Robert L. Daileader
Senior Counsel
T / 202.585.8318
F / 866.947.3769
rdaileader@nixonpeabody.com
Attorneys at Law
nixonpeabody.com
@NixonPeabodyLLP
4923-9080-5463.1
Nixon Peabody LLP
799 9th Street NW
Suite 500
Washington, DC 20001-5327
November 16, 2026
E-TARIFF FILING
The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
RE:
SunZia Transmission, LLC
Docket No. ER27-___-000
Amendments to Transmission Owner Tariff in Compliance with the Docket
No. EL26-71-000 Order to Show Cause
Dear Secretary Reese:
Pursuant to Section 205 of the Federal Power Act1 and Part 35 of the rules and regulations2 of the Federal Energy Regulatory Commission (“Commission”), the Commission’s Order Granting Rescission and Abeyance Requests3 and the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act,4 SunZia Transmission, LLC (“SunZia Transmission”) hereby tenders for filing amendments to its Transmission Owner Transmission Tariff (“TO Tariff”)5 to incorporate changes to those provisions of the TO Tariff necessary to track changes being made simultaneously by the California Independent System Operator Corporation (“CAISO”) to its Open Access Transmission Tariff (the “CAISO Tariff”) to facilitate the fast and reliable interconnection of new large loads and co-located loads to the CAISO-managed transmission system. The revisions to the SunZia Transmission TO Tariff are submitted and designated in accordance with Order No. 7146 and the Commission’s e-Tariff filing requirements.
1 16 U.S.C. § 824d (2021).2 18 C.F.R. Part 35 (2026).3 California Independent System Operator Corporation, et al., 196 FERC ¶ 61,131 (issued August 14, 2026).4 California Independent System Operator Corporation, et al., 195 FERC ¶ 61,214 (issued June 18, 2026) (the “Order to Show Cause”).5 SunZia Transmission, LLC, FERC Electric Tariff Volume 2. 6 Electronic Tariff Filings, Order No. 714, III FERC Stats. & Regs., Regs. Preambles ¶ 31,276 (2008).
PDF page 2
The Honorable Debbie-Anne A. Reese
November 16, 2026
Page 2 of 7
4923-9080-5463.1
I. BACKGROUND
SunZia Transmission is an indirect, wholly-owned subsidiary of Pattern Energy Group LP and has developed, constructed and recently placed into commercial operation, an approximately 552-mile, bi-pole, high voltage, direct current (“HVDC”) 500 kV transmission line (the “Transmission System”) with a transmission capacity of 3,021 MW in New Mexico and Arizona that connects generation resources in the Southwest with markets and customers in California and Arizona.7 SunZia Transmission commenced construction of the Transmission System in 2023 and placed the Transmission System into commercial operations in April, 2026. The Transmission System has been developed as a merchant transmission project with negotiated rate authority contingent on the allocation of its transmission capacity pursuant to an open solicitation process reviewed and approved by the Commission.8
As a result, the entire capacity of the Transmission System is committed to two
Subscribers, SunZia Wind South LLC and SunZia Wind North LLC (collectively, the “SunZia Wind Companies”), both of which own and operate wind-powered electric generating facilities located in Lincoln, Torrance, and San Miguel Counties, New Mexico (the “SunZia Wind Projects”). SunZia Transmission will provide to the SunZia Wind Companies firm point-to- point transmission service for the entire rated capacity of the Transmission System over a thirty- year term9 from the Point of Receipt at the Pete Heinrich 345 kV AC Switchyard to the Point of Delivery at the Salt River Project Agricultural Improvement and Power District’s (“SRP”) Pinal Central 500 kV Substation pursuant to Amended and Restated Transmission Service Agreements
7 SunZia Transmission and the New Mexico Renewable Energy Transmission Authority (“RETA”) have entered into a lease arrangement pursuant to which RETA owns the physical assets of the Transmission System. SunZia Transmission and RETA are both responsible for the co-development of the Transmission System, while SunZia Transmission is responsible for the construction and financing of the Transmission System and is the owner of the capacity rights created by the Transmission System. RETA is a state authority established by the New Mexico legislature in 2007 and charged with implementing the New Mexico Renewable Energy Authority Transmission Act, NMSA 1978 § 62-16A-1, et seq. (the “Act”). As an authority or instrumentality of the State of New Mexico, RETA is not a “public utility” within the meaning of Section 201 of the FPA. See 16 U.S.C. § 824(f) (2019). Under the Act, RETA is authorized to plan, finance, develop and acquire transmission and storage projects (transmitting or storing at least 30% renewable energy) in order to promote the development of renewable energy in New Mexico. For purposes of this filing, SunZia Transmission is considered the Transmission Owner in interest of the Transmission System pursuant to the lease arrangement described above.8 Allocation of Capacity on New Merchant Transmission Projects and New Cost-Based, Participant-Funded Transmission Projects; Priority Rights to New Participant-Funded Transmission, 142 FERC ¶ 61,038, P 16 (2013), recon. den’d, 142 FERC ¶ 61,213 (2013). Capacity on the SunZia Transmission System has been allocated pursuant to two open solicitation processes both of which were filed with, reviewed and accepted by the Commission. See SunZia Transmission, LLC, 160 FERC ¶ 61,074 (2017); SunZia Transmission, LLC, 179 FERC ¶ 61,135 (2022).9 The initial thirty-year term commenced on July 30, 2026. Each of the SunZia Wind Companies has roll-over rights to continue service at the end of the initial term.
PDF page 3
The Honorable Debbie-Anne A. Reese
November 16, 2026
Page 3 of 7
4923-9080-5463.1
dated March 6, 2026 (the “TSAs”), both of which have been filed with and accepted for filing by the Commission.10
In addition, the SunZia Wind Companies have acquired 2,131 MW of long-term, firm point-to-point transmission service from the Pinal Central 500 kV Substation to the Palo Verde 500 kV Hub (which interconnects to the CAISO-controlled transmission system) through a number of transmission service agreements with SRP (1,500 MW), the Desert Southwest Region of the Western Area Power Administration (“WAPA”) (300 MW), and Tucson Electric Power Company (“TEP”) (331 MW) with initial terms ranging from five years to twenty years and, in each case with the SunZia Wind Companies having roll-over rights thereafter (collectively, the “Arizona Entitlements”).11 SunZia Transmission has obtained authorization from the SunZia Wind Companies to administer the Arizona Entitlements (subject at all times to each SunZia Wind Company’s right to use the Arizona Entitlements for the transmission of electricity to the Palo Verde Hub for the benefit of the SunZia Wind Projects) and to grant CAISO operational control of the Arizona Entitlements consistent with the Transmission Rights and Curtailment Instructions that will be provided by SunZia Transmission consistent with applicable terms and conditions of the WAPA, SRP and TEP tariffs and business practices.
On September 22, 2023, in Docket No. ER23-2917-000, the CAISO filed proposed revisions to the CAISO Open Access Transmission Tariff (the “CAISO Tariff”) to implement a Subscriber Participating Transmission Owner (“SPTO”) model to facilitate access by merchant and participant-funded projects located outside of California to the CAISO transmission system, furthering State and Federal goals of increasing access to out-of-state carbon-free generating resources. The Commission accepted the CAISO’s proposed tariff changes by order issued March 12, 2024.12 On January 14, 2024, SunZia Transmission applied to become an SPTO and, on May 23, 2024, the CAISO Board of Governors approved the SunZia Transmission application. As a result, when the Transmission System entered commercial operation in April 9, 2026, operational control of the Transmission System and the Arizona Entitlements was granted by SunZia Transmission to CAISO pursuant to the CAISO’s Transmission Control Agreement at which time the SunZia Transmission Open Access Transmission Tariff (“OATT”) was withdrawn.13 As a result, the CAISO Tariff now governs future transmission and interconnection service over the Transmission System (subject to the rights and obligations of
10 SunZia Transmission, LLC, Docket Nos. ER25-1636-000 and ER25-1637-000 (April 28, 2026) (unpublished letter order).11 The SunZia Wind Companies have the right under the transmission tariffs of WAPA, SRP and TEP to request a change in the Point of Delivery and/or Point of Receipt on either a firm or non-firm basis so that the transmission service is redirectable consistent with the terms of the tariffs and business practices of the three Arizona transmission providers. 12 California Independent System Operator Corporation, 186 FERC ¶ 61,177 (2024).13 SunZia Transmission, LLC, Docket No. ER26-2115-000 (June 4, 2026) (unpublished letter order). The SunZia Transmission OATT was filed on June 15, 2023 in Docket No. ER23-2146-000 and accepted for filing by the Commission by order issued October 20, 2023. SunZia Transmission, LLC, 185 FERC ¶ 61,052 (2023). As discussed in note 14 infra, the SunZia Transmission OATT was subsequently modified to address SunZia Transmission’s transition to SPTO status under the CAISO Tariff.
PDF page 4
The Honorable Debbie-Anne A. Reese
November 16, 2026
Page 4 of 7
4923-9080-5463.1
SunZia Transmission to the SunZia Wind Companies, the customers that are funding the construction of the Transmission System through their obligation to make transmission capacity payments under the TSAs).14
On October 21, 2024, SunZia Transmission filed with the Commission its proposed TO
Tariff pursuant to which its transmission facilities and contractual entitlements would be placed under the operational control of CAISO and made available to provide transmission and interconnection service under the CAISO Tariff. By order issued April 17, 2025, the Commission accepted SunZia Transmission’s TO Tariff for filing, to become effective on the date on which operational control of the transmission facilities and contractual entitlements of SunZia Transmission is granted to CAISO.15 The Commission found that the rates, terms and conditions of the proposed TO Tariff had been shown to be just and reasonable with one exception – the rate design used to calculate the Non-Subscriber Usage Rates set forth in the TO Tariff. On that issue, the Commission found that the filing raised issues of material fact that cannot be resolved based on the record before the Commission.1614 During SunZia Transmission’s transition to SPTO status, SunZia Transmission and CAISO entered into an Applicant Participating Transmission Owner Agreement (the “APTOA”) pursuant to which the parties agreed that the CAISO Tariff govern requests for interconnection with and transmission service over the Transmission System. The APTOA was filed by CAISO with the Commission on July 5, 2024 in Docket No. ER24-2471- 000 and was accepted for filing by the Commission on September 3, 2024, and made effective on September 4, 2024. California Independent System Operator Corporation, 188 FERC ¶ 61,151 (2024). On July 8, 2024, in Docket No. ER24-2473-000, SunZia Transmission filed revisions to its OATT to amend Sections 17 and 18 to notify current and prospective customers that, upon the effective date of the APTOA, all requests for transmission or interconnection service on the Transmission System will be processed by CAISO in accordance with the CAISO Tariff. The SunZia Transmission OATT revisions were accepted for filing by the Commission on September 4, 2024, and to align with the APTOA, was made effective as of September 4, 2024. SunZia Transmission, LLC, Docket No. ER24-2473-000 (Sept. 4, 2024) (unpublished letter order).15 SunZia Transmission, LLC, Order Accepting and Suspending Proposed Tariff Revisions, Subject to Refund and Establishing Hearing and Settlement Judge Procedures,191 FERC ¶ 61,053 (2025) (the “April 17 Order”).16 April 17 Order at PP 54-55. SunZia Transmission and the active participants in the proceeding thereafter reached an uncontested settlement on the NSUR rate design issue as well as additional NSUR issues that resulted in the filing on August 18, 2025 of an Offer of Settlement and Settlement Agreement with the Commission that was supported by the Trial Staff (see Docket No. ER25-170-000, Initial Comments by Trial Staff Supporting Offer of Settlement and Settlement Agreement (Sept. 8, 2025)) and certified by the Settlement Judge (see SunZia Transmission, LLC, 193 FERC ¶ 61,003, Certification of Uncontested Offer of Settlement (Oct. 3, 2025)). The Commission approved the Offer of Settlement and Settlement Agreement by order issued January 26, 2026. SunZia Transmission, LLC, 194 FERC ¶ 61,069 (2026). Following the filing of the Offer of Settlement and Settlement Agreement and prior to Commission approval, the Commission granted the request for rehearing filed by three of the active participants and reversed its prior finding in the April 17 Order that the structuring of the NSUR based on the Commission-accepted Subscriber transmission rates is just and reasonable. SunZia Transmission, LLC, 193 FERC ¶ 61,176 (2025), reh’g req. dism’d, 194 FERC ¶ 61,140 (2026), appeal pending, SunZia Transmission, LLC v. Federal Energy Regulatory Commission, Case No. 26- 1067 (D.C. Cir.). Settlement negotiations on that issue among the active participants in the proceeding remain on-going.
