ER27-529-000 · 2026-11-16 · New York Independent System Operator, Inc., Central Hudson Gas & Electric Corporation and 5 others

Att I Panel Testimony

Text extracted from the eLibrary original (SHA-256 78f1a9a30f61de30…). Download the original from the official source.

Contents · 183 sections
  1. Attachment I p. 1
  2. Attachment I p. 5
  3. Attachment I p. 6
  4. I. INTRODUCTION p. 6
  5. A. My name is Brian McNierney. My business address is 18 Link Drive, Binghamton, New p. 6
  6. A. In 1986, I graduated from St. Bonaventure University with a Bachelor of Business p. 6
  7. A. Yes, I have submitted testimony in New York Public Service Commission (“NYPSC” or p. 6
  8. Attachment I p. 7
  9. A. My name is Carol Teixeira. My business address is 300 Erie Boulevard West, Syracuse, p. 7
  10. A. In 1989, I graduated from Syracuse University with a Bachelor of Science in Electrical p. 7
  11. Attachment I p. 8
  12. A. Yes. I testified before the NYPSC in support of the electric rate proposals in the NMPC’s p. 8
  13. Attachment I p. 9
  14. A. My name is Yan Flishenbaum. My business address is 4 Irving Place, New York, NY p. 9
  15. Attachment I p. 10
  16. A. Yes. I have filed testimony before the NYPSC and the New Jersey Board of Public p. 10
  17. A. My name is Stacy Powers. My business address is 284 South Avenue, Poughkeepsie, New p. 10
  18. Attachment I p. 11
  19. A. Yes, I have filed testimony before the NYPSC. p. 11
  20. A. We are testifying on behalf of Central Hudson, Con Edison, NYSEG, NMPC, Orange and p. 11
  21. A. The purpose of our testimony is to support the Indicated NYTOs’ proposed revisions to p. 11
  22. Attachment I p. 12
  23. A. Yes. On behalf of the Indicated NYTOs,2 we are sponsoring the following exhibits, which p. 12
  24. II. HISTORICAL BACKGROUND p. 12
  25. A. The PSC adopted retail access programs in 1996. Under retail access, electric commodity p. 12
  26. Attachment I p. 13
  27. A. Since the NYISO was formed, Section 5 of the ISO OATT has referenced each p. 13
  28. Attachment I p. 14
  29. III. NYPSC BUNDLED DELIVERY RATES p. 14
  30. A. Central Hudson, Con Edison, NYSEG, NMPC, O&R, and RG&E recover their p. 14
  31. A. There is no stand-alone, transmission-only retail rate in New York that could be applied to p. 14
  32. Attachment I p. 15
  33. IV. THE NYPSC RATEMAKING PROCESS p. 15
  34. A. The Staff of the Department of Public Service (“DPS Staff”) participates as a party in every p. 15
  35. Attachment I p. 16
  36. A. The parties conduct extensive discovery through information requests, and DPS Staff (and p. 16
  37. A. No. Most rate cases are resolved through multi-party settlement negotiations that produce p. 16
  38. A. The PSC does not simply accept a joint proposal because the parties have agreed to it. It p. 16
  39. Attachment I p. 17
  40. A. The PSC issues a final order adopting, modifying, or rejecting the joint proposal, or p. 17
  41. A. Yes. The current rates of Central Hudson, Con Edison, NMPC, and O&R are based on p. 17
  42. V. CURRENT RATES AND CHARGES p. 17
  43. A. Yes. The service classifications available to transmission-voltage customers, including p. 17
  44. Attachment I p. 18
  45. A. Base delivery rates for these classes generally consist of a monthly customer charge plus a p. 18
  46. A. No. Customers in a transmission-voltage service class pay more than transmission charges p. 18
  47. A. Each Indicated Transmission Owner has several PSC-authorized surcharges that apply to p. 18
  48. Attachment I p. 19
  49. A. The components of the SBC related to cost recovery for the program budgets of the New p. 19
  50. A. Pursuant to Section 14.1 of Attachment H, the wholesale Transmission Service Charge p. 19
  51. VI. VOLTAGE DIFFERENTIATION OF PSC-APPROVED DELIVERY RATES p. 19
  52. A. The following table lists, by utility, the various service classifications that will apply to p. 19
  53. Attachment I p. 20
  54. Attachment I p. 21
  55. A. Yes. p. 21
  56. A. Yes. For example, for NYSEG’s PSC service classification SC 7, Large General Service p. 21
  57. A. Yes. For example, for NYSEG’s PSC service classification SC 7, Large General Service p. 21
  58. A. Yes. A 100 MW Large Load with 73,000 MWh of energy consumption for a given month p. 21
  59. Attachment I p. 22
  60. A. Yes. NMPC electric rates have voltage differentiated delivery rates for all of its large p. 22
  61. A. For a customer billed at standard SC3A rates, the customer would pay a much lower p. 22
  62. Attachment I p. 23
  63. A. Yes, but only to a limited extent. SC3A Transmission rates are primarily composed of p. 23
  64. A. Yes. Similar to the example above but for a customer on the SC7 (parent SC3A) rate, p. 23
  65. Attachment I p. 24
  66. A. These hypothetical rate scenarios broadly illustrate the impact of voltage differentiation on p. 24
  67. A. Yes, generally speaking. In accordance with applicable procedures for delivery service, p. 24
  68. A. Under the PSC-approved rate classifications, standby and optional demand rates include p. 24
  69. Attachment I p. 25
  70. A. Yes. Any Large Load demand reduction would produce the same rate reduction benefit p. 25
  71. A. Yes. NYSEG, as well as other Indicated NYTOs, offer Optional Demand Service/Standby p. 25
  72. A. Yes. Consider an example in which a Large Load is curtailed by the NYISO or a utility to p. 25
  73. Attachment I p. 26
  74. A. Yes, the chart below provides the total delivery charges in a month for a large load customer p. 26
  75. Attachment I p. 27
  76. A. These hypothetical rate scenarios illustrate that there are lower charges potentially p. 27
  77. A. In the case of settled rates, isolating the transmission component in the Indicated NYTOs’ p. 27
  78. Attachment I p. 28
  79. A. It would likely disrupt their collection. Many state policy costs are collected through p. 28
  80. Attachment I p. 29
  81. A. Whether an unbundled transmission rate would displace a PSC delivery rate is an open p. 29
  82. A. The revisions extend Section 5 to Eligible Customers serving Large Loads and reference p. 29
  83. Attachment I p. 30
  84. A. As reflected in the Revised Section 5.1.1, each retail access customer, including an Eligible p. 30
  85. A. The revisions update each company-specific description in Section 5.2 to cite the current p. 30
  86. Attachment I p. 31
  87. VIII. THE NYISO’S COMPANION FILING p. 31
  88. A. The NYISO’s filing proposes new Attachment LL to the ISO OATT, including, inter alia, p. 31
  89. A. The two filings are complementary. The NYISO’s charges do not address the embedded p. 31
  90. Attachment I p. 32
  91. A. No. A Large Load that is using Non-Firm Withdrawal Service may be curtailed by the p. 32
  92. A. Yes. The terms of the NYISO’s Non-Firm Withdrawal Service have been evolving until p. 32
  93. Attachment I p. 33
  94. IX. CONCLUSION p. 33
  95. A. Yes. p. 33
  96. Summary p. 96
  97. VIII. SERVICE CLASSIFICATIONS (continued): p. 134
  98. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 134
