ER27-521-000 · 2026-11-16 · San Diego Gas & Electric

ER26-71 Order to Show Cause Tariff Revisions

PDF page 1

Jonathan J.  Newlander
Senior Counsel
San Diego Gas & Electric Company
8330 Century Park Court, CP32D
San Diego, CA  92123

Telephone: (858) 654-1652
Email:   jnewlander@sdge.com
November 16, 2026

The Honorable Debbie-Anne A.  Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C.  20426

Re:
Transmission Owner Tariff Revisions of San Diego Gas & Electric Company
Docket No.  ER27-___-000

Dear Secretary Reese:

Pursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C.  § 824d, and Part 35 of the Regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”), San Diego Gas & Electric Company (“SDG&E”) hereby submits proposed revisions to its Transmission Owner Tariff (“TO Tariff”) to address concerns raised in the Order to Show Cause issued in Docket No.  EL26-71-000 on June 18, 2026.1  The proposed revisions expand upon existing procedures in SDG&E’s TO Tariff to establish the terms and conditions applicable to requests for transmission-level interconnection and transmission service by Eligible Customers on behalf of Large Loads (“ECLL”)2 utilizing SDG&E-owned transmission facilities under the operational control of the California Independent System Operator Corporation (“CAISO”).  The revisions amend Sections 3 (Definitions), 5 (Access Charges and Transmission Rates), 8 (Obligation to Interconnect), 9 (Expansion Process), and 10 (Interconnection Process) of the TO Tariff, and add a pro forma Study Agreement (Appendix XIII) and a pro forma Interconnection Agreement (“IA”) (Appendix XIV).

The tariff revisions proposed in this filing respond to the concerns expressed in the Show Cause Order regarding the interconnection of, and provision of service to, an ECLL.  These

1
See California Independent System Operator Corporation, et al., 195 FERC ¶ 61,214 (2026) (“Show Cause Order” or “Order”).

2 Among the definition changes proposed in this filing, SDG&E proposes “Large Load” and “Eligible Customer for Large Load” as new defined terms in TO Tariff Sections 3.60 and 3.25, respectively.

PDF page 2

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 2 of 25

concerns include the need for transparent and workable application and study procedures, appropriate operational requirements, a mechanism that allows for partial energization of Large Loads pending completion of network upgrades, and measures designed to ensure that costs associated with interconnections do not create the possibility of unwarranted cost shifting to other transmission customers.  The tariff revisions proposed in this Section 205 filing establish a defined framework under which SDG&E will receive and process requests for service from ECLLs.  Under this framework, SDG&E will perform the studies necessary to identify facilities required to accommodate those requests, apply security provisions that protect other transmission ratepayers from the possibility of undue cost shifts, and establish other requirements associated with interconnection to SDG&E-owned transmission facilities.

With respect to cost shift protection specifically, based on ongoing discussions among other CAISO Participating Transmission Owners (“PTOs”) and SDG&E’s understanding of other PTOs’ approaches for mitigating cost shifting risks, SDG&E believes its approach is substantively aligned with that of Southern California Edison Company (“SCE”) and DesertLink, LLC (“LS Power”).  The SDG&E, SCE, and LS Power frameworks all require initial security tied to the cost of the network upgrades that the PTO determines are necessary to interconnect Eligible Customers requesting interconnection service on behalf of Large Loads.  Each also provides that the PTO will draw on the security in the event the Large Load ceases operation or provides an amount of transmission revenues that is less than what is necessary to offset the cost of the network upgrades, considering the long-term benefits such upgrades provide to all transmission ratepayers.

Indeed, discussions between SDG&E and others in California in the months since the issuance of the Show Cause Order addressed a far broader range of topics than the important questions concerning cost shift mitigation.  SDG&E developed its proposed tariff revisions after consultation with the CAISO and the other PTOs, and in recognition of the respective and complementary responsibilities of CAISO and the PTOs for transmission service and interconnections to the CAISO Controlled Grid.  Under the proposed framework, SDG&E, as the Transmission Owner (“TO”) under its TO Tariff, will administer the application and study process for requests involving SDG&E-owned transmission facilities, while coordinating with CAISO with respect to matters affecting the reliability and operation of the CAISO Controlled Grid.  This coordination is necessary because ECLL interconnections may require modifications to transmission facilities under CAISO operational control where such modifications are identified by SDG&E outside of the CAISO’s annual Transmission Planning Process (“TPP”).  Such modifications also may affect the reliable operation of the broader CAISO Controlled Grid.

The proposed revisions are just and reasonable because they establish a transparent, durable, and nondiscriminatory framework for processing transmission-level requests on behalf of new Large Loads while addressing the reliability and cost-shifting concerns identified by the Commission in the Show Cause Order.  The revisions provide consistency between SDG&E’s TO Tariff and the corresponding CAISO tariff framework while preserving the respective responsibilities of SDG&E as a PTO and the CAISO as operator of the Balancing Authority Area in which SDG&E’s transmission facilities are located.

PDF page 3

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 3 of 25

SDG&E respectfully requests that the Commission accept the proposed tariff revisions as described herein, effective February 16, 2027, and terminate the show cause proceeding in Docket No.  EL26-71-000 as to SDG&E.

I. BACKGROUND

A. SDG&E and Its TO Tariff

SDG&E is a California public utility corporation with its principal place of business at 8330 Century Park Court, San Diego, California 92123.  SDG&E provides electric transmission, distribution, and other energy services in San Diego and Orange Counties, California, subject to the respective jurisdictions of this Commission and the California Public Utilities Commission (“CPUC”).  SDG&E, has transferred operational control of its transmission facilities to the CAISO and is an Original PTO in the CAISO.  SDG&E’s transmission facilities subject to CAISO’s Operational Control are part of the CAISO Controlled Grid.

SDG&E’s TO Tariff sets forth SDG&E’s Transmission Revenue Requirement and the rates and charges for access to the CAISO Controlled Grid.  The TO Tariff also governs requests for physical interconnection to the SDG&E-owned components of the CAISO Controlled Grid by entities eligible to request interconnection consistent with FPA section 210(a).  Interconnection of wholesale generation is governed by the CAISO Tariff, and interconnections requested by entities not eligible under section 210(a) remain subject to the Local Regulatory Authority.

B. The Show Cause Order

The Show Cause Order recognized that, in CAISO, an Eligible Customer submits an interconnection application to the PTO, which performs the studies needed to interconnect new load, and the Eligible Customer then retains a Scheduling Coordinator to obtain transmission service from CAISO.3  The Commission there found that the TO Tariffs generally do not explain the details of the study processes or the technical and reliability considerations in the studies for requests by Eligible Customers on behalf of large loads.  Accordingly, it directed CAISO and the PTOs to explain whether their tariffs remain just and reasonable without, among other things:

•
a definition of large load;
•
an application process that accepts applications on a rolling basis, with a non- refundable application fee and readiness requirements that escalate at distinct phases of the study process;

•
information and data requirements regarding the characteristics of the large load, including disclosure of substantially similar pending requests on behalf of the same large load;

•
study procedures that evaluate the risks presented by large load behavior, including supplemental studies, and that recognize loads willing and able to limit their withdrawals;

3 Show Cause Order at pp. 19-20.

PDF page 4

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 4 of 25

•
ongoing operational requirements, memorialized in pro forma agreements; and
•
a cost recovery agreement requiring a minimum contribution toward the
transmission owner’s transmission revenue requirement, backed by credit support, with payments and security draws credited to the transmission revenue

requirement.

The Commission invited CAISO and the PTOs to submit proposals in response to the Order or in an FPA Section 205 filing designed to address the concerns expressed in the Show Cause Order, tailored to their unique circumstances.  This filing is SDG&E’s proposal.

II. PROPOSED INTERCONNECTION PROCESS REFORMS

The Show Cause Order identifies concern with the lack of “clear and consistent” tariff provisions governing requests for service by Eligible Customers on behalf of large loads.  SDG&E addresses this concern directly through the development of new and enhanced procedures governing service requests by Eligible Customers under the TO Tariff.  SDG&E’s proposed tariff revisions do not ask the Commission or stakeholders to learn entirely new vocabulary.  Instead, SDG&E’s framework borrows the familiar architecture of generator interconnection, which the Commission and market participants already understand well and that has been found to be just and reasonable, and applies it to Eligible Customers requesting service on behalf of large loads. Elements of SDG&E’s proposed framework include: (1) an application process featuring a time- stamped queue, a scoping meeting, and a Site Control requirement including allowance for deposits in lieu of Site Control; (2) sequential study phases with defined timelines and deposits, and a single amendment right; and, (3) pro forma interconnection agreement with milestones, options for limited operation pending completion of upgrades, financial security and possible withdrawals, and queue forfeiture upon default.

The proposed framework also reflects the complementary roles of SDG&E as a PTO and the CAISO.  SDG&E owns the relevant transmission facilities and will administer the interconnection process established under its TO Tariff.  The CAISO operates the CAISO Controlled Grid and is vested with responsibility for matters assigned to it under the Transmission Control Agreement and the CAISO Tariff.  For instance, interconnection service under the TO Tariff is not the same thing as and does not supplant transmission service governed by CAISO’s tariff; rather, the interconnection customer requesting transmission service over the CAISO Controlled Grid must take such service from CAISO through a Scheduling Coordinator. SDG&E’s proposed pro forma Interconnection Agreement confirms this point (Article 4.3). Additionally, the proposed procedures provide for coordination between SDG&E and the CAISO where necessary to secure the CAISO’s concurrence that the transmission upgrades identified by SDG&E through its study process are not duplicative of transmission upgrades the CAISO has identified through its annual TPP, and that the upgrades and operational requirements identified by SDG&E through its study process are consistent with safe and reliable operation of the CAISO Controlled Grid (pro forma IA, Article 5.5.2).

Importantly, the proposed revisions are limited to matters properly addressed through SDG&E’s Commission-jurisdictional TO Tariff.  They do not alter the respective federal and state

PDF page 5

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 5 of 25

jurisdictional responsibilities applicable to retail electric service.  Nor do they change the class of customers eligible to receive Commission-jurisdictional transmission service under SDG&E’s TO Tariff.  Rather, the revisions establish the procedures and requirements applicable when an Eligible Customer seeks to interconnect its facilities with SDG&E-owned transmission from SDG&E as a TO in order for it – the Eligible Customer – to serve the Large Load directly.  Indeed, while the reforms proposed here are motivated by SDG&E’s desire to address points in the Show Cause Order regarding Eligible Customers requesting service on behalf of large loads, many of the reforms proposed herein will be broadly applicable to other categories of Eligible Customer service requests under SDG&E’s TO Tariff.

A. Definition of Large Load

The Show Cause Order at P 57 states that CAISO and PTO tariffs “lack a definition of large load, as a new category of load[,]” and suggests that “[a]n appropriate definition, including a load size and interconnection voltage threshold, should be based on the characteristics of CAISO’s transmission system.”  The Show Cause Order suggests that a reasonable definition would be “a new commercial or industrial customer, located at a single site behind one or more points of interconnection, and that has a peak load of 50 MW or greater, interconnects to the transmission system at a voltage level of greater than 69 kV, and is not part of a co-location arrangement.”  Rather than adopt the Show Cause Order’s definition, SDG&E proposes to include the following definition of “Large Load” in its TO Tariff: “a new customer, located at a single site behind one or more points of interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater.”4

SDG&E’s proposed definition differs from the definition in the Show Cause Order in three respects.  First, in SDG&E’s view, the Show Cause Order’s call out to “commercial and industrial customers” is not necessary because, as a practical matter, SDG&E expects that loads of 50 MW or greater will likely fall into these two general categories of customers.  Second, SDG&E believes that the express call-out to the CAISO Controlled Grid in its definition is preferable to the general reference to the “transmission system” in the Show Cause Order definition.  This call-out is necessary because some sub-transmission facilities within the CAISO Balancing Authority Area are operated at voltages greater than 69 kV but are not part of the CAISO Controlled Grid, while certain of SDG&E’s transmission facilities that are part of the CAISO Controlled Grid operate at 69 kV.  Thus, the Show Cause Order definition is both over- and under-inclusive relative to SDG&E’s proposed definition.  Finally, SDG&E’s proposed definition does not exclude Large Loads that may be co-located with generation.  In SDG&E’s view, such an exclusion could limit the ratepayer protections that are a key feature of SDG&E’s proposed framework.

B. Application Process

The Show Cause Order at P 58 states that CAISO and PTO tariffs “lack sufficiently clear and consistent provisions establishing the application process and study procedures that will be used when CAISO and/or the Participating Transmission Owners evaluate the provision of

4 SDG&E has added its proposed definition in Section 3.60 of the TO Tariff.

PDF page 6

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 6 of 25

transmission service to Eligible Customers on behalf of large loads.”  The Show Cause Order identifies a rolling application process, non-refundable application fee and escalating readiness requirements, and requirements to provide to the PTO and/or CAISO regarding the large load as elements the Commission believes should be reflected in the CAISO and PTO tariffs.

Discussed in the following subsections are SDG&E’s proposed tariff revisions to address these concerns.

1. Intake and Initiating the Study Process

Section 10 of SDG&E’s TO Tariff already includes an application process and study procedures for Eligible Customer service requests.  In this filing, SDG&E proposes substantial reforms to this existing framework, including through the following modifications:

•
Rolling applications.  The existing TO Tariff interconnection process is serial in nature and does not include any “windows” during which applications must be submitted. Accordingly, SDG&E already accepts applications at any time on a rolling basis.  To address the Commission’s suggestion regarding the need for an application process that accepts applications on a rolling basis, SDG&E proposes to maintain its current serial study process that accepts and studies each application at any time on a rolling basis, with priority based on the date SDG&E, as the PTO, receives the application.  SDG&E has modified Section 10.2 of the TO Tariff to state clearly that applications shall be accepted on a rolling basis.  As part of its framework to deter speculative or duplicative requests discussed in the Readiness Requirements section below, SDG&E proposes a $50,000 non-refundable application fee, also in Section 10.2.

•
Scoping Meeting.  SDG&E has added language to Section 10.3 of the TO Tariff establishing a Scoping Meeting that may occur following receipt of the application fee but before commencement of the System Impact Study.  The Scoping Meeting is proposed to occur at the request of either SDG&E or the Interconnection Customer for the purpose of discussing interconnection options and refining information and models.

•
Single pro forma Study Agreement.  SDG&E proposes a pro forma Study Agreement that is referenced in and attached to its TO Tariff (Appendix XIII).  The Study Agreement establishes the terms and conditions applicable to the System Impact Study and, as applicable, subsequent Facilities and Electromagnetic Transient (“EMT”) Studies.  In particular, the Study Agreement treats sixty (60) calendar days as the default good faith estimate for each of the System Impact and Facilities Studies.  Appendix XIII, Section 8.0. The use of a single pro forma Study Agreement streamlines the study process by eliminating the need to separately tender, negotiate, and execute a new agreement between study phases, thereby reducing administrative delays and facilitating more timely progression of the required studies.  In addition, assuming Commission acceptance of the pro forma Study Agreement, execution of conforming Study Agreements would not require individual filings with, and acceptance by, the Commission.  This will allow the applicable study to proceed without the need for specific Commission action, thereby reducing potential delays for customers.  After providing the required notice and study

PDF page 7

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 7 of 25

deposit, an applicant may immediately proceed to the next applicable study phase under the existing Study Agreement.

Additional details concerning the study process itself are set forth below.

2. Readiness Requirements

To deter speculative or duplicative requests and ensure that projects progressing through the study process continue to demonstrate readiness, SDG&E proposes a readiness framework that includes both upfront financial commitments and ongoing project-development milestones. Specifically, SDG&E proposes a $50,000 non-refundable application fee, an initial $100,000 deposit for the System Impact Study, an additional $100,000 deposit if the applicant elects to proceed with a Facilities Study, and an additional $200,000 study deposit if SDG&E determines that an EMT Study is required.5  Each study deposit will be applied toward the actual cost of the applicable study and will be subject to reconciliation in accordance with the Study Agreement.

SDG&E would also require an ECLL applicant to identify a definitive Point of Interconnection to the CAISO Controlled Grid.  In addition, the proposed TO Tariff revisions include provisions governing an applicant’s demonstration of Site Control, including a limited opportunity to provide documentation and a deposit in lieu of such demonstration, which will expire within 180 Calendar Days of the effective date of its Interconnection Agreement.  SDG&E has reflected these modifications in proposed Sections 10.5 and 10.6 of the TO Tariff.

In addition to these requirements, SDG&E proposes time-bound readiness milestones throughout the study and interconnection process to help ensure that interconnection requests do not remain in the queue indefinitely without demonstrating continued progress:

•
Election to proceed to the Facilities Study.  After the System Impact Study, an applicant must request initiation of the Facilities Study and provide the required deposit; otherwise, its application is deemed withdrawn (TO Tariff Sections 10.12.1, 10.13).

•
Interconnection Agreement execution.  Following tender of an Interconnection Agreement, the ECLL applicant would have thirty (30) days to either execute the Interconnection Agreement or request that SDG&E file an unexecuted Interconnection Agreement with the Commission.  If the ECLL applicant does neither within the 30-day period, its interconnection application would be deemed withdrawn, and the applicant would be responsible for reimbursing SDG&E for all costs reasonably incurred to process the application that are not otherwise covered by the Study Agreement (TO Tariff Section 8.1.5).  As with the proposed pro forma Study Agreement, the proposal to include a form Interconnection Agreement in SDG&E’s TO Tariff is intended as an over-arching process improvement, such that the execution of conforming Interconnection Agreements would not require individual filings with, and acceptance by, the Commission.  This will allow

5 The application fee can be found in the TO Tariff, Section 10.5.  Study amounts are set forth in the Study Agreement, TO Tariff Appendix XIII, Section 8.0.

PDF page 8

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 8 of 25

the satisfaction of early milestones to proceed without the need for specific Commission action, thereby reducing potential delays for customers and providing the most “shovel- ready” projects with speed to power for the service requested.

