ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others

NYTOs 205: Proposed Revisions re: Integration of Large Loads

PDF page 1

Troutman Pepper Locke LLP
401 9th Street, N.W., Suite 1000
Washington, D.C. 20004
troutman.com
November 16, 2026

VIA ETARIFF
The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426

RE:  New York Transmission Owners
Section 205 Filing in Response to the Large Load Show Cause Order1

Docket No. ER27-___-000
Dear Secretary Reese:
Pursuant to section 205 of the Federal Power Act (“FPA”)2 and Rule 205 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure,3 Central Hudson Gas & Electric Corporation (“Central Hudson”), Consolidated Edison Company of New York, Inc. (“Con Edison”), New York State Electric & Gas Corporation (“NYSEG”), Niagara Mohawk Power Corporation d/b/a National Grid (“National Grid”), Orange and Rockland Utilities, Inc. (“O&R”), and Rochester Gas and Electric Corporation (“RG&E”) (collectively referred to herein as the “New York Transmission Owners” or “NYTOs”) submit for filing proposed revisions to the New York Independent System Operator, Inc. (“NYISO”) Open Access Transmission Tariff (“OATT” or “Tariff”)4 and certain pro forma agreements to address concerns the Commission raised in its June 18, 2026 Large Load Show Cause Order in Docket No. EL26- 69-000 that fall within the NYTOs’ responsibilities.5  In particular, the NYTOs submit with this filing letter the following:

1. Attachments A (clean) and B (marked): Tariff amendments to new Attachment LL of the OATT.  Attachment LL is being contemporaneously filed by the NYISO, and the NYTOs

1 N.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216 (2026) (“Large Load Show Cause Order” or “Show Cause Order”).
2 16 U.S.C. § 824d.
3 18 C.F.R. § 385.205 (2025).
4 The NYISO is submitting this filing in FERC’s eTariff system on the NYTOs’ behalf solely in the NYISO’s role as the Tariff Administrator.  The burden of demonstrating that the proposed Tariff amendments are just and reasonable rests on the NYTOs, the sponsoring parties.  If the NYISO has any comments on this filing, the NYISO will submit a separate pleading in this proceeding.  Unless otherwise defined herein, capitalized terms used in this transmittal letter shall have the meanings ascribed to them in the NYISO OATT.
5 See Show Cause Order, 195 FERC ¶ 61,216.

PDF page 2

November 16, 2026
Page 2

are sponsoring the following revisions to Attachment LL:  Section 44.1; Sections 44.2.2, 44.6.8, 44.7.3.1, 44.8.2.4.5, 44.8.3.1.1, 44.8.3.3, 44.10.4.4, 44.12.1.2, 44.12.1.8, 44.14.1, and 44.14.3.2; new Section 44.14.3.5; and new Sections 44.16.8 through 44.16.11 (Appendices 8 through 11 to Attachment LL);

2. Attachments C (clean) and D (marked): Tariff amendments revising Section 5 of the OATT, the definitions in Sections 1.18 and 1.20, and Attachment B of Section 8 of the OATT;6

3. Attachment E: Pro Forma Large Load Cost Recovery Agreement (“CRA”);
4. Attachment F: Pro Forma Large Load Security Agreement;
5. Attachment G: Pro Forma Facilities Study Agreement;
6. Attachment H: Pro Forma Large Load Interconnection Agreement; and
7. Attachment I: Panel Testimony and exhibit of Brian McNierney, Carol Teixeira, Yan Flishenbaum, and Stacy Powers.

I. EXECUTIVE SUMMARY
The NYTOs submit this filing under section 205 of the FPA and their reserved filing rights under section 3.10(a) of the NYISO-TO Agreement7 to address the concerns the Commission identified in the Large Load Show Cause Order that fall within the NYTOs’ responsibilities.  This filing complements, and is submitted in parallel with, the NYISO’s section 205 filing establishing new Large Load Integration Procedures in Attachment LL of the OATT.  The substantial majority of the proposed tariff revisions submitted herewith are amendments to the currently effective NYISO OATT.  In addition, certain amendments submitted in exercise of the NYTOs’ unilateral filing rights propose to amend revisions to the NYISO OATT sponsored by the NYISO in its contemporaneous section 205 filing.8  While the NYISO’s filing establishes the study process, readiness requirements, and new Firm and Non-Firm Withdrawal Services for Large Loads, the NYTOs’ filing addresses the complementary elements necessary to recover the costs of facilities built to serve Large Loads, to protect other customers from cost shifts, and to integrate Large Loads reliably onto the NYTOs’ systems.

6 The NYTOs’ proposed revisions to Section 1.20 and Attachment B of Section 8 of the OATT are added to pending tariff changes as proposed by the NYISO’s companion section 205 filing.
7 NYISO, Foundation Agreements, Agreement Between New York Independent System Operator and Transmission Owners (0.0.0) (“NYISO-TO Agreement”).
8 These sections include the following: (1) Attachment LL; (2) Attachment B of Section 8; and (3) Section 1.20 of the NYISO OATT.  Accordingly, when proposing changes to the NYISO companion filing, the NYTOs accepted the NYISO’s proposed changes and then marked the NYTOs’ proposed changes as though the NYISO’s proposed changes were accepted.

PDF page 3

November 16, 2026
Page 3

Specifically, the NYTOs propose four pro forma agreements.  First, a pro forma CRA allows each Transmission Owner to recover 100% of the costs of Network Upgrades and Attachment Facilities allocated to a Large Load Customer through a formula rate applicable exclusively to Large Load Customers (“Large Load Formula Rate”) that compresses cost recovery into a 15-year term without accelerated depreciation.  Second, a pro forma Large Load Security Agreement requires the Large Load Customer to post security for those allocated costs, which the Transmission Owner may draw upon in the event of abandonment of a Large Load project, default, or other specified events.  Third, a pro forma Facilities Study Agreement provides a uniform framework, fixed study deposits, and a defined schedule for the Facilities Studies the Transmission Owners perform under Attachment LL.  Fourth, a pro forma Large Load Interconnection Agreement establishes the terms and conditions for interconnecting a Large Load, ties service levels and operating requirements to studied load, and incorporates the CRA and Security Agreement.

The NYTOs also propose targeted revisions to Attachment LL that fall within NYTO responsibilities and supplement Attachment LL as proposed by the NYISO.  These revisions:  (i) add definitions, including Franchise Utility, Large Load Customer, and Retail Tariff; (ii) integrate the Facilities Study Agreement into the NYISO’s study timeline through execution, deposit, and withdrawal deadlines; (iii) include a covenant that each NYTO will not recover Large Load upgrade costs from other FERC-jurisdictional customers without explaining the associated rate treatment and revenue credits; (iv) limit Non-Firm Withdrawal Service to thermal and resource adequacy constraints; (v) establish new operating requirements that preserve each Transmission Owner’s authority to maintain bulk and local system reliability, including through requests to the NYISO to reduce Non-Firm withdrawals; and (vi) establish disconnection requirements or capabilities.

Finally, the NYTOs propose revisions to Section 5 of the OATT, and conforming definitions in Sections 1.18 and 1.20, to extend the existing retail access framework to Large Loads and Eligible Customers9 serving Large Loads.  The NYTOs do not propose new delivery rates. Instead, consistent with the cooperative federalism framework the Commission has accepted since the NYISO’s existence, and recognizing that the NYTOs’ transmission and distribution rates are bundled, Section 5 will continue to reference the voltage-differentiated delivery rates and service classifications approved by the New York Public Service Commission (“NYPSC”) or the Long Island Power Authority (“LIPA”) Board of Trustees, including optional classifications that allow Large Loads that are dispatched down or otherwise reduce load to reduce their delivery charges. Because the first Large Loads under the NYISO’s new procedures are not expected to complete Facilities Studies until Q3 2028, the NYTOs request that the Commission allow the NYPSC to address any changes to delivery rates serving Large Loads in the NYPSC’s pending proceeding in

9 NYISO OATT, Section 1.5 defines “Eligible Customer” as an entity that is engaged, or proposes to engage, in the wholesale or retail electric power business, including any electric utility, power marketer, Federal power marketing agency, or any person generating Energy for sale for resale, is an Eligible Customer under the Tariff. Electric energy sold or produced by such entity may be electric energy produced in the United States, Canada or Mexico.

PDF page 4

November 16, 2026
Page 4

the first instance, and the NYTOs commit to make any necessary filing with the Commission before those rates take effect.10

Together with the NYISO’s filing, these proposals provide a robust framework for the study, interconnection, cost recovery, and operation of Large Loads in New York that is just and reasonable, not unduly discriminatory or preferential, and protective of other transmission customers.

This filing is without prejudice to and does not take any position concerning the scope of the NYPSC and FERC jurisdiction over the subject matter contained in this filing.  Rather, since the start of the NYISO’s operations in 1999, the NYTOs have relied on cooperative federalism. The NYPSC has been the sole entity to conduct proceedings to establish retail delivery rates for transmission and distribution services to retail customers unbundled from the supply function.  The NYTOs included references in Section 5 of the NYISO OATT to the delivery rates, terms and conditions contained in their rate schedules authorized by and on file with the NYPSC, as they may be modified or superseded from time to time.

As explained in more detail below, the NYTOs propose to continue a system that has worked since the NYISO’s existence (27 years) to produce retail delivery rates without a major dispute that required FERC intervention.  Accordingly, while the NYTOs believe that this cooperative federal-state framework can and should continue to provide solutions to Large Load procedures and rates addressed in this proceeding, they reserve all jurisdictional positions in the hope that they can continue to satisfy both regulators without creating jurisdictional disputes.11 The NYTOs respectfully request that the Commission accept the instant filing, effective on the various effective dates described below.

II. BACKGROUND
A. The Large Load Show Cause Order
On June 18, 2026, the Commission issued the Show Cause Order, instituting a proceeding under FPA section 206 based on the Commission’s preliminary finding that the NYISO’s OATT12 appears to be unjust, unreasonable, or unduly discriminatory or preferential.13  The Commission issued the Large Load Show Cause Order as part of a suite of six coordinated orders directed to each of the Regional Transmission Organization/Independent System Operator regions subject to the Commission’s jurisdiction.

10 NYPSC Case No. 26-E-0045, Proceeding on Motion of the Commission to Address Interconnection Reforms for Large Loads, Order Instituting Proceeding and Soliciting Comments (Feb. 12, 2026).
11 The NYTOs appreciate that the Commission’s “objective in this proceeding is to respect the cooperative federalism approach established under the FPA.”  Show Cause Order, 195 FERC ¶ 61,216 at P 76. 12 Capitalized terms not otherwise defined herein have the meanings set forth in the NYISO OATT or Market Administration and Control Area Services Tariff, as applicable.
13 Show Cause Order, 195 FERC ¶ 61,216 at P 3.

