ER27-518-000 · 2026-11-16 · LS Power Grid New York Corporation INew York Independent System Operator, Inc.

Hayes Testimony (Exhibit No. GNY-100)

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

LS Power Grid New York Corporation I New York Independent System Operator, Inc. )

)
)
)
Docket No. ER27-___-000
Docket No. EL26-69-000

DIRECT TESTIMONY OF PATRICK HAYES
ON BEHALF OF
LS POWER GRID NEW YORK CORPORATION I Large Load Network Upgrade Cost Recovery November 2026

PDF page 2

TABLE OF CONTENTS
I. Introduction and Experience … 1
II. Purpose and Scope of Testimony … 2
III. The NYISO Show Cause Order … 3
IV. NYISO Stakeholder Process … 5
V. Cost Recovery Agreement … 7
VI. Tariff and Protocol Revisions … 28

PDF page 3

EXHIBITS TO
DIRECT TESTIMONY OF PATRICK HAYES

Exhibit No.
Description
GNY-101:
Illustrative MTRC Calculation
GNY-102:
Example Reconciliation Statement
GNY-103:
Example Charge Statement

PDF page 4

1
DIRECT TESTIMONY OF PATRICK HAYES
I. INTRODUCTION AND EXPERIENCE
1
Q.
PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
2
A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310, 3

Chesterfield, Missouri 63017.
4
Q.
BY WHOM ARE YOU EMPLOYED, AND WHAT ARE YOUR
5
RESPONSIBILITIES?
6
A. I am employed by LS Power and serve as Associate Vice President, Transmission 7

Regulatory. I lead regulatory strategy for LS Power’s transmission business across the 8

California Independent System Operator, Midcontinent Independent System Operator, PJM 9

Interconnection, New York Independent System Operator, and other regional markets. My 10

responsibilities include FERC policy, regional transmission planning, competitive 11

transmission development, cost allocation and recovery, tariff development, and large-load 12

interconnection.
13
Q.
PLEASE SUMMARIZE YOUR PROFESSIONAL EXPERIENCE AND
14
EDUCATION.
15
A. I previously served as LS Power’s Director of Transmission Business Development and 16

Manager of Transmission Policy. Earlier in my career, I held transmission policy, energy 17

trading, and asset optimization positions with Ameren. My experience includes developing 18

strategies for competitive transmission projects and utility partnerships, negotiating 19

commercial and ownership arrangements, evaluating transmission investments, and 20

coordinating multidisciplinary teams. I received a Bachelor of Science in Accounting from 21

the University of Missouri.
22

PDF page 5

2
Q.
ON WHOSE BEHALF ARE YOU SUBMITTING THIS TESTIMONY?
1
A. I am testifying on behalf of LS Power Grid New York Corporation I (“LSPGNY”), a non- 2

incumbent Transmission Owner in the New York Independent System Operator, Inc. 3

(“NYISO”) region. LSPGNY and the New York Power Authority developed Segment A of 4

the AC Transmission Public Policy Transmission Need, a 345 kV project between the 5

Marcy/Edic and New Scotland substations now in service as part of Central East Energy 6

Connect.
7
II. PURPOSE AND SCOPE OF TESTIMONY
8
Q.
WHAT IS THE PURPOSE OF YOUR TESTIMONY?
9
A. I explain how LSPGNY proposes to recover the costs of Large Load-Driven Upgrades on 10

its facilities and protect other transmission customers from bearing costs caused by a large 11

load. LSPGNY would calculate upgrade revenue requirements under its formula rate and 12

recover the resulting amounts through NYISO under revised Rate Schedule 10. The 13

revenue requirements for Large Load-Driven Upgrades would be combined with Segment 14

A’s revenue requirement in a single Regulated Transmission Facilities Charge (“RTFC”), 15

using Segment A’s existing cost allocation. For upgrades covered by this filing, where 16

LSPGNY is the Connecting Transmission Owner, a Cost Recovery Agreement (“CRA”) 17

establishes the responsible Eligible Customer’s minimum revenue contribution and security 18

obligations. Projected Supplemental Minimum Transmission Revenue Contribution 19

(“Supplemental MTRC”) and Annual Termination Fee Remittances would be recognized as 20

general revenue credits in the Annual Projection. In the Annual Update, those projected 21

credits would be replaced by actual cash receipts, including applicable Security proceeds 22

received and applied to Supplemental MTRC obligations and Annual Termination Fee 23

PDF page 6

3
Remittances received, under the formula rate template. Segment A’s existing tariff cost 1

allocation would apply to the combined RTFC, including the Large Load-Driven Upgrade 2

costs and applicable CRA revenue credits.
3
I describe the Commission’s Show Cause Order, LSPGNY’s stakeholder outreach, the 4

proposed CRA, and the tariff and protocol changes needed to implement it. My testimony 5

addresses policy and implementation. The detailed formula-rate calculations and supporting 6

workpapers are addressed in the separate rate testimony of Eric Arzola. 7

Q.  ARE YOU SPONSORING ANY EXHIBITS IN SUPPORT OF YOUR TESTIMONY
8
IN THIS CASE?
9
A.  Yes. I am sponsoring the following exhibits:
10
Exhibit No.
Description
GNY-101:
Illustrative MTRC Calculation
GNY-102:
Example Reconciliation Statement
GNY-103:
Example Charge Statement
III. THE NYISO SHOW CAUSE ORDER
11
Q.
WHAT DID THE COMMISSION DIRECT IN THIS PROCEEDING?
12
A. On June 18, 2026, the Federal Energy Regulatory Commission (“Commission” or “FERC”) 13

instituted this proceeding under section 206 of the Federal Power Act. It directed NYISO 14

and the named Transmission Owners, including LSPGNY, to show cause why the NYISO 15

Open Access Transmission Tariff (“OATT”) remains just and reasonable and free of undue 16

discrimination or preference without provisions addressing the Commission’s concerns, or 17

to explain what tariff changes would remedy them if the Commission establishes a 18

replacement rate. The Commission granted a 90-day abeyance on August 14, 2026, setting 19

November 16, 2026, as the response deadline, subject to the order’s provision for a 20

PDF page 7

4
respondent that makes a timely section 205 filing addressing the preliminary findings. See 1

N.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216 at P 3 (2026) (“Show Cause Order”); 2

Order Granting Abeyance, Docket No. EL26-69-000, at PP 10–11 (Aug. 14, 2026). 3

Q.
WHICH ASPECTS OF THE SHOW CAUSE ORDER DOES YOUR TESTIMONY
4
ADDRESS?
5
A. I address the Commission’s preliminary findings on cost transparency and cost shifting. 6

The Commission identified a risk that other transmission customers could pay for upgrades 7

built for a large load if that load is delayed, takes less service than requested, or never 8

materializes. It identified public posting of upgrade and cost information and a pro forma 9