•
Limited amendments.  SDG&E proposes to clarify the types of modifications that may be made through the existing one-amendment allowance for a Completed Interconnection Application.  Permitted modifications include reductions in interconnection service capacity, certain changes to project technical parameters or interconnection configuration, and modifications to the proposed in-service date or Commercial Operation Date, subject to the conditions specified in the proposed TO Tariff.  The proposed revisions also establish the timeframe for submitting such an amendment and clarify the applicant’s responsibility for any additional study costs resulting from the amendment, including costs associated with revisions to studies for later-queued applicants (TO Tariff Section 10.7).

•
Security posting.  If the ECLL applicant executes the pro forma Interconnection Agreement, the applicant would be required to post the financial security required under the Interconnection Agreement by the applicable deadline specified therein.  Failure to timely post the required financial security, or any other default under the Interconnection Agreement, would result in forfeiture of the applicant’s queue position and withdrawal of its interconnection request (TO Tariff Section 10.23).

Together, these requirements establish clear and enforceable readiness milestones that escalate at distinct phases, as the Commission described, and are intended to maintain an actionable queue, minimize speculative interconnection requests, and prevent inactive applicants from continuing to hold queue positions.

Finally, SDG&E also views the cost responsibility framework, including cost shift protections discussed in greater detail below, as critical elements of its proposed readiness approach.  In summary, SDG&E’s proposed 100 percent cost-shift protection for network upgrades6 (TO Tariff Sections 8.1.2 and 8.1.3 and pro forma IA Articles 11.3, 11.5, and 11.6) and advance funding requirement for Direct Assignment Facilities (TO Tariff Section 8.1.2 and pro forma IA Articles 5.10 and 11.2) establish clear financial responsibility for interconnection-related infrastructure costs at the outset of the interconnection process.  Providing ECLL applicants with certainty as to their funding requirements, and the amount and duration of security obligations, should help ensure that interconnection requests enter and remain in the queue only where the applicant has determined that such funding and security do not jeopardize the commercial viability of their planned projects.

3. Information and Data Requirements

After recognizing that “CAISO and/or the Participating Transmission Owners may have existing load integration processes[,]” the Show Cause Order at P 49 expressed:

6 The proposed Interconnection Agreement uses the term “Network Upgrades,” which is synonymous with the TO Tariff’s pre-existing definition of “Reliability Upgrades.”  See Section 3.93 of the proposed TO Tariff; pro forma IA Article 1 (defining Network Upgrades as synonymous with Reliability Upgrades).

PDF page 9

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 9 of 25

concern[] that those processes and any required studies … are not described in their tariffs with the degree of clarity and specificity necessary to … mitigate operational risks…, avoid disputes regarding how studies are conducted, deter speculative or duplicative requests…, and help avoid excessive and unnecessary network

upgrades.

In the months since the issuance of the Show Cause Order, SDG&E has been working in conjunction with CAISO, SCE, Pacific Gas and Electric Company (“PG&E”), and other stakeholders in the Large Load Technical Requirement Working Group (“LLTRWG”) to develop additional technical requirements to be considered in the study process.  Holistically, these additional requirements address technical aspects of the ECLL interconnection process and address the Commission’s concerns.

SDG&E proposes to modify its TO Tariff to require the ECLL to submit to SDG&E, as the PTO, data that the LLTRWG recommends be made available for study and operational purposes.  These data include: large load operating characteristics; hourly load profile; ramping behavior; power quality; and telemetry and communications data.  Specifically, an ECLL must submit the data specified in the System Impact Study Data Template Submittal Form, including facility characteristics, load composition and expected hourly operating profile, MW capacity, minimum and maximum operating levels, electrical and dynamic model data, voltage and frequency ride-through characteristics, protection and control settings, load reconnection behavior, expected CAISO market participation model, curtailment and ramping capabilities, and behind- the-meter generation capacity and characteristics, and must complete CAISO’s Large Load Technical Data Request.  An ECLL must also disclose whether substantially similar interconnection requests on behalf of the same Large Load have been submitted and whether it is requesting Flexible Interim Load Interconnection (“FILI”) Service.

SDG&E has added these data requirements in Section 10.5 of the TO Tariff and
Attachment B to the pro forma Study Agreement.

C. Transmission Service Study

The Show Cause Order notes at P 49 that CAISO and PTO tariffs “do not contain provisions addressing with sufficient clarity and consistency how CAISO and/or the Participating Transmission Owners will study the provision of transmission service to Eligible Customers on behalf of large loads,” and expresses concern at P 51 that “CAISO’s Tariff and/or the TO Tariffs may not clearly specify which entity will be responsible for studying the provision of transmission service to Eligible Customers on behalf of large loads.”  Later, in paragraph 62 of the Show Cause Order, the Commission discusses the need for study processes, and clarity about such processes, that include “a report to the Eligible Customer with the results of the studies” that identify “any Direct Assignment Facilities and network upgrades necessary to accommodate the transmission service request as well as a non-binding good-faith estimate of the cost and the time to construct such facilities.”  The study should “recognize … the unique operational characteristics of large

PDF page 10

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 10 of 25

loads” and, the Show Cause Order suggests, should have “a study deadline of no more than 60-90 calendar days.”  Id.

In response to the Show Cause Order’s concerns, SDG&E clarifies first that with respect to requests by an Eligible Customer to interconnect a new project, SDG&E’s TO Tariff already outlines the process for both the System Impact Study and the Facilities Study.  Under the existing TO Tariff, for instance, “[t]he System Impact Study will identify whether any Direct Assignment Facilities or Reliability Upgrades as well as, if applicable, any Delivery Upgrades are necessary to deliver a New Facility’s full output over the ISO Controlled Grid.”7  This study process is already available for wholesale load interconnection requests by Eligible Customers.  This includes ECLL, whether or not a newly-created sub-category of wholesale load called ECLL is created.

In this filing, however, SDG&E proposes revisions to create a new category of Eligible Customer called ECLL.  These revisions make abundantly clear that the existing System Impact Study and Facilities Study processes apply to the newly-created ECLL customer type, as a new category of wholesale load service requested on behalf of a large load, and in recognition of the unique technical issues large loads entail, to add an EMT Study where needed.  Thus, for purposes of clarity and consistency, SDG&E declares that as the TO, it will, pursuant to the provisions of its TO Tariff, conduct the study process that will identify the operating procedures, Direct Assignment Facilities, and network upgrades necessary to provide transmission service to an ECLL.  Moreover, while not raised in the Show Cause Order, SDG&E commits that it will use the same due diligence in completing studies for others as it uses for itself or its affiliates.  The study process modifications described here are in in Sections 10.9 through 10.17 of the proposed TO Tariff.  Accordingly, SDG&E’s proposed revisions address the Show Cause Order’s concern that studies should identify Direct Assignment Facilities as well as network upgrades required to safely and reliably interconnect the ECLL is satisfied.

With respect to the unique operational characteristics of large loads, the Show Cause Order at P 63 states that existing “tariffs do not require transmission owners to install, and transmission customers to pay for, equipment to enable CAISO to monitor large loads for impacts of, for example, fast-ramping load that may impact the transmission system too quickly to be captured by conventional data acquisition systems (e.g., the need for phasor measurement units or similar equipment).”  That same paragraph further observes that the PTO tariffs “do not specify ramp rate or ride-through requirements with which the transmission customer taking transmission service on behalf of the large load must comply” and do “not specify requirements for necessary control technologies and/or protection systems that may be necessary to limit transmission customer’s withdrawals from the transmission system as appropriate.”

In response, SDG&E states that it proposes to incorporate the unique operational characteristics of Large Loads by implementing the recommendations of the LLTRWG discussed above.  In addition, SDG&E notes that at the time of this writing, the LLTRWG initiative has already identified CAISO data monitoring requirements (including Phasor Measurement Units

7 See redlined version of the TO Tariff section entitled “System Impact Study Procedures,” proposed by this filing to be re-numbered as Section 10.12.

PDF page 11

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 11 of 25

(“PMUs”)), ramp rate and ride-through requirements, and necessary control technologies and protection systems.  SDG&E proposes to incorporate these requirements into its process in several ways.  First, SDG&E will require that the ECLL submitting an interconnection application provide operating characteristics; ramping behavior; and measures to ensure the Large Load does not create, or exacerbate, power quality issues on SDG&E’s transmission facilities.  SDG&E has added this as an application requirement in Section 10.5 of the proposed TO Tariff.   Second, these requirements are captured in the study process in Attachment B of the pro forma Study Agreement (Appendix XIII). In particular, the EMT Study scope of work in the Study Agreement covers model verification, standalone and integrated simulation, voltage ride-through and load-recovery performance, control interactions, sensitivities, and protection and load-tripping response.  Finally, SDG&E also proposes that all data and monitoring requirements related to the LLTRWG be installed and maintained by the ECLL, as outlined in sections 8.2, 9.6, 9.7.3, 9.7.4, and 9.7.5 of SDG&E’s proposed pro forma Interconnection Agreement (Appendix XIV).

SDG&E shares the Show Cause Order’s preference for expeditious processing of
interconnection requests, as evidenced by the Show Cause Order’s suggestion of a 60-90 study process to identify Direct Assignment Facilities and network upgrades and provide non-binding estimates of cost and time to construct.8  The sooner an Eligible Customer receives its study results, the sooner it will be in position to make the business decision regarding whether to make the further financial commitments necessary to advance its request further through the process.

At the same time, however, a step-by-step study process permits a customer to make a decision that best suits its business at each step.  For instance, based on the results of the System Impact Study, a customer may or may not wish to proceed to a Facilities Study; SDG&E’s framework affords that customer with a reasonable amount of time to decide whether to move to the next step.9  SDG&E’s approach of utilizing a single Study Agreement to perform multiple studies in phases appropriately balances the interests in expedition and business flexibility.

D. Stakeholder Access to Information on Large Load Interconnections

The Show Cause Order expresses at P 70 concern about a lack of transparency regarding the “transmission service provided to Eligible Customers on behalf of large loads, for network upgrades evaluated in the local transmission planning process that are needed to accommodate transmission service to Eligible Customers on behalf of those large loads, and the costs for those network upgrades.”  In P 75, the Show Cause Order further states that CAISO and the PTOs should post and update data detailing: (1) aggregate amounts of proposed large load additions, including in each transmission pricing zone; (2) network upgrades planned to accommodate transmission service for Eligible Customers on behalf of large loads, identified by equipment type; and (3) cost estimates for such network upgrades.  Concluding, the Show Cause Order found that CAISO and the PTOs should “consider what other data related to transmission costs resulting from the

8 Show Cause Order at p. 62.
9 TO Tariff Section 10.13.

PDF page 12

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 12 of 25

provision of transmission service to Eligible Customers on behalf of large loads would be useful to include on CAISO’s website.” Id.

In response, SDG&E has been working with CAISO and the other PTOs to determine appropriate data that can be posted publicly.  CAISO already publishes in its TPP documentation those network upgrades that the CAISO has determined, through its concurrence process with the PTOs, are needed to accommodate ECLL interconnections.  Further, CAISO proposes to publicly post:10

• aggregate amounts of proposed large load additions behind interconnections of Eligible Customers to the ISO Controlled Grid, including the aggregate amounts in each transmission pricing zone;

• planned network upgrades needed to accommodate the ECLL taking transmission service, identified by type of equipment and network upgrade (e.g., new substation, reconductoring, a new high-voltage transmission line) for each transmission service request; and

• cost estimates for each planned network upgrade identified as needed for the ECLL. For details on the implementation of these information postings, SDG&E refers to CAISO’s Section 205 filing in response to the Show Cause Order.

E. Cost Shifting Among Transmission Customers

The Show Cause Order states at P 76 that CAISO and PTO tariffs “lack adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service” and expresses concern regarding “the apparent lack of a pro forma cost recovery agreement between CAISO, the relevant transmission owner, and the Eligible Customer taking transmission service on behalf of large loads.”  SDG&E proposes addressing these concerns with a framework that provides comprehensive cost shift protection, as discussed below.

1. Advance Funding and Security

Advance funding and security are the cornerstone features of SDG&E’s proposed framework for ensuring that transmission customers are not called upon to shoulder costs of facilities built to accommodate Eligible Customers requesting service on behalf of large loads. SDG&E proposes that the ECLL has cost responsibility for its Interconnection Facilities, provide

10 See generally CAISO, Large Load Enhancements Draft Final Proposal (Sept.  24, 2026), https://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load- Enhancements-Sep-24-26.pdf.

PDF page 13

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 13 of 25

advance funding for required Direct Assignment Facilities, and post security for required network upgrades.11

The advance funding provides assurance that, should the Large Load not reach its Commercial Operation Date (“COD”), transmission ratepayers will not have incurred any obligations for the costs of Direct Assignment Facilities.  Likewise, the security provisions ensure that transmission ratepayers are held harmless from the network upgrades’ projected revenue requirements in the event the Large Load does not reach COD, or in the event that the transmission revenues provided by the Large Load after COD fall short of what would be required to offset the network upgrades’ projected revenue requirements.  For high voltage network upgrades (200 kV and above), this approach is designed to eliminate the possibility of cost shifting from the ECLL to other transmission ratepayers within the same and different Transmission Access Charge (“TAC”) areas.  Similarly, for low voltage network upgrades (below 200 kV), this approach is designed to eliminate the possibility of cost shifting from the ECLL to other transmission ratepayers within the same TAC area.

2. Security Amount, Term, and Draws

SDG&E’s proposed security requirement will protect ratepayers from the risk that transmission revenues provided by an ECLL could be less than the projected revenue requirements associated with the network upgrades that are necessary to interconnect the ECLL.  The Eligible Customer will provide SDG&E, as the PTO, security equal to the present value of the forecast lifecycle revenue requirement associated with the network upgrades, including both capital and O&M-related costs, calculated using SDG&E’s most recent FERC-authorized weighted cost of capital.  SDG&E believes this approach provides full transmission ratepayer protection and eliminates ambiguity.

SDG&E also proposes that the Eligible Customer maintain security for a period of time beginning with the ECLL’s authorization for SDG&E to begin construction of the network upgrades and ending ten years following the COD of the required network upgrades.  The minimum annual transmission revenues would be set in advance, at the ECLL’s option either escalated at the rate of inflation or levelized, such that their present value equals the present value of the forecast lifecycle revenue requirement.  At any time during the term of the security, the then- available security is therefore sufficient, on a present value basis, to cover any difference between

(i) the forecast lifecycle revenue requirement associated with the network upgrades, and (ii) the sum of all draws on the security plus the sum of the ECLL’s actual “Deemed Transmission

11  See pro forma IA, Articles 5.10, 11.2, and 11.5(ii)(a) (cost responsibility for Interconnection Customer’s Interconnection Facilities and advance funding for Transmission Owner’s Interconnection Facilities and Distribution Upgrades) and Article 11.5(ii)(b) (security for network upgrades).

PDF page 14

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 14 of 25

Revenues.”12  These terms are specified in the proposed pro forma Interconnection Agreement, Appendix XIV to the TO Tariff.13

Once the ECLL-required upgrades reach COD, the required security would decline over time as the ECLL generates “Deemed Transmission Revenues.” Deemed transmission revenues will be calculated as the product of the applicable high voltage or low voltage TAC rate and the ECLL’s metered energy withdrawals from the transmission grid.14  To the extent actual Deemed Transmission Revenues in a given year are less than the minimum amount for that year, SDG&E, as the PTO, will draw the shortfall on the posted security.  As discussed below, the amount of such draws will be recorded in SDG&E’s Transmission Revenue Balancing Account Adjustment (“TRBAA”) as a credit which will reduce TAC rates.15

In the event the ECLL becomes aware that it or the Large Load it intends to serve will fail to reach COD, or will cease operation after COD, the ECLL will be required to promptly notify SDG&E, and SDG&E will draw all remaining security (effectively, an “exit fee”).  Accordingly, the security functions as a financial backstop, ensuring that the ECLL provides revenues on a present value basis (Deemed Transmission Revenues plus any draws on security) that are at least equal to the forecast present value revenue requirement of the network upgrades.  If the ECLL continues operations after the end of the security term, the transmission revenues provided by the ECLL will act to reduce transmission ratepayer costs, since the revenue requirements associated with the upgrades would already have been fully offset.

Finally, SDG&E notes that this proposal could result in security requirements that turn out to be more than is required to cover the actual lifetime revenue requirements of the network upgrades.  This is because the security requirement is established in advance using forecasts of construction costs, operation and maintenance costs, inflation, and other factors such as authorized return that determine a facility’s actual revenue requirement.  However, it is SDG&E’s judgment that the commercial certainty and administrative simplicity of using forecast values offsets the risk that the Eligible Customer will have posted more security than turns out to be necessary during the term of the security.

12  The term “Deemed Transmission Revenues” is defined in Article 11.6.2 of the proposed pro forma Interconnection Agreement.
13  See generally pro forma IA Articles 11.5 and 11.6 and Appendix H.
14  This security mechanism assumes the ECLL proposes that the Large Load be radially connected to SDG&E’s facilities and that the ECLL will thereby pay the applicable CAISO TAC for all grid withdrawals at the Point of Interconnection to the CAISO Controlled Grid.  Metering at the point of interconnection would then be used to compute actual Deemed Transmission Revenues.  If the ECLL does not propose a radial connection, the ECLL and SDG&E will need to agree on a metering arrangement that will allow SDG&E to compute actual Deemed Transmission Revenues.
15  See TO Tariff Sections 3.114 and 8.1.3.

PDF page 15

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 15 of 25

3. Pro Forma Agreement

The Show Cause Order, at P 64, states that the CAISO and PTO tariffs “lack pro forma provisions in a transmission service agreement, or other applicable agreement, between CAISO and/or the Participating Transmission Owner and the transmission customer taking transmission service on behalf of a large load to memorialize the above terms (e.g., equipment requirements, data requirements, remote disconnect capability).”  SDG&E agrees that a pro forma agreement does not currently exist in the context of an ECLL taking transmission service.

