ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others
Att G Pro Forma Facilities Study Agreement
PDF page 1
Attachment G
Pro Forma Facilities Study Agreement
PDF page 2
44.16.8 Appendix 8 to Attachment LL – Pro Forma Facilities Study Agreement
PRO FORMA FACILITIES STUDY AGREEMENT
BETWEEN
[TRANSMISSION OWNER LEGAL NAME]
(Transmission Owner)
AND
[LARGE LOAD CUSTOMER LEGAL NAME]
(Large Load Customer)
[Project Name] – NYISO Queue No. [_____]
PDF page 3
TABLE OF CONTENTS
Recitals
Section 1.0: Definitions
Section 2.0: Performance of Facilities Study
Section 3.0: Scope of Work
Section 4.0: Contents of Facilities Study
Section 5.0: Point of Change in Ownership
Section 6.0: Large Load Customer’s Responsibilities
Section 7.0: Study Deposit
Section 8.0: Study Costs and Invoicing
Section 9.0: Payment, Refunds and Disputed Amounts
Section 10.0: Modifications; Mandated Changes
Section 11.0: Scope of Agreement; Subsequent Agreements
Section 12.0: Draft Report
Section 13.0: Comments and Final Report
Section 14.0: Limitation of Liability
Section 15.0: Term and Termination
Section 16.0: Confidentiality
Section 17.0: Subcontractors or Agents
Section 18.0: Notices
Section 19.0: Governing Law; Regulatory Authority
Section 20.0: Reservation of Rights
Section 21.0: Miscellaneous
Exhibit A: Information and Required Data to Be Provided by Large Load Customer Exhibit B: Description of Scope of Work Performed During Facilities Study Exhibit C: Description of Schedule and Cost Estimate for the Facilities Study Exhibit D: Preliminary Point of Change in Ownership
PDF page 4
PRO FORMA
FACILITIES STUDY AGREEMENT
[Project Name] – NYISO Queue No. [_____]
This FACILITIES STUDY AGREEMENT (this “Agreement”) is made and entered into as of this [___] day of [_______], 20[__] (the “Effective Date”) by and between [TRANSMISSION OWNER LEGAL NAME], a [corporation] organized and existing under the laws of the State of New York, acting in its capacity as either the Connecting Transmission Owner (“CTO”) or an Affected Transmission Owner (“ATO”), as applicable, and hereinafter referred to as the “Transmission Owner,” and [LARGE LOAD CUSTOMER LEGAL NAME], a [entity type]
organized and existing under the laws of the State of [_____], hereinafter referred to as the “Large Load Customer.” Transmission Owner and Large Load Customer may be referred to herein individually as a “Party” and collectively as the “Parties.”
RECITALS
WHEREAS, Transmission Owner owns, operates, or has responsibility for certain transmission facilities that form part of the New York State Transmission System, including the [[___] kilovolt (“kV”) [_____] transmission line or the [_____] Substation located at [Utility Facility Location]] (collectively, the “Transmission Owner Facilities”);
WHEREAS, Large Load Customer is proposing to develop a Large Load Project of approximately [___] megawatts (“MW”), together with associated Large Load Customer-owned substation facilities, located at [Project Site], [_____] County, New York (the “Large Load Project”), consistent with the Large Load Integration Request submitted by Large Load Customer to the New York Independent System Operator, Inc. (“NYISO”) and designated [Queue No. _____]; WHEREAS, Large Load Customer desires to interconnect the Large Load Project with the New York State Transmission System at the Transmission Owner Facilities;
WHEREAS, NYISO performed a System Impact Study and is expected to complete and provide the results of the Assessment of Load Integration Report (“ALI”) to the Parties, and the ALI is expected to identify certain violations and needs to the Transmission Owner Facilities and related facilities;
WHEREAS, Large Load Customer has requested that Transmission Owner perform, or cause to be performed, a facilities study in two parts, with Part 1 addressing the local Network Upgrades and Transmission Owner Attachment Facilities and proceeding in parallel with the ALI, and potentially Part 2 addressing non-local Network Upgrades and coordination and alignment with ALI results after NYISO provides them, in each case to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to complete the Network Upgrades and any Transmission Owner Attachment Facilities; and
WHEREAS, the Parties intend that the results of the Facilities Study will define the Large Load Project to a level sufficient to permit the Parties to negotiate one or more subsequent agreements
PDF page 5
with preliminary scope, cost and schedule before detailed design, material ordering and construction begin.
