GridLiance West - Response to Show Cause Order EL26-71
PDF page 1
2000 Pennsylvania Avenue NW
Suite 6000
Washington, DC 20006
202-298-1800
Meghan O’Brien
202-298-1800
mobrien@vnf.com
November 16, 2026
VIA E-TARIFF FILING
Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
Re:
GridLiance West LLC
Docket Nos. ER27-___-000 and EL26-71-000
Response to Show Cause Order
Dear Secretary Reese:
Pursuant to section 205 of the Federal Power Act (“FPA”),1 Part 35 of the Federal Energy Regulatory Commission’s (the “Commission”) regulations and Rules 209 and 213 of the Commission’s Rules of Practice and Procedure,2 GridLiance West LLC (“GridLiance West”) respectfully submits this response to the Commission’s Show Cause Order issued pursuant to section 206 of the FPA on June 18, 2026, in Docket No. EL26-71-000 directing the California Independent System Operator Corporation (“CAISO”) and Participating Transmission Owners (“PTOs”) in CAISO to show cause why their tariffs are just and reasonable and not unduly discriminatory or preferential, or in the alternative to explain the necessary changes to remedy the Commission’s identified concerns.3 In the Show Cause Order, the Commission also encouraged a response in the form of a section 205 filing proposing tariff revisions remedying the concerns identified in the Show Cause Order.4
In the instant filing, GridLiance West proposes revisions to its Transmission Owner Tariff (“GridLiance West Tariff”)5 and supporting explanations in response to the Show Cause Order to remedy the concerns identified therein. GridLiance West’s proposed tariff revisions are just and
1 16 U.S.C. § 824d.2 18 C.F.R. §§ 385.209, 385.213(a).3 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214, at P 3 (2026) (“Show Cause Order”).4 Id. at P 34.5 The GridLiance West Tariff has been accepted by the Commission. GridLiance W. Transco, LLC, 158 FERC ¶ 62,136 (2017); GridLiance W. LLC, 167 FERC ¶ 61,130 (2019); GridLiance W. Transco, LLC, Docket No. ER17- 706-005 (Sep. 18, 2018) (delegated letter order); GridLiance W. LLC, Docket Nos. ER18-2206-000 and -001 (Sep. 18, 2018) (delegated letter order); GridLiance W. LLC, Docket No. ER19-191-000 (Dec. 11, 2018) (delegated letter order).
PDF page 2
2
reasonable and not unduly discriminatory or preferential, and resolve the Commission’s applicable preliminary findings in the Show Cause Order. GridLiance West also explains how certain aspects of the Show Cause Order are not applicable to GridLiance West due to its role as a Non-Load-Serving Entity PTO (“Non-LSE PTO”).6 Thus, GridLiance West requests that the show cause proceeding be terminated with respect to GridLiance West.
Further, GridLiance West respectfully requests a 30-day comment period on this filing. GridLiance West also respectfully requests that the Commission accept the amendments proposed herein effective February 16, 2027. The requested dates align with those requested by CAISO.
I. BACKGROUND
A. GridLiance West
GridLiance West operates transmission facilities within CAISO. GridLiance West is a Delaware limited liability company and a wholly owned subsidiary of NextEra Energy Transmission, LLC. GridLiance West owns and operates the High Voltage Transmission System (“HVTS”) previously owned by Valley Electric Transmission Association, LLC, a wholly owned subsidiary of Valley Electric Association, Inc. The HVTS consists of approximately 165 miles of 230-kV transmission lines and related substation infrastructure that runs through rural Southern Nevada. The HVTS has been incorporated into the CAISO-controlled grid, and GridLiance West is a Non-LSE PTO in CAISO.
GridLiance West recovers its transmission revenue requirement (“TRR”) through a Commission-approved formula rate under the GridLiance West Tariff, which is invoiced and collected through the CAISO Access Charge rates under Section 26 of the CAISO Open Access Transmission Tariff (“CAISO Tariff”). As a Non-LSE PTO under the CAISO Tariff and Transmission Control Agreement,7 GridLiance West serves no retail load.8
B. Show Cause Order
On June 18, 2026, the Commission initiated a show cause proceeding against CAISO and the PTOs pursuant to section 206 of the FPA. The Show Cause Order directed CAISO and the PTOs to explain why the CAISO Tariff and the Transmission Owner Tariffs of the PTOs (“PTO Tariffs”) remain just and reasonable and not unduly discriminatory or preferential without certain tariff provisions addressing:96 CAISO Tariff, App. A (defining Non-Load-Serving Participating TO).7 CAISO Rate Schedules, Amended and Restated Transmission Control Agreement.8 GridLiance West Tariff § 1 (stating that GridLiance West is a Non-LSE PTO and does not provide retail electric service to End-Use Customers); id. § 3.66 (definition of “Non-Load-Serving Participating TO”); see also CAISO Tariff, App. A (Non-LSE PTO).9 Show Cause Order at P 31.
PDF page 3
3
a) the application process, study procedures, and ongoing operational requirements that apply to Eligible Customers10 seeking transmission service on behalf of Large Loads;
b) additional transparency concerning the network upgrade11 costs to provide transmission service to Eligible Customers on behalf of Large Loads; and a pro forma cost recovery agreement between CAISO, the relevant transmission owner, and the Eligible Customer taking transmission service on behalf of the Large Load to mitigate the risk of cost shifting among transmission customers, and a mechanism to ensure such payments are appropriately credited toward transmission owners’ TRRs consistent with the
Commission’s cost-of-service regulations;
c) the rates, terms, and conditions of service that apply to co-location arrangements;
d) transmission services that reflect Eligible Customers taking transmission service on behalf of co-located loads, load with behind the meter generation, and flexible Large Loads that are willing and able to limit their use of the transmission system under certain conditions;12 and
e) the rates, terms, and conditions of service applicable to interconnection customers serving electrically proximate Large Load or co-located load.
Alternatively, respondents may explain what changes to their tariffs would remedy the identified concerns if the Commission were to determine that the tariffs have in fact become unjust and unreasonable or unduly discriminatory or preferential and proceeds to establish a replacement tariff.13
C. Motion for Abeyance
On August 3, 2026, pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure, CAISO and the joint PTOs, which included GridLiance West, each filed motions to hold the above-referenced show cause proceeding in abeyance for 90 days, pending completion of CAISO’s stakeholder proceedings and development of the companies’ respective FPA section 205 filings to address the Commission’s preliminary findings in the Show Cause Order
10 GridLiance West Tariff § 3.20 (definition of “Eligible Customer”).11 The Show Cause Order uses the term network upgrades throughout the order to refer to modifications or additions to transmission-related facilities that are integrated with and support the overall transmission system. See Show Cause Order at P 3 n.13 (citing pro forma OATT § 1.27 (Definitions – Network Upgrades)). CAISO’s current definition of Network Upgrades applies only to additions, modifications, and upgrades required to accommodate the Interconnection of generating facilities. Id. (citing CAISO Tariff, App. A (Definitions), Network Upgrades (0.0.0)).12 For purposes of the Show Cause Order, “flexible” Large Loads are a subset of Large Loads that are not co- located with generation but are willing and able to limit their energy withdrawals from the transmission system under certain conditions. See id. at P 3 n.14.13 Id. at P 3.
