ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others
Att H Pro Forma LL Interconnection Agreement
PDF page 1
Attachment H
Pro Forma Large Load Interconnection Agreement
PDF page 2
44.16.11 Appendix 11 to Attachment LL – Pro Forma Interconnection Agreement
[TRANSMISSION OWNER] SERVICE AGREEMENT NO. [●]
PRO FORMA LARGE LOAD INTERCONNECTION
AGREEMENT
BETWEEN
[LEGAL NAME OF TRANSMISSION OWNER]
(Transmission Owner)
AND
[LEGAL NAME OF CUSTOMER]
(Customer)
Dated as of [●]
PDF page 3
TABLE OF CONTENTS
Recitals
Article 1: Definitions
Article 2: Effective Date, Term, and Termination
Article 3: Scope of Interconnection Service
Article 4: Conditions to Energization and Permission to Operate Article 5: Engineering, Procurement, and Construction Article 6: Cost Responsibility, Security, and Payment Article 7: Operations
Article 8: Emergencies
Article 9: Metering and Telemetry
Article 10: Testing and Inspection
Article 11: Maintenance
Article 12: Modifications
Article 13: Information Requirements
Article 14: Regulatory Requirements and Governing Law Article 15: Notices
Article 16: Force Majeure, Breach, and Default
Article 17: Indemnity, Limitation of Liability, and Consequential Damages Article 18: Insurance
Article 19: Confidentiality
Article 20: Dispute Resolution
Article 21: Representations and Warranties
Article 22: Assignment
Article 23: Miscellaneous
• Exhibit A: Large Load Project and Customer Attachment Facilities
• Exhibit B: Point(s) of Interconnection and Point(s) of Change of Ownership, TO Attachment Facilities, and Network Upgrade Facilities
PDF page 4
• Exhibit C: Simplified One-Line Diagram
• Exhibit D: Milestones
• Exhibit E: Operating Requirements
• Exhibit F: Conditions to Initial Energization and Parallel Operation
• Exhibit G: Cost Recovery, Security, and Related Agreements
• Exhibit H: Form of Commercial Operation Date Notice
• Exhibit I: Addresses for Notices and Billings
PDF page 5
PRO FORMA
LARGE LOAD INTERCONNECTION AGREEMENT
This LARGE LOAD INTERCONNECTION AGREEMENT (this “Agreement”) is made and
entered into as of [Date] (the “Execution Date”) by and between [LEGAL NAME OF TRANSMISSION OWNER], a [New York corporation / municipal instrumentality / public benefit corporation] organized and existing under the laws of the State of New York, with offices at [Address] (“Transmission Owner” or “TO”), and [LEGAL NAME OF CUSTOMER], a [entity type and jurisdiction], with offices at [Address] (“Customer”). Transmission Owner and Customer are each referred to herein as a “Party” and collectively as the “Parties.” RECITALS
WHEREAS, Transmission Owner owns and operates, among other things, electric transmission facilities that form part of the New York State Transmission System, provides transmission service over such facilities through the New York Independent System Operator, Inc. (“NYISO”) pursuant to the Tariff on file with FERC, and [provides electric delivery service pursuant to its retail tariff on file with the NYPSC];
WHEREAS, Customer intends to design, construct, own, operate, and maintain a large load facility, together with the associated Customer Attachment Facilities, located at [Site Address] (the “Load Facility”), as more particularly described in Exhibit A;
WHEREAS, Customer has requested that the Load Facility be interconnected to Transmission Owner’s transmission system at the Point of Interconnection identified in Exhibit B, with a Maximum Load Facility Peak Demand of [●] MW;
WHEREAS, Transmission Owner, alone or in coordination with NYISO, has conducted or will conduct a System Impact Study, a Facilities Study, and such other engineering, detailed design, and special studies as are required by Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility Practice to determine the effect of the Load Facility on the TO System and the New York State Transmission System and the need, if any, for TO Attachment Facilities and the Customer Attachment Facilities and Network Upgrades[, and the Parties have entered into or will enter into a Cost Recovery Agreement dated [●] with respect to the Network Upgrades and TO Attachment Facilities determined to be necessary as a result of such studies]; WHEREAS, Transmission Owner will design, construct, own, operate, and maintain the TO Attachment Facilities and, if applicable, the Network Upgrades, and Customer will design, construct, own, operate, and maintain the Customer Attachment Facilities, in each case at Customer’s cost to the extent provided in this Agreement or the Cost Recovery Agreement; and WHEREAS, the Parties wish to set forth the terms and conditions under which the Load Facility will be interconnected with, and operated in parallel with, the transmission system. NOW, THEREFORE, in consideration of the mutual covenants and agreements set forth herein, and intending to be legally bound, the Parties agree as follows:
PDF page 6
ARTICLE 1
DEFINITIONS
Whenever used in this Agreement with initial capitalization, the following terms have the meanings specified in this Article 1. Capitalized terms used but not defined in this Agreement have the meanings given in the Tariff or the NYISO Services Tariff, as applicable. 1.1
“Affiliate” means, with respect to a person or entity, any other person or entity directly or indirectly controlling, controlled by, or under common control with such person or entity. “Control” means the possession, directly or indirectly, of the power to direct the management or policies of a person or entity; a voting interest of ten percent (10%) or more creates a rebuttable presumption of control. 1.2
“Applicable Laws and Regulations” means all duly promulgated or issued applicable federal, state, and local laws, treaties, statutes, regulations, rules, ordinances, codes, decrees, judgments, permits, licenses, approvals, directives, and judicial, executive, or administrative orders of any Governmental Authority, including Environmental Law and the NYISO tariffs, manuals, and technical bulletins, in each case as amended from time to time.
1.3
“Applicable Reliability Standards” means the requirements and guidelines of NERC, NPCC, and NYSRC, and of the transmission district to which the Load Facility is directly interconnected, as amended from time to time; provided that no Party waives its right to challenge the applicability or validity of any such requirement or guideline as applied to it.
1.4
“Attachment Facilities” means all facilities and equipment between the Load Facility and the Point of Interconnection, including any modifications, additions, or upgrades that are necessary to physically and electrically interconnect the Load Facility to the New York State Transmission System. Attachment Facilities are sole use facilities and shall not include Network Upgrades. Attachment Facilities may include equipment (e.g., metering) necessary for the entity authorized to serve load within a Transmission District, if Transmission Owner is not the entity authorized to serve that load.
1.5
“Breach” means the failure of a Party to perform any material term, condition, or obligation of this Agreement, and “Breaching Party” means the Party that has committed a Breach.
1.6
“Business Day” means Monday through Friday, excluding federal holidays and [TO holidays].
1.7
“Calendar Day” means any day, including Saturday, Sunday, or a federal holiday. 1.8
“Commercial Operation” means the status of the Load Facility once (a) the Load Facility has successfully completed testing and commissioning in accordance with this Agreement and the Operating Documents; (b) the In-Service Date has occurred for the TO Attachment Facilities and Network Upgrades, and the Customer Attachment Facilities have been completed, energized, and placed into service, in each case to the extent necessary for the Load Facility to take firm electric service at or above its designated minimum capacity commitment; (c) all conditions
PDF page 7
precedent to Delivery Service have been satisfied; (d) Transmission Owner has issued Permission to Operate; and (e) the Load Facility is in operation. 1.9
“Commercial Operation Date” means the date on which the Load Facility has achieved energization and begins taking firm electric service at or above its designated minimum capacity commitment, as confirmed by notice substantially in the form of Exhibit H.
1.10
“Cost Recovery Agreement” means the [Large Load Cost Recovery Agreement] between Transmission Owner and Customer dated [●], attached as or referenced in Exhibit G, which governs Customer’s responsibility for and payment of the costs of the Network Upgrades and the TO Attachment Facilities, including through the Large Load Upgrade Charge (as defined therein), as amended from time to time. 1.11
“Customer Attachment Facilities” means all facilities and equipment on Customer’s side of the Point of Change of Ownership that are owned or controlled by Customer, including but not limited to breakers, switches, transformers, bus work, cables, relays, System Protection Facilities, communication and telemetry equipment, and associated civil and structural works, as described and shown in Exhibits A and C.
1.12
“Default” means the failure of a Breaching Party to cure a Breach in accordance with Article 16.
1.13
“Delivery Service” means the electric delivery service provided to Customer pursuant to the applicable Tariff, for delivery of energy from the New York State Transmission System to the Load Facility.
1.14
“Emergency State” means a condition or situation that, in the reasonable judgment of a Party or NYISO, (a) presents an imminent threat to the safety of persons or property, or (b) requires automatic or immediate manual action to prevent or limit loss of, or threatens the integrity, reliability, or security of, the TO System or the New York State Transmission System.
1.15
“Environmental Law” means Applicable Laws and Regulations relating to pollution or protection of the environment or natural resources. 1.16
“Exceedance Event” means the Load Facility exceeding the energy or demand stated for the applicable period as further defined in Article 3.7 and Exhibits A and
C. 1.17
“FERC” means the Federal Energy Regulatory Commission or any successor agency.
1.18
“Force Majeure” has the meaning set forth in Article 16.1.
1.19
“Good Utility Practice” means any of the practices, methods, and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods, and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety, and expedition. Good Utility Practice is not intended to be limited to the optimum
PDF page 8
practice, method, or act to the exclusion of all others, but rather to delineate acceptable practices, methods, or acts generally accepted in the region. 1.20
“Governmental Authority” means any federal, state, local, or other governmental, regulatory, or administrative agency, court, commission, department, board, legislature, tribunal, or other governmental authority having jurisdiction over a Party, its facilities, or the services it provides. 1.21
“Hazardous Substances” means any chemical, material, or substance defined as or included in the definition of “hazardous substances,” “hazardous wastes,” “hazardous materials,” “toxic substances,” “pollutants,” “contaminants,” or words of similar meaning and regulatory effect under any Environmental Law. 1.22
“In-Service Date” means the date on which the TO Attachment Facilities and Network Upgrades are energized, as set forth in Exhibit D.
