ER27-523-000 · 2026-11-16 · Viridon Path 15 LLC

Viridon Path 15 - Trans. Owner Tariff Response to Show Cause Order EL26-71

PDF page 1

W I L K I N S O N  B A R K E R  K N A U E R ,  L L P
2 1 3 8  W . 3 2
N D  A V E

S U I T E  3 0 0
D E N V E R ,  C O  8 0 2 1 1
T E L  3 0 3 . 6 2 6 . 2 3 5 0
w w w . w b k l a w . c o m

November 16, 2026

Via eTariff

Ms. Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street N.E.
Washington, D.C. 20426

Re:  Viridon Path 15 LLC
        Docket No. ER26-___-000
        Docket No. EL26-71-000
Revisions to Path 15 Transmission Owner Tariff in Response to Show Cause
Order

Dear Secretary Reese:
Pursuant to Section 205 of the Federal Power Act (“FPA”),1 Section 35.13 of the
Regulations of the Federal Energy Regulatory Commission (“FERC” or “Commission”),2 and the Commission’s June 18, 2026 order directed to the California Independent System Operator (“CAISO”) and participating transmission owners (“PTOs”),3 Viridon Path 15 LLC (“Viridon Path 15”)4 hereby respectfully files a revised Transmission Owner Tariff (“Path 15 TO Tariff”). Viridon Path 15 appreciates the Commission’s efforts to address large load

interconnections in organized electric markets. Viridon Path 15 is pleased to present its proposed revisions to its Transmission Owner Tariff (“TO Tariff Revisions”) governing its interest in the Path 15 Upgrade Project. The TO Tariff Revisions, in concert with the tariff revisions proposed

1 16 U.S.C. § 824d.
2 18 C.F.R. § 35.13.
3 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 62,214, at P 5 & n.9 (2026) (“Show Cause Order”).
4 Viridon Path 15 submitted a notice of succession on April 21, 2025, to reflect the name change from DATC Path 15, LLC (“DATC Path 15”) to Viridon Path 15, effective March 28, 2025, following consummation of a Commission-approved transaction through which Viridon California LLC (“VCA”) acquired 100% of the equity interests in Viridon Path 15 (“Transaction”). See Viridon Path 15 LLC, Docket No. ER25-2007-000 (issued June 18, 2025) (unpublished letter order) (accepting Viridon Path 15’s notice of succession and revisions to Transmission Owner Tariff under its former name, DATC Path 15, LLC) (“Notice of Succession”); DATC Path 15, LLC, 190 FERC ¶ 62,162 (2025) (“Section 203 Order”) (approving the Transaction).

PDF page 2

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 2

by the CAISO and other PTOs, address the concerns identified in the Show Cause Order.
Specifically, and as discussed in further detail later in this transmittal letter, the proposed TO Tariff Revisions address: (1) the application process, study procedures, and operational requirements that apply to Eligible Customers seeking transmission service on behalf of large loads; (2) cost- recovery mechanisms that prevent cost-shifts to third parties; (3) the terms and conditions that apply for large loads co-located with generation resources; and (4) the extension of new transmission service to Eligible Customers taking service on behalf of large loads with flexible demand.5 Viridon Path 15 has generally designed the TO Tariff Revisions to be consistent with the tariff revisions proposed by the CAISO and other PTOs. However, given the relatively accelerated timeframe for developing revisions, the differing operating structures for CAISO PTOs, and the complex issues at hand, the TO Tariff Revisions do not perfectly align with every other PTO’s proposed revisions. Viridon Path 15 respectfully requests that the Commission accept the revised TO Tariff Revisions for filing, without a hearing or suspension, with an effective date of February 16, 2027.6

I. BACKGROUND AND SUMMARY OF FILING
Viridon Path 15 is a CAISO PTO and a named respondent to the Show Cause Order.
Viridon Path 15 and its parent company, VCA, are uniquely situated amongst CAISO PTOs.  VCA is a Delaware limited liability company formed to develop, construct, own, and operate

transmission facilities in CAISO. In addition to owning Viridon Path 15, VCA owns a 100% interest in California Grid Holdings LLC (“CalGrid”), which actively pursues competitive solicitations for CAISO-identified Order No. 1000 projects. To date, CalGrid has been selected as an Approved Project Sponsor7 to construct, own, and operate three separate Order No. 1000 projects within the CAISO footprint.8 Because these projects remain under development, CalGrid

5 See generally id. (identifying these features as provisions to be included in relevant tariffs). The Show Cause Order also identified a study process to consider generating facilities that will serve electrically proximate large loads. See id. at P 106-119. CAISO proposes that a future stakeholder initiative can best address this issue. See CAISO, Large Load Enhancements - Draft Final Proposal at 69 (Sept. 24, 2026) (“CAISO Draft Final Proposal”), https://stakeholdercenter.caiso.com/InitiativeDocuments/Draft-Final-Proposal-Large-Load-Enhancements-Sep-24- 26.pdf. Viridon Path 15 agrees and accordingly does not propose any tariff revisions addressing this issue at this time, as discussed below. 6 Viridon Path 15 is cognizant of the Commission’s instruction that “proposed tariff revisions should include a reasonable effective date that accommodates . . . existing commercial arrangements.” Show Cause Order, 195 FERC ¶ 61,214 at P 5. Viridon Path 15 has no pending large load interconnection requests, thus the proposed effective date of February 16, 2027 is reasonable, and aligns with the effective dates that the CAISO has proposed.
7 Capitalized terms not otherwise defined herein are used consistent with the Appendix A of the CAISO tariff.
8 CalGrid is the Approved Project Sponsor to construct, own, and operate the following CAISO-approved transmission solutions: (1) the New Humboldt 500 kV Substation, with a 500/115 kV transformer, together with the

PDF page 3

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 3

is a CAISO Approved Project Sponsor and will be a PTO once the projects are completed. However, CalGrid is not a current CAISO PTO and does not own in-service transmission facilities on the CAISO system.