CRA between the relevant Transmission Owner and the Eligible Customer as potential 10

remedies. The Commission linked the minimum contribution to the requested megawatts 11

that drive the need for upgrades, sought sufficient credit support, and expected amounts 12

paid under a CRA to be credited appropriately to the Transmission Owner’s revenue 13

requirement. It also contemplated a separate workpaper in the annual formula-rate 14

informational filing. See Show Cause Order at PP 72–82, 83–91.
15
Q.
WHY DO THOSE FINDINGS RAISE A DISTINCT ISSUE FOR LSPGNY?
16
A. LSPGNY is a Transmission Owner for purposes of the NYISO tariffs under its Operating 17

Agreement with NYISO. It has no franchised retail service territory or obligation to serve 18

retail load and has no Transmission Service Charge (“TSC”) under Attachment H. Its 19

Commission-accepted formula rate is part of Rate Schedule 10, which provides for 20

recovery of eligible projects under Attachment Y. Segment A is such a project. The 21

existing eligibility provisions do not expressly cover Network Upgrades identified to serve 22

a large load through the load interconnection process. Rate Schedule 10 also excludes 23

PDF page 8

5
projects undertaken through the Local Transmission Owner Planning Process. See NYISO 1

Service Agreement No. 2627, Operating Agreement § 1.01, Docket No. ER21-2104-000; 2

NYISO OATT §§ 6.10.1, 6.10.7, 14.1, and 31.5.1.5.
3
A large load can require an upgrade to an LSPGNY facility even when it connects to 4

another Transmission Owner’s system. A study or interconnection agreement can identify 5

the facilities and assign cost responsibility. LSPGNY also needs a tariff provision that 6

authorizes recovery of the associated cost of service and specifies how NYISO will bill the 7

responsible customer and credit CRA payments. That recovery mechanism is needed 8

whether LSPGNY is the Connecting Transmission Owner or an Affected Transmission 9

Owner. The CRA proposed in this filing addresses LSPGNY as the Connecting 10

Transmission Owner. Arrangements for LSPGNY as an Affected Transmission Owner 11

remain to be resolved.
12
The local planning provisions present a separate question. Attachment Y calls for 13

Transmission Owners to plan their systems, while the definitions of the Local Transmission 14

Owner Plan and the Local Transmission Owner Planning Process refer to the owner’s 15

Transmission District. Because LSPGNY has no obligation to serve load in a Transmission 16

District, OATT revisions are necessary to clarify how LSPGNY can plan upgrades to its 17

own facilities on a comparable basis. See NYISO OATT §§ 1.20, 31.1.1, and 31.2.1. 18

IV. NYISO STAKEHOLDER PROCESS
19
Q.
HOW DID LSPGNY ENGAGE WITH NYISO?
20
A. LSPGNY discussed load study procedures with NYISO staff in late 2025 and participated 21

in NYISO’s discussions with Transmission Owners after the Show Cause Order. In July 22

2026, LSPGNY submitted questions and met with NYISO staff. In written comments on 23

PDF page 9

6
NYISO’s July 23 stakeholder presentation, submitted July 27, LSPGNY requested 1

additional time for stakeholder review, urged a coordinated filing, and asked NYISO to 2

address how a Transmission Owner without retail load would participate as a Connecting 3

or Affected Transmission Owner.
4
NYISO and the incumbent Transmission Owners each filed a motion for abeyance on 5

August 3. LSPGNY and New York Transmission Co., LLC jointly filed a separate motion 6

that day. The Commission granted the motions on August 14. See Order Granting 7

Abeyance at PP 2, 8, 10.
8
On September 24, LSPGNY presented its proposed cost recovery framework to NYISO 9

staff and counsel. On October 8, NYISO explained that Transmission Owners should lead 10

the development of cost recovery frameworks and identified implementation work 11

involving rate design, facility treatment, billing, revenue tracking, and collateral that would 12

need to be addressed. LSPGNY therefore proposed including the core cost-responsibility 13

terms in the initial filing and addressing billing and collateral mechanics later. 14

Q.
HOW DID LSPGNY COORDINATE WITH THE OTHER TRANSMISSION
15
OWNERS AND STAKEHOLDERS?
16
A. On July 20, 2026, LSPGNY contacted counsel for the New York Transmission Owners 17

(“NYTOs”) to discuss coordinating their responses to the Show Cause Order. In a follow- 18

up discussion on July 22, LSPGNY asked to participate in developing the NYTOs’ 19

response and to join their filing. The NYTOs declined both requests.
20

LSPGNY continued to participate in NYISO’s Transmission Owner working sessions. It 21

raised two issues for an Affected Transmission Owner with no retail relationship with the 22

PDF page 10

7
large load: how that owner would recover the costs of upgrades to its facilities and how it 1

would gain access to the financial security supporting payment of those costs. 2

On October 22, the NYTOs presented a proposed cost recovery and security framework 3

that relied on Section 5 of the NYISO OATT, which governs the collection of transmission 4

charges under participating Transmission Owners’ retail access tariffs. LSPGNY does not 5

serve retail customers. As a result, the proposal provided no mechanism for LSPGNY to 6

recover the costs of upgrades to its facilities needed to serve a large load that takes retail 7

service from another Transmission Owner.

8
Q.
HOW DID THE STAKEHOLDER PROCESS AFFECT LSPGNY’S APPROACH?
9
A. The discussions identified the need for a rate provision that works for non-incumbent 10

Transmission Owners and for NYISO settlement rules that put that provision into effect. 11

The coordinated process did not yield a joint proposal that resolved both issues for 12

LSPGNY within the time available. LSPGNY is therefore presenting a separate framework 13

for upgrades where it is the Connecting Transmission Owner. Affected-system cost 14

recovery and security arrangements remain to be addressed in coordination with the other 15

Transmission Owners’ proposals and, if necessary, through a subsequent filing. It is 16

designed to work alongside NYISO’s regional study and interconnection procedures and 17

the cost recovery arrangements developed for owners with a TSC.
18
V. COST RECOVERY AGREEMENT
19
Q.
WHO WOULD ENTER INTO THE CRA, AND WHAT WOULD IT COVER?
20
A. LSPGNY proposes a pro forma CRA between LSPGNY and the Eligible Customer taking 21

wholesale transmission service on behalf of the large load where LSPGNY is the 22

Connecting Transmission Owner. The Large Load Customer would execute a Limited 23

PDF page 11

8
Acknowledgment without becoming a party to the CRA’s wholesale payment obligations. 1

NYISO would not be a CRA party; its billing, collection, security, draw, and remittance 2

responsibilities arise under the proposed Rate Schedule 10 Large Load Provisions. The 3