  99. VIII. SERVICE CLASSIFICATIONS (continued): p. 135
  100. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 135
  101. VIII. SERVICE CLASSIFICATIONS (continued): p. 136
  102. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 136
  103. VIII. SERVICE CLASSIFICATIONS (continued): p. 137
  104. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 137
  105. VIII. SERVICE CLASSIFICATIONS (continued): p. 138
  106. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 138
  107. VIII. SERVICE CLASSIFICATIONS (continued): p. 139
  108. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 139
  109. VIII. SERVICE CLASSIFICATIONS (continued): p. 140
  110. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 140
  111. VIII. SERVICE CLASSIFICATIONS (continued): p. 141
  112. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 141
  113. VIII. SERVICE CLASSIFICATIONS (continued): p. 142
  114. I. SERVICE CLASSIFICATION NO. 2 - MRP p. 142
  115. VIII. SERVICE CLASSIFICATIONS (continued): p. 144
  116. VIII. SERVICE CLASSIFICATIONS (continued): p. 145
  117. VIII. SERVICE CLASSIFICATIONS (continued): p. 146
  118. VIII. SERVICE CLASSIFICATIONS (continued): p. 147
  119. VIII. SERVICE CLASSIFICATIONS (continued): p. 148
  120. VIII. SERVICE CLASSIFICATIONS (continued): p. 149
  121. VIII. SERVICE CLASSIFICATIONS (continued): p. 150
  122. VIII. SERVICE CLASSIFICATIONS (continued): p. 151
  123. VIII. SERVICE CLASSIFICATIONS (continued): p. 152
  124. VIII. SERVICE CLASSIFICATIONS (continued): p. 153
  125. VIII. SERVICE CLASSIFICATIONS (continued): p. 154
  126. VIII. SERVICE CLASSIFICATIONS (continued): p. 155
  127. VIII. SERVICE CLASSIFICATIONS (continued): p. 156
  128. VIII. SERVICE CLASSIFICATIONS (continued): p. 157
  129. VIII. SERVICE CLASSIFICATIONS (continued): p. 158
  130. VIII. SERVICE CLASSIFICATIONS (continued): p. 159
  131. VIII. SERVICE CLASSIFICATIONS (continued): p. 160
  132. VIII. SERVICE CLASSIFICATIONS (continued): p. 161
  133. VIII. SERVICE CLASSIFICATIONS (continued): p. 162
  134. VIII. SERVICE CLASSIFICATIONS (continued): p. 163
  135. VIII. SERVICE CLASSIFICATIONS (continued): p. 164
  136. VIII. SERVICE CLASSIFICATIONS (continued): p. 165
  137. VIII. SERVICE CLASSIFICATIONS (continued): p. 166
  138. VIII. SERVICE CLASSIFICATIONS (continued): p. 167
  139. VIII. SERVICE CLASSIFICATIONS (continued): p. 168
  140. VIII. SERVICE CLASSIFICATIONS (continued): p. 169
  141. A. Combined Metering and Billing: When the Company, pursuant to Rule 25.1.4.3, has provided Electric p. 176
  142. B. Metering Voltage: When a customer provides the high voltage equipment to accept a service voltage higher p. 176
  143. C. Riders: Service taken under this service classification may be eligible for a limited-duration bill reduction p. 176
  144. D. RESERVED FOR FUTURE USE p. 176
  145. E. On-Site Generation Special Provision - Customers are obligated to certify, subject to the Company’s p. 177
  146. F. Retail Access: Customers served in this Rate Classification are eligible to participate in the Retail Access p. 177
  147. G. For customers who operate a generator in excess of 25 MVa or greater and install automatic voltage control p. 177
  148. H. Net Energy Billing for Certain Customers Operating Solar or Farm Waste Electric Generating p. 177
  149. I. Net Energy Billing for Certain Customers Operating Solar or Farm Service Electric Generating p. 177
  150. A. Company Facilities: Company shall not be required to provide facilities for SC-4 Supplemental Service, p. 185
  151. B. Billing Period Adjustments: For a fractional part of a billing period at the beginning or end of service, the p. 185
  152. C. Metering Voltage: When service is metered at a voltage either higher or lower than the voltage of p. 185
  153. D. On-Site Generation Special Provision: Customers are obligated to certify, subject to the Company’s p. 185
  154. E. Individually Negotiated Rates: The Company will entertain, when circumstances warrant and when NYPA consents p. 186
  155. F. Exemption from Certain Provisions of Rate Schedule S.C. No. 3: Customers receiving SC-4 Supplemental Service p. 186
  156. G. Special Rule for SC-4 Supplemental Service: SC-4 Supplemental Service, with the exception of supplemental p. 186
  157. H. Special Rules for HLF Delivery Service p. 186
  158. I. Special Rules for Niagara Power Delivery Service and Preservation Power Delivery Service p. 187
  159. B. Separately Metered Accounts Not Served by OSG p. 195
  160. C. Small Generators p. 195
  161. D. Certain Customers Grandfathered Under Form Gf: Standby service rates shall not apply to p. 195
  162. D. Certain Customers Grandfathered Under Form Gf: (Continued) p. 196
  163. E. NYPA Programs and SC 12 Contracts p. 196
  164. F. Environmentally Advantageous Technologies (“EAT”) Exemptions p. 196
  165. F. Environmentally Advantageous Technologies (“EAT”) Exemptions (Continued) p. 198
  166. F. Environmentally Advantageous Technologies (“EAT”) Exemptions (Continued) p. 199
  167. G. Net Metering for Solar, Farm Waste, Wind, Micro-Combined Heat and Power, Micro-Hydroelectric p. 199
  168. H. Emergency Generators p. 200
  169. I. Customers served on SC-2D with a contract demand less than 50 kW may elect to remain on the SC-2D p. 200
  170. A. Interval Metering: All Standby Service Customers and Optional Rate Customers shall utilize the p. 213
  171. B. Telecommunications: Remote meter reading capability is also required for all Standby Service Customers p. 213
  172. C. Customer-Provided Equipment: Customers providing a telephone connection to the meter will bear all costs p. 213
  173. D. Company-Provided Equipment: Customers who choose the Company-provided meter reading p. 213
  174. E. Exceptions for Customers Smaller Than 50 kW: In addition, customers who would otherwise receive p. 214
  175. A. Contract Demands Larger than 1000 kW: All Standby Service Customers with Contract Demands p. 214
  176. B. SC-4 Customers: Customers who would otherwise receive service under the provisions of Service p. 214
  177. C. Compliance with Reliability Criteria: Standby Service Customers agree to comply with any existing or p. 214
  178. D. Electrically Isolated Loads: In the event that any customer elects to Electrically Isolate (as defined in Rule p. 214
  179. E. Penalties for Reconnecting Isolated Loads without Notice: Notwithstanding any other provision of this p. 215
  180. F. Reduced Customer Charge for Certain Wholesale Generators p. 216
  181. G. Billing for Customers With OSG’s Less Than or Equal to 15% of Maximum Potential Demand: p. 217
  182. H. Waiver of Reactive Demand Charges for Wholesale Generators Larger Than 25 MVA and With p. 218
  183. A. Reserved for Future Use p. 384

Read the parent filing

Topics in the text: Reliability and curtailment · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 34, 112, 113, 114, 115, 117, 118, 119, 120, 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132, 350, 351, 352, 353, 354, 355, 356, 358, 359, 360, 361, 362, 363, 364, 365, 366.