Viridon Path 15 is a PTO as owner of the existing Transmission Service Rights interest (“TSR Interest”) in the Path 15 upgrade. The Path 15 Upgrade includes critical 500 kV transmission infrastructure that was built as a public-private partnership to relieve bottlenecks along the Northern California Path 15 transmission corridor after the California Energy crisis (“Path 15 Upgrade”).  The Western Area Power Administration (“WAPA”) owns the physical transmission infrastructure constituting the Path 15 Upgrade. The entire Path 15 Upgrade—both WAPA’s physical infrastructure and Viridon Path 15’s TSR Interest—are under CAISO operational control.9 The Path 15 TO Tariff is for transmission service along this particular line under the TSR Interest.

The existing Path 15 TO Tariff is limited in scope because it governs only Viridon Path 15’s TSR Interest. Based on the unique ownership structure for the Path 15 Upgrade, Section 8 of the existing Path 15 TO Tariff directs requests for interconnection, construction of transmission expansions and facility upgrades to WAPA, Pacific Gas & Electric Company (“PG&E”), or the CAISO, as applicable.10  Similarly, Section 9 of the existing Path 15 TO Tariff directs expansion requests to WAPA, PG&E, or the CAISO.11  Notwithstanding this direction, the Path 15 TO Tariff includes transmission interconnection and expansion provisions in existing subsections 8a and 9a. These tariff subsections specifically denote that “Section 8a and Section 9a, and their subparts, are provided for consistency with other PTOs’ TO Tariffs. Sections 8a and 9a, and their subparts, have no application to the Entitlements turned over to the ISO’s operational control.”12 Viridon Path 15 maintains this framework in the TO Tariff Revisions by incorporating new Sections 10 and 10a to

new Humboldt to Collinsville 500 kV line, (2) the new Humboldt to Fern Road 500 kV transmission line, and (3) the new Manning to Metcalf 500 kV transmission line. See the CAISO’s June 2, 2025 Project Sponsor Selection Reports at https://stakeholdercenter.caiso.com/InitiativeDocuments/New-Humboldt-Fern-Road-500kV- Transmission-Line-Project-Reconciled-Final-Costs.pdf and

https://stakeholdercenter.caiso.com/InitiativeDocuments/New-Humboldt-Fern-Road-500kV Transmission-Line- Project-Reconciled-Final-Costs.pdf. See also the CAISO’s May 19, 2026 Project Sponsor Selection Report at https://stakeholdercenter.caiso.com/InitiativeDocuments/Manning-to-Metcalf-500-kV-Transmission-Line-Project- Project-Sponsor-Selection-Report-May-20-2026.pdf.

9 See CAISO Transmission Control Agreement, Appendix A at pages 145-146, https://www.caiso.com/Documents/TransmissionControlAgreement.pdf.
10 See Path 15 TO Tariff Section 8.
11 See Path 15 TO Tariff Section 9.
12 See Path 15 TO Tariff Section 8a.

PDF page 4

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 4

address large load interconnections.  Similar to Sections 8 and 9, new Section 10 provides that new interconnections to the Path 15 Upgrade must apply to WAPA, PG&E, or the CAISO, as applicable. New Section 10a describes a proposed interconnection process that is provided only to maintain consistency with other PTO tariffs.  Because Viridon Path 15 owns only the TSR Interest in the Path 15 Upgrade, all interconnection requests to the Path 15 Upgrade infrastructure will be routed to the physical asset owner. The TO Tariff Revisions are necessary because Viridon Path 15 is a named respondent to the Show Cause Order.

Since the Commission issued the Show Cause Order, Viridon Path 15 has worked
collaboratively with the CAISO and other CAISO PTOs to address the issues identified in the Show Cause Order.13 Through that process, Viridon Path 15 developed the TO Tariff Revisions that it hereby submits to the Commission. The TO Tariff Revisions, together with the concurrently filed tariff revisions from the CAISO and other PTOs, address the issues in the Show Cause Order. The TO Tariff Revisions are intended to be consistent with the provisions in CAISO’s most recent proposed tariff revisions as reflected in its October 30th Second Revised Draft Tariff Language.14 The TO Tariff Revisions are also intended to be consistent with other PTO tariff revisions filed in response to the Show Cause Order, to the extent possible. Insofar as Viridon is aware of differences between its TO Tariff Revisions and those expected to be proposed by other PTOs, Viridon has made efforts to explain the rationale for those differences.

II. DESCRIPTION AND BASIS FOR THE TO TARIFF REVISIONS
Viridon developed the TO Tariff Revisions to respond to the concerns identified in the Show Cause Order regarding transmission service to Eligible Customers on behalf of large loads. As described below, the proposed revisions address application and study procedures, ongoing operational requirements and service agreements, cost recovery, co-located generation, and flexible interim interconnection service. Viridon Path 15 has sought to align these provisions with CAISO’s proposed tariff framework and the approaches developed with other PTOs, while accounting for its role as a non-load-serving PTO and the need for coordination among affected transmission owners.

13 See, e.g., Comments of Viridon California Submitted Regarding CAISO Large Loads Straw Proposal (Submitted Aug. 28, 2026), https://stakeholdercenter.caiso.com/Comments/AllComments/43a11ec9-fe21-4255-bb1c- 336ad3703845#org-6c9bf931-895d-4eae-81ad-98b9e78738e0.
14 See https://stakeholdercenter.caiso.com/InitiativeDocuments/Second-Revised-Draft-Tariff-Language-Large- Loads-Order-to-Show-Cause-Oct-30-2026.docx (opens link) (“Second Revised Draft Tariff Language”).