PDF page 4
4
(“Abeyance Motions”).14 The Commission granted the Abeyance Motions and held this proceeding in abeyance, in full, including responses to the Show Cause Order and briefing questions, for 90 days.15
II. GRIDLIANCE WEST’S PROPOSED TRANSMISSION OWNER TARIFF
REVISIONS
The proposed GridLiance West Tariff revisions are just and reasonable and not unduly discriminatory or preferential. The proposed revisions establish an application process, study procedures, operational requirements, and creditworthiness and financial security requirements applicable to requests by Eligible Customers seeking to interconnect a Large Load to the GridLiance West transmission system. The revisions are designed to consistently evaluate the reliability, operational, and planning impacts of proposed Large Loads, identify and allocate responsibility for any Direct Assignment Facilities, Reliability Upgrades, and other Network Upgrades, and mitigate the risk of cost shifting associated with the Interconnection and service of Large Loads. The proposed revisions provide transparency and certainty regarding the information, studies, agreements, and credit and financial security commitments required from Eligible Customers seeking transmission service on behalf of Large Loads.16 The proposed amendments to the GridLiance West Tariff fall into the following categories:
(1) New and revised defined terms in Section 3 of its GridLiance West Tariff, including definitions of Large Load, Flexible Interim Load Interconnection
(“FILI”) Service, Interconnection Facilities, Point of Interconnection, Network Upgrades, Site Control, Gross Load, Transmission Revenue Requirement, and
Reliability Upgrade;
(2) Revisions to Section 5 of its GridLiance West Tariff to clarify Gross Load reporting associated with Large Load, consistent with the CAISO Tariff;
(3) Revisions to Sections 8.1 and 10.1 through 10.17 of its GridLiance West Tariff to establish an interconnection application process, readiness requirements, and study procedures specific to Large Load interconnections;
(4) Revisions to Sections 8.1.5.1, 10.12, 10.17, and 16.12 of its GridLiance West Tariff to establish operational and reliability requirements for Large Loads;
(5) Additions to Section 10.18 of the GridLiance West Tariff to establish rates, terms, and conditions of service applicable to co-located Large Load and FILI Service;
14 Cal. Indep. Sys. Operator Corp., Motion for Abeyance of the California Independent System Operator Corporation, Docket No. EL26-71-000 (Aug. 3, 2026); Cal. Indep. Sys. Operator Corp., Request for Abeyance of Southern California Edison Company et al., Docket No. EL26-71-000 (Aug. 3, 2026).15 Cal. Indep. Sys. Operator Corp., 196 FERC ¶ 61,131, at P 13 (2026).16 GridLiance West developed the proposed revisions herein in a good-faith effort to align with CAISO’s proposed tariff revisions, and to the extent practicable given the parallel development of the PTOs’ filings and GridLiance West’s status as a Non-LSE PTO, with the approaches of the other CAISO PTOs.
PDF page 5
5
(6) Inclusion of cost recovery, creditworthiness, and financial security provisions in Sections 10.11.2, 10.17.2, and 13.2.1, and including a pro forma Cost Recovery Agreement as a new Attachment A to the GridLiance West Tariff for the purpose of protecting against cost shifting and increasing transparency as to the Network Upgrade costs for Large Load interconnection; and
(7) Adoption of transition provisions in Section 10.20 to protect existing and ongoing commercial arrangements for Large Loads that are operational or have a
Completed Interconnection Application before February 16, 2027.
GridLiance West’s proposed revisions are tailored to its status as a Non-LSE PTO, are coordinated with and consistent with proposed CAISO Tariff revisions and satisfy the Show Cause Order requirements applicable to a Non-LSE PTO. GridLiance West has also incorporated certain conforming and ministerial revisions, such as correcting punctuation and applying consistent usage of terms. Accordingly, GridLiance West respectfully submits that the proposed tariff revisions are just and reasonable, not unduly discriminatory or preferential, and should be accepted by the Commission under section 205 of the FPA, effective as requested. GridLiance West further requests that the Commission terminate the show cause proceeding with respect to GridLiance West upon acceptance of the proposed tariff revisions.
A. Large Load Interconnection Process
In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack clear and consistent provisions with respect to the application and study process for Eligible Customers seeking transmission and interconnection service on behalf of Large Loads.17 The GridLiance West Tariff establishes, in Sections 8.1 and 10, a defined and time-limited interconnection process for Large Loads with specific application, readiness, study, and operational requirements, and it clarifies how a Large Load interconnected to GridLiance West’s facilities obtains transmission service over the CAISO Controlled Grid. Elements of this proposal include the following tariff improvements for the integration of Large Loads.
1. Definition of Large Load
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack a definition of Large Load sufficient to capture loads that present the unique challenges described in the Show Cause Order.18
GridLiance West Solution: In response to the Commission’s finding, GridLiance West proposes to define a Large Load as “[a]n End-User located at a single site behind one or more Points of Interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or
17 Show Cause Order at PP 38, 49, 58. Citations herein to the “GridLiance West Tariff” refer to the revised GridLiance West TO Tariff included as Appendices A and B to this filing. Citations to the “CAISO Proposed Tariff” refer to the tariff revisions CAISO is submitting contemporaneously in response to the Show Cause Order.18 Show Cause Order at PP 56, 57.
PDF page 6
6
greater.”19 This definition is identical to the definition CAISO proposes to add to Appendix A of the CAISO Tariff, and adopts the 50 MW threshold the Commission identified as reasonable.20 GridLiance West has also adopted CAISO’s approach of not excluding co-located loads from the definition of Large Load to ensure alignment between the two tariffs.
2. Application and Study Procedures
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack clear and consistent provisions addressing the application process and study procedures for Eligible Customers to request transmission service on behalf of Large Loads.21 The Commission indicated that such processes should clarify that applications be accepted on a rolling basis; require a non-refundable application fee as well as staged readiness requirements; and specify the information and data requirements to be submitted with an application.22 GridLiance West Solution: The proposed tariff revisions leverage GridLiance West’s existing application and study processes while identifying the additional procedures applicable to Large Loads due to their unique operational requirements and reliability impacts on the transmission system. GridLiance West submits that this approach promotes transparency and administrative efficiency by providing a single, integrated framework for Large Load interconnection requests under the GridLiance West Tariff. This is responsive to the Show Cause Order’s concern regarding the lack of specificity for Large Loads and their unique operational characteristics and requirements.
GridLiance West’s proposed tariff revisions establish the applicable provisions for Eligible Customers requesting service on behalf of Large Loads (as defined in the GridLiance West Tariff). First, revised Section 8.1 explicitly extends GridLiance West’s obligation to interconnect to entities eligible to request interconnection pursuant to FPA section 210(a) and Eligible Customers, including Large Loads owned or served by a third party. Because GridLiance West is a Non-LSE PTO with no retail customers, a Large Load connecting directly to GridLiance West’s facilities may not qualify as an “Eligible Customer” in certain instances. GridLiance West therefore proposes, in new Section 10.2, a voluntary offer of unbundled retail transmission service, where consistent with state law, so that Large Loads can request Interconnection and be studied under the GridLiance West Tariff as the Show Cause Order contemplates.23 Second, revised Section 10.1 requires that a Large Load Interconnection be requested pursuant to Section 10 of the GridLiance West Tariff and comply with Section 25.7 of
19 GridLiance West Tariff § 3.52 (definition of “Large Load”).20 CAISO Proposed Tariff, App. A (definition of “Large Load”); Show Cause Order at P 57.21 Show Cause Order at PP 56, 58.22 Id. at P 58.23 Id. at P 38 & n.117; see also id. at P 43 & n.123. See GridLiance West Tariff § 3.20 (definition of “Eligible Customer”), id. § 10.2. The offer covers only Interconnection and associated access to the CAISO Controlled Grid consistent with the CAISO Tariff. It does not include the sale of Energy, distribution service, or scheduling or settlement in the CAISO Markets, and it is available on a non-discriminatory basis to all End-Use Customers on GridLiance West’s facilities, not only Large Loads.
