs incurred
91 Id. at PP 60-61; Nedrud Testimony at 16, 23-24.92 Nedrud Testimony at 20.93 Id.94 Id. at 21.95 Id. 96 TO Tariff, Proposed § 10A.5.5.2.97 Nedrud Testimony at 22-23; TO Tariff, Proposed § 10A.5.3.
PDF page 19
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 19
by PG&E to perform and administer the Phase 2 Study. In addition, the security may be used by PG&E for engineering, design, and procurement, together with applicable labor, materials, contractor charges, and overhead, including applicable ITCC, for the Direct Assignment Facilities and TCLL Interconnection Network Upgrades identified in the Phase 1 Study. This serves two purposes: (1) it further prevents speculative large load interconnection requests and provides ever-increasing financial commitments from large load in accordance with the OSC, and (2) it allows PG&E to begin capital procurement for long lead time materials and preliminary engineering work on required upgrades. The deposit will be refundable,98 less the actual costs incurred, including for capital procurement and engineering, and can be made in the form of cash or security as set forth in proposed Section 10A.5.5.3 of the Tariff. The Phase 2 Study will (i) update, as necessary, analyses performed in the Phase 1 Study to account for the withdrawal of requests after the Phase 1 Study process, (ii) identify Direct Assignment Facilities, TCLL Interconnection Network Upgrades, and TCLL FILLI Facilities,
(iii) assign cost responsibility for Direct Assignment Facilities, TCLL Interconnection Network Upgrades, and TCLL FILLI Facilities needed for the TCLL’s interconnection request, (iv) allocate estimated cost responsibility for financing the identified TCLL Interconnection Network Upgrades, (v) identify for each TCLL Interconnection request a final Point of Withdrawal, and
(vi) preliminarily identify any TCLL Reliability Network Upgrades. Phase 2 also includes a transient stability study and as needed, a voltage stability analysis, which are more detailed analyses that are most useful once the cluster has been narrowed to the requests moving forward under Phase 2.99 Within twenty (20) Business Days of receipt of the final Cluster Study report, the TCLL, Participating TO, the CAISO, and any Affected System Operators, if applicable, and the Interconnection Customer, shall hold a results meeting to discuss the results. Within twenty- five (25) Business Days of receipt of the completed Phase 2 Study, the TCLL must request the TCLL Agreement, the Facilities Agreement, the Cost Assurance Agreement, and if applicable, the Interim Service Agreement or withdraw its application. The parties have thirty (30) Business Days to negotiate and execute the various required interconnection agreements. Given the interrelated nature of these projects and how they can affect each other’s necessary facilities and upgrades, they need to be studied together. As indicated above, studying several interrelated projects together takes additional time. The Participating TO will use reasonable efforts to complete each phase of the Cluster Study within one hundred twenty (120) Business Days, and the entire process, including the meetings to review results, is expected to take a little over a year.100 Although the Cluster Study process will take longer than a single serial study, it is more efficient and accurate than studying the same interdependent requests one at a time (within 90 days each) because they would have to be continually restudied for withdrawals and rescoping from other dependent interconnections. The proposed cluster
98 PG&E proposes to provide refunds with interest at the rate on commercial paper (A2/P2 nonfinancial) as found in “The Fed-Commercial Paper Rates and Outstanding Summary,” or its successor publication. As detailed below, PG&E is not likely able to earn interest at the current FERC interest rate, and instead, proposes to provide interest on refunds at the more attainable commercial paper rate. 99 Nedrud Testimony at 23-24.100 Nedrud Testimony at 26-28.
PDF page 20
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 20
approach thus aligns with the OSC’s 60-90 day timeline where that timeline is achievable, for the Electrically Independent Large Loads, while adopting the most expeditious and practical process for Electrically Dependent Large Loads.101
3. PG&E’s Load Interconnection Studies are Coordinated with the
CAISO’s Concurrence and TPP Processes.
Generally, the Participating TOs are responsible for studying load interconnections, and the CAISO is responsible for studying generation interconnections. The results of PG&E’s load interconnection studies, however, feed directly into the CAISO’s planning processes. PG&E submits its load interconnection study results to the CAISO, which reviews the identified network upgrades in its concurrence process. In addition, the Load identified in PG&E’s interconnection studies, together with other load growth, is considered in the TPP and can trigger TCLL Reliability Network Upgrades.102
V. PG&E PROPOSES A SET OF PRO FORMA AGREEMENTS TO MEET THE
VARIOUS REQUIREMENTS OF THE OSC
A. PG&E Proposes a Just and Reasonable Set of Agreements to Address
the Various Requirements of the OSC.
To address the general operational requirements in the OSC, PG&E proposes to include in its TO Tariff, as Appendix XI, a pro forma Agreement to Interconnect Transmission Customer for Large Load (the “TCLL Agreement”). The pro forma TCLL Agreement also includes separate attachments that address other aspects of the OSC requirements. Those include the Facilities Agreement (Attachment A to Appendix XI), the Cost Assurance Agreement (Attachment B to Appendix XI), and the optional Interim Service Agreement (Attachment C to Appendix XI) (collectively, the “Associated Agreements”).103 Each of those agreements will be discussed in more detail below.
The TCLL and Associated Agreements will be executed after the study process is complete and after the facilities needed for Standard Interconnection Service have been identified and, optionally, the facilities needed for FILLI Service and Interim Standard Interconnection Service.104101 Id. at 27.102 Virani Testimony at 4-5; Nedrud Testimony at 10-11.103 TO Tariff, Proposed § 10A and Appendix XI, including the TCLL Agreement, TCLL Facilities Agreement, Cost Assurance Agreement, and Interim Service Agreement.104 The optional Interim Interconnection Service is discussed in more detail below in Section.V.C.5.
PDF page 21
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 21
B. PG&E Proposes to Address the Operational and General Pro Forma
Requirements of the OSC Through use of the TCLL Agreement.
The OSC preliminarily found that the CAISO Tariff and/or the TO Tariffs appear to be unjust and unreasonable because they lack pro forma provisions in a transmission service agreement, or other applicable agreement, between the CAISO and/or the Participating Transmission Owner and the transmission customer taking transmission service on behalf of a large load. Those provisions would memorialize the ongoing operational requirements that apply to such service, such as equipment requirements, data requirements, and remote disconnect capability.105 The Commission explained that, without such provisions, the CAISO may be unable to enforce those requirements against transmission customers taking transmission service on behalf of large loads.106 The Commission therefore directed the CAISO and/or the Participating TO to propose a pro forma agreement that memorializes the ongoing operational requirements in a transmission service agreement between the CAISO and/or the Participating TO and the transmission customer taking transmission service on behalf of large loads.107 Notably, the OSC did not require a single form of agreement. Instead, it expressly permitted those requirements to be memorialized in a transmission service agreement “or other applicable agreement.”108
To address these general requirements for interconnection service, PG&E proposes a new pro forma TCLL Agreement. The TCLL Agreement is a pro forma service agreement that sets out the terms and conditions PG&E will use to ensure that a TCLL meets the requirements that apply to the requested interconnection service.
Parties. The parties to the TCLL Agreement will be (i) PG&E, acting as a Participating TO; and (ii) the TCLL. While the OSC suggests that the pro forma agreement can be between the CAISO or the Participating TO and the Eligible Customer, PG&E is the appropriate counterparty because it provides wholesale interconnection service to the TCLL. Term and Termination. PG&E proposes that the TCLL Agreement become effective on the later of the Commission’s acceptance of the agreement and the related Facilities Agreement, Cost Assurance Agreement, and Interim Service Agreement, if any, and remain in effect until terminated by mutual agreement, for default, or on sixty (60) days’ notice from the TCLL, subject to any required FERC acceptance of a notice of cancellation. Termination may result in the payment of an exit fee under the Cost Assurance Agreement.
Interconnection and Facilities. The TCLL Agreement reflects the commitment of the TCLL and Participating TO to interconnect and the terms and conditions relating to actual physical interconnection will reside in the Facilities Agreement. Likewise, if Interim Standard
105 OSC at P 64.106 Id.107 Id.108 Id.
PDF page 22
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 22
Interconnection Service and/or FILLI Interconnection Service is to be provided, the TCLL Agreement indicates that the Interim Service Agreement will include the relevant terms and conditions.
Risk Allocation and General Terms. The agreement also includes several terms and conditions found in most pro forma agreements. Those terms include: (1) Indemnity: a mutual indemnity, with exceptions for the indemnified party’s gross negligence or intentional wrongdoing; (2) Damages waiver: a broad waiver of consequential, indirect, and similar damages; (3) Default: a material breach is a default, and the other party may terminate after written notice and a cure period of at least 60 days; (4) Confidentiality: confidentiality obligations last for the term plus three years, with carve-outs for disclosures to FERC and state regulators; (5) Assignment: assignment requires consent, which cannot be unreasonably withheld, with certain exceptions; (6) Disputes and governing law: disputes are resolved under Section 13 of the TO Tariff, and California law governs; (7) Order of priority: the TO Tariff prevails over the TCLL agreement, and the TCLL Agreement prevails over the CAISO Tariff; and (8) Unilateral FERC filings: PG&E may make unilateral filings with FERC under section 205 of the Federal Power Act, and the TCLL may do so under section 206.
C. PG&E Proposes to Address the Cost Assurance Requirements of the
OSC With Pro Forma Cost Recovery Agreements – the Facilities
Agreement and the TCLL Cost Assurance Agreement.
The OSC preliminarily finds that the TO Tariffs appear to be unjust and unreasonable because they lack adequate mechanisms to mitigate the risk of cost shifting among transmission customers.109 The OSC identifies three elements that a just and reasonable cost recovery framework for large load service should include: (1) a cost recovery agreement requiring a minimum contribution toward the transmission owner’s transmission revenue requirement, based on the level of transmission service requested on behalf of the large load; (2) credit support or other financial security sufficient to secure the Eligible Customer’s payment obligations; and
(3) appropriate crediting of any such payments toward the transmission owner’s transmission revenue requirement. PG&E’s proposal satisfies each of these requirements and, in several respects, provides additional protection against cost shifting by matching the cost recovery mechanism to the type of facility needed to serve the Large Load End User.
As explained below, PG&E proposes to address cost responsibility based on the type of facilities required to provide Standard Interconnection Service to a TCLL and to ensure recovery of those costs and to prevent cost shifting through the Facilities Agreement and the TCLL Cost Assurance Agreement. Section V.C.1 describes this facility-based approach, under which the cost recovery mechanism and cost assurance requirements of Direct Assignment Facilities, TCLL FILLI Facilities, TCLL Interconnection Network Upgrades, and TCLL Reliability Network Upgrades are set forth for each type of facility. Section V.C.2 describes how the Facilities Agreement memorializes the determination, funding, and recovery of the costs for Direct Assignment, TCLL FILLI Facilities and TCLL Interconnection Network Upgrades.