PDF page 5
The Honorable Debbie-Anne A. Reese
November 16, 2026
Page 5 of 7
4923-9080-5463.1
SunZia Transmission is in a unique position with respect to its compliance with the Commission’s directives in the Order to Show Cause for several reasons. First, SunZia Transmission does not directly serve load and, accordingly, there are no provisions in its TO Tariff that address the interconnection of the load to the SunZia Transmission System. As a result, the SunZia Transmission TO Tariff is silent with respect to load interconnections and there is no need to modify the Tariff to address the interconnection of large or co-located loads. Second, the SunZia Transmission System is not located within the service territory of a load serving participating transmission owner within the CAISO market that is subject to the Order to Show Cause and that will be submitting tariff changes in response to the Order to Show Cause. The SunZia Transmission System is embedded within the service territories of Arizona and New Mexico load-serving entities that are not subject to the Order to Show Cause or any of the other Orders to Show Cause issued to regional transmission operators or independent system operators throughout the country. Finally, Section 8 of the SunZia Transmission TO Tariff states that all requests for interconnection to the SunZia Transmission System must be directed in the first instance to CAISO with notice of such request being provided to SunZia Transmission. Thus, CAISO is responsible for managing the generator interconnection process for the SunZia Transmission System with SunZia Transmission supporting that process through the undertaking of studies on the impact of the interconnection on the System. Any changes to the generation interconnection process to facilitate the interconnection of co-located load to the transmission system must be set forth in the CAISO Tariff, in which case SunZia Transmission will propose conforming changes to its TO Tariff to remain consistent with the CAISO’s changes.
II. DESCRIPTION OF FILING
Consistent with the description above as to SunZia Transmission’s unique and limited role in the interconnection process overall, Section 8 of the TO Tariff has been amended to clarify that the CAISO Tariff will continue to control with respect to the interconnection of Generating Units, energy storage co-located with Large Load and Co-located Generating Units with Large Loads. In proposing these limited changes to its TO Tariff, SunZia Transmission reserves the right, following review of the proposed tariff changes filed by the other Participating Transmission Owners (“PTOs”) that are subject to the Commission’s Order to Show Cause, to amend this filing to propose additional changes to ensure consistency among all similarly- situated PTOs.
Finally, consistent with its comments made during the stakeholder process, SunZia Transmission continues to support the need to apply these enhanced Large Load interconnection procedures to Electrically Proximate Loads. CAISO has explained that the need for such changes within the CAISO footprint in California will be addressed following the submission of the Large Load compliance filing. SunZia Transmission supports the commencement of that effort as soon as possible because the value proposition and the question surrounding how to study the interconnection of electrically proximate large load and generation in tandem (similar to co-located load and generation) are unique when applied to the SunZia Transmission System in New Mexico and Arizona.
PDF page 6
The Honorable Debbie-Anne A. Reese
November 16, 2026
Page 6 of 7
4923-9080-5463.1
III. ATTACHMENTS TO FILING
Included in this filing are the following documents:
1. This Transmittal Letter;
2. Clean version of the revised SunZia Transmission TO Tariff; and
3. Marked version of the revised SunZia Transmission TO Tariff, showing
changes against the currently-effective SunZia Transmission TO Tariff.17
IV. PROPOSED EFFECTIVE DATE
SunZia Transmission proposes an effective date of sixty days after the Commission issues an order on this compliance filing for the changes to its TO Tariff. A period of sixty days after the Commission approves this filing will allow enough time for SunZia Transmission to seamlessly transition to the new processes. Because a precise effective date is not known at this time, SunZia Transmission is submitting this filing with a 12/31/9998 effective date for the tariff records, and, if necessary, will make a compliance filing to apply the actual effective date once known.
V. COMMUNICATIONS
Correspondence and service regarding this filing should be sent to the following individual:
Robert L. Daileader
Nixon Peabody LLP
799 Ninth Street, Suite 500
Washington, DC 20001
(202) 288-2069
rdaileader@nixonpeabody.com
Cameron Yourkowski
Director, Regulatory Affairs & Markets
SunZia Transmission, LLC
1088 Sansome Street
San Francisco, CA 94111
(503) 432-0982
cameron.yourkowski@patternenergy.com
VI. CONCLUSION
In accordance with the foregoing, SunZia Transmission respectfully requests that the Commission accept the proposed revisions to its TO Tariff as just and reasonable and consistent with its obligations under the Order to Show Cause and grant an effective date of sixty days after the Commission’s order on this filing.
17 On April 10, 2026, SunZia Transmission filed in Docket No. ER25-170-005 a revised TO Tariff with the Commission with an April 9, 2026 effective date (the date on which operational control of the SunZia Transmission System was granted to CAISO) and incorporating the changes to the TO Tariff accepted by the Commission when it approved the Offer of Settlement on January 26, 2026. SunZia Transmission, LLC, 194 FERC ¶ 61,069 (2026). See note 16 supra.
PDF page 7
The Honorable Debbie-Anne A. Reese
November 16, 2026
Page 7 of 7
4923-9080-5463.1
Please direct any questions regarding this filing to the undersigned counsel. Respectfully submitted,
/S/ Robert L. Daileader
Robert L. Daileader
Counsel to SunZia Transmission LLC
Attachments
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 1
Issued by: ______________
Issued on: ______________
Effective ___________
SUNZIA TRANSMISSION, LLC
FERC ELECTRIC TRANSMISSION OWNER TARIFF
PDF page 10
TABLE OF CONTENTS
1. Preamble …
2. Effective Date … 2.1
Termination …
3. TO Definitions … 3.1
Arizona Entitlements … 3.2
Completed Application Date … 3.3
Completed Interconnection Application … 3.4
Direct Assignment Facilities … 3.5
Project Proponent … 3.6
Subscriber … 3.7
Subscriber Encumbrances … 3.8
Subscriber Rights … 3.9
Subscription Agreement … 3.10
SunZia Transmission … 3.11
SunZia Transmission System …
4. Eligibility …
5. Non-Subscriber Usage Rate, Subscriber Cost Recovery and Transmission Rates …
5.1
Non-Subscriber Usage Rate … 5.2
Subscriber Cost Recovery … 5.3
Transmission Rate Recovery … 5.4
Transmission Rates for Subscriber Service …
6. Ancillary Services - Applicability and Charges …
7. Billing and Payment …
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades
8.1
Participating TO Obligation to Interconnect …
9. Expansion Process for SunZia Transmission System and Arizona Entitlements …
9.1
Expansion Process …
10. Interconnection Process for SunZia Transmission’s Arizona Entitlements … 10.1
Interconnection Process … 10.2
Applicability …
11. Uncontrollable Forces and Indemnification … 11.1
Procedures to Follow if Uncontrollable Force Occurs … 11.2
Indemnification … 11.3
Open Access …
PDF page 11
12. Regulatory Filings …
13. Miscellaneous … 13.1
Notices … 13.2
Waiver … 13.3
Confidentiality … 13.4
TO Tariff Supersedes Existing Tariffs … 13.5
Titles … 13.6
Severability … 13.7
Preservation of Obligations … 13.8
Governing Law … 13.9
Appendices Incorporated … 13.10
Consistency with CAISO Tariff … 13.11
Disputes … 13.12
Conflicting Dispatch and Operating Instructions .................................................................. APPENDIX I
APPENDIX II
PDF page 12
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 1
Effective ______________
1. Preamble. The terms and conditions pursuant to which the Regional Transmission Facilities and Arizona Entitlements of SunZia Transmission, LLC (“SunZia Transmission”) placed under the CAISO’s Operational Control, including certain terms and conditions relating to transmission expansion of and interconnection with SunZia Transmission’s Regional Transmission Facilities and Arizona Entitlements placed under the CAISO’s Operational Control, are set forth in this TO Tariff and the CAISO Tariff. SunZia Transmission offers long-term transmission service to subscribers at negotiated rates and offers other transmission service as provided in this TO Tariff, the Transmission Control Agreement (“TCA”) and the CAISO Tariff, as applicable. For purposes of this TO Tariff and the TCA, SunZia Transmission is a Non-Load-Service Participating TO and has no End-Use Customers.
1.1
Transmission Service for Long-Term Subscribers. Long-term transmission service over the Regional Transmission System for one or more years is provided by SunZia Transmission following an open solicitation pursuant to FERC’s Policy Statement, Allocation of Capacity on New Merchant Transmission Projects and New Cost-based, Participant-Funded Transmission, 142 FERC ¶ 61,038 (2013). FERC accepted the results of the two open solicitations in SunZia Transmission, LLC, Docket No. ER17- 388-000, 160 FERC ¶ 61,074 (2017) and SunZia Transmission, LLC, Docket No. ER22- 1208-000, 179 FERC ¶ 61,135 (2022).
1.1.1
Subscriber Encumbrance. Transmission capacity reserved for Subscriber
Service shall be treated as a Subscriber Encumbrance under the TCA.
1.2
Other Transmission Service. Transmission service, other than Subscriber Service, over the Regional Transmission System and the Arizona Entitlements is provided under the CAISO TCA. The applicable Non-Subscriber Usage Rate shall be paid to the CAISO pursuant to the CAISO Tariff.
2. Effective Date. This TO Tariff is effective on the date on which SunZia Transmission becomes a Participating TO under the CAISO Tariff and shall continue to be effective so long as SunZia Transmission is a party to the TCA.
2.1
Termination. This TO Tariff may be terminated by SunZia Transmission upon such advance notice consistent with the TCA and with such authorization as FERC may require.
3. TO Definitions. Certain capitalized terms used in this TO Tariff that are set out immediately below shall have the meanings set out immediately below. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the CAISO Tariff as it may be amended from time to time.