PDF page 7
7
the CAISO Tariff.24 GridLiance West affirms that under the GridLiance West Tariff, applications are accepted on a rolling basis, and revised Section 10.4 requires GridLiance West to timestamp each Large Load Interconnection Application to establish study priority on a rolling basis. Consistent with the Commission’s concern that the tariffs specify which entity is responsible for the study, GridLiance West is proposing revisions to Sections 10.1 and 10.4 to clarify that the Eligible Customer is the entity that requests Interconnection on behalf of a Large Load.25 GridLiance West, as the interconnecting PTO, will perform the System Impact Study and Facilities Study for the Eligible Customer taking transmission service on behalf of a Large Load pursuant to Section 10.26 As part of its study obligations, GridLiance West will apprise CAISO of Large Load interconnections through its inputs to the Base Case, Interconnection Studies, and the Transmission Planning Process.27 Prior to energization of any Large Load, GridLiance West must provide CAISO the information required by Section 25.7.1 of the CAISO Tariff, and the Eligible Customer must provide that information to GridLiance West and notify GridLiance West of any material changes within 10 Business Days.28
Furthermore, GridLiance West proposes new Section 10.5.1 to clarify additional application requirements for Large Load interconnections. Specifically, an Eligible Customer seeking to interconnect a Large Load must submit: (i) the Large Load’s ramp schedule, identifying load additions over time and maximum planned load; (ii) a site plan; (iii) documentation of the local, state, and federal permits and regulatory approvals necessary to develop the Large Load; (iv) documentation demonstrating Site Control; (v) a single-line electrical diagram; (vi) information on any other Interconnection requests made on behalf of the same Large Load or its affiliates; (vii) whether the Large Load intends to request Partial Interim Service or FILI Service; and (viii) for a Large Load co-located with a Generating Facility, information sufficient for GridLiance West to ensure compliance with Sections 25.1.1, 25.7.5, and 25.7.6 of the CAISO Tariff. Because Section 10.4 requires every Interconnection Application to be copied to CAISO, Section 10.5.1(vi) requires disclosure of other pending requests on behalf of the same Large Load to CAISO, as the Commission contemplated.29 GridLiance West and CAISO, as applicable, must determine whether an application is complete within ten (10) Business Days under Section 10.6.
An applicant must pay a $5,000 nonrefundable Large Load Interconnection Application fee.30 At the time of application, they must provide site plans, demonstration of Site Control
24 GridLiance West Tariff §§ 8.1, 10.1; CAISO Proposed Tariff § 25.7 (providing that “End Users, including Large Loads, interconnect to the CAISO Controlled Grid pursuant to PTO and retail tariffs”).25 GridLiance West notes that there are circumstances in which the Large Load could itself be the Eligible Customer, in which case the Large Load would be requesting interconnection on its own behalf. 26 GridLiance West Tariff §§ 10.12, 10.16; Show Cause Order at PP 38 & n.117, 39 & n.118, 51.27 GridLiance West Tariff § 10.3.28 Id. §§ 8.1.5(v), 10.3.29 Show Cause Order at P 58.30 GridLiance West Tariff § 10.5; see also CAISO Tariff, App. KK § 3.5.1.1 (Interconnection Study Deposit).
PDF page 8
8
(which is newly defined to ensure control of the site), and receipt of necessary permits.31 These requirements will ensure that interconnection applications are real, concrete, and nonspeculative. Furthermore, GridLiance West proposes that, at the Large Load System Impact Study phase, the Eligible Customer must provide a refundable study deposit of: (a) $35,000 plus $1,000 per MW for Interconnection Applications less than 80 MW; (b) $150,000 for Interconnection Applications greater than or equal to 80 MW but less than 200 MW; or (c) $250,000 for Interconnection Applications greater than 200 MW.32 The refundable study deposit amounts are consistent with those required in CAISO’s generator interconnection process. At the Facilities Study phase, the Eligible Customer must pay the estimated cost of the Facilities Study, and, before energization, amongst other requirements, it must execute the Interconnection Agreement and pro forma Cost Recovery Agreement, and post all required financial security (Sections 10.17.2, 8.1.5.1(viii), and 13.2.1). These readiness requirements thus escalate at distinct phases throughout the study process, consistent with the Show Cause Order directives.33 An applicant that withdraws from the process at any phase must reimburse GridLiance West for all costs reasonably incurred and may be responsible for the cost of restudying later-queued applicants.
For a Large Load Interconnection, the System Impact Study must evaluate the Large Load’s operational characteristics, including its ramp schedule, its performance during system disturbances, and any ability to limit its withdrawals from the CAISO Controlled Grid, consistent with Section 25.7.1 of the CAISO Tariff. The PTO will evaluate impacts to the transmission system using power flow and short circuit analyses, and any other analyses that may be appropriate including Electromagnetic Transient studies where warranted. The completed System Impact Study will include a non-binding, good-faith estimate of the cost of Direct Assignment Facilities and Network Upgrades needed to accommodate the request and the time required to construct them, which the Facilities Study then refines. GridLiance West may request additional information, data, or models reasonably needed for the study, including models suitable for Electromagnetic Transient studies. The request then proceeds through GridLiance West’s existing Facilities Study procedures, which refine the facilities design and the cost and schedule estimates for incorporation into the Interconnection Agreement.
3. Operational and Reliability Requirements
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack appropriate provisions regarding the ongoing operational requirements that will apply to transmission customers serving Large Loads.34 The Commission further highlighted the lack of detail on data available to CAISO regarding interconnected Large Loads for monitoring and reliability purposes, the lack of language enabling CAISO to remotely disconnect Large Loads
31 A site subject to a development moratorium or other governmental restriction that prohibits the proposed use does not satisfy the Site Control requirement unless the restriction has been lifted or the applicant has obtained all necessary approvals, exemptions, or variances.32 GridLiance West Tariff § 10.11.2; see also CAISO Tariff, App. KK § 3.5.1.1.33 Show Cause Order at PP 55, 58.34 Id. at PP 56, 59, 63.
PDF page 9
9
via installed equipment, the absence of specified ramp rate, ride-through, and control technologies or protection systems required.35
GridLiance West Solution: It is GridLiance West’s understanding that CAISO is proposing changes to Section 25.7.1 of the CAISO Tariff to provide substantial additional clarity regarding ongoing operational requirements for Eligible Customers serving Large Loads, including Frequency Ride-Through, Voltage Ride-Through, Post-Fault Active Power Recovery, and Ramp-Rate Limitation requirements. Accordingly, GridLiance West’s proposed Section 10.17 specifies that any Large Load Interconnection Agreement will require compliance with Section 25.7.1 of the CAISO Tariff, and proposed Section 10.3 requires GridLiance West to provide the information required by Section 25.7.1 to CAISO prior to energization of the Large Load. This approach will ensure that Large Load operational requirements remain current with CAISO standards and provide transparency and regularity of operational standards that will support reliable operation of the overall grid.