PDF page 5

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 5

As discussed below, the TO Tariff Revisions are designed to facilitate timely large load interconnections, protect other transmission customers from cost shifts, and maintain reliable transmission system operations. Further, the TO Tariff Revisions specifically address co-located generation and the conditions under which flexible large loads may obtain interim interconnection service subject to operating limits and curtailment obligations. The proposed tariff changes do not disrupt existing commercial agreements as there are no existing requests to use the TSR Interest to large loads or any other End User.15 Finally, Section II.E discusses electrically proximate generation and explains why, consistent with CAISO’s recommendation, Viridon Path 15 does not propose revisions addressing this topic at this time.

A. Application and Study Procedures Applicable to Eligible Customers Seeking
Transmission Service on Behalf of Large Loads
The Show Cause Order identifies that the Commission is concerned that CAISO and/or PTOs do not currently have tariff provisions expressly addressing how the provision of transmission service to Eligible Customers on behalf of large loads will be studied in a timely fashion.16 The Commission therefore directed CAISO and the PTOs “to explain whether their tariffs remain just and reasonable without an application process, study procedures, and ongoing operational requirements that address the unique characteristics and challenges of providing transmission service to Eligible Customers on behalf of large loads, or to propose appropriate tariff revisions.”17

The Commission specifically identified four particular areas in which tariff provisions could be improved to address the process for providing transmission service to Eligible Customers on behalf of large loads: (1) definition of large load; (2) the application process for requesting transmission service to Eligible Customers on behalf of large loads and the relevant study procedures; (3) ongoing operational requirements for transmission customers serving large loads; and (4) pro forma provisions in transmission service agreements, or other applicable agreements, to memorialize the terms of the operational requirements.18

CAISO addresses each of these four topics and states in its Draft Final Proposal that it “agrees with the Commission that additional clarity and information requirements are necessary

15 Show Cause order at P 34.
16 Show Cause Order at P 38.
17 Id. at P 40.
18 Id. at P 56.

PDF page 6

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 6

within the CAISO tariff, especially if interim or non-firm service is being considered to facilitate ‘speed-to-power,’ or accelerated large load interconnections.”19 CAISO further noted, however, that “PTOs remain largely responsible for processing applications and studying new large loads, while the CAISO remains responsible for reviewing these studies and ensuring alignment with transmission planning activities.”20 Thus, CAISO expects “the PTOs to collectively develop their own consistent set of Tariff reforms to clarify their load interconnection processes and communications, and to align their proposals with the CAISO’s processes.”21

Viridon Path 15 addresses how the Commission framed each issue, how CAISO proposed addressing these issues, and how the TO Tariff Revisions implement the CAISO proposal, where applicable.

1. Definition of Large Load
The Show Cause Order states that a definition of large load would be useful to develop a definition of large load interconnection process.22 In its Second Revised Draft Tariff Language, CAISO proposed to define a large load as: “An End User located at a single site behind one or more Points of Interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater.”23 Viridon Path 15 agrees with this proposed definition and incorporates it directly into the TO Tariff Revisions.24 To Viridon Path 15’s knowledge, other PTOs may propose differing definitions for large load. Viridon Path 15 supports the CAISO’s proposed definition as a straightforward framework consistent with existing CAISO and PTO tariff provisions.

2. Large Load Application
The CAISO Draft Final Proposal “suggests that the PTOs develop consistent application processes, study requirements, and agreements to ensure sufficient transparency in the load application and study process.”25 Viridon Path 15 has worked with other PTOs to develop a consistent application process, and Viridon Path 15 has attempted to develop substantively

19 CAISO Draft Final Proposal at 10.
20 Id. at 10-11.
21 Id. at 11.
22 Show Cause Order at P 57.
23 Second Revised Draft Tariff Language at Appendix A.
24 See TO Tariff Revisions § 3.14.
25 CAISO Draft Final Proposal at 19.

PDF page 7

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 7

consistent application requirements. However, Viridon Path 15 underscores that, given the short timeframe, the complexity of issues involved, and the large number of PTOs, it was not possible to coordinate in perfect lockstep with all other PTOs.

In general, the TO Tariff Revisions incorporate new provisions for large load applications within the existing framework for interconnection applications in existing non-load serving entity (“non-LSE”) PTO tariffs. The TO Tariff Revisions do not establish an entirely separate process for large load interconnection applications, but instead specify additional requirements for applications on behalf of large loads. The TO Tariff Revisions’ provisions on large load application process address the required contents of any such applications, the required application fee, and the timeframe by which the PTO determines an application is complete.26 These provisions are designed to collect sufficient information to move forward with a request by an Eligible Customer on behalf of a large load.

Viridon highlights two specific provisions in the application process that may differ substantively from other CAISO PTO tariffs.  First, proposed Tariff Section 10a.4.2(vii)   requires “disclosure of any other interconnection requests to the ISO Controlled Grid the applicant has filed on behalf of the same Large Load or any of its affiliate(s).”  This section ensures full transparency regarding potentially duplicative requests from a single End User.  Viridon Path 15 understands that other PTOs will require a similar disclosure, with a more limited scope; for example, limiting disclosure to interconnection requests from the same large load customer that are within the Eligible Customer’s footprint.  Viridon Path 15 suggests that limiting the obligation to disclose a single large load customer’s applications within an Eligible Customer “footprint” is vague and potentially under-inclusive.  An applicant requesting interconnection on behalf of a large load customer should be obligated to disclose any interconnection requests it has filed on behalf of the same large load customer.27

Second, Viridon Path 15 notes its proposed Tariff Section 10a.5 requiring a PTO
coordination process for large load interconnections. Viridon Path 15 believes that a transparent and actionable PTO coordination process is vital to ensure that end use large load customers can exercise the most cost-effective and timely options to access the transmission system. Viridon Path 15’s proposed Tariff Section 10a.5 requires the PTO receiving a completed large load

26 See TO Tariff Revisions § 10a.3–10a.5.
27 Additionally, and consistent with the approach that Viridon understands Horizon West Transmission, LLC is including it its tariff revisions, Section 10a.2 of the TO Tariff Revisions provides for the voluntary offer of unbundled retail transmission service to any End-Use Customer whose Point of Interconnection is on facilities owned by Company, in accordance with the CAISO Tariff.

