ER27-533-000 · 2026-11-16 · GridLiance West LLC

GridLiance West - Response to Show Cause Order EL26-71

GridLiance West LLC files tariff revisions under section 205 on November 16, 2026, in ER27-533-000, answering the CAISO show cause order. It adds large load procedures, a pro forma cost recovery agreement and an interim service, and asks to be dropped from the proceeding. The letter closely mirrors the Horizon West and Trans Bay Cable filings, apart from company facts and minor wording.

Asks FERC to: Accept the revisions effective February 16, 2027, allow 30 days for comments, and terminate the show cause proceeding as to GridLiance West.

Filed under section 205 to answer the E-10 show cause order. It follows CAISO's draft tariff language and sets an application process, a cost recovery agreement and an interim service for a non-load-serving owner.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)

Key points

  1. GridLiance West runs about 165 miles of 230 kV line in southern Nevada, inside the CAISO grid.
    The HVTS consists of approximately 165 miles of 230-kV transmission lines and related substation infrastructure that runs through rural Southern Nevada PDF p. 2
  2. It says parts of the show cause order do not apply to a non-load-serving owner, and asks to be dropped from the proceeding.
    GridLiance West also explains how certain aspects of the Show Cause Order are not applicable to GridLiance West due to its role as a Non-Load-Serving Entity PTO PDF p. 2
  3. It copies CAISO's 50 MW definition of large load.
    This definition is identical to the definition CAISO proposes to add to Appendix A of the CAISO Tariff, and adopts the 50 MW threshold the Commission identified as reasonable PDF p. 6
  4. Because it serves no retail load, it offers unbundled retail transmission service so large loads can be studied under its tariff.
    a voluntary offer of unbundled retail transmission service, where consistent with state law, so that Large Loads can request Interconnection and be studied under the GridLiance West Tariff PDF p. 6
  5. Study deposits start at $35,000 plus $1,000 per MW, matching CAISO's generator process.
    must provide a refundable study deposit of: (a) $35,000 plus $1,000 per MW PDF p. 8
  6. The interim service depends on the load's ability to reduce at a point of interconnection, under a three-party agreement.
    FILI Service is available if the Large Load can reduce its load at a specified Point of Interconnection according to protocols in a FILI Service Agreement among the Large Load, GridLiance West, and CAISO PDF p. 13
  7. The customer pays all actual network upgrade costs through a revenue commitment.
    The Cost Recovery Agreement requires the Eligible Customer to pay 100 percent of the actual costs of the Large Load Network Upgrades through the Total Required Revenue Commitment PDF p. 14
  8. Retail credit support does not count toward the security, because it holds no retail agreement and could not enforce it.
    GridLiance West has not proposed to allow an Eligible Customer to satisfy the financial security required under the Cost Recovery Agreement with credit support posted under a retail agreement PDF p. 15

Text extracted from the eLibrary original (SHA-256 4721be916383d5ae…). Download the original from the official source.

Contents · 19 sections
  1. I. BACKGROUND p. 2
  2. A. GridLiance West p. 2
  3. B. Show Cause Order p. 2
  4. C. Motion for Abeyance p. 3
  5. II. GRIDLIANCE WEST’S PROPOSED TRANSMISSION OWNER TARIFF p. 4
  6. A. Large Load Interconnection Process p. 5
  7. B. Co-Located Load p. 11
  8. C. Flexible Large Load Services p. 13
  9. D. Cost Shifting and Cost Recovery Agreements p. 14
  10. E. Pro Forma Transmission Service Agreements or Other Agreements p. 16
  11. F. Protection for Existing Commercial Arrangements p. 17
  12. G. Energization and Coordination with CAISO p. 17
  13. H. Ministerial and Conforming Revisions p. 18
  14. III. RESPONSES TO REMAINING ELEMENTS OF THE SHOW CAUSE ORDER p. 19
  15. IV. RESPONSES TO THE COMMISSION’S REMAINING BRIEFING QUESTIONS p. 20
  16. V. PROPOSED EFFECTIVE DATE AND WAIVER p. 23
  17. VI. CONTENTS OF THE FILING p. 24
  18. VII. CORRESPONDENCE AND SERVICE p. 24
  19. VIII. CONCLUSION p. 25

Topics in the text: Connecting load and generation · Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

GridLiance West also explains how certain aspects of the Show Cause Order are not applicable to GridLiance West due to its role as a Non-Load-Serving Entity PTO (“Non-LSE PTO”).6 Thus, GridLiance West requests that the show cause proceeding be terminated with respect to GridLiance West.
Read this passage

I. BACKGROUND

printed heading

I.
Read this passage

A. GridLiance West

printed heading

GridLiance West GridLiance West operates transmission facilities within CAISO.
Read this passage

B. Show Cause Order

printed heading · Topic match: Connecting load and generation

Show Cause Order On June 18, 2026, the Commission initiated a show cause proceeding against CAISO and the PTOs pursuant to section 206 of the FPA.
Read this passage