109 OSC at P 76.
PDF page 23
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 23
Finally, Section V.C.3 describes the Cost Assurance Agreement, which addresses cost recovery for TCLL Reliability Network Upgrades by establishing a Minimum Annual Revenue Obligation tied to the requested interconnection capacity, an annual reconciliation process, and a financial security requirement securing that obligation, consistent with the cost recovery agreement contemplated by the OSC.110
1. PG&E Proposes to Allocate and Secure Costs Based on the Relevant
Facilities to Ensure that TCLLs and Large Load End Users Pay Their
Fair Share of the Costs of Facilities Necessary to Interconnect Large
Load End Users to the Transmission System.
The TO Tariff and related TCLL Agreement identify four different types of facilities: (1) Direct Assignment Facilities; (2) TCLL FILLI Facilities; (3) TCLL Interconnection Network Upgrades; and (4) TCLL Reliability Network Upgrades.111 Costs will be recovered and cost assurance requirements established based on the unique nature of each facility type as discussed in more detail below.
Importantly, PG&E’s cost recovery proposal must be considered on a holistic basis. The proposal is not a collection of independent cost allocation rules. Rather, it is intended to be an integrated framework designed to ensure that TCLLs and Large Load End Users bear the costs of the facilities needed to serve them, which often involve this array of facilities, while protecting PG&E’s other transmission customers from cost shifts. A summary of the cost responsibility for each type of facility is provided below with a detailed explanation in the following sections that explains the mechanics of how each cost recovery mechanism will work in the relevant sections of each of the pro forma agreements.
Direct Assignment Facilities and TCLL FILLI Facilities. Direct Assignment
Facilities are defined as facilities owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting interconnection. TCLL FILLI Facilities are defined as facilities identified through the Section 10A study process that are required to provide service under the Interim Service Agreement that will be owned by the Participating TO or TCLL. Both Direct Assignment and TCLL FILLI Facilities are developed for the sole use and benefit of the TCLL requesting service under Section 10A of the TO Tariff.112 Accordingly, PG&E proposes to directly assign costs for Direct Assignment Facilities and TCLL FILLI
110 OSC at P 125; TO Tariff, Proposed § 10A and Appendix XI, Attachment A (Facilities Agreement) and Attachment B (Cost Assurance Agreement).111 Under the proposed Electric Rule 30, tariff provisions will apply to our types of transmission facilities needing infrastructure upgrades: Type 1 (Transmission Service Facilities), Type 2 (Transmission Interconnection Upgrades), Type 3 (Transmission Interconnection Network Upgrades), and Type 4 (Transmission Network Upgrades).112 Nedrud Testimony at 20-21. See also Green Development, LLC v. FERC, 77 F.4th 997, 1006-07 (D.C. Cir. 2023) (upholding FERC’s interpretation of direct assignment facilities as facilities constructed for the sole benefit of a particular customer and explaining that direct assignment protects network users from subsidizing facilities that benefit a single user).
PDF page 24
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 24
Facilities to the TCLL. Direct assignment is consistent with the principles of cost causation because it ensures that the costs are allocated to those who caused and fully benefit from the proposed facilities.113 The direct assignment of such facilities is also consistent with the Commission’s policy for direct assignment of interconnection facilities in other contexts.114 TCLL Interconnection Network Upgrades. TCLL Interconnection Network Upgrades
are additional facilities needed to expand the transmission system from the ISO Controlled Grid to the point of interconnection of the TCLL. These facilities will be identified in the Facilities Agreement and are network upgrades caused by the interconnection of the Large Load End Users for which the TCLL seeks interconnection service.115 TCLL Interconnection Network Upgrades are subject to the CAISO’s concurrence review process for transmission planning purposes as discussed above.116 Under Attachment A, the TCLL pays the costs of the TCLL Interconnection Network Upgrades upfront before Interconnection Service begins, but the costs can be refunded as set forth in the Facilities Agreement described below.
The OSC finds that the TO Tariff may be unjust and unreasonable because it fails to prevent unjust and unreasonable costs shifts among transmission customers.117 By requiring the TCLL to fund the costs of the TCLL Interconnection Network Upgrades upfront, PG&E ensures that the TCLL and the Large Load End User for which the TCLL is taking service, pays the full cost of those upgrades before service commences and protects other transmission customers if the Large Load End User does not materialize or does not materialize as intended.
113 Green Development, 77 F.4th at 1006-07 ; Exxon Mobil Corp v. FERC, 517 F.3d 1208, 1213 (D.C. Cir. 2009) (holding that entities bear the full cost of interconnection facilities that solely benefit them); Old Dominion Elec. Co-op, Inc. v. FERC, 518 F.3d 43, 50-51 (D.C. Cir. 2008) (upholding FERC's determination that generation interconnection customers were responsible for 100% of the costs of upgrades to accommodate interconnection requests that would not have been built but for their interconnection request, and denying recovery of those costs through transmission revenue).114 The cost causation principle requires costs to be allocated to those who cause the costs to be incurred and reap the resulting benefits. See S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 87 (D.C. Cir. 2014) (explaining that rates must reflect to some degree the costs actually caused by the customer who must pay them) (citing Nat’l Ass’n of Regul. Util. Com’nrs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007)); Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368-69 (D.C. Cir. 2004) (evaluating cost causation by comparing the costs assessed against a party to the burdens imposed or benefits drawn by that party); Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 476-477 (7th Cir. 2009) (explaining that costs may not be allocated to parties receiving no benefits or benefits trivial in relation to the costs).115 TCLL Interconnection Network Upgrades generally will be consistent with Facility Type 2 and 3, as proposed in PG&E’s Electric Rule 30 Application (A.24-11-007), filed before the California Public Utilities Commission.116 Nedrud Testimony at 10-11, 32.117 OSC at P 80.
PDF page 25
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 25
However, because the facilities are network upgrades, they benefit all transmission customers118 and thus, it is consistent with Commission policy to ensure that the costs are ultimately rolled into network rates, subject to the Large Load End User paying their appropriate share through transmission rates.119 As such, PG&E proposes to make these upfront TCLL Interconnection Network Upgrade costs eligible for refunds based on realized transmission revenues, and disbursed annually at a rate equal to 75% of realized wholesale Transmission revenues until the cost is fully refunded.
This approach of upfront funding with refunds will ensure that the TCLL or Large Load End User fully pays for the costs of the facilities as they are being constructed. If the Large Load End User does not materialize, the TCLL or Large Load End User bears the costs. If the Large Load End User materializes, but is smaller in size than expected, the refund amount will be reduced, such that the TCLL or Large Load End User may never recoup its full costs or may take longer to earn a full refund.
Moreover, PG&E proposes to refund only seventy-five (75) percent of the realized wholesale transmission revenues on an annual basis in conformance with the recently passed legislation in California, SB 886 (known as the California Technology Innovation and Ratepayer Protection Act), signed into law on September 21, 2026.120 SB 886 provides that any refund made by a utility to a large load customer cannot exceed seventy-five percent of the annual net transmission revenue requirement that the utility receives from the large load customer.121 This is also consistent with several recent CPUC orders approving similar arrangements between PG&E and large load customers at the retail level. As the CPUC explains, the twenty-five percent of funds not refunded annually are intended to account for costs that are not part of the project’s direct energization such as ongoing maintenance costs and broad grid upgrades.122 TCLL Reliability Network Upgrades. TCLL Reliability Network Upgrades are
Network Upgrades planned through the CAISO TPP or similar processes and identified as necessary for the provision of Standard Interconnection Service to the TCLL and other load
118 See e.g., Exxon Mobil, F.3d at 1213 (discussing Network Upgrades as those upgrades funded upfront by customer and later refunded); Entergy Servs., Inc. v. FERC, 319 F.3d 536, 539 (D.C. Cir. 2003) (upholding FERC’s policy to provide credits for network upgrades that benefit all users on the grid).119 See also, Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 (2025). 120 S.B. 886, 2025–2026 Reg. Sess. (Cal. 2026) (California Technology Innovation and Ratepayer Protection Act)).121 Id.122 Resolution E-5439 at 17 (Jan. 15, 2026) (directing refund of 75 percent of PG&E’s net annual revenue plus ITCC adjustment); Resolution E-5420 at 18 (same) Resolution E-5420 at 18 (same); Resolution E- 5433 (same).
PDF page 26
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 26
interconnections.123 Importantly, unlike TCLL Interconnection Network Upgrades, the TCLL Reliability Network Upgrades are facilities that are identified as necessary by the CAISO to address Load growth or other reliability driven requirements on the CAISO system, while also being necessary to reliably provide transmission service to the TCLL.124
Accordingly, consistent with the OSC requirements, PG&E proposes to require a Minimum Annual Revenue Obligation backed by security requirements from the TCLL or Large Load End User to ensure that the TCLL or the Large Load End User pays their fair share of the costs of the TCLL Reliability Network Upgrades. PG&E’s approach preserves the CAISO’s integrated planning and cost-of-service framework while satisfying the OSC’s requirement for a minimum contribution and appropriate credit support.125 The OSC specifically finds that “in order to prevent unjust and unreasonable cost shifting among transmission customers it appears necessary” for the relevant parties to “enter into a cost recovery agreement that requires the [TCLL] to make a minimum contribution toward the transmission owner’s revenue requirement.”126 The Minimum Annual Revenue Obligation does exactly that by requiring the TCLL, or Large Load End User if the TCLL is PG&E, to pay its minimum revenue requirement based on requested maximum load and backed by security to prevent unjust and unreasonable cost shifting. As described in more detail below, PG&E also proposes to require an Exit Fee to cover the costs of TCLL Reliability Network Upgrades should the TCLL/Large Load End User prematurely leave.
123 TCLL Reliability Network Upgrades will generally be consistent with Facility Type 4, as used in PG&E’s Electric Rule 30 application.124 In the event a TCLL Reliability Network Upgrade is identified as being attributable to an individual Large Load End User, the TCLL/Large Load End User may be responsible for costs associated with that TCLL Reliability Network Upgrade under the framework provided for TCLL Interconnection Network Upgrades.125 OSC at PP 79–82; PG&E Large Load Comments at 12–13.126 OSC at P 80.
PDF page 27
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 27
2. The Facilities Agreement Provides a Just and Reasonable Solution for
Protecting Customers Against Cost Shifts for the Direct Assignment
Facilities, TCLL FILLI Facilities, and TCLL Interconnection
Network Upgrades.
a. The terms and conditions of the Facilities Agreement are just
and reasonable.
