ER27-518-000 · 2026-11-16 · LS Power Grid New York Corporation INew York Independent System Operator, Inc.

LSPGNY 205: Proposed Revisions re: RS10 Large Load-Driven Upgrade Cost Recovery

PDF page 1

13 Corporate Drive, Halfmoon, NY 12065
lspowergrid.com
November 16, 2026
VIA ETARIFF
The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.

Washington, D.C. 20426

Re:
LS Power Grid New York Corporation I, Docket No. ER27-___-000
New York Independent System Operator, Inc., Docket No. EL26-69-000
Proposed Revisions to Rate Schedule 10 of the NYISO OATT to Provide
for Large Load-Driven Upgrade Cost Recovery

Dear Secretary Reese:
Pursuant to section 205 of the Federal Power Act (“FPA”)1 and Part 35 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) regulations, 2 and in response to the Commission’s order instituting the show-cause proceeding in New York Independent System Operator, Inc.,3 LS Power Grid New York Corporation I (“LS Power Grid”)4 submits revisions to Section 6.10 (Rate Schedule 10) of the NYISO OATT, specifically the generally applicable provisions of Rate Schedule 10 and LS Power Grid’s company-specific provisions in Attachment 1 to Rate Schedule 10, Section 6.10.7. LS Power Grid respectfully requests that the Commission accept the proposed tariff revisions to become effective January 16, 2027, sixty-one (61) days after filing, consistent with the Commission’s prior notice requirement, 5 and grant any necessary waivers.

1 16 U.S.C. § 824d (2022). 2 18 C.F.R. Pt. 35 (2026). 3 195 FERC ¶ 61,216 (2026) (“Show Cause Order”).
4 The New York Independent System Operator, Inc. ("NYISO") is submitting this filing via eTariff on behalf of LS Power Grid solely in its role as the tariff administrator of the NYISO Open Access Transmission Tariff ("OATT"). The burden of demonstrating that the proposed tariff amendments are just and reasonable rests with LS Power Grid, the sponsoring party. The NYISO takes no position on any substantive aspect of the filing at this time and reserves the right to file comments and/or protest the filing. 5 18 C.F.R. § 35.3(a)(1).

PDF page 2

Page 2
I. Introduction and Summary of Filing
The proposed revisions establish a transparent, company-specific mechanism for LS Power Grid to recover the costs of transmission upgrades that are identified as necessary, in whole or in part, to provide transmission service to an Eligible Customer6 on behalf of a Large Load (“Large Load-Driven Upgrades”). The revisions include a pro forma Large Load Cost Recovery Agreement (“CRA”), revisions to the Formula Rate Template (“Template”) and Formula Rate Implementation Protocols (“Protocols”), cost-allocation provisions, and new Rate Schedule 10 provisions governing NYISO billing, collection, security, remittance, data exchange, and formula rate treatment of CRA amounts.

The filing responds to the Commission’s preliminary concerns regarding potential cost shifting by assigning the wholesale payment obligation to the Eligible Customer that takes or requests transmission service on behalf of the Large Load Facility and by requiring Construction Security, Operational Security, NYISO billing and collection, Security-draw procedures, and direct collection rights. The framework is designed to mitigate the risk that other customers bear costs associated with a Large Load Facility that is delayed, reduced, or does not materialize, while preserving NYISO’s existing roles and LS Power Grid’s Formula Rate recovery.

No Large Load-Driven Upgrade is listed in proposed Table 1 as of the requested effective date. Accordingly, the filing does not change currently effective Regulated Transmission Facilities Charge (“RTFC”) rates under the NYISO OATT or impose a Large Load Charge on any customer upon effectiveness. The proposed revisions also make conforming corrections to existing Formula Rate Template and Protocol provisions, including provisions governing the cost-of-capital and true-up calculations. Those corrections do not revise the currently effective RTFC; they will be reflected, as applicable, in future Annual Projections, Annual Updates, and True- Up Adjustments under the Formula Rate. An individual Large Load-Driven Upgrade may be included in the RTFC only after a separate FPA section 205 filing adds that upgrade to Table 1 and the Commission accepts the designation.

6 Capitalized terms used but not otherwise defined in this transmittal letter have the meanings assigned to them in the NYISO OATT, including the proposed revisions to Rate Schedule 10 and Attachment 1 thereto, the proposed pro forma Large Load Cost Recovery Agreement (“CRA”) set forth in Appendix 1 to Attachment 1, and, as applicable, the proposed Formula Rate Template and Formula Rate Implementation Protocols.