Attachment I

printed heading

Attachment I Panel Testimony and exhibit of Brian McNierney, Carol Teixeira, Yan Flishenbaum, and Stacy Powers UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Central Hudson Gas & Electric Corporation ) Consolidated Edison Company of New York, Inc. ) New York State…
Read this passage

TABLE OF CONTENTS

printed heading

TABLE OF CONTENTS I.
Read this passage

Attachment I

printed heading

Attachment I Page 1 of 29 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Central Hudson Gas & Electric Corporation ) Consolidated Edison Company of New York, Inc. ) New York State Electric & Gas Corporation ) Docket No.
Read this passage

Attachment I

printed heading

Attachment I Page 2 of 29
Read this passage

I. INTRODUCTION

printed heading

MCNIERNEY, PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
Read this passage

A. My name is Brian McNierney. My business address is 18 Link Drive, Binghamton, New

printed heading

My business address is 18 Link Drive, Binghamton, New York 13902.
Read this passage

A. In 1986, I graduated from St. Bonaventure University with a Bachelor of Business

printed heading

Bonaventure University with a Bachelor of Business Administration.
Read this passage

A. Yes, I have submitted testimony in New York Public Service Commission (“NYPSC” or

printed heading

Yes, I have submitted testimony in New York Public Service Commission (“NYPSC” or “PSC”) Cases 15-E-5 0283 et al., Cases 19-E-0378 6 et al., Cases 22-E-0317 7 et al. and Cases 25-E-0375 et al.
Read this passage

Attachment I

printed heading

TEIXEIRA, PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
Read this passage

A. My name is Carol Teixeira. My business address is 300 Erie Boulevard West, Syracuse,

printed heading

My business address is 300 Erie Boulevard West, Syracuse, New York 13202.
Read this passage

A. In 1989, I graduated from Syracuse University with a Bachelor of Science in Electrical

printed heading

In 1989, I graduated from Syracuse University with a Bachelor of Science in Electrical Engineering.
Read this passage

Attachment I

printed heading

Attachment I Page 4 of 29 Niagara Mohawk’s system.
Read this passage

A. Yes. I testified before the NYPSC in support of the electric rate proposals in the NMPC’s

printed heading

I testified before the NYPSC in support of the electric rate proposals in the NMPC’s 2017 electric rate case (Case 17-E-0238), the NMPC 2020 rate case (Case 20-E-0380) and the NMPC 2024 rate case (Case 24-E-0322).
Read this passage

Attachment I

printed heading

Attachment I Page 5 of 29 National Grid in support of the NMPC Wholesale Distribution Services tariff, filed with FERC on October 2, 2026, in Docket No.
Read this passage

A. My name is Yan Flishenbaum. My business address is 4 Irving Place, New York, NY

printed heading

My business address is 4 Irving Place, New York, NY 10003.
Read this passage

Attachment I

printed heading

Attachment I Page 6 of 29 Manager of the Orange and Rockland Rates section.
Read this passage

A. Yes. I have filed testimony before the NYPSC and the New Jersey Board of Public

printed heading

I have filed testimony before the NYPSC and the New Jersey Board of Public Utilities.
Read this passage

A. My name is Stacy Powers. My business address is 284 South Avenue, Poughkeepsie, New

printed heading

My business address is 284 South Avenue, Poughkeepsie, New York 12601.
Read this passage

Attachment I

printed heading

POWERS, HAVE YOU PREVIOUSLY TESTIFIED IN REGULATORY PROCEEDINGS?
Read this passage

A. Yes, I have filed testimony before the NYPSC.

printed heading

A.
Read this passage

A. We are testifying on behalf of Central Hudson, Con Edison, NYSEG, NMPC, Orange and

printed heading

We are testifying on behalf of Central Hudson, Con Edison, NYSEG, NMPC, Orange and Rockland Utilities, Inc. (“O&R”), and RG&E (collectively, “Indicated New York Transmission Owners” or “Indicated NYTOs” and individually, “Transmission Owner”) as rates subject matter expert representatives.
Read this passage

A. The purpose of our testimony is to support the Indicated NYTOs’ proposed revisions to

printed heading

The purpose of our testimony is to support the Indicated NYTOs’ proposed revisions to Section 5 of the New York Independent System Operator, Inc. (“NYISO”) Open Access Transmission Tariff (“ISO OATT”), which the Indicated NYTOs are submitting pursuant to section 205 of the Federal Power Act (“FPA”)…
Read this passage

Attachment I

printed heading

Attachment I Page 8 of 29 how bundled New York delivery rates are developed and collected, how those rates are voltage-differentiated and offer Large Loads meaningful choices, and why a separate transmission-only rate for Large Loads at this time would be potentially harmful.
Read this passage

A. Yes. On behalf of the Indicated NYTOs,2 we are sponsoring the following exhibits, which

printed heading

On behalf of the Indicated NYTOs,2 we are sponsoring the following exhibits, which are attached to and made a part of our testimony: Exhibit A – The NYTOs’ PSC Delivery Rates of the Applicable Transmission Owner to Large Loads.
Read this passage

II. HISTORICAL BACKGROUND

printed heading

WHEN DID RETAIL ACCESS BEGIN IN NEW YORK RELATIVE TO THE START OF THE NYISO’S OPERATIONS?
Read this passage

A. The PSC adopted retail access programs in 1996. Under retail access, electric commodity

printed heading

Under retail access, electric commodity supply was unbundled from transmission and distribution service for eligible retail customers and the energy service companies (“ESCOs”) serving them.
Read this passage

Attachment I

printed heading

Attachment I Page 9 of 29 As part of the development of the initial ISO OATT, Section 5 of the ISO OATT was developed to address already State-approved retail access programs, and it identified the rates and charges under which retail access customers would receive service.
Read this passage

A. Since the NYISO was formed, Section 5 of the ISO OATT has referenced each

printed heading

Since the NYISO was formed, Section 5 of the ISO OATT has referenced each Transmission Owner’s PSC-approved retail access tariff or, for LIPA, the rates and terms established under State law, as the respective retail tariffs may be amended from time-to- time.
Read this passage

Attachment I

printed heading

Attachment I Page 10 of 29
Read this passage

III. NYPSC BUNDLED DELIVERY RATES

printed heading

HOW DO THE INDICATED NYTOS RECOVER THEIR TRANSMISSION AND DISTRIBUTION COSTS FROM RETAIL CUSTOMERS?
Read this passage

A. Central Hudson, Con Edison, NYSEG, NMPC, O&R, and RG&E recover their

printed heading · Topic match: Cost allocation

While the commodity supply (capacity and energy) is unbundled from the delivery rates, the delivery rates remain bundled for the most part, even though they are voltage-differentiated based on cost allocations which intentionally remove certain distribution costs from the rates developed for…
Read this passage

A. There is no stand-alone, transmission-only retail rate in New York that could be applied to

printed heading · Topic match: Retail and wholesale authority

There is no stand-alone, transmission-only retail rate in New York that could be applied to Large Loads.
Read this passage