As summarized above, PG&E proposes to include as Attachment A to the TCLL Agreement, a Facilities Agreement to govern the costs of the Direct Assignment Facilities, TCLL FILLI Facilities, and the TCLL Interconnection Network Upgrades (collectively, the “Attachment A Facilities”). The parties to the Facilities Agreement will include PG&E, as the Participating TO, and the TCLL. If PG&E is also the TCLL, the Large Load End User will also execute the agreement.
Section 2 of the Facilities Agreement identifies required Direct Assignment Facilities, TCLL Interconnection Network Upgrades, TCLL FILLI Facilities, and TCLL Reliability Network Upgrades. It also makes clear that the TCLL Reliability Network Upgrades have only been identified on a preliminary basis and the final TCLL Reliability Network Upgrades that must be completed before Standard Interconnection Service may begin will be identified at a later date, subject to the review and agreement of the CAISO.
Section 3 requires each Large Load End User to have the facilities to provide continuous dynamic disturbance recording data and storage on the high-side of the main power transformer or common point of connection, as required by the CAISO. It also requires the facilities to allow PG&E to disconnect or isolate the Large Load End User during a contingency to maintain system reliability.
Section 4 identifies, by reference to the single-line diagram, the PG&E-owned Point of Withdrawal and the Points of Change of Ownership between the parties.
Section 5 addresses the design, engineering, and construction of the TCLL Facilities excluding the TCLL Reliability Network Upgrades and provides that certain Attachment A Facilities may be constructed by the TCLL, with the consent of the Participating TO. This section also includes the general obligations of the parties regarding the development of the Attachment A Facilities.
Section 6 provides the cost estimates to construct the Direct Assignment Facilities, TCLL Interconnection Network Upgrades, and TCLL FILLI Facilities.
Section 7 details how the Attachment A Facility costs will be allocated. Costs for all of Attachment A Facilities will be paid for initially by the TCLL/Large Load End User prior to construction. If the TCLL constructs the Direct Assignment or TCLL FILLI Facility, the agreement makes clear that the facility itself shall constitute the upfront, directly-assigned payment and requires the TCLL to transfer the facility to the Participating TO prior to energization. If the TCLL does not construct the facilities, the Facilities Agreement provides
PDF page 28
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 28
that the upfront payment responsibility will be based on the estimated costs of the facilities, subject to true up and reconciliation, and paid consistent with the payment schedule set forth in the agreement.127 Section 7.3 states that the TCLL/Large Load End User must pay PG&E for the income tax component of contributions (“ITCC”) in connection with the transactions made under the agreement. Section 7.6 sets forth how the cost of ownership charge for the Participating TO- owned Direct Assignment Facilities will be calculated. The cost of ownership charge will reimburse PG&E for the ongoing costs of owning and operating the PG&E-owned Direct Assignment Facilities.
Section 8 details how billing will be performed under the agreement. Section 9 describes the refund methodology for the TCLL Interconnection Network Upgrades. As discussed above, PG&E will refund to the TCLL/Large Load End User, a portion of the upfront payment on an annual basis, including ITCC, made by the TCLL/Large Load End User for the TCLL Interconnection Network Upgrades. Refunds shall commence once the Large Load End User commences retail service. Refunds will be paid annually and will equal 75% multiplied by the amount of MWh counted as Gross Load of the TCLL associated with withdrawals by the Large Load End User multiplied by the Regional Access Charge or by the Regional Access Charge plus the Local Access Charge, as applicable. In order to receive this refund, the TCLL/Large Load End User must inform PG&E of its Gross Load withdrawn as measured by the CAISO revenue meter. The refunds will be paid over a period of fifteen years and may not necessarily equal the full costs of the upfront payments depending on the cost of the upgrades and the amount of service taken by the TCLL/Large Load End User. Termination of this agreement prior to fifteen years from the date refunds commence will result in the end of further refunds as of the date of termination and the unrefunded amount of the upfront payment will serve as an exit fee for prematurely ending service.
As set forth in Section 9, PG&E intends to pay interest on the refunds of the upfront payments made for the TCLL Interconnection Network Upgrades. However, rather than use the traditional interest rate established by the Commission under Section 35.19a, PG&E proposes to use the interest rate on commercial paper (A2/P2 nonfinancial) as found in “The Commercial Paper Rates and Outstanding Summary,” or its successor publication.128 Once PG&E collects the upfront payment for the TCLL Interconnection Network Upgrades, the payments collected will be used to pay for the cost of constructing those upgrades. PG&E believes that because those upgrades will be network upgrades it is appropriate to provide refunds to the TCLL or Large Load End User for those facilities over time. However, requiring PG&E to pay high interest rates will unnecessarily shift costs on to other PG&E transmission customers. PG&E cannot obtain a rate equivalent to the Commission’s interest rate set out in Section 35.19a from a bank or escrow account for such deposits. Thus, even if PG&E were to place the funds collected
127 The Phase 2 Security payment discussed above (equal to 15 percent of the estimated costs of the Direct Assignment Facilities and TCLL Interconnection Network Upgrades), less the actual incurred costs to conduct the Phase 2 Study, may be utilized to satisfy this upfront cost payment responsibility in whole or in part by written agreement of the parties.128 Board of Governors of the Federal Reserve System, Commercial Paper Rates and Outstanding Summary, https://www.federalreserve.gov/releases/cp/.
PDF page 29
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 29
from the TCLL or Large Load End User in an interest-bearing account that aligns with the annual refund obligation, the interest earned is likely to be lower than the interest it would need to pay on refunds to the Large Load End User based on Section 35.19a. The costs of paying a higher interest rate on those funds would be shifted to other transmission customers. This is directly contrary to the Commission’s goals in the OSC of preventing cost shifts.129 Moreover, the Commission has accepted use of interest rates other than the rates used in Section 35.19a in similar situations.130 Accordingly, to the extent necessary, PG&E seeks a waiver of Section 35.19a to allow it to charge a rate other than the prescribed interest rate in Section 35.19a. Section 10 makes the TCLL/Large Load End User responsible, if the agreement is terminated before energization, for PG&E’s unreimbursed design, engineering, and construction costs and for its necessary and reasonable termination costs, including safety, system-integrity, and unavoidable contract cancellation costs. Both Parties must use commercially reasonable efforts to mitigate those costs. Again, this ensures that the TCLL and, in turn, the Large Load End User will pay their fair share of the costs, consistent with the requirements of the OSC. Section 11 sets forth how TCLL Reliability Network Upgrades will be funded. As noted above, the costs of these network upgrades are recovered in accordance with the CAISO Tariff provisions governing the funding of integrated transmission projects, and cost recovery is assured through the Cost Assurance Agreement. The TCLL/Large Load End User cost assurance responsibilities for these types of facilities are covered in Attachment B to the pro forma discussed below. Section 12 includes accounting and audit provisions providing the right for both parties to conduct audits under conditions set forth in the agreement.
Section 13 governs the commencement of Standard Interconnection Service. The Participating TO and TCLL shall exchange a notice in the form of Attachment B memorializing their mutual agreement that the Attachment A Facilities and the TCLL Reliability Network Upgrades have been completed and tested. If another transmission owner or transmission provider must first complete transmission facilities, the parties will also confirm that work is completed and tested. Section 14 provides the Large Load End User obligations and rights, including the requirement to finance the TCLL Facilities as specified under the Facilities Agreement.
The remaining provisions include the following standard contract terms and conditions typically found in pro forma FERC interconnection and transmission service agreements: Section 15 (Indemnification and Liability); Section 16 (Default); Section 17 (Confidential Information); Section 18 (Assignment); and Section 19 (Miscellaneous Provisions).
129 OSC at P 65.130 See e.g., BJ Energy, LLC Franklin Power, LLC Gle Trading, LLC Ocean Power, LLC & Pillar Fund, LLC, 129 FERC ¶ 61, 265 (Dec. 22, 2009) (finding PJM not required to pay interest rate under section 35.19a for funds used as financial security).
PDF page 30
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 30
b. PGE’s proposal to include the Large Load End User as a
signatory to the Facilities Agreement when PG&E is the TCLL
is just and reasonable.
PG&E proposes to include the Large Load End Users as a party to the pro forma Facilities Agreement when PG&E is the TCLL. This will be an administratively efficient mechanism to ensure that Large Load End User pays for the costs of the facilities and does not result in those costs being shifted to other PG&E customers if the Large Load End User does not materialize as anticipated. In those instances when PG&E is a TCLL, if the Large Load End User was not also a signatory to the agreement and given cost responsibility for the relevant facilities, PG&E would be required to enter into an agreement with itself to secure payments for facilities needed to provide transmission interconnection service to that Large Load End User. If that Large Load End User does not materialize, PG&E would have no means to ensure payment by that Large Load End User under the agreement. This could result in costs being shifted to other PG&E transmission customers. Accordingly, to prevent that cost shifting and to avoid needing to enter into multiple complicated agreements, PG&E proposes to require the Large Load End User to execute the Facilities Agreement when PG&E is the TCLL.
The pro forma Facilities Agreement, including the Large Load End User’s obligations under it, is within the Commission’s jurisdiction to approve. The Commission has jurisdiction over the terms and conditions of transmission service.131 The Facilities Agreement is an agreement covering cost assurance for transmission facilities needed to ensure Large Load End Users can safely and reliably connect to the transmission system. Accordingly, because it is a service agreement addressing the terms and conditions for transmission-related service, it is within the Commission’s jurisdiction to approve and the Commission has approved similar transmission security agreements that include end use customers as signatories.132 While the Commission has rejected proposals that include payment and other requirements for retail customers, those obligations were retail energy service obligations, not transmission service obligations.133 Here, PG&E seeks to ensure that other PG&E transmission customers are protected if the Large Load End User does not materialize as anticipated pursuant to the Large Load End User’s transmission service obligations.
131 16 U.S.C. § 824(b); New York v. FERC, 535 U.S. 1, 16-24 (2002) (“That text unquestionably supports FERC’s jurisdiction to order unbundling of wholesale transactions (which none of the parties before us questions), as well as to regulate the unbundled transmissions of electricity retailers.”).132 See PECO Energy Co., 195 FERC ¶ 61,074 (2026) (order accepting transmission security agreement); Commonwealth Edison Co., 194 FERC ¶ 61,109 (2026) (order accepting transmission security agreement); Dayton Power & Light Co., 195 FERC ¶ 61,059 (2026) (order accepting construction service agreement); PECO Energy Co., 193 FERC ¶ 61,148 (2025) (order accepting transmission security agreement).133 PJM Interconnection, L.L.C., 197 FERC ¶ 61,109, P 81 (2026) (finding outside the Commission’s jurisdiction provisions that require retail customers to curtail as part of a wholesale capacity market construct).