PDF page 5

November 16, 2026
Page 5

The Large Load Show Cause Order included preliminary findings that the NYISO’s Tariff appears unjust and unreasonable in five principal respects:

1.  Transmission Service Study Process for Large Loads.  The Commission
preliminarily found that the NYISO’s Tariff lacks sufficiently clear and consistent provisions addressing: (a) a definition of Large Load as a distinct category of load; (b) a mandatory application process, readiness requirements, and study procedures for Eligible Customers seeking transmission service on behalf of Large Loads; (c) study timelines of no more than 60-90 calendar days; (d) ongoing operational requirements – including telemetry, data reporting, remote disconnect capability, ramp rate and ride-through requirements, and protection systems – for transmission customers serving Large Loads; (e) evaluation of alternative transmission technologies as potential solutions in lieu of or in addition to traditional Network Upgrades; and

(f) pro forma provisions in transmission service agreements to memorialize operational requirements.14

2.  Cost Transparency and Cost Recovery.  The Commission preliminarily found that the NYISO Tariff lacks: (a) robust, centralized, publicly accessible data on its website regarding the Network Upgrades and associated costs needed to provide transmission service to Eligible Customers on behalf of Large Loads; and (b) a pro forma CRA between the NYISO, the relevant Transmission Owner, and the Eligible Customer taking transmission service on behalf of a Large Load, with a minimum financial contribution and credit support requirement sufficient to mitigate the risk of cost shifting among transmission customers.15

3.  Co-Location Arrangements and Behind-the-Meter Generation.  The Commission
preliminarily found that the NYISO’s Tariff lacks: (a) a definition of co-located load; (b) sufficiently clear and consistent provisions governing the rates, terms, and conditions of service applicable to interconnection customers serving co-located load, including required ancillary service charges (regulation and black start service on a gross demand basis); and (c) provisions addressing netting of behind-the-meter generation from gross load for purposes of calculating applicable Transmission Service Charges in a manner consistent with the cost causation principle.16

4.  New Transmission Services for Eligible Load and Flexible Large Loads.  The Commission preliminarily found that the NYISO’s Tariff lacks transmission services that reflect the operational capabilities of Eligible Customers taking transmission service on behalf of Eligible Load (co-located load and load with behind-the-meter generation) and flexible Large Loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, specifically:  (a) an interim Non-Firm network transmission service available while

14 Id. PP 56-71.
15 Id. PP 77-91.
16 Id. PP 101-110.  See, e.g., Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868-69 (D.C. Cir. 2024) (“[T]he cost causation principle requires that ‘all approved rates reflect to some degree the costs actually caused by the customer who must pay them.’”) (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 88 (D.C. Cir. 2014)).

PDF page 6

November 16, 2026
Page 6

Network Upgrades are being constructed; and (b) permanent firm and Non-Firm contract demand transmission services.17

5.  Generator Interconnection for Electrically Proximate Large Load and Co-Located Load.  The Commission preliminarily found that the NYISO’s Tariff lacks generator interconnection study procedures and generator interconnection services tailored to reflect an interconnection customer’s commitment to limit a generating facility’s output to match the hourly forecast of an electrically proximate Large Load or large co-located load, thereby potentially reducing the need for Network Upgrades and accelerating the interconnection process.18 The Commission therefore directed the NYISO and the other named parties,19 within 60 days of issuance (i.e., by August 17, 2026), to either:  (1) show cause as to why the Tariff remains just and reasonable and not unduly discriminatory or preferential without provisions addressing the foregoing concerns; or (2) explain what Tariff changes would remedy those concerns were the Commission to determine that the Tariff is in fact unjust and unreasonable and to establish a replacement Tariff.20  Alternatively, the Commission indicated it would consider requests to hold the Show Cause Order proceeding in abeyance for up to 90 days to allow the NYISO and the other named parties time to “work through the stakeholder processes to develop FPA section 205 filings to revise the Tariff to address the issues raised in [the Show Cause Order].”21 On August 3, 2026, the NYISO, certain NYTOs, LS Power Grid New York Corporation I, and New York Transco, LLC submitted separate requests to hold the Show Cause Order proceeding in abeyance for 90 days.22  The Commission granted those requests in an August 14, 2026, order.23

B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement
As the NYTOs explained in their motion to hold the Show Cause Order proceeding in abeyance, the NYTOs have explicitly reserved FPA section 205 filing rights in section 3.10(a) of the NYISO-TO Agreement.24  Section 3.10(a) provides, in relevant part, that:

17 Show Cause Order, 195 FERC ¶ 61,216 at PP 109, 112-113.
18 Id. PP 121-127.
19 The following entities were named as parties to the Show Cause Order: NYISO, Central Hudson, Con Edison, NYSEG, National Grid, O&R, RG&E, LS Power Grid New York Corporation I, New York Transco LLC, and NextEra Energy Transmission New York, Inc.
20 See, e.g., Show Cause Order, 195 FERC ¶ 61,216 at P 3. 21 Id. P 42.
22 New York Power Authority (“NYPA”) and LIPA did not join the abeyance request because they were not named as parties to the Show Cause Order.
23 N.Y. Indep. Sys. Operator, Inc., 196 FERC ¶ 61,130 (2026).
24 NYISO-TO Agreement.

PDF page 7

November 16, 2026
Page 7

Each Transmission Owner shall have the right at any time
unilaterally to file pursuant to Section 205 of the Federal Power Act
to change the ISO OATT, a Service Agreement under the ISO
OATT, or the ISO Agreement to the extent necessary: (i) to recover
all of its reasonably incurred costs, plus a reasonable return on
investment related to services under the ISO OATT and (ii) to
accommodate implementation of, and changes to, a Transmission
Owner’s retail access program.25
Section 3.10(a) confers upon each Transmission Owner the unilateral right to file with the Commission under FPA section 205 – independent of the NYISO’s concurrence – to the extent necessary to recover reasonably incurred costs associated with services provided under the NYISO OATT and to accommodate changes to the NYTOs’ retail access programs.26

The Show Cause Order directly implicates the NYTOs’ ability to recover their reasonably incurred costs through rates filed with the Commission, including rates for recovery of costs of Network Upgrades and Attachment Facilities needed to provide transmission service to Eligible Customers on behalf of Large Loads,27 new study procedures and requirements applicable to Large Load Customers, and new services for Large Load Customers.  Accordingly, the NYTOs’ independent filing rights under section 3.10(a) of the NYISO-TO Agreement are directly exercisable with respect to key issues identified below.

Section 3.10(a) also provides an independent, second basis for the NYTOs’ exercise of their unilateral FPA section 205 filing rights that is equally applicable to certain key issues identified below:  the right to file “to accommodate implementation of, and changes to, a Transmission Owner’s retail access program.”  The Show Cause Order’s directives directly affect the NYTOs’ retail access obligations.  Specifically, the Show Cause Order requires that the NYISO OATT address eligibility for Large Load interconnection study procedures, the procedures themselves, terms of transmission service for Large Load Customers, cost transparency requirements, security and related cost recovery agreements, among other things.  Addressing each of these subjects, including through the associated new pro forma agreements submitted with this filing (the pro forma Facilities Study Agreement, Interconnection Agreement, Large Load Security Agreement, and CRA), all of which requires changes to the portion of Section 5 of the NYISO OATT that deals with each Transmission Owner’s retail access program and retail transmission and distribution services. Because the Tariff reforms at issue necessarily affect each NYTO’s retail

25 Id. § 3.10(a).
26 While the NYISO-TO Agreement recognized that OATT revisions are subject to NYISO stakeholder and governance requirements, it also excepted Section 3.10’s reservation of each Transmission Owner’s right to make unilateral section 205 filings.  See id. § 3.03 (providing that “[n]otwithstanding any other provision in this Agreement except for the provisions of Section 3.10,” proposed OATT revisions are subject to certain stakeholder and NYISO governance procedures (including review by the NYISO Board of Directors) before being filed at FERC) (emphasis added).
27 Show Cause Order, 195 FERC ¶ 61,216 at PP 20, 85.

PDF page 8

November 16, 2026
Page 8

access obligations, section 3.10(a) provides an additional, independent basis for the NYTOs’ filing authority over the OATT revisions and pro forma agreements proposed in this proceeding.

C. Stakeholder Processes
The NYTOs participated in the NYISO stakeholder process relating to this proceeding, culminating in the NYISO’s Management Committee’s unanimous approval with abstentions of the extensive FPA section 205 filing the NYISO makes in parallel with this filing.  Once the parameters of the NYISO filing were identified with reasonable particularity, and after extensive negotiations and meetings over the shared and divided responsibilities for Large Load interconnection processes, studies and reports, the NYTOs addressed the elements for which they were responsible and that the NYISO did not include in its filing.  The NYISO first presented its proposed filing at a special joint meeting of its Operating Committee and the Business Issues Committee on October 21, 2026.28

The NYTOs have unilateral section 205 filing rights that do not require any particular stakeholder process or votes.  Nevertheless, on October 22, 2026, the NYTOs presented their conceptual proposal to a joint meeting of the NYISO Transmission Planning Advisory Subcommittee, the Electric System Planning Working Group, and the Installed Capacity Working Group, the three bodies responsible for vetting the NYISO’s Large Load procedures.29

III. PROPOSED TARIFF REVISIONS AND PRO FORMA AGREEMENTS
The NYTOs have worked extensively in a concentrated time frame to develop with the NYISO new interconnection study procedures for Large Loads.  The NYTOs have assumed responsibility for significant aspects of the Large Load interconnection process, including:

• physical infeasibility screening;
• a preapplication process to lead to better-informed interconnection decisions by Large Loads;

• review and updating of NYISO base cases;
• identification of non-bulk transmission and distribution reliability violations;
• identification of upgrades to solve those violations in addition to the bulk system violations identified by the NYISO;

28
With certain revisions, the NYISO’s proposed filing was approved by the Management Committee on October 28, 2026.

29 See NYTO FPA Section 205 Filing on Certain Large Load Interconnection and Service Matters, NYISO TPAS/ESPWG/ICAP Meeting (Oct. 22, 2026), available at NYTO_Section_205_Large_Load_Deck_Final_TPAS_10.22.26.pdf.

PDF page 9

November 16, 2026
Page 9

• identification of Attachment Facilities; and
• estimates of the cost and time to construct all of the upgrades.
These elements are included in the NYISO FPA section 205 filing but are NYTO commitments to facilitate an improved Large Load interconnection process.  In contrast, this filing addresses complementary and necessary elements within the scope of the NYTOs’ reserved section 205 filing rights.

The NYTOs propose Tariff revisions and certain pro forma agreements regarding the following topics addressed in the Show Cause Order:  (1) Network Upgrade cost allocation and recovery and Attachment Facility cost recovery; (2) mechanisms to ensure that payments made pursuant to cost recovery agreements or Tariff provisions are appropriately credited toward each NYTO’s transmission revenue requirement to the extent such costs are included in such revenue requirements consistent with the Commission’s cost-of-service regulations and rates or formula rates accepted or approved by the Commission for each NYTO; (3) rates applicable to transmission services arranged by Eligible Customers on behalf of Large Loads; (4) certain operational requirements for Eligible Customers taking service on behalf of Large Loads and Large Loads themselves; and (5) a pro forma Large Load Interconnection Agreement, along with necessary agreements and Tariff changes to implement the foregoing.30

The NYISO Tariff already contains Commission-approved provisions pertaining to cost recovery that explicitly reference the New York Public Service Law, the enabling statute for the NYPSC.  For example, section 31.5.1.6 of the NYISO OATT, Attachment Y, with respect to cost recovery for Regulated Non-Transmission Projects, states in part, “[c]osts related to regulated non- transmission projects will be recovered by Responsible Transmission Owners, Transmission Owners, and Other Developers in accordance with the provisions of New York Public Service Law, New York Public Authorities Law, or other applicable state law.”31  Thus, tariff provisions proposed herein that explicitly reference mechanisms that are creatures of the New York Public Service Law are not invoking an unprecedented practice.

Overall, the NYTOs’ FPA section 205 filing contains the following tariff additions and pro forma agreements as complements to the NYISO section 205 Large Load filing:

• Complementary and necessary amendments to the NYISO’s proposed Attachment
LL to its OATT.
• Amendments to NYISO OATT Section 5 pertaining to various aspects of
Transmission Owners’ service to retail access customers as detailed below, as well

30 This is not intended to be an exclusive list of the items within the NYTOs’ unilateral FPA section 205 filing right and does not constitute a waiver of any NYTO filing right.
31 New York Independent System Operator, Inc. – NYISO Tariffs, Attachment Y, Section 31.5, Cost Allocation and Cost Recovery (32.0.0), § 31.5.1.6.

PDF page 10

November 16, 2026
Page 10

as revised rates to accommodate the Commission’s rate directives within the context of the NYISO construct.

• Amendments to Attachment B of Section 8 of the NYISO OATT, the pro forma Transmission Service Agreement (“TSA”), to add cross-references to Section 5 of the NYISO OATT.