3.1
Arizona Entitlements. As used in this TO Tariff, the term Arizona Entitlements shall have the meaning set forth for the term “Entitlements” in the CAISO Tariff and shall include Subscriber’s transmission capacity rights under (i) the three Service Agreements Nos. 24- DSR-13271, 24-DSR-13272 and 24-DSR-13273 for firm point-to-point transmission service, each dated as of December 13, 2023, and each by and among the Desert Southwest Region of the Western Area Power Administration (“WAPA”) and Subscriber; (ii) (a) the two Service Agreement Nos. 479 and 480 in the aggregate for 193 MW of firm point-to- point transmission service, each dated as of April 23, 2021, and each by and between Tucson Electric Power Company (“TEP”) and Subscriber (as assignee of Pattern New Mexico Wind LLC (“PNMW”) pursuant to Service Agreement No. 542 for the Transfer
PDF page 13
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 2
Effective ______________
of Firm Point-to-Point Transmission Service dated January 19, 2024, by and among TEP, PNMW, and Subscriber, as accepted for filing by FERC in Docket No. ER24-1023-000 on March 19, 2024), and (b) the three Service Agreement Nos. 499, 500, and 501 in the aggregate for 138 MW of firm point-to-point transmission service, each dated as of April 7, 2022, and each by and between TEP and Subscriber as assignee of PNMW pursuant to Service Agreement No. 542 described in clause (ii)(a), and (c) the fourteen Service Agreements in the aggregate for 1500 MW firm point-to-point transmission service, each dated as of December 1, 2022, for Transmission Service Request Nos. 94729356, 94729365, 94729400, 94729420, 94729424, 94729431, 94729441, 94729444, 94729447, 94729525, 94729528, 94729532, 94729533 and 94729535, and each by and between the Salt River Project Agricultural Improvement and Power District (“SRP”) and Subscriber (as successor-in-interest to PNMW pursuant to the Agreement for the Transfer of Service Agreements dated December 12, 2023, by and among PNMW, Subscriber, and SRP (collectively, the “Arizona Transmission Rights,” as provided under items (i), (ii), and (iii) above, collectively, the “Arizona TSAs”), of which Operational Control is conveyed to SunZia Transmission pursuant to the AZEA.
The utilization of Arizona Entitlements shall, at all times, be subject to and consistent with the terms and conditions set forth in the respective Open Access Transmission Tariffs and associated business practices of SRP, TEP and WAPA. Nothing in this TO Tariff expands the rights of Subscriber, or a Non-Subscriber, in the Arizona Entitlements beyond that provided in the Arizona TSAs and applicable Open Access Transmission Tariffs or business practices of SRP, TEP or WAPA.
The CAISO will administer Operational Control of the Arizona Entitlements consistent with the Transmission Rights and Curtailment Instructions provided by SunZia Transmission, which SunZia Transmission will ensure are in compliance with the terms and conditions set forth in the Arizona TSAs and applicable Open Access Transmission Tariffs or business practices of SRP, TEP or WAPA.
3.2
Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed Interconnection Application. 3.3
Completed Interconnection Application. An application that satisfies all of the information and other requirements of the CAISO Tariff and this TO Tariff, including any required deposit
3.4
Direct Assignment Facilities. Facilities or portions of facilities that are constructed by the Participating TO for the sole use or benefit of a particular party requesting Interconnection under this TO Tariff. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs service to such party.
3.5
Project Proponent. A Market Participant or group of Market Participants that:
(i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition and upgrade, and thus is not a Project Sponsor; and
(iii) initiates proceedings under the CAISO ADR Procedures to determine the need for the proposed transmission addition or upgrade.
3.6
Regional Transmission Facilities. For purposes of this TO Tariff, the Regional Transmission Facilities shall be the SunZia Transmission System.
PDF page 14
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 3
Effective ______________
3.7
Subscriber. As used herein, the term Subscriber shall have the meaning set forth in the CAISO Tariff and shall include SunZia Wind PowerCo LLC (“SunZia PowerCo”) on behalf of SunZia Wind North LLC and SunZia Wind South LLC. In the event that SunZia PowerCo assigns its rights and obligations under one or more of the Subscriber Encumbrances or Arizona Entitlements to SunZia Wind North LLC and/or SunZia Wind South LLC or SunZia Wind North LLC and/or SunZia Wind South LLC assign such rights and obligations to one or more other assignees, such assignees shall be the Subscriber for purposes of this TO Tariff with respect to such assigned Subscriber Encumbrance or Entitlement, as applicable.
3.8
Subscriber Encumbrances. As used in this TO Tariff, the term Subscriber Encumbrances shall have the meaning set forth in the CAISO Tariff and shall include SunZia Transmission’s obligations to the Subscriber as set forth in the (i) Amended and Restated Transmission Service Agreement dated September 1, 2023, between SunZia Transmission and Subscriber, as accepted by FERC in SunZia Transmission, LLC, Docket No. ER23- 2765-000 (unpublished letter order issued October 25, 2023), and as amended, restated, or supplemented from time to time, (the “TSA”), and (ii) the Arizona Entitlements Agreement dated July 5, 2024, between SunZia Transmission and Subscriber (“AZEA”), and as amended, restated, or supplemented from time to time, which conveys to SunZia Transmission Operational Control of the Arizona Entitlements but subject to Subscriber’s priority rights to use the Arizona Entitlements and in compliance with the Arizona TSAs. 3.9
Subscriber Rights. For purposes of this TO Tariff, the term Subscriber Rights as used herein shall have the meaning set forth in the CAISO Tariff and shall include the rights and obligations of SunZia Transmission to Subscriber under the TSA and AZEA. 3.10
Subscriber Service. The term Subscriber Service shall have the meaning ascribed to it under Section 4 herein.
3.11
Subscription Agreement. For purposes of this TO Tariff, the term Subscription Agreement as used herein shall have the meaning set forth in the CAISO Tariff and shall include the (i) TSA and (ii) AZEA.
3.12
SunZia Transmission. SunZia Transmission is the Participating TO under this TO Tariff. 3.13
SunZia Transmission System. The SunZia Transmission System is an approximately 552-mile, bi-pole, high voltage direct current transmission line in New Mexico and Arizona with a nominal transmission capacity of 3,021 MW (“SunZia Transmission System”). The SunZia Transmission System consists of a 345 kV alternating current switching station in New Mexico referred to as the Pete Heinrich Switching Station along with voltage source converter stations at a nominal direct current voltage of ±525 kV with 2156 kcmil “Bluebird” conductors arranged in a three-conductor bundle for each of the two (2) pole conductors traversing the approximately 552-mile transmission line length. Additionally, the transmission towers include dedicated metallic return conductors insulated at 85 kV which are electrically bundled as two (2) 1590 kcmil “Lapwing” conductors but geographically separated on the towers (i.e., split bundle). The SunZia Transmission System includes two (2), 1,500 MW dynamic braking resistors in New Mexico and two ~0.75-mile 500kV AC transmission lines to connect the SunZia Transmission System to the Pinal Central substation in Pinal County, Arizona.
PDF page 15
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 4
Effective ______________
4. Eligibility. Long-term firm transmission service over SunZia Transmission’s Regional Transmission Facilities placed under the CAISO’s Operational Control is provided by SunZia Transmission to Subscriber pursuant to the TSA. Long-term transmission service over the Arizona Entitlements is provided by WAPA, TEP and SRP to Subscriber under the Arizona TSAs of which operational control is conveyed to SunZia Transmission pursuant to the AZEA. The services to Subscriber over the Regional Transmission Facilities and the Arizona Entitlements shall be the “Subscriber Service”. Transmission capacity reserved for Subscriber Service shall constitute a Subscriber Encumbrance under the TCA. Transmission service other than Subscriber Service shall be provided only to Eligible Customers pursuant to the TCA and the CAISO Tariff.
5. Non-Subscriber Usage Rate, Subscriber Cost Recovery and Transmission Rates. 5.1
Non-Subscriber Usage Rate. To the extent that the Regional Transmission Facilities or Arizona Entitlements are used by a Non-Subscriber to provide transmission service under the CAISO Tariff, the Non-Subscriber shall pay to the CAISO a Non-Subscriber Usage Fee ($/MWh) in accordance with Appendix I.
5.2
Subscriber Cost Recovery. The Subscriber has the right to recover lost production tax credits and/or lost investment tax credits as interconnection-related outage costs and SunZia Transmission has the right to recover lost transmission revenue as interconnection- related outage costs with respect to the SunZia Transmission System, in both cases, as accepted by the FERC in SunZia Transmission, LLC, Order Accepting Tariff, Docket No. ER23-2146-001, 185 FERC ¶ 61,052 PP 25-26 (issued October 20, 2023).
5.3
Transmission Rate Recovery. SunZia Transmission is entitled to all rights, including rate recovery, associated with the SunZia Transmission System.
5.4
Transmission Rates for Subscriber Service. The rates for Subscriber Service are paid outside of the CAISO settlement systems.
6. Ancillary Services - Applicability and Charges. If any Ancillary Services are required, SunZia Transmission will not provide such services directly to the transmission customer and the transmission customer will be required to meet any such requirement in accordance with the CAISO Tariff.
7. Billing and Payment.
7.1
The CAISO, in accordance with the CAISO Tariff, shall pay the Participating TO, among other things, all applicable Non-Subscriber Usage Payments, including applicable Wheeling Revenues in accordance with the CAISO Tariff.
7.2
If, subsequent to the initial build of the SunZia Transmission System, SunZia Transmission is ordered by the CAISO to construct, own and operate additional transmission facilities, then the CAISO in accordance with the CAISO Tariff, shall pay SunZia Transmission, among other things, all applicable FERC-approved Transmission Revenue Requirement in connection with the expansion of the SunZia Transmission System consistent with Section 24 of the CAISO Tariff.
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades. All requests for interconnection with the SunZia Transmission System should be directed to the CAISO with notice of such request provided to SunZia Transmission. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of
PDF page 16
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 5
Effective ______________
Section 210(a) of the Federal Power Act. Expansion of and/or interconnection to the SunZia Transmission System presently placed under the CAISO’s Operational Control by SunZia Transmission by Generating Units, energy storage co-located with Large Loads and Co-located Generating Units with Large Loads shall be governed by the CAISO Tariff. The Arizona Transmission Rights placed under the Operational Control of CAISO by SunZia Transmission are Arizona Entitlements that require the approval of the owners of those transmission facilities for interconnection and SunZia Transmission does not have the legal authority to compel expansion or interconnection to those facilities. SunZia Transmission’s obligation to expand and/or interconnect the SunZia Transmission System to load and/or to facilities providing wholesale transmission service shall be determined in accordance with all applicable FERC and/or Local Regulatory Authority requirements.
