ER27-528-000 · 2026-11-16 · LS Power Grid California, LLC

Revisions to TO Tariff to Provide for Large Load Interconnection

LS Power Grid California files tariff revisions under section 205 on November 16, 2026, in ER27-528-000, answering the CAISO show cause order. It adds a large load interconnection process and a pro forma cost recovery agreement with a 20-year minimum revenue contribution. The letter matches the DesertLink filing in ER27-534; the differences are in the Formula Rate Template and the project descriptions.

Asks FERC to: Accept the revisions effective January 16, 2027, 61 days after filing, and grant any waivers needed.

Filed under section 205 to answer the E-10 show cause order. It adds a large load interconnection process and a pro forma cost recovery agreement to a transmission-only owner's tariff, and defers permanent flexible service to CAISO.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62)

Key points

  1. It adds a process for utilities that buy transmission service on behalf of large loads.
    adding a new Section 10A and a new Appendix VI (Large Load Interconnection Procedures (“LLIP”)) to establish an interconnection process for Eligible Customers for Large Load (“ECLLs”) PDF p. 1
  2. The definition is 50 MW of peak load at a single site.
    a Large Load is an End-User located at a single site behind one or more Points of Withdrawal from the CAISO Controlled Grid with a peak load of 50 MW or greater PDF p. 4
  3. The cost recovery agreement sets a 20-year minimum revenue contribution for each upgrade.
    establishes the Eligible Customer’s twenty-year Minimum Transmission Revenue Contribution (“MTRC”) and related payment and security obligations for each Covered Upgrade PDF p. 2
  4. Ending service early costs the customer all remaining revenue responsibility.
    the Eligible Customer owes a lump-sum Termination Fee equal to the Remaining Cumulative Revenue Responsibility PDF p. 7
  5. Direct security can be reduced by security the large load posted under a retail agreement.
    allowing an Eligible Customer to rely on credit support posted by a large load under a retail agreement, direct Operational Security is reduced dollar-for-dollar by Qualifying Retail Security Support PDF p. 7
  6. Interim curtailable service is curtailed ahead of firm service.
    FILI Service is subject to curtailment, including during normal operating conditions, and is curtailed before Firm Interconnection Service PDF p. 4
  7. LS Power Grid has no retail customers and no retail relationship with a large load.
    LS Power Grid is a non-load-serving PTO with no End-Use Customers; it neither serves retail load nor has a retail relationship with any customer seeking a Large Load interconnection PDF p. 3
  8. This is the difference from DesertLink: LS Power Grid says its formula rate template needs no changes.
    requires no changes to LS Power Grid’s Formula Rate Template or Protocols PDF p. 11

Text extracted from the eLibrary original (SHA-256 2d3d454def2e95c1…). Download the original from the official source.