CRA identifies each Covered Upgrade, the assigned responsibility, calculation inputs, and 4

payment and security obligations. A Covered Upgrade includes an identified Large Load- 5

Driven Upgrade or LSPGNY-owned ISO-Assigned Regional Project share for which the 6

CRA establishes an Annual MTRC. Retail arrangements between the Eligible Customer 7

and the Large Load Customer would remain governed by the applicable retail framework. 8

Q.
WHEN WILL THE CRA AND ASSOCIATED SECURITY BE IN PLACE?
9
A. The study results would identify the Covered Upgrades and the responsibility to be 10

documented in the CRA and applicable construction or interconnection arrangements. 11

Execution or authorized effectiveness of those arrangements, and delivery of the required 12

construction security, will precede the construction commitments they secure. Operational 13

security will support the remaining revenue commitment after the applicable upgrade enters 14

service. The CRA establishes the applicable deadlines, conditions for proceeding, and 15

remedies if the Eligible Customer fails to execute the required arrangements, post security, 16

or maintain it. Those requirements protect against LSPGNY incurring an unsecured 17

obligation in reliance on the large load.
18
Q.
HOW WOULD THE FRAMEWORK APPLY WHEN THE LARGE LOAD
19
CONNECTS TO ANOTHER TRANSMISSION OWNER’S SYSTEM?
20
A. A large load connecting to another Transmission Owner’s system may require an upgrade 21

to an LSPGNY facility. The applicable study would identify the required upgrade and the 22

responsibility attributable to the request. The proposed CRA in this filing, however, covers 23

PDF page 12

9
LSPGNY as the Connecting Transmission Owner; it does not establish a CRA for 1

LSPGNY as an Affected Transmission Owner. The appropriate arrangement will depend 2

on the scope of the other Transmission Owners’ proposed agreements and the associated 3

tariff provisions.
4

LSPGNY needs a mechanism to recover its affected-system upgrade costs and obtain 5

access to the supporting security without a retail service relationship with the end-use load. 6

If the other Transmission Owners’ proposed agreements do not provide that mechanism, a 7

separate affected-system CRA may need to be added as another appendix to Attachment 1 8

of Rate Schedule 10 through a subsequent filing. This filing should not be understood as 9

resolving that remaining issue.
10
Q.
HOW WOULD LSPGNY ASSIGN AND RECOVER THE COST OF A LARGE
11
LOAD-DRIVEN UPGRADE?
12
A. The applicable study would identify the upgrades needed to serve the requested load and 13

the costs attributable to that request. The CRA documents the Eligible Customer’s 14

responsibility for the applicable Covered Upgrades, including assigned shares where 15

multiple requests contribute to the need for an upgrade. That contractual responsibility is 16

distinct from the allocation of LSPGNY’s formula-rate revenue requirement under Rate 17

Schedule 10. Under LSPGNY’s proposed approach, the revenue requirements for Large 18

Load-Driven Upgrades would be combined with Segment A’s revenue requirement in a 19

single RTFC and allocated using Segment A’s existing tariff cost allocation. There would 20

be no separate zonal or subzonal allocation for an individual Large Load-Driven Upgrade. 21

Supplemental MTRC and Annual Termination Fee Remittances would reduce the 22

combined revenue requirement as general revenue credits under the formula rate template. 23

PDF page 13

10
The costs and those credits would therefore be reflected in the same RTFC using the same 1

allocation.
2

The existing RTFC allocation is the established mechanism for collecting LSPGNY’s 3

Commission-authorized revenue requirement. Its use does not rest on a finding that the 4

Responsible LSEs caused the Large Load Facility or its service request. The CRA 5

separately assigns the responsible Eligible Customer an Annual MTRC, satisfied through 6

Qualifying Transmission Revenues and Supplemental MTRC. The formula rate credits the 7

applicable Large Load CRA Revenue against LSPGNY’s revenue requirement. These 8

provisions are intended to mitigate cost shifting to other Responsible LSEs, subject to the 9

relationship between the contractual commitment and actual cost of service described 10

below.
11

Where more than one Large Load Facility drives an upgrade, Schedule 1 identifies an 12

Initial Allocation Percentage for each Large Load Customer using the applicable final study 13

and allocation methodology. That allocation accounts for individually and jointly studied 14

loads; their requested service levels, development phases, and facility configurations; and 15

any portion serving other system needs or customers. Aggregate allocations to Large Load 16

Customers may not exceed one hundred percent. Any unallocated portion remains subject 17

to the otherwise applicable Rate Schedule 10 cost-allocation and recovery rules. 18

LSPGNY would calculate the annual cost of service through its formula rate, including 19

return on net rate base, depreciation, taxes, and allocable operating and administrative 20

expenses, subject to applicable credits. NYISO would recover the resulting revenue 21

requirement through Rate Schedule 10 and separately bill the Eligible Customer for 22

Supplemental MTRC under the CRA. LSPGNY proposes to retain the requirement for 23

PDF page 14

11
Commission acceptance of a section 205 filing adding each Large Load-Driven Upgrade to 1

Table 1 before its revenue requirement could be included in the RTFC. Listing an upgrade 2

would identify the investment eligible for recovery; it would not establish a separate cost 3

allocation for that upgrade. LSPGNY’s recovery would be determined under its formula 4

rate, including the credits for CRA revenue. The Annual Update would credit Supplemental 5

MTRC actually received, including applicable Security proceeds received and applied to 6

that obligation, rather than amounts merely billed. An amount not collected or satisfied 7

from Security would not reduce LSPGNY’s actual formula-rate revenue requirement as a 8

revenue credit. The resulting difference from the projected credit would be reflected in the 9

ordinary formula-rate true-up and included in the next Annual Projection prepared after the 10

Annual Update, with ordinary true-up interest. The Eligible Customer would remain liable, 11

and any later recovery would be credited when received. Other transmission customers 12

could therefore bear a collection shortfall through the RTFC pending a later recovery; the 13

CRA’s payment and security obligations mitigate that exposure but do not eliminate it. 14

Commission acceptance of each Table 1 designation provides an opportunity to evaluate 15

the particular upgrade, its supporting study record, and the application of the CRA 16

protections before its revenue requirement enters the RTFC.
17
The CRA does not determine whether a facility is directly assigned or included in rate base. 18

That determination is made under the applicable NYISO tariff, study process, and 19

interconnection arrangements. Direct Assignment Facilities and other facilities whose costs 20

are directly assigned to and paid by the Eligible Customer, and are not included in 21

LSPGNY’s rate base, are excluded from the definition of Large Load-Driven Upgrades and 22

PDF page 15

12
the MTRC framework. See the CRA definition of “Large Load-Driven Upgrades” and 1