In addition, the following three proposed pro forma agreements are intended to work together to ensure appropriate cost recovery and integration of Large Loads in a manner that avoids undue cost shifts to other transmission customers:

• A pro forma CRA recovering the allocated costs of Transmission Owner
Attachment Facilities and Network Upgrades to Large Load Customers as
explained in greater detail below.
• A pro forma Large Load Security Agreement, which sets forth the security posting requirements for the Large Load.

• A pro forma Large Load Interconnection Agreement which sets forth the terms and conditions for Large Load interconnection between the customer and the

Transmission Owner.
Finally, to meet its study responsibilities under the proposed Attachment LL construct, the NYTOs propose one additional pro forma agreement:

• A pro forma Facilities Study Agreement which establishes the scope of
Transmission Owner study work under Attachment LL and at the request of a Large Load Customer.

Each of these filing components is discussed in turn below following discussion on the jurisdictional status of this filing:

A. Jurisdictional Status of this Filing
In the Show Cause Order, in the context of transmission security agreements and construction service agreements, the Commission “declines to preliminarily find that cost recovery agreements between the transmission owner and the large load customer (rather than from the Eligible Customer taking transmission service on behalf of the large load customer) are necessary to ensure just and reasonable transmission rates, … [and] continue[s] to find that such agreements directly affect Commission-jurisdictional transmission rates.  Therefore, to the extent a Transmission Owner and a Large Load Customer enter into a cost recovery agreement (whether voluntary or pursuant to state law) through which the Large Load Customer guarantees

PDF page 11

November 16, 2026
Page 11

contributions to the transmission owner’s Commission-jurisdictional transmission revenue requirement, we find that such an agreement should be filed with the Commission.”32

The NYTOs present in this filing pro forma Large Load Facilities Study, Security, Cost Recovery, and Interconnection Agreements.  While they relate to the NYISO Large Load Integration Process as proposed in new Attachment LL of the NYISO OATT, they are not appropriate agreements for intermediaries between the Large Loads themselves and the NYTOs responsible for interconnection studies, cost recovery, associated security and interconnection, including certain operational reliability requirements.  In each of these contexts, the NYTOs have dealt directly with the Large Load Customers themselves, who are the financially responsible parties, and propose to continue this practice.

Historically, in New York, energy service companies (“ESCOs”) have provided
commodity supply unbundled from retail delivery services and have been Eligible Customers for purposes of the NYISO’s energy and capacity market settlements.  ESCOs have been Eligible Customers under the NYISO Tariffs for limited purposes, enabling retail access programs intended to introduce competition for supply, but not for purposes of retail customer interconnection studies and associated agreements to effect retail interconnections with grid owners.

ESCOs or other intermediaries have not functioned as the primary interfaces or
contracting parties in the interconnection process for new Large Loads.  This is not by accident; unlike serving as a supply source to enable retail access, ESCOs would serve no legitimate business function as an intermediary in the Large Load Interconnection Process.  In fact, their insertion would only serve to frustrate that process, making it riskier and, not insignificantly, costlier.

Until recently, the interconnection process for loads was subject to NYPSC regulation and not FERC regulation.  The interconnection of retail loads has been to facilitate local distribution of electric energy which the Commission found to be involved in every retail transmission transaction33 and to facilitate retail sales of electric energy.  These functions are subject to State jurisdiction, and the NYPSC regulates such functions.

32 Show Cause Order, 195 FERC ¶ 61,216 at P 88.
33 In Order No. 888, FERC stated: “while we believe in most cases there will be identifiable local distribution facilities subject to state jurisdiction, we also believe that even where there are no identifiable local distribution facilities, states nevertheless have jurisdiction in all circumstances over the service of delivering energy to end users.”  In re Promoting Wholesale Competition by Pub. Utilities, Order No. 888, 75 FERC ¶ 61,080 at 21,626 (1996) (subsequent history omitted).   FERC similarly noted in Order No. 888-B:  “We reiterate that we believe there is always a local distribution service element of a retail transaction, through which the state may impose charges on the retail customer.”  Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utilities Recovery of Stranded Costs by Pub. Utilities & Transmitting Utilities, Order No. 888-B, 81 FERC ¶ 61,248 at 62,098 (1997).

PDF page 12

November 16, 2026
Page 12

The NYISO relatively recently has been more involved in considering bulk power system impacts associated with certain large retail load interconnection requests.  The Show Cause Order asks for clear and transparent rules governing the interconnection of Large Loads.  The NYISO will continue to analyze bulk system impacts and violations caused by the interconnection of Large Loads.  The Transmission Owners, however, are responsible for significant aspects of the Large Load interconnection process, including:

• physical infeasibility screening;
• a preapplication process to lead to better-informed interconnection decisions by Large Loads;

• review and updating of NYISO base cases;
• identification of non-bulk transmission and distribution reliability violations;
• identification of upgrades to solve those violations in addition to the bulk system violations identified by the NYISO;

• identification of Attachment Facilities; and
• estimates of the cost and time to construct all of the upgrades.

The Transmission Owners have extensive experience in handling all forms of retail load interconnection studies and entering into appropriate agreements which have not been subject to FERC jurisdiction or filing requirements.  Each of the six NYTOs has its own forms of agreement.  In response to the Show Cause Order, however, the NYTOs have worked to adopt standardized procedures and forms of agreement to make the process more transparent and easier to navigate.

The Transmission Owners, however, do not agree that the interconnection study process, upgrade and attachment facility cost recovery, associated security and interconnection and operational reliability requirements should be subject to the insertion of an intermediary between the Large Load Customer and the Transmission Owners responsible for a substantial majority of the interconnection study process, building upgrades and Attachment Facilities and maintaining system reliability, including through operating and interconnection requirements.

In the compressed time that the NYTOs have to handle the tasks listed above, direct communications with the Large Load Customer will be necessary in order to have an efficient and effective interconnection study process which inevitably involves discussions with many customers simultaneously.  ESCOs or other intermediaries have not played a significant role in these processes, are not the ultimate parties-in-interest (i.e., the transactions and services addressed by the pro forma agreements bear no relationship to the supply services ESCOs are engaged by customers to perform) and FERC should not enter the process now.

Once the Facilities Study is issued, each Large Load Customer will have a short period of time to enter into a Security Agreement on a Transmission Owner-specific basis for each Upgrade that the Transmission Owner has identified and to secure the Attachment Facility and Network Upgrade costs.  Some upgrades will cost tens or even hundreds of millions of dollars. It is not realistic to have ESCOs or intermediaries cover such large security amounts without

PDF page 13

November 16, 2026
Page 13

relying on the Large Load Customer directly, and expanding such agreements to cover a superfluous party adds risk, delay, and complexity that should be avoided.

Once security is posted, the relevant Transmission Owner(s) will enter into the CRA, Security Agreement, and Large Load Interconnection Agreement with the Large Load Customer (as required by the NYISO’s revisions in proposed Attachment LL section 44.12.1.8) rather than the Eligible Customer.  The CRA as proposed is a long-term agreement and may involve the recovery of tens or even hundreds of millions of dollars in upgrade and attachment facility costs. As noted, ESCOs will be dependent on the Large Load Customers themselves, and if there is a default, the Transmission Owners will be seeking redress directly through the security provided by the Large Load Customer.  Interjecting a third-party intermediary between the Large Load Customer and the Transmission Owners only complicates remedies when needed on short notice and increases risk and costs with high stakes involved.  The goal of avoiding stranded costs being shifted to other customers would not be served by adding intermediaries to the contracting process.

The Interconnection Agreement with Large Load Customers will identify facilities needed to reliably interconnect the customer to the retail franchise utility’s system.  Any special operating conditions that are required will need to be followed by the Large Load Customer, not an ESCO.  The ability to operate a Large Load associated with dispatch instructions, ramping, curtailment, disconnect and restoration will be handled by the Large Load Customer and not by an ESCO or other intermediary, and system reliability will depend on this relationship, direct communication and prompt responsiveness.

The NYTOs do not in this filing or in the companion NYISO filing offer to provide voluntary retail transmission, distribution or delivery services.  They provide such services only as directed by the NYPSC or in accordance with NYPSC policy.  They do not volunteer to enter into Facilities Study, Security, Cost Recovery, and Interconnection Agreements with ESCOs or other intermediaries of Large Load Customers.  It would not be just and reasonable to require such arrangements, and if they were required, it would raise troubling issues associated with 16 U.S.C. § 824k(h).

As discussed in the context of the delivery rates identified in Section 5 of the NYISO OATT and as proposed to be modified in this filing, the NYTOs plan to continue the practice in effect since NYISO started applying NYPSC-determined delivery rates for Large Load Customers as well as for other retail customers.  Cooperative federalism, expressly recognized as a goal of the Commission in the large load context,34 has worked for 27 years whereby the Commission accepted NYPSC-determined rates, terms, and conditions for retail delivery services.  If the Commission were to accept this filing, subject to any amendments the NYTOs make in response to further orders of the NYPSC, the NYTOs would once again seek to satisfy both regulators without endangering jurisdictional or preemption disputes.

34 See Show Cause Order, 195 FERC ¶ 61,216 at P 76.

PDF page 14

November 16, 2026
Page 14

The Commission expressed concerns that the rates the Transmission Owners charge Large Load Customers for Network Upgrades and the associated security agreements may affect other Commission-jurisdictional rates.  The NYTOs have adopted a covenant in the NYISO proposed Section 44.12.1.8 of Attachment LL whereby each NYTO covenants not to include costs recovered through such CRA or Security Agreement in rates for other FERC-jurisdictional transmission customers without an accompanying revenue credit and an explanation of the rate treatment.  This covenant is to directly address the impacts that Large Load Customer interconnections can have on other FERC-jurisdictional rates.

The NYTOs recognize that the Commission may determine that it does not have
jurisdiction over some aspects of the Large Load Integration Process, particularly those elements filed herewith.  The NYTOs reserve the right to submit any agreements, rates, terms and conditions associated with Large Loads to the NYPSC.  As noted below in this filing, the NYPSC commenced a proceeding in February 2026 concerning Large Load matters.  The NYTOs reserve the right to amend this filing based on further guidance and direction from the NYPSC.

The NYTOs, however, submit this filing to be responsive to the Show Cause Order and to provide interested stakeholders an integrated process and forms applicable to Large Load Integration Procedures.

B. Network Upgrade Cost Recovery
The NYTOs submit with this filing a pro forma CRA to recover the costs of Network Upgrades and Attachment Facilities identified by each Transmission Owner in its Large Load Facilities Studies in accordance with NYISO OATT Attachment LL.  The proposed pro forma CRA may be used by as many as three different types of Transmission Owners with a single Large Load Customer.  First, upgrades required to accommodate a Large Load Customer may be limited to a single Transmission Owner, which is often the Connecting Transmission Owner (“CTO”) that owns the transmission facility at the proposed point of interconnection and which is also the retail distribution utility.  Second, a Transmission Owner that owns the line at the proposed point of interconnection (the CTO) may not have a Certificate of Public Convenience and Necessity under Section 68 of the New York Public Service Law to serve retail load at the requested location.  In such a case, the franchise distribution utility with the right to serve retail load, which is not the CTO, will need to install and/or own the retail meter and appurtenant facilities and the Transmission Owner that owns the facility at the proposed point of interconnection will have to modify its facilities and construct any necessary upgrades on its facilities/system.  Third, in either of these cases, the Large Load Customer may cause reliability violations on another ATO’s system. Accordingly, the CTO that is also the retail distribution utility for the Large Load, a CTO that is not the retail utility, and one or more Affected Transmission Owners (“ATOs”), each would need a CRA to recover its costs of the Network Upgrades and Attachment Facilities to interconnect a Large Load Customer.