8.1
Participating TO Obligation to Interconnect. This Section 8.1, 9.1, and 10.1, and their subparts, are provided for consistency with the TO Tariffs of other PTOs and for potential future application should SunZia Transmission acquire transmission facilities or acquire additional legal authority in its existing facilities that would provide SunZia Transmission sufficient legal authority to implement those Sections. Sections 8.1, 9, and 10 and their subparts have no current application to the Arizona Entitlements turned over to CAISO’s Operational Control by SunZia Transmission, which are covered solely by Section 8(exclusive of Section 8.1 and its subparts) as to expansions and interconnections. 8.1.1
Interconnection to Transmission System. Interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations and CAISO reliability criteria for the CAISO Controlled Grid. The Participating TO will not accommodate the Interconnection if doing so would impair system reliability or would otherwise adversely affect the ability of the Participating TO to honor its Encumbrances existing as of the time a party submits its Interconnection Application. The Participating TO shall identify any such adverse effect on its Encumbrances in the Interconnection Study. To the extent the Participating TO determines that the Interconnection will have an adverse effect on Encumbrances, the party requesting Interconnection shall mitigate such adverse effect.
8.1.2
Costs Associated with Interconnection. Each party requesting Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities and, if applicable, any Reliability Upgrades required to provide the requested Interconnection, except as provided in Appendix DD of the CAISO Tariff, and any interconnection-related outage costs as accepted by FERC in Docket No. ER23-2146-001, SunZia Transmission, LLC, Order
Accepting Tariff, 185 FERC ¶ 61,052 PP 25-26 (Oct. 20, 2023). In addition, such party shall implement all existing operating procedures necessary to safely and reliably interconnect such party’s facilities to the facilities of the Participating TO and to ensure the CAISO Controlled Grid’s conformance with the CAISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with accommodating the
Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the CAISO Tariff for transmission expansions or upgrades or, for the expansion and/or interconnection of the SunZia Transmission System to provide service to load and/or to facilities providing wholesale transmission service, in accordance with all applicable FERC and/or Local Regulatory Authority requirements.
PDF page 17
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 6
Effective ______________
8.1.3
Interconnection Agreement. Pursuant to Section 13 of Appendix DD of the CAISO Tariff, the Participating TO will tender to such party an Interconnection Agreement. The Interconnection Agreement will include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, any Delivery Upgrades, if applicable, and for any other mitigation measures consistent with the CAISO Tariff. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs consistent with the CAISO Tariff. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed Interconnection Application shall be deemed withdrawn. To maintain its queue position, the applicant must timely comply with the interconnection requirements of Appendix DD of the CAISO Tariff and Sections 8.1 and 10.1 and its subparts of this TO Tariff.
8.1.4
Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Network Upgrades that it is obligated to construct pursuant to this TO Tariff and, as applicable, Section 24 and Appendix DD of the CAISO Tariff. The Participating TO’s obligation to build will be subject to: (i) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (ii) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the CAISO Tariff or applicable FERC precedent; and (iii) a signed Interconnection Agreement or a signed Engineering and Procurement Agreement or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection Agreement. 8.1.5
Energization. The Participating TO shall not be obligated to energize, nor shall the applicant or wholesale load be entitled to have its Interconnection to the CAISO Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3, and becomes effective and such applicant or wholesale load has demonstrated to the CAISO’s reasonable satisfaction that it has complied with all of the requirements of the CAISO Tariff and the requirements of this TO Tariff.
8.1.6
Coordination with CAISO on Interconnection Requests. The Participating TO shall coordinate with the CAISO, pursuant to the provisions of the TCA and CAISO Tariff.
8.1.7
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations of Section 24 of the CAISO Tariff and this TO Tariff.
8.1.8
Obligation to Construct. A Participating TO shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.1.3.1 hereof have been satisfied.
PDF page 18
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 7
Effective ______________
8.1.9
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the CAISO (including the CAISO’s ADR Procedures), WECC, or the RTG coordinated
planning processes as to the need for or construction of a facility, the need for full cost recovery, and the allocation of costs.
9. Expansion Process for SunZia Transmission System and Arizona Entitlements. The expansion process related to the SunZia Transmission System where SunZia Transmission is the lead Participating TO with respect to a required system expansion is set forth in Section 9.1 of this TO Tariff. The Expansion process for SunZia Transmission’s Arizona Entitlements to the Arizona Transmission Rights, which it has turned over to the Operational Control of the CAISO, is as stated in Section 8 above. Section 9 and its subparts shall not currently apply to those Arizona Entitlements.
9.1
Expansion Process. Unless SunZia Transmission is the lead Participating TO with respect to a required system expansion, the provisions of Section 9.1 of this TO Tariff, and its subparts, shall have no application to Regional Transmission Facilities, Local Transmission Facilities, or the Arizona Entitlements turned over to the CAISO’s Operational Control by SunZia Transmission. With respect to the expansion of the transmission facilities by one or more of the transmission owners providing the Arizona Transmission Rights, the corresponding provisions of the open access transmission tariff of such transmission owner shall govern.
9.1.1
Determination of Facilities. A Participating TO shall perform a study in accordance with this Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 and Appendix DD of the CAISO Tariff and this TO Tariff; (2) a Market Participant agrees to pay the costs of the study and provides an Interconnection Request consistent with the requirements of Appendix DD of the CAISO Tariff
9.1.2
Payment of Study Cost
9.1.2.1 Interconnection Customer to Pay for Interconnection Study. Where an Interconnection Study and the need for the transmission addition or
upgrade has not yet been established in accordance with the procedures
established herein and the CAISO Tariff, the Interconnection Customer
shall pay the cost of the Study consistent with the CAISO Tariff.
9.1.2.2 Project Sponsor or Project Proponent to Pay for Interconnection Study. Where the facilities to be added or upgraded have been determined to be needed in accordance with the procedures established herein and the CAISO Tariff, the Project Sponsor, Project Proponent, or the CAISO
requesting the study shall pay in advance the reasonable cost of the
Interconnection Study.
9.1.2.3 Principal Beneficiaries to Pay for Interconnection Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the CAISO or through the CAISO ADR Procedures in accordance with the CAISO Tariff, the
Project Sponsor and the identified principal beneficiaries shall pay the reasonable cost of the Interconnection Study, in such proportions as may
PDF page 19
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 8
Effective ______________
be agreed, or, failing agreement, as determined in accordance with the CAISO ADR Procedures.
9.1.2.4 Payment Procedure. Where an Interconnection Study is being conducted pursuant to this TO Tariff, the Participating TO shall, within thirty days of receipt of all reasonably required information, tender to the Interconnection Customer, Project Sponsor, Project Proponent, CAISO, or identified principal beneficiaries, as the case may be, an Interconnection Study agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Interconnection Customer, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Interconnection Study. If the Interconnection Customer, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Interconnection Study agreement, they shall execute the Interconnection Study agreement and return it to the Participating TO within ten Business Days. Alternatively, if the Interconnection Customer, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Interconnection Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the CAISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Interconnection Study, and the parties shall submit the disputed terms for resolution under the CAISO’s ADR Procedures.
9.1.2.5 Interconnection Study Procedures. Where an Interconnection Study is being conducted pursuant to the CAISO Tariff, the terms and conditions for such studies shall be in accordance with the CAISO Tariff, including Appendix DD.
9.1.3
Obligation to Build.
9.1.3.1 Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the CAISO Tariff and this TO Tariff.
9.1.3.2 Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify the CAISO with regard to facilities determined to be needed. The Participating TO shall also notify the Project Sponsor, Parties to the Generator Interconnection Agreement and the CAISO as the case may be. In such circumstances, the Participating TO shall, within thirty days of notifying such Project Sponsor, Parties to the Interconnection Agreement, and the CAISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Generator Interconnection Agreement, and the CAISO to discuss the
PDF page 20
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 9
Effective ______________
circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Interconnection Agreement, and the CAISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives.
9.1.3.2.1
Alternatives to the Original Facility Additions. If the
review process of Section 9.1.3.2 determines that one or more alternatives exist to the originally planned construction project, the Participating TO shall present such alternatives for
consideration to the Project Sponsor, Parties to the Generator Interconnection Agreement, and the CAISO, as the case may be. In the event the Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Interconnection Agreement or the CAISO disagree, the dispute shall be resolved pursuant to the CAISO ADR Procedures.
9.1.3.2.2
Refund Obligation for Unfinished Facility Additions.
If the Participating TO and the Project Sponsor, the CAISO, or Parties to the Generator Interconnection Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Section 35.19(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.
9.1.4
Provisions Relating To Transmission Construction On the Systems Of Other TOs.
9.1.4.1 Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any engineering, permitting, and construction of any necessary transmission or distribution facilities additions on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO shall undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice.
9.1.4.2 Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the CAISO Tariff require additions or upgrades on other systems, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the CAISO, and the Project Sponsor, as the case may be, may defer construction if the new
PDF page 21
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 10
Effective ______________
transmission facilities on another system cannot be completed in a timely
manner. The Participating TO shall notify such Project Sponsor, Parties to the Generator Interconnection Agreement, and the CAISO, in writing of
the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or resume construction of the new facilities. Such Project Sponsor, Parties to the Participation
Agreement, or the CAISO may challenge the decision in accordance with
the CAISO ADR Procedures.
10. Interconnection Process for SunZia Transmission’s Arizona Entitlements. The interconnection process for SunZia Transmission’s Arizona Entitlements in the Arizona Transmission Rights, which it has turned over to CAISO Operational Control, is as stated in Section 8 above. Section 10, and its subparts, do not currently apply to those Arizona Entitlements.
10.1
Interconnection Process. Unless SunZia Transmission is the lead Participating TO with respect to a requested interconnection, the provisions of Section 10 of this TO Tariff, and its subparts, shall have no application to the Regional Transmission Facilities, Local Transmission Facilities, or Arizona Entitlements turned over to the CAISO’s Operational Control by SunZia Transmission and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern. All requests for interconnection with the Regional Transmission Facilities, Local Transmission Facilities, or Arizona Entitlements turned over to the CAISO’s Operational Control by SunZia Transmission shall be directed to the lead Participating TO, with notice of the request provided to SunZia Transmission. 10.2
Applicability. All requests for Interconnection directly to the CAISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the CAISO Tariff.
11. Uncontrollable Forces and Indemnification.
11.1
Procedures to Follow if Uncontrollable Force Occurs. In the event of the occurrence of an Uncontrollable Force which prevents a Party from performing any of its obligations under this TO Tariff, such Party shall (i) immediately notify the other Parties in writing of the occurrence of such Uncontrollable Force, (ii) not be entitled to suspend performance in any greater scope or longer duration than is required by the Uncontrollable Force, (iii) use its best efforts to mitigate the effects of such Uncontrollable Force, remedy its inability to perform, and resume full performance hereunder, (iv) keep the other Parties apprised of such efforts on a continual basis and (v) provide written notice of the resumption of performance hereunder. Notwithstanding any of the foregoing, the settlement of any strike, lockout, or labor dispute constituting an Uncontrollable Force shall be within the sole discretion of the Party to this TO Tariff involved in such strike, lockout, or labor dispute and the requirement that a Party must use its best efforts to remedy the cause of the Uncontrollable Force and mitigate its effects and resume full performance hereunder shall not apply to strikes, lockouts, or labor disputes. No Party will be considered in default as to any obligation under this TO Tariff if prevented from fulfilling the obligation due to the occurrence of an Uncontrollable Force.
