ER27-513-000 · 2026-11-16 · Pacific Gas and Electric Company

Exhibit No. PGE-0001 - Application Process Virani

Text extracted from the eLibrary original (SHA-256 8df1f54c932b56e1…). Download the original from the official source.

Contents · 26 sections
  1. I. Introduction p. 2
  2. A. My testimony addresses the same wholesale transmission customers referenced p. 3
  3. A. If a retail load, such as a Large Load End User, is situated in the CAISO p. 4
  4. A. There is no single entity “responsible for studying the provision of p. 5
  5. A. Yes. The new TCLL Interconnection process likely will trigger studies and p. 7
  6. A. PG&E has a process for providing Wholesale Load Interconnection service in p. 8
  7. II. Why Reform Is Needed to the TO Tariff Interconnection Process in Order p. 8
  8. A. Before discussing the specific aspects of the OSC that are relevant, I need to p. 8
  9. A. The OSC also noted that processes and studies with regard to the provision of p. 9
  10. A. Yes, the OSC asks whether there is need for a rolling application process, a p. 10
  11. III. PG&E’s Existing Wholesale Load Application Interconnection Process p. 10
  12. A. PG&E’s existing process for addressing new Wholesale Load Interconnection p. 10
  13. A. As noted above, Section 10.2 outlines the information required in what we p. 11
  14. A. The OSC reflects concerns over ongoing operational requirements for TCLLs. p. 11
  15. A. The Company proposes to retitle Section 10 of the TO Tariff as the “Wholesale p. 13
  16. IV. The TCLL Interconnection Application Process p. 13
  17. A. As I noted above, it is important to remember that a TCLL will not apply for a p. 13
  18. A. Yes, first I will discuss the Site Control attestation required from the TCLL’s p. 14
  19. A. This requirement is in response to the OSC itself (Paragraph 58), which p. 15
  20. A. The new application process allows a TCLL to request FILLI Interconnection p. 16
  21. A. Yes. The CAISO stakeholder documents and proposed tariff changes clearly p. 17
  22. A. Yes. The OSC asks whether a nonrefundable application fee and sufficient p. 18
  23. V. Application Review and Related Processes p. 19
  24. A. Under proposed Section 10A.2.4, PG&E will determine within ten (10) p. 19
  25. A. The next step in the process is the study process and my colleague, p. 20
  26. A. Yes, it does. p. 20

Read the parent filing

Topics in the text: Connecting load and generation · Retail and wholesale authority · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

ER27-XXX-000 EXHIBIT PGE-0001 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Pacific Gas and Electric Company Docket No.
Read this passage

I. Introduction

printed heading · Topic match: Connecting load and generation

My 7 business address is 300 Lakeside Drive, Oakland, California. 8 Q Please briefly describe your current responsibilities at PG&E. 9 A I manage the team responsible for processing load and generation 10 interconnection requests submitted through PG&E’s Wholesale Distribution 11 Tariff (“WDT”) and…
Read this passage

A. My testimony addresses the same wholesale transmission customers referenced

printed heading

Under 2 Order No. 888, a customer requests and reserves transmission service from a 3 transmission provider.
Read this passage

A. If a retail load, such as a Large Load End User, is situated in the CAISO

printed heading · Topic match: Connecting load and generation

If entities outside of the CAISO BAA seek Wholesale 10 Interconnection Service to serve Large Load End Users, those requests will be 11 addressed through the existing process under Section 10 in a similar manner.
Read this passage

A. There is no single entity “responsible for studying the provision of

printed heading · Topic match: Retail and wholesale authority

The difference will be that, in response to the OSC, 2 a retail service request from a Large Load will make a UDC or MSS become a 3 TCLL that must abide by a FERC process to then provide retail services 4 needed.
Read this passage

A. Yes. The new TCLL Interconnection process likely will trigger studies and

printed heading

The new TCLL Interconnection process likely will trigger studies and 11 analysis by both the Participating TO and CAISO that will ensure that the 12 transmission system can safely and reliably deliver energy to the Large Load 13 End User.
Read this passage

A. PG&E has a process for providing Wholesale Load Interconnection service in

printed heading · Topic match: Connecting load and generation

PG&E has a process for providing Wholesale Load Interconnection service in 4 its TO Tarff.
Read this passage

II. Why Reform Is Needed to the TO Tariff Interconnection Process in Order

printed heading

Why Reform Is Needed to the TO Tariff Interconnection Process in Order 16 to Implement the OSC 17 Q.
Read this passage

A. Before discussing the specific aspects of the OSC that are relevant, I need to

printed heading

Before discussing the specific aspects of the OSC that are relevant, I need to 20 discuss the OSC in broader terms.
Read this passage

A. The OSC also noted that processes and studies with regard to the provision of

printed heading

The OSC also noted that processes and studies with regard to the provision of 11 transmission service are not described clearly and specifically in the 12 CAISO/Participating TO tariffs or in a manner that will mitigate operational 13 risks, avoid disputes regarding how studies are conducted, deter…
Read this passage