1.23
“Load Ramp Projection” has the meaning set forth in Article 3.5. 1.24
“Material Modification” means any modification to the Load Facility or Customer Attachment Facilities that, in Transmission Owner’s reasonable judgment, may require changes to the TO Attachment Facilities and the Customer Attachment Facilities or Network Upgrades or may otherwise materially affect system reliability, including (a) an increase or decrease in maximum demand beyond levels specified in the Operating Documents; (b) a material change in power factor, ramp rate, or other operating characteristics, including those reported in the NYISO Load Interconnection Data Request; (c) relocation of the Point of Interconnection; or (d) any modification having a material impact on the cost or timing of any interconnection request with a later queue position. 1.25
“Maximum Annual Energy” means the maximum annual energy (in MWh) to be consumed by the Load Facility, as measured at the Point of Interconnection during any calendar year, as set forth in Exhibit A, prorated for any partial calendar year. 1.26
“Maximum Load Facility Peak Demand” means the maximum peak demand for Firm Withdrawal Service of the Load Facility at any time, as set forth in Exhibit A, not to exceed the amount studied in the System Impact Study and Facilities Study. 1.27
“Metering Equipment” means all revenue-quality metering equipment installed or to be installed at or near the Point of Interconnection, including instrument transformers, meters, data acquisition equipment, transducers, remote terminal units, and communications equipment, as specified in Exhibit B.
1.28
“Minimum Committed Load” means [eighty percent (80%)] of the Maximum Load Facility Peak Demand.
1.29
“NERC” means the North American Electric Reliability Corporation, or its successor.
1.30
“Network Upgrades” means additions, modifications, enhancements, or replacements to the TO System or the New York State Transmission System at or beyond the Point of Interconnection, other than TO Attachment Facilities, that are required to accommodate the interconnection of the Load Facility and maintain system reliability, as identified in the System Impact Study, the Facilities Study,
PDF page 9
and such other engineering, detailed design, and special studies, and set forth in Exhibit B.
1.31
“New York State Transmission System” means the entire New York State electric transmission system, including the transmission facilities under NYISO operational control, the transmission facilities requiring NYISO notification, and all remaining transmission facilities within the New York Control Area. 1.32
“NPCC” means the Northeast Power Coordinating Council, Inc., or its successor. 1.33
“NYISO” has the meaning set forth in the Recitals and includes any successor thereto.
1.34
“NYPSC” means the New York State Public Service Commission, or its successor. 1.35
“NYSRC” means the New York State Reliability Council, L.L.C., or its successor. 1.36
“Operating Documents” means the operating requirements developed by Transmission Owner and provided to Customer before initial energization, including those described in Exhibit E, and the Operations Manual described in Article 7.11, in each case as amended from time to time in accordance with this Agreement.
1.37
“Permission to Operate” or “PTO” means the written authorization issued by Transmission Owner permitting Customer to place the Load Facility into Commercial Operation and to take Delivery Service at the Point of Interconnection upon satisfaction of the conditions set forth in Article 4 and Exhibit F. 1.38
“Point of Change of Ownership” or “PCO” means the point described in Exhibit B and shown in Exhibit C.
1.39
“Point of Interconnection” or “POI” means the physical point, described in Exhibit B and shown in Exhibit C, at which the Attachment Facilities connect to the New York State Transmission System.
1.40
“Reasonable Efforts” means, with respect to an action required to be attempted or taken by a Party, efforts that are timely and consistent with Good Utility Practice and are substantially equivalent to those a Party would use to protect its own interests.
1.41
“Related Agreements” means, collectively, the Cost Recovery Agreement, the Security Agreement, and any other agreements listed in Exhibit G. 1.42
“Security Agreement” means the [Large Load Security Agreement] between the Parties dated [●], attached as or referenced in Exhibit G, which governs the posting, maintenance, adjustment, application, and release of the security Customer provides to Transmission Owner for the TO Attachment Facilities and Network Upgrades, as amended from time to time.
1.43
“Single Contingency Design” means a design of the interconnection under which service to the Load Facility may be interrupted upon the loss of a single element of the TO System, as described in Exhibit E.
PDF page 10
1.44
“System Impact Study” or “SIS” means the study performed by NYISO, in coordination with Transmission Owner, under Attachment LL of the Tariff (including the Assessment of Load Integration) to evaluate the impact of the Load Facility on the New York State Transmission System.
1.45
“Facilities Study” means the study performed by or on behalf of Transmission Owner under the facilities study agreement between the Parties to specify and estimate the cost of the TO Attachment Facilities and Network Upgrades, including any updates thereto.
1.46
“System Protection Facilities” means the equipment, including protection signal communications and direct transfer trip equipment, required to protect (a) the New York State Transmission System from faults or other disturbances occurring at the Load Facility and (b) the Load Facility from faults or other disturbances occurring on the New York State Transmission System.
1.47
“Tariff” means the NYISO Open Access Transmission Tariff, including Transmission Owner-specific rate schedules and attachments on file with and accepted by FERC, and, where applicable, Transmission Owner’s retail electric tariff on file with the NYPSC, each as amended from time to time. “NYISO Services Tariff” means the NYISO Market Administration and Control Area Services Tariff.
1.48
“TO Attachment Facilities” means all facilities and equipment owned or controlled by Transmission Owner between the Point of Interconnection and the Point of Change of Ownership that are constructed or modified for the purpose of interconnecting the Load Facility, including line taps, breakers, disconnect switches, bus work, metering instrument transformers (if owned by Transmission Owner), System Protection Facilities at a Transmission Owner substation, and associated civil and structural works, as described and shown in Exhibits B and C. 1.49
“TO Standards” means Transmission Owner’s design criteria, specifications, procedures, policies, guidelines, and requirements for customer interconnections, as provided to Customer and/or referenced in Exhibit B.
1.50
“TO System” means the electric facilities owned or controlled by Transmission Owner, including its transmission system and distribution system. ARTICLE 2
EFFECTIVE DATE, TERM, AND
TERMINATION
2.1
Effective Date. This Agreement shall become effective upon the later of (a) the Execution Date; (b) Customer’s execution and delivery of the Security Agreement and any other agreements listed in Exhibit G; and (c) if Transmission Owner determines that this Agreement must be filed with FERC or the NYPSC, the effective date established upon acceptance of such filing (the “Effective Date”). 2.2
Conditions to Interconnection Activities. The Parties’ obligations to undertake construction, testing, and other interconnection activities are conditioned upon (a)
PDF page 11
completion of the System Impact Study, Facilities Study, and such other engineering, detailed design, and special studies as are required; (b) execution of any related construction or cost reimbursement agreements, the Cost Recovery Agreement, the Security Agreement, and any transmission service agreement required under the applicable Tariff (“TSA”), and receipt of required deposits and advance payments; (c) receipt of all Required Approvals; and (d) completion of the initial Operating Documents. If this Agreement is required to be filed with FERC or the NYPSC, Transmission Owner shall have no obligation to commence engineering, procurement, or construction before acceptance of such filing. 2.3
Term. This Agreement shall remain in effect for [fifteen (15)] years from the Effective Date [or, if longer, the term of the Cost Recovery Agreement] (the “Initial Term”) and shall thereafter automatically renew for successive [five (5)]-year periods unless either Party provides written notice of non-renewal at least one hundred eighty (180) Calendar Days before the end of the then-current term, unless earlier terminated in accordance with this Agreement (the “Term”). Neither Party may deliver a notice of non-renewal while the Cost Recovery Agreement remains in effect.
2.4
Termination. This Agreement may be terminated as follows:
(1) by mutual written agreement of the Parties;
(2) by Customer for any reason upon at least one hundred eighty (180) Calendar Days’ prior written notice, subject to payment of the Net Present Value Residual Charge (as defined in the Cost Recovery Agreement), all amounts owed under this Agreement, the Security Agreement, the Cost Recovery Agreement, and any other related agreements, and confirmation that all amounts owed to NYISO for the Load Facility have been paid; such termination shall constitute an early termination under the Cost Recovery Agreement;
(3) by Transmission Owner upon thirty (30) Calendar Days’ prior written notice if Customer fails to achieve Commercial Operation within twelve
(12) months after Transmission Owner has completed the TO Attachment Facilities and any required Network Upgrades, or such later date as the Parties agree in writing, or if Customer fails to achieve any Customer milestone in Exhibit D by more than one hundred eighty (180) Calendar Days for reasons other than Force Majeure or Transmission Owner’s Breach; provided that such termination shall not relieve Customer of its obligations under Article 2.6, the Cost Recovery Agreement, or the Security Agreement;
(4) by the non-defaulting Party upon a Default in accordance with Article 16; or
(5) by either Party upon thirty (30) Calendar Days’ prior written notice if a Party is prevented by Force Majeure from materially performing its obligations for twelve (12) consecutive months; provided Customer’s termination under this clause shall not relieve Customer of its obligations
PDF page 12
under Article 2.6, the Cost Recovery Agreement, or the Security
Agreement.
2.5
Transmission Owner Rights Upon Customer Breach. Without limiting Article 2.4, upon a Breach by Customer that remains uncured for ten (10) Business Days after notice, Transmission Owner may suspend work on the TO Attachment Facilities and Network Upgrades, suspend or reduce service to the Load Facility to the extent consistent with Applicable Laws and Regulations, and draw upon security under the Security Agreement, in each case until the Breach is cured. Customer shall bear all costs of suspension and remobilization, and milestone dates shall be extended as reasonably necessary.
2.6
Termination Costs. Upon any termination other than for Transmission Owner’s Default, Customer shall pay all costs incurred or irrevocably committed by Transmission Owner as of the date of termination that are Customer’s responsibility under this Agreement, including cancellation costs for orders and contracts for TO Attachment Facilities and the Customer Attachment Facilities, Network Upgrades, and equipment, and all costs of the removal, relocation, retirement, or other disposition of such facilities to the extent required by Good Utility Practice and necessary to restore the New York State Transmission System to a reliable condition in accordance with Applicable Reliability Standards, in each case except to the extent such costs are recovered under the Cost Recovery Agreement. Each Party shall use Reasonable Efforts to mitigate such costs. Early termination and stranded cost payments, including the Net Present Value Residual Charge (as defined in the Cost Recovery Agreement) for the TO Attachment Facilities and Network Upgrades, are further governed by the Cost Recovery Agreement and the Security Agreement.