NOW, THEREFORE, in consideration of the mutual covenants contained herein, and other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Parties, intending to be legally bound, agree as follows:
1.0
Definitions. When used in this Agreement with initial capitalization, the terms specified shall have the meanings indicated herein or, if not defined herein, the meanings specified in Section 1 of the NYISO Open Access Transmission Tariff (“OATT”) or Section 44.1 of Attachment LL to the OATT, as applicable. “Good Utility Practice” and “Applicable Laws and Regulations” have the meanings given in the OATT. If there is a conflict between this Agreement and the OATT or Attachment LL, the latter shall control to the extent required by Applicable Laws and Regulations.
2.0
Performance of Facilities Study. Large Load Customer elects, and Transmission Owner shall cause, a facilities study (the “Facilities Study”) to be performed in accordance with this Agreement, the applicable criteria, guidelines, standards, specifications, policies, procedures and practices of the North American Electric Reliability Corporation (“NERC”), the Northeast Power Coordinating Council (“NPCC”), the New York State Reliability Council (“NYSRC”), NYISO, Transmission Owner, and Good Utility Practice. 3.0
Scope of Work. The scope of the Facilities Study, including the review of local and non- local Network Upgrades and Transmission Owner Attachment Facilities identified as of the Effective Date, is set forth in Exhibit B (the “Scope of Work”) and shall be subject to the data provided by Large Load Customer in Exhibit A and to information provided by NYISO, including ALI results. Each Party accepts the Scope of Work and acknowledges that it is consistent with such Party’s applicable standards, specifications, requirements and practices. Any material change in scope shall be addressed under Sections 7.0, 8.0 and 10.0.
3.1
Dynamic Nature of the Facilities Study. Due to the dynamic nature of the Transmission System and because the Facilities Study will be performed in parallel with the ALI, additional violations and needs may be identified as the ALI and Transmission Owner’s analyses progress. The Facilities Study and any draft Facilities Study report may be updated to incorporate additional Network Upgrades and Transmission Owner Attachment Facilities within the categories described in Exhibit B without amendment of this Agreement, and the time for completion of the Facilities Study shall be extended by a period commensurate with any such update. Any such update shall be performed as additional work at Large Load Customer’s expense pursuant to Sections 8.0 and 10.0 of this Agreement.
3.2
Additional Studies. Additional studies beyond the scope of this Agreement, including special studies and detailed design studies (such as harmonic analyses or electromagnetic transient studies), may be required to interconnect the Large Load Project, including after completion of the Facilities Study. Transmission owners who are not a party to this Agreement may need to conduct studies beyond the scope of this Agreement based on the impact of the Large Load Project on the Transmission Owner’s Transmission System. Any
PDF page 6
such additional studies, and any Network Upgrades identified through them, shall be at Large Load Customer’s expense.
3.3
Planning Purposes Only. The work performed under this Agreement is for planning and estimation purposes only. Nothing in this Agreement obligates Transmission Owner to construct any Network Upgrades and/or Transmission Owner Attachment Facilities or to interconnect or provide service to the Large Load Project, guarantees any interconnection or service, or reserves for Large Load Customer any capacity, queue position, or priority. Any interconnection or service shall be governed by separate agreement(s) and applicable regulatory requirements.
3.4
Restudy. If Large Load Customer requests a material modification to the Large Load Project in accordance with Section 44 of Attachment LL (e.g., an increase in the requested load or a change to the proposed operating characteristics) such that restudy is required, the restudy shall be performed as additional work at Large Load Customer’s expense pursuant to Sections 8.0 and 10.0 of this Agreement and Section 44 of Attachment LL. The final design of the Large Load Project must comply with all federal, regional, state, and local regulations as well as all applicable criteria, guidelines, standards, specifications, policies, procedures and practices of Transmission Owner, and Good Utility Practice. 3.5
Accuracy of Information. Except as Large Load Customer may otherwise specify in writing when it provides information to Transmission Owner under this Agreement, Large Load Customer represents and warrants that to the best of its knowledge and belief the information it has provided or subsequently provides to Transmission Owner is and shall be accurate and complete as of the date the information is provided. Large Load Customer shall promptly provide Transmission Owner with any additional information needed to update information previously provided.