Under the CRA, each Transmission Owner will recover 100% of its costs of Network Upgrades and Attachment Facilities from Large Load Customers.  For each Network Upgrade or

PDF page 15

November 16, 2026
Page 15

Attachment Facility that is to mitigate or remedy violations caused by more than one project of a Large Load Cluster, the costs of the associated upgrade shall be allocated in accordance with the Allocation Factors identified in the Facilities Study (see discussion of the Facilities Study below). When the CTOs and ATOs complete the Facilities Studies for a Cluster under the NYISO Large Load Integration Procedure (“LLIP”), each Large Load project will be required to post cash or a letter of credit as security for the Network Upgrades and Attachment Facilities assigned to it in the Facilities Study.  A Large Load’s failure to timely post security will result in removal of the Large Load from the LLIP.  If a Large Load that had responsibility for a Network Upgrade shared with one or more other customers in the Cluster is removed from the Cluster, then either:  (a) the other Large Load(s) with shared responsibility for a Network Upgrade will have new allocations of the cost of the upgrade and new security posting requirements, or (b) the CTO or ATO that identified the Network Upgrade may determine that the Network Upgrade is no longer required, and the remaining Large Load(s) will no longer be responsible for that upgrade.  Prior to the issuance of the first Cluster under the NYISO’s November 16, 2026 FPA section 205 Large Load filing, the NYTOs plan for the NYISO or the NYTOs to make a filing under the FPA to adopt procedures governing a failure of one or more projects in the then-current Cluster to timely post required security and the reallocation of costs of such upgrades, unless the upgrade is no longer needed.

Under the CRA, each Transmission Owner would recover the allocable share of the costs of the Network Upgrade(s) and Attachment Facilities over a 15-year period, as described further below.  In each LLIP Cluster, the upgrade costs will be recovered from the Large Load Customer that causes the violation giving rise to the Network Upgrade(s) and Attachment Facilities.  Where more than one Large Load contributes to a violation resulting in an upgrade, costs shall be allocated in accordance with the procedures discussed below.

Under the proposed NYISO LLIP, the NYISO is responsible for identifying violations and overloads on the Bulk Power System caused by the interconnection of a Large Load following the LLIP.  When more than one Large Load contributes to a violation, the NYISO provides contribution factors.  Each CTO and ATO is responsible for identifying:  (a) violations on the non- Bulk Electric System, including local transmission and distribution systems, (b) the Network Upgrades to address both bulk system and non-bulk violations (subject to consultation with the NYISO), (c) cost estimates and time to construct the Network Upgrades, (d) the allocation of costs among the Large Loads following the LLIP Cluster based on the NYISO- and NYTO-determined contribution factors, (e) Attachment Facilities, and (f) estimates of Attachment Facility costs and time to construct.

Consistent with the Show Cause Order, the NYTOs provide with this filing a pro forma CRA pursuant to which each Large Load Customer would compensate the applicable CTO or ATO for its allocable share of the Network Upgrade costs and all of the Transmission Owner Attachment

PDF page 16

November 16, 2026
Page 16

Facility costs.35  The CRA would appear in the NYISO OATT as Appendix 9 to Attachment LL (Section 44.16.9), and the pro forma Security Agreement as Appendix 10 (Section 44.16.10). In its orders related to Large Load Network Upgrade cost allocation, the Commission has

been clear that it seeks to avoid shifting upgrade costs from Large Loads to other customers and to avoid upgrade costs being stranded if a Large Load does not cover its share of such costs before ceasing compensation for the upgrades.  In the Show Cause Order, the Commission stated that it “must act to address the risk of cost shifting among transmission customers” to address, inter alia, costs associated with facilities needed to serve Large Loads as well as the risk of speculative requests associated with Large Load Customers.36

In the Show Cause Order, FERC expressly noted the risk for transmission customers to
“pay for potentially unnecessary Network Upgrades that they neither caused the need for nor benefit commensurately from” if a Large Load fails to materialize as anticipated.37  The Commission has otherwise noted that transmission customers should be protected from paying for transmission facilities to serve Large Load Customers or otherwise bear the costs of a Large Load failing to achieve planned commercial operations.38

The NYTOs have addressed the Commission’s concerns in the CRA and a pro forma Large
Load Security Agreement.  The pro forma CRA includes a Large Load Formula Rate to recover each Large Load Customer’s Allocable Network Upgrade Costs and Attachment Facilities costs from the customer.39  The useful life of many Network Upgrades will be 40 years or longer. Entering into a CRA of such a long duration increases performance and financial security/collateral risks that can result in stranded costs and cost shifts to other customers.  Accordingly, the CRA

35 For ease of reference, we refer to “upgrades” and “Network Upgrades” in discussing the Large Load CRA, but the terms are intended also to apply to Attachment Facilities as noted above.
36 Show Cause Order, 195 FERC ¶ 61,216 at P 74; see also Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 at PP 78-82 (2026) (discussing the need for a cost recovery agreement among other requirements to ensure cost shifting risks to other transmission customers are mitigated).
37 Show Cause Order, 195 FERC ¶ 61,216 at P 85.
38 See Duke Energy Carolinas, LLC, 193 FERC ¶ 61,237 at P 20 (2025) (FERC rejecting a proposed Amended Network Integration Transmission Service Agreement and noting no explanation for how the proposed transmission rate would not shift costs of necessary transmission facilities to other customers); PECO Energy Co., 193 FERC ¶ 61,148 at P 32 (2025) (FERC noting an applicant’s representation that a filed Transmission Security Agreement includes “safeguards to protect customers” by requiring that the Large Load make a minimum contribution to the transmission revenue requirement regardless of whether the Large Load ever achieved operation); The Dayton Power & Light Co., 192 FERC ¶ 61,103 at P 13 (2025) (FERC noting the filed Construction Service Agreement “includes customer protection provisions designed to prevent AES Ohio’s other customers from bearing ultimately cost responsibility if the Data Center fails to achieve commercial operations”).
39 In some circumstances, the NYPSC, a CTO, or ATO may determine that an alternate cost allocation and/or recovery mechanism is justified.  Nothing in the default mechanism of the CRA is intended to limit the NYPSC’s authority to determine an alternative cost allocation methodology pursuant to its own procedures or a CTO or ATO’s right to file an alternative agreement, pro forma agreement or non-conforming agreement governing cost allocation and recovery under FPA section 205.

PDF page 17

November 16, 2026
Page 17

provides for a term of 15 years over which the Transmission Owner that constructs the upgrade would be fully compensated for the cost of the upgrade.

Accelerating depreciation of the assets to correspond to their repayment term, however, would raise accounting and rate-making issues that should be avoided.  For example, accelerated depreciation may conflict with how depreciation rates are established pursuant to the FERC chart of accounts.  Further, certain utility software that marks asset classes for a variety of purposes may not be able to implement separate project-specific depreciation rates.  Accordingly, rather than depreciating the upgrade over 15 years, the risk of cost shifts to other customers and avoids the pitfalls of accelerated depreciation.  The Large Load Upgrade Charge under the CRA compresses cost recovery into the CRA term but does not accelerate depreciation on the Transmission Owner’s books.  Rather, for accounting purposes, the Transmission Owner would depreciate each upgrade over its full economic life on a composite straight-line basis, as usual.  The Large Load, however, pays the full cost within the 15-year term rather than over the decades the equipment will be in service.  This substantially mitigates the risk of cost shifts to other customers and avoids the pitfalls of accelerated depreciation.

As a result, the Large Load’s yearly payments during the term are higher than the equipment’s normal yearly straight-line depreciation cost.  The Transmission Owner will defer in its accounts that excess (the “Annual Deferred Revenue”).  Starting in Year 16 and continuing for the rest of the upgrade’s economic life, the Transmission Owner will credit the deferred amounts back to its cost of service in its bundled T&D rates, or, if unbundled, in its transmission rates, thereby protecting other customers from upgrade costs.

The annual revenue requirement for each upgrade is calculated as if the upgrade were recovered over its Average Service Life, using the Transmission Owner’s approved depreciation rates, and the Transmission Owner earns its return on the depreciated, not the original, cost of the upgrade.  That is, the investment balance used in the annual calculation is the original cost reduced by accumulated depreciation and amortization.  As the equipment depreciates each year, the remaining balance on which the Transmission Owner earns a return reduces in amount, so the return portion of the charge declines over the term, while the depreciation portion stays level under straight-line depreciation.  That annual revenue requirement is then multiplied by the Average Service Life and divided by the 15-year contract term to produce the compressed charge.

1. How the Charge Is Calculated
The Transmission Owner calculates the charge in four steps:

1. Start with upgrade cost.  The Transmission Owner uses estimated costs at first. After construction, it substitutes actual, prudently incurred costs and corrects all prior bills, with interest, back to the start of payments.

2. Apply the carrying charge.  The annual costs associated with the Large Load Upgrade shall consist of two components:  (1) the Large Load Upgrade-specific

return of and return on investment, including associated income taxes; and (2) an

PDF page 18

November 16, 2026
Page 18

estimate of O&M, A&G, property tax, payroll tax, and other applicable expenses associated with the Large Load Upgrade, excluding depreciation, amortization, return, and associated income taxes.  This second component shall be calculated using an Annual Ongoing Charge Factor equal to the applicable system-wide expenses, excluding depreciation, amortization, return, and associated income taxes, divided by total gross plant in service.  The Annual Ongoing Charge Factor shall be applied to the Large Load Upgrade-specific gross plant in service.

3. Compress into the contract term.  The Transmission Owner multiplies that yearly cost by the equipment’s average service life and divides by the number of years in the contract term.

4. Bill monthly.  The Large Load pays one-twelfth of the resulting yearly amount each month.

2. How the Carrying Charge Is Adjusted Each Year

The carrying charge percentage (the “Annual On-going Charge Factor”) changes from year to year.  It equals the Transmission Owner’s total yearly transmission and distribution costs, excluding depreciation, amortization, return, and associated income taxes, divided by total gross plant in service.  Those costs are municipal and payroll taxes, operations and maintenance, and administrative and general expenses, minus rents received.  Because these system-wide figures change, the percentage changes too.

Annual update.  No later than August 1 of each year, the Transmission Owner recalculates the carrying charge percentage using the most recent rate data from NYPSC sources: the Transmission Owner’s NYPSC rate order, its annual and compliance reports to the NYPSC, and its books and records, with FERC Form No. 1 data used only if an input cannot be derived from those NYPSC sources.  All inputs must cover the same reporting period and be measured the same way.  The update calculation reflects changes in the Transmission Owner’s approved return on equity, capital structure, and depreciation rates.  The Transmission Owner then resets the yearly charge, the Annual Deferred Revenue, and the monthly billing schedule for the coming year.  The NYTOs propose using NYPSC data because the NYPSC establishes rates for all retail customer classes in utility-specific, comprehensive rate cases which review transmission, distribution, common costs and overheads, cost allocation and rate design on a regular basis.

True-up.  Each year’s carrying charge percentage relies on prior-year data, so each year’s bills are estimates of actual charges.  The next year, the Transmission Owner compares what it billed with what it would have billed using actual data for that period.  The Transmission Owner

PDF page 19

November 16, 2026
Page 19

refunds any overcharge, or collects any undercharge, with interest at the FERC rate,40 in equal monthly installments over the next rate year.

Transparency and disputes.  With each update, the Transmission Owner provides to the Large Load a written statement showing every input and its source, the true-up calculation, and supporting workpapers.  The Large Load may challenge the calculation under the Agreement’s dispute resolution provisions.

Implementation of formula.  Once the Large Load Formula Rate is accepted or approved by FERC, a change to an NYPSC-approved input will flow through the annual update of the Large Load Formula Rate and will not require a new FERC filing.  A change to the Large Load Formula Rate itself will require a filing with the Commission for acceptance or approval.

3. Relationship to Large Load Security Agreement and Proposed
Effective Date

Even with the shorter term of 15 years, it is possible that some Large Loads will default. To avoid cost shifts and consistent with Commission guidance,41 the NYTOs are submitting a pro forma Large Load Security Agreement for Commission acceptance or approval to secure the NYTOs’ cost recovery in the event of a default or early termination by the Large Load Customer (discussed in the next section of this transmittal).