2.7
Disconnection Upon Termination. Upon termination, Transmission Owner shall take all appropriate steps to disconnect the Load Facility from the New York State Transmission System consistent with Good Utility Practice, and Customer shall cooperate with any disconnection and bear all costs of disconnection. 2.8
Survival. This Agreement shall continue in effect after termination to the extent necessary to provide for final billings and payments; to permit the determination and enforcement of liability and indemnification obligations arising from acts or events that occurred while this Agreement was in effect; to give effect to the confidentiality and dispute resolution provisions; and to permit each Party to access the lands of the other to disconnect, remove, or salvage its facilities. ARTICLE 3
SCOPE OF INTERCONNECTION SERVICE
3.1
Provision of Service. For purposes of this Agreement, Transmission Owner shall provide load interconnection service to Customer at the Point of Interconnection for the Term, up to the Maximum Load Facility Peak Demand, subject to this Agreement, the Tariff, and Applicable Laws and Regulations.
3.2
Load Limits. Customer shall ensure that the actual demand of the Load Facility does not exceed the Maximum Load Facility Peak Demand, the Maximum Annual
PDF page 13
Energy, or the amount fully studied in the System Impact Study and Facilities Study, as measured at the Point of Interconnection.
3.3
Identification of Reliability Violation. If NYISO or Transmission Owner identifies a reliability violation associated with the Load Facility, at any time, Transmission Owner shall notify Customer of the amount of load that may be reliably served, and the Parties shall coordinate operational limitations or mitigation measures to minimize interruptions or reductions; Customer shall conform its load to such amount.
3.4
No Transmission Service or Other Services. This Agreement does not constitute a request for, or agreement to provide, transmission service under the Tariff, or the sale or purchase of energy, capacity, or ancillary services under the NYISO Services Tariff. Transmission Owner does not sell electric energy under this Agreement. Customer shall be solely responsible for arranging its energy supply and shall maintain a service agreement with a load serving entity for the Load Facility. All Delivery Service shall be provided pursuant to, and billed in accordance with, the applicable Tariff, and Customer shall select and qualify for the applicable service classification. Nothing in this Agreement obligates Transmission Owner to provide Delivery Service beyond the Tariff or to expand the transmission system beyond the facilities identified in the studies for the Load Facility.
3.5
Load Ramp Projection. Within ten (10) Business Days after the Effective Date, Customer shall provide monthly projections of energy and demand for the Term in the form of Exhibit A. On the fifth anniversary of the Effective Date and every fifth anniversary thereafter, Customer shall provide updated projections for the remainder of the Term (the most recent version, the “Load Ramp Projection”); provided that no update may change the monthly projections by more than [five percent (5%)] from the prior version (absent prior written authorization by Transmission Owner and NYISO), and in no event may the demand projection exceed the Maximum Load Facility Peak Demand or the annual energy projection exceed the Maximum Annual Energy.
3.6
Reduction of Interconnection Rights. If the Load Facility fails to meet the Minimum Committed Load for [three (3)] consecutive months or [three (3)] non- consecutive months in any [six (6)]-month period after the Commercial Operation Date (a “Shortfall Event”), Transmission Owner may notify Customer that it intends to reduce the Maximum Load Facility Peak Demand if Customer does not consistently meet the Minimum Committed Load during the following sixty (60) Calendar Days. Any reduction shall be proportionate to the average load shortfall over the applicable period, and Exhibit A shall be amended accordingly, subject to any filing with or acceptance by FERC or the NYPSC required under Applicable Laws and Regulations. Any reduction of the Maximum Load Facility Peak Demand under this Article 3.6 shall not reduce Customer’s obligations under the Cost Recovery Agreement or the Security Amount under the Security Agreement. 3.7
Exceedance Events. Customer shall not permit the actual demand or energy consumption of the Load Facility to exceed the limits set forth in Article 3.2, and
PDF page 14
Exceedance Events are not permitted under this Agreement. The parameters, thresholds, number and duration of occurrences, and other criteria that constitute an Exceedance Event shall be as set forth in Exhibits A and C. Upon the occurrence of an Exceedance Event, Transmission Owner may require Customer to reduce load, may interrupt Delivery Service in accordance with Article 7.4, and may require additional study at Customer’s cost to identify any further upgrades necessary to serve the Load Facility and additional security under the Security Agreement.
ARTICLE 4
CONDITIONS TO ENERGIZATION AND
PERMISSION TO OPERATE
4.1
Conditions Precedent. Transmission Owner shall not energize the Load Facility or permit its parallel operation with the TO System until the conditions set forth in Exhibit F have been satisfied to Transmission Owner’s reasonable satisfaction. 4.2
Permission to Operate. Upon satisfaction of the conditions in Exhibit F, Transmission Owner shall issue PTO or identify in writing the deficiencies preventing issuance of PTO within a reasonable time after completion of required testing and receipt of all required documentation.
4.3
Parallel Operation. Upon issuance of PTO, Transmission Owner shall permit parallel operation of the Load Facility with the TO System subject to this Agreement, the Tariff, and Applicable Laws and Regulations.
ARTICLE 5
ENGINEERING, PROCUREMENT, AND
CONSTRUCTION
5.1
Transmission Owner Construction. Transmission Owner shall use Reasonable Efforts to design, procure, construct, and install the TO Attachment Facilities and Network Upgrades described in Exhibit B by the milestone dates in Exhibit D. Transmission Owner will act in accordance with its safety practices, TO Standards, labor agreements, applicable agreements, and Applicable Laws and Regulations. If Transmission Owner reasonably expects not to meet a milestone, it shall promptly notify Customer (and NYISO, if required) and use Reasonable Efforts to meet the earliest practicable date thereafter. Milestones may otherwise be modified by mutual written agreement.
5.2
Customer Attachment Facilities. Customer shall, at its sole expense, design, procure, construct, own, install, operate, and maintain the Customer Attachment Facilities and the Load Facility described in Exhibit A in accordance with Good Utility Practice, TO Standards (including the specifications, technical manuals, and standards furnished by Transmission Owner), and Applicable Laws and Regulations. Customer shall submit design drawings and initial specifications for the Customer Attachment Facilities, including System Protection Facilities, for
PDF page 15
Transmission Owner’s engineering review at least one hundred eighty (180) Calendar Days, and final specifications at least ninety (90) Calendar Days, before the In-Service Date. Transmission Owner shall comment within thirty (30) Calendar Days, and Customer shall make such changes as Transmission Owner reasonably requires for compatibility with its technical, operational, and safety requirements. At least ninety (90) Calendar Days before initial energization, Customer shall deliver as-built or redlined drawings and relay settings for the Customer Attachment Facilities, and within one hundred twenty (120) Calendar Days after the In-Service Date, Customer shall deliver final “as-built” drawings and relay settings. Customer shall use Reasonable Efforts to complete the Customer Attachment Facilities and its other activities by the Customer milestone dates in Exhibit D and acknowledges that Transmission Owner’s ability to meet its milestones may depend on Customer’s timely completion of such activities. 5.3
Affected Transmission Owner Construction. Facilities or Network Upgrades to be constructed by an Affected Transmission Owner shall be governed by a separate agreement between Customer and the applicable Affected Transmission Owner. Customer shall timely execute that agreement, provide all required payments, deposits, information, property rights, and financial security, and promptly notify Transmission Owner of any delay in, or change to, the scope or milestones under such agreement. Transmission Owner shall use Reasonable Efforts to coordinate its work with the Affected Transmission Owner but shall not be responsible for the Affected Transmission Owner’s acts, omissions, performance, or delays. Any Transmission Owner milestone dependent upon Affected Transmission Owner performance shall be equitably extended to reflect the resulting delay. Customer’s ability to receive service may be dependent on the completion of milestones under its agreements with the Affected Transmission Owner, and Transmission Owner shall not be required to energize the Load Facility, issue Permission to Operate, or authorize the applicable level of service until all required Affected Transmission Owner facilities have been completed and placed in service.
5.4
No Warranty. Transmission Owner’s review, approval, inspection, or acceptance of any design, specification, or facility shall not constitute an endorsement or warranty of its design, fitness, safety, durability, or reliability. TRANSMISSION OWNER DISCLAIMS ANY RESPONSIBILITY OR LIABILITY FOR THE
DESIGN OR ENGINEERING OF THE LOAD FACILITY, OR THE
CUSTOMER ATTACHMENT FACILITIES, EXCEPT FOR BREACH OF
TRANSMISSION OWNER’S OBLIGATIONS HEREUNDER.
5.5
Work Progress and Information Exchange. The Parties shall keep each other advised of the progress of their respective design, procurement, and construction efforts, including through engineering and project meetings beginning thirty (30) Calendar Days before the start of construction at a cadence established by Transmission Owner, provide progress reports upon request, and exchange information (and provide NYISO information as required) regarding the design, modification, and compatibility of their facilities, including submission of Customer facility design details for Transmission Owner engineering review.
PDF page 16
5.6
Land Rights. Each Party shall furnish to the other such rights of use, licenses, rights of way, or easements over lands it owns or controls as are reasonably necessary to construct, operate, maintain, test, inspect, replace, or remove facilities under this Agreement. For the avoidance of doubt, this Agreement (i) does not establish on behalf of Customer or the Load Facility any rights or title to Transmission Owner’s real property, other than the limited rights reasonably necessary for the Customer Attachment Facilities to connect to the TO Attachment Facilities, and (ii) does not create an obligation on Transmission Owner to transfer, convey, or use its real property rights on behalf of Customer or the Load Facility, or to acquire property on behalf of Customer or the Load Facility. 5.7
Right of Entry. Upon reasonable notice (or without notice in an Emergency State) and subject to the granting Party’s reasonable safety rules and site access procedures, as amended from time to time, each Party shall permit the other to enter its property as reasonably necessary to perform its obligations under this Agreement. Customer shall provide Transmission Owner unescorted 24-hour access to the TO Attachment Facilities, Metering Equipment, and System Protection Facilities located on Customer’s premises, subject only to compliance with Customer’s site security protocols provided in advance. The accessing Party shall maintain the insurance required under Article 18, shall not unreasonably interfere with the granting Party’s operations, and shall indemnify the granting Party against third-party claims resulting from its acts or omissions in connection with its exercise of such access rights.
5.8
Permits. Customer shall cooperate in good faith to obtain all permits, licenses, and authorizations necessary for the performance of this Agreement.