PDF page 3

Page 3
II. Background
A. LS Power Grid and its Rate Schedule 10 Recovery
LS Power Grid is a non-incumbent Transmission Owner in the NYISO region. LS Power Grid and the New York Power Authority (“NYPA”) developed Segment A of the AC Transmission Public Policy Transmission Need, a 345 kV project between the Marcy/Edic and New Scotland substations (“AC Transmission Project”), which is now in service as part of Central East Energy Connect. LS Power Grid has no franchised retail service territory and no Transmission Service Charge under Attachment H of the NYISO OATT. LS Power Grid currently recovers its Commission-accepted revenue requirement exclusively under Rate Schedule 10 through its formula rate and the associated RTFC.

B. Show Cause Order and Stakeholder Process
On June 18, 2026, the Commission issued the Show Cause Order, instituting a section 206 proceeding in Docket No. EL26-69-000 and identifying concerns about cost shifting, transparency, minimum-revenue commitments, credit support, and the rate treatment of large load payments.7 The Commission later granted abeyance through November 16, 2026, for respondents that make timely section 205 filings addressing its preliminary findings.8

LS Power Grid participated in NYISO and stakeholder discussions concerning large load integration and cost recovery. Those discussions confirmed that a transmission owner without retail customers needs a wholesale mechanism to protect its other transmission customers when a Large Load Facility requires a Large Load-Driven Upgrade to that transmission owner’s facilities. LS Power Grid’s proposal is designed to operate alongside NYISO’s study and interconnection procedures. It does not displace the separate arrangements that an Eligible Customer must enter into with the owner of an Affected System for an Affected System Upgrade.9

III. Description of the Proposed Revisions
A. Rate Schedule 10 Eligibility and Cost Allocation
New Section 6.10.1.1(xii) identifies a Large Load-Driven Upgrade of a Transmission Owner or Other Developer that does not recover a transmission revenue

7 Show Cause Order at PP 72-91.
8 N.Y. Indep. Sys. Operator, Inc., 196 FERC ¶ 61,130 (2026) (granting abeyance).
9 See CRA §§ 4.2 and 6.2 and Schedule 1.

PDF page 4

Page 4
requirement through an Attachment H Transmission Service Charge or NYPA Transmission Adjustment Charge as an eligible project category, subject to Commission acceptance of the applicable Transmission Owner’s or Other Developer’s designation. Section 6.10.1.2 confirms that the otherwise-applicable exclusion for projects outside Attachment Y does not exclude such an eligible Large Load-Driven Upgrade. The definition cross-references NYISO’s proposed definition of “Large Load” in Section 1.12 of the OATT, which is separately being filed. The provisions preserve the exclusion for directly assigned facilities that are paid by the Eligible Customer and not included in the Transmission Owner’s rate base. Under Sections 6.10.3.7.2 and 6.10.7.3.2, a Large Load-Driven Upgrade becomes an Eligible Project only after Commission acceptance of a section 205 filing adding it to Table 1. That section 205 designation filing will provide the appropriate opportunity to evaluate the particular upgrade, the supporting study record, and the application of the CRA protections before the upgrade is included in the RTFC. Each designated Large Load-Driven Upgrade is recovered together with the AC Transmission Project through a single RTFC and allocated to Responsible LSEs in the same manner as the AC Transmission Project. The assignment, reassignment, reduction, or cessation of service by the Large Load does not itself modify that Commission-accepted RTFC allocation.

B. Pro Forma CRA
The pro forma CRA and Limited Acknowledgment are included as Appendix 1 to Attachment 1 to Rate Schedule 10, Section 6.10.7.5.1. The CRA is entered into by LS Power Grid and the Eligible Customer. The Large Load Customer executes a Limited Acknowledgment but does not become a party to the Eligible Customer’s wholesale payment obligations. NYISO is not a party to the CRA; its billing, collection, security, remittance, and data functions arise under the Rate Schedule 10 Large Load Provisions.10

For each Covered Upgrade, the CRA establishes a fixed Annual Minimum Transmission Revenue Contribution (“Annual MTRC”) under the Schedule 5 MTRC Calculation Template. The Annual MTRC is initially estimated and is redetermined to the Final Annual MTRC on the Final MTRC Determination Date, which occurs no later than one year after the applicable Upgrade In-Service Date after actual capital costs are known and accounted for. Schedule 5 uses the applicable capital structure, return on equity, cost of debt, tax, depreciation, and expense-allocation inputs to establish the levelized Fixed Charge Rate and Final Annual MTRC. The