C. Large Load Security Agreement
In the Show Cause Order, the Commission stated, “[w]e further preliminarily find that the cost recovery agreement should include a credit support (or other financial security) requirement …”42  The proposed pro forma Large Load Security Agreement would require the Large Load Customer to post security to cover the allocated costs of Network Upgrades and Transmission Owner Attachment Facilities.  The initial security amount is based on the Facilities Study cost estimates, is subject to adjustment through the cost allocation process when other projects in the Cluster fail to post security, and, once the CRA is executed, is adjusted annually to cover the Large Load Customer’s remaining obligations under the CRA.  The CRA and Large Load Security Agreement are related agreements (along with the Large Load Interconnection Agreement) and these related agreements work to address the Commission’s concerns regarding risks to other customers associated with loads that do “not materialize as planned or is not developed at all.”43  The Large Load Security Agreement allows the Transmission Owner to draw on security, which would be provided by the Large Load Customer in the form of cash or

40 See 18 C.F.R. § 35.19a (2026).
41 See Show Cause Order, 195 FERC ¶ 61,216 at P 85 (noting FERC’s concern that “speculative transmission service requests by Eligible Customers on behalf of large loads that could result in cost shifting among transmission customers, which may lead to unjust and unreasonable increases in jurisdictional transmission rates”). 42 Id. P 89.
43 Id. PP 87, 89.

PDF page 20

November 16, 2026
Page 20

an irrevocable standby letter of credit from a qualifying bank, for such events as abandonment of the project, events of default under the related agreements after any applicable cure period, notification by the customer that it is ceasing to negotiate the CRA or Large Load Interconnection Agreement where the facilities must still be completed, failure to renew or replace a letter of credit, and other events as listed in the Large Load Security Agreement that create undue risks of cost shifts for the Transmission Owner or other customers.  The CRA links to the Large Load Security Agreement by specifying that the Transmission Owner can draw upon the security in the amount and manner specified under the Large Load Security Agreement in order to protect other customers against stranded asset risks in the case of such events as abandonment or customer default, including to satisfy the Net Present Value Residual Charge owed upon early termination.

Overall, the NYTOs respectfully submit that the CRA and the Large Load Security Agreement mitigate undue risks to other customers and Transmission Owners consistent with Commission guidance as set forth in the Show Cause Order.

D. Revenue Crediting
The Commission expressed concern that to the extent Large Load Customers paid for Network Upgrades, the Transmission Owner building and owning the upgrades should provide revenue credits in rates applicable to other customers to avoid double recovery.44  The NYTOs have proposed an addition to Section 44.12.1.8 of Attachment LL of the NYISO OATT that provides a restrictive covenant whereby each NYTO agrees not to recover any costs of Large Load Network Upgrades from any other FERC-jurisdictional transmission customer without a separate section 205 filing explaining the rate treatment and any revenue credit(s) associated with the upgrade costs, or, if the costs of such a Large Load Upgrade are already includable in a formula rate on file with the Commission, the Transmission Owner will explain the costs and revenue credits associated with the Large Load Upgrade in any update to the formula that includes Large Load Upgrade costs.

E. Transmission Service Charges
1. Development and Evolution of Current Delivery Rates Applicable to
Retail Access and Large Load Customers

The NYISO FPA section 205 filing proposes rules governing the market settlements applicable to each Large Load Customer.  In particular, Eligible Customers obtaining Non-Firm Transmission Service for Large Loads will be required to bid into the NYISO Day-Ahead Market and to settle deviations in the Real-Time Market.  The NYISO will apply Transmission Usage Charges for Transmission Congestion and Marginal Losses.  The NYISO will also apply certain Ancillary Service Charges.

44 Id. P 38.

PDF page 21

November 16, 2026
Page 21

The NYISO charges do not address the embedded cost delivery charges (bundled
transmission and distribution rates discussed below) that the utility with the retail franchise to serve retail customers in each service area applies under its NYPSC-authorized retail tariff service classification.  As explained in the attached Panel Testimony, the NYPSC adopted retail access programs in 1996, before the NYISO was operational in late 1999, whereby electric commodity supply was unbundled from transmission and distribution delivery rates applicable to this form of “retail wheeling” or “retail transmission service” – i.e., deliveries of third-party supplied energy to retail customers in New York.45  Since before the NYISO’s inception, the NYPSC has established through many proceedings the retail delivery charges that retail customers in New York pay to NYPSC-jurisdictional distribution companies.  In the spirit of cooperative federalism, the NYTOs identified, in Section 5 of the NYISO OATT, the NYPSC-jurisdictional retail service classifications, and incorporated the rates, terms and conditions applicable to retail delivery service by reference as those NYPSC service classifications may be amended or superseded from time to time.  The Commission accepted these tariff provisions.46

As explained in the attached Panel Testimony, this system has been in place for 27 years, through which the NYPSC has determined voltage-differentiated delivery rates that unbundle supply and apply to delivery service by the jurisdictional Transmission Owners (excluding the NYPA and LIPA).47  While the NYTOs recover almost all of their transmission and distribution costs through “bundled” delivery rates set by the NYPSC,48 some delivery rates are not fully bundled because they are voltage-differentiated based on cost allocations that intentionally remove certain distribution costs from the rates developed for transmission-level customers.49 These voltage-differentiated rates generally provide demand charges that are considerably lower for higher voltage customers, as compared to the rates applicable to lower voltage, distribution-level interconnecting customers.  For example, for NYSEG’s NYPSC service classification SC 7, Large General Service with Time-of-Use Metering, there are three applicable voltages:

• 7-1 – Secondary, 120–480 volts;

45 Prepared Testimony of Brian McNierney, Carol Teixeira, Yan Flishenbaum, and Stacy Powers, Attachment I at 7 (“Panel Testimony”).  See also In the Matter of Competitive Opportunities Regarding Electric Service, Case 94- E-0952, et al., Opinion No. 96-12 (1996).
46 Cent. Hudson Gas & Elec. Corp., 86 FERC ¶ 61,062, order on reh’g and compliance, 88 FERC ¶ 61,138 (1999).
47 Panel Testimony at 9.
48 Certain transmission rates recovered under NYISO OATT Schedules 10 and 19 are facility-specific formula rates for such projects as Public Policy Transmission Projects identified by the NYPSC with cost recovery permitted under the NYISO’s Order No. 1000 Public Policy Transmission Planning Process (Attachment Y of the NYISO OATT).
49 Panel Testimony at 10.

PDF page 22

November 16, 2026
Page 22

• 7-2 – Primary, 2.4–34.5 kV or regulated 46 kV; and
• 7-4 – Transmission, 115 kV and above.
The applicable demand charge (per kW) for each one of those voltage classifications is:
• 7-1 – $14.55;
• 7-2 – $13.76; and
• 7-4 – $2.07.
These rates make clear that the demand charge applicable to the highest transmission level customer is one-seventh of the demand charge applicable to the lowest distribution level customer based in part on the exclusion of certain distribution and lower voltage system costs from the demand charge applicable to transmission level customers.

The Panel Testimony also provides a hypothetical savings example that illustrates how substantially lower the rate and charges would be under the transmission level rate compared to the distribution rate.50

The NYPSC-approved retail tariffs for the franchise distribution utilities provide Large Load Customers an alternative optional rate under which they may take delivery service.  In particular, each utility has “time-of-day” demand delivery rates in which the monthly demand charges will reflect the customer’s metered load for each daily peak or super peak period thereby calculating “as used” demand charges for that day based on actual withdrawals. A Large Load having selected the time-of-use delivery rate would pay less as-used demand when curtailed during the relevant period by the NYISO.  Each Large Load Customer will have the option of determining whether a standard delivery rate or time-of-use rate makes the most sense to that customer, thereby providing the opportunity to reduce costs.  The Panel Testimony provides another example in which a Large Load is curtailed by the NYISO or a utility to zero on five days in which on-peak daily as-used demand is measured, which shows how a flexible Large Load can lower its monthly delivery bill under NYPSC optional demand service if it is subject to persistent curtailments and dispatch during peak or off-peak hours on any given day.51 In the supporting Panel Testimony, NYTO witnesses describe in further detail both the manner in which the retail delivery rates were formed through NYPSC proceedings and the rate options that Large Load Customers have for delivery service.  These NYPSC-approved rates and service classifications are referenced in the proposed revised NYISO OATT Section 5.  These NYPSC-approved delivery rates have evolved significantly through many NYPSC proceedings that have addressed many cost allocation and rate design issues.  The delivery rates applicable to

50 Id. at 17-18.
51 Id. at 21-22.

PDF page 23

November 16, 2026
Page 23

delivery service allocate costs across many classes of customers.  Among other things, the NYPSC-established delivery rates provide for revenue neutrality and are specifically designed to avoid cost shifting among customer classes that would deviate from the NYPSC’s determination of just and reasonable rates.  As the Panel Testimony explains, any changes in rates applicable to one or a few classes in isolation from the others could potentially result in cost shifting and/or violate revenue neutrality, potentially causing unjust and unreasonable rates.52

The NYISO has explained in its FPA section 205 filing how the NYISO system uniquely does not provide for Non-Firm Point-to-Point or Non-Firm Services.  The NYISO is adopting Non- Firm Service that will be available to Large Load Customers under certain circumstances.  For such customers taking Non-Firm Service, the NYISO will dispatch the amount of withdrawal that can be accommodated under economic security constrained dispatch.  There also may be instances of bulk system reliability concerns in which the NYISO, including at the request of the CTO or ATO, may reduce the dispatched withdrawals of a Large Load in whole or in part.  For instance, a Large Load that takes Interim Non-Firm Service prior to completion of bulk upgrades may be dispatched by the NYISO to withdraw only a portion of its requested withdrawal due to conditions on the bulk system despite having requested firm retail service under the utility’s retail service tariff.  For example, if a Large Load requests firm service, and the CTO can provide firm service, but the NYISO requires Non-Firm Service pending new capacity additions because the Large Load fails a Resource Adequacy Screen, then the CTO may still be providing Firm Service on its system and treating the Large Load as a firm load so far as its system is concerned.  The NYISO would have the ability to interrupt the load if the NYISO system was approaching resource deficiency, but this has nothing to do with the CTO’s ability to provide Firm Service and the treatment of the Large Load for purposes of providing service.

As another example, if a CTO can provide Firm Service to a Large Load, but an ATO requires an upgrade before Firm Service is available, then the CTO is still going to provide Firm Service on its system.  The pendency of the Firm Service awaiting another Transmission Owner’s non-local upgrade may be completely unrelated to the manner in which the retail utility provides service and plans its bulk or local system to be able to provide reliable service prospectively. Consequently, the reason that Non-Firm Service is required is relevant to which Transmission Owners are providing Non-Firm Service.  It is not a one-size-fits-all dynamic. The NYISO worked diligently to define the terms of new Non-Firm Withdrawal Services. Until these terms were developed, it was not reasonable to establish new retail delivery rates for these services.  The terms of this new service were evolving until very recently.  Moreover, as discussed in the Panel Testimony, changes in rates applicable to some retail service classifications in isolation from the establishment and updating of rates for other service classifications, a function that has always been overseen by the NYPSC and still is, would create risks of undue cost shifts between Large Load and non-Large Load Customers.  The NYPSC commenced a proceeding in February 2026 to consider changes in Large Load services and associated rates, terms and

52 Id. at 23-24.

PDF page 24

November 16, 2026
Page 24

conditions.53  Any proposed changes to the rates paid by Large Loads should be considered in this broader context before the Commission accepts or approves such changes.