The absence of a pro forma agreement, however, does not mean that no structure exists. An Interconnection Agreement is the instrument through which the TO Tariff already assigns upgrade costs.  It is executed by the party that causes the upgrades and filed with the Commission when required.  While SDG&E, until now, has not had a pro forma Interconnection Agreement as part of its TO Tariff, SDG&E has an executed Interconnection Agreement under the TO Tariff on file with the Commission.  That Interconnection Agreement relied upon the Commission’s pro forma Large Generator Interconnection Agreement (“LGIA”) as “a useful starting point…with [appropriate] modifications….”16  SDG&E believes it can be “a useful starting point” in this context too.  Accordingly, SDG&E proposes to implement contractual terms through a pro forma Interconnection Agreement, based on the Commission’s pro forma LGIA.  SDG&E proposes this as a bilateral agreement between SDG&E and the Eligible Customer, rather than a separate two- or three-party cost recovery agreement.

SDG&E’s proposed agreement would apply to all third-party Eligible Customer requests to interconnect a Project (other than generation, which will remain subject to CAISO’s Tariff) to SDG&E’s transmission facilities.  The proposed pro forma Interconnection Agreement memorializes a broad range of financial terms, such as establishing in contract the financial security necessary to implement SDG&E’s proposed protections against cost shifting,17 as well as a wide range of technical terms.  Regarding the latter specifically, the proposed pro forma Interconnection Agreement includes terms addressing, among other things: continuous dynamic disturbance recording and PMU and digital fault recording capability (Article 8.2); a power factor range of 0.97 lagging to 0.99 leading (Article 9.6.1); compliance with CAISO Tariff voltage, reactive power, and ride-through requirements applicable to Large Loads (Articles 9.6.2.1, 9.7.3); post-fault active power recovery (Article 9.7.4); ramp-rate limitations (Article 9.7.5); telemetry and metering (Articles 7 and 8); SDG&E’s rights to interrupt, reduce, or disconnect service (Articles 9.7.2 and 13.5.2); and updated data submissions with restudy if as-built data differ materially from the data used in the study process (Article 24.3).  Once interconnected, the delivery of energy over the transmission system to the ECLL will be governed by the CAISO Tariff just like other wholesale load in CAISO.

16  See SDG&E’s Transmittal Letter of Interconnection Agreement with NextEra Energy Transmission West, LLC at p. 2, filed Dec.  11, 2018, in Docket No.  ER19-530.

17  See generally TO Tariff Appendix XIV, the pro forma Interconnection Agreement, at Article 11.5 and Appendix H.

PDF page 16

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 16 of 25

4. Minimum Contribution

The Show Cause Order at P 82 draws a connection between the minimum revenue
contribution an ECLL should be expected to make and the level of jurisdictional transmission service the ECLL has requested.  This, in turn, depends on how the requested service is studied and “any necessary network upgrades that must be developed to provide the requested transmission service.”  Id.  SDG&E agrees.

The upgrades necessary to provide transmission service to the interconnecting ECLL will be identified in the interconnection study conducted by SDG&E as the PTO, which will be based on the amount of power that the ECLL may withdraw from the CAISO Controlled Grid.  Under SDG&E’s proposal, the ECLL is required to provide advance funding for Direct Assignment Facilities and, for Reliability Upgrades, an initial amount of security that, on a present value basis, is equal to their forecast lifecycle revenue requirements.  This advance funding and initial amount of security constitutes the “minimum contribution” and must be provided by the ECLL prior to taking transmission service.18

Because the minimum annual revenues may be escalated or levelized, the mechanism also accounts for “potential timing differences between when costs are incurred to develop needed network upgrades and the pace at which the large load ramps toward energizing at its full level of requested service.” Show Cause Order at P 82.  SDG&E has proposed modifications in Section 8.1.2 of the TO Tariff to formalize this.

5. Speculative Requests

The Show Cause Order expresses concern at P 83 that:

cost shifting may occur through the recovery of the Participating Transmission Owners’ transmission revenue requirement through the Access Charge due to

speculative requests to accommodate transmission service to serve large loads, i.e., where large loads do not materialize or where the MW quantity of such large loads is lower than proposed, or because of the study process used to evaluate the facilities needed, and the associated costs, to accommodate the provision of transmission service to Eligible Customers on behalf of large loads.

SDG&E shares this concern.  Toward that end, SDG&E notes that its proposed tariff reforms are designed to address it through a readiness framework that includes both upfront and increasing financial commitments19 and ongoing project-development milestones.  SDG&E’s proposal for the Eligible Customer to provide advance funding for Direct Assignment Facilities and to post an initial amount of security equal, on a present value basis, to the forecast lifecycle

18  The “minimum contribution” for the Interconnection Customer’s Interconnection Facilities is set forth in Article 5.10 of the pro forma IA; for the Transmission Owner’s Interconnection Facilities, in Article 11.2; and for Reliability Upgrades, in Article 11.5(ii).
19  E.g., pro forma IA Articles 5.5.5 and 5.6.5.

PDF page 17

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 17 of 25

revenue requirement of all network upgrade-related costs, sufficiently addresses the scenario where the Large Load does not materialize or provides actual Deemed Transmission Revenues at a level that is less than what is needed to offset the revenue requirements associated with the network upgrades.20

In this way, failure of the Large Load to reach its COD will not burden transmission ratepayers with the costs of under-utilized transmission.  Indeed, the fact that such robust protection for other transmission customers exists should itself provide a deterrent to potential applications for speculative or questionable projects, the economics of which might otherwise have depended upon offloading a project’s risk onto other customers.

6. Crediting of Payments

The Show Cause Order clarifies at P 84 the Commission’s expectation that “any payments made by an Eligible Customer to a transmission owner pursuant to such a cost recovery agreement … will be appropriately credited toward transmission owners’ transmission revenue requirements consistent with the Commission’s cost-of-service regulations.”  SDG&E agrees that any draws on the security provided by the Eligible Customer will reduce the network upgrade costs that transmission ratepayers would otherwise be required to pay.  All draws on the security will be recorded in the TRBAA as a credit against the applicable high voltage or low voltage transmission revenue requirements, and are included in the definition of Transmission Revenue Credit.  SDG&E has added these modifications in Sections 3.114 and 8.1.3 of the proposed TO Tariff.

7. PTO As Eligible Customer

Where SDG&E itself is the entity serving a Large Load at retail, it is neither necessary nor practical for SDG&E to post security to itself.  Accordingly, Section 8.1.4 reflects a comparability commitment on SDG&E’s part by providing that, to the extent permitted or required by California law, SDG&E will impose on a Large Load security requirements comparable to those the TO Tariff requires of an ECLL.  SDG&E will file any such retail agreement with the Commission for informational purposes, if required.  This approach is consistent with the Commission’s finding that agreements between a transmission owner and a large load customer that guarantee contributions to the transmission revenue requirement should be filed with the Commission, its suggestion that a transmission owner may rely on credit support posted by a large load under a retail agreement, and its statement that the Commission “in no way intend[s] to preempt or interfere” with state-level ratepayer protection efforts.21

20  TO Tariff Section 8.1.3.
21  Show Cause Order at p. 83 and n. 183.

PDF page 18

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 18 of 25

III. FLEXIBLE LARGE LOADS AND FLEXIBLE INTERIM LOAD
INTERCONNECTION SERVICE

The Show Cause Order at P 104 preliminarily found “that new transmission services should be available to reflect the operational reality that large loads may use the transmission system to differing extents and certain large loads are willing and able to limit their use of the transmission system under certain conditions.”  While most of the Show Cause Order’s discussion on the subject of flexible loads is directed at CAISO, it also points to PTO tariffs as allegedly “lack[ing] appropriate provisions recognizing within the study process for the provision of transmission service the unique operational characteristics of large loads that are willing and able to limit their energy withdrawals under certain conditions, which may thereby lessen or potentially avoid the need for certain network upgrades.”  Id.  at P 59.

With respect to these concerns, SDG&E has participated in CAISO’s Large Load
Enhancements stakeholder process.22  After considering stakeholder input, the “CAISO proposes to create a new flexible interconnection service option that will enable ECLL and co-located loads to limit their energy withdrawals or injections until their network upgrades are placed into service.”23   SDG&E notes that provision of this particular interconnection service requires a study process to establish and enforce the necessary limits.  However, the “CAISO does not propose to create new ‘transmission services’ or more responsibilities around eligible customers, which would require redesigning transmission and interconnection service entirely”.  Id.  CAISO explains that Load Serving Entities and the Scheduling Coordinator for the ECLL can schedule demand as needed in real time, including those wishing to limit their use of the transmission system.  Id.

The CAISO proposes to create a new FILI service that will enable faster interconnections while mitigating transmission constraints.  The proposed FILI offering would enable an ECLL to interconnect and receive transmission service up to a level that is less than what the ECLL has requested in its interconnection application.  The interim level of service will be established based on grid conditions and constraints until network upgrades are complete, at which time the ECLL would be allowed to take service at its requested level.  The CAISO notes that implementing FILI service may involve a number of tools or measures, including but not limited to a Remedial Action Scheme (“RAS”), TO operator curtailment, or managing to a predetermined schedule.  The CAISO indicates that, with CAISO and Reliability Coordinator concurrence, the TO may implement automated schemes, such as a RAS, for a FILI.

In this filing, SDG&E proposes to establish a FILI framework that is similar to that proposed by the CAISO, although SDG&E will establish limits on ECLL grid withdrawals based on studies conducted during the interconnection process, not on near-real-time or real-time operating conditions.  If the CAISO establishes a limit based on its proposed FILI tariff offering,

22  See generally CAISO, Large Loads Stakeholder Initiative, available at https://stakeholdercenter.caiso.com/StakeholderInitiatives/Large-loads.
23  CAISO Large Load Enhancements, Draft Final Proposal (Sept. 24, 2026) at 67, available at https://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load- Enhancements-Sep-24-26.pdf.

PDF page 19

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 19 of 25

it is SDG&E’s understanding that the CAISO would require that the ECLL enter into a three-party agreement with the PTO and the CAISO.  This agreement would set forth the near-real-time or real-time operating procedures under which the CAISO’s limit would be implemented.

SDG&E’s FILI proposal directly addresses the Commission’s concern that the “study process” within the PTOs’ existing tariffs lacks provisions recognizing that large loads may be willing and able to limit their energy withdrawals under certain conditions.  By providing ECLL withdrawal limits established in the interconnection study process, Large Loads that are willing and able to honor these limits may be able to energize a portion of their requested load prior to completion of the transmission upgrades necessary for full energization.  During the interconnection study process, SDG&E will determine the maximum level of interim load that can be reliably served before completion of all required transmission upgrades, and the energization limits by period will be documented in Appendix I of the Interconnection Agreement.

After COD, SDG&E may update the withdrawal limit to reflect changes in modeling assumptions, system conditions, and then-available transmission capability.  A customer electing FILI service would be required to maintain the capability to manage grid withdrawals in accordance with its Interconnection Agreement and to install and commission the protection, control, and other equipment specified in Appendix J before commencing service.  Where real- time curtailment is required, SDG&E’s TO Tariff revisions contemplate ECLL, SDG&E, and CAISO will execute a further agreement describing the curtailment circumstances, mechanism, response times, restoration, and testing.  The level of FILI service would remain subject to operational assessments by the TO and CAISO and could be curtailed as necessary to preserve reliable grid operations, and SDG&E may disconnect an ECLL whose withdrawals exceed the authorized limit.24

This framework provides a defined means to recognize and utilize an ECLL’s willingness and ability to limit its energy withdrawals, potentially allowing earlier interconnection while maintaining reliability until the required network upgrades and other interconnection facilities are placed in service.  It also mirrors the Commission’s finding that a customer taking interim service should have the control technologies and protection systems needed to limit withdrawals to the approved level.  SDG&E addresses FILI in the TO Tariff in Sections 10.20 and 10.21 and in Article 5.9.1 and Appendices I and J of the pro forma Interconnection Agreement.  To the extent there were any existing partial interim service for Eligible Customers other than ECLLs, such service would continue (Section 10.18).

IV. CO-LOCATED LARGE LOADS

An ECLL serving a Co-Located Large Load must provide information concerning the associated generation, including the executed generator interconnection agreement or, if none exists, a queue number that will allow SDG&E to verify that the generator has submitted an interconnection application (Section 10.5(xi)).  CAISO and SDG&E will publish study results

24  Whether or not a Large Load has elected FILI service, the Large Load, like any other load, is always subject to curtailment in the event of emergencies that jeopardize the reliability of the larger grid.

PDF page 20

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 20 of 25

reflecting the combined presence of the Generating Units and Co-Located Large Loads, and memorialize those results in the generator’s LGIA.  Section 10.22 as proposed allocates responsibility between the two tariffs: the CAISO Tariff governs the interconnection of the Generating Unit, and the TO Tariff governs the interconnection of the ECLL, with neither tariff exempting a party from its cost responsibility obligations under the other tariff.  These provisions respond to the Commission’s concern that an Eligible Customer be designated to take transmission service on behalf of co-located load (P 94).

V. GRID ENHANCING TECHNOLOGIES

The Show Cause Order expresses concern at P 60 that CAISO and PTO tariffs lack clear and consistent provisions requiring the evaluation of alternative transmission technologies25 as potential solutions to accommodate an ECLL request for transmission service.  Continuing, the Order at P 61 states that CAISO and/or the PTOs should either: (a) explain whether their tariffs remain just and reasonable without provisions requiring “evaluation of alternative transmission technologies” and if such technologies are not selected, “demonstration [in study reports] why alternative transmission technologies” either were not feasible, would not lower costs, or would not provide for a faster timeline; or (b) propose implementing tariff changes.

In response, SDG&E states that consistent with California state law,26 SDG&E already evaluates the feasibility of Grid Enhancing Technologies (“GETs”) and other alternative transmission technologies.27  These evaluations consider, among other factors, feasibility, cost, achievable capacity, implementation timelines, reliability, and other relevant considerations. These analyses are performed in connection with SDG&E’s role in the CAISO TPP.  Consistent with this framework, the CAISO’s TPP specifically considers GETs, including advanced conductors, dynamic line ratings, power flow controllers, and topology optimization, as potential alternatives when developing solutions to identified transmission needs.28  SDG&E proposes to leverage this existing analytical framework, in its capacity as a PTO, when evaluating an

25 See Show Cause Order at p. 60 (defining the terms “alternative transmission technologies” and “Grid Enhancing Technologies” interchangeably to include” static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, tower lifting, and dynamic line ratings.”).
26  California Senate Bill 1006 (Chapter 597, Statutes of 2024).
27  See, e.g., “A Study of the Feasibility of Projects Using Grid Enhancing Technologies and Reconductoring with Advanced Conductors,” Submittal to California Independent System Operator Corporation by San Diego Gas and Electric Company in compliance with Cal.  Senate Bill 1006 (Jan. 1, 2026), available at https://www.sdge.com/sites/default/files/documents/2025-12/SDGE_SB- 1006_12292025_Clean.pdf.
28  See CAISO, 2026-2027 Transmission Planning Process Study Plan at 71, § 2.4, https://stakeholdercenter.caiso.com/InitiativeDocuments/2026-2027-Transmission-Planning-Process- and-Study-plan-jun-15-26.pdf.

PDF page 21

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 21 of 25

application to interconnect an ECLL and seeking concurrence from CAISO.  SDG&E has included evaluation of alternative transmission technologies in Section 10.13 of the TO Tariff.

VI. BRIEFING QUESTIONS

The Show Cause Order at PP 123-125 includes three briefing questions that apply to Transmission Owners.

A. Existing Commercial Arrangements

Paragraph 123 of the Show Cause Order states:

We direct further briefing regarding how CAISO and the Participating
Transmission Owners … should protect existing commercial arrangements
including: (1) what would be a reasonable implementation period to ensure minimal disruption to such existing commercial arrangements, and (2) how to allow a reasonable amount of time to finalize ongoing agreements that are nearing completion as of the date such tariff provisions are filed with the Commission.

SDG&E Response: (1) Not applicable to SDG&E.  As of the date of this filing, SDG&E has no existing commercial arrangements that would be affected by SDG&E’s proposed changes to its TO Tariff.  (2) Not applicable to SDG&E.  As of the date of this filing, SDG&E has no in- progress agreements with ECLLs that are “nearing completion.”

B. Planning Impacts from Flexible Services for Large Loads

Paragraph 124 of the Show Cause Order states:

Today’s order proposes ...  to establish new transmission services that recognize flexible large loads’ ability and willingness to limit their use of the transmission system under certain conditions....  Specifically, what, if any, potential impacts on regional and local transmission planning would arise from the introduction of the new transmission services discussed herein? For example, when planning for load growth, how would transmission providers and planners account for flexible large loads’ potential preference to take the new transmission services, including potential uncertainties around the type, location, and quantity of such expected loads?

SDG&E Response: The possible use of FILI service may allow an ECLL to energize load earlier than would otherwise be possible if the ECLL were required to defer its desired load energization until all required network upgrades were in service.  The CAISO’s PTOs coordinate with the CAISO in the development of transmission planning studies and the underlying power flow base cases.  This coordination ensures that the impacts of large loads, both existing and planned, on the transmission system are accounted for.

PDF page 22

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 22 of 25

Because SDG&E’s proposed FILI service will set grid withdrawal limits in the interconnection study process, the established limits can be directly incorporated in the planning base cases that are developed in coordination with the CAISO.  Furthermore, SDG&E will include an ECLL project in regional and local transmission planning base cases only after the ECLL has executed an Interconnection Agreement and provided the required financial security for construction.  This commitment threshold will help ensure that transmission planning reflects sufficiently committed projects and their applicable grid withdrawal limits, while preventing speculative or uncommitted FILI requests evaluated through the interconnection study process from distorting regional or local transmission planning assumptions.