Attachment I

printed heading

Attachment I Page 11 of 29 retail customer classes.
Read this passage

IV. THE NYPSC RATEMAKING PROCESS

printed heading

The rate design testimony proposes how each service class’s share will be recovered through customer charges, demand charges, energy charges, and time-of-use or other rate features.
Read this passage

A. The Staff of the Department of Public Service (“DPS Staff”) participates as a party in every

printed heading

The Staff of the Department of Public Service (“DPS Staff”) participates as a party in every major rate case.
Read this passage

Attachment I

printed heading

Attachment I Page 12 of 29 income customers, ESCOs and their trade associations, environmental advocates, and others.
Read this passage

A. The parties conduct extensive discovery through information requests, and DPS Staff (and

printed heading

The parties conduct extensive discovery through information requests, and DPS Staff (and at times other intervenors) file responsive testimony.
Read this passage

A. No. Most rate cases are resolved through multi-party settlement negotiations that produce

printed heading · Topic match: Cost allocation

A joint proposal typically resolves the revenue requirement, cost allocation, and rate design for every service class at once.
Read this passage

A. The PSC does not simply accept a joint proposal because the parties have agreed to it. It

printed heading · Topic match: Cost allocation

It reviews the joint proposal under its settlement guidelines, which consider, among other things, whether the settlement is consistent with law and PSC policy; whether it produces results within the range of reasonable outcomes that would likely arise from litigation; whether it balances the…
Read this passage

Attachment I

printed heading

Attachment I Page 13 of 29 utility; and whether it is supported by testimony and evidence submitted in the formal record.6 The PSC may review items such as testimony, evidence, statements in support from the parties, and, if applicable a recommended decision, submitted in the formal record to…
Read this passage

A. The PSC issues a final order adopting, modifying, or rejecting the joint proposal, or

printed heading

The PSC issues a final order adopting, modifying, or rejecting the joint proposal, or resolving litigated issues, and directs the utility to file compliance tariffs.
Read this passage

A. Yes. The current rates of Central Hudson, Con Edison, NMPC, and O&R are based on

printed heading

The current rates of Central Hudson, Con Edison, NMPC, and O&R are based on PSC-approved settlements rather than fully litigated orders.
Read this passage

V. CURRENT RATES AND CHARGES

printed heading

HAVE THE RATE DESIGNS FOR TRANSMISSION-VOLTAGE CUSTOMERS BEEN DEVELOPED OVER TIME?
Read this passage

A. Yes. The service classifications available to transmission-voltage customers, including

printed heading

The service classifications available to transmission-voltage customers, including standby and optional demand rates, have been refined or resulted from an evolutionary process over many individual utility rate cases and statewide proceedings and many years. 6 Procedural Guidelines for Settlements,…
Read this passage

Attachment I

printed heading

Attachment I Page 14 of 29 Each iteration was refined through discovery, testimony, and negotiation among parties representing all customer classes, and each was approved by the PSC.
Read this passage

A. Base delivery rates for these classes generally consist of a monthly customer charge plus a

printed heading

Base delivery rates for these classes generally consist of a monthly customer charge plus a per-kW demand charge.
Read this passage

A. No. Customers in a transmission-voltage service class pay more than transmission charges

printed heading

Customers in a transmission-voltage service class pay more than transmission charges alone.
Read this passage

A. Each Indicated Transmission Owner has several PSC-authorized surcharges that apply to

printed heading

Each Indicated Transmission Owner has several PSC-authorized surcharges that apply to its delivery load regardless of who serves as the customer’s LSE.
Read this passage

Attachment I

printed heading

HOW ARE THE SBC AND THE COSTS OF ZERO-EMISSION CREDITS COLLECTED?
Read this passage

A. The components of the SBC related to cost recovery for the program budgets of the New

printed heading

The components of the SBC related to cost recovery for the program budgets of the New York State Energy Research and Development Authority (“NYSERDA”) are split among the utilities on a load ratio share basis and billed to delivery customers as a per-kWh charge.
Read this passage

A. Pursuant to Section 14.1 of Attachment H, the wholesale Transmission Service Charge

printed heading

Pursuant to Section 14.1 of Attachment H, the wholesale Transmission Service Charge (“TSC”) is of limited application and applies primarily to “wheel through” and “export” transactions that exit the New York Control Area.
Read this passage

VI. VOLTAGE DIFFERENTIATION OF PSC-APPROVED DELIVERY RATES

printed heading

VOLTAGE DIFFERENTIATION OF PSC-APPROVED DELIVERY RATES Q.
Read this passage

A. The following table lists, by utility, the various service classifications that will apply to

printed heading

The following table lists, by utility, the various service classifications that will apply to Large Loads, subject to meeting the requirements to receive the specified service.
Read this passage

Attachment I

printed heading

SC 9 / SC 22: Standard Transmission Service SC 9 / 22: Standby Transmission Service Rochester Gas and Electric Corporation SC 8: Large General Service with Time-of-Use Metering SC 14: Standby Service Otherwise Applicable Service Class 8 SC 15: Optional Demand Service Otherwise Applicable Service…
Read this passage

Attachment I

printed heading

HAVE EACH OF THE INDICATED TOS PROVIDED THE SERVICE CLASSIFICATIONS IN EXHIBIT A?
Read this passage

A. Yes.

printed heading

MCNIERNEY, ARE THE PSC-APPROVED DELIVERY RATES THAT WILL APPLY TO LARGE LOADS DIFFERENTIATED BY VOLTAGE?
Read this passage

A. Yes. For example, for NYSEG’s PSC service classification SC 7, Large General Service

printed heading

For example, for NYSEG’s PSC service classification SC 7, Large General Service with Time-of-Use Metering, there are three currently available voltages (SC 7-1, 7-2, and 7-4): 7-1 – Secondary, 120–480 volts; 7-2 – Primary, 2.4–34.5 kV or regulated 46 kV; and 7-4 – Transmission, 115 kV and above.
Read this passage

A. Yes. For example, for NYSEG’s PSC service classification SC 7, Large General Service

printed heading

For example, for NYSEG’s PSC service classification SC 7, Large General Service with Time-of-Use Metering, the applicable demand charge (per kW) for each one of those voltages classifications is currently: 7-1 – $14.55; 7-2 – $13.76; and 7-4 – $2.07.
Read this passage

A. Yes. A 100 MW Large Load with 73,000 MWh of energy consumption for a given month

printed heading

A 100 MW Large Load with 73,000 MWh of energy consumption for a given month would have demand charges under NYSEG’s PSC service classification SC 7: 7-1 of $1,455,000 compared to $207,000 under NYSEG’s transmission voltage level demand charge 7-4 rate.
Read this passage

Attachment I

printed heading

Attachment I Page 18 of 29 connect at distribution voltage.
Read this passage

A. Yes. NMPC electric rates have voltage differentiated delivery rates for all of its large

printed heading

NMPC electric rates have voltage differentiated delivery rates for all of its large commercial and industrial service classes.
Read this passage

A. For a customer billed at standard SC3A rates, the customer would pay a much lower

printed heading

For a customer billed at standard SC3A rates, the customer would pay a much lower demand charge of $4.89 per maximum kW in the billing period at the Transmission level than: the $15.58 per maximum kW at the Secondary or Primary level and $5.42 at the Sub- transmission level.
Read this passage

