ER27-534-000 · 2026-11-16 · DesertLink, LLC

Revisions to TO Tariff to Provide for Large Load Interconnection

PDF page 1

Josh R. Robichaud
Associate
T:+1.202.828.1731             F: +1.800.404.3970
2001 M Street NW, Suite 900, Washington,DC 20036-3310
josh.robichaud@bracewell.com            bracewell.com

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C November 16, 2026

VIA ETARIFF
The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.

Washington, D.C. 20426
Re:
DesertLink, LLC, Docket No. ER27-___-000
California Independent System Operator Corporation, Docket No. EL26-71-___
Proposed Revisions to the DesertLink, LLC Transmission Owner Tariff to Provide for Large Load Interconnection and Cost Recovery

Dear Secretary Reese:
Pursuant to section 205 of the Federal Power Act (“FPA”)1 and Part 35 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) regulations,2 and in response to the Commission’s order instituting the show cause proceeding in California Independent System Operator Corp.,3 DesertLink, LLC (“DesertLink”) submits revisions to its Transmission Owner Tariff (“TO Tariff”) to establish a framework for the interconnection of Large Loads4 and for the recovery of the costs of transmission upgrades driven by Large Loads. The revisions include (1) adding a new Section 10A and a new Appendix VI (Large Load Interconnection Procedures (“LLIP”)) to establish an interconnection process for Eligible Customers for Large Load (“ECLLs”);

(2) corresponding revisions to the TO Tariff; and (3) adding a new Appendix V, the pro forma Large Load Cost Recovery Agreement (“CRA”). DesertLink respectfully requests that the Commission accept the proposed tariff revisions to become effective January 16, 2027, sixty-one

(61) days after filing, consistent with the Commission’s prior notice requirement,5 and grant any necessary waivers.

1  16 U.S.C. § 824d (2022).
2  18 C.F.R. pt. 35 (2026). 3  Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (“Show Cause Order”).
4  Capitalized terms used but not otherwise defined in this transmittal letter have the meanings assigned to them in the TO Tariff, including the proposed revisions to Section 3 and the pro forma CRA in Appendix V, or, if not defined therein, in the CAISO Tariff.
5  18 C.F.R. § 35.3(a)(1).

PDF page 2

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 2

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C
I. INTRODUCTION AND SUMMARY OF FILING
The proposed revisions establish a transparent framework for DesertLink, a transmission-only, non-load-serving Participating Transmission Owner (“PTO”) in the California Independent System Operator Corporation (“CAISO”), to interconnect Large Loads and to recover the costs of transmission upgrades that are driven, in whole or in part, by a Large Load (“Large Load-Driven Upgrades”). New Section 10A and the LLIP in Appendix VI govern ECLL applications, studies, interim service, and interconnection agreements. The pro forma CRA in Appendix V establishes the Eligible Customer’s twenty-year Minimum Transmission Revenue Contribution (“MTRC”) and related payment and security obligations for each Covered Upgrade. Amounts received under a CRA are credited to transmission customers through DesertLink’s existing Transmission Revenue Balancing Account Adjustment (“TRBAA”), and the Formula Rate Template is revised to identify Covered Upgrade plant and to ensure that those credits are not counted twice. The filing responds to the Show Cause Order’s direction that respondents (1) ensure transparency concerning the network upgrade costs to provide transmission service to Eligible Customers on behalf of large loads, (2) establish a pro forma cost recovery agreement to mitigate the risk of cost shifting among transmission customers, and (3) ensure that such payments are appropriately credited toward transmission owners’ transmission revenue requirements.6 The CRA assigns the wholesale revenue-support obligation to the Eligible Customer that takes transmission service on behalf of the Large Load Facility and backs that obligation with Construction Security, Operational Security, and a Termination Fee. The framework is designed to mitigate the risk that other customers bear the costs of a Covered Upgrade if the associated Large Load is delayed, reduced, or does not materialize, while preserving DesertLink’s recovery of its revenue requirement through its Formula Rate and the CAISO Transmission Access Charge (“TAC”), and without changing CAISO cost allocation.

The proposed revisions do not change the cost-of-service inputs, return, depreciation, taxes, or allocators used to calculate DesertLink’s revenue requirement. Absent any Covered Upgrade or CRA, the revised Formula Rate Template produces the same revenue requirement as the currently effective Formula Rate Template, and no changes are proposed to DesertLink’s Formula Rate Implementation Protocols (Appendix IV) or to Appendix I of the TO Tariff. Once these revisions are accepted, a conforming, executed CRA with populated Schedules generally will not require an individual FPA section 205 filing, while unexecuted agreements, agreements containing a material deviation, and other agreements required by Commission rule or order will be filed with the Commission.7

6  Show Cause Order at P 3.
7  See Ex. No. DLK-200 (Arzola Testimony); CRA § 5.1.

PDF page 3

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 3

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C
II. BACKGROUND
A. DesertLink and Its Formula Rate
DesertLink is a transmission-only PTO in the CAISO that owns the Harry Allen to Eldorado 500 kV Transmission Line Project (“Harry Allen to Eldorado Project”), which CAISO selected DesertLink to develop in 2016 through its Order No. 1000-compliant competitive solicitation process and which DesertLink placed in service in August 2020. DesertLink is a non-load-serving PTO; it neither serves retail load nor has a retail relationship with any customer seeking a Large Load interconnection. DesertLink’s formula rate consists of its Formula Rate Template (Appendix III of the TO Tariff) and its Formula Rate Implementation Protocols (“Protocols”) (Appendix IV of the TO Tariff) (together, the “Formula Rate”), which were originally accepted in Docket No. ER17- 135-000 and most recently revised in Docket No. ER26-3479-000. DesertLink’s Transmission Revenue Requirement (“TRR”) is the sum of its Base Transmission Revenue Requirement (“Base TRR”), determined under the Formula Rate, and its TRBAA, and is recovered through the CAISO TAC. DesertLink already uses the TRBAA to credit customers with revenue it receives outside the TAC.

B. Show Cause Order and Stakeholder Process
On June 18, 2026, the Commission issued the Show Cause Order, instituting an FPA section 206 proceeding in Docket No. EL26-71-000 directed to CAISO and its PTOs. The Commission preliminarily found that existing tariffs appear to be unjust, unreasonable, or unduly discriminatory or preferential because they lack sufficiently clear and consistent provisions to address the challenges posed by the rapid growth of large loads and co-location arrangements between loads and generating facilities.8 The Commission directed each respondent either to show cause why its tariff remains just and reasonable or to explain what tariff changes would remedy the identified concerns.9

Following the Show Cause Order, CAISO convened joint coordination meetings with the PTOs to address the Show Cause Order and CAISO’s proposed implementation framework, and DesertLink participated in those meetings from July through October 2026. DesertLink also participated in CAISO’s public stakeholder meetings and submitted written comments on CAISO’s Straw Proposal, Draft Final Proposal, and Draft Tariff Language asking CAISO to recognize non- load-serving and affected PTOs expressly and to preserve a meaningful role for those PTOs in the interconnection and study process. DesertLink further participated in discussions with other non- load-serving PTOs, the broader PTO group, and load-serving PTOs addressing the application and study process, information sharing, technical coordination, and the allocation and recovery of costs.10 Those discussions highlighted the need to ensure that an affected PTO has a meaningful

8  Show Cause Order at P 38.
9  Id. at Ordering Para. B.
10  See Ex. No. DLK-100 (Hayes Testimony), Section IV.

PDF page 4

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 4

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C role in the process even when it does not provide retail service to the requesting load. DesertLink’s proposal does not displace the separate arrangements that an Eligible Customer must enter into with an Affected System Owner for an Affected System Upgrade or with the owner of a regional project share owned by another entity.11

III. DESCRIPTION OF THE PROPOSED REVISIONS
A. Large Load Interconnection Framework (Section 10A and Appendix VI)
A new Section 10A of the TO Tariff establishes an interconnection process for ECLL Interconnections. An ECLL is a Utility Distribution Company or Metered Subsystem that provides retail transmission and interconnection service to Large Load End-Users in the CAISO Balancing Authority Area, and a Large Load is an End-User located at a single site behind one or more Points of Withdrawal from the CAISO Controlled Grid with a peak load of 50 MW or greater. Section 10A.2 specifies the contents of an ECLL Interconnection Application, including the load ramp schedule, site plan, Site Control, permits and approvals, electrical configuration, related requests, technical data, and Co-Located Large Load information. Section 10A.3 directs that ECLL Interconnection Applications be processed, and ECLL Interconnection Agreements be tendered, executed, and filed, under the LLIP in Appendix VI. Section 10A.4 provides for Interim Firm Interconnection Service and Flexible Interim Load Interconnection (“FILI”) Service before the required facilities are completed. FILI Service is subject to curtailment, including during normal operating conditions, and is curtailed before Firm Interconnection Service. If FILI Service is elected, the Large Load Interconnection Customer must ensure that, before the Service Commencement Date, the Large Load Customer executes, or requests the filing of an unexecuted, FILI Service Agreement with DesertLink and, as applicable, CAISO. That agreement identifies the curtailment conditions and the mechanism for implementing curtailment. Section 10A.5 addresses Co-Located Large Loads.12

The LLIP applies to new Large Loads, capacity increases to Large Loads previously processed under the LLIP, and increases of 50 MW or greater to existing loads not previously processed under the LLIP, for completed Interconnection Requests submitted after Appendix VI becomes effective. It provides for a scoping meeting, a Large Load Study Process Agreement, and a Large Load Interconnection Study subject to CAISO review and concurrence, with a ninety-Calendar- Day reasonable-efforts study period. The study must consider alternative transmission technologies, including dynamic line ratings, advanced power flow control devices, advanced conductors, and transmission switching, and, if traditional network upgrades are selected, the PTO must demonstrate why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline.13 The LLIP also establishes financial readiness

11  See CRA §§ 4.2 and 6.3.6.
12  TO Tariff §§ 3.24 and 3.62.
13  LLIP § 4.6.1.1.

PDF page 5

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 5
A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C requirements, including a $250,000 Interconnection Study Deposit, Commercial Readiness Deposits that bring the aggregate deposit to twenty percent (20%) of the estimated construction cost of the Large Load Network Upgrades attributable to the request, and withdrawal penalties, and coordinates those deposits with the CRA so that the same costs are not secured twice.14 The existing Section 10 is retitled the Transmission System Wholesale Load (“TSWL”) Interconnection Process and continues to govern TSWL Interconnections. Section 10.1 directs ECLL requests to Section 10A, and revised Section 10.9 provides that, where a TSWL Interconnection will serve one or more Large Loads, the Eligible Customer taking or requesting transmission service on behalf of the Large Load must execute and maintain a CRA, or request that it be filed unexecuted, as a condition to DesertLink’s design, procurement, construction, or operation of any associated Large Load-Driven Upgrades. Section 3 adds definitions for, among other terms, Co-Located Large Load, Cost Recovery Agreement, ECLL, ECLL Interconnection, Firm Interconnection Service, FILI Service, Interim Firm Interconnection Service, Large Load, Point of Withdrawal, Site Control, and TSWL Interconnection, and renumbers the existing definitions.

B. Pro Forma CRA (Appendix V)
The pro forma CRA is a contract between DesertLink, as Transmission Owner, and the Eligible Customer taking wholesale transmission service under the CAISO Tariff on behalf of a Large Load Customer. Assigning the payment obligation to that Eligible Customer preserves the wholesale obligor structure and does not establish a FERC-jurisdictional retail rate or payment obligation for the Large Load Customer. The Large Load Customer executes a Limited Acknowledgment for information, authorization, notice, and cooperation purposes, but is not a party to the wholesale payment obligations. CAISO is not a party to the CRA, and the CRA creates no obligation of CAISO. Covered Upgrades include Large Load-Driven Upgrades and any DesertLink-owned share of a CAISO-Assigned Regional Project identified in the applicable Schedules for which an Annual MTRC is established; Affected System Upgrades and regional project shares owned by another entity are addressed through separate arrangements. Where DesertLink requires a CRA, Section 10.9 (for a TSWL Interconnection) and LLIP Section 5.3, incorporated through Section 10A.6 (for an ECLL Interconnection), require the applicable Eligible Customer to execute it, or to request that it be filed unexecuted, within the applicable interconnection-agreement execution period.15 For each Covered Upgrade, the CRA establishes an Annual MTRC calculated solely under the MTRC Calculation Template in Schedule 5, separately from the Formula Rate. The Estimated Annual MTRC uses then-current estimated capital cost. Within one year after the Covered Upgrade enters service, when actual capital cost is known, DesertLink establishes the Final Annual MTRC as the final incurred capital cost multiplied by the Project-Specific Levelized Fixed Charge Rate calculated under Schedule 5 using the applicable capital structure, cost of debt, return on equity, income-tax inputs, a fixed five percent (5%) annual levelized-depreciation

14  See LLIP §§ 3.10, 3.10.1, 4.2.1, and 4.6.1.4.
15  See CRA Recitals, § 2.17, Article 5, and Limited Acknowledgment; TO Tariff §§ 10.9 and 10A.6; LLIP § 5.3.

PDF page 6

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 6

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C schedule, and the fixed expense allocator. The MTRC Term begins on the applicable in-service date and ends on the day immediately preceding its twentieth anniversary, with partial Rate Years prorated. The Final Annual MTRC is not recalculated through the Formula Rate and may change only as permitted by Section 6.3.1, including to correct errors or fraud, to implement an effective prospective reassignment or a final Commission order, or to reflect prospectively a Commission-approved change in DesertLink’s return on equity or subsequently enacted tax rates or tax law.16

The twenty-year MTRC Term is a defined contractual revenue-support period, not the depreciable life of a Covered Upgrade. Each Covered Upgrade placed under CAISO’s Operational Control remains in DesertLink’s rate base and Base TRR and is subject to ordinary Formula Rate treatment. Where an upgrade is driven by more than one Large Load, Schedule 1 identifies an Initial Allocation Percentage for each Large Load Customer using the applicable final study and allocation methodology, accounting for loads studied individually, jointly, or in a cluster and for any portion of the facility that serves other transmission system needs or customers. The aggregate Annual MTRC allocated to all Large Load Customers may not exceed one hundred percent (100%) of the Annual MTRC for that Covered Upgrade; any unallocated portion remains subject to otherwise applicable CAISO cost-allocation and rate-recovery requirements. Each allocation percentage is applied only once in calculating the Annual MTRC.17 The Eligible Customer pays a Supplemental MTRC equal to the greater of zero and the applicable Annual MTRC less Qualifying Transmission Revenues (“QTR”). QTR consists of wholesale transmission revenues attributable to service to the Large Load Facility that reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement. As applicable, QTR includes the portion of TAC revenues attributable to the Large Load Facility and allocable to DesertLink under the reproducible methodology in Schedule 2, qualifying Wheeling Access Charges, and other wholesale transmission-access, wheeling, or transmission-service charges, including charges paid through a non-PTO serving entity, without duplicate recognition. The Annual MTRC therefore operates as a revenue floor, not an additive charge or separate capacity-reservation commitment. DesertLink invoices the forecast Supplemental MTRC, including any prior-period true-up adjustment, in monthly installments following each Annual Projection, and serves a Reconciliation Statement with each Annual Update using actual QTR. Under-billed or over-billed amounts are carried into billing following the next Annual Projection, without interest between DesertLink and the Eligible Customer.18 Section 6.7 of the CRA establishes for each Covered Upgrade a Total Required Revenue Commitment equal to the Final Annual MTRC multiplied by twenty, which is reduced by QTR, Supplemental MTRC Receipts, Applied Security Proceeds, and other permitted amounts, without

16  See CRA §§ 2.5, 2.26, 2.38, and 6.3.1 and Schedule 5.
17  See id. § 6.3.2 and Schedule 1.
18  See id. §§ 6.2 and 6.4–6.6 and Schedule 2.

PDF page 7

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 7

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C double counting, and tracked in an upgrade-specific Cumulative Revenue Ledger. Cancellation, downsizing, curtailment, or cessation after an applicable in-service date does not itself eliminate the Eligible Customer’s obligations. Upon effective termination of the CRA or permanent cessation of service after that date, the Eligible Customer owes a lump-sum Termination Fee equal to the Remaining Cumulative Revenue Responsibility, less any Supplemental MTRC billed and unpaid as of the effective termination or cessation date, which remains separately payable and secured. The Termination Fee is an accelerated contractual termination charge, not a penalty. DesertLink holds each Termination Fee in a separately identified, interest-bearing Termination Fee Account and credits it to transmission customers through the TRBAA as Annual Termination Fee Credits equal to the Annual MTRC for each remaining Rate Year of the MTRC Term. The uncredited balance is accounted for as a deferred liability and is not included in rate base.19

Article 7 of the CRA requires Construction Security for incurred and irrevocably committed costs and Pre-In-Service Termination Costs, including applicable cancellation, demobilization, and restoration costs and properly accrued allowance for funds used during construction. Operational Security must be delivered no later than thirty Calendar Days before the earliest expected in- service date and equals one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility. Consistent with the Commission’s decision to reduce unnecessary redundancy by allowing an Eligible Customer to rely on credit support posted by a large load under a retail agreement, direct Operational Security is reduced dollar-for-dollar by Qualifying Retail Security Support identified in a currently effective Retail Security Certification. That reduction does not reduce the underlying wholesale obligation and does not apply to Construction Security or Pre-In-Service Termination Costs. Security does not cap the Eligible Customer’s liability. Construction Security provided under an interconnection or engineering and procurement agreement for the same costs counts toward, and is not duplicated by, the CRA requirement. A Commercial Readiness Deposit may be credited dollar-for-dollar toward required CRA Construction Security only if it is in a form permitted under Schedule 3 and DesertLink elects that treatment in writing; no amount may be applied or credited more than once.20 This filing adopts the conservative requirement that direct Operational Security equal one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility, subject only to Qualifying Retail Security Support. DesertLink expects to work with CAISO and interested stakeholders to evaluate whether, and under what objectively defined circumstances, a lower requirement or another credit-support structure could provide comparable protection against cost shifting. Any future change would be submitted to the Commission for review under FPA section 205.

19  See id. §§ 3.3.4, 3.5, and 6.7.
20  Show Cause Order, Comm’r See Concurrence at P 9.

PDF page 8

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 8

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C
C. Crediting CRA Amounts Through the TRBAA (Sections 3 and 5.5)
CRA amounts are credited to transmission customers through DesertLink’s existing TRBAA, not as Formula Rate revenue credits. Because the TO Tariff defines Transmission Revenue Credits as amounts received from, or charges imposed by, CAISO, DesertLink proposes to revise the definition of the TRBAA (Section 3.103) and Section 5.5 so that the TRBAA also flows through to transmission customers all amounts that a CRA requires to be credited through it. The revisions clarify that Section 5.5 does not require the payment of interest between DesertLink and a party to a CRA, which is governed solely by the CRA, and the definition of Interest (Section 3.60) is revised to the same effect. The definition of Transmission Revenue Credits is unchanged.21 Each October, DesertLink will include a Forecast TRBAA Credit equal to the projected Supplemental MTRC for the following year, increased or reduced by any prior-period true-up adjustment, plus any Annual Termination Fee Credit scheduled for that year. The Forecast TRBAA Credit lowers the TRR effective January 1 and, through the TAC, the transmission charges paid by all customers, while the Eligible Customer pays the Supplemental MTRC directly to DesertLink. Supplemental MTRC cash receipts, Applied Security Proceeds applied to Supplemental MTRC obligations, Annual Termination Fee Credits, and any duplicate-recovery credits are recorded in the TRBA. A billed but unpaid Supplemental MTRC is not a TRBAA Credit. If DesertLink later receives payment or applies Security proceeds to that obligation, the amount is recorded only in the Rate Year in which it is received or applied. Any difference between the Forecast TRBAA Credit and the actual amounts recorded in the TRBA is reflected in the TRBA principal balance and flowed through in a subsequent TRBAA. QTR is not credited again, and posting, drawing, or holding Security does not itself produce a credit. The Eligible Customer remains liable for unpaid Large Load Charges, and the CRA’s Security and collection provisions mitigate, but do not eliminate, nonpayment risk. Because the TRBA ensures that DesertLink collects no more and no less than its Base TRR, DesertLink retains none of the TRBAA Credits.22

DesertLink’s annual TRBAA filing is made under FPA section 205 and is noticed by the Commission, open to intervention, comment, and protest, and subject to Commission review and acceptance. DesertLink will include in each filing the calculations, workpapers, and testimony supporting the TRBAA Credits, substantially in the form of Exhibit No. DLK-205, with customer-specific information presented on an aggregated basis or submitted with a request for privileged treatment under 18 C.F.R. § 388.112. No change to Appendix I is required because TRBAA Credits are included in the TRBAA amount stated in Appendix I each year.23

Balances in the TRBA attributable to CRA amounts accrue interest in the same manner as other TRBA balances, because a balance created by a late payment, a non-payment before Security is applied, or the timing of monthly installments reflects an actual over- or under-recovery by

21  TO Tariff §§ 3.60, 3.103, and 5.5; see also Ex. No. DLK-200 (Arzola Testimony).
22  See CRA § 6.8.
23  See id.; Ex. No. DLK-200 (Arzola Testimony).

PDF page 9

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 9

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C DesertLink. By contrast, when further Supplemental MTRC will be invoiced, a prior-period true- up adjustment is added both to the Supplemental MTRC invoiced for a later Rate Year and to the Forecast TRBAA Credit for that same year, so the matched adjustment does not itself create an over- or under-recovery. Consistent with Section 6.6 of the CRA and Section 5.5 of the TO Tariff, no interest accrues on a prior-period true-up adjustment between DesertLink and the Eligible Customer.24

D. Formula Rate Template Revisions and Rate Treatment of Covered Upgrades
DesertLink’s current Formula Rate Template reports plant values only in total and has no means of identifying facilities built to serve Large Loads. The revised Template adds Attachment 1a – Project Plant Detail, which reports gross plant, accumulated depreciation, Construction Work in Progress, unamortized abandoned plant, and net plant separately for the Harry Allen to Eldorado Project and each Covered Upgrade, with totals that tie to Attachment 4 and Appendix III so that total plant and the total revenue requirement are unchanged. Attachment 1 – Project Revenue Requirement Worksheet draws each project’s plant and depreciation from Attachment 1a, with allocation factors unchanged. New Line 17a on Attachment 12 – Revenue Credit Detail removes any TRBAA Credits recorded in revenue accounts, so those amounts are credited to customers once, through the TRBAA, and not also through the Formula Rate. Attachment 1a is also added to the Table of Contents; there are no other changes to the Template. No changes to the Protocols are required because the existing posting, review, challenge, and true-up procedures apply to the new detail.25

Covered Upgrades placed under CAISO’s Operational Control are included in DesertLink’s rate base and Base TRR in the same manner as other DesertLink transmission plant and are subject to the return components reflected in DesertLink’s effective Formula Rate, including any generally applicable Commission-approved return incentive. Covered Upgrades do not receive return-on- equity incentives specific to the Harry Allen to Eldorado Project and are not subject to that project’s Competitive Bid Concession, Binding Cost Cap, or other project-specific cost- containment commitments. Covered Upgrade costs will be separately identified on Attachment 1a and reported as “other costs” in the commitment work paper provided under Attachment A to the Protocols. DesertLink is not requesting a different return on equity or any new incentive in this proceeding.26

E. Supporting Testimony and Illustrative Exhibits
Mr. Patrick Hayes’ testimony (Exhibit No. DLK-100) describes the Show Cause Order, the CAISO stakeholder process, the pro forma CRA, and the associated TO Tariff revisions, and explains how those measures assign cost responsibility for Large Load-Driven Upgrades, mitigate cost shifting

24  See CRA § 6.6; TO Tariff § 5.5.
25  See Ex. Nos. DLK-200 (Arzola Testimony), DLK-201, and DLK-202.
26  See Ex. No. DLK-200 (Arzola Testimony).

PDF page 10

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 10

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C and stranded-asset risk, avoid double recovery, and promote transparency. His supporting exhibits provide an Illustrative MTRC Calculation (Exhibit No. DLK-101), an Example Reconciliation Statement (Exhibit No. DLK-102), and an Example Invoice Statement (Exhibit No. DLK-103). Mr. D. Eric Arzola’s testimony (Exhibit No. DLK-200) explains the crediting of CRA amounts through the TRBAA, the related TO Tariff revisions, and the Formula Rate Template revisions, and explains why no changes are needed to the Protocols or Appendix I. His supporting exhibits include the Clean and Marked Formula Rate Templates (Exhibit Nos. DLK-201 and DLK-202), the Clean Formula Rate Template in native Excel format with all formulas intact (Exhibit No. DLK- 203), an Illustrative Formula Rate Template populated with hypothetical data for the 2030 Rate Year (Exhibit No. DLK-204), and an Illustrative TRBAA Calculation for two consecutive TRBA years (Exhibit No. DLK-205). Using a hypothetical $60 million Covered Upgrade with an Annual MTRC of $7,292,700, projected QTR of $3,363,840, and a Supplemental MTRC of $3,928,860, those exhibits demonstrate that the TRBAA Credits are removed on Attachment 12, Line 17a and returned to customers through the TRBAA, so that they are credited only once.

IV. THE PROPOSED REVISIONS ARE JUST AND REASONABLE
DesertLink’s approach materially mitigates the cost-shifting concern identified in the Show Cause Order. Before in-service, LLIP deposits, Construction Security, and the Pre-In-Service Termination Cost provisions protect against cancellation and related exposure. After an upgrade enters service, the Annual MTRC, Supplemental MTRC, Total Required Revenue Commitment, Required Operational Security, and Termination Fee establish and secure a defined twenty-year revenue responsibility tied to the allocated capital cost of the identified Covered Upgrades. That design responds to the concern that bilateral revenue contributions “untethered from any assessment of the actual cost of providing transmission service induced by individual large loads” may be insufficient to protect other customers against unjustified cost shifts.27

The proposal also supplies the transparency and crediting mechanisms the Commission identified. The CRA Schedules, Annual Projection workpapers, Reconciliation Statements, and Cumulative Revenue Ledger make the upgrade-specific calculations available to the Eligible Customer, which has information rights under CRA Section 6.12 and dispute rights under Article

11. Attachment 1a separately identifies Covered Upgrade plant, and each annual TRBAA filing is an FPA section 205 proceeding in which interested parties may review and challenge the TRBAA Credits. The LLIP further provides for study reports, a Report Meeting addressing study results and assigned cost responsibility, and CAISO posting of FILI Service Agreements. Customer-specific information is protected under Section 16.3 of the TO Tariff, the CAISO Tariff, and, in TRBAA filings, 18 C.F.R. § 388.112.

Crediting CRA amounts through the TRBAA ensures that Large Load payments are credited toward DesertLink’s TRR. The full cost of each Covered Upgrade remains in the Base TRR,

27  Show Cause Order, Comm’r Chang Concurrence at P 8.

PDF page 11

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 11

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C consistent with CAISO’s requirement that facilities under its Operational Control be included in the TRR, while the TRBAA reduces the TRR paid by all customers through the TAC by the amounts received under the CRA. The TRBA ensures that DesertLink collects no more and no less than its Base TRR, and Attachment 12, Line 17a ensures that each dollar is credited only once. The CRA does not alter CAISO cost allocation or the retail arrangements between an Eligible Customer and a Large Load Customer.

Finally, the proposal is appropriately tailored to DesertLink as a non-load-serving PTO. It gives DesertLink a meaningful interconnection and cost-recovery role when a Large Load affects its facilities, even though DesertLink has no retail relationship with the load, and requires evaluation of alternative transmission technologies before traditional network upgrades are selected, consistent with the Commission’s focus on keeping costs at a responsible and accountable level. It does not disturb the Harry Allen to Eldorado Project, DesertLink’s existing revenue requirement, CAISO cost allocation, or CAISO’s study and planning authority.

V. REQUESTED EFFECTIVE DATE AND WAIVERS
DesertLink requests an effective date of January 16, 2027, sixty-one (61) days after the date of this filing, satisfying the Commission’s sixty-day notice requirement.28 DesertLink requests waiver of the cost-of-service-statement requirements of 18 C.F.R. § 35.13, and any other Part 35 requirements that otherwise may apply, to the extent necessary. The requested waivers are appropriate because the filing establishes a prospective interconnection and contractual framework, does not change the cost-of-service inputs or methods of DesertLink’s Formula Rate, and, absent any Covered Upgrade or CRA, produces the same revenue requirement as the currently effective Formula Rate Template.

VI. CONTENTS OF FILING
DesertLink submits the following materials:
• This transmittal letter;
• Attachment 1: Clean version of the DesertLink TO Tariff revisions;
• Attachment 2: Marked version of the DesertLink TO Tariff revisions;
• Attachment 3: Direct testimony of Patrick Hayes (Exhibit No. DLK-100) and supporting exhibits:

o Illustrative MTRC Calculation (Exhibit No. DLK-101),
o Example Reconciliation Statement (Exhibit No. DLK-102), and
o Example Invoice Statement (Exhibit No. DLK-103).

28  18 C.F.R. § 35.3(a)(1).

PDF page 12

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 12

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C
• Attachment 4: Direct testimony of D. Eric Arzola (Exhibit No. DLK-200) and supporting exhibits:

o Clean Formula Rate Template (Exhibit No. DLK-201),
o Marked Formula Rate Template (Exhibit No. DLK-202),
o Clean Formula Rate Template in native Excel format with all formulas intact
(Exhibit No. DLK-203),
o Illustrative Formula Rate Template (Exhibit No. DLK-204), and
o Illustrative TRBAA Calculation (Exhibit No. DLK-205).
VII. COMMUNICATIONS AND SERVICE
DesertLink requests that all pleadings, correspondence, and other communications concerning this matter be directed to the following persons, and that their names and addresses be placed on the official service list for this proceeding: 29

Josh R. Robichaud
Associate
Bracewell LLP
2001 M Street NW, Suite 900
Washington, DC 20036
(202) 828-1731
josh.robichaud@bracewell.com
Blake R. Urban
Senior Regulatory Counsel
LS Power Development, LLC
16150 Main Circle Drive, Suite 310
Chesterfield, MO 63017
(636) 231-0475
burban@lspower.com

Catherine P. McCarthy
Partner
Bracewell LLP
2001 M Street NW, Suite 900
Washington, DC 20036
(202) 828-5839
cathy.mccarthy@bracewell.com
Patrick Hayes
Associate Vice President, Transmission Regulatory
LS Power Development, LLC
16150 Main Circle Drive, Suite 310
Chesterfield, MO 63017
(636) 532-2200
phayes@lspower.com
DesertLink has served a copy of this filing on CAISO, on the service list in Docket No. EL26-71-000, and on parties otherwise entitled to service under the Commission’s regulations.

29 DesertLink respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3), to the extent necessary to permit designation of more than two persons for service on its behalf in this proceeding.

PDF page 13

Hon. Debbie-Anne A. Reese
November 16, 2026
Page 13

A U S T I N   D A L L A S   D U B A I   H O U S T O N   L O N D O N   N E W  Y O R K   P A R I S   S A N  A N T O N I O   S E A T T L E   W A S H I N G T O N ,  D C
VIII. CONCLUSION
For the reasons stated above and in the supporting testimony, DesertLink respectfully requests
that the Commission accept the proposed tariff revisions effective January 16, 2027, and grant
any necessary waivers.
Respectfully submitted,
/s/ Josh R. Robichaud _
Josh R. Robichaud
Catherine P. McCarthy

Counsel to DesertLink, LLC

PDF page 14

Attachment 1

DesertLink TO Tariff Revisions (Clean)

PDF page 15

DesertLink, LLC
Transmission Owner Tariff

Table of Contents
1. Preamble
1.1
Transmission Access for Participating TOs 1.2

Transmission Access for Wheeling Customers 1.3

Transmission Access for End-User
2. Effective Date
2.1
Termination
3. TO Definitions
3.1
Access Charge
3.2
AGC
3.3
Ancillary Services
3.4
Applicable Reliability Criteria
3.5
Available Transfer Capacity
3.6
Base Transmission Revenue Requirement 3.7

Black Start
3.8
Business Day
3.9
Completed Application Date
3.10
Completed Interconnection Application 3.11

Congestion
3.12
Congestion Management
3.13
Converted Rights
3.14
CPUC
3.15
Demand
3.16
DesertLink
3.17
Direct Assignment Facilities
3.18
Dispatch
3.19
Distribution System
3.20
Eligible Customer
3.21
Encumbrance
3.22
End-Use Customer or End-User
3.23
Energy
3.24
Entitlement
3.25
Existing Contracts
3.26
Existing Rights
3.27
Expedited Interconnection Agreement 3.28

Facilities Study Agreement
3.29
Facility or Facilities Study
3.30
FERC
3.31
FPA
3.32
Generating Unit
3.33
Generation
3.34
Good Utility Practice

PDF page 16

3.35
Gross Load
3.36
High Voltage Access Charge
3.37
High Voltage Transmission Facility
3.38
High Voltage Transmission Revenue Requirement 3.39

High Voltage Utility-Specific Rate
3.40
High Voltage Wheeling Access Charge
3.41
Independent System Operator
3.42
ISO ADR Procedures
3.43
ISO Controlled Grid
3.44
ISO Protocols
3.45
ISO Tariff
3.46
Interconnection
3.47
Interconnection Agreement
3.48
Interconnection Application
3.49
Interest
3.50
Load
3.51
Local Publicly Owned Electric Utility
3.52
Local Regulatory Authority
3.53
Local Reliability Criteria
3.54
Low Voltage Access Charge
3.55
Low Voltage Transmission Revenue Requirement 3.56

Low Voltage Wheeling Access Charge
3.57
Market Participant
3.58
Metered Subsystem (“MSS”)
3.59
NERC
3.60
New Participating TO
3.61
Non-Load Serving Participating TO
3.62
Non-Participating TO
3.63
Non-Spinning Reserve
3.64
Operational Control
3.65
Original Participating TO
3.66
Participating TO (“PTO”)
3.67
Participating Agreement
3.68
Physical Scheduling Plant
3.69
Project
3.70
Project Proponent
3.71
Project Sponsor
3.72
Regional Transmission Group (“RTG”)
3.73
Regulation
3.74
Regulatory Authority
3.75
Reliability Criteria
3.76
Reliability Upgrade
3.77
Request for Expedited Interconnection Procedures 3.78

Scheduling Coordinator
3.79
Scheduling Point
3.80
Spinning Reserve

PDF page 17

3.81
System Impact Study
3.82
System Impact Study Agreement
3.83
TO Tariff
3.84
[Not used]
3.85
[Not used]
3.86
Transmission Control Agreement (“TCA”)
3.87
Transmission Owner (“TO”)
3.88
Transmission Revenue Balancing Account Adjustment (“TRBAA”) 3.89

Transmission Revenue Credit
3.90
Transmission Revenue Requirement (“TRR”)
3.91
Transmission System Rights (“TSRs”)
3.92
Uncontrollable Force
3.93
Utility Distribution Company (“UDC”)
3.94
Voltage Support
3.95
Western Electricity Coordinating Council (“WECC”)
3.96
Wheeling Access Charge
3.97
Wheeling Out
3.98
Wheeling Through
3.99
Wheeling
3.100 Wholesale Customer
4. Eligibility
5. Access Charges and Transmission Rates
5.1
Low Voltage Access Charge
5.2
Wheeling Access Charge
5.3
Transmission Revenue Requirement
5.4
Transmission System Rights
5.5
Transmission Revenue Balancing Account Adjustment
6. Ancillary Services - Applicability and Charges
7. Billing and Payment
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades

8.1
Participating TO Obligation to Interconnect
8.2
Participating TO Obligation to Construct Transmission Expansion or Facility Upgrades

8.3
Request for FERC Deference Regarding Need Determination
9. Expansion Process
9.1
Determination of Facilities
9.2
Obligation to Build
9.3
Provisions Relating To Transmission Construction On the Systems of Other TOs

10. TSWL Interconnection Process
10.1
Applicability
10.2
Applications
10.3
Interconnection Application
10.4
Review of Completed Interconnection Application
10.5
Notice of Need for System Impact Study

PDF page 18

10.6
Impact Study Cost Reimbursement Agreement
10.7
System Impact Study Procedures
10.8
Notice of Need for Facilities Study
10.9
Facilities Study Procedures
10.10 Partial Interim Service
10.11 Expedited Interconnection Procedures
10A. Interconnection Process for ECLL Interconnections

10A.1 Applicability

10A.2 ECLL Application and Application Fee

10A.3 Study Process and ECLL Interconnection Agreement

10A.4 Interim Service

10A.5 Co-Located Large Load

10A.6 Large Load Cost Recovery Agreement
11. Uncontrollable Forces and Indemnification 11.1

Procedures to Follow of Uncontrollable Force Occurs 11.2

Indemnification
12. Regulatory Filings
12.1
Open Access
13. Creditworthiness
13.1
UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low Voltage Transmission Facilities

13.2
End-Users
14. Disputes
15. [Reserved]
16. Miscellaneous
16.1
Notices
16.2
Waiver
16.3
Confidentiality
16.4
TO Tariff Supersedes Existing Tariffs
16.5
Titles
16.6
Severability
16.7
Preservation of Obligations
16.8
Governing Law
16.9
Appendices Incorporated
16.10 Conflict with ISO Tariff
16.11 Conflicting Operating Instructions
16.12 Conflict With Transfer Capability Lease

Appendix I
Transmission Revenue Requirement and TRBAA
Appendix II
Notices
Appendix III
Formula Rate
Appendix IV
Formula Rate Implementation Protocols
Appendix V
Pro Forma Large Load Cost Recovery Agreement Appendix VI

Large Load Interconnection Procedures

PDF page 19

3. TO Definitions. Certain capitalized terms used in this TO Tariff shall have the meanings set out below unless otherwise stated or the context otherwise requires. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the ISO Tariff as it may be amended from time to time.

3.1.
Access Charge. A charge paid by all UDCs, MSSs, and, in certain cases, Scheduling Coordinators delivering Energy to Gross Load, as set forth in Section 26.1 of the ISO Tariff. The Access Charge includes the High Voltage Access Charge and the Low Voltage Access Charge, as applicable.

3.2.
AGC. Generation equipment that automatically responds to signals from the ISO’s EMS control in real time to control the power output of electric generators within a prescribed area in response to a change in system frequency, tie-line loading, or the relation of these to each other, so as to maintain the target system frequency and/or the established interchange with other areas within the predetermined limits.

3.3.
Ancillary Services. Regulation, Spinning Reserve, Non-Spinning Reserve, Voltage Support and Black Start together with such other interconnected operation services as the ISO may develop in cooperation with Market Participants to support the transmission of Energy from generation resources to Loads while maintaining reliable operation of the ISO Controlled Grid in accordance with Good Utility Practice.

3.4.
Applicable Reliability Criteria. The Reliability Standards and reliability criteria established by NERC and WECC, and Local Reliability Criteria, as amended from time to time, including any requirement of the Nuclear Regulatory Commission.

3.5.
Available Transfer Capacity. The available capacity of a given transmission path, in MW after allocation of rights associated with Existing Contracts and Transmission Ownership Rights, to that path’s Operating Transfer Capability established consistent with ISO and WECC transmission capacity rating guidelines, as further described in Appendix L to the ISO Tariff.

3.6.
Base Transmission Revenue Requirement. The Transmission Revenue Requirement which does not reflect amounts for the TRBAA.

3.7.
Black Start. The procedure by which a Generating Unit self-starts without an external source of electricity, thereby restoring power to the ISO Controlled Grid following system or local area blackouts.

3.8.
Business Day. Monday through Friday, excluding federal holidays and the day after Thanksgiving Day.

3.9.
Co-Located Large Load. A Large Load that is physically connected to the facilities of an existing or planned Generating Facility on the Interconnection Customer’s side of the Point of Interconnection to the ISO Controlled Grid (each as defined in the ISO Tariff).

PDF page 20

3.10. Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed TSWL or ECLL Interconnection Application.

3.11. Completed ECLL Interconnection Application. An ECLL Interconnection Application that has been deemed valid under Section 4.3 of Appendix VI.

3.12. Completed TSWL Interconnection Application. A TSWL Interconnection Application that satisfies all of the information and other requirements of this TO Tariff and, if applicable, the information requirements as specified by the ISO and posted on the ISO Home Page.

3.13. Congestion. A characteristic of the transmission system produced by a binding Constraint to the optimum economic dispatch to meet Demand such that the LMP, exclusive of Marginal Cost of Losses, at different Locations of the transmission system is not equal.

3.14. Congestion Management. The alleviation of Congestion in accordance with applicable ISO Protocols and Good Utility Practice.

3.15. Converted Rights. Those transmission service rights determined in accordance with Section 4.3.1.6 of the ISO Tariff.

3.16. Cost Recovery Agreement. An agreement between the Participating TO and an Eligible Customer, including an ECLL, substantially in the form of the pro forma Large Load Cost Recovery Agreement set forth in Appendix V, entered into pursuant to Section 10.9 or Section 10A.6 of this TO Tariff.

3.17. CPUC. The California Public Utilities Commission or its successor.

3.18. Demand. The rates at which Energy is delivered to Load and Scheduling Points by Generation, transmission or distribution facilities. It is the product of voltage and the in- phase component of alternating current measured in units of watts or standard multiples therefore, e.g. 1000 W = 1 kW, 1000 kW= 1 MW, etc.

3.19. DesertLink, LLC (“DesertLink”). The Delaware limited liability company that is the Participating TO under this TO Tariff.

3.20. Direct Assignment Facilities. Facilities or portions of facilities that are owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting a TSWL Interconnection under this TO Tariff to the ISO Controlled Grid at the point of interconnection. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs TSWL Interconnection service to such party and shall be subject to FERC approval.

PDF page 21

3.21. Dispatch. The operating control of an integrated electric system to: i) assign specific Generation Units and other sources of supply to effect the supply to meet the relevant area Demand taken as Load rises or falls; ii) control operations and maintenance of high voltage lines, substations, and equipment, including administration of safety procedures;

iii) operate Interconnections; iv) manage Energy transactions with other interconnected Control Areas; and v) curtail Demand.

3.22. Distribution System. The distribution assets of a TO, UDC, or MSS.

3.23. Eligible Customer. (i) Any utility (including any Participating TO, Market Participant or power marketer), Federal power marketing agency, or any person generating Energy for sale or resale; Energy sold or produced by such entity may be Energy produced in the United States, Canada or Mexico; however, such entity is not eligible for transmission service that would be prohibited by FPA Section 212(h)(2); and (ii) any retail customer taking unbundled transmission service pursuant to a state retail access program or pursuant to a voluntary offer of unbundled retail transmissions service by the Participating TO.

3.24. Eligible Customer for Large Load (“ECLL”). A UDC or MSS that provides retail transmission and interconnection service to Large Load End-Users in the ISO’s Balancing Authority Area.

3.25. ECLL Interconnection Agreement. The agreement between an ECLL and the Participating TO governing an ECLL Interconnection.

3.26. ECLL Interconnection. The interconnection of the facilities of an ECLL to the facilities of the Participating TO that are for the purpose of an ECLL interconnecting and providing transmission service to a Large Load Customer.

3.27. ECLL Interconnection Application. An application that requests an ECLL Interconnection to the ISO Controlled Grid.

3.28. ECLL Interconnection Facilities. The facilities, additions, and upgrades of the Participating TO necessary to accomplish an ECLL Interconnection, as identified in the applicable ECLL Interconnection Agreement.

3.29. Encumbrance. A legal restriction or covenant binding on the Participating TO that affects the operation of any transmission lines or associated facilities and which the ISO needs to take into account in exercising Operational Control over such transmission lines or associated facilities if the Participating TO is not to risk incurring significant liability. Encumbrances shall include Existing Contracts and may include: (1) other local restrictions or covenants meeting the definition of Encumbrance and arising under other arrangements entered into before the ISO Operations Date, if any; and (2) legal restrictions or covenants meeting the definition of Encumbrance and arising under a contract or other arrangement entered into after the ISO Operations Date.

PDF page 22

3.30. End-Use Customer or End-User. A purchaser of electric power that purchases such power to satisfy a Load directly connected to the ISO Controlled Grid or to a Distribution System and who does not resell the power.

3.31. Energy. The electrical energy produced, flowing, or supplied by Generation, transmission, or distribution facilities, being the integral with respect to time of the instantaneous power, measured in units of watt-hours or standard multiples thereof. 3.31.1.1.

E.g. 1000 Wh = 1 kW, 1000 kWh = 1 MWh, etc.

3.32. Entitlement. The right of a Participating TO obtained through contract or other means to use another entity’s transmission facilities for the transmission of Energy.

3.33. Existing Contracts. Those transmission service agreements or other contracts which grant transmission service rights in existence on the ISO Operations Date (including any contracts entered into pursuant to such contracts) as may be amended in accordance with their terms or by agreement between the parties thereto from time to time.

3.34. Existing Rights. Those transmission service rights defined in Section 16.1 of the ISO Tariff.

3.35. Expedited Interconnection Agreement. A contract between a party which has submitted a Request for Expedited Interconnection Procedures and the Participating TO under which the Participating TO agrees to process, on an expedited basis, the Completed Interconnection Application of such party and which sets forth the terms, conditions, and cost responsibilities for such Interconnection.

3.36. Facilities Study Agreement. An agreement between a Participating TO and either a party requesting Interconnection to the ISO Controlled Grid, Market Participants, Project Sponsor, ECLL, or identified principal beneficiaries pursuant to which the party requesting such Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a Facilities Study.

3.37. Facility or Facilities Study. An engineering study conducted to determine required modifications to the Participating TO’s transmission system, including the estimated cost and scheduled completion date for such modifications, that will be required to provide needed services.

3.38. FERC. The Federal Energy Regulatory Commission, or its successor.

3.39. Firm Interconnection Service. The highest quality (priority) load Interconnection service that provides the on-going safe and reliable operation and maintenance of, and the Parties’ rights and responsibilities associated with their facilities.

3.40. Flexible Interim Load Interconnection (“FILI”) Service. A transmission interconnection service offered by the Participating TO and accepted by an Eligible Customer on behalf of a Large Load retail customer to manage operational constraints on

PDF page 23

withdrawals from the transmission system while the interconnection and system upgrades necessary to provide Firm Interconnection Service are being developed.

3.41. FILI Service Agreement. The agreement developed by the Participating TO pursuant to Section 10A.4 that sets forth the terms, conditions, and operating requirements for FILI Service.

3.42. FPA. The Federal Power Act, 16 U.S.C.§ 791a et seq., as it may be amended from time to time.

3.43. Generating Facility. An Interconnection Customer’s Generating Unit(s) used for the production and/or storage for later injection of electricity identified in the Interconnection Request, but shall not include the Interconnection Customer’s Interconnection Facilities.

3.44. Generating Unit. An individual electric generator and its associated plant and apparatus whose electrical output is capable of being separately identified and metered or a Physical Scheduling Plant, that, in either case, is: (a) located within the ISO Control Area; (b) connected to the ISO Controlled Grid, either directly or via interconnected transmission or distribution facilities; and (c) that is capable of producing and delivering net Energy (Energy in excess of a generation stations’ internal power requirements).

3.45. Generation. Energy delivered from a Generating Unit.

3.46. Generator Interconnection. The interconnection of one or more Generating Units to the ISO Controlled Grid facilities owned by the Participating TO.

3.47. Good Utility Practice. Any of the practices, methods, and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods, and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety, and expedition.

3.48. Gross Load. For purposes of calculating the transmission Access Charge, Gross Load is all Energy (adjusted for distribution losses) delivered for the supply of End-Use Customer Loads directly connected to the transmission facilities or directly connected to the Distribution System of a Utility Distribution Company or MSS Operator located in a PTO Service Territory. Gross Load shall exclude (1) Load with respect to which the Wheeling Access Charge is payable, (2) Load that is exempt from the Access Charge pursuant to Section 4.1, Appendix I of the ISO Tariff, and the portion of the load of an individual retail customer of a Utility Distribution Company, Small Utility Distribution Company or MSS Operator that is served by a Generating Unit that: (a) is located on the customer’s site or provides service to the customer’s site through over-the-fence arrangements as authorized by Section 218 of the California Public Utilities Code; (b) is a qualifying small power production facility or qualifying cogeneration facility, as those

PDF page 24

terms are defined in the FERC’s regulations implementing Section 201 of the Public Utility Regulatory Policies Act of 1978; and (c) secures Standby Service from the Participating TO under terms approved by a Local Regulatory Authority or FERC, as applicable, or can be curtailed concurrently with an Outage of the Generating Unit serving the Load. Gross Load forecasts consistent with filed Transmission Revenue Requirements will be provided by each Participating TO to the ISO.

3.49. High Voltage Access Charge. A component of the Access Charge determined by the ISO under Section 26.1 of the ISO Tariff.

3.50. High Voltage Transmission Facility. A transmission facility under the Operational Control of the ISO that is owned by the Participating TO or to which the Participating TO has an Entitlement that may be associated with a Converted Right, which operates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs of which are not directly assigned to one or more specific customers.

3.51. High Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s High Voltage Transmission Facilities and Rights associated with High Voltage Transmission Facilities 3.52. High Voltage Utility-Specific Rate. The Participating TO’s High Voltage Transmission Revenue Requirement divided by the Participating TO’s forecast of its Gross Load.

3.53. High Voltage Wheeling Access Charge. The Wheeling Access Charge assessed by the ISO associated with the recovery of the Participating TO’s High Voltage Transmission Revenue Requirement in accordance with Section 26.1 of the ISO Tariff.

3.54. Independent System Operator (“ISO”). The California Independent System Operator Corporation, a state chartered, nonprofit corporation that controls the transmission facilities of all Participating TOs and dispatches certain Generating Units and Loads. 3.55. ISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13 of the ISO Tariff, as amended from time to time.

3.56. ISO Controlled Grid. The system of transmission lines and associated facilities of the Participating TOs that have been placed under the ISO’s Operational Control.

3.57. ISO Protocols. The rules, protocols, procedures and standards promulgated by the ISO (as amended from time to time) to be complied with by the ISO Scheduling Coordinators, Participating TOs and all other Market Participants in relation to the operation of the ISO Controlled Grid and the participation in the markets for Energy and Ancillary Services in accordance with the ISO Tariff.

3.58. ISO Tariff. The California Independent System Operator Agreement and Tariff, dated November 1, 2013, as it may be modified from time to time.

3.59. Interconnection Agreement. A contract between a party requesting a TSWL

PDF page 25

Interconnection and  a Participating TO, as it may be amended from time to time, and, for an ECLL Interconnection, the ECLL Interconnection Agreement.

3.60. Interest. Interest shall be calculated in accordance with the methodology specified for interest on refunds in the regulations of FERC at 18 C.F.R. § 35.19a. Interest on delinquent amounts shall be calculated from the due date of the bill to the date of payment. When payments are made by mail, bills shall be considered as having been paid on the date of receipt. Notwithstanding the foregoing, interest, if any, on amounts payable or refundable between the Participating TO and a party to a Cost Recovery Agreement shall be governed solely by that Cost Recovery Agreement.

3.61. Interim Firm Interconnection Service. Interconnection service that can be provided, if any, on a firm basis prior to the completion of the ECLL Interconnection Facilities and an authorization for the Large Load to withdraw Energy.

3.62. Large Load. An End-User located at a single site behind one or more Point(s) of Withdrawal from the ISO Controlled Grid and that has a peak load of 50 MW or greater.

3.63. Load. An end-use device of an End-Use Customer that consumes power. Load should not be confused with Demand, which is the measure of power that a Load receives or requires.

3.64. Local Publicly Owned Electric Utility. A municipality or municipal corporation operating as a public utility furnishing electric service, a municipal district furnishing electric services, or a joint powers authority that includes one or more of these agencies and that owns Generation or transmission facilities, or furnishes electric services over its own or its members’ electric Distribution System.

3.65. Local Regulatory Authority. The state or local governmental authority responsible for the regulation or oversight of a utility.

3.66. Local Reliability Criteria. Reliability criteria established by the ISO, unique to the transmission systems of each of the Participating TOs, as they may be updated from time to time.

3.67. Low Voltage Access Charge. The Access Charge applicable under Section 26.1 of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement of the Participating TO.

3.68. Low Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s Low Voltage Transmission Facilities and Converted Rights associated with Low Voltage Transmission Facilities.

3.69. Low Voltage Wheeling Access Charge. The Wheeling Access Charge associated with the recovery of the Participating TO’s Low Voltage Transmission Revenue Requirement

PDF page 26

in accordance with Section 26.1 of the 1SO Tariff.

3.70. Market Participant. An entity, including a Scheduling Coordinator, who participates in the Energy marketplace through the buying, selling, transmission, or distribution of Energy or Ancillary Services into, out of, or through the ISO Controlled Grid.

3.71. Metered Subsystem (“MSS”). A geographically contiguous system, located within a single zone which has been operating as an electric utility for a number of years prior to the ISO Operations Date as a municipal utility, water district, irrigation district, state agency or federal power marketing authority subsumed within the ISO Balancing Authority Area and encompassed by ISO certified revenue quality meters at each interface point with the ISO Controlled Grid and ISO-certified revenue quality meters on all Generating Units or, if aggregated, each individual resource and Participating Load, Reliability Demand Response Resource, and Proxy Demand Resource internal to the system, which is operated in accordance with a MSS agreement described in Section 4.9.1 of the ISO Tariff.

3.72. NERC. The North American Electric Reliability Corporation or its successor.

3.73. New Participating TO. A Participating TO that is not an Original Participating TO.

3.74. Non-Load-Serving Participating TO. A Participating TO that does not serve Load.

3.75. Non-Participating TO. A TO that is not a party to the TCA or, for the purpose of Section 16.1 of the ISO Tariff, the holder of transmission service rights under an Existing Contract that is not a Participating TO.

3.76. Non-Spinning Reserve. The portion of off-line generating capacity that is capable of being synchronized and ramping to a specified load in ten minutes (or load that is capable of being interrupted in ten minutes) and that is capable of running (or being interrupted) for at least two hours.

3.77. Operational Control. The rights of the ISO under the Transmission Control Agreement and the ISO Tariff to direct Participating TOs how to operate their transmission lines and facilities and other electric plant affecting the reliability of those lines and facilities for the purpose of affording comparable nondiscriminatory transmission access and meeting Applicable Reliability Criteria.

3.78. Original Participating TO. A Participating TO that was a Participating TO as of January 1, 2000. The Original Participating TOs are Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company. 3.79. Participating TO (“PTO”). A party to the TCA whose application under Section 2.2 of the TCA has been accepted and who has placed, or expects to place, its transmission assets and/or Entitlements under the ISO’s Operational Control in accordance with the TCA. A PTO may be an Original Participating TO or a New Participating TO. For the purposes of this Tariff, the Participating TO is DesertLink.

PDF page 27

3.80. Participation Agreement. An agreement between a Participating TO and a Project Sponsor that specifies the terms and conditions under which the Participating TO will construct a transmission addition or upgrade on behalf of the Project Sponsor. 3.81. Physical Scheduling Plant. A group of two or more related Generating Units each of which is individually capable of producing Energy, but which either by physical necessity or operational design must be operated as if they were a single Generating Unit and any Generating Unit or Units containing related multiple generating components which meet one or more of the following criteria: (i) multiple generating components are related by a common flow of fuel which cannot be interrupted without substantial loss of efficiency of the combined output of all components; (ii) the Energy production from one component necessarily causes Energy production from other components; (iii) the operational arrangement of related multiple generating components determines the overall physical efficiency of the combined output of all components; (iv) the level of coordination required to schedule individual generating components would cause the ISO to incur scheduling costs far in excess of the benefits of having scheduled such individual components separately; or (v) metered output is available only for the combined output of related multiple generation components and separate generating component metering is either impractical or economically inefficient.

3.82. Point of Withdrawal. Point(s) within the ISO Balancing Authority Area, or for purposes of scheduling and operating the Day Ahead Market only, the EDAM Area where Energy and Ancillary Services are made available to a receiving party under the ISO Tariff, for purposes of scheduling and operating the Real-Time Market only, the EIM Area where Energy and Ancillary Services are made available to a receiving party under the ISO Tariff, or for purposes of the definition of Large Load only, the point(s) where a non- transmission facility that is used to withdraw Energy from the ISO Controlled Grid to serve an End-User connects to the ISO Controlled Grid.

3.83. Project. DesertLink’s interest in the single-circuit 500 kV (AC) overhead transmission line connecting the existing Harry Allen Substation in Nevada to the existing Eldorado Substation in Nevada, including series compensation. For the avoidance of doubt, the Project does not include any required work within the fence line of each substation.

3.84. Project Proponent. A Market Participant or group of Market Participants that (i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition or upgrade, and thus is not a Project Sponsor; and (iii) initiates proceedings under the ISO ADR Procedures to determine the need for the proposed transmission addition or upgrade.

3.85. Project Sponsor. A Market Participant or group of Market Participants or a Participating TO that proposes the construction of a transmission addition or upgrade in accordance with Section 24 of the ISO Tariff.

3.86. Regional Transmission Group (“RTG”). A voluntary organization approved by FERC

PDF page 28

and composed of transmission owners, transmission users, and other entities, organized to efficiently coordinate the planning, expansion, and use of transmission on a regional and inter-regional basis.

3.87. Regulation. The service provided either by Generating Units certified by the ISO as equipped and capable of responding to the ISO’s direct digital control (AGC) signals, or by System Resources that have been certified by the ISO as capable of delivering such service to the ISO Balancing Authority Area, in an upward and downward direction to match, on a Real Time basis, Demand and resources, consistent with established NERC and WECC reliability standards, including any requirements of the Nuclear Regulatory Commission. Regulation is used to control the Power output of electric generators within a prescribed area in response to a change in system frequency, tie-line loading, or the relation of these to each other so as to maintain the target system frequency and/or the established interchange with other Balancing Authority Areas within the predetermined Regulation Limits. Regulation includes both the increase of output by a Generating unit or System Resource (Regulation Up) and the decrease in output by a Generating unit or System Resource (Regulation Down). Regulation Up and Regulation Down are distinct capacity products, with separately stated requirements and ASMPs in each Settlement Period.

3.88. Regulatory Authority. The Federal Energy Regulatory Commission.

3.89. Reliability Criteria. Pre-established criteria that are to be followed in order to maintain desired performance of the ISO Controlled Grid under contingency or steady state conditions.

3.90. Reliability Upgrade. The transmission facilities, other than Direct Assignment Facilities, beyond the first point of Interconnection necessary to accomplish a TSWL Interconnection safely and reliably to the ISO Controlled Grid, which would not have been necessary but for the TSWL Interconnection, including network upgrades necessary to remedy short circuit or stability problems resulting from the TSWL Interconnection. Reliability Upgrades also include, consistent with WECC practice, the facilities necessary to mitigate any adverse impact a TSWL Interconnection may have on a path’s WECC path rating. Reliability Upgrades shall be specified in the Interconnection Agreement that governs a TSWL Interconnection and shall be subject to FERC approval.

3.91. Requests for Expedited Interconnection Procedures. A written request by which an applicant for Interconnection can request expedited processing of its TSWL Interconnection Application.

3.92. Scheduling Coordinator. An entity certified by the ISO for the purpose of undertaking the functions specified in Section 4.5 of the ISO Tariff.

3.93. Scheduling Point. A location at which the ISO Controlled Grid or a transmission facility owned by a Transmission Ownership Right holder is connected, by a group of transmission paths for which a physical, non-simultaneous transmission capacity rating

PDF page 29

has been established for Congestion Management, to transmission facilities that are outside the ISO’s Operational Control.

3.94. Site Control. An ECLL may demonstrate that its Large Load Customer has Site Control by:

an option for a lease or an executed lease for real property of sufficient size to house the Large Load; or

an option to purchase or title to real property of sufficient size to house the Large Load.

3.95. Spinning Reserve. The portion of unloaded synchronized generating capacity that is immediately responsive to system frequency and that is capable of being loaded in ten minutes, and that is capable of running for at least two hours.

3.96. System Impact Study. An engineering study conducted to determine whether a request for Interconnection to the ISO Controlled Grid would require new transmission additions, upgrades, or other mitigation measures.

3.97. System Impact Study Agreement. An agreement between a Participating TO and an entity that has requested Interconnection to the Participating TO’s transmission system pursuant to which the entity requesting Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a System Impact Study.

3.98. TO Tariff. This Transmission Owner Tariff, as it may be amended or superseded.

3.99. [Reserved].
3.100. [Reserved].
3.101. Transmission Control Agreement (“TCA”). The agreement between the ISO and Participating TOs establishing the terms and conditions under which TOs will become Participating TOs and how the ISO and each Participating TO will discharge its respective duties and responsibilities, as may be modified from time to time.

3.102. Transmission Owner (“TO”). An entity owning transmission facilities or having firm contractual rights to use transmission facilities.

3.103. Transmission Revenue Balancing Account Adjustment (“TRBAA”). A mechanism established by the Participating TO which will ensure that all Transmission Revenue Credits and other credits specified in Section 6 and 8 of Appendix F, Schedule 3 of the ISO Tariff, and all amounts that a Cost Recovery Agreement requires to be credited through the TRBAA, flow through to ISO Tariff and TO Tariff transmission customers.

3.104. Transmission Revenue Credit. The proceeds received from the ISO (other than for the recovery of the Participating TO’s High Voltage and Low Voltage Transmission Revenue Requirement through the High Voltage and Low Voltage Transmission Access Charges) and charges imposed by the ISO that are received and paid by the Participating TO in its

PDF page 30

role as Participating TO, as defined in the ISO Tariff.
3.105. Transmission Revenue Requirement (“TRR’). The total annual authorized revenue requirement associated with transmission facilities and Entitlements turned over to the Operational Control of the ISO by the Participating TO. The costs of any transmission facility turned over to the Operational Control of the ISO shall be fully included in the Participating TO’s TRR. The TRR includes the costs of transmission facilities and Entitlements and deducts Transmission Revenue Credits and is shown in Appendix I.

3.106. Transmission System Rights (“TSRs”). TSRs represent DesertLink’s exclusive transmission entitlement on its share of the Project. DesertLink, as the holder of the TSRs, is entitled to all associated rights as are available under the ISO Tariff and Protocols. The use of this definition does not limit DesertLink from seeking any additional revenues or rights that are authorized by FERC due to a beneficial increase in the ISO controlled grid capacity resulting from the Project.

3.107. Transmission System Wholesale Load (“TSWL”) Interconnection. The
interconnection of the transmission facilities of the Participating TO to the transmission facilities of a Transmission Owner, electric utility, or other entity eligible to request interconnection. A TSWL Interconnection does not include a Generator Interconnection or an ECLL Interconnection.

3.108. TSWL Interconnection Application. An application that requests a TSWL Interconnection to the ISO Controlled Grid, including any modifications to existing points of interconnection.

3.109. Uncontrollable Force. Any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities or any other cause beyond the reasonable control of the ISO or Market Participant, as the case may be, which could not be avoided through the exercise of Good Utility Practice.

3.110. Utility Distribution Company (“UDC”). An entity that owns a Distribution System for the delivery of Energy to and from the ISO Controlled Grid, and/or that provides regulated retail electric service to End-Users.

3.111. Voltage Support. Services provided by Generating Units or other equipment such- as shunt capacitors, static vat compensators, or synchronous condensers that are required to maintain established grid voltage criteria. This service is required under normal or system emergency conditions.

3.112. Western Electricity Coordinating Council (“WECC”). The Western Electricity Coordinating Counsel or its successor.

3.113. Wheeling Access Charge. The charge assessed by the ISO that is paid by a Scheduling Coordinator for Wheeling in accordance with Section 26.1.4.1 of the ISO Tariff.

PDF page 31

Wheeling Access Charges shall not apply for Wheeling under a bundled non-economy Energy coordination agreement of a Participating TO executed prior to July 9, 1996. The Wheeling Access Charge consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge.

3.114. Wheeling Out. Except for Existing Rights exercised under an Existing Contract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a Generating Unit located within the ISO Controlled Grid to serve a Load located outside the transmission and Distribution System of a Participating TO.

3.115. Wheeling Through. Except for Existing Rights exercised under an Existing Contract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a resource located outside the ISO Controlled Grid to serve a Load located outside the transmission and Distribution System of a Participating TO. 3.116. Wheeling. Wheeling Out or Wheeling Through.

3.117. Wholesale Customer. A person wishing to purchase Energy and Ancillary Services at a Bulk Supply Point or a Scheduling Point for resale.

PDF page 32

4. Eligibility for Service. Transmission service over a Participating TO’s system shall be provided only to Eligible Customers for transmission service under the ISO Tariff. Any dispute as to whether an entity that resells power is eligible for an interconnection under this TO Tariff shall be resolved by the FERC. Any dispute as to whether an End-User is eligible for an interconnection under this TO Tariff will be resolved by the Local Regulatory Authority.

PDF page 33

5. Access Charges and Transmission Rates. The applicable Access Charges are provided in the ISO Tariff.

5.1
Low Voltage Access Charge. The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff. As DesertLink is a Non-Load- Serving Participant TO, the ISO shall charge for and collect the Low Voltage Access Charge on DesertLink’s behalf pursuant to Section 26.1 and Appendix F, Schedule 3, Section 13 of the ISO Tariff from the Participating TO to whose facilities DesertLink’s Low Voltage Transmission Facilities are directly connected. The rate for DesertLink’s Low Voltage Access Charge Shall be DesertLink’s Low Voltage Transmission Revenue Requirement divided by the forecasted Gross Load of the Participating TO that is the Low Voltage Access Charge customer. The Low Voltage Access Charge customer shall pay the ISO a Low Voltage Access Charge equal to the product of DesertLink’s Low Voltage Access Charge rate and the actual Gross Load of the Participating TO that is the Low Voltage Access Charge Customer.

5.2
Wheeling Access Charge. The Wheeling Access Charge shall be determined in accordance with the ISO Tariff. The Wheeling Access Charge assessed by the ISO consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge. The High Voltage Wheeling Access Charge is set forth in the ISO Tariff.

5.3
Transmission Revenue Requirement. As set forth in the ISO Tariff, the Transmission Revenue Requirement for each Participating TO is used to develop the Access Charges set forth in the ISO Tariff and is used by the ISO to calculate the disbursement of Wheeling revenues among Participating TOs. Wheeling revenues are disbursed by the ISO to Participating TOs pursuant to Section 26.1.4.3 of the ISO Tariff. DesertLink’s TRR is set forth in Appendix I.

5.4
Transmission System Rights. DesertLink owns the TSRs with respect to the Project consistent with its ownership percentage of the Project and owns the TSRs with respect to any subsequent project it develops.

5.5
Transmission Revenue Balancing Account Adjustment (“TRBAA”). The
Participating TO shall maintain a Transmission Revenue Balancing Account with an annual TRBAA that will ensure that all Transmission Revenue Credits and adjustments for any over-or under-recovery of its annual Transmission Revenue Requirement, if any, specified in Sections 6, 8 and 13 of Appendix F, Schedule 3 of the ISO Tariff, flow through to transmission customers. The TRBAA used to calculate the High Voltage Revenue Requirement shall include other adjustments specified in Appendix F, Schedule 3, Sections 6, 8 and 13 of the ISO Tariff. The TRBAA shall also ensure that all amounts that a Cost Recovery Agreement requires to be credited to transmission customers through the TRBAA flow through to transmission customers.

PDF page 34

The TRBAA shall be equal to:
TRBAA = Cr + Cf + I
Where:

Cr =
The principal balance in the Transmission Revenue Balancing Account (“TRBA”) recorded in FERC Account No. 254 as of September 30 of the year prior to commencement of the January billing cycle. This balance represents the unamortized balance in the TRBA from the previous period and the difference in the amount of revenues or expenditures from Transmission Revenue Credits, amounts recorded in the TRBA under any Cost Recovery Agreement, and any over- or under-recovery of its annual Transmission Revenue Requirement and the amount of such revenues or expenditures that has been refunded to or collected from customers through operation of the TRBAA;

Cf =
The forecast of Transmission Revenue Credits, if any, for the following calendar year, plus any forecast credit that a Cost Recovery Agreement requires to be included in the TRBAA for the following calendar year;

I =
The interest balance for the TRBA, which shall be calculated using the interest rate pursuant to Section 35.19a of FERC’s regulations under the Federal Power Act (18 CFR Section 35.19a). Interest shall be calculated based on the average TRBA principal balance each month, compounded quarterly. Amounts recorded in the TRBA under any Cost Recovery

Agreement shall be included in the TRBA principal balance for purposes of this calculation. Nothing in this Section 5.5 requires the payment of interest between the Participating TO and a party to a Cost Recovery Agreement on amounts payable or refundable under that agreement, which shall be governed solely by the terms of the Cost Recovery

Agreement; and

The DesertLink TRBAA, calculated in accordance with the ISO Tariff and approved by the FERC, is stated in Appendix I.

PDF page 35

8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades. Unless DesertLink is the lead Participating TO with respect to an Interconnection, the provisions of Section 8 of this TO Tariff, and its subparts, shall have no application to the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink, and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern.

8.1
Participating TO Obligation to Interconnect. The Participating TO shall, at the request of a third party, interconnect its system to the wholesale generation or Load of such third party, or modify an existing wholesale Interconnection. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the FPA. The procedures for the Interconnections of Load to the ISO Controlled Grid shall be governed by this TO Tariff and the ISO Tariff. The procedures for Interconnection of wholesale generation to the ISO Controlled Grid shall be governed by the ISO Tariff.

8.1.1 Interconnection to Transmission System. Any interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, and ISO reliability criteria for the ISO Controlled Grid. The Participating TO will not accommodate the interconnection if doing so would impair systems reliability, or would otherwise impair the ability of the Participating TO to honor its Encumbrances existing as of the time an entity submits its interconnection application. The Participating TO shall identify any such adverse effect on its Encumbrances in the interconnection studies. To the extent the Participating TO determines that the interconnection will have an adverse effect on Encumbrances, the party requesting interconnection shall mitigate such adverse effect.

8.1.1.1 Letter Agreement for Generator Interconnections. Pursuant to Section 12 of Appendix DD or KK of the ISO Tariff, prior to executing a Generator Interconnection Agreement, a party seeking a Generator Interconnection may, in order to advance the implementation of its Interconnection, request, and the Participating TO shall offer the party, a Letter Agreement that authorizes the Participating TO to begin engineering, design, and procurement of long lead-time items, or construction necessary for the establishment of the Generator Interconnection. However, the Participating TO shall not be obligated to offer a Letter Agreement if the party seeking Generator

Interconnection is in Dispute Resolution as a result of an allegation that the party seeking Interconnection has failed to meet any milestones or comply with any prerequisites specified in the ISO Tariff. The Letter Agreement is an optional procedure. The Letter

PDF page 36

Agreement shall provide for the party seeking Generator
Interconnection to pay the cost of all activities authorized by the party and to make advance payments or provide other satisfactory security for such costs.

Following a party seeking Interconnection’s request for a Letter Agreement, the Participating TO shall prepare and tender to the party seeking Interconnection a draft Letter Agreement, including draft exhibits that include the proposed scope of work, estimated costs, payments, financial security and milestones, as applicable. The party seeking Generator Interconnection shall provide written comments, or notification of no comments, to the draft exhibits within thirty (30) Calendar Days. The Participating TO and the party seeking Interconnection shall negotiate concerning any disputed provisions of the exhibits to the draft Letter Agreement for not more than ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Generator Interconnection. If the party seeking Interconnection determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the draft Letter Agreement and request submission of the unexecuted Letter Agreement with FERC or initiate dispute resolution procedures pursuant to Section 14 of this TO Tariff. If the party seeking Generator Interconnection requests termination of the negotiations, but within ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Interconnection, fails to request either the filing of the unexecuted Letter Agreement or initiate dispute resolution procedures, it shall be deemed to have withdrawn its request for a Letter Agreement and the Participating TO shall have no further obligation to enter into a Letter Agreement, unless an extension is mutually agreed to by the parties. The Participating TO shall provide to the party seeking Interconnection a final Letter Agreement within fifteen (15) Business Days after the completion of the negotiation process.

Following submission of the final Letter Agreement to the party seeking Generator Interconnection, the party shall either: (i) execute two originals of the tendered Letter Agreement and return them to the Participating TO; or (ii) request in writing that the Participating TO file with FERC a Letter Agreement in unexecuted form. As soon as practicable, but not later than ten (10) Business Days after receiving either the two executed originals of the tendered Letter Agreement or the request to file an unexecuted Letter Agreement, the Participating TO shall file the Letter Agreement with FERC, together with its explanation of any matters as to which the party seeking Interconnection and the Participating TO disagree and support for the costs that the Participating TO proposes to charge to the party seeking

PDF page 37

Generator Interconnection under the Letter Agreement. An unexecuted Letter Agreement should contain terms and conditions deemed appropriate by the Participating TO for the Generator Interconnection request.

If the party seeking Interconnection executes the final Letter Agreement, the Participating TO and the party seeking Generator Interconnection shall perform their respective obligations in accordance with the terms of the Letter Agreement, subject to modification by FERC. Upon submission of an unexecuted Letter Agreement, the party seeking Generator Interconnection and the Participating TO shall promptly comply with the unexecuted Letter Agreement, subject to modification by FERC.

8.1.2 Costs Associated with Interconnection. Each party requesting Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities and, if applicable, any Reliability Upgrades required to provide the requested Interconnection. In addition, such party shall implement all existing operating procedures necessary to safely and reliability interconnect such party’s generation or wholesale load to the facilities of the Participating TO and to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the ISO Tariff for transmission expansions or upgrades.

8.1.3 Interconnection Agreement. Interconnection Agreements shall be tendered, executed, and filed as provided in Sections 10.9 and 10A.3.

8.1.4 Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Reliability Upgrades that it is obligated to construct pursuant to this TO Tariff and Section 24 of the ISO Tariff. The Participating TO’s obligation to build will be subject to: (1) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (2) the presence of a cost recovery mechanism with cost responsibility assigned to accordance with the ISO Tariff or applicable FERC precedent; and

(3) a signed Interconnection Agreement or a signed Expedited Interconnection Agreement, or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection Agreement.

8.1.5 Energization. The Participating TO shall not be obligated to energize,

PDF page 38

nor shall the applicant or wholesale load be entitled to have its interconnection to the ISO Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3, and become effective and such applicant or wholesale load has demonstrated to the ISO’s reasonable satisfaction that it has complied with all of the requirements of the ISO Tariff and the requirements of this TO Tariff.

8.1.6 Coordination with ISO on Interconnection Requests. The Participating TO shall coordinate with the ISO, pursuant to the provisions of the TCA, in developing interconnection standards and guidelines for processing interconnection request under this TO Tariff.

8.2
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to: (1) perform System Impact or Facility Studies where the Project Sponsor or the ISO agrees to pay the study cost and specifies the project objectives to be achieved, and (2) build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations under Section 24 of the ISO Tariff’ and this TO Tariff.

8.2.1 Obligation to Construct. A Participating TO shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.2.1 hereof have been satisfied.

8.3
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the ISO, (including the ISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated planning processes as to the need for or construction of a facility, the need for full cost recovery, end the allocation of costs.

PDF page 39

9. Participating TO Process for Construction or Expansion of Transmission Facilities. Unless DesertLink is the lead Participating TO with respect to a required system expansion, the provisions of Section 9 of this TO Tariff, and its subparts, shall have no application to the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern.

9.1
Applicability and Determination of Facilities. A Participating TO shall perform a Facilities Study in accordance with the Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 of the ISO Tariff and this TO Tariff (other than if the obligation to expand or construct is pursuant to Section 10 or 10A of this TO Tariff or the ISO’s generator interconnection procedures); (2) a Market Participant agrees to pay the costs of the Facilities Study and specifies the project objectives to be achieved in terms of increase capacity or reduce congestion; or (3) the Participating TO is required to perform a Facilities Study pursuant to the ISO Tariff.

9.1.1 Payment of Facilities Study’s Cost.
9.1.1.1 Market Participant to Pay for Facilities Study. Where a Market Participant requests a Facilities Study and the need for the transmission addition or upgrade has not been established in accordance with the procedures established herein and the ISO Tariff, the Market Participant shall pay the cost of the Facilities Study.

9.1.1.2 Project Sponsor or Project Proponent to Pay for Facility Study. Where the facilities to be added or upgraded have been determined to be needed in accordance with the procedures

established herein, the Project Sponsor, Project Proponent, or the ISO requesting the study shall pay in advance the reasonable

cost of the Facilities Study. When the Participating TO is the Project Sponsor in accordance with the ISO Tariff, the costs of the Facilities Study shall be recovered through its Access

Charges and transmission rates.

9.1.1.3 Principal Beneficiaries to Pay for Facilities Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the ISO or ISO ADR Procedures in accordance with the ISO Tariff

the Project Sponsor and the identified principal beneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as may be agreed, or, failing agreement, as

determined in accordance with the ISO ADR Procedures.

PDF page 40

9.1.2 Payment Procedure. Where a Facilities Study is being conducted pursuant to this Section 9, the Participating TO shall, within thirty days of the receipt of all reasonably required information, tender to the Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal beneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Facilities Study. If the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Facilities Study Agreement, they shall execute the Facilities Study Agreement and return it to the Participating TO within ten Business Days. Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Facilities Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures.

9.1.3 Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or alternative request to proceed as provided for in Section 9.1.2, a copy of which has been provided to the ISO by the party requesting the Facilities Study, the Participating TO will use due diligence to complete the required Facilities Study within a sixty (60) day period. If the Participating TO is unable to complete the Facilities Study in the allotted time period, the Participating TO shall notify the Market Participant and provide an estimate of the time needed to reach a final determination along with an explanation of the reasons that additional time is required to complete the study. If additional time is required, the Participating TO will use best efforts to complete the study within 10 months, provided adequate information is provided by all the parties.

9.2
Obligation to Build.
9.2.1 Due Diligence to Construct. Subject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the ISO Tariff and this TO Tariff. Alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to

PDF page 41

abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement.

Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement, commence construction of the additions or upgrades or incur other costs under the Participation Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Participation Agreement has been issued by the applicable court or regulatory authority. The Participating TO’s obligation to build will be subject to:

1) its ability, after making a good faith effort, to obtain the necessary approvals and property rights under applicable federal, state, and local laws; 2) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the ISO Tariff or this TO Tariff; and 3) a signed Participation Agreement. The Participating TO will not construct or expand its existing or planned transmission system, if doing so would impair system reliability as determined through systems analysis based on the Applicable Reliability Criteria. 9.2.2

Delay in Construction or Expansion. If any event occurs
that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify:

(1) the Project Sponsor with regard to facilities determined to be needed;
(2) the Parties to the Participation Agreement with regard to facilities determined to be needed pursuant to the ISO Tariff where principal beneficiaries were identified; and (3) the ISO. In such circumstances, the Participating TO shall, within thirty days of notifying such Project Sponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Participation Agreement, and the ISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the ParticipatingTO that is reasonably needed to evaluate the alternatives.

9.2.2.1 Alternatives to the Original Facility Additions. If the review process of Section 9.2.2 determines that one or more alternatives exist to the originally planned construction project, the Participating TO shall present such alternatives for consideration to the Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be. If upon review of any alternatives, such Project Sponsor, the ISO,

PDF page 42

or Parties to the Participation Agreement wish to evaluate or to proceed with one of the alternative additions or upgrades, such Project Sponsor, the ISO, or Parties to the Participation Agreement may request that the Participating TO prepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO Tariff. In the event the Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Participation Agreement or the ISO disagree, the dispute shall be resolved pursuant to the ISO ADR Procedure.

9.2.2.2 Refund Obligation for Unfinished Facility Additions. If the Participating TO and the Project Sponsor, the ISO, or Parties to the Participation Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Regulation 35.19a(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.

9.3
Provisions Relating To Transmission Construction On the System Of Other TOs.

9.3.1 Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any

engineering, permitting, and construction of transmission or distribution facilities on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO will undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice.

9.3.2 Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the ISO Tariff require additions or upgradeson other systems, to the extent consistent with Section 9.3.3 of this TO Tariff, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the ISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or

PDF page 43

resume construction of the new facilities. Within forty Business Days of receiving written notification by the Participating TO of its intent to defer construction pursuant to this section, such Project Sponsor, Parties to the Participation Agreement, or the ISO may challenge the decision in accordance with the ISO ADR Procedure.

PDF page 44

10. TSWL Interconnection Process. All requests for TSWL Interconnection with the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink shall be directed to the Participating TO.

10.1
Applicability. All requests for TSWL Interconnection directly to the ISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the provisions of this Section 10. All requests for Interconnection of wholesale generation directly to the ISO Controlled Grid shall be processed pursuant to the provisions of the ISO Tariff. Requests for interconnection submitted by an ECLL on behalf of Large Load Customers shall be processed pursuant to Section 10A of this TO Tariff.

10.2
TSWL Interconnection Applications. An applicant requesting TSWL
Interconnection shall submit a written TSWL Interconnection Application which provides the information detailed below to the Participating TO. The Participating TO shall timestamp the application to establish study priority.

(i) the identity, address, telephone number, and email of the applicant requesting TSWL Interconnection;

(ii) the Interconnection point(s) to the ISO Controlled Grid contemplated by the applicant;

(iii) the resultant (or new) maximum amount of TSWL Interconnection capacity contemplated by the applicant;

(iv) the proposed date for energizing the TSWL Interconnection and the term of the interconnection service, and

(v) such other information as the Participating TO reasonably required to process the application.

In addition to the information specified above, the following information may also be provided in order to properly evaluate system conditions:

(vi) If the applicant is a wholesale load, the electrical location of the source of the power (if known) to be transmitted pursuant to applicant’s request for Interconnection. If the source of the power is not known, a system purchase will be assumed. If the location of the load is not known, a system sale will be assumed; and, in addition, if an applicant proposes to perform or cause a third party to perform any required System Impact Study or any required Facilities Study, it shall so indicate in its Interconnection Application.

The results of any study or studies performed by an applicant must be approved by both the ISO and the Participating TO. Within ten (10) Business Days after receipt of a TSWL Interconnection Application, the Participating TO and the ISO if applicable shall determine whether the application is complete (“Completed TSWL Interconnection Application”). Whenever possible, the participating TO will attempt to remedy deficiencies in the TSWL Interconnection Application

PDF page 45

through informal communications with the applicant. If such efforts are unsuccessful, the Participating TO shall return the Interconnection Application to the applicant.

The Participating TO will treat the information in the TSWL Interconnection Application, including the applicant’s identity, as confidential at the request of the applicant except to the extent that disclosure of the information is required by this TO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations. 10.2.1 Amendment to Completed TSWL Interconnection Application. An applicant shall only be limited to amending its Completed TSWL

Interconnection Application once. Such amendment shall occur on or before ten (10) Business Days following the date the Participating TO tenders any Facilities Study Agreement. Specifically, an applicant may submit an amendment to its Completed TSWL Interconnection

Application to reflect a revised configuration for its New Facility. The amended Completed TSWL Interconnection Application shall be treated in accordance with Section 25 of the ISO Tariff and Section 10.5 of this TO Tariff; the applicant’s Completed TSWL Interconnection Application shall be deemed withdrawn; and the applicant shall maintain its existing queue position, if (a) the amended Completed TSWL Interconnection Application is received by the Participating TO within ten (10) Business Days of the Participating TO’s tender of a Facilities Study Agreement; and (b) the applicant has not submitted a previous amendment to the Completed TSWL Interconnection Application. In the event an applicant amends its Completed TSWL Interconnection Application, it will be responsible for any additional study costs that result from that amendment, including costs associated with revisions to studies for other applicants holding later queue positions.