SDG&E’s proposed approach is comparable to the framework used by the California Energy Commission (“CEC”) in developing its large-load forecasts used for CAISO transmission planning.  Under the CEC’s framework, proposed data-center loads are differentiated based on project maturity, including whether the project is an inquiry, an active application, or has a signed agreement, with different confidence levels applied based on the likelihood of project completion.29  Accordingly, both approaches seek to ensure that transmission planning appropriately reflects the degree of commitment and likelihood of materialization of prospective large-load projects, rather than treating all project requests as equally certain.

C. Structures to Prevent Cost Shifts

Paragraph 125 of the Show Cause Order requires:

Respondents to include information regarding potential structures for agreements between the transmission owner/provider and an Eligible Customer to prevent

unjust and unreasonable cost shifts among transmission customers related to
network upgrade costs required for large loads.  Further, please include information on what an appropriate minimum level of cost recovery and financial security from an Eligible Customer would be under any such agreements.

SDG&E Response: SDG&E’s proposed pro forma Interconnection Agreement includes the complete agreement between SDG&E as the TO and the ECLL regarding the measures that SDG&E will use to effectively eliminate any possibility of cost shifting from the ECLL to other transmission ratepayers as a result of Large Load failure or under-performance.  As an initial matter, the ECLL will be required to provide up-front funding in cash of all Interconnection Facilities, thereby eliminating any possible cost shifting for those facilities.30  Further, because the financial security for necessary network upgrades must be posted by the ECLL prior to the start of construction for those upgrades,31 and because the amount of such security is equal to the full

29  See CEC, Data Center Data Collection and Forecasting, slide 9, available at https://www.energy.ca.gov/sites/default/files/2026- 08/Data_Center_Data_Collection_and_Forecasting_ada.pdf.
30  See Appendix XIV, Article 11.5(ii)(a).
31  Id., Article 11.5.

PDF page 23

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 23 of 25

projected present value of the lifecycle revenue requirements of the network upgrades,32 there is virtually no cost-shifting risk.

VII. ISSUES TO BE ADDRESSED THROUGH THE CAISO TARIFF

The Show Cause Order raised concerns and issued directives that apply to the CAISO and not the PTOs.  SDG&E understands these concerns and directives will be addressed through the CAISO’s tariff and related processes.  CAISO’s proposals are discussed and detailed in CAISO’s Large Load Enhancements stakeholder process, in which SDG&E participated and provided input. These directives include:

•
the definitions of co-located load and Behind the Meter Generation (“BTMG”) (PP 88-89);
•
the rates, terms, and conditions of service that apply to interconnection customers serving co-located load, including the scope of CAISO’s analyses of co-location arrangements (PP 93, 96);

•
transmission services reflecting an Eligible Customer’s willingness and ability to limit withdrawals, including interim non-firm network transmission service and permanent firm and non-firm contract demand transmission services (PP 94, 100-101);

•
transmission and ancillary service charges, including regulation and black start services, for Eligible Customers taking service on behalf of Eligible Load (PP 95, 98-99);

•
the netting of BTMG against gross load for purposes of calculating Regional Access Charges (P 102); and

•
generator interconnection study processes and services for generating facilities serving electrically proximate large loads or large co-located loads, and the transmission service such Eligible Customers must take (PP 113-119).

VIII. CONFORMING AND MINISTERIAL REVISIONS

SDG&E notes that in addition to defining the new term “Large Load,” it has added related definitions necessary to make its proposed framework operative, and these additions have required the re-numbering of virtually all definitions within Section 3.  Among the added definitions are Co-Located Large Load (Section 3.9), Commercial Operation Date (Section 3.11), EMT Study (Section 3.23), Eligible Customer for Large Load (Section 3.25), FILI Service (Section 3.36), Interconnection Customer (Section 3.53), Project (Section 3.86), Scoping Meeting (Section 3.98), and Site Control (Section 3.99).  In addition, the existing, but revised, definition of Reliability Upgrade (Section 3.93) now applies to any “Project,” so that the cost responsibility provisions apply uniformly, and the revised definition of Transmission Revenue Credit (Section 3.114) now has new language stating that the term includes any draw on or liquidation of security posted in connection with network upgrades under an Interconnection Agreement with an ECLL.

32  Id., Article 11.5(ii)(b).

PDF page 24

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 24 of 25

SDG&E also proposes conforming changes, including replacing outdated cross-references to specific CAISO Tariff sections with references to “applicable sections” of the CAISO Tariff; replacing references to WSCC with WECC; updating website references from OASIS to SDG&E’s website; updating the Rate Effective Period to a calendar-year basis; specifying that the TACBAA will be revised effective January 1 of each year (Section 5.6); replacing separate System Impact Study and Facilities Study Agreements with a single Study Agreement (Sections 3.106, 9.1.2, 9.1.3, 10); and clarifying that the procedures for interconnection of wholesale generation are governed by the CAISO Tariff (Section 8.1).

Finally, in preparing this filing, SDG&E became aware that a recent eTariff filing inadvertently superseded most of Section 3 of the TO Tariff with only a partial version of Section 3.33  Specifically, the filing in question intended to modify the definition of “Transmission Revenue Credit” to include potential revenues from CAISO as a result of its implementation of the Extended Day-Ahead Market (“EDAM”), but in so doing replaced the entire section with a truncated version.  This filing uses what should have been the correct version of Section 3 as the base reflecting the full section as it existed before being inadvertently superseded, plus the definition change made in the EDAM Revenues Filing, i.e., the version of Section 3 that would exist but for this inadvertent eTariff error.  The redlined version of Section 3 shows the proposed changes to that base.

IX. ENCLOSURES

Enclosed for filing are an eTariff Electronic Filing Package containing all required Tariff Record Content Data and metadata, as well as the following filing attachments in PDF for posting on eLibrary:

1. this transmittal letter;
2. a clean version of each new or modified Section or Appendix of the TO Tariff as filed in eTariff, including the pro forma Study Agreement (Appendix XIII) and pro forma Interconnection Agreement (Appendix XIV); and

3. redlined versions of each modified Section of the TO Tariff as filed in eTariff.

X. EFFECTIVE DATE

SDG&E requests that the Commission accept the tariff revisions contained in this filing effective Tuesday, February 16, 2027, which is ninety-two (92) days from the date of this filing. SDG&E is prepared to implement the proposed revisions to its TO Tariff upon acceptance by the Commission.  In view of the upcoming holiday season, however, SDG&E believes that a modest extension to the usual 60-day notice period for Section 205 filings will facilitate the comment and review processes on the tariff changes proposed herein.  SDG&E understands that CAISO, PG&E,

33  See generally EDAM, Appendix IV, and Appendix VI Revisions to Transmission Owner Tariff, Docket No.  ER26-1506-000 (filed Feb.  25, 2026) (the “EDAM Revenues Filing”), which was accepted, effective May 1, 2026, by unpublished letter order dated April 23, 2026.

PDF page 25

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 25 of 25

SCE, and other California PTOs are requesting the same effective date for their proposed tariff changes.

XI. REQUEST FOR WAIVER

To the extent that any filing requirement in Part 35 of the Commission’s regulations is not satisfied by this filing and the materials enclosed herewith, SDG&E respectfully requests waiver of such requirements.

XII. COMMUNICATIONS

All communications, correspondence, and documents related to this proceeding should be served upon the following persons:

Pamela J.  Mills

Jonathan J.  Newlander
Regulatory Policy Manager

Senior Counsel
San Diego Gas & Electric Company
San Diego Gas & Electric Company
8330 Century Park Court, CP31E

8330 Century Park Court, CP32D
San Diego, CA 92123

San Diego, CA 92123
Phone: 858-637-3746

Phone: 858-654-1652
E-mail: PMills@sdge.com

E-mail: JNewlander@sdge.com

XIII. SERVICE

SDG&E has served a copy of this filing upon the CAISO and the CPUC.

XIV. CONCLUSION

WHEREFORE, for the foregoing reasons, SDG&E respectfully requests that the
Commission: (A) accept the proposed revisions to SDG&E’s TO Tariff as just and reasonable and not unduly discriminatory or preferential; (B) grant the requested effective date of February 16, 2027; and (C) terminate the show cause proceeding in Docket No.  EL26-71-000 as to SDG&E.

Respectfully submitted,

/s/ Jonathan J.  Newlander
________________________
Jonathan J.  Newlander
San Diego Gas & Electric Company
8330 Century Park Court, CP32D
San Diego, California 92123
Telephone:
(858) 654-1652
Email:
JNewlander@sdge.com
November 16, 2026

Attorney for San Diego Gas & Electric Company26

PDF page 26

CERTIFICATE OF SERVICE
I hereby certify that, pursuant to Rule 2010 of FERC’s Regulations, 18 C.F.R. § 385.2010, I have this day served the foregoing document upon the following representatives of the Public Utilities Commission of the State of California and the California Independent System Operator Corporation:

NAME
ORGANIZATION/ADDRESS
E-MAIL ADDRESS
Christine J.  Hammond
Assistant General Counsel
California Public Utilities
Commission
505 Van Ness Avenue
San Francisco, CA  94102
Christine.hammond@cpuc.ca.gov
Anthony Ivancovich
Deputy General Counsel
California Independent System
Operator Corporation
250 Outcropping Way
Folsom, CA  95630
aivancovich@caiso.com
Andrew Ulmer
Assistant General Counsel
California Independent System
Operator Corporation
250 Outcropping Way
Folsom, CA  95630
aulmer@caiso.com

Dated at San Diego, California, this 16th day of November, 2026.

/s/ Jonathan J.  Newlander

Jonathan J.  Newlander

PDF page 27

SECTION 3
DEFINITIONS - REDLINES

PDF page 28

3. TO Definitions. Capitalized terms used in this TO Tariff shall have the meanings set out below unless otherwise stated or the context otherwise requires. Capitalized terms used in this tariff and not defined below shall have the meanings set out in the ISO Tariff.

3.1.
Access Charge. A charge paid to the ISO by all UDCs, MSSs and, in certain cases, Scheduling Coordinators, delivering Energy to Gross Load, as set forth in Section 7.1applicable sections of the ISO Tariff. The Access Charge includes the High Voltage Access Charge, the Transition Charge, and the Low Voltage Access Charge.

3.2.
AGC. Generation equipment that automatically responds to signals from the ISO’s EMS control in real time to control the power output of electric generators within a prescribed area in response to a change in system frequency, tieline loading, or the relation of these to each other, so as to maintain the target system frequency and/or the established interchange with other areas within the predetermined limits.

3.3.
Ancillary Services. Regulation, Spinning Reserve, Non-Spinning Reserve, Replacement Reserve, Voltage Support and Black Start together with such other interconnected operation services as the ISO may develop in cooperation with Market Participants to support the transmission of Energy from Generation resources to Loads while maintaining reliable operation of the ISO Controlled Grid in accordance with Good Utility Practice.

3.4.
Applicable Reliability Criteria. The reliability standards established by

PDF page 29

NERC, WSCCWECC, and Local Reliability Criteria as amended from time to time, including any requirements of the Nuclear Regulatory Commission.

3.5.
Available Transfer Capacity. For a given transmission path, the capacity rating in MW of the path established consistent with ISO and WSCCWECC transmission capacity rating guidelines, less any reserved uses applicable to the path.

3.6.
Base Transmission Revenue Requirement. The Transmission Revenue Requirement which does not reflect the Transmission Revenue Balancing Account Adjustment (TRBAA) and Standby Transmission Revenues. 3.7.

Black Start. The procedure by which a Generating Unit self-starts without an external source of electricity thereby restoring power to the ISO Controlled Grid following system or local area blackouts.

3.8.
Business Day. A day on which banks are open to conduct general banking business in California.

3.9.
Co-Located Large Load. A Large Load that is physically connected to the facilities of an existing or planned generating facility on the Interconnection Customer’s side of the point of interconnection to the ISO Controlled Grid.

3.10. Commercial Operation. The status of a Project that has commenced the generation, consumption, or transmission of electricity, excluding electricity generated, consumed, or transmitted during initial testing and commissioning.

PDF page 30

3.11. 3.9Commercial Operation Date (“COD”). The date on which a Project commences Commercial Operation as agreed to by the TO and the Interconnection Customer pursuant to the Interconnection Agreement, and in accordance with the implementation plan agreed to by the TO and the CAISO.

3.12. Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed Interconnection Application.

3.1013.
Completed Interconnection Application. An Interconnection Application  that satisfies all of the information and other requirements of Section 10.3

of the TO Tariff and, if applicable, the information
requirements as specified by the ISO and posted on the ISO Home Page. 3.11. 3.14. Congestion. A condition that occurs when there is insufficient Available

Transfer Capacity to implement all Preferred Schedules
simultaneously or,
 in real time, to serve all Generation and Demand.
“Congested” shall be  construed accordingly.
.3.12 3.15. Congestion Management. The alleviation of Congestion in accordance

with applicable ISO Protocols and Good Utility Practice.
3.13.3.16.
Converted Rights. Those transmission service rights as defined in Section

2.4.4.2.1applicable sections of the ISO Tariff.
3.17. 3.14. CPUC. The California Public Utilities Commission, or its successor.

3.18. 3.15. Delivery Upgrade. The transmission facilities, other than Direct

PDF page 31

Assignment  Facilities and Reliability Upgrades, necessary to relieve constraints on the

 ISO Controlled Grid and to ensure the delivery of
energy from a New

 Facility to Load.
3.193.1.6.
Demand. The rate at which Energy is delivered to Loads and
Scheduling Points by Generation, transmission or distribution facilities. It is the product of voltage and the in-phase component of alternating current measured in units of watts or standard multiples thereof, e.g., 1,000 W = 1 kW, 1,000 kW = 1 MW, etc.

3.1720.
Direct Assignment Facilities. Facilities or portions of facilities that are owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting Interconnection under this TO Tariff to the ISO Controlled Grid at the point of interconnection. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval..

3.1821.
Dispatch. The operating control of an integrated electric system to:
i) assign specific Generation Units and other sources of supply to effect the supply to meet the relevant area Demand taken as Load rises or falls;

ii) control operations and maintenance of high voltage lines, substations, and equipment, including administration of safety procedures; iii) operate interconnections; iv) manage Energy transactions with other

interconnected Control Areas; and v) curtail Demand.
3.1922.
Distribution System. The distribution assets of a TO or UDC or

PDF page 32

MSS.
3..20  23.
Electromagnetic Transient (“EMT”) Study. A study using
electromagnetic time-domain simulation and detailed equipment and control models, as applicable, to evaluate the performance of an Interconnection request and its potential interactions with or impacts on the transmission system, consistent with applicable NERC requirements, as may be modified from time to time.

3.24. Eligible Customer. (i) Any utility (including Participating TOs, Market Participants and any power marketer), Federal power marketing agency, or any person generating Energy for sale or resale; Energy sold or produced by such entity may be Energy produced in the United States, Canada or Mexico; however, such entity is not eligible for transmission service that would be prohibited by Section 212(h)(2) of the Federal Power Act; and

(ii) any retail customer taking unbundled transmission service pursuant to a state retail access program or pursuant to a voluntary offer of unbundled retail transmission service by the Participating TO.

.3.213.25.
Eligible Customer for Large Load (“ECLL”). An Eligible
Customer taking transmission service on behalf of a Large Load. 3.26. Encumbrance. A legal restriction or covenant binding on the Participating TO that affects the operation of any transmission lines or associated facilities and which the ISO needs to take into account in exercising Operational Control over such transmission lines or associated if the Participating TO is not to risk incurring significant liability.

PDF page 33

Encumbrances shall include Existing Contracts and may include: (1) other legal restrictions or covenants meeting the definition of Encumbrance and arising under other arrangements entered into before the ISO Operations date, if any; and (2) legal restrictions or covenants meeting the definition of Encumbrance and arising under a contract or other arrangement entered into after the ISO Operations Date.

3.2227.
End Use Customer or End-User. A purchaser of electric power who purchases such power to satisfy a Load directly connected to the ISO Controlled Grid or to a Distribution System and who does not resell the power.

3.2328.
Energy. The electrical energy produced, flowing, or supplied by generation, transmission or distribution facilities, being the integral with respect to time of the instantaneous power, measured in units of watt- hours or standard multiples thereof, e.g., 1,000 Wh = 1 kWh, 1,000 kWh = 1 MWh, etc.

3.2429.
Entitlements. The right of the Participating TO obtained through contract or other means to use another entity’s transmission facilities for the transmission of Energy.

3.24130.
Exceptional Dispatch. As defined in Appendix A of the currently effective MRTU Tariff, a Dispatch Instruction issued for the purposes specified in Section 34.9 of the MRTU Tariff.

3.2531.
Existing Contracts. The contracts which grant transmission service rights in existence on the ISO Operations Date (including any contacts

PDF page 34

entered into pursuant to such contracts) as may be amended in accordance with their terms or by agreement between the parties thereto from time to time.

3.2632.
Existing Rights. Those transmission service rights defined in Section 2.4.4.1.1applicable sections of the ISO Tariff.

3.2733.
Expedited Interconnection Agreement. A contract between a party which has submitted a Request for Expedited Interconnection Procedures and the Participating TO to agree to process, on an expedited basis, the Completed Interconnection Application of such party and which sets forth the terms, conditions, and cost responsibilities for such interconnection. .3.28 Facilities Study Agreement. An agreement between a Participating TO and either a party requesting Interconnection to the ISO Controlled Grid, Market Participant, Project Sponsor, or identified principal beneficiaries pursuant to which the party requesting such Interconnection, Market Participants, Project Sponsor, or identified principal beneficiaries agrees to reimburse the Participating TO for the cost of performing or reviewing a Facilities Study.

3.293.34.
Facility or Facilities Study. An engineering study conducted to determine required modifications to the Participating TO’s transmission system, including the estimated cost and scheduled completion date for such modifications that will be required to provide needed services. 3.3035.

FERC. The Federal Energy Regulatory Commission, or its
successor.

PDF page 35

3.31.3.36.
Flexible Interim Load Interconnection (“FILI”) Service.
Interconnection service provided by the TO to an ECLL at the ECLL’s option, as set forth in the ECLL’s IA, enabling energization of a portion of the ECLL’s requested load addition pending completion of such Reliability Upgrades as the TO determines are necessary for full load energization.