3.6
Disclaimer of Warranty. In performing the Facilities Study or restudy, Transmission Owner and any subcontractors and/or consultants engaged by Transmission Owner will have to rely on information provided by Large Load Customer, and possibly by third parties, and may not have control over the accuracy of such information. Accordingly, neither Transmission Owner nor any subcontractor or consultant engaged by Transmission Owner makes any warranties, express or implied, whether arising by operation of law, course of performance or dealing, custom, usage in the trade or profession, or otherwise, including without limitation implied warranties of merchantability and fitness for a particular purpose, with regard to the accuracy, content, or conclusions of the Facilities Study or restudy. Large Load Customer acknowledges that it has not relied on any representations or warranties by Transmission Owner or its subcontractors or consultants not specifically set forth herein and that no such representations or warranties have formed the basis of its bargain hereunder.
4.0
Contents of Facilities Study. The Facilities Study shall specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the ALI and any other applicable NYISO study or process, as of the Effective Date of this Agreement, and to construct the local and non- local Network Upgrades and Transmission Owner Attachment Facilities. The Facilities Study shall also identify: (1) the scope and estimated cost of the Network Upgrades and any Transmission Owner Attachment Facilities; (2) an estimate of the time required to
PDF page 7
complete the construction and installation of such facilities; (3) the preliminary one-line diagram reflecting the preliminary understanding of the Point of Change in Ownership and the Point of Interconnection as reflected in Exhibit D, as of the Effective Date of this Agreement; and (4) the assumptions and exclusions necessary to develop the cost of the Network Upgrades and any Transmission Owner Attachment Facilities. For each Network Upgrade associated with a violation to which more than one Large Load Project in a [Cluster] contributes, the Facilities Study shall identify the allocation of upgrade costs on an upgrade-specific basis, using the contribution factors NYISO identified in the ALI for [Bulk Electric System] violations and the contribution factors Transmission Owner determined for non-[Bulk Electric System] violations.
5.0
Point of Change in Ownership. As applicable, the Parties’ preliminary understanding of the point at which ownership of facilities changes from Transmission Owner to Large Load Customer (the “Point of Change in Ownership”) is set forth in Exhibit D. The Point of Change in Ownership is preliminary and non-binding, and shall be confirmed or revised in the Facilities Study and in any subsequent interconnection, cost recovery, security, or transmission service agreements.
6.0
Large Load Customer’s Responsibilities. Exhibit A contains the tasks, forms, and drawings that must be completed and provided by Large Load Customer to Transmission Owner, and the time by which each must be provided, to ensure accurate and timely completion of the Facilities Study under this Agreement. Failure by Large Load Customer to provide accurate, complete, and on-time responses to the requests made by Transmission Owner, including but not limited to those made in Exhibit A, may result in delays to the completion of the Facilities Study and/or an increase in study costs pursuant to Section 8.0, and may result in termination of this Agreement under Section 15.0 and withdrawal of the Large Load Project, subject to applicable tariff requirements.
7.0
Study Deposit. Large Load Customer shall provide to Transmission Owner a deposit in the amount set forth in Exhibit C (the “Study Deposit”) within ten (10) Business Days after execution of this Agreement and, in all events, before Transmission Owner begins study work. Transmission Owner shall not be obligated to begin or continue the Facilities Study until it has received the Study Deposit and any supplemental deposit required under this Agreement. If Large Load Customer does not provide the Study Deposit within ten (10) Business Days after execution of this Agreement, the Large Load Project shall be subject to withdrawal, without a withdrawal cure period. If Exhibit C is revised under Sections 8.0 or 10.0, Large Load Customer shall pay any supplemental deposit reasonably requested by Transmission Owner within ten (10) Business Days after notice, subject to any applicable tariff or deadline of the Federal Energy Regulatory Commission (“FERC”). 8.0
Study Costs and Invoicing. Study costs shall be based on Transmission Owner’s actual, documented and reasonably incurred costs, including applicable taxes and overheads, and shall be invoiced to Large Load Customer periodically. Large Load Customer acknowledges that the estimated rates and amounts in Exhibit C are estimates only, are not an exhaustive list of charges, and that Large Load Customer shall pay the actual costs incurred by Transmission Owner under this Agreement. Transmission Owner shall provide reasonable periodic status updates and shall notify Large Load Customer promptly, and before incurring material additional costs where practicable, if it anticipates that actual
PDF page 8
costs will exceed the Study Deposit by more than thirty percent (30%). The notice shall include the reasons for the variance, a revised estimate, and any proposed schedule impact. The Parties shall address the resulting supplemental deposit or scope change under Sections 7.0 and 10.0.