10.3
Review of Completed TSWL Interconnection Application. After receiving a Completed TSWL Interconnection Application, the Participating TO and the ISO, if applicable, will determine on a non-discriminatory basis whether a System Impact Study is required. Whenever the Participating TO, and the ISO, if applicable, determines that a System impact Study is not required and that neither Reliability Upgrades nor changes in existing operating procedures are required, the Participating TO shall notify the applicant within fifteen (15) Business Days of the Completed Application Date. If the TSWL Interconnection can be accommodated without any Direct Assignment Facilities, then within thirty (30) Business Days of such notice from the Participating TO, the applicant shall request the Participating TO to tender to the applicant an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in this Section 10. If the Participating TO determines upon review of the Completed

PDF page 46

TSWL Interconnection Application, that Direct Assignment Facilities are required, the Participating TO shall tender to the applicant a Facilities Study Agreement within twenty (20) Business Days of the Completed Application Date and continue the Interconnection process pursuant to Section 10.8.

10.4 Notice of Need for System Impact Study. If the Participating TO, and the ISO, if applicable, determines that a System Impact Study is necessary to accommodate the requested Interconnection, the Participating TO shall so inform the applicant as soon as practicable. In such cases, the Participating TO shall within twenty (20) Business Days of receipt of a Completed TSWL Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO, the estimated time required to complete it, and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of performing the required System Impact Study. A description of the Participating TO’s transmission assessment practices for completing a System Impact Study shall be provided in the Participating TO’s FERC Form 715.

Alternatively, if the applicant will perform the System Impact Study, the Participating TO shall within twenty (20) Business Days of receipt of a Completed TSWL Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of reviewing the required System Impact Study.

For a TSWL Interconnection request to remain a Completed TSWL
Interconnection Application, the applicant shall execute the System Impact Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated cost of performing the System Impact Study or reviewing the applicant’s System Impact Study. Alternatively, if the applicant request the Participating TO to proceed with the System Impact Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the System Impact Study provided that such request is accompanied by payment of the reasonable estimated cost of the System Impact Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. If the applicant elects not to execute a System Impact Study Agreement, and does not request that the Participating TO proceed with the System Impact Study or review thereof, its application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application.

PDF page 47

10.5
System Impact Study Cost Reimbursement and Agreement.
10.5.1 Cost Reimbursement. The System Impact Study Agreement shall clearly specify the charge, based on the Participating TO’s estimate of the cost and time for completion of the System Impact Study. The charge shall not exceed the reasonable actual cost of the study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any modifications to existing planning studies that are reasonably necessary to evaluate the impact on the applicant’s request.

10.6
System Impact Study Procedures. Upon receipt of an executed System Impact Study Agreement or initiation of the ISO ADR Procedures and receipt of payment for estimated study costs, the Participating TO will use due diligence to either (a) complete the required System Impact Study within a sixty (60) calendar day period or (b) complete its review of an applicant’s System Impact Study within thirty (30) calendar days of its receipt of the completed study. The System Impact Study will identify whether any Direct Assignment Facilities or Reliability Upgrades are necessary to deliver a New Facility’s full output over the ISO Controlled Grid, or any transmission additions or upgrades are necessary to serve a wholesale load. The System Impact Study will also identify any adverse impact on Encumbrances existing as of the applicant’s Completed Application Date. In the event that the Participating TO is unable to complete the required System Impact Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed System Impact Study and related work papers shall be made available to the applicant and the ISO. The Participating TO shall notify the applicant and the ISO immediately upon completion of the System Impact Study.

10.6.1 Procedures Upon Completion of System Impact Study. Within fifteen
(15) Business Days of completion of the System Impact Study or review and approval of an applicant’s System Impact Study, the Participating TO shall notify the applicant whether the transmission system will be adequate to accommodate all of a request for Interconnection. If no costs are likely to be incurred for any Direct Assignment Facilities, any Reliability Upgrades, or implementing any operating procedures, then within thirty (30) Business Days of receipt of written approval of the applicant’s System Impact Study from the Participating TO and the ISO the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty (30) Business Days of such

PDF page 48

request. The Participating TO shall tender to the applicant an
Interconnection Agreement as provided in Section 10.9. If costs are likely to be incurred to accommodate a request for Interconnection, the Participating TO shall tender to the applicant a Facilities Study Agreement pursuant to Section 10.8.

10.7
Notice of Need for Facilities Study. If a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid are needed to satisfy an applicant’s request for interconnection, the Participating TO shall, within fifteen

(15) Business Days of the date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study by the Participating TO, tender to the applicant a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete the required study; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of performing the required Facilities Study. Alternatively, if the applicant will perform the Facilities Study, the Participating TO shall within fifteen (15) Business Days of the completion date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study, tender a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete the required review; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of reviewing the required Facilities study. For an Interconnection request to remain a Completed TSWL Interconnection Application, the applicant shall execute the Facilities Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated costs of performing the Facilities Study or reviewing the applicant’s Facilities Study. Alternatively, if the applicant request the Participating TO to proceed with the Facilities Study or review thereof and commits to abide by terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study provided that such request is accompanied by payment for the reasonable estimated cost of the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO ADR Procedures. If the applicant elects not to execute a Facilities Study Agreement and does not request that the Participating TO proceed with the Facilities Study or review thereof, its application shall be deemed withdrawn and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by the System Impact Study Agreement.

10.8
Facilities Study Procedures. Upon receipt of an executed Facilities Study

PDF page 49

Agreement or initiation of the ISO ADR Procedures and receipt of payment for the estimated study costs, the Participating TO will use due diligence to either

(a) complete the required Facilities Study within a sixty (60) calendar day period or (b) complete its review of an applicant’s Facilities Study within thirty

(30) calendar days of its receipt of the Completed Study. In the event that Participating TO is unable to complete the required Facilities Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed Facilities Study shall be made available to the applicant.

10.8.1 Tender of Interconnection Agreement. Within thirty (30) Business Days of receipt of the completed Facilities Study performed by the Participating TO or receipt of written approval of the applicant’s Facilities Study from the Participating TO, the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty

(30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 10.9.

10.9
Interconnection Agreement.
Pursuant to Section 10.3, 10.6.1, or 10.8.1, a
party requesting Interconnection shall request in writing that the Participating TO tender to such party an Interconnection Agreement that will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement shall include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, and for any other mitigation measures. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs.

For a TSWL Interconnection request to remain a Completed TSWL
Interconnection Application, the applicant requesting the Interconnection or the entity with whom the Participating TO will interconnect for the Interconnection shall execute the Interconnection Agreement and return it to the Participating TO within thirty (30) Business Days of receipt. Alternatively, if an applicant requesting the TSWL Interconnection or the entity with whom the Participating TO will interconnect for the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is a eligible for a TSWL Interconnection, the Participating TO shall not be obligated to file an unexecuted Interconnection Agreement or commence construction of any facilities or incur other costs under the Interconnection Agreement until a

PDF page 50

final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority. If the applicant or the entity with whom the Participating TO will interconnect for the Interconnection elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed TSWL Interconnection Application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by any System Impact Study Agreement or Facilities Study Agreement.

Where a TSWL Interconnection will serve one or more Large Loads, as a condition to the Participating TO’s design, procurement, construction, or operation of any Large Load-Driven Upgrades (as defined in the pro forma Large Load Cost Recovery Agreement set forth in Appendix V) associated with the TSWL Interconnection, the applicant or Eligible Customer shall also, within the same period and subject to the same consequences as the Interconnection Agreement, execute and maintain a Cost Recovery Agreement substantially in the form set forth in Appendix V to this TO Tariff, or, if the applicant or Eligible Customer requests that the Cost Recovery Agreement be filed unexecuted with FERC, comply with that agreement as made effective by FERC, in each case as applicable to the requested TSWL Interconnection. Disputes arising under a Cost Recovery Agreement shall be resolved under the dispute resolution provisions of that agreement.

10.10 Partial Interim Service. If the Participating TO determines that there will not be adequate transmission capability to satisfy the full amount requested in a Completed TSWL Interconnection Application, the Participating TO nonetheless shall be obligated to offer and provide the portion of the requested TSWL Interconnection that can be accommodated without any additional Direct Assignments Facilities or Reliability Upgrades. However, the Participating TO shall not be obligated to provide the incremental amount of requested TSWL Interconnection that requires such additional facilities or upgrades until such facilities or upgrades have been placed in service.

10.11 Expedited Interconnection Procedures. In lieu of the procedures set forth above, the applicant shall have the option to expedite the processing of its Completed TSWL Interconnection Application. In order to exercise this option, the applicant shall submit in writing a Request for Expedited Interconnection Procedures to the Participating TO within ten (10) Business Days after receiving a copy of the System Impact Study for the proposed TSWL Interconnection. Within ten (10) Business Days after receiving a Request for Expedited Procedures, the Participating TO shall tender an Expedited Interconnection Agreement that requires the applicant to compensate the Participating TO for all costs reasonably incurred pursuant to the terms of this TO Tariff for processing the Completed TSWL Interconnection Application and providing the requested Interconnection. While the Participating TO agrees to provide the applicant with

PDF page 51

its best estimate of the costs of any needed Direct Assignment Facilities and, if applicable, Reliability Upgrades, and such other charges that may be incurred, unless otherwise agreed by the parties, such estimate shall not be binding and the applicant must agree in writing to compensate the Participating TO for all actual TSWL Interconnection costs reasonably incurred pursuant to the provisions of this TO Tariff. The applicant shall execute and return such Expedited Interconnection Agreement within ten (10) Business Days of its receipt or the applicant’s request for Interconnection will cease to be a Completed TSWL Interconnection Application and will be deemed terminated and withdrawn. In that event, the applicant shall reimburse the Participating TO for all costs reasonably incurred in processing the application not covered by the terms of the System Impact Study Agreement.

PDF page 52

10A. Interconnection Process for ECLL Interconnections. All requests for ECLL Interconnection shall be directed to the Participating TO.

10A.1
Applicability. An ECLL Interconnection must be requested in order to connect the facilities of the Participating TO to the facilities of an ECLL that has received a request to connect and provide retail transmission service to a Large Load Customer.

10A.2 ECLL Application and Application Fee

10A.2.1
Application Contents. An ECLL requesting an ECLL Interconnection shall submit an ECLL Interconnection Application in the form of Attachment 1 to Appendix VI, which provides the following required information, and shall send a copy of the application to the ISO. The ECLL Interconnection Application and all supporting documentation shall be submitted electronically to the Participating TO in the manner posted on the Participating TO’s public website.

(a) the identity, address, telephone number, and email of the ECLL;
(b) the Point of Withdrawal;
(c) a proposed Large Load Customer load ramp schedule identifying anticipated load additions over time and the Large Load Customer’s maximum load;

(d) a site plan;
(e) documentation demonstrating that the Large Load Customer has Site Control;

(f) documentation demonstrating that the Large Load Customer has local permits and regulatory approvals for development of its Large Load;

(g) a single-line electrical diagram;
(h) the electrical location of the source of the power (if known) to be transmitted pursuant to the ECLL’s request for ECLL Interconnection. If the source of the power is not known, a system purchase will be assumed;

(i) disclosure of ECLL interconnection requests in the ECLL’s footprint that are for the same Large Load Customer or any of its affiliate(s);

(j) a completed technical data form in the form of Appendix A to Attachment 1 to Appendix VI;

(k) if the Large Load Customer will be a Co-Located Large Load, information concerning the relevant Generating Facility must be provided by the ECLL. Such information may be either: (1) if the Generating Facility has not signed a generator interconnection agreement, the identifying queue number of the Generating Facility; or (2) if the Generating Facility has signed a generator interconnection agreement, information that will allow the Participating TO to identify such agreement; and

(l) the proposed date for energizing the ECLL Interconnection and the proposed term of the ECLL Interconnection service.

PDF page 53

10A.2.2
Participating TO Review of ECLL Interconnection Application. Within ten (10) Business Days after receipt of an ECLL Interconnection Application, the Participating TO shall determine whether the application is complete (“Completed ECLL Interconnection Application”). Wherever possible, the Participating TO will attempt to remedy deficiencies in the ECLL Interconnection Application through informal communications with the ECLL. If such efforts are unsuccessful, the Participating TO shall return the ECLL Interconnection Application to the ECLL.

The Participating TO will treat the information provided in the ECLL Interconnection Application, including the ECLL’s and Large Load Customer’s identity, as confidential at the request of the ECLL except to the extent that disclosure of this information is required by this TO Tariff or the ISO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations.

10A.3 Study Process and ECLL Interconnection Agreement. ECLL Interconnection Applications shall be processed, and ECLL Interconnection Agreements shall be tendered, executed, and filed, in accordance with the Large Load Interconnection Procedures set forth in Appendix VI. Disputes arising under a Cost Recovery Agreement shall be resolved under the dispute resolution provisions of that agreement.

10A.4 Interim Service

10A.4.1
Interim Firm Interconnection Service and Flexible Interim Load Interconnection (FILI) Service. If the ECLL has requested Interim Firm Interconnection Service and/or FILI Service, the Participating TO shall perform an analysis and report the extent to which the requested interim services can be provided, prior to such time that all ECLL Interconnection Facilities are in service and the Large Load Customer is authorized to withdraw Energy. However, the Participating TO shall not be obligated to provide any amount of Firm Interconnection Service requested until necessary facilities have been placed in service. FILI Service will be available for all remaining Load that cannot receive Interim Firm Interconnection Service, if the Large Load Customer has the ability to reduce the load at a specified point of interconnection according to the timelines and protocols set forth in an executed and effective FILI Service Agreement, until the ECLL Interconnection Facilities are in service. As ECLL Interconnection Facilities are placed into service and transmission interconnection capability is increased, available quantities of Firm Interconnection Service and FILI Service will be updated and reflected in the applicable FILI Service Agreement.

PDF page 54

If the Large Load Customer seeks FILI Service, the ECLL will ensure that the Large Load Customer signs a FILI Service Agreement developed by the Participating TO, or asks for the agreement to be filed unexecuted.

10A.4.2
Study Process for Interim Service and Determination of Availability of Interim Firm Interconnection Service and FILI Service. The Participating TO shall perform a FILI Study in accordance with Section 4.6.2 of Appendix VI to determine the maximum amount of any Interim Firm Interconnection Service, if any, and FILI Service, if any, that may be provided based on the anticipated availability of transmission capacity once the Large Load Customer is permitted to withdraw energy by the ECLL. The Participating TO shall update this analysis under the terms of the FILI Service Agreement, at least annually.

The actual amount of any FILI Service to be provided during any operating period shall be determined by the Participating TO through operational assessments and analysis conducted closer to real-time operating conditions. Accordingly, the maximum FILI Service established in the annual analysis does not guarantee the availability of such service under actual system conditions.

10A.4.3
Conditions Related to FILI Service

10A.4.3.1 FILI Service Reliability Requirements. The FILI Service Agreement will identify what ECLL Interconnection Facilities must be installed, the necessary protection and control systems and any other equipment necessary to be installed, and operating limitations to allow the Large Load Customer to withdraw energy (“FILI Service Reliability Requirements”). FILI Service shall not commence until the Participating TO and ECLL have completed installation and commissioning of all equipment specified under the FILI Service Agreement.

10A.4.3.2 Curtailment of FILI Service. FILI Service is subject to curtailment at all times, unless the Participating TO’s right to curtail is expressly conditioned or otherwise limited in an executed and effective FILI Service Agreement. A Large Load Customer receiving FILI Service shall be subject to curtailment prior to any curtailment of customers receiving Firm Interconnection Service. The Participating TO and ISO may curtail FILI Service as necessary to maintain the reliable operation of the ISO Controlled Grid, including during normal operating conditions.

10A.4.3.3 Exceedance of Authorized FILI Service. An ECLL shall ensure that the operating instructions issued by the Participating TO pursuant to a FILI Service Agreement are not exceeded at the relevant Point of Withdrawal. The Participating TO shall have the right to disconnect service to the Large Load Customer in the event that energy withdrawals violate the terms of the

PDF page 55

FILI Service Agreement. The Participating TO shall follow Good Utility Practice in carrying out any such disconnection and subsequent reconnection when the conditions for such reconnection set forth in the FILI Service Agreement have been met. Nothing in this TO Tariff prevents the ISO from applying any financial penalties applicable to Large Load Customers.

10A.5 Co-Located Large Load. The interconnection processes applicable to a Co-Located Large Load shall be determined based on whether the Generating Facility is a (1) non-exporting Generating Facility interconnected in accordance with the generator interconnection rules of the applicable ECLL, as approved by its Local Regulatory Authority (including, for a UDC subject to the jurisdiction of the CPUC, CPUC Electric Rule 21); or (2) an exporting Generating Facility subject to the applicable ISO generator interconnection procedures and requirements. The ECLL for a Co- Located Large Load connecting to facilities of an exporting Generating Facility will be subject to this Section 10A.

For a Co-Located Large Load interconnected to the facilities of an exporting Generating Facility, the ISO will be a party to a pro forma agreement that bridges the pro forma Large Generator Interconnection Agreement (LGIA) with the ECLL Interconnection Agreement, or will negotiate a non-conforming LGIA to account for certain details of the Co-Located Large Load interconnection on an individual basis. The Generating Facility developer will also execute an ISO pro forma Participating Generator Agreement for the Generating Facility, but not a Participating Load Agreement for the Co-Located Large Load.

10A.6 Large Load Cost Recovery Agreement. As a condition to the Transmission Owner’s design, procurement, construction, or operation of a Large Load-Driven Upgrade, the Eligible Customer shall execute and maintain a Large Load Cost Recovery Agreement substantially in the form set forth in Appendix V to this TO Tariff, as applicable to the requested service and associated Large Load Facility.

PDF page 56

13. Creditworthiness
13.1
UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low Voltage Transmission Facilities. For the purpose of determining the ability of a UDC, MSS, and Scheduling Coordinator to meet its obligations related to using the Participating TO’s Low Voltage Transmission Facilities hereunder, where the Participating TO is collecting the Low Voltage Access Charge directly from each UDC, MSS and Scheduling Coordinator, the Participating TO may require reasonable credit review procedures for the UDC, MSS, or Scheduling Coordinator. This review shall be made in accordance with standard commercial practices. In addition, the Participating TO may require the UDC, MSS, or Scheduling Coordinator to provide and maintain in effect during the term of the service, an unconditional and irrevocable letter of credit as security to meet its responsibilities and obligations under this TO Tariff, or an alternative form of security proposed by the UDC, MSS, or Scheduling Coordinator and acceptable to the Participating TO, and consistent with commercial practices established by the Uniform Commercial Code, that protect the Participating TO against the risk of non-payment.

13.2
End-Users. Creditworthiness and security rules applicable to End-Users shall be pursuant to the then-current rules of the applicable Local Regulatory Authority and any agreement under this TO Tariff to which the End-User is a party.

PDF page 57

14. Disputes. Except as limited below, as provided in Sections 10.9 and 10A.3, or as otherwise limited by law, the ISO ADR procedures shall apply to all disputes between parties which arise under this TO Tariff or under or in respect of the proposed terms and conditions of a Facilities Study Agreement, System Impact Study Agreement or Expedited Interconnection Agreement. The ISO ADR Procedures set forth in Section 13 of the ISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.

PDF page 58

16. Miscellaneous.
16.1
Notices. Any notice, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person or electronically via email, (ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return electronic facsimile if sent by facsimile, or (iv) upon Party at the address set forth in Appendix II. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix II to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff or in connection with operation of facilities shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.

16.2
Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver.

16.3
Confidentiality.

16.3.1 Maintaining Confidentiality If Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the documents, data, and information provided to it by any other Market Participant that such Market Participant may designate as confidential, provided, however, that the information will not be held confidential by the Participating TO if (1) the Participating TO or Market Participant is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory requirements, or (2) the information becomes available to the public on a non-confidential basis (other than from the Participating TO).

16.3.2 Disclosure of Confidential Information. Notwithstanding anything in this Section 16.3 to the contrary, if the Participating TO or any Market Participant is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to this Section 16.3, the Participating TO or Market Participant may disclose such information; provided, however, that as soon as such Participating TO or Market Participant learns of the disclosure requirement and prior to making such disclosure, such Participating TO or Market Participant shall notify the affected Participating TO or Market Participants of the requirement and the terms thereof. The affected Participating TO or

PDF page 59

Market Participants may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Participating TO or Market Participant shall cooperate with such affected Participating TO or Market Participants to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Participating TO or Market Participant shall cooperate with the affected Participating TO or Market Participants to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure.

16.4
TO Tariff Supersedes Existing Tariffs. This TO Tariff, together with the ISO Tariff and wholesale distribution access tariff if any, supersedes any pre- existing open access transmission tariff of the Participating TO.

16.5
Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.

16.6
Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Participating TO and Market Participants shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.

16.7
Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of any entity shall be preserved until satisfied.

16.8
Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.

16.9
Appendices Incorporated. The several appendices to this TO Tariff, as may be revised from time to time, are attached to this TO Tariff and are incorporated by reference as if fully set forth herein.

16.10
Conflict With ISO Tariff. If a Market Participant identifies a conflict between the TO Tariff and the ISO Tariff, the Participating TO and the Market

PDF page 60

Participant shall make good-faith efforts to resolve the conflict. If the Participating TO and Market Participant are unable to informally resolve that conflict, the Participating TO and Market Participant may use the ISO ADR Procedures to resolve it as set forth in Section 14 of this Tariff.

16.11
Conflicting Operating Instructions. In the event a Market Participant receives conflicting operating instructions from the ISO and one or more Participating TO(s), if human safety would not knowingly be neither jeopardized nor electric facilities subject to damage while the Market Participant seeks to reconcile the conflict with the appropriate ISO and Participating TO employees before acting, the Market Participant should attempt a reconciliation. Otherwise, the Market Participant shall adhere to ISO Tariff Section 4.2 and follow the ISO’s instructions. In no event shall a Market Participant be required to follow operating instructions from the ISO if following those instructions would knowingly jeopardize human safety.

PDF page 61

Projected ATRR
For the 12 months ended
12/31/__
Formula Rate Index
DesertLink, LLC
Table of Contents
Formula Rate Template
Attachments:
Attachment No
Worksheet Name
1
Project Revenue Requirement Worksheet
1a
Project Plant Detail Worksheet
2
Incentive Return
3
Formula Rate True-Up
4
Rate Base Worksheet
5
Return on Rate Base Worksheet
6
Interest on True-Up
6A
True-Up Interest Rate Calculator
7
Weighted Average Federal and State Income Tax Rates
8
Cost of Debt Prior to Issuing Non-Construction Financing
9
True-Up - Construction Financing Cost of Debt
10
Depreciation Rates
11
Prior Period Adjustments
12
Revenue Credit Detail
13
Excess or Deficient Accumulated Deferred Income Taxes - Summary 13.1

Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments 13.2

Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities

PDF page 62

Formula Rate - Non-Levelized
Page 1 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
Projected ATRR
For the 12 months ended
12/31/__
(1) (2)
(3) (4)
(5) Line
Allocated
No.
Source
Amount
1
GROSS REVENUE REQUIREMENT, without incentives (Page 3, Line 49)

 $                               -
REVENUE CREDITS
(Note A)
Total
Allocator (W)
2
Account No. 454
(Page 4, Line 20)
                                                  -
TP
         1.0000
 $                               -
3
Account No. 456.1
(Page 4, Line 21)
                                                  -
TP
         1.0000
 $                               -
4
Revenues from Grandfathered Interzonal Transactions (Note B)

                                                  -
TP
         1.0000
 $                               -
5
Revenues from service provided by the ISO at a discount
                                                  -
TP
         1.0000
 $                               -
6
TOTAL REVENUE CREDITS
(Sum of Lines 2 through 5)
                                                  -
 $                               -
7
Prior Period Adjustments
Attachment 11, Line 18, Col. B
                                                  -
DA
         1.0000
 $                               -
8
True-up Adjustment with Interest
Attachment 3, Line 9, Col. J
                                                  -
DA
         1.0000
 $                               -
9
NET ANNUAL TRANSMISSION REVENUE REQUIREMENT
(Line 1 less Line 6 plus Lines 7 and 8)
 $                               -

PDF page 63

Page 2 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
RATE BASE: (Note R)
Source
Company Total
Allocator (W)
Transmission
GROSS PLANT IN SERVICE
Note C
(Col 3 times Col 4)
1
Production
205.46.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
2
Transmission
Attachment 4, Line 14, Col. (b)
                                                  -
TP
         1.0000
                                  -
3
Distribution
207.75.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
4
General & Intangible
Attachment 4, Line 14, Col. (c)
                                                  -
WS
         1.0000
                                  -
5
TOTAL GROSS PLANT
(Sum of Lines 1 through 4)
                                                  -
GP=
         1.0000
                                  -
6
ACCUMULATED DEPRECIATION
Note C
7
Production
219.20-24.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
8
Transmission
Attachment 4, Line 14, Col. (h)
                                                  -
TP
         1.0000
                                  -
9
Distribution
219.26.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
10
General & Intangible
Attachment 4, Line 14, Col. (i)
                                                  -
WS
         1.0000
                                  -
11
TOTAL ACCUM. DEPRECIATION
(Sum of Lines 7 through 10)
                                                  -
                                  -
12
NET PLANT IN SERVICE
13
Production
(Line 1 - Line 7)
                                              -
                               -
14
Transmission
(Line 2 - Line 8)
                                              -
                               -
15
Distribution
(Line 3 - Line 9)
                                              -
                               -
16
General & Intangible
(Line 4 - Line 10)
                                              -
                               -
17
TOTAL NET PLANT
( Sum of Lines 13 through 16)
                                              -
NP=
         1.0000
                               -
18
ADJUSTMENTS TO RATE BASE
19
Account No. 281 (enter negative)
Attachment 4, Line 28, Col. (d) (Note D)
                                              -
N/A
                 -
                               -
20
Account No. 282 (enter negative)
Attachment 4, Line 28, Col. (e) (Note D)
                                              -
NP
         1.0000
                               -
21
Account No. 283 (enter negative)
Attachment 4, Line 28, Col. (f) (Note D)
                                              -
NP
         1.0000
                               -
22
Account No. 190
Attachment 4, Line 28, Col. (g) (Note D)
                                              -
NP
         1.0000
                               -
22a
Deficient or (Excess) Accumulated Deferred Income Taxes Attachment 13, Line 7 (Note X)

                                                  -
NP
         1.0000
                               -
23
Account No. 255 (enter negative)
Attachment 4, Line 28, Col. (h) (Note D)
                                              -
NP
         1.0000
                               -
24
Unfunded Reserves (enter negative)
Attachment 4, Line 43, Col. (h)
                                              -
DA
         1.0000
                               -
25
CWIP
Attachment 4, Line 14, Col. (d)
                                              -
DA
         1.0000
                               -
26
Unamortized Regulatory Asset
Attachment 4, Line 28, Col. (b) (Note E)
                                              -
DA
         1.0000
                               -
27
Unamortized Abandoned Plant
Attachment 4, Line 28, Col. (c) (Note F)
                                              -
DA
         1.0000
                               -
28
TOTAL ADJUSTMENTS
( Sum of Lines 19 through 27)
                                              -
                                  -
29
LAND HELD FOR FUTURE USE
Attachment 4, Line 14, Col. (e) (Note G)
                                              -
TP
         1.0000
                               -
30
WORKING CAPITAL
Note H
31
Cash Working Capital
1/8*(Page 3, Line 17 minus Page 3, Line 14)
                                              -
                               -
32
Materials & Supplies
Attachment 4, Line 14, Col. (f)
                                              -
TP
         1.0000
                               -
33
Prepayments (Account 165)
Attachment 4, Line 14, Col. (g)
                                              -
GP
         1.0000
                               -
34
TOTAL WORKING CAPITAL
( Sum of Lines 31 through 33)
                                              -
                                  -
35
RATE BASE
( Sum of Lines 17, 28, 29, and 34)
                                              -
                                  -
Formula Rate - Non-Levelized

PDF page 64

Page 3 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
Source
Company Total
Allocator (W)
Transmission
O&M
(Col 3 times Col 4)
1
Transmission
321.112.b
                                                  -
TP
         1.0000
                                  -
2
Less Account 566 (Misc Trans Expense)
321.97.b
                                                  -
TP
         1.0000
                                  -
3
Less Account 565
321.96.b
                                                  -
TP
         1.0000
                                  -
4
A&G
323.197.b
                                                  -
WS
         1.0000
                                  -
5
Less FERC Annual Fees
351.h (Note I)
                                                  -
WS
         1.0000
                                  -
6
Less EPRI Dues
Note J
                                                  -
WS
         1.0000
                                  -
7
Less Reg. Commission Expense Account 928
Note J
                                                  -
WS
         1.0000
                                  -
8
Less: Non-safety Advertising account 930.1
Note J
                                                  -
WS
         1.0000
                                  -
9
10
Plus Transmission Related Reg. Comm. Exp.
Note K
                                                  -
TP
         1.0000
                                  -
11
12
Plus Transmission Lease Payments in Acct 565 Note V

                                                  -
DA
         1.0000
                                  -
13
Account 566
14
Amortization of Regulatory Asset
Note E
                                                  -
DA
         1.0000
                                  -
15
Misc. Transmission Expense (less amort. of regulatory asset) 321.97.b less line 14

                                                  -
TP
         1.0000
                                  -
16
Total Account 566
(Sum of Lines 14 through 15) Ties to 321.97b
                                                  -
                                  -
17
TOTAL O&M
                                                  -
                                  -
18
DEPRECIATION EXPENSE
Note C
19
Transmission
336.7.b&d
                                                  -
TP
         1.0000
                                  -
20
General & Intangible
336.10.b&d, 336.1.b&d
                                                  -
WS
         1.0000
                                  -
21
Amortization of Abandoned Plant
Note F
                                                  -
DA
         1.0000
                                  -
22
TOTAL DEPRECIATION
(Sum of Lines 19 through 21)
                                                  -
                                  -
23
TAXES OTHER THAN INCOME TAXES   (Note M)
24
LABOR RELATED
25
Payroll
263.i
                                                  -
WS
         1.0000
                                  -
26
263.i
                                                  -
WS
         1.0000
                                  -
27
PLANT RELATED
28
Property
263.i
                                                  -
GP
         1.0000
                                  -
29
Gross Receipts
263.i
                                                  -
N/A

                                  -
30
Other
263.i
                                                  -
GP
         1.0000
                                  -
31
Payments in lieu of taxes
263.i
                                                  -
GP
         1.0000
                                  -
32
TOTAL OTHER TAXES
( Sum of Lines 25 through 31)
                                                  -
                                  -
33
INCOME TAXES    (Note N)
Note N
34
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} 0.00%

35
CIT=(T/1-T) * (1-(WCLTD/R)) =
WCLTD = Page 4, Line 15, R = Page 4, Line 18 0.00%

36
FIT & SIT & P
37
38
1 / (1 - T)  = (from line 35)
1 / (1 - T), T from Line 35
                                         1.0000
39
Amortized Investment Tax Credit
266.8f (enter negative) (Note D)
                                                  -
40
Deficient or (Excess) Deferred Income Taxes Attachment 13, Line 12, Col. (d) (Note X)

                                                  -
41
Tax Effect of Permanent Differences
Note O
                                                  -
42
Income Tax Calculation
(Line 35 times Line 48)
                                                  -
N/A
                                  -
43
ITC adjustment
(Line 38 times Line 39)
                                                  -
NP
         1.0000
                                  -
44
Deficient or (Excess) Deferred Income Tax Adjustment Attachment 13, Line 12, Col. (f) (Note X)

                                                  -
NP
         1.0000
                                  -
45
Permanent Differences Tax Adjustment
(Line 38 times Line 41)
                                                  -
NP
         1.0000
                                  -
46
Total Income Taxes
(Sum of Lines 42 through 45)
                                                  -
                                  -
47
RETURN
48
Rate Base times Return
(Page 2, Line 35 times Page 4, Line 18)
                                                  -
N/A
                 -
                                  -
49
GROSS REVENUE REQUIREMENT
( Sum of Lines  17, 22, 32, 46, and 48)
                                                  -
                                  -
(Sum of Lines 1, 4, 10, 12, and 16 less Sum of Lines 2, 3, and 5 through 8)

Highway and vehicle

PDF page 65

Formula Rate - Non-Levelized
Page 4 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
SUPPORTING CALCULATIONS AND NOTES
TRANSMISSION PLANT INCLUDED IN ISO RATES
1
Total Transmission plant
(Page 2, Line 2, Col. 3)
                                  -
2
(Note P)
                                  -
3
(Note S)
                                  -
4
Transmission plant included in ISO rates
(Line 1 minus Lines 2 and 3)
                                  -
5
Percentage of Transmission plant included in ISO Rates (Line 4 divided by Line 1)

TP =                               1.00
6
WAGES & SALARY ALLOCATOR (W&S)
Form 1 Reference
$
TP
Allocation
7
Production
354.20.b
                                                  -
            -                    -
8
Transmission
354.21.b
                                                  -
        1.00                  -
9
Distribution
354.23.b
                                                  -
            -                    -
W&S Allocator
10
Other
354.24,25,26.b
                                                  -
            -                    -
($ / Allocation)
11
Total (W&S Allocator is 1 if lines 7-10 are zero) (Sum of Lines 7 through 10)

                                                  -
                 -
=
                        1.00000  = WS
12
RETURN (R)
13
14
$
%
Cost
Weighted
15
Long Term Debt
Attachment 5, Line 8 (Notes Q & R)
                                                  -
50.0%
0.00%
0.00% = WCLTD
16
Preferred Stock (112.3.c)
Attachment 5, Line 9 (Notes Q & R)
                                                  -
0.0%
0.00%
0.00%
17
Common Stock
Attachment 5, Line 10 (Notes Q, R, and T)
                                                  -
50.0%
9.80%
4.90%
18
Total
( Sum of Lines 15 through 17)
                                                  -
4.90% = R
19
REVENUE CREDITS
$
20
Attachment 12, Line 8, Col. C (Note U)
                                  -
21
ACCOUNT 456.1 (OTHER ELECTRIC REVENUES)
Attachment 12, Line 18, Col. C (Note A)
                                  -
Less Transmission plant excluded from ISO rates Less Transmission plant included in OATT Ancillary Service rates

ACCOUNT 454 (RENT FROM ELECTRIC

PDF page 66

Formula Rate - Non-Levelized
Page 5 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
General Note: References to pages in this formula rate template are indicated as: (Page #, Line #, Col. #)
References to data from FERC Form 1 are indicated as: #.y.x (page, line, column)
Notes
A
B
Company will not have any grandfathered agreements. Therefore, this line shall remain zero.
C
Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
D
E
F
Unamortized Abandoned Plant and Amortization of Abandoned Plant will be zero until the Commission accepts or approves recovery of the cost of Abandoned Plant. Utility must submit a Section 205 filing to recover the cost of abandoned plant. G

Identified in FERC Form 1, or Company records if not so indicated on the FERC Form 1, as being transmission related.
H
I
J
Page 3, Line 6 - Subtract all EPRI Annual Membership Dues listed in Form 1 at 353.f, all Regulatory Commission Expenses in account 928 itemized at 351.h, and non-safety related advertising included in Account 930.1. K

Page 3, Line 8-Add back Regulatory Commission Expenses directly related to transmission service, ISO filings, or transmission siting itemized at 351.h.
M
N
Inputs Required:
FIT =
0.0%
(Weighted Average Federal Income Tax Rate (Attachment 7, line 4, col. (i))
SIT =
0.0%
(Weighted Average State Income Tax Rate (Attachment 7, line 8, col. (i))
p =
0.0%
(Percent of federal income tax deductible for state purposes)
O
P
Removes transmission plant determined by Commission order to be state-jurisdictional according to the seven-factor test (until Form 1 balances are adjusted to reflect application of seven-factor test).
Q
R
S
T
The rate of return on common equity ("ROE") will be supported in the original Section 205 filing and shall, at no time during the life of the Project, be higher than 9.8%, including adders.  No change in ROE may be made absent a filing with FERC. U

Includes only income related to transmission facilities, such as pole attachments, rentals and special use from general ledger.
V
Add back any lease expense of transmission assets used to provide service under this tariff included in account 565. Amount to be obtained from company books and records.
W
DA = Direct Assignment; GP = Gross Plant Allocator (page 2, line 5); N/A = Not Applicable; NP = Net Plant Allocator (page 2, line 17); TP = Transmission Plant Allocator (page 4, line 5); WS = Wage and Salary Allocator (page 4, line 11). X

The revenues credited on page 1, lines 2-6, shall include only the amounts received by DesertLink for service rendered using facilities for which recovery is provided under this tariff. They do not include revenues associated with FERC annual charges, gross receipts taxes, or facilities not included in this template (e.g., direct assignment facilities and GSUs) which are not recovered under this Rate Formula Template.

Accumulated deferred income tax amounts associated with asset or liability accounts excluded from rate base (such as ADIT related to asset retirement obligations and certain tax-related regulatory assets or liabilities) do not affect rate base.  Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income. Account 281 is not allocated to Transmission.

Recovery of Regulatory Asset permitted only for pre-commercial and formation expenses as authorized by the Commission. Recovery of any other regulatory assets requires authorization from the Commission. A carrying charge equal to the AFUDC rate will be applied to the Regulatory Asset prior to the rate year when costs are first recovered.

Cash Working Capital assigned to transmission is one-eighth of O&M allocated to transmission at page 3, line 17, column 5 minus amortization of Regulatory Asset at page 3, line 14, column 5.  Prepayments are the electric related prepayments booked to Account No. 165 and reported on page 111, line 57 in the Form 1.

The FERC's annual charges for the year assessed the Transmission Owner for service under this tariff.  To the extent the charges are separately identified on the FERC Form 1, page 350, column 1, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 350 will be obtained from Company books and records.

Includes only FICA, unemployment, highway, property, gross receipts, and other assessments charged in the current year.  Taxes related to income are excluded.  Enter the line number on page 262-63 upon which each item is identified.  To the extent individual types of taxes are separately identified on the FERC Form 1, page 262, column a, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 262-63 will be obtained from Company books and records.

FIT is the weighted average Federal income tax rate and SIT is the weighted average State income tax rate, both from Attachment 7, and p is the "the percentage of federal income tax deductible for state income taxes". A utility that elected to utilize amortization of tax credits against taxable income, rather than book tax credits to Account No. 255 and reduce rate base, must reduce its income tax expense by the amount of the Amortized Investment Tax Credit (Form 1, 266.8.f) multiplied by (1/1-T) (page 3, line 26). Excess Deferred Income Taxes reduce income tax expense by the amount of the expense multiplied by (1/(1-T)).

The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Tax Effect equals Permanent Differences multiplied by T.

The cost of debt will be determined based on the financing in place during each stage of project development. Before debt is obtained, a proxy interest rate which will be supported in the original Section 205 filing will be used. This rate is provided on Attachment 8 line 36. If construction debt (wherein principal is drawn down over time) is issued, the rate plus an amortization of fees projected to be incurred on the construction debt during the rate year will be the cost of debt. This construction debt rate (inclusive of fees) will be reset and trued-up every year using the method on Attachment 9 for multi-year construction projects. Once non-construction debt is obtained, the actual interest rate and fees on the debt in place at the end of the year such non- construction debt is obtained will become the cost of debt. In the first full year after non-construction debt is obtained, the cost of debt will be the actual cost of debt determined using the method on Attachment 5. A h

h i
l
i l
f 50% E
i
d 50% d b
ill b
d
il h fi
i i
i
l
d i
i
il
h
i
h
i
d b
h C
i i
Af
h f
ili i
l
d i
i
h l
f
50%
i
h
h i
l
Calculate rate base using 13 month average balance, except ADIT.  The calculation of ADIT in the annual true-up calculation will use the beginning-of-year and end-of-year balances, and will be performed in accordance with IRS regulation Section 1.167(l)- 1(h)(6).  The calculation of ADIT in the annual projection will be performed in accordance with IRS Regulation Section 1.167(l)-1(h)(6).

Removes dollar amount of transmission plant to be included in the development of OATT ancillary services rates and generation step-up facilities, which are deemed to be included in OATT ancillary services. For these purposes, generation step-up facilities are those facilities at a generator substation on which there is no through-flow when the generator is shut down.

Upon enactment of changes in tax law, ADIT balances are re-measured and adjusted in the Company’s books of account, resulting in excess or deficient accumulated deferred income tax assets and liabilities.  Excess or deficient ADIT attributable to timing differences between the amounts of expenses or revenues recognized for income tax purposes and amounts of expenses or revenues recognized for ratemaking purposes as well as subsequent recoverable or refundable amortization of such amounts will be based upon Company records and be calculated and recorded in accordance with ASC 740 and any applicable normalization requirements of the taxing jurisdiction.  The Deficient or (Excess) Deferred Income Tax Adjustment (page 3, line 44) is computed by multiplying each component of Deficient or (Excess) Deferred Income Taxes (page 3, line 40) by the applicable tax gross-up factor.  For each re-measurement of ADIT, the amounts entered as the Deficient or (Excess) Accumulated Deferred Income Taxes component of ADJUSTMENTS TO RATE BASE (page 2, line 22a) or as the Deficient or (Excess) Deferred Income Tax Adjustment component of INCOME TAXES (page 3, line 44) will be supported by Attachment 13 (Deficient or Excess Accumulated Deferred Income Taxes) providing the balance for each taxing jurisdiction at the beginning and end of the year, amortization for the year, calculation of the gross-up to the revenue requirement level and any other information required to support compliance with any applicable normalization requirements.

PDF page 67

Page 1 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
To be completed in conjunction with Appendix III. Line

(1) (2)
(3) (4)
No.
Appendix III, Page, Line, Col.
Transmission
Allocator
1
Gross Transmission Plant plus CWIP
Appendix III, p 2, line 2, col 5 plus line 25, col 5 (Note A)
                                                         -
2
Net Transmission Plant plus CWIP and Abandoned Plant Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5 (Note B)

                                                         -
O&M EXPENSE
3
Total O&M Allocated to Transmission
Appendix III, p 3, line 17, col 5
                                                         -
4
Annual Allocation Factor for O&M
(line 3 divided by line 1, col 3)
0.00%
0.00%
GENERAL AND INTANGIBLE (G&I) DEPRECIATION EXPENSE 5

Total G&I Depreciation Expense
Appendix III, p 3, line 20, col 5 (Note C)
                                                         -
6
Annual Allocation Factor for G&I Depreciation Expense (line 5 divided by line 1, col 3)

0.00%
0.00%
TAXES OTHER THAN INCOME TAXES
7
Total Other Taxes
Appendix III, p 3, line 32, col 5
                                                         -
8
Annual Allocation Factor for Other Taxes
(line 7 divided by line 1, col 3)
0.00%
0.00%
9
Less Revenue Credits
Appendix III, p 1, line 6 col 5
                                                         -
10
Annual Allocation Factor for Revenue Credits (line 9 divided by line 1, col 3)

0.00%
0.00%
11
Annual Allocation Factor for Expense
Sum of lines 4, 6, 8, and 10
0.00%
INCOME TAXES
12
Total Income Taxes
Appendix III, p 3, line 46, col 5
                                                         -
13
Annual Allocation Factor for Income Taxes
(line 12 divided by line 2, col 3)
0.00%
0.00%
RETURN
14
Return on Rate Base
Appendix III, p 3, line 48, col 5
                                                         -
15
Annual Allocation Factor for Return on Rate Base (line 14 divided by line 2, col 3)

0.00%
0.00%
16
Annual Allocation Factor for Return
Sum of lines 13 and 15
0.00%

PDF page 68

Page 2 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template.
(1) (2)
(3) (4)
(5) (6)
(7) (8)
Project Name
CAISO Category
Identifier
Project Gross Plant
Project Net Plant
Annual Return Charge
(Note D)
(Page 1, line 11)
(Col. 3 * Col. 4)
(Note E)
(Page 1, line 16)
(Col. 6 * Col. 7)
1a
Project A
AAAA
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
1b
Project B
BBBB
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
2
Total Schedule 12
                                                  -
                       -    $                                                      -
                                        -
3a
Project C
CCCC
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
3b
Project D
DDDD
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
4
Total Zonal
                                                  -
                       -    $                                                      -
                                        -
5
Other
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
6
Annual Totals
                                                  -
                       -    $                                                      -
                                        -
This worksheet is used to compute project specific revenue requirements for any projects for which such calculation is required by CAISO. Other projects which comprise the remaining revenue requirement on Appendix III will not be entered on this schedule.

Line
No.
Annual Allocation
Factor for Expense
Annual
Expense
Charge
Annual
Allocation
Factor for
Return

PDF page 69

Page 3 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
(9) (10)
(11) (12)
(12a) (13)
(14) (15)
(16) Incentive Return
Ceiling Rate
(Note F)
(Sum Col. 5, 8 & 9)
(Note G)
(Sum Col. 10 & 12)
(Note H)
(Sum Col. 10 & 12 Less Col. 13)
(Note I)
(Sum Col. 14 & 15)
1a
                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
1b
                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
2
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                           - 3a

                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
3b
                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
4
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                           - 5

                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
6
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                           - Notes

A
Gross Transmission Plant is that identified on page 2 line 2 of Appendix III inclusive of any CWIP or unamortized abandoned plant included in rate base when authorized by FERC order. B

Net Plant is that identified on page 2 line 14 of Appendix III inclusive of any CWIP or unamortized Abandoned Plant included in rate base when authorized by FERC order less any prefunded AFUDC, if applicable. C

D
E
Project Net Plant is the Project Gross Plant Identified in Column 3 less the associated Accumulated Depreciation plus CWIP in rate base if applicable and Unamortized Abandoned Plant.  Refer to Attachment 1a for detail. F

G
Requires approval by FERC of incentive return applicable to the specified project(s).
H
I
True-Up Adjustment is calculated on the Project True-up Schedule for the relevant true-up year.
Line
No.
Project
Depreciation/Amortizatio
n Expense
Annual Revenue
Requirement
Incentive Return in
Basis Points
Competitive
Concession
Total Annual Revenue
Requirement
True-Up
Adjustment
Net Revenue
Requirement
(Attachment 2, Line 28 Incentive
Return * Col. 6 * Col. 11/100)
General and Intangible Depreciation and Amortization Expense includes all expenses (except depreciation and armortization of G&I Asset Retirement Obligations) not directly associated with a project, which is entered on page 3 , column 9.

Project Gross Plant is the total capital investment including CWIP for the project calculated from Company books and records in the same method as the gross plant value in line 1.  This value includes subsequent capital investments required to maintain the facilities to their original capabilities.  Refer to Attachment 1a for detail.

Project Depreciation Expense is the actual value booked for the project (excluding General and Intangible depreciation) at Appendix III, page 3, line 19, plus amortization of Abandoned Plant at Appendix III, page 3, line 21.  For each project on Attachment 1a, Depreciation Expense is Attachment 1a, Line 2, Column (15) minus Column (3), and Amortization of Abandoned Plant is the difference between Columns (3) and (15) on Attachment 1a, Line 4. The Competitive Concession is the reduction in revenue, if any, that the company agreed to, for instance, to be selected to build facilities as the result of a competitive process and equals the amount by which the  annual revenue requirement is reduced from the ceiling rate.

PDF page 70

Att 1a - Project Plant Detail
 Page 10
Page 1 of 1
For the twelve months ended 12/31/__
Attachment 1a
Project Plant Detail Worksheet
DesertLink, LLC
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
1a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1

Total Project Transmission Gross Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
2a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2

Total Project Transmission Accumulated Depreciation
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
3a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3

Total Project CWIP
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
4a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4

Total Project Unamortized Abandoned Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
Project Name
5a
Project A
                                                                -
5b
Project B
                                                                -
…
…
 …
5
Total Project Transmission Net Plant
                                                                -   Ties to Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5; Used on Attachment 1, Column (6)
Line
No.
Project
Transmission
Gross Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission Accumulated
Depreciation
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project CWIP
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Unamortized Abandoned Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission
Net Plant
13-month average
(Line 1 - Line 2 + Line 3 + Line 4)

PDF page 71

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 2
Incentive Return
DesertLink, LLC
Line
1
Rate Base
Appendix III, Page 2, Line 35, Col.5
                                                                         -
2
100 Basis Point Incentive Return
$
Cost
$
%
Weighted
3
Long Term Debt
(Notes Q & R from Appendix III)
                            -
50.00%
0.00%
0.00%
4
Preferred Stock
(Notes Q & R from Appendix III)
                            -
0.00%
0.00%
0.00%
5
Common Stock
(Notes Q, R, & T from Appendix III)
                            -
50.00%
10.80%
5.40%
6
Total (sum lines 3-5)
                            -
5.40%
7
100 Basis Point Incentive Return multiplied by Rate Base (line 1 * line 6)
                                                                         -
8
INCOME TAXES
9
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =
0.00%
10
CIT=(T/1-T) * (1-(WCLTD/R)) =
0.00%
11
WCLTD
Line 3
0.00%
12
FIT, SIT & p are as given in Appendix III footnote N.
13
1 / (1 - T)
Line 9
                    1.0000
14
Amortized Investment Tax Credit (266.8f) (enter negative)
Appendix III, Page 3, Line 39
                            -
15
Deficient or (Excess) Deferred Income Taxes
Appendix III, Page 3, Line 40
                            -
16
Tax Effect of Permanent Differences (Note B)
Appendix III, Page 3, Line 41
                            -
17
Income Tax Calculation
Line 7 times Line 10
                        -
18
ITC adjustment
Line 13 times Line 14
                            -
NP             1.00                         -
19
Deficient or (Excess) Deferred Income Tax Adjustment
Appendix III, Page 3, Line 44
                            -
NP             1.00                         -
20
Permanent Differences Tax Adjustment
Line 13 times Line 16
                            -
NP             1.00                         -
21
Total Income Taxes
Sum of Lines 17 through 20
                            -
                        -                                                                            - 22

Return and Income Taxes with 100 basis point increase in ROE
                                                                         -
23
Return
(Appendix III, page 3, line 48, col 5)
                                                                         -
24
Income Tax
(Appendix III, page 3, line 46, col 5)
                                                                         -
25
Return and Income Taxes without 100 basis point increase in ROE Sum of Lines 23 and 24

                                                                         -
26
Incremental Return and Income Taxes for 100 basis point increase in ROE Line 22 less Line 25

                                                                         -
27
Rate Base
Line 1
                                                                         -
28
Incremental Return and Income Taxes for 100 basis point increase in ROE divided by Rate Base Line 26 divided by Line 27 0.00%

Notes
A
B
The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Cost = Appendix III, Page 4, Line 17,

plus 100 bp
The 100 basis point increase in ROE is used only to determine the increase in return and income taxes associated with a 100 basis point increase in ROE and does not reflect what incentives the Commission may approve for a specific transmission project. The overall ROE inclusive of incentives is subject to the limitations noted in Appendix III, Note T.  Any ROE actual incentive must be approved by the Commission.

PDF page 72

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 3
Formula Rate True-Up
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template. Annual True-Up Calculation

Line
1
True-Up Year
2
C
D
                             -
F
G
H
I
J
A
B
E
Project Name
3
Remaining Appendix III
0.0%
                             -
                               -    $                          -
                             -
4a
Project A
AAAA
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
4b
Project B
BBBB
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
5 Total Schedule 12
                             -
                             -                                  -                                  -    $                          -                                -                                -
6a
Project C
CCCC
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
6b
Project D
DDDD
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
7
Total Zonal
                             -
                             -                                  -                                  -    $                          -                                -                                -
8
Other
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
9
                             -
0.0%
                             -                                  -                                  -                                -                                -                                -
10
 $                          -   Total Interest on True-Up - Attachment 6
Prior Period Adjustment
A
B
Source
11
Description of Adjustment
                 -
Notes
1) The revenue received is the total amount of revenue distributed to company in the  year as shown on pages 328-330 of the Form No 1. The Revenue Received is input on line 2, Col. E.
2) From the Attachment 1, lines 1a through 6, col. 16 from the template in which the true-up year revenue requirement was initially projected.
3) From True-Up revenue requirement template Attachment 1, lines 1a through 6, col. 14.
4) 5)
Corrections to true-ups for previous rate years including interest will be computed on Attachment 11 and entered on the appropriate line 3-8 above.
This Attachment 3 is used to calculate the annual formula rate true-up. Any projects for which the RTO requires a true-up on an individual project basis, as shown on Attachment 1, will be computed separately. The remainder of the revenue requirement will also be trued up. The utility will individually enter the projected true-up year revenue requirements in Column C. A percentage of total will be calculated in Column D. Actual revenue received during the true-up year is entered into Column E, line 2 and allocated using the Column D percentage. The utility will prepare this formula rate template with the actual inputs for the true-up year, with the resulting revenue requirement for each line being separately entered in Column F.  In Col. G, Col. F is subtracted from Col. E to calculate the true-up adjustment. Interest on the true-up is computed in Column H. Any adjustments to prior period true-ups are entered in Col.

I.  Col. J computes the total true-up as the sum of Col. G, H and I.
Projected True-Up Year Revenue
Requirement Calculation
True-Up Year
Revenue Received1
Actual True-Up
Year Revenue Req.
CAISO
Identification
Project # Or
Other
Identifier
Net Revenue
Requirement2
% of Total
Revenue
Requirement
Allocation of
Revenue Received

                    (E, Line
2) x (D)
True-Up Net Revenue
Requirement3
Net Under/(Over)
Collection   (F)-(E)
True-Up Interest
Income (Expense)4
(D) x (H, line 10)
Prior Period
Adjustment with
Interest5
Total True-Up
(G) + (H) + (I)
Total Annual Revenue
Requirements
Prior Period Adjustment
(Note 5)
Adjustment
Amount
Attachment
11
Interest due on the true up is calculated for the 24 month period from the start of the true-up year until the end of the year following the true-up year when the true up will be included in rates. Total True up Interest calculate on Attachment 6 and allocated to projects based on the percentage in Column D.

PDF page 73

Page 1 of 2
For the twelve months ended 12/31/__
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Gross Plant in Service
CWIP
LHFFU
Working Capital
Accumulated Depreciation
Month
Transmission
CWIP in Rate Base
Held for Future Use
Materials & Supplies
Prepayments
Transmission
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (Note A)
1
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 2

January
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 3

February
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 4

March
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 5

April
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 6

May
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 7

June
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 8

July
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 9

August
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 10

September
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 11

October
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 12

November
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 13

December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 14

                             -                                -                                  -                                       -                                      -                                      -                                    -                                    - Adjustments to Rate Base

Month
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(Note A)
Note C
Note D
272.8.b & 273.8.k
274.2.b & 275.2.k
276.9.b & 277.9.k
234.8.b & c
15
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 16

January
                   -                                -                                -
                                 -
17
February
                   -                                -                                -
                                 -
18
March
                   -                                -                                -
                                 -
19
April
                   -                                -                                -
                                 -
20
May
                   -                                -                                -
                                 -
21
June
                   -                                -                                -
                                 -
22
July
                   -                                -                                -
                                 -
23
August
                   -                                -                                -
                                 -
24
September
                   -                                -                                -
                                 -
25
October
                   -                                -                                -
                                 -
26
November
                   -                                -                                -
                                 -
27
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 28

                             -                                -                                  -                                       -                                      -                                      -                                    -
Line
No
General &
Intangible
General & Intangible
207.58.g less
207.57.g for end of
year, records for
other months
205.5.g & 207.99.g
less 207.98.g for
end of year, records
for other months
Note B - page 2,
column C
214.47.d for end of
year, records for other
months
227.8.c & 227.16.c for
end of year, records for
other months
111.57.c for end of
year, records for other
months
219.25.c less ARO for
end of year, records
for other months
219.28.c & 200.21.c
less ARO for end of
year, records for other
months
Average of the 13
Monthly Balances
Unamortized
Regulatory Asset
Unamortized
Abandoned Plant
Account No. 281
Accumulated
Deferred Income
Taxes (Note E)
Account No. 282
Accumulated Deferred
Income Taxes (Note E)
Account No. 283
Accumulated Deferred
Income Taxes (Note E)
Account No. 190
Accumulated
Deferred Income
Taxes (Note E)
Account No. 255
Accumulated
Deferred Investment
Credit (Note I)
Consistent with
266.8.b & 267.8.h
Average of the 13
Monthly Balances

PDF page 74

Page 2 of 2
For the twelve months ended 12/31/
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Total CWIP
(a) (b)
(c) = (a) - (b)
Company records
29
December
                   -                                -                                -                                  -
30
January
                   -                                -                                -                                  -
31
February
                   -                                -                                -                                  -
32
March
                   -                                -                                -                                  -
33
April
                   -                                -                                -                                  -
34
May
                   -                                -                                -                                  -
35
June
                   -                                -                                -                                  -
36
July
                   -                                -                                -                                  -
37
August
                   -                                -                                -                                  -
38
September
                   -                                -                                -                                  -
39
October
                   -                                -                                -                                  -
40
November
                   -                                -                                -                                  -
41
December
                   -                                -                                -                                  -
                             -                                -                                  -
Unfunded Reserves   (Notes A and F and G)
(a) (b)
(b.i)
(b.ii)
(c) (d)
(e) (f)
(g) (h)
List of all reserves
Amount
42a
Reserve 1
 -
 -
                               -
 -
 -
 -
                                 -                                    -
42b
Reserve 2
 -
 -
                               -
 -
 -
 -
                                 -                                    -
43
Total
                               -
                                 -
Notes:
A
Calculate using 13 month average balance, except ADIT which is calculated based on the average of the beginning of the year and the end of the year balances
B
C
D
Recovery of abandoned plant is limited to any abandoned plant recovery authorized by FERC.
E
ADIT is computed using the average of the beginning of the year and the end of the year balances. Electric ADIT only, Excludes ARO-related ADIT.
F
G
H
I
Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income.
Reconciliation of CWIP in Rate Base to FERC Form 1 - Note B
Less: CWIP and
AFUDC Excluded
from Rate Base
CWIP allowed in
Rate Base
216.b for end of
year, records for
other months
Average of the 13
Monthly Balances
FERC balance sheet
account where
reserves are
recorded
FERC income
statement account
where expenses are
recorded
Enter 1 if NOT in a
trust or reserved
account, enter zero (0)
if included in a trust or
reserved account
Enter 1 if the accrual
account is included in
the formula rate, enter
(0) if the accrual
account is NOT
included in the formula
rate
Enter the percentage
paid for by customers
less the percent
associated with an
offsetting liability on
the balance sheet (Note
H) Allocation (Plant or
Labor Allocator)
Amount Allocated,
col. c x col. d x col. e
x col. f x col. g
Recovery of CWIP in rate base must be approved by FERC.  Lines 29-41 of page 2 provide a reconciliation of the Company's total CWIP to the CWIP allowed in rate base. The annual report filed pursuant to the Protocols will include for each project under construction (i) the CWIP balance eligible for inclusion in rate base; (ii) the CWIP balance ineligible for inclusion in rate base; and (iii) a demonstration that AFUDC is only applied to the CWIP balance that is not included in rate base The annual report will also describe the reconciliation prepared on this Attachment

Recovery of a Regulatory Asset is permitted only for pre-commercial and formation expenses, and is subject to FERC approval before the amortization of the Regulatory Asset can be included in rates. Recovery of any other regulatory assets requires authorization from the Commission.

The Formula Rate shall include a credit to rate base for all unfunded reserves (funds collected from customers that (1) have not been set aside in a trust, escrow or restricted account; (2) whose balance are collected from customers through cost accruals to accounts that are recovered under the Formula Rate; and (3) exclude the portion of any balance offset by a balance sheet ac count (see Note H)).  Each unfunded reserve will be included on lines 42 above. The allocator in Col. (g) will be the same allocator used in the formula for the cost accruals to the account that is recovered under the Formula Rate.  Since reserves can be created by creating an offsetting balance sheet account, rather than through cost accruals, the amount to be deducted from rate base should exclude the portion offset by another balance sheet account. Not all unfunded reserves are created only from contributions from customers. Many are created by creating an offsetting liability in whole or in part.  Column (f) ensures only the portion of the unfunded reserve contributed by the customer (and not created by an offsetting liability) is a reduction to rate base.

The inputs in Column (f) are the percentage of the unfunded reserve that was created by an offsetting liability. The percentage shown in Column (f) is then equal to the percentage that customers have contributed to the unfunded reserve.

PDF page 75

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 5
Return on Rate Base Worksheet
DesertLink, LLC
RETURN ON RATE BASE ( R )
$
1
Long Term Interest (117, sum of 62.c through 67.c) (Note D)
                                -
2
Preferred Dividends (118.29c) (positive number)
                                -
3
Proprietary Capital (Line 25 (c))
                                -
4
Less Preferred Stock (Line 9)
                                -
5
Less Account 216.1 Undistributed Subsidiary Earnings (Line 25 (d))
                                -
6
Less Account 219 Accum. Other Comprehensive Income (Line 25 (e))
                                -
7
Common Stock
(Sum of Lines 3 through 6)
                                -
$
%
Cost
Weighted
8
Long Term Debt
Line 25 (a), Note A and Appendix III Note Q
                                -
50.00%
0.000%
0.00%
=WCLTD
9
Preferred Stock
Line 25 (b), Note B and Appendix III Note Q
                                -
0.00%
0.00%
0.00%
10
Common Stock
Line 7, Note C  and Appendix III Notes Q and T
                                -
50.00%
9.80%
4.900%
11
Total
(Sum of Lines 8 through 10)
                                -
4.90%
=R
(a) (b)
( c )
(d) ( e )
Monthly Balances for Capital Structure
12
December (Prior Year)
                               -                                 -                             -                                   -                                 - 13

January
                               -                                 -                             -                                   -                                 - 14

February
                               -                                 -                             -                                   -                                 - 15

March
                               -                                 -                             -                                   -                                 - 16

April
                               -                                 -                             -                                   -                                 - 17

May
                               -                                 -                             -                                   -                                 - 18

June
                               -                                 -                             -                                   -                                 - 19

July
                               -                                 -                             -                                   -                                 - 20

August
                               -                                 -                             -                                   -                                 - 21

September
                               -                                 -                             -                                   -                                 - 22

October
                               -                                 -                             -                                   -                                 - 23

November
                               -                                 -                             -                                   -                                 - 24

December
                               -                                 -                             -                                   -                                 - 25

13-Month Average
                               -                                 -                             -                                   -                                 - Notes

A
B
Preferred Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112 line 3.c in the Form No. 1 C

Common Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on Form 1 page 112 line 16.c less lines 3.c , 12.c, and 15.c D

Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies Long Term Debt

(Note A)
Preferred Stock
(112.3.c)
Proprietary
Capital (112.16.c)
Undistributed Sub
Earnings 216.1
(112.12.c)
Accum Other Comp.
Income 219
(112.15.c)
Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, lines 18.c to 21.c, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 76

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6
Interest on True-Up
DesertLink, LLC
Appendix III K23
Line
Rate Year
Rate Year
Projected Revenue Requirement (Note A)
1
                                                                                         -
Less
 $                             -
Equals
 $                        -
Note A - Projected ATRR for the true-up year from Page 1, Line 1 of Projection Appendix III minus Line 6 of Projection Appendix III. Note B - Actual Net ATRR for the true-up year from Page 1, Line 9 of True-Up Appendix III. Interest Rate on Amount of Refunds or Surcharges

Months
Amortization
2
0.000%
An over or under collection will be recovered pro rata over year collected, held for one year and returned pro rata over next year Monthly

3
January
Rate Year
                                -
0.000%
12
                          -
                              -
4
February
Rate Year
                                -
0.000%
11
                          -
                              -
5
March
Rate Year
                                -
0.000%
10
                          -
                              -
6
April
Rate Year
                                -
0.000%
9
                          -
                              -
7
May
Rate Year
                                -
0.000%
8
                          -
                              -
8
June
Rate Year
                                -
0.000%
7
                          -
                              -
9
July
Rate Year
                                -
0.000%
6
                          -
                              -
10
August
Rate Year
                                -
0.000%
5
                          -
                              -
11
September
Rate Year
                                -
0.000%
4
                          -
                              -
12
October
Rate Year
                                -
0.000%
3
                          -
                              -
13
November
Rate Year
                                -
0.000%
2
                          -
                              -
14
December
Rate Year
                                -
0.000%
1
                          -
                              -
15
                          -
                              -
Annual
16
January through December
Rate Yr. + 1                                 -
0.000%
12
                          -
                              -
Over (Under) Recovery Plus Interest Amortized and Recovered Over 12 Months Monthly

17
January
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 18

February
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 19

March
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 20

April
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 21

May
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 22

June
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 23

July
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 24

August
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 25

September
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 26

October
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 27

November
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 28

December
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 29

                          -
30
Total Amount of True-Up Adjustment
 $                           -
31
Less Over (Under) Recovery
 $                        -
32
Total Interest
 $                           -
Actual Net Revenue
Requirement (Note B)
Over (Under)
Recovery
Over (Under)
Recovery Plus
Interest
Monthly Interest
Rate on Attachment
6a
Calculated
Interest
Surcharge (Refund)
Owed
Calculation of Interest

PDF page 77

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6a
True-Up Interest Rate Calculator
DesertLink, LLC
This Attachment is used to compute the interest rate to be applied to each year's revenue requirement true-up.
Applicable FERC Interest Rate (Note A):
1
Rate Year January
0.00%
2
Rate Year February
-
3
Rate Year March
-
4
Rate Year April
-
5
Rate Year May
-
6
Rate Year June
-
7
Rate Year July
-
8
Rate Year August
-
9
Rate Year September
-
10
Rate Year October
-
11
Rate Year November
-
12
Rate Year December
-
13
Rate Year Plus 1  January
-
14
Rate Year Plus 1  February
-
15
Rate Year Plus 1  March
-
16
Rate Year Plus 1  April
-
17
Rate Year Plus 1  May
-
18
Average Rate
0.00%
19
Monthly Average Rate
0.00%
Note A - Lines 1-17 are the FERC interest rates under section 35.19a of the regulations for the period shown. Line 18 is the average of lines 1-17.

PDF page 78

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 7
Weighted Average Federal and State Income Tax Rates
DesertLink, LLC
Subchapter C
Mutual
Pensions, IRAs
UBTI
Non-Taxpaying
Weighted
Line
Description
Source
Corporations
Individuals
Funds
Keogh Plans
Entities
Entities
Average
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) 1
Weighted Marginal Federal Income Tax Rate
Note A
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
2
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
3
Weighted Average
Line 1 x Line 2
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4
Weighted Average Federal Income Tax Rate
Sum of Line 3, Col. (c)-(h)
0.00%
5
Weighted Marginal State Income Tax Rate
Note C
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
6
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
7
Weighted Average
Line 5 x Line 6
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
8
Weighted Average State Income Tax Rate
Sum of Line 7, Col. (c)-(h)
0.00%
A
For each Rate Year, DesertLink will develop a schedule calculating the weighted average federal income tax rate for each category of partners. B

This percentage is developed based on the distributive income allocated to each category of partners rather than their respective ownership percentages. C

For each Rate Year, DesertLink will develop a schedule calculating the weighted average state income tax rate for each category of partners.

PDF page 79

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 8
Cost of Debt Prior to Issuing Non-Construction Financing
DesertLink, LLC
This Attachment 8 is to be utilized to determine the cost of debt prior to issuing non-construction financing.  Once non-construction financing is issued the cost of debt shall be determined using the methodology described in Note Q on Appendix III. If construction debt has not or will not be issued when construction starts, a proxy rate will be used for the cost of debt, which will be supported in the initial section 205 filing. The proxy rate will be entered on line 36 of this attachment. If construction financing is obtained, all rates, fees and monthly debt balances will be subject to true up pursuant to Attachment 9. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template. Line No

1
Interest rate on Construction Debt for Rate Year - Line 19 (g)
0.00%
2
Rate Year Debt Fee expense - Line 35 (e)
0.00%
3
Total Cost of Debt - Sum of Lines 1 and 2
0.0000%
Interest Rate Information
4
Commitment Fee Rate (%)
5
Projected Average Drawn Rate for Rate Year (%) - Note A
Month During Rate Year
Total Loan Amount ($000)
Interest Expense ($000)
(a) (b)
(c) (d)
(e) (f)
(g) 6
December Prior Year
                            -                                         -                                          -                                          - 7

January
                            -                                         -                                          -                                          - 8

February
                            -                                         -                                          -                                          - 9

March
                            -                                         -                                          -                                          - 10

April
                            -                                         -                                          -                                          - 11

May
                            -                                         -                                          -                                          - 12

June
                            -                                         -                                          -                                          - 13

July
                            -                                         -                                          -                                          - 14

August
                            -                                         -                                          -                                          - 15

September
                            -                                         -                                          -                                          - 16

October
                            -                                         -                                          -                                          - 17

November
                            -                                         -                                          -                                          - 18

December
                            -                                         -                                          -                                          - 19

Average of the 13 Monthly Balances
                            -
                                        -                                          -
0.00%
Example Fee Calculation - All amounts represent actual rate year expenses.
(a) (b)
(c) (d)
(e) (f)
(g) Origination Fees
Rate/Fees
Gross Fee Amount ($000)
Year Fee Incurred
20
Underwriting Discount
0.00%
 -
 -
21
Arrangement Fee
0.00%
 -
 -
22
Upfront Fee
0.00%
 -
 -
23
Rating Agency Fee
0.00%
 -
 -
24
Legal Fees
0.00%
 -
 -
25
Other
0.00%
 -
 -
26
   Total Issuance Expense / Origination Fees - Sum of Lines 20-25
 -
 -
 -
 -
27
28
Annual Fees
29
Annual Rating Agency Fee
0.00%
N/A
 -
N/A
N/A
30
Annual Bank Agency Fee
0.00%
N/A                                      -
N/A
N/A
31
Utilization Fee
0.00%
N/A
 -
N/A
N/A
32
Other Fees
0.00%
N/A
 -
N/A
N/A
33
Total Fees
 -
 -
 -
 -
34
13 Month Average Debt balance - Line 19 (c)
                                        -
35
Rate Year cost of fees
0.00%
36
Proxy Debt rate. Used prior to issuance of construction financing and supported in initial section 205 filing. 3.2220%

Notes
A
LIBOR
0.0000%
Spread
2.3500%
Total
2.3500%
If construction financing has been obtained, the cost of debt prior the issuance of non-construction financing shall be based on the terms of the construction financing and determined below. Up-front fees including origination fees will be amortized and included in the cost of debt.

Principal Drawn
($000)
Unutilized Loan
Balance ($000)
Commitment Fee &
Utilization Fee ($000)
Effective Annual
Interest Rate (%)
Fee Amortization Period
(years)
Rate Year Amortized Fee
Amount, col. b / col. d
Prior Years Accumulated
Fee Amortization
Unamortized Balance
- End of Rate Year
Projected rate will be Average LIBOR for rate year + spread. Spread will be supported in initial section 205 filing. LIBOR will be updated based on information in the Wall Street Journal as of the 15th day of the month prior to population of this template.

PDF page 80

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 9
True-Up - Construction Financing Cost of Debt
DesertLink, LLC
One time up-front debt fees, including origination fees will be amortized and included in the cost of debt.
Line No.
$
1
Long Term Interest and Fees (117, sum of 62.c through 67.c) -- Notes A and B
                                    -
2
Line of Credit Fees (68.c) -- Note C
                                    -
3
Total Interest and Fees
                                    -
13 Month Average Long-Term Debt - Notes A and D
Month During Rate Year
Long Term Debt
(a) (d)
4
December Prior Year
                                    -
5
January
                                    -
6
February
                                    -
7
March
                                    -
8
April
                                    -
9
May
                                    -
10
June
                                    -
11
July
                                    -
12
August
                                    -
13
September
                                    -
14
October
                                    -
15
November
                                    -
16
December
                                    -
17
Average of the 13 Monthly Balances
                                    -
18
True-Up Cost of Debt (Line 3 / Line 17)
0.00%
Notes
A
B
Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies.
C
Line of credit fees will include only those related to long-term debt and not for short-term debt.
D
Long-term debt will exclude any short-term debt included in FERC Account 233, Notes Payable to Associated Companies.
This Attachment 9 is to be utilized only in the event construction financing has been obtained to compute the actual cost of debt to be included in the return on rate base calculation for the true-up each year prior to the issuance of non-construction financing. Once non-construction financing has been obtained the cost of debt shall be determined using the methodology described in Note Q on Appendix III. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template.

Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, line 24, columns d and c, respectively, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 81

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 10
Depreciation Rates
DesertLink, LLC
TRANSMISSION AND GENERAL PLANT DEPRECIATION RATES
Annual Depreciation Rates
Line No.
(Note A)
INTANGIBLE PLANT
1
303.1
Contributions in Aid of Construction
Note B
2
303.2
Interconnections
2.27%
3
303.3
Licenses
1.59%
TRANSMISSION PLANT
4
350.2
Land Rights
1.43%
5
351.1
Computer Hardware
20.00%
6
352.0
Structures & Improvements
1.95%
7
353.0
Station Equipment
2.58%
8
354.0
Towers & Fixtures
1.86%
9
355.0
Poles & Fixtures
2.17%
10
356.0
Overhead Conductors & Devices
2.01%
11
392.0
Transportation Equipment
10.00%
12
393.0
Stores Equipment
6.67%
13
394.0
Tools, Shop, and Garage Equipment
12.50%
14
397.2
Computer Software
11.64%
Notes
A
These depreciation rates will not be changed absent a FERC order.
B
GENERAL PLANT
In the event a Contribution in Aid of Construction (CIAC) is made for a transmission facility, the transmission depreciation rates above will be weighted based on the relative amount of underlying plant booked to the accounts shown in lines 4-12 above, and the resultant weighted average depreciation rate will be used to amortize the CIAC.   The CIAC depreciation rate for each facility will be determined at the time the plant is placed into service, and will not change  without FERC approval.

PDF page 82

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 11
Prior Period Adjustments
DesertLink, LLC
(a) (b)
Calendar Year
Line No. Description
Source
Revenue Impact of Correction
Revenue Requirement
1
Filing Name and Date
                                                        -
2
Original Revenue Requirement
                                                              -
3
4
Description of Correction 1
                                                              -
5
Description of Correction 2
                                                              -
6
7
Total Corrections
Line 4 + 5
                                                              -
8
9
Corrected Revenue Requirement
Line 2 + 7
                                                              -
10
11
12
Total Corrections
Line 7
                                                              -
13
14
Average Monthly FERC Refund Rate
Note A
0.00%
15
Number of Months of Interest
Note B
30
16
Interest on Correction
Line 12 x 14 x 15
                                                              -
17
18
Total Annual Amount Due from / (to) Customers
Line 12 + 16
                                                              -
Notes
A
B
The interest rate on corrections will be the average monthly FERC interest rate for the period from the beginning of the year being corrected through the most recent  month available as of the time the correction is computed and included in an annual filing.

The number of months interest due on the correction will be the number of months from the beginning of the year being corrected through June of the year in which the correction will be reflected in rates. In this manner the interest computed will reflect all years prior to when the correction is reflected in rates plus interest on the average unrefunded balance of the correction during the year the correction is reflected in rates.

PDF page 83

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 12
Revenue Credit Detail
DesertLink, LLC
(a) (b)
(c) = (a) - (b)
Line No.
(Note A)
Source
Company Total
Less: Non Transmission
Transmission-related
1
Account 454 - Rent from Electric Property
2
Joint pole attachments - telephone
Company books
                                          -                                                      -                                                                                                                 - 3

Joint pole attachments - cable
Company books
                                          -                                                      -                                                                                                                 - 4

Underground rentals
Company books
                                          -                                                      -                                                                                                                 - 5

Transmission tower wireless rentals
Company books
                                          -                                                      -                                                                                                                 - 6

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 7

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 8

Account 454 Revenue Credit
Form 1 300.19.b
                                          -                                                      -                                                                                                                 - 9

Account 456.1 Other Operating Revenues
10
CAISO NITS
Company books
                                          -                                                      -                                                                                                                 - 11

CAISO Point to Point
Company books
                                          -                                                      -                                                                                                                 - 12

Over/Under recovery deferral
Company books
                                          -                                                      -                                                                                                                 - 13

Other Transmission Service Revenues
Company books
                                          -                                                      -                                                                                                                 - 14

Other
Company books
                                          -                                                      -                                                                                                                 - 15

Total Per Books
Form 1 330.n
                                          -                                                      -                                                                                                                 - 16

Less: revenues received pursuant to this Formula Rate
                                          -                                                      -                                                                                                                 - 17

Less: Over/Under recovery deferral
                                          -                                                      -                                                                                                                 - 17a

Less: Revenue Credits included in the TRBAA
                                          -                                                      -                                                                                                                 - 18

Account 456.1 Revenue Credit
                                          -                                                      -                                                                                                                 - 19

Total Revenue Credits
(Line 8 + line 18)
                                          -                                                      -                                                                                                                 - Note A

All 454 and 456.1 revenues will be detailed from Company books and records or FERC Form 1, and additional rows added if necessary.  Non-transmission-related amounts will be deducted to determine transmission-related amounts. (Line 15 - line 16 - line 17

- line 17a)

PDF page 84

DesertLink, LLC
Attachment 13 - Excess or Deficient Accumulated Deferred Income Taxes - Summary
[Year]
[Projected or Actual]
Line No.
1
2
[List of tax law changes, accounting treatment, and asscociated explanatory notes.]
3
Rate Base Adjustment Mechanism - Summary
4
Account
Amount
References
5
182.3 (debit or <credit>)
                        -
6
254 (debit or <credit>)
                        -
7
Total Deficient or (Excess) ADIT (sum of lines 5-6)
                        -   To Appendix III, Page 2, Line 22a, Col. (3)
8
9
Income Tax Allowance Adjustment Mechanism - Summary
(a) (b)
(c) (d)
(e) (f)
10
11
[Insert rows as necessary]
                        -
                        -
11a
[Insert rows as necessary]
                        -
                        -
11…
[Insert rows as necessary]
                        -
                        -
12
Total
(sum of lines 11_)
                        -
                        -
13
14
[Explanatory statements as needed]
The primary purposes of this worksheet are to:
 - reconcile the amounts of regulatory assets and liabilities comprising the rate base adjustment mechanism on Appendix III, Page 2, Line 22a (ADJUSTMENTS TO RATE BASE > Deficient or (Excess) ADIT) as of the beginning and end of the current test period (summarized beginning at Line 3 below) and

- to support the amount of excess deferred tax expense or benefit recognized due to enacted change(s) in tax rate(s) on Appendix III, Page 3, Line 40 (INCOME TAXES > Deficient or (Excess) Deferred Income Taxes) and the effect of such excess deferred tax expense or benefit on the revenue requirement as reflected in the income tax allowance adjustment mechanism on Appendix III, Page 3, Line 44 (INCOME TAXES > Deficient or (Excess) Deferred Income Tax Adjustment) during the test period (summarized beginning on Line 9 below).

This worksheet supports the computation of the projected revenue requirement or, as appropriate, the actual revenue requirement used to compute the true-up adjustment.
Each tax law change addressed by this worksheet with its associated explanatory note is listed below.  Amounts related to each tax law change are provided and supported throughout this worksheet.  Additional lines and explanatory notes will be added to this worksheet as necessary as tax law changes are enacted without the need for an FPA Section 205 filing.

The amounts summarized above are computed in the Rate Base Adjustment Mechanism-Reconciliation of Beginning and End of Test Period Balances section of the worksheet with proration and averaging of activity during the test period computed in different section of Attachment 13.1 for projected revenue requirement calculations and actual revenue requirement calculations.

 Amortization or
Mitigation of
Deficient or
<Excess> ADIT
 Tax Gross-up
Factor
 Amortization or
Mitigation with
Tax Gross-up
 To Appendix III,
Page 3, Line 40,
Col. (3)
 To Appendix III,
Page 3, Line 44,
Col. (3)

PDF page 85

15
Rate Base Adjustment Mechanism - Reconciliation of Beginning and End of Test Period Balances
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
16
Description (+ = debit, <> = credit)
Amortization period and method
17
[Insert rows as necessary]
                        -                           -                           -                           -                           - 17a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 18

Total for account 182.3
(sum of lines 17_)
                        -                           -                           -                           -                           - 19

 FN1. pg 232
 FN1. pg 232
20
[Insert rows as necessary]
                        -                           -                           -                           -                           - 20a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 21

Total for account 254
(sum of lines 20_)
                        -                           -                           -                           -                           - 22

 FN1. pg 278
 FN1. pg 278
23
24
Income Tax Allowance Adjustment Mechanism
25
26
Amortization of Excess or Deficient ADIT
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
27
Description (+ = debit, <> = credit)
Comments
28
[Insert rows as necessary]
                        -                           -                           -                           -                            - 28a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 29

Total for account 182.3
(sum of lines 28_)
                        -                           -                           -                           -                            - 30

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 31

Total for account 254
(sum of lines 30_)
                        -                           -                           -                           -                            - 32

Total amortization and offsetting entries
(sum of lines 29 & 31)                         -                           -                           -                           -                            - 33

Net income tax expense or benefit
(sum of lines 32(f) & 32(g))
                        -
 To line 11
Balance at
Beginning of
Year
Re-
measurement of
ADIT
Annual
Amortization
(Note 4)
Other
Adjustments
(Note 5)
Balance at End
of Year
(d)+(e)+(f)+
(g) Whether subject
to normalization
rules
(Note 6)
Analysis - Balances of tax-related regulatory assets and liabilities include tax gross-up.  Accordingly, for the regulatory assets and liabilities for deficient or excess deferred taxes included in rate base, the related deferred tax assets and liabilities are also included in rate base.  Remeasurements in column (e) are described in Notes 2 and 3 and are based on the journal entry below and the support on the worksheet for the applicable tax law change.  Averaging or proration of amounts affecting rate base is computed on different sections of Attachment 13.1 for projected revenue requirement and actual revenue requirement. The income tax allowance adjustment mechanism may include amortization of excess or deficient ADIT pertaining to deferred tax expense or benefit reflected in rates at a historical tax rate when the underlying timing difference(s) originated (computed under Amortization of Excess or Deficient ADIT within the Income Tax Allowance Adjustment Mechanism section of this worksheet) as well as an adjustment for tax law changes with prospective effective dates intended to mitigate the over- or under- recovery of deferred income taxes originating prior to the effective date of such tax law changes (computed under Adjustment for Tax Law Changes with Prospective Effective Dates within the Income Tax Allowance Adjustment Mechanism section of this worksheet).