3.37. FPA. Parts II and III of the Federal Power Act, 16 U.S.C. § 824 et seq., as they may be amended from time to time.

3.3238.
FTR (Firm Transmission Right). A contractual right, subject to the terms and conditions of the ISO Tariff, that entitles the FTR Holder to receive, for each hour of the term of the FTR, a portion of the Usage Charges received by the ISO for transportation of energy from a specific originating Zone to a specific receiving Zone and, in the event of an uneconomic curtailment to manage Day-Ahead congestion, to a Day- Ahead scheduling priority higher than that of a schedule using Converted Rights capacity that does not have an FTR.

3.3339.
FTR Holder. The owner of an FTR, as registered with the ISO. 3.3440.

Generating Unit. An individual electric generator and its associated plant and apparatus whose electrical output is capable of being separately identified and metered or a Physical Scheduling Plant that, in either case, is: (a) located within the ISO Control Area; (b) connected to the ISO Controlled Grid, either directly or via interconnected transmission, or distribution facilities, and (c) that is capable of producing and delivering

PDF page 36

net Energy (Energy in excess of a generating station’s internal power requirements).

3.3541.
Generation. Energy delivered from a Generating Unit.
3.3642.
Good Utility Practice. Any of the practices, methods, and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods, and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety, and expedition. Good Utility Practice is not intended to be any one of a number of the optimum practices, methods, or acts to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region. 3.3743.

Gross Load. Gross Load is all energy (adjusted for distribution losses) delivered for the supply of End-User Loads directly connected to the transmission facilities or distribution system of the Participating TO. Gross Load shall exclude the portion of the load of an individual End-Use Customer of the Participating TO that is served by a Generating Unit that:

(a) is located on the customer’s site through over-the-fence arrangements as authorized by Section 218 of the California Public Utilities Code; (b) is a qualifying small power production facility or qualifying cogeneration facility, as those terms are defined in the FERC’s regulations implementing Section 201 of the Public Utility Regulatory Policies Act of

PDF page 37

1978; (c) was serving the customer’s Load on or before March 31, 2000; and (d) secured Standby Service from the Participating TO under terms approved by a Local Regulatory Authority or FERC as applicable, as of March 31, 2000 and continues to secure Standby Service from the Participating TO or can be curtailed concurrently with an outage of the Generating Unit serving the Load.

3.3844.
High Voltage Access Charge. A component of the Access Charge determined by the ISO and assessed to the Participating TO under Section 7.1applicable sections of the ISO Tariff.

3.3945.
High Voltage Transmission Facility. A transmission facility under the operational control of the ISO that is owned by the Participating TO or to which the Participating TO has an Entitlement that is represented by a Converted right and that operates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs of which are not directly assigned to one or more specific customers.

3.4046.
High Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s High Voltage Transmission Facilities and Converted Rights associated with High Voltage Transmission Facilities. 3.4147.

High Voltage Utility Specific Rate. The Participating TO’s High Voltage Transmission Revenue Requirement divided by the Participating TO’s forecasted Gross Load.

3.4248.
High Voltage Wheeling Access Charge. The Wheeling Access

PDF page 38

Charge assessed by the ISO associated with the recovery of the Participating TOs’ High Voltage Transmission Revenue Requirements in accordance with Section 7.1applicable sections of the ISO Tariff. 3.4349.

Inter-Zonal Interface. The (i) group of transmission paths between two adjacent Zones of the ISO Controlled Grid, for which a physical, non- simultaneous transmission capacity rating (the rating of the interface) has been established or will be established prior to the use of the interface for Congestion Management; (ii) the group of transmission paths between an ISO Zone and an adjacent Scheduling Point, for which a physical, non- simultaneous transmission capacity rating (the rating of the interface) has been established or will be established prior to the use of the interface for Congestion Management; or (iii) the group of transmission paths between two adjacent Scheduling Points, where the group of paths has an established transfer capability and established transmission rights. 3.4450.

Interconnection. Transmission facilities, other than additions or replacements to existing facilities that: i) connect one system to another system where the facilities emerge from one and only one substation of the two systems and are functionally separate from the ISO Controlled Grid facilities such that the facilities are, or can be, operated and planned as a single facility; or ii) are identified as radial transmission lines pursuant to contract; or iii) produced Generation at a single point on the ISO Controlled Grid; provided that such interconnection does not include facilities that, if not owned by the Participating TO, would result in a

PDF page 39

reduction in the ISO’s Operational Control of the Participating TO’s portion of the ISO Controlled Grid.

3.4551.
Interconnection Agreement. A contract between a party requesting interconnection and the Participating TO that owns the transmission facility with which the requesting party wishes to interconnect. 3.4652.

Interconnection Application. An application that requests
Interconnection to the ISO Controlled Grid.
3.53.3.47.
Interconnection Customer.  The Eligible Customer requesting
interconnection to the ISO Controlled Grid.
3.54. Interest. Interest shall be calculated in accordance with the methodology specified for interest on refunds in the regulations of FERC at 18 C.F.R. §35.19(a)(2)(iii)(1996). Interest on delinquent amounts shall be calculated from the due date of the bill to the date of payment. When payments are made by mail, bills shall be considered as having been paid on the date of receipt.

3.4855.
Independent System Operator (“ISO” or “CAISO”). The California Independent System Operator Corporation, as state chartered, nonprofit corporation that controls the transmission facilities of all Participating TOs and dispatches certain Generating Units and Loads.

3.4956.
ISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13applicable sections of the ISO Tariff, as amended from time to time.

3.5057.
ISO Controlled Grid or CAISO Controlled Grid. The system of

PDF page 40

transmission lines and associated facilities of the Participating TOs that have been placed under the ISO’s Operational Control.

3.5158.
ISO Protocols. The rules, protocols, procedures and standards attached to the ISO Tariff as Appendix L, promulgated by the ISO (as amended from time to time) to be complied with by the ISO Scheduling Coordinators, Participating TOs and all other Market Participants in relation to the operation of the ISO Controlled Grid and the participation in the markets for Energy and Ancillary Services in accordance with the ISO Tariff.

3.5259.
ISO Tariff. The California Independent System Operator
Corporation Operating Agreement and Tariff, dated March 31, 1997, as it may be modified from time to time.

3.60
Large Load.  A new customer, located at a single site behind one or more points of interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater.

3.61.3.53.
Load. An end-use device of an End-Use Customer that consumes power. Load should not be confused with Demand, which is the measure of power that a Load receives or requires.

3.5462.
Local Furnishing Bond. Tax-exempt bonds utilized to finance facilities for the local furnishing of electric energy, as described in section 142(f) of the Internal Revenue Code, 26 U.S.C. § 142(f).

3.5563.
Local Furnishing Participating TO. Any Tax-Exempt Participating TO that owns facilities financed by Local Furnishing Bonds.

PDF page 41

3.5664.
Local Publicly Owned Electric Utilities. A municipality or municipal corporation operating as a public utility furnishing electric service, a municipal utility district furnishing electric service, a public utility district furnishing electric services, and irrigation district furnishing electric services, or a joint powers authority that include one or more of these agencies and that owns Generation or transmission facilities, or furnishes electric services over its own or its members’ electric Distribution System.

3.5765.
Local Regulatory Authority. The state or local governmental authority responsible for the regulation or oversight of a utility. 3..5866.

Local Reliability Criteria. Reliability criteria established at the ISO Operations Date, unique to the transmission systems of each of the Participating TOs.

3.5967.
Low Voltage Access Charge. The Access Charge applicable under Section 7.1applicable sections of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement of the Participating TO. 3.6068.

Low Voltage Transmission Facility. A transmission facility under the operational control of the ISO owned by the Participating TO or to which the Participating TO has an Entitlement that is represented by a Converted Right, which is not a High Voltage Transmission Facility, and supporting facilities, and the costs of which are not directly assigned to one or more specific customers.

3.6169.
Low Voltage Transmission Revenue Requirement. The portion of

PDF page 42

the Participating TO’s TRR associated with and allocable to the Participating TO’s Low Voltage Transmission Facilities and Converted Rights associated with Low Voltage Transmission Facilities. 3..6270.

Low Voltage Wheeling Access Charge. The Wheeling Access
Charge associated with the recovery of the Participating TO’s Low Voltage Transmission Revenue Requirement in accordance with Section 7.1applicable sections of the ISO Tariff.

3.6371.
Market Participant. An entity, including a Scheduling Coordinator, who participates in the Energy marketplace though the buying, selling, transmission, or distribution of Energy or Ancillary Services into, out of, or through the ISO Controlled Grid.

3.6472.
MSS (Metered Subsystem). A geographically contiguous system of a New Participating TO, located within a single Zone which has been operating for a number of years prior to the ISO Operations Date subsumed within the ISO Control Area and encompassed by ISO certified revenue quality meters at each interface point with the ISO Controlled Grid and ISO certified revenue quality meters on all Generating Units internal to the system, which is operated in accordance with an agreement described in Section 3.3.1applicable sections of the ISO Tariff. 3.6573.

NERC. The North American Electric Reliability Council or its successor.

3.6674.
New Facility. (a) Each generating unit that proposes to sell its Generation at wholesale that seeks to connect to the ISO Controlled Grid;

PDF page 43

(b) each existing generating unit directly interconnected to the ISO Controlled Grid that will be repowered and increases the total capability of the power plant; or (c) each existing generating unit directly interconnected to the ISO Controlled Grid that will be repowered, increasing the total capability of the power plant but has changed the electrical characteristics of the power plant such that its reenergization may violate Applicable Reliability Criteria and require additional Direct Assignment Facilities or Reliability Upgrades.

3.6775.
New Facility Operator. The owner of a planned New Facility, or its designee.

3.6876.
New High Voltage Transmission Facility. A High Voltage
Transmission Facility of the Participating TO that enters service after the beginning of the transmission period described in Section 4 of Schedule 3 of Appendix Fapplicable sections of the ISO Tariff, or a capital addition made after the beginning of the transition period described in Section 4.1 of Schedule 3 of Appendix F of the ISO Tariff to an Existing High Voltage Transmission Facility.

3.6977.
New Participating TO. A Participating TO that is not an Original Participating TO.

3.7078.
Non-Participating TO. A TO that is not a party to the TCA or for the purposes of Sections 2.4.3 and 2.4.4applicable sections of the ISO Tariff the holder of transmission service rights under an Existing Contract that is not a Participating TO.

PDF page 44

3.7179.
Non-Self-Sufficient Access Charge. A charge for access to the ISO Controlled Grid, referenced in certain Existing Contracts to be paid by the Existing Contract holder to the Participating TO. The Participating TO’s non-self-sufficient contract demand rate shall be calculated by dividing the Base Transmission Revenue Requirement by the sum of the highest hourly system demand forecast to be delivered by the Participating TO to End- Use Customers connected to its transmission and distribution facilities for each month of the year used by the Participating TO for base transmission rate development.

3..7280.
Non-Spinning Reserve. The portion of off-line generating capacity that is capable of being synchronized and ramping to a specified load in ten minutes (or load that is capable of being interrupted in ten minutes) and that is capable of running (or being interrupted) for at least two hours. 3.7381.

Operational Control. The rights of the ISO under the Transmission Control Agreement and the ISO Tariff to direct Participating TOs how to operate their transmission lines and facilities and other electric plant affecting the reliability of those lines and facilities for the purpose of affording comparable non-discriminatory transmission access and meeting Applicable Reliability Criteria.

3.7482.
Original Participating TO. A participating TO that was a
Participating TO as of January 1, 2000. The Original Participating TO’s are Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company.

PDF page 45

3.7583.
Participating TO. A party to the TCA whose application under Section 2.2 of the TCA has been accepted and who has placed its transmission assets and Entitlements under the ISO’s Operational Control in accordance with the TCA.  A Participating TO may be an Original Participating TO or a New Participating TO. For purposes of this TO Tariff, the Participating TO is San Diego Gas & Electric Company. 3.7684.

Participation Agreement. An agreement between a Participating TO and a Project Sponsor that specifies the terms and conditions under which the Participating TO will construct a transmission addition or upgrade on behalf of the Project Sponsor.

3.7785.
Physical Scheduling Plant. A group of two or more related Generating Units, each of which is individually capable of producing Energy, but which either by physical necessity or operational design must be operated as if they were a single Generating Unit and any Generating Unit or Units containing related multiple generating components which meet one or more of the following criteria: i) multiple generating components are related by a common flow of fuel which cannot be interrupted without a substantial loss of efficiency of the combined output of all components; ii) the Energy production from one component necessarily causes Energy production from other components; iii) the operational arrangement of related multiple generating components determines the overall physical efficiency of the combined output of all components; iv) the level of coordination required to schedule individual

PDF page 46

generating components would cause the ISO to incur scheduling costs far in excess of the benefits of having scheduled such individual components separately; or v) metered output is available only for the combined output of related multiple generation components and separate generating component metering is either impractical or economically inefficient. .3.783.86.

Project. The facilities for which the Interconnection Customer is requesting interconnection, but shall not include the Interconnection Customer’s owned Interconnection facilities.

3.87. Project Proponent. A Market Participant or group of Market Participants that: (i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition and upgrade, and thus is not a Project Sponsor; and (iii) initiates proceedings under the ISO ADR Procedures to determine the need for the proposed transmission addition or upgrade.

3.7988.
Project Sponsor. A Market Participant or group of Market
Participants or a Participating TO that proposes the construction of a transmission addition or upgrade in accordance with Section 3.2applicable sections of the ISO Tariff.

3.8089.
Regional Transmission Group (“RTG”). A voluntary organization approved by FERC and composed of transmission owners, transmission users, and other entities, organized to efficiently coordinate the planning, expansion and use of transmission on a regional and inter-regional basis. 3.8190.

Regulation. The service provided by Generating Units equipped

PDF page 47

and operating with AGC which will enable such units to respond to the ISO’s direct digital control signals in an upward and downward direction to match, on a real time basis, Demand and resources, consistent with established NERC and WSCCWECC operating criteria. Regulation is used to control the power output of electric generators within a prescribed area in response to a change in system frequency, tieline loading, or the relation of these to each other so as to maintain the target system frequency and/or the established interchange with other areas within the predetermined limits.

3.8291.
Reliability Criteria. Pre-established criteria that are to be followed in order to maintain desired performance of the ISO Controlled Grid under contingency or steady state conditions.

3.8392.
Reliability Services. Those services provided by the ISO: 1) that are deemed by the ISO as necessary to maintain reliable electric in the ISO Control Area; and 2) whose costs are billed by the ISO to the Participating TO pursuant to the ISO Tariff. In addition, Reliability Services shall include services provided by the Participating TO as a result of implementing ISO Operating Procedure M-438, whose stated purpose is to enhance reliability grid operations and local area reliability; services obtained from Reliability Must Run units; local out of market dispatch calls; generation committed pursuant to the ISO’s must-offer requirement when the unit is committed for local reliability; and local out of market dispatch calls; upon implementation of Market Redesign and Technology

PDF page 48

Upgrade, generators committed pursuant to the ISO’s Exceptional Dispatch authority., and any default loss pursuant to applicable sections of the ISO Tariff billed to the Participating TO resulting from the ISO’s use of its Exceptional Dispatch authority.

3.8493.
Reliability Upgrade. The transmission facilities, other than Direct Assignment Facilities, at or beyond the first point of

Interconnectioninterconnection necessary to interconnect a New Facility or wholesale loadProject safely and reliably to the ISO Controlled Grid, which would not have been necessary but for the Interconnection of a New Facility or wholesale loadProject, including network upgrades necessary to remedy short circuit or stability problems resulting from the interconnection of a New Facility or wholesale loadProject to the ISO Controlled Grid.  Reliability Upgrades also include, consistent with WSCCWECC practice, the facilities necessary to mitigate any adverse impact a New Facility’s or wholesale load’sProject’s interconnection may have on a path’s WSCCWECC path rating. Reliability Upgrades shall be specified in the Interconnection Agreement that governs Interconnection service to the New Facility Operator or wholesale load and shall be subject to FERC approvalProject.

3.8594.
Replacement Reserve. Generating capacity that is dedicated to the ISO, capable of starting up if not already operating, being synchronized to the ISO Controlled Grid, and ramping to a specified Load point within a sixty (60) minute period, the output of which can be continuously

PDF page 49

maintained for a two hour period. Also, Curtailable Demand that is capable of being curtailed within sixty minutes and that can remain curtailed for two hours.

3.8695.
Request for Expedited Interconnection Procedures. A written request by which an applicant for Interconnection can request expedited processing of its Interconnection Application.

3.8796.
Scheduling Coordinator. An entity certified by the ISO for the purposes of undertaking the functions specified in Section 2.2.6applicable sections of the ISO Tariff.

3.8897.
Scheduling Point. A location at which the ISO Controlled Grid is connected, by a group of transmission paths for which a physical, non- simultaneous transmission capacity rating has been established for Congestion Management, to transmission facilities that are outside the ISO’s Operational Control. A Scheduling Point typically is physically located at an “outside” boundary of the ISO Controlled Grid (e.g., at the point of interconnection between a Control Area utility and the ISO Controlled Grid). For most practical purposes, a Scheduling Point can be considered to be a Zone that is outside the ISO’s Controlled Grid. .3.893.98.

Scoping Meeting. The meeting between representatives of the Interconnection Customer and Transmission Owner conducted for the purpose of discussing the interconnection request and interconnection options, exchanging information including any transmission data and earlier study evaluations that would be reasonably expected to impact such

PDF page 50

interconnection options, refining information and models provided by the Interconnection Customer, and analyzing such information.

3.99. Site Control.  Documentation reasonably demonstrating: (1) ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Project; (2) an option to purchase or acquire a leasehold site for such purpose; or (3) an exclusivity or other business relationship between Interconnection Customer and the entity having the right to sell, lease or grant Interconnection Customer the right to possess or occupy a site for such purpose.

3.100. Spinning Reserve. The portion of unloaded synchronized generating capacity that is immediately responsive to system frequency and that is capable of being loaded in ten minutes, and that is capable of running for at least two hours.