9.0
Payment, Refunds and Disputed Amounts. Transmission Owner shall issue a final invoice after delivery of the final Facilities Study report or, if this Agreement terminates earlier, within thirty (30) Calendar Days after termination. Large Load Customer shall pay all invoiced amounts in excess of the Study Deposit within thirty (30) Calendar Days after receipt of the invoice. If the Study Deposit exceeds the final invoiced amounts, Transmission Owner shall refund the excess within thirty (30) Calendar Days after issuing the final invoice, without interest. If Large Load Customer disputes an invoice, it shall provide written notice describing the basis of the dispute within ten (10) Business Days after receipt, and the dispute shall be resolved in accordance with Section 9.1. A dispute shall not delay payment of undisputed amounts. Transmission Owner may suspend study work after notice if Large Load Customer fails to pay undisputed amounts or a required supplemental deposit when due, subject to applicable tariff requirements. 9.1
Dispute Resolution. The Parties shall attempt in good faith to resolve any dispute arising under this Agreement through negotiation between senior representatives for a period of [thirty (30)] Calendar Days after written notice of the dispute. Disputes not so resolved may be pursued [under the dispute resolution procedures of the NYISO OATT] or before FERC, the New York State Public Service Commission, or a court of competent jurisdiction, as applicable to the subject matter of the dispute. Pending resolution, each Party shall continue to perform its obligations under this Agreement, Large Load Customer shall pay all undisputed amounts in accordance with Section 9.0, and Large Load Customer shall pay any disputed amount to Transmission Owner or into a non-interest-bearing escrow account mutually acceptable to the Parties. Upon resolution of the dispute, the disputed amount shall be retained by or released to the Party in whose favor the dispute is resolved, without interest.
10.0
Modifications; Mandated Changes. Neither Party shall change, modify, adjust or alter its responsibilities under this Agreement or the Exhibits without the prior written consent of the other Party; provided, however, that such consent shall not be required to the extent the change is necessary to comply with (i) a change in Good Utility Practice made after the Effective Date, (ii) a change in Applicable Laws and Regulations promulgated after the Effective Date, (iii) any change in Transmission Owner’s procedures, policies, standards, or business practices, or (iv) a new or modified final directive, order, standard, requirement, rule or other action of a Governmental Authority having jurisdiction issued after the Effective Date (each, a “Mandated Change”). The Party required to make a Mandated Change shall notify the other Party in writing within fifteen (15) Business Days after it first becomes aware of the need for the Mandated Change, or sooner if required to comply timely with Applicable Laws and Regulations, together with its expected effect on study cost, scope, or schedule. The Parties shall cooperate in good faith to implement the Mandated Change without impairing compliance with the OATT or applicable NYISO requirements.
PDF page 9
11.0
Scope of Agreement; Subsequent Agreements. This Agreement is an agreement to perform a study only. It is not an agreement to provide or take utility services of any kind, including, without limitation, interconnection or other electric transmission or delivery service, and it does not provide for the procurement of goods, materials or equipment or for installation or construction services. Any engineering, procurement, construction, or interconnection of the Large Load Project shall be governed by one or more separate agreements, which may include a Security Agreement, [an applicable Transmission Service Agreement], a Network Upgrade Cost Recovery Agreement, an engineering and procurement agreement, and/or an interconnection agreement.
12.0
Draft Report. Upon completion of the Facilities Study, Transmission Owner shall prepare and promptly transmit a draft Facilities Study report to Large Load Customer. Within ten
(10) Calendar Days after providing the draft report, the Parties may meet to discuss the results of the Facilities Study.
13.0
Comments and Final Report. Large Load Customer may, within ten (10) Business Days after receipt of the draft report, provide written comments for Transmission Owner’s consideration. Transmission Owner shall consider the comments in good faith but shall not be required to accept or include every comment in the final report. Transmission Owner shall issue the final Facilities Study report within fifteen (15) Business Days after receiving Large Load Customer’s comments or promptly after receiving Large Load Customer’s statement that it will not provide comments. If Large Load Customer does not provide written comments within ten (10) Business Days after receiving the draft report, Transmission Owner shall be authorized to issue the final Facilities Study report. Transmission Owner may reasonably extend that period on notice to Large Load Customer if the comments require additional analyses or other significant modifications, and shall provide a revised issuance date. Any unresolved issue shall be resolved in accordance with Section 9.1.