Under the NYISO’s proposal, the earliest that new Non-Firm Withdrawal Services would
be available for projects is after the first Cluster has proceeded under the proposed LLIP.  As filed, the NYISO process would result in Facilities Study completion and security posting in or after July 2028.  This time frame should precede service to the new Large Loads.  In the meantime, the NYTOs have updated Section 5 of the NYISO OATT to better address Large Load delivery rates and to include the flexibility of the Large Load Customers to choose among the NYPSC service classifications for which they are eligible that best meet their needs.

The Commission’s acceptance of the NYTOs’ reliance on NYPSC rate proceedings and
cross-references in the NYISO OATT represents cooperative federalism as envisioned by the
Commission and the U.S. Supreme Court.  FERC has repeatedly deferred to the states’ respective role pertaining to retail facilities used in “local distribution.”54  Thus, deferring to the NYPSC rate proceedings is consistent with the Commission’s recognition of enabling cooperative federalism as an objective of its regulation.55  Further, the U.S. Supreme Court has expressly recognized cooperative federalism as a guiding principle for FERC’s regulation.56

The NYTOs respectfully urge the Commission to permit the NYTOs to work with the
NYPSC in the first instance on any new rates that may be appropriate and then, if necessary, to make appropriate filings with the Commission.  Subject to their jurisdictional reservations, the NYTOs request that the Commission accept the proposed changes to Section 5 to the extent they are subject to the Commission’s jurisdiction.

53 NYPSC Case No. 26-E-0045, Proceeding on Motion of the Commission to Address Interconnection Reforms for Large Loads, Order Instituting Proceeding and Soliciting Comments (Feb. 12, 2026).
54 See Am. Elec. Power Serv. Corp., 153 FERC ¶ 61,167 at P 16 (2015) (FERC recognizing that section 201 of the FPA demonstrates “the authority of the states over retail sales and facilities used in ‘local distribution’”); Bldg. for the Future Through Elec. Reg’l Transmission Plan. & Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 at P 254 (2024) (FERC’s Order No. 1920 recognizing that it does not “regulate, aim at, or otherwise attempt to influence … decisions related to the siting and construction transmission facilities … or any other matters reserved to states under FPA section 201”).
55 Bldg. for the Future Through Elec. Reg’l Transmission Plan. & Cost Allocation, Order No. 1920-B, 191 FERC ¶ 61,026 at P 91 (2025) (FERC noting that the U.S. Supreme Court’s holding that a state’s “veto power” in the Commission’s regulation of demand response ensured “the Commission’s compliance with principles of cooperative federalism”); Show Cause Order, 195 FERC ¶ 61,216 at P 76 (noting the Commission’s objective in this FPA section 206 proceeding is “to respect the cooperative federalism approach established under the FPA”).
56 New York v. F.E.R.C., 535 U.S. 1, 28 (2002) (holding that “a federal order claiming jurisdiction over all retail transmission would have even greater implications for the States’ regulation of retail sales—a state regulatory power recognized by the same statutory provision that authorizes FERC’s transmission jurisdiction”); F.E.R.C. v. Elec. Power Supply Ass’n, 577 U.S. 260, 288 (2016) (holding that wholesale demand response “is a program of cooperative federalism, in which the States retain the last word”); Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 151 (2016) (recognizing that “[s]tates may regulate within their assigned domain even when their laws incidentally affect areas within FERC’s domain”).

PDF page 25

November 16, 2026
Page 25

2. Changes to Section 5 of the NYISO OATT (Retail Access)

The NYTOs do not propose new rates in Section 5 of the NYISO OATT.  Instead, the
NYTOs’ rates continue the existing practice of referencing the applicable NYPSC-approved delivery service classifications, as they may be amended or superseded from time to time.  The proposed revisions to Section 5 clarify that its terms apply to Large Loads and to Eligible Customers serving Large Loads and reference currently applicable NYPSC-approved, or LIPA Board of Trustees-approved, service classifications and delivery rates.57  Revisions to the Preamble clarify that Section 5 applies to all retail access service, delivery service unbundled from commodity supply, irrespective of whether the retail Large Load Customer takes commodity supply from an ESCO or the Transmission Owner that is the franchise utility to serve the Large Load Customer.58

More specifically, revised Section 5.1.1 requires each retail access customer, including Eligible Customers serving Large Loads, to pay the Retail Transmission Service Charge to the Transmission Owner that is the retail franchise utility authorized under state law to serve at retail in the service area in which the Large Load is located, consistent with the rates, terms, and conditions of that Transmission Owner’s retail tariff, as approved by the NYPSC and referenced in Sections 5.2 and 5.3.59  Revised Section 5.1.3 allows each Transmission Owner to collect the Retail Transmission Service Charge from customers that take service under its retail tariffs, including Eligible Customers serving Large Loads, and these retail tariffs are approved by the NYPSC or the LIPA Board of Trustees.60

Revised Section 5.2 now contains references to the current NYPSC tariffs and notes the applicability to Eligible Customers serving Large Loads under Attachment LL.61  Newly created Section 5.2.8 sets out the rates, terms, and conditions of service for Eligible Customers taking service on behalf of Large Loads and lists the applicable service classifications for each Transmission Owner.62  Newly created Section 5.2.9 reserves each Transmission Owner’s right to modify its rates, terms, and conditions, subject to required filings under the New York Public

57 Panel Testimony at 25.  Historically, Section 5 of the NYISO OATT has included language addressing LIPA’s service in support of retail choice programs, on an informational basis.  Consistent with that process, the NYTOs requested, and LIPA has provided, information on the service classifications within the LIPA Tariff for Electric Service which are applicable to large loads.  As a non-jurisdictional utility, the LIPA service classifications referenced in the proposed changes to NYISO OATT, Section 5 are subject to review and approval by the LIPA’s Board of Trustees under applicable state law.  Inclusion of the LIPA service classification references in NYISO OATT Section 5 is for informational purposes and shall in no way be considered to be a waiver of LIPA's non-jurisdictional status pursuant to Section 201(f) of the FPA, including with respect to the Commission's exercise of its FPA general ratemaking authority.
58 Id. 59 Id. at 26.
60 Id.
61 Id.
62 Id.

PDF page 26

November 16, 2026
Page 26

Service Law, the New York Public Authorities Law, or the FPA.63  Section 5.2.9 also requires Eligible Customers both to satisfy certain interconnection requirements established in Attachments HH and LL and to execute the Transmission Service Agreement attached to the OATT.64

Newly created Section 5.3 references cost responsibilities for Large Loads as described in the CRA in the NYISO OATT.65  Newly created Section 5.4.1 requires Transmission Owners to apply revenue credits or adjustments to prevent double recovery of costs recovered under CRAs through FERC-jurisdictional wholesale transmission rates.66  Finally, newly created Section 5.4.2 requires Transmission Owners to file an annual informational report with FERC and the NYPSC to identify CRA revenues received by upgrade(s) during the following year and demonstrate that appropriate revenue credits have been or will be applied.67

The NYTOs also propose conforming changes to the definitions in Sections 1.18 and 1.20 of the NYISO OATT to support the revised Section 5.  First, the NYTOs propose to add to Section 1.18 a new defined term, “Retail Transmission Service Charge,” meaning a charge incurred by a retail access customer, including a Large Load or an Eligible Customer on behalf of a Large Load, for Transmission Service and/or delivery service, as appropriate, pursuant to Section 5 of the NYISO OATT, as defined therein.  Second, the NYTOs propose to revise the definition of “Transmission Service Charge” (“TSC”) in Section 1.20 to clarify that, for the avoidance of doubt, the TSC is separate and apart from the Retail Transmission Service Charge. Together, these changes distinguish the wholesale TSC from the retail delivery charges that all retail customers, including Eligible Customers serving Large Loads, pay under the NYPSC- or LIPA Board of Trustees-approved retail tariffs referenced in Section 5.  Finally, the NYTOs propose cross-references to Section 5 of the NYISO OATT in the pro forma TSA.

3. Request for Relief

The NYTOs respectfully urge the Commission:

• To accept the proposed revisions to Section 5 of the NYISO OATT to update the NYPSC rate designations incorporated by reference and applicable to retail access delivery service, including service for Large Loads, as amended from time to time;

• To provide the NYPSC time to work within its Large Load proceeding commenced in February 2026, with a white paper including recommendations from DPS Staff due no

63 Panel Testimony at 24.
64 Id. at 26-27.
65 Id. at 27; see NYISO Companion Filing, proposed § 44.16.9 – Appendix 9.
66 Panel Testimony at 27.
67 Id.

PDF page 27

November 16, 2026
Page 27

later than February 2027, to determine whether any of the Large Load embedded cost delivery rates should be modified in the first instance;

• To provide the NYTOs time to consider and act on any such NYPSC determinations if changes to the currently effective delivery rates are warranted and to make an amendment filing under Section 205 of the FPA with this Commission if any is deemed necessary or appropriate.  In undertaking that review, the NYTOs will also consider whether relevant NYPSC determinations warrant changes to the default Network Upgrade cost allocation and recovery methodology proposed in the CRA and, where appropriate, may pursue such changes through a subsequent filing under Section 205; and

The NYTOs commit to make an informational or Section 205 filing with the Commission concerning any changes in rates that would apply to Large Load Customers, depending on the rates established or approved by the NYPSC or any guidance the NYPSC provides.  The NYTOs commit to make any necessary filing with the Commission before the Facilities Studies for Large Load Customers in the first LLIP Cluster under the NYISO’s new rules are issued and intend to make the filing at least 60 days before the proposed effective date of any new rates.

F. Operating Terms Applicable to Non-Firm Transmission Withdrawal
Service and Paired or Behind-the-Meter Generation Supplies
The NYTOs propose revisions to the NYISO’s proposed Attachment LL to establish operating requirements that apply to Large Loads interconnected under the LLIP, including Large Loads that take Non-Firm Transmission Withdrawal Service at a level below their maximum potential withdrawal and Large Loads paired with Co-Located or Partner Resources.  The NYISO section 205 filing establishes how Non-Firm Transmission Withdrawal Service is studied, scheduled, and dispatched in the NYISO-administered markets.  It does not, however, fully address the operating authority the NYTOs need to maintain bulk and local system reliability, including on non-Bulk Electric System facilities and in conditions outside the NYISO’s operational visibility or direct control.  The proposed revisions fill that gap.  They complement the NYISO section 205 filing and do not displace the NYISO’s scheduling and dispatch authority under the NYISO Services Tariff.