PDF page 31
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 31
Moreover, PG&E proposes to require the Large Load End User to sign when PG&E is the TCLL for a combination of legal, efficiency, and transparency reasons. A TCLL that is also the Participating TO from whom the interconnection is sought is differently situated than a “third-party TCLL.” PG&E has no legal right to seek payment for services from the retail customer of a third-party TCLL. In contrast, where the PTO and TCLL are a single legal entity, that one entity already has a legal relationship with, and transacts directly with, the Large Load End User. In addition, requiring PG&E as a Participating TO to “collect” amounts from another business unit (i.e., PG&E as the TCLL) before the bill can be sent to the Large Load End User would be administratively inefficient, and as detailed above, could result in stranded costs if the Large Load End User load does not materialize.
3. The TCLL Cost Assurance Agreement Provides a Just and
Reasonable Solution for Protecting Customers Against Cost Shifts for
TCLL Reliability Network Upgrades.
a. The terms and conditions of the Cost Assurance Agreement
are just and reasonable and protect against cost shifting.
PG&E proposes to address the OSC’s concerns regarding cost shifting for TCLL Reliability Network Upgrades through a Cost Assurance Agreement. The Cost Assurance Agreement will be a pro forma agreement included as Attachment B to the TCLL Agreement among PG&E, in its capacity as Participating TO under its TO Tariff, the TCLL, and the Large Load End User if PG&E is the TCLL. If PG&E is not the TCLL, the agreement will be among PG&E and the TCLL and the TCLL will have the option of requiring the Large Load End User to execute the agreement.
Consistent with the requirements of the OSC, the Cost Assurance Agreement establishes a Minimum Annual Revenue Obligation payable by the TCLL/Large Load End User and a Financial Security requirement equal to five (5) times the Minimum Annual Revenue Obligation to secure that obligation. The Cost Assurance Agreement also provides for an Exit Fee should the Large Load End User prematurely leave and the agreement is terminated. Calculation of Minimum Annual Revenue Obligation. Section 3 of the Cost
Assurance Agreement establishes and calculates a Minimum Annual Revenue Obligation that must be collected from the TCLL or Large Load End User. The Minimum Annual Revenue Obligation is a minimum amount of revenue that must be collected from the TCLL or Large Load End User each year to ensure that entity contributes sufficiently to the Gross Load in the CAISO BAA. If the TCLL or Large Load End User does not meet the minimum obligation, a short fall amount will be charged to the TCLL or Large Load End User as discussed below, that will be flowed through PG&E’s revenue requirement.
The Minimum Annual Revenue Obligation is based on the applicable RAC or LAC, as applicable, assessed on Gross Load. RAC/LAC is the applicable CAISO charge to the TCLL for transmission access that is assessed on the Gross Load of the Large Load End User, including any applicable components of that charge under the CAISO Tariff. Each year the Minimum Annual Revenue Obligation will be calculated using the following formula:
PDF page 32
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 32
Minimum Annual Revenue Obligation = Minimum Obligation
Capacity (MW) × [hours in the year] × 80% × 75% × Regional
Access Charge (if connected to High Voltage facilities) or
Regional Access Charge + PG&E’s Local Access Charge (if
connected to Low Voltage facilities)
The Minimum Obligation Capacity will be the expected maximum capacity during the relevant annual period. Section 3 includes a schedule that will reflect the Minimum Obligation Capacity during each year. The Minimum Obligation Capacity will increase on specified dates set out in the Cost Assurance Agreement but should reach the Requested Interconnection Capacity no later than Year 5 under the schedule. Section 3.1 defines “Requested Interconnection Capacity” as the ultimate peak demand, expressed in MW, specified by the TCLL on behalf of the Large Load End User in the application. The agreement requires the Parties to complete the minimum capacity schedule before executing the agreement.134 The Minimum Annual Revenue Obligation is intended to ensure that a TCLL or Large Load End User contributes toward revenues associated with the Gross Load in the CAISO BAA, even if load ramps more slowly than anticipated. The use of realized transmission revenues for refunds and annual reconciliation aligns the obligation with actual service and reduces the risk of cost shifting. As noted above, the seventy-five (75) percent factor allows variation in Large Load End User usage while preserving a substantial contribution toward the broader transmission system, consistent with PG&E’s CPUC-approved practice for end users.135
The formula also appropriately uses an eighty (80) percent capacity factor. Because the CAISO bills transmission service based on Energy withdrawals, a capacity factor is required to convert the MWs of interconnection capacity to the anticipated annual Energy withdrawals of a Large Load End User. While a typical End-Use Customer could have a capacity factor of 50% or lower, PG&E’s assumption here, reflects the fact that the utilization anticipated from Large Loads such as data centers is expected to be significantly higher. A recent study of actual data center operation by E3 indicates that “[o]nly two data centers had load factors above 90% of their reported peak loads, and fewer than half had load factors above 80%.”136 As a result, PG&E proposes to convert the scheduled capacity into an annual Energy quantity for calculating the Minimum Annual Revenue Obligation by assuming an 80% annual capacity factor. Annual Minimum Revenue Obligation Reconciliation Process. After each calendar year, PG&E will compare the Minimum Annual Revenue Obligation with the wholesale
134 Section 1.1 defines “Requested Interconnection Capacity” as the ultimate peak demand, expressed in MW, specified on behalf of the Large Load End User in the application process in the TO Tariff.135 Resolution E-5439 at 17 (Jan. 15, 2026) (directing refund of 75 percent of PG&E’s net annual revenue plus ITCC adjustment); Resolution E-5420 at 18 Resolution E-5420 at 18 (same); Resolution E-5433 (same). 136 Energy and Environmental Economics, Forecasting Large Loads in the Age of AI and Data Centers (December 2025), www.ethree.com/wp- content/uploads/2025/12/E3Whitepaper_DataCenterForecasting.pdf.
PDF page 33
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 33
transmission revenue associated with the Gross Load of the Large Load End User, as measured by the CAISO revenue meter (“Annual LL Gross Load Revenue”). The Annual LL Gross Load Revenue will be calculated by the TCLL/Large Load End User providing PG&E the Gross Load of the Large Load End User and multiplying that amount by the Regional Access Charge only, or the Regional Access Charge plus Local Access Charge, as appropriate. If the Annual LL Gross Load Revenue is less than the Minimum Annual Revenue Obligation, PG&E will invoice the TCLL or Large Load End User for the difference (“MARO Shortfall”). And the difference must be paid in thirty (30) calendar days. This will ensure that the TCLL or Large Load End User pays its fair share of its requested Load, including for relevant TCLL Reliability Network Upgrades that are necessary, in part, to bring the Large Load online and enable it to receive its required transmission service.
Failure to Pay the Shortfall. If the Participating TO informs the TCLL of a MARO Shortfall, the TCLL may recover such amount from its Large Load End User through retail rate mechanisms or may allow PG&E to draw on the Financial Security for any MARO Shortfall that remains unpaid more than sixty (60) days after its due date. Within five (5) Business Days after a draw, the Large Load End User/TCLL is required to restore the available Financial Security to the required amount.
Financial Security Obligation. Section 4 establishes the Financial Security obligations under the Cost Assurance Agreement. If PG&E is the TCLL, the Large Load End User will assume the Financial Security obligation. If the TCLL is not PG&E, the TCLL will have the option to assume the Financial Security obligation or require the Large Load End User to assume the Financial Security obligation, in which event the Large Load End User must be a Party to the Cost Assurance Agreement. Financial Security must be provided within thirty (30) Business Days of Construction Activities commencing on any TCLL Reliability Network Upgrade identified as being required, in part, for Standard Interconnection Service under the Facilities Agreement.137
The Cost Assurance Agreement requires that Financial Security be maintained for as long as the Minimum Annual Revenue Obligation remains in effect, including any period necessary to resolve and pay a final annual reconciliation. The Financial Security requirement shall equal five (5) years times the Minimum Annual Revenue Obligation calculated using the formula discussed above. However, instead of the Minimum Obligation Capacity being used in determining the Financial Security amount, PG&E shall use the full Requested Interconnection Capacity.
Acceptable Financial Security for the TCLL/Large Load End User will be determined by the Creditworthiness Procedures attached as Exhibit 1 to the Cost Assurance Agreement, which allows for a cash deposit,138 letter of credit, parent guaranty, or surety bond. The TCLL/Large
137 Construction Activities are defined as actions by any entity constructing the Reliability Network Upgrades that result in irrevocable financial commitments for the purchase of major electrical equipment or land.138 If the cash deposit is paid to PG&E, PG&E proposes to pay interest on refunds from when fully paid until refunded (the Financial Security is released) at the commercial paper rate for the reasons detailed
PDF page 34
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 34
Ender User shall maintain the form of Financial Security in the required amount without interruption. The Cost Assurance Agreement also allows that in each of the Years 12-15 of the Cost Assurance Agreement, the TCLL/Large Load End User may reduce its Financial Security by one year’s Minimum Annual Revenue Obligation.
Early Termination and Exit Fee. If the Cost Assurance Agreement is terminated prior to the expiration of the Term, the Cost Assurance Agreement provides for an Exit Fee equal to the value of the required Financial Security on the date of termination. If the TCLL/Large Load End User does not otherwise pay the Exit Fee in the required time under the agreement, PG&E is allowed to draw on all Financial Security to pay the Exit Fee.
The Exit Fee and Financial Security obligations are consistent with the directives contemplated by the OSC. The Commission called for a secured minimum contribution, based on the level of requested jurisdictional transmission service in MW and credited to the revenue requirement, sufficient to “mitigate cost shifting if the Eligible Customer ultimately takes less transmission service than anticipated because the large load does not materialize as planned or is not developed at all.”139 Here, PG&E’s proposal will treat amounts recovered for MARO Shortfalls as a credit in PG&E’s wholesale revenue requirements, consistent with the OSC. The proposed Exit Fee also protects other customers from cost shifts that result from a Large Load End User failing to maintain service for the full term of the Cost Assurance Agreement. If the Large Load End User departs before the full term is satisfied, the cost of the upgrades needed to provide, at least in part, interconnection service to the TCLL will remain in PG&E’s transmission revenue requirement, but the revenue expected from the departing load will not materialize. To mitigate this concern, PG&E’s proposed Exit Fee requires the Large Load End User to pay five (5) years of their targeted expected Minimum Annual Revenue Obligation to avoid shifting costs onto other customers.