10 See id. Article 1 and Limited Acknowledgment; Rate Schedule 10 §§ 6.10.3.7 and 6.10.7.4.

PDF page 5

Page 5
MTRC Term begins on the actual Upgrade In-Service Date and ends on the day immediately preceding its twentieth anniversary, with the first and final Rate Years prorated. The CRA does not reset the final contractual Annual MTRC through ordinary annual formula rate updates, except for the limited prospective adjustments expressly identified in the CRA.11

The twenty-year MTRC Term is a defined contractual revenue-support period, not the depreciable life of a Covered Upgrade. Schedule 5 establishes a levelized Annual MTRC for that period, while the Covered Upgrade remains subject to ordinary Formula Rate depreciation and other cost-of-service treatment. The term provides a substantial, predictable period of revenue responsibility for the Large Load-Driven Upgrade and is reinforced by Operational Security based on the remaining Cumulative Revenue Responsibility and a Termination Fee equal to that remaining responsibility less any Supplemental MTRC already billed and remaining unpaid upon an early termination or permanent cessation of service. The excluded unpaid bills remain separately payable.12

The Eligible Customer owes a Supplemental MTRC to the extent Qualifying Transmission Revenues attributable to the Large Load Facility are less than the applicable Annual MTRC. The CRA provides for annual reconciliation. Construction Security protects pre-service commitments and cancellation exposure. After an upgrade enters service, Operational Security equals the nominal remaining Cumulative Revenue Responsibility, subject to Qualifying Retail Security Support that is legally available for the corresponding wholesale obligation. A termination or permanent cessation after in-service triggers a Termination Fee equal to the Remaining Cumulative Revenue Responsibility less any Supplemental MTRC already billed and remaining unpaid as of the effective termination or cessation date, as provided in CRA Section 3.3.4. Those unpaid bills remain separately payable as Large Load Charges. NYISO’s receipt of the Termination Fee in full discharges only the remaining responsibility included in the fee and does not discharge the excluded unpaid bills. The Termination Fee is an accelerated contractual termination charge, not a penalty. Rather than producing a one-time Formula Rate Credit, the Termination Fee Balance is held by NYISO and remitted as Annual Termination Fee Remittances over the remaining MTRC Term, so the resulting Formula Rate Credits follow the annual schedule that would have applied absent termination.13

11 See CRA §§ 3.2 and 6.3.1 and Schedule 5.
12 See id. §§ 3.3.4–3.3.6, 6.3, 6.7, and Article 7; Schedule 5.
13 See id. §§ 3.3.4–3.3.6, 6.4–6.8, and Article 7; Rate Schedule 10 § 6.10.7.4.

PDF page 6

Page 6
The CRA requires Operational Security equal to one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility. The Commission preliminarily found that “an Eligible Customer may include a credit support or other financial security posted by a large load as part of a retail agreement to avoid creating duplicative credit support requirements.”14 To avoid duplicative collateral, the direct Operational Security requirement may be reduced dollar-for-dollar by qualifying retail security support only where the Eligible Customer delivers a current Retail Security Certification. The certification must confirm that the retail Large Load Customer has posted security available to the Eligible Customer for the corresponding wholesale obligations and that the Eligible Customer has enforceable draw or application rights, or the benefit of a binding undertaking, permitting it to use the proceeds for that purpose. Qualifying retail security support does not reduce the Eligible Customer’s underlying payment obligations, does not apply to Construction Security or Pre-In-Service Termination Costs, and is subject to notice and verification requirements if the support is reduced, drawn, expires, is not renewed, or otherwise may be impaired.15

LS Power Grid recognizes that, after further stakeholder experience and discussion, a lower Operational Security requirement may be appropriate in defined circumstances where an alternative credit support arrangement provides equivalent protection against a cost shift. The Show Cause Order also invited further consideration of alternative mechanisms that could provide comparable or greater protection against cost shifting.16 This filing nonetheless adopts a conservative requirement of Operational Security equal to one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility, subject only to the limited treatment of qualifying retail security support described above. LS Power Grid intends to work with NYISO and interested stakeholders to evaluate whether, and under what objectively defined circumstances, a different security level or alternative credit support structure could provide comparable protection. Any future change to the security requirement would be submitted to the Commission for review and acceptance under section 205 of the Federal Power Act.