Contents · 109 sections
  1. I. INTRODUCTION AND SUMMARY OF FILING p. 2
  2. II. BACKGROUND p. 3
  3. A. LS Power Grid and Its Formula Rate p. 3
  4. B. Show Cause Order and Stakeholder Process p. 3
  5. III. DESCRIPTION OF THE PROPOSED REVISIONS p. 4
  6. A. Large Load Interconnection Framework (Section 10A and Appendix VI) p. 4
  7. B. Pro Forma CRA (Appendix V) p. 5
  8. C. Crediting CRA Amounts Through the TRBAA (Sections 3 and 5.3) p. 8
  9. D. Formula Rate Template and Rate Treatment of Covered Upgrades p. 9
  10. E. Supporting Testimony and Illustrative Exhibits p. 10
  11. IV. THE PROPOSED REVISIONS ARE JUST AND REASONABLE p. 10
  12. V. REQUESTED EFFECTIVE DATE AND WAIVERS p. 11
  13. VI. CONTENTS OF FILING p. 12
  14. VII. COMMUNICATIONS AND SERVICE p. 12
  15. VIII. CONCLUSION p. 13
  16. I. Large Load Interconnection Customer (ECLL) Contact Information p. 164
  17. II. Large Load Customer Information p. 164
  18. III. Point of Interconnection p. 164
  19. IV. Large Load Capacity and Load Ramp Schedule p. 165
  20. V. Proposed Service Commencement Date and Term p. 165
  21. VI. Source of Power p. 165
  22. VII. Site Plan, Site Control, and Permits p. 165
  23. VIII. Co-Located Generation p. 166
  24. IX. Single-Line Diagram and Modeling Information p. 166
  25. X. Required Submittals (LLIP Section 4.2.1) p. 166
  26. XI. Acknowledgment p. 166
  27. I. Large Load Interconnection Customer (ECLL) Contact Information p. 322
  28. II. Large Load Customer Information p. 322
  29. III. Point of Interconnection p. 322
  30. IV. Large Load Capacity and Load Ramp Schedule p. 323
  31. V. Proposed Service Commencement Date and Term p. 323
  32. VI. Source of Power p. 323
  33. VII. Site Plan, Site Control, and Permits p. 323
  34. VIII. Co-Located Generation p. 324
  35. IX. Single-Line Diagram and Modeling Information p. 324
  36. X. Required Submittals (LLIP Section 4.2.1) p. 324
  37. XI. Acknowledgment p. 324
  38. I. INTRODUCTION AND EXPERIENCE p. 330
  39. A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310, p. 330
  40. II. PURPOSE AND SCOPE OF TESTIMONY p. 331
  41. A. The purpose of this testimony is to provide relevant context and details regarding p. 331
  42. A. Yes. I am sponsoring the following exhibits: p. 332
  43. III. FERC SHOW CAUSE ORDERS p. 332
  44. A. On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the p. 332
  45. A. Yes, Commissioners Chang and See each issued separate concurrences providing p. 333
  46. IV. CAISO STAKEHOLDER PROCESS p. 335
  47. A. CAISO convened joint coordination meetings with the California Participating p. 335
  48. A. LSPGC coordination highlighted the need to ensure that an affected PTO has a p. 336
  49. A. LSPGC proposes a pro forma CRA that establishes the Eligible Customer’s minimum p. 337
  50. V. COST RECOVERY AGREEMENT p. 337
  51. A. The CRA is a pro forma contract between LSPGC, as Transmission Owner, and the p. 337
  52. A. At a high level, the CRA responds directly to the three cost-recovery concerns identified p. 338
  53. A. The core payment mechanism is the Supplemental Minimum Transmission Revenue p. 339
  54. A. The Annual MTRC operates as a revenue floor, not an additive charge. Under Section p. 340
  55. A. The CRA addresses stranded-asset risk through a twenty-year revenue commitment, p. 341
  56. A. Section 7.1 recognizes Construction Security provided under an interconnection or p. 344
  57. A. Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits. In each p. 345
  58. VI. TARIFF IMPLEMENTATION AND REVIEW p. 346
  59. A. The pro forma CRA establishes the contractual revenue-support and security obligations p. 346
  60. A. The CRA contemplates an Eligible Customer for Large Load (“ECLL”) or Transmission p. 346
  61. A. LSPGC’s existing Attachment 1a – Project Plant Detail Worksheet reports plant p. 347
  62. A. Article 5 identifies the CRA as the form of agreement required under Section 10.9 and p. 347
  63. A. As Mr. Arzola explains, Covered Upgrades are subject to LSPGC’s Commission- p. 348
  64. A. Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the p. 348
  65. A. Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into p. 349
  66. A. The Annual Projection workpapers and annual Reconciliation Statement make the p. 350
  67. A. Yes, it does. p. 351
  68. D. ERIC ARZOLA p. 362
  69. D. ERIC ARZOLA p. 365
  70. I. INTRODUCTION AND EXPERIENCE p. 365
  71. A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310, p. 365
  72. A. Yes. I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or p. 365
  73. II. PURPOSE AND SUMMARY OF TESTIMONY p. 366
  74. A. The purpose of my testimony is to explain how LSPGC will recover the cost of p. 366
  75. A. LSPGC proposes to credit the amounts it receives under its CRAs to transmission p. 366
  76. A. No. LSPGC’s Formula Rate is unchanged. Covered Upgrades are included in LSPGC’s p. 367
  77. A. Yes. I am sponsoring the following exhibits: p. 367
  78. III. LSPGC AND FORMULA RATE BACKGROUND p. 367
  79. A. LSPGC is a transmission-only Participating Transmission Owner in the CAISO. LSPGC p. 367
  80. A. By October 5, LSPGC posts an Annual Projection of its net revenue requirement for the p. 368
  81. A. As provided in Appendix I of the TO Tariff, LSPGC’s Transmission Revenue p. 368
  82. A. In the Show Cause Order, the Commission directed the CAISO and its transmission p. 369
  83. IV. THE LARGE LOAD COST RECOVERY FRAMEWORK p. 369
  84. A. Each Covered Upgrade placed under the CAISO’s Operational Control is included in p. 370
  85. A. The Supplemental MTRC is calculated separately for each Covered Upgrade as the p. 370
  86. A. The Supplemental MTRC follows the same calendar as the Formula Rate. With each p. 370
  87. A. If an Eligible Customer does not pay, LSPGC may draw on the Eligible Customer’s p. 371
  88. A. The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the p. 372
  89. A. Covered Upgrades will be subject to LSPGC’s Commission-accepted Formula Rate and p. 373
  90. V. CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA p. 374
  91. A. Through the TRBAA. Each October, LSPGC will include the Forecast TRBAA Credit p. 374
  92. A. There are several reasons. First, the TRBAA already exists to credit customers with p. 374
  93. A. No. LSPGC’s annual TRBAA filing is made under Section 205 of the Federal Power Act. p. 375
  94. A. Section 5.3 of the TO Tariff currently provides for the TRBAA to flow Transmission p. 375
  95. A. LSPGC will add the following lines to the TRBA and TRBAA calculation it files each p. 376
  96. A. Interest applies when LSPGC holds funds that belong to transmission customers, or when p. 377
  97. A. Yes. In each annual TRBAA filing, LSPGC will provide the TRBA and TRBAA p. 378
  98. A. No. Appendix I states that LSPGC’s TRR equals its Base TRR plus its TRBAA, and that p. 378
  99. VI. LSPGC’S FORMULA RATE TEMPLATE p. 378
  100. A. No. LSPGC’s Formula Rate Template already contains the features the proposal requires: p. 378
  101. A. Consistent with Section 6.8 of the CRA, TRBAA Credits are credited solely through the p. 379
  102. A. No. The Formula Rate Implementation Protocols already require LSPGC to provide p. 379
  103. VII. ILLUSTRATIVE EXHIBITS p. 380
  104. A. Exhibit No. LSC-201 is LSPGC’s currently effective Formula Rate Template populated p. 380
  105. A. Exhibit No. LSC-202 illustrates the TRBA and TRBAA calculation for two consecutive p. 381
  106. VIII. CONCLUSION p. 382
  107. A. The revisions implement the Commission’s direction that large load payments be credited p. 382
  108. A. Yes. p. 383
  109. D. Eric Arzola p. 384

