ER27-518-000 · 2026-11-16 · LS Power Grid New York Corporation INew York Independent System Operator, Inc.

Arzola Testimony (Exhibit No. GNY-200)

Text extracted from the eLibrary original (SHA-256 c6f9f7207a836962…). Download the original from the official source.

Contents · 47 sections
  1. D. ERIC ARZOLA p. 1
  2. I. INTRODUCTION AND EXPERIENCE p. 1
  3. A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310, p. 1
  4. A. Yes. I have submitted testimony in FERC Docket Nos. ER22-221, ER23-206, ER24- p. 1
  5. II. PURPOSE AND SUMMARY OF TESTIMONY p. 2
  6. A. The purpose of my testimony is to explain the revisions LSPGNY proposes to its p. 2
  7. A. LSPGNY proposes the following changes: p. 3
  8. A. No. The cost of service inputs, return, depreciation, taxes, and allocators are unchanged. p. 4
  9. A. Yes. I am sponsoring the following exhibits: p. 4
  10. III. LSPGNY AND FORMULA RATE BACKGROUND p. 5
  11. A. LSPGNY is a transmission-only company that owns Segment A, developed with the New p. 5
  12. A. By September 30, LSPGNY posts an Annual Projection of its revenue requirement for p. 5
  13. A. In the Show Cause Order, the Commission directed the NYISO and its transmission p. 5
  14. IV. THE LARGE LOAD COST RECOVERY FRAMEWORK p. 6
  15. A. The cost of each Covered Upgrade is included in LSPGNY’s rate base and revenue p. 6
  16. A. The Supplemental MTRC is the amount, if any, by which an Eligible Customer’s Annual p. 6
  17. A. The Supplemental MTRC follows the same projection and true-up cycle as the rest of the p. 7
  18. A. Billing the projected amount during the Rate Year matches the timing of the p. 7
  19. A. If an Eligible Customer terminates its CRA after an applicable in-service date, it pays a p. 7
  20. A. The Supplemental MTRC and Annual Termination Fee Remittances (together, “Large p. 8
  21. A. No. The return on equity (“ROE”) incentive the Commission granted for Segment A in p. 9
  22. V. LSPGNY’S PROPOSED FORMULA RATE TEMPLATE CHANGES p. 9
  23. A. The existing Formula Rate Template reports transmission plant only in total. To identify p. 9
  24. A. Attachment 2a has five sections, each with a line for Segment A and lines for Covered p. 9
  25. A. LSPGNY proposes a new Line 5a, Large Load CRA Revenue – Supplemental MTRC p. 10
  26. A. Revenue credits are the Formula Rate Template’s existing means of passing revenue back p. 10
  27. A. Attachment 1a calculates Projected Large Load CRA Revenue, and records Actual Large p. 11
  28. A. Lines 24–34 are completed in the Annual Update. For each Eligible Customer and p. 12
  29. A. New lines a1 through c on Appendix A show the Large Load CRA Revenue the NYISO p. 12
  30. A. LSPGNY proposes a new section, Lines 14–24, that trues up the Supplemental MTRC p. 13
  31. A. The difference between projected and actual Qualifying Transmission Revenues relates to p. 13
  32. A. Attachment 1a reports information by Eligible Customer and Covered Upgrade. Under p. 14
  33. A. Yes. Attachments 1a and 2a are added to the Index. In addition, LSPGNY proposes the p. 14
  34. VI. MINISTERIAL CORRECTIONS p. 14
  35. A. LSPGNY proposes the following corrections to the existing Formula Rate Template: p. 14
  36. A. No. Each correction conforms a formula or label to the methodology the Commission p. 15
  37. VII. FORMULA RATE IMPLEMENTATION PROTOCOLS p. 15
  38. A. LSPGNY proposes the following changes: p. 15
  39. A. The existing posting, review, challenge, and true-up procedures apply to the Large Load p. 16
  40. VIII. NATIVE AND ILLUSTRATIVE FORMULA RATE TEMPLATES p. 17
  41. A. Exhibit No. GNY-203 is the revised Formula Rate Template in native Excel format with p. 17
  42. A. Exhibit No. GNY-204 is the revised Formula Rate Template populated with hypothetical p. 17
  43. A. Exhibit No. GNY-205 is the revised Formula Rate Template populated with hypothetical p. 18
  44. IX. CONCLUSION p. 19
  45. A. The revisions implement the Commission’s direction that large load payments be credited p. 19
  46. A. Yes. p. 20
  47. D. Eric Arzola p. 21

