ER27-518-000 · 2026-11-16 · LS Power Grid New York Corporation INew York Independent System Operator, Inc.

Hayes Testimony (Exhibit No. GNY-100)

Text extracted from the eLibrary original (SHA-256 2c05f52efd032a1f…). Download the original from the official source.

Contents · 35 sections
  1. I. INTRODUCTION AND EXPERIENCE p. 4
  2. A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310, p. 4
  3. II. PURPOSE AND SCOPE OF TESTIMONY p. 5
  4. A. Yes. I am sponsoring the following exhibits: p. 6
  5. III. THE NYISO SHOW CAUSE ORDER p. 6
  6. A. On June 18, 2026, the Federal Energy Regulatory Commission (“Commission” or “FERC”) p. 6
  7. A. LSPGNY is a Transmission Owner for purposes of the NYISO tariffs under its Operating p. 7
  8. IV. NYISO STAKEHOLDER PROCESS p. 8
  9. A. LSPGNY discussed load study procedures with NYISO staff in late 2025 and participated p. 8
  10. A. On July 20, 2026, LSPGNY contacted counsel for the New York Transmission Owners p. 9
  11. A. The discussions identified the need for a rate provision that works for non-incumbent p. 10
  12. V. COST RECOVERY AGREEMENT p. 10
  13. A. LSPGNY proposes a pro forma CRA between LSPGNY and the Eligible Customer taking p. 10
  14. A. The study results would identify the Covered Upgrades and the responsibility to be p. 11
  15. A. The applicable study would identify the upgrades needed to serve the requested load and p. 12
  16. A. The CRA establishes an Annual Minimum Transmission Revenue Contribution (“Annual p. 15
  17. A. The Annual MTRC is a levelized contractual amount calculated using the inputs specified p. 17
  18. A. Capital cost alone does not measure the full revenue contribution associated with an p. 17
  19. A. No. The Eligible Customer and the transmission customers responsible for the combined p. 19
  20. A. LSPGNY would include the projected Supplemental MTRC, including any prior-period p. 20
  21. A. Reflecting projected Supplemental MTRC allows the expected contribution to reduce the p. 21
  22. A. Before Rate Year Y, the Annual Projection would include the projected revenue p. 22
  23. A. The customer-level true-up of the difference between the Supplemental MTRC billed for p. 23
  24. A. Exhibit No. GNY-204, Attachment 1a, illustrates an Annual MTRC of $7,320,060 and p. 24
  25. A. Each Covered Upgrade would have its own applicable in-service date, Annual MTRC, and p. 24
  26. A. Schedule 5 includes an unpopulated MTRC Calculation Template and the supporting FCR p. 25
  27. A. The proposed CRA revenue credits reduce the combined RTFC by $6,195,840 under the p. 25
  28. A. Project 1 assumes $60 million of capital cost, a $7,320,060 Annual MTRC, 8,760 billing p. 27
  29. A. Before a Covered Upgrade enters service, construction security would cover the costs and p. 28
  30. A. Under CRA Section 3.3.4, when the applicable termination provisions are triggered, the p. 29
  31. A. LSPGNY would separately track assigned upgrade costs, Qualifying Transmission p. 30
  32. VI. TARIFF AND PROTOCOL REVISIONS p. 31
  33. A. LSPGNY proposes revisions to Rate Schedule 10 to authorize recovery of eligible Large p. 31
  34. A. The Annual Projection and Annual Update include upgrade-specific workpapers showing p. 32
  35. A. Yes. p. 33

Read the parent filing

Topics in the text: Cost allocation · Credit and exit · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

EL26-69-000 DIRECT TESTIMONY OF PATRICK HAYES ON BEHALF OF LS POWER GRID NEW YORK CORPORATION I Large Load Network Upgrade Cost Recovery November 2026
Read this passage

TABLE OF CONTENTS

printed heading

Description GNY-101: Illustrative MTRC Calculation GNY-102: Example Reconciliation Statement GNY-103: Example Charge Statement 1 DIRECT TESTIMONY OF PATRICK HAYES
Read this passage

I. INTRODUCTION AND EXPERIENCE

printed heading

I.
Read this passage

A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310,

printed heading · Topic match: Cost allocation

My 10 responsibilities include FERC policy, regional transmission planning, competitive 11 transmission development, cost allocation and recovery, tariff development, and large-load 12 interconnection. 13 Q.
Read this passage

II. PURPOSE AND SCOPE OF TESTIMONY

printed heading · Topic match: Cost allocation

I explain how LSPGNY proposes to recover the costs of Large Load-Driven Upgrades on 10 its facilities and protect other transmission customers from bearing costs caused by a large 11 load.
Read this passage