Section 6.2.
2
Covered Upgrades are separately identified in the formula rate and use the capital structure 3

and generally applicable return components applicable to LSPGNY under Rate Schedule 4

10, including any Commission-approved generally applicable ROE incentive, as applicable. 5

They do not receive incentives specific to the AC Transmission Project or become subject 6

to that project’s Competitive Bid Concession, cost cap, or other project-specific cost- 7

containment commitments. See CRA Section 6.2 and Eric Arzola’s rate testimony. 8

Q.
HOW WOULD THE MINIMUM CONTRIBUTION WORK?
9
A. The CRA establishes an Annual Minimum Transmission Revenue Contribution (“Annual 10

MTRC”) for each Covered Upgrade using the separate MTRC Calculation Template in 11

Schedule 5. The calculation uses a levelized fixed charge rate (“FCR”) over a twenty-year 12

MTRC Term, applied to the assigned capital cost, with the capital recovery, income-tax, 13

and other capital-related components specified in Schedule 5, plus any fixed annual 14

components not included in the FCR. The calculation excludes the Segment A project-risk 15

incentive adder. Estimated capital cost would initially support an Estimated Annual MTRC. 16

LSPGNY would establish the Final Annual MTRC using actual capital cost within one year 17

after the Covered Upgrade enters service, with estimated charges reconciled under the 18

CRA. The finalized contractual MTRC would not be reset through routine annual formula- 19

rate updates, subject to the CRA’s expressly permitted adjustments.
20
Q.
WHY DOES LSPGNY PROPOSE A TWENTY-YEAR, LEVELIZED MTRC?
21
A. A large-load request may require a substantial transmission investment before the load 22

reaches its expected operating level. A twenty-year commitment provides an extended 23

PDF page 16

13
period of customer accountability for that investment, while establishing a defined period 1

over which the Eligible Customer can evaluate its obligation. Levelization spreads the 2

calculated revenue contribution over that period rather than concentrating it in the initial 3

years. The purpose is to secure a meaningful contribution toward the investment 4

undertaken for the requested service and reduce the exposure of other customers if the load 5

is delayed, reduced, or discontinued.
6

The twenty-year MTRC Term is a contractual revenue-support period. Under CRA 7

Sections 3.2 and 6.7, earlier Break-Even is available if a final Reconciliation Statement 8

determines that the Total Required Revenue Commitment has been satisfied before the end 9

of that term. Operational payment and security obligations then terminate, subject to final 10

true-ups and correction of errors or fraud for periods before satisfaction. Once finally 11

satisfied, the responsibility does not revive because of a later change in return on equity, 12

expense, load, forecast, or other formula-rate input. It does not establish the upgrade’s 13

accounting depreciation rate or require removal of the facility from rate base at the end of 14

that term. The facility’s continued inclusion in the formula rate would remain governed by 15

the applicable tariff and Commission requirements. Amounts recovered under the CRA 16

would receive the credits and other treatment provided in the formula rate template so that 17

the contractual commitment does not create duplicate recovery.
18

The twenty-year term is supported by Operational Security based on the remaining 19

Cumulative Revenue Responsibility and, when the applicable termination provisions are 20

triggered, a Termination Fee equal to the remaining contractual commitment less any 21

Supplemental MTRC already billed and remaining unpaid. Those unpaid bills remain 22

separately payable and are not discharged by payment of the Termination Fee. It does not 23

PDF page 17

14
eliminate all risk over the Covered Upgrade’s depreciable life. Neither a levelized Annual 1

MTRC nor the single-year illustration below, standing alone, demonstrates that the total 2

commitment equals or exceeds the upgrade’s cost of service over its entire life. Such a 3

conclusion would require a comparison using consistent cost, revenue, timing, and 4

discount-rate assumptions.
5
Q.
WHY CAN THE FIXED ANNUAL MTRC DIFFER FROM THE UPGRADE’S
6
ANNUAL FORMULA-RATE REVENUE REQUIREMENT?
7
A. The Annual MTRC is a levelized contractual amount calculated using the inputs specified 8

in the CRA. The formula rate separately determines the annual cost of service using the 9

applicable rate base, depreciation, expenses, taxes, return, and credits. As net plant declines 10

and other formula-rate inputs change, the annual cost of service can differ from the fixed 11

contractual amount. The Annual MTRC is therefore not a representation that the 12

customer’s minimum contribution will equal the actual incremental revenue requirement in 13

every year.
14

The effect on other customers depends on the actual revenue requirement, qualifying large- 15

load revenues, Supplemental MTRC, and the credit and allocation provisions in the 16

template and tariff. The contractual floor, security, and reconciliation provisions mitigate 17

exposure to the large load; they do not support an unconditional assurance that every other 18

customer’s rate will remain unchanged under every operating or cost scenario. 19

Q.
WHY DOES THE FIXED CHARGE CALCULATION INCLUDE CAPITAL
20
RECOVERY, INCOME TAXES, AND OTHER SPECIFIED COMPONENTS?
21
A. Capital cost alone does not measure the full revenue contribution associated with an 22

upgrade. Schedule 5 calculates the Annual MTRC using a levelized capital charge rate plus 23

PDF page 18

15
an expense allocator, consistent with the FCR worksheet in Exhibit No. GNY-101. The 1

calculation first determines an after-tax discount rate using the applicable capital structure, 2

return on equity, cost of debt, and composite income-tax rate. It then subtracts the present 3

value of federal and state tax-depreciation benefits from allocated capital cost and applies 4

an income-tax revenue conversion factor. The resulting present-value capital revenue 5

requirement is annualized over the twenty-year MTRC Term using the after-tax discount 6

rate and divided by allocated capital cost to determine the levelized capital charge rate. The 7

expense allocator reflects operating and maintenance expense, less project-specific 8

regulatory asset amortization included in that expense, plus taxes other than income taxes, 9

divided by total gross transmission plant in service. The levelized capital charge rate and 10

expense allocator are each rounded to six decimal places and added to determine the Fixed 11

Charge Rate. The Annual MTRC equals allocated capital cost multiplied by that rate, plus 12

any separately identified fixed annual costs not already included. Supporting workpapers 13

identify the inputs, their sources, and each calculation, and prevent duplicate inclusion of 14

any cost.
15

The FCR calculation establishes the contractual minimum contribution; it is not an 16

additional formula-rate charge imposed on top of the same cost of service without an offset. 17

LSPGNY would continue to calculate its revenue requirement through the formula rate, 18

and Supplemental MTRC and other applicable amounts would receive the treatment 19

specified in the template. Schedule 5 and its supporting workpapers provide the contractual 20

calculation and input reconciliation; the separate rate testimony of Eric Arzola explains 21

how the resulting Annual MTRC is used in the formula rate template.
22

PDF page 19

16
The MTRC is a contractual revenue floor calculated separately from LSPGNY’s annual 1

formula-rate cost of service. Supplemental MTRC is the greater of zero and the applicable 2