Attachment I

printed heading

TEIXEIRA, DO SC3A TRANSMISSION RATES INCLUDE ANY DISTRIBUTION-RELATED CHARGES?
Read this passage

A. Yes, but only to a limited extent. SC3A Transmission rates are primarily composed of

printed heading · Topic match: Cost allocation

These costs are minimal relative to the overall cost allocation, with the vast majority of costs allocated to SC3A Transmission customers being transmission-related.
Read this passage

A. Yes. Similar to the example above but for a customer on the SC7 (parent SC3A) rate,

printed heading

Similar to the example above but for a customer on the SC7 (parent SC3A) rate, below are the monthly delivery charges at current rates.
Read this passage

Attachment I

printed heading

WHAT DO THESE HYPOTHETICAL EXAMPLES BROADLY ILLUSTRATE?
Read this passage

A. These hypothetical rate scenarios broadly illustrate the impact of voltage differentiation on

printed heading

These hypothetical rate scenarios broadly illustrate the impact of voltage differentiation on rates and the significantly lower demand charges applicable to a transmission level customer compared to a distribution customer based on PSC approved rates.
Read this passage

A. Yes, generally speaking. In accordance with applicable procedures for delivery service,

printed heading

In accordance with applicable procedures for delivery service, Large Loads and their LSEs may choose among the applicable classifications identified in revised OATT Section 5.2.8.
Read this passage

A. Under the PSC-approved rate classifications, standby and optional demand rates include

printed heading

Under the PSC-approved rate classifications, standby and optional demand rates include daily as-used demand charges.
Read this passage

Attachment I

printed heading

WOULD THE LARGE LOAD RECEIVE THE SAME RATE REDUCTION BENEFIT REGARDLESS OF WHETHER IT IS CURTAILED BY THE NYISO OR A UTILITY, OR IT VOLUNTARILY REDUCES ITS WITHDRAWALS?
Read this passage

A. Yes. Any Large Load demand reduction would produce the same rate reduction benefit

printed heading

Any Large Load demand reduction would produce the same rate reduction benefit whether it is directed by the NYISO or a utility, or it is the result of a voluntary reduction.
Read this passage

A. Yes. NYSEG, as well as other Indicated NYTOs, offer Optional Demand Service/Standby

printed heading

NYSEG, as well as other Indicated NYTOs, offer Optional Demand Service/Standby Service which can apply to a Large Load customer.
Read this passage

A. Yes. Consider an example in which a Large Load is curtailed by the NYISO or a utility to

printed heading

Consider an example in which a Large Load is curtailed by the NYISO or a utility to zero for five weekdays during the billing period.
Read this passage

Attachment I

printed heading · Topic match: Reliability and curtailment

TEIXEIRA, CAN YOU PROVIDE A HYPOTHETICAL EXAMPLE OF WHAT THE RESULTING CHARGE WOULD BE FOR A LARGE LOAD UNDER NMPC’S PSC STANDARD SERVICE CLASSIFICATION SC3A VS UNDER SC 7 (PARENT SC3A), WHEN THE CUSTOMER HAS REDUCED LOAD IN RESPONSE TO INTERRUPTIBLE LOAD REDUCTION REQUESTS?
Read this passage

A. Yes, the chart below provides the total delivery charges in a month for a large load customer

printed heading

Yes, the chart below provides the total delivery charges in a month for a large load customer when a customer pays for As-used Daily Demand charges for 15 on-peak days of the month instead of all the on-peak days of the month in the previous NMPC examples.
Read this passage

Attachment I

printed heading

WHAT DO THESE HYPOTHETICAL EXAMPLES BROADLY ILLUSTRATE?
Read this passage

A. These hypothetical rate scenarios illustrate that there are lower charges potentially

printed heading

These hypothetical rate scenarios illustrate that there are lower charges potentially applicable to a Large Load customer if it is subject to persistent curtailments or dispatch during peak or off-peak hours on any given day.
Read this passage

A. In the case of settled rates, isolating the transmission component in the Indicated NYTOs’

printed heading

Each joint proposal resolves the revenue requirement, cost allocation, and rate design for all classes as a package.
Read this passage

Attachment I

printed heading

Moreover, the Indicated NYTOs could have to re-open retail settlements to adjust existing rate classes in a revenue-neutral manner.
Read this passage

A. It would likely disrupt their collection. Many state policy costs are collected through

printed heading · Topic match: Cost allocation

Surcharges are not an insignificant portion of customers’ overall delivery charges and are necessary to achieve the overall retail cost allocation and rate design established in state regulatory proceedings.
Read this passage

Attachment I

printed heading

WOULD AN UNBUNDLED TRANSMISSION RATE ELIMINATE THE NEED FOR STATE DELIVERY CHARGES?
Read this passage

A. Whether an unbundled transmission rate would displace a PSC delivery rate is an open

printed heading

Whether an unbundled transmission rate would displace a PSC delivery rate is an open question.
Read this passage

A. The revisions extend Section 5 to Eligible Customers serving Large Loads and reference

printed heading

The revisions extend Section 5 to Eligible Customers serving Large Loads and reference the applicable PSC-approved, or LIPA Board of Trustees-approved, service classifications and delivery rates.7 The revised Section 5 details applicable delivery service classifications and rates for retail access…
Read this passage

Attachment I

printed heading

WHAT DO THE REVISIONS PROVIDE REGARDING THE CHARGES THAT APPLY TO LARGE LOADS?
Read this passage

A. As reflected in the Revised Section 5.1.1, each retail access customer, including an Eligible

printed heading

As reflected in the Revised Section 5.1.1, each retail access customer, including an Eligible Customer serving a Large Load, is responsible for paying the Retail Transmission Service Charge to the affected Transmission Owner consistent with the rates, terms and conditions of that Transmission…
Read this passage

A. The revisions update each company-specific description in Section 5.2 to cite the current

printed heading

The revisions update each company-specific description in Section 5.2 to cite the current PSC tariffs and to note the applicability to Eligible Customers serving Large Loads under Attachment LL.
Read this passage

Attachment I

printed heading

Attachment I Page 27 of 29 LL, and require Eligible Customers serving Large Loads to execute the form of Transmission Service Agreement attached to the ISO OATT.
Read this passage

VIII. THE NYISO’S COMPANION FILING

printed heading

WHAT DOES THE NYISO’S COMPANION SECTION 205 FILING PROPOSE?
Read this passage

A. The NYISO’s filing proposes new Attachment LL to the ISO OATT, including, inter alia,

printed heading

The NYISO’s filing proposes new Attachment LL to the ISO OATT, including, inter alia, new Firm Withdrawal Service and Non-Firm Withdrawal Service for Eligible Customers serving Large Loads.
Read this passage

A. The two filings are complementary. The NYISO’s charges do not address the embedded

printed heading

The NYISO’s charges do not address the embedded cost delivery charges that the utility holding the retail franchise applies under its PSC- authorized service classifications.
Read this passage

Attachment I

printed heading · Topic match: Reliability and curtailment

DOES CURTAILMENT OF A LARGE LOAD UNDER THE NYISO’S NON-FIRM SERVICE NECESSARILY REFLECT THE TRANSMISSION OWNER’S COST TO PROVIDE DELIVERY SERVICE?
Read this passage

A. No. A Large Load that is using Non-Firm Withdrawal Service may be curtailed by the

printed heading · Topic match: Cost allocation

That is another reason why a discounted non-firm delivery rate, keyed to NYISO curtailments, would not necessarily reflect cost causation.
Read this passage

