ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others

NYTOs 205: Proposed Revisions re: Integration of Large Loads

Six New York transmission owners file under section 205 on November 16, 2026, in ER27-529-000, with NYISO submitting it as tariff administrator. They add four pro forma agreements: cost recovery, security, facilities study and interconnection. The cost recovery agreement recovers 100 percent of allocated upgrade costs over 15 years from the large load customer.

Asks FERC to: Accept the tariff amendments and pro forma agreements as just and reasonable, mostly effective February 1, 2027, with waiver of the 120-day filing limit.

Filed under section 205 to answer the E-12 show cause order for NYISO, as the owners' companion to NYISO's own filing in ER27-517. It covers cost recovery, security and operating terms, which NYISO's filing leaves to the owners.

E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Cost transparency (P 73, p. 47)

Key points

  1. NYISO's filing sets the study process and services. The owners' filing covers cost recovery and operations.
    While the NYISO’s filing establishes the study process, readiness requirements, and new Firm and Non-Firm Withdrawal Services for Large Loads, the NYTOs’ filing addresses the complementary elements necessary to recover the costs of facilities built to serve Large Loads PDF p. 2
  2. Each owner recovers all allocated upgrade and facility costs from the large load customer.
    recover 100% of the costs of Network Upgrades and Attachment Facilities allocated to a Large Load Customer PDF p. 3
  3. Recovery runs over 15 years, without accelerated depreciation.
    that compresses cost recovery into a 15-year term without accelerated depreciation PDF p. 3
  4. The customer posts security that the owner can draw on if the project is abandoned or the customer defaults.
    requires the Large Load Customer to post security for those allocated costs, which the Transmission Owner may draw upon in the event of abandonment of a Large Load project, default, or other specified events PDF p. 3
  5. Non-firm withdrawal service would be offered only where thermal or resource adequacy limits rule out firm service.
    limit Non-Firm Withdrawal Service to thermal and resource adequacy constraints PDF p. 3
  6. The owners propose no new delivery rates. Section 5 keeps pointing to state-approved rates.
    Section 5 will continue to reference the voltage-differentiated delivery rates and service classifications approved by the New York Public Service Commission PDF p. 3
  7. The owners will contract with the large load customer directly, not with energy service companies or other intermediaries.
    They do not volunteer to enter into Facilities Study, Security, Cost Recovery, and Interconnection Agreements with ESCOs or other intermediaries of Large Load Customers PDF p. 13
  8. Most revisions would take effect February 1, 2027, matching NYISO's filing.
    request an effective date for the revisions to Attachment LL and Attachment B of Section 8 of the NYISO OATT of February 1, 2027 PDF p. 34
  9. The owners' agreement for facilities studies sets fixed deposits and a schedule inside NYISO's study timeline.
    a pro forma Facilities Study Agreement provides a uniform framework, fixed study deposits, and a defined schedule for the Facilities Studies the Transmission Owners perform under Attachment LL PDF p. 3
  10. The owners add operating requirements for large loads paired with co-located or partner generation.
    operating requirements that apply to Large Loads interconnected under the LLIP, including Large Loads that take Non-Firm Transmission Withdrawal Service at a level below their maximum potential withdrawal and Large Loads paired with Co-Located or Partner Resources PDF p. 27

Text extracted from the eLibrary original (SHA-256 3bc6942441842057…). Download the original from the official source.

Contents · 19 sections
  1. I. EXECUTIVE SUMMARY p. 2
  2. II. BACKGROUND p. 4
  3. A. The Large Load Show Cause Order p. 4
  4. B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement p. 6
  5. C. Stakeholder Processes p. 8
  6. III. PROPOSED TARIFF REVISIONS AND PRO FORMA AGREEMENTS p. 8
  7. A. Jurisdictional Status of this Filing p. 10
  8. B. Network Upgrade Cost Recovery p. 14
  9. C. Large Load Security Agreement p. 19
  10. D. Revenue Crediting p. 20
  11. E. Transmission Service Charges p. 20
  12. Request for Relief p. 26
  13. F. Operating Terms Applicable to Non-Firm Transmission Withdrawal p. 27
  14. G. Interconnection Study Provisions and Pro Forma Facilities Study and p. 30
  15. IV. EFFECTIVE DATE AND REQUESTS FOR WAIVER p. 34
  16. V. COMMUNICATIONS p. 35
  17. VI. CONTENTS OF THE FILING p. 35
  18. VII. SERVICE p. 36
  19. VIII. CONCLUSION p. 36

Topics in the text: Cost allocation · Retail and wholesale authority · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Unless otherwise defined herein, capitalized terms used in this transmittal letter shall have the meanings ascribed to them in the NYISO OATT. 5 See Show Cause Order, 195 FERC ¶ 61,216.
Read this passage

I. EXECUTIVE SUMMARY

printed heading · Topic match: Cost allocation

Because the first Large Loads under the NYISO’s new procedures are not expected to complete Facilities Studies until Q3 2028, the NYTOs request that the Commission allow the NYPSC to address any changes to delivery rates serving Large Loads in the NYPSC’s pending proceeding in 9 NYISO OATT, Section…
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