3.90101.
Standby Rate. A rate assessed a Standby Service Customer by the Participating TO, as approved by the Local Regulatory Authority, or FERC, as applicable, for Standby Service which compensates the Participating TO, among other things for costs of High Voltage Transmission Facilities.

3.91102.
Standby Service. Service provided by the Participating TO which allows a Standby Service Customer, among other things, access to High Voltage Transmission Facilities for the delivery of backup power on an instantaneous basis to ensure that Energy may be reliably delivered to the Standby Service Customer in the event of an outage of a generating Unit

PDF page 51

serving the customer’s Load.
3.92103.
Standby Service Customer. A retail End-Use Customer of the Participating TO that receives Standby Service and pays a Standby Rate. 3.93104.

Standby Transmission Revenue. The transmission rate revenues associated with Standby Service collected by the Participating TO from those Standby Service Customers who are not billed for Standby Service on a Gross Load basis.

3.94105.
System Impact Study. An engineering study conducted to
determine whether a request for Interconnection to the ISO Controlled Grid would require new transmission additions, upgrades, or other mitigation measures.

3..95 System Impact 106. Study Agreement. An agreement between a Participating TO and an entity that has requested Interconnection to the Participating TO’s transmission system pursuant to which the entity requesting Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a System Impact Study., a Facilities Study, and/or an Electromagnetic Transient Study.

3.96107.
Rate Effective Period. The period during which transmission service rates calculated pursuant to the formula rate provisions contained in Appendix IX are effective. The initial Rate Effective Period shall be OctoberSeptember 1, 20032013, or such other date as may be provided by FERC, through June 30, 2004.December 31, 2014. Each subsequent Rate Effective Period shall be the twelve-month period from JulyJanuary 1

PDF page 52

through June 30December 31.
3.97108.
TO Tariff. This Transmission Owner Tariff, as it may be amended or superseded.

3.98109.
Transition Charge. A component of the Access charge determined by the ISO and assessed the Participating TO along with the High Voltage Access Charge in accordance with Section 5.7 of Appendix F, Schedule 3applicable sections of the ISO Tariff.

3.99110.
Transmission Access Charge Balancing Account Adjustment
(“TACBAA”). A mechanism established by the Participating TO which will ensure that the difference between (i) the actual billings by the ISO pursuant to Section 7.1.2applicable sections of the ISO Tariff for the High Voltage Access Charge and Transition Charge and (ii) the revenues disbursed by the ISO pursuant to Section 7.1.3applicable sections of the ISO Tariff are recovered from the Participating TO’s End-Use Customers. 3.100111.

Transmission Control Agreement (“TCA”). The agreement
between the ISO and Participating TOs establishing the terms and conditions under which TOs will become Participating TOs and how the ISO and each Participating TO will discharge their respective duties and responsibilities, as may be modified from time to time.

3.101112.
Transmission Owner (“TO”). An entity owning transmission
facilities or having firm contractual rights to use transmission facilities. 3.102113.

Transmission Revenue Balancing Account Adjustment
(“TRBAA”). A mechanism established by the Participating TO which will

PDF page 53

ensure that all Transmission Revenue Credits and other credits specified in Sections 6 and 8 of Appendix F, Schedule 3applicable sections of the ISO Tariff, flow through to transmission customers.

3.103114.
Transmission Revenue Credit. The net of: 1) the revenues received by the Participating TO from the ISO for Wheeling service, including EDAM Recoverable Revenue, Usage Charges (excluding any Usage Charges received by the Participating TO as an FTR Holder) and from the sale of an FTR; and any additional appropriate amounts included in the ISO tariff definition of Transmission Revenue Credit set forth in Appendix A of the CAISO Tariff; 2) Existing Transmission Contract (“ETC”) and Transmission Ownership Rights (“TOR”) Cost Differentials which include the shortfall or surplus resulting from any cost differences between Transmission Losses and Ancillary Service requirements associated with Existing Rights and the ISO’s rules and protocols; 3) ISO Charge Type 4575 identified as Settlements, Metering, and Client Relations charge; and

4) CAISO Charge Types 7989 and 7999, identified as Invoice Deviation Interest Distribution and Invoice Deviation Interest Allocation, as determined by the CAISO and consistent with the CAISO tariff. ;  and 5) a draw or liquidation of security in connection with Network Upgrades under an Interconnection Agreement with an ECLL.

3.104115.
Transmission Revenue Requirement (“TRR”). The TRR is the total annual authorized revenue requirement associated with transmission facilities and Entitlements turned over to the Operational Control of the

PDF page 54

ISO by the Participating TO. The costs of any transmission facility turned over to the Operational Control of the ISO shall be fully included in the Participating TO’s TRR. The TRR includes the costs of transmission facilities and Entitlements and deducts Transmission Revenue Credits and credits for Standby Transmission Revenue and the transmission revenue expected to be actually received by the Participating TO for Existing Rights and Converted Rights. The TRR is shown in Appendix I. 3.105116.

Uncontrollable Force. Any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, order, regulation or restriction imposed by governmental military or lawfully established civilian authorities or any other cause beyond the reasonable control of the ISO or Market Participant (as the case may be) which could not be avoided through the exercise of Good Utility Practice.

3.106117.
Usage Charge. The amount of money, per 1kW of scheduled flow, that the ISO charges a Scheduling Coordinator for use of a specific congested Inter-Zonal Interface during a given hour.

3.107118.
Utility Distribution Company (“UDC”). An entity that owns a Distribution System for the delivery of Energy to and from the ISO Controlled Grid, and that provides regulated retail electric service to Eligible Customers, as well as regulated procurement service to those End-Use Customers who are not yet eligible for direct access, or who choose not to arrange services through another retailer.

PDF page 55

3.108119.
Voltage Support. Services provided by Generating Units or other equipment such as shunt capacitors, static var compensators, or synchronous condensers that are required to maintain established grid voltage criteria.  This service is required under normal or system emergency conditions.

3.109120.
Western System Coordinating Council (“WSCCWECC”). The
Western Systems Coordinating Council or its successor.
3.110121.
Wheeling Access Charge. The charge assessed by the ISO that is paid by a Scheduling Coordinator for Wheeling in accordance with Section 7.1applicable sections of the ISO Tariff. Wheeling Access Charges shall not apply for Wheeling under a bundled non-economy Energy coordination agreement of a Participating TO executed prior to July 9, 1996. The Wheeling Access Charge may consist of a High Voltage Wheeling Access Charge and a Low Voltage Wheeling Access Charge. 3.111122.

Wheeling Out. Except for Existing Rights exercised under an Existing Contract in accordance with Sections 2.4.3 and 2.4.4.applicable sections of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a Generating Unit located within the ISO Controlled Grid to serve a Load located outside the transmission and Distribution system of a Participating TO.

3.112123.
Wheeling Through. Except for Existing Rights and Non-Converted Rights exercised under an Existing Contract in accordance with Sections 2.4.3 and 2.4.4 of the ISO Tariff, the use of the ISO Controlled Grid for

PDF page 56

the transmission of Energy from a resource located outside the ISO Controlled Grid to serve a Load located outside the transmission and distribution system of a Participating TO.

3.113124.
Wheeling. Wheeling Out or Wheeling Through.
3.114125.
Wholesale Customer. A person wishing to purchase Energy and Ancillary Services at a Bulk Supply Point or a Scheduling Point for resale. 3.115126.

Zone. A portion of the ISO Controlled Grid within which
Congestion is expected to be small in magnitude or to occur infrequently. “Zonal” shall be construed accordingly.

PDF page 57

SECTION 5
ACCESS CHARGES AND TRANSMISSION RATES - REDLINES

PDF page 58

5. Access Charges and Transmission Rates.
5.1.
Low Voltage Access Charge. The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff. The Low Voltage Access Charge customer, shall pay the Participating TO, Low Voltage Access Charge equal to the product of the Participating TO’s Low Voltage Access Charge rate and the Low Voltage Access Charge customer’s Gross Load, as provided by the ISO. The Participating TO’s monthly charges to be applied to Low Voltage Access Charge customers are determined pursuant to the provisions of Appendices VIII and IX hereof. The Low Voltage Access Charge applicable for the current Rate Effective Period is shown on SDG&E’s OASISwebsite, which can be accessed at www.sdge.com\toforum,www.sdge.com or through a link to SDG&E’s web page that is located on the CAISO website at www.caiso.com.

5.2.
Wheeling Access Charge. The Wheeling Access Charge shall be determined in accordance with the ISO Tariff. The Wheeling Access Charge, assessed by the ISO, consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge. The High Voltage Wheeling Access Charge is set forth in the ISO Tariff. The Participating TO’s Low Voltage Wheeling Access Charge is determined pursuant to the provisions of Appendices VIII and IX hereof. The Low Voltage

PDF page 59

Wheeling Access Charge applicable for the current Rate Effective Period is available on SDG&E’s OASISwebsite, which is shown at www.sdge.com\toforum,www.sdge.com, or through a link to SDG&E’s web page that is accessible through the CAISO’s OASIS at www.caiso.com.

5.3.
End-User Transmission Rates. End-User transmission rates for a FERC-jurisdictional Participating TO shall be based on the Base Transmission Revenue Requirement authorized by FERC. In addition, all End-Use Customers of a FERC-jurisdictional Participating TO shall be subject to the FERC-authorized TRBAA rate and TACBAA rate. For a Local Publicly Owned Electric Utility that is a Participating TO, such rates shall be submitted to the ISO for information only. In addition, all customers of a Local Publicly Owned Electric Utility that is a Participating TO shall be subject to the Local Regulatory Authority authorized TRBAA, which shall also be submitted to the ISO. The Participating TO’s End-User transmission rates, by retail rate schedule, are determined pursuant to the provisions of Appendices VIII and IX hereof. The End-User transmission rates applicable during the Rate Effective Period are available on SDG&E’s OASISwebsite, which is shown at www.sdge.com\toforum,www.sdge.com, or through a link to SDG&E’s web page that is accessible through the CAISO’s OASIS at www.caiso.com. An End-User shall pay the

PDF page 60

same End-User transmission rate as other similarly situated End- Use Customers of the Participating TO regardless of its energy supplier. End-Users withdrawing power from the Participating TO’s transmission or distribution facilities shall not qualify for transmission access under the Wheeling Access Charge if FERC would be prohibited from ordering transmission service for such customer by Section 212(h) of the FPA.

5.4.
Transmission Revenue Requirement. As set forth in the ISO Tariff, the Transmission Revenue Requirement for each Participating TO shall be used to develop the Access Charges set forth in the ISO Tariff. The Transmission Revenue Requirement, High Voltage Transmission Revenue Requirement, and Low Voltage Transmission Revenue Requirement for the Participating TO are set forth in Appendix I.

5.5.
Transmission Revenue Balancing Account Adjustment (TRBAA). The Participating TO shall maintain a Transmission Revenue Balancing Account Adjustment (“TRBAA”) that will ensure that all Transmission Revenue Credits and the refunds, specified in Sections 6 and 8 of Appendix F. Schedule 3 of the ISO Tariff, associated with transmission service are flowed through to customers taking transmission service from the ISO. The TRBAA shall be equal to:

TRBAA = Cr + Cf + I +FF&U

PDF page 61

Where:

 Cr =  The principal balance in the TRBAA recorded in FERC Account No. 254 as of September 30 of the year prior to commencement of the January billing cycle. This balance represents the unamortized balance in the TRBAA from the previous period and the difference in the amount of revenues from Transmission Revenue Credits and the amount of such revenues that has been refunded to customers through operation of the TRBAA, adjusted for franchise fees and uncollectible accounts expense; Cf = The forecast of Transmission Revenue Credits for the following calendar year;

I =
The interest balance for the TRBAA, which shall be calculated using the interest rate pursuant to Section 35.19(a) of FERC’s regulations under the Federal Power Act (18 CFR Section 35.19(a)). Interest shall be calculated based on the average TRBAA principal balance each month, compounded quarterly; and FF&U=

An adjustment for franchise fees and uncollectible accounts.

Beginning in January of each year, the bills of End-Use Customers of the Participating TO shall include, as a component of the End-User transmission rates, a TRBAA rate per kilowatt- hour (rounded to the nearest $0.00001) equal to:

TRBAA Rate = TRBAA

PDF page 62

S

Where:
S = The total kilowatt-hours of Gross Load measured at the customer meter level as recorded for the twelve month period ending September 30 of the year prior to commencement of the January billing cycle.

5.6
Transmission Access Charge Balancing Account Adjustment (TACBAA). Commencing on the transition date determined under Section 4 ofUnder Schedule 3 to Appendix F of the ISO Tariff, the Participating TO shall maintain a Transmission Access Charge Balancing Account Adjustment (TACBAA). Each month the Participating TO shall make two entries to the TACBAA. One entry will equal the difference between (i) the actual charges by the ISO to the Participating TO pursuant to Section 26.1.2 of the ISO Tariff for the High Voltage Access Charge and Transition Charge and (ii) the Revenues disbursed by the ISO to the Participating TO pursuant to Section 26.1.3 of the ISO Tariff. The second entry will equal the TACBAA rate revenues, adjusted for franchise fees and uncollectible accounts expense, billed to End-Use Customers during the month. Interest on the amounts accumulated in the TACBAA shall be calculated based on the average TACBAA principal balance each month, compounded quarterly, using the interest rate pursuant to Section

PDF page 63

35.19(a) of FERC’s regulations under the Federal Power Act (18 C F R  Section 35.19(a)). For service rendered on and after the effective date of new retail rates, authorized by the CPUC, modifying the frozen retail rates established pursuant to California Assembly Bill 1890, the bills of End-Use Customers of the

Participating TO shall include, as a component of the End- User transmission rates, a TACBAA rate per kilowatt-hour (rounded to the nearest $0.00001) equal to:

TACBAA Rate = Br + Bf – Rf + FF&U
S
Where:
Br = The Balance of the TACBAA, including interest, consisting of the recorded balance and the projected change for the remaining months of the  period prior to the commencement of the billing cycle implementing a new rate;

Bf = A forecast of the annual Access Charge billings from the ISO; Rf = A forecast of the annual revenues disbursed by the ISO to the Participating TO pursuant to Section 26.1.3 of the ISO Tariff;

FF&U = An adjustment for franchise fees and uncollectible accounts; and S = Total Gross Load, in kilowatt-hours measured at the customer meter level, recorded for the most recent twelve-month period prior to the Participating TO’s filing with FERC to revise the TACBAA rate. The TACBAA shall be revised effective January 1 of each year; however, nothing

PDF page 64

herein shall preclude the Participating TO from filing with the FERC to revise the TACBAA rate at any other time.

PDF page 65

SECTION 8
OBLIGATION TO INTERCONNECT OR CONSTRUCT TRANSMISSION EXPANSIONS & FACILITY UPGRADES - REDLINES

PDF page 66

8. Obligation to Interconnect or Construct Transmission Expansions & Facility Upgrades.

8.1.
Participating TO Obligation to Interconnect. The Participating TO shall, at the request of a third party pursuant to Section 10, interconnect its system to the generation or loadProject of such third party, or modify an existing Interconnection. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the FPA. Interconnections requested by entities or individuals that are not so eligible shall be governed by the Local Regulatory Authority. The procedures to interconnect transmission facilities and wholesale load to the ISO Controlled Grid shall be governed by this TO Tariff and the ISO Tariff, as applicable.  The procedures for Interconnection of wholesale generation to the ISO Controlled Grid shall be governed by the ISO Tariff.

8.1.1. Interconnection to Transmission System. Interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, and ISO reliability criteria for the ISO Controlled Grid. The Participating TO will not accommodate the Interconnection if doing so would impair system reliability, or would otherwise adversely affect the ability of the Participating TO to honor its Encumbrances existing as of the time an entity submits its Interconnection Application. The Participating TO shall identify any such adverse effect on its

PDF page 67

Encumbrances in the System Impact Study performed pursuant to Section 10.7. To the extent that Participating TO determines that the Interconnection of a New FacilityProject will have an adverse effect on Encumbrances, the New Facility OperatorEligible Customer shall mitigate such adverse effect.

8.1.2. Costs Associated with Interconnection. Each partyEligible Customer requesting Interconnection of a Project shall be solely responsible for and shall pay the costs of planning, installing, operating, and maintaining Direct Assignment Facilities and if applicable, as further set forth below, any Reliability Upgrades required to provide the requested Interconnection.

As set forth in Section 8.1.3 below, and as shall be documented in the Interconnection Agreement, Appendix XIV of this TO Tariff, each ECLL shall be responsible for posting initial security sufficient to cover the estimated present value of the life- cycle revenue requirements for required Reliability Upgrades. In addition, such partyeach Eligible Customer shall

implement all existing operating procedures necessary to safely and reliably interconnect such party’s generation or wholesale loadProject (including an ECLL) to the facilities of the Participating TO and to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. A New

PDF page 68

Facility OperatorAn Eligible Customer shall be responsible for the costs of Reliability Upgrades only: (a) if the necessaryCAISO does not identify such facilities are not includedas needed in the ISO Controlled Grid Transmission Expansion Plan approved as the New Facility Operator’s Completed Application Date, orits transmission planning process ; or (b) the date for the installation of a facility CAISO has previously identified as needed in its transmission planning process is advanced by the interconnection of the New FacilityProject, in which case the New Facility OperatorEligible Customer shall be responsible only for the incremental costs associated with the earlier installation of the facility.  Each New Facility Operator may, at its own discretion, sponsor, pursuant to Section 3.2applicable sections of the ISO Tariff and Section 9 of this TO Tariff, any Delivery Upgrades. Any additional costs associated with accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the ISO Tariff for transmission expansions or upgrades, if applicable, or for an Eligible Customer (including ECLL) other than New Facility Operator, the cost responsibility methodology set forth in this TO Tariff.