Large Load End User Rights and Obligations. In Section 6 of the Cost Assurance Agreement, the Large Load End User agrees that its obligations under the agreement are: (i) the annual payment of any MARO Shortfall; (ii) posting of Financial Security; and (iii) payment of Exit Fee, if any.
Other Provisions. The remaining provisions of the Cost Assurance Agreement include standard contract terms and conditions typically found in pro forma Commission-approved interconnection and transmission service agreements. They include Section 7 (Indemnification and Liability); Section 8 (Default); Section 9 (Confidential Information); Section 10 (Assignment); and Section 11 (Miscellaneous Provisions).
above. If the cash deposit is paid into escrow, the interest obtained in the escrow account will accrue to the benefit of the TCLL/Large Load End User.
139 OSC at PP 80, 82, 84.
PDF page 35
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 35
b. PGE’s proposal to include the Large Load End User as a
signatory to the Cost Assurance Agreement when PG&E is the
TCLL is just and reasonable.
Like the Facilities Agreement, PG&E proposes to include the Large Load End User as a party to the pro forma Cost Assurance Agreement when PG&E is the TCLL for the reasons detailed in Section V(C)(2)(b) above.
4. PG&E Proposes to Include the Payments Received from TCLLs and
Large Load End Users in the TO Formula Rate in Accordance with
Cost-Of-Service Requirements
The OSC requires that payments made by an Eligible Customer to a transmission owner pursuant to a cost recovery agreement will be appropriately credited toward the transmission owner’s transmission revenue requirement consistent with the Commission’s cost-of-service regulations.140 The Commission preliminarily finds in the OSC that it appears reasonable for filers of formula rates to provide a separate workpaper in the annual informational filing describing how any payments made pursuant to a cost recovery agreement are reflected in the transmission owner’s transmission formula rate.141
PG&E proposes to treat the cost recovery associated with the four different types of facilities, i.e., (1) Direct Assignment Facilities; (2) TCLL FILLI Facilities; (3) TCLL Interconnection Network Upgrades; and (4) TCLL Reliability Network Upgrades in accordance with the Uniform System of Accounts, its approved formula rate,142 and where appropriate, make certain modifications to the formula rate to allow specific cost recording and transparency into how TCLL and/or Large Load End User payments will be recorded in PG&E’s revenue requirement.
Direct Assignment Facilities and TCLL FILLI Facilities. Consistent with current practice, Direct Assignment Facilities and payments for those facilities are removed from the TO formula rate. This is done through PG&E’s accounting system by recording the payment of Direct Assignment Facilities and associated plant and other costs in certain Maintenance Activity Types (“MAT”) codes143 and Unbundled Cost Categories (“UCCs”)144 that are excluded from recovery in the approved formula rate. PG&E will utilize this same methodology for Direct
140 OSC at P 84 (citing 18 C.F.R. pt. 101 (2025)).141 Id.142 Pac. Gas & Elec. Co., Transmission Owner Tariff, FERC Electric Tariff, Vol. No. 5, App. VIII (Formula Rate).143 PG&E uses MAT codes to categorize costs for capital work, replacements, emergency work, new business, etc. according to the type of work being done. MAT codes 82A/82N are direct-connect, non- CAISO controlled facilities that are excluded from the TO formula rate.144 UCCs are regulatory categories used to separate and categorize Plant, Accumulated Depreciation, and Depreciation Expense for reporting and ratemaking purposes.
PDF page 36
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 36
Assignment Facilities and TCLL FILLI Facilities to exclude those upfront payments from recovery in the formula rate.
TCLL Interconnection Network Upgrades. As explained above, the costs of TCLL Interconnection Network Upgrades are paid upfront by the TCLL before Interconnection Service begins and may be refunded over fifteen (15) years based on the transmission revenues generated by the TCLL. PG&E proposes to include the upfront payment as a rate base credit. Currently, the TO formula rate provides for the crediting of generator interconnection upfront payments as a credit to rate base in Schedule 15-NUC (Network Upgrade and Credit Interest Expense).145 These amounts are supported in Workpaper WP_15-NUC, which details the calculations.146 PG&E proposes the same treatment for Large Load End User upfront payments, i.e., those amounts would be recorded to Schedule 15-NUC (Network Upgrade and Credit Interest Expense) and act as a rate base credit. To increase transparency, if PG&E’s proposed cost responsibility framework is accepted, PG&E proposes to submit on compliance the form of an additional workpaper to support the Large Load End User payment amounts that will be reflected in Schedule 15-NUC (Network Upgrade and Credit Interest Expense) similar to the current WP_15-NUC for generator interconnection upfront payments.
When the asset is placed in service, it is recorded in the appropriate plant accounts. If those upfront costs are refunded to the TCLL or Large Load End User, PG&E would reduce the rate base credit. In this manner, when the asset is placed in service it is recorded in plant and appropriately depreciated, offset by a rate base credit for the upfront payment made by the customer. When the Large Load End User pays for the upfront cost of the facilities through its targeted contribution to transmission revenue, the upfront cost is refunded and the rate base credit is reduced. PG&E proposes to treat the non-refundable portion of the upfront payment in a manner similar to direct assignment facilities, i.e., the upfront payment and associated costs of the asset are excluded from the TO formula rate.
TCLL Reliability Network Upgrades. As discussed above, for TCLL Reliability Network Upgrades, PG&E proposes to require a Minimum Annual Revenue Obligation backed by security from the TCLL or Large Load End User to ensure that the TCLL or Large Load End User pays their expected targeted transmission revenue. Any relevant TCLL Reliability Network Upgrades constructed, in part, for the Large Load End Users’ interconnection would be recorded to the appropriate plant account when placed in service and recovered through PG&E’s TO revenue requirement and associated Regional Access Charge or Regional Access Charge plus Local Access Charge, as applicable. As stated in the pro forma, the Minimum Annual Revenue Obligation Shortfall or Exit Fee recovered from the TCLL/Large Load End User will be treated as a credit in PG&E’s wholesale revenue requirements. In this manner, PG&E would properly account for customer revenue in its TO formula rate in accordance with cost-of-service principles, the Uniform System of Accounts, and the approved formula rate, with limited modifications where required. If PG&E’s proposed cost responsibility framework is accepted,
145 Appendix VIII, TO Formula Rate, Schedule 1-Base TRR, line 112.146 Id. Att. 1, Protocols, Section 20 (List of Work Papers).
PDF page 37
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 37
PG&E proposes to submit on compliance the necessary edits to the Appendix VIII: Formula Rate to effectuate this treatment.
5. PG&E Proposes a Just and Reasonable Interim Standard
Interconnection Service and Flexible Interim Large Load
Interconnection Service to Accommodate Transmission Customers
Seeking to Take Transmission Service on Behalf of Large Load End
Users
The OSC found that CAISO’s Tariff may be unjust and unreasonable because it lacks “transmission services that reflect the use of the transmission system by Eligible Customers on behalf of flexible large load, on both an interim and permanent basis.”147 The OSC directs the CAISO to explain whether the CAISO’s Tariff remains just and reasonable without (1) an interim non-firm network transmission service while network upgrades are being constructed and
(2) permanent firm and non-firm contract-demand transmission services (service up to a specified MW contract level on a firm or non-firm basis), or to propose such revisions—or, alternatively, to explain how the CAISO’s existing framework provides comparable options. As discussed above, unlike other regions, the CAISO does not process stand-alone requests for transmission service; therefore, a flexible service for Large Loads cannot be offered as a separate transmission product. Instead, any flexible transmission service must be offered as part of the interconnection services.148 Accordingly, PG&E proposes to address this directive of the OSC through its interconnection process and proposes to amend its TO Tariff to incorporate an Interim Standard Interconnection Service and Flexible Interim Large Load Interconnection (“FILLI”) Service.
PG&E proposes to allow TCLLs, on behalf of Large Load End Users, to request Interim Standard Interconnection Service and/or FILLI Interconnection Service in their TCLL Interconnection Application. The terms and conditions of Interim Standard Interconnection Service and FILLI Interconnection Service will be set forth in the pro forma Interim Service Agreement (Attachment C of Appendix XI). Interim Standard Interconnection Service is defined as Standard Interconnection Service that can be provided, if any, prior to the completion of all TCLL Facilities identified as necessary for the Large Load to withdraw Energy. However, proposed Section 10A.7.1 makes it clear that the Participating TO is not obligated to provide any amount of Standard Interconnection Service until necessary facilities have been placed in service.
When Interim Standard Interconnection Service is not available, or only partially available, FILLI Interconnection Service is available for all remaining Load if the Large Load End User can reduce Load at a specified Point of Withdrawal. FILLI Interconnection Service is intended to be a temporary, as-available transmission interconnection service that allows PG&E, working with the CAISO and the Large Load End User, to manage operational constraints on
147 OSC at P 105.148 Virani Testimony at 5-6.
PDF page 38
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 38
withdrawals from the transmission system while the interconnection and system upgrades necessary to provide standard, firm service are being developed.149 As discussed in more detail below, if the TCLL requests FILLI Interconnection Service or Interim Standard Interconnection Service, PG&E will identify the extent to which interim services can be provided, prior to when all TCLL Facilities are in service. The rates charged for transmission service, subject to the FILLI Interconnection Service restrictions, will also not be discounted because it is a voluntary service.
FILLI Interconnection Service automatically terminates once Standard Interconnection Service is available to serve the entire requested capacity. PG&E is not proposing permanent non-firm or conditional-firm interconnection service at this time. PG&E will work with the CAISO to develop any permanent option through a future stakeholder initiative informed by experience with FILLI Interconnection Service and customer interest.150
However, PG&E believes that its proposed FILLI Interconnection Service is functionally equivalent to the interim non-firm network transmission service contemplated by the OSC and therefore satisfies this requirement of the OSC. PG&E also believes that FILLI Interconnection Service, together with CAISO’s Tariff, addresses the OSC directive by providing a functionally comparable service. PG&E proposes to include a new Section 10A.7 in its TO Tariff, along with a pro forma Interim Service Agreement, that together will govern Interim Standard Interconnection Service and FILLI Interconnection Service for those Large Load End Users voluntarily electing to take it.
a. PG&E proposes to include new sections in the TO Tariff to
address the requirements for applying for, studying, and
implementing Interim Standard Interconnection Service and
FILLI Interconnection Service.