PDF page 8

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 8

interconnection application to provide notice and a copy of the application to the CAISO and any other PTO with potentially affected transmission facilities.  In addition, this section requires the PTO receiving the interconnection application to coordinate with other PTOs to determine the most cost-effective solution to provide the requested transmission service.

An effective PTO coordination process is essential to ensure the existing transmission system is utilized at maximum efficiency.  Without PTO coordination at the application stage, large load customers will have limited, or non-existent, insight regarding where to interconnect to the CAISO Controlled Grid.  Non-LSE PTOs do not have direct relationships with large load retail customers and, without a PTO coordination process, may not be aware of large load interconnection requests that are geographically or electrically proximate to their transmission facilities.  As a result, non-LSE PTO facilities could be underutilized by large load customers.  A large load interconnection process that favored connecting to load serving entity PTO facilities would not be just and reasonable.  The CAISO’s Order No. 1000 process has been incredibly successful and the majority of regional transmission projects have been awarded to non-LSE competitive transmission developers.  This means that non-LSE PTOs will likely own and operate an increasingly large portion of the CAISO transmission system in the foreseeable future.  The Commission should ensure the large load interconnection process allows end users to effectively use those new facilities.

Viridon Path 15 recommends that all CAISO PTO tariffs include similar coordination language to ensure alignment.

3. Large Load Study Process
Regarding large load interconnection study processes, “CAISO [did] not propose changing the allocation of rights and responsibilities for studying large load interconnection requests from the framework in place today: the PTOs will continue to manage the bulk of the study responsibilities.”28  Rather, the CAISO Draft Final Proposal “encourages the PTOs to align their load interconnection study procedures among themselves and with the CAISO resource interconnection standards and [transmission planning process (“TPP”)] for enhanced clarity and consistency for customers.”29 CAISO also stated that it “expects the PTOs to develop consistent study procedures to be completed within 60 to 90 days, as required by the Commission,” and that

28 Id. at 25.
29 Id.

PDF page 9

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 9

the study procedures should account for large loads with load flexibility.30 CAISO also “expects PTOs to propose enhanced alignment of their load interconnection request windows and study timelines with the CAISO processes.”31

Viridon Path 15 has largely aligned its proposed study procedures with those of other PTOs, though it has not had prior opportunity to review other PTOs’ final proposed language.  The TO Tariff Revisions may differ from other PTO study processes by proposing a serial study process for large load interconnections rather than a cluster study process.  At this time, Viridon Path 15 does not believe there is a need to implement a cluster study process.

Consistent with other PTOs, under the TO Tariff Revisions, the Transmission Owner and CAISO (if applicable) will determine whether a system impact study is required.32 If no such study is required, the TO Tariff Revisions set forth a process for expeditiously entering an interconnection agreement if no direct assignment facilities are required, or if direct assignment facilities are required, then the parties will enter a facilities study agreement and continue the interconnection process.33 If a system impact study is required, the TO Tariff Revisions then set forth the process by which such study will be completed, including the relevant timelines and payment for the costs of the study.34

Viridon Path 15 highlights that its proposed Tariff Section 10a.6.4 includes a requirement for a PTO to share its System Impact Studies with other potentially affected PTOs, in addition to the applicant and the CAISO.  Viridon Path 15 recommends requiring PTOs to share System Impact Studies to enable affected PTOs to study and identify upgrades to downstream facilities, as well as the right to construct, own, and operate those upgrades.

30 Id.
31 Id. at 26. CAISO explains that this approach “is needed for all the information to be communicated back to the CAISO in a timely and consistent manner to inform the CAISO’s broader transmission planning, resource interconnection, and deliverability allocation procedures.” Id.
32 See TO Tariff Revisions § 10a.6.1.
33 See id. § 10a.6.6.
34 See id. §§ 10a.6.2 – 10a.6.5.

PDF page 10

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 10

The TO Tariff Revisions provide for the study process being completed within 60 to 90 days of a completed application and system impact study agreement, consistent with the Show Cause Order and the CAISO Draft Final Proposal.35

4. Large Load Operational Requirements
The Commission also identified the potential need to provide for tariff provisions addressing “ongoing operational requirements for transmission customers serving large loads necessary to ensure reliable operation of the transmission system.”36

CAISO’s Draft Final Proposal notes in response that CAISO’s Large Load Technical Requirements Working Group (“LLTRWG”) has been developing requirements to address this issue.37 Based on the LLTRWG’s work and in coordination between CAISO and PTOs, CAISO proposes that its tariff will address: requirements on ramp-rates; frequency and voltage ride- through requirements, forecasts, telemetry, and other necessary operational data; communication protocols for remote disconnection; and maintaining communication channels between CAISO and transmission customers serving large loads.38

CAISO then proposes that the following requirements be addressed through PTO tariffs: required installation of phasor measurement units or other high-speed monitoring equipment, with cost assigned to the transmission customer; and requirements for systems that can limit large load withdrawals from the transmission system.39 CAISO identifies, however, that the LLTRWG continues to refine technical requirements, with potential changes to flow through to the CAISO tariff, PTO tariffs, or other mechanisms.40

35 See id. § 10a.6.
36 Show Cause Order at P 56 (footnote omitted). See also id. at P 63 (“The unique nature of these large loads creates challenges for operation of the transmission system and necessitates greater visibility and operational control when providing transmission service to transmission customers on behalf of large loads, without which the reliability of the transmission system could be at risk. For example, we are concerned that CAISO’s Tariff and/or the TO Tariffs do not require transmission customers to provide CAISO hourly forecasts, telemetry data, and other data to ensure sufficient visibility or specify requirements for maintaining communication channels between CAISO and the transmission customer on behalf of the large load.” (footnote omitted)).
37 See CAISO Draft Final Proposal at 36.
38 Id.
39 Id. at 36-37.
40 Id. at 37.