Read the parent filing

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

GNY-200 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION LS POWER GRID NEW YORK CORPORATION I ) Docket No.
Read this passage

D. ERIC ARZOLA

printed heading

D.
Read this passage

I. INTRODUCTION AND EXPERIENCE

printed heading

I.
Read this passage

A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310,

printed heading

My business address is 16150 Main Circle Drive, Suite 310, 3 Chesterfield, Missouri 63017. 4 Q.
Read this passage

A. Yes. I have submitted testimony in FERC Docket Nos. ER22-221, ER23-206, ER24-

printed heading

ER22-221, ER23-206, ER24- 14 264, ER24-2668, ER25-321, ER25-2025, ER26-140, ER26-315, ER27-165, and ER27- 15 482. 16 Exhibit No.
Read this passage

II. PURPOSE AND SUMMARY OF TESTIMONY

printed heading

II.
Read this passage

A. The purpose of my testimony is to explain the revisions LSPGNY proposes to its

printed heading

The purpose of my testimony is to explain the revisions LSPGNY proposes to its 13 Formula Rate Template and Formula Rate Implementation Protocols so that LSPGNY 14 can recover the cost of transmission facilities built to serve large loads and covered by a 15 Large Load Cost Recovery Agreement…
Read this passage

A. LSPGNY proposes the following changes:

printed heading

GNY-200 Page 4 of 20 LSPGNY also proposes limited changes to the Formula Rate Implementation Protocols to 1 define the new terms, add work paper and notice requirements, address how Large Load 2 CRA Revenue is reflected in the True-Up Adjustment, and address customer-specific 3 information. 4 Q.
Read this passage

A. No. The cost of service inputs, return, depreciation, taxes, and allocators are unchanged.

printed heading

The cost of service inputs, return, depreciation, taxes, and allocators are unchanged. 7 Covered Upgrades are included in LSPGNY’s rate base and revenue requirement in the 8 same manner as any other LSPGNY transmission plant.
Read this passage

A. Yes. I am sponsoring the following exhibits:

printed heading

I am sponsoring the following exhibits: 16 • Exhibit No.
Read this passage

III. LSPGNY AND FORMULA RATE BACKGROUND

printed heading

PLEASE PROVIDE AN OVERVIEW OF LSPGNY AND ITS FORMULA RATE. 2
Read this passage

A. LSPGNY is a transmission-only company that owns Segment A, developed with the New

printed heading

LSPGNY is a transmission-only company that owns Segment A, developed with the New 3 York Power Authority to meet the AC Transmission Public Policy Transmission Need. 4 LSPGNY’s formula rate consists of its Formula Rate Template (NYISO Open Access 5 Transmission Tariff (“OATT”) Section 6.10.7.2.1)…
Read this passage

A. By September 30, LSPGNY posts an Annual Projection of its revenue requirement for

printed heading

WHY MUST LSPGNY REVISE ITS FORMULA RATE? 16
Read this passage

A. In the Show Cause Order, the Commission directed the NYISO and its transmission

printed heading

In the Show Cause Order, the Commission directed the NYISO and its transmission 17 owners to show cause why their tariffs remain just and reasonable or to propose changes 18 for integrating large loads.
Read this passage

IV. THE LARGE LOAD COST RECOVERY FRAMEWORK

printed heading

A CRA is an agreement between LSPGNY and an Eligible Customer taking transmission 3 service on behalf of a large load.
Read this passage

A. The cost of each Covered Upgrade is included in LSPGNY’s rate base and revenue

printed heading

The cost of each Covered Upgrade is included in LSPGNY’s rate base and revenue 12 requirement and recovered under the NYISO OATT together with the cost of Segment A. 13 Each Eligible Customer pays transmission charges for the service it takes, like any other 14 transmission customer.
Read this passage