Annual
Amortization
from Table
Above
(Note 4)
Debit or
<Credit> to
Account 410.1
Debit or
<Credit> to
Account 411.1
Debit or
<Credit> to
Account 190
Debit or
<Credit> to
Account 283

PDF page 86

34
Adjustment for Tax Law Changes with Prospective Effective Dates
35
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) 36
37
 (c) x (d)
1 / (1- (d))
 (e) x (f)
 - [(c) x (h)]
 (e) + (i)
 (j) x (f)
38
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
38…
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
39
Note 1 - Summary of re-measurement of ADIT resulting from tax law changes
40
41
Note 1a - Summary of re-measurement of ADIT resulting from
[name of tax law change]
Additional information is provided in Note
42
Re-measurement entry
(a) (b)
(c) 43
Account
Comments or References
44
190
45
281
46
282
47
283
48
182.3 (tax-related, included in rate base - protected)
49
182.3 (tax-related, included in rate base - unprotected)
50
182.3 (tax-related, not in rate base))
51
190 (related to portion of acct. 182.3 not in rate base)
52
254 (tax-related, included in rate base - protected)
53
254 (tax-related, included in rate base - unprotected)
54
254 (tax-related, not in rate base)
55
283 (related to portion of acct. 254 not in rate base)
56
Account 410.1
57
Account 411.1
58
Account 410.2
59
Account 411.2
60
Total
 (sum of lines
                        -
61
[Insert additional analysis.]
In the case of tax law changes with an effective date(s) after the beginning of the test period, the impact of a timing difference on current tax expense or benefit differs from the impact on ADIT.  For example, in the case of a deductible timing difference originating in a tax year with a higher enacted tax rate than will apply when the difference will reverse, the current tax benefit will exceed the deferred tax expense.  In this situation, the adjustment computed below to recoverable income tax expense is made in order to avoid over-recovering income tax expense in the current test period due to the excess of current tax benefit over deferred tax expense (computed based on the estimated amount of the future tax liability) with respect to a given timing difference.  The adjustment to recoverable tax expense during the test period in which a timing difference originates mitigates the need for refund of a regulatory liability for excess deferred taxes in a future period (or, as applicable, the need for recovery of a regulatory asset for deficient deferred taxes in a future period).  Amounts in column (i) are reported in the Income Tax Allowance Adjustment Mechanism - Summary on this worksheet.

 Originating
Taxable or
(Deductible)
Book / Tax
Difference for
Test Year
 Tax Rate for
Test Year
 Current Tax
Expense or
(Benefit) in Test
Year
 Tax Gross-up
Factor for Test
Year
 Revemue
Requirement
Imapct for Test
Year
 Enacted Tax
Rate for the
Reversal Year(s)
 Deferred Tax
Expense or
(Benefit) in Test
Year
 Total Tax
Expense or
(Benefit) in Test
Year
 Adjustment to
Mitigate
Over/under-
recovery of
Deferred Taxes
The purposes of this portion of the worksheet are, for each change in tax law, to explain:
- how any ADIT accounts were re-measured,
- the excess or deficient ADIT contained therein, and
- the accounting for any excess or deficient amounts in Accounts 182.3 (Other Regulatory Assets) and 254 (Other Regulatory Liabilities).
Note 2 describes how ADIT accounts are re-measured upon a change in income tax law.  A separate summary (i.e., Note 1a, Note 1b, etc.) will be added for each tax law change resulting in a re-measurement of ADIT. Debit or

<Credit>

PDF page 87

62
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
63
[Insert additional analysis.]
64
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
65
66
67
68
69
[Continuation of note with respect to particular changes in tax law.]
70
[Insert additional notes as needed.]
Note 2 - Explanation of how ADIT accounts are re-measured upon a change in income tax law
Deferred tax assets and liabilities are adjusted (re-measured) for the effect of the changes in tax law (including tax rates) in the period that the change is enacted.  Adjustments are recorded in the appropriate deferred tax balance sheet accounts (Accounts 190, 281, 282 and 283) based on the nature of the temporary difference and the related classification requirements of the accounts.   If as a result of action or expected action by a regulator, it is probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, a regulatory asset or liability is recognized in Account 182.3 (Other Regulatory Assets), or Account 254 (Other Regulatory Liabilities), as appropriate, for that probable future revenue or reduction in future revenue.  Re-measurements of deferred tax balance sheet accounts may also result in re-measurements of tax-related regulatory assets or liabilities that had been recorded prior to the change in tax law.  If it is not probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, tax expense is recognized in Account 410.2 (Provision for Deferred Income Taxes, Other Income or Deductions) or tax benefit is recognized in Account 411.2 (Provision for Deferred Income Taxes-Credit, Other Income or Deductions), as appropriate.

Note 3 - [Complete to support information above.]
Note 4 - The amortization of the deficient or excess ADIT reducing Account 254 (Other Regulatory Liabilities) is recorded with credits to Account 411.1 (Provision for Deferred Income Taxes – Credit, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance.  The amortization of the deficient or excess ADIT reducing Account 182.3 (Other Regulatory Assets) is recorded with debits to Account 410.1 (Provision for Deferred Income Taxes, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance. This activity is summarized in the table "Income Tax Allowance Mechanism - Projected" or the table "Income Tax Allowance Mechanism - Actual," as appropriate.  The annual amortization in the tables above reflects tax gross-up and is stated at the revenue requirement level.

Note 5 - [Complete to support information above.]
Note 6 -  The worksheet indicates whether each excess or deficient ADIT amounts are protected (i.e., subject to normalization rules of a taxing jurisdiction) or unprotected (i.e., not subject to normalization rules of a taxing jurisdiction).  To the extent that normalization requirements apply to ADIT remeasurements, additional computations (e.g., proration of excess deferred tax activity related to future test periods) may be necessary.

PDF page 88

DesertLink, LLC
Attachment 13.1 - Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments
Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)
[Year]
[Projected or Actual]
Line No.
1
Rate year =
2
Test period days after rates become effective
3
4
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
5
6
Beginning balance  (debit or <credit>)
                        -
7
Less:  Portion not related to transmission
                        -
8
Less:  Portion not reflected in rate base
                        -
9
Subtotal:  Portion reflected in rate base
                        -
10
Less:  Portion subject to proration
                        -
11
Portion subject to averaging  (debit or <credit>)
                        -
12
Ending balance  (debit or <credit>)
                        -
13
Less:  Portion not related to transmission
                        -
14
Less:  Portion not reflected in rate base
                        -
15
Subtotal:  Portion reflected in rate base
                        -
16
Less:  Portion subject to proration (before proration)
                        -
17
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
18
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 36(n)
19
Average balance of portion subject to averaging
                        -
20
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 5
This attachment includes sections that are populated only with actual data and thus, these sections remain blank when the formula rate template is calculating a projected revenue requirement. Columns (i) through (n) below are not used for the projection and are only populated with actual data for the Annual Update.

Note 1 - The computations below apply the proration rules of Treasury Regulation section 1.167(l)-1(h)(6) to the annual activity of the portions of the deficient or excess accumulated deferred income taxes recorded in account 182.3 or 254 that are subject to the normalization requirements.  Activity related to the portions of the account balances reflected in rate base but not subject to the proration requirement is averaged instead of prorated.  The balances below include tax gross-up.  The corresponding portions of the deferred tax asset related to the portions of the regulatory liability and the corresponding portions of the deferred tax liability related to the portions of the regulatory asset are also reflected in rate base and prorated or averaged, as appropriate.  Columns (a) through (h) are used for projected and actual revenue requirements computations.  Columns (i) through (n) are used for actual revenue requirement computations.

Amount
debit / <credit>

PDF page 89

21
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
22
Month
Year
23

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
24
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA
 NA                              -
25
January
-
                              -                                 -
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 26

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 27

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 28

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 29

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 30

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 31

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 32

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 33

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 34

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 35

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 36

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 37

Total
                              -
                             -                                -
38
39
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
40
41
Beginning balance  (debit or <credit>)
                        -
42
Less:  Portion not related to transmission
                        -
43
Less:  Portion not reflected in rate base
                        -
44
Subtotal:  Portion reflected in rate base
                        -
45
Less:  Portion subject to proration
                        -
46
Portion subject to averaging  (debit or <credit>)
                        -
47
Ending balance  (debit or <credit>)
                        -
48
Less:  Portion not related to transmission
                        -
49
Less:  Portion not reflected in rate base
                        -
50
Subtotal:  Portion reflected in rate base
                        -
51
Less:  Portion subject to proration (before proration)
                        -
52
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
53
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 70(n)
54
Average balance of portion subject to averaging
                        -
55
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 6
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 2 -
Amount
debit / <credit>

PDF page 90

56
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
57
Month
Year
58

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
58
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA                              -
59
January
-
                              -                                 -
0
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 60

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 61

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 62

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 63

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 64

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 65

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 66

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 67

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 68

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 69

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 70

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 71

Total
                              -
                             -                                -
72
73
74
75
76
77
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 3 -
Note 4  -  Column J is the difference between actual monthly and projected monthly activity (Column I minus Column C).  Specifically, if projected and actual activity are both positive, a negative in Column J represents over-projection (i.e., the amount of projected activity that did not occur) and a positive in Column J represents under-projection (i.e., the excess of actual activity over projected activity). If projected and actual activity are both negative, a negative in Column J represents under-projection (i.e., the excess of actual activity over projected activity) and a positive in Column J represents over-projection (i.e., the amount of projected activity that did not occur).

Note 5  -  Column K preserves the effects of excess ADIT proration from the projected revenue requirement when actual monthly excess ADIT activity and projected monthly excess ADIT activity are either both increases or decreases.  Specifically, if Column J indicates that excess ADIT activity was over-projected, enter Column G x [Column I / Column C].  If Column J indicates that excess ADIT activity was under-projected, enter the amount from Column G and complete Column L).  In other situations, enter zero.

Note 6  -  Column L applies when (1) Column J indicates that excess ADIT activity was under-projected AND (2) actual monthly and projected monthly activity are either both increases or both decreases.  Enter 50 percent of the amount from Column J.  In other situations, enter zero.  The excess ADIT activity in column L is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 7  -  Column M applies when (1) projected monthly activity was an increase while actual monthly activity was a decrease OR (2) projected monthly activity was a decrease while actual monthly activity was an increase.  Enter 50 percent of the amount of actual monthly activity (Column I).  In other situations, enter zero.  The excess ADIT activity in column M is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 8  -  Column N is computed by adding the balance at the end of the prior month to EITHER (1) the sum of prorated monthly excess ADIT activity, if any, from Column K and the portion of monthly excess ADIT activity, if any, from Column L OR (2) the portion of monthly excess ADIT activity in Column M.

PDF page 91

DesertLink, LLC
Attachment 13.2 - Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities Resulting from the Tax Change Identified in Line 1 Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)

[Year]
[Projected or Actual]
Line No.
1
[Identify/describe the tax legislation/change]
2
[Describe the computation.]
3
4
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
5
Balances and rates prior to remeasurement
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
6
Temporary Difference
Account
Account
Account
Account
Account
7
Item
Normalized?
Amount
190
282
283
182.3
283
8
[Insert rows as necessary]
8a
[Insert rows as necessary]
8b
[Insert rows as necessary]
8...
[Insert rows as necessary]
9
Total
                     -                      -                      -                      -                      -
10
Remeasured balances and rates
Other accounts affected by remeasurement
11
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
[1/(1-tax rate [tax rate] /(1-tax rate [tax rate]
12
Temporary Difference
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
13
Item
Normalized?
Amount
190
282
283
182.3
283
410.2
411.2
254
190
182.3
283
14
[Insert rows as necessary]
14a
[Insert rows as necessary]
14b
[Insert rows as necessary]
14...
[Insert rows as necessary]
15
Total
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
16
Remeasurement journal entry:  debt or <credit> (to Attachment 13)
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
17
Summary of Effects on Tax-related Regulatory Assets and Liabilities
18
Account 182.3 - included in rate base, subject to normalization rules
19
Account 182.3 - included in rate base, not subject to normalization rules
20
Account 182.3 - not included in rate base
21
Account 254 - included in rate base, subject to normalization rules
22
Account 254 - included in rate base, not subject to normalization rules
23
Account 254 - not included in rate base
The ratemaking treatment of each item in terms of whether it is subject to the normalization requirements (i.e., P or "protected") or not subject to the normalization requirements (i.e., U or "unprotected") and included in rate base or not (i.e., RB or non-RB) is indicated in column (b).  The balances are measured at the composite tax rate in effect immediately before effective date of the change in tax law and remeasured immediately after the change in tax law.  Each set of balances includes the appropriate income tax rates and tax gross-up factors (as computed in the specific note for this tax law change in Att. 13).  The journal entry to record the remeasurements (Line 16) is based on the differences in balances of accounts recorded prior to the change in law (columns (d)-(h)) and activity in other accounts resulting from the remeasurement (columns (i)-(n)).  The remeasurement entry is also included in Att. 13.  The accounting is further described in Att. 13, Note 2. This worksheet will be included in support of the revenue requirement computation until the excess or deficient ADIT is fully amortized.  A similar worksheet will be used for subsequent changes in tax law resulting in re-measurement of ADIT.

PDF page 92

Appendix V  PRO FORMA LARGE LOAD COST RECOVERY AGREEMENT

PDF page 93

1

DESERTLINK, LLC
[PRO FORMA] LARGE LOAD COST RECOVERY AGREEMENT

This Large Load Cost Recovery Agreement (this “Agreement”) is entered into as of this __ day of _______ 20  , by and between [________], a [●] and an Eligible Customer under the CAISO Tariff (“Eligible Customer”), and DesertLink, LLC, a Delaware limited liability company (“DesertLink” or “Transmission Owner”). DesertLink and Eligible Customer are referred to collectively as the “Parties” and individually as a “Party.”

[_______], a [●] (“Large Load Customer”), executes the Limited Acknowledgment set forth below solely for the purposes stated therein and is not a Party to the wholesale payment obligations established by this Agreement.

RECITALS

WHEREAS, DesertLink is a transmission-only company established to develop, own, and operate transmission facilities (“Transmission Facilities”) pursuant to the provisions of its Transmission Owner Tariff (“TO Tariff”) and the California Independent System Operator Corporation (“CAISO”) Open Access Transmission Tariff (“CAISO Tariff”);

WHEREAS, Eligible Customer is eligible to take transmission service under the CAISO Tariff and does or will take such service on behalf of the Large Load Customer, whether or not Eligible Customer owns or operates an electric distribution system;

WHEREAS, Eligible Customer and Transmission Owner are parties to, or are entering into, an Eligible Customer for Large Load (“ECLL”) Interconnection Agreement or Transmission System Wholesale Load (“TSWL”) Interconnection Agreement (each, an “Interconnection Agreement”) concerning the Large Load Facility;

WHEREAS, Large Load Customer owns, operates, or proposes to develop the Large Load Facility identified in Schedule 1;

WHEREAS, the Eligible Customer has submitted an ECLL Interconnection Application or TSWL Interconnection Application for the interconnection of the Large Load Facility as a new or incremental load;

WHEREAS, Eligible Customer intends to procure transmission service pursuant to the CAISO Tariff and its associated schedules on behalf of Large Load Customer; WHEREAS, in connection with the Large Load Facility, Transmission Owner must make additions and/or modifications to its transmission system, including the Large Load-Driven Upgrades identified in Schedule 1;

WHEREAS, CAISO may, under the CAISO Tariff or a Commission-accepted
methodology, formally assign to the Large Load Facility a specific share of the costs or revenue requirement of a regional transmission project, and the Parties intend this Agreement to address

PDF page 94

2

that assigned share without changing any allocation otherwise established under the CAISO Tariff;

WHEREAS, the applicable studies may identify impacts on transmission systems other than DesertLink’s transmission system and may identify Affected System Upgrades necessary to accommodate or mitigate such impacts;

WHEREAS, Eligible Customer is responsible for entering into and maintaining the arrangements, payment obligations, and financial security or credit support required by each applicable Affected System Owner to ensure that costs and financial risks associated with Affected System Upgrades are not shifted to customers that did not cause those costs; WHEREAS, Transmission Owner, Eligible Customer, and Distribution Utility have executed or expect to execute an engineering and procurement agreement and/or an Interconnection Agreement governing the design, construction, and interconnection of the Transmission Owner’s facilities to the Distribution Utility’s facilities, including the Network Upgrades, required to support service of the Large Load Facility;

WHEREAS, the Parties enter into this Agreement to establish the Eligible Customer’s wholesale revenue-support and security obligations associated with the Large Load Facility and the Large Load-Driven Upgrades, without establishing or prescribing the retail rates, charges, or recovery arrangements between Eligible Customer and Large Load Customer;

WHEREAS, the Commission has recognized that the framework under which CAISO provides transmission service is unique and that certain responsibilities fall to the Participating Transmission Owners, Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214, at P 37 (2026), and this Agreement is the form of agreement established under Sections 10.9 and 10A.6 of the TO Tariff to secure Eligible Customer’s minimum contribution toward Transmission Owner’s transmission revenue requirement;

WHEREAS, CAISO is not a party to this Agreement; this Agreement does not create any obligation of CAISO, including any obligation to provide settlement, metering, billing, resettlement, or allocation data, which arises, if at all, under the CAISO Requirements; and DesertLink shall recover the costs of the Covered Upgrades through its Formula Rate and shall flow TRBAA Credits, including any adjustment resulting from the resolution of a dispute under this Agreement, through to transmission customers through its TRBAA;

NOW, THEREFORE, in consideration of the mutual promises and covenants set forth herein, and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Parties intending to be legally bound, agree as follows:

1. Recitals. The statements set forth in the recitals above are hereby incorporated herein into the terms and conditions of this Agreement as if fully set forth herein.

PDF page 95

3

2. Definitions
Capitalized terms not defined herein have the meanings given in the CAISO Tariff, the DesertLink TO Tariff Formula Rate Implementation Protocols in Appendix IV of the TO Tariff (“Protocols”), or the relevant Interconnection Agreement.

2.1.
“Affected System” means an electric transmission system, other than DesertLink’s transmission system, that an applicable study determines may be materially affected by the interconnection or service of the Large Load Facility, including the transmission system of another Participating TO or a transmission system outside the CAISO Controlled Grid.

2.2.
“Affected System Arrangement” means an executed agreement or other binding arrangement entered into by Eligible Customer with an Affected System Owner that establishes the applicable study, engineering, design, procurement, construction, ownership, cost responsibility, cancellation-cost, revenue-support, payment, financial security or credit support, true-up, and other obligations associated with an Affected System Upgrade.

2.3.
“Affected System Owner” means the owner or operator responsible for an Affected System.

2.4.
“Affected System Upgrade” means an addition, modification, or upgrade to an Affected System that an applicable study determines is necessary to accommodate or mitigate an impact caused, in whole or in part, by the interconnection or service of the Large Load Facility.

2.5.
“Annual MTRC” means the annual Minimum Transmission Revenue Contribution for a Covered Upgrade, calculated solely under the MTRC Calculation Template in Schedule 5. Before the Final MTRC Determination Date for a Covered Upgrade, the Annual MTRC is the Estimated Annual MTRC. On and after that date, it is the Final Annual MTRC fixed under Section 6.3. Each Annual MTRC is levelized over a twenty (20)-year MTRC Term beginning on the applicable Upgrade In-Service Date or Regional Project In-Service Date, as applicable. The Annual MTRC is not an input to, or calculation made under, DesertLink’s annual Formula Rate update. 2.6.

“Annual Termination Fee Credit” means the annual amount of a Termination Fee Balance included in the TRBAA under Section 3.3.4.

2.7.
“Applicable Allocation Percentage” has the meaning set forth in Section 6.3.3. 2.8.

“Applicable Laws and Regulations” means all duly promulgated applicable federal, state, and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, judicial or administrative orders, permits, and other duly authorized actions of any Governmental Authority.

2.9.
“Applied Security Proceeds” means proceeds of Operational Security that Transmission Owner has applied under Section 7.6 to an identified Supplemental

PDF page 96

4

MTRC, prior-period true-up adjustment, Termination Fee, or other payment obligation arising under Article 6 or Section 3.3.4. Proceeds of Construction Security applied to Pre-In-Service Termination Costs or other construction-related obligations are not Applied Security Proceeds and shall be treated as provided in Sections 3.3.2 and 3.3.3. 2.10. “ARR” means annual revenue requirement.

2.11. “Break-Even” has the meaning set forth in Section 6.7.
2.12. “Business Day” means a Business Day as defined in Appendix A to the CAISO Tariff, as amended from time to time.

2.13. “CAISO-Assigned Regional Project” means a regional transmission project approved or designated through a CAISO Tariff process for which CAISO, under the CAISO Tariff or a Commission-accepted methodology, formally assigns a specific percentage or amount of project costs or revenue requirement to the Large Load Facility. The project and assignment must be identified in Schedule 4. A project’s regional designation, general system benefit, or inclusion in a CAISO transmission plan, without a specific assignment to the Large Load Facility, does not by itself make the project a CAISO-Assigned Regional Project.

2.14. “CAISO Requirements” means the CAISO Tariff, the Transmission Control Agreement, any other agreement to which CAISO is a party that is on file with or accepted by the Commission, and any Commission order, regulation, or Commission- accepted methodology applicable to CAISO, each as amended from time to time, together with any CAISO business practice manual or procedure to the extent it implements any of the foregoing.

2.15. “Calendar Day” means every day, including Saturdays, Sundays, federal holidays, and other holidays.

2.16. “Construction Security” has the meaning set forth in Section 7.1. 2.17. “Covered Upgrade” means each Large Load-Driven Upgrade and each DesertLink- owned CAISO-Assigned Regional Project share that is included in Schedule 1 or Schedule 4, as applicable, and for which an Annual MTRC is established under this Agreement.

2.18. “Credit Review Event” means a payment default, credit rating downgrade of the Eligible Customer or an issuing bank that has not yet triggered a Material Adverse Credit Event, a notice of nonrenewal of a Letter of Credit, or another event that, in DesertLink’s reasonable judgment, warrants updated credit information. A Credit Review Event does not, by itself, require delivery of additional Security absent a resulting shortfall.

2.19. “Cumulative Revenue Ledger” means the customer-, Large Load Facility-, project-, and Covered Upgrade-specific record maintained by DesertLink under Section 6.7. The Cumulative Revenue Ledger shall identify the applicable Total Required Revenue

PDF page 97

5

Commitment, Annual MTRC, Qualifying Transmission Revenues, Supplemental MTRC Receipts, Applied Security Proceeds, effective prospective reassignments, other permitted adjustments, and the resulting Remaining Cumulative Revenue Responsibility and Required Operational Security.

2.20. “Cumulative Revenue Responsibility” or “Remaining Cumulative Revenue Responsibility” means the Total Required Revenue Commitment less amounts that have satisfied that commitment under Section 6.7.

2.21. “Dispute Determination” has the meaning set forth in Section 11.5. 2.22. “Distribution Utility” means the public utility, municipal utility, cooperative, or other entity that owns, operates, or is responsible for the distribution facilities to which the Large Load Facility is interconnected or proposed to be interconnected, including its successors and permitted assigns.

2.23. “Effective Date” has the meaning set forth in Section 3.1.
2.24. “Estimated Annual MTRC” means the annual MTRC for a Covered Upgrade calculated from the then-current estimated capital cost using the MTRC Calculation Template in Schedule 5. DesertLink may update the Estimated Annual MTRC as costs change during construction, including when DesertLink requires additional Construction Security.

2.25. “Event of Default” has the meaning set forth in Section 7.11.
2.26. “Final Annual MTRC” means the fixed Annual MTRC for a Covered Upgrade established on the Final MTRC Determination Date using final incurred capital cost and the Project-Specific Levelized Fixed Charge Rate calculated under the MTRC Calculation Template in Schedule 5, including the agreed five percent (5%) annual levelized-depreciation schedule over the twenty (20)-year MTRC Term. The Final Annual MTRC is not recalculated through DesertLink’s Formula Rate or Protocols and may be recalculated only as provided in Section 6.3.1.

2.27. “Final MTRC Determination Date” means the date on which DesertLink establishes the Final Annual MTRC for a Covered Upgrade, which shall occur within one (1) year after the applicable Covered Upgrade enters service, when the actual capital cost of that Covered Upgrade is known and all costs associated with its estimated capital cost have been accounted for.

2.28. “Force Majeure” means any cause beyond the reasonable control of the Party claiming, and without the fault or negligence of such Party, which materially prevents or impairs the performance of such Party’s obligations hereunder, including but not limited to landslides, storms, ice storms, flood, drought, tornado, hurricane, lightning, earthquake, fire, explosion, failure or imminent threat of failure of facilities, supply chain issues, civil disturbance, strike, or other labor disturbance, sabotage, vandalism,

PDF page 98

6

riot, terrorism, blockade, insurrection, war, national emergency, or restraint by any Governmental Authority.

2.29. “Forecast TRBAA Credit” has the meaning set forth in Section 6.8. 2.30. “Formula Rate” means DesertLink’s transmission formula rate template and associated provisions in the TO Tariff, as accepted by the Commission and amended from time to time.

2.31. “Governmental Authority” means any federal, state, local, or other governmental, regulatory, or administrative agency, court, commission, department, board, legislature, rulemaking body, tribunal, or other governmental authority having jurisdiction over a Party, the Large Load Facility, any Large Load-Driven Upgrade, or the services or obligations addressed by this Agreement.

2.32. “Initial Allocation Percentage” has the meaning set forth in Section 6.3.2. 2.33. “Large Load-Driven Upgrades” means the transmission facilities owned or to be constructed by DesertLink and identified in Schedule 1 that the applicable study determines are driven in whole or in part by the Large Load Facility, alone or together with one or more other large loads. Large Load-Driven Upgrades do not include Affected System Upgrades or any facilities whose costs are directly assigned to and paid by Eligible Customer under an Interconnection Agreement and are not included in DesertLink’s rate base. Where a Large Load-Driven Upgrade is an addition to or modification of a facility jointly owned by DesertLink and another entity, the Large Load-Driven Upgrade includes only DesertLink’s ownership share identified in Schedule 1.

2.34. “Large Load Facility” means the new or incremental load facility owned, operated, or proposed to be developed by Large Load Customer and identified in Schedule 1. 2.35. “Large Load Service Commencement Date” means the date on which the Large Load Facility first takes electric service through the CAISO Controlled Grid or otherwise begins receiving service under the applicable CAISO Tariff arrangement, as specified in Schedule 1. If the Large Load Facility is not reflected in a CAISO billing determinant used to assess TAC, Schedule 2 shall identify the applicable wholesale transmission-access, wheeling, or other CAISO Tariff billing arrangement. 2.36. “Letter of Credit” means an irrevocable, transferable standby letter of credit issued for the benefit of DesertLink, meeting the requirements of Schedule 3. 2.37. “Material Adverse Credit Event” means any of the following: (a) a bankruptcy, insolvency, receivership, or similar event described in Section 7.6(e); (b) a reduction in the long-term senior unsecured debt rating of the Eligible Customer or an issuing bank below the standards set out in Section 4 of Schedule 3; (c) loss, cancellation, material impairment, or expiration of Qualifying Retail Security Support without timely replacement; (d) an incorrect, expired, withdrawn, unavailable, or materially

PDF page 99

7

misleading Retail Security Certification, as described in Section 7.7 of this Agreement; or (e) another event that, in DesertLink’s reasonable judgment, materially impairs Eligible Customer's ability to perform its payment or Security obligations under this Agreement.

2.38. “MTRC Term” means, with respect to each Covered Upgrade, the period beginning on and including the applicable Upgrade In-Service Date or Regional Project In- Service Date, as applicable, and ending on the day immediately preceding the twentieth (20th) anniversary of that in-service date (the “MTRC Term End Date”). The first and final Rate Years of the MTRC Term shall be prorated for partial-year service. 2.39. “MTRC Term End Date” has the meaning set forth in the definition of “MTRC Term.”

2.40. “Net Revenue Requirement” means DesertLink’s Net Annual Transmission Revenue Requirement calculated under its Formula Rate for the applicable Rate Year. 2.41. “Notice of Dispute” has the meaning set forth in Section 11.1. 2.42. “Operational Security” has the meaning set forth in Sections 7.2 and 7.5. 2.43. “Outside Date” means the date identified as the Outside Date in Schedule 1, as such date may be extended by written agreement of the Parties.

2.44. “Pre-In-Service Termination Costs” has the meaning set forth in Section 3.3.2. 2.45. “Qualifying Retail Security Support” means retail-customer security for which Eligible Customer has delivered a currently effective Retail Security Certification under Schedule 3.

2.46. “Qualifying Transmission Revenues” or “QTR” has the meaning set forth in Section 6.2.

2.47. “Reconciliation Statement” has the meaning set forth in Section 6.6. 2.48. “Regional Project Allocated ARR” means, for the share of a CAISO-Assigned Regional Project that is owned by DesertLink, included in DesertLink’s Formula Rate, and formally allocated to the Large Load Facility under the applicable CAISO Tariff provision or Commission-accepted methodology, the Annual MTRC for that project share calculated under Section 6.3.5 and the MTRC Calculation Template in Schedule 5, which shall be the Estimated Annual MTRC before the Final MTRC Determination Date and the Final Annual MTRC on and after that date. The Regional Project Allocated ARR is calculated using DesertLink’s allocated share of the project’s estimated or final capital cost, as applicable, by applying the Project-Specific Levelized Fixed Charge Rate calculated under Schedule 5. For purposes of calculating present-worth federal and state income-tax depreciation benefits, Schedule 5 applies a levelized-depreciation rate of five percent (5%) of that allocated capital-cost share in each year of the applicable twenty (20)-year MTRC Term. The resulting Regional

PDF page 100

8

Project Allocated ARR shall be recorded in Schedule 4. If CAISO states the assignment as an annual revenue-requirement share rather than a capital-cost amount, the equivalent capital-cost input shall be determined only under the allocation method established by the CAISO Tariff or a Commission-accepted methodology. 2.49. “Regional Project In-Service Date” means, for a CAISO-Assigned Regional Project owned by DesertLink, the date the project, or a separately identifiable and separately allocated portion of it, is energized, placed in service, and recorded as electric plant in service on DesertLink’s books. Schedule 4 shall identify the expected Regional Project In-Service Date for each project or separately identifiable portion. Inclusion of Construction Work in Progress in rate base before that date does not constitute a Regional Project In-Service Date.

2.50. “Required Operational Security” means the amount of Operational Security required under Section 7.3 and Schedule 3, equal to the nominal Remaining Cumulative Revenue Responsibility except to the extent satisfied by Qualifying Retail Security Support.

2.51. “Required Security Amount” means the aggregate Security then required under this Agreement.

2.52. “Retail Security Certification” means a certification substantially in the form of Exhibit A contained in Schedule 3 of this Agreement, signed by an authorized officer of Eligible Customer, confirming that the Large Load Customer has posted retail security with Eligible Customer that is available, through enforceable draw or application rights or a binding undertaking, to satisfy the corresponding wholesale obligations under this Agreement.

2.53. “Security” means Construction Security or Operational Security, as the context requires.

2.54. “Security Notice” means DesertLink’s written notice of a required increase, restoration, replacement, or other adjustment to Security, including reasonable supporting detail then available.

2.55. “Successor Eligible Customer” means an Eligible Customer that assumes responsibility under Section 6.10.

2.56. “Supplemental MTRC” has the meaning set forth in Section 6.4.
2.57. “Supplemental MTRC Receipts” means payments of Supplemental MTRC received by Transmission Owner from or on behalf of Eligible Customer, excluding Applied Security Proceeds.

2.58. “TAC” means the Transmission Access Charge, as defined in Appendix A to the CAISO Tariff, including the applicable Access Charge components identified in Schedule 2.

PDF page 101

9

2.59. “Termination Cost Reconciliation” has the meaning set forth in Section 3.3.2. 2.60. “Termination Fee” has the meaning set forth in Section 3.3.4. 2.61. “Termination Fee Account” has the meaning set forth in Section 3.3.4. 2.62. “Termination Fee Balance” has the meaning set forth in Section 3.3.4. 2.63. “Total Required Revenue Commitment” has the meaning set forth in Section 6.7. 2.64. “Transmission Revenue Balancing Account Adjustment” or “TRBAA” means the Transmission Revenue Balancing Account Adjustment maintained by DesertLink under Section 5.5 of the TO Tariff, as amended from time to time, and “Transmission Revenue Balancing Account” or “TRBA” means the associated balancing account maintained under that Section.

2.65. “TRBAA Credit” means a Forecast TRBAA Credit or an amount recorded in the TRBA under Section 6.8 for Supplemental MTRC Receipts, Applied Security Proceeds other than Applied Security Proceeds applied to a Termination Fee, Annual Termination Fee Credits, or a duplicate-recovery credit under Section 3.3.3(d) or Section 6.3.5, in each case as flowed through to transmission customers through the TRBAA. A TRBAA Credit is not an input to the MTRC Calculation Template or the Formula Rate.

2.66. “Upgrade In-Service Date” means, with respect to each Large Load-Driven Upgrade, the date on which that Large Load-Driven Upgrade is energized, placed in service, and included as Electric Plant in Service in DesertLink’s rate base. Schedule 1 shall identify the expected Upgrade In-Service Date for each Large Load-Driven Upgrade. Inclusion of Construction Work in Progress in rate base before an upgrade is placed in service does not constitute its Upgrade In-Service Date.

3. Effective Date, Term and Termination
3.1.
Effective Date. This Agreement shall become effective upon execution by the Parties, subject to acceptance by the Federal Energy Regulatory Commission (“FERC” or “Commission”) (if applicable), or, if filed unexecuted, upon the date specified by FERC (the “Effective Date”).

3.2.
Term. This Agreement shall remain in effect from the Effective Date until DesertLink issues a final Reconciliation Statement determining that the Total Required Revenue Commitment for every Covered Upgrade has been satisfied, transferred to a successor, prospectively reassigned, or otherwise discharged. The MTRC Term for each Covered Upgrade begins on its applicable Upgrade In-Service Date or Regional Project In- Service Date and ends on its applicable MTRC Term End Date. Earlier Break-Even remains available if the Total Required Revenue Commitment is satisfied before the applicable MTRC Term End Date. If DesertLink holds a Termination Fee Balance when the Total Required Revenue Commitment is otherwise discharged, this Agreement shall remain in effect for purposes of the Termination Fee Account

PDF page 102

10

provisions in Section 3.3.4 until the Termination Fee Balance has been fully credited or released.

3.3.
Termination. This Agreement may be terminated as follows:
3.3.1.
Termination Before the First Applicable In-Service Date. Before any Large Load-Driven Upgrade reaches its Upgrade In-Service Date and before any DesertLink-owned CAISO-Assigned Regional Project reaches its Regional Project In-Service Date, this Agreement may be terminated upon thirty (30) Calendar Days’ written notice if: (a) the Large Load Service Commencement Date has not occurred by the Outside Date; (b) Eligible Customer or Large Load Customer cancels or abandons the Large Load Facility or associated request for service; (c) the applicable interconnection, access to the CAISO Controlled Grid, or other arrangement necessary for the Large Load Facility is terminated; (d) an Event of Default has occurred and is continuing, or DesertLink exercises a termination right arising from default under this Agreement or an applicable interconnection or transmission service agreement; or (e) Eligible Customer fails to timely execute, maintain, or provide the documentation, financial security, or credit support required under Sections 4.2, 6.3.6, or 7.1, and such failure continues for ten (10) Business Days after written notice from DesertLink or cannot reasonably be cured by the date on which DesertLink must commence or continue physical construction or incur a material noncancelable procurement or construction commitment. Any such termination shall be subject to Applicable Laws and Regulations and any required Commission authorization or acceptance and shall not release or limit the obligations described in Sections 3.3.2 and 3.3.3.

If any Large Load-Driven Upgrade has reached its Upgrade In-Service Date or any DesertLink-owned CAISO-Assigned Regional Project has reached its Regional Project In-Service Date identified in Schedule 4, cancellation, abandonment, termination, or failure of the Large Load Facility to commence or continue service shall not terminate this Agreement. Section 3.3.4 and Articles 6 and 7 shall apply to each Large Load-Driven Upgrade and DesertLink-owned CAISO-Assigned Regional Project for which the applicable in-service date has occurred. Section 6.3.6 shall govern any assigned share of a project owned by another entity.

3.3.2.
Pre-In-Service Termination Costs and Construction Security. If the Large Load Facility, its associated request for service, or any associated Large Load- Driven Upgrade is cancelled, abandoned, or otherwise terminated before an applicable Large Load-Driven Upgrade reaches its Upgrade In-Service Date, Eligible Customer shall be responsible for all actual and reasonable costs prudently incurred or irrevocably committed by DesertLink with respect to that Large Load-Driven Upgrade that have not otherwise been recovered by DesertLink (“Pre-In-Service Termination Costs”). Pre-In-Service Termination Costs include costs incurred before or after the applicable cancellation,

PDF page 103

11

abandonment, or termination to wind down, secure, remove, or otherwise address the unfinished Large Load-Driven Upgrade.

Pre-In-Service Termination Costs include, as applicable:
(a) engineering, design, study, permitting, environmental, siting, land and land- right, procurement, construction, testing, project management, legal, regulatory, and administrative costs;

(b) vendor and contractor cancellation charges, termination charges, change- order costs, restocking charges, demobilization costs, contract closeout costs, and third-party claims;

(c) the costs of securing, preserving, mothballing, relocating, redeploying, dismantling, removing, transporting, storing, selling, or disposing of equipment, materials, and partially completed facilities;

(d) site restoration, environmental remediation, and the restoration or modification of DesertLink’s existing facilities made necessary by the cancellation or abandonment;

(e) Allowance for Funds Used During Construction (“AFUDC”) properly accrued in accordance with the Commission’s Uniform System of Accounts through the date on which the applicable construction activities cease or the applicable project is determined to have been abandoned, excluding AFUDC associated with amounts of Construction Work in Progress included in rate base or otherwise recovered through rates; and

(f) any other costs reasonably incurred by DesertLink as a direct result of the cancellation, abandonment, suspension, or termination.

DesertLink may draw upon and apply Construction Security to Pre-In-Service Termination Costs as such costs are incurred or the associated obligations become fixed and payable. DesertLink may retain Construction Security until all Pre-In-Service Termination Costs are reasonably determinable and DesertLink has served on Eligible Customer a final statement reconciling Pre-In-Service Termination Costs, Construction Security applied, and the recoveries described in this Section, together with supporting information (the “Termination Cost Reconciliation”). Construction Security does not limit Eligible Customer’s underlying liability. Eligible Customer shall pay any deficiency within ten (10) Business Days after receipt of the Termination Cost Reconciliation. The Termination Cost Reconciliation shall become final in the same manner and within the same period as a Reconciliation Statement under Section 6.6, and DesertLink shall release any excess Construction Security after the Termination Cost Reconciliation becomes final, including through resolution of any dispute under Article 11. Construction Security applied under this Section does not constitute Applied Security Proceeds and does not produce a TRBAA Credit except to the extent provided in Section 3.3.3(d). Nothing in this Agreement limits DesertLink’s right to seek recovery of unpaid Pre-In-Service Termination Costs through its Formula Rate or otherwise as the Commission may authorize.

PDF page 104

12

DesertLink shall use commercially reasonable efforts to mitigate Pre-In-Service Termination Costs, provided that DesertLink shall not be required to take any action inconsistent with prudent utility practice, safety requirements, Applicable Laws and Regulations, existing contractual obligations, or the reliable operation of its transmission facilities. The Termination Cost Reconciliation shall reflect, when realized, applicable vendor refunds, insurance recoveries, net salvage proceeds, reuse or redeployment credits, and other recoveries attributable to the cancelled or abandoned scope, but shall not credit amounts representing DesertLink’s lawfully earned return or carrying costs except to the extent necessary to prevent duplicate recovery.

This Section applies separately to each Large Load-Driven Upgrade. If one or more Large Load-Driven Upgrades have reached their Upgrade In-Service Dates when the Large Load Facility or associated request for service is cancelled, this Section shall apply only to the Large Load-Driven Upgrades and portions of the project that have not reached their Upgrade In-Service Dates. The treatment of each Large Load-Driven Upgrade that has reached its Upgrade In-Service Date shall be governed by Section 3.3.4 and Articles 6 and 7.

3.3.3.
Rate Base and Formula Rate Treatment Before an Upgrade In-Service Date. To the extent costs associated with a cancelled or abandoned Large Load- Driven Upgrade that has not reached its Upgrade In-Service Date have been included in Construction Work in Progress or any other component of DesertLink’s rate base, DesertLink shall, consistent with the Commission’s Uniform System of Accounts, its Formula Rate and Protocols, and other Applicable Laws and Regulations:

(a) remove, reclassify, or otherwise exclude such costs from rate base to the extent required by applicable Commission accounting and ratemaking requirements;

(b) reflect that treatment in the next practicable Annual Update and corresponding true-up;

(c) cease accruing AFUDC to the extent and at the time required by the Commission’s accounting requirements; and

(d) make any adjustment or credit necessary to prevent DesertLink from recovering the same cost both through Construction Security or another payment by Eligible Customer and through its Formula Rate; provided that any such credit to transmission customers shall be recorded in the TRBA and flowed through to transmission customers through the TRBAA as provided in Section 6.8, and not through a revenue credit or other input to the Formula Rate.

Any depreciation, amortization, or other amount recovered through DesertLink’s Formula Rate that represents recovery of the same underlying capital or expense included in Pre-In-Service Termination Costs shall be reflected, without duplication, in the Termination Cost Reconciliation under Section 3.3.2. Application of Construction Security shall not require DesertLink to refund or

PDF page 105

13

surrender any return, carrying cost, tax allowance, or other amount lawfully recovered for a period during which DesertLink’s investment was properly included in rate base, except to the extent necessary to prevent duplicate recovery.

This Section 3.3.3 applies only to a Large Load-Driven Upgrade, or portion thereof, that has not reached its Upgrade In-Service Date.

3.3.4.
Effect of Cancellation After an Upgrade or Regional Project In-Service Date. After any Large Load-Driven Upgrade reaches its Upgrade In-Service Date or any DesertLink-owned CAISO-Assigned Regional Project reaches its Regional Project In-Service Date specified in Schedule 4, Eligible Customer shall promptly notify DesertLink if Eligible Customer or Large Load Customer anticipates or becomes aware of the cancellation, abandonment, downsizing, curtailment, permanent cessation, or material reduction of service at the Large Load Facility.

Cancellation, abandonment, suspension, downsizing, termination, or failure of the Large Load Facility to commence or continue service shall not, by itself:

(a) terminate this Agreement;
(b) require the removal from rate base of a Large Load-Driven Upgrade or a DesertLink-owned CAISO-Assigned Regional Project that has reached its in- service date;

(c) reduce or cap any Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, or remaining Cumulative Revenue

Responsibility; or
(d) terminate, reduce, or excuse Eligible Customer’s obligation to pay the Supplemental MTRC and prior-period true-up adjustments under Section 6.6, maintain and replenish Operational Security, or satisfy the remaining Cumulative Revenue Responsibility.

Upon any effective termination of this Agreement, or upon the permanent cessation of service by the Large Load Facility following an applicable Upgrade In-Service Date or Regional Project In-Service Date, Eligible Customer shall pay DesertLink a one-time lump-sum termination fee equal to the Remaining Cumulative Revenue Responsibility, less any Supplemental MTRC that has been billed and remains unpaid as of the effective termination or cessation date (the “Termination Fee”). DesertLink shall calculate the Termination Fee separately for each Covered Upgrade that has reached its applicable in-service date from the most recently served Cumulative Revenue Ledger, updated through the effective termination or cessation date for then-known Qualifying Transmission Revenues, Supplemental MTRC Receipts, Applied Security Proceeds, billed and unpaid Supplemental MTRC, and any effective prospective reassignment. Billed and unpaid Supplemental MTRC excluded from the Termination Fee remains separately payable and secured; its later payment, satisfaction through Applied Security Proceeds, or direct recovery shall reduce the Cumulative Revenue

PDF page 106

14

Responsibility. The Termination Fee is due thirty (30) Calendar Days after DesertLink’s invoice. It is an accelerated contractual termination charge, not a penalty or consideration for future transmission service. Its receipt in full discharges only the remaining Cumulative Revenue Responsibility included in the fee. The Termination Fee is not a Supplemental MTRC Receipt, Applied Security Proceeds, prepayment for future transmission service, customer advance for construction, contribution in aid of construction, or reduction to rate base. DesertLink shall administer the Termination Fee only as provided in Section 3.3.4 and Article 6.

Each Large Load-Driven Upgrade that has reached its Upgrade In-Service Date and each DesertLink-owned CAISO-Assigned Regional Project for which an Annual MTRC has been established shall remain subject to the applicable Formula Rate and Protocols for so long as it is properly includable in rate base under applicable Commission requirements. The associated payment, Security, reconciliation, and TRBAA Credit obligations shall continue in accordance with Articles 6 and 7, subject to any prospective reassignment or adjustment authorized under the CAISO Tariff or a Commission-accepted methodology, or transfer to a Successor Eligible Customer under Section 6.10.

DesertLink shall hold each Termination Fee, and any proceeds of Operational Security applied to its payment, in a separately identified, interest bearing Termination Fee Account for the applicable Covered Upgrade. The amounts in that account, together with actual earnings and less amounts credited or released, constitute the “Termination Fee Balance.” For each Covered Upgrade, the Annual Termination Fee Credit for each Rate Year remaining in the MTRC Term shall equal the applicable Annual MTRC, prorated for any partial Rate Year, but shall not exceed the then-available Termination Fee Balance. In the final Rate Year of the MTRC Term, the Annual Termination Fee Credit shall include the entire remaining Termination Fee Balance, including actual earnings, so that the Termination Fee Account is reduced to zero, subject to any amount required to be released under this Section 3.3.4. DesertLink shall include each Annual Termination Fee Credit in the TRBAA only for the Rate Year for which it is scheduled. The Termination Fee Balance shall be separately accounted for as a deferred liability pending its scheduled annual TRBAA treatment, shall not be included in rate base, and shall not itself be a TRBAA Credit or Formula Rate input. If a prospective reassignment becomes effective after receipt of a Termination Fee, DesertLink shall release the portion of the Termination Fee Balance attributable to the reassigned responsibility, together with actual earnings, and prospectively adjust the remaining Annual Termination Fee Credits.

If the Commission subsequently requires DesertLink to retire, remove, reclassify, or exclude all or a portion of an in-service Large Load-Driven Upgrade or DesertLink-owned CAISO-Assigned Regional Project from rate base, DesertLink shall make corresponding prospective adjustments to the applicable Annual MTRC, Regional Project Allocated ARR, Total Required Revenue

PDF page 107

15

Commitment, Cumulative Revenue Responsibility, Supplemental MTRC, and Operational Security. Such adjustments shall prevent Eligible Customer from remaining responsible under this Agreement for costs that are no longer included in DesertLink’s transmission revenue requirement, without requiring a refund or reopening of amounts properly determined for a prior Rate Year.

If, at the time of cancellation or abandonment, one or more Large Load-Driven Upgrades have reached their Upgrade In-Service Dates or a DesertLink-owned CAISO-Assigned Regional Project has reached its project in-service date, and one or more other upgrades or project shares have not, Sections 3.3.2 and 3.3.3 shall apply to Large Load-Driven Upgrades and project scope that have not reached their applicable in-service dates; this Section 3.3.4 and Articles 6 and 7 shall apply to the upgrades and DesertLink-owned project shares that have reached their applicable in-service dates; and Section 6.3.6 shall continue to govern any assigned share of a project owned by another entity.

3.3.5.
Mutual Termination. The Parties may terminate this Agreement by mutual written consent only after addressing all incurred construction costs, the continuing Cumulative Revenue Responsibility, Supplemental MTRC amounts, prior-period true-up adjustments, and Security. No termination is effective to extinguish such obligations unless expressly accepted or approved by FERC. 3.4.

Regulatory Effect of Termination. No termination shall become effective until the Parties comply with all Applicable Laws and Regulations, including any required notice to or acceptance by FERC. A regulatory rejection, cancellation, downsizing, curtailment, cessation, Force Majeure event, or termination shall not excuse incurred construction costs or the obligations arising on or after an applicable Upgrade In- Service Date or Regional Project In-Service Date unless FERC expressly determines otherwise.

3.5.
Effect of Termination. Termination does not release Eligible Customer from obligations arising under Articles 4, 6, or 7, including future annual Supplemental MTRC payments, prior-period true-up adjustments, and Security maintenance and replenishment, until the Cumulative Revenue Responsibility is finally satisfied or transferred in accordance with this Agreement. Upon DesertLink’s receipt of the Termination Fee in full, no further Supplemental MTRC shall accrue for any period after the effective termination or cessation date, subject to final true-ups and reconciliation for periods before that date. Security does not limit the underlying liability. The Large Load Customer’s information, notice, authorization, and cooperation obligations stated in its Limited Acknowledgment also survive.

4. Transmission Project
4.1.
Design, Procurement, and Construction. Subject to Eligible Customer’s execution of this Agreement and the relevant Interconnection Agreement, delivery of Construction Security under Section 7.1, and satisfaction of Section 4.2, DesertLink shall design, procure, construct, install, and own the Large Load-Driven Upgrades

PDF page 108

16

described in the relevant Interconnection Agreement and Schedule 1, using reasonable efforts to meet the applicable construction schedule and expected Upgrade In-Service Dates.

Eligible Customer shall maintain Construction Security under Section 7.1 sufficient to secure DesertLink’s incurred and committed construction costs and the Pre-In-Service Termination Costs described in Section 3.3.2. Construction Security shall apply separately to each Large Load-Driven Upgrade until that upgrade reaches its Upgrade In-Service Date and the conditions for release or conversion under Section 7.2 have been satisfied.

If different Large Load-Driven Upgrades reach their Upgrade In-Service Dates on different dates, Construction Security shall continue to apply to each Large Load- Driven Upgrade and portion of the project that has not reached its Upgrade In-Service Date, notwithstanding the release or conversion of Construction Security attributable to an upgrade that has entered service.

Upon cancellation, abandonment, or termination, before an applicable Large Load- Driven Upgrade reaches its Upgrade In-Service Date, DesertLink may draw, retain, and apply Construction Security in accordance with Sections 3.3.2 and 7.1 and the relevant Interconnection Agreement. DesertLink shall not be required to take action inconsistent with its safety practices, design criteria, construction procedures, Applicable Laws and Regulations, or the reliable operation of its transmission facilities.

4.2.
Affected Systems
4.2.1. Identification and Coordination. Eligible Customer shall cooperate with DesertLink, CAISO, each affected Participating TO, and each other Affected System Owner in identifying and studying potential impacts of the interconnection or service of the Large Load Facility on any Affected System.

4.2.2. Required Affected System Arrangements. For each Affected System Upgrade identified through an applicable study, Eligible Customer shall timely enter into and maintain an Affected System Arrangement with the applicable Affected System Owner. Each Affected System Arrangement shall address, as applicable:

(a) study, engineering, design, procurement, construction, testing, and energization responsibilities;

(b) responsibility for the costs of the Affected System Upgrade;
(c) responsibility for cancellation, abandonment, demobilization, equipment removal, disposition, remediation, restoration, AFUDC, and other costs resulting from cancellation or failure of the Large Load Facility to proceed;

(d) construction-period and post-in-service payment obligations and financial security or credit support sufficient to protect the Affected System Owner and its other customers against cost shifting;

PDF page 109

17

(e) applicable invoicing, reconciliation, true-up, refund, and release procedures; and

(f) any Commission filing, acceptance, or other regulatory authorization required for the Affected System Arrangement.

4.2.3. Evidence Before DesertLink Construction. At least thirty (30) Calendar Days before DesertLink’s scheduled commencement of physical construction, and in all events before any notice to proceed for physical construction may occur or DesertLink incurs a material noncancelable procurement or construction commitment, Eligible Customer shall provide DesertLink:

(a) a complete copy of each executed Affected System Arrangement;
(b) evidence that all financial security or credit support required to be effective before construction under each Affected System Arrangement has been provided;

(c) evidence of any required Commission filing, acceptance, or other regulatory authorization; and

(d) a certification that each Affected System Arrangement remains in full force and effect and that Eligible Customer is not in default thereunder.

DesertLink may permit specifically identified preliminary engineering, procurement, or other limited activities to proceed before satisfaction of this Section by written notice. Such permission shall not waive any requirement of this Section or obligate DesertLink to commence or continue physical construction. 4.2.4. Continuing Obligation. Eligible Customer shall promptly provide DesertLink a copy of any material amendment, replacement, termination notice, default notice, demand upon financial security or credit support, or other material notice concerning an Affected System Arrangement. Eligible Customer shall maintain each required Affected System Arrangement and all financial security or credit support required thereunder until the obligations secured by that arrangement have been finally satisfied, transferred, or released.

4.2.5. Later-Identified Affected Systems. If an Affected System or Affected System Upgrade is identified after DesertLink has commenced work, Eligible Customer shall promptly enter into the required Affected System Arrangement and provide the documentation required by this Section. Subject to the applicable tariffs and agreements, DesertLink may suspend further work, procurement, energization, or service to the extent reasonably necessary to avoid additional exposure until the requirement is satisfied.

4.2.6. Failure to Satisfy Requirements. Eligible Customer’s failure to timely execute, maintain, or provide evidence of an Affected System Arrangement or required financial security or credit support constitutes a material default under this Agreement. Subject to Applicable Laws and Regulations and the applicable tariffs and agreements, DesertLink may: (a) decline to commence or continue construction or material procurement commitments; (b) suspend work, energization, or service;

PDF page 110

18

(c) exercise the termination right in Section 3.3.1; and (d) recover all resulting Pre- In-Service Termination Costs and other amounts payable under this Agreement. 4.2.7. Confidentiality. Documents provided under this Section shall be subject to the confidentiality protections in Section 6.12. Eligible Customer may redact commercially sensitive provisions unrelated to the requirements of this Section, but may not redact information reasonably necessary for DesertLink to verify the scope, effectiveness, cost responsibility, financial security or credit support, termination protection, or continuing enforceability of the Affected System Arrangement. 4.2.8. Separate Administration. Costs, revenues, payments, and financial security or credit support arising under an Affected System Arrangement shall be administered under that arrangement and the applicable Affected System Owner’s tariff. Such amounts shall not be included in any Annual MTRC, Total Required Revenue Commitment, Supplemental MTRC, Cumulative Revenue Responsibility, or TRBAA Credit, except to the extent expressly authorized by the Commission and necessary to prevent duplicate recovery.

5. Regulatory Approval(s)
5.1.
FERC Filing. This Agreement is the form of agreement required under Sections 10.9 and 10A.6 of the TO Tariff as a condition of DesertLink’s design, procurement, and construction of Large Load-Driven Upgrades. Consistent with 18 C.F.R. § 35.1(g), a conforming, executed Agreement entered into under the Commission-accepted pro forma with populated Schedules generally shall not require an individual filing under Section 205 of the Federal Power Act. DesertLink shall file an unexecuted Agreement or an Agreement containing a material deviation, and any other agreement required to be filed by Commission order or rule. If FERC does not accept a required filing in its entirety, the Parties shall use reasonable efforts to amend and refile it; regulatory rejection does not excuse incurred construction costs or payment, Security, and true-up obligations for facilities placed in service, except to the extent FERC expressly determines otherwise.

6. Cost Recovery
6.1.
Cost Recovery and Minimum Contribution. DesertLink shall include the Large Load-Driven Upgrades in its Formula Rate to the extent the project costs are properly includable under the Formula Rate, the Protocols, and applicable law. This Agreement does not remove any Covered Upgrade from rate base or require a capital-cost reimbursement. The fixed twenty (20)-year Annual MTRC for each Covered Upgrade is instead calculated under the MTRC Calculation Template in Schedule 5, initially using estimated cost and then using final incurred cost on the applicable Final MTRC Determination Date. DesertLink shall recover its formula-rate revenue requirement through TAC and shall flow TRBAA Credits through to transmission customers through the TRBAA as provided in Section 6.8. Amounts received under this Agreement are not inputs to the Formula Rate, and this Agreement does not require any modification of the Formula Rate. Eligible Customer shall pay a Supplemental

PDF page 111

19

MTRC only to the extent forecast or actual Qualifying Transmission Revenues are less than the applicable Annual MTRC. The Annual MTRC is a revenue floor, not an additive charge, and does not alter CAISO cost allocation or DesertLink plant accounting.

Eligible Customer acknowledges that DesertLink will incur costs and undertake planning, engineering, procurement, and construction in reliance on the Large Load Facility’s development and operation. Eligible Customer therefore accepts the wholesale payment and Security obligations in this Agreement. Any retail recovery from the Large Load Customer remains governed exclusively by applicable state law and Eligible Customer’s retail arrangements.

Affected System Upgrades and the associated costs, revenues, payments, and financial security or credit support are governed by Section 4.2 and the applicable Affected System Arrangement. Unless expressly authorized by the Commission, no Affected System Upgrade or associated revenue requirement shall be included in DesertLink’s Annual MTRC, Total Required Revenue Commitment, Supplemental MTRC, Cumulative Revenue Responsibility, or TRBAA Credit.

6.2.
Qualifying Transmission Revenues. For each Rate Year or partial Rate Year, “Qualifying Transmission Revenues” means wholesale transmission revenues paid by or on behalf of Eligible Customer under the CAISO Tariff or another Commission- accepted arrangement that are attributable to service to the Large Load Facility and reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement. Qualifying Transmission Revenues include: (a) the portion of TAC revenue attributable to the Large Load Facility and allocable to DesertLink under the reproducible methodology in Schedule 2; and (b) Wheeling Access Charges and other wholesale transmission-access, wheeling, or transmission-service charges paid to CAISO, a Participating TO, or a non-PTO transmission or load-serving entity for deliveries serving the Large Load Facility, but only to the extent they reduce transmission revenues otherwise collected through TAC or directly credit DesertLink’s Net Revenue Requirement and are not otherwise reflected as a credit in calculating the Annual MTRC, the Supplemental MTRC, or a TRBAA Credit. Qualifying Transmission Revenues do not include Supplemental MTRC Receipts, Applied Security Proceeds, retail charges, or amounts that do not reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement.

6.3.
Annual MTRC and Allocation.
6.3.1. Upgrade-Specific MTRC Calculation. DesertLink shall calculate a separate Annual MTRC for each Covered Upgrade solely under the MTRC Calculation Template in Schedule 5. Before the Final MTRC Determination Date, DesertLink shall calculate and update the Estimated Annual MTRC from the then-current estimated capital cost. Within one (1) year after the applicable Covered Upgrade enters service, when the actual capital cost of that Covered Upgrade is known and all costs associated with its estimated capital cost have been accounted for,

PDF page 112

20

DesertLink shall establish the Final Annual MTRC using final incurred capital cost and the Project-Specific Levelized Fixed Charge Rate calculated under Schedule 5. Schedule 5 shall calculate the Project-Specific Levelized Fixed Charge Rate by: (i) determining the present-worth revenue requirement using the applicable capital structure, cost of debt, return on equity, federal and state income-tax rates, income- tax conversion factor, and levelized-depreciation schedule; (ii) applying a depreciation rate of five percent (5%) of the applicable capital cost input in each year of the twenty (20)-year MTRC Term to calculate present-worth federal and state income-tax depreciation benefits; (iii) annualizing the resulting present-worth revenue requirement over the MTRC Term using the applicable after-tax discount rate and annualization factor; and (iv) adding the fixed expense allocator specified in Schedule 5. The Final Annual MTRC shall equal the applicable final incurred capital cost multiplied by the resulting Project-Specific Levelized Fixed Charge Rate. No component reflected in the Project-Specific Levelized Fixed Charge Rate or the fixed expense allocator shall be added again as a separate component of the Annual MTRC. The Final Annual MTRC and the Schedule 5 inputs used to calculate it are fixed as of the Final MTRC Determination Date and shall not be recalculated for later changes in actual cost, Formula Rate inputs, or other cost-of- service components, except to correct an error or fraud, to implement an effective prospective reassignment, to implement a final FERC order applicable to the calculation, or to reflect, prospectively, a change in (i) DesertLink’s return on equity component of its Formula Rate, resulting from a final FERC order accepting or approving such change, or (ii) applicable federal or state income tax rates or income tax law enacted after the Final MTRC Determination Date; provided that, the five percent (5%) annual levelized-depreciation schedule in Schedule 5 shall remain fixed for the MTRC Term unless a final FERC order requires otherwise. If DesertLink adjusts the Final Annual MTRC after the Final MTRC Determination Date pursuant to the foregoing provision, DesertLink shall update the MTRC Calculation Template and serve it upon Eligible Customer in accordance with the notice provisions contained in this Agreement. Upon such service to Eligible Customer, the updated MTRC Calculation Template shall replace the existing MTRC Calculation Template in its entirety and become effective on the date of such service. The foregoing effectiveness of an updated MTRC Calculation Template does not preclude Eligible Customer from disputing any change to the MTRC Calculation Template pursuant to Article 11 of this Agreement. Any resulting adjustment to the Total Required Revenue Commitment shall apply only to the Rate Years remaining in the MTRC Term as provided in Section 6.7.

Each Annual MTRC shall apply for its separate twenty (20)-year MTRC Term, with the initial and final partial Rate Years prorated based on the number of monthly Billing Periods in the applicable Rate Year during which the Covered Upgrade is in service. Schedule 1 shall identify the initial Estimated Annual MTRC and initial projected Total Required Revenue Commitment for each Large Load-Driven Upgrade, and Schedule 5 shall record the Final MTRC Determination Date, Final Annual MTRC, Total Required Revenue Commitment, and the completed

calculation for each Covered Upgrade. Schedule 4 shall provide the corresponding

PDF page 113

21

project-specific information for a DesertLink-owned CAISO-Assigned Regional Project, if applicable.

6.3.2. Initial Allocation. Schedule 1 shall identify, separately for each Large Load- Driven Upgrade, the percentage of the upgrade initially allocated to the Large Load Customer under this Agreement (the “Initial Allocation Percentage”). The Initial Allocation Percentage shall be determined using the applicable final study and allocation methodology and shall account for:

(a) Large Load Customers studied individually, jointly, or in a cluster;
(b) the extent to which two or more Large Load Customers caused the need for or share a Large Load-Driven Upgrade;

(c) differing requested service levels, development phases, and facility configurations; and

(d) any portion of the facility determined at the outset to serve other transmission system needs or customers.

The aggregate percentages allocated to all Large Load Customers for a Large Load- Driven Upgrade shall not exceed one hundred percent (100%). Any portion not allocated to a Large Load Customer shall be excluded from the Annual MTRC allocable to any Large Load Customer and remain subject to the otherwise- applicable CAISO cost allocation and rate recovery requirements. 6.3.3. Applicable Allocation Percentage. For each Large Load-Driven Upgrade, the “Applicable Allocation Percentage” shall equal the Initial Allocation Percentage identified in Schedule 1, as adjusted prospectively by any reassignment effective under Section 6.9 or as otherwise required by a final Commission order or applicable tariff provision. A cancellation, abandonment, downsizing, curtailment, permanent cessation, or material reduction of service by the Large Load Customer shall not, by itself, reduce the Applicable Allocation Percentage. 6.3.4. Annual MTRC Allocation. The Annual MTRC applicable to Eligible Customer shall equal the Annual MTRC for the Covered Upgrade as a whole multiplied by the Applicable Allocation Percentage; provided that, where Schedule 5 applies that percentage to capital cost or otherwise calculates the Annual MTRC for an already allocated project share, the resulting Annual MTRC is already allocated and the percentage shall not be applied again. DesertLink shall maintain the calculation separately by Large Load Customer, Large Load Facility, and Covered Upgrade. The aggregate Annual MTRCs allocated to all large load customers shall not exceed the Annual MTRC for the Covered Upgrade as a whole.

6.3.5. CAISO-Assigned Regional Projects Owned by DesertLink. For each CAISO- Assigned Regional Project owned by DesertLink and included in its Formula Rate, DesertLink shall calculate separately the Regional Project Allocated ARR attributable to the specific share formally assigned to the Large Load Facility. The Regional Project Allocated ARR shall be calculated solely under the MTRC Calculation Template in Schedule 5, using DesertLink’s allocated share of the

PDF page 114

22

project’s estimated capital cost before the Final MTRC Determination Date and its allocated share of final incurred capital cost on that date, and shall be established, updated, and fixed in the same manner and on the same schedule that Section 6.3.1 provides for other Covered Upgrades. The resulting Annual MTRC shall be included in the Supplemental MTRC calculation and the Total Required Revenue Commitment beginning on the Regional Project In-Service Date. The allocated share shall be determined under the applicable allocation under the CAISO Tariff or Commission-accepted methodology and the project-specific information in Schedule 4. No portion assigned to other customers, other facilities, or broader regional needs shall be included. Before the Regional Project In-Service Date, any costs of a cancelled or abandoned project shall be treated under the applicable CAISO Tariff, Commission order, and any abandoned-plant incentive specifically authorized for that project. This Agreement does not create a separate pre-service payment or Construction Security obligation solely because CAISO has assigned a regional project share to Large Load Facility. Any pre-service payment, contribution, or security required by the CAISO Tariff, an applicable Interconnection Agreement, or another Commission-accepted arrangement remains due under that authority and shall be identified in Schedule 4. Any abandoned-plant recovery, customer payment, or security proceeds shall receive the accounting and rate treatment required by the Commission, and any credit necessary to prevent duplicate recovery of the same costs shall be recorded in the TRBA and flowed through to transmission customers through the TRBAA as provided in Section 6.8. Any prospective adjustment or reassignment of the share assigned to the Large Load Facility shall occur only as provided by the CAISO Tariff or a Commission- accepted methodology. Rate base inclusion, depreciation, and other accounting for the underlying project share remain subject to the Formula Rate, the Protocols, and the Commission's Uniform System of Accounts; this Section 6.3.5 governs only the calculation of the Annual MTRC applicable to the Large Load Facility under this Agreement.

6.3.6. CAISO-Assigned Regional Projects Owned by Another Entity. If CAISO formally assigns a specific share of a CAISO-Assigned Regional Project to the Large Load Facility and that project is not owned by DesertLink or is not included in DesertLink’s Formula Rate, Eligible Customer shall satisfy the assigned share under the CAISO Tariff or enter into and maintain the required arrangement with the project owner or other responsible entity. The arrangement shall address, as applicable, payment of assigned costs and revenue responsibility, construction and cancellation obligations, security or credit support, invoicing, reconciliation, true- up, refund, release, and any required regulatory filing or acceptance. Eligible Customer shall provide DesertLink a copy of the executed arrangement or other evidence reasonably sufficient to demonstrate compliance, including the amount and basis of the assigned share, the billing party, payment terms, and required security. Eligible Customer shall provide the required arrangement or evidence by the deadline specified in Schedule 4, which shall be no later than the earliest applicable deadline under the CAISO Tariff or project-owner arrangement and, where the

PDF page 115

23

assignment is known before construction, before the project owner commences construction. If CAISO makes the assignment after construction has commenced or after the project enters service, Eligible Customer shall comply within the period specified by CAISO or the project owner and provide evidence to DesertLink promptly. Failure to comply is an Event of Default if not cured as provided in Section 7.11(c).

Amounts owed to another project owner are not included in any Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, Supplemental MTRC, Cumulative Revenue Responsibility, or TRBAA Credit unless the amount is included in DesertLink’s Formula Rate and Schedule 4 expressly identifies it as DesertLink’s assigned share. The applicable tariff or project-owner arrangement shall identify and apply any credits required to prevent duplicate recovery of the same assigned share through both a direct charge and a transmission rate. Payments to another owner satisfy only the corresponding obligation under that tariff or arrangement and do not reduce the Cumulative Revenue Responsibility owed to DesertLink unless they satisfy the same underlying obligation included in DesertLink’s Formula Rate. The Eligible Customer’s obligations under this Section survive termination of this Agreement and cessation of service until the assigned share has been paid or assumed by a successor and the obligation has been discharged, transferred, or released under the applicable CAISO Tariff or project-owner arrangement by the entity entitled to enforce it. 6.4.

Supplemental MTRC. Beginning on the in-service date of each Covered Upgrade, Eligible Customer shall pay the positive shortfall, if any, between the applicable Annual MTRC, prorated for a partial Rate Year based on the number of monthly Billing Periods in that Rate Year during which the Covered Upgrade is in service, and Qualifying Transmission Revenues attributable to the Large Load Facility during the corresponding Rate Year or partial Rate Year. Until the Final MTRC Determination Date, billing shall use the Estimated Annual MTRC. Upon initial finalization, the Final Annual MTRC shall apply back to the applicable in-service date, and estimated charges shall be reconciled in the next Reconciliation Statement under Section 6.6. Thereafter, the calculation shall use the Final Annual MTRC, subject to adjustments permitted by Section 6.3.1. Qualifying Transmission Revenues attributable to a specific Covered Upgrade shall be applied to that upgrade. Qualifying Transmission Revenues not attributable to a specific Covered Upgrade shall be allocated among the Covered Upgrades then in their MTRC Terms pro rata based on their respective prorated Annual MTRCs for the applicable period.

The calculation may be expressed as:
Supplemental MTRC = max (applicable Annual MTRC − Qualifying Transmission Revenues, $0).

The Annual MTRC is not an annual true-up of project cost or Formula Rate inputs. Annual reconciliation is limited to Qualifying Transmission Revenues, Supplemental MTRC invoices and receipts, Applied Security Proceeds, TRBAA Credits, partial-year

PDF page 116

24

proration, effective prospective reassignment, and correction of error, fraud, a final FERC order applicable to the calculation, and any prospective recalculation of the Final Annual MTRC permitted by Section 6.3.1.

6.5.
Invoice. With each Annual Projection, DesertLink shall forecast Qualifying Transmission Revenues and calculate the projected Supplemental MTRC using the applicable fixed or estimated Annual MTRC from Schedule 5, increased or reduced by any prior-period true-up adjustment under Section 6.6. DesertLink shall invoice the forecasted Supplemental MTRC for the applicable Rate Year or partial Rate Year in equal monthly installments for each Billing Period in that Rate Year during which the Covered Upgrade is in service; for a full Rate Year, the projected Supplemental MTRC shall be invoiced in twelve (12) equal monthly installments. Each installment is payable within thirty (30) Calendar Days after receipt of the invoice. If a Covered Upgrade reaches its applicable in-service date during a Rate Year for which the Annual Projection did not include a projected Supplemental MTRC for that Covered Upgrade, DesertLink shall promptly forecast Qualifying Transmission Revenues and invoice the prorated Supplemental MTRC for the remaining Billing Periods of that Rate Year. DesertLink shall include the projected Supplemental MTRC, including any prior-period true-up adjustment, as a Forecast TRBAA Credit in the next annual TRBAA under Section 6.8. Only cash actually received by DesertLink, or Applied Security Proceeds actually applied by DesertLink, constitutes an actual receipt for purposes of Sections 6.6 through 6.8. Concurrently with each Annual Projection, DesertLink shall provide Eligible Customer upgrade-specific workpapers showing the applicable Annual MTRC, forecast Qualifying Transmission Revenues, projected Supplemental MTRC, any prior-period true-up adjustment, Forecast TRBAA Credit, Total Required Revenue Commitment, and Required Operational Security. 6.6.

Annual Reconciliation Statement. In connection with each Annual Update, DesertLink shall determine the actual Supplemental MTRC obligation using actual Qualifying Transmission Revenues and the applicable fixed or estimated Annual MTRC from Schedule 5. DesertLink shall identify, by Eligible Customer and Covered Upgrade, the opening unpaid billed Supplemental MTRC balance, Supplemental MTRC invoiced during the Rate Year, cash received by DesertLink, Applied Security Proceeds applied to identified obligations, direct recoveries, closing unpaid billed balance, and each Annual Termination Fee Credit. Concurrently with each Annual Update, DesertLink shall serve on Eligible Customer a Reconciliation Statement containing those determinations, the updated Cumulative Revenue Ledger, Required Operational Security recalculated under Section 7.4, a reconciliation of the Forecast TRBAA Credit to actual amounts recorded in the TRBA, and supporting workpapers. An unpaid Supplemental MTRC remains due from Eligible Customer and, when later received or satisfied through Applied Security Proceeds, is recorded in the TRBA only in the Rate Year of receipt or application. The Reconciliation Statement shall not reopen the Final Annual MTRC or Total Required Revenue Commitment except as expressly allowed by Section 6.3.1.

The difference between the Supplemental MTRC billed for a Rate Year, excluding any prior-period true-up adjustment included in that billing, and the actual Supplemental

PDF page 117

25

MTRC determined in the Reconciliation Statement for that Rate Year shall constitute a “prior-period true-up adjustment,” which shall increase (if under-billed) or reduce (if over-billed) the projected Supplemental MTRC invoiced under Section 6.5 following the next Annual Projection. If no further Supplemental MTRC will be invoiced under this Agreement, DesertLink shall invoice any under-billed amount, payable within thirty (30) Calendar Days after receipt of the invoice, and shall refund any over-billed amount to Eligible Customer within thirty (30) Calendar Days after service of the Reconciliation Statement. No interest shall accrue on the Supplemental MTRC or on any prior-period true-up adjustment, invoice, refund, or other adjustment of the Supplemental MTRC between DesertLink and Eligible Customer. Any refund to Eligible Customer of an amount previously recorded as a TRBAA Credit shall be reversed in the TRBA when paid, and any under-billed amount later received shall be recorded in the TRBA when received, in each case as provided in Section 6.8. Any amount returned by DesertLink to transmission customers through the TRBAA shall include interest as provided in Section 5.5 of the TO Tariff.

A Reconciliation Statement shall become final on the earlier of (a) Eligible Customer’s written acceptance of the Reconciliation Statement or (b) ninety (90) Calendar Days after service, unless before that date Eligible Customer serves a Notice of Dispute under Section 11.1 identifying with reasonable specificity the items disputed. If a Notice of Dispute is timely served, the undisputed portions of the Reconciliation Statement shall become final on the date that would otherwise apply, and the disputed items shall become final upon the applicable Dispute Determination under Section 11.5. A final Reconciliation Statement may be revised only to implement a Dispute Determination, to reflect CAISO resettlements or other corrected data as provided in Schedule 2, or to correct errors or fraud. Finality of a Reconciliation Statement under this Agreement does not affect the Commission’s review and approval of any TRBAA.

For purposes of this Agreement, Supplemental MTRC Receipts exclude Applied Security Proceeds. Applied Security Proceeds shall be counted only when DesertLink applies such proceeds to satisfy an identified payment obligation and shall reduce that obligation dollar-for-dollar. The posting, maintenance, replenishment, drawing, or holding of Security shall not, by itself, constitute a Supplemental MTRC Receipt, an Applied Security Proceed, satisfaction of the Cumulative Revenue Responsibility, or a TRBAA Credit.

No amount shall be counted both as a Supplemental MTRC Receipt and as an Applied Security Proceed. If DesertLink receives payment of an obligation previously satisfied through Applied Security Proceeds, DesertLink shall not count the subsequent payment toward the Cumulative Revenue Responsibility or a TRBAA Credit and shall instead return the duplicative amount, release an equivalent amount of Security, or, with supporting notice to Eligible Customer, apply the amount to another then- outstanding obligation under this Agreement.

6.7.
Cumulative Revenue Responsibility and Break-Even. DesertLink shall maintain a Cumulative Revenue Ledger for each Covered Upgrade and shall update it at least

PDF page 118

26

annually in connection with the Annual Update. DesertLink shall include an updated Cumulative Revenue Ledger statement, with supporting workpapers, in each Reconciliation Statement served on Eligible Customer under Section 6.6. For each Covered Upgrade, the Total Required Revenue Commitment equals the Final Annual MTRC multiplied by twenty (20), adjusted only for partial-year proration and any prospective recalculation of the Final Annual MTRC permitted by Section 6.3.1, which shall apply only to the Rate Years remaining in the MTRC Term after the recalculation takes effect. Until the Final MTRC Determination Date, the projected Total Required Revenue Commitment shall equal the Estimated Annual MTRC multiplied by twenty (20).

Remaining Cumulative Revenue Responsibility equals the applicable Total Required Revenue Commitment less:

(a) cumulative Qualifying Transmission Revenues;
(b) cumulative Supplemental MTRC Receipts;
(c) cumulative Applied Security Proceeds;
(d) effective prospective reassignment credits; and
(e) cash amounts received and applied toward the Termination Fee, excluding any portion satisfied through Applied Security Proceeds already counted under clause (c).

Each dollar shall be entered in the Cumulative Revenue Ledger only once. Supplemental MTRC Receipts shall exclude Applied Security Proceeds. Applied Security Proceeds shall be entered only when applied to an identified Supplemental MTRC, prior-period true-up adjustment, Termination Fee, or other payment obligation under Article 6 or Section 3.3.4. Security that is posted, drawn but not applied, held as a deferred liability, replenished, replaced, or returned shall not reduce the Cumulative Revenue Responsibility. Annual Termination Fee Credits and the corresponding Termination Fee Balance shall be separately identified in the Reconciliation Statement and in the workpapers required under Section 6.8 and shall not again reduce the Cumulative Revenue Responsibility.

If an amount previously credited in the Cumulative Revenue Ledger is subsequently refunded, reversed, disallowed, or otherwise ceases to satisfy the applicable obligation, DesertLink shall make a corresponding adjustment to the ledger, subject to the finality and no-revival provisions of this Section.

Cancellation, downsizing, curtailment, or departure does not extinguish the remaining responsibility. When a final Reconciliation Statement determines that the responsibility has reached zero (“Break-Even”), DesertLink shall terminate the operational payment and Security obligations and release any excess Security. Once finally satisfied, the responsibility shall not revive because of a later change in ROE, expense, load, forecast, or other Formula Rate input, subject only to final true-ups and correction of errors or fraud for periods before satisfaction.

PDF page 119

27

6.8.
TRBAA Credit and No Double Recovery. Supplemental MTRC Receipts, Applied Security Proceeds other than Applied Security Proceeds applied to a Termination Fee, Annual Termination Fee Credits, and any duplicate-recovery credit under Section 3.3.3(d) or Section 6.3.5 shall be credited to transmission customers solely through the TRBAA and shall not be recorded as revenue credits in, or otherwise included as inputs to, the Formula Rate. In each annual TRBAA, DesertLink shall include as the Forecast TRBAA Credit: (a) the projected Supplemental MTRC for the following Rate Year, increased or reduced by any prior-period true-up adjustment invoiced under Section 6.5; and (b) for any Covered Upgrade with a Termination Fee Balance, the Annual Termination Fee Credit scheduled under Section 3.3.4 for the following Rate Year, prorated as applicable and limited to the available Termination Fee Balance. DesertLink shall record in the TRBA only Supplemental MTRC cash receipts, Applied Security Proceeds other than Applied Security Proceeds applied to a Termination Fee, and Annual Termination Fee Credits actually received, applied, or scheduled for the applicable Rate Year, respectively. Applied Security Proceeds applied to a Termination Fee shall be deposited into and held in the Termination Fee Account under Section 3.3.4 and shall be credited to transmission customers solely through the applicable Annual Termination Fee Credits. The difference between the Forecast TRBAA Credit and those actual amounts shall be reflected in the principal balance of the TRBA and flowed through to transmission customers in a subsequent TRBAA. A billed but unpaid Supplemental MTRC is not a TRBAA Credit. A later Supplemental MTRC Receipt or Applied Security Proceeds, other than Applied Security Proceeds applied to a Termination Fee, shall be recorded only in the Rate Year in which it is received or applied, respectively. Any amount previously recorded as a TRBAA Credit that is later refunded, reversed, or otherwise ceases to satisfy the applicable obligation shall be reversed in the TRBA when refunded or reversed. Interest on the TRBA balance shall be calculated as provided in Section 5.5 of the TO Tariff. Qualifying Transmission Revenues shall not be included again as a TRBAA Credit because they are already reflected in calculating the Supplemental MTRC.

Each dollar shall be included in a TRBAA Credit only once. Applied Security Proceeds shall not also be treated as Supplemental MTRC Receipts, and the posting, drawing, holding, replenishment, replacement, or return of Security shall not independently produce a TRBAA Credit. A Forecast TRBAA Credit applies only to the forecast Rate Year and shall be reconciled through the TRBA to actual Supplemental MTRC Receipts, Applied Security Proceeds other than those applied to a Termination Fee, and Annual Termination Fee Credits, as applicable. DesertLink shall maintain workpapers reconciling each Forecast TRBAA Credit and each amount recorded in the TRBA under this Section 6.8 to the applicable Annual MTRC calculation in Schedule 5, forecast and actual Qualifying Transmission Revenues, opening unpaid billed balance, Supplemental MTRC invoiced, prior-period true-up adjustment, Supplemental MTRC cash receipt, Applied Security Proceed, direct recovery, closing unpaid billed balance, Termination Fee Balance, Annual Termination Fee Credit, resulting forecast-to-actual TRBA difference, Rate Year, Large Load Customer, and Covered Upgrade. DesertLink shall include with each

PDF page 120

28

TRBAA filing workpapers sufficient to permit transmission customers to verify the TRBAA Credits reflected in that TRBAA, which may present customer-specific information on an aggregated basis or be submitted subject to a request for privileged treatment under 18 C.F.R. § 388.112 or other appropriate confidentiality protections. 6.9.

Prospective Reassignment of Revenue Responsibility.
6.9.1. Eligibility for Reassignment of Revenue Responsibility. Whether or not the Large Load Customer remains in service, a portion of the prospective revenue responsibility associated with a Large Load-Driven Upgrade may be reassigned to a subsequent load customer if an objective transmission study conducted under the applicable tariff or study process determines that:

(a) the subsequent large load customer relies upon identifiable incremental capability created by the Large Load-Driven Upgrade; and

(b) that reliance avoids or reduces identifiable transmission upgrades that otherwise would have been required to provide the subsequent large load customer’s requested service.

Incidental power flows, generalized system benefits, or use of the transmission system that does not satisfy both requirements shall not support a reassignment. This Section 6.9 applies only to a load customer other than the Large Load Customer, at a facility other than the Large Load Facility. It does not apply to a transfer of ownership or operation of the Large Load Facility, a change in Eligible Customer, or an assignment of this Agreement, which are governed by Sections 6.10 and 10.1 and do not alter the Applicable Allocation Percentage or the Large Load-Driven Upgrades attributable to the Large Load Facility.

6.9.2. Reassignment Calculation. DesertLink shall determine the prospective reassignment separately for each Large Load-Driven Upgrade satisfying Section 6.9.1 (each, a “Shared Upgrade”). For each Shared Upgrade:

(a) the Demonstrated Avoided Upgrade Cost shall equal the reasonable estimated cost of the transmission upgrades that would have been required for the subsequent large load customer absent the Shared Upgrade, less the reasonable estimated cost of any additional transmission upgrades required when the capability of the Shared Upgrade is considered;

(b) the Remaining Allocated Net Plant shall equal the portion of the Shared Upgrade’s net plant balance included in rate base immediately before the reassignment that remains assigned to the Large Load Customer under this Agreement;

(c) the Capability-Supported Amount shall equal the portion of the Remaining Allocated Net Plant reasonably attributable to the incremental capability of the Shared Upgrade actually relied upon by the subsequent large load customer; and

(d) the Reassigned Investment Amount shall equal the least of:

PDF page 121

29

(i) the Demonstrated Avoided Upgrade Cost;
(ii) the Capability-Supported Amount; and
(iii) the Remaining Allocated Net Plant.
The Demonstrated Avoided Upgrade Cost, Capability-Supported Amount, and Remaining Allocated Net Plant shall be determined using a consistent cost basis and price year. If Remaining Allocated Net Plant is greater than zero, the Reassignment Percentage shall equal the Reassigned Investment Amount divided by the Remaining Allocated Net Plant, bounded between zero and one hundred percent (100%). If Remaining Allocated Net Plant is zero or negative, no Reassignment Percentage shall be calculated under this methodology; any reassignment shall require an applicable tariff methodology or Commission determination addressing that circumstance.