PDF page 11

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 11

The TO Tariff Revisions would require that certain of the necessary information for collection would be required as part of any interconnection application, to be provided to CAISO during the interconnection process. However, Viridon Path 15 proposes that such information be included in the interconnection agreements.41

5. Large Load Service Agreements
The Show Cause Order also identifies the potential need for “pro forma provisions in transmission service agreements, or other applicable agreements, to memorialize” the terms set forth regarding operational requirements.42 The Commission explained its concern that “without such pro forma provisions in a transmission service agreement, or other applicable agreement, between CAISO and/or the Participating Transmission Owner and the transmission customer, CAISO may be unable to enforce ongoing operational requirements for transmission customers taking transmission service on behalf of large loads.”43

To address this issue, CAISO proposes that the PTOs develop “consistent pro forma agreements to memorialize the technical and operational terms the Order describes.”44 CAISO explains that, in its view, “it is not clear whether the CAISO should always be a signatory to a three-party agreement for large load interconnections.”45 CAISO identifies that it would likely need to be a signatory in an agreement addressing non-firm interconnection service based on the operational procedures necessary to provide such service.46 And for co-located large loads with exporting generation, CAISO states that it would need to be a party to “a pro forma agreement that bridges the pro forma Large Generator Interconnection Agreement (LGIA) with the pro forma large load interconnection agreement or negotiate a non-conforming LGIA to account for certain details of the co-located large load interconnection on an individual basis.”47 The TO Tariff Revisions contemplate a Large Load Interconnection Agreement that will require the applicant to provide the technical and operational requirements provided by the Show

41 See id. § 10a.6.8.1.
42 Show Cause Order at P 56.
43 Id. at P 64.
44 CAISO Draft Final Proposal at 40.
45 Id.
46 Id.
47 Id.

PDF page 12

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 12

Cause Order and the CAISO’s proposed tariffs.48 Viridon Path 15 understands that CAISO PTOs have developed a pro forma Large Load Interconnection Agreement that incorporates these technical and operational requirements, but Viridon Path 15 was not able to substantively review the proposal prior to making this filing.  In an effort to coordinate with other PTOs and maintain consistency to the extent possible, the TO Tariff Revisions do not include a separate pro forma Large Load Interconnection Agreement.  Instead, Viridon Path 15 will review the pro forma Large Load Interconnection Agreement proposed by other CAISO PTOs and provide recommended edits or comments as necessary.

B. Cost-Recovery Mechanisms that Prevent Cost-Shifts to Third Parties
In the Show Cause Order, the Commission preliminarily found “that cost transparency measures are needed to provide stakeholders with sufficient information and visibility regarding the network upgrades, and their associated costs, needed to accommodate transmission service to Eligible Customers on behalf of large loads.”49 The Commission therefore called for measures to increase transparency.50

In addition to improved transparency, the Commission cited the need for development of a pro forma cost recovery agreement between CAISO, the applicable PTO, and the Eligible Customer taking transmission service on behalf of large loads.51 The Show Cause Order identifies a concern that speculative transmission service requests could result in cost shifting among transmission customers, which could result, for example, if an “Eligible Customer takes less transmission service than anticipated because the large load operates at a lower demand than anticipated or fails to materialize at all” after network upgrades are already constructed to serve that load.52 The Commission urged that cost recovery agreements “would help ensure that the Eligible Customer makes a minimum contribution to the transmission owner’s transmission revenue requirement commensurate with the costs incurred to provide the requested transmission service, including the costs of any needed network upgrades.”53 The Show Cause Order therefore “preliminarily find[s] that … cost recovery agreements are necessary to help ensure that the

48 See TO Tariff Revisions § 10a.6.8.1.
49 Show Cause Order at P 70.
50 Id. at P 75.
51 Id. at P 76.
52 Id. at P 78.
53 Id. at P 79.

PDF page 13

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 13

Eligible Customer is responsible for timely paying the costs of large load-driven transmission (i.e., the costs incurred to provide them with the requested transmission service, including the costs of any needed network upgrades) ….”54

To address the potential for cost shifts, the CAISO Draft Proposal proposes that the PTO tariffs address the cost allocation issues identified by the Commission.55 “CAISO believes that the PTOs may develop their own proposals to address any cost shifting, and that the current transmission revenue requirement and credit mechanisms in the TAC can accommodate those proposals.”56 CAISO also suggests that PTOs should account for the impact of construction contributions, revenues, or other cost offsets associated with network upgrade costs directly attributed to large loads and paid for by the large load customer through the utility distribution company or metered subsystem in determining its transmission revenue requirement.57 As to cost data transparency, CAISO identifies the data already shared on its website and “proposes to clarify in the TPP where network upgrades were needed to accommodate both general load growth and large load interconnection specifically,” and to publicly post certain information on its website.58 Viridon Path 15 supports this approach and notes that this obligation falls on CAISO and not PTOs.