Proposed Section 10A.7 allows TCLLs to request Interim Standard Interconnection Service and/or FILLI Interconnection Service as part of their TCLL Interconnection Application and establishes a process for reviewing and processing Interim Standard Interconnection Service and/or FILLI Interconnection Service requests. If the TCLL on behalf of the Large Load End User has requested one or both of these interim interconnection services, PG&E will perform an analysis to identify the extent to which the Large Load End User can be served by Interim Standard Interconnection Service and the amount of remaining requested capacity that can be served by FILLI Interconnection Service.151 Proposed Section 10A.7.1 makes clear that PG&E will not be obligated to provide any amount of Standard Interconnection Service requested until
149 Nedrud Testimony at 29-30.150 CAISO, Large Loads Enhancements Draft Final Proposal, at 68 (Sept. 24, 2026), https://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load- Enhancements-Sep-24-26.pdf (“Although the CAISO is not proposing to advance the permanent flexible interconnection offering, FLIP, in this draft final proposal, the CAISO does commit to further exploration of this permanent offering in a future stakeholder initiative.”).151 Nedrud Testimony at 29-30.
PDF page 39
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 39
necessary facilities have been placed in service. It also specifies that the actual amount of Energy that a Large Load End User may withdraw is based on expected operations and real-time operations. As discussed in more detail below, FILLI Interconnection Service will also be governed by an Interim Service Agreement.
Proposed Section 10A.7.2 establishes a study process for interim service to determine the maximum amount of Interim Standard Interconnection Service and/or FILLI Interconnection Service available to the Large Load End User. The study is performed as part of the applicable Serial or Cluster Study Process and evaluates service under NERC Transmission System Planning Performance Requirement conditions, including normal and contingency conditions, to determine firm and curtailable amounts and required operating protections.152 The analysis does not guarantee that the maximum amount will be available under actual system conditions. PG&E will require studying load under both N-1-1 and N-1 conditions to determine how much, if any, FILLI Interconnection Service can be offered while upgrades are being constructed to enable Standard Interconnection Service for the entire load request.153 The study will identify capacity (in MW) of Interim Standard Interconnection Service and FILLI Interconnection Service (which can vary seasonally and over time) as well as any operational requirements, protections, and control systems to maintain safe and reliable service, consistent with the data requirements for flexible interim load interconnection service set forth in the proposed CAISO Tariff.154 FILLI Interconnection Service is subject to curtailment at all times, and is available only where the Participating TO determines service may be provided within limitations in certain periods under normal operating conditions.155
Proposed Section 10A.7.3.1 and the Interim Service Agreement, discussed below, set forth the FILLI Interconnection Service reliability requirements, including what TCLL Interconnection facilities must be installed, the necessary protection and control systems, and operating procedures to allow the Large Load End User to withdraw Energy. Proposed Section 10A.7.3.1 also specifies that FILLI Interconnection Service will not commence until PG&E and the TCLL have completed installation of all equipment specified under the Interim Service Agreement.
Proposed Section 10A.7.3.2 provides that Exhibit 1 to the Interim Service Agreement shall set forth the circumstances, contingencies, and operating conditions under which FILLI Interconnection Service will be curtailed. Specifically, a TCLL receiving FILLI Interconnection Service will be subject to curtailment prior to any curtailment of a TCLL receiving Standard Interconnection Service, and PG&E may curtail FILLI Interconnection Service as necessary to
152 Nedrud Testimony at 29-30.153 Id.154 CAISO Tariff, Proposed § 25.7.2 (Flexible Interim Load Interconnection).155 See Nedrud Testimony at 29-30.
PDF page 40
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 40
maintain the reliable operation of the CAISO Controlled Grid, including during normal operating conditions.
Proposed Section 10A.7.3.3 provides that a Large Load End User receiving FILLI Interconnection Service shall not exceed the authorized quantity of FILLI Interconnection Service and that PG&E may disconnect service to the Large Load End User if the Large Load End User’s Energy withdrawals violate the terms of the Interim Service Agreement. b. PG&E Proposes to Include a Pro Forma Interim Service
Agreement as Attachment C to the TCLL Agreement That will
Provide the Terms and Conditions of Interim Standard
Interconnection Service and/or FILLI Interconnection Service.
PG&E proposes to include as Attachment C to the TCLL Agreement a pro forma Interim Service Agreement among PG&E (as Participating TO under its TO Tariff), the CAISO, the TCLL (if not PG&E), and the Large Load End User. An executed and effective Interim Service Agreement will supply the operative terms for Interim Standard Interconnection Service and/or FILLI Interconnection Service for each Large Load End User opting to take such service. Section 1 (Definitions) references the TCLL Agreement and the CAISO and TO Tariffs for Definitions.
Section 2 (Interconnection Service Quantities) provides the amounts and types of interconnection service that PG&E expects to initially provide to the TCLL based on the results of the requisite studies.
Section 3 (Curtailment of FILLI Interconnection Service) provides the Interim Service Agreement shall set forth the circumstances, contingencies, and operating conditions under which FILLI Interconnection Service will be curtailed. It also makes clear that FILLI Interconnection Service shall be subject to curtailment prior to any curtailment of customers receiving Standard Interconnection Service and that the Participating TO may curtail FILLI Service as necessary to maintain the reliable operation of the CAISO Controlled Grid, including during normal operating conditions.
Section 4 (TCLL and Large Load End User Obligations) provides that the TCLL and Large Load End User will abide by the requirements set forth in the Interim Service Agreement, and that the Large Load End User shall ensure that it and its Scheduling Coordinator comply with all applicable requirements in the CAISO Tariff.
Section 5 (FILLI Interconnection Service Reliability Requirements) provides that Exhibit 1 to the Interim Service Agreement addresses the CAISO and Participating TO requirements for FILLI Interconnection Service. Section 5 also specifies that the Facilities Agreement identifies the TCLL Facilities to be owned by the Participating TO or the TCLL and addresses cost responsibility for such facilities.
PDF page 41
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 41
Section 6 (Exceedances) requires the Large Load End User to avoid exceedances, which can result in disconnection.
Section 7 (Termination of FILLI Interconnection Service and/or Interim Standard Interconnection Service) provides that FILLI Interconnection Service automatically terminates upon PG&E’s notice to the TCLL of the completion of the transmission facilities needed to provide Standard Interconnection Service, at which time the service automatically transitions to service pursuant to the standard, non-FILLI Interconnection Service provisions of the TO Tariff and the Interim Service Agreement.
Section 8 (Conditions Precedent) addresses the requirements that need to be in place before FILLI Interconnection Service or Interim Standard Interconnection Service can be provided.
The remaining provisions are similar in nature to the standard provisions included in the TCLL Agreement and other attachments.
c. Inclusion of the Large Load End User on the pro forma Interim
Service Agreement is necessary and within the Commission’s
jurisdiction to approve.
PG&E proposes to include the Large Load End User as a party to the pro forma Interim Service Agreement because PG&E must have a binding commitment from the Large Load End User that it will adhere to curtailment requirements. FILLI Interconnection Service is voluntary. To take the service, both the TCLL and the Large Load End User must elect it, and that election places a reliability burden on the transmission system. It is critical for reliability that the Large Load End User comply with curtailments, particularly where PG&E serves as both the Participating TO and the TCLL. FILLI Interconnection Service will also impose equipment and other operational requirements with which PG&E must have assurance that the Large Load End User will comply.156 Without binding obligations running directly to the Large Load End User, PG&E would have no guarantee of that compliance.
The pro forma Interim Service Agreement, including the Large Load End User’s obligations under it, is within the Commission’s jurisdiction to approve. The Commission has jurisdiction over the terms and conditions of transmission service.157 The Interim Service Agreement allows TCLLs, on behalf of Large Load End Users, to take transmission-level, flexible interconnection service before the transmission facilities necessary to provide Standard Interconnection Service are in place.158 In other regions, FILLI Interconnection Service would be offered as a transmission service, but given the structure of the CAISO market it is offered by
156 See Nedrud Testimony at 29-30.157 16 U.S.C. § 824(b); New York, 535 U.S. at 16-24.158 Nedrud Testimony at 29-30.
PDF page 42
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 42
PG&E, the Participating TO, as an interconnection service.159 Accordingly, because it is a transmission service agreement, it is within the Commission’s jurisdiction to approve.160 While the Commission has rejected proposals that place certain obligations on retail customers, those obligations were placed in the context of wholesale capacity market constructs where the Commission does not have jurisdiction over the provision of retail energy service.161 Here, however, PG&E seeks to ensure the retail customer, the Large Load End User, adheres to the requirements for TCLL taking flexible transmission interconnection service on its behalf. The provision of this flexible transmission service is also completely voluntary.
D. PG&E Proposes Changes to the TO Tariff That Provide a Just and
Reasonable Process for Affected Systems
The OSC does not separately address affected systems. It does, however, find that the TO Tariffs lack clear provisions for studying the transmission system impacts of large loads. It also requires that large load-driven costs not shift to customers who neither caused nor benefit from them.162
Proposed Sections 10A.4.3 and 10A.6 address Affected Systems directly. When PG&E’s studies show that another system will be affected by a TCLL Interconnection request, PG&E must notify the Affected System Operator, the TCLL, and the CAISO. PG&E will then coordinate any studies to determine the impact of the TCLL Interconnection request on the Affected System and include the Affected System Operator in the applicable meetings with the TCLL. Section 10A.6 requires the TCLL to fund any required upgrades on the Affected System, which are identified in the Facilities Agreement. An Affected System Operator taking service under PG&E's TO Tariff must inform the Participating TO and TCLL within forty (40) Business Days whether it intends to perform an affected system study, at the TCLL's expense. If the Affected System Operator fails to notify PG&E within forty (40) Business Days, it waives its rights to bring any related claims against PG&E.
These provisions meet the OSC’s directives. They establish a clear, timely process for identifying and studying impacts beyond PG&E's system. They also assign the resulting costs to the TCLL, whose request causes them, rather than to other transmission customers.
159 Virani Testimony at 3-6.160 Supra, note 131.161 PJM Interconnection, L.L.C., 197 FERC ¶ 61,109, P 81 (2026) (finding outside the Commission’s jurisdiction provisions that require retail customers to curtail as part of a wholesale capacity market construct); FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 278-80 (2016) (explaining that FERC may regulate practices directly affecting wholesale rates but may not regulate retail electricity sales, which are reserved to the states).162 OSC at P 80.