6.9.3. Prospective Adjustment of Revenue Responsibility. Beginning on the Reassignment Effective Date, the applicable Annual MTRC assigned to the Large Load Customer shall be prospectively reduced by the Reassignment Percentage applied to the Shared Upgrade. DesertLink shall record a separate effective prospective reassignment credit in the Cumulative Revenue Ledger equal to the Reassignment Percentage multiplied by the Remaining Cumulative Revenue Responsibility associated with the Shared Upgrade that remains assigned to the Large Load Customer immediately before the Reassignment Effective Date. That credit shall be the sole Cumulative Revenue Ledger adjustment for the reassigned responsibility. It shall not adjust the Total Required Revenue Commitment or result in a second reduction to the Remaining Cumulative Revenue Responsibility or Required Operational Security for the same reassigned responsibility. DesertLink shall recalculate the Supplemental MTRC and Operational Security under this Agreement to reflect the reassignment. The Reassignment Effective Date shall be the latest of:

(a) the date the subsequent large load customer commences the service for which the Shared Upgrade provides the identified incremental capability;

(b) the effective date of a cost recovery agreement establishing the subsequent large load customer’s corresponding revenue responsibility;

(c) the date on which all Security required from the eligible customer serving the subsequent large load customer becomes effective; and

(d) the date on which the study and any other approvals required under the applicable tariff become final.

No reduction in the Large Load Customer’s Operational Security shall occur until the corresponding responsibility and required Security have become effective for the subsequent large load customer.

6.9.4. Prospective Treatment and Prevention of Duplicate Reassignment. A reassignment under this Section shall:

PDF page 122

30

(a) operate prospectively only and shall not produce a refund, credit, or reopening of amounts properly determined for a prior Rate Year;

(b) transfer prospective revenue responsibility only and shall not constitute a sale or transfer of transmission facilities, a transfer of plant ownership, a change in plant accounting, or a modification of any CAISO cost allocation;

(c) not exceed the prospective responsibility remaining under this Agreement for the Shared Upgrade; and

(d) not assign the same transmission capability, avoided upgrade cost, Annual MTRC, or Cumulative Revenue Responsibility to more than one large load customer.

DesertLink shall maintain an upgrade-specific reassignment ledger identifying the capability and responsibility assigned to each large load customer. Once responsibility has been effectively reassigned, that responsibility shall not revert to the Large Load Customer if the subsequent large load customer later terminates, reduces, or fails to commence service. The reassigned responsibility shall instead remain with the subsequent large load customer and the Eligible Customer responsible for its payment, subject to any further prospective reassignment permitted under the applicable agreement and tariff.

Any prospective reassignment, adjustment, or change in the cost share of a CAISO- Assigned Regional Project shall be recognized under this Agreement only to the extent authorized or required by the CAISO Tariff or a Commission-accepted methodology. DesertLink shall apply an effective change prospectively to the Regional Project Allocated ARR, Cumulative Revenue Responsibility, Supplemental MTRC, TRBAA Credit, and Operational Security, and shall update Schedule 4 and the applicable workpapers. The change shall not assign the same project share to more than one customer or alter costs allocated to other customers under the CAISO Tariff.

6.10. Change in Eligible Customer. Cost responsibility is assigned to the Large Load Customer and Large Load Facility, as paid by the Eligible Customer then taking wholesale transmission service on behalf of the Large Load Customer and Large Load Facility. If the Eligible Customer serving a Large Load Customer or Large Load Facility changes, the Successor Eligible Customer must execute an assumption agreement covering the Cumulative Revenue Responsibility and any outstanding obligations under Section 6.3.6, provide required Security, and become responsible on a date coordinated with CAISO billing before the prior Eligible Customer is released. Following the complete departure of the Large Load Customer, the last responsible Eligible Customer remains obligated unless responsibility is transferred under an applicable tariff or state-law mechanism, assumed by a successor, or prospectively reassigned as permitted under this Agreement and the CAISO Requirements. If ownership or operation of the Large Load Facility is transferred, Eligible Customer shall notify DesertLink within thirty (30) Calendar Days and shall cause the transferee to execute a Limited Acknowledgment in the form attached to this Agreement. The transfer shall not alter the Applicable Allocation Percentage, Cumulative Revenue Responsibility, or Security obligations under this Agreement.

PDF page 123

31

A sale, lease, or other transfer of the Large Load Facility, or of the Large Load Customer’s interest in such Large Load Facility, is not a reassignment under Section 6.9 and does not require a study under Section 6.9.1. Cost responsibility shall continue to follow the Large Load Facility, the transferee shall execute a Limited Acknowledgment substantially in the form included in this Agreement, and Eligible Customer shall remain responsible for its obligations under this Agreement unless they are transferred to a Successor Eligible Customer under this Section 6.10. 6.11. CAISO Data and Settlement Coordination. Eligible Customer shall provide DesertLink, or authorize and direct its Scheduling Coordinator, Utility Distribution Company, Metering Coordinator, and other applicable entities to provide DesertLink, with the metering, settlement, billing, resettlement, allocation, and other data reasonably necessary to calculate and verify Qualifying Transmission Revenues and administer this Agreement. Eligible Customer shall execute any authorization or data- release documentation reasonably necessary for DesertLink to obtain such information.

To the extent authorized or required by the CAISO Tariff, CAISO may provide or make available relevant settlement, metering, billing, resettlement, and allocation data as provided under the CAISO Requirements. Nothing in this Agreement, however, imposes an obligation on CAISO or makes CAISO a party to this Agreement. DesertLink and Eligible Customer shall cooperate with CAISO and other applicable entities to establish and maintain the billing identifiers, metering points, data exchanges, and authorizations identified in Schedule 2.

DesertLink shall calculate Qualifying Transmission Revenues, the Annual MTRC, and the Supplemental MTRC; maintain the Cumulative Revenue Ledger; and serve on Eligible Customer the Reconciliation Statement, including the Cumulative Revenue Ledger statement, required by Sections 6.6 and 6.7.

If final data are not available when a calculation is required, DesertLink may use reasonable estimates based on the best information then available, subject to reconciliation under Section 6.6 when final or corrected data become available. 6.12. Information Rights and Confidentiality. Upon reasonable request, DesertLink shall provide Eligible Customer the workpapers, data, and other information reasonably necessary to verify the identification of Large Load-Driven Upgrades and CAISO- Assigned Regional Projects and all calculations of each Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, Qualifying Transmission Revenues, Supplemental MTRC, Cumulative Revenue Responsibility, TRBAA Credits, reassignment, and Security under this Agreement. Any dispute concerning those matters shall be resolved under Article 11. Large Load Customer and any Successor Eligible Customer may participate in a dispute under Article 11 to the extent the dispute affects its obligations under this Agreement or its Limited Acknowledgment. Customer-specific information shall be protected under Section 16.3 of the TO Tariff, the CAISO Tariff, and any applicable confidentiality agreement.

PDF page 124

32

7. Security and Payment Obligations
7.1.
Construction Security. Before an applicable Large Load-Driven Upgrade reaches its Upgrade In-Service Date, Eligible Customer shall maintain Construction Security under the relevant agreement sufficient to secure:

(a) DesertLink’s incurred and irrevocably committed engineering, design, procurement, permitting, construction, testing, and related costs attributable to that upgrade; and

(b) the Pre-In-Service Termination Costs described in Section 3.3.2, including properly accrued AFUDC and applicable cancellation, demobilization,

equipment removal, disposition, remediation, and restoration costs
(“Construction Security”).
Construction Security secures, but does not limit, Eligible Customer’s liability for those amounts. Construction Security provided under the relevant Interconnection Agreement or an engineering and procurement agreement for the same costs shall count toward, and shall not be duplicated by, the Construction Security required under this Agreement. Construction Security shall remain in effect for each Large Load- Driven Upgrade until that upgrade reaches its Upgrade In-Service Date and the applicable release or conversion conditions in Section 7.2 are satisfied. A Large Load-Driven Upgrade reaching its Upgrade In-Service Date shall not result in the release of Construction Security attributable to another Large Load-Driven Upgrade that has not reached its Upgrade In-Service Date. Eligible Customer shall replenish Construction Security within ten (10) Business Days after notice of a permitted draw and supporting information if additional secured obligations remain and the remaining Construction Security is less than the amount required under this Section.

For a CAISO-Assigned Regional Project owned by DesertLink, any pre-service payment, contribution, or security required from Eligible Customer for its formally assigned share shall be provided only as required by the CAISO Tariff, an applicable Interconnection Agreement, or another Commission-accepted arrangement, and shall be identified in Schedule 4. This Agreement does not independently require pre- service Construction Security solely because CAISO has assigned a share of a regional project to the Large Load Facility. The treatment of costs for a cancelled or abandoned regional project shall be governed by Section 6.3.5 and the applicable Commission order, CAISO Tariff, and any project-specific abandoned-plant incentive authorized by the Commission. For a project owned by another entity, construction and operational security shall be provided under the CAISO Tariff or the arrangement required by Section 6.3.6 and Schedule 4; it shall not be treated as DesertLink Operational Security unless included in DesertLink’s Formula Rate and expressly identified as DesertLink’s share.

7.2.
Delivery of Operational Security. No later than thirty (30) Calendar Days before the earliest expected Upgrade In-Service Date identified in Schedule 1 or Regional Project

PDF page 125

33

In-Service Date identified in Schedule 4 for a DesertLink-owned CAISO-Assigned Regional Project, Eligible Customer shall deliver Operational Security calculated under this Article for the Large Load-Driven Upgrades and DesertLink-owned CAISO-Assigned Regional Project expected to enter service. Operational Security must be fully effective before any applicable Upgrade In-Service Date or Regional Project In-Service Date.

If different Large Load-Driven Upgrades or DesertLink-owned CAISO-Assigned Regional Projects are expected to reach their applicable in-service dates on different dates, DesertLink shall recalculate the Required Operational Security before each subsequent in-service date to include the additional Cumulative Revenue Responsibility attributable to the upgrade or project share entering service. Eligible Customer shall provide any resulting increase no later than fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier. Inclusion of pre-service Construction Work in Progress in rate base shall not constitute an Upgrade In-Service Date or independently trigger the Operational Security requirement. Construction Security shall remain applicable to each Large Load-Driven Upgrade that has not reached its Upgrade In-Service Date.

No Construction Security attributable to a Large Load-Driven Upgrade shall be released or converted unless:

(a) the Required Operational Security attributable to that upgrade is effective;
(b) that upgrade has reached its Upgrade In-Service Date; and
(c) DesertLink has determined that all Pre-In-Service Termination Costs and other construction-related obligations attributable to that upgrade have been paid or adequately reserved for.

Any portion of Construction Security retained for unresolved construction costs shall be released after DesertLink determines that those costs have been paid or adequately reserved for or, if Section 3.3.2 applies, after the Termination Cost Reconciliation becomes final. Failure to timely deliver Required Operational Security is a default permitting DesertLink, to the extent authorized by the applicable tariffs and agreements, to suspend energization or service, terminate applicable interconnection arrangements, and draw Construction Security for secured obligations. 7.3.

Required Operational Security. Required Operational Security shall equal one hundred percent (100%) of the nominal Remaining Cumulative Revenue

Responsibility. DesertLink shall reduce that amount only by the portion of Qualifying Retail Security Support identified in a currently effective Retail Security Certification. A Retail Security Certification is accepted in reliance on Eligible Customer’s representations and does not require DesertLink to review the underlying retail- security documents in the ordinary course. If DesertLink has a reasonable basis to question the certification, or after a payment default, Credit Review Event, or Material Adverse Credit Event, DesertLink may request supporting information reasonably necessary to verify continued compliance. Any resulting deficiency shall be delivered

PDF page 126

34

or restored within fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier.

7.4.
Annual Resizing and Security Notices. DesertLink shall recalculate Required Operational Security with each Annual Projection, Final MTRC Determination Date, recalculation of a Final Annual MTRC under Section 6.3.1, Reconciliation Statement, effective prospective reassignment, replacement or expiration of Qualifying Retail Security Support, or Credit Review Event. If DesertLink reasonably determines that the Required Security Amount exceeds available Security, it may issue a Security Notice identifying the required increase or restoration and reasonable supporting detail then available. Eligible Customer shall provide the required increase or restoration within fifteen (15) Business Days after receipt of the Security Notice, or by the applicable in-service date if earlier. A reduction shall be released only after the relevant calculation and reconciliation are final.

7.5.
Form of Operational Security. Except to the extent of currently effective Qualifying Retail Security Support, Eligible Customer shall provide direct Operational Security in the form of cash, an irrevocable standby Letter of Credit meeting Schedule 3, or any combination of cash and Letter of Credit. DesertLink may accept another form of Security that it determines, in its sole discretion, is acceptable.

Each Letter of Credit shall have an initial stated term of at least twelve (12) months and shall remain continuously effective until released under this Agreement; provided, however, that a Letter of Credit may have a stated expiration date before its release date if Eligible Customer timely extends or replaces it so that Security in an amount not less than the Required Security Amount remains continuously available to DesertLink.

If an issuing bank has the right not to renew a Letter of Credit, the Letter of Credit shall require the issuing bank to provide DesertLink and Eligible Customer at least ninety (90) Calendar Days’ prior written notice of nonrenewal. Eligible Customer shall provide a conforming extension or replacement Letter of Credit, or additional cash collateral or other Security accepted by DesertLink, no later than sixty (60) Calendar Days before the applicable expiration date.

If Eligible Customer fails to provide the required extension, replacement, or other Security by that deadline, DesertLink may, before the Letter of Credit expires, draw all or any portion of the then-available amount under the Letter of Credit and retain the proceeds as cash collateral, apply the proceeds to secured obligations, or both. Any proceeds retained but not applied shall continue to constitute Security until released under this Agreement.

7.6.
Draw and Application. DesertLink may draw against all or any portion of a Letter of Credit, apply cash collateral, or apply another form of Security accepted by DesertLink to secured obligations upon: (a) an unpaid Supplemental MTRC, true-up, Termination Fee, or other amount due after the applicable payment period; (b) Eligible Customer’s failure to timely deliver, maintain, replace, restore, or increase Security;

PDF page 127

35

(c) cancellation, termination, withdrawal, abandonment, or permanent cessation of the Large Load Facility or a material breach of this Agreement; (d) a material inaccuracy in a Retail Security Certification or Security instrument; (e) Eligible Customer: (i) files a voluntary petition in bankruptcy or seeks reorganization, arrangement, or similar relief under any bankruptcy, insolvency, or debtor-relief law; (ii) becomes subject to an involuntary bankruptcy or insolvency proceeding that is not dismissed within sixty

(60) Calendar Days; (iii) has a receiver, trustee, liquidator, or custodian appointed for it or a substantial portion of its assets, which appointment is not vacated within sixty

(60) Calendar Days; (iv) makes a general assignment for the benefit of creditors; or (v) admits in writing its inability to pay debts as they become due; or (f) Eligible Customer fails to extend, replace, or otherwise maintain Security in the amount and within the time required by Section 7.5, including following a notice of nonrenewal, issuer rating reduction, or other event affecting the availability of a Letter of Credit. A draw shall not automatically require replenishment to the amount maintained immediately before the draw. Following any application of drawn proceeds to an amount due, DesertLink shall recalculate the remaining Cumulative Revenue Responsibility and the Operational Security then required under this Article. Eligible Customer shall replenish only the amount, if any, by which the remaining Operational Security is less than the recalculated Required Security Amount, within fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier.

Proceeds drawn solely to prevent the expiration or nonrenewal of a Letter of Credit, and cash collateral not yet applied to an identified payment obligation, shall remain refundable Security and shall continue to constitute Operational Security until applied to an amount then due or released under Section 7.9. Such proceeds and cash collateral shall be included in determining the amount of remaining Operational Security and shall not create an additional replenishment obligation merely because they are held by DesertLink.

The posting, drawing, holding, replacement, or replenishment of Operational Security shall not, by itself, satisfy the secured obligation, reduce Cumulative Revenue Responsibility, or produce a TRBAA Credit. Drawn proceeds of Operational Security shall become Applied Security Proceeds only when DesertLink applies them to an identified Supplemental MTRC, prior-period true-up adjustment, Termination Fee, or other secured payment obligation arising under Article 6 or Section 3.3.4. Upon application, the proceeds shall reduce that obligation dollar-for-dollar and shall receive the TRBAA treatment required by Section 6.8; provided, however, that Applied Security Proceeds applied to a Termination Fee shall be administered under Section 3.3.4 and credited to transmission customer only through the Annual Termination Fee Credits provided under Section 6.8. Proceeds of Construction Security applied to Pre- In-Service Termination Costs or other construction-related obligations shall be treated as provided in Sections 3.3.2 and 3.3.3.

7.7.
Security Maintenance. Because Required Operational Security is initially one hundred percent (100%) of nominal Remaining Cumulative Revenue Responsibility,

PDF page 128

36

no separate acceleration concept applies. An incorrect, expired, withdrawn, unavailable, or materially misleading Retail Security Certification, or the loss of enforceable retail-security rights described in it, is a Material Adverse Credit Event. Eligible Customer shall provide replacement direct Security for any resulting uncovered amount within fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier.

7.8.
Post-Termination Administration and Cash Collateral. DesertLink shall continue the annual calculations, invoices, and true-ups required under this Agreement following termination of service to, or the departure, permanent cessation, or material reduction of service by, the Large Load Customer until the Cumulative Revenue Responsibility and all other obligations under this Agreement have been finally satisfied, transferred, reassigned, refunded, or otherwise resolved. The Parties intend that cash collateral and proceeds of Security be treated as a deposit or deferred liability rather than as a Contribution in Aid of Construction, customer financing of transmission plant, or a reduction to DesertLink’s rate base. To the extent permitted by applicable Commission accounting and ratemaking requirements and tax law, DesertLink shall record and administer such amounts as the corresponding annual costs and payment obligations arise. The treatment described in this Section is subject to the Commission’s Uniform System of Accounts, the Formula Rate, the Protocols, applicable Commission orders, and other Applicable Laws and Regulations. If the Commission requires a different accounting or ratemaking treatment, DesertLink shall implement the required treatment and make corresponding adjustments necessary to prevent duplicate recovery and preserve, to the extent permitted, the economic allocation established by this Agreement. The Parties shall cooperate in seeking any necessary Commission authorization or acceptance.

Nothing in this Agreement guarantees a particular accounting, ratemaking, or tax result. Cash collateral and unapplied Security proceeds shall remain subject to release under Section 7.9, including release to reflect an effective prospective reassignment under Section 6.9.

7.9.
Release of Security. DesertLink shall release excess Operational Security only after the applicable Reconciliation Statement becomes final. DesertLink shall release Security attributable to an effective prospective reassignment and shall release all remaining Security within thirty (30) Calendar Days after final satisfaction of the Cumulative Revenue Responsibility and all other secured obligations. Termination alone does not require release.

7.10. Security Does Not Limit Liability. The Required Security Amount is based on DesertLink’s then-current estimates and calculations and does not cap, replace, or discharge Eligible Customer’s underlying obligations. A shortfall between Security and the amount due remains immediately payable to DesertLink.

7.11. Events of Default; Remedies. Each of the following is an “Event of Default” by Eligible Customer: (a) failure to pay any undisputed amount when due that continues for ten (10) Business Days after written notice from DesertLink; (b) failure to deliver,

PDF page 129

37

maintain, replace, restore, or increase Security when required under this Article 7 or Schedule 3 that continues after the applicable cure period; (c) any other material breach of this Agreement, including under Section 4.2 or 6.3.6, that continues for thirty (30) Calendar Days after written notice from DesertLink or, if the breach cannot reasonably be cured within that period, for such longer period, not to exceed ninety

(90) Calendar Days, as Eligible Customer diligently pursues a cure; and (d) any event described in Section 7.6(e). Upon an Event of Default, DesertLink may, subject to Applicable Laws and Regulations and the applicable tariffs and agreements: (i) draw and apply Security under Section 7.6; (ii) exercise the rights described in Sections 4.2.6 and 7.2; (iii) before the first Upgrade In-Service Date or Regional Project In- Service Date, terminate this Agreement under Section 3.3.1; and (iv) pursue any other remedy available at law or in equity or before the Commission. No termination after an Upgrade In-Service Date or Regional Project In-Service Date releases the obligations described in Section 3.3.4.

8. Force Majeure.
8.1.
If a Party is rendered unable, wholly or in part, by Force Majeure to carry out a nonmonetary obligation, that obligation shall be suspended only to the extent and for the period performance is prevented. Force Majeure does not suspend or excuse payment of incurred construction costs, Pre-In-Service Termination Costs, Supplemental MTRC, the Termination Fee, prior-period true-up adjustments, or the maintenance, replacement, replenishment, or increase of Security. If a Force Majeure event continues for more than twenty (20) Calendar Days in a sixty (60)-Calendar Day period, the Parties shall meet to address performance; any resulting termination remains subject to Sections 3.4 and 3.5.

9. Indemnification
9.1.
Indemnity. Each Party (the “Indemnifying Party”) shall at all times indemnify, defend, and hold the other Party and its Affiliates and their respective directors, officers, employees, and agents (each, an “Indemnified Person”) harmless from any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the Indemnifying Party’s actions or omissions in performing its obligations under this Agreement, except to the extent caused by the gross negligence or willful misconduct of the Indemnified Person.

9.1.1.
Indemnified Person. If an Indemnified Person is entitled to indemnification as a result of a claim by a third party, and the Indemnifying Party fails, after notice and reasonable opportunity to proceed, to assume the defense of such claim, such Indemnified Person may at the expense of the Indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.

PDF page 130

38

9.1.2.
Indemnifying Party. If an Indemnifying Party is obligated to indemnify and hold any Indemnified Person harmless, the amount owing to the Indemnified Person shall be the amount of such Indemnified Person’s actual loss, net of any insurance or other recovery.

9.2.
Indemnity Procedures. Promptly after receipt by an Indemnified Person of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in Section 9.1 may apply, the Indemnified Person shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect a Party’s indemnification obligation unless such failure or delay is materially prejudicial to the Indemnifying Party. The Indemnifying Party shall have the right to assume the defense thereof with counsel designated by such Indemnifying Party and reasonably satisfactory to the Indemnified Person. If the defendants in any such action include one or more Indemnified Persons and the Indemnifying Party and if the Indemnified Person reasonably concludes that there may be legal defenses available to it and/or other Indemnified Persons which are different from or additional to those available to the Indemnifying Party, the Indemnified Person shall have the right to select separate counsel to assert such legal defenses and to otherwise participate in the defense of such action on its own behalf. In such instances, the Indemnifying Party shall only be required to pay the fees and expenses of one additional attorney to represent an Indemnified Person or Indemnified Persons having such differing or additional legal defenses.

The Indemnified Person shall be entitled, at its expense, to participate in any such action, suit or proceeding, the defense of which has been assumed by the Indemnifying Party. Notwithstanding the foregoing, the Indemnifying Party (i) shall not be entitled to assume and control the defense of any such action, suit or proceedings if and to the extent that, in the opinion of the Indemnified Person and its counsel, such action, suit or proceeding involves the potential imposition of criminal liability on the Indemnified Person, or there exists a conflict or adversity of interest between the Indemnified Person and the Indemnifying Party, in which event the Indemnifying Party shall pay the reasonable expenses of the Indemnified Person, and (ii) shall not settle or consent to the entry of any judgment in any action, suit or proceeding without the consent of the Indemnified Person, which shall not be unreasonably withheld, conditioned or delayed.

9.3.
Consequential Damages. Except for amounts expressly payable under Articles 3, 4, 6, and 7, no Party shall be liable under this Agreement for special, indirect, incidental, consequential, or punitive damages, including lost profit or revenue, loss of use, cost of capital, or temporary equipment or services, under any theory of liability. Amounts required to satisfy the Cumulative Revenue Responsibility, Supplemental MTRC, construction costs, prior-period true-up adjustments, and Security obligations are direct contractual payment obligations and are not excluded damages.

PDF page 131

39

10. Assignment
10.1. Except for a change in Eligible Customer governed by Section 6.10, a Party may assign this Agreement only with the other Party’s written consent; provided that a Party may assign to an Affiliate with equal or greater creditworthiness and legal and operational capacity to perform. No assignment or change in retail service provider releases the existing Eligible Customer until the assignee or Successor Eligible Customer executes the required assumption, provides required Security, and the transfer becomes effective under the applicable tariffs. Any prohibited assignment is void, and Security provided by or on behalf of Large Load Customer does not make Large Load Customer the wholesale obligor.

11. Disputes
All disputes, claims, or controversies arising out of or relating to this Agreement, including any dispute concerning the identification or allocation of Large Load-Driven Upgrades or Covered Upgrades; any calculation, update, or recalculation of an Estimated Annual MTRC, Final Annual MTRC, Regional Project Allocated ARR, or the MTRC Calculation Template; Qualifying Transmission Revenues; Supplemental MTRC; Total Required Revenue Commitment; Cumulative Revenue Responsibility; TRBAA Credits; Pre-In-Service Termination Costs; the Termination Fee; prospective reassignment; or Security, shall be resolved under this Article 11, except that a dispute concerning CAISO’s designation of a regional project or assignment of a project cost share shall be resolved under the applicable CAISO Tariff procedures. Any payment, refund, credit, or other adjustment resulting from the resolution of a dispute under this Article 11 shall be implemented as provided in Section 11.5. 11.1. Submission and Informal Resolution. In the event of a dispute or claim arising out of or relating to this Agreement, the disputing Party shall provide the other Party with a written notice describing the dispute (“Notice of Dispute”). The dispute shall be referred promptly to designated senior representatives for informal resolution. The representatives shall meet or confer within ten (10) Business Days and shall use reasonable efforts to resolve the matter within thirty (30) Calendar Days after receipt of the Notice of Dispute. This informal process is not a condition to seeking emergency relief, filing a FERC complaint, or invoking any ADR processes. 11.2. Alternative Dispute Resolution. If a dispute is not resolved informally, any Party may request Alternative Dispute Resolution (“ADR”). The Parties shall use the ADR procedures, neutral-selection process, confidentiality protections, and timing requirements specified in the applicable FERC rules. ADR shall be conducted by persons knowledgeable in electric utility, transmission, and FERC matters and shall not alter a jurisdictional rate, term, or condition unless accepted or approved by the FERC.

11.3. FERC Complaints and Other Rights. Any Party may instead file a complaint, petition, or other pleading with the FERC under Section 206 or Section 306 of the Federal Power Act, or seek other relief available under the Federal Power Act or Applicable Laws and Regulations, and DesertLink may make any filing under Section

PDF page 132

40

205 of the Federal Power Act permitted by Section 12.12. No Party’s participation in informal negotiations or ADR waives or limits its right to seek FERC action. A final ADR determination affecting jurisdictional rates, terms, conditions, charges, or Network Upgrades shall be filed with the FERC if required.

11.4. Costs and Interim Performance. Unless otherwise determined through ADR, the Parties shall bear their own costs and share neutral costs as specified by the applicable ADR procedure. During a dispute, each Party shall continue performing undisputed payment and operational obligations, and shall pay undisputed amounts when due. 11.5. Implementation of Dispute Determinations; TRBAA. Within thirty (30) Calendar Days after a dispute under this Article 11 is finally resolved, whether by written agreement of the Parties, a final ADR determination (subject to any required Commission filing or acceptance), or a final Commission order (each, a “Dispute Determination”), DesertLink shall: (a) update the affected MTRC Calculation Template, Schedules, Cumulative Revenue Ledger, Reconciliation Statement, and Required Operational Security, as applicable, and serve the updated documents on Eligible Customer; and (b) invoice or refund, as applicable, any amount owed between the Parties as a result of the Dispute Determination, without interest. To the extent a Dispute Determination changes a TRBAA Credit or any other amount previously credited to, or recovered from, transmission customers, including any change in Supplemental MTRC Receipts or Applied Security Proceeds for a prior Rate Year, DesertLink shall record the resulting difference in the TRBA under Section 6.8 and flow it through to transmission customers through the TRBAA, and any amount so returned by DesertLink to transmission customers shall include interest as provided in Section 5.5 of the TO Tariff. If a final Commission order in a proceeding concerning DesertLink’s TRBAA requires a change to any TRBAA Credit attributable to this Agreement, DesertLink shall implement that order in the TRBA and shall make any corresponding updates and adjustments between the Parties under this Section 11.5 as if the order were a Dispute Determination. Nothing in this Section reopens the Final Annual MTRC or Total Required Revenue Commitment except as required to implement a Dispute Determination or as permitted by Section 6.3.1.

12. Miscellaneous.
12.1. Amendment. Except for updates to the MTRC Calculation Template expressly authorized by Section 6.3.1, updates implementing a Dispute Determination under Section 11.5, and administrative updates expressly permitted elsewhere in this Agreement, this Agreement may be amended only by a written instrument executed by the Parties. An authorized template update shall not change the substantive methodology or other terms of this Agreement. Any material deviation from the Commission-accepted pro forma and any unexecuted amendment shall be filed with FERC as required by the applicable tariffs and Commission rules.

12.2. Entire Agreement. This Agreement, its Schedules, the relevant Interconnection Agreement, and other agreements expressly incorporated herein state the Parties’ complete understanding concerning the wholesale cost recovery mechanism. Nothing

PDF page 133

41

in this Agreement establishes the retail rates, charges, or security arrangements between Eligible Customer and Large Load Customer.

12.3. Governing Tariffs and Order of Precedence. This Agreement shall be interpreted and administered consistently with the Federal Power Act, applicable Commission orders, the CAISO Tariff, and the TO Tariff. The CAISO Tariff, the TO Tariff, and any other tariff or agreement within the CAISO Requirements that is on file with or accepted by the Commission control over this Agreement and its Schedules to the extent of an irreconcilable conflict, with each controlling the matters within its respective scope. Nothing in this Agreement shall require a Party or CAISO to take action inconsistent with an applicable Commission-accepted tariff, agreement, or order.

Subject to the preceding paragraph:
(a) the Formula Rate and Protocols shall control the calculation, information exchange, and true-up of DesertLink’s Net Revenue Requirement, including the rate base treatment of the Covered Upgrades; Section 5.5 of the TO Tariff shall control the flow-through of TRBAA Credits to transmission customers through the TRBAA; and any dispute concerning a TRBAA Credit, or any other matter arising under this Agreement, shall be resolved under Article 11, and any resulting adjustment shall be implemented as provided in Section 11.5. The MTRC Calculation Template in Schedule 5, and not the Formula Rate or Protocols, shall control calculation of the Estimated Annual MTRC and Final Annual MTRC;

(b) this Agreement shall control the determination and administration of the Supplemental MTRC, Cumulative Revenue Responsibility, Operational Security, prospective reassignment, and the other wholesale revenue-support obligations established herein;

(c) the applicable Interconnection Agreement shall control the physical interconnection, design, engineering, procurement, construction, testing, energization, and operating requirements, except to the extent this Agreement expressly establishes or supplements construction-cost, pre-service termination- cost, revenue-support, or Security obligations; provided that the applicable instruments shall be interpreted, to the extent reasonably possible, to give effect to both agreements and prevent duplicate recovery;

(d) each applicable Affected System Arrangement shall control the design, construction, ownership, operation, cost responsibility, financial security or credit support, and cost recovery applicable to the corresponding Affected System Upgrade as between the parties to that arrangement. Nothing in this Agreement modifies an Affected System Owner’s tariff, makes DesertLink responsible for an obligation of an Affected System Owner, or makes an Affected System Owner a Party to this Agreement;

(e) the body of this Agreement shall control over a Schedule in the event of a conflict, except where the Schedule identifies a project-specific election, value, methodology, or term that this Agreement expressly authorizes the Parties to establish in the Schedule; and

PDF page 134

42

(f) the Schedules shall control over other project-specific supporting documents or workpapers that have not been filed with or accepted by the Commission. The Parties shall attempt to interpret the applicable instruments so that each is given effect and no provision is rendered superfluous. If an irreconcilable conflict affects a Commission-jurisdictional rate, term, or condition, the Parties shall seek any required Commission clarification, acceptance, or authorization. Pending resolution, the Parties shall continue performing all undisputed obligations.

12.4. Governing Law. This Agreement shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.

12.5. Severability. If any term, covenant, or condition of this Agreement or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this Agreement and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this Agreement.

12.6. No Third Party Beneficiaries. Except for the rights of Large Load Customer and any Successor Eligible Customer under Section 6.12, this Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.

12.7. Survival. Expiration or termination of this Agreement shall not affect any right, liability, or obligation that accrued before the effective date of expiration or termination or that, by its express terms or nature, is intended to continue thereafter. Without limiting the foregoing, the following shall survive expiration or termination for the period necessary to give them effect:

(a) all outstanding payment, refund, reimbursement, reconciliation, true-up, Security, and release obligations arising under Articles 3, 4, 6, and 7;

(b) the determination and final satisfaction, transfer, or prospective reassignment of the Cumulative Revenue Responsibility;

(c) the calculation and implementation of TRBAA Credits and other adjustments necessary to prevent duplicate recovery;

PDF page 135

43

(d) the confidentiality and information-protection obligations applicable under Section 6.12, Section 16.3 of the TO Tariff, the CAISO Tariff, and any applicable confidentiality agreement;

(e) the Parties’ rights to obtain, inspect, retain, verify, and challenge books, records, metering data, settlement data, calculations, and supporting workpapers relating to periods before expiration or termination;

(f) the indemnification obligations in Article 9 with respect to acts, omissions, circumstances, or claims arising before expiration or termination;

(g) the dispute-resolution provisions in Article 11 with respect to any surviving right, liability, or obligation; and

(h) any provision that expressly states that it survives or that must survive to prevent duplicate recovery or give effect to the Parties’ rights and obligations. Survival of a provision shall not extend the underlying payment or Security obligation beyond the point at which that obligation has been finally satisfied, transferred, reassigned, refunded, or released in accordance with this Agreement.

12.8. No Waiver. A Party’s delay or failure to exercise any right or remedy under this Agreement shall not constitute a waiver of that or any other right or remedy. A waiver shall be effective only if stated in a written instrument executed by the Party granting the waiver and shall apply only to the specific matter and circumstances stated therein. A waiver on one occasion shall not constitute a continuing waiver or a waiver on any other occasion. No course of performance or dealing shall amend this Agreement or waive any Commission-jurisdictional rate, term, or condition. Nothing in this Section limits a Party’s rights under the Federal Power Act or Applicable Laws and Regulations.

12.9. Counterparts and Electronic Signatures. This Agreement, any amendment, and any assumption or acknowledgment executed pursuant to it may be executed in counterparts, each of which shall be deemed an original and all of which together shall constitute one instrument. Signatures transmitted electronically, including by portable document format or an electronic-signature platform, shall have the same force and effect as original signatures to the extent permitted by Applicable Laws and Regulations. Each Party agrees that it shall not contest the validity or enforceability of an instrument solely because it was executed or transmitted electronically. 12.10. Authority. Each Party represents and warrants that:

(a) it is duly organized, validly existing, and in good standing under the laws of its jurisdiction of organization, to the extent such concepts apply;

(b) it has the requisite power and authority to execute, deliver, and perform this Agreement;

(c) the execution, delivery, and performance of this Agreement have been duly authorized by all necessary organizational action;

(d) the individual executing this Agreement on its behalf is authorized to do so; and

PDF page 136

44

(e) subject to any required Commission acceptance or other regulatory approval expressly identified in this Agreement, this Agreement constitutes its valid and binding obligation, enforceable in accordance with its terms.

The Large Load Customer represents only that the individual executing the Limited Acknowledgment is authorized to execute that acknowledgment on its behalf. Execution of the Limited Acknowledgment does not make the Large Load Customer a Party or expand its obligations beyond those expressly stated in the Limited Acknowledgment or in a separate undertaking executed by the Large Load Customer. 12.11. Notices. All notices, requests, demands, and other communications hereunder (herein collectively called “Notice”) shall be in writing and will be deemed to have been duly given when (a) personally delivered to the receiving Party’s physical address, (b) sent by overnight courier service to the receiving Party’s physical address, or (c) delivered via electronic transmission with a courtesy copy sent by overnight courier service to the receiving Party’s physical address, in each case to the appropriate addresses or email addresses set forth below (or to such other addresses or email addresses as a Party may designate by Notice to the other Party); provided that any such deliveries received after normal business hours in the place of business of the receiving Party shall be deemed to be received on the next Business Day:

If to DesertLink:

DesertLink, LLC
Attn: Asset Manager
16150 Main Circle Drive, Suite 310
Chesterfield, Missouri 63017
Email: rhohlt@lspower.com

With a copy to:

DesertLink, LLC
Attn: Legal Department
16150 Main Circle Drive, Suite 310
Chesterfield, Missouri 63017
Email: legalnotices@lspower.com

If to Eligible Customer:

[Company name]
[Contact name]
[Address]
Email: [Insert]
If to Large Load Customer:
[Company name]

PDF page 137

45

[Contact name]
[Address]
Email: [Insert]
12.12. Reservation of Rights. DesertLink shall have the right to make a unilateral filing with the Commission under Section 205 of the Federal Power Act to modify this Agreement or the pro forma form of this Agreement, and Eligible Customer shall have the right to make a unilateral filing with the Commission under Section 206 of the Federal Power Act to modify this Agreement. Each Party shall have the right to protest any such filing and to participate fully in any proceeding before the Commission. The standard of review for any proposed change to this Agreement, whether proposed by a Party, a non-party, or the Commission acting on its own motion, shall be the just and reasonable standard under Sections 205 and 206 of the Federal Power Act.

13. Project-Specific Schedules
13.1. Required Schedules. Each executed Agreement shall include the following completed schedules, which are incorporated into this Agreement.

Schedule 1 — Project and Allocation Data;
Schedule 2 — Qualifying Transmission Revenues Methodology;
Schedule 3 — Credit and Security Standards;
Schedule 4 — CAISO Regional Project Allocation and Responsibility; and Schedule 5 — MTRC Calculation Template and Cumulative Revenue Ledger [Signature page follows.]

PDF page 138

46

IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers as of the day and year first above written.

DESERTLINK, LLC
By: __________________________
Name: ________________________
Title: _________________________
Date: _________________________
[ELIGIBLE CUSTOMER]
By: __________________________
Name: ________________________
Title: _________________________
Date: _________________________

LIMITED ACKNOWLEDGMENT OF LARGE LOAD CUSTOMER
Large Load Customer acknowledges the assignment of cost responsibility to its facility and agrees to provide information and notices, authorize release of metering and settlement data, and cooperate in a transition to a Successor Eligible Customer. This acknowledgment does not make Large Load Customer the wholesale obligor, establish a FERC-jurisdictional retail rate, or constitute a guarantee of Eligible Customer’s payment obligations. Any separate guarantee or collateral undertaking by Large Load Customer shall be governed by its own terms and filed with FERC if required.

[LARGE LOAD CUSTOMER]
By: __________________________
Name: ________________________
Title: _________________________
Date: _________________________

PDF page 139

Schedule 1 - 1

Schedule 1
Project and Allocation Data
1. Purpose
This Schedule identifies the Large Load Facility, the applicable service request, each Large Load-Driven Upgrade covered by this Agreement, the initial allocation of each Large Load- Driven Upgrade, and the applicable construction and operational security information. This Schedule is incorporated into and made part of the Agreement.

2. Large Load Facility and Service Information
Large Load Customer
[●]
Eligible Customer
[●]
Large Load Facility
[Name and description]
Physical Location of Large
Load Facility
[●]
Point of Interconnection
[●]
Metering Point or Settlement
Identifier
[●]
Requested Service Level
[●] MW
Requested Service Phases
[Identify the MW and expected commencement date of
each phase]
Expected Large Load Service
Commencement Date
[●]
Outside Date
[●]
Applicable Study or
Authorization
[Study name, number, version, and date]
Applicable Interconnection,
Transmission Service, or Other
Agreement
[●]
CAISO or Other Relevant
Project Identifier
[●]

PDF page 140

Schedule 1 - 2

3. Large Load-Driven Upgrade Information
Each Large Load-Driven Upgrade shall be identified separately. Upgrade 1

Upgrade Description
[●]
Applicable Study or
Authorization
[●]
Owner and Construction
Responsibility
[●]
Initial Estimated Capital Cost
$[●]
Expected Construction
Commencement Date
[●]
Expected Upgrade In-Service
Date
[●]
Actual Upgrade In-Service Date [●]
MTRC Term End Date
[●]
Shared, Phased, or Dependent
Facility
[●]

PDF page 141

Schedule 1 - 3

Upgrade 2
Upgrade Description
[●]
Applicable Study or
Authorization
[●]
Owner and Construction
Responsibility
[●]
Initial Estimated Capital Cost
$[●]
Expected Construction
Commencement Date
[●]
Expected Upgrade In-Service
Date
[●]
Actual Upgrade In-Service Date [●]
MTRC Term End Date
[●]
Shared, Phased, or Dependent
Facility
[●]

Upgrade 3
Upgrade Description
[●]
Applicable Study or
Authorization
[●]
Owner and Construction
Responsibility
[●]
Initial Estimated Capital Cost
$[●]
Expected Construction
Commencement Date
[●]
Expected Upgrade In-Service
Date
[●]
Actual Upgrade In-Service Date [●]
MTRC Term End Date
[●]
Shared, Phased, or Dependent
Facility
[●]

PDF page 142

Schedule 1 - 4

4. Initial Allocation and Annual MTRC Information
For each Large Load-Driven Upgrade, the Initial Allocation Percentage assigned to the Large Load Customer under this Agreement shall be identified below. The sum of the percentages allocated to all Large Load Customers for a Large Load-Driven Upgrade shall not exceed one hundred percent (100%).

Upgrade 1
Initial Estimated Annual
MTRC Attributable to Covered
Upgrade
$[●]
Initial Allocation Percentage
Assigned to This Large Load
Customer
[●]%
Initial Estimated Annual
MTRC Allocated to This Large
Load Customer
$[●]
Aggregate Initial Allocation
Percentage Assigned to All
Large Load Customers
[●]%
Percentage Allocated to Other
System Needs or Customers
[●]%

PDF page 143

Schedule 1 - 5

Upgrade 2
Initial Estimated Annual
MTRC Attributable to Covered
Upgrade
$[●]
Initial Allocation Percentage
Assigned to This Large Load
Customer
[●]%
Initial Estimated Annual
MTRC Allocated to This Large
Load Customer
$[●]
Aggregate Initial Allocation
Percentage Assigned to All
Large Load Customers
[●]%
Percentage Allocated to Other
System Needs or Customers
[●]%

Upgrade 3
Initial Estimated Annual
MTRC Attributable to Covered
Upgrade
$[●]
Initial Allocation Percentage
Assigned to This Large Load
Customer
[●]%
Initial Estimated Annual
MTRC Allocated to This Large
Load Customer
$[●]
Aggregate Initial Allocation
Percentage Assigned to All
Large Load Customers
[●]%
Percentage Allocated to Other
System Needs or Customers
[●]%

Any portion of a Large Load-Driven Upgrade not allocated to a Large Load Customer shall be excluded from the Annual MTRC allocable to any Large Load Customer and shall remain subject to otherwise-applicable CAISO cost allocation and rate recovery requirements.

PDF page 144

Schedule 1 - 6

5. Allocation Methodology and Capability Basis
The Initial Allocation Percentage for each Large Load-Driven Upgrade is supported by the following study findings and allocation methodology:

Upgrade 1
Customers or Projects Studied
Together
[●]
Allocation Methodology
[●]
Requested Service or Electrical
Impact Used in Allocation
[●]
Incremental Capability Created
by Upgrade, if Quantified
[●] MW or other applicable measure
Capability Initially Assigned to
This Large Load Customer
[●]
Explanation of Any Percentage
Allocated to Other System
Needs or Customers
[●]
Upgrade 2
Customers or Projects Studied
Together
[●]
Allocation Methodology
[●]
Requested Service or Electrical
Impact Used in Allocation
[●]
Incremental Capability Created
by Upgrade, if Quantified
[●] MW or other applicable measure
Capability Initially Assigned to
This Large Load Customer
[●]
Explanation of Any Percentage
Allocated to Other System
Needs or Customers
[●]

PDF page 145

Schedule 1 - 7

Upgrade 3
Customers or Projects Studied
Together
[●]
Allocation Methodology
[●]
Requested Service or Electrical
Impact Used in Allocation
[●]
Incremental Capability Created
by Upgrade, if Quantified
[●] MW or other applicable measure
Capability Initially Assigned to
This Large Load Customer
[●]
Explanation of Any Percentage
Allocated to Other System
Needs or Customers
[●]

The allocation methodology shall account for, as applicable:
(a) Large Load Customers studied individually, jointly, or in a cluster;
(b) the extent to which two or more Large Load Customers caused the need for or share a Large Load-Driven Upgrade;

(c) differing requested service levels, electrical impacts, development phases, and facility configurations;

(d) facilities constructed in phases or placed in service on different dates; and
(e) any portion of a facility determined at the outset to serve other system needs or customers.

6. Initial Cumulative Revenue Responsibility and Security Information
Upgrade 1
Initial Projected Cumulative
Revenue Responsibility
$[●]
Construction Security
Attributable to Upgrade
$[●]
Date Operational Security Must
Become Effective
[●]
Initial Projected Incremental
Operational Security
Attributable to Upgrade
$[●]

PDF page 146

Schedule 1 - 8

Upgrade 2
Initial Projected Cumulative
Revenue Responsibility
$[●]
Construction Security
Attributable to Upgrade
$[●]
Date Operational Security Must
Become Effective
[●]
Initial Projected Incremental
Operational Security
Attributable to Upgrade
$[●]
Upgrade 3
Initial Projected Cumulative
Revenue Responsibility
$[●]
Construction Security
Attributable to Upgrade
$[●]
Date Operational Security Must
Become Effective
[●]
Initial Projected Incremental
Operational Security
Attributable to Upgrade
$[●]

The Initial Projected Cumulative Revenue Responsibility stated above represents the initial projection of the Total Required Revenue Commitment for the applicable Large Load-Driven Upgrade, calculated as the Estimated Annual MTRC multiplied by twenty (20) using the MTRC Calculation Template in Schedule 5.

Construction Security shall remain applicable separately to each Large Load-Driven Upgrade until that upgrade reaches its Upgrade In-Service Date and the applicable conditions for release or conversion under Section 7.2 have been satisfied.

Operational Security must be fully effective before the applicable Upgrade In-Service Date. If different Large Load-Driven Upgrades are expected to reach their Upgrade In-Service Dates on different dates, DesertLink shall recalculate the required Operational Security before each subsequent Upgrade In-Service Date in accordance with Article 7.

PDF page 147

Schedule 1 - 9

7. Schedule Qualifications
7.1 Projected Amounts. The capital costs, Estimated Annual MTRC, projected Total Required Revenue Commitment, Cumulative Revenue Responsibility, and Operational Security amounts stated in this Schedule are initial projections provided for planning and administration purposes. They do not constitute fixed amounts, caps, or guarantees.

7.2 Initial and Applicable Allocation Percentages. The Initial Allocation Percentage identified for each Large Load-Driven Upgrade shall remain the initial allocation of that upgrade to the Large Load Customer. The Applicable Allocation Percentage shall equal the Initial Allocation Percentage, as adjusted prospectively by any reassignment effective under Section 6.9 or as otherwise required by a final Commission order or applicable tariff provision. A change in capital costs, the Upgrade In-Service Date, Formula Rate inputs, or the annual revenue requirement shall not, by itself, change the Initial Allocation Percentage or Applicable Allocation Percentage. Cancellation, abandonment, downsizing, curtailment, permanent cessation, or material reduction of service by the Large Load Customer also shall not, by itself, reduce either percentage.

7.3 Allocation Limitation. The aggregate Annual MTRC assigned to all Large Load Customers for a Covered Upgrade shall not exceed one hundred percent (100%) of the Annual MTRC for that Covered Upgrade. DesertLink shall not allocate the same upgrade cost, transmission capability, or annual revenue requirement to more than one Large Load Customer. 7.4 Upgrade In-Service Dates and MTRC Term End Dates. Each Expected Upgrade In- Service Date stated in this Schedule is a planning estimate. DesertLink shall provide written notice to Eligible Customer of a material change to an Expected Upgrade In-Service Date. Within five (5) Business Days after a Covered Upgrade achieves its Upgrade In-Service Date, DesertLink shall provide written notice to Eligible Customer stating the actual Upgrade In- Service Date and the corresponding MTRC Term End Date. DesertLink shall update this Schedule and the applicable Cumulative Revenue Ledger to reflect those dates. The actual Upgrade In-Service Date shall be determined in accordance with the definition of that term in the Agreement. Inclusion of pre-service Construction Work in Progress in rate base does not constitute an Upgrade In-Service Date.

7.5 Annual Updates. Changes in the Estimated Annual MTRC, Final Annual MTRC, Total Required Revenue Commitment, Cumulative Revenue Responsibility, Supplemental MTRC, Qualifying Transmission Revenues, or Operational Security resulting from the MTRC Calculation Template in Schedule 5, the Annual Projection, the Annual Update and Reconciliation Statement, or an effective prospective reassignment under Section 6.9 do not require an amendment to this Schedule.

7.6 Prospective Reassignment. DesertLink shall maintain the customer-, project-, and upgrade-specific ledger required by Sections 6.7 and 6.9. Any prospective reassignment shall be reflected in that ledger and in the applicable Annual Projection and Reconciliation Statement. A prospective reassignment shall adjust the Applicable Allocation Percentage but shall not revise the Initial Allocation Percentage, produce a historical refund, or reopen a prior Rate Year.

PDF page 148

Schedule 1 - 10

7.7 Updated Expected Dates. An update to an expected construction commencement date, Expected Upgrade In-Service Date, or expected Large Load Service Commencement Date may be made by written notice and does not require an amendment to this Schedule unless the update also changes a material rate, term, condition, facility scope, or allocation established by this Agreement.

8. Supporting Materials
The following supporting materials are attached to or incorporated by reference into this Schedule:

1. the applicable final transmission study or studies;
2. the facilities list and cost estimate supporting each Large Load-Driven Upgrade;
3. the study-based allocation methodology and calculations;
4. the initial Annual MTRC and Total Required Revenue Commitment workpapers (per Schedule 5);

5. the initial Cumulative Revenue Responsibility calculation;
6. the Construction Security calculation;
7. the initial projected Operational Security calculation;
8. any applicable project diagrams, metering diagrams, or service-phase schedules; and
9. each applicable Affected System study, Affected System Arrangement, and evidence of required financial security or credit support.

9. Affected System Information
The following information shall be completed for each potential or confirmed Affected System. Eligible Customer shall update the information and provide the documentation required by Section 4.2 if an Affected System or Affected System Upgrade is identified or the status of an Affected System Arrangement changes.

1. Affected System Owner: [●]
2. CAISO Participating TO or External Affected System: [●]
3. Applicable Study and Project Identifier: [●]
4. Identified System Impact: [●]
5. Affected System Upgrade: [●]
6. Estimated Cost: $[●]
7. Affected System Arrangement: [Agreement name, parties, and date]
8. Required Construction Financial Security or Credit Support: $[●]
9. Required Post-In-Service Financial Security or Credit Support: $[●]
10. Commission Filing or Acceptance Required: [Yes/No; docket and status]
11. Deadline for Delivery to DesertLink: [●]
12. Current Status: [Pending/Executed/Effective]
13. If no Affected System or Affected System Upgrade has been identified when this Schedule is executed, insert the following certification:

PDF page 149

Schedule 1 - 11

No Affected System or Affected System Upgrade has been identified as of [date]. This statement does not limit Eligible Customer’s continuing obligations under Section 4.2 if an Affected System or Affected System Upgrade is subsequently identified.

PDF page 150

Schedule 2 - 1

Schedule 2
Qualifying Transmission Revenues Methodology
1. Purpose and Controlling Principles
This Schedule establishes the reproducible methodology for calculating projected and actual Qualifying Transmission Revenues attributable to the Large Load Facility. It is intended to identify wholesale transmission revenues paid by or on behalf of Eligible Customer that are attributable to the Large Load Facility and reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement. Such revenues may include applicable TAC revenues and qualifying Wheeling Access Charges or other wholesale transmission-access, wheeling, or transmission-service charges under the CAISO Tariff or another Commission-accepted arrangement, including charges paid through a non-PTO serving entity. The Supplemental MTRC therefore measures only the remaining shortfall below the applicable Annual MTRC.

Qualifying Transmission Revenues shall be counted once in calculating the Supplemental MTRC and the Cumulative Revenue Responsibility against the combined Annual MTRC for all Covered Upgrades. They shall not also be treated as a TRBAA Credit under Section 6.8 because they reduce transmission revenues otherwise collected from CAISO customers. This Schedule does not modify CAISO settlement rules, establish a retail rate, impose any obligation on CAISO, or alter any cost allocation established under the CAISO Requirements.

2. Project and Settlement Identifiers
The following information shall be completed for each Large Load Facility and updated administratively when a meter, settlement identifier, Eligible Customer, or other listed item changes. An administrative update that does not alter the Commission-accepted methodology does not require an amendment to the Agreement unless a filing is otherwise required by Applicable Laws and Regulations.

Large Load Customer
[●]
Large Load Facility
[●]
Physical location and applicable
CAISO or out-of-state service
area
[●]
Eligible Customer at service
commencement
[●]
Scheduling Coordinator
[●]
Utility Distribution Company,
Metered Subsystem, or non-
PTO serving entity
[●]

PDF page 151

Schedule 2 - 2

CAISO resource, settlement, or
load identifier(s)
[●]
Revenue-quality meter
identifier(s) and location(s)
[●]
Metering point used for this
calculation
[●]
Large Load Service
Commencement Date
[●]
Applicable TAC, Wheeling
Access Charge, or other CAISO
Tariff charge(s)
[●]
Primary source of settlement
and metering data
[●]

3. Data Sources and Responsibilities
(a) DesertLink shall calculate projected and actual Qualifying Transmission Revenues using the best available data from CAISO settlement statements, wheeling, transmission-access, and transmission service invoices, revenue-quality meter data, Eligible Customer and non-PTO serving entity billing records, Scheduling Coordinator records, and other data made available under the CAISO Tariff, another Commission-accepted arrangement, or authorized by Eligible Customer and Large Load Customer.

(b) Eligible Customer shall provide, or cause its Scheduling Coordinator, Utility Distribution Company, Metering Coordinator, or other authorized agent to provide, all information reasonably necessary to identify and verify withdrawals attributable to the Large Load Facility. Eligible Customer shall maintain all authorizations reasonably necessary for release of that information.

(c) The Large Load Customer shall provide the information and authorizations required by its Limited Acknowledgment, including information needed to distinguish the Large Load Facility from other load behind a common meter or within a common settlement identifier.

(d) DesertLink may use CAISO data made available under the CAISO Requirements or through the authorizations provided under this Agreement. Nothing in this Schedule makes CAISO a party to the Agreement or independently requires CAISO to calculate, invoice, collect, or administer the Supplemental MTRC.

(e) If final data are unavailable when a projection, invoice, Annual Update, or Reconciliation Statement is due, DesertLink may use a reasonable estimate based on the most recent available data, the service forecast, applicable TAC rates, and known settlement adjustments. Estimated amounts shall be replaced with actual data in the next practicable reconciliation.

PDF page 152

Schedule 2 - 3

4. Applicable Withdrawals
For each CAISO settlement interval or other reproducible billing interval, Applicable Withdrawals shall equal the metered energy withdrawals attributable to the Large Load Facility at the metering point identified in Section 2 of this Schedule, expressed in MWh and adjusted as follows:

(a) Imports, exports, station service, auxiliary load, behind-the-meter generation, storage charging and discharging, and other injections or withdrawals shall be treated consistently with the manner in which they are recognized for the applicable TAC charge under the CAISO Tariff.

(b) Distribution losses and transmission losses shall be included only to the extent they are included in the billing determinant for the applicable TAC component. The loss factor or method shall be identified in the project-specific table in Section 10 of this Schedule.

(c) If the Large Load Facility shares a meter or settlement identifier with other load, the withdrawals attributable to the Large Load Facility shall be determined from revenue- quality submeters or another objective allocation method identified in Section 10 of this Schedule. An allocation based solely on estimates may be used temporarily but shall be reconciled when reliable data become available.

(d) Withdrawals shall not be counted for a period before the corresponding Annual MTRC is included in the Supplemental MTRC calculation under Section 6.4 of the Agreement, except where necessary to correct a prior-period error or resettlement.

5. Applicable TAC Revenue
Applicable TAC Revenue for an interval shall equal Applicable Withdrawals multiplied by the CAISO transmission rate or rates actually applicable to those withdrawals for that interval. The calculation shall include only transmission charge components that contribute to recovery of the revenue requirement in which DesertLink’s costs are included. It shall exclude retail distribution charges, generation charges, non-transmission surcharges, taxes collected for another governmental entity, and any other charge that does not contribute to recovery of DesertLink’s transmission revenue requirement.

If CAISO uses a monthly, annual, or other non-interval billing determinant, DesertLink shall perform the calculation using that same billing period and determinant. If more than one TAC rate or component applies, each component shall be calculated separately before applying the DesertLink Allocation Factor.

6. DesertLink Allocation Factor
The DesertLink Allocation Factor shall identify the portion of Applicable TAC Revenue allocable to DesertLink for the relevant period. Unless a different Commission-accepted method is stated in Section 10 of this Schedule, the factor shall be calculated from the same revenue requirement, billing determinant, allocation percentage, and other inputs used by CAISO to include DesertLink’s net transmission revenue requirement in the applicable TAC rate. For each applicable rate component and period:

PDF page 153

Schedule 2 - 4

DesertLink Allocation Factor = DesertLink Net Revenue Requirement included in the applicable TAC component ÷ Total Net Revenue Requirement recovered through that TAC component.

If DesertLink’s revenue requirement is recovered through a project-specific, zonal, or other direct allocation rather than a systemwide factor, the corresponding Commission-accepted allocation percentage or rate component shall be used. The supporting workpapers shall identify the source and calculation of each factor.

7. Calculation of Qualifying Transmission Revenues
Projected and actual Qualifying Transmission Revenues shall be calculated as follows for each applicable interval, month, or billing period and then aggregated for the Rate Year or partial Rate Year:

Qualifying Transmission Revenues =  Qualifying TAC Revenue + Qualifying Wheeling and Other Wholesale Transmission Revenues ± Applicable Adjustments.

Qualifying TAC Revenue = Σ [(Applicable Withdrawals × Applicable TAC Rate) × DesertLink Allocation Factor]. Qualifying Wheeling and Other Wholesale Transmission Revenues equal Wheeling Access Charges and other wholesale transmission-access, wheeling, or transmission- service charges actually paid by or on behalf of Eligible Customer to CAISO, a Participating TO, or a non-PTO transmission or load-serving entity for deliveries serving the Large Load Facility, but only to the extent those revenues reduce transmission revenues otherwise collected through TAC or directly credit DesertLink’s Net Revenue Requirement. Applicable Adjustments shall include only amounts attributable to the Large Load Facility, including CAISO resettlements, billing corrections, refunds, charge reversals, balancing-account adjustments, and other adjustments that change the qualifying transmission revenue. Bad debt or uncollectible amounts shall reduce Qualifying Transmission Revenues only to the extent the corresponding revenue is not recovered from another source and is not otherwise included in DesertLink’s Formula Rate recovery.

8. Projections, Actuals, Resettlements, and Customer Changes
(a) The Annual Projection shall use forecast withdrawals, then-effective or forecast TAC rates, the most recent DesertLink Allocation Factor, and known adjustments. The workpapers shall separately identify each material assumption.

(b) The Reconciliation Statement shall replace projected values with actual withdrawals, rates, factors, and adjustments for the applicable period. CAISO resettlements or other corrections received after a Reconciliation Statement becomes final shall be reflected in the next practicable Reconciliation Statement and Annual Update, subject to Section 6.6 of the Agreement, and any dispute concerning them shall be resolved under Article 11 of the Agreement.

(c) A change in Eligible Customer, Scheduling Coordinator, or retail service provider shall not interrupt the calculation or cause the same withdrawals or revenues to be omitted or counted more than once. Qualifying Transmission Revenues shall remain associated with the Large Load Customer and Large Load Facility, regardless of which Eligible Customer is responsible for payment during the applicable period.

PDF page 154

Schedule 2 - 5

(d) If two or more Eligible Customers serve the Large Load Facility during a Rate Year, the Qualifying Transmission Revenues and corresponding Supplemental MTRC shall be assigned between them based on the periods during which each provided service, unless the applicable transition agreement provides another Commission-accepted allocation.

9. Workpapers, Verification, and Records
With each Annual Projection and Reconciliation Statement, DesertLink shall provide workpapers sufficient for Eligible Customer to reproduce the calculation, including applicable meter quantities, TAC rates, DesertLink Allocation Factors, adjustments, source references, and a reconciliation to the corresponding Supplemental MTRC and Cumulative Revenue Ledger. Customer-specific or commercially sensitive information may be provided subject to the confidentiality provisions of Section 16.3 of the TO Tariff, the CAISO Tariff, and any applicable confidentiality agreement.

DesertLink, Eligible Customer, and Large Load Customer shall retain supporting records for the period required by the CAISO Tariff, Commission regulations, and Applicable Laws and Regulations, and in all events until completion of any timely initiated review, audit, or dispute concerning the applicable Rate Year. Any dispute concerning the calculation shall be resolved under Article 11 of the Agreement.

10. Project-Specific Methodology Elections
Applicable Withdrawals
methodology
[●]
Treatment of shared meters or
identifiers
[●]
Treatment of behind-the-meter
generation and storage
[●]
Applicable TAC, Wheeling
Access Charge, or other CAISO
Tariff rate component(s)
[●]
DesertLink Allocation Factor
methodology
[●]
Loss factor or loss methodology
[●]
Treatment of exports and
station service
[●]
Treatment of refunds and
resettlements
[●]
Treatment of bad debt or
uncollectible amounts
[●]

PDF page 155

Schedule 2 - 6

Projection methodology
[●]
Data-delivery process and
timing
[●]
Other Commission-accepted
project-specific provision
[●]

The methodology shall specify the metering point, applicable local and regional TAC components, DesertLink allocation factor, applicable Wheeling Access Charges or other wholesale transmission access, wheeling, or transmission charges, the identity of any non-PTO serving entity collecting the charge, the basis for attributing each charge to the Large Load Facility, and evidence that the charge reduces transmission revenues otherwise collected through TAC or directly credits DesertLink’s Net Revenue Requirement. It also shall specify treatment of losses, refunds, resettlements, bad debt and balancing-account adjustments, treatment of a change in Eligible Customer, the source of billing and meter data, and the calculation and verification of projected and actual revenue. Qualifying Transmission Revenues count toward the annual and cumulative responsibility but are not separately credited against DesertLink’s transmission revenue requirement because they already reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement.

PDF page 156

Schedule 3 - 1

Schedule 3
Credit and Security Standards
1. Purpose and Application
This Schedule establishes the forms, delivery, maintenance, replacement, draw, application, and release requirements for all Construction Security and Operational Security required under Article 7. Except for the limited reduction of direct Operational Security provided in Section 3, all Security shall be provided directly by Eligible Customer.

2. Permitted Forms of Security
Eligible Customer may provide Security in the form of cash, a Letter of Credit, or any combination thereof. DesertLink may accept another form of Security if it determines, in its sole discretion, that the form is acceptable.

Cash collateral shall be delivered in immediately available funds to an account designated by DesertLink and shall count dollar-for-dollar toward the applicable Required Security Amount while held by DesertLink.

(a) Construction Security
Eligible Customer shall provide and maintain all Construction Security directly in one or more forms permitted under this Section 2. A Retail Security Certification and Qualifying Retail Security Support shall not constitute, reduce, replace, or satisfy Construction Security or any Pre- In-Service Termination Costs.

(b) Operational Security
Except to the extent reduced under Section 3, Eligible Customer shall provide and maintain direct Operational Security in one or more forms permitted under this Section 2 in an amount equal to one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility.

3. Retail Security Certification
A current Retail Security Certification reduces the direct Operational Security requirement dollar-for-dollar by the amount of Qualifying Retail Security Support identified in that certification. It does not reduce Eligible Customer’s underlying obligations, constitute Security posted directly with DesertLink, or apply to Construction Security or Pre-In-Service Termination Costs.

Each Retail Security Certification must be substantially in the form of Exhibit A contained in Schedule 3 of this Agreement. Eligible Customer shall deliver a Retail Security Certification before first relying on Qualifying Retail Security Support to reduce the direct Operational

PDF page 157

Schedule 3 - 2

Security requirement. The Retail Security Certification shall remain effective unless and until superseded, withdrawn, or deemed ineffective under this Agreement. Eligible Customer shall deliver an updated Retail Security Certification within three (3) Business Days after any reduction, draw, expiration, nonrenewal, termination, amendment, loss of enforceable draw or application rights, or other event that could impair the certified support.

With each Reconciliation Statement, DesertLink may identify the amount of Qualifying Retail Security Support then reflected in calculating Required Operational Security. That identification does not require Eligible Customer to deliver a new Retail Security Certification unless an event requiring an update has occurred.

DesertLink may rely on the certification without reviewing the underlying retail security documents in the ordinary course, but may request supporting information after a payment default, Credit Review Event, Material Adverse Credit Event, or reasonable basis to question the certification.

4. Letter of Credit Requirements
If Eligible Customer provides a Letter of Credit as Security, the Letter of Credit must be irrevocable, unconditional, transferable, payable at sight, and permit partial and multiple draws. It must be issued by a major United States commercial bank or United States branch of a major foreign commercial bank rated at least A- by S&P, A3 by Moody’s, or A- by Fitch, in each case by at least two of those three agencies, and otherwise be in form and substance reasonably acceptable to DesertLink.

Each Letter of Credit must have an initial stated term of at least twelve (12) months and provide DesertLink at least ninety (90) Calendar Days’ prior written notice of nonrenewal. Eligible Customer shall provide a conforming extension, replacement Letter of Credit, cash collateral, or other Security accepted by DesertLink no later than sixty (60) Calendar Days before the applicable expiration date following a notice of nonrenewal, and within fifteen (15) Business Days after an issuer rating reduction.

If Eligible Customer fails to timely provide the required replacement or substitute Security, DesertLink may, before the applicable Letter of Credit expires, draw all or any portion of the then-available amount and retain the proceeds as cash collateral, apply the proceeds to secured obligations, or both.

5. Security Notices; Maintenance; and Replenishment
DesertLink may issue a Security Notice whenever it reasonably determines that the Required Security Amount exceeds available Security, including as a result of a draw, application of cash collateral, change in the Required Security Amount, loss of Qualifying Retail Security Support, or other event affecting Security availability.

Eligible Customer shall provide any required increase, restoration, replacement, or other cure within fifteen (15) Business Days after receipt of the Security Notice, or by the applicable in- service date if earlier.

PDF page 158

Schedule 3 - 3

6. Draws; Application; and Release
DesertLink may draw against a Letter of Credit, apply cash collateral, or apply another accepted form of Security as permitted under Article 7. A draw, the holding of proceeds or cash collateral, or replenishment does not by itself satisfy an obligation or reduce Cumulative Revenue Responsibility. Proceeds of Operational Security become Applied Security Proceeds only when applied to an identified secured obligation as provided in Section 7.6; proceeds of Construction Security are treated as provided in Sections 3.3.2 and 3.3.3.

DesertLink shall release excess Security after the applicable Reconciliation Statement becomes final. DesertLink shall release all remaining Security within thirty (30) Calendar Days after final satisfaction of all secured obligations, subject to any specifically identified unresolved dispute.

7. Required Security Amount Not a Limitation
The Required Security Amount is based on then-current estimates and calculations and does not limit Eligible Customer’s total liability or responsibility for its obligations under this Agreement.

PDF page 159

Schedule 3, Exhibit A
Form of Retail Security Certification
Retail Security Certification
To: DesertLink, LLC
Re: Large Load Cost Recovery Agreement dated [●] between DesertLink, LLC and [Eligible Customer] (the “Agreement”)

The undersigned, an authorized officer of [Eligible Customer], certifies on behalf of Eligible Customer, as of the date of this certification, as follows:

1. The retail Large Load Customer is [name], and the Large Load Facility is [identify facility].
2. The retail security arrangement is [identify agreement, security type, provider or issuer, instrument number if applicable, and effective and expiration dates].

3. The amount of retail security currently available to Eligible Customer and available for the wholesale obligations under the Agreement is $[●].

4. Eligible Customer has enforceable draw or application rights, or the benefit of a binding undertaking, that permit it to use the retail-security proceeds to satisfy the corresponding wholesale obligations under the Agreement.

5. The certified amount has not been counted for another inconsistent obligation and has not been reduced, drawn, expired, cancelled, or otherwise impaired except as disclosed here: [●].

6. The retail security arrangement has the following renewal, expiration, and notice terms: [●]. Eligible Customer will deliver an updated Retail Security Certification to DesertLink within three (3) Business Days after any reduction, draw, expiration, nonrenewal, termination, amendment, loss of enforceable draw or application rights, or other event that could impair the certified support.

7. The statements in this certification are true and complete in all material respects as of the date of this certification. Eligible Customer understands that DesertLink is entitled to rely on this continuing certification without reviewing the underlying retail-security documents in the ordinary course, subject to DesertLink’s rights under Article 7 and Schedule 3. No annual renewal or recertification is required unless an updated Retail Security Certification is required under Item 6.

This Retail Security Certification is continuing and shall remain effective unless and until superseded, withdrawn, or deemed ineffective under the Agreement.

ELIGIBLE CUSTOMER
By: ________________________________
Name: ______________________________
Title: _______________________________
Date: _______________________________

PDF page 160

Schedule 4 - 1

Schedule 4
CAISO Regional Project Allocation and Responsibility
This Schedule shall identify each CAISO-Assigned Regional Project associated with the Large Load Facility. If no CAISO-Assigned Regional Project has been identified as of the Effective Date, this Schedule shall state “None identified as of [date]” and shall be updated promptly after CAISO formally assigns a specific project share to the Large Load Facility. The assigned share, ownership, expected and actual Regional Project In-Service Date, any Commission-authorized abandoned-plant incentive and its applicable order, any pre-service payment or security required by the CAISO Tariff or another Commission-accepted arrangement, billing path, applicable operational security, and credits or true-ups shall be documented below. The Schedule shall not be read to impose pre-service Construction Security under this Agreement unless separately required by the applicable tariff or Commission-accepted arrangement.

Required project information
Project-specific entry
CAISO project name and identification number
[to be completed]
Project owner and other responsible entities
[to be completed]
CAISO Tariff provision, order, study, or formal
determination establishing the specific assignment
[to be completed]
Date the assignment is made and its effective date
[to be completed]
Large Load Facility to which the specific share is
assigned
[to be completed]
Assigned share: percentage, dollar amount, or other
CAISO-approved measure
[to be completed]
Allocation basis and calculation, including any share
assigned to other beneficiaries
[to be completed]
Project ownership and whether costs are included in
DesertLink’s Formula Rate
[to be completed]
Expected and actual project in-service date
[to be completed]
Estimated Annual MTRC and, once established,
Final Annual MTRC for the project share (the
Regional Project Allocated ARR), together with the
projected Total Required Revenue Commitment, if
DesertLink-owned and included in its Formula Rate
[to be completed]

PDF page 161

Schedule 4 - 2

Required project information
Project-specific entry
Billing entity, payment method, applicable tariff or
project-owner arrangement, and invoicing schedule
[to be completed]
Construction and operational security required,
security provider, amount, effective date, and
deadline
[to be completed]
Treatment of TAC revenues, direct payments, credits,
refunds, and true-ups to prevent duplicate recovery
[to be completed]
Deadline for Eligible Customer to provide executed
arrangement or compliance evidence
[to be completed]
Method and timing for any prospective assignment
change authorized by the CAISO Tariff or
Commission-accepted methodology
[to be completed]
Commission order and status authorizing abandoned-
plant incentive for the project, including applicable
project scope and recovery terms
[to be completed]
Pre-service cancellation or abandonment cost
treatment under the CAISO Tariff, Commission
order, or approved project arrangement; any
customer contribution or security required and
applicable credits
[to be completed]
For a CAISO-Assigned Regional Project owned by another entity, this Schedule records the Eligible Customer’s separate obligation under the CAISO Tariff or project-owner arrangement. That obligation is not included in any Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, Cumulative Revenue Responsibility, or TRBAA Credit unless the costs are included in DesertLink’s Formula Rate and the specific share is expressly identified as DesertLink’s responsibility. Any applicable CAISO Tariff credit or project-owner credit shall be applied to prevent recovery of the same assigned share more than once.

PDF page 162

Schedule 5 - 1

Schedule 5
MTRC Calculation Template and Cumulative Revenue Ledger
This Schedule contains the project-specific calculation of each Estimated Annual MTRC and Final Annual MTRC and the Cumulative Revenue Ledger. DesertLink shall calculate each Annual MTRC solely under this Schedule. The Final Annual MTRC shall equal the applicable final incurred capital cost multiplied by the Project-Specific Levelized Fixed Charge Rate calculated in this Schedule. The calculation shall identify the applicable capital-cost input, present-worth tax-depreciation benefits, Formula Rate inputs, fixed expense allocator, applicable allocation percentage, Annual MTRC, Total Required Revenue Commitment, Remaining Cumulative Revenue Responsibility, and supporting inputs.

For purposes of calculating present-worth federal and state income-tax depreciation benefits, the Schedule applies a levelized-depreciation rate of five percent (5%) of the applicable capital cost input in each year of the twenty (20)-year MTRC Term. This levelized-depreciation schedule is not a separate annual charge. The Schedule is fixed on the Final MTRC Determination Date except to correct an error or fraud, to implement an effective prospective reassignment, to implement a final FERC order applicable to the calculation, to implement a Dispute Determination under Section 11.5, or to reflect, prospectively, a change in (i) DesertLink’s return on equity component of its Formula Rate, resulting from a final FERC order accepting or approving such change, or (ii) applicable federal or state tax rates or tax law enacted after the Final MTRC Determination Date; provided that, the five percent (5%) annual levelized- depreciation schedule shall remain fixed for the MTRC Term unless a final FERC order requires otherwise.

The following project-specific calculation and ledger shall be completed for each Covered Upgrade. DesertLink shall include an updated ledger statement in each Reconciliation Statement served on Eligible Customer under Sections 6.6 and 6.7; this Schedule does not impose a separate FERC filing requirement.

Annual Ledger Service. DesertLink shall update the Cumulative Revenue Ledger at least annually in connection with its Annual Update and shall include the resulting statement and the supporting workpapers in each Reconciliation Statement served on Eligible Customer. The statement is an agreement-administration record and is not required to be filed with FERC unless FERC otherwise requires. Any dispute concerning the statement shall be resolved under Article 11 of the Agreement.

PDF page 163

Schedule 5 - 2

Inputs and Security

PDF page 164

Schedule 5 - 3

Qualifying Revenue and Cumulative Revenue Ledger

PDF page 165

Schedule 5 - 4

Present Worth and Annualization Calculation

PDF page 166

Schedule 5 - 5

Expense and Capital Structure Inputs

PDF page 167

Schedule 5 - 6

Twenty-Year Depreciation Schedule

PDF page 168

i

Appendix VI  LARGE LOAD INTERCONNECTION PROCEDURES

PDF page 169

ii

TABLE OF CONTENTS

 Page No.
Section 1.  Objectives and Applicability … 1

1.1 Objectives……………………………………………………………….1

1.2 Applicability……………………………………………………………. 1

Section 2.
Definitions … 1

Section 3.
General Provisions Applicable to All Interconnection Requests … 6

3.1 Interconnection Requests … 6

3.2 Transmission Interconnection Service … 6

3.2.1
The Product … 6

3.2.2
No Applicability to Transmission Service … 7

3.2.3
Roles and Responsibilities … 7

3.3 Comparability … 7

3.4 Base Case Data … 8

3.5 Coordination with Affected Systems … 8

3.6  Capacity of the Large Load … 8

3.7  Proposed Service Commencement Date … 9

3.7.1
Interconnection Request … 9

3.7.2
After Start of the Large Load Interconnection Study … 9
3.8 Queue Position … 10 3.9 Withdrawal … 10

3.10 Withdrawal Penalty … 11 3.10.1  Calculation of the Withdrawal Penalty … 11 3.11 Standards for Co-located Inverter Based Generating Facilities … 12

Section 4. Large Load Study Process … 12

4.1 Timing for Submitting Interconnection Requests … 12

4.2 Processing of Interconnection Request … 12

4.2.1
Initiating an Interconnection Request … 13

4.2.1.1 Use of Interconnection Study Deposit … 13

4.3 Validation of Interconnection Request … 14

4.3.1
Acknowledgment of Interconnection Request … 14

4.3.2
Deficiencies in Interconnection Request … 14

4.4   Potential Deferral of the Interconnection Studies … 15 4.5 Scoping Meeting … 15

4.6 Interconnection Studies … 16

4.6.1
Large Load Interconnection Study … 17

4.6.1.1  Scope of the Large Load Interconnection Study … 17

4.6.1.2  Timing of the Large Load Interconnection Study Results .18

4.6.1.3   Large Load Interconnection Study Report Meeting … 19

4.6.1.4 Increase in the Commercial Readiness Deposit … 19
4.6.1.5  Restudy … 20 4.6.1.6  Modifications … 20

PDF page 170

iii

4.6.2     Optional Flexible Interim Load Interconnection (FILI) Study and
Agreement … 21 4.6.3     Additional Studies … 23

4.6.4     Financing of Participating TO’s Interconnection Facilities and Large
Load Network Upgrades … 24 4.7 Interconnection Financial Security … 24

4.7.1
Types of Interconnection Financial Security … 24

Section 5.
Large Load Interconnection Agreement … 25

5.1 Tender … 25 5.2   Negotiation … 25

5.3 Execution and Filing … 26 5.4   Commencement of Interconnection Activities … 27

Section 6.
Construction of Participating TO’s Interconnection Facilities

 and Large Load Network Upgrades … 27

6.1 Schedule … 27 6.2 Construction Sequencing … 27

6.2.1
General … 27

6.2.2
Advancing Construction of
Large Load Network Upgrades that are Part of an Expansion Plan of the
Participating TO … 27

6.3 Special Provisions for Affected Systems … 28

Section 7.
Miscellaneous … 28

7.1 Confidentiality … 28

7.1.1
Scope … 28

7.1.2
Release of Confidential Information … 29

7.1.3
Rights … 29

7.1.4
No Warranties … 29

7.1.5
Standard of Care … 30

7.1.6
Order of Disclosure … 30

7.1.7
Remedies … 30

7.1.8
Disclosure to FERC, its Staff, or a State … 30

7.2 Disputes … 31 7.2.1

Submission … 31

Attachment 1 – Interconnection Request Form

PDF page 171

1

 LARGE LOAD INTERCONNECTION PROCEDURES (LLIP)

Section 1.
Objectives and Applicability
1.1 Objectives

The objective of this LLIP is to implement requirements for Large Load interconnections to the Participating TO’s Transmission System pursuant to the TO Tariff.  For purposes of this LLIP, the “Participating TO” is DesertLink, LLC (“DesertLink”), and the “TO Tariff” is the DesertLink, LLC Transmission Owner Tariff.  Because DesertLink is a Non-Load-Serving Participating TO and has no End-Use Customers, a Large Load interconnecting under this LLIP will not be a retail transmission customer of the Participating TO.

1.2 Applicability

The LLIP is applicable to a Large Load Interconnection Customer that is either (1) proposing to interconnect a Large Load to the Participating TO’s Transmission System; (2) seeking to increase the capacity of an existing Large Load processed under the LLIP; or (3) with respect to an existing load interconnected to the Participating TO’s Transmission System that was not processed under the LLIP, seeking an increase of 50 MW or greater.  This LLIP only applies to completed Interconnection Requests submitted after the effective date of this Appendix VI to the TO Tariff.  Consistent with Section 10A of the TO Tariff, all requests for ECLL Interconnection shall be directed to the Participating TO.  An Interconnection Request submitted under this LLIP shall constitute the ECLL Interconnection Application, and the Interconnection Studies and the Large Load Interconnection Agreement under this LLIP shall constitute the study process and the ECLL Interconnection Agreement, respectively, for purposes of Section 10A of the TO Tariff.

Section 2.
Definitions

Terms used in this LLIP with initial capitalization shall have the meanings set forth below.  The singular of any definition shall include the plural and the plural shall include the singular.  If a term with initial capitalization used herein is not defined, such term shall have the meanings ascribed to such term in Section 3 of the TO Tariff.

Affected System shall mean an electric system other than the Participating TO’s Transmission System that may be affected by the proposed interconnection.

Affected System Operator shall mean the entity that owns or operates an Affected System, and includes an Affected System Owner as defined in any Cost Recovery Agreement.

Applicable Laws and Regulations shall mean all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any Governmental Authority.

PDF page 172

2

Base Case shall mean data including, but not limited to, base power flow, short circuit and stability data bases, underlying load, generation, and transmission facility assumptions, contingency lists, including relevant remedial action schemes, and transmission diagrams used to perform the Interconnection Studies.  The Base Case may include Critical Energy Infrastructure Information (as that term is defined by FERC).  The Base Case may include transmission facilities as approved by the Participating TO or ISO, as applicable, Reliability Network Upgrades that are included in a signed interconnection agreement, Large Load Network Upgrades, Large Loads and any co-located generation, and load forecast. The Base Case may also include generation facilities that (i) are directly interconnected to a Distribution System or the ISO Controlled Grid; (ii) are interconnected to Affected Systems and may have an impact on the Interconnection Request; (iii) have a pending request to interconnect to a Distribution System or an Affected System; or (iv) are not interconnected to a Distribution System or the ISO Controlled Grid, but are subject to the terms and conditions of a fully executed interconnection agreement (or its equivalent predecessor agreement) or for which an unexecuted interconnection agreement (or its equivalent predecessor agreement) has been requested to be filed with FERC.

Business Day shall mean Monday through Friday, excluding Federal Holidays.

Calendar Day shall mean any day including Saturday, Sunday or a Federal Holiday.

Commercial Readiness Deposit shall mean a deposit paid as set forth in LLIP Sections 4.2.1 and 4.6.1.4.

Confidential Information shall mean any confidential, proprietary or trade secret information of a plan, specification, pattern, procedure, design, device, list, concept, policy or compilation relating to the present or planned business of a Party, which is designated as confidential by the Party supplying the information, whether conveyed orally, electronically, in writing, through inspection, or otherwise.

Cost Recovery Agreement shall have the meaning set forth in Section 3 of the TO Tariff.

Dispute Resolution shall mean the applicable procedure for resolution of a dispute between the Parties as described in Section 14 of the TO Tariff, including, as applicable, the ISO ADR Procedures.

Flexible Interim Load Interconnection (FILI) Service shall have the meaning set forth in Section 3 of the TO Tariff.

FILI Study shall mean the study performed by the Participating TO pursuant to LLIP Section 4.6.2 to determine the availability of Interim Firm Interconnection Service and FILI Service.