14.0
Limitation of Liability. Except for a Party’s payment obligations, breach of confidentiality or Critical Energy/Electric Infrastructure Information (“CEII”) obligations, fraud, gross negligence, willful misconduct, violation of Applicable Laws and Regulations, or obligations under an express indemnity, in no event, whether as a result of breach of contract, tort (including negligence and strict liability) or otherwise, shall either Party be liable in connection with this Agreement for any special, indirect, incidental, penal, punitive or consequential damages of any nature, including delays, lost profits, business interruptions and claims of suppliers and customers, whether or not such damages were reasonably foreseeable or such Party was advised that such damages might be incurred. Nothing in this Section limits FERC’s authority or liability that cannot lawfully be limited. 15.0
Term and Termination. This Agreement shall become effective on the Effective Date and shall remain in effect until the earliest of (i) issuance of the final Facilities Study report and payment of all amounts due under this Agreement, (ii) withdrawal or cancellation of the Large Load Integration Request or the Large Load Project, (iii) termination by Large Load Customer on written notice, (iv) termination by Transmission Owner for Large Load Customer’s failure to pay an undisputed amount or required supplemental deposit within five (5) Business Days after written notice, (v) termination by Transmission Owner for Large Load Customer’s failure to provide information required under Section 6.0 or
PDF page 10
Exhibit A within ten (10) Business Days after written notice of such failure, (vi) termination by Transmission Owner for Large Load Customer’s failure to timely post the security required, based on the Facilities Study, under Attachment LL or any applicable Security Agreement, or (vii) termination by mutual written consent of the Parties. Upon termination, Large Load Customer shall pay all costs incurred by Transmission Owner through the date of termination, together with reasonable costs of winding down the study work, and any remaining balance of the Study Deposit shall be refunded in accordance with Section 9.0. Termination or default of this Agreement by Large Load Customer for any reason shall not waive Large Load Customer’s rights under the OATT, Attachment LL, or Applicable Laws and Regulations. Sections 3.3, 3.6, 8.0, 9.0, 9.1, 14.0, 16.0, 19.0, and 21.0 shall survive expiration or termination.
16.0
Confidentiality. Information exchanged under this Agreement that is designated confidential by the disclosing Party, or that reasonably should be understood to be confidential given its nature and the circumstances of disclosure, shall be treated as confidential information, used only for purposes of this Agreement, and disclosed only to personnel, advisors, contractors, subcontractors, vendors, agents, or Governmental Authorities with a need to know and subject to appropriate confidentiality obligations. These obligations shall not apply to information that is publicly available through no breach, already lawfully known, independently developed without use of the information, or lawfully received from a third party without a duty of confidentiality, or to disclosure required by Applicable Laws and Regulations, provided that the receiving Party gives advance notice where legally permitted. CEII shall be protected and disclosed only as permitted by 18 C.F.R. § 388.113, the OATT, applicable NYISO procedures, and any FERC order. Transmission Owner may require Large Load Customer and its contractors, subcontractors, vendors, or agents to execute a separate non-disclosure agreement as a condition of receiving confidential information or CEII, and nothing in this Agreement shall limit, modify, or supersede any such non-disclosure agreement. If this Section conflicts with those requirements, the applicable law, regulation, tariff, procedure, or order shall control.
17.0
Subcontractors or Agents. Nothing in this Agreement shall prevent a Party from using contractors, subcontractors, vendors, or agents as it deems appropriate to perform its obligations hereunder; provided that each Party shall require its contractors, subcontractors, vendors, or agents to comply with the applicable terms of this Agreement, including the confidentiality obligations of Section 16.0 and any non-disclosure agreement required by Transmission Owner thereunder, and shall remain primarily liable for their performance. The creation of a subcontract shall not relieve the hiring Party of any obligation under this Agreement; provided, however, that in no event shall Transmission Owner be liable for the actions or inactions of Large Load Customer or its contractors, subcontractors, vendors, or agents with respect to Large Load Customer’s obligations under this Agreement. These obligations shall not be limited by any limitation of a contractor’s, subcontractor’s, vendor’s, or agent’s insurance.