GridLiance West also proposes a series of additional operational requirements mirroring CAISO Tariff measures, specifically:
Following proposed CAISO Tariff Section 25.7.4 by requiring the Eligible Customer, Large Load, Scheduling Coordinator, and GridLiance West to comply with any CAISO, Regional Entity, or Reliability Coordinator data request after a disturbance or other reliability event involving a Large Load (Section 16.12); Ensuring visibility into Large Load operations by extending proposed CAISO Tariff Section 25.7.3 requirements for the Scheduling Coordinator for each Large Load to provide daily and hourly forecasts, material real-time deviations, outage information, and real-time telemetry (Sections 8.1.5.1(iii) and 10.17); and Following proposed CAISO Tariff Sections 25.7.1.1, 25.7.1.2, 25.7.1.3, and 25.7.1.4, by requiring Large Load to meet all frequency ride-through
requirements, voltage ride through requirements, post-fault active power recovery requirements, and ramp rate limitations established therein (Section 8.1.5.1(x)). Finally, GridLiance West proposes requirements for installation and maintenance of the equipment required to disconnect or otherwise isolate the Large Load (Sections 8.1.5.1(vi) and 10.17), with those costs directly assigned to the applicant to avoid cost shifting to transmission customers (Section 8.1.2).
4. Alternative Transmission Technologies
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack clear and consistent provisions requiring the evaluation of alternative transmission technologies as potential solutions to an Eligible Customer’s request for service on behalf of a
35 Id. at P 63.
PDF page 10
10
Large Load,36 or requiring an explanation to the Eligible Customer why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline accommodating the request.37
GridLiance West Solution: The proposed revisions to Section 10.12.1 commit
GridLiance West to considering alternative transmission technologies in the System Impact Study for every Large Load Interconnection Application, without the need for a request from the Eligible Customer. If GridLiance West selects traditional Network Upgrades instead, it must demonstrate why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline for accommodating the request.38 This provision is consistent with the proposed revision to CAISO Tariff Section 24.1, which extends CAISO’s consideration of alternative transmission technologies to Large Loads and contemplates the inclusion of similar language in the PTO Tariffs.
5. Study Process Timeline
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the study processes could culminate in a report to the Eligible Customer describing the Network Upgrades necessary to accommodate the service request as well as a non-binding good-faith estimate of the cost and the time to construct such facilities, which should take no more than 60-90 days calendar days to complete.39
GridLiance West Solution: GridLiance West proposes the adoption of revised Section 10.12 and 10.12.1 to its tariff requiring that a System Impact Study for a Large Load provide a non-binding, good-faith estimate of the cost of Direct Assignment Facilities and Network Upgrades needed to accommodate the request and a similar good-faith time estimate required to construct them. Following the System Impact Study, pursuant to Section 10.16 the Facilities Study will refine those estimates leading into the Interconnection Agreement process.40 The report will be available following the System Impact Study, consistent with the Show Cause Order directive.
GridLiance West also recognizes the need for timely progression of required studies. Accordingly, the proposed GridLiance West Tariff revisions shorten the timeline for interconnection studies at each step of the process to the maximum extent achievable (Sections 10.8 - 10.12). Under the proposed Large Load study procedures, GridLiance West must notify the applicant whether a System Impact Study is required within ten (10) Business Days of the Completed Application Date and must tender a System Impact Study Agreement within ten (10) Business Days of receipt of the Completed Interconnection Application. The applicant must execute that agreement within ten (10) Business Days and, for a Large Load Interconnection, remit a study deposit together with financial security drawable to cover System Impact Study
36 Id. at P 60.37 Id. at P 61.38 GridLiance West Tariff § 10.12.1.39 Show Cause Order at P 62.40 GridLiance West Tariff § 10.16.
PDF page 11
11
costs and, if necessary, Facilities Study costs. GridLiance West must complete the System Impact Study no later than ninety (90) Calendar Days after the Completed Application Date. This 90-day timeline runs from the Completed Application Date, not from execution of the System Impact Study Agreement, and therefore includes the time for the System Impact Study Agreement and deposit steps. The result of this proposed schedule is the initiation and completion of a System Impact Study within the 60-90 calendar day range that the Commission identified as reasonable.
This proposed structure is consistent with the study process the Commission accepted for Southwest Power Pool, Inc.’s (“SPP”) High Impact Large Loads (“HILL”). For that process, SPP must complete its HILL Delivery Point Study and issue a study report within 90 calendar days after receiving the executed study agreement, study data, and deposit.41 That study uses power flow and short circuit analyses; SPP then performs an Electromagnetic Transient study only when those analyses identify system weaknesses caused by the Large Load, similar to GridLiance West’s Large Load System Impact Study process.42 The HILL Delivery Point Study works “in conjunction with” SPP’s existing load connection study requirements.43 It is followed, as needed, by a supplemental load connection study performed by the host transmission owner and by SPP’s existing processes for obtaining long-term transmission service. SPP’s tariff does not subject those later steps to the 90-day deadline,44 but the Commission found this process just and reasonable.45 GridLiance West’s approach follows the same structure. A time-certain System Impact Study culminates in a report within 90 days, and that report gives the Eligible Customer the information the Show Cause Order requires.
B. Co-Located Load
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff appears to be unjust and unreasonable because it lacks sufficiently clear and consistent tariff provisions addressing the rates, terms, and conditions that apply to co- location arrangements.46
GridLiance West Solution: As acknowledged by the Commission in its Show Cause Order and further addressed in Part III below, GridLiance West has a limited role in addressing co-location of generation with Large Load. The interconnection of wholesale generation to the CAISO Controlled Grid is governed by the CAISO Tariff, including the Resource Interconnection Standards in Appendix KK. GridLiance West’s role is to process and study the Interconnection of a Large Load and to coordinate with CAISO so that the generating facility and
41 See Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 15 (2026).42 Id.43 Id. at P 62.44 Id. at P 16.45 Id. at P 62.46 Show Cause Order at PP 85, 93-102.
PDF page 12
12
the Large Load are studied, interconnected, and operated together. As revised, the GridLiance West Tariff and CAISO Tariff jointly allocate those responsibilities.
Recognizing CAISO’s predominant role in studying generator interconnections, GridLiance West proposes the adoption of tariff provisions that tie into CAISO requirements including:
New Section 10.18.6 requires GridLiance West to study co-located Large Loads in accordance with proposed CAISO Tariff Section 25.7.6 and requires specific information regarding the net injection or net withdrawal of the combined co- located arrangement.47
Proposed Section 10.5.1(viii) requires the Large Load Interconnection Application to include information about the co-located Generating Facility sufficient to ensure compliance with Sections 25.1.1, 25.7.5, and 25.7.6 of the CAISO Tariff. Alignment of GridLiance West procedures to ensure the planned coordination envisioned in the proposed CAISO Tariff Section 25.7.6 by which CAISO will
conduct Interconnection Studies in coordination with the PTO that account for the net impact of the co-located configuration on the CAISO Controlled Grid, with memorialization of the combined co-located operation in the Generator
Interconnection Agreement. GridLiance West respectfully defers to CAISO on its description of the generator interconnection revisions and processes.
However, GridLiance West notes that proposed new Section 10.18.6 of the GridLiance West Tariff provides that the Interconnection processes applicable to a co-located Large Load are otherwise the same as those applicable to any other Large Load, and are, therefore, subject to the same readiness requirements, study timelines, ride-through and ramp-rate requirements, energization conditions, and cost recovery obligations as a Large Load. This treatment avoids undue discrimination between the two configurations while accounting for the technical characteristics unique to co-location.