8.1.3. Security Requirement for ECLL.  The ECLL shall maintain security for a period of time beginning with the ECLL’s

PDF page 69

authorization for SDG&E to begin construction of the Reliability Upgrades.  The requirement for the ECLL to maintain security shall end on the earlier of (i) the date when the TO has drawn all available security, or (ii) ten years after the COD of the required Reliability Upgrade having the latest COD.

The TO may draw annually on the then-available security.  In the event the ECLL becomes aware that the Large Load will fail to reach COD, or will cease operation after COD, the ECLL shall promptly notify TO.  The TO may draw the full amount of the then-available security at any time the TO has reasonably determined that the Large Load will not reach COD, or following COD will cease operations.  The amount of such annual draws, if any, shall be determined by subtracting the ECLL’s actual Deemed Transmission Revenues for the year from that year’s minimum requirement, where such subtraction returns a positive result.  The amount of such draws shall be recorded in SDG&E’s Transmission Revenue Balancing Account Adjustment (“TRBAA”) as a credit which will reduce TAC rates.

The minimum annual requirements shall be set in advance and documented in the Interconnection Agreement.  The minimum annual requirements shall be set such that the estimated present value of those annual requirements equals the estimated present value of the forecast lifecycle revenue requirements associated

PDF page 70

with required Reliability Upgrades, including both capital and O&M-related costs.  Actual Deemed Transmission Revenues shall be calculated for each year as the product of the applicable high voltage/low voltage TAC rate and the ECLL’s metered energy withdrawals from the transmission grid.  The term “Deemed Transmission Revenues” shall mean the product of such calculation.  Metering arrangements necessary to determine actual deemed transmission revenues, shall be as mutually agreed by the ECLL and the TO.

The amount of security remaining at the end of each year will be the larger of zero, or the amount of security remaining at the end of the preceding year, less the sum of (a) actual Deemed Transmission Revenues during the current year, and (b) any security draws during the current year.

The required security will decline over time as the ECLL generates actual deemed transmission revenues and/or the TO draws upon such security.

8.1.4. Security Requirement for TO Sponsored Projects.  It is neither necessary nor practical for SDG&E to execute an agreement with itself or to collect/post security from/to itself.  However, to the extent permitted or required by California state law, if SDG&E is the entity responsible for providing retail electric service to a Large

PDF page 71

Load, SDG&E shall impose security requirements on such Large Load comparable to those that this TO Tariff requires of an ECLL. If required, SDG&E shall file with FERC for informational purposes, any such retail agreement under which such security is imposed.

8.1.5. Interconnection Agreement. Pursuant to, and in accordance with the procedures set forth in Section 10.4, 10.7.1, or 10.9.1 of this TO Tariff, a party requesting Interconnection shall request in writing that the Participating TO tender an Interconnection Agreement to such party. The Participating TO shall tender to the party requesting Interconnection an Interconnection Agreement that, if necessary, will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement will include, without limitation, cost, responsibilities and payment provisions for any engineering, equipment, construction, operation and maintenance costs for any Direct Assignment Facilities and any Reliability Upgrades, and Delivery Upgrades, if applicable, and for any other mitigation measures.  For an Interconnection request to remain a Completed Interconnection Application, the party requesting the Interconnection shall, within thirty (30) Calendar days of receipt of the tendered Interconnection Agreement, either (i) execute the Interconnection Agreement and return it to the Participating TO

PDF page 72

within thirty (30) Calendar days of receipt. Alternatively, if, or (ii) request that the Participating TO file the Interconnection Agreement unexecuted at FERC. If an Eligible Customer requesting the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Interconnection Agreement or commence construction of the Interconnection facilities or incur other costs under the Interconnection Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority.  The Interconnection Agreement will, the form for which is Appendix XIV to this TO Tariff, as tendered shall set forth a payment schedule that enables the Participating TO to recover its costs. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement,

PDF page 73

its Completed Interconnection Application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the applicant not covered by any System Impact Study Agreement or Facilities Study Agreement.

8.1.35.1 Queuing Provisions. To maintain its queue position, the New Facility OperatorEligible Customer must timely comply with the interconnection requirements of Section 5.7applicable sections of the ISO Tariff and/or Sections 8.1 and 10 of this TO Tariff. If the New Facility

OperatorEligible Customer fails to timely comply with such interconnection requirements, such New Facility

OperatorEligible Customer shall pay the reasonable costs of revising the System Impact Studies for other New Facility Operator’sEligible Customers that have established a new queue position due to the New Facility OperatorEligible Customer either withdrawing its Interconnection

Application or because its queue position has been modified pursuant to the queuing provisions in Section

5.7.4.4applicable sections of the ISO Tariff.
8.1.46 Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Reliability Upgrades that it is

PDF page 74

obligated to construct pursuant to this TO Tariff and, as applicable, Section 5.7 sections of the ISO Tariff.

8.1.57 Energization. The Participating TO shall not be obligated to energize, nor shall the New Facility Operator or wholesale loadEligible Customer be entitled to have its interconnection to the ISO Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3, and becomes effective and such New Facility Operator or wholesale loadEligible Customer has demonstrated to the ISO’s and the Participating TO’s reasonable satisfaction that it has complied with all of the requirements of Section 5.7applicable sections of the ISO Tariff and the requirements of this TO Tariff. 8.1.68 Coordination with ISO on Interconnection Requests. The Participating TO shall coordinate with the ISO, pursuant to the provisions of the TCA and the ISO Tariff, as applicable, in developing Interconnection standards and guidelines for processing Interconnection requests under this TO Tariff.

8.2
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to: (1) perform System Impact or Facility Studies where the Project Sponsor or the ISO agrees to pay the study cost and specifies the project objectives to be achieved, and (2) build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in

PDF page 75

accordance with and subject to the limitations of Section 3.2,applicable sections of the ISO Tariff, and this TO Tariff.

8.2.1 Obligation to Construct. A Participating TO shall not be obligated to construct or expand Interconnection facilities, transmission facilities or system upgrades unless and until the conditions stated in Section 9.2.1 hereof have been satisfied.

8.2.2 Local Furnishing Participating TO Obligation to Construct. A Local Furnishing Participating TO shall not be obligated to construct or expand Interconnection facilities, transmission facilities or system upgrades unless and until the conditions stated in Section 9.3.3 hereof have been satisfied.

8.3
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the ISO, (including the ISO’s ADR Procedures), the CPUC, WSCCWECC, or RTG coordination planning processes as to the need for or construction of a facility, the need for full cost recovery, and the allocation of costs.

PDF page 76

SECTION 9 EXPANSION
PROCESS - REDLINES

PDF page 77

9. Expansion Process.
9.1.
Determination of Facilities. A Participating TO shall perform a Facilities Study in accordance with this Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 3.2applicable sections of the ISO Tariff and this TO Tariff; (2) a Market Participant agrees to pay the costs of the Facilities Study and specifies the project objectives to be achieved in terms of increased capacity or reduced congestion; or (3) the Participating TO is required to perform a Facilities Study pursuant to the ISO Tariff.

9.1.1. Payment of Facilities Study’s Cost.
9.1.1.1.
Market Participant to Pay for Facilities Study. Where a
Market Participant requests a Facilities Study and the need for the transmission addition or upgrade has not yet been

established in accordance with the procedures established
herein and the ISO Tariff, the Market Participant shall pay the cost of the Facilities Study.

9.1.1.2.
Project Sponsor or Project Proponent to Pay for Facilities
Study. Where the facilities to be added or upgraded have
been determined to be needed in accordance with the
procedures established herein and the ISO Tariff, the
Project Sponsor, Project Proponent, or the ISO requesting
the study shall pay the reasonable cost of the Facilities
Study. When the Participating TO is the Project Sponsor in

PDF page 78

accordance with the ISO Tariff, the costs of the Facilities Study shall be recovered through the Access Charges and transmission rates.

9.1.1.3.
Principal Beneficiaries to Pay for Facilities Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the ISO or ISO ADR Procedures in

accordance with the ISO Tariff, the Project Sponsor and the identified principal beneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as may be agreed, or, failing agreement, as determined in accordance with the ISO ADR Procedures.

9.1.2. Payment Procedure. Where a Facilities Study is being conducted pursuant to this TO Tariff, the Participating TO shall, as soon as practicable, tender to the Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal beneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required

PDF page 79

Facilities Study. If the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, agreeagrees to the terms of the Facilities Study Agreement, they shall execute the Facilities Study Agreement and return it to the Participating TO within ten Business Days. If such Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiary elects not to execute a Facilities Study Agreement, the Participating TO shall have no obligation to complete a Facilities Study.

.9.1.3 Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement, a copy of which has been provided to the ISO by the party requesting the Facilities Study, the Participating TO will use due diligence to complete the required Facilities Study in accordance with the terms of the Facilities Study Agreement. 9.2.

Obligation to Build.
9.2.1. Due Diligence to Construct. Subject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the ISO Tariff and this TO Tariff. The Participating TO’s obligation to build will be subject to: 1) its ability, after making a good faith effort, to obtain the necessary approvals and property rights under applicable federal, state, and local laws; 2) the presence of a cost recovery

PDF page 80

mechanism with cost responsibility assigned in accordance with, as applicable, the ISO Tariff or this TO Tariff; and 3) a signed Participation Agreement, if applicable. The Participating TO will not construct or expand its existing or planned transmission system, if doing so would impair system reliability as determined through systems analysis based on the Applicable Reliability Criteria.

9.2.2. Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify: (1) the Project Sponsor with regard to facilities determined to be needed; (2) the Parties to the Participation Agreement with regard to facilities determined to be needed pursuant to the ISO Tariff where principal beneficiaries were identified; and (3) the ISO. In such circumstances, the Participating TO shall, within thirty days of notifying such Project Sponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Participation Agreement, and the ISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be, studies and work papers related to the cause and extent of

PDF page 81

the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives.

9.2.2.1
Alternatives to the Original Facility Additions. If the review process of Section 9.2.2 determines that one or more alternatives exist to the originally planned construction project, the Participating TO shall present such alternatives for consideration to the Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be. If upon review of any alternatives, such Project Sponsor, the ISO, or Parties to the Participation Agreement wish to evaluate or to proceed with one of the alternative additions or upgrades, such Project Sponsor, the ISO, or Parties to the Participation Agreement may request that the Participating TO prepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO Tariff. In the event the Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Participation Agreement or the ISO disagree, the dispute shall be resolved pursuant to the ISO ADR Procedure. 9.2.2.2

Refund Obligation for Unfinished Facility Additions. If the

PDF page 82

Participating TO and the Project Sponsor, the ISO, or Parties to the Participation Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Regulation 35.19(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.

9.3.
Provisions Relating to Transmission Construction on the Systems of Other TOs.

9.3.1 Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any engineering, permitting, and construction of transmission or distribution facilities on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO will undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice. 9.3.2. Coordination of Third-Party System Additions. Where transmission

PDF page 83

additions or upgrades being built pursuant to the ISO Tariff require additions or upgrades on other systems, to the extent consistent with Section 9.3.3 of this TO Tariff, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the ISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or resume construction of the new facilities. Within forty Business Days of receiving written notification by the Participating TO of its intent to defer construction pursuant to this section, such Project Sponsor, Parties to the Participation Agreement, or the ISO may challenge the decision in accordance with the ISO ADR Procedure.

9.3.3. Expansion
by
“Local
Furnishing
Participating
TO’s”.
Notwithstanding any other provision of this TO Tariff, prior to requesting that a Local Furnishing Participating TO construct or expand facilities, or utilize existing facilities, the ISO or, Project Sponsor, and/or Eligible Customer if necessary as determined by the Local Furnishing Participating TO, shall tender (or cause to be

PDF page 84

tendered) an application under Section 211 of the FPA requesting FERC to issue an order directing the Local Furnishing Participating TO to construct or expand facilities as necessary to provide Interconnection or transmission service as determined pursuant to the ISO Tariff. Such Local Furnishing Participating TO shall thereafter, within ten Business Days of receiving a copy of the Section 211 application, waive its right to a request for service under Section 213(a) of the FPA and to the issuance of a proposed order under Section 212(c) of the FPA. Upon receipt of a final order from FERC under Section 211 of the FPA that is no longer subject to rehearing or appeal, such Local Furnishing Participating TO shall construct or expand facilities, or permit the utilization of existing facilities, to comply with that FERC order and shall transfer to the ISO Operational Control over the Local Furnishing Participating TO’s expanded transmission facilities in accordance with the ISO Tariff.

PDF page 85

SECTION 10 INTERCONNECTION
PROCESS - REDLINES

PDF page 86

10. Interconnection Process.
10.1. Applicability. All requests for Interconnection directly to the ISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the applicable provisions of this Section 10.

10.2. Applications.10.2.
Applications. SDG&E accepts applications on a
rolling basis and the application process is administered as described in this Section 10. Except as provided in Section 10.2.1, a party requesting Interconnection shall submit written Interconnection Applications which providesprovide the information required in Section 10.3Attachment B to the Participating TO TO’s Study Agreement and described in Section 10.5 of this TO Tariff. The Interconnection Application shall sendinclude a copy of the$50,000 non-refundable application to the ISOfee. The Participating TO shall time-stamp the application to establish study priority. 10.2.110.3.

Scoping Meeting. Following receipt by Transmission Owner of the application fee, the Transmission Owner or the Interconnection Customer may request a Scoping Meeting prior to commencement of the System Impact Study, provided that the Interconnection Application contains sufficient information to conduct the Scoping Meeting.

10.4. New Facility Operator. If the party requesting Interconnection to the ISO Controlled Grid is a New Facility Operator, such party shall submit a written Interconnection Application to the ISO pursuant to Section 5.7.3applicable sections of the ISO Tariff that shall include, but shall not

PDF page 87

be limited to, as applicable, the information required in Section 10.35 of this TO Tariff.

10.35. Completed Interconnection Application. A Completed Interconnection Application shall provide, where applicable, all of the information listed in 18 CFR § 2.20, includingand such additional information as the TO reasonably requires to process Interconnection Customer’s application. The information provided shall include, but is not limited to, the following:

(i) The identity, address, telephone number, and facsimilee-mail number of the party requesting Interconnection;

(ii) The Interconnection point(s) to the ISO Controlled Grid contemplatedproposed by the applicant;

(iii) The resultant (or new) maximum amount of Interconnection capacity;

(iv) The proposed date for energizing the Interconnection and the term of the Interconnection service;

(v) If the applicant is a New Facility Operator, completed generator data sheets pursuant to the requirements of the Participating TO.; and,

(vi) Such other information as the Participating TO reasonably requires to process the application. In addition to the information specified above, the following information may also be provided in order to properly evaluate system

PDF page 88

conditions.
(vii) If the applicant is a wholesale load, (including ECLL), the electrical of the source of the power (if known) to be transmitted pursuant to the applicant’s request for Interconnection. If the source of the power is not known, a system sale will be assumed; and

(viii) The electrical location of the ultimate load (if known). If the location of the load is not known, a system sale will be assumed.; and

(ix) If the applicant is an ECLL, the applicant shall submit the data required by the Participating TO and CAISO, as specified in the System Impact Study Data Template Submittal Form, including applicable facility characteristics, load composition and expected hourly operating profile, MW capacity, minimum and maximum operating levels, electrical and dynamic model data, voltage and frequency ride-through characteristics, protection and control settings, load reconnection behavior, expected CAISO market participation model (if any), curtailment and ramping capabilities, and behind-the-meter generation capacity and characteristics (if any); and

(x) Documentation demonstrating that the Large Load to be served by the ECLL has Site Control; and

(xi) If the Large Load will be co-located with generation,

PDF page 89

information concerning the relevant generation must be provided by the ECLL.  Such information shall include the executed generator interconnection agreement or, if none exists, an identifying queue number that will allow the TO to verify that generator has submitted an interconnection application; and

(xii) If the applicant is an ECLL, disclosure of whether any substantially similar interconnection requests on behalf of the same Large Load have been submitted outside of the

Participating TO service area; and
(xiii) If the applicant is an ECLL, whether it is requesting FILI service.

In addition, if the applicant proposes to perform or cause a third party to perform any required System Impact Study or any required Facilities Study, it shall so indicate in its Interconnection Application. The results of any study or studies performed by a New Facility Operatoran Eligible Customer must be approved and/or concurred by botheach of the ISO and the Participating TO, as applicable. Within 10 Business Days after receipt of an Interconnection Application, the Participating TO, and the ISO, if applicable, shall determine whether the application is complete (“Completed Interconnection Application”). Wherever possible, the Participating TO will attempt to remedy deficiencies in the

PDF page 90

Interconnection Application through informal communications with the applicant. If such efforts are unsuccessful, the Participating TO shall return the Interconnection Application to the applicant or to the ISO if the applicant is a New Facility Operator. The Participating TO will treat the information provided in the Interconnection Application, including the applicant’s identity, as confidential at the request of the applicant except to the extent that disclosure of this information is required by this TO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations. 10.3.1  Amendment to Completed Interconnection Application. An applicant shall only be limited to amending its Completed Interconnection Application once. 10.6

Site Control Requirements: Demonstration of no less than
ninety percent (90%) Site Control; or (1) a signed affidavit from an officer of the company indicating that Site Control is unobtainable due to regulatory limitations as defined by Participating TO on its public website;

(2) documentation sufficiently describing and explaining the source and effects of such regulatory limitations, including a description of any conditions that must be met to satisfy the regulatory limitations and the anticipated time by which the Interconnection Customer expects to satisfy the regulatory requirements; and (3) a deposit in lieu of Site Control of

PDF page 91

$10,000 per MW, subject to a minimum of $500,000 and a maximum of $2,000,000. Interconnection Requests from multiple Interconnection Customers for multiple Projects that share a site must include a contract or other agreement that allows for shared land use. If the Project no longer satisfies the applicable Site Control requirements, the Participating TO may provide the Interconnection Customer an opportunity to cure the deficiency within ten (10) Business Days to demonstrate satisfaction with the applicable requirement subject to Participating TO’s approval. Absent such approval, the Participating TO shall deem the Interconnection Request withdrawn.