A. The Supplemental MTRC is the amount, if any, by which an Eligible Customer’s Annual

printed heading

The Supplemental MTRC is the amount, if any, by which an Eligible Customer’s Annual 19 MTRC for a Covered Upgrade exceeds its Qualifying Transmission Revenues for that 20 Covered Upgrade.
Read this passage

A. The Supplemental MTRC follows the same projection and true-up cycle as the rest of the

printed heading

The Supplemental MTRC follows the same projection and true-up cycle as the rest of the 4 Formula Rate.
Read this passage

A. Billing the projected amount during the Rate Year matches the timing of the

printed heading

Billing the projected amount during the Rate Year matches the timing of the 15 Supplemental MTRC credit to the Rate Year in which it reduces the revenue requirement, 16 spreads the Eligible Customer’s payments evenly over the year, and uses the projection 17 and true-up process that stakeholders…
Read this passage

A. If an Eligible Customer terminates its CRA after an applicable in-service date, it pays a

printed heading

If an Eligible Customer terminates its CRA after an applicable in-service date, it pays a 23 Termination Fee equal to its Remaining Cumulative Revenue Responsibility less any 24 Exhibit No.
Read this passage

A. The Supplemental MTRC and Annual Termination Fee Remittances (together, “Large

printed heading

The Supplemental MTRC and Annual Termination Fee Remittances (together, “Large 16 Load CRA Revenue”) are credited against LSPGNY’s revenue requirement as a revenue 17 credit.
Read this passage

A. No. The return on equity (“ROE”) incentive the Commission granted for Segment A in

printed heading

The return on equity (“ROE”) incentive the Commission granted for Segment A in 5 Docket No.
Read this passage

V. LSPGNY’S PROPOSED FORMULA RATE TEMPLATE CHANGES

printed heading

LSPGNY’S PROPOSED FORMULA RATE TEMPLATE CHANGES 14 Q.
Read this passage

A. The existing Formula Rate Template reports transmission plant only in total. To identify

printed heading

To identify 16 the investment in each Covered Upgrade, the Formula Rate Template must report 17 Segment A and each Covered Upgrade separately.
Read this passage

A. Attachment 2a has five sections, each with a line for Segment A and lines for Covered

printed heading

Attachment 2a has five sections, each with a line for Segment A and lines for Covered 20 Upgrades.
Read this passage

A. LSPGNY proposes a new Line 5a, Large Load CRA Revenue – Supplemental MTRC

printed heading

LSPGNY proposes a new Line 5a, Large Load CRA Revenue – Supplemental MTRC 12 and Annual Termination Fee Remittances, which will be included in Total Revenue 13 Credits on Line 6.
Read this passage

A. Revenue credits are the Formula Rate Template’s existing means of passing revenue back

printed heading

Revenue credits are the Formula Rate Template’s existing means of passing revenue back 23 to customers.
Read this passage

A. Attachment 1a calculates Projected Large Load CRA Revenue, and records Actual Large

printed heading

In an Annual Projection, the Line 11 total is credited on 22 Attachment 1, Line 5a.
Read this passage

A. Lines 24–34 are completed in the Annual Update. For each Eligible Customer and

printed heading

For each Eligible Customer and 4 Covered Upgrade, they show the opening unpaid Supplemental MTRC, the Supplemental 5 MTRC billed during the Rate Year, and the amounts LSPGNY received during the Rate 6 Year: Supplemental MTRC payments the NYISO collected and remitted (Column (c)), 7 Applied Security…
Read this passage

A. New lines a1 through c on Appendix A show the Large Load CRA Revenue the NYISO

printed heading

New lines a1 through c on Appendix A show the Large Load CRA Revenue the NYISO 17 will bill and remit during the Rate Year: the projected Supplemental MTRC (line a1), 18 prior-period true-up adjustments (line a2), the total Supplemental MTRC to be billed 19 (line a), Annual Termination Fee…
Read this passage