Additionally, in Section 10.18.6, GridLiance West provides a path for adhering to CAISO’s proposed revised CAISO Tariff Section 25.1.1 such that a Generating Unit that will not inject Energy onto the CAISO Controlled Grid and will instead serve a co-located End User as permitted by the Local Regulatory Authority is not required to submit an Interconnection Request pursuant to CAISO’s Appendix KK. Section 10.18.6 also requires that, under such arrangements, the Generating Unit has sufficient control technologies to ensure the co-located arrangement has no material impact on the CAISO Controlled Grid.48 Proposed new Section 8.1.5.1(ix) further provides that GridLiance West is not obligated to energize a co-located Large Load until necessary control and system protection technologies have been installed, tested, and validated; it also requires the Large Load to be metered separately from its co-located generation.
47 GridLiance West Tariff §§ 10.5.1(viii), 10.18.6; CAISO Proposed Tariff § 25.7.6; CAISO Proposed Tariff, App. KK § 2.4.4.48 CAISO Proposed Tariff § 25.1.1.
PDF page 13
13
C. Flexible Large Load Services
Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack a study process for evaluating the ability of Large Loads to flexibly reduce demand and the information required to study providing flexible service while maintaining reliability.49 The Commission also noted that the CAISO Tariff allows an interconnection customer to request a limited operation study for a generating unit before its Interconnection Facilities or Network Upgrades are complete, but it offers no comparable interim option for load.50 GridLiance West Solution: GridLiance West defers to CAISO regarding transmission service offerings such as the non-firm or flexible services discussed in the Show Cause Order.
With respect to interconnection service, GridLiance West proposes two interim services that allow a Large Load to begin taking interconnection service before all of its upgrades are in place that reflects the Large Load’s ability to reduce load: the existing Partial Interim Service and FILI Service. Both services will be available to Eligible Customers serving Large Load. The process for application and receipt of these forms of interconnection service will include the following steps:
GridLiance West proposes to define FILI Service as aligned with CAISO’s proposed definition.51 Under new Section 10.18.2, FILI Service is available if the Large Load can reduce its load at a specified Point of Interconnection according to protocols in a FILI Service Agreement among the Large Load, GridLiance West, and CAISO. The FILI Service Agreement specifies the Network Upgrades or Interconnection Facilities needed to conclude FILI Service and provide full Interconnection service.52 To align with CAISO’s revised Tariff, Section 10.18.3 requires the agreement to identify required Interconnection Facilities, protection and control systems, equipment, and operating limitations that apply, and FILI Service may not commence until all such equipment is installed and commissioned.
The Eligible Customer must state in its Interconnection Application whether it intends to request Partial Interim Service or FILI Service. Under the new Section 10.18, GridLiance West will then perform an analysis and report the extent to which each requested interim service can be provided consistent with the GridLiance West Tariff and proposed Section 25.7.2 of the CAISO Tariff establishing FILI Service.53 The maximum amount of interim service is based on the anticipated availability of capacity and the information the Eligible Customer submits, and GridLiance West will update the analysis annually. In addition, Section 10.12.1 requires the
49 Show Cause Order at PP 59, 104-05.50 Id. at P 27.51 GridLiance West Tariff § 3.31 (definition of “Flexible Interim Load Interconnection (‘FILI’) Service”); CAISO Proposed Tariff, App. A; CAISO Proposed Tariff § 25.7.2. FILI Service is defined as “[c]urtailable, interim interconnection service for a Large Load provided by the CAISO and Participating TO, enabling the Large Load to interconnect prior to the completion of the Large Load’s Network Upgrades or Interconnection Facilities.”52 CAISO will post the FILI Service Agreement on its website. See CAISO Proposed Tariff § 25.7.2.53 GridLiance West Tariff §§ 10.18, 8.1.5.1(vii).
PDF page 14
14
Large Load System Impact Study procedures to evaluate any ability of the Large Load to limit its withdrawals from the CAISO Controlled Grid so that the study process itself recognizes the operational characteristics of flexible Large Loads.
New Section 10.18.4 requires the FILI Service Agreement to specify the circumstances, contingencies, and operating conditions under which the Large Load may be curtailed; the curtailment mechanism; the entity responsible for performing the curtailment; and the notification method, required response times, permissible duration, restoration timeline, testing and verification requirements, and interim operating limits. Further, new Section 10.18.5 permits CAISO or GridLiance West to terminate FILI Service and disconnect the Large Load if it does not adhere to the FILI Service Agreement, consistent with Good Utility Practice. Further, Section 10.17 requires the Large Load Interconnection Agreement to contain provisions requiring the installation and maintenance of any equipment or facilities necessary for the PTO to ensure its ability to disconnect or otherwise isolate the Large Load as required by Section 25.7.1 of the CAISO Tariff. Section 8.1.5.1(vii) makes an effective FILI Service Agreement a condition of energization where applicable. These provisions align with CAISO’s proposal in Section 25.7.2 of the CAISO Tariff.
D. Cost Shifting and Cost Recovery Agreements
Commission Concern: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack adequate mechanisms to mitigate the risk of cost shifting among transmission customers.54 The Show Cause Order directed the PTOs to address: (i) assignment of the Network Upgrade costs and their associated costs, that are needed to provide transmission service to Eligible Customers serving Large Loads; (ii) the need for a pro forma cost recovery agreement to mitigate the risk of cost shifting; and (iii) a mechanism to ensure that any payments attributable to the Large Load are appropriately credited toward the PTO’s TRR and documented in the annual informational filing for formula rates.55 The Commission also indicated a response should clarify how the minimum contribution and financial security required by an Eligible Customer serving a Large Load is calculated, i.e., whether by a per-MW figure or another methodology.56
GridLiance West Solution: Through Section 10.17.2, GridLiance West will utilize a Cost Recovery Agreement in the form of Attachment A to the GridLiance West Tariff to address assignment of costs associated with the construction and operation of any Network Upgrades resulting from the Interconnection of the Large Load. The Cost Recovery Agreement will be between GridLiance West and the Eligible Customer, and CAISO may join at its election.57 The Cost Recovery Agreement requires the Eligible Customer to pay 100 percent of the actual costs of the Large Load Network Upgrades through the Total Required Revenue Commitment. The Total Required Revenue Commitment establishes both the obligation to pay actual costs and the
54 Show Cause Order at P 65.55 Id. at PP 65-66, 76-84.56 Id. at PP 81-82.57 GridLiance West Tariff § 10.17.2; Attachment A.
PDF page 15
15
obligation to maintain financial security for the Eligible Customer. If the Eligible Customer does not provide sufficient service revenue attributable to the Large Load to GridLiance West through CAISO’s Access Charges to cover the Eligible Customer’s Annual Required Revenue Commitment, the Eligible Customer must provide Cost Recovery Payments58 to fill the gap in cost recovery. Cost Recovery Payments received are credited against GridLiance West’s Transmission Revenue Requirement. This ensures the Eligible Customer pays the full costs of their Network Upgrades. GridLiance West will provide a separate workpaper in the informational filing detailing the accounting treatment and crediting for the Annual Required Revenue Commitment.
The Cost Recovery Agreement also provides that the required amount of financial security shall be decreased as the Eligible Customer pays the Total Required Revenue Commitment over time. GridLiance West may draw upon the required financial security in the event of non-payment, termination, cancellation, or withdrawal to ensure that the Large Load is responsible for costs incurred to provide transmission service, including the cost of network upgrades and to prevent cost shifting to other customers.
