ER27-523-000 · 2026-11-16 · Viridon Path 15 LLC

Viridon Path 15 - Trans. Owner Tariff Response to Show Cause Order EL26-71

Viridon Path 15 LLC files tariff revisions under section 205 on November 16, 2026, in ER27-523-000, answering the CAISO show cause order. It owns only a transmission service rights interest in the Path 15 Upgrade, so interconnection requests route to WAPA, PG&E or CAISO. It files no cost recovery mechanism and no pro forma interconnection agreement.

Asks FERC to: Accept the revisions without hearing or suspension, effective February 16, 2027.

Filed under section 205 to answer the E-10 show cause order. It aligns with CAISO's draft tariff language on definition, study and interim service, and defers cost recovery and the interconnection agreement to the other owners' work.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)

Key points

  1. Viridon owns only a service rights interest in Path 15. WAPA owns the physical facilities.
    The Western Area Power Administration (“WAPA”) owns the physical transmission infrastructure constituting the Path 15 Upgrade PDF p. 3
  2. It says it could not fully align with the other owners in the time available.
    given the short timeframe, the complexity of issues involved, and the large number of PTOs, it was not possible to coordinate in perfect lockstep with all other PTOs PDF p. 7
  3. It requires applicants to disclose other requests for the same large load or its affiliates.
    disclosure of any other interconnection requests to the ISO Controlled Grid the applicant has filed on behalf of the same Large Load or any of its affiliate(s) PDF p. 7
  4. It proposes a coordination process between owners and argues a process favoring load-serving owners' facilities would not be just and reasonable.
    A large load interconnection process that favored connecting to load serving entity PTO facilities would not be just and reasonable PDF p. 8
  5. It files no cost recovery mechanism of its own.
    the TO Tariff Revisions do not include a separate pro forma Large Load Interconnection Agreement or cost recovery mechanisms PDF p. 14
  6. Co-located loads would be studied net of the co-located generation's output.
    facilities will be studied based on their expected load on the transmission system, net of the co- located generation’s output that offsets the large load’s energy usage PDF p. 15
  7. It says curtailment duties for the interim service must be enforceable.
    for the FILLI offering to function as intended, curtailment obligations must be enforceable and the chain of authority must be clear PDF p. 16
  8. It proposes no tariff changes on electrically proximate generation, following CAISO.
    Viridon Path 15 does not propose making any changes to its Path 15 Tariff on this issue PDF p. 19

Text extracted from the eLibrary original (SHA-256 14924880bdf54731…). Download the original from the official source.

Contents · 17 sections
  1. I. BACKGROUND AND SUMMARY OF FILING p. 2
  2. II. DESCRIPTION AND BASIS FOR THE TO TARIFF REVISIONS p. 4
  3. A. Application and Study Procedures Applicable to Eligible Customers Seeking p. 5
  4. B. Cost-Recovery Mechanisms that Prevent Cost-Shifts to Third Parties p. 12
  5. C. Rates, Terms, and Conditions for Large Loads Co-Located with Generation p. 14
  6. D. Extending New Transmission Service to Eligible Customers Taking Service on p. 15
  7. E. Large Load Electrically Proximate to Generation Resources p. 18
  8. III. INFORMATION REQUIRED UNDER 18 C.F.R. § 35.13(b) p. 20
  9. A. Documents Submitted with this Filing94 p. 20
  10. B. Proposed Effective Date95 p. 20
  11. C. Persons Receiving Service96 p. 20
  12. D. Description of Rate Change98 p. 20
  13. E. Statement of the Reasons for the Rate Change99 p. 20
  14. F. Requisite Agreement to the Rate Change100 p. 21
  15. IV. REQUEST FOR WAIVERS p. 21
  16. V. COMMUNICATIONS p. 21
  17. VI. CONCLUSION p. 22

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Viridon Path 15 respectfully requests that the Commission accept the revised TO Tariff Revisions for filing, without a hearing or suspension, with an effective date of February 16, 2027.6
Read this passage

I. BACKGROUND AND SUMMARY OF FILING

printed heading

CAISO proposes that a future stakeholder initiative can best address this issue.
Read this passage

II. DESCRIPTION AND BASIS FOR THE TO TARIFF REVISIONS

printed heading · Topic match: Cost allocation

The proposed tariff changes do not disrupt existing commercial agreements as there are no existing requests to use the TSR Interest to large loads or any other End User.15 Finally, Section II.E discusses electrically proximate generation and explains why, consistent with CAISO’s recommendation,…
Read this passage