Topics in the text: Connecting load and generation · Registry access · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

LS Power Grid respectfully requests that the Commission accept the proposed tariff revisions to become effective January 16, 2027, sixty-one (61) days after filing, consistent with the Commission’s prior notice requirement,5 and grant any necessary waivers. 1 16 U.S.C. § 824d (2022). 2 18 C.F.R.…
Read this passage

I. INTRODUCTION AND SUMMARY OF FILING

printed heading · Topic match: Cost allocation

The filing responds to the Show Cause Order’s direction that respondents (1) ensure transparency concerning the network upgrade costs to provide transmission service to Eligible Customers on behalf of large loads, (2) establish a pro forma cost recovery agreement to mitigate the risk of cost…
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

A. LS Power Grid and Its Formula Rate

printed heading

LS Power Grid and Its Formula Rate LS Power Grid is a transmission-only PTO in the CAISO that owns the Gates and Round Mountain projects, which CAISO selected LS Power Grid to develop through its competitive solicitation process, and is developing additional competitively selected projects.
Read this passage

B. Show Cause Order and Stakeholder Process

printed heading · Topic match: Retail and wholesale authority

LS Power Grid’s proposal does not displace the separate arrangements that an Eligible Customer must enter into with an Affected System Owner for an Affected System Upgrade or with the owner of a regional project share owned by another entity.11
Read this passage

III. DESCRIPTION OF THE PROPOSED REVISIONS

printed heading

III.
Read this passage

A. Large Load Interconnection Framework (Section 10A and Appendix VI)

printed heading · Topic match: Connecting load and generation

Section 10A.2 specifies the contents of an ECLL Interconnection Application, including the load ramp schedule, site plan, Site Control, permits and approvals, electrical configuration, related requests, technical data, and Co-Located Large Load information.
Read this passage

B. Pro Forma CRA (Appendix V)

printed heading · Topic match: Cost allocation

Operational Security must be delivered no later than thirty Calendar Days before the earliest expected in-service date and equals one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility.
Read this passage

C. Crediting CRA Amounts Through the TRBAA (Sections 3 and 5.3)

printed heading

Because the TO Tariff defines Transmission Revenue Credits as amounts received from, or charges imposed by, CAISO, LS Power Grid proposes to revise the definitions of the Transmission Revenue Balancing Account (“TRBA”) (Section 3.97) and the TRBAA (Section 3.98) and Section 5.3 so that the TRBAA also…
Read this passage

D. Formula Rate Template and Rate Treatment of Covered Upgrades

printed heading

Formula Rate Template and Rate Treatment of Covered Upgrades No changes to LS Power Grid’s Formula Rate Template or Protocols are required.
Read this passage

E. Supporting Testimony and Illustrative Exhibits

printed heading · Topic match: Cost allocation

LSC-100) describes the Show Cause Order, the CAISO stakeholder process, the pro forma CRA, and the associated TO Tariff revisions, and explains how those measures assign cost responsibility for Large Load-Driven Upgrades, mitigate cost shifting and stranded-asset risk, avoid double recovery, and…
Read this passage

IV. THE PROPOSED REVISIONS ARE JUST AND REASONABLE

printed heading · Topic match: Cost allocation

Reese November 16, 2026 Page 11 A U S T I N D A L L A S D U B A I H O U S T O N L O N D O N N E W Y O R K P A R I S S A N A N T O N I O S E A T T L E W A S H I N G T O N , D C assessment of the actual cost of providing transmission service induced by individual large loads” may be insufficient to…
Read this passage