As noted above, the TO Tariff Revisions contemplate adopting a pro forma Large Load Interconnection Agreement.  Cost recovery mechanisms that ensure that the Eligible Customer is responsible for timely paying the costs of large load-driven transmission (i.e., the costs incurred to provide the requested transmission service, including the costs of any needed network upgrades) will be reflected in the pro forma Large Load Interconnection Agreement. As also noted above, Viridon Path 15 understands that other CAISO PTOs have developed a pro forma Large Load Interconnection Agreement that incorporates these cost recovery mechanisms that

54 Id. at P 80. The Show Cause Order further identified that a potentially appropriate approach for determining the level of minimum contribution would be the “based on the level of jurisdictional transmission service (in MW) requested by the Eligible Customer on behalf of large load.” Id. at 82. The Commission further explained that in addition to the minimum contribution, “the cost recovery agreement should include a credit support (or other financial security) requirement sufficient to secure the obligations of the Eligible Customer taking transmission service on behalf of a large load to pay the amounts owed pursuant to the cost recovery agreement.” Id.

55 CAISO Final Draft Proposal at 44.
56 Id.
57 Id. at 45.
58 Id. at 48.

PDF page 14

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 14

meet the Show Cause Order requirements, but Viridon Path 15 was not able to substantively review the proposal prior to making this filing.

In an effort to coordinate with other PTOs and maintain consistency to the extent possible, the TO Tariff Revisions do not include a separate pro forma Large Load Interconnection Agreement or cost recovery mechanisms.  Viridon Path 15 believes that developing an entirely separate and distinct cost recovery mechanism for this filing would not have been productive, especially given that Viridon Path 15’s current ownership in the Path 15 Upgrade is limited to the TSR Interest.  Rather than proposing its own separate cost recovery mechanisms, Viridon Path 15 will review the pro forma Large Load Interconnection Agreement and the cost recovery mechanisms proposed by other CAISO PTOs and provide recommended edits or comments as necessary.

C. Rates, Terms, and Conditions for Large Loads Co-Located with Generation
Resources
The Show Cause Order directed CAISO and PTOs, to the extent applicable to PTO tariffs, to explain whether their tariffs are “just and reasonable without provisions addressing the rates, terms, and conditions that apply to interconnection customers serving co-located load and for Eligible Customers taking transmission service on behalf of Eligible Load, or [to] propose Tariff revisions establishing the rates, terms, and conditions that apply to co-location arrangements.”59 The CAISO Draft Final Proposal states in response to this concern that CAISO proposes to clarify co-location arrangements that would not require a CAISO resource interconnection request and could be accommodated through applicable PTO or CPUC-jurisdictional retail interconnection tariffs.60 Additionally, for large loads seeking to co-locate with new generation that may export to the grid, CAISO proposes requiring a CAISO interconnection study, with scoring and study results based on the requested capacity figures the developer may provide, allowing the generator to “significantly limit the generation potentially to be exported based on how much generation will serve the large load.”61

Accordingly, because of the changes CAISO intends to make to address co-located loads set forth in its Second Revised Draft Tariff Language, PTOs do not need to make extensive revisions to specifically address co-located loads in their tariffs. The TO Tariff Revisions specifically address co-located large loads by providing that large loads with co-located generation

59 Show Cause Order at P 86.
60 CAISO Draft Final Proposal at 55.
61 See id.

PDF page 15

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 15

facilities will be studied based on their expected load on the transmission system, net of the co- located generation’s output that offsets the large load’s energy usage.62 For co-located generation resources that may export to the transmission system, the TO Tariff Revisions specify that such generation must comply with the applicable CAISO generator interconnection procedures and requirements.63

D. Extending New Transmission Service to Eligible Customers Taking Service on Behalf of Flexible Large Loads

In the Show Cause Order, the Commission identified that flexible large loads can potentially defer the need for transmission network upgrades, which in turn would allow for faster interconnection and potentially avoid the need for transmission system build-out.64 The Commission further noted that the CAISO tariff does not currently “include transmission services that reflect the use of the transmission system by Eligible Customers on behalf of flexible large load, on both an interim and permanent basis,” and the Commission directed CAISO to explain whether the Tariff remains just and reasonable without an interim or permanent non-firm network transmission service, or in the alternative, “explain what specific changes to its existing transmission service framework would effectively provide comparable transmission service options for flexible large loads.”65

In the CAISO Draft Final Proposal, CAISO explains that its straw proposal created two new flexible interconnection service offerings, “one offered on an interim basis and one offered for permanent use, to shorten interconnection timelines and reduce interconnection costs, respectively.”66 CAISO proposed to advance the interim option at present, given time constraints and because the interim option is meant to shorten interconnection timeframes.67 For the interim approach, CAISO proposed creating a new flexible interconnection service that would allow large loads and co-located loads to limit their energy withdrawals or injections until their network upgrades are placed into service.68 The CAISO Draft Final Proposal states that “CAISO believes

62 See TO Tariff Revisions § 10a.8.
63 See id.
64 Show Cause Order at PP 103-104.
65 Id. at P 105.
66 CAISO Draft Final Proposal at 63.
67 See id. at 64.
68 Id. at 66.

PDF page 16

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 16

this will provide large load developers with the option to interconnect quickly through enforceable physical and operational controls to prevent transmission congestion.”69 To implement this approach, CAISO proposed creating a new Flexible Interim Load Interconnection (“FILI”) service to be implemented in close coordination with the CAISO PTOs to enable faster interconnections while mitigating transmission constraints.70

Accordingly, within the TO Tariff Revisions presented here, Viridon Path 15 has implemented a new service for that concept, identified as Flexible Interim Large Load Interconnection (“FILLI”).71 The TO Tariff Revisions are intended to be closely consistent with the framework set forth in CAISO’s Second Revised Draft Tariff Language, along with other PTOs that Viridon Path 15 has coordinated with, to maintain uniformity within the CAISO footprint. The TO Tariff Revisions also address the need to ensure that there is an enforceable chain of authority and obligations to curtail when required so that any flexibility credited in interconnection studies is realized in operation. These provisions are just and reasonable because they reasonably balance the benefits of facilitating flexible load additions earlier and at lower cost, while at the same time providing the terms necessary to ensure the stability and reliability of the transmission system. It is important to emphasize that for the FILLI offering to function as intended, curtailment obligations must be enforceable and the chain of authority must be clear. Experience with existing reliability-based demand response arrangements suggests that voluntary curtailment commitments are difficult to enforce in practice. Flexible interconnection service agreements should therefore include clear performance obligations, verification through the telemetry and monitoring requirements described above, and meaningful consequences for non-performance to ensure that the benefits of flexibility are achieved in practice. The Path 15 Tariff Revision sections addressing FILLI are designed with these considerations in mind, requiring a FILLI service agreement that would fill in the operational details.