Interconnection Financial Security shall mean any of the financial instruments listed in LLIP Section 4.7.1 provided by the Large Load Interconnection Customer to comply with its obligations under the LLIP or the Large Load Interconnection Agreement.

PDF page 173

3

Interconnection Request shall mean a request, in the form of Attachment 1 to Appendix VI to the TO Tariff, to interconnect a new Large Load, or to increase the capacity of, or make a Material Modification to the operating characteristics of, an existing Large Load that is interconnected with the Participating TO’s Transmission System.

Interconnection Study shall mean any of the following studies: the Large Load Interconnection Study, the FILI Study, restudies, and any additional studies performed pursuant to LLIP Section 4.6.3.

Interconnection Study Deposit shall mean the cash deposit provided to the Participating TO under LLIP Section 4.2.1 as a requirement of a valid Interconnection Request to be used to offset the cost of the Interconnection Studies.

Large Load Capacity shall mean the maximum capacity of the Large Load at the Point of Interconnection.

Large Load Customer shall mean the End-User that owns, operates, or proposes to develop the Large Load and receives, or will receive, retail transmission service from the Large Load Interconnection Customer, and shall be the Large Load Customer for purposes of the TO Tariff and any Cost Recovery Agreement.

Large Load Interconnection Agreement shall mean the interconnection agreement between the Participating TO and the Large Load Interconnection Customer, developed by the Participating TO consistent with the TO Tariff and the results of the Interconnection Studies and negotiated between the Parties pursuant to LLIP Section 5, which sets forth the terms and conditions governing the interconnection of the Large Load to the Participating TO’s Transmission System, including, without limitation, cost responsibility, payment provisions, cost recovery, and financial security for the Participating TO’s Interconnection Facilities and Large Load Network Upgrades, as it may be amended from time to time. The Large Load Interconnection Agreement shall constitute the ECLL Interconnection Agreement for purposes of the TO Tariff, as applicable, and shall be filed with FERC by the Participating TO to the extent required. For purposes of the TO Tariff, the Participating TO’s Interconnection Facilities and Large Load Network Upgrades identified in the Large Load Interconnection Agreement shall together constitute the ECLL Interconnection Facilities.

Large Load Interconnection Customer shall mean an Eligible Customer for Large Load (“ECLL”), as defined in Section 3 of the TO Tariff, that proposes to interconnect its facilities with the Participating TO’s Transmission System for the purpose of providing retail transmission service to a Large Load.

Large Load Interconnection Customer Interconnection Facilities shall mean all facilities and equipment owned, controlled, or operated by the Large Load Interconnection Customer or the Large Load Customer up to the Point of Change of Ownership as identified in the Large Load Interconnection Agreement, including any modifications, additions or upgrades to such facilities and equipment.

PDF page 174

4

Large Load Interconnection Procedures (LLIP) shall mean the interconnection procedures applicable to an Interconnection Request set forth in this Appendix VI to the TO Tariff.

Large Load Interconnection Study shall mean an engineering study conducted by the Participating TO for a Large Load Interconnection Customer under the LLIP that evaluates the impact of the proposed interconnection on the safety and reliability of Participating TO’s Transmission System and, if applicable, an Affected System. The Large Load Interconnection Study will also determine a list of facilities (including Participating TO’s Interconnection Facilities and Large Load Network Upgrades), the cost of those facilities, and the time required to interconnect the Large Load with the Participating TO’s Transmission System. The scope of the study is defined in LLIP Section 4.6.1.1.

Large Load Network Upgrades shall mean the additions, modifications, and upgrades to the ISO Controlled Grid at or beyond the Point of Interconnection necessary to serve one or more Large Loads safely and reliably that are identified through the Large Load Interconnection Study and submitted to the ISO for concurrence pursuant to Section 25.7 of the ISO Tariff. Large Load Network Upgrades do not include Participating TO’s Interconnection Facilities. To the extent a Large Load Network Upgrade is owned or to be constructed by the Participating TO and is identified in Schedule 1 to a Cost Recovery Agreement, such Large Load Network Upgrades shall constitute Large Load-Driven Upgrades, as defined in that Cost Recovery Agreement.

Large Load Study Process Agreement shall mean the agreement, developed and tendered by the Participating TO pursuant to LLIP Section 4.5, entered into by the Large Load Interconnection Customer and the Participating TO which sets forth the Parties’ agreement to perform Interconnection Studies under the LLIP.

Material Modification shall mean those modifications that have a material impact on the cost or timing of any Interconnection Request, or any other valid interconnection request to the Participating TO or the ISO, with an equal or later Queue Position date.

Participating TO’s Interconnection Facilities shall mean all facilities and equipment owned, controlled, or operated by the Participating TO from the Point of Change of Ownership to the Point of Interconnection as identified in the Large Load Interconnection Agreement, including any modifications, additions or upgrades to such facilities and equipment. Participating TO’s Interconnection Facilities are transmission facilities but are not controlled by the ISO.  Participating TO’s Interconnection Facilities are sole use facilities and shall not include Large Load Network Upgrades.

Participating TO’s Transmission System shall mean the facilities owned and operated by the Participating TO and that have been placed under the ISO’s Operational Control, which facilities form part of the ISO Controlled Grid.

Point of Change of Ownership shall mean the point, as set forth in the Large Load Interconnection Agreement, where the Large Load Interconnection Customer's interconnection facilities connect to the Participating TO’s Interconnection Facilities.

PDF page 175

5

Point of Interconnection shall mean the point, as set forth in the Large Load Interconnection Agreement, where the Participating TO’s Interconnection Facilities connect to the Participating TO’s Transmission System.  For purposes of the TO Tariff, the Point of Interconnection shall be the Point of Withdrawal for the Large Load.

Queue Position shall mean the order of a valid Interconnection Request, relative to all other pending valid Interconnection Requests, established pursuant to LLIP Section 3.8.

Reasonable Efforts shall mean, with respect to an action required to be attempted or taken by a Party under the LLIP or the Large Load Interconnection Agreement, efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.

Report Meeting shall mean the meeting among the Participating TO, the Large Load Interconnection Customer, and if applicable, the ISO and other Affected System Operators to discuss the results of the Interconnection Studies as set forth in the LLIP.

Scoping Meeting shall mean the meeting between representatives of the Large Load Interconnection Customer and Participating TO, and if applicable, the ISO, conducted for the purpose of discussing alternative interconnection options, to exchange information including any transmission data and earlier study evaluations that would be reasonably expected to impact such interconnection options, to analyze such information, and to determine the potential feasible Points of Interconnection.

Service Commencement Date shall mean the date the Large Load is initially operated in parallel with the Participating TO’s Transmission System and transmission interconnection service is provided to the Large Load Interconnection Customer pursuant to the terms of an executed Large Load Interconnection Agreement. For purposes of any Cost Recovery Agreement, the Service Commencement Date shall be the Large Load Service Commencement Date specified in Schedule 1 to that agreement.

Site Control shall have the meaning set forth in Section 3 of the TO Tariff.

System Protection Facilities shall mean the equipment, including necessary protection signal communications equipment, that protects (1) the Participating TO’s Transmission System, Participating TO’s Interconnection Facilities, ISO Controlled Grid, and Affected Systems from faults or other electrical disturbances occurring at the Large Load and (2) the Large Load from faults or other electrical system disturbances occurring on the ISO Controlled Grid, Participating TO’s Interconnection Facilities, and Affected Systems or on other delivery systems or other generating systems to which the ISO Controlled Grid is directly connected.

Transmission Interconnection Service shall mean the service provided by the Participating TO associated with interconnecting the Large Load to the Participating TO’s Transmission System and enabling the Large Load Interconnection Customer to receive electric energy at the Point of Interconnection, pursuant to the terms of the Large Load Interconnection Agreement and the TO Tariff.

PDF page 176

6

Withdrawal Penalty shall mean the penalty assessed by Participating TO to a Large Load Interconnection Customer that chooses to withdraw or is deemed withdrawn from Participating TO’s interconnection queue or whose Large Load does not otherwise reach its Service Commencement Date. The calculation of the Withdrawal Penalty is set forth in LLIP Section 3.10.1.

Section 3.
General Provisions Applicable to All Interconnection Requests

3.1
Interconnection Requests
A Large Load Interconnection Customer shall submit to Participating TO an Interconnection Request in the form of Attachment 1 to this LLIP for processing under the LLIP.  Consistent with Section 10A.2.1 of the TO Tariff, the Large Load Interconnection Customer shall send a copy of the Interconnection Request to the ISO, and the Interconnection Request and all supporting documentation shall be submitted electronically to the Participating TO in the manner posted on the Participating TO’s public website.

An Interconnection Request for the expansion of capacity of an existing Large Load shall be treated the same as an Interconnection Request for a new Large Load pursuant to this LLIP.

Co-located generation serving a Large Load that will not export to the ISO Controlled Grid shall be interconnected in accordance with the generator interconnection rules of the applicable ECLL, as approved by its Local Regulatory Authority (including, for a UDC subject to the jurisdiction of the CPUC, CPUC Electric Rule 21), consistent with Section 10A.5 of the TO Tariff; provided that, where such co-located generation is included in the Interconnection Request, the Participating TO will evaluate its incremental impacts on the Participating TO’s Transmission System as part of the LLIP study process. Co- located generation that will export to the ISO Controlled Grid is required to submit a generator interconnection request to the ISO in accordance with Section 25.7.6 of the ISO Tariff for evaluation of the proposed generator interconnection and the Large Load will be evaluated pursuant to the LLIP.  For a Large Load co- located with an exporting generating facility, the ISO will be a party to a pro forma agreement that bridges the generator’s Large Generator Interconnection Agreement with the Large Load Interconnection Agreement, or will negotiate a non-conforming Large Generator Interconnection Agreement, consistent with Section 10A.5 of the TO Tariff.

3.2
Transmission Interconnection Service

3.2.1 The Product.  Transmission Interconnection Service allows Large Load Interconnection Customer to connect the Large Load to the Participating TO’s Transmission System and be eligible to receive electric energy and capacity from the ISO Controlled Grid.

PDF page 177

7

3.2.2 No Applicability to Transmission Service.  Nothing in this LLIP shall constitute a request for transmission service or confer upon a Large Load Interconnection Customer any right to receive transmission service.

3.2.3 Roles and Responsibilities.

3.2.3.1 Each Interconnection Request will be subject to the direction and oversight of the Participating TO.  The Participating TO will conduct or cause to be performed the required Interconnection Studies and any additional studies the Participating TO determines to be reasonably necessary.  The analysis of impacts on, and upgrades required to, the Participating TO’s Transmission System will be performed by the Participating TO and will be subject to review and concurrence by the ISO.  The Participating TO will perform all required studies related to the Participating TO’s Transmission System and will coordinate with Affected System Operators in accordance with LLIP Section 3.5.

3.2.3.2 The Participating TO will complete or cause to be completed all studies as required within the timelines provided in this LLIP.

3.2.3.3 Each Large Load Interconnection Customer shall pay the actual costs of all Interconnection Studies, and any additional studies the Participating TO determines to be reasonably necessary in response to the Interconnection Request.  The Participating TO shall reimburse the ISO for the actual cost of any portion of the Interconnection Studies that the ISO performs related to the ISO Controlled Grid, as applicable.

3.2.3.3.1 The Participating TO shall issue invoices for Interconnection Studies that shall include a detailed and itemized accounting of the cost of each Interconnection Study.  Whenever the actual cost of performing the

Interconnection Studies exceeds the Interconnection
Study Deposit, the Large Load Interconnection Customer shall pay the undisputed difference in accordance with the Participating TO issued invoice within thirty (30)

Calendar Days.  The Participating TO shall not be
obligated to continue to have any studies conducted
unless the Large Load Interconnection Customer has paid all undisputed amounts in compliance herewith.

3.3
Comparability
Participating TO shall receive, process and analyze all Interconnection Requests in a timely manner as set forth in this LLIP.  Participating TO will use the same

PDF page 178

8

Reasonable Efforts in processing and analyzing Interconnection Requests from all Large Load Interconnection Customers, whether the Large Load is owned by Participating TO and its Affiliates or by a third party.

3.4
Base Case Data
Participating TO shall provide Base Case data to a Large Load Interconnection Customer upon request subject to confidentiality provisions in LLIP Section 7.1. Participating TO shall provide base power flow, short circuit databases, including all underlying assumptions, and contingency list used in the Large Load Interconnection Customer’s Interconnection Studies.  Participating TO is permitted to require that the Large Load Interconnection Customer sign a confidentiality agreement before the release of commercially sensitive information or Critical Energy Infrastructure Information in the Base Case data. Such Base Cases may include all (i) Large Loads, (ii) generation projects, and (iii) transmission projects, including merchant transmission projects that are proposed for the Participating TO’s Transmission System for which a transmission expansion plan has been submitted and approved by the applicable authority.

3.5
Coordination with Affected Systems
The Participating TO will notify the Affected System Operators that are potentially affected by a Large Load Interconnection Customer’s Interconnection Request.  The Participating TO will coordinate the conduct of any studies required to determine the impact of the Interconnection Request on Affected Systems with Affected System Operators and, if possible, include those results (if available) in its applicable Interconnection Study within the time frame specified in this LLIP.  Participating TO will include such Affected System Operators in all meetings held with Large Load Interconnection Customer as required by this LLIP.  Large Load Interconnection Customer will cooperate with Participating TO in all matters related to the conduct of studies and the determination of modifications to Affected Systems.  If an Affected System Operator, that has been informed its system is an Affected System refuses to cooperate with the Participating TO with whom interconnection has been requested in all matters related to the conduct of studies and the determination of whether modifications to its Affected System are necessary to avoid adverse impacts, it waives any right in any fora that the Participating TO’s provision of service has adversely impacted such Affected System Operator.

3.6
Capacity of the Large Load

The Interconnection Request shall be evaluated using the maximum capacity requested by the Large Load Interconnection Customer.  However, if the maximum capacity that the Large Load is capable of receiving is greater than the maximum capacity requested by the Large Load Interconnection Customer, the Large Load Interconnection Customer will be required to limit the Large Load capacity to no greater than the amount requested (e.g., through use of a control

PDF page 179

9

system, power relay(s), or other similar device settings or adjustments), and the Large Load Interconnection Customer must obtain the Participating TO’s agreement, with such agreement not to be unreasonably withheld, that the manner in which the Large Load Interconnection Customer proposes to implement such a limit will not adversely affect the safety and reliability of the Participating TO’s Transmission System.  If the Participating TO does not so agree, then the Interconnection Request must be withdrawn or revised to specify the maximum capacity that the Large Load is capable of receiving.    Furthermore, nothing in this section shall prevent a Participating TO from considering a capacity higher than the limited capacity, if appropriate, when evaluating system protection impacts.

3.7
Proposed Service Commencement Date
The  proposed Service Commencement Date of the new Large Load or increase in capacity of the existing Large Load shall not exceed seven years from the date the Interconnection Request is received by Participating TO for those Interconnection Requests studied in accordance with the Large Load Interconnection Procedures, unless Large Load Interconnection Customer demonstrates and the Participating TO agrees, such agreement not to be unreasonably withheld, that engineering, permitting and construction of the new Large Load or increase in capacity of the existing Large Load will take longer than the seven-year period.

3.7.1 Interconnection Request.  If the proposed Service Commencement Date in the Interconnection Request is more than seven years from the date the Interconnection Request is received by the Participating TO, the Large Load Interconnection Customer must demonstrate, subject to the Participating TO’s agreement, such agreement not to be unreasonably withheld, that the required engineering, permitting and construction of the Large Load will take longer than the seven-year period.

3.7.2 After Start of the Large Load Interconnection Study.  Any request to extend the Service Commencement Date after commencement of the Large Load Interconnection Study under the LLIP, or following execution of a Large Load Interconnection Agreement, shall be subject to the following:

(i) Requested extension does not exceed seven years from Service Commencement Date in the original Interconnection Request.  A request to extend the Service Commencement Date that does not exceed seven years from the Service Commencement Date in the original

Interconnection Request is subject to the modification assessment process specified in LLIP Section 4.6.1.6.1.

(ii) Requested extension exceeds seven years from Service Commencement Date in the original Interconnection Request.  A request to extend the Service Commencement Date that exceeds seven years from the Service Commencement Date in the original Interconnection Request shall (a) demonstrate, subject to the Participating TO’s agreement, such agreement

PDF page 180

10

not to be unreasonably withheld, that engineering, permitting and construction of the new Large Load or increase in capacity of the existing Large Load will take longer than the seven-year period, and (b) be subject to the modification assessment process specified in LLIP Section 4.6.1.6.1.

Any extension of the Service Commencement Date under this LLIP Section 3.7.2 shall not extend the Outside Date under any applicable Cost Recovery Agreement unless the parties to that agreement agree in writing to such extension.

3.8   Queue Position

           3.8.1 Assignment of Queue Position.
Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1.

3.8.2 Higher Queue Position.
A higher Queue Position assigned to an Interconnection Request is one that has been placed “earlier” in the queue in relation to another Interconnection Request that is assigned a lower Queue Position.

3.9
Withdrawal
Large Load Interconnection Customer may withdraw its Interconnection Request at any time by written notice of such withdrawal to Participating TO, and the Participating TO will notify the ISO and Affected System Operators, if any, within three (3) Business Days of receipt of such a notice.  In addition, after confirmation by the Participating TO of a valid Interconnection Request, if the Large Load Interconnection Customer fails to adhere to all requirements of this LLIP, except as provided in LLIP Section 7.2 (Disputes), Participating TO shall deem the Interconnection Request to be withdrawn and shall provide written notice to Large Load Interconnection Customer of the deemed withdrawal within five (5) Business Days and an explanation of the reasons for such deemed withdrawal.  Upon receipt of such written notice, Large Load Interconnection Customer shall have five (5) Business Days in which to either (i) respond with information or action that cures the deficiency, or (ii) support its position that the deemed withdrawal was erroneous and notify the Participating TO of its intent to pursue Dispute Resolution.

For an Interconnection Request under the LLIP, withdrawal shall result in the removal of the Interconnection Request from the Interconnection Studies.  If a Large Load Interconnection Customer disputes the withdrawal and removal from the Interconnection Studies and has elected to pursue Dispute Resolution, Large Load Interconnection Customer's Interconnection Request will not be considered in any ongoing Interconnection Study during the Dispute Resolution process.

PDF page 181

11

In the event of such withdrawal, Participating TO, subject to the provisions in LLIP Section 7.1, as applicable, shall provide, at Large Load Interconnection Customer's request, all information that Participating TO developed for any completed study conducted up to the date of withdrawal of the Interconnection Request.

3.10
Withdrawal Penalty

A Large Load Interconnection Customer with an Interconnection Request being processed under the LLIP will be subject to a Withdrawal Penalty if it withdraws its Interconnection Request or is deemed withdrawn, or the Large Load does not otherwise achieve its Service Commencement Date, which date may be modified if the necessary Participating TO-owned facilities cannot be constructed on a timeline that meets such date, unless: (1) the withdrawal does not have a material impact on the cost or timing of any equal or later queued interconnection request;

(2) Large Load Interconnection Customer withdraws after receiving Large Load Interconnection Customer’s most recent Interconnection Study report and the Large Load Network Upgrade costs assigned to the Interconnection Request identified in that report have increased by more than twenty-five percent (25%) compared to costs identified in Large Load Interconnection Customer’s preceding Interconnection Study report; or (3) Large Load Interconnection Customer withdraws after receiving an Interconnection Study report issued after completion of the initial Large Load Interconnection Study and the Large Load Network Upgrade costs assigned to the Interconnection Request identified in such Interconnection Study report have increased by more than one hundred percent (100%) compared to costs identified in the initial Large Load Interconnection Study report.

3.10.1 Calculation of the Withdrawal Penalty

If the Large Load Interconnection Customer withdraws its Interconnection Request or is deemed withdrawn prior to the commencement of the Large Load Interconnection Study, Large Load Interconnection Customer will not be subject to a Withdrawal Penalty.  If Large Load Interconnection Customer withdraws, is deemed withdrawn, or otherwise does not achieve its Service Commencement Date at any point after the commencement of the Large Load Interconnection Study, that Large Load Interconnection Customer’s Withdrawal Penalty will be the greater of: (1) the Large Load Interconnection Customer’s Interconnection Study Deposit required under LLIP Section 4.2.1; or (2) as follows in (a)–(c):

(a) If Large Load Interconnection Customer withdraws or is deemed withdrawn during the Large Load Interconnection Study or after receipt of a Large Load Interconnection Study report, Large Load Interconnection Customer will be charged two (2) times the actual cost

PDF page 182

12

of the Large Load Interconnection Study performed for the Large Load Interconnection Customer.

(b) If Large Load Interconnection Customer withdraws or is deemed withdrawn after receipt of the draft Large Load Interconnection Agreement but before Large Load Interconnection Customer has executed a Large Load Interconnection Agreement or has requested that its Large Load Interconnection Agreement be filed unexecuted, Large Load Interconnection Customer will be charged ten percent (10%) of its estimated Large Load Network Upgrade costs as reflected in the most recently completed Interconnection Study.

(c) If Large Load Interconnection Customer has executed a Large Load Interconnection Agreement or has requested that its Large Load Interconnection Agreement be filed unexecuted and subsequently withdraws its Interconnection Request, the Large Load Interconnection Customer’s Withdrawal Penalty will be calculated as set forth in the Large Load Interconnection Agreement.

The Commercial Readiness Deposit shall be retained as financial security for the Withdrawal Penalty (if applicable) and, other than as set forth in the Large Load Interconnection Agreement, any security not applied to the Withdrawal Penalty will be released to the Large Load Interconnection Customer following withdrawal or the Service Commencement Date. Where a Cost Recovery Agreement applies, (i) any Commercial Readiness Deposit or Interconnection Financial Security provided for the same costs shall count toward, and shall not be duplicated by, the Construction Security required under the Cost Recovery Agreement, and (ii) any Withdrawal Penalty paid with respect to a Large Load Network Upgrade shall be credited against the Pre-In-Service Termination Costs payable under the Cost Recovery Agreement for that upgrade, so that the Participating TO does not recover the same costs more than once.

3.11
Standards for Co-located Inverter Based Generating Facilities

Inverters used for the production, and/or later injection from storage, of electricity shall meet the inverter certification standards of UL-1741 and UL-1741 Supplement B.

Section 4.  Large Load Study Process

4.1
Timing For Submitting Interconnection Requests
A Large Load Interconnection Customer may submit an Interconnection Request for processing under the LLIP at any time during the year. The Participating TO, in coordination with the ISO, as applicable, will study the Interconnection Request.

4.2
Processing of Interconnection Request

PDF page 183

13

4.2.1
Initiating an Interconnection Request.  To initiate an
Interconnection Request under the LLIP, Large Load Interconnection Customer must submit all of the following: (i) an Interconnection Study Deposit of $250,000; (ii) a completed Interconnection Request in the form of Attachment 1 to the LLIP, including preferred Point of Interconnection and voltage level, all information required by Section 10A.2.1 of the TO Tariff (other than any election of interim service, which shall be made in accordance with LLIP Section 4.6.2), and all other technical data; (iii) a Commercial Readiness Deposit equal to two times the Interconnection Study Deposit described in this LLIP Section 4.2.1 in the form of an irrevocable letter of credit, cash, a surety bond, or other form of security that is reasonably acceptable to Participating TO, in accordance with LLIP Section 4.7.1. This Commercial Readiness Deposit is refunded to Large Load Interconnection Customer according to LLIP Section 3.10.1; however, the Participating TO shall be entitled to hold the Commercial Readiness Deposit until the Large Load Interconnection Customer’s Large Load achieves its Service Commencement Date; and (iv) demonstration of Site Control.

4.2.1.1 Use of Interconnection Study Deposit.  The Interconnection Study Deposit shall be applied to pay for prudent costs incurred by the Participating TO, the ISO, or third parties at the direction of the Participating TO or ISO, as applicable, to perform and administer the Interconnection Studies.

In the event a Large Load Interconnection Customer withdraws its Interconnection Request prior to the commencement of the Large Load Interconnection Study, Large Load Interconnection Customer must pay Participating TO the actual costs of processing its Interconnection Request. In the event a Large Load

Interconnection Customer withdraws after commencement of the Large Load Interconnection Study, Participating TO shall charge and Large Load Interconnection Customer shall pay the actual costs of the Interconnection Studies.

Any difference between the Interconnection Study Deposit and the actual cost of the Interconnection Studies shall be paid by or refunded to the Large Load Interconnection Customer. Any

invoices for Interconnection Studies shall include a detailed and itemized accounting of the cost of each Interconnection Study. Large Load Interconnection Customers shall pay any such

undisputed costs within thirty (30) Calendar Days of receipt of an invoice. If Large Load Interconnection Customer fails to pay such undisputed costs within the time allotted, its Interconnection Request shall be deemed withdrawn and will be subject to a Withdrawal Penalty pursuant to LLIP Section 3.10.1.

PDF page 184

14

The Participating TO will reimburse the ISO or third parties, as applicable, for all work performed on behalf of the withdrawn Interconnection Request at the Participating TO’s direction. The Large Load Interconnection Customer must pay all monies due before it is allowed to obtain any Interconnection Study data or results.

4.3
Validation of Interconnection Request

4.3.1 Acknowledgment of Interconnection Request.  Participating TO shall notify the Large Load Interconnection Customer within ten (10) Business Days of receipt of the Interconnection Request, which notice shall state whether the Interconnection Request is deemed valid.

4.3.2 Deficiencies in Interconnection Request.  An Interconnection Request will not be considered to be a valid request until all items in LLIP Section 4.2.1 have been received by Participating TO and deemed valid by the Participating TO.  If an Interconnection Request fails to meet the requirements set forth in LLIP Section 4.2.1, Participating TO shall include in its notification to the Large Load Interconnection Customer under LLIP Section 4.3.1 the reasons for such failure and that the Interconnection Request does not constitute a valid request.  Consistent with Section 10A.2.3 of the TO Tariff, the Participating TO will attempt to remedy deficiencies in the Interconnection Request through informal communications with the Large Load Interconnection Customer, and the Large Load Interconnection Customer shall provide Participating TO the additional requested information needed to constitute a valid request. Whenever the additional requested information is provided by the Large Load Interconnection Customer, the Participating TO shall notify the Large Load Interconnection Customer within five (5) Business Days of receipt of the additional requested information whether the Interconnection Request is valid.  If the Interconnection Request continues to fail to meet the requirements set forth in LLIP Section 4.2.1, the Participating TO shall include in its notification to the Large Load Interconnection Customer the reasons for such failure.  If an Interconnection Request has not been deemed valid, the Large Load Interconnection Customer must submit all information necessary to meet the requirements of LLIP Section 4.2.1 no later than twenty (20) Business Days after the date the original Interconnection Request was submitted, or ten (10) Business Days after the Participating TO first provided notice that the Interconnection Request was not valid, whichever is later. Interconnection Requests that have not met the requirements of LLIP Section 4.2.1 within twenty (20) Business Days after the date the original Interconnection Request was submitted or ten (10) Business Days after the Participating TO first provided notice that the Interconnection Request

PDF page 185

15

was not valid, whichever is later, will be deemed invalid, will be returned to the Large Load Interconnection Customer in accordance with Section 10A.2.3 of the TO Tariff, and will not be included in the LLIP.

Interconnection Requests deemed invalid under this LLIP Section 4.3.2 are not subject to LLIP Section 3.9.  Large Load Interconnection Customers with invalid Interconnection Requests under this LLIP Section 4.3.2 may seek relief under LLIP Section 7.2 by so notifying the Participating TO within two (2) Business Days of the notice of invalidity.

4.4     Potential Deferral of the Interconnection Studies

           The Participating TO may defer commencement of the Large Load
Interconnection Study when it determines, using Good Utility Practice and reasonable engineering judgment, that the Interconnection Request cannot be studied meaningfully until other pending study results for higher-queued projects are available.

           Within ten (10) Business Days after deeming an Interconnection Request valid under LLIP Section 4.3.1, the Participating TO will notify the Large Load Interconnection Customer in writing if it is deferring the start of the Interconnection Studies. The notice will include: (i) information regarding the pending studies; and (ii) the estimated start date of the Large Load Interconnection Study.  During the period of deferral, the Participating TO will provide a monthly status update to the Large Load Interconnection Customer.

4.5
Scoping Meeting
Within fifteen (15) Business Days after the Participating TO notifies the Large Load Interconnection Customer that the Interconnection Request has been deemed valid as set forth in LLIP Section 4.3.2, the Participating TO shall establish a date agreeable to the Large Load Interconnection Customer, and the ISO, if applicable, for the Scoping Meeting.

The purpose of the Scoping Meeting shall be to discuss reasonable Service Commencement Dates and alternative interconnection options, to exchange information including any transmission data that would reasonably be expected to impact such interconnection options, to analyze such information and to determine the potential feasible Points of Interconnection and eliminate alternatives given resources and available information. The Scoping Meeting shall also include discussion of a deferral of the Interconnection Studies in accordance with LLIP Section 4.4.

The Participating TO will bring to the meeting, as reasonably necessary to accomplish its purpose, such already available technical data, including, but not limited to, (i) general facility loadings, (ii) general instability issues, (iii) general short circuit issues, (iv) general voltage issues, and (v) general reliability issues.

PDF page 186

16

The Large Load Interconnection Customer will bring to the Scoping Meeting, in addition to the technical data form (Appendix A to Attachment 1) submitted with its Interconnection Request, any system studies previously performed.  The Participating TO, the ISO, if applicable, and the Large Load Interconnection Customer will also bring to the meeting personnel and other resources as may be reasonably required to accomplish the purpose of the meeting in the time allocated for the meeting.  On the basis of the meeting, the Large Load Interconnection Customer shall designate its Point of Interconnection.  The duration of the meeting shall be sufficient to accomplish its purpose.

Within five (5) Business Days after the Scoping Meeting, the Participating TO shall tender to the Large Load Interconnection Customer a Large Load Study Process Agreement developed by the Participating TO consistent with the TO Tariff and this LLIP, which shall contain an outline of the scope of the Large Load Interconnection Study, contain a non-binding good faith estimate of the cost to perform such study, and shall specify that the Large Load Interconnection Customer is responsible for the actual cost of the Interconnection Studies, including reasonable administrative costs.  No later than thirty (30) Calendar Days after the Scoping Meeting, the Large Load Interconnection Customer shall either execute and deliver to the Participating TO  the Large Load Study Process Agreement or request that the Participating TO file it unexecuted with FERC, or the Interconnection Request shall be deemed withdrawn.  If an unexecuted filing is requested, the Interconnection Studies will be paused until the Large Load Study Process Agreement is made effective by FERC.

4.6
Interconnection Studies
The Interconnection Studies shall consist of a Large Load Interconnection Study, any FILI Study requested pursuant to LLIP Section 4.6.2, and any additional studies, including but not limited to those identified in LLIP Section 4.6.3 required for interconnection of the Large Load, and co-located generation not exporting to the ISO Controlled Grid, to the Participating TO’s Transmission System.    The analysis of impacts on, and upgrades required to, the Participating TO’s Transmission System will be performed by the Participating TO and will be subject to the review and concurrence of the ISO in accordance with Section 25.7 of the ISO Tariff. The Interconnection Studies will identify Participating TO’s Interconnection Facilities and required Large Load Network Upgrades necessary to mitigate thermal overloads and voltage violations, and address short circuit, stability, and reliability issues associated with the requested Transmission Interconnection Service.

All cost estimates for Participating TO’s Interconnection Facilities and Large Load Network Upgrades, as applicable, contained in the Interconnection Studies will be set forth in the Interconnection Study report in present dollar costs as well as time-adjusted dollar costs, adjusted to the estimated year of construction of the components being constructed.

PDF page 187

17

The Participating TO will prepare an Interconnection Study report to document the results of the Interconnection Studies.

4.6.1 Large Load Interconnection Study.

4.6.1.1  Scope of the Large Load Interconnection Study.  The Large Load Interconnection Study will consist of a  short circuit analysis, a power flow analysis, an electromagnetic transient (“EMT”) screening, a non-binding good faith estimate of the scope and cost of the Participating TO’s Interconnection Facilities and Large Load Network Upgrades, and any other studies that are deemed necessary. The Large Load Interconnection Study will also identify the need for any additional studies (e.g., stability analysis, EMT study, etc.) to be performed as part of the scope of work set forth in the Large Load Interconnection Agreement pursuant to LLIP Section 4.6.3.  When there is co-located generation not exporting to the ISO Controlled Grid and not subject to electrical short circuit duty dependence, the Large Load Interconnection Study will identify the impacts associated with the Large Load and any incremental impacts of the co-located generation.

The Large Load Interconnection Study will consider the use of alternative transmission technologies including dynamic line ratings, advanced power flow control devices, advanced conductors, and transmission switching, when evaluating transmission solutions to accommodate new Large Loads and their associated transmission system impacts.  If traditional network upgrades are selected instead of alternative transmission technologies, the Participating TO will provide a demonstration of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline for accommodating the interconnection of the Large Load.

The Large Load Interconnection Study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested Transmission Interconnection Service, including an estimate of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the Interconnection.

The Large Load Interconnection Study shall provide a list of Participating TO’s Interconnection Facilities and Large Load Network Upgrades, as applicable, that are required as a result of the Interconnection Request.

PDF page 188

18

4.6.1.2 Timing of the Large Load Interconnection Study Results.  The Participating TO shall use Reasonable Efforts to complete the Large Load Interconnection Study within ninety (90) Calendar Days after the execution of a Large Load Study Process Agreement or, if the Large Load Study Process Agreement is filed unexecuted, after it is made effective by FERC.  The Participating TO will issue a Large Load Interconnection Study report to the Large Load Interconnection Customer. The Participating TO will share study results with the ISO for review and concurrence.

At any time the Participating TO determines that it will not meet the required time frame for completing the Large Load Interconnection  Study, Participating TO shall notify the Large Load Interconnection Customer as to the schedule status of the Large Load Interconnection Study and provide an estimated completion date with an explanation of the reasons why additional time is required.

Upon request, the Participating TO shall provide the Large Load Interconnection Customer all supporting documentation, workpapers and relevant pre-Interconnection Request and post- Interconnection Request power flow and short circuit databases for the Large Load Interconnection Study, subject to confidentiality arrangements consistent with LLIP Section 7.1.

Should the Large Load Interconnection Customer provide written comments on the Large Load Interconnection Study report at least five (5) Business Days before the Report Meeting conducted to discuss the report, the Participating TO will address the written comments in the Large Load Interconnection Study Report Meeting.  Should the Large Load Interconnection Customer provide comments at any later time (up to the time of the Report Meeting), then such comments shall be considered informal inquiries to which the Participating TO will provide informal, informational responses at the Report Meeting, to the extent possible.

The Large Load Interconnection Customer may submit, in writing, additional comments on the final Large Load Interconnection Study report up to three (3) Business Days following the Report Meeting.  Based on any discussion at the Report Meeting and any comments received from the Large Load Interconnection Customer or the ISO, the Participating TO will determine whether it is necessary to follow the Large Load Interconnection Study report with a revised study report.  The Participating TO will issue any such revised report to the Large Load Interconnection Customer no later than fifteen (15) Business Days following the Report

PDF page 189

19

Meeting. If the ISO has not completed its review of the Large Load Interconnection Study report, the Participating TO shall delay its determination of whether a revised study report is required until that review is complete.

4.6.1.3 Large Load Interconnection Study Report Meeting.  A Report Meeting shall be held among the Participating TO, the ISO, if applicable, and the Large Load Interconnection Customer to discuss the results of the Large Load Interconnection Study, including assigned cost responsibility.  Any such Report Meeting will be held within ten (10) Business Days of the date the Large Load Interconnection Study report is provided to the Large Load Interconnection Customer.

4.6.1.4 Commercial Readiness Deposit.  Within thirty (30) Calendar Days after receiving the final Large Load Interconnection Study report, the Large Load Interconnection Customer shall provide an additional Commercial Readiness Deposit sufficient to bring the aggregate Commercial Readiness Deposit to twenty percent (20%) of the Participating TO’s then-current estimated construction cost of the Large Load Network Upgrades identified in that report that are attributable to the Interconnection Request.  If the final Large Load Interconnection Study report is revised following ISO review, the required Commercial Readiness Deposit shall be adjusted to reflect twenty percent (20%) of the corresponding estimated construction cost identified in the revised final report, and any required increase shall be provided within thirty (30) Calendar Days after issuance of that report.

The Commercial Readiness Deposit secures the Withdrawal Penalty and other pre-in-service obligations under this LLIP and the Large Load Interconnection Agreement. It does not establish a direct assignment of the Large Load Network Upgrade costs, constitute a payment toward an Annual MTRC, reduce the Total Required Revenue Commitment, or satisfy Operational Security under a Cost Recovery Agreement.

To the extent a Commercial Readiness Deposit is in a form permitted under Schedule 3 of an applicable Cost Recovery Agreement, DesertLink may elect in writing to credit it dollar-for- dollar toward required Construction Security under that agreement. No amount of Commercial Readiness Deposit may be applied or

PDF page 190

20

credited more than once. Any portion not so credited shall be administered and released under Sections 3.9 and 3.10 of this LLIP and the Large Load Interconnection Agreement.

4.6.1.5 Restudy. If restudy of the Large Load Interconnection Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to LLIP Section 4.6.1.6, Participating TO shall notify Large Load Interconnection Customer in writing. Such restudy shall take no longer than forty-five (45) Calendar Days from the date of notice. Any cost of restudy shall be borne by the Large Load Interconnection Customer.

4.6.1.6 Modifications.  At any time during the course of the Interconnection Studies, the Large Load Interconnection Customer, the Participating TO, or the ISO, as applicable, may identify changes to the planned interconnection that may improve the costs and benefits (including reliability) of the interconnection, and the ability of the proposed change to accommodate the Interconnection Request.  To the extent the identified changes are acceptable to the Participating TO, the ISO, as applicable, and Large Load Interconnection Customer, such acceptance not to be unreasonably withheld, Participating TO shall modify the configuration in accordance with such changes without altering the Interconnection Request’s eligibility for participating in Interconnection Studies.

4.6.1.6.1 For any modifications other than those agreed upon under LLIP Section 4.6.1.6, the Large Load Interconnection Customer must first request that Participating TO evaluate whether such modification is a Material Modification.  In response to Large Load Interconnection Customer's

request, Participating TO, in coordination with the ISO, if applicable, shall evaluate the proposed modifications prior to making them and inform Large Load Interconnection Customer in writing of whether the modifications would constitute a Material Modification.  The Participating TO may, at its option, engage the services of the ISO to assist in the assessment of the modification.  Any change to the Point of Interconnection shall constitute a Material Modification.

The Large Load Interconnection Customer shall provide the Participating TO a $30,000 deposit for the modification assessment at the time the request is submitted.  Except as provided below, any modification assessment will be

concluded, and a response provided to the Large Load Interconnection Customer in writing, within forty-five (45)

PDF page 191

21

Calendar Days from the date the Participating TO receives all of the following: 1) the Large Load Interconnection Customer’s written notice to modify the project; 2) a narrative description of the requested modification; 3) technical data required to assess the request, including an updated technical data form (Appendix A to Attachment 1 to this LLIP), if requested by the Participating TO; 4) any additional information requested by Participating TO; and

5) payment of the $30,000 deposit.  If applicable, the Participating TO shall coordinate the modification request with the ISO.  If the modification assessment cannot be completed within that time period, the Participating TO shall notify the Large Load Interconnection Customer and provide an estimated completion date with an explanation of the reasons why additional time is required.  The Large Load Interconnection Customer will be responsible for the actual costs incurred by the Participating TO and, if applicable, the ISO in conducting the modification assessment.  If the actual costs of the modification assessment are less than the deposit provided by the Large Load Interconnection Customer, the Large Load

Interconnection Customer will be refunded the balance within thirty (30) Calendar Days of being invoiced.  If the actual costs of the modification assessment are greater than the deposit provided by the Large Load Interconnection Customer, the Large Load Interconnection Customer shall pay the balance within thirty (30) Calendar Days of being invoiced.

If the proposed modification is determined to be a Material Modification by the Participating TO pursuant to the modification assessment described above, the Large Load Interconnection Customer shall then either:

(i) withdraw the proposed modification, or

(ii) withdraw the proposed modification and submit a new Interconnection Request reflecting such

modification.

4.6.2   Optional Flexible Interim Load Interconnection (FILI) Study and Agreement. If the Large Load Interconnection Study finds that the full amount of the Interconnection Request cannot be accommodated prior to the time that all ECLL Interconnection Facilities are in service, the Large Load Interconnection Customer may request a FILI Study, by written notice to the Participating TO within thirty (30) Calendar Days after receipt of the final Large Load Interconnection Study report, to

PDF page 192

22

determine, consistent with Section 10A.4 of the TO Tariff, whether Interim Firm Interconnection Service and/or FILI Service may be provided.  A Large Load Interconnection Customer may elect to be studied only for Interim Firm Interconnection Service and not FILI Service.  If the Large Load Interconnection Customer elects to proceed with a FILI Study, the Participating TO shall use Reasonable Efforts to complete the FILI Study within sixty (60) Calendar Days after receipt of such request. Large Load Interconnection Customer will be responsible for the actual costs of the FILI Study. The Participating TO will perform the FILI Study. At any time the Participating TO determines that it will not meet the required time frame for completing the FILI Study, Participating TO shall notify the Large Load Interconnection Customer as to the schedule status of the FILI Study and provide an estimated completion date with an explanation of the reasons why additional time is required.

 The FILI Study will determine (i) the maximum amount of Interim Firm Interconnection Service, if any, that can be provided prior to completion of the Participating TO’s Interconnection Facilities and Large Load Network Upgrades; (ii) whether the Large Load Interconnection Customer is eligible to receive FILI Service and the maximum amount of such service; (iii) the conditions and limitations of such service; (iv) the upgrades and the associated cost; and (v) the estimated duration required to provide the interim service. The Participating TO will share study results with the ISO for review and concurrence.  The Participating TO shall update its analysis of the availability of FILI Service at least annually under the terms of the FILI Service Agreement, and the actual amount of FILI Service available during any operating period shall be determined by the Participating TO through operational assessments conducted closer to real-time operating conditions, consistent with Section 10A.4 of the TO Tariff.  If requested by the Large Load Interconnection Customer within ten (10) Business Days of the date of the issuance of the FILI Study report, a Report Meeting shall be scheduled among the Participating TO, the ISO, and the Large Load Interconnection Customer.

The Large Load Interconnection Customer should note the following considerations:

a) Temporary limits may be adjusted if unforeseen conditions arise.
b) Advance notice of non-firm load curtailment may not be possible.
c) Non-firm load may be curtailed during planned or repair outages, which may last longer than 6 months.

d) ISO may have additional operational requirements.
e) Participating TO is not obligated to provide flexibility beyond what it can, in its sole judgment, manage operationally.

PDF page 193

23

f) Participating TO’s Interconnection Facilities costs for interim interconnection service will be directly assigned to the Large Load Interconnection Customer.

g) Large Load Interconnection Customers not adhering to the contractual agreement and conditions may be curtailed indefinitely.

4.6.2.1 FILI Service Agreement. If the Large Load Interconnection Customer has elected FILI Service, as reflected in the Large Load Interconnection Agreement, the Large Load Interconnection

Customer shall ensure that, prior to the Service Commencement Date, the Large Load Customer executes, or requests to be filed unexecuted with FERC, a FILI Service Agreement with the

Participating TO and, as applicable, the ISO, developed by the Participating TO consistent with Section 10A.4 of the TO Tariff and in accordance with ISO Tariff Section 25.7.2. The FILI Service Agreement shall describe the circumstances in which the ISO or Participating TO may temporarily curtail the Large Load receiving FILI Service, and the mechanism the ISO or

Participating TO will use to perform the curtailment. The ISO will post such FILI Service Agreements on the ISO Website.

4.6.3   Additional Studies. The Participating TO may identify the need for additional studies to comply with Applicable Reliability Standards. These additional studies may include, but are not limited to, the following: stability analysis, variable load impact analysis, and EMT analysis.  The associated new scope will be identified in the Large Load Interconnection Study pursuant to LLIP Section 4.6.1.1. The additional studies will be performed by the Participating TO as part of the scope of work set forth in the Large Load Interconnection Agreement. The additional studies may result in the identification of additional facilities scope and cost, and may require a revision to the schedule set forth in the Large Load Interconnection Agreement. The Large Load Interconnection Customer will be responsible for providing the necessary technical information and/or models requested by the Participating TO to conduct the additional studies. The Large Load Interconnection Customer will be responsible for the costs of such studies.

If an additional study results in the need to revise the scope of work of the Large Load Network Upgrades identified in the Large Load

Interconnection Study and the updated assigned costs have increased by more than twenty-five percent (25%) compared to costs identified in the Large Load Interconnection Study report, the Large Load Interconnection Customer shall not be subject to a Withdrawal Penalty under LLIP Section 3.10.1 if the Interconnection Request is withdrawn within thirty (30) Calendar Days of receipt of the additional study report.  If the Large Load Interconnection Customer elects to continue with its Interconnection Request, the Large Load Interconnection Agreement will be amended to

PDF page 194

24

reflect the results of the additional study.

4.6.4   Financing of Participating TO’s Interconnection Facilities and Large Load Network Upgrades.  The responsibility to finance Participating TO’s Interconnection Facilities shall be assigned solely to the Large Load Interconnection Customer. The Participating TO will be responsible for financing Large Load Network Upgrades in accordance with the Large Load Interconnection Agreement and, as to any Large Load Network Upgrades that constitute Large Load-Driven Upgrades, the Cost Recovery Agreement required under LLIP Section 5.3.

4.7
Interconnection Financial Security

4.7.1 Types of Interconnection Financial Security.  The Interconnection Financial Security posted by a Large Load Interconnection Customer may be any combination of the following types of Interconnection Financial Security provided in favor of the Participating TO:

(a) an irrevocable and unconditional letter of credit issued by a bank or financial institution that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s;

(b) an irrevocable and unconditional surety bond issued by an insurance company that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s;

(c) an unconditional and irrevocable guaranty issued by a company that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s;

(d) a cash deposit standing to the credit of the Participating TO and in an interest-bearing escrow account maintained at a bank or financial institution that is reasonably acceptable to the Participating TO;

(e) a certificate of deposit in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s; or

(f) a payment bond certificate in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s.

Interconnection Financial Security instruments as listed above shall be in such form as the Participating TO may reasonably require from time to time by notice to Large Load Interconnection Customers, or in such other

PDF page 195

25

form as has been evaluated and approved as reasonably acceptable by the Participating TO.

The Participating TO shall require the use of standardized forms of Interconnection Financial Security to the greatest extent possible.  If at any time the guarantor of the Interconnection Financial Security fails to maintain the credit rating required by this LLIP Section 4.7.1, the Large Load Interconnection Customer shall provide to the Participating TO replacement Interconnection Financial Security meeting the requirements of this LLIP Section 4.7.1 within five (5) Business Days of the change in credit rating.

Interest on a cash deposit standing to the credit of the Participating TO in an interest-bearing escrow account under subpart (d) of this LLIP Section 4.7.1 will accrue to the Large Load Interconnection Customer’s benefit.

Execution and filing of the Large Load Interconnection Agreement at FERC are addressed in LLIP Section 5.

Section 5.
Large Load Interconnection Agreement

5.1
Tender.  Within thirty (30) Calendar Days after the Report Meeting for the final Large Load Interconnection Study report or, if the Large Load Interconnection Customer has timely requested a FILI Study pursuant to LLIP Section 4.6.2, within thirty (30) Calendar Days after issuance of the final FILI Study report (or, if a Report Meeting is requested for the FILI Study, after such Report Meeting), the Participating TO shall tender to the Large Load Interconnection Customer a draft Large Load Interconnection Agreement developed by the Participating TO consistent with the TO Tariff, this LLIP, and the results of the Interconnection Studies.  The draft Large Load Interconnection Agreement shall address, without limitation, the scope, schedule, cost responsibility, payment provisions, cost recovery, and financial security for the Participating TO’s Interconnection Facilities and Large Load Network Upgrades, and any applicable operating requirements.  The Large Load Interconnection Customer shall provide written comments, or notification of no comments, on the draft Large Load Interconnection Agreement within thirty (30) Calendar Days.

5.2
Negotiation.  Notwithstanding LLIP Section 5.1, at the request of Large Load Interconnection Customer, Participating TO shall begin negotiations with Large Load Interconnection Customer concerning the terms and conditions of the Large Load Interconnection Agreement at any time after the Participating TO provides the Large Load Interconnection Customer with the final Large Load Interconnection Study report, or the final FILI Study report, if applicable. Participating TO and Large Load Interconnection Customer shall negotiate in good faith concerning any disputed provisions of the draft Large Load Interconnection Agreement for not more than sixty (60) Calendar Days after the Participating TO provides the Large Load Interconnection Customer with the final

PDF page 196

26

Large Load Interconnection Study report or the final FILI Study report if applicable.  If Large Load Interconnection Customer determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the draft Large Load Interconnection Agreement pursuant to LLIP Section 5.1 and request submission of the unexecuted Large Load Interconnection Agreement with FERC or initiate Dispute Resolution procedures pursuant to LLIP Section 7.2.  If Large Load Interconnection Customer requests termination of the negotiations, but within sixty (60) Calendar Days after issuance of the final Large Load Interconnection Study report, or the final FILI Study report if applicable, fails to request either the filing of the unexecuted Large Load Interconnection Agreement or initiate Dispute Resolution, it shall be deemed to have withdrawn its Interconnection Request.  Unless otherwise agreed by the Parties, if Large Load Interconnection Customer has not executed the Large Load Interconnection Agreement, requested filing of an unexecuted Large Load Interconnection Agreement, or initiated Dispute Resolution procedures pursuant to LLIP Section 7.2 within the time period set forth in LLIP Section 5.3, it shall be deemed to have withdrawn its Interconnection Request.  Participating TO shall provide to Large Load Interconnection Customer a final Large Load Interconnection Agreement within fifteen (15) Business Days after the completion of the negotiation process.

The Participating TO may declare an impasse upon sixty (60) Calendar Days after issuance of the final Large Load Interconnection Study report, or the final FILI Study report if applicable, or at any time following sixty (60) Calendar Days after issuance of the final Large Load Interconnection Study report, or the final FILI Study report if applicable, if the Parties have agreed to extend negotiation of the Large Load Interconnection Agreement.  If the Participating TO declares an impasse, the Participating TO will file the Large Load Interconnection Agreement unexecuted with FERC within twenty-one (21) Calendar Days.

5.3
Execution and Filing
Within thirty (30) Business Days after receipt of the final Large Load Interconnection Agreement, Large Load Interconnection Customer shall either: (i) execute the final Large Load Interconnection Agreement and return it to Participating TO; or (ii) request in writing that Participating TO file with FERC the Large Load Interconnection Agreement in unexecuted form, or its Interconnection Request shall be deemed withdrawn and subject to LLIP Section 3.10.  To the extent FERC filing is required, as soon as practicable, but not later than ten (10) Business Days after receiving either the executed Large Load Interconnection Agreement or the request to file an unexecuted Large Load Interconnection Agreement, Participating TO shall file the Large Load Interconnection Agreement with FERC, together with, in the case of an unexecuted Large Load Interconnection Agreement, its explanation of any matters as to which Large Load Interconnection Customer and Participating TO disagree and support for the costs that Participating TO proposes to charge to Large Load Interconnection Customer under the Large Load Interconnection Agreement.  An unexecuted Large Load Interconnection Agreement should contain terms and conditions deemed appropriate by Participating TO for the Interconnection

PDF page 197

27

Request.  If the Parties agree to proceed with design, procurement, and construction of facilities and upgrades under the agreed-upon terms of the unexecuted Large Load Interconnection Agreement, they may proceed pending FERC action.  As a condition to the Participating TO’s design, procurement, construction, or operation of any Large Load-Driven Upgrades (as defined in the pro forma Large Load Cost Recovery Agreement set forth in Appendix V to the TO Tariff) associated with the Interconnection Request, the Large Load Interconnection Customer shall also, within the same period and subject to the same consequences as the Large Load Interconnection Agreement, execute and maintain a Cost Recovery Agreement substantially in the form set forth in Appendix V to the TO Tariff, or, if the Large Load Interconnection Customer requests that the Cost Recovery Agreement be filed unexecuted with FERC, comply with that agreement as made effective by FERC.  A Cost Recovery Agreement required by this LLIP Section 5.3 is entered into pursuant to the TO Tariff.

5.4
Commencement of Interconnection Activities
If Large Load Interconnection Customer executes the final Large Load Interconnection Agreement, Participating TO and Large Load Interconnection Customer shall perform their respective obligations in accordance with the terms of the Large Load Interconnection Agreement, subject to modification by FERC. Upon submission of an unexecuted Large Load Interconnection Agreement, Large Load Interconnection Customer and Participating TO shall promptly comply with the unexecuted Large Load Interconnection Agreement, if agreed to by the Parties pursuant to LLIP Section 5.3, subject to modification by FERC.

Section 6.
Construction of Participating TO's Interconnection Facilities and Large Load Network Upgrades

6.1
Schedule
Participating TO and Large Load Interconnection Customer shall negotiate in good faith concerning a schedule for the Participating TO’s construction of Participating TO's Interconnection Facilities and the Large Load Network Upgrades.

6.2
Construction Sequencing

6.2.1 General.  In general, the Service Commencement Date will determine the sequence of construction of Large Load Network Upgrades.

6.2.2 Advancing Construction of Large Load Network Upgrades that are Part of an Expansion Plan of the Participating TO.  A Large Load Interconnection Customer with a Large Load Interconnection Agreement, in order to maintain its Service Commencement Date, may request that Participating TO advance to the extent necessary the completion of Large Load Network Upgrades that:  (i) are necessary to support such Service Commencement Date and (ii) would otherwise not be completed, pursuant

PDF page 198

28

to an expansion plan of Participating TO or approved ISO Transmission Plan covering the Participating TO’s facilities, in time to support such Service Commencement Date.  Upon such request, Participating TO will use Reasonable Efforts to advance the construction of such Large Load Network Upgrades to accommodate such request; provided that Large Load Interconnection Customer commits to pay Participating TO any associated expediting costs.

6.3
Special Provisions for Affected Systems
The Large Load Interconnection Customer shall timely enter into and maintain an agreement with each applicable Affected System Operator for each addition, modification, or upgrade to an Affected System identified through the Interconnection Studies or an applicable Affected System study.  The agreement shall specify the terms governing payments to be made by the Large Load Interconnection Customer to the Affected System Operator, including financial security or credit support sufficient to protect the Affected System Operator and its other customers against cost shifting.  Where a Cost Recovery Agreement applies, the Large Load Interconnection Customer shall provide the Participating TO the evidence of such agreements required by, and within the time specified in, the Cost Recovery Agreement, and the Participating TO may decline to commence, or may suspend, construction as provided in the Cost Recovery Agreement.

Section 7.
Miscellaneous

7.1
Confidentiality

For the purposes of this LLIP Section 7.1, “Party” or “Parties” shall mean the Participating TO, Large Load Interconnection Customer, ISO, or any combination of the Participating TO, Large Load Interconnection Customer, or ISO.

Confidential Information shall include, without limitation, all information relating to a Party's technology, research and development, business affairs, and pricing.

Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Party receiving the information that the information is confidential.

If requested by either Party, the other Party shall provide in writing, the basis for asserting that the information referred to in this LLIP Section 7.1 warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority.  Each Party shall be responsible for the costs associated with affording confidential treatment to its information.

7.1.1 Scope.  Confidential Information shall not include information that the receiving Party can demonstrate: (1) is generally available to the public

PDF page 199

29

other than as a result of a disclosure by the receiving Party; (2) was in the lawful possession of the receiving Party on a non-confidential basis before receiving it from the disclosing Party; (3) was supplied to the receiving Party without restriction by a third party, who, to the knowledge of the receiving Party after due inquiry, was under no obligation to the disclosing Party to keep such information confidential; (4) was independently developed by the receiving Party without reference to Confidential Information of the disclosing Party; (5) is, or becomes, publicly known, through no wrongful act or omission of the receiving Party or Breach of the Large Load Interconnection Agreement; or (6) is required, in accordance with LLIP Section 7.1.6, Order of Disclosure, to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena, or is necessary in any legal proceeding establishing rights and obligations under the Large Load Interconnection Agreement. Information designated as Confidential Information will no longer be deemed confidential if the Party that designated the information as confidential notifies the other Party that it no longer is confidential.

7.1.2  Release of Confidential Information.  Neither Party shall release or disclose Confidential Information to any other person, except to its Affiliates (limited by the Standards of Conduct requirements), employees, consultants, Affected System Operators, the Large Load Customer, or to parties who may be providing or considering providing financing to or equity participation with Large Load Interconnection Customer or the Large Load Customer, or to potential purchasers or assignees of Large Load Interconnection Customer or the Large Load Customer, on a need- to-know basis in connection with these procedures, unless such person has first been advised of the confidentiality provisions of this LLIP Section 7.1 and has agreed to comply with such provisions.  Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible for any release of Confidential Information in contravention of this LLIP Section 7.1.

7.1.3 Rights.  Each Party retains all rights, title, and interest in the Confidential Information that each Party discloses to the other Party.  The disclosure by each Party to the other Party of Confidential Information shall not be deemed a waiver by either Party or any other person or entity of the right to protect the Confidential Information from public disclosure.

7.1.4 No Warranties.  By providing Confidential Information, neither Party makes any warranties or representations as to its accuracy or completeness.  In addition, by supplying Confidential Information, neither Party obligates itself to provide any particular information or Confidential Information to the other Party nor to enter into any further agreements or proceed with any other relationship or joint venture.

PDF page 200

30

7.1.5 Standard of Care.  Each Party shall use at least the same standard of care to protect Confidential Information it receives as it uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination.  Each Party may use Confidential Information solely to fulfill its obligations to the other Party under these procedures or its regulatory requirements.

7.1.6 Order of Disclosure.  If a court or a Governmental Authority or entity with the right, power, and apparent authority to do so requests or requires either Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the other Party with prompt notice of such request(s) or requirement(s) so that the other Party may seek an appropriate protective order or waive compliance with the terms of these confidentiality provisions. Notwithstanding the absence of a protective order or waiver, the Party may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose.  Each Party will use Reasonable Efforts to obtain reliable assurance that confidential treatment will be accorded any Confidential Information so furnished.

7.1.7 Remedies.  The Parties agree that monetary damages would be inadequate to compensate a Party for the other Party's Breach of its obligations under this LLIP Section 7.1.  Each Party accordingly agrees that the other Party shall be entitled to equitable relief, by way of injunction or otherwise, if the first Party Breaches or threatens to Breach its obligations under this LLIP Section 7.1, which equitable relief shall be granted without bond or proof of damages, and the receiving Party shall not plead in defense that there would be an adequate remedy at law.  Such remedy shall not be deemed an exclusive remedy for the Breach of this LLIP Section 7.1, but shall be in addition to all other remedies available at law or in equity.  The Parties further acknowledge and agree that the covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope.  No Party, however, shall be liable for indirect, incidental, or consequential or punitive damages of any nature or kind resulting from or arising in connection with this LLIP Section 7.1.

7.1.8 Disclosure to FERC, its Staff, or a State.  Notwithstanding anything in this LLIP Section 7.1 to the contrary, and pursuant to 18 CFR section 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence pursuant to the LLIP, the Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information.  In providing the information to FERC or its staff, the Party must, consistent with 18 CFR section 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld

PDF page 201

31

from public disclosure.  Parties are prohibited from notifying the other Party prior to the release of the Confidential Information to FERC or its staff.  The Party shall notify the other Party to the Large Load Interconnection Agreement when it is notified by FERC or its staff that a request to release Confidential Information has been received by FERC, at which time either of the Parties may respond before such information would be made public, pursuant to 18 CFR section 388.112.  Requests from a state regulatory body conducting a confidential investigation shall be treated in a similar manner, consistent with applicable state rules and regulations.

7.1.9 Subject to the exception in LLIP Section 7.1.8, any information that a Party claims is competitively sensitive, commercial or financial information ("Confidential Information") shall not be disclosed by the other Party to any person not employed or retained by the other Party, except to the extent disclosure is (i) required by law; (ii) reasonably deemed by the disclosing Party to be required to be disclosed in connection with a dispute between or among the Parties, or the defense of litigation or dispute; (iii) otherwise permitted by consent of the other Party, such consent not to be unreasonably withheld;  or (iv) necessary to fulfill its obligations under this LLIP or as a Participating TO, including disclosing the Confidential Information to the ISO or to a subregional, regional or national reliability organization or planning group.  The Party asserting confidentiality shall notify the other Party in writing of the information it claims is confidential.  Prior to any disclosures of the other Party's Confidential Information under this subparagraph, or if any third party or Governmental Authority makes any request or demand for any of the information described in this subparagraph, the disclosing Party agrees to promptly notify the other Party in writing and agrees to assert confidentiality and cooperate with the other Party in seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order or other reasonable measures.

7.1.10 This provision shall not apply to any information that was or is hereafter in the public domain (except as a result of a Breach of this provision).

7.1.11 Participating TO shall, at Large Load Interconnection Customer's election, destroy, in a confidential manner, or return the Confidential Information provided at the time the Confidential Information is no longer needed.

7.2
Disputes

7.2.1  Submission.  In the event either Party has a dispute, or asserts a claim, that arises out of or in connection with the Large Load Interconnection Agreement, the LLIP, or their performance, such Party (the "disputing Party") shall provide the other Party with written notice of the dispute or claim ("Notice of Dispute").  Such dispute or claim shall be resolved in

PDF page 202

32

accordance with Section 14 of the TO Tariff, including, as applicable, the ISO ADR Procedures; provided, however, that disputes arising under a Cost Recovery Agreement shall be resolved under the dispute resolution provisions of that agreement.

PDF page 203

33

ATTACHMENT 1
TO APPENDIX VI – LARGE LOAD INTERCONNECTION PROCEDURES

INTERCONNECTION REQUEST FORM

This Interconnection Request is submitted to DesertLink, LLC (“Participating TO”) by the Eligible Customer for Large Load (“ECLL”) identified below, acting as the Large Load Interconnection Customer, pursuant to LLIP Section 4.2.1 and Section 10A of the TO Tariff. Consistent with LLIP Section 3.1, the Large Load Interconnection Customer shall send a copy of this Interconnection Request to the ISO.  Capitalized terms not defined herein have the meanings set forth in the LLIP or, if not defined in the LLIP, in Section 3 of the TO Tariff.

I. Large Load Interconnection Customer (ECLL) Contact Information
Company Name

Type of ECLL (UDC or MSS)

Representative

Address

Email

Phone

II. Large Load Customer Information
Large Load Customer Name

Large Load Customer Representative and
Contact Information

Large Load Site Location/Address

Type of Large Load Facility (e.g., data
center, industrial)

Other ECLL interconnection requests
submitted for the same Large Load
Customer or any of its affiliates (see
Section 10A.2.1 of the TO Tariff)

III. Point of Interconnection

Please identify the location and voltage
level of the preferred Point of
Interconnection in as much detail as
possible. If proposing to connect to a
transmission line, provide the approximate
distance from one of the existing line
terminals.  The Point of Interconnection
will serve as the Point of Withdrawal under
the TO Tariff.

PDF page 204

34

IV. Large Load Capacity and Load Ramp Schedule

Proposed load ramp schedule identifying anticipated load additions over time: Date (MM/DD/YYYY)

Incremental Load (MW)
Cumulative Load (MW)

V. Proposed Service Commencement Date and Term

VI. Source of Power

VII. Site Plan, Site Control, and Permits

Please attach: (a) a site plan for the Large Load; (b) documentation demonstrating Site Control, as defined in Section 3 of the TO Tariff; and (c) documentation demonstrating that the Large Maximum Large Load capacity requested

at the Point of Interconnection (MW) (see
LLIP Section 3.6)

Maximum capacity the Large Load is
capable of withdrawing, if greater than the
amount requested, and the proposed means
of limiting withdrawals to the requested
amount

Expected power factor and load factor

Proposed date for energizing the ECLL
Interconnection (MM/DD/YYYY)

Proposed Service Commencement Date
(MM/DD/YYYY) (see LLIP Section 3.7)

Proposed term of service (years)

Please identify the electrical location of the
source of power to be delivered to the
Large Load, if known.  If the source of the
power is not known, a system purchase
will be assumed.  Nothing in this
Interconnection Request constitutes a
request for transmission service (see LLIP
Section 3.2.2).

PDF page 205

35

Load Customer has local permits and regulatory approvals for development of the Large Load, consistent with Section 10A.2.1(f) of the TO Tariff.

VIII. Co-Located Generation

Will the Large Load be co-located with a
generating facility? (Yes/No)

Will the generating facility export to the
ISO Controlled Grid? (Yes/No)

Generating facility queue number or, if
executed, identification of its generator
interconnection agreement

Generating facility nameplate capacity
(MW)

IX. Single-Line Diagram and Modeling Information

Please attach a single-line diagram of the Large Load and the Large Load Interconnection Customer’s Interconnection Facilities and/or KMZ files to this Interconnection Request.  Please provide power flow modeling files (PSS/E or PSLF format preferred) or spreadsheet format containing modeling data such as impedances and ratings of customer-owned equipment. Also provide short-circuit modeling data, dynamic and electromagnetic transient (EMT) models, load characteristics (including ride-through capability, ramp rates, and harmonic characteristics), any other details to be taken into consideration in the Interconnection Studies, and the completed technical data form in the form of Appendix A to this Attachment 1.

X. Required Submittals (LLIP Section 4.2.1)
Item
Included (Yes/No)
Interconnection Study Deposit of $250,000

Commercial Readiness Deposit equal to
two times the Interconnection Study
Deposit, in a form permitted by LLIP
Section 4.7.1

Demonstration of Site Control

Completed technical data form in the form
of Appendix A to this Attachment 1 (TO
Tariff Section 10A.2.1(j))

Copy of this Interconnection Request sent
to the ISO

XI. Acknowledgment

By submission of this Interconnection Request, the Large Load Interconnection Customer acknowledges that additional detail may be required to satisfactorily perform the Interconnection

PDF page 206

36

Studies related to this Interconnection Request and agrees to work with DesertLink, LLC in good faith to provide additional information as necessary.  The Large Load Interconnection Customer may designate information in this Interconnection Request, including the identity of the Large Load Customer, as Confidential Information in accordance with LLIP Section 7.1.

Interconnection Request Submitted By:

Interconnection Request Received By DesertLink, LLC:

Printed Name:

Date:

Printed Name:

Date:

PDF page 207

Attachment 2

DesertLink TO Tariff Revisions (Marked)

PDF page 208

DesertLink, LLC
Transmission Owner Tariff

Table of Contents
1. Preamble
1.1
Transmission Access for Participating TOs 1.2

Transmission Access for Wheeling Customers 1.3

Transmission Access for End-User
2. Effective Date
2.1
Termination
3. TO Definitions
3.1
Access Charge
3.2
AGC
3.3
Ancillary Services
3.4
Applicable Reliability Criteria
3.5
Available Transfer Capacity
3.6
Base Transmission Revenue Requirement 3.7

Black Start
3.8
Business Day
3.9
Completed Application Date
3.10
Completed Interconnection Application 3.11

Congestion
3.12
Congestion Management
3.13
Converted Rights
3.14
CPUC
3.15
Demand
3.16
DesertLink
3.17
Direct Assignment Facilities
3.18
Dispatch
3.19
Distribution System
3.20
Eligible Customer
3.21
Encumbrance
3.22
End-Use Customer or End-User
3.23
Energy
3.24
Entitlement
3.25
Existing Contracts
3.26
Existing Rights
3.27
Expedited Interconnection Agreement 3.28

Facilities Study Agreement
3.29
Facility or Facilities Study
3.30
FERC
3.31
FPA
3.32
Generating Unit
3.33
Generation
3.34
Good Utility Practice

PDF page 209

3.35
Gross Load
3.36
High Voltage Access Charge
3.37
High Voltage Transmission Facility
3.38
High Voltage Transmission Revenue Requirement 3.39

High Voltage Utility-Specific Rate
3.40
High Voltage Wheeling Access Charge
3.41
Independent System Operator
3.42
ISO ADR Procedures
3.43
ISO Controlled Grid
3.44
ISO Protocols
3.45
ISO Tariff
3.46
Interconnection
3.47
Interconnection Agreement
3.48
Interconnection Application
3.49
Interest
3.50
Load
3.51
Local Publicly Owned Electric Utility
3.52
Local Regulatory Authority
3.53
Local Reliability Criteria
3.54
Low Voltage Access Charge
3.55
Low Voltage Transmission Revenue Requirement 3.56

Low Voltage Wheeling Access Charge
3.57
Market Participant
3.58
Metered Subsystem (“MSS”)
3.59
NERC
3.60
New Participating TO
3.61
Non-Load Serving Participating TO
3.62
Non-Participating TO
3.63
Non-Spinning Reserve
3.64
Operational Control
3.65
Original Participating TO
3.66
Participating TO (“PTO”)
3.67
Participating Agreement
3.68
Physical Scheduling Plant
3.69
Project
3.70
Project Proponent
3.71
Project Sponsor
3.72
Regional Transmission Group (“RTG”)
3.73
Regulation
3.74
Regulatory Authority
3.75
Reliability Criteria
3.76
Reliability Upgrade
3.77
Request for Expedited Interconnection Procedures 3.78

Scheduling Coordinator
3.79
Scheduling Point
3.80
Spinning Reserve

PDF page 210

3.81
System Impact Study
3.82
System Impact Study Agreement
3.83
TO Tariff
3.84
[Not used]
3.85
[Not used]
3.86
Transmission Control Agreement (“TCA”)
3.87
Transmission Owner (“TO”)
3.88
Transmission Revenue Balancing Account Adjustment (“TRBAA”) 3.89

Transmission Revenue Credit
3.90
Transmission Revenue Requirement (“TRR”)
3.91
Transmission System Rights (“TSRs”)
3.92
Uncontrollable Force
3.93
Utility Distribution Company (“UDC”)
3.94
Voltage Support
3.95
Western Electricity Coordinating Council (“WECC”)
3.96
Wheeling Access Charge
3.97
Wheeling Out
3.98
Wheeling Through
3.99
Wheeling
3.100 Wholesale Customer
4. Eligibility
5. Access Charges and Transmission Rates
5.1
Low Voltage Access Charge
5.2
Wheeling Access Charge
5.3
Transmission Revenue Requirement
5.4
Transmission System Rights
5.5
Transmission Revenue Balancing Account Adjustment
6. Ancillary Services - Applicability and Charges
7. Billing and Payment
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades

8.1
Participating TO Obligation to Interconnect
8.2
Participating TO Obligation to Construct Transmission Expansion or Facility Upgrades

8.3
Request for FERC Deference Regarding Need Determination
9. Expansion Process
9.1
Determination of Facilities
9.2
Obligation to Build
9.3
Provisions Relating To Transmission Construction On the Systems of Other TOs

10. TSWL Interconnection Process
10.1
Applicability
10.2
Applications
10.3
Interconnection Application
10.4
Review of Completed Interconnection Application
10.5
Notice of Need for System Impact Study

PDF page 211

10.6
Impact Study Cost Reimbursement Agreement
10.7
System Impact Study Procedures
10.8
Notice of Need for Facilities Study
10.9
Facilities Study Procedures
10.10 Partial Interim Service
10.11 Expedited Interconnection Procedures
10A. Interconnection Process for ECLL Interconnections

10A.1 Applicability

10A.2 ECLL Application and Application Fee

10A.3 Study Process and ECLL Interconnection Agreement

10A.4 Interim Service

10A.5 Co-Located Large Load

10A.6 Large Load Cost Recovery Agreement
11. Uncontrollable Forces and Indemnification 11.1

Procedures to Follow of Uncontrollable Force Occurs 11.2

Indemnification
12. Regulatory Filings
12.1
Open Access
13. Creditworthiness
13.1
UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low Voltage Transmission Facilities

13.2
End-Users
14. Disputes
15. [Reserved]
16. Miscellaneous
16.1
Notices
16.2
Waiver
16.3
Confidentiality
16.4
TO Tariff Supersedes Existing Tariffs
16.5
Titles
16.6
Severability
16.7
Preservation of Obligations
16.8
Governing Law
16.9
Appendices Incorporated
16.10 Conflict with ISO Tariff
16.11 Conflicting Operating Instructions
16.12 Conflict With Transfer Capability Lease

Appendix I
Transmission Revenue Requirement and TRBAA
Appendix II
Notices
Appendix III
Formula Rate
Appendix IV
Formula Rate Implementation Protocols
Appendix V
Pro Forma Large Load Cost Recovery Agreement Appendix VI

Large Load Interconnection Procedures

PDF page 212

3. TO Definitions. Certain capitalized terms used in this TO Tariff shall have the meanings set out below unless otherwise stated or the context otherwise requires. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the ISO Tariff as it may be amended from time to time.

3.1.
Access Charge. A charge paid by all UDCs, MSSs, and, in certain cases, Scheduling Coordinators delivering Energy to Gross Load, as set forth in Section 26.1 of the ISO Tariff. The Access Charge includes the High Voltage Access Charge and the Low Voltage Access Charge, as applicable.

3.2.
AGC. Generation equipment that automatically responds to signals from the ISO’s EMS control in real time to control the power output of electric generators within a prescribed area in response to a change in system frequency, tie-line loading, or the relation of these to each other, so as to maintain the target system frequency and/or the established interchange with other areas within the predetermined limits.

3.3.
Ancillary Services. Regulation, Spinning Reserve, Non-Spinning Reserve, Voltage Support and Black Start together with such other interconnected operation services as the ISO may develop in cooperation with Market Participants to support the transmission of Energy from generation resources to Loads while maintaining reliable operation of the ISO Controlled Grid in accordance with Good Utility Practice.

3.4.
Applicable Reliability Criteria. The Reliability Standards and reliability criteria established by NERC and WECC, and Local Reliability Criteria, as amended from time to time, including any requirement of the Nuclear Regulatory Commission.

3.5.
Available Transfer Capacity. The available capacity of a given transmission path, in MW after allocation of rights associated with Existing Contracts and Transmission Ownership Rights, to that path’s Operating Transfer Capability established consistent with ISO and WECC transmission capacity rating guidelines, as further described in Appendix L to the ISO Tariff.

3.6.
Base Transmission Revenue Requirement. The Transmission Revenue Requirement which does not reflect amounts for the TRBAA.

3.7.
Black Start. The procedure by which a Generating Unit self-starts without an external source of electricity, thereby restoring power to the ISO Controlled Grid following system or local area blackouts.

3.8.
Business Day. Monday through Friday, excluding federal holidays and the day after Thanksgiving Day.

3.9.
Co-Located Large Load. A Large Load that is physically connected to the facilities of an existing or planned Generating Facility on the Interconnection Customer’s side of the Point of Interconnection to the ISO Controlled Grid (each as defined in the ISO Tariff).

PDF page 213

3.93.10.
Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed TSWL or ECLL Interconnection Application.

3.11. Completed ECLL Interconnection Application. An ECLL Interconnection Application that has been deemed valid under Section 4.3 of Appendix VI.

3.103.12. Completed TSWL Interconnection Application. AnA TSWL Interconnection Application that satisfies all of the information and other requirements of Section 10.3 of this TO Tariff and, if applicable, the information requirements as specified by the ISO and posted on the ISO Home Page.

3.113.13. Congestion. A characteristic of the transmission system produced by a binding Constraint to the optimum economic dispatch to meet Demand such that the LMP, exclusive of Marginal Cost of Losses, at different Locations of the transmission system is not equal.

3.123.14. Congestion Management. The alleviation of Congestion in accordance with applicable ISO Protocols and Good Utility Practice.

3.133.15. Converted Rights. Those transmission service rights determined in accordance with Section 4.3.1.6 of the ISO Tariff.

3.16. Cost Recovery Agreement. An agreement between the Participating TO and an Eligible Customer, including an ECLL, substantially in the form of the pro forma Large Load Cost Recovery Agreement set forth in Appendix V, entered into pursuant to Section 10.9 or Section 10A.6 of this TO Tariff.

3.143.17. CPUC. The California Public Utilities Commission or its successor. 3.153.18. Demand. The rates at which Energy is delivered to Load and Scheduling Points by Generation, transmission or distribution facilities. It is the product of voltage and the in- phase component of alternating current measured in units of watts or standard multiples therefore, e.g. 1000 W = 1 kW, 1000 kW= 1 MW, etc.

3.163.19. DesertLink, LLC (“DesertLink”). The Delaware limited liability company that is the Participating TO under this TO Tariff.

3.173.20. Direct Assignment Facilities. Facilities or portions of facilities that are owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting interconnectiona TSWL Interconnection under this TO Tariff to the ISO Controlled Grid at the point of interconnection. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs TSWL Interconnection service to such party and shall be subject to FERC approval.

PDF page 214

3.183.21. Dispatch. The operating control of an integrated electric system to: i) assign specific Generation Units and other sources of supply to effect the supply to meet the relevant area Demand taken as Load rises or falls; ii) control operations and maintenance of high voltage lines, substations, and equipment, including administration of safety procedures;

iii) operate Interconnections; iv) manage Energy transactions with other interconnected Control Areas; and v) curtail Demand.

3.193.22. Distribution System. The distribution assets of a TO, UDC, or MSS.

3.203.23. Eligible Customer. (i) Any utility (including any Participating TO, Market Participant or power marketer), Federal power marketing agency, or any person generating Energy for sale or resale; Energy sold or produced by such entity may be Energy produced in the United States, Canada or Mexico; however, such entity is not eligible for transmission service that would be prohibited by FPA Section 212(h)(2); and

(ii) any retail customer taking unbundled transmission service pursuant to a state retail access program or pursuant to a voluntary offer of unbundled retail transmissions service by the Participating TO.

3.24. Eligible Customer for Large Load (“ECLL”). A UDC or MSS that provides retail transmission and interconnection service to Large Load End-Users in the ISO’s Balancing Authority Area.

3.25. ECLL Interconnection Agreement. The agreement between an ECLL and the Participating TO governing an ECLL Interconnection.

3.26. ECLL Interconnection. The interconnection of the facilities of an ECLL to the facilities of the Participating TO that are for the purpose of an ECLL interconnecting and providing transmission service to a Large Load Customer.

3.27. ECLL Interconnection Application. An application that requests an ECLL Interconnection to the ISO Controlled Grid.

3.28. ECLL Interconnection Facilities. The facilities, additions, and upgrades of the Participating TO necessary to accomplish an ECLL Interconnection, as identified in the applicable ECLL Interconnection Agreement.

3.213.29. Encumbrance. A legal restriction or covenant binding on the Participating TO that affects the operation of any transmission lines or associated facilities and which the ISO needs to take into account in exercising Operational Control over such transmission lines or associated facilities if the Participating TO is not to risk incurring significant liability. Encumbrances shall include Existing Contracts and may include: (1) other local restrictions or covenants meeting the definition of Encumbrance and arising under other arrangements entered into before the ISO Operations Date, if any; and (2) legal restrictions or covenants meeting the definition of Encumbrance and arising under a contract or other arrangement entered into after the ISO Operations Date.

PDF page 215

3.223.30. End-Use Customer or End-User. A purchaser of electric power that purchases such power to satisfy a Load directly connected to the ISO Controlled Grid or to a Distribution System and who does not resell the power.

3.233.31. Energy. The electrical energy produced, flowing, or supplied by Generation, transmission, or distribution facilities, being the integral with respect to time of the instantaneous power, measured in units of watt-hours or standard multiples thereof. 3.31.1.1.

E.g. 1000 Wh = 1 kW, 1000 kWh = 1 MWh, etc.

3.243.32. Entitlement. The right of a Participating TO obtained through contract or other means to use another entity’s transmission facilities for the transmission of Energy.

3.253.33. Existing Contracts. Those transmission service agreements or other contracts which grant transmission service rights in existence on the ISO Operations Date (including any contracts entered into pursuant to such contracts) as may be amended in accordance with their terms or by agreement between the parties thereto from time to time.

3.263.34. Existing Rights. Those transmission service rights defined in Section 16.1 of the ISO Tariff.

3.273.35. Expedited Interconnection Agreement. A contract between a party which has submitted a Request for Expedited Interconnection Procedures and the Participating TO under which the Participating TO agrees to process, on an expedited basis, the Completed Interconnection Application of such party and which sets forth the terms, conditions, and cost responsibilities for such Interconnection.

3.283.36. Facilities Study Agreement. An agreement between a Participating TO and either a party requesting Interconnection to the ISO Controlled Grid, Market Participants, Project Sponsor, ECLL, or identified principal beneficiaries pursuant to which the party requesting such Interconnection, Market Participant, Project Sponsor or identified principal beneficiaries  agrees to reimburse the Participating TO for the cost of performing or reviewing a Facilities Study.

3.293.37. Facility or Facilities Study. An engineering study conducted to determine required modifications to the Participating TO’s transmission system, including the estimated cost and scheduled completion date for such modifications, that will be required to provide needed services.

3.303.38. FERC. The Federal Energy Regulatory Commission, or its successor.

3.39. Firm Interconnection Service. The highest quality (priority) load Interconnection service that provides the on-going safe and reliable operation and maintenance of, and the Parties’ rights and responsibilities associated with their facilities.

3.40. Flexible Interim Load Interconnection (“FILI”) Service. A transmission interconnection service offered by the Participating TO and accepted by an Eligible

PDF page 216

Customer on behalf of a Large Load retail customer to manage operational constraints on withdrawals from the transmission system while the interconnection and system upgrades necessary to provide Firm Interconnection Service are being developed.

3.41. FILI Service Agreement. The agreement developed by the Participating TO pursuant to Section 10A.4 that sets forth the terms, conditions, and operating requirements for FILI Service.

3.313.42. FPA. The Federal Power Act, 16 U.S.C.§ 791a et seq., as it may be amended from time to time.

3.43. Generating Facility. An Interconnection Customer’s Generating Unit(s) used for the production and/or storage for later injection of electricity identified in the Interconnection Request, but shall not include the Interconnection Customer’s Interconnection Facilities.

3.323.44. Generating Unit. An individual electric generator and its associated plant and apparatus whose electrical output is capable of being separately identified and metered or a Physical Scheduling Plant, that, in either case, is: (a) located within the ISO Control Area; (b) connected to the ISO Controlled Grid, either directly or via interconnected transmission or distribution facilities; and (c) that is capable of producing and delivering net Energy (Energy in excess of a generation stations’ internal power requirements).

3.333.45. Generation. Energy delivered from a Generating Unit.

3.46. Generator Interconnection. The interconnection of one or more Generating Units to the ISO Controlled Grid facilities owned by the Participating TO.

3.343.47. Good Utility Practice. Any of the practices, methods, and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods, and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety, and expedition.