V. REQUESTED EFFECTIVE DATE AND WAIVERS

printed heading

REQUESTED EFFECTIVE DATE AND WAIVERS LS Power Grid requests an effective date of January 16, 2027, sixty-one (61) days after the date of this filing, satisfying the Commission’s sixty-day notice requirement.29 LS Power Grid requests waiver of the cost-of-service-statement requirements of 18 C.F.R.…
Read this passage

VI. CONTENTS OF FILING

printed heading

CONTENTS OF FILING LS Power Grid submits the following materials: • This transmittal letter; • Attachment 1: Clean version of the LS Power Grid TO Tariff revisions • Attachment 2: Marked version of the LS Power Grid TO Tariff revisions • Attachment 3: Direct testimony of Patrick Hayes (Exhibit No.
Read this passage

VII. COMMUNICATIONS AND SERVICE

printed heading

COMMUNICATIONS AND SERVICE LS Power Grid requests that all pleadings, correspondence, and other communications concerning this matter be directed to the following persons, and that their names and addresses be placed on the official service list for this proceeding:30 Josh R.
Read this passage

VIII. CONCLUSION

printed heading

CONCLUSION For the reasons stated above and in the supporting testimony, LS Power Grid respectfully requests that the Commission accept the proposed tariff revisions effective January 16, 2027, and grant any waivers deemed necessary.
Read this passage

Table of Contents

printed heading · Topic match: Connecting load and generation

A Large Load Customer receiving FILI Service shall be subject to curtailment prior to any curtailment of customers receiving Firm Interconnection Service.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.
Read this passage

I. Large Load Interconnection Customer (ECLL) Contact Information

printed heading

Large Load Interconnection Customer (ECLL) Contact Information Company Name Type of ECLL (UDC or MSS) Representative Address Email Phone
Read this passage

II. Large Load Customer Information

printed heading

Large Load Customer Information Large Load Customer Name Large Load Customer Representative and Contact Information Large Load Site Location/Address Type of Large Load Facility (e.g., data center, industrial) Other ECLL interconnection requests submitted for the same Large Load Customer or any of…
Read this passage

III. Point of Interconnection

printed heading

Point of Interconnection Please identify the location and voltage level of the preferred Point of Interconnection in as much detail as possible.
Read this passage

IV. Large Load Capacity and Load Ramp Schedule

printed heading

Large Load Capacity and Load Ramp Schedule Proposed load ramp schedule identifying anticipated load additions over time: Date (MM/DD/YYYY) Incremental Load (MW) Cumulative Load (MW)
Read this passage

V. Proposed Service Commencement Date and Term

printed heading

V.
Read this passage

VI. Source of Power

printed heading

VI.
Read this passage

VII. Site Plan, Site Control, and Permits

printed heading

If the source of the power is not known, a system purchase will be assumed.
Read this passage

VIII. Co-Located Generation

printed heading

Co-Located Generation Will the Large Load be co-located with a generating facility? (Yes/No) Will the generating facility export to the ISO Controlled Grid? (Yes/No) Generating facility queue number or, if executed, identification of its generator interconnection agreement Generating facility…
Read this passage

IX. Single-Line Diagram and Modeling Information

printed heading

Single-Line Diagram and Modeling Information Please attach a single-line diagram of the Large Load and the Large Load Interconnection Customer’s Interconnection Facilities and/or KMZ files to this Interconnection Request.
Read this passage

X. Required Submittals (LLIP Section 4.2.1)

printed heading

Required Submittals (LLIP Section 4.2.1) Item Included (Yes/No) Interconnection Study Deposit of $250,000 Commercial Readiness Deposit equal to two times the Interconnection Study Deposit, in a form permitted by LLIP Section 4.7.1 Demonstration of Site Control Completed technical data form in the…
Read this passage

XI. Acknowledgment

printed heading · Topic match: Registry access

The Large Load Interconnection Customer may designate information in this Interconnection Request, including the identity of the Large Load Customer, as Confidential Information in accordance with LLIP Section 7.1.
Read this passage

Table of Contents

printed heading · Topic match: Connecting load and generation

A Large Load Customer receiving FILI Service shall be subject to curtailment prior to any curtailment of customers receiving Firm Interconnection Service.
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.
Read this passage

I. Large Load Interconnection Customer (ECLL) Contact Information

printed heading

Large Load Interconnection Customer (ECLL) Contact Information Company Name Type of ECLL (UDC or MSS) Representative Address Email Phone
Read this passage

II. Large Load Customer Information

printed heading

Large Load Customer Information Large Load Customer Name Large Load Customer Representative and Contact Information Large Load Site Location/Address Type of Large Load Facility (e.g., data center, industrial) Other ECLL interconnection requests submitted for the same Large Load Customer or any of…
Read this passage

III. Point of Interconnection

printed heading

Point of Interconnection Please identify the location and voltage level of the preferred Point of Interconnection in as much detail as possible.
Read this passage