The TO Tariff Revisions would define FILLI as “A transmission interconnection service offered by the Participating TO and accepted by an Eligible Customer on behalf of a Large Load retail customer to manage operational constraints on withdrawals from the transmission system while the interconnection and system upgrades necessary to provide Firm Interconnection Service are being developed.”72 The TO Tariff Revisions then define the interconnection service for FILLI

69 Id.
70 Id. at 67.
71 See TO Tariff Revisions §§ 3.12, 10a.7.
72 See id. § 3.12.

PDF page 17

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 17

customers, including the study process used to identify the maximum amount of FILLI service, if any, that may be provided based on the anticipated availability of transmission capacity, and conditions for FILLI service.73

For interconnection service to FILLI customers, the TO Tariff Revisions specify that FILLI service will be available for load that cannot receive interim firm interconnection service, if the large load customer is able to reduce load according to requirements specified in a FILLI service agreement.74

The TO Tariff Revisions also include a study process for FILLI service, where the Participating TO performs an initial study to determine the maximum amount of interim firm service, if any, and FILLI service, if any, that may be provided based on the projected availability of transmission capacity available to serve the large load customer.75 The PTO shall determine the level of FILLI service available on an annual basis to accommodate changing conditions on the transmission system over time.76

The TO Tariff Revisions also specify certain prerequisite conditions related to FILLI service by providing that a FILLI Service Agreement will identify what Eligible Customer interconnection facilities must be installed, protection and control equipment to be installed, and operating limits to allow the FILLI customer to withdraw energy.77  The TO Tariff Revisions contemplate including the FILLI Service Agreement as an Appendix to the TO Tariff.  Viridon Path 15 understands that other CAISO PTOs have developed a pro forma FILLI Service Agreement that incorporates terms for offering FILLI service, FILLI service reliability requirements, rules for curtailment and protocols for reducing load, and consequences for exceeding authorities FILLI Service.78  To date, Viridon Path 15 has not had the opportunity to substantively review the pro forma FILLI Service Agreement.

In an effort to coordinate with other PTOs and maintain consistency to the extent possible, the TO Tariff Revisions do not include a separate pro forma FILLI Service Agreement.  Viridon Path 15 believes that developing an entirely separate and distinct FILLI Service Agreement for

73 See id. §§ 10a.7.1 – 10a.7.2.
74 See id. § 10a.7.1.
75 See id. § 10a.7.2.
76 See id. § 10a.7.
77 See id. § 10a.7.3.
78 See id. § 10a.7.

PDF page 18

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 18

this filing would not have been productive, especially given that Viridon Path 15’s current ownership in the Path 15 Upgrade is limited to the TSR Interest.  Rather than proposing its own separate FILLI Service Agreement, Viridon Path 15 will review the pro forma agreement proposed by other CAISO PTOs and provide recommended edits or comments as necessary.

 Additionally, the TO Tariff Revisions set forth when service to FILLI customers may be curtailed and the priority of FILLI service relative to firm service.79 As provided in the TO Tariff Revisions, the PTO and CAISO may curtail FILLI service as necessary to maintain the reliable operation of the CAISO-controlled transmission system.80 The TO Tariff Revisions further provide that the Eligible Customer shall ensure that the PTO’s operating instructions are not exceeded at the point of withdrawal and that the PTO has the right to disconnect service to the FILLI customer if energy withdrawals by the FILLI customer violate the terms of the relevant service agreement, with the PTO following good utility practice in carrying out any such disconnection and subsequent reconnection.81

E. Large Load Electrically Proximate to Generation Resources
The Show Cause Order identifies the potential need for a specific process that would prioritize interconnecting generation resources that are electrically proximate to large loads.82 The Commission explained that

[w]here a generating facility’s output is matched to the demand of the electrically proximate large load or large co-located load or if the generating facility’s output is limited to ensure no new injection, the impacts to the transmission system of interconnecting the generating facility to serve that electrically proximate large load or large co-located load may be limited.83

The Commission further stated that these limited impacts may reduce the need for network upgrades, which would accelerate the generator interconnection process.84 The Commission stated that it was concerned by the CAISO tariff’s lack of study procedures and generator interconnection

79 See id. § 10a.7.3.2.
80 See id.
81 See id. § 10a.7.3.3.
82 Show Cause Order at PP 106-119.
83 Id. at P 113.
84 Id.

PDF page 19

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 19

services addressing electrically proximate generation resources.85 The Commission stated that it preliminarily found the absence may be unjust and unreasonable.86 However, the Commission notably did not state that any PTOs’ tariffs may be unjust and unreasonable,87 because the CAISO tariff provisions are where these types of procedures would typically reside.88 In CAISO’s Draft Final Proposal, CAISO proposed that it would consider provisions for interconnection customers to serve electrically proximate large loads in a future stakeholder initiative.89 In support of its approach, CAISO explained that “it currently has a process for connecting generator interconnection request applications to non-load-serving entities (e.g. commercial and industrial consumers) in its generator interconnection process, which awards ‘points’ in the interconnection scoring process to projects that have a commercial arrangement with a non-load-serving entity off-taker.”90 This process “seeks to tie generation projects to loads to the extent that they have a commercial arrangement with the goal of enabling large loads to procure generation.”91 While CAISO agreed “with many stakeholders that it is worth continuing to explore the potential benefits of proximate loads,” it did not “propose development of this option” in immediate response to the Show Cause Order.92 PTOs commenting on this approach agreed.93

Because CAISO plans to address the issue of generation interconnection electrically proximate to large loads in a future stakeholder process, and because the terms of such interconnection service best reside within the CAISO tariff, Viridon Path 15 does not propose making any changes to its Path 15 Tariff on this issue. Viridon Path 15 looks forward to participating in the CAISO stakeholder process on this issue and understands the potential benefits from pairing electrically proximate generation and large loads to achieve faster interconnection.