A. Yes. I am sponsoring the following exhibits:

printed heading

I am sponsoring the following exhibits: 10 Exhibit No.
Read this passage

III. THE NYISO SHOW CAUSE ORDER

printed heading

WHAT DID THE COMMISSION DIRECT IN THIS PROCEEDING? 12
Read this passage

A. On June 18, 2026, the Federal Energy Regulatory Commission (“Commission” or “FERC”)

printed heading · Topic match: Filing procedure

The Commission granted a 90-day abeyance on August 14, 2026, setting 19 November 16, 2026, as the response deadline, subject to the order’s provision for a 20 4 respondent that makes a timely section 205 filing addressing the preliminary findings.
Read this passage

A. LSPGNY is a Transmission Owner for purposes of the NYISO tariffs under its Operating

printed heading · Topic match: Retail and wholesale authority

It has no franchised retail service territory or obligation to serve 18 retail load and has no Transmission Service Charge (“TSC”) under Attachment H.
Read this passage

IV. NYISO STAKEHOLDER PROCESS

printed heading

IV.
Read this passage

A. LSPGNY discussed load study procedures with NYISO staff in late 2025 and participated

printed heading · Topic match: Credit and exit

In written comments on 23 6 NYISO’s July 23 stakeholder presentation, submitted July 27, LSPGNY requested 1 additional time for stakeholder review, urged a coordinated filing, and asked NYISO to 2 address how a Transmission Owner without retail load would participate as a Connecting 3 or Affected…
Read this passage

A. On July 20, 2026, LSPGNY contacted counsel for the New York Transmission Owners

printed heading

The NYTOs declined both requests. 20 LSPGNY continued to participate in NYISO’s Transmission Owner working sessions.
Read this passage

A. The discussions identified the need for a rate provision that works for non-incumbent

printed heading

The discussions identified the need for a rate provision that works for non-incumbent 10 Transmission Owners and for NYISO settlement rules that put that provision into effect. 11 The coordinated process did not yield a joint proposal that resolved both issues for 12 LSPGNY within the time…
Read this passage

V. COST RECOVERY AGREEMENT

printed heading

WHO WOULD ENTER INTO THE CRA, AND WHAT WOULD IT COVER? 20
Read this passage

A. LSPGNY proposes a pro forma CRA between LSPGNY and the Eligible Customer taking

printed heading

LSPGNY proposes a pro forma CRA between LSPGNY and the Eligible Customer taking 21 wholesale transmission service on behalf of the large load where LSPGNY is the 22 Connecting Transmission Owner.
Read this passage

A. The study results would identify the Covered Upgrades and the responsibility to be

printed heading · Topic match: Retail and wholesale authority

The appropriate arrangement will depend 2 on the scope of the other Transmission Owners’ proposed agreements and the associated 3 tariff provisions. 4 LSPGNY needs a mechanism to recover its affected-system upgrade costs and obtain 5 access to the supporting security without a retail service…
Read this passage

A. The applicable study would identify the upgrades needed to serve the requested load and

printed heading · Topic match: Cost allocation

The CRA documents the Eligible Customer’s 14 responsibility for the applicable Covered Upgrades, including assigned shares where 15 multiple requests contribute to the need for an upgrade.
Read this passage

A. The CRA establishes an Annual Minimum Transmission Revenue Contribution (“Annual

printed heading

The CRA establishes an Annual Minimum Transmission Revenue Contribution (“Annual 10 MTRC”) for each Covered Upgrade using the separate MTRC Calculation Template in 11 Schedule 5.
Read this passage

A. The Annual MTRC is a levelized contractual amount calculated using the inputs specified

printed heading

The Annual MTRC is a levelized contractual amount calculated using the inputs specified 8 in the CRA.
Read this passage

A. Capital cost alone does not measure the full revenue contribution associated with an

printed heading · Topic match: Credit and exit

DOES THE CRA REPLACE ORDINARY TRANSMISSION-SERVICE PAYMENT 19 OR COLLATERAL OBLIGATIONS? 20
Read this passage

A. No. The Eligible Customer and the transmission customers responsible for the combined

printed heading · Topic match: Credit and exit

Ordinary 5 transmission-service credit requirements continue to apply under the governing tariff. 6 Qualifying retail security support may satisfy the corresponding CRA security exposure 7 only to the extent the CRA and tariff recognize it and the support is legally available when 8 needed. 9 Q.
Read this passage

A. LSPGNY would include the projected Supplemental MTRC, including any prior-period

printed heading

LSPGNY would include the projected Supplemental MTRC, including any prior-period 11 true-up adjustment, and any projected Annual Termination Fee Remittances as a credit in 12 the Annual Projection in accordance with the formula rate template, and NYISO would bill 13 and remit the applicable…
Read this passage