5.9
Transfers Regarding Real Property. To the extent that the TO Attachment Facilities or Network Upgrades require the acquisition of real estate, Customer represents and warrants that it holds, or will hold prior to transfer, and shall transfer, at Customer’s sole cost, all real estate rights necessary to own, operate, and maintain the TO Attachment Facilities or Network Upgrades, free and clear of liens and encumbrances, and the ability to convey such rights to Transmission Owner in accordance with Transmission Owner requirements, by the date set forth in Exhibit
D. ARTICLE 6
COST RESPONSIBILITY, SECURITY, AND
PAYMENT
6.1
Customer Cost Responsibility. Customer’s responsibility for, and the recovery of, the costs of the TO Attachment Facilities and the Network Upgrades shall be governed exclusively by the Cost Recovery Agreement or any other rate or agreement directed by FERC or the NYPSC, and no such costs shall be invoiced or payable under this Agreement.
6.2
Security. As a condition to Transmission Owner’s performance with respect to the TO Attachment Facilities and Network Upgrades, Customer shall provide and
PDF page 17
maintain, at its sole cost, security in favor of Transmission Owner in the amounts, forms, and at the times specified in the Security Agreement. The amount, form, replenishment, adjustment, draw, and release of such security shall be governed by the Security Agreement. Transmission Owner may require additional security upon a Material Modification. Failure to timely provide, maintain, or replenish such security as required by the Security Agreement or this Article 6.2 shall constitute a Breach of this Agreement, in addition to any rights or remedies of Transmission Owner under the Security Agreement, and Article 6.6 shall not be construed to limit the foregoing. Customer acknowledges that a Default under this Agreement, among other events, shall constitute a draw event under the Security Agreement. 6.3
Invoicing and Payment. Transmission Owner reserves the right to invoice Customer for any amount that may be due under this Agreement, including in advance of performing the applicable work. Any such invoices shall be paid within thirty (30) Calendar Days of receipt in immediately available funds to the account designated in Exhibit I. Late payments shall bear interest calculated in accordance with 18 C.F.R. § 35.19a(a)(2)(iii).
6.4
Billing Disputes. Transmission Owner shall continue to perform during a billing dispute so long as Customer pays all amounts to Transmission Owner on or before their due date, regardless of whether Customer disputes the same in good faith. Any balances that remain unpaid when due shall accrue interest at the interest rate specified at 18 C.F.R. § 35.19a or successor regulation. Transmission Owner may include unpaid balances, with any accrued interest, on the next monthly bill. Any disputes shall be addressed in accordance with Article 20. If Customer fails to pay any amount when due, Transmission Owner may issue a notice of Breach under Article 16 and may exercise its rights under Article 6.2. Upon resolution of the dispute, the disputed amount shall be retained by or released to the Party in whose favor the dispute is resolved, without interest, within thirty (30) Calendar Days after resolution. Billing disputes not raised within twelve (12) months after the invoice date are waived.
6.5
Taxes. The Parties intend that payments and property transfers by Customer to Transmission Owner for the TO Attachment Facilities and Network Upgrades be non-taxable to the extent permitted by law. Customer shall indemnify Transmission Owner for the cost consequences of any tax liability imposed on Transmission Owner as a result of such payments or transfers, including interest and penalties other than those attributable to Transmission Owner’s delay.
6.6
Relationship to Cost Recovery Agreement and Security Agreement. This Agreement is entered into in connection with, and shall be read together with, the Cost Recovery Agreement between Transmission Owner and Customer dated [●] and/or other applicable agreement and the Security Agreement between Transmission Owner and Customer dated [●]. Customer shall be the same legal entity as the customer under the Cost Recovery Agreement (or other applicable agreement) and the Security Agreement. No cost recovered under the Cost Recovery Agreement shall be recovered again under this Agreement. In the event of any conflict between this Agreement and the Cost Recovery Agreement regarding the costs of, or charges for, the Network Upgrades or the TO Attachment
PDF page 18
Facilities, the Cost Recovery Agreement shall control, and in the event of any conflict regarding security, the Security Agreement shall control. ARTICLE 7
OPERATIONS
7.1
Compliance; Change in Law. Each Party shall comply with Applicable Laws and Regulations and Applicable Reliability Standards and provide the other Party information reasonably required for such compliance. If a change in Applicable Laws and Regulations or Applicable Reliability Standards materially affects a Party’s rights, obligations, or performance, the affected Party shall notify the other, and the Parties shall negotiate in good faith an amendment to address such change. 7.2
Transmission Owner Obligations. Transmission Owner shall operate and maintain the TO Attachment Facilities and Network Upgrades in a safe and reliable manner in accordance with TO Standards, the Tariff, and Applicable Laws and Regulations, and shall use Reasonable Efforts to maintain service to the Load Facility in accordance with the Operating Documents [and the Single Contingency Design]. Transmission Owner may issue operating instructions consistent with this Agreement and its operating protocols.
7.3
Customer Obligations. Customer shall, at its own expense:
(1) operate, maintain, and control the Load Facility and Customer Attachment Facilities in a safe and reliable manner in accordance with Good Utility Practice, TO Standards, the Operating Documents (including Exhibit E), and Applicable Laws and Regulations;
(2) maintain the Load Facility within the Maximum Load Facility Peak Demand, power factor, voltage, ramp rate, and other operating
characteristics specified in Exhibits A and E, it being understood that Customer shall not be compensated for reactive power;
(3) implement under-frequency and over-frequency relay set points and permit NYISO or Transmission Owner to shed load as required by NPCC, NYISO, or Transmission Owner load-shed programs; and
(4) notify Transmission Owner immediately by telephone, and in writing within twenty-four (24) hours, of any condition that materially affects or may affect the safe and reliable operation of the Load Facility, the Customer Attachment Facilities, or the TO System.
7.4
Interruption and Disconnection. Transmission Owner may interrupt, reduce, or disconnect service to the Load Facility, in whole or in part: (a) consistent with Firm Withdrawal Service, Non-Firm Withdrawal Service, or any other type of transmission service for which Customer has taken service as specified in an executed TSA, as the case may be; (b) as necessary to construct, maintain, repair, replace, or test the TO System or TO Attachment Facilities and the Customer Attachment Facilities; (c) if continued operation may endanger persons or property or adversely affect the safety or reliability of the TO System or the New York State Transmission System; (d) upon operation of any protective device or direct transfer
PDF page 19
trip equipment; (e) as required or directed by NYISO or any Governmental Authority; (f) upon Exceedance Events as provided in Article 3.7; (g) if Customer lacks the agreements required for the purchase of energy; (h) upon a Default by Customer or as provided in Article 2.5; (i) if Customer operates the Load Facility without PTO or implements a Material Modification without approval; or (j) as otherwise permitted by the Tariff or Applicable Laws and Regulations. Any interruption shall continue only as long as reasonably necessary under Good Utility Practice, be made on a non-discriminatory basis, and, except in an Emergency State, be scheduled after advance notice and, to the extent practicable, during periods of least impact. Where advance notice is not possible, Transmission Owner shall notify Customer by telephone as soon as practicable, followed by written notice. Interruptions resulting from the Single Contingency Design shall not constitute a Breach by Transmission Owner, and Transmission Owner shall have no liability therefor except to the extent caused by its gross negligence or willful misconduct.
7.5
Outages. Each Party may, in accordance with Good Utility Practice and in coordination with the other, remove from service its facilities that may affect the other Party to perform maintenance, testing, or replacement, using Reasonable Efforts to schedule such outages at mutually acceptable times and to minimize their effect. Customer shall submit planned maintenance schedules for a rolling eighteen (18)-month period, and Transmission Owner may request rescheduling to maintain reliability. The owner of a facility that is out of service shall use Reasonable Efforts to restore it promptly and keep the other Party informed. Nothing in this Agreement restricts Transmission Owner’s use of the TO System to serve other customers. 7.6
Customer Disconnection. Customer may temporarily disconnect the Load Facility in accordance with TO Standards and the Operating Documents on at least thirty
(30) Calendar Days’ prior notice of a planned disconnection and [prompt advance] notice of an emergency disconnection.
7.7
System Protection and Power Quality. Customer shall, at its expense, install, operate, and maintain System Protection Facilities, including a load-interrupting disconnecting device accepted by Transmission Owner at a mutually agreed location, and any System Protection Facilities as required by Transmission Owner due to the interconnection. Each Party’s protection shall be coordinated in accordance with Good Utility Practice and Applicable Reliability Standards, include necessary test switches, and be calibration- and functional-trip-tested before the In-Service Date and at intervals required by Good Utility Practice. Neither Party’s facilities shall cause excessive voltage flicker or harmonic distortion as defined by ANSI C84.1 and IEEE 519, or any successor standards. 7.8
Switching and Tagging. All switching and tagging affecting the TO System or the TO Attachment Facilities and the Customer Attachment Facilities shall be performed by Transmission Owner, or pursuant to switching orders issued by Transmission Owner, and in accordance with the Operating Documents and Transmission Owner’s switching and tagging rules. Transmission Owner’s system operator shall have operational jurisdiction over switching operations affecting the TO System, as identified in Exhibit E.
PDF page 20
7.9
Use of TO Attachment Facilities and the Customer Attachment Facilities. Except as required by Applicable Laws and Regulations or agreed in writing, the TO Attachment Facilities and Customer Attachment Facilities shall be used solely to interconnect the Load Facility.
7.10
Disturbance Analysis. The Parties shall cooperate in the analysis of disturbances affecting the Load Facility or the New York State Transmission System by providing disturbance recorder data, relay targets, breaker operations, sequence-of- events records, and logs.
7.11
Operations Manual. At least ninety (90) Calendar Days before initial energization, Customer shall prepare and submit for Transmission Owner’s review and approval an operations manual for the Load Facility and Customer Attachment Facilities containing, at a minimum, 24/7 emergency and operating contacts, maintenance contacts, customer-specific operating characteristics, switching and clearance procedures, outage and maintenance coordination procedures, SCADA and telemetry points, and communication protocols (the “Operations Manual”). Customer shall address Transmission Owner’s comments in good faith and resubmit the Operations Manual for approval. Customer shall update the Operations Manual as necessary and at least annually and shall submit any changes for Transmission Owner’s review and approval before implementation. The Operations Manual shall be consistent with, and shall not conflict with, the Operating Documents and TO Standards, and in the event of any conflict, the Operating Documents and TO Standards shall control. The Parties shall perform their obligations under Articles 7, 8, 11, and 15 in accordance with the Operations Manual.