3.353.48. Gross Load. For purposes of calculating the transmission Access Charge, Gross Load is all Energy (adjusted for distribution losses) delivered for the supply of End-Use Customer Loads directly connected to the transmission facilities or directly connected to the Distribution System of a Utility Distribution Company or MSS Operator located in a PTO Service Territory. Gross Load shall exclude (1) Load with respect to which the Wheeling Access Charge is payable, (2) Load that is exempt from the Access Charge pursuant to Section 4.1, Appendix I of the ISO Tariff, and the portion of the load of an individual retail customer of a Utility Distribution Company, Small Utility Distribution Company or MSS Operator that is served by a Generating Unit that: (a) is located on the customer’s site or provides service to the customer’s site through over-the-fence

PDF page 217

arrangements as authorized by Section 218 of the California Public Utilities Code; (b) is a qualifying small power production facility or qualifying cogeneration facility, as those terms are defined in the FERC’s regulations implementing Section 201 of the Public Utility Regulatory Policies Act of 1978; and (c) secures Standby Service from the Participating TO under terms approved by a Local Regulatory Authority or FERC, as applicable, or can be curtailed concurrently with an Outage of the Generating Unit serving the Load. Gross Load forecasts consistent with filed Transmission Revenue Requirements will be provided by each Participating TO to the ISO.

3.363.49. High Voltage Access Charge. A component of the Access Charge determined by the ISO under Section 26.1 of the ISO Tariff.

3.373.50. High Voltage Transmission Facility. A transmission facility under the Operational Control of the ISO that is owned by the Participating TO or to which the Participating TO has an Entitlement that may be associated with a Converted Right, which operates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs of which are not directly assigned to one or more specific customers.

3.383.51. High Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s High Voltage Transmission Facilities and Rights associated with High Voltage Transmission Facilities 3.393.52. High Voltage Utility-Specific Rate. The Participating TO’s High Voltage Transmission Revenue Requirement divided by the Participating TO’s forecast of its Gross Load.

3.403.53. High Voltage Wheeling Access Charge. The Wheeling Access Charge assessed by the ISO associated with the recovery of the Participating TO’s High Voltage Transmission Revenue Requirement in accordance with Section 26.1 of the ISO Tariff.

3.413.54. Independent System Operator (“ISO”). The California Independent System Operator Corporation, a state chartered, nonprofit corporation that controls the transmission facilities of all Participating TOs and dispatches certain Generating Units and Loads.

3.423.55. ISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13 of the ISO Tariff, as amended from time to time.

3.433.56. ISO Controlled Grid. The system of transmission lines and associated facilities of the Participating TOs that have been placed under the ISO’s Operational Control.

3.443.57. ISO Protocols. The rules, protocols, procedures and standards promulgated by the ISO (as amended from time to time) to be complied with by the ISO Scheduling Coordinators, Participating TOs and all other Market Participants in relation to the operation of the ISO Controlled Grid and the participation in the markets for Energy and Ancillary Services in accordance with the ISO Tariff.

PDF page 218

3.453.58. ISO Tariff. The California Independent System Operator Agreement and Tariff, dated November 1, 2013, as it may be modified from time to time.

3.46
Interconnection. Transmission facilities, other than additions or replacements to existing facilities that: (i) connect one system to another system where the facilities emerge from one and only one substation of the two systems and are functionally separate from the ISO Controlled Grid facilities such that the facilities are, or can be, operated and planned as a single facility; (ii) are identified as retail transmission lines pursuant to contract; or

(iii) produce Generation at a single point on the ISO Controlled Grid; provided that such interconnection does not include facilities that, if not owned by the Participating TO, would result in a reduction in the ISO’s Operational Control of the Participating TO’s portion of the ISO Controlled Grid.

3.473.59. Interconnection Agreement. A contract between a party requesting a TSWL Interconnection and the a Participating TO that owns the transmission facility with which the requesting party wishes to interconnect, as it may be amended from time to time, and, for an ECLL Interconnection, the ECLL Interconnection Agreement.

3.48
Interconnection Application. An application that requests Interconnection to the ISO Controlled Grid.

3.493.60. Interest. Interest shall be calculated in accordance with the methodology specified for interest on refunds in the regulations of FERC at 18 C.F.R. § 35.19a. Interest on delinquent amounts shall be calculated from the due date of the bill to the date of payment. When payments are made by mail, bills shall be considered as having been paid on the date of receipt. Notwithstanding the foregoing, interest, if any, on amounts payable or refundable between the Participating TO and a party to a Cost Recovery Agreement shall be governed solely by that Cost Recovery Agreement.

3.61. Interim Firm Interconnection Service. Interconnection service that can be provided, if any, on a firm basis prior to the completion of the ECLL Interconnection Facilities and an authorization for the Large Load to withdraw Energy.

3.62. Large Load. An End-User located at a single site behind one or more Point(s) of Withdrawal from the ISO Controlled Grid and that has a peak load of 50 MW or greater.

3.503.63. Load. An end-use device of an End-Use Customer that consumes power. Load should not be confused with Demand, which is the measure of power that a Load receives or requires.

3.513.64. Local Publicly Owned Electric Utility. A municipality or municipal corporation operating as a public utility furnishing electric service, a municipal district furnishing electric services, or a joint powers authority that includes one or more of these agencies and that owns Generation or transmission facilities, or furnishes electric services over its own or its members’ electric Distribution System.

3.523.65. Local Regulatory Authority. The state or local governmental authority responsible for the regulation or oversight of a utility.

PDF page 219

3.533.66. Local Reliability Criteria. Reliability criteria established by the ISO, unique to the transmission systems of each of the Participating TOs, as they may be updated from time to time.

3.543.67. Low Voltage Access Charge. The Access Charge applicable under Section 26.1 of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement of the Participating TO.

3.553.68. Low Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s Low Voltage Transmission Facilities and Converted Rights associated with Low Voltage Transmission Facilities.

3.563.69. Low Voltage Wheeling Access Charge. The Wheeling Access Charge associated with the recovery of the Participating TO’s Low Voltage Transmission Revenue Requirement in accordance with Section 26.1 of the 1SO Tariff.

3.573.70. Market Participant. An entity, including a Scheduling Coordinator, who participates in the Energy marketplace through the buying, selling, transmission, or distribution of Energy or Ancillary Services into, out of, or through the ISO Controlled Grid.

3.583.71. Metered Subsystem (“MSS”). A geographically contiguous system, located within a single zone which has been operating as an electric utility for a number of years prior to the ISO Operations Date as a municipal utility, water district, irrigation district, state agency or federal power marketing authority subsumed within the ISO Balancing Authority Area and encompassed by ISO certified revenue quality meters at each interface point with the ISO Controlled Grid and ISO-certified revenue quality meters on all Generating Units or, if aggregated, each individual resource and Participating Load, Reliability Demand Response Resource, and Proxy Demand Resource internal to the system, which is operated in accordance with a MSS agreement described in Section 4.9.1 of the ISO Tariff.

3.593.72. NERC. The North American Electric Reliability Corporation or its successor.

3.603.73. New Participating TO. A Participating TO that is not an Original Participating TO.

3.613.74. Non-Load-Serving Participating TO. A Participating TO that does not serve Load.

3.623.75. Non-Participating TO. A TO that is not a party to the TCA or, for the purpose of Section 16.1 of the ISO Tariff, the holder of transmission service rights under an Existing Contract that is not a Participating TO.

3.633.76. Non-Spinning Reserve. The portion of off-line generating capacity that is capable of being synchronized and ramping to a specified load in ten minutes (or load that is capable of being interrupted in ten minutes) and that is capable of running (or being interrupted) for at least two hours.

PDF page 220

3.643.77. Operational Control. The rights of the ISO under the Transmission Control Agreement and the ISO Tariff to direct Participating TOs how to operate their transmission lines and facilities and other electric plant affecting the reliability of those lines and facilities for the purpose of affording comparable nondiscriminatory transmission access and meeting Applicable Reliability Criteria.

3.653.78. Original Participating TO. A Participating TO that was a Participating TO as of January 1, 2000. The Original Participating TOs are Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company. 3.663.79. Participating TO (“PTO”). A party to the TCA whose application under Section 2.2 of the TCA has been accepted and who has placed, or expects to place, its transmission assets and/or Entitlements under the ISO’s Operational Control in accordance with the TCA. A PTO may be an Original Participating TO or a New Participating TO. For the purposes of this Tariff, the Participating TO is DesertLink.

3.673.80. Participation Agreement. An agreement between a Participating TO and a Project Sponsor that specifies the terms and conditions under which the Participating TO will construct a transmission addition or upgrade on behalf of the Project Sponsor. 3.683.81. Physical Scheduling Plant. A group of two or more related Generating Units each of which is individually capable of producing Energy, but which either by physical necessity or operational design must be operated as if they were a single Generating Unit and any Generating Unit or Units containing related multiple generating components which meet one or more of the following criteria: (i) multiple generating components are related by a common flow of fuel which cannot be interrupted without substantial loss of efficiency of the combined output of all components; (ii) the Energy production from one component necessarily causes Energy production from other components; (iii) the operational arrangement of related multiple generating components determines the overall physical efficiency of the combined output of all components; (iv) the level of coordination required to schedule individual generating components would cause the ISO to incur scheduling costs far in excess of the benefits of having scheduled such individual components separately; or (v) metered output is available only for the combined output of related multiple generation components and separate generating component metering is either impractical or economically inefficient.

3.82. Point of Withdrawal. Point(s) within the ISO Balancing Authority Area, or for purposes of scheduling and operating the Day Ahead Market only, the EDAM Area where Energy and Ancillary Services are made available to a receiving party under the ISO Tariff, for purposes of scheduling and operating the Real-Time Market only, the EIM Area where Energy and Ancillary Services are made available to a receiving party under the ISO Tariff, or for purposes of the definition of Large Load only, the point(s) where a non- transmission facility that is used to withdraw Energy from the ISO Controlled Grid to serve an End-User connects to the ISO Controlled Grid.

PDF page 221

3.693.83. Project. DesertLink’s interest in the single-circuit 500 kV (AC) overhead transmission line connecting the existing Harry Allen Substation in Nevada to the existing Eldorado Substation in Nevada, including series compensation. For the avoidance of doubt, the Project does not include any required work within the fence line of each substation.

3.703.84. Project Proponent. A Market Participant or group of Market Participants that (i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition or upgrade, and thus is not a Project Sponsor; and (iii) initiates proceedings under the ISO ADR Procedures to determine the need for the proposed transmission addition or upgrade.

3.713.85. Project Sponsor. A Market Participant or group of Market Participants or a Participating TO that proposes the construction of a transmission addition or upgrade in accordance with Section 24 of the ISO Tariff.

3.723.86. Regional Transmission Group (“RTG”). A voluntary organization approved by FERC and composed of transmission owners, transmission users, and other entities, organized to efficiently coordinate the planning, expansion, and use of transmission on a regional and inter-regional basis.

3.733.87. Regulation. The service provided either by Generating Units certified by the ISO as equipped and capable of responding to the ISO’s direct digital control (AGC) signals, or by System Resources that have been certified by the ISO as capable of delivering such service to the ISO Balancing Authority Area, in an upward and downward direction to match, on a Real Time basis, Demand and resources, consistent with established NERC and WECC reliability standards, including any requirements of the Nuclear Regulatory Commission. Regulation is used to control the Power output of electric generators within a prescribed area in response to a change in system frequency, tie-line loading, or the relation of these to each other so as to maintain the target system frequency and/or the established interchange with other Balancing Authority Areas within the predetermined Regulation Limits. Regulation includes both the increase of output by a Generating unit or System Resource (Regulation Up) and the decrease in output by a Generating unit or System Resource (Regulation Down). Regulation Up and Regulation Down are distinct capacity products, with separately stated requirements and ASMPs in each Settlement Period.

3.743.88. Regulatory Authority. The Federal Energy Regulatory Commission.

3.753.89. Reliability Criteria. Pre-established criteria that are to be followed in order to maintain desired performance of the ISO Controlled Grid under contingency or steady state conditions.

3.763.90. Reliability Upgrade. The transmission facilities, other than Direct Assignment Facilities, beyond the first point of Interconnection necessary to interconnect a New Facility or wholesale Loadaccomplish a TSWL Interconnection safely and reliably to the

PDF page 222

ISO Controlled Grid, which would not have been necessary but for the TSWL Interconnection of a New Facility or wholesale Load, including network upgrades necessary to remedy short circuit or stability problems resulting from the TSWL Interconnection of the new Facility or wholesale Load to the ISO Controlled Grid. Reliability Upgrades also include, consistent with WECC practice, the facilities necessary to mitigate any adverse impact a New Facility’s or wholesale Load’sTSWL Interconnection may have on a path’s WECC path rating. Reliability Upgrades shall be specified in the Interconnection Agreement that governs a TSWL Interconnection service and shall be subject to FERC approval.

3.773.91. Requests for Expedited Interconnection Procedures. A written request by which an applicant for Interconnection can request expedited processing of its TSWL Interconnection Application.

3.783.92. Scheduling Coordinator. An entity certified by the ISO for the purpose of undertaking the functions specified in Section 4.5 of the ISO Tariff.

3.793.93. Scheduling Point. A location at which the ISO Controlled Grid or a transmission facility owned by a Transmission Ownership Right holder is connected, by a group of transmission paths for which a physical, non-simultaneous transmission capacity rating has been established for Congestion Management, to transmission facilities that are outside the ISO’s Operational Control.

3.94. Site Control. An ECLL may demonstrate that its Large Load Customer has Site Control by:

an option for a lease or an executed lease for real property of sufficient size to house the Large Load; or

an option to purchase or title to real property of sufficient size to house the Large Load.

3.803.95. Spinning Reserve. The portion of unloaded synchronized generating capacity that is immediately responsive to system frequency and that is capable of being loaded in ten minutes, and that is capable of running for at least two hours.

3.813.96. System Impact Study. An engineering study conducted to determine whether a request for Interconnection to the ISO Controlled Grid would require new transmission additions, upgrades, or other mitigation measures.

3.823.97. System Impact Study Agreement. An agreement between a Participating TO and an entity that has requested Interconnection to the Participating TO’s transmission system pursuant to which the entity requesting Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a System Impact Study.

3.833.98. TO Tariff. This Transmission Owner Tariff, as it may be amended or superseded.

3.843.99. [Reserved].

PDF page 223

3.853.100. [Reserved].
3.863.101. Transmission Control Agreement (“TCA”). The agreement between the ISO and Participating TOs establishing the terms and conditions under which TOs will become Participating TOs and how the ISO and each Participating TO will discharge its respective duties and responsibilities, as may be modified from time to time.

3.873.102. Transmission Owner (“TO”). An entity owning transmission facilities or having firm contractual rights to use transmission facilities.

3.883.103. Transmission Revenue Balancing Account Adjustment (“TRBAA”). A mechanism established by the Participating TO which will ensure that all Transmission Revenue Credits and other credits specified in Section 6 and 8 of Appendix F, Schedule 3 of the ISO Tariff, and all amounts that a Cost Recovery Agreement requires to be credited through the TRBAA, flow through to ISO Tariff and TO Tariff transmission customers.

3.893.104. Transmission Revenue Credit. The proceeds received from the ISO (other than for the recovery of the Participating TO’s High Voltage and Low Voltage Transmission Revenue Requirement through the High Voltage and Low Voltage Transmission Access Charges) and charges imposed by the ISO that are received and paid by the Participating TO in its role as Participating TO, as defined in the ISO Tariff.

3.903.105. Transmission Revenue Requirement (“TRR’). The total annual authorized revenue requirement associated with transmission facilities and Entitlements turned over to the Operational Control of the ISO by the Participating TO. The costs of any transmission facility turned over to the Operational Control of the ISO shall be fully included in the Participating TO’s TRR. The TRR includes the costs of transmission facilities and Entitlements and deducts Transmission Revenue Credits and is shown in Appendix I.

3.913.106. Transmission System Rights (“TSRs”). TSRs represent DesertLink’s exclusive transmission entitlement on its share of the Project. DesertLink, as the holder of the TSRs, is entitled to all associated rights as are available under the ISO Tariff and Protocols. The use of this definition does not limit DesertLink from seeking any additional revenues or rights that are authorized by FERC due to a beneficial increase in the ISO controlled grid capacity resulting from the Project.

3.107. Transmission System Wholesale Load (“TSWL”) Interconnection. The interconnection of the transmission facilities of the Participating TO to the transmission facilities of a Transmission Owner, electric utility, or other entity eligible to request interconnection. A TSWL Interconnection does not include a Generator Interconnection or an ECLL Interconnection.

3.108. TSWL Interconnection Application. An application that requests a TSWL Interconnection to the ISO Controlled Grid, including any modifications to existing points of interconnection.

PDF page 224

3.923.109. Uncontrollable Force. Any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities or any other cause beyond the reasonable control of the ISO or Market Participant, as the case may be, which could not be avoided through the exercise of Good Utility Practice.

3.933.110. Utility Distribution Company (“UDC”). An entity that owns a Distribution System for the delivery of Energy to and from the ISO Controlled Grid, and/or that provides regulated retail electric service to End-Users.

3.943.111. Voltage Support. Services provided by Generating Units or other equipment such- as shunt capacitors, static vat compensators, or synchronous condensers that are required to maintain established grid voltage criteria. This service is required under normal or system emergency conditions.

3.953.112. Western Electricity Coordinating Council (“WECC”). The Western Electricity Coordinating Counsel or its successor.

3.963.113. Wheeling Access Charge. The charge assessed by the ISO that is paid by a Scheduling Coordinator for Wheeling in accordance with Section 26.1.4.1 of the ISO Tariff. Wheeling Access Charges shall not apply for Wheeling under a bundled non- economy Energy coordination agreement of a Participating TO executed prior to July 9, 1996. The Wheeling Access Charge consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge.

3.973.114. Wheeling Out. Except for Existing Rights exercised under an Existing Contract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a Generating Unit located within the ISO Controlled Grid to serve a Load located outside the transmission and Distribution System of a Participating TO.

3.983.115. Wheeling Through. Except for Existing Rights exercised under an Existing Contract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a resource located outside the ISO Controlled Grid to serve a Load located outside the transmission and Distribution System of a Participating TO.

3.993.116. Wheeling. Wheeling Out or Wheeling Through.

3.1003.117.
Wholesale Customer. A person wishing to purchase Energy and Ancillary
Services at a Bulk Supply Point or a Scheduling Point for resale.

PDF page 225

4. Eligibility for Service. Transmission service over a Participating TO’s system shall be provided only to Eligible Customers as defined byfor transmission service under the ISO Tariff. Any dispute as to whether a customeran entity that resells power is eligible for servicean interconnection under this TO Tariff shall be resolved by the FERC. Any dispute as to whether an End-User is eligible for an interconnection under this TO Tariff will be resolved by the Local Regulatory Authority.

PDF page 226

5. Access Charges and Transmission Rates. The applicable Access Charges are provided in the ISO Tariff.

5.1
Low Voltage Access Charge. The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff. As DesertLink is a Non-Load- Serving Participant TO, the ISO shall charge for and collect the Low Voltage Access Charge on DesertLink’s behalf pursuant to Section 26.1 and Appendix F, Schedule 3, Section 13 of the ISO Tariff from the Participating TO to whose facilities DesertLink’s Low Voltage Transmission Facilities are directly connected. The rate for DesertLink’s Low Voltage Access Charge Shall be DesertLink’s Low Voltage Transmission Revenue Requirement divided by the forecasted Gross Load of the Participating TO that is the Low Voltage Access Charge customer. The Low Voltage Access Charge customer shall pay the ISO a Low Voltage Access Charge equal to the product of DesertLink’s Low Voltage Access Charge rate and the actual Gross Load of the Participating TO that is the Low Voltage Access Charge Customer.

5.2
Wheeling Access Charge. The Wheeling Access Charge shall be determined in accordance with the ISO Tariff. The Wheeling Access Charge assessed by the ISO consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge. The High Voltage Wheeling Access Charge is set forth in the ISO Tariff.

5.3
Transmission Revenue Requirement. As set forth in the ISO Tariff, the Transmission Revenue Requirement for each Participating TO is used to develop the Access Charges set forth in the ISO Tariff and is used by the ISO to calculate the disbursement of Wheeling revenues among Participating TOs. Wheeling revenues are disbursed by the ISO to Participating TOs pursuant to Section 26.1.4.3 of the ISO Tariff. DesertLink’s TRR is set forth in Appendix I.

5.4
Transmission System Rights. DesertLink owns the TSRs with respect to the Project consistent with its ownership percentage of the Project and owns the TSRs with respect to any subsequent project it develops.

5.5
Transmission Revenue Balancing Account Adjustment (“TRBAA”). The
Participating TO shall maintain a Transmission Revenue Balancing Account with an annual TRBAA that will ensure that all Transmission Revenue Credits and adjustments for any over-or under-recovery of its annual Transmission Revenue Requirement, if any, specified in Sections 6, 8 and 13 of Appendix F, Schedule 3 of the ISO Tariff, flow through to transmission customers. The TRBAA used to calculate the High Voltage Revenue Requirement shall include other adjustments specified in Appendix F, Schedule 3, Sections 6, 8 and 13 of the ISO Tariff. The TRBAA shall also ensure that all amounts that a Cost Recovery Agreement requires to be credited to transmission customers through the TRBAA flow through to transmission customers.

PDF page 227

The TRBAA shall be equal to:
TRBAA = Cr + Cf + I
Where:

Cr =
The principal balance in the Transmission Revenue Balancing Account (“TRBA”) recorded in FERC Account No. 254 as of September 30 of the year prior to commencement of the January billing cycle. This balance represents the unamortized balance in the TRBA from the previous period and the difference in the amount of revenues or expenditures from Transmission Revenue Credits, amounts recorded in the TRBA under any Cost Recovery Agreement, and any over- or under-recovery of its annual Transmission Revenue Requirement and the amount of such revenues or expenditures that has been refunded to or collected from customers through operation of the TRBAA;

Cf =
The forecast of Transmission Revenue Credits, if any, for the following calendar year, plus any forecast credit that a Cost Recovery Agreement requires to be included in the TRBAA for the following calendar year;

I =
The interest balance for the TRBA, which shall be calculated using the interest rate pursuant to Section 35.19(a)35.19a of FERC’s regulations under the Federal Power Act (18 CFR Section 35.19(a)35.19a). Interest shall be calculated based on the average TRBA principal balance each month,

compounded quarterly; and. Amounts recorded in the TRBA under any Cost Recovery Agreement shall be included in the TRBA principal balance for purposes of this calculation. Nothing in this Section 5.5 requires the payment of interest between the Participating TO and a party to a Cost Recovery Agreement on amounts payable or refundable under that

agreement, which shall be governed solely by the terms of the Cost Recovery Agreement; and

The DesertLink TRBAA, calculated in accordance with the ISO Tariff and approved by the FERC, is stated in Appendix I.

PDF page 228

8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades. Unless DesertLink is the lead Participating TO with respect to an Interconnection, the provisions of Section 8 of this TO Tariff, and its subparts, shall have no application to the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink, and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern.

8.1
Participating TO Obligation to Interconnect. The Participating TO shall, at the request of a third party, interconnect its system to the wholesale generation or Load of such third party, or modify an existing wholesale Interconnection. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the FPA. The procedures for the Interconnections of Load to the ISO Controlled Grid shall be governed by this TO Tariff and the ISO Tariff. The procedures for Interconnection of wholesale generation to the ISO Controlled Grid shall be governed by the ISO Tariff.

8.1.1 Interconnection to Transmission System. InterconnectionAny interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, and ISO reliability criteria for the ISO Controlled Grid. The Participating TO will not accommodate the interconnection Interconnection if doing so would impair systems reliability, or would otherwise impair the ability of the Participating TO to honor its Encumbrances existing as of the time an entity submits its

Interconnection Applicationinterconnection application. The
Participating TO shall identify any such adverse effect on its Encumbrances in the System Impact Study performed pursuant to Section 10.7interconnection studies. To the extent the Participating TO determines that the Interconnectioninterconnection will have an adverse effect on Encumbrances, the party requesting

Interconnectioninterconnection shall mitigate such adverse effect.

8.1.1.1 Letter Agreement for Generator Interconnections. Pursuant to Section 12 of Appendix DD or KK of the ISO Tariff, prior to executing a Generator Interconnection Agreement, a party seeking a Generator Interconnection may, in order to advance the implementation of its Interconnection, request, and the Participating TO shall offer the party, a Letter Agreement that authorizes the Participating TO to begin engineering, design, and procurement of long lead-time items, or construction necessary for the establishment of the Generator Interconnection. However, the Participating TO shall not be obligated to offer a Letter Agreement if the party seeking Generator

Interconnection is in Dispute Resolution as a result of an allegation

PDF page 229

that the party seeking Interconnection has failed to meet any milestones or comply with any prerequisites specified in the ISO Tariff. The Letter Agreement is an optional procedure. The Letter Agreement shall provide for the party seeking Generator

Interconnection to pay the cost of all activities authorized by the party and to make advance payments or provide other satisfactory security for such costs.

Following a party seeking Interconnection’s request for a Letter Agreement, the Participating TO shall prepare and tender to the party seeking Interconnection a draft Letter Agreement, including draft exhibits that include the proposed scope of work, estimated costs, payments, financial security and milestones, as applicable. The party seeking Generator Interconnection shall provide written comments, or notification of no comments, to the draft exhibits within thirty (30) Calendar Days. The Participating TO and the party seeking Interconnection shall negotiate concerning any disputed provisions of the exhibits to the draft Letter Agreement for not more than ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Generator Interconnection. If the party seeking Interconnection determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the draft Letter Agreement and request submission of the unexecuted Letter Agreement with FERC or initiate dispute resolution procedures pursuant to Section 14 of this TO Tariff. If the party seeking Generator Interconnection requests termination of the negotiations, but within ninety (90) Calendar Days after the Participating TO tenders the draft Letter Agreement to the party seeking Interconnection, fails to request either the filing of the unexecuted Letter Agreement or initiate dispute resolution procedures, it shall be deemed to have withdrawn its request for a Letter Agreement and the Participating TO shall have no further obligation to enter into a Letter Agreement, unless an extension is mutually agreed to by the parties. The Participating TO shall provide to the party seeking Interconnection a final Letter Agreement within fifteen (15) Business Days after the completion of the negotiation process.

Following submission of the final Letter Agreement to the party seeking Generator Interconnection, the party shall either: (i) execute two originals of the tendered Letter Agreement and return them to the Participating TO; or (ii) request in writing that the Participating TO file with FERC a Letter Agreement in unexecuted form. As soon as practicable, but not later than ten (10) Business Days after receiving either the two executed originals of the tendered Letter Agreement or the request to file an unexecuted Letter Agreement, the Participating TO shall file the Letter Agreement with FERC, together with its

PDF page 230

explanation of any matters as to which the party seeking Interconnection and the Participating TO disagree and support for the costs that the Participating TO proposes to charge to the party seeking Generator Interconnection under the Letter Agreement. An unexecuted Letter Agreement should contain terms and conditions deemed appropriate by the Participating TO for the Generator Interconnection request.

If the party seeking Interconnection executes the final Letter Agreement, the Participating TO and the party seeking Generator Interconnection shall perform their respective obligations in accordance with the terms of the Letter Agreement, subject to modification by FERC. Upon submission of an unexecuted Letter Agreement, the party seeking Generator Interconnection and the Participating TO shall promptly comply with the unexecuted Letter Agreement, subject to modification by FERC.

8.1.2 Costs Associated with Interconnection. Each party requesting Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities and, if applicable, any Reliability Upgrades required to provide the requested Interconnection. In addition, such party shall implement all existing operating procedures necessary to safely and reliability interconnect such party’s generation or wholesale load to the facilities of the Participating TO and to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in the ISO Tariff for transmission expansions or upgrades.

8.1.3 Interconnection Agreement. Interconnection Agreements shall be tendered, executed, and filed as provided in Sections 10.9 and 10A.3. 8.1.3 Interconnection Agreement. Pursuant to Section 10.4, 10.7.1, or 10.9.1, a party requesting an Interconnection shall request in writing that the Participating TO tender to such part an Interconnection Agreement that will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement will include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, and construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, any Delivery Upgrades, if applicable, and for any other mitigation measures. For an Interconnection request to remain a Completed Interconnection Application, the party requesting the Interconnection shall execute the Interconnection Agreement and return it to the Participating TO within thirty (30) Business Days of receipt.

PDF page 231

Alternatively, if an Eligible Customer requesting the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the

requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted interconnection Agreement or commence construction of the Interconnection facilities or incur other costs under the Interconnection Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed Interconnection Agreement shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by any System Impact Study Agreement or Facilities Study Agreement. To maintain its queue position, the applicant must timely comply with the Interconnection requirements of Section 5.76 of the ISO Tariff and Sections 8.1 and 10 of this TO Tariff. If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application or because its queue position has been modified pursuant to the queuing provisions in Section 25 of the ISO Tariff.

8.1.4 Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Reliability Upgrades that it is obligated to construct pursuant to this TO Tariff and Section 24 of the ISO Tariff. The Participating TO’s obligation to build will be subject to: (1) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (2) the presence of a cost recovery mechanism with cost responsibility assigned to accordance with the ISO Tariff or applicable FERC precedent; and

(3) a signed Interconnection Agreement or a signed Expedited
Interconnection Agreement, or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection

Agreement.
8.1.5 Energization. The Participating TO shall not be obligated to energize, nor shall the applicant or wholesale load be entitled to have its interconnection to the ISO Controlled Grid energized, unless and until

PDF page 232

an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 8.1.3, and become effective and such applicant or wholesale load has demonstrated to the ISO’s reasonable satisfaction that it has complied with all of the requirements of the ISO Tariff and the requirements of this TO Tariff.

8.1.6 Coordination with ISO on Interconnection Requests. The
Participating TO shall coordinate with the ISO, pursuant to the provisions of the TCA, in developing interconnection standards and guidelines for processing interconnection request under this TO Tariff.

8.2
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to: (1) perform System Impact or Facility Studies where the Project Sponsor or the ISO agrees to pay the study cost and specifies the project objectives to be achieved, and (2) build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations under Section 24 of the ISO Tariff’ and this TO Tariff.

8.2.1 Obligation to Construct. A Participating TO shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.2.1 hereof have been satisfied.

8.3
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the ISO, (including the ISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated planning processes as to the need for or construction of a facility, the need for full cost recovery, end the allocation of costs.

PDF page 233

9. ExpansionParticipating TO Process for Construction or Expansion of Transmission Facilities. Unless DesertLink is the lead Participating TO with respect to a required system expansion, the provisions of Section 9 of this TO Tariff, and its subparts, shall have no application to the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern.

9.1
Applicability and Determination of Facilities. A Participating TO shall perform a Facilities Study in accordance with the Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 of the ISO Tariff and this TO Tariff (other than if the obligation to expand or construct is pursuant to Section 10 or 10A of this TO Tariff or the ISO’s generator interconnection procedures); (2) a Market Participant agrees to pay the costs of the Facilities Study and specifies the project objectives to be achieved in terms of increase capacity or reduce congestion; or

 (3) the Participating TO is required to perform a Facilities Study pursuant to the ISO Tariff.

9.1.1 Payment of Facilities Study’s Cost.
9.1.1.1 Market Participant to Pay for Facilities Study. Where a Market Participant requests a Facilities Study and the need for the transmission addition or upgrade has not been established in accordance with the procedures established herein and the ISO

Tariff, the Market Participant shall pay the cost of the Facilities Study.

9.1.1.2 Project Sponsor or Project Proponent to Pay for Facility Study. Where the facilities to be added or upgraded have been

determined to be needed in accordance with the procedures
established herein, the Project Sponsor, Project Proponent, or the ISO requesting the study shall pay in advance the reasonable

cost of the Facilities Study. When the Participating TO is the Project Sponsor in accordance with the ISO Tariff, the costs of the Facilities Study shall be recovered through its Access

Charges and transmission rates.

9.1.1.3 Principal Beneficiaries to Pay for Facilities Study. Where the facilities to be added or upgraded have been determined to be

needed and the principal beneficiaries have been identified by the ISO or ISO ADR Procedures in accordance with the ISO Tariff

the Project Sponsor and the identified principal beneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as may be agreed, or, failing agreement, as

determined in accordance with the ISO ADR Procedures.

PDF page 234

9.1.2 Payment Procedure. Where a Facilities Study is being conducted pursuant to this TO TariffSection 9, the Participating TO shall, within thirty days of the receipt of all reasonably required information, tender to the Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal beneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Facilities Study. If the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Facilities Study Agreement, they shall execute the Facilities Study Agreement and return it to the Participating TO within ten Business Days. Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Facilities Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures.

9.1.3 Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or alternative request to proceed as provided for in Section 9.1.2, a copy of which has been provided to the ISO by the party requesting the Facilities Study, the Participating TO will use due diligence to complete the required Facilities Study within a sixty (60) day period. If the Participating TO is unable to complete the Facilities Study in the allotted time period, the Participating TO shall notify the Market Participant and provide an estimate of the time needed to reach a final determination along with an explanation of the reasons that additional time is required to complete the study. If additional time is required, the Participating TO will use best efforts to complete the study within 10 months, provided adequate information is provided by all the parties.

9.2
Obligation to Build.
9.2.1 Due Diligence to Construct. Subject to Section 9.3.3 of this TO Tariff, the Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the ISO Tariff and this TO Tariff. Alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to

PDF page 235

abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement or alternatively, if a Market Participant requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement.

Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement, commence construction of the additions or upgrades or incur other costs under the Participation Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Participation Agreement has been issued by the applicable court or regulatory authority. The Participating TO’s obligation to build will be subject to:

1) its ability, after making a good faith effort, to obtain the necessary approvals and property rights under applicable federal, state, and local laws; 2) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the ISO Tariff or this TO Tariff; and 3) a signed Participation Agreement. The Participating TO will not construct or expand its existing or planned transmission system, if doing so would impair system reliability as determined through systems analysis based on the Applicable Reliability Criteria. 9.2.2 Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify: (1) the Project Sponsor with regard to facilities determined to be needed; (2) the Parties to the Participation Agreement with regard to facilities determined to be needed pursuant to the ISO Tariff where principal beneficiaries were identified; and (3) the ISO. In such circumstances, the Participating TO shall, within thirty days of notifying such Project Sponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Participation Agreement, and the ISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be,

PDF page 236

studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the ParticipatingTO that is circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives.

TO that is reasonably needed to evaluate the alternatives.

9.2.2.1 Alternatives to the Original Facility Additions. If the review process of Section 9.2.2 determines that one or more alternatives exist to the originally planned construction project, the Participating TO shall present such alternatives for consideration to the Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be. If upon review of any alternatives, such Project Sponsor, the ISO, or Parties to the Participation Agreement wish to evaluate or to proceed with one of the alternative additions or upgrades, such Project Sponsor, the ISO, or Parties to the Participation Agreement may request that the Participating TO prepare a revised Facility Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO Tariff. In the event the Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Participation Agreement or the ISO disagree, the dispute shall be resolved pursuant to the ISO ADR Procedure.

9.2.2.2 Refund Obligation for Unfinished Facility Additions. If the Participating TO and the Project Sponsor, the ISO, or Parties to the Participation Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Regulation 35.1935.19a(a)(2)(iii). However, the Project Sponsor and any identified principal beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.

9.3
Provisions Relating To Transmission Construction On the System Of Other TOs.

9.3.1 Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any

engineering, permitting, and construction of transmission or distribution facilities on the system(s) of any other entity or for

PDF page 237

obtaining any regulatory approval for such facilities. The Participating TO will undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice.

9.3.2 Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the ISO Tariff require additions or upgradeson other systems, to the extent consistent with Section 9.3.3 of this TO Tariff, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the ISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or resume construction of the new facilities. Within forty Business Days of receiving written notification by the Participating TO of its intent to defer construction pursuant to this section, such Project Sponsor, Parties to the Participation Agreement, or the ISO may challenge the decision in accordance with the ISO ADR Procedure.

PDF page 238

10. TSWL Interconnection Process. Unless DesertLink is the lead Participating TO with respect to a requested interconnection, the provisions of Section 10 of this TO Tariff, and its subparts, shall have no application to the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink and the corresponding provisions of the lead Participating TO’s TO Tariff shall govern. All requests for interconnectionTSWL Interconnection with the Project or any other High Voltage Transmission Facilities, Low Voltage Transmission Facilities, or Entitlements turned over to the ISO’s operational control by DesertLink shall be directed to the lead Participating TO, with notice of the request provided to DesertLink.

10.1
Applicability. All requests for TSWL Interconnection directly to the ISO Controlled Grid from parties eligible to request such Interconnection consistent with Section 210(a) of the FPA shall be processed pursuant to the provisions of this Section 10. All requests for Interconnection of wholesale generation directly to the ISO Controlled Grid shall be processed pursuant to the provisions of the ISO Tariff. Requests for interconnection submitted by an ECLL on behalf of Large Load Customers shall be processed pursuant to Section 10A of this TO Tariff.

10.2
TSWL Interconnection Applications. Except as provided in Section 10.2.1, a partyAn applicant requesting TSWL Interconnection shall submit a written TSWL Interconnection Application which provides the information required in Section 10.3detailed below to the Participating TO and shall send a copy of the application to the ISO. The Participating TO shall timestamp the application to establish study priority.

10.3
Interconnection Application. An Interconnection Application shall provide all the information listed in 18 CFR § 2.20, including, but not limited to, the following:

(i) the identity, address, telephone
number, and facsimile numberemail of the entityapplicant requesting TSWL Interconnection;

(ii) the Interconnection point(s) to the ISO Controlled Grid contemplated by the applicant;

(iii) the resultant (or new) maximum amount of TSWL Interconnection capacity contemplated by the applicant;

(iv) the proposed date for energizing the TSWL Interconnection and the term of the Interconnectioninterconnection service, and

(v) such other information as the Participating TO reasonably required to process the application.

In addition to the information specified above, the following information may also be provided in order to properly evaluate system conditions:

(vi) If the applicant is a wholesale load, the electrical location of the source of the power (if known) to be transmitted pursuant to applicant’s request for Interconnection. If the source of the power is not known, a system purchase

PDF page 239

will be assumed. If the location of the load is not known, a system sale will be assumed; and, in addition, if an applicant proposes to perform or cause a third party to perform any required System Impact Study or any required Facilities Study, it shall so indicate in its Interconnection Application.

The results of any study or studies performed by an applicant must be approved by both the ISO and the Participating TO. Within tenWithin ten (10) Business Days after receipt of ana TSWL Interconnection Application, the Participating TO and the ISO if applicable shall determine whether the application is complete (“Completed TSWL Interconnection AgreementApplication”). Whenever possible, the participating TO will attempt to remedy deficiencies in the TSWL Interconnection Application through informal communications with the applicant. If such efforts are unsuccessful, the Participating TO shall return the Interconnection Application to the applicant.

The Participating TO will treat the information in the TSWL Interconnection AgreementApplication, including the applicant’s identity, as confidential at the request of the applicant except to the extent that disclosure of the information is required by this TO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations.

10.3.110.2.1
Amendment to Completed TSWL Interconnection
Application. An applicant shall only be limited to amending its Completed TSWL Interconnection Application once. Such amendment shall occur on or before ten (10) Business Days following the date the Participating TO tenders any Facilities Study Agreement. Specifically, an applicant may submit an amendment to its Completed TSWL

Interconnection Application to reflect a revised configuration for its New Facility. The amended Completed TSWL Interconnection Application shall be treated in accordance with Section 25 of the ISO Tariff and Section 10.5 of this TO Tariff; the applicant’s Completed TSWL

Interconnection Application shall be deemed withdrawn; and the
applicant shall maintain its existing queue position, if (a) the amended Completed TSWL Interconnection Application is received by the

Participating TO within ten (10) Business Days of the Participating TO’s tender of a Facilities Study Agreement; and (b) the applicant has not submitted a previous amendment to the Completed TSWL

Interconnection Application. In the event an applicant amends its Completed TSWL Interconnection Application, it will be responsible for any additional study costs that result from that amendment, including costs associated with revisions to studies for other applicants holding later queue positions.

10.410.3 Review of Completed TSWL Interconnection Application. After receiving

PDF page 240

a Completed TSWL Interconnection Application, the Participating TO and the ISO, if applicable, will determine on a non-discriminatory basis whether a System Impact Study is required. Whenever the Participating TO, and the ISO, if applicable, determines that a System impact Study is not required and that neither Reliability Upgrades nor changes in existing operating procedures are required, the Participating TO shall notify the applicant within fifteen (15) Business Days of the Completed Application Date. If the TSWL Interconnection can be accommodated without any Direct Assignment Facilities, then within thirty (30) Business Days of such notice from the Participating TO, the applicant shall request the Participating TO to tender to the applicant an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provideprovided in this Section 8.1.310. If the Participating TO determines upon review of the Completed TSWL Interconnection Application, that Direct Assignment Facilities are required, the Participating TO shall tender to the applicant a Facilities Study Agreement within twenty (20) Business Days of the Completed Application Date and continue the Interconnection process pursuant to Section 10.8.

10.510.4 Notice of Need for System Impact Study. If the Participating TO, and the ISO, if applicable, determines that a System Impact Study is necessary to accommodate the requested Interconnection, the Participating TO shall so inform the applicant as soon as practicable. In such cases, the Participating TO shall within twenty (20) Business Days of receipt of a Completed TSWL Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO, the estimated time required to complete it, and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of performing the required System Impact Study. A description of the Participating TO’s transmission assessment practices for completing a System Impact Study shall be provided in the Participating TO’s FERC Form 715. Alternatively, if the applicant will perform the System Impact Study, the Participating TO shall within twenty (20) Business Days of receipt of a Completed TSWL Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of reviewing the required System Impact Study.

For ana TSWL Interconnection request to remain a Completed TSWL
Interconnection Application, the applicant shall execute the System Impact Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated cost of performing the System Impact Study or reviewing the applicant’s System Impact Study.

PDF page 241

Alternatively, if the applicant request the Participating TO to proceed with the System Impact Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the System Impact Study provided that such request is accompanied by payment of the reasonable estimated cost of the System Impact Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. If the applicant elects not to execute a System Impact Study Agreement, and does not request that the Participating TO proceed with the System Impact Study or review thereof, its application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application.

10.6
10.5
System Impact Study Cost Reimbursement and Agreement.
10.6.110.5.1
Cost Reimbursement. The System Impact Study
Agreement shall clearly specify the charge, based on the Participating TO’s estimate of the cost and time for completion of the System Impact Study. The charge shall not exceed the reasonable actual cost of the study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any

modifications to existing planning studies that are reasonably necessary to evaluate the impact on the applicant’s request.

10.6.2 Multiple Parties. If multiple parties request Interconnection at the same location, the participating TO may conduct a single System Impact Study. The costs of that study shall be pro-rated among the parties requesting Interconnection.

10.710.6 System Impact Study Procedures. Upon receipt of an executed System Impact Study Agreement or initiation of the ISO ADR Procedures and receipt of payment for estimated study costs, the Participating TO will use due diligence to either (a) complete the required System Impact Study within a sixty (60) calendar day period or (b) complete its review of an applicant’s System Impact Study within thirty (30) calendar days of its receipt of the completed study. The System Impact Study will identify whether any Direct Assignment Facilities or Reliability Upgrades are necessary to deliver a New Facility’s full output over the ISO Controlled Grid, or any transmission additions or upgrades are necessary to serve a wholesale load. The System Impact Study will also identify any adverse impact on Encumbrances existing as of the applicant’s Completed Application Date. In the event that the Participating TO is unable to complete the required System Impact Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why

PDF page 242

additional time is required to complete the required studies. A copy of the completed System Impact Study and related work papers shall be made available to the applicant and the ISO. The Participating TO shall notify the applicant and the ISO immediately upon completion of the System Impact Study.

10.7.110.6.1
Procedures Upon Completion of System Impact Study.
Within fifteen (15) Business Days of completion of the System Impact Study or review and approval of an applicant’s System Impact Study, the Participating TO shall notify the applicant whether the transmission system will be adequate to accommodate all of a request for

Interconnection. If no costs are likely to be incurred for any Direct Assignment Facilities, any Reliability Upgrades, or implementing any operating procedures, then within thirty (30) Business Days of receipt of written approval of the applicant’s System Impact Study from the Participating TO and the ISO the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.310.9. If costs are likely to be incurred to accommodate a request for Interconnection, the Participating TO shall tender to the applicant a Facilities Study Agreement pursuant to Section 10.8.

10.810.7 Notice of Need for Facilities Study. If a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid are needed to satisfy an applicant’s request for interconnection, the Participating TO shall, within fifteen

(15) Business Days of the date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study by the Participating TO, tender to the applicant a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete the required study; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of performing the required Facilities Study. Alternatively, if the applicant will perform the Facilities Study, the Participating TO shall within fifteen (15) Business Days of the completion date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study, tender a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete the required review; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of reviewing the required Facilities study. For an Interconnection request to remain a Completed TSWL Interconnection Application, the applicant shall execute the Facility StudiesFacilities Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the

PDF page 243

reasonable estimated costs of performing the Facilities Study or reviewing the applicant’s Facilities Study. Alternatively, if the applicant request the Participating TO to proceed with the Facilities Study toor review thereof and commits to abide by terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study provided that such request is accompanied by payment for the reasonable estimated cost of the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO ADR Procedures. If the applicant elects not to execute a Facilities Study Agreement and does not request that the Participating TO proceed with the Facilities Study or review thereof, its application shall be deemed withdrawn and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by the System Impact Study Agreement.

10.910.8 Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or initiation of the ISO ADR Procedures and receipt of payment for the estimated study costs, the Participating TO will use due diligence to either

(a) complete the required Facilities Study within a sixty (60) calendar day period or (b) complete its review of an applicant’s Facilities Study within thirty

(30) calendar days of its receipt of the Completed Study. In the event that Participating TO is unable to complete the required Facilities Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed Facilities Study shall be made available to the applicant.

10.9.1 Execution10.8.1 Tender of Interconnection Agreement. Within thirty
(30) Business Days of receipt of the completed Facilities Study
performed by the Participating TO or receipt of written approval of the applicant’s Facilities Study from the Participating TO, the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 8.1.310.9.

10.9
Interconnection Agreement.
Pursuant to Section 10.3, 10.6.1, or 10.8.1, a
party requesting Interconnection shall request in writing that the Participating TO tender to such party an Interconnection Agreement that will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement shall include, without limitation, cost responsibilities and payment provisions for any engineering, equipment, construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, any Reliability Upgrades, and for any other mitigation measures. The Interconnection Agreement will set forth a payment

PDF page 244

schedule that enables the Participating TO to recover its costs.

For a TSWL Interconnection request to remain a Completed TSWL
Interconnection Application, the applicant requesting the Interconnection or the entity with whom the Participating TO will interconnect for the Interconnection shall execute the Interconnection Agreement and return it to the Participating TO within thirty (30) Business Days of receipt. Alternatively, if an applicant requesting the TSWL Interconnection or the entity with whom the Participating TO will interconnect for the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is a eligible for a TSWL Interconnection, the Participating TO shall not be obligated to file an unexecuted Interconnection Agreement or commence construction of any facilities or incur other costs under the Interconnection Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority. If the applicant or the entity with whom the Participating TO will interconnect for the Interconnection elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed TSWL Interconnection Application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by any System Impact Study Agreement or Facilities Study Agreement.

Where a TSWL Interconnection will serve one or more Large Loads, as a condition to the Participating TO’s design, procurement, construction, or operation of any Large Load-Driven Upgrades (as defined in the pro forma Large Load Cost Recovery Agreement set forth in Appendix V) associated with the TSWL Interconnection, the applicant or Eligible Customer shall also, within the same period and subject to the same consequences as the Interconnection Agreement, execute and maintain a Cost Recovery Agreement substantially in the form set forth in Appendix V to this TO Tariff, or, if the applicant or Eligible Customer requests that the Cost Recovery Agreement be filed unexecuted with FERC, comply with that agreement as made effective by FERC, in each case as applicable to the requested TSWL Interconnection. Disputes arising under a Cost Recovery Agreement shall be resolved under the dispute resolution provisions of that agreement.

10.10 Partial Interim Service. If the Participating TO determines that there will not be adequate transmission capability to satisfy the full amount requested in a Completed TSWL Interconnection Application, the Participating TO nonetheless shall be obligated to offer and provide the portion of the requested TSWL

PDF page 245

Interconnection that can be accommodated without any additional Direct Assignments Facilities or Reliability Upgrades. However, the Participating TO shall not be obligated to provide the incremental amount of requested TSWL Interconnection that requires such additional facilities or upgrades until such facilities or upgrades have been placed in service.

10.11 Expedited Interconnection Procedures. In lieu of the procedures set forth above, the applicant shall have the option to expedite the processing of its Completed TSWL Interconnection Application. In order to exercise this option, the applicant shall submit in writing a Request for Expedited Interconnection Procedures to the Participating TO within ten (10) Business Days after receiving a copy of the System Impact Study for the proposed TSWL Interconnection. Within ten (10) Business Days after receiving a Request for Expedited Procedures, the Participating TO shall tender an Expedited Interconnection Agreement that requires the applicant to compensate the Participating TO for all costs reasonably incurred pursuant to the terms of this ToTO Tariff for processing the Completed TSWL Interconnection Application and providing the requested Interconnection. While the Participating TO agrees to provide the applicant with its best estimate of the costs of any needed Direct Assignment Facilities and, if applicable, Reliability Upgrades, and such other charges that may be incurred, unless otherwise agreed by the parties, such estimate shall not be binding and the applicant must agree in writing to compensate the Participating TO for all actual TSWL Interconnection costs reasonably incurred pursuant to the provisions of this TO Tariff. The applicant shall execute and return such Expedited ServiceInterconnection Agreement within ten (10) Business Days of its receipt or the applicant’s request for Interconnection will cease to be a Completed TSWL Interconnection Application and will be deemed terminated and withdrawn,. In that event, the applicant shall reimburse the Participating TO for all costs reasonably incurred in processing the application not covered by the terms of the System Impact Study Agreement.

PDF page 246

10A. Interconnection Process for ECLL Interconnections. All requests for ECLL Interconnection shall be directed to the Participating TO.

10A.1
Applicability. An ECLL Interconnection must be requested in order to connect the facilities of the Participating TO to the facilities of an ECLL that has received a request to connect and provide retail transmission service to a Large Load Customer.

10A.2 ECLL Application and Application Fee

10A.2.1
Application Contents. An ECLL requesting an ECLL Interconnection shall submit an ECLL Interconnection Application in the form of Attachment 1 to Appendix VI, which provides the following required information, and shall send a copy of the application to the ISO. The ECLL Interconnection Application and all supporting documentation shall be submitted electronically to the Participating TO in the manner posted on the Participating TO’s public website.

(a) the identity, address, telephone number, and email of the ECLL;
(b) the Point of Withdrawal;
(c) a proposed Large Load Customer load ramp schedule identifying anticipated load additions over time and the Large Load Customer’s maximum load;

(d) a site plan;
(e) documentation demonstrating that the Large Load Customer has Site Control;

(f) documentation demonstrating that the Large Load Customer has local permits and regulatory approvals for development of its Large Load;

(g) a single-line electrical diagram;
(h) the electrical location of the source of the power (if known) to be transmitted pursuant to the ECLL’s request for ECLL Interconnection. If the source of the power is not known, a system purchase will be assumed;

(i) disclosure of ECLL interconnection requests in the ECLL’s footprint that are for the same Large Load Customer or any of its affiliate(s);

(j) a completed technical data form in the form of Appendix A to Attachment 1 to Appendix VI;

(k) if the Large Load Customer will be a Co-Located Large Load, information concerning the relevant Generating Facility must be provided by the ECLL. Such information may be either: (1) if the Generating Facility has not signed a generator interconnection agreement, the identifying queue number of the Generating Facility; or (2) if the Generating Facility has signed a generator interconnection agreement, information that will allow the Participating TO to identify such agreement; and

(l) the proposed date for energizing the ECLL Interconnection and the proposed term of the ECLL Interconnection service.

PDF page 247

10A.2.2
Participating TO Review of ECLL Interconnection Application. Within ten (10) Business Days after receipt of an ECLL Interconnection Application, the Participating TO shall determine whether the application is complete (“Completed ECLL Interconnection Application”). Wherever possible, the Participating TO will attempt to remedy deficiencies in the ECLL Interconnection Application through informal communications with the ECLL. If such efforts are unsuccessful, the Participating TO shall return the ECLL Interconnection Application to the ECLL.

The Participating TO will treat the information provided in the ECLL Interconnection Application, including the ECLL’s and Large Load Customer’s identity, as confidential at the request of the ECLL except to the extent that disclosure of this information is required by this TO Tariff or the ISO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations.

10A.3 Study Process and ECLL Interconnection Agreement. ECLL Interconnection Applications shall be processed, and ECLL Interconnection Agreements shall be tendered, executed, and filed, in accordance with the Large Load Interconnection Procedures set forth in Appendix VI. Disputes arising under a Cost Recovery Agreement shall be resolved under the dispute resolution provisions of that agreement.

10A.4 Interim Service

10A.4.1
Interim Firm Interconnection Service and Flexible Interim Load Interconnection (FILI) Service. If the ECLL has requested Interim Firm Interconnection Service and/or FILI Service, the Participating TO shall perform an analysis and report the extent to which the requested interim services can be provided, prior to such time that all ECLL Interconnection Facilities are in service and the Large Load Customer is authorized to withdraw Energy. However, the Participating TO shall not be obligated to provide any amount of Firm Interconnection Service requested until necessary facilities have been placed in service. FILI Service will be available for all remaining Load that cannot receive Interim Firm Interconnection Service, if the Large Load Customer has the ability to reduce the load at a specified point of interconnection according to the timelines and protocols set forth in an executed and effective FILI Service Agreement, until the ECLL Interconnection Facilities are in service. As ECLL Interconnection Facilities are placed into service and transmission interconnection capability is increased, available quantities of Firm Interconnection Service and FILI Service will be updated and reflected in the applicable FILI Service Agreement.

PDF page 248

If the Large Load Customer seeks FILI Service, the ECLL will ensure that the Large Load Customer signs a FILI Service Agreement developed by the Participating TO, or asks for the agreement to be filed unexecuted.

10A.4.2
Study Process for Interim Service and Determination of Availability of Interim Firm Interconnection Service and FILI Service. The Participating TO shall perform a FILI Study in accordance with Section 4.6.2 of Appendix VI to determine the maximum amount of any Interim Firm Interconnection Service, if any, and FILI Service, if any, that may be provided based on the anticipated availability of transmission capacity once the Large Load Customer is permitted to withdraw energy by the ECLL. The Participating TO shall update this analysis under the terms of the FILI Service Agreement, at least annually.

The actual amount of any FILI Service to be provided during any operating period shall be determined by the Participating TO through operational assessments and analysis conducted closer to real-time operating conditions. Accordingly, the maximum FILI Service established in the annual analysis does not guarantee the availability of such service under actual system conditions.

10A.4.3
Conditions Related to FILI Service

10A.4.3.1 FILI Service Reliability Requirements. The FILI Service Agreement will identify what ECLL Interconnection Facilities must be installed, the necessary protection and control systems and any other equipment necessary to be installed, and operating limitations to allow the Large Load Customer to withdraw energy (“FILI Service Reliability Requirements”). FILI Service shall not commence until the Participating TO and ECLL have completed installation and commissioning of all equipment specified under the FILI Service Agreement.

10A.4.3.2 Curtailment of FILI Service. FILI Service is subject to curtailment at all times, unless the Participating TO’s right to curtail is expressly conditioned or otherwise limited in an executed and effective FILI Service Agreement. A Large Load Customer receiving FILI Service shall be subject to curtailment prior to any curtailment of customers receiving Firm Interconnection Service. The Participating TO and ISO may curtail FILI Service as necessary to maintain the reliable operation of the ISO Controlled Grid, including during normal operating conditions.

10A.4.3.3 Exceedance of Authorized FILI Service. An ECLL shall ensure that the operating instructions issued by the Participating TO pursuant to a FILI Service Agreement are not exceeded at the relevant Point of Withdrawal. The Participating TO shall have the right to disconnect service to the Large Load Customer in the event that energy withdrawals violate the terms of the

PDF page 249

FILI Service Agreement. The Participating TO shall follow Good Utility Practice in carrying out any such disconnection and subsequent reconnection when the conditions for such reconnection set forth in the FILI Service Agreement have been met. Nothing in this TO Tariff prevents the ISO from applying any financial penalties applicable to Large Load Customers. 10A.5 Co-Located Large Load. The interconnection processes applicable to a Co-Located Large Load shall be determined based on whether the Generating Facility is a (1) non-exporting Generating Facility interconnected in accordance with the generator interconnection rules of the applicable ECLL, as approved by its Local Regulatory Authority (including, for a UDC subject to the jurisdiction of the CPUC, CPUC Electric Rule 21); or (2) an exporting Generating Facility subject to the applicable ISO generator interconnection procedures and requirements. The ECLL for a Co- Located Large Load connecting to facilities of an exporting Generating Facility will be subject to this Section 10A.

For a Co-Located Large Load interconnected to the facilities of an exporting Generating Facility, the ISO will be a party to a pro forma agreement that bridges the pro forma Large Generator Interconnection Agreement (LGIA) with the ECLL Interconnection Agreement, or will negotiate a non-conforming LGIA to account for certain details of the Co-Located Large Load interconnection on an individual basis. The Generating Facility developer will also execute an ISO pro forma Participating Generator Agreement for the Generating Facility, but not a Participating Load Agreement for the Co-Located Large Load.

10A.6 Large Load Cost Recovery Agreement. As a condition to the Transmission Owner’s design, procurement, construction, or operation of a Large Load-Driven Upgrade, the Eligible Customer shall execute and maintain a Large Load Cost Recovery Agreement substantially in the form set forth in Appendix V to this TO Tariff, as applicable to the requested service and associated Large Load Facility.

PDF page 250

13. Creditworthiness
13.1
UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low Voltage Transmission Facilities. For the purpose of determining the ability of a UDC, MSS, and Scheduling Coordinator to meet its obligations related to service using the Participating TO’s Low Voltage Transmission Facilities hereunder, where the Participating TO is collecting the Low Voltage Access Charge directly from each UDC, MSS and Scheduling Coordinator, the Participating TO may require reasonable credit review procedures for the UDC, MSS, or Scheduling Coordinator. This review shall be made in accordance with standard commercial practices. In addition, the Participating TO may require the UDC, MSS, or Scheduling Coordinator to provide and maintain in effect during the term of the service, an unconditional and irrevocable letter of credit as security to meet its responsibilities and obligations under this TO Tariff, or an alternative form of security proposed by the UDC, MSS, or Scheduling Coordinator and acceptable to the Participating TO, and consistent with commercial practices established by the Uniform Commercial Code, that protect the Participating TO against the risk of non-payment.

13.2
End-Users. Creditworthiness and security rules applicable to End-Users shall be pursuant to the then-current rules of the applicable Local Regulatory Authority and any agreement under this TO Tariff to which the End-User is a party.

PDF page 251

14. Disputes. Except as limited below, as provided in Sections 10.9 and 10A.3, or as otherwise limited by law, the ISO ADR procedures shall apply to all disputes between parties which arise under this TO Tariff or under or in respect of the proposed terms and conditions of a Facilities Study Agreement, System Impact Study Agreement or Expedited

ServiceInterconnection Agreement. The ISO ADR Procedures set forth in Section 13 of the ISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.

PDF page 252

16. Miscellaneous.
16.1
Notices. Any notice, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person or electronically via email, (ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return electronic facsimile if sent by facsimile, or (iv) upon Party at the address set forth in Appendix IVII. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix IVII to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff or in connection with operation of facilities shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.

16.2
Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver.

16.3
Confidentiality.

16.3.1 Maintaining Confidentiality If Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the documents, data, and information provided to it by any other Market Participant that such Market Participant may designate as confidential, provided, however, that the information will not be held confidential by the Participating TO if (1) the Participating TO or Market

Participant is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory requirements, or (2) the information becomes available to the public on a non-confidential basis (other than from the Participating TO).

16.3.2 Disclosure of Confidential Information. Notwithstanding anything in this Section 16.3 to the contrary, if the Participating TO or any Market Participant is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to this Section 16.3, the Participating TO or Market Participant may disclose such information; provided, however, that as soon as such Participating TO or Market Participant learns of the disclosure requirement and prior to making such disclosure, such Participating TO or Market Participant shall notify the affected Participating TO or Market Participants of the

PDF page 253

requirement and the terms thereof. The affected Participating TO or Market Participants may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Participating TO or Market Participant shall cooperate with such affected Participating TO or Market Participants to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Participating TO or Market Participant shall cooperate with the affected Participating TO or Market Participants to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure.

16.4
TO Tariff Supersedes Existing Tariffs. This TO Tariff, together with the ISO Tariff and wholesale distribution access tariff if any, supersedes any pre- existing open access transmission tariff of the Participating TO.

16.5
Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.

16.6
Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Participating TO and Market Participants shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.

16.7
Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of any entity shall be preserved until satisfied.

16.8
Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.

16.9
Appendices Incorporated. The several appendices to this TO Tariff, as may be revised from time to time, are attached to this TO Tariff and are incorporated by reference as if fully set forth herein.

16.10
Conflict With ISO Tariff. If a Market Participant identifies a conflict between

PDF page 254

the TO Tariff and the ISO Tariff, the Participating TO and the Market Participant shall make good-faith efforts to resolve the conflict. If the Participating TO and Market Participant are unable to informally resolve that conflict, the Participating TO and Market Participant may use the ISO ADR Procedures to resolve it as set forth in Section 14 of this Tariff.

16.11
Conflicting Operating Instructions. In the event a Market Participant receives conflicting operating instructions from the ISO and one or more Participating TO(s), if human safety would not knowingly be neither jeopardized nor electric facilities subject to damage while the Market Participant seeks to reconcile the conflict with the appropriate ISO and Participating TO employees before acting, the Market Participant should attempt a reconciliation. Otherwise, the Market Participant shall adhere to ISO Tariff Section 4.2 and follow the ISO’s instructions. In no event shall a Market Participant be required to follow operating instructions from the ISO if following those instructions would knowingly jeopardize human safety.

PDF page 255

Projected ATRR
For the 12 months ended
12/31/__
Formula Rate Index
DesertLink, LLC
Table of Contents
Formula Rate Template
Attachments:
Attachment No
Worksheet Name
1
Project Revenue Requirement Worksheet
1a
Project Plant Detail Worksheet
2
Incentive Return
3
Formula Rate True-Up
4
Rate Base Worksheet
5
Return on Rate Base Worksheet
6
Interest on True-Up
6A
True-Up Interest Rate Calculator
7
Weighted Average Federal and State Income Tax Rates
8
Cost of Debt Prior to Issuing Non-Construction Financing
9
True-Up - Construction Financing Cost of Debt
10
Depreciation Rates
11
Prior Period Adjustments
12
Revenue Credit Detail
13
Excess or Deficient Accumulated Deferred Income Taxes - Summary 13.1

Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments 13.2

Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities

PDF page 256

Formula Rate - Non-Levelized
Page 1 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
Projected ATRR
For the 12 months ended
12/31/__
(1) (2)
(3) (4)
(5) Line
Allocated
No.
Source
Amount
1
GROSS REVENUE REQUIREMENT, without incentives (Page 3, Line 49)

 $                               -
REVENUE CREDITS
(Note A)
Total
Allocator (W)
2
Account No. 454
(Page 4, Line 20)
                                                  -
TP
         1.0000
 $                               -
3
Account No. 456.1
(Page 4, Line 21)
                                                  -
TP
         1.0000
 $                               -
4
Revenues from Grandfathered Interzonal Transactions (Note B)

                                                  -
TP
         1.0000
 $                               -
5
Revenues from service provided by the ISO at a discount
                                                  -
TP
         1.0000
 $                               -
6
TOTAL REVENUE CREDITS
(Sum of Lines 2 through 5)
                                                  -
 $                               -
7
Prior Period Adjustments
Attachment 11, Line 18, Col. B
                                                  -
DA
         1.0000
 $                               -
8
True-up Adjustment with Interest
Attachment 3, Line 9, Col. J
                                                  -
DA
         1.0000
 $                               -
9
NET ANNUAL TRANSMISSION REVENUE REQUIREMENT
(Line 1 less Line 6 plus Lines 7 and 8)
 $                               -

PDF page 257

Page 2 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
RATE BASE: (Note R)
Source
Company Total
Allocator (W)
Transmission
GROSS PLANT IN SERVICE
Note C
(Col 3 times Col 4)
1
Production
205.46.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
2
Transmission
Attachment 4, Line 14, Col. (b)
                                                  -
TP
         1.0000
                                  -
3
Distribution
207.75.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
4
General & Intangible
Attachment 4, Line 14, Col. (c)
                                                  -
WS
         1.0000
                                  -
5
TOTAL GROSS PLANT
(Sum of Lines 1 through 4)
                                                  -
GP=
         1.0000
                                  -
6
ACCUMULATED DEPRECIATION
Note C
7
Production
219.20-24.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
8
Transmission
Attachment 4, Line 14, Col. (h)
                                                  -
TP
         1.0000
                                  -
9
Distribution
219.26.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
10
General & Intangible
Attachment 4, Line 14, Col. (i)
                                                  -
WS
         1.0000
                                  -
11
TOTAL ACCUM. DEPRECIATION
(Sum of Lines 7 through 10)
                                                  -
                                  -
12
NET PLANT IN SERVICE
13
Production
(Line 1 - Line 7)
                                              -
                               -
14
Transmission
(Line 2 - Line 8)
                                              -
                               -
15
Distribution
(Line 3 - Line 9)
                                              -
                               -
16
General & Intangible
(Line 4 - Line 10)
                                              -
                               -
17
TOTAL NET PLANT
( Sum of Lines 13 through 16)
                                              -
NP=
         1.0000
                               -
18
ADJUSTMENTS TO RATE BASE
19
Account No. 281 (enter negative)
Attachment 4, Line 28, Col. (d) (Note D)
                                              -
N/A
                 -
                               -
20
Account No. 282 (enter negative)
Attachment 4, Line 28, Col. (e) (Note D)
                                              -
NP
         1.0000
                               -
21
Account No. 283 (enter negative)
Attachment 4, Line 28, Col. (f) (Note D)
                                              -
NP
         1.0000
                               -
22
Account No. 190
Attachment 4, Line 28, Col. (g) (Note D)
                                              -
NP
         1.0000
                               -
22a
Deficient or (Excess) Accumulated Deferred Income Taxes Attachment 13, Line 7 (Note X)

                                                  -
NP
         1.0000
                               -
23
Account No. 255 (enter negative)
Attachment 4, Line 28, Col. (h) (Note D)
                                              -
NP
         1.0000
                               -
24
Unfunded Reserves (enter negative)
Attachment 4, Line 43, Col. (h)
                                              -
DA
         1.0000
                               -
25
CWIP
Attachment 4, Line 14, Col. (d)
                                              -
DA
         1.0000
                               -
26
Unamortized Regulatory Asset
Attachment 4, Line 28, Col. (b) (Note E)
                                              -
DA
         1.0000
                               -
27
Unamortized Abandoned Plant
Attachment 4, Line 28, Col. (c) (Note F)
                                              -
DA
         1.0000
                               -
28
TOTAL ADJUSTMENTS
( Sum of Lines 19 through 27)
                                              -
                                  -
29
LAND HELD FOR FUTURE USE
Attachment 4, Line 14, Col. (e) (Note G)
                                              -
TP
         1.0000
                               -
30
WORKING CAPITAL
Note H
31
Cash Working Capital
1/8*(Page 3, Line 17 minus Page 3, Line 14)
                                              -
                               -
32
Materials & Supplies
Attachment 4, Line 14, Col. (f)
                                              -
TP
         1.0000
                               -
33
Prepayments (Account 165)
Attachment 4, Line 14, Col. (g)
                                              -
GP
         1.0000
                               -
34
TOTAL WORKING CAPITAL
( Sum of Lines 31 through 33)
                                              -
                                  -
35
RATE BASE
( Sum of Lines 17, 28, 29, and 34)
                                              -
                                  -
Formula Rate - Non-Levelized

PDF page 258

Page 3 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
Source
Company Total
Allocator (W)
Transmission
O&M
(Col 3 times Col 4)
1
Transmission
321.112.b
                                                  -
TP
         1.0000
                                  -
2
Less Account 566 (Misc Trans Expense)
321.97.b
                                                  -
TP
         1.0000
                                  -
3
Less Account 565
321.96.b
                                                  -
TP
         1.0000
                                  -
4
A&G
323.197.b
                                                  -
WS
         1.0000
                                  -
5
Less FERC Annual Fees
351.h (Note I)
                                                  -
WS
         1.0000
                                  -
6
Less EPRI Dues
Note J
                                                  -
WS
         1.0000
                                  -
7
Less Reg. Commission Expense Account 928
Note J
                                                  -
WS
         1.0000
                                  -
8
Less: Non-safety Advertising account 930.1
Note J
                                                  -
WS
         1.0000
                                  -
9
10
Plus Transmission Related Reg. Comm. Exp.
Note K
                                                  -
TP
         1.0000
                                  -
11
12
Plus Transmission Lease Payments in Acct 565 Note V

                                                  -
DA
         1.0000
                                  -
13
Account 566
14
Amortization of Regulatory Asset
Note E
                                                  -
DA
         1.0000
                                  -
15
Misc. Transmission Expense (less amort. of regulatory asset) 321.97.b less line 14

                                                  -
TP
         1.0000
                                  -
16
Total Account 566
(Sum of Lines 14 through 15) Ties to 321.97b
                                                  -
                                  -
17
TOTAL O&M
                                                  -
                                  -
18
DEPRECIATION EXPENSE
Note C
19
Transmission
336.7.b&d
                                                  -
TP
         1.0000
                                  -
20
General & Intangible
336.10.b&d, 336.1.b&d
                                                  -
WS
         1.0000
                                  -
21
Amortization of Abandoned Plant
Note F
                                                  -
DA
         1.0000
                                  -
22
TOTAL DEPRECIATION
(Sum of Lines 19 through 21)
                                                  -
                                  -
23
TAXES OTHER THAN INCOME TAXES   (Note M)
24
LABOR RELATED
25
Payroll
263.i
                                                  -
WS
         1.0000
                                  -
26
263.i
                                                  -
WS
         1.0000
                                  -
27
PLANT RELATED
28
Property
263.i
                                                  -
GP
         1.0000
                                  -
29
Gross Receipts
263.i
                                                  -
N/A

                                  -
30
Other
263.i
                                                  -
GP
         1.0000
                                  -
31
Payments in lieu of taxes
263.i
                                                  -
GP
         1.0000
                                  -
32
TOTAL OTHER TAXES
( Sum of Lines 25 through 31)
                                                  -
                                  -
33
INCOME TAXES    (Note N)
Note N
34
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} 0.00%

35
CIT=(T/1-T) * (1-(WCLTD/R)) =
WCLTD = Page 4, Line 15, R = Page 4, Line 18 0.00%

36
FIT & SIT & P
37
38
1 / (1 - T)  = (from line 35)
1 / (1 - T), T from Line 35
                                         1.0000
39
Amortized Investment Tax Credit
266.8f (enter negative) (Note D)
                                                  -
40
Deficient or (Excess) Deferred Income Taxes Attachment 13, Line 12, Col. (d) (Note X)

                                                  -
41
Tax Effect of Permanent Differences
Note O
                                                  -
42
Income Tax Calculation
(Line 35 times Line 48)
                                                  -
N/A
                                  -
43
ITC adjustment
(Line 38 times Line 39)
                                                  -
NP
         1.0000
                                  -
44
Deficient or (Excess) Deferred Income Tax Adjustment Attachment 13, Line 12, Col. (f) (Note X)

                                                  -
NP
         1.0000
                                  -
45
Permanent Differences Tax Adjustment
(Line 38 times Line 41)
                                                  -
NP
         1.0000
                                  -
46
Total Income Taxes
(Sum of Lines 42 through 45)
                                                  -
                                  -
47
RETURN
48
Rate Base times Return
(Page 2, Line 35 times Page 4, Line 18)
                                                  -
N/A
                 -
                                  -
49
GROSS REVENUE REQUIREMENT
( Sum of Lines  17, 22, 32, 46, and 48)
                                                  -
                                  -
(Sum of Lines 1, 4, 10, 12, and 16 less Sum of Lines 2, 3, and 5 through 8)

Highway and vehicle

PDF page 259

Formula Rate - Non-Levelized
Page 4 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
SUPPORTING CALCULATIONS AND NOTES
TRANSMISSION PLANT INCLUDED IN ISO RATES
1
Total Transmission plant
(Page 2, Line 2, Col. 3)
                                  -
2
(Note P)
                                  -
3
(Note S)
                                  -
4
Transmission plant included in ISO rates
(Line 1 minus Lines 2 and 3)
                                  -
5
Percentage of Transmission plant included in ISO Rates (Line 4 divided by Line 1)

TP =                               1.00
6
WAGES & SALARY ALLOCATOR (W&S)
Form 1 Reference
$
TP
Allocation
7
Production
354.20.b
                                                  -
            -                    -
8
Transmission
354.21.b
                                                  -
        1.00                  -
9
Distribution
354.23.b
                                                  -
            -                    -
W&S Allocator
10
Other
354.24,25,26.b
                                                  -
            -                    -
($ / Allocation)
11
Total (W&S Allocator is 1 if lines 7-10 are zero) (Sum of Lines 7 through 10)

                                                  -
                 -
=
                        1.00000  = WS
12
RETURN (R)
13
14
$
%
Cost
Weighted
15
Long Term Debt
Attachment 5, Line 8 (Notes Q & R)
                                                  -
50.0%
0.00%
0.00% = WCLTD
16
Preferred Stock (112.3.c)
Attachment 5, Line 9 (Notes Q & R)
                                                  -
0.0%
0.00%
0.00%
17
Common Stock
Attachment 5, Line 10 (Notes Q, R, and T)
                                                  -
50.0%
9.80%
4.90%
18
Total
( Sum of Lines 15 through 17)
                                                  -
4.90% = R
19
REVENUE CREDITS
$
20
Attachment 12, Line 8, Col. C (Note U)
                                  -
21
ACCOUNT 456.1 (OTHER ELECTRIC REVENUES)
Attachment 12, Line 18, Col. C (Note A)
                                  -
Less Transmission plant excluded from ISO rates Less Transmission plant included in OATT Ancillary Service rates

ACCOUNT 454 (RENT FROM ELECTRIC

PDF page 260

Formula Rate - Non-Levelized
Page 5 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
General Note: References to pages in this formula rate template are indicated as: (Page #, Line #, Col. #)
References to data from FERC Form 1 are indicated as: #.y.x (page, line, column)
Notes
A
B
Company will not have any grandfathered agreements. Therefore, this line shall remain zero.
C
Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
D
E
F
Unamortized Abandoned Plant and Amortization of Abandoned Plant will be zero until the Commission accepts or approves recovery of the cost of Abandoned Plant. Utility must submit a Section 205 filing to recover the cost of abandoned plant. G

Identified in FERC Form 1, or Company records if not so indicated on the FERC Form 1, as being transmission related.
H
I
J
Page 3, Line 6 - Subtract all EPRI Annual Membership Dues listed in Form 1 at 353.f, all Regulatory Commission Expenses in account 928 itemized at 351.h, and non-safety related advertising included in Account 930.1. K

Page 3, Line 8-Add back Regulatory Commission Expenses directly related to transmission service, ISO filings, or transmission siting itemized at 351.h.
M
N
Inputs Required:
FIT =
0.0%
(Weighted Average Federal Income Tax Rate (Attachment 7, line 4, col. (i))
SIT =
0.0%
(Weighted Average State Income Tax Rate (Attachment 7, line 8, col. (i))
p =
0.0%
(Percent of federal income tax deductible for state purposes)
O
P
Removes transmission plant determined by Commission order to be state-jurisdictional according to the seven-factor test (until Form 1 balances are adjusted to reflect application of seven-factor test).
Q
R
S
T
The rate of return on common equity ("ROE") will be supported in the original Section 205 filing and shall, at no time during the life of the Project, be higher than 9.8%, including adders.  No change in ROE may be made absent a filing with FERC. U

Includes only income related to transmission facilities, such as pole attachments, rentals and special use from general ledger.
V
Add back any lease expense of transmission assets used to provide service under this tariff included in account 565. Amount to be obtained from company books and records.
W
DA = Direct Assignment; GP = Gross Plant Allocator (page 2, line 5); N/A = Not Applicable; NP = Net Plant Allocator (page 2, line 17); TP = Transmission Plant Allocator (page 4, line 5); WS = Wage and Salary Allocator (page 4, line 11). X

The revenues credited on page 1, lines 2-6, shall include only the amounts received by DesertLink for service rendered using facilities for which recovery is provided under this tariff. They do not include revenues associated with FERC annual charges, gross receipts taxes, or facilities not included in this template (e.g., direct assignment facilities and GSUs) which are not recovered under this Rate Formula Template.

Accumulated deferred income tax amounts associated with asset or liability accounts excluded from rate base (such as ADIT related to asset retirement obligations and certain tax-related regulatory assets or liabilities) do not affect rate base.  Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income. Account 281 is not allocated to Transmission.

Recovery of Regulatory Asset permitted only for pre-commercial and formation expenses as authorized by the Commission. Recovery of any other regulatory assets requires authorization from the Commission. A carrying charge equal to the AFUDC rate will be applied to the Regulatory Asset prior to the rate year when costs are first recovered.

Cash Working Capital assigned to transmission is one-eighth of O&M allocated to transmission at page 3, line 17, column 5 minus amortization of Regulatory Asset at page 3, line 14, column 5.  Prepayments are the electric related prepayments booked to Account No. 165 and reported on page 111, line 57 in the Form 1.

The FERC's annual charges for the year assessed the Transmission Owner for service under this tariff.  To the extent the charges are separately identified on the FERC Form 1, page 350, column 1, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 350 will be obtained from Company books and records.

Includes only FICA, unemployment, highway, property, gross receipts, and other assessments charged in the current year.  Taxes related to income are excluded.  Enter the line number on page 262-63 upon which each item is identified.  To the extent individual types of taxes are separately identified on the FERC Form 1, page 262, column a, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 262-63 will be obtained from Company books and records.

FIT is the weighted average Federal income tax rate and SIT is the weighted average State income tax rate, both from Attachment 7, and p is the "the percentage of federal income tax deductible for state income taxes". A utility that elected to utilize amortization of tax credits against taxable income, rather than book tax credits to Account No. 255 and reduce rate base, must reduce its income tax expense by the amount of the Amortized Investment Tax Credit (Form 1, 266.8.f) multiplied by (1/1-T) (page 3, line 26). Excess Deferred Income Taxes reduce income tax expense by the amount of the expense multiplied by (1/(1-T)).

The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Tax Effect equals Permanent Differences multiplied by T.

The cost of debt will be determined based on the financing in place during each stage of project development. Before debt is obtained, a proxy interest rate which will be supported in the original Section 205 filing will be used. This rate is provided on Attachment 8 line 36. If construction debt (wherein principal is drawn down over time) is issued, the rate plus an amortization of fees projected to be incurred on the construction debt during the rate year will be the cost of debt. This construction debt rate (inclusive of fees) will be reset and trued-up every year using the method on Attachment 9 for multi-year construction projects. Once non-construction debt is obtained, the actual interest rate and fees on the debt in place at the end of the year such non- construction debt is obtained will become the cost of debt. In the first full year after non-construction debt is obtained, the cost of debt will be the actual cost of debt determined using the method on Attachment 5. A h

h i
l
i l
f 50% E
i
d 50% d b
ill b
d
il h fi
i i
i
l
d i
i
il
h
i
h
i
d b
h C
i i
Af
h f
ili i
l
d i
i
h l
f
50%
i
h
h i
l
Calculate rate base using 13 month average balance, except ADIT.  The calculation of ADIT in the annual true-up calculation will use the beginning-of-year and end-of-year balances, and will be performed in accordance with IRS regulation Section 1.167(l)- 1(h)(6).  The calculation of ADIT in the annual projection will be performed in accordance with IRS Regulation Section 1.167(l)-1(h)(6).

Removes dollar amount of transmission plant to be included in the development of OATT ancillary services rates and generation step-up facilities, which are deemed to be included in OATT ancillary services. For these purposes, generation step-up facilities are those facilities at a generator substation on which there is no through-flow when the generator is shut down.

Upon enactment of changes in tax law, ADIT balances are re-measured and adjusted in the Company’s books of account, resulting in excess or deficient accumulated deferred income tax assets and liabilities.  Excess or deficient ADIT attributable to timing differences between the amounts of expenses or revenues recognized for income tax purposes and amounts of expenses or revenues recognized for ratemaking purposes as well as subsequent recoverable or refundable amortization of such amounts will be based upon Company records and be calculated and recorded in accordance with ASC 740 and any applicable normalization requirements of the taxing jurisdiction.  The Deficient or (Excess) Deferred Income Tax Adjustment (page 3, line 44) is computed by multiplying each component of Deficient or (Excess) Deferred Income Taxes (page 3, line 40) by the applicable tax gross-up factor.  For each re-measurement of ADIT, the amounts entered as the Deficient or (Excess) Accumulated Deferred Income Taxes component of ADJUSTMENTS TO RATE BASE (page 2, line 22a) or as the Deficient or (Excess) Deferred Income Tax Adjustment component of INCOME TAXES (page 3, line 44) will be supported by Attachment 13 (Deficient or Excess Accumulated Deferred Income Taxes) providing the balance for each taxing jurisdiction at the beginning and end of the year, amortization for the year, calculation of the gross-up to the revenue requirement level and any other information required to support compliance with any applicable normalization requirements.

PDF page 261

Page 1 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
To be completed in conjunction with Appendix III. Line

(1) (2)
(3) (4)
No.
Appendix III, Page, Line, Col.
Transmission
Allocator
1
Gross Transmission Plant plus CWIP
Appendix III, p 2, line 2, col 5 plus line 25, col 5 (Note A)
                                                         -
2
Net Transmission Plant plus CWIP and Abandoned Plant Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5 (Note B)

                                                         -
O&M EXPENSE
3
Total O&M Allocated to Transmission
Appendix III, p 3, line 17, col 5
                                                         -
4
Annual Allocation Factor for O&M
(line 3 divided by line 1, col 3)
0.00%
0.00%
GENERAL AND INTANGIBLE (G&I) DEPRECIATION EXPENSE 5

Total G&I Depreciation Expense
Appendix III, p 3, line 20, col 5 (Note C)
                                                         -
6
Annual Allocation Factor for G&I Depreciation Expense (line 5 divided by line 1, col 3)

0.00%
0.00%
TAXES OTHER THAN INCOME TAXES
7
Total Other Taxes
Appendix III, p 3, line 32, col 5
                                                         -
8
Annual Allocation Factor for Other Taxes
(line 7 divided by line 1, col 3)
0.00%
0.00%
9
Less Revenue Credits
Appendix III, p 1, line 6 col 5
                                                         -
10
Annual Allocation Factor for Revenue Credits (line 9 divided by line 1, col 3)

0.00%
0.00%
11
Annual Allocation Factor for Expense
Sum of lines 4, 6, 8, and 10
0.00%
INCOME TAXES
12
Total Income Taxes
Appendix III, p 3, line 46, col 5
                                                         -
13
Annual Allocation Factor for Income Taxes
(line 12 divided by line 2, col 3)
0.00%
0.00%
RETURN
14
Return on Rate Base
Appendix III, p 3, line 48, col 5
                                                         -
15
Annual Allocation Factor for Return on Rate Base (line 14 divided by line 2, col 3)

0.00%
0.00%
16
Annual Allocation Factor for Return
Sum of lines 13 and 15
0.00%

PDF page 262

Page 2 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template.
(1) (2)
(3) (4)
(5) (6)
(7) (8)
Project Name
CAISO Category
Identifier
Project Gross Plant
Project Net Plant
Annual Return Charge
(Note D)
(Page 1, line 11)
(Col. 3 * Col. 4)
(Note E)
(Page 1, line 16)
(Col. 6 * Col. 7)
1a
Project A
AAAA
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
1b
Project B
BBBB
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
2
Total Schedule 12
                                                  -
                       -    $                                                      -
                                         -
3a
Project C
CCCC
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
3b
Project D
DDDD
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
4
Total Zonal
                                                  -
                       -    $                                                      -
                                         -
5
Other
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
6
Annual Totals
                                                  -
                       -    $                                                      -
                                         -
This worksheet is used to compute project specific revenue requirements for any projects for which such calculation is required by CAISO. Other projects which comprise the remaining revenue requirement on Appendix III will not be entered on this schedule.

