LSPGNY 205: Proposed Revisions re: RS10 Large Load-Driven Upgrade Cost Recovery
LS Power Grid New York Corporation I files revisions to Rate Schedule 10 of the NYISO tariff under section 205 on November 16, 2026, in ER27-518-000, answering the New York show cause order. It adds a pro forma cost recovery agreement with a 20-year minimum revenue contribution, security and NYISO billing. No upgrade is yet listed, so current rates do not change.
Asks FERC to: Accept the revisions effective January 16, 2027, 61 days after filing, and grant the requested waivers.
Filed under section 205 to answer the E-12 show cause order for NYISO. It covers cost recovery for one non-incumbent owner with no retail customers, separate from NYISO's and the other owners' filings.
E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Cost transparency (P 73, p. 47)
Key points
- LS Power Grid proposes a company-specific way to recover the cost of upgrades driven by large loads.
a transparent, company-specific mechanism for LS Power Grid to recover the costs of transmission upgrades that are identified as necessary PDF p. 2
- No upgrade is listed yet, so the filing does not change current rates.
No Large Load-Driven Upgrade is listed in proposed Table 1 as of the requested effective date PDF p. 2
- An upgrade enters the rate only after a separate section 205 filing adds it to the table.
a Large Load-Driven Upgrade becomes an Eligible Project only after Commission acceptance of a section 205 filing adding it to Table 1 PDF p. 4
- The agreement sets a fixed annual minimum revenue contribution for each covered upgrade.
the CRA establishes a fixed Annual Minimum Transmission Revenue Contribution (“Annual MTRC”) PDF p. 4
- The contribution runs 20 years from the upgrade's in-service date.
MTRC Term begins on the actual Upgrade In-Service Date and ends on the day immediately preceding its twentieth anniversary PDF p. 5
- Operational security equals all remaining revenue responsibility.
The CRA requires Operational Security equal to one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility PDF p. 6
- Retail security can offset it dollar for dollar if the customer certifies it is available and enforceable.
the direct Operational Security requirement may be reduced dollar-for-dollar by qualifying retail security support only where the Eligible Customer delivers a current Retail Security Certification PDF p. 6
- It calls the termination fee an accelerated contractual charge, not a penalty.
The Termination Fee is an accelerated contractual termination charge, not a penalty PDF p. 5
Text extracted from the eLibrary original (SHA-256 5066b78c9fce11ad…). Download the original from the official source.
Contents · 15 sections
- I. Introduction and Summary of Filing
- II. Background
- A. LS Power Grid and its Rate Schedule 10 Recovery
- B. Show Cause Order and Stakeholder Process
- III. Description of the Proposed Revisions
- A. Rate Schedule 10 Eligibility and Cost Allocation
- B. Pro Forma CRA
- C. Revenue Attribution, Allocation, and Rate Treatment
- D. NYISO Billing Security and Remittance Functions
- E. Supporting Testimony and Illustrative Exhibits
- IV. The Proposed Revisions Are Just and Reasonable
- V. Requested Effective Date and Waivers
- VI. Contents of Filing
- VII. Communications and Service
- VIII. Conclusion
Topics in the text: Cost allocation · Filing procedure · Credit and exit
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
LS Power Grid respectfully requests that the Commission accept the proposed tariff revisions to become effective January 16, 2027, sixty-one (61) days after filing, consistent with the Commission’s prior notice requirement, 5 and grant any necessary waivers. 1 16 U.S.C. § 824d (2022). 2 18 C.F.R.Read this passage
I. Introduction and Summary of Filing
printed heading · Topic match: Cost allocation
The filing responds to the Commission’s preliminary concerns regarding potential cost shifting by assigning the wholesale payment obligation to the Eligible Customer that takes or requests transmission service on behalf of the Large Load Facility and by requiring Construction Security, Operational…Read this passage
II. Background
printed heading
II.Read this passage
A. LS Power Grid and its Rate Schedule 10 Recovery
printed heading · Topic match: Retail and wholesale authority
LS Power Grid has no franchised retail service territory and no Transmission Service Charge under Attachment H of the NYISO OATT.Read this passage
B. Show Cause Order and Stakeholder Process
printed heading · Topic match: Cost allocation
It does not displace the separate arrangements that an Eligible Customer must enter into with the owner of an Affected System for an Affected System Upgrade.9Read this passage
III. Description of the Proposed Revisions
printed heading
III.Read this passage
A. Rate Schedule 10 Eligibility and Cost Allocation
printed heading · Topic match: Cost allocation
Rate Schedule 10 Eligibility and Cost Allocation New Section 6.10.1.1(xii) identifies a Large Load-Driven Upgrade of a Transmission Owner or Other Developer that does not recover a transmission revenue 7 Show Cause Order at PP 72-91. 8 N.Y.Read this passage
B. Pro Forma CRA
printed heading · Topic match: Cost allocation
The certification must confirm that the retail Large Load Customer has posted security available to the Eligible Customer for the corresponding wholesale obligations and that the Eligible Customer has enforceable draw or application rights, or the benefit of a binding undertaking, permitting it to…Read this passage
C. Revenue Attribution, Allocation, and Rate Treatment
printed heading
Revenue Attribution, Allocation, and Rate Treatment Qualifying Transmission Revenues are not a separate retail or load-based charge imposed by LS Power Grid.Read this passage
D. NYISO Billing Security and Remittance Functions
printed heading
NYISO Billing Security and Remittance Functions New Section 6.10.3.7 confirms that the Attachment-level Large Load Provisions are part of Rate Schedule 10, directs NYISO to perform the functions assigned to it under those provisions, distinguishes Large Load Charges from RTFC charges and revenues,…Read this passage
E. Supporting Testimony and Illustrative Exhibits
printed heading
Supporting Testimony and Illustrative Exhibits Mr.Read this passage
IV. The Proposed Revisions Are Just and Reasonable
printed heading
The Proposed Revisions Are Just and Reasonable The proposal materially mitigates the cost-shifting concern identified in the Show Cause Order.Read this passage
V. Requested Effective Date and Waivers
printed heading
Requested Effective Date and Waivers LS Power Grid requests an effective date of January 16, 2027, sixty-one (61) days after the date of this filing, satisfying the Commission’s sixty-day notice requirement.23 LS Power Grid requests waiver of the cost-of-service-statement requirements of 18 C.F.R.…Read this passage
VI. Contents of Filing
printed heading
Contents of Filing LS Power Grid submits the following materials: • This transmittal letter; 23 18 C.F.R. § 35.3(a)(1).Read this passage
VII. Communications and Service
printed heading
Communications and Service LS Power Grid requests that all pleadings, correspondence, and other communications concerning this matter be directed to the following persons, and their names and addresses be placed on the official service list for this docket: Patrick Hayes LS Power Development, LLC…Read this passage
VIII. Conclusion
printed heading
Conclusion For the reasons stated above and in the supporting testimony, LS Power Grid respectfully requests that the Commission accept the proposed tariff revisions effective January 16, 2027, subject to the requested waivers.Read this passage
CERTIFICATE OF SERVICE
printed heading
EL26-69-000 and upon each other person entitled to service under the Commission’s regulations.Read this passage