C. Revenue Attribution, Allocation, and Rate Treatment
Qualifying Transmission Revenues are not a separate retail or load-based charge imposed by LS Power Grid. They are the portion of RTFC revenues assessed on the

14 Show Cause Order at P 89.
15 See CRA Article 7 and Schedule 3.
16 Show Cause Order at PP 88–89.

PDF page 7

Page 7
Actual Energy Withdrawals of the Large Load Facility, collected from the Responsible LSE or LSEs serving that facility, and remitted to LS Power Grid that is attributable to the applicable Covered Upgrade and reduces the RTFC otherwise collected from other Responsible LSEs. Schedule 2 to the CRA provides a reproducible methodology using the applicable metering data, RTFC rate, Load Zone or Subzone allocation, and Covered Upgrade Revenue Share.17

Where an upgrade is driven by more than one Large Load Facility, Schedule 1 identifies an Initial Allocation Percentage for each Large Load Customer based on the applicable final study and allocation methodology. That allocation accounts for the large loads studied individually, jointly, or in a cluster; their differing requested service levels, development phases, and facility configurations; and any portion of the facility that serves other system needs or customers. The aggregate allocation to all Large Load Customers may not exceed one hundred percent (100%), and any unallocated portion remains subject to the otherwise applicable Rate Schedule 10 cost-allocation and recovery rules.18

The CRA does not itself determine whether a facility is directly assigned or included in rate base. That determination is made under the applicable NYISO tariff, study process, and interconnection arrangements. Direct Assignment Facilities and other facilities whose costs are directly assigned to, and paid by, the Eligible Customer and are not included in LS Power Grid’s rate base are excluded from the definition of Large Load-Driven Upgrades and from the MTRC framework.19

Covered Upgrades are separately identified in LS Power Grid’s Formula Rate and use the capital structure and generally applicable return components applicable to LS Power Grid under Rate Schedule 10, including any Commission-approved generally applicable return on equity incentive, as applicable. Covered Upgrades do not receive return on equity incentives that are specific to the AC Transmission Project or become subject to the AC Transmission Project’s Competitive Bid Concession, cost cap, or other project-specific cost-containment commitments.20

17 See CRA § 6.2 and Schedule 2.
18 See id. § 6.3.2–6.3.4 and Schedule 1.
19 See id. §§ 2.37 (definition of “Large Load-Driven Upgrades”), 6.2.
20 See id. § 6.2 and Arzola Testimony.

PDF page 8

Page 8
D. NYISO Billing Security and Remittance Functions
New Section 6.10.3.7 confirms that the Attachment-level Large Load Provisions are part of Rate Schedule 10, directs NYISO to perform the functions assigned to it under those provisions, distinguishes Large Load Charges from RTFC charges and revenues, and confirms that NYISO does not become a party to a Large Load CRA. New Section 6.10.7.4 requires execution of an applicable CRA and delivery of Construction Security before LS Power Grid undertakes specified construction commitments. It directs NYISO to bill customer-specific Large Load Charges based on LS Power Grid Charge Statements; hold and administer CRA Security; draw and apply Security under defined conditions; hold and remit Termination Fees; provide load and settlement data; and remit collected amounts to LS Power Grid. The provision separately identifies these charges from RTFC charges and preserves applicable NYISO billing and dispute procedures.21

The proposed Template and Protocols provide the rate treatment and supporting workpapers. In the Annual Projection, Large Load CRA Revenue consists of projected Supplemental MTRC, including any prior-period Supplemental MTRC true-up adjustment, and projected Annual Termination Fee Remittances. In the Annual Update, the Formula Rate Credit reflects Actual Large Load CRA Revenue actually received by LS Power Grid during the Rate Year, including Supplemental MTRC payments collected and remitted by NYISO, Applied Security Proceeds applied and remitted to LS Power Grid, direct recoveries from an Eligible Customer applied to Supplemental MTRC obligations, and Annual Termination Fee Remittances. The Annual Update replaces the projected credit with actual cash receipts, and any difference is addressed through the Formula Rate true-up mechanism in the next Rate Year, with the applicable Formula Rate interest treatment. An Eligible Customer remains liable for all unpaid Large Load Charges, and the CRA’s Security and collection provisions are designed to mitigate the risk of nonpayment.22