Line
No.
Annual Allocation
Factor for Expense
Annual
Expense
Charge
Annual
Allocation
Factor for
Return

PDF page 263

Page 3 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
(9) (10)
(11) (12)
(12a) (13)
(14) (15)
(16) Incentive Return
Ceiling Rate
(Note F)
(Sum Col. 5, 8 & 9)
(Note G)
(Sum Col. 10 & 12)
(Note H)
(Sum Col. 10 & 12 Less Col. 13)
(Note I)
(Sum Col. 14 & 15)
1a
                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
1b
                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
2
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                            - 3a

                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
3b
                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
4
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                            - 5

                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
6
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                            - Notes

A
Gross Transmission Plant is that identified on page 2 line 2 of Appendix III inclusive of any CWIP or unamortized abandoned plant included in rate base when authorized by FERC order. B

Net Plant is that identified on page 2 line 14 of Appendix III inclusive of any CWIP or unamortized Abandoned Plant included in rate base when authorized by FERC order less any prefunded AFUDC, if applicable. C

D
E
F
G
Requires approval by FERC of incentive return applicable to the specified project(s).
H
I
True-Up Adjustment is calculated on the Project True-up Schedule for the relevant true-up year.
Line
No.
Project
Depreciation/Amortizatio
n Expense
Annual Revenue
Requirement
Incentive Return in
Basis Points
Competitive
Concession
Total Annual Revenue
Requirement
True-Up
Adjustment
Net Revenue
Requirement
(Attachment 2, Line 28 Incentive
Return * Col. 6 * Col. 11/100)
General and Intangible Depreciation and Amortization Expense includes all expenses (except depreciation and armortization of G&I Asset Retirement Obligations) not directly associated with a project, which is entered on page 3 , column 9.

Project Gross Plant is the total capital investment including CWIP for the project calculated from Company books and records in the same method as the gross plant value in line 1.  This value includes subsequent capital investments required to maintain the facilities to their original capabilities.  Refer to Attachment 1a for detail.

Project Net Plant is the Project Gross Plant Identified in Column 3 less the associated Accumulated Depreciation plus CWIP in rate base if applicable and Unamortized Abandoned Plant.  Refer to Attachment 1a for detail. Project Depreciation Expense is the actual value booked for the project (excluding General and Intangible depreciation) at Appendix III, page 3, line 19, plus amortization of Abandoned Plant at Appendix III, page 3, line 21.  For each project on Attachment 1a, Depreciation Expense is Attachment 1a, Line 2, Column (15) minus Column (3), and Amortization of Abandoned Plant is the difference between Columns (3) and (15) on Attachment 1a, Line 4. The Competitive Concession is the reduction in revenue, if any, that the company agreed to, for instance, to be selected to build facilities as the result of a competitive process and equals the amount by which the  annual revenue requirement is reduced from the ceiling rate.

PDF page 264

Att 1a - Project Plant Detail
 Page 10
Page 1 of 1
For the twelve months ended 12/31/__
Attachment 1a
Project Plant Detail Worksheet
DesertLink, LLC
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
1a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1

Total Project Transmission Gross Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
2a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2

Total Project Transmission Accumulated Depreciation
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
3a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3

Total Project CWIP
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
4a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4

Total Project Unamortized Abandoned Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
Project Name
5a
Project A
                                                                -
5b
Project B
                                                                -
…
…
 …
5
Total Project Transmission Net Plant
                                                                -   Ties to Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5; Used on Attachment 1, Column (6)
Line
No.
Project
Transmission
Gross Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission Accumulated
Depreciation
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project CWIP
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Unamortized Abandoned Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission
Net Plant
13-month average
(Line 1 - Line 2 + Line 3 + Line 4)

PDF page 265

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 2
Incentive Return
DesertLink, LLC
Line
1
Rate Base
Appendix III, Page 2, Line 35, Col.5
                                                                         -
2
100 Basis Point Incentive Return
$
Cost
$
%
Weighted
3
Long Term Debt
(Notes Q & R from Appendix III)
                            -
50.00%
0.00%
0.00%
4
Preferred Stock
(Notes Q & R from Appendix III)
                            -
0.00%
0.00%
0.00%
5
Common Stock
(Notes Q, R, & T from Appendix III)
                            -
50.00%
10.80%
5.40%
6
Total (sum lines 3-5)
                            -
5.40%
7
100 Basis Point Incentive Return multiplied by Rate Base (line 1 * line 6)
                                                                         -
8
INCOME TAXES
9
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =
0.00%
10
CIT=(T/1-T) * (1-(WCLTD/R)) =
0.00%
11
WCLTD
Line 3
0.00%
12
FIT, SIT & p are as given in Appendix III footnote N.
13
1 / (1 - T)
Line 9
                    1.0000
14
Amortized Investment Tax Credit (266.8f) (enter negative)
Appendix III, Page 3, Line 39
                            -
15
Deficient or (Excess) Deferred Income Taxes
Appendix III, Page 3, Line 40
                            -
16
Tax Effect of Permanent Differences (Note B)
Appendix III, Page 3, Line 41
                            -
17
Income Tax Calculation
Line 7 times Line 10
                        -
18
ITC adjustment
Line 13 times Line 14
                            -
NP             1.00                         -
19
Deficient or (Excess) Deferred Income Tax Adjustment
Appendix III, Page 3, Line 44
                            -
NP             1.00                         -
20
Permanent Differences Tax Adjustment
Line 13 times Line 16
                            -
NP             1.00                         -
21
Total Income Taxes
Sum of Lines 17 through 20
                            -
                        -                                                                            - 22

Return and Income Taxes with 100 basis point increase in ROE
                                                                         -
23
Return
(Appendix III, page 3, line 48, col 5)
                                                                         -
24
Income Tax
(Appendix III, page 3, line 46, col 5)
                                                                         -
25
Return and Income Taxes without 100 basis point increase in ROE Sum of Lines 23 and 24

                                                                         -
26
Incremental Return and Income Taxes for 100 basis point increase in ROE Line 22 less Line 25

                                                                         -
27
Rate Base
Line 1
                                                                         -
28
Incremental Return and Income Taxes for 100 basis point increase in ROE divided by Rate Base Line 26 divided by Line 27 0.00%

Notes
A
B
The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Cost = Appendix III, Page 4, Line 17,

plus 100 bp
The 100 basis point increase in ROE is used only to determine the increase in return and income taxes associated with a 100 basis point increase in ROE and does not reflect what incentives the Commission may approve for a specific transmission project. The overall ROE inclusive of incentives is subject to the limitations noted in Appendix III, Note T.  Any ROE actual incentive must be approved by the Commission.

PDF page 266

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 3
Formula Rate True-Up
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template. Annual True-Up Calculation

Line
1
True-Up Year
2
C
D
                             -
F
G
H
I
J
A
B
E
Project Name
3
Remaining Appendix III
0.0%
                             -
                               -    $                          -
                             -
4a
Project A
AAAA
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
4b
Project B
BBBB
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
5 Total Schedule 12
                             -
                             -                                  -                                  -    $                          -                                -                                -
6a
Project C
CCCC
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
6b
Project D
DDDD
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
7
Total Zonal
                             -
                             -                                  -                                  -    $                          -                                -                                -
8
Other
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
9
                             -
0.0%
                             -                                  -                                  -                                -                                -                                -
10
 $                          -   Total Interest on True-Up - Attachment 6
Prior Period Adjustment
A
B
Source
11
Description of Adjustment
                 -
Notes
1) The revenue received is the total amount of revenue distributed to company in the  year as shown on pages 328-330 of the Form No 1. The Revenue Received is input on line 2, Col. E.
2) From the Attachment 1, lines 1a through 6, col. 16 from the template in which the true-up year revenue requirement was initially projected.
3) From True-Up revenue requirement template Attachment 1, lines 1a through 6, col. 14.
4) 5)
Corrections to true-ups for previous rate years including interest will be computed on Attachment 11 and entered on the appropriate line 3-8 above.
This Attachment 3 is used to calculate the annual formula rate true-up. Any projects for which the RTO requires a true-up on an individual project basis, as shown on Attachment 1, will be computed separately. The remainder of the revenue requirement will also be trued up. The utility will individually enter the projected true-up year revenue requirements in Column C. A percentage of total will be calculated in Column D. Actual revenue received during the true-up year is entered into Column E, line 2 and allocated using the Column D percentage. The utility will prepare this formula rate template with the actual inputs for the true-up year, with the resulting revenue requirement for each line being separately entered in Column F.  In Col. G, Col. F is subtracted from Col. E to calculate the true-up adjustment. Interest on the true-up is computed in Column H. Any adjustments to prior period true-ups are entered in Col.

I.  Col. J computes the total true-up as the sum of Col. G, H and I.
Projected True-Up Year Revenue
Requirement Calculation
True-Up Year
Revenue Received1
Actual True-Up
Year Revenue Req.
CAISO
Identification
Project # Or
Other
Identifier
Net Revenue
Requirement2
% of Total
Revenue
Requirement
Allocation of
Revenue Received

                    (E, Line
2) x (D)
True-Up Net Revenue
Requirement3
Net Under/(Over)
Collection   (F)-(E)
True-Up Interest
Income (Expense)4
(D) x (H, line 10)
Prior Period
Adjustment with
Interest5
Total True-Up
(G) + (H) + (I)
Total Annual Revenue
Requirements
Prior Period Adjustment
(Note 5)
Adjustment
Amount
Attachment
11
Interest due on the true up is calculated for the 24 month period from the start of the true-up year until the end of the year following the true-up year when the true up will be included in rates. Total True up Interest calculate on Attachment 6 and allocated to projects based on the percentage in Column D.

PDF page 267

Page 1 of 2
For the twelve months ended 12/31/__
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Gross Plant in Service
CWIP
LHFFU
Working Capital
Accumulated Depreciation
Month
Transmission
CWIP in Rate Base
Held for Future Use
Materials & Supplies
Prepayments
Transmission
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (Note A)
1
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 2

January
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 3

February
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 4

March
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 5

April
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 6

May
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 7

June
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 8

July
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 9

August
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 10

September
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 11

October
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 12

November
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 13

December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 14

                             -                                -                                  -                                       -                                      -                                      -                                    -                                    - Adjustments to Rate Base

Month
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(Note A)
Note C
Note D
272.8.b & 273.8.k
274.2.b & 275.2.k
276.9.b & 277.9.k
234.8.b & c
15
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 16

January
                   -                                -                                -
                                 -
17
February
                   -                                -                                -
                                 -
18
March
                   -                                -                                -
                                 -
19
April
                   -                                -                                -
                                 -
20
May
                   -                                -                                -
                                 -
21
June
                   -                                -                                -
                                 -
22
July
                   -                                -                                -
                                 -
23
August
                   -                                -                                -
                                 -
24
September
                   -                                -                                -
                                 -
25
October
                   -                                -                                -
                                 -
26
November
                   -                                -                                -
                                 -
27
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 28

                             -                                -                                  -                                       -                                      -                                      -                                    -
Line
No
General &
Intangible
General & Intangible
207.58.g less
207.57.g for end of
year, records for
other months
205.5.g & 207.99.g
less 207.98.g for
end of year, records
for other months
Note B - page 2,
column C
214.47.d for end of
year, records for other
months
227.8.c & 227.16.c for
end of year, records for
other months
111.57.c for end of
year, records for other
months
219.25.c less ARO for
end of year, records
for other months
219.28.c & 200.21.c
less ARO for end of
year, records for other
months
Average of the 13
Monthly Balances
Unamortized
Regulatory Asset
Unamortized
Abandoned Plant
Account No. 281
Accumulated
Deferred Income
Taxes (Note E)
Account No. 282
Accumulated Deferred
Income Taxes (Note E)
Account No. 283
Accumulated Deferred
Income Taxes (Note E)
Account No. 190
Accumulated
Deferred Income
Taxes (Note E)
Account No. 255
Accumulated
Deferred Investment
Credit (Note I)
Consistent with
266.8.b & 267.8.h
Average of the 13
Monthly Balances

PDF page 268

Page 2 of 2
For the twelve months ended 12/31/
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Total CWIP
(a) (b)
(c) = (a) - (b)
Company records
29
December
                   -                                -                                -                                  -
30
January
                   -                                -                                -                                  -
31
February
                   -                                -                                -                                  -
32
March
                   -                                -                                -                                  -
33
April
                   -                                -                                -                                  -
34
May
                   -                                -                                -                                  -
35
June
                   -                                -                                -                                  -
36
July
                   -                                -                                -                                  -
37
August
                   -                                -                                -                                  -
38
September
                   -                                -                                -                                  -
39
October
                   -                                -                                -                                  -
40
November
                   -                                -                                -                                  -
41
December
                   -                                -                                -                                  -
                             -                                -                                  -
Unfunded Reserves   (Notes A and F and G)
(a) (b)
(b.i)
(b.ii)
(c) (d)
(e) (f)
(g) (h)
List of all reserves
Amount
42a
Reserve 1
 -
 -
                               -
 -
 -
 -
                                 -                                    -
42b
Reserve 2
 -
 -
                               -
 -
 -
 -
                                 -                                    -
43
Total
                               -
                                 -
Notes:
A
Calculate using 13 month average balance, except ADIT which is calculated based on the average of the beginning of the year and the end of the year balances
B
C
D
Recovery of abandoned plant is limited to any abandoned plant recovery authorized by FERC.
E
ADIT is computed using the average of the beginning of the year and the end of the year balances. Electric ADIT only, Excludes ARO-related ADIT.
F
G
H
I
Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income.
Reconciliation of CWIP in Rate Base to FERC Form 1 - Note B
Less: CWIP and
AFUDC Excluded
from Rate Base
CWIP allowed in
Rate Base
216.b for end of
year, records for
other months
Average of the 13
Monthly Balances
FERC balance sheet
account where
reserves are
recorded
FERC income
statement account
where expenses are
recorded
Enter 1 if NOT in a
trust or reserved
account, enter zero (0)
if included in a trust or
reserved account
Enter 1 if the accrual
account is included in
the formula rate, enter
(0) if the accrual
account is NOT
included in the formula
rate
Enter the percentage
paid for by customers
less the percent
associated with an
offsetting liability on
the balance sheet (Note
H) Allocation (Plant or
Labor Allocator)
Amount Allocated,
col. c x col. d x col. e
x col. f x col. g
Recovery of CWIP in rate base must be approved by FERC.  Lines 29-41 of page 2 provide a reconciliation of the Company's total CWIP to the CWIP allowed in rate base. The annual report filed pursuant to the Protocols will include for each project under construction (i) the CWIP balance eligible for inclusion in rate base; (ii) the CWIP balance ineligible for inclusion in rate base; and (iii) a demonstration that AFUDC is only applied to the CWIP balance that is not included in rate base The annual report will also describe the reconciliation prepared on this Attachment

Recovery of a Regulatory Asset is permitted only for pre-commercial and formation expenses, and is subject to FERC approval before the amortization of the Regulatory Asset can be included in rates. Recovery of any other regulatory assets requires authorization from the Commission.

The Formula Rate shall include a credit to rate base for all unfunded reserves (funds collected from customers that (1) have not been set aside in a trust, escrow or restricted account; (2) whose balance are collected from customers through cost accruals to accounts that are recovered under the Formula Rate; and (3) exclude the portion of any balance offset by a balance sheet ac count (see Note H)).  Each unfunded reserve will be included on lines 42 above. The allocator in Col. (g) will be the same allocator used in the formula for the cost accruals to the account that is recovered under the Formula Rate.  Since reserves can be created by creating an offsetting balance sheet account, rather than through cost accruals, the amount to be deducted from rate base should exclude the portion offset by another balance sheet account. Not all unfunded reserves are created only from contributions from customers. Many are created by creating an offsetting liability in whole or in part.  Column (f) ensures only the portion of the unfunded reserve contributed by the customer (and not created by an offsetting liability) is a reduction to rate base.

The inputs in Column (f) are the percentage of the unfunded reserve that was created by an offsetting liability. The percentage shown in Column (f) is then equal to the percentage that customers have contributed to the unfunded reserve.

PDF page 269

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 5
Return on Rate Base Worksheet
DesertLink, LLC
RETURN ON RATE BASE ( R )
$
1
Long Term Interest (117, sum of 62.c through 67.c) (Note D)
                                -
2
Preferred Dividends (118.29c) (positive number)
                                -
3
Proprietary Capital (Line 25 (c))
                                -
4
Less Preferred Stock (Line 9)
                                -
5
Less Account 216.1 Undistributed Subsidiary Earnings (Line 25 (d))
                                -
6
Less Account 219 Accum. Other Comprehensive Income (Line 25 (e))
                                -
7
Common Stock
(Sum of Lines 3 through 6)
                                -
$
%
Cost
Weighted
8
Long Term Debt
Line 25 (a), Note A and Appendix III Note Q
                                -
50.00%
0.000%
0.00%
=WCLTD
9
Preferred Stock
Line 25 (b), Note B and Appendix III Note Q
                                -
0.00%
0.00%
0.00%
10
Common Stock
Line 7, Note C  and Appendix III Notes Q and T
                                -
50.00%
9.80%
4.900%
11
Total
(Sum of Lines 8 through 10)
                                -
4.90%
=R
(a) (b)
( c )
(d) ( e )
Monthly Balances for Capital Structure
12
December (Prior Year)
                               -                                 -                             -                                   -                                 - 13

January
                               -                                 -                             -                                   -                                 - 14

February
                               -                                 -                             -                                   -                                 - 15

March
                               -                                 -                             -                                   -                                 - 16

April
                               -                                 -                             -                                   -                                 - 17

May
                               -                                 -                             -                                   -                                 - 18

June
                               -                                 -                             -                                   -                                 - 19

July
                               -                                 -                             -                                   -                                 - 20

August
                               -                                 -                             -                                   -                                 - 21

September
                               -                                 -                             -                                   -                                 - 22

October
                               -                                 -                             -                                   -                                 - 23

November
                               -                                 -                             -                                   -                                 - 24

December
                               -                                 -                             -                                   -                                 - 25

13-Month Average
                               -                                 -                             -                                   -                                 - Notes

A
B
Preferred Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112 line 3.c in the Form No. 1 C

Common Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on Form 1 page 112 line 16.c less lines 3.c , 12.c, and 15.c D

Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies Long Term Debt

(Note A)
Preferred Stock
(112.3.c)
Proprietary
Capital (112.16.c)
Undistributed Sub
Earnings 216.1
(112.12.c)
Accum Other Comp.
Income 219
(112.15.c)
Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, lines 18.c to 21.c, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 270

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6
Interest on True-Up
DesertLink, LLC
Appendix III K23
Line
Rate Year
Rate Year
Projected Revenue Requirement (Note A)
1
                                                                                         -
Less
 $                             -
Equals
 $                        -
Note A - Projected ATRR for the true-up year from Page 1, Line 1 of Projection Appendix III minus Line 6 of Projection Appendix III. Note B - Actual Net ATRR for the true-up year from Page 1, Line 9 of True-Up Appendix III. Interest Rate on Amount of Refunds or Surcharges

Months
Amortization
2
0.000%
An over or under collection will be recovered pro rata over year collected, held for one year and returned pro rata over next year Monthly

3
January
Rate Year
                                -
0.000%
12
                          -
                              -
4
February
Rate Year
                                -
0.000%
11
                          -
                              -
5
March
Rate Year
                                -
0.000%
10
                          -
                              -
6
April
Rate Year
                                -
0.000%
9
                          -
                              -
7
May
Rate Year
                                -
0.000%
8
                          -
                              -
8
June
Rate Year
                                -
0.000%
7
                          -
                              -
9
July
Rate Year
                                -
0.000%
6
                          -
                              -
10
August
Rate Year
                                -
0.000%
5
                          -
                              -
11
September
Rate Year
                                -
0.000%
4
                          -
                              -
12
October
Rate Year
                                -
0.000%
3
                          -
                              -
13
November
Rate Year
                                -
0.000%
2
                          -
                              -
14
December
Rate Year
                                -
0.000%
1
                          -
                              -
15
                          -
                              -
Annual
16
January through December
Rate Yr. + 1                                 -
0.000%
12
                          -
                              -
Over (Under) Recovery Plus Interest Amortized and Recovered Over 12 Months Monthly

17
January
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 18

February
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 19

March
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 20

April
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 21

May
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 22

June
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 23

July
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 24

August
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 25

September
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 26

October
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 27

November
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 28

December
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 29

                          -
30
Total Amount of True-Up Adjustment
 $                           -
31
Less Over (Under) Recovery
 $                        -
32
Total Interest
 $                           -
Actual Net Revenue
Requirement (Note B)
Over (Under)
Recovery
Over (Under)
Recovery Plus
Interest
Monthly Interest
Rate on Attachment
6a
Calculated
Interest
Surcharge (Refund)
Owed
Calculation of Interest

PDF page 271

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6a
True-Up Interest Rate Calculator
DesertLink, LLC
This Attachment is used to compute the interest rate to be applied to each year's revenue requirement true-up.
Applicable FERC Interest Rate (Note A):
1
Rate Year January
0.00%
2
Rate Year February
-
3
Rate Year March
-
4
Rate Year April
-
5
Rate Year May
-
6
Rate Year June
-
7
Rate Year July
-
8
Rate Year August
-
9
Rate Year September
-
10
Rate Year October
-
11
Rate Year November
-
12
Rate Year December
-
13
Rate Year Plus 1  January
-
14
Rate Year Plus 1  February
-
15
Rate Year Plus 1  March
-
16
Rate Year Plus 1  April
-
17
Rate Year Plus 1  May
-
18
Average Rate
0.00%
19
Monthly Average Rate
0.00%
Note A - Lines 1-17 are the FERC interest rates under section 35.19a of the regulations for the period shown. Line 18 is the average of lines 1-17.

PDF page 272

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 7
Weighted Average Federal and State Income Tax Rates
DesertLink, LLC
Subchapter C
Mutual
Pensions, IRAs
UBTI
Non-Taxpaying
Weighted
Line
Description
Source
Corporations
Individuals
Funds
Keogh Plans
Entities
Entities
Average
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) 1
Weighted Marginal Federal Income Tax Rate
Note A
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
2
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
3
Weighted Average
Line 1 x Line 2
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4
Weighted Average Federal Income Tax Rate
Sum of Line 3, Col. (c)-(h)
0.00%
5
Weighted Marginal State Income Tax Rate
Note C
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
6
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
7
Weighted Average
Line 5 x Line 6
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
8
Weighted Average State Income Tax Rate
Sum of Line 7, Col. (c)-(h)
0.00%
A
For each Rate Year, DesertLink will develop a schedule calculating the weighted average federal income tax rate for each category of partners. B

This percentage is developed based on the distributive income allocated to each category of partners rather than their respective ownership percentages. C

For each Rate Year, DesertLink will develop a schedule calculating the weighted average state income tax rate for each category of partners.

PDF page 273

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 8
Cost of Debt Prior to Issuing Non-Construction Financing
DesertLink, LLC
This Attachment 8 is to be utilized to determine the cost of debt prior to issuing non-construction financing.  Once non-construction financing is issued the cost of debt shall be determined using the methodology described in Note Q on Appendix III. If construction debt has not or will not be issued when construction starts, a proxy rate will be used for the cost of debt, which will be supported in the initial section 205 filing. The proxy rate will be entered on line 36 of this attachment. If construction financing is obtained, all rates, fees and monthly debt balances will be subject to true up pursuant to Attachment 9. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template. Line No

1
Interest rate on Construction Debt for Rate Year - Line 19 (g)
0.00%
2
Rate Year Debt Fee expense - Line 35 (e)
0.00%
3
Total Cost of Debt - Sum of Lines 1 and 2
0.0000%
Interest Rate Information
4
Commitment Fee Rate (%)
5
Projected Average Drawn Rate for Rate Year (%) - Note A
Month During Rate Year
Total Loan Amount ($000)
Interest Expense ($000)
(a) (b)
(c) (d)
(e) (f)
(g) 6
December Prior Year
                            -                                         -                                          -                                          - 7

January
                            -                                         -                                          -                                          - 8

February
                            -                                         -                                          -                                          - 9

March
                            -                                         -                                          -                                          - 10

April
                            -                                         -                                          -                                          - 11

May
                            -                                         -                                          -                                          - 12

June
                            -                                         -                                          -                                          - 13

July
                            -                                         -                                          -                                          - 14

August
                            -                                         -                                          -                                          - 15

September
                            -                                         -                                          -                                          - 16

October
                            -                                         -                                          -                                          - 17

November
                            -                                         -                                          -                                          - 18

December
                            -                                         -                                          -                                          - 19

Average of the 13 Monthly Balances
                            -
                                        -                                          -
0.00%
Example Fee Calculation - All amounts represent actual rate year expenses.
(a) (b)
(c) (d)
(e) (f)
(g) Origination Fees
Rate/Fees
Gross Fee Amount ($000)
Year Fee Incurred
20
Underwriting Discount
0.00%
 -
 -
21
Arrangement Fee
0.00%
 -
 -
22
Upfront Fee
0.00%
 -
 -
23
Rating Agency Fee
0.00%
 -
 -
24
Legal Fees
0.00%
 -
 -
25
Other
0.00%
 -
 -
26
   Total Issuance Expense / Origination Fees - Sum of Lines 20-25
 -
 -
 -
 -
27
28
Annual Fees
29
Annual Rating Agency Fee
0.00%
N/A
 -
N/A
N/A
30
Annual Bank Agency Fee
0.00%
N/A                                      -
N/A
N/A
31
Utilization Fee
0.00%
N/A
 -
N/A
N/A
32
Other Fees
0.00%
N/A
 -
N/A
N/A
33
Total Fees
 -
 -
 -
 -
34
13 Month Average Debt balance - Line 19 (c)
                                        -
35
Rate Year cost of fees
0.00%
36
Proxy Debt rate. Used prior to issuance of construction financing and supported in initial section 205 filing. 3.2220%

Notes
A
LIBOR
0.0000%
Spread
2.3500%
Total
2.3500%
If construction financing has been obtained, the cost of debt prior the issuance of non-construction financing shall be based on the terms of the construction financing and determined below. Up-front fees including origination fees will be amortized and included in the cost of debt.

Principal Drawn
($000)
Unutilized Loan
Balance ($000)
Commitment Fee &
Utilization Fee ($000)
Effective Annual
Interest Rate (%)
Fee Amortization Period
(years)
Rate Year Amortized Fee
Amount, col. b / col. d
Prior Years Accumulated
Fee Amortization
Unamortized Balance
- End of Rate Year
Projected rate will be Average LIBOR for rate year + spread. Spread will be supported in initial section 205 filing. LIBOR will be updated based on information in the Wall Street Journal as of the 15th day of the month prior to population of this template.

PDF page 274

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 9
True-Up - Construction Financing Cost of Debt
DesertLink, LLC
One time up-front debt fees, including origination fees will be amortized and included in the cost of debt.
Line No.
$
1
Long Term Interest and Fees (117, sum of 62.c through 67.c) -- Notes A and B
                                    -
2
Line of Credit Fees (68.c) -- Note C
                                    -
3
Total Interest and Fees
                                    -
13 Month Average Long-Term Debt - Notes A and D
Month During Rate Year
Long Term Debt
(a) (d)
4
December Prior Year
                                    -
5
January
                                    -
6
February
                                    -
7
March
                                    -
8
April
                                    -
9
May
                                    -
10
June
                                    -
11
July
                                    -
12
August
                                    -
13
September
                                    -
14
October
                                    -
15
November
                                    -
16
December
                                    -
17
Average of the 13 Monthly Balances
                                    -
18
True-Up Cost of Debt (Line 3 / Line 17)
0.00%
Notes
A
B
Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies.
C
Line of credit fees will include only those related to long-term debt and not for short-term debt.
D
Long-term debt will exclude any short-term debt included in FERC Account 233, Notes Payable to Associated Companies.
This Attachment 9 is to be utilized only in the event construction financing has been obtained to compute the actual cost of debt to be included in the return on rate base calculation for the true-up each year prior to the issuance of non-construction financing. Once non-construction financing has been obtained the cost of debt shall be determined using the methodology described in Note Q on Appendix III. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template.

Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, line 24, columns d and c, respectively, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 275

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 10
Depreciation Rates
DesertLink, LLC
TRANSMISSION AND GENERAL PLANT DEPRECIATION RATES
Annual Depreciation Rates
Line No.
(Note A)
INTANGIBLE PLANT
1
303.1
Contributions in Aid of Construction
Note B
2
303.2
Interconnections
2.27%
3
303.3
Licenses
1.59%
TRANSMISSION PLANT
4
350.2
Land Rights
1.43%
5
351.1
Computer Hardware
20.00%
6
352.0
Structures & Improvements
1.95%
7
353.0
Station Equipment
2.58%
8
354.0
Towers & Fixtures
1.86%
9
355.0
Poles & Fixtures
2.17%
10
356.0
Overhead Conductors & Devices
2.01%
11
392.0
Transportation Equipment
10.00%
12
393.0
Stores Equipment
6.67%
13
394.0
Tools, Shop, and Garage Equipment
12.50%
14
397.2
Computer Software
11.64%
Notes
A
These depreciation rates will not be changed absent a FERC order.
B
GENERAL PLANT
In the event a Contribution in Aid of Construction (CIAC) is made for a transmission facility, the transmission depreciation rates above will be weighted based on the relative amount of underlying plant booked to the accounts shown in lines 4-12 above, and the resultant weighted average depreciation rate will be used to amortize the CIAC.   The CIAC depreciation rate for each facility will be determined at the time the plant is placed into service, and will not change  without FERC approval.

PDF page 276

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 11
Prior Period Adjustments
DesertLink, LLC
(a) (b)
Calendar Year
Line No. Description
Source
Revenue Impact of Correction
Revenue Requirement
1
Filing Name and Date
                                                        -
2
Original Revenue Requirement
                                                              -
3
4
Description of Correction 1
                                                              -
5
Description of Correction 2
                                                              -
6
7
Total Corrections
Line 4 + 5
                                                              -
8
9
Corrected Revenue Requirement
Line 2 + 7
                                                              -
10
11
12
Total Corrections
Line 7
                                                              -
13
14
Average Monthly FERC Refund Rate
Note A
0.00%
15
Number of Months of Interest
Note B
30
16
Interest on Correction
Line 12 x 14 x 15
                                                              -
17
18
Total Annual Amount Due from / (to) Customers
Line 12 + 16
                                                              -
Notes
A
B
The interest rate on corrections will be the average monthly FERC interest rate for the period from the beginning of the year being corrected through the most recent  month available as of the time the correction is computed and included in an annual filing.

The number of months interest due on the correction will be the number of months from the beginning of the year being corrected through June of the year in which the correction will be reflected in rates. In this manner the interest computed will reflect all years prior to when the correction is reflected in rates plus interest on the average unrefunded balance of the correction during the year the correction is reflected in rates.

PDF page 277

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 12
Revenue Credit Detail
DesertLink, LLC
(a) (b)
(c) = (a) - (b)
Line No.
(Note A)
Source
Company Total
Less: Non Transmission
Transmission-related
1
Account 454 - Rent from Electric Property
2
Joint pole attachments - telephone
Company books
                                          -                                                      -                                                                                                                 - 3

Joint pole attachments - cable
Company books
                                          -                                                      -                                                                                                                 - 4

Underground rentals
Company books
                                          -                                                      -                                                                                                                 - 5

Transmission tower wireless rentals
Company books
                                          -                                                      -                                                                                                                 - 6

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 7

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 8

Account 454 Revenue Credit
Form 1 300.19.b
                                          -                                                      -                                                                                                                 - 9

Account 456.1 Other Operating Revenues
10
CAISO NITS
Company books
                                          -                                                      -                                                                                                                 - 11

CAISO Point to Point
Company books
                                          -                                                      -                                                                                                                 - 12

Over/Under recovery deferral
Company books
                                          -                                                      -                                                                                                                 - 13

Other Transmission Service Revenues
Company books
                                          -                                                      -                                                                                                                 - 14

Other
Company books
                                          -                                                      -                                                                                                                 - 15

Total Per Books
Form 1 330.n
                                          -                                                      -                                                                                                                 - 16

Less: revenues received pursuant to this Formula Rate
                                          -                                                      -                                                                                                                 - 17

Less: Over/Under recovery deferral
                                          -                                                      -                                                                                                                 - 17a

Less: Revenue Credits included in the TRBAA
                                          -                                                      -                                                                                                                 - 18

Account 456.1 Revenue Credit
                                          -                                                      -                                                                                                                 - 19

Total Revenue Credits
(Line 8 + line 18)
                                          -                                                      -                                                                                                                 - Note A

All 454 and 456.1 revenues will be detailed from Company books and records or FERC Form 1, and additional rows added if necessary.  Non-transmission-related amounts will be deducted to determine transmission-related amounts. (Line 15 - line 16 - line 17

- line 17a)

PDF page 278

DesertLink, LLC
Attachment 13 - Excess or Deficient Accumulated Deferred Income Taxes - Summary
[Year]
[Projected or Actual]
Line No.
1
2
[List of tax law changes, accounting treatment, and asscociated explanatory notes.]
3
Rate Base Adjustment Mechanism - Summary
4
Account
Amount
References
5
182.3 (debit or <credit>)
                        -
6
254 (debit or <credit>)
                        -
7
Total Deficient or (Excess) ADIT (sum of lines 5-6)
                        -   To Appendix III, Page 2, Line 22a, Col. (3)
8
9
Income Tax Allowance Adjustment Mechanism - Summary
(a) (b)
(c) (d)
(e) (f)
10
11
[Insert rows as necessary]
                        -
                        -
11a
[Insert rows as necessary]
                        -
                        -
11…
[Insert rows as necessary]
                        -
                        -
12
Total
(sum of lines 11_)
                        -
                        -
13
14
[Explanatory statements as needed]
The primary purposes of this worksheet are to:
 - reconcile the amounts of regulatory assets and liabilities comprising the rate base adjustment mechanism on Appendix III, Page 2, Line 22a (ADJUSTMENTS TO RATE BASE > Deficient or (Excess) ADIT) as of the beginning and end of the current test period (summarized beginning at Line 3 below) and

- to support the amount of excess deferred tax expense or benefit recognized due to enacted change(s) in tax rate(s) on Appendix III, Page 3, Line 40 (INCOME TAXES > Deficient or (Excess) Deferred Income Taxes) and the effect of such excess deferred tax expense or benefit on the revenue requirement as reflected in the income tax allowance adjustment mechanism on Appendix III, Page 3, Line 44 (INCOME TAXES > Deficient or (Excess) Deferred Income Tax Adjustment) during the test period (summarized beginning on Line 9 below).

This worksheet supports the computation of the projected revenue requirement or, as appropriate, the actual revenue requirement used to compute the true-up adjustment.
Each tax law change addressed by this worksheet with its associated explanatory note is listed below.  Amounts related to each tax law change are provided and supported throughout this worksheet.  Additional lines and explanatory notes will be added to this worksheet as necessary as tax law changes are enacted without the need for an FPA Section 205 filing.

The amounts summarized above are computed in the Rate Base Adjustment Mechanism-Reconciliation of Beginning and End of Test Period Balances section of the worksheet with proration and averaging of activity during the test period computed in different section of Attachment 13.1 for projected revenue requirement calculations and actual revenue requirement calculations.

 Amortization or
Mitigation of
Deficient or
<Excess> ADIT
 Tax Gross-up
Factor
 Amortization or
Mitigation with
Tax Gross-up
 To Appendix III,
Page 3, Line 40,
Col. (3)
 To Appendix III,
Page 3, Line 44,
Col. (3)

PDF page 279

15
Rate Base Adjustment Mechanism - Reconciliation of Beginning and End of Test Period Balances
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
16
Description (+ = debit, <> = credit)
Amortization period and method
17
[Insert rows as necessary]
                        -                           -                           -                           -                           - 17a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 18

Total for account 182.3
(sum of lines 17_)
                        -                           -                           -                           -                           - 19

 FN1. pg 232
 FN1. pg 232
20
[Insert rows as necessary]
                        -                           -                           -                           -                           - 20a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 21

Total for account 254
(sum of lines 20_)
                        -                           -                           -                           -                           - 22

 FN1. pg 278
 FN1. pg 278
23
24
Income Tax Allowance Adjustment Mechanism
25
26
Amortization of Excess or Deficient ADIT
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
27
Description (+ = debit, <> = credit)
Comments
28
[Insert rows as necessary]
                        -                           -                           -                           -                            - 28a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 29

Total for account 182.3
(sum of lines 28_)
                        -                           -                           -                           -                            - 30

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 31

Total for account 254
(sum of lines 30_)
                        -                           -                           -                           -                            - 32

Total amortization and offsetting entries
(sum of lines 29 & 31)                         -                           -                           -                           -                            - 33

Net income tax expense or benefit
(sum of lines 32(f) & 32(g))
                        -
 To line 11
Balance at
Beginning of
Year
Re-
measurement of
ADIT
Annual
Amortization
(Note 4)
Other
Adjustments
(Note 5)
Balance at End
of Year
(d)+(e)+(f)+
(g) Whether subject
to normalization
rules
(Note 6)
Analysis - Balances of tax-related regulatory assets and liabilities include tax gross-up.  Accordingly, for the regulatory assets and liabilities for deficient or excess deferred taxes included in rate base, the related deferred tax assets and liabilities are also included in rate base.  Remeasurements in column (e) are described in Notes 2 and 3 and are based on the journal entry below and the support on the worksheet for the applicable tax law change.  Averaging or proration of amounts affecting rate base is computed on different sections of Attachment 13.1 for projected revenue requirement and actual revenue requirement. The income tax allowance adjustment mechanism may include amortization of excess or deficient ADIT pertaining to deferred tax expense or benefit reflected in rates at a historical tax rate when the underlying timing difference(s) originated (computed under Amortization of Excess or Deficient ADIT within the Income Tax Allowance Adjustment Mechanism section of this worksheet) as well as an adjustment for tax law changes with prospective effective dates intended to mitigate the over- or under- recovery of deferred income taxes originating prior to the effective date of such tax law changes (computed under Adjustment for Tax Law Changes with Prospective Effective Dates within the Income Tax Allowance Adjustment Mechanism section of this worksheet).

Annual
Amortization
from Table
Above
(Note 4)
Debit or
<Credit> to
Account 410.1
Debit or
<Credit> to
Account 411.1
Debit or
<Credit> to
Account 190
Debit or
<Credit> to
Account 283

PDF page 280

34
Adjustment for Tax Law Changes with Prospective Effective Dates
35
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) 36
37
 (c) x (d)
1 / (1- (d))
 (e) x (f)
 - [(c) x (h)]
 (e) + (i)
 (j) x (f)
38
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
38…
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
39
Note 1 - Summary of re-measurement of ADIT resulting from tax law changes
40
41
Note 1a - Summary of re-measurement of ADIT resulting from
[name of tax law change]
Additional information is provided in Note
42
Re-measurement entry
(a) (b)
(c) 43
Account
Comments or References
44
190
45
281
46
282
47
283
48
182.3 (tax-related, included in rate base - protected)
49
182.3 (tax-related, included in rate base - unprotected)
50
182.3 (tax-related, not in rate base))
51
190 (related to portion of acct. 182.3 not in rate base)
52
254 (tax-related, included in rate base - protected)
53
254 (tax-related, included in rate base - unprotected)
54
254 (tax-related, not in rate base)
55
283 (related to portion of acct. 254 not in rate base)
56
Account 410.1
57
Account 411.1
58
Account 410.2
59
Account 411.2
60
Total
 (sum of lines
                        -
61
[Insert additional analysis.]
In the case of tax law changes with an effective date(s) after the beginning of the test period, the impact of a timing difference on current tax expense or benefit differs from the impact on ADIT.  For example, in the case of a deductible timing difference originating in a tax year with a higher enacted tax rate than will apply when the difference will reverse, the current tax benefit will exceed the deferred tax expense.  In this situation, the adjustment computed below to recoverable income tax expense is made in order to avoid over-recovering income tax expense in the current test period due to the excess of current tax benefit over deferred tax expense (computed based on the estimated amount of the future tax liability) with respect to a given timing difference.  The adjustment to recoverable tax expense during the test period in which a timing difference originates mitigates the need for refund of a regulatory liability for excess deferred taxes in a future period (or, as applicable, the need for recovery of a regulatory asset for deficient deferred taxes in a future period).  Amounts in column (i) are reported in the Income Tax Allowance Adjustment Mechanism - Summary on this worksheet.

 Originating
Taxable or
(Deductible)
Book / Tax
Difference for
Test Year
 Tax Rate for
Test Year
 Current Tax
Expense or
(Benefit) in Test
Year
 Tax Gross-up
Factor for Test
Year
 Revemue
Requirement
Imapct for Test
Year
 Enacted Tax
Rate for the
Reversal Year(s)
 Deferred Tax
Expense or
(Benefit) in Test
Year
 Total Tax
Expense or
(Benefit) in Test
Year
 Adjustment to
Mitigate
Over/under-
recovery of
Deferred Taxes
The purposes of this portion of the worksheet are, for each change in tax law, to explain:
- how any ADIT accounts were re-measured,
- the excess or deficient ADIT contained therein, and
- the accounting for any excess or deficient amounts in Accounts 182.3 (Other Regulatory Assets) and 254 (Other Regulatory Liabilities).
Note 2 describes how ADIT accounts are re-measured upon a change in income tax law.  A separate summary (i.e., Note 1a, Note 1b, etc.) will be added for each tax law change resulting in a re-measurement of ADIT. Debit or

<Credit>

PDF page 281

62
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
63
[Insert additional analysis.]
64
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
65
66
67
68
69
[Continuation of note with respect to particular changes in tax law.]
70
[Insert additional notes as needed.]
Note 2 - Explanation of how ADIT accounts are re-measured upon a change in income tax law
Deferred tax assets and liabilities are adjusted (re-measured) for the effect of the changes in tax law (including tax rates) in the period that the change is enacted.  Adjustments are recorded in the appropriate deferred tax balance sheet accounts (Accounts 190, 281, 282 and 283) based on the nature of the temporary difference and the related classification requirements of the accounts.   If as a result of action or expected action by a regulator, it is probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, a regulatory asset or liability is recognized in Account 182.3 (Other Regulatory Assets), or Account 254 (Other Regulatory Liabilities), as appropriate, for that probable future revenue or reduction in future revenue.  Re-measurements of deferred tax balance sheet accounts may also result in re-measurements of tax-related regulatory assets or liabilities that had been recorded prior to the change in tax law.  If it is not probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, tax expense is recognized in Account 410.2 (Provision for Deferred Income Taxes, Other Income or Deductions) or tax benefit is recognized in Account 411.2 (Provision for Deferred Income Taxes-Credit, Other Income or Deductions), as appropriate.

Note 3 - [Complete to support information above.]
Note 4 - The amortization of the deficient or excess ADIT reducing Account 254 (Other Regulatory Liabilities) is recorded with credits to Account 411.1 (Provision for Deferred Income Taxes – Credit, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance.  The amortization of the deficient or excess ADIT reducing Account 182.3 (Other Regulatory Assets) is recorded with debits to Account 410.1 (Provision for Deferred Income Taxes, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance. This activity is summarized in the table "Income Tax Allowance Mechanism - Projected" or the table "Income Tax Allowance Mechanism - Actual," as appropriate.  The annual amortization in the tables above reflects tax gross-up and is stated at the revenue requirement level.

Note 5 - [Complete to support information above.]
Note 6 -  The worksheet indicates whether each excess or deficient ADIT amounts are protected (i.e., subject to normalization rules of a taxing jurisdiction) or unprotected (i.e., not subject to normalization rules of a taxing jurisdiction).  To the extent that normalization requirements apply to ADIT remeasurements, additional computations (e.g., proration of excess deferred tax activity related to future test periods) may be necessary.

PDF page 282

DesertLink, LLC
Attachment 13.1 - Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments
Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)
[Year]
[Projected or Actual]
Line No.
1
Rate year =
2
Test period days after rates become effective
3
4
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
5
6
Beginning balance  (debit or <credit>)
                        -
7
Less:  Portion not related to transmission
                        -
8
Less:  Portion not reflected in rate base
                        -
9
Subtotal:  Portion reflected in rate base
                        -
10
Less:  Portion subject to proration
                        -
11
Portion subject to averaging  (debit or <credit>)
                        -
12
Ending balance  (debit or <credit>)
                        -
13
Less:  Portion not related to transmission
                        -
14
Less:  Portion not reflected in rate base
                        -
15
Subtotal:  Portion reflected in rate base
                        -
16
Less:  Portion subject to proration (before proration)
                        -
17
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
18
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 36(n)
19
Average balance of portion subject to averaging
                        -
20
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 5
This attachment includes sections that are populated only with actual data and thus, these sections remain blank when the formula rate template is calculating a projected revenue requirement. Columns (i) through (n) below are not used for the projection and are only populated with actual data for the Annual Update.

Note 1 - The computations below apply the proration rules of Treasury Regulation section 1.167(l)-1(h)(6) to the annual activity of the portions of the deficient or excess accumulated deferred income taxes recorded in account 182.3 or 254 that are subject to the normalization requirements.  Activity related to the portions of the account balances reflected in rate base but not subject to the proration requirement is averaged instead of prorated.  The balances below include tax gross-up.  The corresponding portions of the deferred tax asset related to the portions of the regulatory liability and the corresponding portions of the deferred tax liability related to the portions of the regulatory asset are also reflected in rate base and prorated or averaged, as appropriate.  Columns (a) through (h) are used for projected and actual revenue requirements computations.  Columns (i) through (n) are used for actual revenue requirement computations.

Amount
debit / <credit>

PDF page 283

21
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
22
Month
Year
23

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
24
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA
 NA                              -
25
January
-
                              -                                 -
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 26

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 27

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 28

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 29

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 30

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 31

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 32

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 33

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 34

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 35

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 36

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 37

Total
                              -
                             -                                -
38
39
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
40
41
Beginning balance  (debit or <credit>)
                        -
42
Less:  Portion not related to transmission
                        -
43
Less:  Portion not reflected in rate base
                        -
44
Subtotal:  Portion reflected in rate base
                        -
45
Less:  Portion subject to proration
                        -
46
Portion subject to averaging  (debit or <credit>)
                        -
47
Ending balance  (debit or <credit>)
                        -
48
Less:  Portion not related to transmission
                        -
49
Less:  Portion not reflected in rate base
                        -
50
Subtotal:  Portion reflected in rate base
                        -
51
Less:  Portion subject to proration (before proration)
                        -
52
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
53
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 70(n)
54
Average balance of portion subject to averaging
                        -
55
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 6
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 2 -
Amount
debit / <credit>

PDF page 284

56
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
57
Month
Year
58

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
58
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA                              -
59
January
-
                              -                                 -
0
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 60

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 61

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 62

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 63

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 64

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 65

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 66

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 67

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 68

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 69

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 70

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 71

Total
                              -
                             -                                -
72
73
74
75
76
77
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 3 -
Note 4  -  Column J is the difference between actual monthly and projected monthly activity (Column I minus Column C).  Specifically, if projected and actual activity are both positive, a negative in Column J represents over-projection (i.e., the amount of projected activity that did not occur) and a positive in Column J represents under-projection (i.e., the excess of actual activity over projected activity). If projected and actual activity are both negative, a negative in Column J represents under-projection (i.e., the excess of actual activity over projected activity) and a positive in Column J represents over-projection (i.e., the amount of projected activity that did not occur).

Note 5  -  Column K preserves the effects of excess ADIT proration from the projected revenue requirement when actual monthly excess ADIT activity and projected monthly excess ADIT activity are either both increases or decreases.  Specifically, if Column J indicates that excess ADIT activity was over-projected, enter Column G x [Column I / Column C].  If Column J indicates that excess ADIT activity was under-projected, enter the amount from Column G and complete Column L).  In other situations, enter zero.

Note 6  -  Column L applies when (1) Column J indicates that excess ADIT activity was under-projected AND (2) actual monthly and projected monthly activity are either both increases or both decreases.  Enter 50 percent of the amount from Column J.  In other situations, enter zero.  The excess ADIT activity in column L is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 7  -  Column M applies when (1) projected monthly activity was an increase while actual monthly activity was a decrease OR (2) projected monthly activity was a decrease while actual monthly activity was an increase.  Enter 50 percent of the amount of actual monthly activity (Column I).  In other situations, enter zero.  The excess ADIT activity in column M is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 8  -  Column N is computed by adding the balance at the end of the prior month to EITHER (1) the sum of prorated monthly excess ADIT activity, if any, from Column K and the portion of monthly excess ADIT activity, if any, from Column L OR (2) the portion of monthly excess ADIT activity in Column M.

PDF page 285

DesertLink, LLC
Attachment 13.2 - Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities Resulting from the Tax Change Identified in Line 1 Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)

[Year]
[Projected or Actual]
Line No.
1
[Identify/describe the tax legislation/change]
2
[Describe the computation.]
3
4
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
5
Balances and rates prior to remeasurement
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
6
Temporary Difference
Account
Account
Account
Account
Account
7
Item
Normalized?
Amount
190
282
283
182.3
283
8
[Insert rows as necessary]
8a
[Insert rows as necessary]
8b
[Insert rows as necessary]
8...
[Insert rows as necessary]
9
Total
                     -                      -                      -                      -                      -
10
Remeasured balances and rates
Other accounts affected by remeasurement
11
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
[1/(1-tax rate [tax rate] /(1-tax rate [tax rate]
12
Temporary Difference
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
13
Item
Normalized?
Amount
190
282
283
182.3
283
410.2
411.2
254
190
182.3
283
14
[Insert rows as necessary]
14a
[Insert rows as necessary]
14b
[Insert rows as necessary]
14...
[Insert rows as necessary]
15
Total
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
16
Remeasurement journal entry:  debt or <credit> (to Attachment 13)
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
17
Summary of Effects on Tax-related Regulatory Assets and Liabilities
18
Account 182.3 - included in rate base, subject to normalization rules
19
Account 182.3 - included in rate base, not subject to normalization rules
20
Account 182.3 - not included in rate base
21
Account 254 - included in rate base, subject to normalization rules
22
Account 254 - included in rate base, not subject to normalization rules
23
Account 254 - not included in rate base
The ratemaking treatment of each item in terms of whether it is subject to the normalization requirements (i.e., P or "protected") or not subject to the normalization requirements (i.e., U or "unprotected") and included in rate base or not (i.e., RB or non-RB) is indicated in column (b).  The balances are measured at the composite tax rate in effect immediately before effective date of the change in tax law and remeasured immediately after the change in tax law.  Each set of balances includes the appropriate income tax rates and tax gross-up factors (as computed in the specific note for this tax law change in Att. 13).  The journal entry to record the remeasurements (Line 16) is based on the differences in balances of accounts recorded prior to the change in law (columns (d)-(h)) and activity in other accounts resulting from the remeasurement (columns (i)-(n)).  The remeasurement entry is also included in Att. 13.  The accounting is further described in Att. 13, Note 2. This worksheet will be included in support of the revenue requirement computation until the excess or deficient ADIT is fully amortized.  A similar worksheet will be used for subsequent changes in tax law resulting in re-measurement of ADIT.

PDF page 286

Appendix V  PRO FORMA LARGE LOAD COST RECOVERY AGREEMENT

PDF page 287

1

DESERTLINK, LLC
[PRO FORMA] LARGE LOAD COST RECOVERY AGREEMENT

This Large Load Cost Recovery Agreement (this “Agreement”) is entered into as of this __ day of _______ 20  , by and between [________], a [●] and an Eligible Customer under the CAISO Tariff (“Eligible Customer”), and DesertLink, LLC, a Delaware limited liability company (“DesertLink” or “Transmission Owner”). DesertLink and Eligible Customer are referred to collectively as the “Parties” and individually as a “Party.”

[_______], a [●] (“Large Load Customer”), executes the Limited Acknowledgment set forth below solely for the purposes stated therein and is not a Party to the wholesale payment obligations established by this Agreement.

RECITALS

WHEREAS, DesertLink is a transmission-only company established to develop, own, and operate transmission facilities (“Transmission Facilities”) pursuant to the provisions of its Transmission Owner Tariff (“TO Tariff”) and the California Independent System Operator Corporation (“CAISO”) Open Access Transmission Tariff (“CAISO Tariff”);

WHEREAS, Eligible Customer is eligible to take transmission service under the CAISO Tariff and does or will take such service on behalf of the Large Load Customer, whether or not Eligible Customer owns or operates an electric distribution system;

WHEREAS, Eligible Customer and Transmission Owner are parties to, or are entering into, an Eligible Customer for Large Load (“ECLL”) Interconnection Agreement or Transmission System Wholesale Load (“TSWL”) Interconnection Agreement (each, an “Interconnection Agreement”) concerning the Large Load Facility;

WHEREAS, Large Load Customer owns, operates, or proposes to develop the Large Load Facility identified in Schedule 1;

WHEREAS, the Eligible Customer has submitted an ECLL Interconnection Application or TSWL Interconnection Application for the interconnection of the Large Load Facility as a new or incremental load;

WHEREAS, Eligible Customer intends to procure transmission service pursuant to the CAISO Tariff and its associated schedules on behalf of Large Load Customer; WHEREAS, in connection with the Large Load Facility, Transmission Owner must make additions and/or modifications to its transmission system, including the Large Load-Driven Upgrades identified in Schedule 1;

WHEREAS, CAISO may, under the CAISO Tariff or a Commission-accepted
methodology, formally assign to the Large Load Facility a specific share of the costs or revenue requirement of a regional transmission project, and the Parties intend this Agreement to address

PDF page 288

2

that assigned share without changing any allocation otherwise established under the CAISO Tariff;

WHEREAS, the applicable studies may identify impacts on transmission systems other than DesertLink’s transmission system and may identify Affected System Upgrades necessary to accommodate or mitigate such impacts;

WHEREAS, Eligible Customer is responsible for entering into and maintaining the arrangements, payment obligations, and financial security or credit support required by each applicable Affected System Owner to ensure that costs and financial risks associated with Affected System Upgrades are not shifted to customers that did not cause those costs; WHEREAS, Transmission Owner, Eligible Customer, and Distribution Utility have executed or expect to execute an engineering and procurement agreement and/or an Interconnection Agreement governing the design, construction, and interconnection of the Transmission Owner’s facilities to the Distribution Utility’s facilities, including the Network Upgrades, required to support service of the Large Load Facility;

WHEREAS, the Parties enter into this Agreement to establish the Eligible Customer’s wholesale revenue-support and security obligations associated with the Large Load Facility and the Large Load-Driven Upgrades, without establishing or prescribing the retail rates, charges, or recovery arrangements between Eligible Customer and Large Load Customer;

WHEREAS, the Commission has recognized that the framework under which CAISO provides transmission service is unique and that certain responsibilities fall to the Participating Transmission Owners, Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214, at P 37 (2026), and this Agreement is the form of agreement established under Sections 10.9 and 10A.6 of the TO Tariff to secure Eligible Customer’s minimum contribution toward Transmission Owner’s transmission revenue requirement;

WHEREAS, CAISO is not a party to this Agreement; this Agreement does not create any obligation of CAISO, including any obligation to provide settlement, metering, billing, resettlement, or allocation data, which arises, if at all, under the CAISO Requirements; and DesertLink shall recover the costs of the Covered Upgrades through its Formula Rate and shall flow TRBAA Credits, including any adjustment resulting from the resolution of a dispute under this Agreement, through to transmission customers through its TRBAA;

NOW, THEREFORE, in consideration of the mutual promises and covenants set forth herein, and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Parties intending to be legally bound, agree as follows:

1. Recitals. The statements set forth in the recitals above are hereby incorporated herein into the terms and conditions of this Agreement as if fully set forth herein.

PDF page 289

3

2. Definitions
Capitalized terms not defined herein have the meanings given in the CAISO Tariff, the DesertLink TO Tariff Formula Rate Implementation Protocols in Appendix IV of the TO Tariff (“Protocols”), or the relevant Interconnection Agreement.

2.1.
“Affected System” means an electric transmission system, other than DesertLink’s transmission system, that an applicable study determines may be materially affected by the interconnection or service of the Large Load Facility, including the transmission system of another Participating TO or a transmission system outside the CAISO Controlled Grid.

2.2.
“Affected System Arrangement” means an executed agreement or other binding arrangement entered into by Eligible Customer with an Affected System Owner that establishes the applicable study, engineering, design, procurement, construction, ownership, cost responsibility, cancellation-cost, revenue-support, payment, financial security or credit support, true-up, and other obligations associated with an Affected System Upgrade.

2.3.
“Affected System Owner” means the owner or operator responsible for an Affected System.

2.4.
“Affected System Upgrade” means an addition, modification, or upgrade to an Affected System that an applicable study determines is necessary to accommodate or mitigate an impact caused, in whole or in part, by the interconnection or service of the Large Load Facility.

2.5.
“Annual MTRC” means the annual Minimum Transmission Revenue Contribution for a Covered Upgrade, calculated solely under the MTRC Calculation Template in Schedule 5. Before the Final MTRC Determination Date for a Covered Upgrade, the Annual MTRC is the Estimated Annual MTRC. On and after that date, it is the Final Annual MTRC fixed under Section 6.3. Each Annual MTRC is levelized over a twenty (20)-year MTRC Term beginning on the applicable Upgrade In-Service Date or Regional Project In-Service Date, as applicable. The Annual MTRC is not an input to, or calculation made under, DesertLink’s annual Formula Rate update. 2.6.

“Annual Termination Fee Credit” means the annual amount of a Termination Fee Balance included in the TRBAA under Section 3.3.4.

2.7.
“Applicable Allocation Percentage” has the meaning set forth in Section 6.3.3. 2.8.

“Applicable Laws and Regulations” means all duly promulgated applicable federal, state, and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, judicial or administrative orders, permits, and other duly authorized actions of any Governmental Authority.

2.9.
“Applied Security Proceeds” means proceeds of Operational Security that Transmission Owner has applied under Section 7.6 to an identified Supplemental

PDF page 290

4

MTRC, prior-period true-up adjustment, Termination Fee, or other payment obligation arising under Article 6 or Section 3.3.4. Proceeds of Construction Security applied to Pre-In-Service Termination Costs or other construction-related obligations are not Applied Security Proceeds and shall be treated as provided in Sections 3.3.2 and 3.3.3. 2.10. “ARR” means annual revenue requirement.

2.11. “Break-Even” has the meaning set forth in Section 6.7.
2.12. “Business Day” means a Business Day as defined in Appendix A to the CAISO Tariff, as amended from time to time.

2.13. “CAISO-Assigned Regional Project” means a regional transmission project approved or designated through a CAISO Tariff process for which CAISO, under the CAISO Tariff or a Commission-accepted methodology, formally assigns a specific percentage or amount of project costs or revenue requirement to the Large Load Facility. The project and assignment must be identified in Schedule 4. A project’s regional designation, general system benefit, or inclusion in a CAISO transmission plan, without a specific assignment to the Large Load Facility, does not by itself make the project a CAISO-Assigned Regional Project.

2.14. “CAISO Requirements” means the CAISO Tariff, the Transmission Control Agreement, any other agreement to which CAISO is a party that is on file with or accepted by the Commission, and any Commission order, regulation, or Commission- accepted methodology applicable to CAISO, each as amended from time to time, together with any CAISO business practice manual or procedure to the extent it implements any of the foregoing.

2.15. “Calendar Day” means every day, including Saturdays, Sundays, federal holidays, and other holidays.

2.16. “Construction Security” has the meaning set forth in Section 7.1. 2.17. “Covered Upgrade” means each Large Load-Driven Upgrade and each DesertLink- owned CAISO-Assigned Regional Project share that is included in Schedule 1 or Schedule 4, as applicable, and for which an Annual MTRC is established under this Agreement.

2.18. “Credit Review Event” means a payment default, credit rating downgrade of the Eligible Customer or an issuing bank that has not yet triggered a Material Adverse Credit Event, a notice of nonrenewal of a Letter of Credit, or another event that, in DesertLink’s reasonable judgment, warrants updated credit information. A Credit Review Event does not, by itself, require delivery of additional Security absent a resulting shortfall.

2.19. “Cumulative Revenue Ledger” means the customer-, Large Load Facility-, project-, and Covered Upgrade-specific record maintained by DesertLink under Section 6.7. The Cumulative Revenue Ledger shall identify the applicable Total Required Revenue

PDF page 291

5

Commitment, Annual MTRC, Qualifying Transmission Revenues, Supplemental MTRC Receipts, Applied Security Proceeds, effective prospective reassignments, other permitted adjustments, and the resulting Remaining Cumulative Revenue Responsibility and Required Operational Security.

2.20. “Cumulative Revenue Responsibility” or “Remaining Cumulative Revenue Responsibility” means the Total Required Revenue Commitment less amounts that have satisfied that commitment under Section 6.7.

2.21. “Dispute Determination” has the meaning set forth in Section 11.5. 2.22. “Distribution Utility” means the public utility, municipal utility, cooperative, or other entity that owns, operates, or is responsible for the distribution facilities to which the Large Load Facility is interconnected or proposed to be interconnected, including its successors and permitted assigns.

2.23. “Effective Date” has the meaning set forth in Section 3.1.
2.24. “Estimated Annual MTRC” means the annual MTRC for a Covered Upgrade calculated from the then-current estimated capital cost using the MTRC Calculation Template in Schedule 5. DesertLink may update the Estimated Annual MTRC as costs change during construction, including when DesertLink requires additional Construction Security.

2.25. “Event of Default” has the meaning set forth in Section 7.11.
2.26. “Final Annual MTRC” means the fixed Annual MTRC for a Covered Upgrade established on the Final MTRC Determination Date using final incurred capital cost and the Project-Specific Levelized Fixed Charge Rate calculated under the MTRC Calculation Template in Schedule 5, including the agreed five percent (5%) annual levelized-depreciation schedule over the twenty (20)-year MTRC Term. The Final Annual MTRC is not recalculated through DesertLink’s Formula Rate or Protocols and may be recalculated only as provided in Section 6.3.1.

2.27. “Final MTRC Determination Date” means the date on which DesertLink establishes the Final Annual MTRC for a Covered Upgrade, which shall occur within one (1) year after the applicable Covered Upgrade enters service, when the actual capital cost of that Covered Upgrade is known and all costs associated with its estimated capital cost have been accounted for.

2.28. “Force Majeure” means any cause beyond the reasonable control of the Party claiming, and without the fault or negligence of such Party, which materially prevents or impairs the performance of such Party’s obligations hereunder, including but not limited to landslides, storms, ice storms, flood, drought, tornado, hurricane, lightning, earthquake, fire, explosion, failure or imminent threat of failure of facilities, supply chain issues, civil disturbance, strike, or other labor disturbance, sabotage, vandalism,

PDF page 292

6

riot, terrorism, blockade, insurrection, war, national emergency, or restraint by any Governmental Authority.

2.29. “Forecast TRBAA Credit” has the meaning set forth in Section 6.8. 2.30. “Formula Rate” means DesertLink’s transmission formula rate template and associated provisions in the TO Tariff, as accepted by the Commission and amended from time to time.

2.31. “Governmental Authority” means any federal, state, local, or other governmental, regulatory, or administrative agency, court, commission, department, board, legislature, rulemaking body, tribunal, or other governmental authority having jurisdiction over a Party, the Large Load Facility, any Large Load-Driven Upgrade, or the services or obligations addressed by this Agreement.

2.32. “Initial Allocation Percentage” has the meaning set forth in Section 6.3.2. 2.33. “Large Load-Driven Upgrades” means the transmission facilities owned or to be constructed by DesertLink and identified in Schedule 1 that the applicable study determines are driven in whole or in part by the Large Load Facility, alone or together with one or more other large loads. Large Load-Driven Upgrades do not include Affected System Upgrades or any facilities whose costs are directly assigned to and paid by Eligible Customer under an Interconnection Agreement and are not included in DesertLink’s rate base. Where a Large Load-Driven Upgrade is an addition to or modification of a facility jointly owned by DesertLink and another entity, the Large Load-Driven Upgrade includes only DesertLink’s ownership share identified in Schedule 1.

2.34. “Large Load Facility” means the new or incremental load facility owned, operated, or proposed to be developed by Large Load Customer and identified in Schedule 1. 2.35. “Large Load Service Commencement Date” means the date on which the Large Load Facility first takes electric service through the CAISO Controlled Grid or otherwise begins receiving service under the applicable CAISO Tariff arrangement, as specified in Schedule 1. If the Large Load Facility is not reflected in a CAISO billing determinant used to assess TAC, Schedule 2 shall identify the applicable wholesale transmission-access, wheeling, or other CAISO Tariff billing arrangement. 2.36. “Letter of Credit” means an irrevocable, transferable standby letter of credit issued for the benefit of DesertLink, meeting the requirements of Schedule 3. 2.37. “Material Adverse Credit Event” means any of the following: (a) a bankruptcy, insolvency, receivership, or similar event described in Section 7.6(e); (b) a reduction in the long-term senior unsecured debt rating of the Eligible Customer or an issuing bank below the standards set out in Section 4 of Schedule 3; (c) loss, cancellation, material impairment, or expiration of Qualifying Retail Security Support without timely replacement; (d) an incorrect, expired, withdrawn, unavailable, or materially

PDF page 293

7

misleading Retail Security Certification, as described in Section 7.7 of this Agreement; or (e) another event that, in DesertLink’s reasonable judgment, materially impairs Eligible Customer's ability to perform its payment or Security obligations under this Agreement.

2.38. “MTRC Term” means, with respect to each Covered Upgrade, the period beginning on and including the applicable Upgrade In-Service Date or Regional Project In- Service Date, as applicable, and ending on the day immediately preceding the twentieth (20th) anniversary of that in-service date (the “MTRC Term End Date”). The first and final Rate Years of the MTRC Term shall be prorated for partial-year service. 2.39. “MTRC Term End Date” has the meaning set forth in the definition of “MTRC Term.”

2.40. “Net Revenue Requirement” means DesertLink’s Net Annual Transmission Revenue Requirement calculated under its Formula Rate for the applicable Rate Year. 2.41. “Notice of Dispute” has the meaning set forth in Section 11.1. 2.42. “Operational Security” has the meaning set forth in Sections 7.2 and 7.5. 2.43. “Outside Date” means the date identified as the Outside Date in Schedule 1, as such date may be extended by written agreement of the Parties.

2.44. “Pre-In-Service Termination Costs” has the meaning set forth in Section 3.3.2. 2.45. “Qualifying Retail Security Support” means retail-customer security for which Eligible Customer has delivered a currently effective Retail Security Certification under Schedule 3.

2.46. “Qualifying Transmission Revenues” or “QTR” has the meaning set forth in Section 6.2.

2.47. “Reconciliation Statement” has the meaning set forth in Section 6.6. 2.48. “Regional Project Allocated ARR” means, for the share of a CAISO-Assigned Regional Project that is owned by DesertLink, included in DesertLink’s Formula Rate, and formally allocated to the Large Load Facility under the applicable CAISO Tariff provision or Commission-accepted methodology, the Annual MTRC for that project share calculated under Section 6.3.5 and the MTRC Calculation Template in Schedule 5, which shall be the Estimated Annual MTRC before the Final MTRC Determination Date and the Final Annual MTRC on and after that date. The Regional Project Allocated ARR is calculated using DesertLink’s allocated share of the project’s estimated or final capital cost, as applicable, by applying the Project-Specific Levelized Fixed Charge Rate calculated under Schedule 5. For purposes of calculating present-worth federal and state income-tax depreciation benefits, Schedule 5 applies a levelized-depreciation rate of five percent (5%) of that allocated capital-cost share in each year of the applicable twenty (20)-year MTRC Term. The resulting Regional

PDF page 294

8

Project Allocated ARR shall be recorded in Schedule 4. If CAISO states the assignment as an annual revenue-requirement share rather than a capital-cost amount, the equivalent capital-cost input shall be determined only under the allocation method established by the CAISO Tariff or a Commission-accepted methodology. 2.49. “Regional Project In-Service Date” means, for a CAISO-Assigned Regional Project owned by DesertLink, the date the project, or a separately identifiable and separately allocated portion of it, is energized, placed in service, and recorded as electric plant in service on DesertLink’s books. Schedule 4 shall identify the expected Regional Project In-Service Date for each project or separately identifiable portion. Inclusion of Construction Work in Progress in rate base before that date does not constitute a Regional Project In-Service Date.

2.50. “Required Operational Security” means the amount of Operational Security required under Section 7.3 and Schedule 3, equal to the nominal Remaining Cumulative Revenue Responsibility except to the extent satisfied by Qualifying Retail Security Support.

2.51. “Required Security Amount” means the aggregate Security then required under this Agreement.

2.52. “Retail Security Certification” means a certification substantially in the form of Exhibit A contained in Schedule 3 of this Agreement, signed by an authorized officer of Eligible Customer, confirming that the Large Load Customer has posted retail security with Eligible Customer that is available, through enforceable draw or application rights or a binding undertaking, to satisfy the corresponding wholesale obligations under this Agreement.

2.53. “Security” means Construction Security or Operational Security, as the context requires.

2.54. “Security Notice” means DesertLink’s written notice of a required increase, restoration, replacement, or other adjustment to Security, including reasonable supporting detail then available.

2.55. “Successor Eligible Customer” means an Eligible Customer that assumes responsibility under Section 6.10.

2.56. “Supplemental MTRC” has the meaning set forth in Section 6.4.
2.57. “Supplemental MTRC Receipts” means payments of Supplemental MTRC received by Transmission Owner from or on behalf of Eligible Customer, excluding Applied Security Proceeds.

2.58. “TAC” means the Transmission Access Charge, as defined in Appendix A to the CAISO Tariff, including the applicable Access Charge components identified in Schedule 2.

PDF page 295

9

2.59. “Termination Cost Reconciliation” has the meaning set forth in Section 3.3.2. 2.60. “Termination Fee” has the meaning set forth in Section 3.3.4. 2.61. “Termination Fee Account” has the meaning set forth in Section 3.3.4. 2.62. “Termination Fee Balance” has the meaning set forth in Section 3.3.4. 2.63. “Total Required Revenue Commitment” has the meaning set forth in Section 6.7. 2.64. “Transmission Revenue Balancing Account Adjustment” or “TRBAA” means the Transmission Revenue Balancing Account Adjustment maintained by DesertLink under Section 5.5 of the TO Tariff, as amended from time to time, and “Transmission Revenue Balancing Account” or “TRBA” means the associated balancing account maintained under that Section.

2.65. “TRBAA Credit” means a Forecast TRBAA Credit or an amount recorded in the TRBA under Section 6.8 for Supplemental MTRC Receipts, Applied Security Proceeds other than Applied Security Proceeds applied to a Termination Fee, Annual Termination Fee Credits, or a duplicate-recovery credit under Section 3.3.3(d) or Section 6.3.5, in each case as flowed through to transmission customers through the TRBAA. A TRBAA Credit is not an input to the MTRC Calculation Template or the Formula Rate.

2.66. “Upgrade In-Service Date” means, with respect to each Large Load-Driven Upgrade, the date on which that Large Load-Driven Upgrade is energized, placed in service, and included as Electric Plant in Service in DesertLink’s rate base. Schedule 1 shall identify the expected Upgrade In-Service Date for each Large Load-Driven Upgrade. Inclusion of Construction Work in Progress in rate base before an upgrade is placed in service does not constitute its Upgrade In-Service Date.

3. Effective Date, Term and Termination
3.1.
Effective Date. This Agreement shall become effective upon execution by the Parties, subject to acceptance by the Federal Energy Regulatory Commission (“FERC” or “Commission”) (if applicable), or, if filed unexecuted, upon the date specified by FERC (the “Effective Date”).

3.2.
Term. This Agreement shall remain in effect from the Effective Date until DesertLink issues a final Reconciliation Statement determining that the Total Required Revenue Commitment for every Covered Upgrade has been satisfied, transferred to a successor, prospectively reassigned, or otherwise discharged. The MTRC Term for each Covered Upgrade begins on its applicable Upgrade In-Service Date or Regional Project In- Service Date and ends on its applicable MTRC Term End Date. Earlier Break-Even remains available if the Total Required Revenue Commitment is satisfied before the applicable MTRC Term End Date. If DesertLink holds a Termination Fee Balance when the Total Required Revenue Commitment is otherwise discharged, this Agreement shall remain in effect for purposes of the Termination Fee Account

PDF page 296

10

provisions in Section 3.3.4 until the Termination Fee Balance has been fully credited or released.

3.3.
Termination. This Agreement may be terminated as follows:
3.3.1.
Termination Before the First Applicable In-Service Date. Before any Large Load-Driven Upgrade reaches its Upgrade In-Service Date and before any DesertLink-owned CAISO-Assigned Regional Project reaches its Regional Project In-Service Date, this Agreement may be terminated upon thirty (30) Calendar Days’ written notice if: (a) the Large Load Service Commencement Date has not occurred by the Outside Date; (b) Eligible Customer or Large Load Customer cancels or abandons the Large Load Facility or associated request for service; (c) the applicable interconnection, access to the CAISO Controlled Grid, or other arrangement necessary for the Large Load Facility is terminated; (d) an Event of Default has occurred and is continuing, or DesertLink exercises a termination right arising from default under this Agreement or an applicable interconnection or transmission service agreement; or (e) Eligible Customer fails to timely execute, maintain, or provide the documentation, financial security, or credit support required under Sections 4.2, 6.3.6, or 7.1, and such failure continues for ten (10) Business Days after written notice from DesertLink or cannot reasonably be cured by the date on which DesertLink must commence or continue physical construction or incur a material noncancelable procurement or construction commitment. Any such termination shall be subject to Applicable Laws and Regulations and any required Commission authorization or acceptance and shall not release or limit the obligations described in Sections 3.3.2 and 3.3.3.

If any Large Load-Driven Upgrade has reached its Upgrade In-Service Date or any DesertLink-owned CAISO-Assigned Regional Project has reached its Regional Project In-Service Date identified in Schedule 4, cancellation, abandonment, termination, or failure of the Large Load Facility to commence or continue service shall not terminate this Agreement. Section 3.3.4 and Articles 6 and 7 shall apply to each Large Load-Driven Upgrade and DesertLink-owned CAISO-Assigned Regional Project for which the applicable in-service date has occurred. Section 6.3.6 shall govern any assigned share of a project owned by another entity.

3.3.2.
Pre-In-Service Termination Costs and Construction Security. If the Large Load Facility, its associated request for service, or any associated Large Load- Driven Upgrade is cancelled, abandoned, or otherwise terminated before an applicable Large Load-Driven Upgrade reaches its Upgrade In-Service Date, Eligible Customer shall be responsible for all actual and reasonable costs prudently incurred or irrevocably committed by DesertLink with respect to that Large Load-Driven Upgrade that have not otherwise been recovered by DesertLink (“Pre-In-Service Termination Costs”). Pre-In-Service Termination Costs include costs incurred before or after the applicable cancellation,

PDF page 297

11

abandonment, or termination to wind down, secure, remove, or otherwise address the unfinished Large Load-Driven Upgrade.

Pre-In-Service Termination Costs include, as applicable:
(a) engineering, design, study, permitting, environmental, siting, land and land- right, procurement, construction, testing, project management, legal, regulatory, and administrative costs;

(b) vendor and contractor cancellation charges, termination charges, change- order costs, restocking charges, demobilization costs, contract closeout costs, and third-party claims;

(c) the costs of securing, preserving, mothballing, relocating, redeploying, dismantling, removing, transporting, storing, selling, or disposing of equipment, materials, and partially completed facilities;

(d) site restoration, environmental remediation, and the restoration or modification of DesertLink’s existing facilities made necessary by the cancellation or abandonment;

(e) Allowance for Funds Used During Construction (“AFUDC”) properly accrued in accordance with the Commission’s Uniform System of Accounts through the date on which the applicable construction activities cease or the applicable project is determined to have been abandoned, excluding AFUDC associated with amounts of Construction Work in Progress included in rate base or otherwise recovered through rates; and

(f) any other costs reasonably incurred by DesertLink as a direct result of the cancellation, abandonment, suspension, or termination.

DesertLink may draw upon and apply Construction Security to Pre-In-Service Termination Costs as such costs are incurred or the associated obligations become fixed and payable. DesertLink may retain Construction Security until all Pre-In-Service Termination Costs are reasonably determinable and DesertLink has served on Eligible Customer a final statement reconciling Pre-In-Service Termination Costs, Construction Security applied, and the recoveries described in this Section, together with supporting information (the “Termination Cost Reconciliation”). Construction Security does not limit Eligible Customer’s underlying liability. Eligible Customer shall pay any deficiency within ten (10) Business Days after receipt of the Termination Cost Reconciliation. The Termination Cost Reconciliation shall become final in the same manner and within the same period as a Reconciliation Statement under Section 6.6, and DesertLink shall release any excess Construction Security after the Termination Cost Reconciliation becomes final, including through resolution of any dispute under Article 11. Construction Security applied under this Section does not constitute Applied Security Proceeds and does not produce a TRBAA Credit except to the extent provided in Section 3.3.3(d). Nothing in this Agreement limits DesertLink’s right to seek recovery of unpaid Pre-In-Service Termination Costs through its Formula Rate or otherwise as the Commission may authorize.

PDF page 298

12

DesertLink shall use commercially reasonable efforts to mitigate Pre-In-Service Termination Costs, provided that DesertLink shall not be required to take any action inconsistent with prudent utility practice, safety requirements, Applicable Laws and Regulations, existing contractual obligations, or the reliable operation of its transmission facilities. The Termination Cost Reconciliation shall reflect, when realized, applicable vendor refunds, insurance recoveries, net salvage proceeds, reuse or redeployment credits, and other recoveries attributable to the cancelled or abandoned scope, but shall not credit amounts representing DesertLink’s lawfully earned return or carrying costs except to the extent necessary to prevent duplicate recovery.

This Section applies separately to each Large Load-Driven Upgrade. If one or more Large Load-Driven Upgrades have reached their Upgrade In-Service Dates when the Large Load Facility or associated request for service is cancelled, this Section shall apply only to the Large Load-Driven Upgrades and portions of the project that have not reached their Upgrade In-Service Dates. The treatment of each Large Load-Driven Upgrade that has reached its Upgrade In-Service Date shall be governed by Section 3.3.4 and Articles 6 and 7.

3.3.3.
Rate Base and Formula Rate Treatment Before an Upgrade In-Service Date. To the extent costs associated with a cancelled or abandoned Large Load- Driven Upgrade that has not reached its Upgrade In-Service Date have been included in Construction Work in Progress or any other component of DesertLink’s rate base, DesertLink shall, consistent with the Commission’s Uniform System of Accounts, its Formula Rate and Protocols, and other Applicable Laws and Regulations:

(a) remove, reclassify, or otherwise exclude such costs from rate base to the extent required by applicable Commission accounting and ratemaking requirements;

(b) reflect that treatment in the next practicable Annual Update and corresponding true-up;

(c) cease accruing AFUDC to the extent and at the time required by the Commission’s accounting requirements; and

(d) make any adjustment or credit necessary to prevent DesertLink from recovering the same cost both through Construction Security or another payment by Eligible Customer and through its Formula Rate; provided that any such credit to transmission customers shall be recorded in the TRBA and flowed through to transmission customers through the TRBAA as provided in Section 6.8, and not through a revenue credit or other input to the Formula Rate.

Any depreciation, amortization, or other amount recovered through DesertLink’s Formula Rate that represents recovery of the same underlying capital or expense included in Pre-In-Service Termination Costs shall be reflected, without duplication, in the Termination Cost Reconciliation under Section 3.3.2. Application of Construction Security shall not require DesertLink to refund or

PDF page 299

13

surrender any return, carrying cost, tax allowance, or other amount lawfully recovered for a period during which DesertLink’s investment was properly included in rate base, except to the extent necessary to prevent duplicate recovery.

This Section 3.3.3 applies only to a Large Load-Driven Upgrade, or portion thereof, that has not reached its Upgrade In-Service Date.

3.3.4.
Effect of Cancellation After an Upgrade or Regional Project In-Service Date. After any Large Load-Driven Upgrade reaches its Upgrade In-Service Date or any DesertLink-owned CAISO-Assigned Regional Project reaches its Regional Project In-Service Date specified in Schedule 4, Eligible Customer shall promptly notify DesertLink if Eligible Customer or Large Load Customer anticipates or becomes aware of the cancellation, abandonment, downsizing, curtailment, permanent cessation, or material reduction of service at the Large Load Facility.

Cancellation, abandonment, suspension, downsizing, termination, or failure of the Large Load Facility to commence or continue service shall not, by itself:

(a) terminate this Agreement;
(b) require the removal from rate base of a Large Load-Driven Upgrade or a DesertLink-owned CAISO-Assigned Regional Project that has reached its in- service date;

(c) reduce or cap any Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, or remaining Cumulative Revenue

Responsibility; or
(d) terminate, reduce, or excuse Eligible Customer’s obligation to pay the Supplemental MTRC and prior-period true-up adjustments under Section 6.6, maintain and replenish Operational Security, or satisfy the remaining Cumulative Revenue Responsibility.

Upon any effective termination of this Agreement, or upon the permanent cessation of service by the Large Load Facility following an applicable Upgrade In-Service Date or Regional Project In-Service Date, Eligible Customer shall pay DesertLink a one-time lump-sum termination fee equal to the Remaining Cumulative Revenue Responsibility, less any Supplemental MTRC that has been billed and remains unpaid as of the effective termination or cessation date (the “Termination Fee”). DesertLink shall calculate the Termination Fee separately for each Covered Upgrade that has reached its applicable in-service date from the most recently served Cumulative Revenue Ledger, updated through the effective termination or cessation date for then-known Qualifying Transmission Revenues, Supplemental MTRC Receipts, Applied Security Proceeds, billed and unpaid Supplemental MTRC, and any effective prospective reassignment. Billed and unpaid Supplemental MTRC excluded from the Termination Fee remains separately payable and secured; its later payment, satisfaction through Applied Security Proceeds, or direct recovery shall reduce the Cumulative Revenue

PDF page 300

14

Responsibility. The Termination Fee is due thirty (30) Calendar Days after DesertLink’s invoice. It is an accelerated contractual termination charge, not a penalty or consideration for future transmission service. Its receipt in full discharges only the remaining Cumulative Revenue Responsibility included in the fee. The Termination Fee is not a Supplemental MTRC Receipt, Applied Security Proceeds, prepayment for future transmission service, customer advance for construction, contribution in aid of construction, or reduction to rate base. DesertLink shall administer the Termination Fee only as provided in Section 3.3.4 and Article 6.