GridLiance West has not proposed to allow an Eligible Customer to satisfy the financial security required under the Cost Recovery Agreement with credit support posted under a retail agreement. The Commission’s preliminary finding that an Eligible Customer “may include” such security permits this approach but does not require it.59 The approach does not fit a Non- LSE PTO. GridLiance West has no retail customers and is not party to any retail service agreement. Any retail security would be held by a third-party load-serving entity, would secure that entity’s retail obligations, and be subject to that entity’s draw rights and priorities, none of which GridLiance West can control or enforce. Such security therefore would not be sufficient to secure the Eligible Customer’s obligations under the Cost Recovery Agreement. Accepting it would leave other transmission customers exposed to the cost-shifting risk the Order is intended to prevent. The concern about duplicative credit requirements also does not arise here. The security required under the Cost Recovery Agreement secures a separate, Commission- jurisdictional payment obligation owed to GridLiance West, not the retail obligation owed to the load-serving entity. Requiring a single form of security held directly by the transmission owner is also simpler to administer and applies uniformly.
GridLiance West Tariff Section 10.17 requires the Interconnection Agreement itself to include cost responsibilities, financial security, and payment provisions for all engineering, equipment, construction, ownership, operation, and maintenance costs of any Direct Assignment Facilities, Reliability Upgrades, Interconnection Facilities, or Network Upgrades. Section 8.1.2 requires the party requesting Interconnection to pay all such costs, and GridLiance West has specified that this includes Interconnection for Large Loads throughout the GridLiance West Tariff.
Lastly, GridLiance West’s Section 13.2.1 requires GridLiance West to conduct reasonable credit review procedures and obtain financial security from the Eligible Customer. The financial
58 As defined in GridLiance West Tariff, Att. A § 1.3.59 Show Cause Order at P 82.
PDF page 16
16
security may take the form of an unconditional and irrevocable letter of credit or an alternative form acceptable to GridLiance West and consistent with commercial practices under the Uniform Commercial Code, in the amount of the Total Required Revenue Commitment set forth in the Cost Recovery Agreement.60 GridLiance West’s Tariff conditions Large Load energization on posting all required financial security pursuant to Section 8.1.5.1(viii) and asserts that this requirement will be effectuated through the Cost Recovery Agreement.
These provisions ensure that Eligible Customers and Large Loads, not other transmission customers, bear the costs incurred to serve them.
E. Pro Forma Transmission Service Agreements or Other Agreements
In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff and PTO Tariffs appear to be unjust and unreasonable because they lack pro forma transmission service agreement language memorializing the above terms.61 GridLiance West notes that the CAISO Tariff controls the provision of transmission service and defers to CAISO on this point.62
Specific to interconnection, GridLiance West believes the specificity in the revised GridLiance West Tariff will provide certainty to potential Eligible Customers serving Large Load with respect to the Commission’s primary concerns, including what ongoing operational and reliability requirements will apply, and the control CAISO will have over the Large Load. Those areas and their enforceability appeared to be the primary concerns raised by the Commission in the Show Cause Order.63 While GridLiance West understands including the language in a pro forma agreement may simplify compliance, GridLiance West has provided binding tariff language to remedy the Commission’s concern. CAISO will be fully able to enforce this tariff language to ensure the ongoing operational requirements are fully realized through individualized interconnection agreements consistent with the GridLiance West Tariff.64 GridLiance West is further concerned that developing a pro forma transmission service agreement in advance of establishing the procedures through the GridLiance West Tariff, and CAISO Tariff as applicable, may be premature and commit GridLiance West to language that does not meet the needs of either GridLiance West or an Eligible Customer taking transmission service on behalf of Large Loads. GridLiance West also has yet to process any Large Load interconnection requests which could further inform the needs of a pro forma Interconnection Agreement. However, GridLiance West commits to participating in any future initiative involving the development of a pro forma Large Load Interconnection Agreement, in coordination with CAISO and other PTOs, and updating its Tariff accordingly.
60 GridLiance West Tariff §§ 8.1.5.1(viii), 13.2.1.61 Show Cause Order at PP 56, 63.62 See id. at P 39 (“CAISO, however, is responsible for access to and the provision of transmission service, including transmission and ancillary services, to all Eligible Customers, and the reliability of that transmission service.”).63 Id. at P 64.64 Id. (raising concerns that requirements may be unenforceable by CAISO without a pro forma agreement).
PDF page 17
17
F. Protection for Existing Commercial Arrangements
Commission Concern: The Show Cause Order directed respondents to provide a reasoned explanation for how their proposal will avoid disrupting any existing commercial arrangements and provide a reasonable implementation period, including time to finalize agreements nearing completion, and include a reasonable effective date.65 GridLiance West Solution: GridLiance West requests an effective date of February 16, 2027, which is coordinated with the effective date CAISO is requesting for its companion tariff revisions and gives Eligible Customers and Large Loads reasonable notice of the new requirements. The new Section 10.20 of the GridLiance West Tariff provides that the provisions specific to Eligible Customers and Large Loads do not apply to a Load that is operational, or that has a Completed Interconnection Application, before February 16, 2027, unless and until the Load is modified or increased such that it would be a Large Load, or the Load elects to be treated as a Large Load.66 This transition provision mirrors proposed Section 25.7 of the CAISO Tariff. This approach is just and reasonable.
G. Energization and Coordination with CAISO
GridLiance West also clarifies in Section 8.1.5.1 that energization is conditioned on the Eligible Customer demonstrating that:
The Interconnection Agreement and Cost Recovery Agreement are effective; Any Energy the Large Load withdraws from the CAISO Controlled Grid will be purchased from an entity authorized to make such sales by the applicable Local Regulatory Authority;
A Scheduling Coordinator will represent the Large Load in compliance with Section 25.7.3 or 25.7.3.1 of the CAISO Tariff;
Access Charges will be paid consistent with the CAISO Tariff;
The information required by Section 25.7.1 of the CAISO Tariff has been provided;
Required equipment to facilitate monitoring, disturbance recording, telemetry, communication, control, protection, and disconnection has been installed, tested, and commissioned;
Any FILI Service Agreement is effective;
All required financial security has been posted;
For co-located or behind-the-meter configurations, control and protection technologies have been validated, and the Large Load is separately metered; and
65 Id. at P 34.66 GridLiance West Tariff § 10.20.
PDF page 18
18
The Large Load meets all frequency ride-through requirements, voltage ride through requirements, post-fault active power recovery requirements, and ramp rate limitations in accordance with CAISO Tariff Sections 25.7.1.1, 25.7.1.2, 25.7.1.3, and 25.7.1.4. This ensures no Large Load is energized until the information and equipment necessary to preserve reliability and to operate consistent with CAISO requirements is in place.
