SunZia Trans. Large Load Compliance Filing
Text extracted from the eLibrary original (SHA-256 e40db66eb90a5f25…). Download the original from the official source.
Contents · 6 sections
Topics in the text: Connecting load and generation · Registry access · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
Daileader Senior Counsel T / 202.585.8318 F / 866.947.3769 rdaileader@nixonpeabody.com Attorneys at Law nixonpeabody.com @NixonPeabodyLLP 4923-9080-5463.1 Nixon Peabody LLP 799 9th Street NW Suite 500 Washington, DC 20001-5327 November 16, 2026 E-TARIFF FILING The Honorable Debbie-Anne A.Read this passage
I. BACKGROUND
printed heading · Topic match: Connecting load and generation
ER24-2473-000, SunZia Transmission filed revisions to its OATT to amend Sections 17 and 18 to notify current and prospective customers that, upon the effective date of the APTOA, all requests for transmission or interconnection service on the Transmission System will be processed by CAISO in…Read this passage
II. DESCRIPTION OF FILING
printed heading · Topic match: Connecting load and generation
SunZia Transmission supports the commencement of that effort as soon as possible because the value proposition and the question surrounding how to study the interconnection of electrically proximate large load and generation in tandem (similar to co-located load and generation) are unique when…Read this passage
III. ATTACHMENTS TO FILING
printed heading
ATTACHMENTS TO FILING Included in this filing are the following documents: 1.Read this passage
IV. PROPOSED EFFECTIVE DATE
printed heading
PROPOSED EFFECTIVE DATE SunZia Transmission proposes an effective date of sixty days after the Commission issues an order on this compliance filing for the changes to its TO Tariff.Read this passage
V. COMMUNICATIONS
printed heading
COMMUNICATIONS Correspondence and service regarding this filing should be sent to the following individual: Robert L.Read this passage
VI. CONCLUSION
printed heading
CONCLUSION In accordance with the foregoing, SunZia Transmission respectfully requests that the Commission accept the proposed revisions to its TO Tariff as just and reasonable and consistent with its obligations under the Order to Show Cause and grant an effective date of sixty days after the…Read this passage
TABLE OF CONTENTS
printed heading · Topic match: Registry access
To maintain its queue position, the applicant must timely comply with the interconnection requirements of Appendix DD of the CAISO Tariff and Sections 8.1 and 10.1 and its subparts of this TO Tariff. 8.1.4 Due Diligence to Construct.Read this passage
TABLE OF CONTENTS
printed heading · Topic match: Registry access
To maintain its queue position, the applicant must timely comply with the interconnection requirements of Appendix DD of the CAISO Tariff and Sections 8.1 and 10.1 and its subparts of this TO Tariff. 8.1.4 Due Diligence to Construct.Read this passage