An Interconnection Customer that submits a deposit in lieu of Site Control due to demonstrated regulatory limitations must demonstrate that it is taking identifiable steps to secure the necessary regulatory approvals from the applicable federal, state, and/or tribal entities no later than the completion of the System Impact Study. An Interconnection Customer facing qualifying regulatory limitations must demonstrate one hundred percent (100%) Site Control within one hundred eighty (180) Calendar Days of the effective date of the Interconnection Agreement. Participating TO shall deposit all Site Control deposits in an interest-bearing account at a bank or financial institution designated by the Participating TO. The Site Control Deposit shall be refundable to Interconnection Customer at any time upon demonstration of one hundred percent (100%) Site Control or the Interconnection Request is withdrawn by Interconnection Customer or

PDF page 92

deemed withdrawn by the Participating TO by written notice. The refund of the Site Control deposit shall include interest from the date of receipt by the Participating TO to the date of payment to Interconnection Customer. The applicable interest shall be computed in accordance with the FERC’s regulations at 18 CFR § 35.19a(a)(2)(iii). The Site Control deposit shall continue to be required after Interconnection Customer either executes an Interconnection Agreement or requests the filing of an unexecuted Interconnection Agreement under this TO tariff if Site Control has not been demonstrated.

10.7  Amendment to Completed Interconnection Application. An applicant shall be limited to amending its Completed Interconnection Application once. Modifications permitted under this Section shall include specifically:

i. a decrease in interconnection service capacity size
(MW/MVA);
ii. modifying the technical parameters associated with the Project technology or the Project step-up transformer

impedance characteristics Changes;
iii. modifying the interconnection configuration;
iv. modifying the in-service date or Commercial Operation
Date, subject to the approval of the Participating TO, which approval shall not be unreasonably withheld.

Such amendment shall occur on or before ten (10) Business Days

PDF page 93

following the date the Participating TO tenders anystarts the Facilities Study Agreement. Specifically, as an alternative to executing and returning Facilities Study Agreement, a New Facility OperatorEligible Customer may submit an amendment to its Completed Interconnection Application to reflect a revised configuration for its New Facility.Project. The amended Completed Interconnection Application shall be treated in accordance with Section 5.7.4.2.1applicable sections of the ISO Tariff and Section 10.7 of this TO Tariff, the New Facility Operator’sas applicable, and the Eligible Customer’s Completed Interconnection Application shall not be deemed withdrawn; and the New Facility Operator.  Eligible Customer shall maintain its existing queue position, only if (a) the amended Completed Interconnection Application is received by the Participating TO within ten (10) Business Days of the Participating TO’s tenderstart of a Facilities Study Agreement; and (b) the New Facility OperatorEligible Customer has not submitted a previous amendment to the Completed Interconnection Application.  In the event a New Facility Operatoran Eligible Customer amends its Completed Interconnection Application, it will be responsible for any additional study costs that result from that amendment, including costs associated with revisions to studies for other applicants holding later queue positions.

10.48 Review of Completed Interconnection AgreementApplication. After receiving a Completed Interconnection Application, the Participating TO, and the ISO, if applicable, will determine on a non-discriminatory basis

PDF page 94

whether a System Impact Study is required. Whenever the Participating TO, and the ISO, if applicable, determines that a System Impact Study is not required and that neither Reliability Upgrades nor changes in existing operating procedures are required, the Participating TO shall notify the applicant within fifteen (15) Business Days of the Completed Application Date. If the Interconnection can be accommodated without any Direct Assignment Facilities, within thirty (30) Business Days of such notice from the Participating TO, the applicant shall request the Participating TO to tender to the applicant an Interconnection Agreement. Within twenty

(20) Business Days of such request, the Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. of this TO Tariff.  If the Participating TO determines, upon the review of the Completed Interconnection Application, that Direct Assignment Facilities are required, the Participating TO shall tender to the applicant a Facilities Study Agreement within twenty (20) Business Days of the Completed Application Date and continue the Interconnection process pursuant to Section 10.810 of this TO Tariff.

10.5
Notice of Need for System Impact Study. If the Participating TO, and the ISO, if applicable, determines10.9

Study Deposits. The Participating
TO shall perform interconnection studies in accordance with the terms of a Study Agreement executed pursuant to Section 10.10 below; provided, however, that the performance of such studies is conditioned upon the Interconnection Customer’s timely provision of study deposits required in

PDF page 95

the Study Agreement.  The Participating TO shall return to the Eligible Customer any deposited funds remaining after completion of the studies. Upon the Participating TO’s determination that the deposited funds will not be sufficient to complete one or more of the studies, the Participating TO may request that additional funds be deposited and the Interconnection Customer shall promptly provide such additional deposit.

10.10 Notice of Need for System Impact Study. If the Participating TO and/or the ISO, as applicable, determine(s) that a System Impact Study is necessary to accommodate the requested Interconnection, the Participating TO shall so inform the applicant as soon as practicable. In such cases, the Participating TO shall within twenty (20) Business Days of receipt of a Completed Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of performing or reviewing the required System Impact Study. A description of the Participating TO’s transmission assessment practices for completing a System Impact Study is provided in the Participating TO’s FERC Form 715. Alternatively, if the New Facility Operator will perform the System Impact Study, the Participating TO shall within twenty (20) Business Days of receipt of a Completed Interconnection Application, tender a System

PDF page 96

Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of reviewing the required System Impact Study. For an

Interconnectioninterconnection request to remain a Completed Interconnection Application, the applicant shall execute the System Impact Study Agreement and return it to the Participating TO within ten

(10) Business Days together with payment for the reasonable estimated cost of the System Impact Study or reviewing the New Facility Operator’s System Impact Study. Alternatively, if the applicant requests the Participating TO to proceed with the System Impact Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the System Impact Study provided that such request is accompanied by payment for the reasonable estimated cost of the System Impact Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. If the applicant elects not to execute a System Impact Study Agreement, and does not request that the Participating TO proceed with the System Impact Study or review thereof,

PDF page 97

its application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application.

10.611 System Impact Study Cost Reimbursement.
10.611.1
Cost Reimbursement. The System Impact Study Agreement shall clearly specify the charge, based on the Participating TO’s estimate of the cost and time for completion of the System Impact Study. The charge shall not exceed the reasonable actual cost of the study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any modifications to existing planning studies that are reasonably necessary to evaluate the impact of the applicant’s request. 10.69.2

Multiple Parties. If multiple parties request Interconnection at the same location, the Participating TO may conduct a single System Impact Study. The costs of that study shall be pro-rated among the parties requesting Interconnection.

10.712 System Impact Study Procedures. Upon receipt of an executed System Impact Study Agreement or initiation of the ISO ADR Procedures and receipt of payment for estimated study costs, the Participating TO will use due diligence to either (a) complete the required System Impact Study

PDF page 98

within a sixty (60) day period or (b) complete its review of a New Facility Operator’san Eligible Customer’s System Impact Study within thirty (30) Calendar Days of its receipt of the completed study. The System Impact Study will identity whether any Direct Assignment Facilities or Reliability Upgrades as well as, if applicable, any Delivery Upgrades are necessary to deliver a New Facility’s full output over the ISO Controlled Grid. The System Impact Study will also identify any adverse impact on Encumbrances existing as of the applicant’s New Facility

Operator’sEligible Customer’s Completed Application Date. In the event that the Participating TO is unable to complete the required System Impact Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed System Impact Study and related work papers shall be made available to the applicant and the ISO. The Participating TO will use the same due diligence in completing the System Impact Study for others as it uses when completing studies for its affiliateditself as UDC. The Participating TO shall notify the applicant and the ISO immediately upon completion of the System Impact Study.  The Participating TO may, using Good Utility Practice and reasonable engineering judgment, defer commencement of a System Impact Study if the study cannot be meaningfully completed until results are available for other similarly situated or electrically related interconnection requests. The Participating

PDF page 99

TO shall notify the applicant of any such deferral.
10.712.1
Procedures Upon Completion of System Impact Study.
Within fifteen (15) Business Days of completion of the System Impact Study or review and approval of a New Facility Operator’s System Impact Study, the Participating TO shall notify the applicant whether the transmission system will be adequate to accommodate all of a request for Interconnection. If no costs are likely to be incurred for any Direct Assignment Facilities, any Reliability Upgrades, or implementing any operating procedures, then within thirty (30) Business Days of receipt of the completed System Impact Study performed by the Participating TO or receipt of written approval of the New Facility Operator’s System Impact Study from the Participating TO and the ISO, the applicant shall request the Participating TO to tender an Interconnection Agreement. Within twenty (20) Business Days of such request, the Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.3. If costs are likely to be incurred to accommodate a request for Interconnection, then the applicant shall request the Participating TO shall tender to the applicant perform a Facilities Study Agreement pursuant to Section 10.8.

10.810.12.2
Restudy. The Participating TO may perform a restudy if the withdrawal or modification of a higher-queued Interconnection

PDF page 100

Request materially affects the results of a completed System Impact Study.  The affected Interconnection Customer shall be responsible for the reasonable actual cost of the restudy.

10.13 Notice of Need for Facilities Study. If a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid are needed to satisfy an applicant’s request for Interconnection, the Participating TOInterconnection Customer shall, within fifteen (15) Business Days of the completion date of the System Impact Study, or the completion of review and approval of the New Facility Operator’s System Impact Study by the Participating TO and the ISO, tender to the applicant a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete the required study; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees torequest that the Participating TO to initiate the Facilities Study pursuant to the Study Agreement. In evaluating mitigation measures, the Participating TO shall consider, as appropriate, alternative transmission technologies consistent with applicable reliability requirements and Good Utility Practice.  The applicant shall reimburse the Participating TO for the reasonable actual costs of performing the required Facilities Study. in accordance with the Study Agreement. Alternatively, if thea New Facility Operator will perform the Facilities Study, the Participating TONew Facility Operator shall within fifteen (15)

PDF page 101

Business Days of the completion date of the System Impact Study or the completion of the Participating TO’s and ISO’s review and/or approval of the New Facility Operator’s System Impact Study, tenderintiate a Facilities Study Agreement that defines the scope, content, assumptions and term of reference for such study to be reviewed by the Participating TO; and the ISO. The Study Agreement shall reflect the estimated time required to complete the requiredsuch review; and such, other provisions as the parties may reasonably require, and pursuant to which the applicant agreesthe applicant’s obligation to reimburse the Participating TO for the reasonable actual cost of reviewing the required Facilities Study. For an Interconnection request to remain a Completed Interconnection Application, following the applicant’s election to proceed with the Facilities Study, the applicant shall maintain and execute the Facilities Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated cost of the Facilities Study or reviewing the New Facility Operator’s Facilities Study., as applicable. Alternatively, if the applicant requests the Participating TO to proceed with the Facilities Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study provided that such request is accompanied by payment for the

PDF page 102

reasonable estimated cost of the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO ADR Procedures. If the applicant elects not to execute a Facilities Study Agreement and does not request that the Participating TO proceed with the Facilities Study, its application shall be deemed withdrawn and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by the System Impact Study Agreement.

10.914 Facilities Study Procedure. Upon receipt of an executedthe applicant’s request to proceed with the Facilities Study and payment of the required deposit pursuant to the Study Agreement, or initiation of the ISO ADR Procedures and receipt of payment for the estimated study costs, the Participating TO will use due diligence to either (a) complete the required Facilities Study within a sixty (60) Calendar day period or (b) complete its review of a New Facility Operator’s Facilities Study within thirty (30) Calendar Days of its receipt of the completed study. In the event that the Participating TO is unable to complete the required Facilities Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed Facilities Study shall be made available to the applicant. 10.9.1 Execution of Interconnection Agreement.10.15

Electromagnetic
Transient Study. If the Participating TO determines that an

PDF page 103

Electromagnetic Transient (“EMT”) Study is required, it shall notify the applicant of the estimated cost and time required to complete the study. Within ten (10) Business Days of such notice, the applicant shall request that the Participating TO proceed with the EMT Study and provide payment of the reasonable estimated study cost pursuant to the Study Agreement. The EMT Study may be performed at any time after completion of the Facilities Study, as determined by the Participating TO. The Participating TO will use due diligence to complete the EMT Study within the estimated timeframe and provide the completed study to the applicant.

10.16 No Preferential Treatment.  The Participating TO will use the same due diligence in completing studies under this tariff for others as it uses for itself or its affiliates.

10.17 Tender of Interconnection Agreement. Within thirty (30) Business Days of receipt of the completed Facilities Study performed by the Participating TO or receipt of written approval of the New Facility Operator’s or Eligible Customer’s Facilities Study from the Participating TO, the applicant shall request the Participating TO to tender an Interconnection Agreement. Within twenty (20) Business Days of such request, the Participating TO shall tender to applicant an Interconnection Agreement as provided in Section 8.1.3.

10.1018
Partial Interim Service for Eligible Customers other than ECLL. If the Participating TO determines that there will not be adequate

PDF page 104

transmission capability to satisfy fully the full amountservice requested in a Completed Interconnection Application for Eligible Customers other than ECLL, the Participating TO nonetheless shall be obligated to offer and provide the portion of the requested Interconnection that can be accommodated without any additional Direct Assignment Facilities or Reliability Upgrades. However, the Participating TO shall not be obligated to provide the incremental amount of requested Interconnection that requires such additional facilities or upgrades to the transmission system until such facilities or upgrades have been placed in service. 10.1119

Expedited Interconnection Procedures. In lieu of the procedures set forth above, the applicant shall have the option to expedite the processing of its Completed Interconnection Application. In order to exercise this option, the applicant shall submit in writing a Request for Expedited Interconnection Procedures to the Participating TO, and to the ISO, if the applicant is a New Facility Operator, within ten (10) Business Days after receiving a copy of the System Impact Study for the proposed Interconnection. Within ten (10) Business Days after receiving a Request for Expedited Procedures, the Participating TO shall tender an Expedited Interconnection Agreement that requires the applicant to compensate the Participating TO for all costs reasonably incurred pursuant to the terms of this TO Tariff for processing the Completed Interconnection Application and providing the requested Interconnection. While the Participating TO agrees to provide the applicant with its best estimate of the costs of any

PDF page 105

needed Direct Assignment Facilities and, if applicable, Reliability Upgrades and other charges that may be incurred, unless otherwise agreed by the parties, such estimate shall not be binding and the applicant must agree in writing to compensate the Participating TO for all actual interconnection costs reasonably incurred pursuant to the provisions of this TO Tariff. The applicant shall execute and return such Expedited Interconnection Agreement within ten (10) Business Days of its receipt or the applicant’s request for Interconnection will cease to be a Completed Interconnection Application and will be deemed terminated and withdrawn. In that event, the applicant shall reimburse the Participating TO for all costs reasonably incurred in processing the application not covered by the terms of the System Impact Study Agreement.Study Agreement.

10.20 Flexible Interim Load Interconnection (“FILI”) Service For ECLL.  If the ECLL is requesting FILI Service, the TO shall perform, as part of the System Impact Study, an analysis and determine the portion of the ECLL’s maximum operating level that may be energized prior to such time that all network upgrades necessary for full energization of the studied loads are in service.  The portion that may be energized will be documented in the executed and effective Interconnection Agreement.

Pursuant to Section 25.7.1 of the ISO Tariff, the ECLL may be required to execute an agreement with the ISO and TO if real-time operating procedures are necessary to effectuate the limit determined by the TO in

PDF page 106

this Section 10.20.  Such agreement will describe the circumstances in which the Large Load may be temporarily curtailed and the mechanism used to perform the curtailment.

10.21 Conditions Related to FILI Service For ECLL.
10.21.1
FILI Service Reliability Requirements. The Participating TO shall have sole discretion to specify the protection, control systems and any other equipment necessary to ensure the Large Load does not withdraw more power from the ISO Controlled Grid than allowed by the limit established pursuant to Section 10.20. The required protection, control systems and other equipment; and the party responsible for installing, owning and maintaining those systems and equipment; will be identified in the Interconnection Agreement.  FILI Service shall not commence until the installation and commissioning of all systems and equipment identified in the Interconnection Agreement has been completed. 10.21.2

Curtailment of FILI Service.  The TO and ISO may curtail FILI Service as necessary to maintain the safe and reliable operation of the ISO Controlled Grid, including during normal operating conditions.

10.21.3
Exceedance of Authorized FILI Service.  The TO shall have the right to disconnect service to the ECLL in the event that withdrawals from the ISO Controlled Grid exceed the limit established pursuant to Section 10.20. The TO shall follow Good

PDF page 107

Utility Practice in carrying out any such disconnection and subsequent reconnection.

10.22 Co-Located Generation Units and Large Loads. ECLL for a Co-Located Large Load connecting to facilities of an exporting Generating Facilities will be subject to this Section 10.22.  The CAISO and the Participating TO will publish study results reflecting the combined presence of the Generating Units and co-located Large Loads.  The CAISO and SDG&E will memorialize the result of such studies in a Large Generation Interconnection Agreement (LGIA) with the New Facility Operator.  For clarity, the New Facility Operator may be the same legal entity as either the ECLL or the Large Load, but not both.  The Participating TO’s System Impact Study shall consider co-located generation to the extent it does not export power to the ISO Controlled Grid.  Any requested export service shall be addressed under the applicable generator interconnection procedures of the ISO Tariff.

In the event of a conflict between the CAISO Tariff and this TO Tariff pertaining to the interconnection of the Generating Unit, the CAISO Tariff shall control.  In the event of a conflict between the CAISO Tariff and this TO Tariff pertaining to the interconnection of an ECLL, this TO Tariff shall control.  Nothing in the CAISO Tariff shall be interpreted to contradict or exempt an ECLL from its cost responsibility obligations pursuant to this TO Tariff, and nothing in this TO Tariff shall be interpreted to contradict or exempt a New Facility Operator from its cost

PDF page 108

responsibility obligations pursuant to the CAISO Tariff.
10.23 Effect of Default Under Interconnection Agreement.  Interconnection Customer shall forfeit its queue position and its Completed Interconnection Application shall be deemed withdrawn with respect to any Project as to which Interconnection Customer is in default under the applicable Interconnection Agreement, including without limitation failure to provide required security.