ARTICLE 8
EMERGENCIES
8.1
Obligations. Each Party shall comply with the Emergency State procedures of NYISO, Applicable Reliability Standards, and Applicable Laws and Regulations. 8.2
Notice. Each Party shall promptly notify the other upon becoming aware of an Emergency State that may reasonably be expected to affect the other Party’s facilities, describing (to the extent known) the Emergency State, the extent of damage, the expected effect, its anticipated duration, and corrective action taken or planned, followed as soon as practicable by written notice.
8.3
Transmission Owner Authority. Transmission Owner may take whatever actions it deems necessary during an Emergency State to preserve public health and safety, preserve reliability, limit or prevent damage, and expedite restoration, including curtailing, reducing, or disconnecting the Load Facility, in coordination with NYISO as applicable, and shall use Reasonable Efforts to minimize the effect on Customer and to restore service as soon as practicable.
8.4
Customer Authority. Customer shall take actions with respect to the Load Facility during an Emergency State consistent with Good Utility Practice, using Reasonable Efforts to minimize the effect on the New York State Transmission System. Unless immediate action is required in Customer’s reasonable judgment, Customer shall
PDF page 21
obtain Transmission Owner’s consent, not to be unreasonably withheld, before performing manual switching in response to an Emergency State.
8.5
Limited Liability. No Party shall be liable to the other for any action taken in good faith and consistent with Good Utility Practice in responding to an Emergency State, except to the extent caused by its gross negligence or willful misconduct. ARTICLE 9
METERING AND TELEMETRY
9.1
Metering Equipment. Customer shall pay for the purchase and installation of Transmission Owner-approved revenue-quality Metering Equipment at or near the Point of Interconnection before any operation of the Load Facility, including a lockable cabinet for instrument transformers as specified in Exhibit B. Transmission Owner shall [provide the meters and] own, operate, test, and maintain the Metering Equipment used for billing and settlement, and Customer shall bear all reasonable costs thereof. While the Cost Recovery Agreement is in effect, such costs shall be recovered pursuant to the Cost Recovery Agreement; thereafter, such costs shall be invoiced and paid in accordance with Article 6.3. The Metering Equipment shall record interval demand and energy (including MW, MVAR, and MWh) in sufficient detail to support billing and NYISO settlement. 9.2
Standards. Metering Equipment shall be installed, calibrated, and tested in accordance with applicable ANSI and NYPSC standards, the NYISO Revenue Metering Requirements Manual, and TO Standards.
9.3
Check Meters. Customer may, at its expense, install and operate check meters on its side of the Point of Interconnection, subject to inspection by Transmission Owner. Check meters shall not be used for billing except as provided in Article 9.4. 9.4
Testing and Adjustment. Transmission Owner shall test the Metering Equipment upon installation and at least once every [four (4)] years thereafter, and more frequently at Customer’s request and expense, upon reasonable notice and with Customer’s right to be present. If Metering Equipment fails to register or is found inaccurate by more than [two percent (2%)], it shall be repaired or replaced at Customer’s expense (unless due to Transmission Owner’s failure to maintain), and measurements shall be corrected for the period of inaccuracy using check meter data, if available, or otherwise for one-half of the period since the last test, or as provided in the Tariff.
9.5
Metering Data. Metered data shall be telemetered at Customer’s expense to locations designated by Transmission Owner and shall be the official measurement under normal operating conditions. Transmission Owner shall make interval metering data available to Customer upon request.
9.6
Telemetry and Communications. Before the In-Service Date, Customer shall install, own, and maintain remote terminal units and dedicated data circuits, as specified in Exhibit B, to provide Transmission Owner (and NYISO, as applicable) real-time telemetry of, at a minimum, real power demand, reactive power or power factor, voltage at the Point of Interconnection, and breaker and switch status, and
PDF page 22
shall coordinate SCADA requirements, points lists, and protocols with Transmission Owner and NYISO. Customer shall maintain voice communications with Transmission Owner’s control center and shall promptly correct telemetry failures. Each Party shall promptly advise the other of any metering, telemetry, or communications errors requiring correction.
9.7
No Annexation. Equipment placed on a Party’s premises shall remain the property of the Party providing it, regardless of the mode of annexation, unless otherwise agreed.
ARTICLE 10 TESTING AND INSPECTION
10.1
Pre-Energization Testing. Before energization, Transmission Owner shall test the TO Attachment Facilities and Network Upgrades, and Customer shall test the Load Facility and Customer Attachment Facilities (including System Protection Facilities), as required by the Operating Documents or as Transmission Owner reasonably requests. Each Party shall make modifications found necessary as a result, and Customer shall bear the cost of such testing and modifications. Customer shall deliver test results within five (5) Business Days after testing. 10.2
Post-Energization Testing. Each Party shall, at its own expense, perform routine inspection and testing of its facilities in accordance with Good Utility Practice and Applicable Reliability Standards. Each Party may require reasonable additional testing of the other’s facilities at the requesting Party’s expense. 10.3
Right to Observe and Inspect. Each Party shall notify the other (and NYISO, as applicable) in advance of post-energization tests of its TO Attachment Facilities and the Customer Attachment Facilities, and the other Party may observe such tests at its own expense. Transmission Owner may, upon reasonable notice (or without notice in an Emergency State) and subject to Customer’s reasonable safety and security requirements, inspect the Load Facility and Customer Attachment Facilities, review and require changes to protective settings, review maintenance records, and witness or require re-testing whenever it reasonably believes the facilities do not comply with this Agreement, in which case Customer shall bear the cost of such re-testing and any required corrective action. The exercise or non- exercise of such rights shall not constitute an endorsement or warranty or impose any liability on Transmission Owner. Information Transmission Owner obtains in such exercise shall be treated as Confidential Information.
ARTICLE 11 MAINTENANCE
11.1
Maintenance Obligations. Transmission Owner shall maintain the TO Attachment Facilities and Network Upgrades, and Customer shall maintain the Load Facility, Customer Attachment Facilities, and any System Protection Facilities on Customer’s property, in each case in a safe and reliable condition in accordance with Good Utility Practice, TO Standards, the Operating Documents, and Applicable Laws and Regulations.
PDF page 23
11.2
Coordination. The Parties shall confer regularly to coordinate preventive and corrective maintenance, keep NYISO informed as required, and schedule maintenance in accordance with NYISO procedures.
11.3
Secondary Systems. Each Party shall cooperate in the inspection, maintenance, and testing of control and power circuits operating below 600 volts that may reasonably be expected to affect the other Party, and shall give advance notice before working on such circuits, especially those involving breaker trip and close contacts and instrument transformers.
ARTICLE 12 MODIFICATIONS
12.1
Notice of Modification. Either Party may modify its facilities. A Party planning a modification that may reasonably be expected to affect the other Party’s facilities shall provide drawings, plans, specifications, and timing information at least [one hundred eighty (180)] Calendar Days in advance (or such longer period as reasonably required for evaluation). Notice of any change to the load characteristics reported in the NYISO Load Interconnection Data Request (NYISO Technical Bulletin 266 or its successor) shall be provided in substantially that form. Modifications required in response to an Emergency State do not require the advance notification specified in this Article 12.1 but shall be noticed as soon as practicable.
12.2
Material Modifications. Transmission Owner shall determine, in its reasonable discretion, whether a proposed modification is a Material Modification. Customer shall not implement a Material Modification or change the configuration of the Customer Attachment Facilities or the Load Facility without Transmission Owner’s prior written approval. Transmission Owner has no obligation to approve a Material Modification until (a) required studies are complete; (b) all required approvals are obtained; and (c) Customer has provided any additional security required under the Security Agreement. A Material Modification may require amendment of this Agreement.
12.3
Studies and Costs. Transmission Owner or NYISO may perform studies reasonably necessary to evaluate a proposed modification. Customer shall pay the cost of such studies and all costs incurred by Transmission Owner as a result of any modification requested or implemented by Customer, and shall be responsible for the costs of modifications to the Customer Attachment Facilities required by Applicable Laws and Regulations, Applicable Reliability Standards, or Good Utility Practice. All modifications shall comply with this Agreement, NYISO requirements, and TO Standards.
(1) Customer shall pay the costs of all required engineering or design studies prior to the provision of service (e.g., transient studies) that result in the need for further scope of work.
PDF page 24
ARTICLE 13 INFORMATION REQUIREMENTS
13.1
Pre-Energization Information. At least ninety (90) Calendar Days before initial energization, Customer shall provide complete and accurate information regarding the electrical characteristics and configuration of the Load Facility and Customer Attachment Facilities, including as-built or redlined single-line diagrams and protective device settings, for review by Transmission Owner’s testing and commissioning, engineering, construction management, and control center personnel.
13.2
Load Information. Upon request, Customer shall promptly provide load data and forecast information (in MW and MWh) required for Transmission Owner to perform its load forecasting obligations under the NYISO tariffs and manuals. 13.3
Supplementation and Updates. Before the In-Service Date, each Party shall supplement its submissions with “as-built” and “as-tested” information or confirm that no differences exist. After the In-Service Date, each Party shall provide the other with information on changes due to equipment replacement, repair, or adjustment that may affect the other’s ratings, protection, or operating requirements within thirty (30) Calendar Days.
13.4
Environmental Releases. Customer shall notify Transmission Owner, first orally and then in writing, of any release of Hazardous Substances, asbestos or lead abatement, or remediation related to the Load Facility, TO Attachment Facilities, Customer Attachment Facilities, or Network Upgrades that may reasonably be expected to affect Transmission Owner, in good faith within twenty-four (24) hours after becoming aware, and shall furnish copies of publicly available reports filed with Governmental Authorities.
ARTICLE 14 REGULATORY REQUIREMENTS AND
GOVERNING LAW
14.1
Regulatory Approvals. Each Party’s obligations are subject to its receipt of any required approval of a Governmental Authority (“Required Approvals”). Each Party shall timely seek, using Reasonable Efforts and at its own expense, all approvals, permits, and authorizations required of it, including those of FERC, the NYPSC, and NYISO. [Nothing in this Agreement shall require Transmission Owner to take any action that could result in the loss of its status or exemption under the Federal Power Act, the Public Utility Holding Company Act of 2005, or the Public Utility Regulatory Policies Act of 1978.]