11.2
Indemnification. A Market Participant shall at all times indemnify, defend, and save the Participating TO harmless from any and all damages, losses, claims, (including claims and actions relating to injury or to death of any person or damage to property), demands, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to
PDF page 22
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 11
Effective ______________
third parties, arising out of or resulting from the Participating TO’s performance of its obligations under this TO Tariff on behalf of a Market Participant, except in cases of negligence or intentional wrongdoing by the Participating TO.
11.3
Open Access. For purposes of the Stranded Cost Recovery available under Order Nos. 888 and 888-A, this Tariff, combined with the CAISO Tariff and wholesale distribution access tariff, if any, shall be considered an open access tariff under FERC Order Nos. 888 and 888-A.
12. Regulatory Filings. Nothing contained herein shall be construed as affecting, in any way, the right of SunZia Transmission to unilaterally make application to FERC as it deems necessary and appropriate to revise its Non-Subscriber Usage Rate, or for a change in its terms and conditions, including changes in rate methodology, or for a change in designation of the Arizona Entitlements to be placed under the CAISO’s Operational Control, pursuant to the applicable FERC rules, regulations, policies, and governing statutes.
13. Miscellaneous.
13.1
Notices. Any notices, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person, (ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return email, or (iv) upon delivery if delivered by prepaid commercial courier service, in each case addressed to a Party at the address set forth in Appendix III. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix II to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.
13.2
Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver. 13.3
Confidentiality.
13.3.1 Maintaining Confidentiality if Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the documents, data, and information provided to it by any other Party that such Party may designate as confidential, provided, however, that the information will not be held confidential by the receiving Party if (1) the designating Party is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory
requirements, or (2) the information becomes available to the public on a non- confidential basis (other than from the receiving Party).
13.3.2 Disclosure of Confidential Information. Notwithstanding anything in this Section 13.3.2 to the contrary, if any Party is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to
PDF page 23
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 12
Effective ______________
this Section 13.3.2, the Party may disclose such information; provided, however, that as soon as such Party learns of the disclosure requirement and prior to making such disclosure, such Party shall notify the affected Party or Parties of the requirement and the terms thereof The affected Party or Parties may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Party shall cooperate with such affected Party or Parties to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Party shall cooperate with the affected Parties to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure.
13.4
TO Tariff Supersedes Existing Tariffs. Upon the filing of this TO Tariff at FERC and FERC’s acceptance of such TO Tariff for filing and FERC’s acceptance of the withdrawal of SunZia Transmission’s open access transmission tariff as accepted by FERC in Docket No. ER23-2146-001, SunZia Transmission, LLC, Order Accepting Tariff, 185 FERC ¶ 61,052 (Oct. 20, 2023), this TO Tariff, together with the CAISO Tariff and wholesale distribution access tariff if any, supersedes any pre-existing open access transmission tariff of the Participating TO.
13.5
Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.
13.6
Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.
13.7
Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of each Party shall be preserved until satisfied.
13.8
Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.
13.9
Appendices Incorporated. The appendices to this TO Tariff are attached to this TO Tariff and are incorporated by reference as if fully set forth herein.
13.10
Consistency with CAISO Tariff. This TO Tariff, with the exception of Section 5.2, is intended to be consistent with the CAISO Tariff, and, if necessary, shall be amended to conform with any changes authorized or required in any final order in a FERC proceeding mandating such changes in the CAISO Tariff. If a Market Participant identifies a conflict
PDF page 24
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 13
Effective ______________
between the TO Tariff and the CAISO Tariff other than Section 5.2 of this TO Tariff, the Participating TO and the Market Participant shall make good-faith efforts to resolve the conflict. If the Parties are unable to informally resolve that conflict, the Parties may use the CAISO ADR Procedures to resolve it as set forth in Section 13.11 of this Tariff. 13.11
Disputes. Except as limited by law, the CAISO ADR Procedures shall apply to all disputes between parties which arise under this TO Tariff. The CAISO ADR Procedures set forth in Section 13 of the CAISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.
13.12
Conflicting Dispatch and Operating Instructions. In the event a Market Participant receives conflicting dispatch or operating instructions from the CAISO and one or more Participating TO(s), if human safety would not knowingly be neither jeopardized nor electric facilities subject to damage while the Market Participant seeks to reconcile the conflict with the appropriate CAISO and Participating TO employees before acting, the Market Participant should attempt a reconciliation. Otherwise, the Market Participant shall adhere to the CAISO Tariff Section 4.2 and follow the CAISO’s instructions. In no event shall a Market Participant be required to follow dispatch or operating instructions from the CAISO if following those instructions would knowingly jeopardize human safety.
PDF page 25
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 1
Effective ______________
APPENDIX I
Non-Subscriber Usage Rates
The Generation COD Date shall occur on the commercial operation date of the last generating unit of the SunZia Transmission Subscriber that is interconnected to the SunZia Transmission System which generating unit is entitled to schedule energy delivery over the SunZia Transmission System using Subscriber Rights.
Non-Subscriber Usage Rate for the SunZia Transmission System Only (Pete Heinrich to Pinal Central) – As of the Grant of Operational Control to CAISO:
For the period commencing on the grant of operational control of the SunZia Transmission System to CAISO and the subsequent two-year period following the Generation COD Date and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for both import and export transactions over the SunZia Transmission System shall be set at $0.00 per MWh. For the one-year period beginning on the second anniversary of the Generation COD Date and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for both import and export transactions over the SunZia Transmission System shall be set at $2.0775 per kW/month (which increases annually by one-half of one percent (0.5%) commencing on the date on which operational control of the SunZia Transmission System is granted to CAISO) converted to an annual rate (i.e., multiplying by twelve) and then divided by 8,760 hours to derive an hourly off-peak rate for use of the SunZia Transmission System by Non-Subscribers. Commencing on the third anniversary of the Generation COD Date and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for both import and export transactions over the SunZia Transmission System shall be the current monthly point-to-point transmission rate charged by SunZia Transmission for use of the SunZia Transmission System by Subscribers in the TSA, as amended, supplemented, or restated from time to time and as accepted by the Commission (which increases annually by one-half of one percent (0.5%) commencing on the date on which operational control of the SunZia Transmission System is granted to CAISO), converted to an annual rate (i.e., multiplying by twelve) and then divided by 8,760 hours to derive an hourly off-peak rate for use of the SunZia Transmission System by Non- Subscribers. In no event shall the Non-Subscriber Usage Rate for the use of the SunZia Transmission System exceed the applicable CAISO Regional Access Charge in effect at the time service is provided to the Non-Subscriber.
Non-Subscriber Usage Rate for the Arizona Transmission Rights Only (Pinal Central to Palo Verde) – As of the Grant of Operational Control to CAISO:
For the period commencing on the grant of operational control of the Arizona Entitlements to CAISO and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for the Arizona Transmission Rights shall be the weighted average (weighted by the amount of firm point-to-point transmission service held as an Arizona Entitlement by SunZia Transmission) of the current firm, monthly point-to-point transmission rates of WAPA, SRP and TEP, as shown on the Open Access Same-Time Information System (“OASIS”) of each transmission provider, converted to an annual rate (i.e., multiplying by twelve) and then divided by 8,760 hours to derive an hourly off-peak rate for use of the Arizona Transmission Rights by Non-Subscribers plus the actual Schedule 1 and 2 charges imposed by WAPA, SRP and TEP. In no event shall the Non-Subscriber Usage Rate for the Arizona Transmission Rights exceed the applicable CAISO Regional Access Charge in effect at the time service is provided to the Non-Subscriber.
PDF page 26
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 2
Effective ______________
Non-Subscriber Usage Rate for Combined Segments of SunZia Transmission System and Arizona Transmission Rights (Pete Heinrich to Palo Verde) – As of the Grant of Operational Control to CAISO:
The Non-Subscriber Usage Rate for the combined segments of the SunZia Transmission System and the Arizona Transmission Rights shall be the sum of the Non-Subscriber Usage Rates for each respective segment, as defined above, but such Non-Subscriber Usage Rate shall not exceed the applicable CAISO Regional Access Charge in effect at the time service is provided to the Non- Subscriber.
The currently-effective components used in the calculation of the Non-Subscriber Usage Rates as such components change from time to time will be publicly posted on CAISO’s website.
PDF page 27
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 1First Revised Sheet No. 1
Effective ______________
APPENDIX II
NOTICES
Designated Representative:
Deral Danis
Vice President, Transmission
200 South Wacker, Suite 1650
Chicago, IL 60606
Tel. No. (312) 259-9989
Email Address: deral.danis@patternenergy.com Alternate Representative:
General Counsel
Pattern Energy Group LP
1088 Sansome Street
San Francisco, CA 94111
Email Address: generalcounsel@patternenergy.com
PDF page 28
4889-6591-0000.2
Attachment 2
SuZia Transmission, LLC
Black-line of Revised Transmission Owner Tariff Showing Changes from As-Filed Transmission Owner Tariff
PDF page 29
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 1SUNZIA TRANSMISSION, LLC
FERC ELECTRIC TRANSMISSION OWNER TARIFF
Issued by: ______________
Issued on: ______________
Effective ___________
PDF page 30
TABLE OF CONTENTS
1. Preamble …
2. Effective Date … 2.1
Termination …
3. TO Definitions … 3.1
Arizona Entitlements … 3.2
Completed Application Date … 3.3
Completed Interconnection Application … 3.4
Direct Assignment Facilities … 3.5
Project Proponent … 3.6
Subscriber … 3.7
Subscriber Encumbrances … 3.8
Subscriber Rights … 3.9
Subscription Agreement … 3.10
SunZia Transmission … 3.11
SunZia Transmission System …
4. Eligibility …
5. Non-Subscriber Usage Rate, Subscriber Cost Recovery and Transmission Rates …
5.1
Non-Subscriber Usage Rate … 5.2
Subscriber Cost Recovery … 5.3
Transmission Rate Recovery … 5.4
Transmission Rates for Subscriber Service …
6. Ancillary Services - Applicability and Charges …
7. Billing and Payment …
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades
8.1
Participating TO Obligation to Interconnect …
9. Expansion Process for SunZia Transmission System and Arizona Entitlements …
9.1
Expansion Process …
10. Interconnection Process for SunZia Transmission’s Arizona Entitlements … 10.1
Interconnection Process … 10.2
Applicability …
11. Uncontrollable Forces and Indemnification … 11.1
Procedures to Follow if Uncontrollable Force Occurs … 11.2
Indemnification … 11.3
Open Access …
PDF page 31
12. Regulatory Filings …
13. Miscellaneous … 13.1
Notices … 13.2
Waiver … 13.3
Confidentiality … 13.4
TO Tariff Supersedes Existing Tariffs … 13.5
Titles … 13.6
Severability … 13.7
Preservation of Obligations … 13.8
Governing Law … 13.9
Appendices Incorporated … 13.10
Consistency with CAISO Tariff … 13.11
Disputes … 13.12
Conflicting Dispatch and Operating Instructions .................................................................. APPENDIX I
APPENDIX II
PDF page 32
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 1
1. Preamble. The terms and conditions pursuant to which the Regional Transmission Facilities and Arizona Entitlements of SunZia Transmission, LLC (“SunZia Transmission”) placed under the CAISO’s Operational Control, including certain terms and conditions relating to transmission expansion of and interconnection with SunZia Transmission’s Regional Transmission Facilities and Arizona Entitlements placed under the CAISO’s Operational Control, are set forth in this TO Tariff and the CAISO Tariff. SunZia Transmission offers long-term transmission service to subscribers at negotiated rates and offers other transmission service as provided in this TO Tariff, the Transmission Control Agreement (“TCA”) and the CAISO Tariff, as applicable. For purposes of this TO Tariff and the TCA, SunZia Transmission is a Non-Load-Service Participating TO and has no End-Use Customers.