A. Yes, the OSC asks whether there is need for a rolling application process, a

printed heading

Yes, the OSC asks whether there is need for a rolling application process, a 3 nonrefundable application fee, sufficient readiness requirements and/or other 4 means to deter duplicative or speculative requests and effectively imposes 5 requirements to submit data on substantially similar pending…
Read this passage

III. PG&E’s Existing Wholesale Load Application Interconnection Process

printed heading

PG&E’s Existing Wholesale Load Application Interconnection Process 9 Q.
Read this passage

A. PG&E’s existing process for addressing new Wholesale Load Interconnection

printed heading

PG&E’s existing process for addressing new Wholesale Load Interconnection 12 Requests is contained in Section 10 of the TO Tariff.
Read this passage

A. As noted above, Section 10.2 outlines the information required in what we

printed heading · Topic match: Connecting load and generation

As noted above, Section 10.2 outlines the information required in what we 7 propose to call a Wholesale Load Interconnection Application and provides 8 that the Company will determine whether a Wholesale Load Interconnection 9 Application is complete within ten (10) Business Days after receipt. 10…
Read this passage

A. The OSC reflects concerns over ongoing operational requirements for TCLLs.

printed heading

PG&E also intends to treat those customers similarly to 16 TCLLs, including how PG&E studies their Interconnection requests through 17 the new proposed Cluster Study Process for those requests meeting the 18 definition of Electrically Dependent Load. 19 Docket No.
Read this passage

A. The Company proposes to retitle Section 10 of the TO Tariff as the “Wholesale

printed heading

The Company proposes to retitle Section 10 of the TO Tariff as the “Wholesale 3 Load Interconnection Process” to clarify that it outlines the application, study, 4 and interconnection process for Wholesale Load Interconnections other than 5 TCLL Interconnections.
Read this passage

IV. The TCLL Interconnection Application Process

printed heading

The TCLL Interconnection Application Process 11 Q.
Read this passage

A. As I noted above, it is important to remember that a TCLL will not apply for a

printed heading · Topic match: Connecting load and generation

ER27-XXX-000 EXHIBIT PGE-0001 Page 13 of 20 the TCLL to attest to PG&E that the Large Load End User has Site Control. 1 Proposed Section 10A.2.1 establishes the informational requirements 2 for a TCLL Interconnection Application, which are designed to deter 3 duplicative or speculative requests for…
Read this passage

A. Yes, first I will discuss the Site Control attestation required from the TCLL’s

printed heading

ER27-XXX-000 EXHIBIT PGE-0001 Page 14 of 20 Section 10A.2.1, the TCLL must attest that its Large Load End User has Site 1 Control, which the TO Tariff defines as either (i) an option for a fifteen year or 2 longer lease, or an executed lease for a term of at least fifteen years, for real 3 property…
Read this passage

A. This requirement is in response to the OSC itself (Paragraph 58), which

printed heading · Topic match: Connecting load and generation

You mentioned that a customer must specify whether it is also seeking 1 Interim Standard Interconnection Service or FILLI Interconnection Service 2 in its TCLL Interconnection Application, why is that necessary? 3
Read this passage

A. The new application process allows a TCLL to request FILLI Interconnection

printed heading · Topic match: Connecting load and generation

The 12 proposed FILLI Interconnection Service is an as-available service, subject to 13 curtailment or interruption, which is available to TCLLs for Large Load End 14 Users, if the end user has the ability to reduce Load at a specified Point of 15 Withdrawal according to the timelines and protocols…
Read this passage

A. Yes. The CAISO stakeholder documents and proposed tariff changes clearly

printed heading

And, 6 in its September 24, 2026 Draft Final Proposal on Large Load Enhancements, 7 the CAISO “reiterate[d] that the Participating TOs will continue to govern and 8 study all load interconnection requests pursuant to their tariffs.”7 The TCLL 9 Interconnection process thus would be triggered if a…
Read this passage

A. Yes. The OSC asks whether a nonrefundable application fee and sufficient

printed heading

The OSC asks whether a nonrefundable application fee and sufficient 8 readiness requirements are needed to deter speculative or duplicative requests. 9 PG&E’s proposed fee structure under proposed Sections 10A.2.2 and 10A.2.3 10 answers that question in a manner that aligns with established…
Read this passage

V. Application Review and Related Processes

printed heading

After a TCLL submits an application, what is the next step in the application 9 process? 10
Read this passage

A. Under proposed Section 10A.2.4, PG&E will determine within ten (10)

printed heading

Under proposed Section 10A.2.4, PG&E will determine within ten (10) 11 Business Days of receipt whether the application is complete.
Read this passage

A. The next step in the process is the study process and my colleague,

printed heading

The next step in the process is the study process and my colleague, 2 Mr.
Read this passage

A. Yes, it does.

printed heading

Yes, it does. 5 Pacific Gas and Electric Company Docket No.
Read this passage