A. Yes. The terms of the NYISO’s Non-Firm Withdrawal Service have been evolving until

printed heading

The terms of the NYISO’s Non-Firm Withdrawal Service have been evolving until very recently.
Read this passage

Attachment I

printed heading

That leaves time for the PSC and the Indicated NYTOs to develop any new rates that prove appropriate.
Read this passage

IX. CONCLUSION

printed heading

IX.
Read this passage

A. Yes.

printed heading · Topic match: Reliability and curtailment

Effective March 31, 1991, regardless of the type of service offered, electric service utilized exclusively with such religious purposes or utilized at such community residences, as defined in the Service Classification No. 1 Section entitled Applicable to Use of Service For, shall be charged at…
Read this passage

Summary

printed heading

The interval meter must be compatible with the Company’s metering infrastructure, and the customer must provide and maintain all meter communications services.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

SERVICE CLASSIFICATION NO. 2 - MRP Large General and Industrial Service With Multiple Rate Periods: (Rate Codes: 284, 285, M284, M285) 1.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

SERVICE CLASSIFICATION NO. 2 - MRP Large General and Industrial Service With Multiple Rate Periods (continued): (Rate Codes: 284, 285, M284, M285) Character of Service (continued): e) The Authority may consider loads with a minimum estimated demand of 10,000 kW for service at 23,000 volts or…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

SERVICE CLASSIFICATION NO. 2 - MRP Large General and Industrial Service With Multiple Rate Periods (continued): (Rate Codes: 284, 285, M284, M285) Rates and Charges per Meter per Month (continued): Rate Code 284 Secondary Primary Transmission Service Charge per day $ 3.83 $ 5.20 $ 5.20 Rate…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

Reactive Demand Charges - Rate Codes 284, 285, M284, and M285 a) Transmission and primary service Customers who use electricity at a Power Factor of less than 90% and choose to pay a monthly Reactive Demand Charge of $0.27 per KVAR, shall pay for the additional metering equipment either when it is…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

Terms of Payment The Customer shall pay the balance due in cash, including checks and money orders, on receiving the bill.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

Special Provisions a) Corrective Equipment Requirements When the installation includes welders, x-rays, or other apparatus having a highly fluctuating or large instantaneous demand, the Customer shall provide batteries, rotating equipment, or other corrective equipment to reduce the inrush current…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

There will be no demand charges associated with the incremental load subsequent to the ESD Approval Date.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

The hours June through September, Monday through Friday, from 10 a.m. to 3 p.m. and Saturday from 10 a.m. to 10 p.m., are included in the Intermediate period for Rate Code M285. e) Choosing Rate Code 284 or Rate Code 285 New Customers shall choose either Rate Code 284 or Rate Code 285 at the time…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

VIII.
Read this passage

I. SERVICE CLASSIFICATION NO. 2 - MRP

printed heading

SERVICE CLASSIFICATION NO. 2 - MRP Large General and Industrial Service With Multiple Rate Periods (continued): (Rate Codes: 284, 285, M284, M285) Special Provisions (continued): f) Transfer to Service Classification No. 2-L or 2L-VMRP At their option, Customers taking service at Service…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Standby rates will also apply to Generators that take station power through the same bus bar as they supply the grid. h) For Standby Service Customers, the Parent Service Classification shall be defined based upon the applicable Contract Demand at the delivery point (as initially calculated by the…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

This common point of interconnection may include up to one load serving connection, or tap, (such tap is in addition to the single point of delivery service from the generating customer to the Authority’s delivery system being metered), from a single physical bus bar (one tap must be connecting the…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

The Sub/Transmission Rate will apply to Radial transmission service. f) For Optional Standby Customers, service must comply with parent Service Classification based on the otherwise applicable Rate Code.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Exemptions From SC-12 The following customers shall not be subject to SC-12, but shall be served under the customer's otherwise applicable service classification unless Customers make a one-time irrevocable election to forfeit or refuse the exemption and join the Standby Rate or the in progress…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Units that have completed a Coordinated Electric System Interconnection Review (CESIR) by April 1, 2018 will be subject to the previously applicable standard of no more than 4.4 lbs./MWh of NOx emissions. (v) The CHP facility must be placed in service before May 31, 2021. (vi) Customers shall…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 Standby Service and Optional Rate Service (continued): (Rate Codes: 179, 680, 682) Exemptions from SC-12 (continued) In the event the Customer fails to comply with provisions (i) through (ii) above, the Authority shall have the following rights: To bill the customer…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

This log shall be made available to the Authority upon request.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Application for Service Standby Service: Customers with on-site generation that will run in parallel with the LIPA system must apply for service by providing the Authority with an executed Standby Service Application and SGIP, both of which are available on the Authority’s website or from an…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SC-1 rates shall have the determination of their Contract Demand (kW) and As Used Daily Demand (kW) based on a 60-minute integrated metered demand, which shall be determined as the sum of the four 15-minute intervals in an hour.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SC-12 customers billed under Parent Service Classification SC-2 Small rates shall have the determination of their Contract Demand (kW) and As Used Daily Demand (kW) based on a 60-minute integrated metered demand, which shall be determined as the sum of the four 15-minute intervals in an hour.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SC 2-L rates shall have the determination of their Contract Demand (kW) and As Used Daily Demand (kW) based on a 15-minute integrated metered demand.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SC 2-MRP rates shall have the determination of their Contract Demand (kW) and As Used Daily Demand (kW) based on a 15-minute integrated metered demand.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SC 2-MRP (Transmission) rates shall have the determination of their Contract Demand (kW) and As Used Daily Demand (kW) based on a 15-minute integrated metered demand.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Terms of Payment The Customer shall pay the balance due in cash, including checks and money orders, on receiving the bill.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

In the case of a new customer (i.e., a customer for whom historical consumption data does not exist), the Contract Demand shall be the maximum anticipated demand of load consumed as prescribed in the customer’s load letter.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Thereafter, the Contract Demand shall automatically be increased to the highest measured demand in any billing period during the term hereunder.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Interconnection Requirements a) The Authority may disconnect a Customer from the system if the Customer operates a generator in parallel with the Authority’s system without an Interconnection Agreement (IA) with the Authority. b) The Customer must sign an IA within ninety (90) days of written…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

Schedules must include starting and ending times for all planned outages.
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 Standby Service and Optional Rate Service (continued): (Rate Codes: 179, 680, 682) Special Provisions (continued) d) Penalties for Reconnecting Isolated Loads without Notice Notwithstanding any other provision of the Tariff, in the event that the customer connects…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 Standby Service and Optional Rate Service (continued): (Rate Codes: 179, 680, 682) Special Provisions (continued) f) Billing for Customers with Excelsior Jobs Program (“EJP”) Load Not Separately Metered (1) Only customers billed at commercial rates are eligible to…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 Standby Service and Optional Rate Service (continued): (Rate Codes: 179, 680, 682) Special Provisions (continued) g) SC-12 Phase-In Customers Existing customers prior to December 1, 2025 may elect to be billed the SC-12 Phase-In Standby Rate delivery charges beginning…
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 [CANCELLED] Long Island Power Authority Seventh Revised Leaf No. 266 Effective: January 1, 2026 Tariff For Electric Service
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 [CANCELLED] Long Island Power Authority Third Revised Leaf No. 267 Effective: January 1, 2026 Tariff For Electric Service
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 [CANCELLED] Long Island Power Authority Fourth Revised Leaf No. 268 Effective: January 1, 2026 Tariff For Electric Service
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 12 [CANCELLED] Long Island Power Authority Fourth Revised Leaf No. 269 Effective: January 1, 2026 Tariff for Electric Service
Read this passage

