ER27-521-000 · 2026-11-16 · San Diego Gas & Electric

ER26-71 Order to Show Cause Tariff Revisions

San Diego Gas & Electric files tariff revisions under section 205 on November 16, 2026, in ER27-521-000, answering the CAISO show cause order. It sets terms for utilities that buy transmission service for large loads, with security equal to the present value of the upgrades' lifecycle revenue requirement and a pro forma interconnection agreement.

Asks FERC to: Accept the revisions effective February 16, 2027, as just and reasonable, and terminate the show cause proceeding as to SDG&E.

Filed under section 205 to answer the E-10 show cause order for SDG&E's own transmission owner tariff. SDG&E covers the application, cost shifting and interim service items and leaves permanent flexible service to CAISO.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62)

Key points

  1. SDG&E says its approach is substantively aligned with SCE's and DesertLink's, which it also calls LS Power.
    SDG&E believes its approach is substantively aligned with that of Southern California Edison Company (“SCE”) and DesertLink, LLC (“LS Power”) PDF p. 2
  2. Its definition differs from CAISO's wording. It covers a new customer, not an end user.
    a new customer, located at a single site behind one or more points of interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater PDF p. 5
  3. SDG&E keeps its serial study process, ranked by the date it receives each application.
    SDG&E proposes to maintain its current serial study process that accepts and studies each application at any time on a rolling basis, with priority based on the date SDG&E, as the PTO, receives the application PDF p. 6
  4. It proposes full protection for network upgrade costs.
    SDG&E’s proposed 100 percent cost-shift protection for network upgrades PDF p. 8
  5. Security equals the present value of the upgrades' lifecycle revenue requirement.
    security equal to the present value of the forecast lifecycle revenue requirement associated with the network upgrades PDF p. 13
  6. Security is held until ten years after the upgrades enter service.
    maintain security for a period of time beginning with the ECLL’s authorization for SDG&E to begin construction of the network upgrades and ending ten years following the COD of the required network upgrades PDF p. 13
  7. If the load fails or stops, SDG&E draws all remaining security.
    SDG&E will draw all remaining security (effectively, an “exit fee”) PDF p. 14
  8. Limits on the interim service are set in the study, not from real-time conditions.
    SDG&E will establish limits on ECLL grid withdrawals based on studies conducted during the interconnection process, not on near-real-time or real-time operating conditions PDF p. 18

Text extracted from the eLibrary original (SHA-256 ba53fcd334660c18…). Download the original from the official source.

Contents · 24 sections
  1. I. BACKGROUND p. 3
  2. A. SDG&E and Its TO Tariff p. 3
  3. B. The Show Cause Order p. 3
  4. II. PROPOSED INTERCONNECTION PROCESS REFORMS p. 4
  5. A. Definition of Large Load p. 5
  6. B. Application Process p. 5
  7. C. Transmission Service Study p. 9
  8. D. Stakeholder Access to Information on Large Load Interconnections p. 11
  9. E. Cost Shifting Among Transmission Customers p. 12
  10. III. FLEXIBLE LARGE LOADS AND FLEXIBLE INTERIM LOAD p. 18
  11. IV. CO-LOCATED LARGE LOADS p. 19
  12. V. GRID ENHANCING TECHNOLOGIES p. 20
  13. VI. BRIEFING QUESTIONS p. 21
  14. A. Existing Commercial Arrangements p. 21
  15. B. Planning Impacts from Flexible Services for Large Loads p. 21
  16. C. Structures to Prevent Cost Shifts p. 22
  17. VII. ISSUES TO BE ADDRESSED THROUGH THE CAISO TARIFF p. 23
  18. VIII. CONFORMING AND MINISTERIAL REVISIONS p. 23
  19. IX. ENCLOSURES p. 24
  20. X. EFFECTIVE DATE p. 24
  21. XI. REQUEST FOR WAIVER p. 25
  22. XII. COMMUNICATIONS p. 25
  23. XIII. SERVICE p. 25
  24. XIV. CONCLUSION p. 25

Topics in the text: Cost allocation · Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

Under this framework, SDG&E will perform the studies necessary to identify facilities required to accommodate those requests, apply security provisions that protect other transmission ratepayers from the possibility of undue cost shifts, and establish other requirements associated with…
Read this passage

I. BACKGROUND

printed heading

I.
Read this passage

A. SDG&E and Its TO Tariff

printed heading

The TO Tariff also governs requests for physical interconnection to the SDG&E-owned components of the CAISO Controlled Grid by entities eligible to request interconnection consistent with FPA section 210(a).
Read this passage

B. The Show Cause Order

printed heading

The Show Cause Order The Show Cause Order recognized that, in CAISO, an Eligible Customer submits an interconnection application to the PTO, which performs the studies needed to interconnect new load, and the Eligible Customer then retains a Scheduling Coordinator to obtain transmission service…
Read this passage

II. PROPOSED INTERCONNECTION PROCESS REFORMS

printed heading · Topic match: Connecting load and generation

For instance, interconnection service under the TO Tariff is not the same thing as and does not supplant transmission service governed by CAISO’s tariff; rather, the interconnection customer requesting transmission service over the CAISO Controlled Grid must take such service from CAISO through a…
Read this passage

A. Definition of Large Load

printed heading · Topic match: Cost allocation

In SDG&E’s view, such an exclusion could limit the ratepayer protections that are a key feature of SDG&E’s proposed framework.
Read this passage

B. Application Process

printed heading · Topic match: Connecting load and generation

Specifically, an ECLL must submit the data specified in the System Impact Study Data Template Submittal Form, including facility characteristics, load composition and expected hourly operating profile, MW capacity, minimum and maximum operating levels, electrical and dynamic model data, voltage and…
Read this passage