E. Supporting Testimony and Illustrative Exhibits
Mr. Patrick Hayes’ testimony (Exhibit No. GNY-100) explains the need for the CRA framework and describes the operation of the Annual MTRC, Supplemental MTRC, revenue responsibility, security, and termination provisions. His supporting exhibits provide an illustrative MTRC Calculation (Exhibit No. GNY-101), an example Reconciliation Statement (Exhibit No. GNY-102), and an example Charge Statement

21 See Rate Schedule 10 §§ 6.10.3.7 and 6.10.7.4; CRA Articles 5 and 7.
22 See CRA §§ 6.10.7.4.5, 6.10.7.4.7, and 6.10.7.4.11; CRA §§ 6.6, 6.8, 6.13.5, and Article 7.

PDF page 9

Page 9
(Exhibit No. GNY-103), each of which tracks the corresponding provisions of the CRA, including Schedule 5 and Sections 6.4 through 6.8.

Mr. D. Eric Arzola’s testimony (Exhibit No. GNY-200) sponsors the Template and Protocol revisions and explains the Formula Rate Credit for Large Load CRA Revenue. His supporting exhibits include the clean and marked Formula Rate Templates (Exhibit Nos. GNY-201 and GNY-202), the clean Formula Rate Template in native Excel format with all formula intact (Exhibit No. GNY-203), an illustrative Formula Rate Template – Annual Projection (Exhibit No. GNY-204), an illustrative Formula Rate Template – Annual Update (Exhibit No. GNY-205), and the clean and marked Formula Rate Implementation Protocols (Exhibit Nos. GNY-206 and GNY- 207). Exhibit No. GNY-205 illustrates the Annual Update, including the customer- level Supplemental MTRC true-up and the ordinary Formula Rate true-up of projected CRA revenue credits to actual receipts. Together, those materials demonstrate the projected, annual-update, and true-up treatment of Supplemental MTRC and Annual Termination Fee Remittances.

IV. The Proposed Revisions Are Just and Reasonable
The proposal materially mitigates the cost-shifting concern identified in the Show Cause Order. Before in-service, Construction Security and termination-cost provisions protect against cancellation and related exposure. After an upgrade enters service, the Annual MTRC, Supplemental MTRC, Required Operational Security, and termination provisions establish a defined revenue responsibility associated with the service request that caused the upgrade. Required Operational Security equals one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility, subject to any qualifying retail-security support recognized under the CRA. NYISO billing, mandatory Security draws, and LS Power Grid’s direct collection rights further protect against nonpayment.

The proposal also supplies the transparency and crediting mechanisms the Commission identified. The pro forma CRA in Appendix 1, Table 1, Schedules 1 and 5, the Template and Protocol workpapers, and the Annual Projection and Annual Update provide a traceable record of the relevant upgrades, customer obligations, credits, billings, and reconciliations. The illustrative MTRC Calculation (Exhibit No. GNY-101), example Reconciliation Statement (Exhibit No. GNY-102), and example Charge Statement (Exhibit No. GNY-103) further demonstrate the calculation and administration of these requirements. Customer-specific information is protected under CRA § 6.12 and Protocols § 8, while the required public information remains available in aggregated or redacted form as appropriate.

PDF page 10

Page 10
The proposed use of the existing Rate Schedule 10 RTFC allocation does not assign responsibility for a Large Load-Driven Upgrade to Responsible LSEs on the theory that those LSEs caused the underlying Large Load Facility or its service request. Rather, once the Commission accepts a designation of a Covered Upgrade in Table 1, the existing RTFC provides the established mechanism for collecting LS Power Grid’s Commission-authorized revenue requirement for that transmission facility. The CRA separately requires the Eligible Customer serving the Large Load Facility to provide the Annual MTRC through Qualifying Transmission Revenues and Supplemental MTRC payments, and the Formula Rate credits Actual Large Load CRA Revenue dollar-for-dollar against LS Power Grid’s revenue requirement. Thus, the RTFC allocation supplies the collection path, while the CRA framework assigns the relevant payment obligation to the Eligible Customer and materially mitigates the associated risk through Security, NYISO billing and collection, and direct enforcement rights.

Finally, the proposal is appropriately tailored to LS Power Grid. It provides a cost- recovery and security path for a non-incumbent Transmission Owner with no retail customers or Attachment H Transmission Service Charge. It does not disturb the current AC Transmission Project allocation, existing RTFC recovery, NYISO study authority, or the retail arrangements between an Eligible Customer and a Large Load Customer.