A. Reflecting projected Supplemental MTRC allows the expected contribution to reduce the

printed heading

Reflecting projected Supplemental MTRC allows the expected contribution to reduce the 14 amount initially recovered from other transmission customers under the template.
Read this passage

A. Before Rate Year Y, the Annual Projection would include the projected revenue

printed heading

Before Rate Year Y, the Annual Projection would include the projected revenue 15 requirement and a credit for the projected Supplemental MTRC and any Annual 16 Termination Fee Remittances for that year.
Read this passage

A. The customer-level true-up of the difference between the Supplemental MTRC billed for

printed heading

The customer-level true-up of the difference between the Supplemental MTRC billed for 11 the Rate Year, excluding any prior-period true-up adjustment included in that billing, and 12 the actual Supplemental MTRC would not bear interest in either direction.
Read this passage

A. Exhibit No. GNY-204, Attachment 1a, illustrates an Annual MTRC of $7,320,060 and

printed heading

GNY-204, Attachment 1a, illustrates an Annual MTRC of $7,320,060 and 2 projected Qualifying Transmission Revenues of $6,132,000 for Customer A’s Large Load 3 Project 1, producing projected Supplemental MTRC of $1,188,060 before prior-period 4 adjustments.
Read this passage

A. Each Covered Upgrade would have its own applicable in-service date, Annual MTRC, and

printed heading

Each Covered Upgrade would have its own applicable in-service date, Annual MTRC, and 16 twenty-year MTRC Term, subject to earlier final satisfaction of its cumulative revenue 17 responsibility under CRA Sections 3.2 and 6.7.
Read this passage

A. Schedule 5 includes an unpopulated MTRC Calculation Template and the supporting FCR

printed heading · Topic match: Cost allocation

The supporting 12 calculations permit review and replication of the contractual calculation. 13 The supplemental ratepayer-protection illustration below compares the combined RTFC 14 with and without CRA revenue credits and demonstrates how the supplemental obligation 15 changes when qualifying…
Read this passage

A. The proposed CRA revenue credits reduce the combined RTFC by $6,195,840 under the

printed heading · Topic match: Cost allocation

Segment A’s existing tariff cost allocation would apply to the reduced RTFC 11 as described in my testimony.
Read this passage

A. Project 1 assumes $60 million of capital cost, a $7,320,060 Annual MTRC, 8,760 billing

printed heading

Project 1 assumes $60 million of capital cost, a $7,320,060 Annual MTRC, 8,760 billing 3 hours, and an illustrative qualifying rate of $1.75/MWh.
Read this passage

A. Before a Covered Upgrade enters service, construction security would cover the costs and

printed heading

Before a Covered Upgrade enters service, construction security would cover the costs and 14 cancellation exposure specified in the CRA.
Read this passage

A. Under CRA Section 3.3.4, when the applicable termination provisions are triggered, the

printed heading

Under CRA Section 3.3.4, when the applicable termination provisions are triggered, the 13 Eligible Customer owes a Termination Fee equal to the Remaining Cumulative Revenue 14 Responsibility less any Supplemental MTRC already billed and remaining unpaid as of the 15 effective termination or…
Read this passage

A. LSPGNY would separately track assigned upgrade costs, Qualifying Transmission

printed heading · Topic match: Cost allocation

Segment A’s existing tariff cost allocation would apply to the single RTFC that 13 combines Segment A and Large Load-Driven Upgrade revenue requirements, net of the 14 applicable general CRA revenue credits. 15
Read this passage

VI. TARIFF AND PROTOCOL REVISIONS

printed heading

WHAT CHANGES ARE NEEDED TO PUT THE FRAMEWORK INTO EFFECT? 17
Read this passage

A. LSPGNY proposes revisions to Rate Schedule 10 to authorize recovery of eligible Large

printed heading · Topic match: Cost allocation

LSPGNY proposes revisions to Rate Schedule 10 to authorize recovery of eligible Large 18 Load-Driven Upgrade costs through its company-specific formula rate and establish the 19 associated CRA framework.
Read this passage

A. The Annual Projection and Annual Update include upgrade-specific workpapers showing

printed heading

The Annual Projection and Annual Update include upgrade-specific workpapers showing 13 the applicable Annual MTRC, forecast Qualifying Transmission Revenues, projected 14 Supplemental MTRC, the Total Required Revenue Commitment, and Required Operational 15 Security.
Read this passage

A. Yes.

printed heading

Yes. 19 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION LS Power Grid New York Corporation I New York Independent System Operator, Inc. ) ) ) ) Docket No.
Read this passage