14.2
Governing Law. The validity, interpretation, and performance of this Agreement shall be governed by and construed in accordance with the laws of the State of New York, without regard to conflict-of-laws principles (other than Section 5-1401 of the New York General Obligations Law), except to the extent preempted by federal law. This Agreement is subject to all Applicable Laws and Regulations, and each
PDF page 25
Party reserves the right to seek changes in, appeal, or contest any law, order, rule, or regulation of a Governmental Authority.
14.3
Forum; Waiver of Jury Trial. Subject to the jurisdiction of FERC or the NYPSC, any action arising out of or relating to this Agreement shall be brought exclusively in the Supreme Court of the State of New York, [County] County, or the United States District Court for the applicable (i.e., Northern, Southern, Western, or Eastern) District of New York, and the Parties irrevocably submit to the jurisdiction of such courts. EACH PARTY EXPRESSLY WAIVES ANY RIGHT TO TRIAL
BY JURY IN ANY ACTION ARISING OUT OF OR IN CONNECTION WITH
THIS AGREEMENT.
ARTICLE 15 NOTICES
15.1
General. Unless otherwise provided, any notice required or permitted under this Agreement shall be in writing and shall be effective when delivered by hand, nationally recognized overnight courier, certified or registered mail (return receipt requested), or electronic mail, to the addresses in Exhibit I. A Party may change its notice information on five (5) Business Days’ written notice.
15.2
Billings and Payments. Billings and payments shall be effectuated through the wire instructions or sent to the addresses included in Exhibit I or as otherwise mutually agreed to by the Parties.
15.3
Alternative and Operational Communications. Notices not required to be in writing may be given by telephone or email to the contacts in Exhibit I. Operational communications,
including
outage
coordination
and
Emergency
State
communications, shall be made to the 24/7 contacts in Exhibit E using three-part communication consistent with NERC Reliability Standards. Each Party shall designate in writing its points of contact for operations and maintenance. ARTICLE 16 FORCE MAJEURE, BREACH, AND DEFAULT
16.1
Force Majeure. “Force Majeure” means any event or circumstance beyond a Party’s reasonable control that prevents the Party from performing an obligation, is not the result of the negligence or intentional wrongdoing of such Party, and could not have been prevented or mitigated by the exercise of Good Utility Practice (in the case of Transmission Owner) or due diligence (in the case of Customer), including acts of God, fire, flood, storm, lightning, explosion, breakage of or accident to machinery, epidemic or pandemic, cyber-attack (except to the extent caused by or resulting from Customer’s failure to comply with its obligations under this Agreement), sabotage, terrorism, war, civil disturbance, strikes and labor disturbances, acts or orders of any Governmental Authority, and curtailment or interruption directed by NYISO for reliability reasons. Force Majeure shall not include, with respect to Customer: (a) economic hardship, changes in market conditions, or the cost or unavailability of financing; (b) delays in Customer’s procurement of equipment or failure of Customer’s suppliers or contractors, unless
PDF page 26
caused by an independent Force Majeure event; (c) labor disputes involving only Customer’s or its contractors’ workforce; (d) Customer’s failure to obtain required permits or approvals, unless it has diligently and timely pursued them; or (e) changes in the demand for, or the business case of, the Load Facility’s end use. Interruptions resulting from the Single Contingency Design shall not be treated as Force Majeure. Force Majeure shall not excuse the failure to make payments when due or to timely post or maintain the Financial Security.
16.2
Effect of Force Majeure. A Party shall be excused from performance (other than the obligation to pay money when due) to the extent prevented by Force Majeure, provided it gives prompt notice with full particulars (confirming any telephone notice in writing), keeps the other Party informed, and exercises due diligence to remedy the effects with reasonable dispatch. A Party shall not be required to settle a labor dispute on terms unsatisfactory to it.
16.3
Breach and Cure. No Breach shall exist where the failure (other than to pay money or to provide or maintain security) results from Force Majeure or the other Party’s act or omission. Upon a Breach, the non-breaching Party shall give written notice describing the Breach in reasonable detail. The Breaching Party shall have thirty
(30) Calendar Days from receipt to cure; provided that (a) a Breach consisting of a failure to pay any amount when due or to provide, maintain, or replenish security shall be cured within five (5) Business Days after notice; (b) if a non-monetary Breach cannot reasonably be cured within thirty (30) Calendar Days, the Breaching Party shall commence the cure within such period, provide a written cure plan, and diligently complete it within [sixty (60)] Calendar Days after receipt of notice; and
(c) no cure period shall apply to a Breach that creates an Emergency State, operation without PTO, or an unauthorized Material Modification, or to an Event of Insolvency. Where a Breach is also a default under the Cost Recovery Agreement or the Security Agreement, the applicable cure periods shall run concurrently. 16.4
Insolvency. An “Event of Insolvency” occurs if Customer (a) files a voluntary petition in bankruptcy or for reorganization or similar relief, (b) has an involuntary petition filed against it that is not dismissed within sixty (60) Calendar Days, (c) makes a general assignment for the benefit of creditors, (d) has a receiver, trustee, or custodian appointed for all or substantially all of its assets, (e) is generally unable to pay its debts as they become due, or (f) undergoes dissolution. An Event of Insolvency shall constitute a Default without notice or cure, to the extent permitted by applicable bankruptcy law.
16.5
Default; Remedies. If a Breach is not cured as provided in Article 16.3, a Default shall exist, and the non-defaulting Party may terminate this Agreement by written notice, recover all amounts due, and pursue all other remedies available at law or in equity, including specific performance and injunctive relief.
16.6
Cross-Default. Each of the following shall constitute a Breach by Customer under this Agreement: (a) a default, event of default, or material breach by Customer under the Cost Recovery Agreement, the Security Agreement, or any other agreement listed in Exhibit G, in each case after the expiration of any cure period provided therein, which shall constitute a Default under this Agreement and shall
PDF page 27
not be subject to any further cure period under this Agreement; (b) Customer’s failure to pay amounts owed to NYISO for the Load Facility, or the suspension or termination of Customer’s or its load serving entity’s NYISO market participation for the Load Facility for credit reasons; (c) Customer’s failure to pay undisputed amounts owed to Transmission Owner under its retail electric tariff or any other agreement between Customer (or its Affiliate) and Transmission Owner relating to the Load Facility; and (d) a default by Customer or its Affiliate under any other interconnection or service agreement with Transmission Owner relating to a facility on the same site or that shares the TO Attachment Facilities or Network Upgrades. The Breaches described in clauses (b) through (d) shall be subject to the cure period applicable under Article 16.3(a).
16.7
Reporting of Non-Force Majeure Events. Each Party shall notify the other when it becomes aware of its inability to comply with this Agreement for a reason other than Force Majeure, including the date, duration, reason, and corrective actions it is taking or will take; such notification shall not by itself give rise to a claim of anticipatory breach.
ARTICLE 17 INDEMNITY, LIMITATION OF LIABILITY,
AND CONSEQUENTIAL DAMAGES
17.1
Single Contingency Design. Customer acknowledges that Transmission Owner may design and operate the interconnection using a Single Contingency Design, and Customer has elected to accept the reliability level associated therewith. Transmission Owner shall have no liability for loss or damage, including loss of data, computing operations, or business interruption, resulting from service interruptions, reductions, or power quality events due to contingencies reasonably contemplated by the Single Contingency Design, and Customer shall be solely responsible for installing any backup generation, uninterruptible power supply, or redundancy it requires.
17.2
Customer Indemnity. To the fullest extent permitted by law, Customer shall indemnify, defend, and hold harmless Transmission Owner, its Affiliates, and their respective trustees, directors, officers, employees, and agents (the “TO Indemnitees”) from and against all claims, demands, suits, losses, liabilities, damages, fines, penalties (including penalties assessed under Applicable Reliability Standards to the extent attributable to the Load Facility or Customer’s acts or omissions), costs, and expenses, including reasonable attorneys’ fees and claims for injury to or death of any person or damage to property (“Losses”), arising out of or resulting from (a) the design, construction, ownership, operation, or maintenance of the Load Facility or Customer Attachment Facilities; (b) Customer’s performance or non-performance under this Agreement; (c) Customer’s violation of Environmental Law or release of Hazardous Substances by Customer or arising from the Load Facility or the Customer Attachment Facilities;
(d) pre-existing environmental contamination encountered or exacerbated by Customer on property conveyed by Customer to Transmission Owner or pre-
PDF page 28
existing environmental contamination that Customer encounters or exacerbates on Transmission Owner’s property; (e) claims by Customer’s contractors, tenants, end users, or customers relating to interruptions or quality of service; (f) any claim by a third party that the Load Facility’s operation caused harm to other customers or affected systems; and (g) any cybersecurity incident, breach, or attack affecting, originating from, or arising out of the Load Facility, the Customer Attachment Facilities, or Customer’s systems, or Customer’s failure to comply with its physical or cybersecurity obligations under this Agreement, except, in each case, to the extent caused by the gross negligence or willful misconduct of a TO Indemnitee. 17.3
Indemnity Procedures. Transmission Owner shall promptly notify Customer of any claim; failure or delay shall not relieve Customer except to the extent materially prejudiced. Customer may assume the defense with counsel reasonably satisfactory to Transmission Owner, subject to Transmission Owner’s right to participate at its own expense and to retain separate counsel at Customer’s expense (limited to one additional firm) where it has different or additional defenses or a conflict of interest exists, or the claim involves potential criminal liability. Customer shall not settle any claim without Transmission Owner’s consent, not to be unreasonably withheld, conditioned, or delayed. If Customer fails to assume the defense, Transmission Owner may contest, settle, or pay the claim at Customer’s expense. The amount owed shall be the actual Loss, net of insurance or other recovery. 17.4
No Consequential Damages; Limitation of Liability. EXCEPT FOR (A) INDEMNIFICATION OBLIGATIONS FOR THIRD-PARTY CLAIMS UNDER
THIS ARTICLE 17; (B) DAMAGES ARISING FROM A PARTY’S GROSS
NEGLIGENCE OR WILLFUL MISCONDUCT; (C) DAMAGES RESULTING
FROM A BREACH OF ARTICLE 19; AND (D) AMOUNTS PAYABLE BY
CUSTOMER UNDER THIS AGREEMENT, THE COST RECOVERY
AGREEMENT, THE SECURITY AGREEMENT, OR OTHER SEPARATE
AGREEMENTS LISTED IN EXHIBIT G (INCLUDING TERMINATION
COSTS UNDER SECTION 2.6), NEITHER PARTY SHALL BE LIABLE TO
THE
OTHER
FOR
ANY
SPECIAL,
INDIRECT,
INCIDENTAL,
CONSEQUENTIAL, EXEMPLARY, PENAL, OR PUNITIVE DAMAGES,
INCLUDING DELAYS, LOSS OF PROFIT OR REVENUE, LOSS OF USE OF
EQUIPMENT, LOSS OF DATA, BUSINESS INTERRUPTION, COST OF
CAPITAL, COST OF TEMPORARY EQUIPMENT OR SERVICES, OR
CLAIMS OF SUPPLIERS AND CUSTOMERS, WHETHER IN CONTRACT,
TORT (INCLUDING NEGLIGENCE), STRICT LIABILITY, OR OTHERWISE,
AND WHETHER OR NOT SUCH DAMAGES WERE REASONABLY
FORESEEABLE. IN ADDITION, EXCEPT FOR ITS GROSS NEGLIGENCE
OR WILLFUL MISCONDUCT, TRANSMISSION OWNER’S AGGREGATE
LIABILITY TO CUSTOMER ARISING OUT OF OR RELATING TO THIS
AGREEMENT SHALL NOT EXCEED THE LESSER OF [$1,000,000] OR TWO
PERCENT (2%) OF THE AMOUNTS PAID BY CUSTOMER TO
TRANSMISSION OWNER UNDER THIS AGREEMENT [AND THE COST
RECOVERY AGREEMENT].