IV. Large Load Capacity and Load Ramp Schedule

printed heading

Large Load Capacity and Load Ramp Schedule Proposed load ramp schedule identifying anticipated load additions over time: Date (MM/DD/YYYY) Incremental Load (MW) Cumulative Load (MW)
Read this passage

V. Proposed Service Commencement Date and Term

printed heading

V.
Read this passage

VI. Source of Power

printed heading

VI.
Read this passage

VII. Site Plan, Site Control, and Permits

printed heading

If the source of the power is not known, a system purchase will be assumed.
Read this passage

VIII. Co-Located Generation

printed heading

Co-Located Generation Will the Large Load be co-located with a generating facility? (Yes/No) Will the generating facility export to the ISO Controlled Grid? (Yes/No) Generating facility queue number or, if executed, identification of its generator interconnection agreement Generating facility…
Read this passage

IX. Single-Line Diagram and Modeling Information

printed heading

Single-Line Diagram and Modeling Information Please attach a single-line diagram of the Large Load and the Large Load Interconnection Customer’s Interconnection Facilities and/or KMZ files to this Interconnection Request.
Read this passage

X. Required Submittals (LLIP Section 4.2.1)

printed heading

Required Submittals (LLIP Section 4.2.1) Item Included (Yes/No) Interconnection Study Deposit of $250,000 Commercial Readiness Deposit equal to two times the Interconnection Study Deposit, in a form permitted by LLIP Section 4.7.1 Demonstration of Site Control Completed technical data form in the…
Read this passage

XI. Acknowledgment

printed heading · Topic match: Cost allocation

The Large Load Interconnection Customer may designate information in this Interconnection Request, including the identity of the Large Load Customer, as Confidential Information in accordance with LLIP Section 7.1.
Read this passage

TABLE OF CONTENTS

printed heading

EXHIBITS TO DIRECT TESTIMONY OF PATRICK HAYES Exhibit No.
Read this passage

I. INTRODUCTION AND EXPERIENCE

printed heading

I.
Read this passage

A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310,

printed heading · Topic match: Cost allocation

My responsibilities include Federal Energy Regulatory Commission 10 (“FERC”) policy, regional transmission planning, competitive transmission development, 11 cost allocation and recovery, tariff development, and large-load interconnection. 12 Q.
Read this passage

II. PURPOSE AND SCOPE OF TESTIMONY

printed heading

II.
Read this passage

A. The purpose of this testimony is to provide relevant context and details regarding

printed heading · Topic match: Cost allocation

I describe the proposed Large Load Cost 13 Recovery Agreement (“CRA”) and associated tariff framework, and explain how these 14 measures assign cost responsibility for large-load-driven transmission upgrades, mitigate 15 cost shifting and stranded-asset risk, avoid double recovery, and promote…
Read this passage

A. Yes. I am sponsoring the following exhibits:

printed heading

I am sponsoring the following exhibits: 7 Exhibit No.
Read this passage

III. FERC SHOW CAUSE ORDERS

printed heading

III.
Read this passage

A. On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the

printed heading

On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the 10 Federal Power Act through six show cause orders addressing the integration of large and 11 co-located loads onto the interstate transmission system.
Read this passage

A. Yes, Commissioners Chang and See each issued separate concurrences providing

printed heading · Topic match: Cost allocation

Page 5 provide transmission service — as a necessary step to protect wholesale customers 1 against unjustified cost shifts.7 Commissioner Chang also cautioned that bilateral 2 agreements that simply provide transmission revenue contributions "untethered from any 3 assessment of the actual cost of…
Read this passage

IV. CAISO STAKEHOLDER PROCESS

printed heading

PLEASE DESCRIBE THE CAISO PROCESS FOLLOWING THE ISSUANCE OF 11 THE SHOW CAUSE ORDERS. 12
Read this passage

A. CAISO convened joint coordination meetings with the California Participating

printed heading · Topic match: Connecting load and generation

LSPGC participated in the joint coordination process 15 meetings on July 1, July 10, July 23, and July 28; August 4, August 11, August 18, and 16 August 25; September 1, September 8, September 10, September 15, and September 22; 17 and October 23, 2026. 18 The meetings addressed applications and…
Read this passage

A. LSPGC coordination highlighted the need to ensure that an affected PTO has a

printed heading · Topic match: Retail and wholesale authority

LSPGC coordination highlighted the need to ensure that an affected PTO has a 9 meaningful role in the process even when that PTO does not provide retail service to the 10 requesting load.
Read this passage

A. LSPGC proposes a pro forma CRA that establishes the Eligible Customer’s minimum

printed heading

LSPGC proposes a pro forma CRA that establishes the Eligible Customer’s minimum 11 revenue contribution and related security obligations for Covered Upgrades.
Read this passage

V. COST RECOVERY AGREEMENT

printed heading

V.
Read this passage

A. The CRA is a pro forma contract between LSPGC, as Transmission Owner, and the

printed heading

The CRA is a pro forma contract between LSPGC, as Transmission Owner, and the 20 Eligible Customer taking wholesale transmission service under the CAISO Tariff on 21 behalf of a Large Load Customer.
Read this passage