VIII. SERVICE CLASSIFICATIONS (continued):

printed heading

SERVICE CLASSIFICATION NO. 3A LARGE GENERAL SERVICE - TIME OF USE RATE APPLICABLE TO USE OF SERVICE FOR: Service shall be available throughout the Company's service area from existing circuits of adequate capacity and appropriate character.
Read this passage

A. Combined Metering and Billing: When the Company, pursuant to Rule 25.1.4.3, has provided Electric

printed heading

Combined Metering and Billing: When the Company, pursuant to Rule 25.1.4.3, has provided Electric Service at the customer's single location through more than one Retail Delivery Point, the quantities derived from all necessary meters will be combined for billing purposes in accordance with the…
Read this passage

B. Metering Voltage: When a customer provides the high voltage equipment to accept a service voltage higher

printed heading

Metering Voltage: When a customer provides the high voltage equipment to accept a service voltage higher than 2,200 volts, the Electric Service voltage will be the Company's incoming line voltage.
Read this passage

C. Riders: Service taken under this service classification may be eligible for a limited-duration bill reduction

printed heading

Riders: Service taken under this service classification may be eligible for a limited-duration bill reduction treatment as described in Rule 34, Economic Development Programs.
Read this passage

D. RESERVED FOR FUTURE USE

printed heading

Wynter, President, Syracuse, NY PSC NO: 220 ELECTRICITY LEAF: 396 NIAGARA MOHAWK POWER CORPORATION REVISION: 2 INITIAL EFFECTIVE DATE: MARCH 1, 2024 SUPERSEDING REVISION: 1 SERVICE CLASSIFICATION NO. 3A (Continued) SPECIAL PROVISIONS (Continued)
Read this passage

E. On-Site Generation Special Provision - Customers are obligated to certify, subject to the Company’s

printed heading

On-Site Generation Special Provision - Customers are obligated to certify, subject to the Company’s approval, on-site generation (OSG) installations on the Company’s Form G, Application for Electric Standby Service, and will be subject to the provisions of Service Classification No. 7 unless the…
Read this passage

F. Retail Access: Customers served in this Rate Classification are eligible to participate in the Retail Access

printed heading

Retail Access: Customers served in this Rate Classification are eligible to participate in the Retail Access Program in accordance with Rule 39, Retail Access Program.
Read this passage

G. For customers who operate a generator in excess of 25 MVa or greater and install automatic voltage control

printed heading

For customers who operate a generator in excess of 25 MVa or greater and install automatic voltage control (AVC) at their facilities, reactive demand charges shall be waived, with the parameters defined by the Company during the period in which such AVC is operating and maintained in good working…
Read this passage

H. Net Energy Billing for Certain Customers Operating Solar or Farm Waste Electric Generating

printed heading

Net Energy Billing for Certain Customers Operating Solar or Farm Waste Electric Generating Equipment- Customers who own or operate Solar Electric Generating Equipment located and used at its premises or Farm Waste Electric Generating Equipment located and used at the customer’s ‘Farm Operation”, as…
Read this passage

I. Net Energy Billing for Certain Customers Operating Solar or Farm Service Electric Generating

printed heading

Net Energy Billing for Certain Customers Operating Solar or Farm Service Electric Generating Equipment - Residential, farm service, and non-residential customers, who own or operate Wind Electric Generating Equipment may deliver electricity to the Company generated by the wind electric generating…
Read this passage

A. Company Facilities: Company shall not be required to provide facilities for SC-4 Supplemental Service,

printed heading

Company Facilities: Company shall not be required to provide facilities for SC-4 Supplemental Service, Niagara Power Delivery Service, Preservation Power Delivery Service or HLF Delivery Service in excess of the amount of the total demands for such services specified in the customer’s Application…
Read this passage

B. Billing Period Adjustments: For a fractional part of a billing period at the beginning or end of service, the

printed heading

Billing Period Adjustments: For a fractional part of a billing period at the beginning or end of service, the kilowatt Demand and Reactive Demand charges and the minimum charge shall each be proportionately adjusted in the ratio that the number of hours that electric service is furnished to…
Read this passage

C. Metering Voltage: When service is metered at a voltage either higher or lower than the voltage of

printed heading

Metering Voltage: When service is metered at a voltage either higher or lower than the voltage of delivery, metered quantities will be adjusted for billing as provided in Rule 25.4.
Read this passage

D. On-Site Generation Special Provision: Customers are obligated to certify, subject to the Company’s

printed heading

On-Site Generation Special Provision: Customers are obligated to certify, subject to the Company’s approval, on-site generation (OSG) installations on the Company’s Form G, Application For Electric Standby Service, and will be subject to the provisions of Service Classification No. 7 unless the…
Read this passage

E. Individually Negotiated Rates: The Company will entertain, when circumstances warrant and when NYPA consents

printed heading

Individually Negotiated Rates: The Company will entertain, when circumstances warrant and when NYPA consents to any required changes in the applicable billing methodology for the delivery of NYPA Power, individually negotiated contracts under rate schedule S.C.
Read this passage

F. Exemption from Certain Provisions of Rate Schedule S.C. No. 3: Customers receiving SC-4 Supplemental Service

printed heading

No. 3 shall be exempt from Special Provisions E, F, and H of that rate schedule.
Read this passage

G. Special Rule for SC-4 Supplemental Service: SC-4 Supplemental Service, with the exception of supplemental

printed heading

Special Rule for SC-4 Supplemental Service: SC-4 Supplemental Service, with the exception of supplemental service that is EJP qualifying load, shall be subject to all surcharges and tax factors imposed on service under the applicable Parent Service Classification, including without limitation the…
Read this passage

H. Special Rules for HLF Delivery Service

printed heading

This adjustment shall be performed by subtracting the contribution to the customer’s maximum metered demand in each of the preceding eleven billing months prior to July 1, 2013 only, made by the customer’s reduced contract capacity for NYPA ESS from the customer’s overall maximum metered demand in…
Read this passage

I. Special Rules for Niagara Power Delivery Service and Preservation Power Delivery Service

printed heading

In no instance, however, shall the total demand (the sum of the historic and additional power demands) billed by Company under its rates exceed the total metered demand for the billing period.
Read this passage

B. Separately Metered Accounts Not Served by OSG

printed heading

Separately Metered Accounts Not Served by OSG All separately metered service accounts within the premises whereby electricity consumption is not otherwise served directly through facilities owned by the customer (e.g., power to the facility's outer buildings) shall be provided at the standard…
Read this passage

C. Small Generators

printed heading

Small Generators Customers with a nameplate aggregate generator(s) 5 kVA or smaller shall be served at the standard tariff rates for the Parent Service Classification.
Read this passage