PDF page 29
ARTICLE 18 INSURANCE
18.1
Required Coverage. As applicable, Customer shall, as determined by Transmission Owner in its sole discretion, at Customer’s own expense, procure and maintain throughout the Term, with insurers licensed in, or eligible surplus lines carriers in, the State of New York rated A- (VIII) or better by A.M. Best, the following minimum coverages:
(1) Workers’ Compensation (statutory) and Employers’ Liability with limits of not less than $1,000,000 per accident, including coverage under the U.S. Longshore and Harbor Workers’ Compensation Act and Federal
Employers’ Liability Act where applicable;
(2) Commercial General Liability on ISO Form CG 00 01 or equivalent, including premises and operations, products and completed operations, contractual liability, independent contractors, explosion, collapse, and underground hazards, with limits of not less than $2,000,000 per occurrence and $2,000,000 in the aggregate;
(3) Automobile Liability covering owned, non-owned, and hired vehicles with a combined single limit of not less than $1,000,000 per accident;
(4) Umbrella/Excess Liability in excess of the foregoing with limits of not less than $20,000,000 per occurrence and in the aggregate;
(5) Contractor’s Pollution Liability with limits of not less than $[7,500,000] per occurrence and in the aggregate;
(6) Cyber/Network Security and Data Privacy Liability with limits of not less than $[10,000,000] per occurrence and in the aggregate;
(7) Professional Liability of not less than $[3,000,000] (or $[5,000,000] for structural design services) where professional services are performed, and Builder’s Risk coverage during construction;
(8) Property insurance on an “all risk” basis covering the Load Facility and Customer Attachment Facilities; and
(9) Premises Pollution Liability with limits of not less than $[____] for property conveyed by Customer to Transmission Owner.
18.2
Additional Insureds; Primary Coverage; Subrogation. The liability policies required of Customer shall name Transmission Owner, its Affiliates, and their respective directors, officers, and employees as additional insureds, shall be primary and non-contributory, and shall contain waivers of subrogation. All policies required of Customer shall be issued in the name of, or expressly cover, the Customer entity executing this Agreement, and not solely a parent or Affiliate. Customer shall be responsible for its deductibles and retentions. Claims-made policies shall be maintained for at least three (3) years after termination. 18.3
Certificates and Notice. Upon execution of this Agreement and upon each renewal, Customer shall provide Transmission Owner certificates of insurance and
PDF page 30
shall give at least thirty (30) Calendar Days’ prior written notice of cancellation, non-renewal, or material change.
18.4
Self-Insurance. Customer, if its senior debt is rated investment grade by Standard & Poor’s, Moody’s, or Fitch, may self-insure to meet these requirements upon notice and evidence that its program meets the minimum requirements. 18.5
Contractors; No Limitation. Customer shall cause its contractors and subcontractors to maintain, as applicable, the insurance described in Article 18.1 with additional insured status and waivers of subrogation in favor of Transmission Owner. The insurance requirements shall not limit Customer’s liability. All amounts are in U.S. Dollars. Transmission Owner may reasonably adjust required limits upon annual review. Each Party shall report to the other in writing all accidents or occurrences resulting in injury or property damage arising out of this Agreement.
ARTICLE 19 CONFIDENTIALITY
19.1
Confidential Information. “Confidential Information” means non-public information furnished by a Party in connection with this Agreement that is identified in writing as confidential at or promptly after disclosure, or that reasonably should be understood to be confidential, including system plans, studies, specifications, operating procedures, and customer-specific usage data, and information designated confidential under the NYISO Code of Conduct. 19.2
Exclusions. Confidential Information does not include information that the receiving Party can demonstrate (a) is or becomes publicly available other than through its breach; (b) was lawfully in its possession on a non-confidential basis;
(c) was supplied by a third party without restriction; (d) was independently developed; or (e) is required to be disclosed by law, subpoena, or Governmental Authority [, including pursuant to Article 6 of the New York Public Officers Law (FOIL)], or is necessary in a proceeding to enforce this Agreement. 19.3
Obligation and Standard of Care. During the Term and for three (3) years thereafter (or, with respect to Critical Energy/Electric Infrastructure Information and information concerning the physical or cyber security of the TO System, for so long as such information remains non-public), each Party shall hold the other’s Confidential Information in confidence, use it solely to perform this Agreement and its regulatory obligations, and protect it with at least the same care it uses for its own confidential information, but no less than reasonable care.
19.4
Permitted Disclosures. A Party may disclose Confidential Information to its Affiliates, employees, contractors, consultants, professional advisors, prospective financiers, and permitted assignees on a need-to-know basis, provided they are bound by confidentiality obligations, and the disclosing Party shall remain responsible for their compliance.
19.5
Compelled Disclosure. If disclosure is requested or required by a court or Governmental Authority, the receiving Party shall give the other prompt notice so
PDF page 31
it may seek a protective order, shall cooperate in seeking confidential treatment, and may disclose only what its counsel advises is legally required. Disclosures to FERC, the NYPSC, or a state regulatory body in a confidential investigation shall be handled consistent with applicable rules.
19.6
Rights; No Warranties; Return. Each Party retains all rights in its Confidential Information. No Party warrants the accuracy or completeness of Confidential Information. Upon termination or written request, the receiving Party shall return or destroy Confidential Information, except one archival copy.
19.7
Equitable Relief. Monetary damages may be inadequate for a breach of this Article 19, and the non-breaching Party shall be entitled to seek injunctive relief and specific performance in addition to other remedies.
19.8
Non-Disclosure Agreement; CEII. Critical Energy/Electric Infrastructure Information (“CEII”) shall be protected and disclosed only as permitted by 18 C.F.R. § 388.113, the Tariff, applicable NYISO procedures, and any FERC order. Transmission Owner may require Customer and its contractors, subcontractors, vendors, or agents to execute a separate non-disclosure agreement as a condition of receiving Confidential Information or CEII, and nothing in this Agreement shall limit, modify, or supersede any such non-disclosure agreement. ARTICLE 20 DISPUTE RESOLUTION
20.1
Notice and Informal Resolution. A Party asserting a dispute arising out of or relating to this Agreement (a “Dispute”) shall give written notice (a “Notice of Dispute”). The Dispute shall be referred to designated senior representatives of the Parties for good-faith negotiation.
20.2
Arbitration by Agreement. If the Dispute is not resolved within [thirty (30) / sixty (60)] Calendar Days after receipt of the Notice of Dispute, the Parties may, by mutual agreement, submit it to arbitration under Article 20.3. Absent such agreement, either Party may pursue any remedy available at law or in equity, including proceedings before FERC, the NYPSC, or a court identified in Article 14.3. Notwithstanding this Article 20, (a) either Party may at any time seek temporary, preliminary, or injunctive relief, or specific performance, from a court identified in Article 14.3 or from FERC or the NYPSC to prevent irreparable harm, protect system reliability or safety, or preserve the status quo, without first complying with Article 20.1; and (b) the informal resolution and arbitration procedures shall not delay or limit Transmission Owner’s exercise of its rights under Articles 2.4, 6.2, 7.4, and 8, or Customer’s payment obligations under Articles 6.3 and 6.4.
20.3
Arbitration Procedures. Any arbitration shall be conducted before a single neutral arbitrator, or, if the Parties cannot agree on one within ten (10) Calendar Days, a three-member panel (one appointed by each Party and a third selected by the two party-appointed arbitrators), each knowledgeable in electric utility matters and without substantial business relationships with either Party, under the Commercial Arbitration Rules of the American Arbitration Association, except as modified
PDF page 32
herein. The arbitrator(s) shall render a written, reasoned decision within ninety (90) Calendar Days of appointment, shall have no authority to modify this Agreement, and the decision shall be final, with judgment enterable in any court of competent jurisdiction, subject to appeal only on grounds permitted by the Federal Arbitration Act. Each Party shall bear its own costs, the cost of its appointed arbitrator, and one-half of the cost of the single or third arbitrator.
20.4
Continued Performance; Termination. Pending resolution, each Party shall continue to perform its obligations, subject to Article 6.4; provided that the pendency of a Dispute shall not suspend or toll any cure period under Article 16 or limit Transmission Owner’s rights described in Article 20.2(b). Whether a termination is proper shall not be subject to arbitration unless the Parties agree otherwise.