V. Requested Effective Date and Waivers
LS Power Grid requests an effective date of January 16, 2027, sixty-one (61) days after the date of this filing, satisfying the Commission’s sixty-day notice requirement.23 LS Power Grid requests waiver of the cost-of-service-statement requirements of 18 C.F.R. § 35.13, and any other Part 35 requirements that otherwise may apply, to the extent necessary. The requested waivers are appropriate because the filing establishes a prospective formula rate and contractual framework, identifies no Large Load-Driven Upgrade in Table 1, does not change currently effective RTFC rates, and makes only conforming Formula Rate Template and Protocol corrections that will be implemented through the ordinary formula- rate processes.

VI. Contents of Filing
LS Power Grid submits the following materials:
• This transmittal letter;

23 18 C.F.R. § 35.3(a)(1).

PDF page 11

Page 11
• Clean and marked tariff records revising Rate Schedule 10 and Attachment 1 to Rate Schedule 10, including the proposed changes in Sections 6.10.7.3 through 6.10.7.5 and the pro forma CRA and Limited Acknowledgment in Appendix 1, Section 6.10.7.5.1;

• Direct testimony of Patrick Hayes (Exhibit No. GNY-100) and supporting exhibits: illustrative MTRC Calculation (Exhibit No. GNY-101), example Reconciliation Statement (Exhibit No. GNY-102), and example Charge Statement (Exhibit No. GNY-103); and

• Direct testimony of D. Eric Arzola (Exhibit No. GNY-200) and supporting exhibits: clean and marked Formula Rate Templates (Exhibit Nos. GNY-201 and GNY-202), clean Formula Rate Template in native Excel format with all formulas intact (Exhibit No. GNY-203), illustrative Formula Rate Template – Annual Projection (Exhibit No. GNY-204), illustrative Formula Rate Template – Annual Update (Exhibit No. GNY-205), and clean and marked Formula Rate Implementation Protocols (Exhibit Nos. GNY-206 and GNY-207),

demonstrating the customer-level Supplemental MTRC true-up and the ordinary Formula Rate true-up of projected CRA revenue credits to actual receipts.

VII. Communications and Service
LS Power Grid requests that all pleadings, correspondence, and other communications concerning this matter be directed to the following persons, and their names and addresses be placed on the official service list for this docket: Patrick Hayes

LS Power Development, LLC
Associate Vice President, Transmission
Regulatory
(636) 532-2200 | phayes@lspower.com
Blake R. Urban
LS Power Development, LLC
Senior Regulatory Counsel
(636) 231-0475 | burban@lspower.com
LS Power Grid has confirmed with the NYISO that a complete copy of this filing will be posted on the NYISO’s website at www.nyiso.com. The NYISO has also informed LS Power Grid that it will send an electronic link to this filing to the official representative of each its customers and each participant on its stakeholder committees. Additionally, LS Power Grid has served a copy of this filing on the service list in Docket No. EL26-69-000 and on parties otherwise entitled to service under the Commission’s regulations.

PDF page 12

Page 12
VIII. Conclusion
For the reasons stated above and in the supporting testimony, LS Power Grid respectfully requests that the Commission accept the proposed tariff revisions effective January 16, 2027, subject to the requested waivers.

Respectfully submitted,
/s/ Blake R. Urban
Blake R. Urban
Senior Regulatory Counsel
Seth Yeazel
Associate Regulatory Counsel
LS Power Development, LLC
16150 Main Circle Drive
Suite 310
Chesterfield, MO 63017
Tel: (636) 231-0475
Tel: (240) 904-5109
burban@lspower.com
syeazel@lspower.com

Attorneys for LS Power Grid New York
Corporation I

PDF page 13

Page 13
CERTIFICATE OF SERVICE

Pursuant to Rule 2010 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission, 18 C.F.R. § 385.2010, I hereby certify that I have this day caused a copy of the foregoing filing of LS Power Grid New York Corporation I to be served electronically upon each person designated on the official service list in Docket No. EL26-69-000 and upon each other person entitled to service under the Commission’s regulations.

Dated at Rockville, Maryland this 16th day of November 2026.
/s/ Blake R. Urban

Blake R. Urban
Senior Regulatory Counsel
LS Power Development, LLC
16150 Main Circle Drive
Suite 310
Chesterfield, MO 63017
Tel: (636) 231-0475
burban@lspower.com