A. Application and Study Procedures Applicable to Eligible Customers Seeking

printed heading · Topic match: Connecting load and generation

First, proposed Tariff Section 10a.4.2(vii) requires “disclosure of any other interconnection requests to the ISO Controlled Grid the applicant has filed on behalf of the same Large Load or any of its affiliate(s).” This section ensures full transparency regarding potentially duplicative requests…
Read this passage

B. Cost-Recovery Mechanisms that Prevent Cost-Shifts to Third Parties

printed heading · Topic match: Cost allocation

Reese November 16, 2026 Page 13 Eligible Customer is responsible for timely paying the costs of large load-driven transmission (i.e., the costs incurred to provide them with the requested transmission service, including the costs of any needed network upgrades) ….”54 To address the potential for…
Read this passage

C. Rates, Terms, and Conditions for Large Loads Co-Located with Generation

printed heading · Topic match: Connecting load and generation

Reese November 16, 2026 Page 15 facilities will be studied based on their expected load on the transmission system, net of the co- located generation’s output that offsets the large load’s energy usage.62 For co-located generation resources that may export to the transmission system, the TO Tariff…
Read this passage

D. Extending New Transmission Service to Eligible Customers Taking Service on

printed heading · Topic match: Connecting load and generation

It is important to emphasize that for the FILLI offering to function as intended, curtailment obligations must be enforceable and the chain of authority must be clear.
Read this passage

E. Large Load Electrically Proximate to Generation Resources

printed heading · Topic match: Connecting load and generation

Viridon Path 15 looks forward to participating in the CAISO stakeholder process on this issue and understands the potential benefits from pairing electrically proximate generation and large loads to achieve faster interconnection. 85 Id. at P 117. 86 Id. 87 See id. 88 See Joint Participating…
Read this passage

III. INFORMATION REQUIRED UNDER 18 C.F.R. § 35.13(b)

printed heading

INFORMATION REQUIRED UNDER 18 C.F.R. § 35.13(b) In accordance with Section 35.13(a)(2)(iii) and 35.13(b) of the Commission’s regulations, Viridon Path 15 provides the following information:
Read this passage

A. Documents Submitted with this Filing94

printed heading

Documents Submitted with this Filing94 In addition to this transmittal letter, Viridon Path 15 is also submitting clean and redlined versions of the TO Tariff Revisions.
Read this passage

B. Proposed Effective Date95

printed heading

Proposed Effective Date95 Viridon Path 15 proposes a February 16, 2027 effective date for the TO Tariff Revisions.
Read this passage

C. Persons Receiving Service96

printed heading

Persons Receiving Service96 Viridon Path 15 has served a copy of this filing electronically, including attachments, upon all Path 15 Tariff customers and all parties to Docket No.
Read this passage

D. Description of Rate Change98

printed heading

Description of Rate Change98 Viridon Path 15 describes the rate change in detail in Section II of this transmittal letter.
Read this passage

E. Statement of the Reasons for the Rate Change99

printed heading

Statement of the Reasons for the Rate Change99 As discussed in more detail in Section II of this transmittal letter, Viridon Path 15 is revising its Path 15 Tariff because of the Commission’s Show Cause Order and based on the stakeholder process that has occurred through CAISO. 94 18 C.F.R. §…
Read this passage

F. Requisite Agreement to the Rate Change100

printed heading

Requisite Agreement to the Rate Change100 No third-party agreement is required for Viridon Path 15 to file or implement the proposed changes presented here.
Read this passage

IV. REQUEST FOR WAIVERS

printed heading

REQUEST FOR WAIVERS Pursuant to 18 C.F.R. § 385.101(e), Viridon Path 15 respectfully requests, to the extent necessary, that the Commission waive the requirement to provide the information identified in 18 C.F.R. § 35.13(c) relating to the effect of rate changes because the TO Tariff Revisions…
Read this passage

V. COMMUNICATIONS

printed heading

COMMUNICATIONS Viridon Path 15 respectfully requests that all correspondence related to this filing be sent to the following individuals, and that they be placed on the official service list in this docket:102 100 Id. § 35.13(b)(6). 101 ISO New England Inc.
Read this passage

VI. CONCLUSION

printed heading

CONCLUSION Viridon Path 15 respectfully requests that the Commission permit the revised Path 15 Tariff to become effective as of February 16, 2027.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated, this 16th day of November, 2026 /s/ Jordan Pinjuv Jordan Pinjuv