PDF page 43
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 43
VI. PG&E PROPOSES CHANGES TO THE TO TARIFF THAT PROVIDE A JUST
AND REASONABLE PROCESS FOR LARGE LOADS THAT SEEK TO CO-
LOCATE WITH GENERATION PROJECTS
In the OSC, the Commission preliminarily found that the CAISO Tariff appears to be unjust and unreasonable because it does not contain provisions addressing with sufficient clarity and consistency the rates, terms, and conditions of service that apply to interconnection customers serving co-located load, and because it does not reflect that an Eligible Customer taking transmission service on behalf of such load is willing and able to limit its energy withdrawals from the transmission system under certain conditions.163 The Commission described co-located load as end-use customer load physically connected to the facilities of an existing or planned generating facility on the generator interconnection customer’s side of the point of interconnection to the transmission system, and it referred to the co-located load and its associated generating facility together as a co-location arrangement.164 The Commission directed the CAISO and the Participating TOs to address these issues.165
A. The CAISO and the Participating TOs Propose to Maintain the
Existing Division of Requirements Between the CAISO Tariff and the
Participating TO Tariffs, with the CAISO Remaining Responsible for
Generator Interconnections and PG&E Remaining Responsible for
Load Interconnections.
As noted above, the OSC’s co-location directives fall principally on the CAISO rather than on the Participating TOs. The Commission recognized that co-location concerns “mostly implicate the CAISO Tariff,” because only the CAISO Tariff governs the generator interconnection process.166 Accordingly, the OSC directs the CAISO to clarify how interconnection customers may use the generator interconnection process to serve co-located load—including whether a generating facility may request interconnection service below its maximum facility output and may use provisional and surplus interconnection service—and to account in its study process for the dynamic impacts of co-located load and any request to modify an existing generating facility’s interconnection service level to serve that load.167 The OSC also directs the CAISO to address cost-causation concerns, including whether an Eligible Customer taking service on behalf of co-located load should pay for regulation and black start services on a gross demand basis, so that these costs are not shifted to other transmission customers.168163 OSC at P 93.164 Id. at P 88. The Commission uses the term “Eligible Load” to refer to co-located load and/or load with behind-the-meter generation. Id. at P 90.165 Id. at P 86.166 Id. at P 86 n.77.167 Id. at P 96.168 Id. at PP 98-100.
PDF page 44
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 44
The OSC’s directives to the Participating TOs are correspondingly narrower, reaching the provision of transmission service to an Eligible Customer on behalf of co-located load and the prevention of cost shifting. As a Participating TO, PG&E must ensure that its TO Tariff provides a clear and consistent process for a TCLL to interconnect a Co-Located Large Load End User, coordinated with the CAISO-administered generator interconnection process that governs the associated generating facility.
Based on stakeholder discussions with the CAISO, PG&E expects the CAISO to address the directives of the OSC in its filing by clarifying how co-located large loads and generation may interconnect to, and operate within, the CAISO-controlled grid. Consistent with the existing division of responsibilities, PG&E expects that the changes in the CAISO Tariff will apply to the generation component of a co-location arrangement and PG&E’s proposed changes will apply to the Large Load End User, with the CAISO continuing to govern and study wholesale generation interconnection requests and PG&E continuing to govern and study Load interconnection requests.169 Where a new or existing Large Load proposes to co-locate with a new Generating Facility that may export Energy to the transmission grid, PG&E understands the CAISO will propose that the Generating Facility will require a CAISO interconnection study under its Resource Interconnection Standards (Appendix KK to the CAISO Tariff), so that the request is screened and competes for capacity in the next cluster study based on the CAISO’s scoring criteria. Because scoring, financial requirements, and study results would be based on the capacity the developer requests, a developer may limit the quantity of Generation to be exported in light of how much Generation will instead serve the Co-Located Large Load End User, and the CAISO would work with the affected Participating TO to produce study results reflecting the combined impact of the Co-Located Large Load End User and Generating Facility.170
B. PG&E Proposes to Include a New Process for Addressing the TCLL
Portion of the Co-Located Large Load End User Interconnection
Process that will Ensure Coordination with the CAISO’s Generator
Interconnection Process.
PG&E proposes to include a new Section 10A.8 that will govern Co-Located Large Load End Users. Proposed Section 10A.8 describes the interconnection process applicable to Co- Located Large Load End Users connecting to facilities of a Generating Facility. For such Co- Located Large Load End Users, the TCLL will be subject to the TCLL Interconnection process in Section 10A. The CAISO will be a party to a pro forma agreement that bridges the pro forma Large Generator Interconnection Agreement (“LGIA”) with the TCLL Agreement or will negotiate a non-conforming LGIA to account for certain details of the Co-Located Large Load End User interconnection on an individual basis. The Generating Facility developer will also execute a CAISO pro forma Participating Generator Agreement for the generating facility, but not a Participating Load Agreement for the Co-Located Large Load End User.
169 See e.g., California Independent System Operator Corp., Large Loads Enhancements Draft Final Proposal, Serving Co-Located Loads (Sept. 17, 2026) (“CAISO Draft Final Proposal”).170 CAISO Draft Final Proposal, Serving Co-Located Loads.
PDF page 45
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 45
The Section 10A.8 process will coordinate the Large Load study with the CAISO generator-interconnection study for any Co-Located Large Load End User and produce study results reflecting the combined operation of the Generating Facility and the Large Loads. The studies will account for the combined operating configuration, requested export capacity, and any controls or protections needed to ensure that the assumed withdrawal arrangement is effective.
C. Electrically Proximate Load
In the OSC, the Commission preliminarily finds that the CAISO Tariff appears to be unjust and unreasonable because it lacks a generator interconnection study process and/or generator interconnection service to reflect an interconnection customer’s commitment to limit the generating facility’s output to minimize the impact on the transmission system while serving an electrically proximate large load.171 The CAISO has deferred addressing electrically proximate generators and large loads until a future stakeholder initiative. PG&E supports this approach and believes that the CAISO should first discuss with stakeholders whether any such initiative is necessary. PG&E is unclear how a Generator’s sale of Energy to a Large Load (even using a wholesale sleeve), using wires it does not own would be in accord with state, municipal, and other public power service area rights. Indeed, co-location itself may be rare in the CAISO, given state laws on when a retail seller is deemed to be a CPUC-jurisdictional electrical corporation, subject to CPUC rate regulation and myriad other California laws and CPUC regulation.172 In CPUC-regulated utility service areas, renewable and cogeneration generators are permitted in limited circumstances to serve up to two retail loads without being regulated by the CPUC, such that even co-location relies on a fairly narrow legal exception, which does not cover electrically proximate generators and loads. Public power utilities can prohibit co-location altogether.173
VII. PG&E PROPOSES A TRANSITION PERIOD CONSISTENT WITH THE
REQUIREMENTS OF THE OSC.
The OSC states that it is “not intended to disrupt existing commercial arrangements” and specifically recognizes that any proposed changes to the Participating TO Tariffs should “(a) propose a reasonable implementation period to ensure minimal disruption to such existing commercial arrangements, and (b) allow a reasonable amount of time to finalize ongoing agreements that are nearing completion as of the date such tariff provisions are filed with the
171 OSC at P 113.172 S.B. 886, 2025–2026 Reg. Sess. (Cal. 2026) (California Technology Innovation and Ratepayer Protection Act)).173 Presumably there are transmission owners similarly located in states throughout the United States with service area laws that render transactions between electrically proximate generators and retail loads unlawful, such that RTOs in such regions would need to restrict study procedures based on whether the Local Regulatory Authority permits the service in the first place.
PDF page 46
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 46
Commission.”174 Consistent with that directive, PG&E proposes a new Section 10A.9 of the TO Tariff to govern the transition to the new Section 10A process. Proposed Section 10A.9 provides that, as to a retail customer with a load of 50 MW or greater that has provided its UDC or MSS with a completed application for retail service before the original effective date of Section 10A, the UDC or MSS is not required to obtain a TCLL Interconnection under Section 10A. In addition, because PG&E must begin its annual Cluster Study Process no later than April of each year, Section 10A.5.1 provides that, if there are no Completed TCLL Interconnection Applications that have been found to be electrically dependent by the end of February 2027, there will be no Cluster Study Process commencing on April 1, 2027, under the proposed tariff. As a result, any TCLL Interconnection Applications completed before the effective date of the new Section 10A process will be processed under PG&E’s existing Large Load process, and PG&E will make any filings necessary to obtain Commission approval of agreements associated with those requests.
VIII. OTHER CHANGES TO THE TO TARIFF
In addition to adding a new Section 10A, as well as replacing the currently unused Appendix XI, the new Large Load processes had a ripple effect on other TO Tariff sections, including, most importantly, the Definitions, where many new terms were added. The changes that required PG&E to add new processes for Large Load also evidenced the fact certain portions of the TO Tariff had not always been revised through the past nearly three decades in a manner that kept it congruent with the CAISO Tariff. Thus, PG&E has revised the body of its TO Tariff in a variety of ways.175
First, PG&E observed that Section 1 no longer reflected Appendix F of the CAISO Tariff regarding how in-BAA transmission service was paid for. Section 1 also was the first section that indicated that PG&E had not adopted the CAISO’s “Regional” and “Local” vernacular rather than “High Voltage” and “Low Voltage.” The sets of terms are identical, and the Definitions now indicate that they are interchangeable. But, PG&E chose only to update the terms in the body of the TO Tariff (as they were relevant) and left the terms High- and Low- Voltage in its Appendices I-X.176 As noted, many new terms had to be defined, not only to reflect Section 10A, but to differentiate the TCLL Interconnection process from the existing Wholesale Load Interconnection process. The term “Wholesale Load Interconnection” is now used for this more traditional service, primarily in Sections 8 and 10. The definition of “Gross Load” was updated to the CAISO definition because Gross Load is used in Appendix XI. Sections 4, 5.1, and 8.1 were redrafted to better reflect the entities subject to the TO Tariff for interconnection purposes. When the TO Tariff was drafted, the wholesale interconnections
174 OSC at P 5.175 To avoid excessive redlining, “ISO,” “ISO Controlled Grid,” and “ISO Tariff” were retained rather than updated. 176 Section 5, which addresses rates, retains usage of “High-Voltage” and “Low-Voltage.”
PDF page 47
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 47
envisioned were not the same as today given Order No. 1000 and other changes. Thus, Section 10 was modified to reflect a new term “Wholesale Load Interconnection.”
Finally, the new Large Load procedures required a second look at the creditworthiness section of the TO Tariff (Section 13). The existing provisions addressed those paying the Low Voltage (a/k/a Local) Access Charge and End Users, whose rates are identified in the TO Tariff but whose creditworthiness was a matter for the CPUC. With the proposed changes in Section 10A and Appendix XI, TCLLs will be seeking to add load on behalf of Large Load End Users (thus triggering capital projects). Additionally, for efficiency, Large Load End Users may transact directly with PG&E, which requires a new approach to credit as to both these entities, which is found in Exhibit 1 to the Cost Assurance Agreement (Attachment B to Appendix XI). Finally, given the congruent nature of PG&E and the CAISO’s large load tariff filings, there may be additional conforming changes that need to be made on compliance.