18.0
Notices. Any notice under this Agreement shall be in writing and shall be hand delivered, sent by registered or certified mail, delivered by reputable overnight courier, or sent by email with electronic confirmation of receipt, to the following representatives, or to such other representative as a Party may designate by notice. A notice is effective upon delivery
PDF page 11
or, for email, upon electronic confirmation of receipt, provided that a notice received after 5:00 p.m. Eastern Time or on a non-Business Day is deemed received on the next Business Day.
If to Transmission Owner: [Name], [Title], [Address], [Email]
If to Large Load Customer: [Name], [Title], [Address], [Email]
19.0
Governing Law; Regulatory Authority. The validity, interpretation and enforcement of this Agreement shall be governed by the laws of the State of New York, without regard to its conflicts of law principles. This Agreement is subject to all Applicable Laws and Regulations, the OATT, Attachment LL, and applicable NYISO requirements. To the extent of a conflict, the Federal Power Act, FERC orders and regulations, the OATT, Attachment LL, and mandatory NYISO requirements shall control. Each Party reserves the right to seek changes in, appeal or otherwise contest any laws, orders or regulations of a Governmental Authority.
20.0
Reservation of Rights. Nothing in this Agreement shall alter the right of Transmission Owner to make unilateral filings with FERC to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under Section 205 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations, or the existing rights of Large Load Customer to make a unilateral filing with FERC to modify this Agreement under any applicable provision of the Federal Power Act; provided that each Party shall have the right to protest any such filing by the other Party and to participate fully in any related proceeding. Nothing in this Agreement shall limit the rights of the Parties or of FERC under Sections 205 or 206 of the Federal Power Act, except to the extent the Parties otherwise agree herein.
21.0
Miscellaneous.
21.1
Amendment; Waiver. This Agreement may be amended, superseded or modified by a written instrument executed by both Parties, except for a Mandated Change under Section 10.0 or a change required by Applicable Laws and Regulations, the OATT, a FERC order, or a mandatory NYISO requirement. No waiver shall be effective unless in writing and signed by the Party against whom it is sought to be enforced. The failure of a Party to insist on strict performance on any occasion shall not be a waiver, and no waiver of any breach shall be a continuing waiver or a waiver of any other breach.
21.2
No Third-Party Beneficiaries. This Agreement does not create rights, remedies or benefits in favor of any person other than the Parties and their successors in interest and, where permitted, their assigns.
21.3
No Partnership. This Agreement shall not be construed to create an association, joint venture, agency relationship or partnership between the Parties, and neither Party shall have authority to bind the other.
21.4
Assignment. Neither Party may assign this Agreement without the prior written consent of the other Party, which consent shall not be unreasonably withheld, conditioned or delayed; provided that either Party may assign this Agreement to an
PDF page 12
Affiliate on notice, so long as the assignee assumes in writing all obligations under this Agreement, the assignment does not impair compliance with the OATT or Applicable Laws and Regulations, and the assigning Party remains responsible unless the other Party agrees otherwise in writing.
21.5
Severability. If any provision of this Agreement is held invalid, illegal or unenforceable by a court or Governmental Authority of competent jurisdiction, (a) such provision shall be deemed separate and independent, (b) the Parties shall negotiate in good faith to restore as nearly as practicable the benefits affected, and
(c) the remainder of this Agreement shall remain in full force and effect. 21.6
Entire Agreement. This Agreement, including its Exhibits, constitutes the entire agreement between the Parties with respect to its subject matter and supersedes all prior discussions and understandings with respect thereto.
21.7
Authority. Each Party represents that the signatory identified beneath its name has full authority to execute this Agreement on its behalf.
21.8
Counterparts; Electronic Signatures. This Agreement may be executed in counterparts, each of which shall be deemed an original and all of which together constitute one instrument. Signatures delivered by facsimile or other electronic means (including e-mailed PDF) shall be deemed original signatures for all purposes.