C. Motion for Abeyance

printed heading · Topic match: Filing procedure

See id. at P 3 n.14. 13 Id. at P 3. 4 (“Abeyance Motions”).14 The Commission granted the Abeyance Motions and held this proceeding in abeyance, in full, including responses to the Show Cause Order and briefing questions, for 90 days.15
Read this passage

II. GRIDLIANCE WEST’S PROPOSED TRANSMISSION OWNER TARIFF

printed heading · Topic match: Cost allocation

The proposed revisions establish an application process, study procedures, operational requirements, and creditworthiness and financial security requirements applicable to requests by Eligible Customers seeking to interconnect a Large Load to the GridLiance West transmission system.
Read this passage

A. Large Load Interconnection Process

printed heading · Topic match: Cost allocation

Finally, GridLiance West proposes requirements for installation and maintenance of the equipment required to disconnect or otherwise isolate the Large Load (Sections 8.1.5.1(vi) and 10.17), with those costs directly assigned to the applicant to avoid cost shifting to transmission customers (Section…
Read this passage

B. Co-Located Load

printed heading · Topic match: Connecting load and generation

Co-Located Load Commission Concerns: In the Show Cause Order, the Commission made a preliminary finding that the CAISO Tariff appears to be unjust and unreasonable because it lacks sufficiently clear and consistent tariff provisions addressing the rates, terms, and conditions that apply to co-…
Read this passage

C. Flexible Large Load Services

printed heading · Topic match: Connecting load and generation

With respect to interconnection service, GridLiance West proposes two interim services that allow a Large Load to begin taking interconnection service before all of its upgrades are in place that reflects the Large Load’s ability to reduce load: the existing Partial Interim Service and FILI Service.
Read this passage

D. Cost Shifting and Cost Recovery Agreements

printed heading · Topic match: Cost allocation

If the Eligible Customer does not provide sufficient service revenue attributable to the Large Load to GridLiance West through CAISO’s Access Charges to cover the Eligible Customer’s Annual Required Revenue Commitment, the Eligible Customer must provide Cost Recovery Payments58 to fill the gap in…
Read this passage

E. Pro Forma Transmission Service Agreements or Other Agreements

printed heading

GridLiance West also has yet to process any Large Load interconnection requests which could further inform the needs of a pro forma Interconnection Agreement.
Read this passage

F. Protection for Existing Commercial Arrangements

printed heading

Protection for Existing Commercial Arrangements Commission Concern: The Show Cause Order directed respondents to provide a reasoned explanation for how their proposal will avoid disrupting any existing commercial arrangements and provide a reasonable implementation period, including time to…
Read this passage

G. Energization and Coordination with CAISO

printed heading

This ensures no Large Load is energized until the information and equipment necessary to preserve reliability and to operate consistent with CAISO requirements is in place.
Read this passage

H. Ministerial and Conforming Revisions

printed heading

Ministerial and Conforming Revisions GridLiance West has also made several ministerial or conforming revisions to either clarify or correct its tariff language or to better clarify the GridLiance West Tariff’s relation to the CAISO Tariff.
Read this passage

III. RESPONSES TO REMAINING ELEMENTS OF THE SHOW CAUSE ORDER

printed heading · Topic match: Connecting load and generation

As such, GridLiance West proposes no tariff revisions in this filing for such elements identified in the Show Cause Order.71 This ensures that GridLiance West remains aligned with CAISO in this evolving process.
Read this passage

IV. RESPONSES TO THE COMMISSION’S REMAINING BRIEFING QUESTIONS

printed heading · Topic match: Connecting load and generation

GridLiance West requests an effective date of February 16, 2027, which aligns with the effective date CAISO is requesting for its tariff revisions, gives GridLiance West time to implement the revised procedures and update its business practices, and gives Eligible Customers and Large Loads…
Read this passage

V. PROPOSED EFFECTIVE DATE AND WAIVER

printed heading

For these reasons, GridLiance West respectfully requests that the Commission find that the proposed effective date is just and reasonable and complies with the Commission’s directive regarding implementation timing.
Read this passage

VI. CONTENTS OF THE FILING

printed heading

CONTENTS OF THE FILING In addition to this transmittal letter, this filing contains the following components: Appendix A: Clean Version of the Revised Sections of the GridLiance West Tariff; Appendix B: Redlined Version of the Revised Sections of the GridLiance West Tariff; and Appendix C: Pro…
Read this passage

VII. CORRESPONDENCE AND SERVICE

printed heading

CORRESPONDENCE AND SERVICE The following persons are authorized to receive notices and service with respect to this filing: Elizabeth Ramey Senior Attorney NextEra Energy, Inc. 801 Pennsylvania Avenue, NW Suite 220 Washington, DC 20004 (202) 909-5696 elizabeth.ramey@nexteraenergy.com Meghan O’Brien…
Read this passage

VIII. CONCLUSION

printed heading

CONCLUSION For the reasons set forth above, GridLiance West respectfully requests that the Commission accept the proposed revisions to the GridLiance West Tariff, effective February 16, 2027.
Read this passage