Annual MTRC less Qualifying Transmission Revenues for the corresponding period. The 3

CRA and Schedule 2 define the qualifying RTFC revenues attributable to the Large Load 4

Facility and the methodology for attributing or allocating those revenues among Covered 5

Upgrades. Each dollar would count only once. LSPGNY would maintain customer- and 6

Covered Upgrade-specific records of the commitment and its satisfaction. That tracking 7

does not require formula-rate credits to be applied exclusively to the revenue requirement 8

of the corresponding upgrade. Instead, CRA revenue is a general revenue credit that 9

reduces LSPGNY’s overall revenue requirement rather than the revenue requirement of any 10

individual Covered Upgrade.
11
Qualifying Transmission Revenues are not a separate retail or load-based charge imposed 12

by LSPGNY. They are the portion of RTFC revenues assessed on the Large Load Facility’s 13

Actual Energy Withdrawals, collected from the Responsible LSE or LSEs serving that 14

facility, and remitted to LSPGNY that is attributable to the applicable Covered Upgrade 15

and reduces the RTFC otherwise collected from other Responsible LSEs. Schedule 2 16

provides the methodology using the applicable metering data, RTFC rate, Load Zone or 17

Subzone allocation, and Covered Upgrade Revenue Share.
18
Q.
DOES THE CRA REPLACE ORDINARY TRANSMISSION-SERVICE PAYMENT
19
OR COLLATERAL OBLIGATIONS?
20
A. No. The Eligible Customer and the transmission customers responsible for the combined 21

RTFC would remain subject to their respective payment obligations under the applicable 22

transmission tariffs. The CRA determines which qualifying RTFC revenues attributable to 23

PDF page 20

17
the Large Load Facility satisfy the minimum contribution. Supplemental MTRC would be 1

due only for the positive difference between the applicable Annual MTRC and those 2

qualifying revenues. It would not replace ordinary transmission charges or permit the same 3

revenue to be credited twice.
4

CRA security supports the obligations established by that agreement. Ordinary 5

transmission-service credit requirements continue to apply under the governing tariff. 6

Qualifying retail security support may satisfy the corresponding CRA security exposure 7

only to the extent the CRA and tariff recognize it and the support is legally available when 8

needed.
9
Q.
HOW WOULD PROJECTED AND ACTUAL AMOUNTS BE RECONCILED?
10
A. LSPGNY would include the projected Supplemental MTRC, including any prior-period 11

true-up adjustment, and any projected Annual Termination Fee Remittances as a credit in 12

the Annual Projection in accordance with the formula rate template, and NYISO would bill 13

and remit the applicable customer-specific amounts under the tariff and CRA. In the 14

Annual Update, that projected credit would be replaced by Supplemental MTRC cash 15

receipts and Annual Termination Fee Remittances actually received during the Rate Year, 16

supported by billing, cash-receipt, and settlement records. Supplemental MTRC receipts 17

would include applicable Security proceeds received and applied to Supplemental MTRC 18

obligations and later collections of amounts billed in earlier years, counted once. 19

Differences between projected credits and actual receipts would flow through the ordinary 20

formula-rate true-up. The separate customer-level reconciliation would continue to 21

compare amounts billed with the contractual amount due; nonpayment would not itself 22

create an additional customer-level charge. The CRA Reconciliation Statement compares 23

PDF page 21

18
the Supplemental MTRC billed for the Rate Year, excluding any prior-period true-up 1

adjustment included in that billing, with the actual Supplemental MTRC determined from 2

actual Qualifying Transmission Revenues. The difference, calculated without interest, 3

would be carried into the Eligible Customer’s projected Supplemental MTRC in the next 4

Annual Projection as a prior-period true-up adjustment. If no further Supplemental MTRC 5

will be billed under the CRA, LSPGNY would include any under-billed amount in a 6

Charge Statement and refund any over-billed amount to the Eligible Customer, in each case 7

without interest. The Reconciliation Statement would serve as a supporting worksheet 8

rather than impose an additional charge or duplicate a template calculation. This annual 9

reconciliation is separate from finalizing the MTRC using actual capital cost. An example 10

CRA Reconciliation Statement is provided as Exhibit No. GNY-102.
11
Q.
WHY SHOULD PROJECTED SUPPLEMENTAL MTRC BE REFLECTED IN THE
12
ANNUAL PROJECTION?
13
A. Reflecting projected Supplemental MTRC allows the expected contribution to reduce the 14

amount initially recovered from other transmission customers under the template. If the 15

contribution were excluded until after receipt and a later true-up, those customers could 16

temporarily bear amounts that the CRA assigns to the Eligible Customer. The projection 17

uses the expected upgrade in-service dates, load, qualifying revenues, and applicable 18

Annual MTRC. Those assumptions are subject to reconciliation when actual information 19

becomes available.
20

Forecasts can overstate or understate the actual contribution. The Reconciliation Statement 21

would identify the difference between the Supplemental MTRC billed for the Rate Year, 22

excluding any prior-period true-up adjustment included in that billing, and the actual 23

PDF page 22

19
Supplemental MTRC, and that difference would be billed or credited to the Eligible 1

Customer through the next Annual Projection, or directly billed or refunded without 2

interest if no further Supplemental MTRC will be billed under the CRA. This approach 3

combines timely recognition of the expected customer contribution with correction of 4

forecast differences at the customer level. Collection risk is treated separately. Because the 5

Annual Update credits actual cash receipts, a delayed or unpaid amount not satisfied from 6

Security would reduce the actual revenue credit and could increase the amount recovered 7

from other customers through the ordinary formula-rate true-up, with applicable interest. 8

The unpaid amount would remain owed by the Eligible Customer and subject to the CRA’s 9

payment and security provisions. Any later recovery would be credited in the year received, 10

without duplicating a previously recognized receipt. The principal reason for projected 11

treatment is timely protection of other customers, supported by transparent reconciliation. 12

Q.
HOW WOULD THE PROJECTION AND RECONCILIATION PROCESS
13
OPERATE OVER TIME?
14
A. Before Rate Year Y, the Annual Projection would include the projected revenue 15

requirement and a credit for the projected Supplemental MTRC and any Annual 16

Termination Fee Remittances for that year. By October 31 preceding Rate Year Y, 17

LSPGNY would deliver a Charge Statement to NYISO, and during Rate Year Y, NYISO 18

would bill the projected Supplemental MTRC in twelve equal monthly installments under 19

the tariff and CRA. By June 30 of Rate Year Y+1, LSPGNY would prepare the Annual 20