First, the NYTOs propose to limit the circumstances in which Non-Firm Transmission Withdrawal Service may be offered.  Under proposed Section 44.8.2.4.5, Non-Firm Transmission Withdrawal Service may be offered only where thermal transmission constraints on Business Management System-secured facilities under N-1 and N-1-1 conditions, and/or resource adequacy violations, prevent the offering of Firm Transmission Withdrawal Service.  In order to maintain reliability, Non-Firm Service may not be used to mitigate voltage, stability, oscillatory stability, short-circuit, cascading, or other non-thermal reliability concerns, and may not rely on a Special

PDF page 28

November 16, 2026
Page 28

Protection System or Remedial Action Scheme.68  This limitation ensures that Non-Firm Service is used only for constraints that economic scheduling and dispatch can reliably manage. Second, the NYTOs propose new Section 44.14.3.5, which sets out the operating requirements that apply to each Large Load from initial energization through disconnection, under normal, abnormal, and emergency conditions, whether the Large Load takes Firm Transmission Withdrawal Service, Non-Firm Transmission Withdrawal Service, or both.69  The NYTOs also propose a new defined term, “Large Load Operating Action,” to describe the actions a Transmission Owner may take under that section.  Section 44.14.3.5 confirms that nothing in Attachment LL or the NYISO Services Tariff limits a Transmission Owner’s retained authority to address bulk and local system reliability.  It also requires each CTO to set out in its procedures the applicable communications requirements, operator authority, curtailment and restoration procedures, loss-of-telemetry and loss-of-communications actions, and performance enforcement measures.70

Under proposed Section 44.14.3.5.2, under normal conditions the NYISO will continue to schedule and dispatch economically a Large Load’s Non-Firm Transmission Withdrawal Service. Under abnormal conditions, a Transmission Owner may request that the NYISO reduce the dispatch of a Large Load’s Non-Firm withdrawals using the NYISO’s existing Out-of-Merit and Day-Ahead Reliability Unit procedures, in the same manner that Transmission Owners request such actions for Generators.  A CTO may directly order a Large Load to ramp down or curtail its Non-Firm withdrawals only if a NYISO-implemented reduction cannot be achieved in time, or if economic dispatch does not reduce withdrawals enough, to address an actual or imminent reliability condition.  In that case, the Large Load must comply within ten (10) minutes, the CTO must notify the NYISO immediately, and the order must be limited in extent and duration to what is reasonably necessary.71

Proposed Sections 44.14.3.2 and 44.14.3.5.3 provide that the CTO or, where the Franchise Utility is not the CTO, the Franchise Utility may disconnect a Large Load in whole or in part where necessary to maintain or restore bulk or local system reliability.  The NYTOs also propose new defined terms for “Franchise Utility” and “Retail Tariff” to reflect that retail service to a Large Load may be provided by an entity other than the CTO.72  Disconnections must be coordinated in advance with the NYISO and the Franchise Utility for non-urgent situations, such as maintenance outages, and in all other cases must be reported as soon as practicable.  Each disconnection must follow defined communication protocols.  If a CTO determines, consistent with Good Utility Practice, that a requested disconnection would create or worsen a reliability problem, it may defer or modify the request only to the extent necessary while the NYISO and the affected Transmission

68 See Attachment A, § 44.8.2.4.5.
69 See Attachment A, § 44.14.3.5.
70 See Attachment A, § 44.14.3.5.1(ii).
71 See Attachment A, § 44.14.3.5.2(iv).
72 See Attachment A, § 44.1.

PDF page 29

November 16, 2026
Page 29

Owners coordinate an alternative.  A disconnection directed by the NYISO in an Emergency State must still be implemented unless it would endanger persons or equipment.

The proposed revisions also:  (i) set out the actions to be taken upon loss of telemetry or communications (Section 44.14.3.5.4); (ii) state each Large Load’s obligations, including compliance with dispatch and operator instructions, maintaining a 24-hour operating contact, observing ramp and step limits, and providing timely notice of unplanned changes in withdrawal, including transfers to on-site generation (Section 44.14.3.5.5); (iii) require restoration to be coordinated with the CTO and, for Non-Firm Service, to be consistent with NYISO dispatch (Section 44.14.3.5.6); (iv) provide for performance enforcement, cost reimbursement, and possible review of repeated non-compliance through a Load Modification Request (Section 44.14.3.5.7);

(v) preserve a Franchise Utility’s rights under its Retail Tariff (Section 44.14.3.5.8); (vi) establish a process for Transmission Owners and Franchise Utilities to ask the NYISO to act on a Large Load that is not meeting applicable performance requirements, including ramp rate requirements, and allow the CTO to order a Large Load to hold, limit, or ramp its withdrawals when ramp or step limits are exceeded or reliability is threatened (Section 44.14.3.5.9); and (vii) allow a Transmission Owner to ask the NYISO to model local transmission constraints, including constraints on non-Bulk Electric System facilities, in its scheduling and dispatch (Section 44.14.3.5.10).

The NYTOs also propose conforming changes.  Section 44.14.1 is revised to cross- reference the new operating requirements in the interconnection agreement provisions.  Section 44.8.3.3 is revised to clarify that the normal operating procedures that may allow a Large Load to enter service before Network Upgrades are complete include the Large Load Operating Actions, and that the Large Load must comply with any interim operating limitations set by the NYISO, the CTO, or the ATO as a condition of entering service.  In addition, Section 44.8.3.1.1 is revised to clarify that the withdrawal of Energy by a retail load in the Long Island Transmission District remains subject to the LIPA Tariff for Electric Service.  Non-Firm Transmission Withdrawal Service will not be available to Large Loads taking service under that tariff unless and until the tariff is amended under applicable law.73

The proposed operating provisions are just and reasonable and not unduly discriminatory or preferential.  Large Loads that take less-than-firm transmission service, or that rely on paired or behind-the-meter supply, can change their withdrawals quickly and in large amounts.  Those changes can affect transmission facilities that the NYISO does not monitor or control.  The proposed provisions give the NYTOs clear, transparent, and limited authority to manage those effects, consistent with their reliability obligations under North American Electric Reliability Corporation, Northeast Power Coordinating Council, Inc., and New York State Reliability Council, L.L.C. reliability standards.  The provisions rely on the NYISO’s market procedures wherever practicable, apply on the same terms to Large Loads taking Firm and Non-Firm Service, and give Eligible Customers clear notice, before they interconnect, of the operating conditions that apply to their service.

73 See Attachment A, § 44.8.3.1.1.

PDF page 30

November 16, 2026
Page 30

G. Interconnection Study Provisions and Pro Forma Facilities Study and
Interconnection Agreements
In its filing under section 205, the NYISO proposes to retain the existing structure of the Facilities Study for new Firm Withdrawal Service and Non-Firm Withdrawal Service. Specifically, the Facilities Study will remain a bilateral study outside the NYISO’s study procedures, performed under separate two-party agreements between the Large Load Customer and the CTO and, as needed, each ATO.  The NYISO will not be a party to the Facilities Study. Further, under the NYISO’s proposal, the NYTOs will continue to be responsible for determining the cost allocation of Network Upgrades identified through the study process.  In doing so, the NYTOs may use the impact allocation findings developed in the NYISO’s studies to determine the appropriate cost allocation for Network Upgrades during the Facilities Study. The NYTOs also propose two definitional changes to Section 44.1 of Attachment LL to support the Facilities Study and the related agreements.  First, the definition of “Connecting Transmission Owner” is revised to make clear that the CTO includes a Franchise Utility that meets the definition’s ownership and Transmission Service criteria.  Second, the NYTOs propose a new defined term, “Large Load Customer,” meaning the Eligible Customer acting as agent for the Large Load, or the Large Load customer itself, that is responsible for the Large Load Project under Attachment LL, including for purposes of the Facilities Study, the posting of security, and the interconnection and construction agreements.  Because an Eligible Customer may act as agent for a Large Load, the new term identifies the entity that is contractually and financially responsible for the project, so that the Transmission Owners can tender study, cost recovery, security, and interconnection agreements to that entity.74

Because the NYISO section 205 filing leaves the Facilities Study as a bilateral process outside the NYISO’s study procedures, the NYTOs are proposing, as part of this filing, a pro forma Facilities Study Agreement to govern that process.  The pro forma Facilities Study Agreement may be used by each Transmission Owner acting as the CTO or an ATO, and provides a uniform framework for the Facilities Study performed in two parts:  Part 1, which addresses Transmission Owner Attachment Facilities and local Network Upgrades and proceeds in parallel with the NYISO’s Assessment of Load Integration (“ALI”), and, as needed, Part 2, which addresses non- local Network Upgrades and alignment with the ALI results once the NYISO provides them. Under Section 44.8.2.4.1 of Attachment LL of the NYISO OATT, the NYISO is responsible for identifying bulk system violations associated with each LLIP Cluster and for each violation to which more than one Large Load contributes, each Large Load’s contribution to the violation. Each CTO and ATO shall determine violations on non-bulk system facilities and each Large Load’s contribution to each violation.  Each CTO and ATO shall identify upgrades to address all such violations identified by the NYISO or the CTO or ATO itself and provide non-binding cost estimates and estimates of time to construct the upgrades and each CTO or ATO shall identify and estimate the cost of Attachment Facilities and Upgrades and estimates of the time to construct. Such cost estimates shall include the cost of the equipment, engineering, procurement, and

74 See Attachment A, § 44.1.

PDF page 31

November 16, 2026
Page 31

construction work (including overheads) for the Attachment Facilities and Network Upgrades needed to implement the conclusions of the ALI.  Because the Facilities Study proceeds in parallel with the ALI, the pro forma Facilities Study Agreement permits the study to be updated, at the Large Load Customer’s expense and with a commensurate schedule extension, to incorporate additional Network Upgrades and Attachment Facilities identified as the ALI progresses. Among other things, the pro forma Facilities Study Agreement:  (i) establishes the scope of the Facilities Study and the data the Large Load Customer must provide, and confirms that the study is for planning and estimation purposes only and does not reserve capacity, queue position, or priority; (ii) requires the Large Load Customer to post a fixed Study Deposit based on the size of the Large Load Project ($300,000 for projects of 50 MW to 199 MW, $350,000 for projects of 200 MW to 499 MW, and $400,000 for projects of 500 MW and above) within ten (10) business days of execution, subject to withdrawal of the project without a cure period if the deposit is not timely posted, and to pay the Transmission Owner’s actual, documented, and reasonably incurred study costs, with notice if costs are expected to exceed the Study Deposit by more than 30%; (iii) provides that the Transmission Owner will use reasonable efforts to complete the Facilities Study within twelve (12) months (six (6) months for Attachment Facilities and local Network Upgrades and six (6) months for non-local Network Upgrades), beginning on the later of receipt of the Study Deposit or a complete study data package; (iv) sets out a process for a draft report, a results meeting, Large Load Customer comments for the Transmission Owner’s consideration, and issuance of a final report; (v) provides for refunds of any excess deposit and the resolution of disputed invoices; (vi) permits changes required by changes in Good Utility Practice, Applicable Laws and Regulations, Transmission Owner procedures and standards, or Governmental Authority directives; (vii) permits termination for, among other things, the Large Load Customer’s failure to pay, to provide required information, or to post the security required under Attachment LL based on the Facilities Study; and (viii) makes clear that it is an agreement to perform a study only, with any engineering, procurement, construction, or interconnection to be governed by separate agreements, which may include a Security Agreement, a transmission service agreement, a cost recovery agreement, an engineering and procurement agreement, and/or an interconnection agreement.

The NYTOs also propose conforming revisions to Attachment LL to integrate the Facilities Study Agreement into the NYISO’s study timeline.  Under revised Section 44.12.1.2, the CTO and each ATO will tender a Facilities Study Agreement in the form set forth in Appendix 8 of Attachment LL to the Eligible Customer acting as agent for the Large Load, or to the Large Load Customer itself.  In the Facilities Study Agreement, the Large Load Customer agrees to reimburse the Transmission Owner(s) for performing the Facilities Study and to provide the study deposit each Transmission Owner requires.  The Large Load Customer must execute a Facilities Study Agreement with each applicable Transmission Owner and return it within ten (10) calendar days of the Transmission Owner’s tender, and must pay the study deposit required by each applicable Transmission Owner within ten (10) business days after execution of the agreement.75

75 See Attachment A, § 44.12.1.2.

PDF page 32

November 16, 2026
Page 32

If the Large Load Customer fails to timely execute and return the agreement or to timely pay the study deposit, the applicable Transmission Owner will notify the NYISO, and the NYISO will withdraw the Large Load Project from the Load Queue and from the Group for the ALI and Facilities Study pursuant to Section 44.7.3, without a withdrawal cure period.  Section 44.7.3.1 is revised to confirm that the general fifteen (15) Business Day cure period does not extend these deadlines.  Section 44.10.4.4 is revised to provide for withdrawal where the Large Load Customer fails to satisfy these Transmission Owner requirements, and to require the Transmission Owner to notify the NYISO in writing within [two (2)] Business Days of the failure.76 In addition, Section 44.6.8 is revised to confirm that the information the NYISO, a CTO, or an ATO may request from an Eligible Customer includes information needed to perform the Facilities Study, which the Eligible Customer must submit within five (5) business days of the request.  Where a CTO or ATO requested the information and the Eligible Customer fails to provide it on time, the Transmission Owner may notify the NYISO in writing, identifying the request, the information not provided, and any resulting delay to the study of other Large Load Projects in the Group.  The NYISO will then, within five (5) business days, confirm the failure, deem the Large Load Integration Request withdrawn, and remove the Large Load Project from the Group.  Together, these provisions keep a Large Load Project that does not timely commit to the Facilities Study from delaying the study of other projects in the same Group. For each Upgrade associated with a violation to which more than one Large Load in an LLIP cluster of projects (a group of projects analyzed together under the LLIP or an “LLIP Cluster”) contributes, the applicable Transmission Owner shall use the contribution factors for [BES] violations the NYISO identified in the ALI and the contribution factors the Transmission Owner itself determined for non-BES violations in determining allocation of upgrade costs on an upgrade-specific and Large Load-specific basis.  A pro forma Facilities Study Agreement will provide Eligible Customers with transparency and consistency across the NYTOs’ service territories, ensure that the costs of Network Upgrades are allocated in a manner consistent with cost causation principles, and coordinate with the NYISO’s study process so that Eligible Customers can proceed to security posting (under a Security Agreement discussed above) and execution of the Interconnection Agreement in a timely manner.