C. Transmission Service Study

printed heading

In response to the Show Cause Order’s concerns, SDG&E clarifies first that with respect to requests by an Eligible Customer to interconnect a new project, SDG&E’s TO Tariff already outlines the process for both the System Impact Study and the Facilities Study.
Read this passage

D. Stakeholder Access to Information on Large Load Interconnections

printed heading

Further, CAISO proposes to publicly post:10 • aggregate amounts of proposed large load additions behind interconnections of Eligible Customers to the ISO Controlled Grid, including the aggregate amounts in each transmission pricing zone; • planned network upgrades needed to accommodate the ECLL…
Read this passage

E. Cost Shifting Among Transmission Customers

printed heading · Topic match: Cost allocation

Cost Shifting Among Transmission Customers The Show Cause Order states at P 76 that CAISO and PTO tariffs “lack adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service” and expresses concern…
Read this passage

III. FLEXIBLE LARGE LOADS AND FLEXIBLE INTERIM LOAD

printed heading · Topic match: Connecting load and generation

With respect to these concerns, SDG&E has participated in CAISO’s Large Load Enhancements stakeholder process.22 After considering stakeholder input, the “CAISO proposes to create a new flexible interconnection service option that will enable ECLL and co-located loads to limit their energy…
Read this passage

IV. CO-LOCATED LARGE LOADS

printed heading · Topic match: Connecting load and generation

CO-LOCATED LARGE LOADS An ECLL serving a Co-Located Large Load must provide information concerning the associated generation, including the executed generator interconnection agreement or, if none exists, a queue number that will allow SDG&E to verify that the generator has submitted an…
Read this passage

V. GRID ENHANCING TECHNOLOGIES

printed heading

Consistent with this framework, the CAISO’s TPP specifically considers GETs, including advanced conductors, dynamic line ratings, power flow controllers, and topology optimization, as potential alternatives when developing solutions to identified transmission needs.28 SDG&E proposes to leverage…
Read this passage

VI. BRIEFING QUESTIONS

printed heading

BRIEFING QUESTIONS The Show Cause Order at PP 123-125 includes three briefing questions that apply to Transmission Owners.
Read this passage

A. Existing Commercial Arrangements

printed heading

Existing Commercial Arrangements Paragraph 123 of the Show Cause Order states: We direct further briefing regarding how CAISO and the Participating Transmission Owners … should protect existing commercial arrangements including: (1) what would be a reasonable implementation period to ensure minimal…
Read this passage

B. Planning Impacts from Flexible Services for Large Loads

printed heading

This commitment threshold will help ensure that transmission planning reflects sufficiently committed projects and their applicable grid withdrawal limits, while preventing speculative or uncommitted FILI requests evaluated through the interconnection study process from distorting regional or local…
Read this passage

C. Structures to Prevent Cost Shifts

printed heading · Topic match: Cost allocation

As an initial matter, the ECLL will be required to provide up-front funding in cash of all Interconnection Facilities, thereby eliminating any possible cost shifting for those facilities.30 Further, because the financial security for necessary network upgrades must be posted by the ECLL prior to…
Read this passage

VII. ISSUES TO BE ADDRESSED THROUGH THE CAISO TARIFF

printed heading · Topic match: Connecting load and generation

These directives include: • the definitions of co-located load and Behind the Meter Generation (“BTMG”) (PP 88-89); • the rates, terms, and conditions of service that apply to interconnection customers serving co-located load, including the scope of CAISO’s analyses of co-location arrangements (PP…
Read this passage

VIII. CONFORMING AND MINISTERIAL REVISIONS

printed heading

Reese November 16, 2026 Page 24 of 25 SDG&E also proposes conforming changes, including replacing outdated cross-references to specific CAISO Tariff sections with references to “applicable sections” of the CAISO Tariff; replacing references to WSCC with WECC; updating website references from OASIS…
Read this passage

IX. ENCLOSURES

printed heading

ENCLOSURES Enclosed for filing are an eTariff Electronic Filing Package containing all required Tariff Record Content Data and metadata, as well as the following filing attachments in PDF for posting on eLibrary: 1. this transmittal letter; 2. a clean version of each new or modified Section or…
Read this passage

X. EFFECTIVE DATE

printed heading

EFFECTIVE DATE SDG&E requests that the Commission accept the tariff revisions contained in this filing effective Tuesday, February 16, 2027, which is ninety-two (92) days from the date of this filing.
Read this passage

XI. REQUEST FOR WAIVER

printed heading

REQUEST FOR WAIVER To the extent that any filing requirement in Part 35 of the Commission’s regulations is not satisfied by this filing and the materials enclosed herewith, SDG&E respectfully requests waiver of such requirements.
Read this passage

XII. COMMUNICATIONS

printed heading

COMMUNICATIONS All communications, correspondence, and documents related to this proceeding should be served upon the following persons: Pamela J.
Read this passage

XIII. SERVICE

printed heading

SERVICE SDG&E has served a copy of this filing upon the CAISO and the CPUC.
Read this passage

XIV. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, SDG&E respectfully requests that the Commission: (A) accept the proposed revisions to SDG&E’s TO Tariff as just and reasonable and not unduly discriminatory or preferential; (B) grant the requested effective date of February 16, 2027; and (C)…
Read this passage

CERTIFICATE OF SERVICE

printed heading · Topic match: Connecting load and generation

If the New Facility OperatorEligible Customer fails to timely comply with such interconnection requirements, such New Facility OperatorEligible Customer shall pay the reasonable costs of revising the System Impact Studies for other New Facility Operator’sEligible Customers that have established a…
Read this passage