A. The Large Load Show Cause Order

printed heading · Topic match: Connecting load and generation

Cir. 2024) (“[T]he cost causation principle requires that ‘all approved rates reflect to some degree the costs actually caused by the customer who must pay them.’”) (quoting S.C.
Read this passage

B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement

printed heading · Topic match: Filing procedure

The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement As the NYTOs explained in their motion to hold the Show Cause Order proceeding in abeyance, the NYTOs have explicitly reserved FPA section 205 filing rights in section 3.10(a) of the NYISO-TO Agreement.24 Section 3.10(a) provides, in…
Read this passage

C. Stakeholder Processes

printed heading

Stakeholder Processes The NYTOs participated in the NYISO stakeholder process relating to this proceeding, culminating in the NYISO’s Management Committee’s unanimous approval with abstentions of the extensive FPA section 205 filing the NYISO makes in parallel with this filing.
Read this passage

III. PROPOSED TARIFF REVISIONS AND PRO FORMA AGREEMENTS

printed heading · Topic match: Cost allocation

In addition, the following three proposed pro forma agreements are intended to work together to ensure appropriate cost recovery and integration of Large Loads in a manner that avoids undue cost shifts to other transmission customers: • A pro forma CRA recovering the allocated costs of Transmission…
Read this passage

A. Jurisdictional Status of this Filing

printed heading · Topic match: Retail and wholesale authority

Therefore, to the extent a Transmission Owner and a Large Load Customer enter into a cost recovery agreement (whether voluntary or pursuant to state law) through which the Large Load Customer guarantees November 16, 2026 Page 11 contributions to the transmission owner’s Commission-jurisdictional…
Read this passage

B. Network Upgrade Cost Recovery

printed heading · Topic match: Cost allocation

For each Network Upgrade or November 16, 2026 Page 15 Attachment Facility that is to mitigate or remedy violations caused by more than one project of a Large Load Cluster, the costs of the associated upgrade shall be allocated in accordance with the Allocation Factors identified in the Facilities…
Read this passage

C. Large Load Security Agreement

printed heading · Topic match: Cost allocation

November 16, 2026 Page 20 an irrevocable standby letter of credit from a qualifying bank, for such events as abandonment of the project, events of default under the related agreements after any applicable cure period, notification by the customer that it is ceasing to negotiate the CRA or Large…
Read this passage

D. Revenue Crediting

printed heading

D.
Read this passage

E. Transmission Service Charges

printed heading · Topic match: Cost allocation

For example, if a Large Load requests firm service, and the CTO can provide firm service, but the NYISO requires Non-Firm Service pending new capacity additions because the Large Load fails a Resource Adequacy Screen, then the CTO may still be providing Firm Service on its system and treating the…
Read this passage

Request for Relief

printed heading · Topic match: Cost allocation

In undertaking that review, the NYTOs will also consider whether relevant NYPSC determinations warrant changes to the default Network Upgrade cost allocation and recovery methodology proposed in the CRA and, where appropriate, may pursue such changes through a subsequent filing under Section 205;…
Read this passage

F. Operating Terms Applicable to Non-Firm Transmission Withdrawal

printed heading · Topic match: Reliability and curtailment

The NYTOs also propose new defined terms for “Franchise Utility” and “Retail Tariff” to reflect that retail service to a Large Load may be provided by an entity other than the CTO.72 Disconnections must be coordinated in advance with the NYISO and the Franchise Utility for non-urgent situations,…
Read this passage

G. Interconnection Study Provisions and Pro Forma Facilities Study and

printed heading · Topic match: Cost allocation

Interconnection Study Provisions and Pro Forma Facilities Study and Interconnection Agreements In its filing under section 205, the NYISO proposes to retain the existing structure of the Facilities Study for new Firm Withdrawal Service and Non-Firm Withdrawal Service.
Read this passage

IV. EFFECTIVE DATE AND REQUESTS FOR WAIVER

printed heading

EFFECTIVE DATE AND REQUESTS FOR WAIVER The NYISO (on the NYTOs’ behalf) is submitting the enclosed Tariff revisions in eTariff format in accordance with the requirements of Order No. 714 and a requested effective date of February 1, 2027, though many tariff sheets apply to only those customers and…
Read this passage

V. COMMUNICATIONS

printed heading

COMMUNICATIONS All communications and correspondence regarding this filing should be forwarded to the following individuals, whose names should be placed on the Commission’s service list:81 William R.
Read this passage

VI. CONTENTS OF THE FILING

printed heading

CONTENTS OF THE FILING In addition to this transmittal letter, this filing includes the following components: 1.
Read this passage

VII. SERVICE

printed heading

SERVICE Copies of this filing have been served on all customers under the NYISO OATT and the NYPSC.82 This filing also will be posted in conformance with the Commission’s regulations.83
Read this passage

VIII. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, the NYTOs respectfully request that the Commission accept as just and reasonable and not unduly discriminatory or preferential the Tariff provisions and pro forma agreements proposed herein with the above-specified effective dates. [Signatures on…