A. At a high level, the CRA responds directly to the three cost-recovery concerns identified

printed heading · Topic match: Cost allocation

At a high level, the CRA responds directly to the three cost-recovery concerns identified 14 in the Show Cause Order by: (i) establishing a pro forma contract between LSPGC and 15 the Eligible Customer that formalizes cost responsibility for the Covered Upgrades; (ii) 16 establishing payment and…
Read this passage

A. The core payment mechanism is the Supplemental Minimum Transmission Revenue

printed heading

The core payment mechanism is the Supplemental Minimum Transmission Revenue 3 Contribution (the "Supplemental MTRC") in Section 6.4 of the CRA.
Read this passage

A. The Annual MTRC operates as a revenue floor, not an additive charge. Under Section

printed heading

The Annual MTRC operates as a revenue floor, not an additive charge.
Read this passage

A. The CRA addresses stranded-asset risk through a twenty-year revenue commitment,

printed heading · Topic match: Reliability and curtailment

Operational Security must be delivered no later than thirty Calendar 11 Days before the earliest expected applicable in-service date and be fully effective before 12 service.
Read this passage

A. Section 7.1 recognizes Construction Security provided under an interconnection or

printed heading

Section 7.1 recognizes Construction Security provided under an interconnection or 6 engineering and procurement agreement for the same costs, avoiding duplication.
Read this passage

A. Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits. In each

printed heading

Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits.
Read this passage

VI. TARIFF IMPLEMENTATION AND REVIEW

printed heading

PLEASE DESCRIBE THE ASSOCIATED TARIFF REVISIONS. 2
Read this passage

A. The pro forma CRA establishes the contractual revenue-support and security obligations

printed heading

LSPGC also proposes to revise 4 the definition of the TRBAA and Section 5.3 so that amounts required to be credited 5 under a CRA flow through to transmission customers.
Read this passage

A. The CRA contemplates an Eligible Customer for Large Load (“ECLL”) or Transmission

printed heading

The CRA contemplates an Eligible Customer for Large Load (“ECLL”) or Transmission 13 System Wholesale Load (“TSWL”) Interconnection Agreement.
Read this passage

A. LSPGC’s existing Attachment 1a – Project Plant Detail Worksheet reports plant

printed heading

LSPGC’s existing Attachment 1a – Project Plant Detail Worksheet reports plant 3 separately by project, and Attachment 1 – Project Revenue Requirement Worksheet 4 calculates each project’s revenue requirement using the applicable allocation factors. 5 Covered Upgrades can be reported as separate…
Read this passage

A. Article 5 identifies the CRA as the form of agreement required under Section 10.9 and

printed heading

LSPGC must file unexecuted agreements, agreements 22 containing material deviations, and any other agreement required by Commission rule or 23 order.
Read this passage

A. As Mr. Arzola explains, Covered Upgrades are subject to LSPGC’s Commission-

printed heading

Arzola explains, Covered Upgrades are subject to LSPGC’s Commission- 5 accepted Formula Rate and the return on equity (“ROE”) and capital structure reflected in 6 the effective Formula Rate.
Read this passage

A. Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the

printed heading

Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the 24 calculation, information exchange, and true-up of LSPGC’s Net Revenue Requirement 25 Page 20 and the rate-base treatment of Covered Upgrades.
Read this passage

A. Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into

printed heading

Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into 21 billing following the next Annual Projection.
Read this passage

A. The Annual Projection workpapers and annual Reconciliation Statement make the

printed heading

The Annual Projection workpapers and annual Reconciliation Statement make the 15 upgrade-specific minimum contribution, forecast and actual QTR, Supplemental MTRC, 16 cumulative commitment, security, and TRBAA credit calculations available to the 17 Eligible Customer.
Read this passage

A. Yes, it does.

printed heading

Yes, it does. 13 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION LS Power Grid California, LLC California Independent System Operator Corporation ) ) Docket No.
Read this passage

D. ERIC ARZOLA

printed heading · Topic match: Cost allocation

ERIC ARZOLA ON BEHALF OF LS POWER GRID CALIFORNIA, LLC Large Load Network Upgrade Cost Recovery November 2026
Read this passage

TABLE OF CONTENTS

printed heading

Description LSC-201: Illustrative Formula Rate Template LSC-202: Illustrative TRBAA Calculation DIRECT TESTIMONY OF
Read this passage

D. ERIC ARZOLA

printed heading

D.
Read this passage

I. INTRODUCTION AND EXPERIENCE

printed heading

I.
Read this passage

A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310,

printed heading

My business address is 16150 Main Circle Drive, Suite 310, 3 Chesterfield, Missouri 63017. 4 Q.
Read this passage

A. Yes. I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or

printed heading

I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or 14 “Commission”) Docket Nos.
Read this passage