Update using actual information for Rate Year Y, together with a Reconciliation Statement 21

identifying the prior-period true-up adjustment. That adjustment would be included in the 22

next Annual Projection and therefore billed during Rate Year Y+2, under the timetable 23

PDF page 23

20
specified in the template and tariff. Separately, the Annual Update in Rate Year Y+1 would 1

replace the projected CRA revenue credit for Rate Year Y with actual receipts during Rate 2

Year Y. The resulting ordinary formula-rate true-up, including applicable interest, would be 3

included in the Annual Projection prepared in Y+1 for recovery or credit in Rate Year Y+2. 4

A later collection would be recognized as a revenue credit in the year received and 5

reconciled through that year’s Annual Update. Workpapers would identify the billing year 6

and receipt year so that a later collection is not mistaken for a new obligation or credited 7

twice. An example Charge Statement illustrating the billing instructions LSPGNY would 8

deliver to NYISO is provided as Exhibit No. GNY-103.
9
Q.
HOW WOULD INTEREST APPLY TO RECONCILIATION ADJUSTMENTS?
10
A. The customer-level true-up of the difference between the Supplemental MTRC billed for 11

the Rate Year, excluding any prior-period true-up adjustment included in that billing, and 12

the actual Supplemental MTRC would not bear interest in either direction. That adjustment 13

changes the Eligible Customer’s share of the cost, not LSPGNY’s own revenue 14

requirement. Interest calculated under 18 C.F.R. § 35.19a would apply to an amount 15

determined through a dispute to have been overbilled. The ordinary formula-rate over- or 16

under-recovery resulting from differences between projected Large Load CRA Revenue 17

and actual cash receipts, including collection shortfalls and later recoveries, would be 18

subject to the ordinary formula-rate true-up interest provisions. That interest would apply 19

through the formula-rate true-up and would not impose interest on the separate customer- 20

level Supplemental MTRC reconciliation. The template and supporting workpapers 21

distinguish these types of adjustments.
22

PDF page 24

21
Q.
CAN YOU ILLUSTRATE THE SUPPLEMENTAL MTRC CALCULATION?
1
A. Exhibit No. GNY-204, Attachment 1a, illustrates an Annual MTRC of $7,320,060 and 2

projected Qualifying Transmission Revenues of $6,132,000 for Customer A’s Large Load 3

Project 1, producing projected Supplemental MTRC of $1,188,060 before prior-period 4

adjustments. The qualifying-revenue forecast uses 400 MW, 8,760 annual billing hours, 5

and an illustrative qualifying transmission rate of $1.75 per MWh. A prior-period true-up 6

adjustment of $307,440 increases the projected amount to be billed for that Covered 7

Upgrade to $1,495,500. The example assumes a full modeled Rate Year of 2030. Applying 8

the illustrative Annual MTRC over a full twenty-year term produces an unadjusted Total 9

Required Revenue Commitment of $146,401,200. These are illustrative assumptions rather 10

than amounts established for an actual customer. A separate populated CRA calculation 11

exhibit is provided with my testimony as GNY-101 and reconciles to the applicable 12

assumptions in GNY-204.
13
Q.
HOW WOULD MULTIPLE COVERED UPGRADES WITH DIFFERENT IN-
14
SERVICE DATES AFFECT THE COMMITMENT?
15
A. Each Covered Upgrade would have its own applicable in-service date, Annual MTRC, and 16

twenty-year MTRC Term, subject to earlier final satisfaction of its cumulative revenue 17

responsibility under CRA Sections 3.2 and 6.7. The obligation for a Rate Year would 18

reflect the Covered Upgrades then subject to the commitment, with the applicable partial- 19

year proration. As additional upgrades enter service, their contributions would be added to 20

the customer’s combined annual obligation. The same approach would identify when each 21

upgrade’s term ends. An upgrade that has not yet entered service would remain subject to 22

PDF page 25

22
the applicable construction-security and cancellation provisions rather than being treated as 1

though it had already begun its operational MTRC Term.
2

Customer- and Covered Upgrade-specific workpapers show the applicable terms, proration, 3

qualifying-revenue attribution or allocation, and resulting Supplemental MTRC. 4

Aggregating the presentation would not erase each Covered Upgrade’s separate term or 5

permit the same qualifying revenue to satisfy more than one obligation. 6

Q.
WHAT CALCULATION MATERIALS SUPPORT THE CRA?
7
A. Schedule 5 includes an unpopulated MTRC Calculation Template and the supporting FCR 8

calculation needed to derive the Annual MTRC. A separate populated illustration is 9

provided as an exhibit to my testimony as GNY-101, rather than included in the pro forma 10

CRA, and will show how the inputs produce the Annual MTRC, Supplemental MTRC, 11

Total Required Revenue Commitment, and projected security balances. The supporting 12

calculations permit review and replication of the contractual calculation. 13

The supplemental ratepayer-protection illustration below compares the combined RTFC 14

with and without CRA revenue credits and demonstrates how the supplemental obligation 15

changes when qualifying load falls short. It uses disclosed assumptions and is separate from 16

the formal CRA calculation exhibit. It does not allocate the illustrated benefit among 17

customers.
18
Q.
WHAT DOES THE NUMERICAL ILLUSTRATION DEMONSTRATE?
19
A. The proposed CRA revenue credits reduce the combined RTFC by $6,195,840 under the 20

assumptions in Exhibit No. GNY-204. This illustration holds the same investment, load, 21

ordinary revenue credits, and formula-rate true-up constant. It isolates the effect of CRA 22

support rather than comparing the upgrades against a system in which they were never 23

PDF page 26

23
built. Table 1 presents the comparison for the illustrative Rate Year 2030. The table shows 1

projected CRA revenue credits; in an Annual Update, the credits would reflect actual cash 2

receipts. Any collection shortfall would affect the ordinary formula-rate true-up rather than 3

change the Eligible Customer’s underlying obligation.
4
Table 1. Reduction in the Combined RTFC1
Annual calculation
Without CRA credits
With CRA credits
Gross formula-rate revenue requirement
$144,314,351
$144,314,351
Ordinary revenue credits
($100,000)
($100,000)
Supplemental MTRC including prior-period
adjustments
$0
($2,622,030)
Annual Termination Fee Remittances
$0
($3,573,810)
Formula-rate true-up adjustment
$702,705
$702,705
Combined RTFC
$144,917,056
$138,721,216
Reduction in combined RTFC
—
$6,195,840

The reduction equals approximately 4.28% of the otherwise applicable combined RTFC. 5

Of the $2,622,030 projected Supplemental MTRC credit, $2,545,410 represents current- 6

year Supplemental MTRC and $76,620 represents net prior-period adjustments. The 7

$3,573,810 termination credit is the annual remittance from funds held by NYISO, not the 8

entire termination fee.
9

The $6,195,840 is a reduction in the combined RTFC, including any portion paid on behalf 10

of large loads. Segment A’s existing tariff cost allocation would apply to the reduced RTFC 11

as described in my testimony. This example does not quantify how the reduction is 12

distributed among customers or the savings realized exclusively by other customers. 13

1 Source: Exhibit No. GNY-204, Appendix A, Lines 1–5 and Large Load CRA Revenue Lines a–c; Attachment 1a, Lines 1–4 and 11–13. Ordinary revenue credits equal total revenue credits less Large Load CRA Revenue. Amounts are calculated at full precision and displayed in whole dollars.