D. Certain Customers Grandfathered Under Form Gf: Standby service rates shall not apply to

printed heading

Certain Customers Grandfathered Under Form Gf: Standby service rates shall not apply to customers served on the standard classification as of January 1, 2002 that have executed a form Gf and were grandfathered as a result of Form Gf of PSC 207 as of January 1, 2002; except where such customer is a…
Read this passage

D. Certain Customers Grandfathered Under Form Gf: (Continued)

printed heading

Certain Customers Grandfathered Under Form Gf: (Continued) For the purposes of this provision, New Generating Equipment shall include the installation or the replacement of the following items of electric plant: (i) for steam production plant: boiler plant equipment; engines and engine-driven…
Read this passage

E. NYPA Programs and SC 12 Contracts

printed heading

NYPA Programs and SC 12 Contracts Standby service rates shall not apply to that portion of a customer's delivery service associated with the provision of applicable NYPA programs or that portion of delivery service served under the terms and conditions of an SC-12 contract.
Read this passage

F. Environmentally Advantageous Technologies (“EAT”) Exemptions

printed heading

Environmentally Advantageous Technologies (“EAT”) Exemptions Standby service rates shall not apply to customers who install On-Site Generators (“OSG”) that are: (1) solar thermal; (2) solar photovoltaic; (3) onshore and offshore wind; (4) hydroelectric; (5) geothermal electric; (6) geothermal…
Read this passage

F. Environmentally Advantageous Technologies (“EAT”) Exemptions (Continued)

printed heading

Customers qualifying for the EAT Exemption shall comply with all the following requirements: a) The OSG is placed in service after July 1, 2002, except that for CHP facilities, in accordance with Section 7 above, the OSG is placed in service between June 1, 2015 and May 31, 2021. b) The OSG is…
Read this passage

F. Environmentally Advantageous Technologies (“EAT”) Exemptions (Continued)

printed heading

Environmentally Advantageous Technologies (“EAT”) Exemptions (Continued) Customers qualifying for the EAT Exemption shall be allowed to make a one-time irrevocable election to refuse the EAT Exemption and, instead, take service at full standby service rates, upon providing thirty (30) days written…
Read this passage

G. Net Metering for Solar, Farm Waste, Wind, Micro-Combined Heat and Power, Micro-Hydroelectric

printed heading

Net Metering for Solar, Farm Waste, Wind, Micro-Combined Heat and Power, Micro-Hydroelectric Generating Equipment, and Fuel Cell Electric Generating Systems - Standby service rates shall not apply to Customer-Generators who have the above electric generating equipment provided they have executed an…
Read this passage

H. Emergency Generators

printed heading

This log shall be made available to the Company upon request.
Read this passage

I. Customers served on SC-2D with a contract demand less than 50 kW may elect to remain on the SC-2D

printed heading

SERVICE CLASSIFICATION NO. 7 (Continued) APPLICATION FOR SERVICE: Standby Rate Service: Customers with on-site generation must apply for service by providing the Company with an executed Form G, Application For Electric Standby Service and interconnection agreement, both of which are available from…
Read this passage

A. Interval Metering: All Standby Service Customers and Optional Rate Customers shall utilize the

printed heading

Interval Metering: All Standby Service Customers and Optional Rate Customers shall utilize the Company's interval recording meter at the customer Premises.
Read this passage

B. Telecommunications: Remote meter reading capability is also required for all Standby Service Customers

printed heading

Telecommunications: Remote meter reading capability is also required for all Standby Service Customers and Optional Rate Service Customers.
Read this passage

C. Customer-Provided Equipment: Customers providing a telephone connection to the meter will bear all costs

printed heading

Customer-Provided Equipment: Customers providing a telephone connection to the meter will bear all costs associated with the installation, operation and maintenance of the telephone line including, but not limited to, all telephone service bills.
Read this passage

D. Company-Provided Equipment: Customers who choose the Company-provided meter reading

printed heading

Company-Provided Equipment: Customers who choose the Company-provided meter reading communication option shall pay a monthly Incremental Customer Communications Charge as set forth in a schedule provided by the Company.
Read this passage

E. Exceptions for Customers Smaller Than 50 kW: In addition, customers who would otherwise receive

printed heading

No. 2 Demand, who have Standby Contract Demands less than 50 kW will have the option of taking service at either (i) the otherwise applicable demand rate and shall not be subject to any additional metering and communication charges under S.C-7; or (ii) upon installation of required interval…
Read this passage

A. Contract Demands Larger than 1000 kW: All Standby Service Customers with Contract Demands

printed heading

Schedules must include starting and ending times for all planned outages.
Read this passage

B. SC-4 Customers: Customers who would otherwise receive service under the provisions of Service

printed heading

SC-4 Customers: Customers who would otherwise receive service under the provisions of Service Classification No. 4 shall have their demand measured on an integrated 30-minute basis, pursuant to the terms of that tariff.
Read this passage

C. Compliance with Reliability Criteria: Standby Service Customers agree to comply with any existing or

printed heading

Compliance with Reliability Criteria: Standby Service Customers agree to comply with any existing or future criteria, guidelines, and procedures established by the North American Electric Reliability Council (or its successor) to ensure the continued reliability of North America's interconnected…
Read this passage

D. Electrically Isolated Loads: In the event that any customer elects to Electrically Isolate (as defined in Rule

printed heading

Electrically Isolated Loads: In the event that any customer elects to Electrically Isolate (as defined in Rule 1.48) some or all of the facilities at the Customer's Location and to thereafter serve such facilities with electricity from on-site generation without connection to the Company's system,…
Read this passage

E. Penalties for Reconnecting Isolated Loads without Notice: Notwithstanding any other provision of this

printed heading

Penalties for Reconnecting Isolated Loads without Notice: Notwithstanding any other provision of this Tariff, in the event that the customer connects on-site generation to its electric system without: (1) notifying the Company; and (2) executing Form “G”, and in the event that the Company…
Read this passage

F. Reduced Customer Charge for Certain Wholesale Generators

printed heading

Reduced Customer Charge for Certain Wholesale Generators SC-7 customers who are Wholesale Generators who: (a) have a parent service classification of SC-3 or SC-3A and are served at the subtransmission or transmission voltage level and (b) have paid for all of their interconnection facilities as…
Read this passage

G. Billing for Customers With OSG’s Less Than or Equal to 15% of Maximum Potential Demand:

printed heading

Billing for Customers With OSG’s Less Than or Equal to 15% of Maximum Potential Demand: Standby Service Customers that install an OSG after December 31, 2011 with a total nameplate rating that is 15% or less of their maximum potential demand over the previous 12 months shall be subject to the…
Read this passage

H. Waiver of Reactive Demand Charges for Wholesale Generators Larger Than 25 MVA and With

printed heading · Topic match: Reliability and curtailment

Waiver of Reactive Demand Charges for Wholesale Generators Larger Than 25 MVA and With Automatic Voltage Control: For customers who operate a Wholesale Generator in larger than 25 MVA and install automatic voltage control (AVC) at their facilities, reactive demand charges shall be waived, within…
Read this passage

A. Reserved for Future Use

printed heading · Topic match: Reliability and curtailment

NYISO Incentivized Day-Ahead Economic Load Curtailment Program Rider (continued) f) Bidding by the DSR 1.) The DSR will submit its demand reduction bids to the DRP in accordance with the agreement. 2.) Bids must be submitted to the DRP by 11:00 a.m. two days ahead of the curtailment day, (e.g. by…
Read this passage