Following completion of the Facilities Study, the NYISO section 205 filing provides that the Eligible Customer may elect to proceed with the interconnection of its Large Load Project by:

(i) entering into an interconnection agreement with the CTO to whose system the Eligible Customer proposes to interconnect, and (ii) as applicable, entering into construction agreement(s) for Network Upgrades with any ATO(s) or Affected System Operator(s) on whose system a Network Upgrade is required in connection with the Large Load Project.77  The NYTOs propose to revise Section 44.14.1 to provide that the interconnection agreement will be in the form set forth in Appendix 11 of Attachment LL, and that these agreements must identify any required Attachment Facilities and Network Upgrades and specify the Large Load Project’s cost

76 See Attachment A, § 44.10.4.4.
77 See NYISO Companion Filing, proposed OATT Section 44.14.1.

PDF page 33

November 16, 2026
Page 33

responsibility for those facilities consistent with the terms of the applicable Transmission Owner’s CRA and Security Agreement in the forms set forth in Appendices 9 and 10 of Attachment LL, respectively.78  Conforming revisions to Sections 44.2.2 and 44.12.1.8 likewise reference these pro forma forms, and new Sections 44.16.8 through 44.16.11 add the pro forma Facilities Study Agreement, CRA, Security Agreement, and pro forma Large Load Interconnection Agreement (“Interconnection Agreement”) as Appendices 8 through 11 to Attachment LL.79  The NYISO does not intend to be a signatory to the interconnection agreement.

The NYISO section 205 filing requires the Eligible Customer and the CTO to enter into an interconnection agreement.  The NYTOs are proposing, as part of this filing, a pro forma Interconnection Agreement to govern the interconnection of Large Load Projects following the Facilities Study because it implicates the costs the NYTOs are entitled to recover pursuant to their reserved rights under the NYISO-TO Agreement and directly affects retail access.  The pro forma Interconnection Agreement is a two-party agreement between the Transmission Owner and the Large Load Customer, which must be the same legal entity that executes the pro forma CRA and the separate pro forma Large Load Security Agreement, and it operates together with those agreements as Related Agreements.

Among other things, the pro forma Interconnection Agreement:  (i) conditions construction and interconnection activities on completion of the System Impact Study and Facilities Study and other required engineering, design and special studies, execution of the CRA, the Large Load Security Agreement, any related construction or cost reimbursement agreements, and any required transmission service agreement, receipt of required deposits and advance payments, receipt of all required regulatory approvals, and completion of the initial operating documents; (ii) provides load interconnection service at the Point of Interconnection up to a Maximum Load Facility Peak Demand that may not exceed the amount studied in the System Impact Study and Facilities Study, and requires additional study and Transmission Owner approval before any Material Modification;

(iii) requires the Large Load Customer to provide a monthly Load Ramp Projection and to update it every five years within limits, and sets out mechanisms to reduce interconnection rights where the load fails to meet a Minimum Committed Load and to address Exceedance Events in which the load exceeds its studied load limits; (iv) identifies the Attachment Facilities and Network Upgrades determined in the Facilities Study and addresses their engineering, procurement, and construction; (v) provides that the Large Load Customer’s responsibility for, and the recovery of, the costs of the Network Upgrades and the Transmission Owner Attachment Facilities will be governed exclusively by the CRA, and that the posting and maintenance of security will be governed exclusively by the Large Load Security Agreement; (vi) establishes conditions to energization and Permission to Operate, together with operational, metering, telemetry, insurance and cyber-security requirements and the Transmission Owner’s rights to interrupt or disconnect service for safety, reliability, and emergencies; (vii) establishes an initial term of fifteen (15) years (or, if longer, the term of the CRA) and provides that early termination by the Large Load Customer triggers the Net Present Value Residual Charge under the CRA; and (viii) makes clear

78 Id.
79 Id.

PDF page 34

November 16, 2026
Page 34

that it does not provide Transmission Service or the sale of energy, which remain subject to the applicable Tariff and the Transmission Owner’s retail tariff.

The proposed pro forma Interconnection Agreement provides Large Load Customers transparency and consistency to the extent of interconnection terms and conditions common to the NYTOs.  Because the Interconnection Agreement ties service levels to studied load and defers Network Upgrade and Transmission Owner Attachment Facility cost responsibility and security to the CRA and Large Load Security Agreement, it also protects against the risk of shifting costs to other transmission customers that the Commission identified in the Show Cause Order.

IV. EFFECTIVE DATE AND REQUESTS FOR WAIVER
The NYISO (on the NYTOs’ behalf) is submitting the enclosed Tariff revisions in eTariff format in accordance with the requirements of Order No. 714 and a requested effective date of February 1, 2027, though many tariff sheets apply to only those customers and activities under the NYISO’s new LLIP and will not affect prior and pending interconnection processes.80 The NYTOs request an effective date for the revisions to Attachment LL and Attachment B of Section 8 of the NYISO OATT of February 1, 2027, as consistent with the NYISO section 205 Filing.

The NYTOs request an effective date for the amendments to Section 5 of the NYISO OATT of February 1, 2027, while recognizing that the first LLIP Cluster under the NYISO’s new rules contained in Attachment LL will not complete Facilities Studies until Q3 2028.  Accordingly, the rates, terms and conditions of Section 5 will not apply to new Large Loads going through the first LLIP Cluster applying the new rules until some time after Q3 2028.

The NYTOs request an effective date for the Pro Forma Facilities Study Agreement, applicable to the first Cluster under the NYISO’s new LLIP, of February 1, 2027. The NYTOs request an effective date for the Pro Forma Large Load Security Agreement, Pro Forma Interconnection Agreement and Pro Forma Large Load Cost Recovery Agreement of May 1, 2028, a date at least 60 days in advance of completion of the first Facilities Study under the NYISO’s new LLIP and to allow the NYPSC time to advance its ongoing proceeding on Large Loads so that the NYTOs may consider how best to try to satisfy both the NYPSC and this Commission with respect to the content of those pro forma agreements.

To the extent that any of these effective dates are more than 120 days in the future, the NYTOs seek waiver, for good cause, of the requirement in section 35.3(a)(1) of the Commission’s regulations that rate schedules be filed no more than 120 days prior to the date on which service is to commence.

80 Elec. Tariff Filings, Order No. 714, 124 FERC ¶ 61,270 (2008), clarified, Order No. 714-A, 147 FERC ¶ 61,115 (2014).

PDF page 35

November 16, 2026
Page 35

Finally, the NYTOs request waiver of any other applicable requirement of 18 C.F.R. Part 35 that is found not to be completely satisfied by this filing.

V. COMMUNICATIONS
All communications and correspondence regarding this filing should be forwarded to the following individuals, whose names should be placed on the Commission’s service list:81 William R. Derasmo

Miles H. Kiger
Antonia M. Douglas
Benjamin L. Duwve
TROUTMAN PEPPER LOCKE LLP
401 9th Street, N.W., Suite 1000
Washington, D.C. 20004
(202) 274-2886
william.derasmo@troutman.com
miles.kiger@troutman.com
antonia.douglas@troutman.com
benjamin.duwve@troutman.com

Marina Chu
Regulatory Attorney – Regulatory Affairs
Central Hudson Gas & Electric Corporation
284 South Avenue
Poughkeepsie, NY 12601
mchu@cenhud.com

Phillip D. Demanchick Jr.
Senior Counsel
New York State Electric & Gas Corporation
Rochester Gas and Electric Corporation
180 South Clinton Avenue
Rochester, NY 14604
phillip.demanchick@avangrid.com

Christopher J. Novak
Senior Counsel
National Grid USA
170 Data Drive
Waltham, MA 02451
chris.novak@nationalgrid.com

Susan J. Kimball
Associate Counsel
Joshua A. Kirstein
Senior Attorney
Consolidated Edison Co. of New York, Inc.
Orange and Rockland Utilities, Inc.
4 Irving Place
New York, NY 10003
kimballs@coned.com
kirsteinj@coned.com
VI. CONTENTS OF THE FILING
In addition to this transmittal letter, this filing includes the following components:
1. Attachments A (clean) and B (marked): Tariff amendments to new Attachment LL of the OATT.  Attachment LL is being contemporaneously filed by the NYISO, and the NYTOs

81 The NYTOs respectfully request waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two individuals to be designated for service on the official service list in this proceeding.

PDF page 36

November 16, 2026
Page 36

are sponsoring the following revisions to Attachment LL:  Section 44.1; Sections 44.2.2, 44.6.8, 44.7.3.1, 44.8.2.4.5, 44.8.3.1.1, 44.8.3.3, 44.10.4.4, 44.12.1.2, 44.12.1.8, 44.14.1, and 44.14.3.2; new Section 44.14.3.5; and new Sections 44.16.8 through 44.16.11 (Appendices 8 through 11 to Attachment LL);

2. Attachments C (clean) and D (marked): Tariff amendments revising Section 5 of the OATT, the definitions in Sections 1.18 and 1.20 of the OATT, and Attachment B of Section 8 of the OATT;

3. Attachment E: Pro Forma Large Load Cost Recovery Agreement;
4. Attachment F: Pro Forma Large Load Security Agreement;
5. Attachment G: Pro Forma Large Load Facilities Study Agreement;
6. Attachment H: Pro Forma Large Load Interconnection Agreement; and
7. Attachment I: Panel Testimony and exhibit of Brian McNierney, Carol Teixeira, Yan Flishenbaum, and Stacy Powers.

VII. SERVICE
Copies of this filing have been served on all customers under the NYISO OATT and the NYPSC.82  This filing also will be posted in conformance with the Commission’s regulations.83

VIII. CONCLUSION
WHEREFORE, for the foregoing reasons, the NYTOs respectfully request that the Commission accept as just and reasonable and not unduly discriminatory or preferential the Tariff provisions and pro forma agreements proposed herein with the above-specified effective dates. [Signatures on following page]

82 18 C.F.R. § 35.13(b)(3) (2025).
83 Id. § 35.2(e).

PDF page 37

November 16, 2026
Page 37

Respectfully submitted,

/s/ William R. Derasmo
William R. Derasmo
Miles H. Kiger
Antonia M. Douglas
Benjamin L. Duwve
TROUTMAN PEPPER LOCKE LLP

Counsel to the New York Transmission Owners

/s/ Marina Chu
Marina Chu
Central
Hudson
Gas
&
Electric
Corporation

/s/ Phillip D. Demanchick Jr.
Phillip D. Demanchick Jr.
New
York
State
Electric
&
Gas
Corporation
Rochester Gas and Electric Corporation

/s/ Christopher J. Novak
Christopher J. Novak
National Grid USA

/s/ Susan J. Kimball
Susan J. Kimball
Joshua A. Kirstein
Consolidated Edison Co. of New York, Inc. Orange and Rockland Utilities, Inc.

Dated: November 16, 2026