A. LSPGNY proposes a new section, Lines 14–24, that trues up the Supplemental MTRC

printed heading

LSPGNY proposes a new section, Lines 14–24, that trues up the Supplemental MTRC 2 for each active Eligible Customer and Covered Upgrade.
Read this passage

A. The difference between projected and actual Qualifying Transmission Revenues relates to

printed heading

The difference between projected and actual Qualifying Transmission Revenues relates to 13 a specific Eligible Customer’s commitment.
Read this passage

A. Attachment 1a reports information by Eligible Customer and Covered Upgrade. Under

printed heading

Attachment 1a reports information by Eligible Customer and Covered Upgrade.
Read this passage

A. Yes. Attachments 1a and 2a are added to the Index. In addition, LSPGNY proposes the

printed heading

In addition, LSPGNY proposes the 18 ministerial corrections described in the next section. 19
Read this passage

VI. MINISTERIAL CORRECTIONS

printed heading

PLEASE DESCRIBE THE MINISTERIAL CORRECTIONS LSPGNY 21 PROPOSES. 22
Read this passage

A. LSPGNY proposes the following corrections to the existing Formula Rate Template:

printed heading

LSPGNY proposes the following corrections to the existing Formula Rate Template: 23 Exhibit No.
Read this passage

A. No. Each correction conforms a formula or label to the methodology the Commission

printed heading

Each correction conforms a formula or label to the methodology the Commission 8 accepted in Docket No.
Read this passage

VII. FORMULA RATE IMPLEMENTATION PROTOCOLS

printed heading

WHAT CHANGES DOES LSPGNY PROPOSE TO THE FORMULA RATE 11 IMPLEMENTATION PROTOCOLS? 12
Read this passage

A. LSPGNY proposes the following changes:

printed heading

LSPGNY proposes the following changes: 13 • A new paragraph following the introductory paragraph defines “Cost Recovery 14 Agreement” (“CRA”), “Eligible Customer,” “Annual MTRC,” “Qualifying 15 Transmission Revenues,” “Supplemental MTRC,” “Large Load CRA Revenue,” 16 “Projected Large Load CRA…
Read this passage

A. The existing posting, review, challenge, and true-up procedures apply to the Large Load

printed heading

The existing posting, review, challenge, and true-up procedures apply to the Large Load 22 CRA Revenue calculations, and the calculations themselves are in the Formula Rate 23 Exhibit No.
Read this passage

VIII. NATIVE AND ILLUSTRATIVE FORMULA RATE TEMPLATES

printed heading

NATIVE AND ILLUSTRATIVE FORMULA RATE TEMPLATES 6 Q.
Read this passage

A. Exhibit No. GNY-203 is the revised Formula Rate Template in native Excel format with

printed heading

GNY-203 is the revised Formula Rate Template in native Excel format with 8 all formulas and links intact, including new Attachments 1a and 2a.
Read this passage

A. Exhibit No. GNY-204 is the revised Formula Rate Template populated with hypothetical

printed heading

GNY-204 is the revised Formula Rate Template populated with hypothetical 13 data to illustrate the treatment of Covered Upgrades and Eligible Customers.
Read this passage

A. Exhibit No. GNY-205 is the revised Formula Rate Template populated with hypothetical

printed heading

GNY-205 is the revised Formula Rate Template populated with hypothetical 13 data to illustrate the Annual Update for the same 2030 Rate Year.
Read this passage

IX. CONCLUSION

printed heading

WHY ARE THE PROPOSED REVISIONS JUST AND REASONABLE? 16
Read this passage

A. The revisions implement the Commission’s direction that large load payments be credited

printed heading

The revisions implement the Commission’s direction that large load payments be credited 17 toward transmission owners’ revenue requirements, using the Formula Rate’s existing 18 revenue credit and true-up mechanisms.
Read this passage

A. Yes.

printed heading

Yes. 4 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION LS Power Grid New York Corporation I New York Independent System Operator, Inc. ) ) ) ) Docket No.
Read this passage

D. Eric Arzola

printed heading

D.
Read this passage