Horizon West Transmission - Response to Show Cause Order EL26-71-
Horizon West Transmission, LLC files tariff revisions under section 205 on November 16, 2026, in ER27-530-000, answering the CAISO show cause order. It adds large load procedures, a pro forma cost recovery agreement and an interim service, and asks to be dropped from the proceeding. The letter closely mirrors the GridLiance West and Trans Bay Cable filings, apart from company facts and minor wording.
Asks FERC to: Accept the revisions effective February 16, 2027, allow 30 days for comments, and terminate the show cause proceeding as to Horizon West.
Filed under section 205 to answer the E-10 show cause order. It follows CAISO's draft tariff language and sets an application process, a cost recovery agreement and an interim service for a non-load-serving owner.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)
Key points
- Horizon West owns a reactive power project and has others under development.
Horizon West currently owns and operates the 230 kV +300/100 MVAr Suncrest Reactive Power Project PDF p. 2
- It says parts of the show cause order do not apply to a non-load-serving owner.
Horizon West also explains how certain aspects of the Show Cause Order are not applicable to Horizon West due to its role as a Non-Load-Serving Entity PTO PDF p. 2
- It copies CAISO's 50 MW definition of large load.
This definition is identical to the definition CAISO proposes to add to Appendix A of the CAISO Tariff, and adopts the 50 MW threshold the Commission identified as reasonable PDF p. 5
- Because it serves no retail load, it offers unbundled retail transmission service so large loads can be studied under its tariff.
a voluntary offer of unbundled retail transmission service, where consistent with state law, so that Large Loads can request Interconnection and be studied under the Horizon West Tariff PDF p. 6
- Study deposits start at $35,000 plus $1,000 per MW, matching CAISO's generator process.
must provide a refundable study deposit of: (a) $35,000 plus $1,000 per MW PDF p. 7
- The interim service depends on the load's ability to reduce at a point of interconnection, under a three-party agreement.
FILI Service is available if the Large Load can reduce its load at a specified Point of Interconnection according to protocols in a FILI Service Agreement among the Large Load, Horizon West, and CAISO PDF p. 13
- The customer pays all actual network upgrade costs through a revenue commitment.
The Cost Recovery Agreement requires the Eligible Customer to pay 100% of the actual costs of the Large Load Network Upgrades through the Total Required Revenue Commitment PDF p. 14
- Horizon West reports no pending load requests that the new rules would affect.
Horizon West has not received any Load interconnection requests on its facilities that would be affected by the proposed revisions PDF p. 20
Text extracted from the eLibrary original (SHA-256 85d45a1e0ee32c6d…). Download the original from the official source.
Contents · 19 sections
- I. BACKGROUND
- A. Horizon West
- B. Show Cause Order
- C. Motion for Abeyance
- II. HORIZON WEST’S PROPOSED TRANSMISSION OWNER TARIFF
- A. Large Load Interconnection Process
- B. Co-Located Load
- C. Flexible Large Load Services
- D. Cost Shifting and Cost Recovery Agreements
- E. Pro Forma Transmission Service Agreements or Other Agreements
- F. Protection for Existing Commercial Arrangements
- G. Coordination with CAISO
- H. Ministerial and Conforming Revisions
- III. RESPONSES TO REMAINING ELEMENTS OF THE SHOW CAUSE ORDER
- IV. RESPONSES TO THE COMMISSION’S REMAINING BRIEFING QUESTIONS
- V. PROPOSED EFFECTIVE DATE AND WAIVER
- VI. CONTENTS OF THE FILING
- VII. CORRESPONDENCE AND SERVICE
- VIII. CONCLUSION
Topics in the text: Connecting load and generation · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Horizon West also explains how certain aspects of the Show Cause Order are not applicable to Horizon West due to its role as a Non-Load-Serving Entity PTO (“Non-LSE PTO”).6 Thus, Horizon West requests that the show cause proceeding be terminated with respect to Horizon West.Read this passage
I. BACKGROUND
printed heading
I.Read this passage
A. Horizon West
printed heading
Horizon West Horizon West is a Non-LSE PTO in the CAISO region.Read this passage
B. Show Cause Order
printed heading · Topic match: Connecting load and generation
Show Cause Order On June 18, 2026, the Commission initiated a show cause proceeding against CAISO and the PTOs pursuant to section 206 of the FPA.Read this passage
C. Motion for Abeyance
printed heading · Topic match: Filing procedure
See id. at P 3 n.14. 13 Id. at P 3. 4 (“Abeyance Motions”).14 The Commission granted the Abeyance Motions and held this proceeding in abeyance, in full, including responses to the Show Cause Order and briefing questions, for 90 days.15Read this passage
II. HORIZON WEST’S PROPOSED TRANSMISSION OWNER TARIFF
printed heading · Topic match: Cost allocation
The proposed revisions establish an application process, study procedures, operational requirements, and creditworthiness and financial security requirements applicable to requests by Eligible Customers seeking to interconnect a Large Load to the Horizon West transmission system.Read this passage