ARTICLE 21 REPRESENTATIONS AND WARRANTIES
Each Party represents and warrants to, and covenants and agrees with, the other, as of the Execution Date and throughout the Term, that:
21.1
it is duly organized, validly existing, and in good standing under the laws of its jurisdiction of organization and is qualified to do business in each jurisdiction where required to perform this Agreement;
21.2
it has all requisite power and authority to execute, deliver, and perform this Agreement, and this Agreement is its legal, valid, and binding obligation, enforceable in accordance with its terms, subject to bankruptcy, insolvency, and similar laws and general equitable principles;
21.3
the execution, delivery, and performance of this Agreement do not violate its organizational documents or any law, judgment, order, or material agreement binding on it; and
21.4
it has sought or obtained, or will seek or obtain, all Required Approvals necessary for its performance of this Agreement.
21.5
Additional Customer Representations. Customer further represents and warrants to, and covenants and agrees with, Transmission Owner, as of the Execution Date and throughout the Term, that (a) it has executed and delivered the Security Agreement and has provided the security required thereunder in the amounts and forms specified therein, and such security remains in full force and effect; and (b) the representations in Articles 21.1 through 21.4 are true and correct with respect to each Related Agreement to which Customer is a party. ARTICLE 22 ASSIGNMENT
22.1
Assignment. This Agreement may be assigned by a Party only with the other Party’s written consent, not to be unreasonably withheld, conditioned, or delayed; provided that (a) Transmission Owner may assign without consent to an Affiliate
PDF page 33
or successor with the legal authority and operational ability to perform; (b) Transmission Owner may assign without consent in connection with a sale, merger, restructuring, or transfer of all or substantially all of its assets, including the TO Attachment Facilities and the Customer Attachment Facilities, if the assignee assumes in writing all obligations hereunder; and (c) Customer may assign without consent for collateral security purposes to aid in financing the Load Facility, upon prompt notice to Transmission Owner. Any assignment by Customer (other than a collateral assignment) and any change of control of Customer shall require Transmission Owner’s prior written consent, not to be unreasonably withheld, conditioned, or delayed, and shall be conditioned on (i) the assignee assuming in writing all obligations under this Agreement, the Cost Recovery Agreement, the Security Agreement, and the other agreements listed in Exhibit G; (ii) the assignee posting replacement security under the Security Agreement before the assignment becomes effective and having a credit rating equal to or greater than that of Customer as of the date of assignment or providing such additional security under the Security Agreement as Transmission Owner reasonably requires; and (iii) Customer reimbursing Transmission Owner’s reasonable costs of administering the assignment or performing due diligence with respect to a change of control, including reissuing invoices and amending related contracts. Any financing obtained by Customer shall require the secured party to notify Transmission Owner before exercising assignment rights and to demonstrate compliance with Article 6.2 and Article 18. Any assignment in violation of this Article is void. No assignment by Customer shall release Customer or any existing security until the assignee’s replacement security has been posted and accepted. No assignment shall relieve a Party of, or enlarge, its obligations.
ARTICLE 23 MISCELLANEOUS
23.1
Binding Effect. This Agreement shall be binding upon and inure to the benefit of the Parties and their successors and permitted assigns.
23.2
Rules of Interpretation. Unless a contrary intention clearly appears: the singular includes the plural; references to any agreement, tariff, or law mean it as amended from time to time; references to Articles (including numbered subdivisions thereof) and Exhibits are to this Agreement; “including” means including without limitation; “hereunder,” “herein,” and similar words refer to this Agreement as a whole; and “from” means “from and including,” “to” means “to but excluding,” and “through” means “through and including.”
23.3
Compliance. Each Party shall perform in accordance with Applicable Laws and Regulations, Applicable Reliability Standards, and Good Utility Practice, and shall not be in Breach for compliance therewith; a Party becoming aware of such a situation shall promptly notify the other so the Parties may discuss an appropriate amendment.
23.4
Comparability. The Parties shall comply with all applicable comparability and code of conduct laws, rules, and regulations.
PDF page 34
23.5
Several Obligations. The obligations of the Parties are several, and not joint or joint and several.
23.6
Entire Agreement. This Agreement and the Related Agreements are intended to operate together and shall be interpreted consistently with one another. This Agreement, including its Exhibits and the Related Agreements, constitutes the entire agreement of the Parties with respect to its subject matter and supersedes all prior understandings, oral or written.
23.7
No Third-Party Beneficiaries. Except for the TO Indemnitees under Article 17.2, this Agreement is solely for the benefit of the Parties and their successors and permitted assigns.
23.8
Waiver. No waiver shall be effective unless in writing and signed by the waiving Party, and no waiver of any Breach shall be a waiver of any other or subsequent Breach. Failure to insist on strict performance shall not constitute a waiver. 23.9
Amendment. This Agreement, including its Exhibits, may be amended by a written instrument executed by both Parties, effective upon satisfaction of any requirements of Applicable Laws and Regulations.
23.10 Reservation of Rights. Transmission Owner reserves the right to make unilateral filings with any appropriate regulatory agency or Governmental Authority to modify this Agreement as permitted by law, and Customer reserves its right to protest any such filing.
23.11 Severability. If any provision is finally determined to be invalid or unenforceable by a court or Governmental Authority, the remaining provisions shall continue in full force and effect.
23.12 Headings. Headings are for convenience only and do not affect interpretation. 23.13 Counterparts; Electronic Signatures. This Agreement may be executed in counterparts, each of which shall be an original and all of which together constitute one instrument. Electronic signatures shall be deemed originals. 23.14 No Partnership. Nothing in this Agreement creates a partnership, joint venture, agency, or fiduciary relationship, and neither Party may bind the other. 23.15 Contractors and Subcontractors. Either Party may use contractors and subcontractors, provided that each Party requires its contractors and subcontractors to comply with applicable terms of this Agreement and remains primarily liable for their performance. Notwithstanding the foregoing, all materials, equipment, vendors, contractors, and subcontractors used by or for Customer for work on existing or future Transmission Owner facilities shall be approved in advance in writing by Transmission Owner. Transmission Owner shall not be liable for the acts or omissions of Customer or its contractors or subcontractors with respect to Customer’s obligations under Article 5. Subcontractor obligations shall not be limited by any limitation of the subcontractor’s insurance.
23.16 Physical and Cyber Security Arrangements. Customer shall comply with the physical, operational, and cyber-security requirements set forth in Exhibit B, TO
PDF page 35
Standards, and applicable NERC Critical Infrastructure Protection standards, and shall implement and maintain cybersecurity controls consistent with recognized industry best practices appropriate to the systems used in the performance of this Agreement.
IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their duly authorized representatives as of the Execution Date.
[LEGAL NAME OF TRANSMISSION
OWNER]
By: _______________________________
Name:
Title:
Date: _____________________________
[LEGAL NAME OF CUSTOMER]
By: _______________________________
Name:
Title:
Date: _____________________________
PDF page 36
EXHIBIT A – LARGE LOAD PROJECT AND CUSTOMER
ATTACHMENT FACILITIES
1. Description of Large Load Project
[Insert description of Large Load Project]
2. Customer Attachment Facilities
[Insert description of Customer Attachment Facilities]
PDF page 37
EXHIBIT B – POINT(S) OF INTERCONNECTION AND
POINT(S) OF CHANGE OF OWNERSHIP, TO ATTACHMENT
FACILITIES, AND NETWORK UPGRADE FACILITIES
1. Point(s) of Interconnection (“POI”)
[Insert description of Point(s) of Interconnection]
2. Point(s) of Change of Ownership (“PCO”)
[Insert description of Point(s) of Change of Ownership]
3. TO Attachment Facilities
[Insert description of TO Attachment Facilities]
4. Network Upgrades
a. Local Network Upgrades
[Insert description of Local Network Upgrades]
b. Non-local Network Upgrades
[Insert description of Non-local Network Upgrades]
5. Affected Systems
[Insert description of any Network Upgrades for Affected Systems and reference related agreement (e.g., Engineering, Procurement, and Construction Agreement)]
6. External Affected Systems
[Insert description of upgrades required on External Affected Systems]
7. Phasor Measurement Unit Responsibilities
[Describe PMU responsibilities, if applicable, or specify “none.”]
8. Metering, Telemetry, and Security Requirements
[Insert Metering Equipment configuration, CT/PT ratios, approved meter model [NYTO- SPECIFIC PROVISION], interval data requirements, telemetry points, RTU and communication protocols, data retention requirements, and physical, operational, and cyber-security requirements.]
PDF page 38
EXHIBIT C – SIMPLIFIED ONE-LINE DIAGRAM
[Parties to insert simplified one-line diagram that clearly shows Customer Attachment Facilities, TO Attachment Facilities, Network Upgrades, POI, and PCO]
PDF page 39
EXHIBIT D – MILESTONES
[If applicable: Where the interconnection of the Load Facility requires facilities or upgrades to be constructed by an Affected Transmission Owner, the provision of service to the Load Facility is also dependent upon completion of the milestones set forth in Customer’s agreement(s) with such Affected Transmission Owner(s).]
[Insert table of Milestones]
PDF page 40
EXHIBIT E – OPERATING REQUIREMENTS
[Transmission Owner to insert a high-level description of the operating requirements applicable to the Load Facility, which may incorporate by reference Transmission Owner’s interconnection and operating requirements, as amended from time to time, including, as applicable, the following:]
PDF page 41
EXHIBIT F – CONDITIONS TO INITIAL ENERGIZATION AND
PARALLEL OPERATION
[Transmission Owner will provide the pre-conditions to service.]
PDF page 42
EXHIBIT G – COST RECOVERY, SECURITY, AND RELATED
AGREEMENTS
[List and/or copies of the Cost Recovery Agreement, the Security Agreement, and any related agreements.]
PDF page 43
EXHIBIT H – FORM OF COMMERCIAL OPERATION DATE
NOTICE
[Date]
[Transmission Owner Name and Address], with a copy to:
New York Independent System Operator, Inc.
Attn: Vice President, Operations
10 Krey Boulevard
Rensselaer, NY 12144
Re: [Load Facility]
This letter confirms that [Customer] commenced Commercial Operation of the Load Facility effective as of [Date].
Thank you,
[Signature] [Customer Representative]
PDF page 44
EXHIBIT I – ADDRESSES FOR NOTICES AND BILLINGS
Notices – Transmission Owner: [●] Customer: [●]
Billings and Payments – Transmission Owner: [●] Customer: [●] Alternative Forms of Notice (telephone/email) – Transmission Owner: [●] Customer: [●] NYISO: interconnectionsupport@nyiso.com [confirm current address]