1.1
Transmission Service for Long-Term Subscribers. Long-term transmission service over the Regional Transmission System for one or more years is provided by SunZia Transmission following an open solicitation pursuant to FERC’s Policy Statement, Allocation of Capacity on New Merchant Transmission Projects and New Cost-based, Participant-Funded Transmission, 142 FERC ¶ 61,038 (2013). FERC accepted the results of the two open solicitations in SunZia Transmission, LLC, Docket No. ER17-388-000, 160 FERC ¶ 61,074 (2017) and SunZia Transmission, LLC, Docket No. ER22-1208-000, 179 FERC ¶ 61,135 (2022).
1.1.1
Subscriber Encumbrance. Transmission capacity reserved for Subscriber
Service shall be treated as a Subscriber Encumbrance under the TCA.
1.2
Other Transmission Service. Transmission service, other than Subscriber Service, over the Regional Transmission System and the Arizona Entitlements is provided under the CAISO TCA. The applicable Non-Subscriber Usage Rate shall be paid to the CAISO pursuant to the CAISO Tariff.
2. Effective Date. This TO Tariff is effective on the date on which SunZia Transmission becomes a Participating TO under the CAISO Tariff and shall continue to be effective so long as SunZia Transmission is a party to the TCA.
2.1
Termination. This TO Tariff may be terminated by SunZia Transmission upon such advance notice consistent with the TCA and with such authorization as FERC may require.
3. TO Definitions. Certain capitalized terms used in this TO Tariff that are set out immediately below shall have the meanings set out immediately below. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the CAISO Tariff as it may be amended from time to time.
3.1
Arizona Entitlements. As used in this TO Tariff, the term Arizona Entitlements shall have the meaning set forth for the term “Entitlements” in the CAISO Tariff and shall include Subscriber’s transmission capacity rights under (i) the three Service Agreements Nos. 24-DSR-13271, 24-DSR-13272 and 24-DSR-13273 for firm point-to-point
transmission service, each dated as of December 13, 2023, and each by and among the Desert Southwest Region of the Western Area Power Administration (“WAPA”) and Subscriber; (ii) (a) the two Service Agreement Nos. 479 and 480 in the aggregate for 193 MW of firm point-to-point transmission service, each dated as of April 23, 2021, and each by and between Tucson Electric Power Company (“TEP”) and Subscriber (as Effective ______________
PDF page 33
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 2
assignee of Pattern New Mexico Wind LLC (“PNMW”) pursuant to Service Agreement No. 542 for the Transfer of Firm Point-to-Point Transmission Service dated January 19, 2024, by and among TEP, PNMW, and Subscriber, as accepted for filing by FERC in Docket No. ER24-1023-000 on March 19, 2024), and (b) the three Service Agreement Nos. 499, 500, and 501 in the aggregate for 138 MW of firm point-to-point transmission service, each dated as of April 7, 2022, and each by and between TEP and Subscriber as assignee of PNMW pursuant to Service Agreement No. 542 described in clause (ii)(a), and (c) the fourteen Service Agreements in the aggregate for 1500 MW firm point-to-point transmission service, each dated as of December 1, 2022, for Transmission Service Request Nos. 94729356, 94729365, 94729400, 94729420, 94729424, 94729431, 94729441, 94729444, 94729447, 94729525, 94729528, 94729532, 94729533 and 94729535, and each by and between the Salt River Project Agricultural Improvement and Power District (“SRP”) and Subscriber (as successor-in-interest to PNMW pursuant to the Agreement for the Transfer of Service Agreements dated December 12, 2023, by and among PNMW, Subscriber, and SRP (collectively, the “Arizona Transmission Rights,” as provided under items (i), (ii), and (iii) above, collectively, the “Arizona TSAs”), of which Operational Control is conveyed to SunZia Transmission pursuant to the AZEA. The utilization of Arizona Entitlements shall, at all times, be subject to and consistent with the terms and conditions set forth in the respective Open Access Transmission Tariffs and associated business practices of SRP, TEP and WAPA. Nothing in this TO Tariff expands the rights of Subscriber, or a Non-Subscriber, in the Arizona Entitlements beyond that provided in the Arizona TSAs and applicable Open Access Transmission Tariffs or business practices of SRP, TEP or WAPA.
The CAISO will administer Operational Control of the Arizona Entitlements consistent with the Transmission Rights and Curtailment Instructions provided by SunZia Transmission, which SunZia Transmission will ensure are in compliance with the terms and conditions set forth in the Arizona TSAs and applicable Open Access Transmission Tariffs or business practices of SRP, TEP or WAPA.
3.2
Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed Interconnection Application. 3.3
Completed Interconnection Application. An application that satisfies all of the information and other requirements of the CAISO Tariff and this TO Tariff, including any required deposit
3.4
Direct Assignment Facilities. Facilities or portions of facilities that are constructed by the Participating TO for the sole use or benefit of a particular party requesting Interconnection under this TO Tariff. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs service to such party.
3.5
Project Proponent. A Market Participant or group of Market Participants that:
(i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition and upgrade, and thus is not a Project Sponsor; and
(iii) initiates proceedings under the CAISO ADR Procedures to determine the need for the proposed transmission addition or upgrade.
Effective ______________
PDF page 34
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 3
3.6
Regional Transmission Facilities. For purposes of this TO Tariff, the Regional Transmission Facilities shall be the SunZia Transmission System.
3.7
Subscriber. As used herein, the term Subscriber shall have the meaning set forth in the CAISO Tariff and shall include SunZia Wind PowerCo LLC (“SunZia PowerCo”) on behalf of SunZia Wind North LLC and SunZia Wind South LLC. In the event that SunZia PowerCo assigns its rights and obligations under one or more of the Subscriber Encumbrances or Arizona Entitlements to SunZia Wind North LLC and/or SunZia Wind South LLC or SunZia Wind North LLC and/or SunZia Wind South LLC assign such rights and obligations to one or more other assignees, such assignees shall be the Subscriber for purposes of this TO Tariff with respect to such assigned Subscriber Encumbrance or Entitlement, as applicable.
3.8
Subscriber Encumbrances. As used in this TO Tariff, the term Subscriber Encumbrances shall have the meaning set forth in the CAISO Tariff and shall include SunZia Transmission’s obligations to the Subscriber as set forth in the (i) Amended and Restated Transmission Service Agreement dated September 1, 2023, between SunZia Transmission and Subscriber, as accepted by FERC in SunZia Transmission, LLC, Docket No. ER23-2765-000 (unpublished letter order issued October 25, 2023), and as amended, restated, or supplemented from time to time, (the “TSA”), and (ii) the Arizona Entitlements Agreement dated July 5, 2024, between SunZia Transmission and Subscriber (“AZEA”), and as amended, restated, or supplemented from time to time, which conveys to SunZia Transmission Operational Control of the Arizona Entitlements but subject to Subscriber’s priority rights to use the Arizona Entitlements and in compliance with the Arizona TSAs.
3.9
Subscriber Rights. For purposes of this TO Tariff, the term Subscriber Rights as used herein shall have the meaning set forth in the CAISO Tariff and shall include the rights and obligations of SunZia Transmission to Subscriber under the TSA and AZEA. 3.10
Subscriber Service. The term Subscriber Service shall have the meaning ascribed to it under Section 4 herein.
3.11
Subscription Agreement.
For purposes of this TO Tariff, the term Subscription
Agreement as used herein shall have the meaning set forth in the CAISO Tariff and shall include the (i) TSA and (ii) AZEA.
3.12
SunZia Transmission.
SunZia Transmission is the Participating TO under this TO
Tariff.
3.13
SunZia Transmission System. The SunZia Transmission System is an approximately 552-mile, bi-pole, high voltage direct current transmission line in New Mexico and Arizona with a nominal transmission capacity of 3,021 MW (“SunZia Transmission System”). The SunZia Transmission System consists of a 345 kV alternating current switching station in New Mexico referred to as the Pete Heinrich Switching Station along with voltage source converter stations at a nominal direct current voltage of ±525 kV with 2156 kcmil “Bluebird” conductors arranged in a three-conductor bundle for each of the two (2) pole conductors traversing the approximately 552-mile transmission line length. Additionally, the transmission towers include dedicated metallic return conductors insulated at 85 kV which are electrically bundled as two (2) 1590 kcmil “Lapwing” conductors but geographically separated on the towers (i.e., split bundle). Effective ______________
PDF page 35
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 4
The SunZia Transmission System includes two (2), 1,500 MW dynamic braking resistors in New Mexico and two ~0.75-mile 500kV AC transmission lines to connect the SunZia Transmission System to the Pinal Central substation in Pinal County, Arizona.
4. Eligibility. Long-term firm transmission service over SunZia Transmission’s Regional Transmission Facilities placed under the CAISO’s Operational Control is provided by SunZia Transmission to Subscriber pursuant to the TSA. Long-term transmission service over the Arizona Entitlements is provided by WAPA, TEP and SRP to Subscriber under the Arizona TSAs of which operational control is conveyed to SunZia Transmission pursuant to the AZEA. The services to Subscriber over the Regional Transmission Facilities and the Arizona Entitlements shall be the “Subscriber Service”. Transmission capacity reserved for Subscriber Service shall constitute a Subscriber Encumbrance under the TCA. Transmission service other than Subscriber Service shall be provided only to Eligible Customers pursuant to the TCA and the CAISO Tariff.
5. Non-Subscriber Usage Rate, Subscriber Cost Recovery and Transmission Rates. 5.1
Non-Subscriber Usage Rate. To the extent that the Regional Transmission Facilities or Arizona Entitlements are used by a Non-Subscriber to provide transmission service under the CAISO Tariff, the Non-Subscriber shall pay to the CAISO a Non-Subscriber Usage Fee ($/MWh) in accordance with Appendix I.
5.2
Subscriber Cost Recovery. The Subscriber has the right to recover lost production tax credits and/or lost investment tax credits as interconnection-related outage costs and SunZia Transmission has the right to recover lost transmission revenue as interconnection-related outage costs with respect to the SunZia Transmission System, in both cases, as accepted by the FERC in SunZia Transmission, LLC, Order Accepting Tariff, Docket No. ER23-2146-001, 185 FERC ¶ 61,052 PP 25-26 (issued October 20, 2023).
5.3
Transmission Rate Recovery. SunZia Transmission is entitled to all rights, including rate recovery, associated with the SunZia Transmission System.
5.4
Transmission Rates for Subscriber Service. The rates for Subscriber Service are paid outside of the CAISO settlement systems.