21.9
Force Majeure. “Force Majeure” means any event or circumstance beyond a Party’s reasonable control that prevents the Party from performing an obligation, is not the result of the negligence or intentional wrongdoing of such Party, and could not have been prevented or mitigated by the exercise of Good Utility Practice (in the case of Transmission Owner) or due diligence (in the case of Large Load Customer), including acts of God, fire, flood, storm, lightning, explosion, breakage of or accident to machinery, epidemic or pandemic, cyber-attack (except to the extent caused by or resulting from Large Load Customer’s failure to comply with its obligations under this Agreement), sabotage, terrorism, war, civil disturbance, strikes and labor disturbances, acts or orders of any Governmental Authority, and curtailment or interruption directed by NYISO for reliability reasons. Force Majeure shall not include, with respect to Large Load Customer: (a) economic hardship, changes in market conditions, or the cost or unavailability of financing;
(b) delays in Large Load Customer’s procurement of equipment or failure of Large Load Customer’s suppliers or contractors, unless caused by an independent Force Majeure event; (c) labor disputes involving only Large Load Customer’s or its contractors’ workforce; (d) Large Load Customer’s failure to obtain required permits or approvals, unless it has diligently and timely pursued them; or (e) changes in the demand for, or the business case of, the Large Load Project’s end use. Interruptions resulting from the Single Contingency Design shall not be treated as Force Majeure. Force Majeure shall not excuse the failure to make payments when due or to timely post or maintain the Financial Security.
21.10 Effect of Force Majeure. A Party shall be excused from performance (other than the obligation to pay money when due) to the extent prevented by Force Majeure,
PDF page 13
provided it gives prompt notice with full particulars (confirming any telephone notice in writing), keeps the other Party informed, and exercises due diligence to remedy the effects with reasonable dispatch. A Party shall not be required to settle a labor dispute on terms unsatisfactory to it.
IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their duly authorized representatives as of the Effective Date.
[TRANSMISSION OWNER]
By: ______________________________
Name: ______________________________
Title: ______________________________
Date: ______________________________
[LARGE LOAD CUSTOMER]
By: ______________________________
Name: ______________________________
Title: ______________________________
Date: ______________________________
PDF page 14
EXHIBIT A
Information and Required Data to Be Provided by Large Load Customer
[Transmission Owner to insert its TO-specific study data request form and drawing requirements (the “Study Data Package”).]
PDF page 15
EXHIBIT B
Description of Scope of Work Performed During Facilities Study
[Transmission Owner to insert its TO-specific Scope of Work for Part 1 and Part 2 of the Facilities Study, including the ALI-identified Network Upgrades and Transmission Owner Attachment Facilities to be studied.]
PDF page 16
EXHIBIT C
Description of Schedule and Cost Estimate for the Facilities Study
Study schedule. Transmission Owner shall use reasonable efforts to complete the Facilities Study within twelve (12) months, consisting of six (6) months for the study of Transmission Owner Attachment Facilities and local Network Upgrades and six (6) months for the study of non-local Network Upgrades. The twelve (12)-month study period shall commence on the later of (i) Transmission Owner’s receipt of the Study Deposit or (ii) Transmission Owner’s determination that the Study Data Package is complete. If Transmission Owner determines that the Facilities Study cannot be completed within the applicable twelve (12)-month study period, Transmission Owner shall notify Large Load Customer and provide an explanation for the delay and a revised estimated completion date.
Study Deposit. Based on the size of the Large Load Project, as follows: 50 MW to 199 MW – $300,000; 200 MW to 499 MW – $350,000; 500 MW and above – $400,000. The Study Deposit shall be paid at the time and in the manner provided in Section 7.0, and shall be subject to supplemental deposit, final invoicing, and refund under Sections 7.0, 8.0, and 9.0. Estimated rates. [Transmission Owner to insert.] All rates are estimates and subject to adjustment. Large Load Customer shall pay all actual, documented and reasonably incurred costs, including applicable taxes and overheads, incurred by Transmission Owner under this Agreement, as provided in Sections 8.0 and 9.0.
PDF page 17
EXHIBIT D
Preliminary Point of Change in Ownership
Preliminary Point of Change in Ownership. The Point of Change in Ownership is preliminarily expected to be located at [_______] [within the footprint of the proposed Large Load Project substation]. Transmission Owner, as applicable to the CTO or ATO facilities, is expected to own [the ___ kV transmission line from the Point of Interconnection at the [_____] Substation to the proposed Large Load Project substation]. Large Load Customer will own all facilities on its side of the Point of Change in Ownership. The ownership allocation is preliminary and shall be confirmed in the Facilities Study and the applicable subsequent agreements.