A. Large Load Interconnection Process
printed heading · Topic match: Cost allocation
Finally, Horizon West proposes requirements for installation and maintenance of the equipment required to disconnect or otherwise isolate the Large Load (Sections 8.1.5.1(vi) and 10.17), with those costs directly assigned to the applicant to avoid cost shifting to transmission customers (Section…Read this passage
B. Co-Located Load
printed heading · Topic match: Connecting load and generation
Recognizing CAISO’s predominant role in studying generator interconnections, Horizon West proposes the adoption of tariff provisions that tie into CAISO requirements including: • New Section 10.18.6 requires Horizon West to study co-located Large Loads in accordance with proposed CAISO Tariff…Read this passage
C. Flexible Large Load Services
printed heading · Topic match: Connecting load and generation
The process for application and receipt of these forms of interconnection service will include the following steps: Horizon West proposes to define FILI Service as aligned with CAISO’s proposed definition.51 Under new Section 10.18.2, FILI Service is available if the Large Load can reduce its load…Read this passage
D. Cost Shifting and Cost Recovery Agreements
printed heading · Topic match: Cost allocation
If the Eligible Customer does not provide sufficient service revenue attributable to the Large Load to Horizon West through CAISO’s Access Charges to cover the Eligible Customer’s Annual Required Revenue Commitment, the Eligible Customer must provide Cost Recovery Payments to fill the gap in cost…Read this passage
E. Pro Forma Transmission Service Agreements or Other Agreements
printed heading
Horizon West also has yet to process any Large Load interconnection requests which could further inform the needs of a pro forma Interconnection Agreement.Read this passage
F. Protection for Existing Commercial Arrangements
printed heading
Protection for Existing Commercial Arrangements Commission Concern: The Show Cause Order directed respondents to provide a reasoned explanation for how their proposal will avoid disrupting any existing commercial arrangements and provide a reasonable implementation period, including time to…Read this passage
G. Coordination with CAISO
printed heading
This ensures no Large Load is energized until the information and equipment necessary to preserve reliability and to operate consistent with CAISO requirements is in place; and • The Large Load meet all frequency ride-through requirements, voltage ride through requirements, post-fault active power…Read this passage
H. Ministerial and Conforming Revisions
printed heading
Ministerial and Conforming Revisions Horizon West has also made several ministerial or conforming revisions to either clarify or correct its tariff language or to better clarify the Horizon West Tariff’s relation to the CAISO Tariff.Read this passage
III. RESPONSES TO REMAINING ELEMENTS OF THE SHOW CAUSE ORDER
printed heading · Topic match: Connecting load and generation
As 67 Show Cause Order at P 34. 68 Id. at PP 66, 70-75. 69 Id. at PP 93-102 (covering rate design, ancillary services, transmission service, behind-the-meter netting, and interconnection via generator processes). 70 Id. at PP 104 & n.222, 120-22. 19 such, Horizon West proposes no tariff revisions…Read this passage
IV. RESPONSES TO THE COMMISSION’S REMAINING BRIEFING QUESTIONS
printed heading · Topic match: Connecting load and generation
Horizon West requests an effective date of February 16, 2027, which aligns with the effective date CAISO is requesting for its tariff revisions, gives Horizon West time to implement the revised procedures and update its business practices, and gives Eligible Customers and Large Loads reasonable…Read this passage
V. PROPOSED EFFECTIVE DATE AND WAIVER
printed heading
For these reasons, Horizon West respectfully requests that the Commission find that the proposed effective date is just and reasonable and complies with the Commission’s directive regarding implementation timing.Read this passage
VI. CONTENTS OF THE FILING
printed heading
CONTENTS OF THE FILING In addition to this transmittal letter, this filing contains the following components: Appendix A: Clean Version of the Revised Sections of the Horizon West Tariff; Appendix B: Redlined Version of the Revised Sections of the Horizon West Tariff; and Appendix C: Pro Forma Cost…Read this passage
VII. CORRESPONDENCE AND SERVICE
printed heading
CORRESPONDENCE AND SERVICE The following persons are authorized to receive notices and service with respect to this filing:79 77 CAISO Proposed Tariff § 25.7. 78 Show Cause Order at P 5. 79 To the extent necessary, Horizon West respectfully requests a waiver of Rule 203(b)(3) of the Commission’s…Read this passage
VIII. CONCLUSION
printed heading
CONCLUSION For the reasons set forth above, Horizon West respectfully requests that the Commission accept the proposed revisions to the Horizon West Tariff, effective February 16, 2027.Read this passage