6. Ancillary Services - Applicability and Charges. If any Ancillary Services are required, SunZia Transmission will not provide such services directly to the transmission customer and the transmission customer will be required to meet any such requirement in accordance with the CAISO Tariff.
7. Billing and Payment.
7.1
The CAISO, in accordance with the CAISO Tariff, shall pay the Participating TO, among other things, all applicable Non-Subscriber Usage Payments, including applicable Wheeling Revenues in accordance with the CAISO Tariff.
7.2
If, subsequent to the initial build of the SunZia Transmission System, SunZia Transmission is ordered by the CAISO to construct, own and operate additional transmission facilities, then the CAISO in accordance with the CAISO Tariff, shall pay SunZia Transmission, among other things, all applicable FERC-approved Transmission Revenue Requirement in Effective ______________
PDF page 36
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 5
connection with the expansion of the SunZia Transmission System consistent with Section 24 of the CAISO Tariff.
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades. All requests for interconnection with the SunZia Transmission System should be directed to the CAISO with notice of such request provided to SunZia Transmission. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the Federal Power Act. Expansion of and/or interconnection to the SunZia Transmission System presently placed under the CAISO’s Operational Control by SunZia Transmission by Generating Units, energy storage co-located with Large Loads and Co-located Generating Units with Large Loads shall be governed by the CAISO Tariff. The Arizona Transmission Rights placed under the Operational Control of CAISO by SunZia Transmission are Arizona Entitlements that require the approval of the owners of those transmission facilities for interconnection and SunZia Transmission does not have the legal authority to compel expansion or interconnection to those facilities. SunZia Transmission’s obligation to expand and/or interconnect the SunZia Transmission System to load and/or to facilities providing wholesale transmission service shall be determined in accordance with all applicable FERC and/or Local Regulatory Authority requirements.
8.1
Participating TO Obligation to Interconnect. This Section 8.1, 9.1, and 10.1, and their subparts, are provided for consistency with the TO Tariffs of other PTOs and for potential future application should SunZia Transmission acquire transmission facilities or acquire additional legal authority in its existing facilities that would provide SunZia Transmission sufficient legal authority to implement those Sections. Sections 8.1, 9, and 10 and their subparts have no current application to the Arizona Entitlements turned over to CAISO’s Operational Control by SunZia Transmission, which are covered solely by Section 8(exclusive of Section 8.1 and its subparts) as to expansions and interconnections.
8.1.1
Interconnection to Transmission System. Interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations and CAISO reliability criteria for the CAISO Controlled Grid. The Participating TO will not accommodate the
Interconnection if doing so would impair system reliability or would otherwise adversely affect the ability of the Participating TO to honor its Encumbrances existing as of the time a party submits its Interconnection Application. The Participating TO shall identify any such adverse effect on its Encumbrances in the Interconnection Study. To the extent the Participating TO determines that the Interconnection will have an adverse effect on Encumbrances, the party requesting Interconnection shall mitigate such adverse effect.
8.1.2
Costs Associated with Interconnection. Each party requesting Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities and, if applicable, any Reliability Upgrades required to provide the requested Interconnection, except as provided in Appendix DD of the CAISO Tariff, and any interconnection-related outage costs as accepted by FERC in Docket No. ER23-2146-001, SunZia Transmission,
LLC, Order Accepting Tariff, 185 FERC ¶ 61,052 PP 25-26 (Oct. 20, 2023). In addition, such party shall implement all existing operating procedures necessary to safely and reliably interconnect such party’s facilities to the facilities of the Participating TO and to ensure the CAISO Controlled Grid’s conformance with Effective ______________
PDF page 37
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 6
the CAISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the CAISO Tariff for transmission expansions or upgrades or, for the expansion and/or interconnection of the SunZia Transmission System to provide service to load and/or to facilities providing wholesale transmission service, in accordance with all applicable FERC and/or Local Regulatory Authority requirements.
8.1.3
Interconnection Agreement. Pursuant to Section 13 of Appendix DD of the CAISO Tariff, the Participating TO will tender to such party an Interconnection Agreement. The Interconnection Agreement will include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, any Delivery Upgrades, if applicable, and for any other mitigation measures consistent with the CAISO Tariff. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs consistent with the CAISO Tariff. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed Interconnection Application shall be deemed withdrawn. To maintain its queue position, the applicant must timely comply with the interconnection requirements of Appendix DD of the CAISO Tariff and Sections 8.1 and 10.1 and its subparts of this TO Tariff.
8.1.4
Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Network Upgrades that it is obligated to construct pursuant to this TO Tariff and, as applicable, Section 24 and Appendix DD of the CAISO Tariff. The Participating TO’s obligation to build will be subject to: (i) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (ii) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the CAISO Tariff or applicable FERC precedent; and (iii) a signed Interconnection Agreement or a signed Engineering and Procurement Agreement or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection Agreement.
8.1.5
Energization. The Participating TO shall not be obligated to energize, nor shall the applicant or wholesale load be entitled to have its Interconnection to the CAISO Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3, and becomes effective and such applicant or wholesale load has demonstrated to the CAISO’s reasonable satisfaction that it has complied with all of the requirements of the CAISO Tariff and the requirements of this TO Tariff.
8.1.6
Coordination with CAISO on Interconnection Requests. The Participating TO shall coordinate with the CAISO, pursuant to the provisions of the TCA and CAISO Tariff.
Effective ______________
PDF page 38
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 7
8.1.7
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations of Section 24 of the CAISO Tariff and this TO Tariff. 8.1.8
Obligation to Construct. A Participating TO shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.1.3.1 hereof have been satisfied.
8.1.9
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the CAISO (including the CAISO’s ADR Procedures), WECC, or the RTG
coordinated planning processes as to the need for or construction of a facility, the need for full cost recovery, and the allocation of costs.
9. Expansion Process for SunZia Transmission System and Arizona Entitlements. The expansion process related to the SunZia Transmission System where SunZia Transmission is the lead Participating TO with respect to a required system expansion is set forth in Section 9.1 of this TO Tariff. The Expansion process for SunZia Transmission’s Arizona Entitlements to the Arizona Transmission Rights, which it has turned over to the Operational Control of the CAISO, is as stated in Section 8 above. Section 9 and its subparts shall not currently apply to those Arizona Entitlements.
9.1
Expansion Process. Unless SunZia Transmission is the lead Participating TO with respect to a required system expansion, the provisions of Section 9.1 of this TO Tariff, and its subparts, shall have no application to Regional Transmission Facilities, Local Transmission Facilities, or the Arizona Entitlements turned over to the CAISO’s Operational Control by SunZia Transmission. With respect to the expansion of the transmission facilities by one or more of the transmission owners providing the Arizona Transmission Rights, the corresponding provisions of the open access transmission tariff of such transmission owner shall govern.
9.1.1
Determination of Facilities. A Participating TO shall perform a study in accordance with this Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 and Appendix DD of the CAISO Tariff and this TO Tariff; (2) a Market Participant agrees to pay the costs of the study and provides an Interconnection Request consistent with the requirements of Appendix DD of the CAISO Tariff
9.1.2
Payment of Study Cost
9.1.2.1 Interconnection Customer to Pay for Interconnection Study. Where an Interconnection Study and the need for the transmission addition or upgrade has not yet been established in accordance with the procedures established herein and the CAISO Tariff, the Interconnection Customer shall pay the cost of the Study consistent with the CAISO Tariff. 9.1.2.2 Project Sponsor or Project Proponent to Pay for Interconnection Study. Where the facilities to be added or upgraded have been
determined to be needed in accordance with the procedures established Effective ______________
PDF page 39
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 8
herein and the CAISO Tariff, the Project Sponsor, Project Proponent, or the CAISO requesting the study shall pay in advance the reasonable cost of the Interconnection Study.
9.1.2.3 Principal Beneficiaries to Pay for Interconnection Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the CAISO or through the CAISO ADR Procedures in accordance with the CAISO Tariff, the Project Sponsor and the identified principal beneficiaries shall pay the reasonable cost of the Interconnection Study, in such proportions as may be agreed, or, failing agreement, as determined in accordance with the CAISO ADR Procedures.
9.1.2.4 Payment Procedure. Where an Interconnection Study is being conducted pursuant to this TO Tariff, the Participating TO shall, within thirty days of receipt of all reasonably required information, tender to the Interconnection Customer, Project Sponsor, Project Proponent, CAISO, or identified principal beneficiaries, as the case may be, an Interconnection Study agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Interconnection Customer, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Interconnection Study. If the Interconnection Customer, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Interconnection Study agreement, they shall execute the Interconnection Study agreement and return it to the Participating TO within ten Business Days. Alternatively, if the Interconnection Customer, Project Sponsor, Project Proponent, the CAISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Interconnection Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the CAISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Interconnection Study, and the parties shall submit the disputed terms for resolution under the CAISO’s ADR Procedures.
9.1.2.5 Interconnection Study Procedures. Where an Interconnection Study is being conducted pursuant to the CAISO Tariff, the terms and conditions for such studies shall be in accordance with the CAISO Tariff, including Appendix DD.
9.1.3
Obligation to Build.
9.1.3.1 Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to Effective ______________
PDF page 40
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 9
its transmission system that it is obligated to construct pursuant to the CAISO Tariff and this TO Tariff.
9.1.3.2 Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify the CAISO with regard to facilities determined to be needed. The Participating TO shall also notify the Project Sponsor, Parties to the Generator Interconnection Agreement and the CAISO as the case may be. In such circumstances, the Participating TO shall, within thirty days of notifying such Project Sponsor, Parties to the Interconnection Agreement, and the CAISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Generator Interconnection Agreement, and the CAISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Interconnection Agreement, and the CAISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives. 9.1.3.2.1
Alternatives to the Original Facility Additions. If the
review process of Section 9.1.3.2 determines that one or more alternatives exist to the originally planned construction project, the Participating TO shall present such alternatives for
consideration to the Project Sponsor, Parties to the Generator Interconnection Agreement, and the CAISO, as the case may be. In the event the Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Interconnection Agreement or the CAISO disagree, the dispute shall be resolved pursuant to the CAISO ADR Procedures.
9.1.3.2.2
Refund Obligation for Unfinished Facility Additions.
If the Participating TO and the Project Sponsor, the CAISO, or Parties to the Generator Interconnection Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Section 35.19(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.
9.1.4
Provisions Relating To Transmission Construction On the Systems Of Other TOs.
9.1.4.1 Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any engineering, Effective ______________
PDF page 41
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 10
permitting, and construction of any necessary transmission or
distribution facilities additions on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO shall undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without
limitation, providing any information or data required by such other
electric system pursuant to Good Utility Practice.
9.1.4.2 Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the CAISO Tariff require additions or upgrades on other systems, the Participating TO shall
coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the CAISO, and the Project Sponsor, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Generator Interconnection Agreement, and the CAISO, in writing of the basis for any decision to defer construction and the
specific problems which must be resolved before it will initiate or
resume construction of the new facilities. Such Project Sponsor, Parties to the Participation Agreement, or the CAISO may challenge the
decision in accordance with the CAISO ADR Procedures.