II. PURPOSE AND SUMMARY OF TESTIMONY

printed heading

II.
Read this passage

A. The purpose of my testimony is to explain how LSPGC will recover the cost of

printed heading

The purpose of my testimony is to explain how LSPGC will recover the cost of 7 transmission facilities built to serve large loads and covered by a Large Load Cost 8 Recovery Agreement (“CRA”) (such facilities, “Covered Upgrades”), and how it will 9 credit the amounts Eligible Customers pay under…
Read this passage

A. LSPGC proposes to credit the amounts it receives under its CRAs to transmission

printed heading

LSPGC proposes to credit the amounts it receives under its CRAs to transmission 23 customers through its TRBAA, the existing mechanism LSPGC uses to pass revenue that 24 3 it does not receive through the California Independent System Operator Corporation 1 (“CAISO”) Transmission Access Charge…
Read this passage

A. No. LSPGC’s Formula Rate is unchanged. Covered Upgrades are included in LSPGC’s

printed heading

Covered Upgrades are included in LSPGC’s 10 rate base and revenue requirement in the same manner as any other LSPGC transmission 11 plant, and are reported as separate projects on the existing Attachment 1a – Project Plant 12 Detail Worksheet and Attachment 1 – Project Revenue Requirement Worksheet.
Read this passage

A. Yes. I am sponsoring the following exhibits:

printed heading

I am sponsoring the following exhibits: 19 Exhibit No.
Read this passage

III. LSPGC AND FORMULA RATE BACKGROUND

printed heading

PLEASE PROVIDE AN OVERVIEW OF LSPGC AND ITS FORMULA RATE. 21
Read this passage

A. LSPGC is a transmission-only Participating Transmission Owner in the CAISO. LSPGC

printed heading

LSPGC is a transmission-only Participating Transmission Owner in the CAISO.
Read this passage

A. By October 5, LSPGC posts an Annual Projection of its net revenue requirement for the

printed heading

By October 5, LSPGC posts an Annual Projection of its net revenue requirement for the 9 upcoming Rate Year.
Read this passage

A. As provided in Appendix I of the TO Tariff, LSPGC’s Transmission Revenue

printed heading

As provided in Appendix I of the TO Tariff, LSPGC’s Transmission Revenue 16 Requirement (“TRR”) is the sum of its Base Transmission Revenue Requirement (“Base 17 TRR”), determined under the Formula Rate, and its TRBAA.
Read this passage

A. In the Show Cause Order, the Commission directed the CAISO and its transmission

printed heading

In the Show Cause Order, the Commission directed the CAISO and its transmission 4 owners to show cause why their tariffs remain just and reasonable or to propose changes 5 for integrating large loads.
Read this passage

IV. THE LARGE LOAD COST RECOVERY FRAMEWORK

printed heading

A CRA is an agreement between LSPGC and an Eligible Customer taking transmission 14 service on behalf of a large load.
Read this passage

A. Each Covered Upgrade placed under the CAISO’s Operational Control is included in

printed heading

Each Covered Upgrade placed under the CAISO’s Operational Control is included in 2 LSPGC’s rate base and Base TRR and recovered through the CAISO TAC together with 3 the cost of LSPGC’s other transmission facilities.
Read this passage

A. The Supplemental MTRC is calculated separately for each Covered Upgrade as the

printed heading

The Supplemental MTRC is calculated separately for each Covered Upgrade as the 14 amount, if any, by which the applicable Annual MTRC, prorated for a partial Rate Year, 15 exceeds the Qualifying Transmission Revenues allocated to that upgrade under Section 16 6.4.
Read this passage

A. The Supplemental MTRC follows the same calendar as the Formula Rate. With each

printed heading

The Supplemental MTRC follows the same calendar as the Formula Rate.
Read this passage

A. If an Eligible Customer does not pay, LSPGC may draw on the Eligible Customer’s

printed heading

If an Eligible Customer does not pay, LSPGC may draw on the Eligible Customer’s 13 Operational Security and apply the proceeds to the unpaid amount (“Applied Security 14 Proceeds”).
Read this passage

A. The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the

printed heading

The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the 12 amounts LSPGC records in the TRBA and credits to transmission customers through the 13 TRBAA: payments of Supplemental MTRC received from or on behalf of the Eligible 14 Customer (“Supplemental MTRC Receipts”), Applied…
Read this passage

A. Covered Upgrades will be subject to LSPGC’s Commission-accepted Formula Rate and

printed heading

Covered Upgrades will be subject to LSPGC’s Commission-accepted Formula Rate and 3 the return on equity (“ROE”) and capital structure reflected in the effective Formula Rate. 4 LSPGC’s commitments to limit its ROE to 9.8%, inclusive of incentive ROE adders, and 5 to limit the equity component of…
Read this passage

V. CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA

printed heading

CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA 1 Q.
Read this passage

A. Through the TRBAA. Each October, LSPGC will include the Forecast TRBAA Credit

printed heading

Each October, LSPGC will include the Forecast TRBAA Credit 3 for the following calendar year in Cf.
Read this passage

A. There are several reasons. First, the TRBAA already exists to credit customers with

printed heading

First, the TRBAA already exists to credit customers with 20 revenue LSPGC receives outside the TAC, and the Commission and stakeholders review 21 it each year.
Read this passage

A. No. LSPGC’s annual TRBAA filing is made under Section 205 of the Federal Power Act.

printed heading

LSPGC’s annual TRBAA filing is made under Section 205 of the Federal Power Act. 9 Each filing is noticed by the Commission, is open to intervention, comment, and protest, 10 and is subject to Commission review and acceptance.
Read this passage

A. Section 5.3 of the TO Tariff currently provides for the TRBAA to flow Transmission

printed heading

Because CRA-related credits include amounts received 25 12 directly from or on behalf of the Eligible Customer and Annual Termination Fee Credits 1 scheduled under Section 3.3.4, LSPGC proposes to revise the definition of the TRBAA 2 and Section 5.3 so that the TRBAA also flows through to…
Read this passage

A. LSPGC will add the following lines to the TRBA and TRBAA calculation it files each

printed heading

LSPGC will add the following lines to the TRBA and TRBAA calculation it files each 12 year, as shown in Exhibit No.
Read this passage

A. Interest applies when LSPGC holds funds that belong to transmission customers, or when

printed heading

Interest applies when LSPGC holds funds that belong to transmission customers, or when 9 transmission customers hold funds owed to LSPGC.
Read this passage

A. Yes. In each annual TRBAA filing, LSPGC will provide the TRBA and TRBAA

printed heading

In each annual TRBAA filing, LSPGC will provide the TRBA and TRBAA 3 calculation substantially in the form of Exhibit No.
Read this passage

A. No. Appendix I states that LSPGC’s TRR equals its Base TRR plus its TRBAA, and that

printed heading

Appendix I states that LSPGC’s TRR equals its Base TRR plus its TRBAA, and that 10 the TRBAA is computed in accordance with Section 5.3 of the TO Tariff and the CAISO 11 Tariff.
Read this passage

VI. LSPGC’S FORMULA RATE TEMPLATE

printed heading

ARE ANY CHANGES TO LSPGC’S FORMULA RATE TEMPLATE NEEDED 15 TO IMPLEMENT THE PROPOSAL? 16
Read this passage

A. No. LSPGC’s Formula Rate Template already contains the features the proposal requires:

printed heading

LSPGC’s Formula Rate Template already contains the features the proposal requires: 17 • Attachment 1a – Project Plant Detail Worksheet reports monthly transmission 18 gross plant, accumulated depreciation, Construction Work in Progress (“CWIP”), 19 and unamortized abandoned plant, and the resulting…
Read this passage

A. Consistent with Section 6.8 of the CRA, TRBAA Credits are credited solely through the

printed heading

Consistent with Section 6.8 of the CRA, TRBAA Credits are credited solely through the 10 TRBAA and are not Formula Rate revenue credits.
Read this passage

A. No. The Formula Rate Implementation Protocols already require LSPGC to provide

printed heading

The Formula Rate Implementation Protocols already require LSPGC to provide 17 supporting documentation for data used in the Formula Rate that are not stated in the 18 FERC Form No. 1, and to include a variance analysis of revenue credits with an 19 explanation of material changes, which will…
Read this passage

VII. ILLUSTRATIVE EXHIBITS

printed heading

VII.
Read this passage

A. Exhibit No. LSC-201 is LSPGC’s currently effective Formula Rate Template populated

printed heading

LSC-201 is LSPGC’s currently effective Formula Rate Template populated 3 with hypothetical data for the 2030 Rate Year to illustrate the treatment of a Covered 4 Upgrade.
Read this passage

A. Exhibit No. LSC-202 illustrates the TRBA and TRBAA calculation for two consecutive

printed heading

LSC-202 illustrates the TRBA and TRBAA calculation for two consecutive 14 TRBA years ending September 30, 2030 and 2031, using the Supplemental MTRC from 15 Exhibit No.
Read this passage

VIII. CONCLUSION

printed heading

WHY ARE THE PROPOSED REVISIONS JUST AND REASONABLE? 19
Read this passage

A. The revisions implement the Commission’s direction that large load payments be credited

printed heading

The revisions implement the Commission’s direction that large load payments be credited 20 toward transmission owners’ revenue requirements, using LSPGC’s existing TRBAA 21 mechanism.
Read this passage

A. Yes.

printed heading

Yes. 6 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION LS Power Grid California, LLC California Independent System Operator Corporation ) ) Docket No.
Read this passage

D. Eric Arzola

printed heading

LSC-201 Illustrative Formula Rate Template (Excel) Ex.
Read this passage

CERTIFICATE OF SERVICE