H. Ministerial and Conforming Revisions
GridLiance West has also made several ministerial or conforming revisions to either clarify or correct its tariff language or to better clarify the GridLiance West Tariff’s relation to the CAISO Tariff. These include:
Updating the Cover Sheet, including the Table of Contents;
Clarifying in Section 1 that GridLiance West does not provide retail electric service;
Clarifying in Section 1.3 how End-Users access the CAISO Controlled Grid; Updating the definition of Ancillary Services in Section 3.3;
Updating the definition of Available Transfer Capacity in Section 3.5; Updating the definition of Congestion Management in Section 3.13; Updating the definition of Dispatch in Section 3.18;
Updating the definition of End-Use Customer or End-User in Section 3.22; Updating the definition of Generating Unit in Section 3.33;
Updating the definition of Good Utility Practice in Section 3.35; Updating the definition of Interest in Section 3.51 to align with CAISO Tariff; Updating the definition of Local Publicly Owned Electric Utility in Section 3.54; Updating the definition of Metered Subsystem in Section 3.61;
Updating the definition of Non-Load-Serving Participating TO in Section 3.66 to align with CAISO Tariff;
Updating the definition of Non-Spinning Reserve in Section 3.68 to align with CAISO Tariff;
Updating the definition of Spinning Reserve in Section 3.87 to align with CAISO Tariff;
Updating the definition of Utility Distribution Company in Section 3.99; Defining FILI Service in Section 3.31 consistent with the CAISO Tariff; Clarifying Gross Load’s definition in Section 3.36 to better match CAISO; Revising the definition of “Interconnection” in Section 3.47 to address a typographical error;
Defining Interconnection Facilities in Section 3.50 to provide clarity; Defining Point of Interconnection in Section 3.74 to align with CAISO; Revising the definition of Reliability Upgrade in Section 3.82 to refer to a “facility” rather than an undefined term;
Ministerial additions of subsections and headers throughout Sections 8, 9, and 10 to enhance readability of the tariff for customers and stakeholders; Retitling Section 13 “Creditworthiness and Financial Security”;
PDF page 19
19
Clarified tariff by consistent use of Eligible Customer throughout; and Updating the Designated Representatives in Appendix II to ensure responsiveness.
III. RESPONSES TO REMAINING ELEMENTS OF THE SHOW CAUSE ORDER
The Show Cause Order directed PTOs to explain which of the Commission’s directives their filing resolves and how it resolves them.67 GridLiance West submits that the remaining elements of the Show Cause Order are either inapplicable to GridLiance West as a Non-LSE PTO or were directed to CAISO in the Show Cause Order.
This includes the requirement to provide data on CAISO’s website regarding Network Upgrade costs and planning for serving Large Loads.68 CAISO has proposed that each Transmission Plan report the aggregate amounts of proposed and completed Large Load additions by Transmission Zone and the planned Network Upgrades and estimated costs needed to accommodate Large Loads, identified by type of equipment. For its part, GridLiance West will facilitate this by providing relevant data under Section 10.3, which commits GridLiance West to apprise CAISO of Large Load interconnections through its inputs to the Base Case, Interconnection Studies, and the Transmission Planning Process.
The Commission primarily directed its questions and findings on co-located load to CAISO, given CAISO’s role in generator interconnection.69 GridLiance West therefore defers to CAISO on matters governed by the CAISO Tariff. To the extent the Commission’s directive implicates the PTO Tariffs, GridLiance West has addressed it through Sections 8.1.5.1(ix), 10.5.1, and 10.18.6 of the GridLiance West Tariff. GridLiance West has revised its tariff to align with CAISO’s co-location approach.
Similarly, the Commission directed its preliminary finding regarding new transmission services for flexible Large Loads, and its directive to submit an informational report regarding resource adequacy, solely to CAISO.70
Last, GridLiance West notes that CAISO has indicated that it intends to take up the matter of interconnection of electrically proximate Large Load in a future stakeholder proceeding. As such, GridLiance West proposes no tariff revisions in this filing for such elements identified in the Show Cause Order.71 This ensures that GridLiance West remains aligned with CAISO in this evolving process. GridLiance West commits to participation in any such future stakeholder process with CAISO.
67 Show Cause Order at P 34.68 Id. at PP 66, 70-75.69 Id. at PP 93-102 (covering rate design, ancillary services, transmission service, behind-the-meter netting, and interconnection via generator processes).70 Id. at PP 104 & n.222, 120-22.71 Id. at PP 113-19, 127.
PDF page 20
20
IV. RESPONSES TO THE COMMISSION’S REMAINING BRIEFING QUESTIONS
The Show Cause Order requested responses to specific briefing questions.72 Consistent with the division of responsibilities between CAISO and the PTOs recognized by the Commission in the Show Cause Order, GridLiance West responds to those briefing questions applicable to it as a PTO and defers to CAISO on those questions directed to CAISO or that concern matters governed by the CAISO Tariff.
In the Show Cause Order, the Commission recognized that the framework under which CAISO provides transmission service is unique among the RTOs/ISOs and that certain responsibilities fall to the PTOs. The Commission explained that the PTOs “have responsibility for wholesale load interconnection studies,” while CAISO “is responsible for access to and the provision of transmission service, including transmission and ancillary services, to all Eligible Customers, and the reliability of that transmission service.”73 The Commission further recognized that the PTOs may be primarily responsible for conducting the studies that evaluate whether a Large Load may be interconnected to the transmission system and whether Network Upgrades are necessary, that this role stems from how CAISO and the PTOs allocated rights and responsibilities in the governing documents establishing CAISO, and that the Commission does not seek to alter that allocation of rights and responsibilities.74 Consistent with that framework, the Commission directed the PTOs to respond to the extent the matters addressed herein implicate aspects of their respective tariffs.75
Within this framework, GridLiance West’s role is to process and study requests to interconnect Eligible Customer Large Loads to its facilities under the GridLiance West Tariff, to construct any Direct Assignment Facilities and Reliability Upgrades required for those interconnections and recover their costs from the Eligible Customer, and to provide CAISO with the necessary information for its operations and its Transmission Planning Process. Transmission service over the CAISO Controlled Grid, including GridLiance West’s facilities, is provided by CAISO under the CAISO Tariff. CAISO likewise administers the CAISO Markets and the generator interconnection procedures under the CAISO Tariff, and the California Public Utilities Commission has primary responsibility for resource adequacy within the CAISO footprint.76 Moreover, as a Non-LSE PTO, GridLiance West serves no retail load and does not forecast or plan for load growth within a retail service territory.
Accordingly, where a briefing question is directed to CAISO or concerns matters governed by the CAISO Tariff, GridLiance West indicates the question is not applicable. Where a briefing question concerns matters within GridLiance West’s responsibilities as a PTO, GridLiance West has addressed it through the proposed revisions to the GridLiance West Tariff,
72 Id. at PP 123-27.73 Id. at P 39.74 Id. at P 51.75 Id. at P 40; see also id. at P 34.76 Id. at P 122.
PDF page 21
21
most of which are discussed in Part II above. To assist the Commission’s review, GridLiance West identifies below each briefing question and where it is addressed in this transmittal letter.
1. What would be a reasonable implementation period to ensure minimal
disruption to such existing commercial arrangements?
This question is addressed in Part II.F and Part V of this transmittal letter. GridLiance West requests an effective date of February 16, 2027, which aligns with the effective date CAISO is requesting for its tariff revisions, gives GridLiance West time to implement the revised procedures and update its business practices, and gives Eligible Customers and Large Loads reasonable notice of the new requirements.
2. How to allow a reasonable amount of time to finalize ongoing agreements
that are nearing completion as of the date such tariff provisions are filed with the Commission.
This question is addressed in Part II.F of this transmittal letter. Consistent with CAISO’s proposed Section 25.7, the provisions of the GridLiance West Tariff specific to Eligible Customers and Large Loads will not apply to a Load that is operational, or that has a Completed Interconnection Application, before the effective date, unless and until the Load is modified or increased such that it would be a Large Load, or the Load elects to be treated as a Large Load. An interconnection request that is complete before the effective date may therefore proceed through its studies and Interconnection Agreement under the existing provisions of the GridLiance West Tariff, without being required to satisfy the new application, readiness, and financial security requirements.
3. What, if any, potential impacts on regional and local transmission planning would arise from the introduction of the new transmission services discussed herein?