10. Interconnection Process for SunZia Transmission’s Arizona Entitlements. The
interconnection process for SunZia Transmission’s Arizona Entitlements in the Arizona Transmission Rights, which it has turned over to CAISO Operational Control, is as stated in Section 8 above. Section 10, and its subparts, do not currently apply to those Arizona Entitlements.
10.1
Interconnection Process. Unless SunZia Transmission is the lead Participating TO with respect to a requested interconnection, the provisions of Section 10 of this TO Tariff, and its subparts, shall have no application to the Regional Transmission Facilities, Local Transmission Facilities, or Arizona Entitlements turned over to the CAISO’s Operational Control by SunZia Transmission and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern. All requests for interconnection with the Regional Transmission Facilities, Local Transmission Facilities, or Arizona Entitlements turned over to the CAISO’s Operational Control by SunZia Transmission shall be directed to the lead Participating TO, with notice of the request provided to SunZia Transmission.
10.2
Applicability. All requests for Interconnection directly to the CAISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the CAISO Tariff.
11. Uncontrollable Forces and Indemnification.
11.1
Procedures to Follow if Uncontrollable Force Occurs. In the event of the occurrence of an Uncontrollable Force which prevents a Party from performing any of its obligations under this TO Tariff, such Party shall (i) immediately notify the other Parties in writing of the occurrence of such Uncontrollable Force, (ii) not be entitled to suspend performance in any greater scope or longer duration than is required by the Effective ______________
PDF page 42
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 11
Uncontrollable Force, (iii) use its best efforts to mitigate the effects of such Uncontrollable Force, remedy its inability to perform, and resume full performance hereunder, (iv) keep the other Parties apprised of such efforts on a continual basis and
(v) provide written notice of the resumption of performance hereunder. Notwithstanding any of the foregoing, the settlement of any strike, lockout, or labor dispute constituting an Uncontrollable Force shall be within the sole discretion of the Party to this TO Tariff involved in such strike, lockout, or labor dispute and the requirement that a Party must use its best efforts to remedy the cause of the Uncontrollable Force and mitigate its effects and resume full performance hereunder shall not apply to strikes, lockouts, or labor disputes. No Party will be considered in default as to any obligation under this TO Tariff if prevented from fulfilling the obligation due to the occurrence of an Uncontrollable Force.
11.2
Indemnification. A Market Participant shall at all times indemnify, defend, and save the Participating TO harmless from any and all damages, losses, claims, (including claims and actions relating to injury or to death of any person or damage to property), demands, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the Participating TO’s performance of its obligations under this TO Tariff on behalf of a Market Participant, except in cases of negligence or intentional wrongdoing by the Participating TO. 11.3
Open Access. For purposes of the Stranded Cost Recovery available under Order Nos. 888 and 888-A, this Tariff, combined with the CAISO Tariff and wholesale distribution access tariff, if any, shall be considered an open access tariff under FERC Order Nos. 888 and 888-A.
12. Regulatory Filings. Nothing contained herein shall be construed as affecting, in any way, the right of SunZia Transmission to unilaterally make application to FERC as it deems necessary and appropriate to revise its Non-Subscriber Usage Rate, or for a change in its terms and conditions, including changes in rate methodology, or for a change in designation of the Arizona Entitlements to be placed under the CAISO’s Operational Control, pursuant to the applicable FERC rules, regulations, policies, and governing statutes.
13. Miscellaneous.
13.1
Notices. Any notices, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person, (ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return email, or (iv) upon delivery if delivered by prepaid commercial courier service, in each case addressed to a Party at the address set forth in Appendix III. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix II to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.
13.2
Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the Effective ______________
PDF page 43
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 12
statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver.
13.3
Confidentiality.
13.3.1 Maintaining Confidentiality if Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the documents, data, and information provided to it by any other Party that such Party may designate as confidential, provided, however, that the information will not be held confidential by the receiving Party if (1) the designating Party is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory requirements, or (2) the information becomes available to the public on a non-confidential basis (other than from the receiving Party). 13.3.2 Disclosure of Confidential Information. Notwithstanding anything in this Section 13.3.2 to the contrary, if any Party is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to this Section 13.3.2, the Party may disclose such information; provided, however, that as soon as such Party learns of the disclosure requirement and prior to making such disclosure, such Party shall notify the affected Party or Parties of the requirement and the terms thereof The affected Party or Parties may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Party shall cooperate with such affected Party or Parties to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Party shall cooperate with the affected Parties to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure.
13.4
TO Tariff Supersedes Existing Tariffs. Upon the filing of this TO Tariff at FERC and FERC’s acceptance of such TO Tariff for filing and FERC’s acceptance of the withdrawal of SunZia Transmission’s open access transmission tariff as accepted by FERC in Docket No. ER23-2146-001, SunZia Transmission, LLC, Order Accepting Tariff, 185 FERC ¶ 61,052 (Oct. 20, 2023), this TO Tariff, together with the CAISO Tariff and wholesale distribution access tariff if any, supersedes any pre-existing open access transmission tariff of the Participating TO.
13.5
Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.
13.6
Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency Effective ______________
PDF page 44
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 13
of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.
13.7
Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of each Party shall be preserved until satisfied.
13.8
Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.
13.9
Appendices Incorporated. The appendices to this TO Tariff are attached to this TO Tariff and are incorporated by reference as if fully set forth herein. 13.10
Consistency with CAISO Tariff. This TO Tariff, with the exception of Section 5.2, is intended to be consistent with the CAISO Tariff, and, if necessary, shall be amended to conform with any changes authorized or required in any final order in a FERC proceeding mandating such changes in the CAISO Tariff. If a Market Participant identifies a conflict between the TO Tariff and the CAISO Tariff other than Section 5.2 of this TO Tariff, the Participating TO and the Market Participant shall make good-faith efforts to resolve the conflict. If the Parties are unable to informally resolve that conflict, the Parties may use the CAISO ADR Procedures to resolve it as set forth in Section 13.11 of this Tariff.
13.11
Disputes. Except as limited by law, the CAISO ADR Procedures shall apply to all disputes between parties which arise under this TO Tariff. The CAISO ADR Procedures set forth in Section 13 of the CAISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.
13.12
Conflicting Dispatch and Operating Instructions. In the event a Market Participant receives conflicting dispatch or operating instructions from the CAISO and one or more Participating TO(s), if human safety would not knowingly be neither jeopardized nor electric facilities subject to damage while the Market Participant seeks to reconcile the conflict with the appropriate CAISO and Participating TO employees before acting, the Market Participant should attempt a reconciliation. Otherwise, the Market Participant shall adhere to the CAISO Tariff Section 4.2 and follow the CAISO’s instructions. In no event shall a Market Participant be required to follow dispatch or operating instructions from the CAISO if following those instructions would knowingly jeopardize human safety.
Effective ______________
PDF page 45
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 1
APPENDIX I
Non-Subscriber Usage Rates
The Generation COD Date shall occur on the commercial operation date of the last generating unit of the SunZia Transmission Subscriber that is interconnected to the SunZia Transmission System which generating unit is entitled to schedule energy delivery over the SunZia Transmission System using Subscriber Rights.
Non-Subscriber Usage Rate for the SunZia Transmission System Only (Pete Heinrich to Pinal Central) – As of the Grant of Operational Control to CAISO:
For the period commencing on the grant of operational control of the SunZia Transmission System to CAISO and the subsequent two-year period following the Generation COD Date and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for both import and export transactions over the SunZia Transmission System shall be set at $0.00 per MWh. For the one-year period beginning on the second anniversary of the Generation COD Date and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for both import and export transactions over the SunZia Transmission System shall be set at $2.0775 per kW/month (which increases annually by one-half of one percent (0.5%) commencing on the date on which operational control of the SunZia Transmission System is granted to CAISO) converted to an annual rate (i.e., multiplying by twelve) and then divided by 8,760 hours to derive an hourly off-peak rate for use of the SunZia Transmission System by Non-Subscribers. Commencing on the third anniversary of the Generation COD Date and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for both import and export transactions over the SunZia Transmission System shall be the current monthly point-to-point transmission rate charged by SunZia Transmission for use of the SunZia Transmission System by Subscribers in the TSA, as amended, supplemented, or restated from time to time and as accepted by the Commission (which increases annually by one-half of one percent (0.5%) commencing on the date on which operational control of the SunZia Transmission System is granted to CAISO), converted to an annual rate (i.e., multiplying by twelve) and then divided by 8,760 hours to derive an hourly off-peak rate for use of the SunZia Transmission System by Non-Subscribers. In no event shall the Non-Subscriber Usage Rate for the use of the SunZia Transmission System exceed the applicable CAISO Regional Access Charge in effect at the time service is provided to the Non-Subscriber.
Non-Subscriber Usage Rate for the Arizona Transmission Rights Only (Pinal Central to Palo Verde) – As of the Grant of Operational Control to CAISO:
For the period commencing on the grant of operational control of the Arizona Entitlements to CAISO and in accordance with the CAISO Tariff, the Non-Subscriber Usage Rate for the Arizona Transmission Rights shall be the weighted average (weighted by the amount of firm point-to-point transmission service held as an Arizona Entitlement by SunZia Transmission) of the current firm, monthly point-to-point transmission rates of WAPA, SRP and TEP, as shown on the Open Access Same-Time Information System (“OASIS”) of each transmission provider, converted to an annual rate (i.e., multiplying by twelve) and then divided by 8,760 hours to derive an hourly off-peak rate for use of the Arizona Transmission Rights by Non-Subscribers plus the actual Schedule 1 and 2 charges imposed by WAPA, SRP and TEP. In no event shall the Non-Subscriber Usage Rate for the Arizona Transmission Rights exceed the applicable CAISO Regional Access Charge in effect at the time service is provided to the Non-Subscriber. Effective ______________
PDF page 46
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 2First Revised Sheet No. 2
Non-Subscriber Usage Rate for Combined Segments of SunZia Transmission System and Arizona Transmission Rights (Pete Heinrich to Palo Verde) – As of the Grant of Operational Control to CAISO:
The Non-Subscriber Usage Rate for the combined segments of the SunZia Transmission System and the Arizona Transmission Rights shall be the sum of the Non-Subscriber Usage Rates for each respective segment, as defined above, but such Non-Subscriber Usage Rate shall not exceed the applicable CAISO Regional Access Charge in effect at the time service is provided to the Non-Subscriber.
The currently-effective components used in the calculation of the Non-Subscriber Usage Rates as such components change from time to time will be publicly posted on CAISO’s website. Effective ______________
PDF page 47
SUNZIA TRANSMISSION, LLCFERC Electric Tariff Volume 1First Revised Sheet No. 1
APPENDIX II
NOTICES
Designated Representative:
Deral Danis
Assistant Vice President, Transmission
1088 Sansome Street
200 South Wacker, Suite 1650
San Francisco, CA 94111Chicago, IL 60606
Tel. No. (312) 259-9989
Email Address: deral.danis@patternenergy.com
Alternate Representative:
Meghan Gruebner
SeniorGeneral Counsel
Pattern Energy Group LP
1088 Sansome Street
San Francisco, CA 94111
Tel. No. (415) 412-4917
Email Address: meghan.gruebnergeneralcounsel@patternenergy.com Effective ______________