IX. RESPONSES TO THE OSC BRIEFING QUESTIONS
Section IV of the OSC directs further briefing on five sets of questions. PG&E responds to each below, in the order presented in the OSC, to the extent the questions implicate PG&E’s TO Tariff.
A. Protection of Existing Commercial Arrangements
The OSC asks how the CAISO and the Participating TOs should protect existing commercial arrangements, including (1) what would be a reasonable implementation period to ensure minimal disruption to such arrangements, and (2) how to allow a reasonable amount of time to finalize ongoing agreements that are nearing completion as of the date the tariff provisions are filed.177 As discussed in Section VII, PG&E proposes a new Section 10A.9 under which a UDC or MSS serving a retail customer with a Load of 50 MW or greater that has submitted a completed application for retail service before the original effective date of Section 10A is not required to obtain a TCLL Interconnection under Section 10A. Requests completed before the effective date will continue to be processed under PG&E’s existing Section 10 process for Wholesale Load Interconnection Applications. In addition, PG&E requests an effective date of February 16, 2027, which, together with the annual Cluster Study timing in Section 10A.5.1, provides a reasonable implementation period and avoids disrupting arrangements that are nearing completion.
B. Impacts of New FILLI Interconnection Service on Transmission
Planning
The OSC also asks what potential impacts on regional and local transmission planning would arise from the introduction of new transmission services for flexible Large Loads, including how providers and planners would account for flexible large loads’ potential
177 OSC at P 123.
PDF page 48
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 48
preference to take such services and the associated uncertainties around the type, location, and quantity of expected Loads.178 As discussed above, PG&E is not proposing a new permanent non-firm or conditional-firm service at this time, and proposed Section 10A.7 makes clear that PG&E is not obligated to provide any amount of Standard Interconnection Service requested until necessary facilities have been placed in service. Instead, Interim Standard Interconnection Service and FILLI Interconnection Service are temporary as-available services that are studied within the applicable Serial Study Process or Cluster Study Process, subject to identified operating limits and curtailment, and automatically terminated once Standard Interconnection Service is available for the full requested capacity. Any TCLL FILLI Facilities necessary to initiate interim service, will be identified in the Facilities Agreement. Because the full requested capacity of each Large Load End User will continue to be studied and planned for under the CAISO’s TPP and concurrence process, PG&E’s proposal does not alter the inputs to regional or local transmission planning.
To facilitate this flexible service, the CAISO is also proposing Section 25.7.2, which specifies that the CAISO, Participating TO, and Large Load End User or its authorized agent will execute an agreement, for PG&E this is the Interim Service Agreement, to enable Large Load End Users to interconnect prior to the completion of the Large Load’s transmission upgrades. However, the Interim Service Agreement does not alter the current transmission planning processes in the CAISO; rather, it specifies the circumstances in which the Large Load End User receiving interim service may be temporarily curtailed and the mechanisms used to perform the curtailment. PG&E will continue to work with the CAISO to consider any permanent flexible option, and its planning implications, in a future stakeholder initiative.
C. Structure of Cost Recovery Agreements and Minimum Cost Recovery
and Financial Security
The OSC directs respondents to provide information on potential structures for agreements between the transmission owner or provider and an Eligible Customer to prevent unjust and unreasonable cost shifts related to network upgrades required for Large Loads, and on the appropriate minimum level of cost recovery and Financial Security under such agreements.179 As discussed in Section V.C, PG&E proposes a facility-specific structure to ensure there are adequate cost recovery protections when Large Loads require transmission upgrades or additions. Direct Assignment Facilities and TCLL FILLI Facilities are directly assigned to the TCLL or Large Load End User and fully funded before service begins. TCLL Interconnection Network Upgrades are funded upfront by the TCLL or Large Load End User and refunded over fifteen years at 75 percent of realized wholesale transmission revenues. TCLL Reliability Network Upgrades are only preliminarily identified in the Facilities Agreement found in Attachment A to Appendix XI and remain subject to funding in accordance with the CAISO Tariff. The Cost Assurance Agreement found in Attachment B to Appendix XI, however, provides Financial Security requirements and establishes a Minimum Annual Revenue
178 OSC at P 124.179 Id. at P 125.
PDF page 49
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 49
Obligation to ensure that Large Load End Users that do not materialize or fail to meet an expected minimum capacity are financially responsible for any shortfall to prevent shifting costs to other customers.
D. Evaluation of Alternative Transmission Technologies
The OSC seeks further briefing on whether specific characteristics of providing transmission service to Eligible Customers on behalf of Large Loads warrant requirements beyond (1) the evaluation of alternative transmission technologies in all studies, without the need for a request, and (2) a demonstration in the study report of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline when traditional network upgrades are selected.180 As discussed in Section IV.B, PG&E’s proposed Serial Study Process and Cluster Study Process require PG&E to consider alternative transmission technologies in every TCLL Interconnection study and, where traditional network upgrades are selected, to demonstrate why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline.
E. Generating Facilities Serving Electrically Proximate Large Load or
Large Co-Located Load
The OSC asks (a) to what extent the CAISO would allow an interconnection customer’s generating facility serving electrically proximate large load or large co-located load to participate in the CAISO’s energy and ancillary services markets, and what restrictions or mitigation would apply; and (b) whether, and how, the CAISO would account for such generating facilities in its resource adequacy construct, including participation and accreditation in any capacity market.181 These questions are directed to the CAISO and implicate the CAISO Tariff rather than PG&E’s TO Tariff, and PG&E defers to the CAISO’s response. For its part, PG&E’s proposed Section 10A.8 addresses the Load side of a co-location arrangement by requiring the TCLL for a Co- Located Large Load End User to proceed under Section 10A and by coordinating PG&E’s study with the CAISO’s Generator interconnection study so that the results reflect the combined operation of the Generating Facility and the Large Load.
X. ETARIFF CHANGES
When PG&E initially sectionalized its TO Tariff, it sectionalized the tariff to a greater degree than required (i.e., three levels). Due to the number of changes required, the third level tariff records of Section 3, i.e., 3.1, 3.2, etc. will all be cancelled and the new version of the Tariff Record “3., TO Definitions (1.0.0)” will contain all Definitions.
180 OSC at P 126.181 Id. at P 127; TO Tariff, Proposed § 10A.8; CAISO Tariff, Proposed §§ 25.5.1, 25.7.6.
PDF page 50
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 50
XI. EFFECTIVE DATE
PG&E requests that the Commission accept the proposed amendment to the TO Tariff without hearing, modification, or condition effective Tuesday, February 16, 2027.
XII. CORRESPONDENCE AND COMMUNICATIONS
PG&E requests that all correspondence, pleadings, and other communications concerning this filing be served upon the following:
Tara Kaushik
John P. Perkins, III
William Brenc
Christopher Randall
Pacific Gas and Electric Company
Law Department, 19th Floor
300 Lakeside Drive, Suite 210
Oakland, CA 94612
Telephone: 925-359-5235
E-Mail: John.Perkins@pge.com
Amy Barr
Pacific Gas and Electric Company
Regulatory Relations
300 Lakeside Drive, Suite 210
Oakland, CA 94612
Telephone: 510-203-0187
E-Mail: Amy.Barr@pge.com
William M. Keyser
Jennifer Key
Kelsey Robinson
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC 20036
(202) 429-8186
wkeyser@steptoe.com
jkey@steptoe.com
krobinson@steptoe.com
XIII. ADDITIONAL INFORMATION REQUIRED BY REGULATION 35.13(b)
A. Contents of Filing
This filing consists of the following documents in addition to the Tariff Records:
• The instant Transmittal Letter;
• Clean Tariff Attachment;
• Marked Tariff Attachment;182182 The Marked Tariff Attachment does not include Section 10A and Appendix XI, which are entirely new.
PDF page 51
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 51
• Exhibit PGE-0001: Testimony of Nadim Virani; and
• Exhibit PGE-0002: Testimony of Jens Nedrud.
B. Service
Copies of this filing have been served upon the CPUC and the CAISO. Notice of this filing will be made and served via email to the official service list in the OSC Docket No. EL26- 71-000. In addition, this filing will be available on PG&E’s website at Wholesale Transmission Service | PG&E.183
C. Description of and Reason for Changes
A detailed description of the changes are included above.
D. Request for Waivers
The information submitted with this filing substantially complies with the requirements of Part 35 of the Commission’s rules and regulations applicable to filings of this type. To the extent necessary, PG&E requests waiver of the requirement to submit cost-of-service data required by 18 C.F.R. § 35.13. Further, PG&E requests waiver of any applicable requirement of Part 35 for which a waiver is not specifically requested, if necessary, to permit this filing to become effective as proposed.
XIV. CONCLUSION
PG&E requests that the Commission find the proposed changes to the TO Tariff detailed herein just and reasonable and that the changes address the issues raised in the OSC. PG&E requests that the Commission accept the proposed changes effective February 16, 2027, and requests that the Commission, through its acceptance of PG&E’s proposed tariff changes, terminate the show cause proceeding as to PG&E.
183 See https://www.pge.com/en/regulation/wholesale-transmission-service.html.
PDF page 52
Ms. Debbie-Anne A. Reese, SecretaryNovember 16, 2026Page 52
Sincerely,
/s/ John P. Perkins, III
Tara Kaushik
John P. Perkins, III
William Brenc
Christopher Randall
Pacific Gas and Electric Company
Law Department, 19th Floor
300 Lakeside Drive, Suite 210
Oakland, CA 94612
Telephone: 925-359-5235
E-Mail: John.Perkins@pge.com
William M. Keyser
Jennifer Key
Kelsey Robinson
Steptoe LLP
1330 Connecticut Avenue, NW
Washington, DC 20036
(202) 429-8186
wkeyser@steptoe.com
jkey@steptoe.com
krobinson@steptoe.com
November 16, 2026
PDF page 53
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused a copy of the foregoing document to be served upon all affected parties in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure and the additional parties listed below: NAME
ORGANIZATION/ADDRESS
E-MAIL ADDRESS
Christine J. Hammond
Assistant General
Counsel
California Public Utilities
Commission
505 Van Ness Avenue
San Francisco, CA 94102
Christine.hammond@cpuc.ca.gov
Anthony Ivancovich
Deputy General Counsel
California Independent System
Operator Corporation
250 Outcropping Way
Folsom, CA 95630
aivancovich@caiso.com
Energy Division
California Public Utilities
Commission
505 Van Ness Avenue
San Francisco, CA 94102
energydivisioncentralfiles@cpuc
.ca.gov
Dated at Oakland, California, this 16th day of November, 2026.