85 Id. at P 117.
86 Id.
87 See id.
88 See Joint Participating Transmission Owners, Request for Abeyance at 5-6 (Aug. 3, 2026).
89 CAISO Draft Final Proposal at 69.
90 Id.
91 Id.
92 Id.
93 See id. (noting that PG&E and SDG&E agreed with not creating new tariff provisions at this time for interconnection customers to serve electrically proximate large loads).

PDF page 20

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 20

III. INFORMATION REQUIRED UNDER 18 C.F.R. § 35.13(b)
In accordance with Section 35.13(a)(2)(iii) and 35.13(b) of the Commission’s regulations, Viridon Path 15 provides the following information:

A. Documents Submitted with this Filing94
In addition to this transmittal letter, Viridon Path 15 is also submitting clean and redlined versions of the TO Tariff Revisions.

B. Proposed Effective Date95
Viridon Path 15 proposes a February 16, 2027 effective date for the TO Tariff Revisions.
C. Persons Receiving Service96
Viridon Path 15 has served a copy of this filing electronically, including attachments, upon all Path 15 Tariff customers and all parties to Docket No. EL26-71-000. This filing will also be posted in conformance with the Commission’s regulations.97

D. Description of Rate Change98
Viridon Path 15 describes the rate change in detail in Section II of this transmittal letter.
E. Statement of the Reasons for the Rate Change99
As discussed in more detail in Section II of this transmittal letter, Viridon Path 15 is revising its Path 15 Tariff because of the Commission’s Show Cause Order and based on the stakeholder process that has occurred through CAISO.

94 18 C.F.R. § 35.13(b)(1).
95 Id. § 35.13(b)(2).
96 Id. § 35.13(b)(3).
97 Id. § 35.2(e).
98 Id. § 35.13(b)(4).
99 Id. § 35.13(b)(5).

PDF page 21

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 21

F. Requisite Agreement to the Rate Change100
No third-party agreement is required for Viridon Path 15 to file or implement the proposed changes presented here. However, Viridon Path 15 notes that its proposed changes are largely consistent with Viridon Path 15’s understanding of the changes that will be proposed by other Transmission Owners within the CAISO footprint.

IV. REQUEST FOR WAIVERS
Pursuant to 18 C.F.R. § 385.101(e), Viridon Path 15 respectfully requests, to the extent necessary, that the Commission waive the requirement to provide the information identified in 18 C.F.R. § 35.13(c) relating to the effect of rate changes because the TO Tariff Revisions would not change the cost of service or Viridon Path 15’s revenue requirement. Waiver is appropriate where such information is not “necessary for the Commission to determine whether a rate is just and reasonable.”101

The TO Tariff Revisions are targeted to the specific issues that FERC identified in the Show Cause Order, including study processes, cost-shifts, and co-located large loads. These revisions are not focused on the cost of service or revenue requirement and do not yield any readily calculable differences in projected revenues from sales and services. Thus, to the extent the Commission concludes that 18 C.F.R. § 35.13(c) is applicable, Viridon Path 15 respectfully requests that the Commission waive the requirements contained therein.

V. COMMUNICATIONS
Viridon Path 15 respectfully requests that all correspondence related to this filing be sent to the following individuals, and that they be placed on the official service list in this docket:102

100 Id. § 35.13(b)(6).
101 ISO New England Inc. New England Power Co. d/b/a Nat’l Grid, 178 FERC ¶ 61,115, at P 57 (Feb. 18, 2022); see also id. at P 57 n.91 (collecting previous FERC orders on this point).
102 Pursuant to 18 C.F.R. § 385.101(e), Viridon Path 15 respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) to permit more than two persons to be added to the Commission’s official service list in this proceeding.

PDF page 22

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 22

Verónica Gómez
General Counsel and
Chief Administrative Officer
Chad Newhouse
Vice President Regulatory
Viridon Services LLC
515 North State Street
Suite 1150
Chicago, IL 60654
(773) 551-1920
veronica@viridon.com
chad@viridon.com
Jordan Pinjuv
Michael Miller
Wilkinson Barker Knauer, LLP
2138 W. 32nd Ave.
Suite 300
Denver, CO 80211
303-626-2350
jpinjuv@wbklaw.com
mmiller@wbklaw.com

VI. CONCLUSION
Viridon Path 15 respectfully requests that the Commission permit the revised Path 15 Tariff to become effective as of February 16, 2027.

Respectfully Submitted,

WILKINSON BARKER KNAUER, LLP

/s/ Jordan Pinjuv
Jordan Pinjuv
Michael Miller

Counsel for Viridon Path 15 LLC

Dated: November 16, 2026

PDF page 23

Ms. Debbie-Anne A. Reese
November 16, 2026
Page 23

CERTIFICATE OF SERVICE
 I hereby certify that a copy of this filing, including attachments, has been served electronically upon all Path 15 Tariff customers and each registered person on the official service list compiled by the Secretary in Docket No. EL26-71-000.

Dated, this 16th day of November, 2026

/s/ Jordan Pinjuv

Jordan Pinjuv