PDF page 27

24
Q.
HOW DOES THE FRAMEWORK RESPOND WHEN THE LARGE LOAD TAKES
1
LESS SERVICE THAN EXPECTED?
2
A. Project 1 assumes $60 million of capital cost, a $7,320,060 Annual MTRC, 8,760 billing 3

hours, and an illustrative qualifying rate of $1.75/MWh. The upgrade is in service for the 4

full year in each condition. Prior-period adjustments are excluded to isolate the annual 5

obligation. Table 2 compares expected load, reduced use after service begins, and delayed 6

load commencement.
7
Table 2. Project Load Shortfall Illustration2
Annual calculation
Expected load
Reduced load
Delayed load
Qualifying load
400 MW
200 MW
0 MW
Qualifying Transmission Revenues
$6,132,000
$3,066,000
$0
Annual MTRC
$7,320,060
$7,320,060
$7,320,060
Supplemental MTRC
$1,188,060
$4,254,060
$7,320,060
Qualifying revenues plus
Supplemental MTRC
$7,320,060
$7,320,060
$7,320,060

Qualifying Transmission Revenues = qualifying MW × 8,760 × $1.75/MWh. Supplemental 8

MTRC = the positive difference between Annual MTRC and Qualifying Transmission 9

Revenues. The 200 MW condition represents reduced use after service begins; the 0 MW 10

condition represents delayed commencement after the upgrade enters service. 11

The qualifying rate is held constant to isolate the shortfall mechanism. This is not a 12

calculation of actual NYISO billing rates, billing denominators, or customer shares. 13

Qualifying revenues reduce the supplemental obligation; they are not credited a second 14

time against the formula-rate revenue requirement.
15

2 Source: GNY-101, CRA Exhibit, Annual MTRC and Project 1 inputs; Exhibit No. GNY-204, Attachment 1a, Line 1 and qualifying-revenue workpaper Line 14. The 200 MW and 0 MW conditions are additional illustrative assumptions.

PDF page 28

25

The responsible Eligible Customer’s supplemental obligation increases as qualifying 1

revenues decline. For Project 1, reducing qualifying load from 400 MW to 200 MW lowers 2

qualifying revenues by $3,066,000 and increases annual Supplemental MTRC by the same 3

amount, from $1,188,060 to $4,254,060. If the upgrade is in service but the load has not 4

commenced service for the full year, the annual supplemental obligation equals the 5

$7,320,060 Annual MTRC. These amounts represent the annual obligation as finally 6

reconciled. Forecast differences can affect billing timing, with the customer-level 7

adjustment reflected in Rate Year Y+2. Security supports payment but posting security is 8

not itself a revenue credit. The illustration shows the contractual amounts due, rather than 9

cash collections. Any unpaid amount not satisfied from Security would be excluded from 10

the actual revenue credit and reflected in the ordinary formula-rate true-up, with applicable 11

interest; a later recovery would be credited when received.
12
Q.
HOW WOULD THE CRA ADDRESS CANCELLATION AND DEFAULT?
13
A. Before a Covered Upgrade enters service, construction security would cover the costs and 14

cancellation exposure specified in the CRA. After the Covered Upgrade enters service, 15

Required Operational Security would equal the nominal Remaining Cumulative Revenue 16

Responsibility, except to the extent satisfied by qualifying retail security support. The Total 17

Required Revenue Commitment is based on the applicable Annual MTRC over its twenty- 18

year term. Recognized Qualifying Transmission Revenues, Supplemental MTRC receipts, 19

applied security proceeds, and other permitted adjustments would reduce the remaining 20

commitment without double counting. Exhibit GNY-101 provided with my testimony 21

includes a forecast security schedule illustrating expected reductions assuming settlement; 22

projected collections alone do not discharge the secured obligation.
23

PDF page 29

26
NYISO would hold and draw security under the proposed tariff provisions, and LSPGNY 1

would maintain the Cumulative Revenue Ledger and provide the required supporting 2

calculations and notices. These arrangements provide timely access and remittance for 3

upgrades covered by the proposed CRA where LSPGNY is the Connecting Transmission 4

Owner. Comparable arrangements for LSPGNY as an Affected Transmission Owner 5

remain to be resolved. Qualifying retail security support could satisfy the corresponding 6

wholesale security requirement only to the extent it is legally available for that obligation 7

under the CRA and tariff. Security does not limit the Eligible Customer’s underlying 8

liability, and LSPGNY’s tariff recovery would remain subject to the applicable 9

Commission-approved recovery provisions.
10
Q.
HOW WOULD TERMINATION FUNDS BE HANDLED AFTER AN UPGRADE
11
ENTERS SERVICE?
12
A. Under CRA Section 3.3.4, when the applicable termination provisions are triggered, the 13

Eligible Customer owes a Termination Fee equal to the Remaining Cumulative Revenue 14

Responsibility less any Supplemental MTRC already billed and remaining unpaid as of the 15

effective termination or cessation date. Those unpaid bills remain separately payable as 16

Large Load Charges. NYISO’s receipt of the Termination Fee in full, including qualifying 17

applied security proceeds, would discharge only the remaining contractual revenue 18

responsibility included in that fee; it would not discharge the billed and unpaid 19

Supplemental MTRC excluded from the fee. NYISO would hold the fee in a segregated 20

Termination Fee Account and remit it to LSPGNY over the remaining MTRC Term under 21

CRA Section 3.3.6. Each Annual Termination Fee Remittance would equal the Annual 22

MTRC for the Covered Upgrade for each Rate Year remaining in its MTRC Term, prorated 23

PDF page 30

27
for partial Rate Years, until the balance is exhausted. Any balance remaining at the end of 1

the MTRC Term, including actual account earnings, would be remitted with the final 2

remittance. The full fee would not immediately become an LSPGNY formula-rate credit. 3

Each Annual Termination Fee Remittance would be projected in the Annual Projection and 4

reflected as a general revenue credit in the Annual Update for the Rate Year in which 5