As to the effects on regional and local transmission planning, GridLiance West participates in CAISO’s Transmission Planning Process, and its proposed revisions are designed to give CAISO and other planners accurate, timely information about Large Loads. Under Section 10.3, GridLiance West will apprise CAISO of Large Load interconnections through its inputs to the Base Case, Interconnection Studies, and the Transmission Planning Process. CAISO, in turn, proposes to include planned and forecasted Large Loads, including transmission additions or upgrades planned under all PTO Tariff interconnection processes, as inputs to its Unified Planning Assumptions and Study Plan. CAISO will also review those planned additions monthly and identify any that indicate high operational risk or uncertainty based on NERC Reliability Standards.
4. When planning for load growth, how would transmission providers and
planners account for flexible Large Loads’ potential preference to take the
new transmission services, including potential uncertainties around the type, location, and quantity of such expected loads?
The readiness requirements in Section 10.5.1, including ramp schedules, Site Control, permits, and disclosure of affiliated requests, reduce uncertainty about the type, location, and
PDF page 22
22
quantity of expected Large Loads and help ensure that planners rely on credible projects rather than speculative ones. For flexible Large Loads that elect interim service, each FILI Service Agreement will identify the Network Upgrades or Interconnection Facilities required to conclude FILI Service. CAISO will account for FILI loads in its Base Case, Full Network Model, and Operating Procedures. Thus, following the proposed revisions CAISO can therefore account for both the curtailable interim operation of these loads and the facilities required to transition them to full service. The proposed revisions from CAISO, GridLiance West, and other PTOs should enhance the flow of information regarding Large Loads into CAISO’s transmission planning process.
5. Information regarding potential structures for agreements between the
transmission owner/provider and an Eligible Customer to prevent unjust and
unreasonable cost shifts among transmission customers related to Network
Upgrade costs required for Large Loads.
This question is addressed in Part II.D of this transmittal letter.
6. Information on what an appropriate minimum level of cost recovery and
financial security from an Eligible Customer would be under any such
agreements.
This question is addressed in Part II.D of this transmittal letter.
7. Whether the Tariff remains just and reasonable without provisions that
require the evaluation of alternative transmission technologies in studies for the provision of transmission service, using models that are capable of
evaluating the transmission system to accurately account for advanced
transmission technologies, in all instances, without the need for a request from the Eligible Customer seeking transmission service on behalf of Large
Load.
This question is addressed in Part II.A.4 of this transmittal letter. GridLiance West proposed provisions that require the evaluation of alternative transmission technologies.
8. If traditional Network Upgrades are selected instead of alternative
transmission technologies, inclusion in the study report to the Eligible
Customer seeking transmission service on behalf of Large Load of a
sufficiently clear demonstration of why alternative transmission technologies are not feasible (i.e., would not resolve reliability violations identified or meet the relevant planning criteria) or would not result in lower costs or a faster timeline for accommodating the transmission service request.
This question is likewise addressed in Part II.A.4 of this transmittal letter. Section 10.12.1 of the GridLiance West Tariff provides that, if traditional Network Upgrades are selected instead of alternative transmission technologies, GridLiance West will provide a demonstration of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline for accommodating the Large Load Interconnection request, and a copy of the completed System Impact Study will be made available to the Eligible Customer.
PDF page 23
23
9. Whether specific characteristics of providing transmission service to Eligible Customers on behalf of Large Loads warrant requirements beyond those
contemplated here, we seek further briefing.
GridLiance West does not propose requirements beyond those described in Part II of this transmittal letter at this time.
10. To what extent would CAISO allow an interconnection customer’s
generating facility serving electrically proximate Large Load or large co- located load to participate in CAISO’s energy and ancillary services market, and if CAISO were to allow them to participate, what restrictions or
mitigation would CAISO apply?
Not applicable.
11. To the extent that CAISO plans for the electrically proximate Large Load or large co-located load associated with an interconnection customer’s
generating facility for resource adequacy purposes, would CAISO account for the generating facilities serving electrically proximate Large Load or large co-located load in the resource adequacy construct?
Not applicable.
a. Would CAISO allow the generating facilities serving electrically
proximate Large Load or large co-located load to participate in
CAISO’s capacity market?
Not applicable.
b. Would CAISO accredit these generating facilities using the same
method as other CAISO generating facilities?
Not applicable.
V. PROPOSED EFFECTIVE DATE AND WAIVER
GridLiance West respectfully requests that the Commission accept the proposed revisions as of February 16, 2027, which aligns with the effective date proposed by the CAISO in its section 205 filing.77 The requested effective date is consistent with the Commission’s directive that tariff revisions include a reasonable implementation period and a reasonable effective date to ensure minimal disruption to existing or ongoing commercial arrangements.78 Although GridLiance West is not aware of any existing commercial arrangements that would be affected by the tariff revisions proposed herein, the requested effective date will provide GridLiance West adequate time to implement the tariff changes, update applicable procedures and business
77 CAISO Proposed Tariff § 25.7.78 Show Cause Order at P 5.
PDF page 24
24
practices, and ensure that requests for service from Eligible Customers taking transmission service on behalf of Large Loads are processed in a manner consistent with the revised tariff framework. Establishing an effective date that aligns with CAISO’s implementation schedule will promote consistent application of the revised tariff provisions throughout the CAISO Controlled Grid and avoid unnecessary operational and procedural uncertainty. For these reasons, GridLiance West respectfully requests that the Commission find that the proposed effective date is just and reasonable and complies with the Commission’s directive regarding implementation timing.
To the extent necessary, GridLiance West respectfully requests waiver of any applicable requirement of Part 35 not addressed herein.
VI. CONTENTS OF THE FILING
In addition to this transmittal letter, this filing contains the following components:
Appendix A: Clean Version of the Revised Sections of the GridLiance West Tariff;
Appendix B: Redlined Version of the Revised Sections of the GridLiance West Tariff; and
Appendix C: Pro Forma Cost Recovery Agreement.
VII. CORRESPONDENCE AND SERVICE
The following persons are authorized to receive notices and service with respect to this filing:
Elizabeth Ramey
Senior Attorney
NextEra Energy, Inc.
801 Pennsylvania Avenue, NW
Suite 220
Washington, DC 20004
(202) 909-5696
elizabeth.ramey@nexteraenergy.com
Meghan O’Brien
Van Ness Feldman, LLP
2000 Pennsylvania Avenue, NW
Suite 6000
Washington, DC 20006
(202) 298-1800
mobrien@vnf.com
PDF page 25
25
VIII. CONCLUSION
For the reasons set forth above, GridLiance West respectfully requests that the Commission accept the proposed revisions to the GridLiance West Tariff, effective February 16, 2027. GridLiance West furthermore requests that the Commission determine with respect to the remaining elements of the Show Cause Order that GridLiance West has complied with the Show Cause Order components applicable to it as a Non-LSE PTO. Accordingly, GridLiance West respectfully requests that the show cause proceeding be terminated with respect to GridLiance West.
Respectfully submitted,
/s/ Meghan O’Brien
Meghan O’Brien
Nolan Brickwood
Joseph B. Nelson
Jedrick M. Kim
Van Ness Feldman, LLP
2000 Pennsylvania Avenue, NW
Suite 6000
Washington, DC 20006
(202) 298-1800
mobrien@vnf.com
nbrickwood@vnf.com
jbn@vnf.com
jkim@vnf.com
Counsel for GridLiance West LLC
Enclosure