LSPGNY actually receives it, and would not reduce the contractual commitment a second 6

time. Actual earnings on held termination funds are distinct from interest on customer-level 7

reconciliation adjustments.
8
Q.
HOW WOULD THE FORMULA RATE PREVENT DUPLICATE RECOVERY?
9
A. LSPGNY would separately track assigned upgrade costs, Qualifying Transmission 10

Revenues, Supplemental MTRC billed, Supplemental MTRC receipts, applied security 11

proceeds, and Annual Termination Fee Remittances. Qualifying Transmission Revenues 12

reduce the Supplemental MTRC shortfall and would not be counted again as a separate 13

CRA formula-rate credit. The Annual Update would credit Supplemental MTRC actually 14

received, including applicable Security proceeds received and applied to that obligation and 15

amounts LSPGNY recovers directly from the Eligible Customer. Later collections of 16

previously unpaid amounts would be credited in the year received, even if the earlier 17

collection shortfall was recovered through the ordinary formula-rate true-up. Each receipt 18

would be credited only once. Recovery through the RTFC would not discharge the Eligible 19

Customer’s unpaid CRA obligation, and any subsequent recovery from that customer 20

would reduce the formula-rate revenue requirement through the receipt-based credit. 21

Posting or holding security does not constitute payment. Amounts applied to an identified 22

obligation would be recognized once in the Cumulative Revenue Ledger, while formula- 23

PDF page 31

28
rate credits would be reflected as provided in the template. The workpapers distinguish 1

satisfaction of the contractual commitment from recognition of amounts in rates. 2

Attachment 1a and the supporting workpapers identify the applicable Annual MTRC, 3

Qualifying Transmission Revenues, and Supplemental MTRC by Eligible Customer and 4

Covered Upgrade. Projected Supplemental MTRC and Annual Termination Fee 5

Remittances in the Annual Projection, replaced by actual receipts in the Annual Update, 6

would flow through the formula rate as Large Load CRA Revenue, a revenue credit on 7

Appendix A, Line 2, that is spread through the base carrying charge rather than applied to 8

individual Covered Upgrades. The customer-level true-up would be calculated on 9

Attachment 5. Amounts would be traceable to billing and settlement records and applicable 10

FERC Form No. 1 accounts. These records prevent duplicate recognition of CRA amounts 11

and distinguish customer-level true-up adjustments from LSPGNY’s revenue-requirement 12

true-up. Segment A’s existing tariff cost allocation would apply to the single RTFC that 13

combines Segment A and Large Load-Driven Upgrade revenue requirements, net of the 14

applicable general CRA revenue credits.
15
VI. TARIFF AND PROTOCOL REVISIONS
16
Q.
WHAT CHANGES ARE NEEDED TO PUT THE FRAMEWORK INTO EFFECT?
17
A. LSPGNY proposes revisions to Rate Schedule 10 to authorize recovery of eligible Large 18

Load-Driven Upgrade costs through its company-specific formula rate and establish the 19

associated CRA framework. The proposed tariff revisions retain the requirement for a 20

section 205 filing and Commission acceptance adding an upgrade to Table 1 before its 21

revenue requirement enters the RTFC. They provide that Large Load-Driven Upgrade 22

revenue requirements are combined with Segment A’s revenue requirement in a single 23

PDF page 32

29
RTFC using Segment A’s existing tariff cost allocation. Table 1 identifies eligible upgrades 1

without establishing separate zonal or subzonal allocations for them. Supplemental MTRC 2

is billed to the responsible Eligible Customer. The tariff, formula rate template, and 3

protocols would consistently recognize projected CRA revenue in the Annual Projection 4

and actual cash receipts in the Annual Update, with receipt-related differences reflected 5

through the ordinary formula-rate true-up and its applicable interest provisions. The 6

Eligible Customer would remain liable for unpaid amounts, and later recoveries would be 7

credited when received. Section 3.08(a) of LSPGNY’s Operating Agreement reserves a 8

filing right for recovery of reasonably incurred costs and a reasonable return for services 9

under the OATT.
10
Q.
WHAT DO THE FORMULA RATE IMPLEMENTATION PROTOCOLS
11
PROVIDE?
12
A. The Annual Projection and Annual Update include upgrade-specific workpapers showing 13

the applicable Annual MTRC, forecast Qualifying Transmission Revenues, projected 14

Supplemental MTRC, the Total Required Revenue Commitment, and Required Operational 15

Security. The Annual Update workpapers would reconcile projected CRA revenue credits 16

to actual Supplemental MTRC cash receipts, applicable Security proceeds received and 17

applied to those obligations, and Annual Termination Fee Remittances received. They 18

would separately identify billed amounts, unpaid balances, later collections of prior-year 19

bills, and refunds of previously credited receipts, and reconcile receipt-based credits to 20

FERC Form No. 1 accounting amounts. Workpapers would be organized by Eligible 21

Customer, Large Load Facility, and Covered Upgrade. The Reconciliation Statement 22

supports the separate customer-level adjustment based on actual Qualifying Transmission 23

PDF page 33

30
Revenues, without interest and without duplicating that adjustment. Differences between 1

projected CRA revenue credits and actual receipts would be reconciled through the 2

ordinary formula-rate true-up under Protocols Section 2.B, with interest under Section 2.C. 3

Workpapers identify the relevant template lines, reconcile billed and received amounts, and 4

distinguish customer-level true-up adjustments from over- or under-recovery of LSPGNY’s 5

revenue requirement. The Annual Update would be prepared by June 30 following the Rate 6

Year, with the ordinary true-up included in the next Annual Projection prepared after the 7

Annual Update for the following Rate Year. Projection workpapers would disclose prior- 8

year unpaid Supplemental MTRC balances separately. Expected collections of those 9

balances would be excluded from Projected Large Load CRA Revenue and credited as 10

Actual Large Load CRA Revenue only in the Rate Year in which received.
11
Interested parties would be able to review the data, calculations, and application of the filed 12

formula rate under the protocols. The protocols add the parties to each CRA to the service 13

list and require confidential treatment of customer-specific information, with aggregated or 14

redacted public versions. The review would test whether the CRA amounts were correctly 15

reflected in rates. The process would leave the underlying contractual commitment to the 16

CRA and applicable tariff and Commission procedures.
17
Q.
DOES THIS CONCLUDE YOUR TESTIMONY?
18
A. Yes.
19

PDF page 34

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

LS Power Grid New York Corporation I
New York Independent System Operator, Inc.
)
)
)
)
Docket No. ER27-___-000
Docket No. EL26-69-000

VERIFICATION
I, Patrick Hayes, verify under penalty of perjury that I have read the testimony, know the contents thereof, and that the facts and representations set forth therein are true to the best of my knowledge, information and belief.

_/s/ Patrick Hayes________________
Patrick Hayes
Date __November 14, 2026_________