Each Large Load-Driven Upgrade that has reached its Upgrade In-Service Date and each DesertLink-owned CAISO-Assigned Regional Project for which an Annual MTRC has been established shall remain subject to the applicable Formula Rate and Protocols for so long as it is properly includable in rate base under applicable Commission requirements. The associated payment, Security, reconciliation, and TRBAA Credit obligations shall continue in accordance with Articles 6 and 7, subject to any prospective reassignment or adjustment authorized under the CAISO Tariff or a Commission-accepted methodology, or transfer to a Successor Eligible Customer under Section 6.10.

DesertLink shall hold each Termination Fee, and any proceeds of Operational Security applied to its payment, in a separately identified, interest bearing Termination Fee Account for the applicable Covered Upgrade. The amounts in that account, together with actual earnings and less amounts credited or released, constitute the “Termination Fee Balance.” For each Covered Upgrade, the Annual Termination Fee Credit for each Rate Year remaining in the MTRC Term shall equal the applicable Annual MTRC, prorated for any partial Rate Year, but shall not exceed the then-available Termination Fee Balance. In the final Rate Year of the MTRC Term, the Annual Termination Fee Credit shall include the entire remaining Termination Fee Balance, including actual earnings, so that the Termination Fee Account is reduced to zero, subject to any amount required to be released under this Section 3.3.4. DesertLink shall include each Annual Termination Fee Credit in the TRBAA only for the Rate Year for which it is scheduled. The Termination Fee Balance shall be separately accounted for as a deferred liability pending its scheduled annual TRBAA treatment, shall not be included in rate base, and shall not itself be a TRBAA Credit or Formula Rate input. If a prospective reassignment becomes effective after receipt of a Termination Fee, DesertLink shall release the portion of the Termination Fee Balance attributable to the reassigned responsibility, together with actual earnings, and prospectively adjust the remaining Annual Termination Fee Credits.

If the Commission subsequently requires DesertLink to retire, remove, reclassify, or exclude all or a portion of an in-service Large Load-Driven Upgrade or DesertLink-owned CAISO-Assigned Regional Project from rate base, DesertLink shall make corresponding prospective adjustments to the applicable Annual MTRC, Regional Project Allocated ARR, Total Required Revenue

PDF page 301

15

Commitment, Cumulative Revenue Responsibility, Supplemental MTRC, and Operational Security. Such adjustments shall prevent Eligible Customer from remaining responsible under this Agreement for costs that are no longer included in DesertLink’s transmission revenue requirement, without requiring a refund or reopening of amounts properly determined for a prior Rate Year.

If, at the time of cancellation or abandonment, one or more Large Load-Driven Upgrades have reached their Upgrade In-Service Dates or a DesertLink-owned CAISO-Assigned Regional Project has reached its project in-service date, and one or more other upgrades or project shares have not, Sections 3.3.2 and 3.3.3 shall apply to Large Load-Driven Upgrades and project scope that have not reached their applicable in-service dates; this Section 3.3.4 and Articles 6 and 7 shall apply to the upgrades and DesertLink-owned project shares that have reached their applicable in-service dates; and Section 6.3.6 shall continue to govern any assigned share of a project owned by another entity.

3.3.5.
Mutual Termination. The Parties may terminate this Agreement by mutual written consent only after addressing all incurred construction costs, the continuing Cumulative Revenue Responsibility, Supplemental MTRC amounts, prior-period true-up adjustments, and Security. No termination is effective to extinguish such obligations unless expressly accepted or approved by FERC. 3.4.

Regulatory Effect of Termination. No termination shall become effective until the Parties comply with all Applicable Laws and Regulations, including any required notice to or acceptance by FERC. A regulatory rejection, cancellation, downsizing, curtailment, cessation, Force Majeure event, or termination shall not excuse incurred construction costs or the obligations arising on or after an applicable Upgrade In- Service Date or Regional Project In-Service Date unless FERC expressly determines otherwise.

3.5.
Effect of Termination. Termination does not release Eligible Customer from obligations arising under Articles 4, 6, or 7, including future annual Supplemental MTRC payments, prior-period true-up adjustments, and Security maintenance and replenishment, until the Cumulative Revenue Responsibility is finally satisfied or transferred in accordance with this Agreement. Upon DesertLink’s receipt of the Termination Fee in full, no further Supplemental MTRC shall accrue for any period after the effective termination or cessation date, subject to final true-ups and reconciliation for periods before that date. Security does not limit the underlying liability. The Large Load Customer’s information, notice, authorization, and cooperation obligations stated in its Limited Acknowledgment also survive.

4. Transmission Project
4.1.
Design, Procurement, and Construction. Subject to Eligible Customer’s execution of this Agreement and the relevant Interconnection Agreement, delivery of Construction Security under Section 7.1, and satisfaction of Section 4.2, DesertLink shall design, procure, construct, install, and own the Large Load-Driven Upgrades

PDF page 302

16

described in the relevant Interconnection Agreement and Schedule 1, using reasonable efforts to meet the applicable construction schedule and expected Upgrade In-Service Dates.

Eligible Customer shall maintain Construction Security under Section 7.1 sufficient to secure DesertLink’s incurred and committed construction costs and the Pre-In-Service Termination Costs described in Section 3.3.2. Construction Security shall apply separately to each Large Load-Driven Upgrade until that upgrade reaches its Upgrade In-Service Date and the conditions for release or conversion under Section 7.2 have been satisfied.

If different Large Load-Driven Upgrades reach their Upgrade In-Service Dates on different dates, Construction Security shall continue to apply to each Large Load- Driven Upgrade and portion of the project that has not reached its Upgrade In-Service Date, notwithstanding the release or conversion of Construction Security attributable to an upgrade that has entered service.

Upon cancellation, abandonment, or termination, before an applicable Large Load- Driven Upgrade reaches its Upgrade In-Service Date, DesertLink may draw, retain, and apply Construction Security in accordance with Sections 3.3.2 and 7.1 and the relevant Interconnection Agreement. DesertLink shall not be required to take action inconsistent with its safety practices, design criteria, construction procedures, Applicable Laws and Regulations, or the reliable operation of its transmission facilities.

4.2.
Affected Systems
4.2.1. Identification and Coordination. Eligible Customer shall cooperate with DesertLink, CAISO, each affected Participating TO, and each other Affected System Owner in identifying and studying potential impacts of the interconnection or service of the Large Load Facility on any Affected System.

4.2.2. Required Affected System Arrangements. For each Affected System Upgrade identified through an applicable study, Eligible Customer shall timely enter into and maintain an Affected System Arrangement with the applicable Affected System Owner. Each Affected System Arrangement shall address, as applicable:

(a) study, engineering, design, procurement, construction, testing, and energization responsibilities;

(b) responsibility for the costs of the Affected System Upgrade;
(c) responsibility for cancellation, abandonment, demobilization, equipment removal, disposition, remediation, restoration, AFUDC, and other costs resulting from cancellation or failure of the Large Load Facility to proceed;

(d) construction-period and post-in-service payment obligations and financial security or credit support sufficient to protect the Affected System Owner and its other customers against cost shifting;

PDF page 303

17

(e) applicable invoicing, reconciliation, true-up, refund, and release procedures; and

(f) any Commission filing, acceptance, or other regulatory authorization required for the Affected System Arrangement.

4.2.3. Evidence Before DesertLink Construction. At least thirty (30) Calendar Days before DesertLink’s scheduled commencement of physical construction, and in all events before any notice to proceed for physical construction may occur or DesertLink incurs a material noncancelable procurement or construction commitment, Eligible Customer shall provide DesertLink:

(a) a complete copy of each executed Affected System Arrangement;
(b) evidence that all financial security or credit support required to be effective before construction under each Affected System Arrangement has been provided;

(c) evidence of any required Commission filing, acceptance, or other regulatory authorization; and

(d) a certification that each Affected System Arrangement remains in full force and effect and that Eligible Customer is not in default thereunder.

DesertLink may permit specifically identified preliminary engineering, procurement, or other limited activities to proceed before satisfaction of this Section by written notice. Such permission shall not waive any requirement of this Section or obligate DesertLink to commence or continue physical construction. 4.2.4. Continuing Obligation. Eligible Customer shall promptly provide DesertLink a copy of any material amendment, replacement, termination notice, default notice, demand upon financial security or credit support, or other material notice concerning an Affected System Arrangement. Eligible Customer shall maintain each required Affected System Arrangement and all financial security or credit support required thereunder until the obligations secured by that arrangement have been finally satisfied, transferred, or released.

4.2.5. Later-Identified Affected Systems. If an Affected System or Affected System Upgrade is identified after DesertLink has commenced work, Eligible Customer shall promptly enter into the required Affected System Arrangement and provide the documentation required by this Section. Subject to the applicable tariffs and agreements, DesertLink may suspend further work, procurement, energization, or service to the extent reasonably necessary to avoid additional exposure until the requirement is satisfied.

4.2.6. Failure to Satisfy Requirements. Eligible Customer’s failure to timely execute, maintain, or provide evidence of an Affected System Arrangement or required financial security or credit support constitutes a material default under this Agreement. Subject to Applicable Laws and Regulations and the applicable tariffs and agreements, DesertLink may: (a) decline to commence or continue construction or material procurement commitments; (b) suspend work, energization, or service;

PDF page 304

18

(c) exercise the termination right in Section 3.3.1; and (d) recover all resulting Pre- In-Service Termination Costs and other amounts payable under this Agreement. 4.2.7. Confidentiality. Documents provided under this Section shall be subject to the confidentiality protections in Section 6.12. Eligible Customer may redact commercially sensitive provisions unrelated to the requirements of this Section, but may not redact information reasonably necessary for DesertLink to verify the scope, effectiveness, cost responsibility, financial security or credit support, termination protection, or continuing enforceability of the Affected System Arrangement. 4.2.8. Separate Administration. Costs, revenues, payments, and financial security or credit support arising under an Affected System Arrangement shall be administered under that arrangement and the applicable Affected System Owner’s tariff. Such amounts shall not be included in any Annual MTRC, Total Required Revenue Commitment, Supplemental MTRC, Cumulative Revenue Responsibility, or TRBAA Credit, except to the extent expressly authorized by the Commission and necessary to prevent duplicate recovery.

5. Regulatory Approval(s)
5.1.
FERC Filing. This Agreement is the form of agreement required under Sections 10.9 and 10A.6 of the TO Tariff as a condition of DesertLink’s design, procurement, and construction of Large Load-Driven Upgrades. Consistent with 18 C.F.R. § 35.1(g), a conforming, executed Agreement entered into under the Commission-accepted pro forma with populated Schedules generally shall not require an individual filing under Section 205 of the Federal Power Act. DesertLink shall file an unexecuted Agreement or an Agreement containing a material deviation, and any other agreement required to be filed by Commission order or rule. If FERC does not accept a required filing in its entirety, the Parties shall use reasonable efforts to amend and refile it; regulatory rejection does not excuse incurred construction costs or payment, Security, and true-up obligations for facilities placed in service, except to the extent FERC expressly determines otherwise.

6. Cost Recovery
6.1.
Cost Recovery and Minimum Contribution. DesertLink shall include the Large Load-Driven Upgrades in its Formula Rate to the extent the project costs are properly includable under the Formula Rate, the Protocols, and applicable law. This Agreement does not remove any Covered Upgrade from rate base or require a capital-cost reimbursement. The fixed twenty (20)-year Annual MTRC for each Covered Upgrade is instead calculated under the MTRC Calculation Template in Schedule 5, initially using estimated cost and then using final incurred cost on the applicable Final MTRC Determination Date. DesertLink shall recover its formula-rate revenue requirement through TAC and shall flow TRBAA Credits through to transmission customers through the TRBAA as provided in Section 6.8. Amounts received under this Agreement are not inputs to the Formula Rate, and this Agreement does not require any modification of the Formula Rate. Eligible Customer shall pay a Supplemental

PDF page 305

19

MTRC only to the extent forecast or actual Qualifying Transmission Revenues are less than the applicable Annual MTRC. The Annual MTRC is a revenue floor, not an additive charge, and does not alter CAISO cost allocation or DesertLink plant accounting.

Eligible Customer acknowledges that DesertLink will incur costs and undertake planning, engineering, procurement, and construction in reliance on the Large Load Facility’s development and operation. Eligible Customer therefore accepts the wholesale payment and Security obligations in this Agreement. Any retail recovery from the Large Load Customer remains governed exclusively by applicable state law and Eligible Customer’s retail arrangements.

Affected System Upgrades and the associated costs, revenues, payments, and financial security or credit support are governed by Section 4.2 and the applicable Affected System Arrangement. Unless expressly authorized by the Commission, no Affected System Upgrade or associated revenue requirement shall be included in DesertLink’s Annual MTRC, Total Required Revenue Commitment, Supplemental MTRC, Cumulative Revenue Responsibility, or TRBAA Credit.

6.2.
Qualifying Transmission Revenues. For each Rate Year or partial Rate Year, “Qualifying Transmission Revenues” means wholesale transmission revenues paid by or on behalf of Eligible Customer under the CAISO Tariff or another Commission- accepted arrangement that are attributable to service to the Large Load Facility and reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement. Qualifying Transmission Revenues include: (a) the portion of TAC revenue attributable to the Large Load Facility and allocable to DesertLink under the reproducible methodology in Schedule 2; and (b) Wheeling Access Charges and other wholesale transmission-access, wheeling, or transmission-service charges paid to CAISO, a Participating TO, or a non-PTO transmission or load-serving entity for deliveries serving the Large Load Facility, but only to the extent they reduce transmission revenues otherwise collected through TAC or directly credit DesertLink’s Net Revenue Requirement and are not otherwise reflected as a credit in calculating the Annual MTRC, the Supplemental MTRC, or a TRBAA Credit. Qualifying Transmission Revenues do not include Supplemental MTRC Receipts, Applied Security Proceeds, retail charges, or amounts that do not reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement.

6.3.
Annual MTRC and Allocation.
6.3.1. Upgrade-Specific MTRC Calculation. DesertLink shall calculate a separate Annual MTRC for each Covered Upgrade solely under the MTRC Calculation Template in Schedule 5. Before the Final MTRC Determination Date, DesertLink shall calculate and update the Estimated Annual MTRC from the then-current estimated capital cost. Within one (1) year after the applicable Covered Upgrade enters service, when the actual capital cost of that Covered Upgrade is known and all costs associated with its estimated capital cost have been accounted for,

PDF page 306

20

DesertLink shall establish the Final Annual MTRC using final incurred capital cost and the Project-Specific Levelized Fixed Charge Rate calculated under Schedule 5. Schedule 5 shall calculate the Project-Specific Levelized Fixed Charge Rate by: (i) determining the present-worth revenue requirement using the applicable capital structure, cost of debt, return on equity, federal and state income-tax rates, income- tax conversion factor, and levelized-depreciation schedule; (ii) applying a depreciation rate of five percent (5%) of the applicable capital cost input in each year of the twenty (20)-year MTRC Term to calculate present-worth federal and state income-tax depreciation benefits; (iii) annualizing the resulting present-worth revenue requirement over the MTRC Term using the applicable after-tax discount rate and annualization factor; and (iv) adding the fixed expense allocator specified in Schedule 5. The Final Annual MTRC shall equal the applicable final incurred capital cost multiplied by the resulting Project-Specific Levelized Fixed Charge Rate. No component reflected in the Project-Specific Levelized Fixed Charge Rate or the fixed expense allocator shall be added again as a separate component of the Annual MTRC. The Final Annual MTRC and the Schedule 5 inputs used to calculate it are fixed as of the Final MTRC Determination Date and shall not be recalculated for later changes in actual cost, Formula Rate inputs, or other cost-of- service components, except to correct an error or fraud, to implement an effective prospective reassignment, to implement a final FERC order applicable to the calculation, or to reflect, prospectively, a change in (i) DesertLink’s return on equity component of its Formula Rate, resulting from a final FERC order accepting or approving such change, or (ii) applicable federal or state income tax rates or income tax law enacted after the Final MTRC Determination Date; provided that, the five percent (5%) annual levelized-depreciation schedule in Schedule 5 shall remain fixed for the MTRC Term unless a final FERC order requires otherwise. If DesertLink adjusts the Final Annual MTRC after the Final MTRC Determination Date pursuant to the foregoing provision, DesertLink shall update the MTRC Calculation Template and serve it upon Eligible Customer in accordance with the notice provisions contained in this Agreement. Upon such service to Eligible Customer, the updated MTRC Calculation Template shall replace the existing MTRC Calculation Template in its entirety and become effective on the date of such service. The foregoing effectiveness of an updated MTRC Calculation Template does not preclude Eligible Customer from disputing any change to the MTRC Calculation Template pursuant to Article 11 of this Agreement. Any resulting adjustment to the Total Required Revenue Commitment shall apply only to the Rate Years remaining in the MTRC Term as provided in Section 6.7.

Each Annual MTRC shall apply for its separate twenty (20)-year MTRC Term, with the initial and final partial Rate Years prorated based on the number of monthly Billing Periods in the applicable Rate Year during which the Covered Upgrade is in service. Schedule 1 shall identify the initial Estimated Annual MTRC and initial projected Total Required Revenue Commitment for each Large Load-Driven Upgrade, and Schedule 5 shall record the Final MTRC Determination Date, Final Annual MTRC, Total Required Revenue Commitment, and the completed

calculation for each Covered Upgrade. Schedule 4 shall provide the corresponding

PDF page 307

21

project-specific information for a DesertLink-owned CAISO-Assigned Regional Project, if applicable.

6.3.2. Initial Allocation. Schedule 1 shall identify, separately for each Large Load- Driven Upgrade, the percentage of the upgrade initially allocated to the Large Load Customer under this Agreement (the “Initial Allocation Percentage”). The Initial Allocation Percentage shall be determined using the applicable final study and allocation methodology and shall account for:

(a) Large Load Customers studied individually, jointly, or in a cluster;
(b) the extent to which two or more Large Load Customers caused the need for or share a Large Load-Driven Upgrade;

(c) differing requested service levels, development phases, and facility configurations; and

(d) any portion of the facility determined at the outset to serve other transmission system needs or customers.

The aggregate percentages allocated to all Large Load Customers for a Large Load- Driven Upgrade shall not exceed one hundred percent (100%). Any portion not allocated to a Large Load Customer shall be excluded from the Annual MTRC allocable to any Large Load Customer and remain subject to the otherwise- applicable CAISO cost allocation and rate recovery requirements. 6.3.3. Applicable Allocation Percentage. For each Large Load-Driven Upgrade, the “Applicable Allocation Percentage” shall equal the Initial Allocation Percentage identified in Schedule 1, as adjusted prospectively by any reassignment effective under Section 6.9 or as otherwise required by a final Commission order or applicable tariff provision. A cancellation, abandonment, downsizing, curtailment, permanent cessation, or material reduction of service by the Large Load Customer shall not, by itself, reduce the Applicable Allocation Percentage. 6.3.4. Annual MTRC Allocation. The Annual MTRC applicable to Eligible Customer shall equal the Annual MTRC for the Covered Upgrade as a whole multiplied by the Applicable Allocation Percentage; provided that, where Schedule 5 applies that percentage to capital cost or otherwise calculates the Annual MTRC for an already allocated project share, the resulting Annual MTRC is already allocated and the percentage shall not be applied again. DesertLink shall maintain the calculation separately by Large Load Customer, Large Load Facility, and Covered Upgrade. The aggregate Annual MTRCs allocated to all large load customers shall not exceed the Annual MTRC for the Covered Upgrade as a whole.

6.3.5. CAISO-Assigned Regional Projects Owned by DesertLink. For each CAISO- Assigned Regional Project owned by DesertLink and included in its Formula Rate, DesertLink shall calculate separately the Regional Project Allocated ARR attributable to the specific share formally assigned to the Large Load Facility. The Regional Project Allocated ARR shall be calculated solely under the MTRC Calculation Template in Schedule 5, using DesertLink’s allocated share of the

PDF page 308

22

project’s estimated capital cost before the Final MTRC Determination Date and its allocated share of final incurred capital cost on that date, and shall be established, updated, and fixed in the same manner and on the same schedule that Section 6.3.1 provides for other Covered Upgrades. The resulting Annual MTRC shall be included in the Supplemental MTRC calculation and the Total Required Revenue Commitment beginning on the Regional Project In-Service Date. The allocated share shall be determined under the applicable allocation under the CAISO Tariff or Commission-accepted methodology and the project-specific information in Schedule 4. No portion assigned to other customers, other facilities, or broader regional needs shall be included. Before the Regional Project In-Service Date, any costs of a cancelled or abandoned project shall be treated under the applicable CAISO Tariff, Commission order, and any abandoned-plant incentive specifically authorized for that project. This Agreement does not create a separate pre-service payment or Construction Security obligation solely because CAISO has assigned a regional project share to Large Load Facility. Any pre-service payment, contribution, or security required by the CAISO Tariff, an applicable Interconnection Agreement, or another Commission-accepted arrangement remains due under that authority and shall be identified in Schedule 4. Any abandoned-plant recovery, customer payment, or security proceeds shall receive the accounting and rate treatment required by the Commission, and any credit necessary to prevent duplicate recovery of the same costs shall be recorded in the TRBA and flowed through to transmission customers through the TRBAA as provided in Section 6.8. Any prospective adjustment or reassignment of the share assigned to the Large Load Facility shall occur only as provided by the CAISO Tariff or a Commission- accepted methodology. Rate base inclusion, depreciation, and other accounting for the underlying project share remain subject to the Formula Rate, the Protocols, and the Commission's Uniform System of Accounts; this Section 6.3.5 governs only the calculation of the Annual MTRC applicable to the Large Load Facility under this Agreement.

6.3.6. CAISO-Assigned Regional Projects Owned by Another Entity. If CAISO formally assigns a specific share of a CAISO-Assigned Regional Project to the Large Load Facility and that project is not owned by DesertLink or is not included in DesertLink’s Formula Rate, Eligible Customer shall satisfy the assigned share under the CAISO Tariff or enter into and maintain the required arrangement with the project owner or other responsible entity. The arrangement shall address, as applicable, payment of assigned costs and revenue responsibility, construction and cancellation obligations, security or credit support, invoicing, reconciliation, true- up, refund, release, and any required regulatory filing or acceptance. Eligible Customer shall provide DesertLink a copy of the executed arrangement or other evidence reasonably sufficient to demonstrate compliance, including the amount and basis of the assigned share, the billing party, payment terms, and required security. Eligible Customer shall provide the required arrangement or evidence by the deadline specified in Schedule 4, which shall be no later than the earliest applicable deadline under the CAISO Tariff or project-owner arrangement and, where the

PDF page 309

23

assignment is known before construction, before the project owner commences construction. If CAISO makes the assignment after construction has commenced or after the project enters service, Eligible Customer shall comply within the period specified by CAISO or the project owner and provide evidence to DesertLink promptly. Failure to comply is an Event of Default if not cured as provided in Section 7.11(c).

Amounts owed to another project owner are not included in any Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, Supplemental MTRC, Cumulative Revenue Responsibility, or TRBAA Credit unless the amount is included in DesertLink’s Formula Rate and Schedule 4 expressly identifies it as DesertLink’s assigned share. The applicable tariff or project-owner arrangement shall identify and apply any credits required to prevent duplicate recovery of the same assigned share through both a direct charge and a transmission rate. Payments to another owner satisfy only the corresponding obligation under that tariff or arrangement and do not reduce the Cumulative Revenue Responsibility owed to DesertLink unless they satisfy the same underlying obligation included in DesertLink’s Formula Rate. The Eligible Customer’s obligations under this Section survive termination of this Agreement and cessation of service until the assigned share has been paid or assumed by a successor and the obligation has been discharged, transferred, or released under the applicable CAISO Tariff or project-owner arrangement by the entity entitled to enforce it. 6.4.

Supplemental MTRC. Beginning on the in-service date of each Covered Upgrade, Eligible Customer shall pay the positive shortfall, if any, between the applicable Annual MTRC, prorated for a partial Rate Year based on the number of monthly Billing Periods in that Rate Year during which the Covered Upgrade is in service, and Qualifying Transmission Revenues attributable to the Large Load Facility during the corresponding Rate Year or partial Rate Year. Until the Final MTRC Determination Date, billing shall use the Estimated Annual MTRC. Upon initial finalization, the Final Annual MTRC shall apply back to the applicable in-service date, and estimated charges shall be reconciled in the next Reconciliation Statement under Section 6.6. Thereafter, the calculation shall use the Final Annual MTRC, subject to adjustments permitted by Section 6.3.1. Qualifying Transmission Revenues attributable to a specific Covered Upgrade shall be applied to that upgrade. Qualifying Transmission Revenues not attributable to a specific Covered Upgrade shall be allocated among the Covered Upgrades then in their MTRC Terms pro rata based on their respective prorated Annual MTRCs for the applicable period.

The calculation may be expressed as:
Supplemental MTRC = max (applicable Annual MTRC − Qualifying Transmission Revenues, $0).

The Annual MTRC is not an annual true-up of project cost or Formula Rate inputs. Annual reconciliation is limited to Qualifying Transmission Revenues, Supplemental MTRC invoices and receipts, Applied Security Proceeds, TRBAA Credits, partial-year

PDF page 310

24

proration, effective prospective reassignment, and correction of error, fraud, a final FERC order applicable to the calculation, and any prospective recalculation of the Final Annual MTRC permitted by Section 6.3.1.

6.5.
Invoice. With each Annual Projection, DesertLink shall forecast Qualifying Transmission Revenues and calculate the projected Supplemental MTRC using the applicable fixed or estimated Annual MTRC from Schedule 5, increased or reduced by any prior-period true-up adjustment under Section 6.6. DesertLink shall invoice the forecasted Supplemental MTRC for the applicable Rate Year or partial Rate Year in equal monthly installments for each Billing Period in that Rate Year during which the Covered Upgrade is in service; for a full Rate Year, the projected Supplemental MTRC shall be invoiced in twelve (12) equal monthly installments. Each installment is payable within thirty (30) Calendar Days after receipt of the invoice. If a Covered Upgrade reaches its applicable in-service date during a Rate Year for which the Annual Projection did not include a projected Supplemental MTRC for that Covered Upgrade, DesertLink shall promptly forecast Qualifying Transmission Revenues and invoice the prorated Supplemental MTRC for the remaining Billing Periods of that Rate Year. DesertLink shall include the projected Supplemental MTRC, including any prior-period true-up adjustment, as a Forecast TRBAA Credit in the next annual TRBAA under Section 6.8. Only cash actually received by DesertLink, or Applied Security Proceeds actually applied by DesertLink, constitutes an actual receipt for purposes of Sections 6.6 through 6.8. Concurrently with each Annual Projection, DesertLink shall provide Eligible Customer upgrade-specific workpapers showing the applicable Annual MTRC, forecast Qualifying Transmission Revenues, projected Supplemental MTRC, any prior-period true-up adjustment, Forecast TRBAA Credit, Total Required Revenue Commitment, and Required Operational Security. 6.6.

Annual Reconciliation Statement. In connection with each Annual Update, DesertLink shall determine the actual Supplemental MTRC obligation using actual Qualifying Transmission Revenues and the applicable fixed or estimated Annual MTRC from Schedule 5. DesertLink shall identify, by Eligible Customer and Covered Upgrade, the opening unpaid billed Supplemental MTRC balance, Supplemental MTRC invoiced during the Rate Year, cash received by DesertLink, Applied Security Proceeds applied to identified obligations, direct recoveries, closing unpaid billed balance, and each Annual Termination Fee Credit. Concurrently with each Annual Update, DesertLink shall serve on Eligible Customer a Reconciliation Statement containing those determinations, the updated Cumulative Revenue Ledger, Required Operational Security recalculated under Section 7.4, a reconciliation of the Forecast TRBAA Credit to actual amounts recorded in the TRBA, and supporting workpapers. An unpaid Supplemental MTRC remains due from Eligible Customer and, when later received or satisfied through Applied Security Proceeds, is recorded in the TRBA only in the Rate Year of receipt or application. The Reconciliation Statement shall not reopen the Final Annual MTRC or Total Required Revenue Commitment except as expressly allowed by Section 6.3.1.

The difference between the Supplemental MTRC billed for a Rate Year, excluding any prior-period true-up adjustment included in that billing, and the actual Supplemental

PDF page 311

25

MTRC determined in the Reconciliation Statement for that Rate Year shall constitute a “prior-period true-up adjustment,” which shall increase (if under-billed) or reduce (if over-billed) the projected Supplemental MTRC invoiced under Section 6.5 following the next Annual Projection. If no further Supplemental MTRC will be invoiced under this Agreement, DesertLink shall invoice any under-billed amount, payable within thirty (30) Calendar Days after receipt of the invoice, and shall refund any over-billed amount to Eligible Customer within thirty (30) Calendar Days after service of the Reconciliation Statement. No interest shall accrue on the Supplemental MTRC or on any prior-period true-up adjustment, invoice, refund, or other adjustment of the Supplemental MTRC between DesertLink and Eligible Customer. Any refund to Eligible Customer of an amount previously recorded as a TRBAA Credit shall be reversed in the TRBA when paid, and any under-billed amount later received shall be recorded in the TRBA when received, in each case as provided in Section 6.8. Any amount returned by DesertLink to transmission customers through the TRBAA shall include interest as provided in Section 5.5 of the TO Tariff.

A Reconciliation Statement shall become final on the earlier of (a) Eligible Customer’s written acceptance of the Reconciliation Statement or (b) ninety (90) Calendar Days after service, unless before that date Eligible Customer serves a Notice of Dispute under Section 11.1 identifying with reasonable specificity the items disputed. If a Notice of Dispute is timely served, the undisputed portions of the Reconciliation Statement shall become final on the date that would otherwise apply, and the disputed items shall become final upon the applicable Dispute Determination under Section 11.5. A final Reconciliation Statement may be revised only to implement a Dispute Determination, to reflect CAISO resettlements or other corrected data as provided in Schedule 2, or to correct errors or fraud. Finality of a Reconciliation Statement under this Agreement does not affect the Commission’s review and approval of any TRBAA.

For purposes of this Agreement, Supplemental MTRC Receipts exclude Applied Security Proceeds. Applied Security Proceeds shall be counted only when DesertLink applies such proceeds to satisfy an identified payment obligation and shall reduce that obligation dollar-for-dollar. The posting, maintenance, replenishment, drawing, or holding of Security shall not, by itself, constitute a Supplemental MTRC Receipt, an Applied Security Proceed, satisfaction of the Cumulative Revenue Responsibility, or a TRBAA Credit.

No amount shall be counted both as a Supplemental MTRC Receipt and as an Applied Security Proceed. If DesertLink receives payment of an obligation previously satisfied through Applied Security Proceeds, DesertLink shall not count the subsequent payment toward the Cumulative Revenue Responsibility or a TRBAA Credit and shall instead return the duplicative amount, release an equivalent amount of Security, or, with supporting notice to Eligible Customer, apply the amount to another then- outstanding obligation under this Agreement.

6.7.
Cumulative Revenue Responsibility and Break-Even. DesertLink shall maintain a Cumulative Revenue Ledger for each Covered Upgrade and shall update it at least

PDF page 312

26

annually in connection with the Annual Update. DesertLink shall include an updated Cumulative Revenue Ledger statement, with supporting workpapers, in each Reconciliation Statement served on Eligible Customer under Section 6.6. For each Covered Upgrade, the Total Required Revenue Commitment equals the Final Annual MTRC multiplied by twenty (20), adjusted only for partial-year proration and any prospective recalculation of the Final Annual MTRC permitted by Section 6.3.1, which shall apply only to the Rate Years remaining in the MTRC Term after the recalculation takes effect. Until the Final MTRC Determination Date, the projected Total Required Revenue Commitment shall equal the Estimated Annual MTRC multiplied by twenty (20).

Remaining Cumulative Revenue Responsibility equals the applicable Total Required Revenue Commitment less:

(a) cumulative Qualifying Transmission Revenues;
(b) cumulative Supplemental MTRC Receipts;
(c) cumulative Applied Security Proceeds;
(d) effective prospective reassignment credits; and
(e) cash amounts received and applied toward the Termination Fee, excluding any portion satisfied through Applied Security Proceeds already counted under clause (c).

Each dollar shall be entered in the Cumulative Revenue Ledger only once. Supplemental MTRC Receipts shall exclude Applied Security Proceeds. Applied Security Proceeds shall be entered only when applied to an identified Supplemental MTRC, prior-period true-up adjustment, Termination Fee, or other payment obligation under Article 6 or Section 3.3.4. Security that is posted, drawn but not applied, held as a deferred liability, replenished, replaced, or returned shall not reduce the Cumulative Revenue Responsibility. Annual Termination Fee Credits and the corresponding Termination Fee Balance shall be separately identified in the Reconciliation Statement and in the workpapers required under Section 6.8 and shall not again reduce the Cumulative Revenue Responsibility.

If an amount previously credited in the Cumulative Revenue Ledger is subsequently refunded, reversed, disallowed, or otherwise ceases to satisfy the applicable obligation, DesertLink shall make a corresponding adjustment to the ledger, subject to the finality and no-revival provisions of this Section.

Cancellation, downsizing, curtailment, or departure does not extinguish the remaining responsibility. When a final Reconciliation Statement determines that the responsibility has reached zero (“Break-Even”), DesertLink shall terminate the operational payment and Security obligations and release any excess Security. Once finally satisfied, the responsibility shall not revive because of a later change in ROE, expense, load, forecast, or other Formula Rate input, subject only to final true-ups and correction of errors or fraud for periods before satisfaction.

PDF page 313

27

6.8.
TRBAA Credit and No Double Recovery. Supplemental MTRC Receipts, Applied Security Proceeds other than Applied Security Proceeds applied to a Termination Fee, Annual Termination Fee Credits, and any duplicate-recovery credit under Section 3.3.3(d) or Section 6.3.5 shall be credited to transmission customers solely through the TRBAA and shall not be recorded as revenue credits in, or otherwise included as inputs to, the Formula Rate. In each annual TRBAA, DesertLink shall include as the Forecast TRBAA Credit: (a) the projected Supplemental MTRC for the following Rate Year, increased or reduced by any prior-period true-up adjustment invoiced under Section 6.5; and (b) for any Covered Upgrade with a Termination Fee Balance, the Annual Termination Fee Credit scheduled under Section 3.3.4 for the following Rate Year, prorated as applicable and limited to the available Termination Fee Balance. DesertLink shall record in the TRBA only Supplemental MTRC cash receipts, Applied Security Proceeds other than Applied Security Proceeds applied to a Termination Fee, and Annual Termination Fee Credits actually received, applied, or scheduled for the applicable Rate Year, respectively. Applied Security Proceeds applied to a Termination Fee shall be deposited into and held in the Termination Fee Account under Section 3.3.4 and shall be credited to transmission customers solely through the applicable Annual Termination Fee Credits. The difference between the Forecast TRBAA Credit and those actual amounts shall be reflected in the principal balance of the TRBA and flowed through to transmission customers in a subsequent TRBAA. A billed but unpaid Supplemental MTRC is not a TRBAA Credit. A later Supplemental MTRC Receipt or Applied Security Proceeds, other than Applied Security Proceeds applied to a Termination Fee, shall be recorded only in the Rate Year in which it is received or applied, respectively. Any amount previously recorded as a TRBAA Credit that is later refunded, reversed, or otherwise ceases to satisfy the applicable obligation shall be reversed in the TRBA when refunded or reversed. Interest on the TRBA balance shall be calculated as provided in Section 5.5 of the TO Tariff. Qualifying Transmission Revenues shall not be included again as a TRBAA Credit because they are already reflected in calculating the Supplemental MTRC.

Each dollar shall be included in a TRBAA Credit only once. Applied Security Proceeds shall not also be treated as Supplemental MTRC Receipts, and the posting, drawing, holding, replenishment, replacement, or return of Security shall not independently produce a TRBAA Credit. A Forecast TRBAA Credit applies only to the forecast Rate Year and shall be reconciled through the TRBA to actual Supplemental MTRC Receipts, Applied Security Proceeds other than those applied to a Termination Fee, and Annual Termination Fee Credits, as applicable. DesertLink shall maintain workpapers reconciling each Forecast TRBAA Credit and each amount recorded in the TRBA under this Section 6.8 to the applicable Annual MTRC calculation in Schedule 5, forecast and actual Qualifying Transmission Revenues, opening unpaid billed balance, Supplemental MTRC invoiced, prior-period true-up adjustment, Supplemental MTRC cash receipt, Applied Security Proceed, direct recovery, closing unpaid billed balance, Termination Fee Balance, Annual Termination Fee Credit, resulting forecast-to-actual TRBA difference, Rate Year, Large Load Customer, and Covered Upgrade. DesertLink shall include with each

PDF page 314

28

TRBAA filing workpapers sufficient to permit transmission customers to verify the TRBAA Credits reflected in that TRBAA, which may present customer-specific information on an aggregated basis or be submitted subject to a request for privileged treatment under 18 C.F.R. § 388.112 or other appropriate confidentiality protections. 6.9.

Prospective Reassignment of Revenue Responsibility.
6.9.1. Eligibility for Reassignment of Revenue Responsibility. Whether or not the Large Load Customer remains in service, a portion of the prospective revenue responsibility associated with a Large Load-Driven Upgrade may be reassigned to a subsequent load customer if an objective transmission study conducted under the applicable tariff or study process determines that:

(a) the subsequent large load customer relies upon identifiable incremental capability created by the Large Load-Driven Upgrade; and

(b) that reliance avoids or reduces identifiable transmission upgrades that otherwise would have been required to provide the subsequent large load customer’s requested service.

Incidental power flows, generalized system benefits, or use of the transmission system that does not satisfy both requirements shall not support a reassignment. This Section 6.9 applies only to a load customer other than the Large Load Customer, at a facility other than the Large Load Facility. It does not apply to a transfer of ownership or operation of the Large Load Facility, a change in Eligible Customer, or an assignment of this Agreement, which are governed by Sections 6.10 and 10.1 and do not alter the Applicable Allocation Percentage or the Large Load-Driven Upgrades attributable to the Large Load Facility.

6.9.2. Reassignment Calculation. DesertLink shall determine the prospective reassignment separately for each Large Load-Driven Upgrade satisfying Section 6.9.1 (each, a “Shared Upgrade”). For each Shared Upgrade:

(a) the Demonstrated Avoided Upgrade Cost shall equal the reasonable estimated cost of the transmission upgrades that would have been required for the subsequent large load customer absent the Shared Upgrade, less the reasonable estimated cost of any additional transmission upgrades required when the capability of the Shared Upgrade is considered;

(b) the Remaining Allocated Net Plant shall equal the portion of the Shared Upgrade’s net plant balance included in rate base immediately before the reassignment that remains assigned to the Large Load Customer under this Agreement;

(c) the Capability-Supported Amount shall equal the portion of the Remaining Allocated Net Plant reasonably attributable to the incremental capability of the Shared Upgrade actually relied upon by the subsequent large load customer; and

(d) the Reassigned Investment Amount shall equal the least of:

PDF page 315

29

(i) the Demonstrated Avoided Upgrade Cost;
(ii) the Capability-Supported Amount; and
(iii) the Remaining Allocated Net Plant.
The Demonstrated Avoided Upgrade Cost, Capability-Supported Amount, and Remaining Allocated Net Plant shall be determined using a consistent cost basis and price year. If Remaining Allocated Net Plant is greater than zero, the Reassignment Percentage shall equal the Reassigned Investment Amount divided by the Remaining Allocated Net Plant, bounded between zero and one hundred percent (100%). If Remaining Allocated Net Plant is zero or negative, no Reassignment Percentage shall be calculated under this methodology; any reassignment shall require an applicable tariff methodology or Commission determination addressing that circumstance.

6.9.3. Prospective Adjustment of Revenue Responsibility. Beginning on the Reassignment Effective Date, the applicable Annual MTRC assigned to the Large Load Customer shall be prospectively reduced by the Reassignment Percentage applied to the Shared Upgrade. DesertLink shall record a separate effective prospective reassignment credit in the Cumulative Revenue Ledger equal to the Reassignment Percentage multiplied by the Remaining Cumulative Revenue Responsibility associated with the Shared Upgrade that remains assigned to the Large Load Customer immediately before the Reassignment Effective Date. That credit shall be the sole Cumulative Revenue Ledger adjustment for the reassigned responsibility. It shall not adjust the Total Required Revenue Commitment or result in a second reduction to the Remaining Cumulative Revenue Responsibility or Required Operational Security for the same reassigned responsibility. DesertLink shall recalculate the Supplemental MTRC and Operational Security under this Agreement to reflect the reassignment. The Reassignment Effective Date shall be the latest of:

(a) the date the subsequent large load customer commences the service for which the Shared Upgrade provides the identified incremental capability;

(b) the effective date of a cost recovery agreement establishing the subsequent large load customer’s corresponding revenue responsibility;

(c) the date on which all Security required from the eligible customer serving the subsequent large load customer becomes effective; and

(d) the date on which the study and any other approvals required under the applicable tariff become final.

No reduction in the Large Load Customer’s Operational Security shall occur until the corresponding responsibility and required Security have become effective for the subsequent large load customer.

6.9.4. Prospective Treatment and Prevention of Duplicate Reassignment. A reassignment under this Section shall:

PDF page 316

30

(a) operate prospectively only and shall not produce a refund, credit, or reopening of amounts properly determined for a prior Rate Year;

(b) transfer prospective revenue responsibility only and shall not constitute a sale or transfer of transmission facilities, a transfer of plant ownership, a change in plant accounting, or a modification of any CAISO cost allocation;

(c) not exceed the prospective responsibility remaining under this Agreement for the Shared Upgrade; and

(d) not assign the same transmission capability, avoided upgrade cost, Annual MTRC, or Cumulative Revenue Responsibility to more than one large load customer.

DesertLink shall maintain an upgrade-specific reassignment ledger identifying the capability and responsibility assigned to each large load customer. Once responsibility has been effectively reassigned, that responsibility shall not revert to the Large Load Customer if the subsequent large load customer later terminates, reduces, or fails to commence service. The reassigned responsibility shall instead remain with the subsequent large load customer and the Eligible Customer responsible for its payment, subject to any further prospective reassignment permitted under the applicable agreement and tariff.

Any prospective reassignment, adjustment, or change in the cost share of a CAISO- Assigned Regional Project shall be recognized under this Agreement only to the extent authorized or required by the CAISO Tariff or a Commission-accepted methodology. DesertLink shall apply an effective change prospectively to the Regional Project Allocated ARR, Cumulative Revenue Responsibility, Supplemental MTRC, TRBAA Credit, and Operational Security, and shall update Schedule 4 and the applicable workpapers. The change shall not assign the same project share to more than one customer or alter costs allocated to other customers under the CAISO Tariff.

6.10. Change in Eligible Customer. Cost responsibility is assigned to the Large Load Customer and Large Load Facility, as paid by the Eligible Customer then taking wholesale transmission service on behalf of the Large Load Customer and Large Load Facility. If the Eligible Customer serving a Large Load Customer or Large Load Facility changes, the Successor Eligible Customer must execute an assumption agreement covering the Cumulative Revenue Responsibility and any outstanding obligations under Section 6.3.6, provide required Security, and become responsible on a date coordinated with CAISO billing before the prior Eligible Customer is released. Following the complete departure of the Large Load Customer, the last responsible Eligible Customer remains obligated unless responsibility is transferred under an applicable tariff or state-law mechanism, assumed by a successor, or prospectively reassigned as permitted under this Agreement and the CAISO Requirements. If ownership or operation of the Large Load Facility is transferred, Eligible Customer shall notify DesertLink within thirty (30) Calendar Days and shall cause the transferee to execute a Limited Acknowledgment in the form attached to this Agreement. The transfer shall not alter the Applicable Allocation Percentage, Cumulative Revenue Responsibility, or Security obligations under this Agreement.

PDF page 317

31

A sale, lease, or other transfer of the Large Load Facility, or of the Large Load Customer’s interest in such Large Load Facility, is not a reassignment under Section 6.9 and does not require a study under Section 6.9.1. Cost responsibility shall continue to follow the Large Load Facility, the transferee shall execute a Limited Acknowledgment substantially in the form included in this Agreement, and Eligible Customer shall remain responsible for its obligations under this Agreement unless they are transferred to a Successor Eligible Customer under this Section 6.10. 6.11. CAISO Data and Settlement Coordination. Eligible Customer shall provide DesertLink, or authorize and direct its Scheduling Coordinator, Utility Distribution Company, Metering Coordinator, and other applicable entities to provide DesertLink, with the metering, settlement, billing, resettlement, allocation, and other data reasonably necessary to calculate and verify Qualifying Transmission Revenues and administer this Agreement. Eligible Customer shall execute any authorization or data- release documentation reasonably necessary for DesertLink to obtain such information.

To the extent authorized or required by the CAISO Tariff, CAISO may provide or make available relevant settlement, metering, billing, resettlement, and allocation data as provided under the CAISO Requirements. Nothing in this Agreement, however, imposes an obligation on CAISO or makes CAISO a party to this Agreement. DesertLink and Eligible Customer shall cooperate with CAISO and other applicable entities to establish and maintain the billing identifiers, metering points, data exchanges, and authorizations identified in Schedule 2.

DesertLink shall calculate Qualifying Transmission Revenues, the Annual MTRC, and the Supplemental MTRC; maintain the Cumulative Revenue Ledger; and serve on Eligible Customer the Reconciliation Statement, including the Cumulative Revenue Ledger statement, required by Sections 6.6 and 6.7.

If final data are not available when a calculation is required, DesertLink may use reasonable estimates based on the best information then available, subject to reconciliation under Section 6.6 when final or corrected data become available. 6.12. Information Rights and Confidentiality. Upon reasonable request, DesertLink shall provide Eligible Customer the workpapers, data, and other information reasonably necessary to verify the identification of Large Load-Driven Upgrades and CAISO- Assigned Regional Projects and all calculations of each Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, Qualifying Transmission Revenues, Supplemental MTRC, Cumulative Revenue Responsibility, TRBAA Credits, reassignment, and Security under this Agreement. Any dispute concerning those matters shall be resolved under Article 11. Large Load Customer and any Successor Eligible Customer may participate in a dispute under Article 11 to the extent the dispute affects its obligations under this Agreement or its Limited Acknowledgment. Customer-specific information shall be protected under Section 16.3 of the TO Tariff, the CAISO Tariff, and any applicable confidentiality agreement.

PDF page 318

32

7. Security and Payment Obligations
7.1.
Construction Security. Before an applicable Large Load-Driven Upgrade reaches its Upgrade In-Service Date, Eligible Customer shall maintain Construction Security under the relevant agreement sufficient to secure:

(a) DesertLink’s incurred and irrevocably committed engineering, design, procurement, permitting, construction, testing, and related costs attributable to that upgrade; and

(b) the Pre-In-Service Termination Costs described in Section 3.3.2, including properly accrued AFUDC and applicable cancellation, demobilization,

equipment removal, disposition, remediation, and restoration costs
(“Construction Security”).
Construction Security secures, but does not limit, Eligible Customer’s liability for those amounts. Construction Security provided under the relevant Interconnection Agreement or an engineering and procurement agreement for the same costs shall count toward, and shall not be duplicated by, the Construction Security required under this Agreement. Construction Security shall remain in effect for each Large Load- Driven Upgrade until that upgrade reaches its Upgrade In-Service Date and the applicable release or conversion conditions in Section 7.2 are satisfied. A Large Load-Driven Upgrade reaching its Upgrade In-Service Date shall not result in the release of Construction Security attributable to another Large Load-Driven Upgrade that has not reached its Upgrade In-Service Date. Eligible Customer shall replenish Construction Security within ten (10) Business Days after notice of a permitted draw and supporting information if additional secured obligations remain and the remaining Construction Security is less than the amount required under this Section.

For a CAISO-Assigned Regional Project owned by DesertLink, any pre-service payment, contribution, or security required from Eligible Customer for its formally assigned share shall be provided only as required by the CAISO Tariff, an applicable Interconnection Agreement, or another Commission-accepted arrangement, and shall be identified in Schedule 4. This Agreement does not independently require pre- service Construction Security solely because CAISO has assigned a share of a regional project to the Large Load Facility. The treatment of costs for a cancelled or abandoned regional project shall be governed by Section 6.3.5 and the applicable Commission order, CAISO Tariff, and any project-specific abandoned-plant incentive authorized by the Commission. For a project owned by another entity, construction and operational security shall be provided under the CAISO Tariff or the arrangement required by Section 6.3.6 and Schedule 4; it shall not be treated as DesertLink Operational Security unless included in DesertLink’s Formula Rate and expressly identified as DesertLink’s share.

7.2.
Delivery of Operational Security. No later than thirty (30) Calendar Days before the earliest expected Upgrade In-Service Date identified in Schedule 1 or Regional Project

PDF page 319

33

In-Service Date identified in Schedule 4 for a DesertLink-owned CAISO-Assigned Regional Project, Eligible Customer shall deliver Operational Security calculated under this Article for the Large Load-Driven Upgrades and DesertLink-owned CAISO-Assigned Regional Project expected to enter service. Operational Security must be fully effective before any applicable Upgrade In-Service Date or Regional Project In-Service Date.

If different Large Load-Driven Upgrades or DesertLink-owned CAISO-Assigned Regional Projects are expected to reach their applicable in-service dates on different dates, DesertLink shall recalculate the Required Operational Security before each subsequent in-service date to include the additional Cumulative Revenue Responsibility attributable to the upgrade or project share entering service. Eligible Customer shall provide any resulting increase no later than fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier. Inclusion of pre-service Construction Work in Progress in rate base shall not constitute an Upgrade In-Service Date or independently trigger the Operational Security requirement. Construction Security shall remain applicable to each Large Load-Driven Upgrade that has not reached its Upgrade In-Service Date.

No Construction Security attributable to a Large Load-Driven Upgrade shall be released or converted unless:

(a) the Required Operational Security attributable to that upgrade is effective;
(b) that upgrade has reached its Upgrade In-Service Date; and
(c) DesertLink has determined that all Pre-In-Service Termination Costs and other construction-related obligations attributable to that upgrade have been paid or adequately reserved for.

Any portion of Construction Security retained for unresolved construction costs shall be released after DesertLink determines that those costs have been paid or adequately reserved for or, if Section 3.3.2 applies, after the Termination Cost Reconciliation becomes final. Failure to timely deliver Required Operational Security is a default permitting DesertLink, to the extent authorized by the applicable tariffs and agreements, to suspend energization or service, terminate applicable interconnection arrangements, and draw Construction Security for secured obligations. 7.3.

Required Operational Security. Required Operational Security shall equal one hundred percent (100%) of the nominal Remaining Cumulative Revenue

Responsibility. DesertLink shall reduce that amount only by the portion of Qualifying Retail Security Support identified in a currently effective Retail Security Certification. A Retail Security Certification is accepted in reliance on Eligible Customer’s representations and does not require DesertLink to review the underlying retail- security documents in the ordinary course. If DesertLink has a reasonable basis to question the certification, or after a payment default, Credit Review Event, or Material Adverse Credit Event, DesertLink may request supporting information reasonably necessary to verify continued compliance. Any resulting deficiency shall be delivered

PDF page 320

34

or restored within fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier.

7.4.
Annual Resizing and Security Notices. DesertLink shall recalculate Required Operational Security with each Annual Projection, Final MTRC Determination Date, recalculation of a Final Annual MTRC under Section 6.3.1, Reconciliation Statement, effective prospective reassignment, replacement or expiration of Qualifying Retail Security Support, or Credit Review Event. If DesertLink reasonably determines that the Required Security Amount exceeds available Security, it may issue a Security Notice identifying the required increase or restoration and reasonable supporting detail then available. Eligible Customer shall provide the required increase or restoration within fifteen (15) Business Days after receipt of the Security Notice, or by the applicable in-service date if earlier. A reduction shall be released only after the relevant calculation and reconciliation are final.

7.5.
Form of Operational Security. Except to the extent of currently effective Qualifying Retail Security Support, Eligible Customer shall provide direct Operational Security in the form of cash, an irrevocable standby Letter of Credit meeting Schedule 3, or any combination of cash and Letter of Credit. DesertLink may accept another form of Security that it determines, in its sole discretion, is acceptable.

Each Letter of Credit shall have an initial stated term of at least twelve (12) months and shall remain continuously effective until released under this Agreement; provided, however, that a Letter of Credit may have a stated expiration date before its release date if Eligible Customer timely extends or replaces it so that Security in an amount not less than the Required Security Amount remains continuously available to DesertLink.

If an issuing bank has the right not to renew a Letter of Credit, the Letter of Credit shall require the issuing bank to provide DesertLink and Eligible Customer at least ninety (90) Calendar Days’ prior written notice of nonrenewal. Eligible Customer shall provide a conforming extension or replacement Letter of Credit, or additional cash collateral or other Security accepted by DesertLink, no later than sixty (60) Calendar Days before the applicable expiration date.

If Eligible Customer fails to provide the required extension, replacement, or other Security by that deadline, DesertLink may, before the Letter of Credit expires, draw all or any portion of the then-available amount under the Letter of Credit and retain the proceeds as cash collateral, apply the proceeds to secured obligations, or both. Any proceeds retained but not applied shall continue to constitute Security until released under this Agreement.

7.6.
Draw and Application. DesertLink may draw against all or any portion of a Letter of Credit, apply cash collateral, or apply another form of Security accepted by DesertLink to secured obligations upon: (a) an unpaid Supplemental MTRC, true-up, Termination Fee, or other amount due after the applicable payment period; (b) Eligible Customer’s failure to timely deliver, maintain, replace, restore, or increase Security;

PDF page 321

35

(c) cancellation, termination, withdrawal, abandonment, or permanent cessation of the Large Load Facility or a material breach of this Agreement; (d) a material inaccuracy in a Retail Security Certification or Security instrument; (e) Eligible Customer: (i) files a voluntary petition in bankruptcy or seeks reorganization, arrangement, or similar relief under any bankruptcy, insolvency, or debtor-relief law; (ii) becomes subject to an involuntary bankruptcy or insolvency proceeding that is not dismissed within sixty

(60) Calendar Days; (iii) has a receiver, trustee, liquidator, or custodian appointed for it or a substantial portion of its assets, which appointment is not vacated within sixty

(60) Calendar Days; (iv) makes a general assignment for the benefit of creditors; or (v) admits in writing its inability to pay debts as they become due; or (f) Eligible Customer fails to extend, replace, or otherwise maintain Security in the amount and within the time required by Section 7.5, including following a notice of nonrenewal, issuer rating reduction, or other event affecting the availability of a Letter of Credit. A draw shall not automatically require replenishment to the amount maintained immediately before the draw. Following any application of drawn proceeds to an amount due, DesertLink shall recalculate the remaining Cumulative Revenue Responsibility and the Operational Security then required under this Article. Eligible Customer shall replenish only the amount, if any, by which the remaining Operational Security is less than the recalculated Required Security Amount, within fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier.

Proceeds drawn solely to prevent the expiration or nonrenewal of a Letter of Credit, and cash collateral not yet applied to an identified payment obligation, shall remain refundable Security and shall continue to constitute Operational Security until applied to an amount then due or released under Section 7.9. Such proceeds and cash collateral shall be included in determining the amount of remaining Operational Security and shall not create an additional replenishment obligation merely because they are held by DesertLink.

The posting, drawing, holding, replacement, or replenishment of Operational Security shall not, by itself, satisfy the secured obligation, reduce Cumulative Revenue Responsibility, or produce a TRBAA Credit. Drawn proceeds of Operational Security shall become Applied Security Proceeds only when DesertLink applies them to an identified Supplemental MTRC, prior-period true-up adjustment, Termination Fee, or other secured payment obligation arising under Article 6 or Section 3.3.4. Upon application, the proceeds shall reduce that obligation dollar-for-dollar and shall receive the TRBAA treatment required by Section 6.8; provided, however, that Applied Security Proceeds applied to a Termination Fee shall be administered under Section 3.3.4 and credited to transmission customer only through the Annual Termination Fee Credits provided under Section 6.8. Proceeds of Construction Security applied to Pre- In-Service Termination Costs or other construction-related obligations shall be treated as provided in Sections 3.3.2 and 3.3.3.

7.7.
Security Maintenance. Because Required Operational Security is initially one hundred percent (100%) of nominal Remaining Cumulative Revenue Responsibility,

PDF page 322

36

no separate acceleration concept applies. An incorrect, expired, withdrawn, unavailable, or materially misleading Retail Security Certification, or the loss of enforceable retail-security rights described in it, is a Material Adverse Credit Event. Eligible Customer shall provide replacement direct Security for any resulting uncovered amount within fifteen (15) Business Days after receipt of a Security Notice, or by the applicable in-service date if earlier.

7.8.
Post-Termination Administration and Cash Collateral. DesertLink shall continue the annual calculations, invoices, and true-ups required under this Agreement following termination of service to, or the departure, permanent cessation, or material reduction of service by, the Large Load Customer until the Cumulative Revenue Responsibility and all other obligations under this Agreement have been finally satisfied, transferred, reassigned, refunded, or otherwise resolved. The Parties intend that cash collateral and proceeds of Security be treated as a deposit or deferred liability rather than as a Contribution in Aid of Construction, customer financing of transmission plant, or a reduction to DesertLink’s rate base. To the extent permitted by applicable Commission accounting and ratemaking requirements and tax law, DesertLink shall record and administer such amounts as the corresponding annual costs and payment obligations arise. The treatment described in this Section is subject to the Commission’s Uniform System of Accounts, the Formula Rate, the Protocols, applicable Commission orders, and other Applicable Laws and Regulations. If the Commission requires a different accounting or ratemaking treatment, DesertLink shall implement the required treatment and make corresponding adjustments necessary to prevent duplicate recovery and preserve, to the extent permitted, the economic allocation established by this Agreement. The Parties shall cooperate in seeking any necessary Commission authorization or acceptance.

Nothing in this Agreement guarantees a particular accounting, ratemaking, or tax result. Cash collateral and unapplied Security proceeds shall remain subject to release under Section 7.9, including release to reflect an effective prospective reassignment under Section 6.9.

7.9.
Release of Security. DesertLink shall release excess Operational Security only after the applicable Reconciliation Statement becomes final. DesertLink shall release Security attributable to an effective prospective reassignment and shall release all remaining Security within thirty (30) Calendar Days after final satisfaction of the Cumulative Revenue Responsibility and all other secured obligations. Termination alone does not require release.

7.10. Security Does Not Limit Liability. The Required Security Amount is based on DesertLink’s then-current estimates and calculations and does not cap, replace, or discharge Eligible Customer’s underlying obligations. A shortfall between Security and the amount due remains immediately payable to DesertLink.

7.11. Events of Default; Remedies. Each of the following is an “Event of Default” by Eligible Customer: (a) failure to pay any undisputed amount when due that continues for ten (10) Business Days after written notice from DesertLink; (b) failure to deliver,

PDF page 323

37

maintain, replace, restore, or increase Security when required under this Article 7 or Schedule 3 that continues after the applicable cure period; (c) any other material breach of this Agreement, including under Section 4.2 or 6.3.6, that continues for thirty (30) Calendar Days after written notice from DesertLink or, if the breach cannot reasonably be cured within that period, for such longer period, not to exceed ninety

(90) Calendar Days, as Eligible Customer diligently pursues a cure; and (d) any event described in Section 7.6(e). Upon an Event of Default, DesertLink may, subject to Applicable Laws and Regulations and the applicable tariffs and agreements: (i) draw and apply Security under Section 7.6; (ii) exercise the rights described in Sections 4.2.6 and 7.2; (iii) before the first Upgrade In-Service Date or Regional Project In- Service Date, terminate this Agreement under Section 3.3.1; and (iv) pursue any other remedy available at law or in equity or before the Commission. No termination after an Upgrade In-Service Date or Regional Project In-Service Date releases the obligations described in Section 3.3.4.

8. Force Majeure.
8.1.
If a Party is rendered unable, wholly or in part, by Force Majeure to carry out a nonmonetary obligation, that obligation shall be suspended only to the extent and for the period performance is prevented. Force Majeure does not suspend or excuse payment of incurred construction costs, Pre-In-Service Termination Costs, Supplemental MTRC, the Termination Fee, prior-period true-up adjustments, or the maintenance, replacement, replenishment, or increase of Security. If a Force Majeure event continues for more than twenty (20) Calendar Days in a sixty (60)-Calendar Day period, the Parties shall meet to address performance; any resulting termination remains subject to Sections 3.4 and 3.5.

9. Indemnification
9.1.
Indemnity. Each Party (the “Indemnifying Party”) shall at all times indemnify, defend, and hold the other Party and its Affiliates and their respective directors, officers, employees, and agents (each, an “Indemnified Person”) harmless from any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the Indemnifying Party’s actions or omissions in performing its obligations under this Agreement, except to the extent caused by the gross negligence or willful misconduct of the Indemnified Person.

9.1.1.
Indemnified Person. If an Indemnified Person is entitled to indemnification as a result of a claim by a third party, and the Indemnifying Party fails, after notice and reasonable opportunity to proceed, to assume the defense of such claim, such Indemnified Person may at the expense of the Indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.

PDF page 324

38

9.1.2.
Indemnifying Party. If an Indemnifying Party is obligated to indemnify and hold any Indemnified Person harmless, the amount owing to the Indemnified Person shall be the amount of such Indemnified Person’s actual loss, net of any insurance or other recovery.

9.2.
Indemnity Procedures. Promptly after receipt by an Indemnified Person of any claim or notice of the commencement of any action or administrative or legal proceeding or investigation as to which the indemnity provided for in Section 9.1 may apply, the Indemnified Person shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect a Party’s indemnification obligation unless such failure or delay is materially prejudicial to the Indemnifying Party. The Indemnifying Party shall have the right to assume the defense thereof with counsel designated by such Indemnifying Party and reasonably satisfactory to the Indemnified Person. If the defendants in any such action include one or more Indemnified Persons and the Indemnifying Party and if the Indemnified Person reasonably concludes that there may be legal defenses available to it and/or other Indemnified Persons which are different from or additional to those available to the Indemnifying Party, the Indemnified Person shall have the right to select separate counsel to assert such legal defenses and to otherwise participate in the defense of such action on its own behalf. In such instances, the Indemnifying Party shall only be required to pay the fees and expenses of one additional attorney to represent an Indemnified Person or Indemnified Persons having such differing or additional legal defenses.

The Indemnified Person shall be entitled, at its expense, to participate in any such action, suit or proceeding, the defense of which has been assumed by the Indemnifying Party. Notwithstanding the foregoing, the Indemnifying Party (i) shall not be entitled to assume and control the defense of any such action, suit or proceedings if and to the extent that, in the opinion of the Indemnified Person and its counsel, such action, suit or proceeding involves the potential imposition of criminal liability on the Indemnified Person, or there exists a conflict or adversity of interest between the Indemnified Person and the Indemnifying Party, in which event the Indemnifying Party shall pay the reasonable expenses of the Indemnified Person, and (ii) shall not settle or consent to the entry of any judgment in any action, suit or proceeding without the consent of the Indemnified Person, which shall not be unreasonably withheld, conditioned or delayed.

9.3.
Consequential Damages. Except for amounts expressly payable under Articles 3, 4, 6, and 7, no Party shall be liable under this Agreement for special, indirect, incidental, consequential, or punitive damages, including lost profit or revenue, loss of use, cost of capital, or temporary equipment or services, under any theory of liability. Amounts required to satisfy the Cumulative Revenue Responsibility, Supplemental MTRC, construction costs, prior-period true-up adjustments, and Security obligations are direct contractual payment obligations and are not excluded damages.

PDF page 325

39

10. Assignment
10.1. Except for a change in Eligible Customer governed by Section 6.10, a Party may assign this Agreement only with the other Party’s written consent; provided that a Party may assign to an Affiliate with equal or greater creditworthiness and legal and operational capacity to perform. No assignment or change in retail service provider releases the existing Eligible Customer until the assignee or Successor Eligible Customer executes the required assumption, provides required Security, and the transfer becomes effective under the applicable tariffs. Any prohibited assignment is void, and Security provided by or on behalf of Large Load Customer does not make Large Load Customer the wholesale obligor.

11. Disputes
All disputes, claims, or controversies arising out of or relating to this Agreement, including any dispute concerning the identification or allocation of Large Load-Driven Upgrades or Covered Upgrades; any calculation, update, or recalculation of an Estimated Annual MTRC, Final Annual MTRC, Regional Project Allocated ARR, or the MTRC Calculation Template; Qualifying Transmission Revenues; Supplemental MTRC; Total Required Revenue Commitment; Cumulative Revenue Responsibility; TRBAA Credits; Pre-In-Service Termination Costs; the Termination Fee; prospective reassignment; or Security, shall be resolved under this Article 11, except that a dispute concerning CAISO’s designation of a regional project or assignment of a project cost share shall be resolved under the applicable CAISO Tariff procedures. Any payment, refund, credit, or other adjustment resulting from the resolution of a dispute under this Article 11 shall be implemented as provided in Section 11.5. 11.1. Submission and Informal Resolution. In the event of a dispute or claim arising out of or relating to this Agreement, the disputing Party shall provide the other Party with a written notice describing the dispute (“Notice of Dispute”). The dispute shall be referred promptly to designated senior representatives for informal resolution. The representatives shall meet or confer within ten (10) Business Days and shall use reasonable efforts to resolve the matter within thirty (30) Calendar Days after receipt of the Notice of Dispute. This informal process is not a condition to seeking emergency relief, filing a FERC complaint, or invoking any ADR processes. 11.2. Alternative Dispute Resolution. If a dispute is not resolved informally, any Party may request Alternative Dispute Resolution (“ADR”). The Parties shall use the ADR procedures, neutral-selection process, confidentiality protections, and timing requirements specified in the applicable FERC rules. ADR shall be conducted by persons knowledgeable in electric utility, transmission, and FERC matters and shall not alter a jurisdictional rate, term, or condition unless accepted or approved by the FERC.

11.3. FERC Complaints and Other Rights. Any Party may instead file a complaint, petition, or other pleading with the FERC under Section 206 or Section 306 of the Federal Power Act, or seek other relief available under the Federal Power Act or Applicable Laws and Regulations, and DesertLink may make any filing under Section

PDF page 326

40

205 of the Federal Power Act permitted by Section 12.12. No Party’s participation in informal negotiations or ADR waives or limits its right to seek FERC action. A final ADR determination affecting jurisdictional rates, terms, conditions, charges, or Network Upgrades shall be filed with the FERC if required.

11.4. Costs and Interim Performance. Unless otherwise determined through ADR, the Parties shall bear their own costs and share neutral costs as specified by the applicable ADR procedure. During a dispute, each Party shall continue performing undisputed payment and operational obligations, and shall pay undisputed amounts when due. 11.5. Implementation of Dispute Determinations; TRBAA. Within thirty (30) Calendar Days after a dispute under this Article 11 is finally resolved, whether by written agreement of the Parties, a final ADR determination (subject to any required Commission filing or acceptance), or a final Commission order (each, a “Dispute Determination”), DesertLink shall: (a) update the affected MTRC Calculation Template, Schedules, Cumulative Revenue Ledger, Reconciliation Statement, and Required Operational Security, as applicable, and serve the updated documents on Eligible Customer; and (b) invoice or refund, as applicable, any amount owed between the Parties as a result of the Dispute Determination, without interest. To the extent a Dispute Determination changes a TRBAA Credit or any other amount previously credited to, or recovered from, transmission customers, including any change in Supplemental MTRC Receipts or Applied Security Proceeds for a prior Rate Year, DesertLink shall record the resulting difference in the TRBA under Section 6.8 and flow it through to transmission customers through the TRBAA, and any amount so returned by DesertLink to transmission customers shall include interest as provided in Section 5.5 of the TO Tariff. If a final Commission order in a proceeding concerning DesertLink’s TRBAA requires a change to any TRBAA Credit attributable to this Agreement, DesertLink shall implement that order in the TRBA and shall make any corresponding updates and adjustments between the Parties under this Section 11.5 as if the order were a Dispute Determination. Nothing in this Section reopens the Final Annual MTRC or Total Required Revenue Commitment except as required to implement a Dispute Determination or as permitted by Section 6.3.1.

12. Miscellaneous.
12.1. Amendment. Except for updates to the MTRC Calculation Template expressly authorized by Section 6.3.1, updates implementing a Dispute Determination under Section 11.5, and administrative updates expressly permitted elsewhere in this Agreement, this Agreement may be amended only by a written instrument executed by the Parties. An authorized template update shall not change the substantive methodology or other terms of this Agreement. Any material deviation from the Commission-accepted pro forma and any unexecuted amendment shall be filed with FERC as required by the applicable tariffs and Commission rules.

12.2. Entire Agreement. This Agreement, its Schedules, the relevant Interconnection Agreement, and other agreements expressly incorporated herein state the Parties’ complete understanding concerning the wholesale cost recovery mechanism. Nothing

PDF page 327

41

in this Agreement establishes the retail rates, charges, or security arrangements between Eligible Customer and Large Load Customer.

12.3. Governing Tariffs and Order of Precedence. This Agreement shall be interpreted and administered consistently with the Federal Power Act, applicable Commission orders, the CAISO Tariff, and the TO Tariff. The CAISO Tariff, the TO Tariff, and any other tariff or agreement within the CAISO Requirements that is on file with or accepted by the Commission control over this Agreement and its Schedules to the extent of an irreconcilable conflict, with each controlling the matters within its respective scope. Nothing in this Agreement shall require a Party or CAISO to take action inconsistent with an applicable Commission-accepted tariff, agreement, or order.

Subject to the preceding paragraph:
(a) the Formula Rate and Protocols shall control the calculation, information exchange, and true-up of DesertLink’s Net Revenue Requirement, including the rate base treatment of the Covered Upgrades; Section 5.5 of the TO Tariff shall control the flow-through of TRBAA Credits to transmission customers through the TRBAA; and any dispute concerning a TRBAA Credit, or any other matter arising under this Agreement, shall be resolved under Article 11, and any resulting adjustment shall be implemented as provided in Section 11.5. The MTRC Calculation Template in Schedule 5, and not the Formula Rate or Protocols, shall control calculation of the Estimated Annual MTRC and Final Annual MTRC;

(b) this Agreement shall control the determination and administration of the Supplemental MTRC, Cumulative Revenue Responsibility, Operational Security, prospective reassignment, and the other wholesale revenue-support obligations established herein;

(c) the applicable Interconnection Agreement shall control the physical interconnection, design, engineering, procurement, construction, testing, energization, and operating requirements, except to the extent this Agreement expressly establishes or supplements construction-cost, pre-service termination- cost, revenue-support, or Security obligations; provided that the applicable instruments shall be interpreted, to the extent reasonably possible, to give effect to both agreements and prevent duplicate recovery;

(d) each applicable Affected System Arrangement shall control the design, construction, ownership, operation, cost responsibility, financial security or credit support, and cost recovery applicable to the corresponding Affected System Upgrade as between the parties to that arrangement. Nothing in this Agreement modifies an Affected System Owner’s tariff, makes DesertLink responsible for an obligation of an Affected System Owner, or makes an Affected System Owner a Party to this Agreement;

(e) the body of this Agreement shall control over a Schedule in the event of a conflict, except where the Schedule identifies a project-specific election, value, methodology, or term that this Agreement expressly authorizes the Parties to establish in the Schedule; and

PDF page 328

42

(f) the Schedules shall control over other project-specific supporting documents or workpapers that have not been filed with or accepted by the Commission. The Parties shall attempt to interpret the applicable instruments so that each is given effect and no provision is rendered superfluous. If an irreconcilable conflict affects a Commission-jurisdictional rate, term, or condition, the Parties shall seek any required Commission clarification, acceptance, or authorization. Pending resolution, the Parties shall continue performing all undisputed obligations.

12.4. Governing Law. This Agreement shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California.

12.5. Severability. If any term, covenant, or condition of this Agreement or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this Agreement and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this Agreement.

12.6. No Third Party Beneficiaries. Except for the rights of Large Load Customer and any Successor Eligible Customer under Section 6.12, this Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and, where permitted, their assigns.

12.7. Survival. Expiration or termination of this Agreement shall not affect any right, liability, or obligation that accrued before the effective date of expiration or termination or that, by its express terms or nature, is intended to continue thereafter. Without limiting the foregoing, the following shall survive expiration or termination for the period necessary to give them effect:

(a) all outstanding payment, refund, reimbursement, reconciliation, true-up, Security, and release obligations arising under Articles 3, 4, 6, and 7;

(b) the determination and final satisfaction, transfer, or prospective reassignment of the Cumulative Revenue Responsibility;

(c) the calculation and implementation of TRBAA Credits and other adjustments necessary to prevent duplicate recovery;

PDF page 329

43

(d) the confidentiality and information-protection obligations applicable under Section 6.12, Section 16.3 of the TO Tariff, the CAISO Tariff, and any applicable confidentiality agreement;

(e) the Parties’ rights to obtain, inspect, retain, verify, and challenge books, records, metering data, settlement data, calculations, and supporting workpapers relating to periods before expiration or termination;

(f) the indemnification obligations in Article 9 with respect to acts, omissions, circumstances, or claims arising before expiration or termination;

(g) the dispute-resolution provisions in Article 11 with respect to any surviving right, liability, or obligation; and

(h) any provision that expressly states that it survives or that must survive to prevent duplicate recovery or give effect to the Parties’ rights and obligations. Survival of a provision shall not extend the underlying payment or Security obligation beyond the point at which that obligation has been finally satisfied, transferred, reassigned, refunded, or released in accordance with this Agreement.

12.8. No Waiver. A Party’s delay or failure to exercise any right or remedy under this Agreement shall not constitute a waiver of that or any other right or remedy. A waiver shall be effective only if stated in a written instrument executed by the Party granting the waiver and shall apply only to the specific matter and circumstances stated therein. A waiver on one occasion shall not constitute a continuing waiver or a waiver on any other occasion. No course of performance or dealing shall amend this Agreement or waive any Commission-jurisdictional rate, term, or condition. Nothing in this Section limits a Party’s rights under the Federal Power Act or Applicable Laws and Regulations.

12.9. Counterparts and Electronic Signatures. This Agreement, any amendment, and any assumption or acknowledgment executed pursuant to it may be executed in counterparts, each of which shall be deemed an original and all of which together shall constitute one instrument. Signatures transmitted electronically, including by portable document format or an electronic-signature platform, shall have the same force and effect as original signatures to the extent permitted by Applicable Laws and Regulations. Each Party agrees that it shall not contest the validity or enforceability of an instrument solely because it was executed or transmitted electronically. 12.10. Authority. Each Party represents and warrants that:

(a) it is duly organized, validly existing, and in good standing under the laws of its jurisdiction of organization, to the extent such concepts apply;

(b) it has the requisite power and authority to execute, deliver, and perform this Agreement;

(c) the execution, delivery, and performance of this Agreement have been duly authorized by all necessary organizational action;

(d) the individual executing this Agreement on its behalf is authorized to do so; and

PDF page 330

44

(e) subject to any required Commission acceptance or other regulatory approval expressly identified in this Agreement, this Agreement constitutes its valid and binding obligation, enforceable in accordance with its terms.

The Large Load Customer represents only that the individual executing the Limited Acknowledgment is authorized to execute that acknowledgment on its behalf. Execution of the Limited Acknowledgment does not make the Large Load Customer a Party or expand its obligations beyond those expressly stated in the Limited Acknowledgment or in a separate undertaking executed by the Large Load Customer. 12.11. Notices. All notices, requests, demands, and other communications hereunder (herein collectively called “Notice”) shall be in writing and will be deemed to have been duly given when (a) personally delivered to the receiving Party’s physical address, (b) sent by overnight courier service to the receiving Party’s physical address, or (c) delivered via electronic transmission with a courtesy copy sent by overnight courier service to the receiving Party’s physical address, in each case to the appropriate addresses or email addresses set forth below (or to such other addresses or email addresses as a Party may designate by Notice to the other Party); provided that any such deliveries received after normal business hours in the place of business of the receiving Party shall be deemed to be received on the next Business Day:

If to DesertLink:

DesertLink, LLC
Attn: Asset Manager
16150 Main Circle Drive, Suite 310
Chesterfield, Missouri 63017
Email: rhohlt@lspower.com

With a copy to:

DesertLink, LLC
Attn: Legal Department
16150 Main Circle Drive, Suite 310
Chesterfield, Missouri 63017
Email: legalnotices@lspower.com

If to Eligible Customer:

[Company name]
[Contact name]
[Address]
Email: [Insert]
If to Large Load Customer:
[Company name]

PDF page 331

45

[Contact name]
[Address]
Email: [Insert]
12.12. Reservation of Rights. DesertLink shall have the right to make a unilateral filing with the Commission under Section 205 of the Federal Power Act to modify this Agreement or the pro forma form of this Agreement, and Eligible Customer shall have the right to make a unilateral filing with the Commission under Section 206 of the Federal Power Act to modify this Agreement. Each Party shall have the right to protest any such filing and to participate fully in any proceeding before the Commission. The standard of review for any proposed change to this Agreement, whether proposed by a Party, a non-party, or the Commission acting on its own motion, shall be the just and reasonable standard under Sections 205 and 206 of the Federal Power Act.

13. Project-Specific Schedules
13.1. Required Schedules. Each executed Agreement shall include the following completed schedules, which are incorporated into this Agreement.

Schedule 1 — Project and Allocation Data;
Schedule 2 — Qualifying Transmission Revenues Methodology;
Schedule 3 — Credit and Security Standards;
Schedule 4 — CAISO Regional Project Allocation and Responsibility; and Schedule 5 — MTRC Calculation Template and Cumulative Revenue Ledger [Signature page follows.]

PDF page 332

46

IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed by their duly authorized officers as of the day and year first above written.

DESERTLINK, LLC
By: __________________________
Name: ________________________
Title: _________________________
Date: _________________________
[ELIGIBLE CUSTOMER]
By: __________________________
Name: ________________________
Title: _________________________
Date: _________________________

LIMITED ACKNOWLEDGMENT OF LARGE LOAD CUSTOMER
Large Load Customer acknowledges the assignment of cost responsibility to its facility and agrees to provide information and notices, authorize release of metering and settlement data, and cooperate in a transition to a Successor Eligible Customer. This acknowledgment does not make Large Load Customer the wholesale obligor, establish a FERC-jurisdictional retail rate, or constitute a guarantee of Eligible Customer’s payment obligations. Any separate guarantee or collateral undertaking by Large Load Customer shall be governed by its own terms and filed with FERC if required.

[LARGE LOAD CUSTOMER]
By: __________________________
Name: ________________________
Title: _________________________
Date: _________________________

PDF page 333

Schedule 1 - 1

Schedule 1
Project and Allocation Data
1. Purpose
This Schedule identifies the Large Load Facility, the applicable service request, each Large Load-Driven Upgrade covered by this Agreement, the initial allocation of each Large Load- Driven Upgrade, and the applicable construction and operational security information. This Schedule is incorporated into and made part of the Agreement.

2. Large Load Facility and Service Information
Large Load Customer
[●]
Eligible Customer
[●]
Large Load Facility
[Name and description]
Physical Location of Large
Load Facility
[●]
Point of Interconnection
[●]
Metering Point or Settlement
Identifier
[●]
Requested Service Level
[●] MW
Requested Service Phases
[Identify the MW and expected commencement date of
each phase]
Expected Large Load Service
Commencement Date
[●]
Outside Date
[●]
Applicable Study or
Authorization
[Study name, number, version, and date]
Applicable Interconnection,
Transmission Service, or Other
Agreement
[●]
CAISO or Other Relevant
Project Identifier
[●]

PDF page 334

Schedule 1 - 2

3. Large Load-Driven Upgrade Information
Each Large Load-Driven Upgrade shall be identified separately. Upgrade 1

Upgrade Description
[●]
Applicable Study or
Authorization
[●]
Owner and Construction
Responsibility
[●]
Initial Estimated Capital Cost
$[●]
Expected Construction
Commencement Date
[●]
Expected Upgrade In-Service
Date
[●]
Actual Upgrade In-Service Date [●]
MTRC Term End Date
[●]
Shared, Phased, or Dependent
Facility
[●]

PDF page 335

Schedule 1 - 3

Upgrade 2
Upgrade Description
[●]
Applicable Study or
Authorization
[●]
Owner and Construction
Responsibility
[●]
Initial Estimated Capital Cost
$[●]
Expected Construction
Commencement Date
[●]
Expected Upgrade In-Service
Date
[●]
Actual Upgrade In-Service Date [●]
MTRC Term End Date
[●]
Shared, Phased, or Dependent
Facility
[●]

Upgrade 3
Upgrade Description
[●]
Applicable Study or
Authorization
[●]
Owner and Construction
Responsibility
[●]
Initial Estimated Capital Cost
$[●]
Expected Construction
Commencement Date
[●]
Expected Upgrade In-Service
Date
[●]
Actual Upgrade In-Service Date [●]
MTRC Term End Date
[●]
Shared, Phased, or Dependent
Facility
[●]

PDF page 336

Schedule 1 - 4

4. Initial Allocation and Annual MTRC Information
For each Large Load-Driven Upgrade, the Initial Allocation Percentage assigned to the Large Load Customer under this Agreement shall be identified below. The sum of the percentages allocated to all Large Load Customers for a Large Load-Driven Upgrade shall not exceed one hundred percent (100%).

Upgrade 1
Initial Estimated Annual
MTRC Attributable to Covered
Upgrade
$[●]
Initial Allocation Percentage
Assigned to This Large Load
Customer
[●]%
Initial Estimated Annual
MTRC Allocated to This Large
Load Customer
$[●]
Aggregate Initial Allocation
Percentage Assigned to All
Large Load Customers
[●]%
Percentage Allocated to Other
System Needs or Customers
[●]%

Upgrade 2
Initial Estimated Annual
MTRC Attributable to Covered
Upgrade
$[●]
Initial Allocation Percentage
Assigned to This Large Load
Customer
[●]%
Initial Estimated Annual
MTRC Allocated to This Large
Load Customer
$[●]
Aggregate Initial Allocation
Percentage Assigned to All
Large Load Customers
[●]%
Percentage Allocated to Other
System Needs or Customers
[●]%

PDF page 337

Schedule 1 - 5

Upgrade 3
Initial Estimated Annual
MTRC Attributable to Covered
Upgrade
$[●]
Initial Allocation Percentage
Assigned to This Large Load
Customer
[●]%
Initial Estimated Annual
MTRC Allocated to This Large
Load Customer
$[●]
Aggregate Initial Allocation
Percentage Assigned to All
Large Load Customers
[●]%
Percentage Allocated to Other
System Needs or Customers
[●]%

Any portion of a Large Load-Driven Upgrade not allocated to a Large Load Customer shall be excluded from the Annual MTRC allocable to any Large Load Customer and shall remain subject to otherwise-applicable CAISO cost allocation and rate recovery requirements.

5. Allocation Methodology and Capability Basis
The Initial Allocation Percentage for each Large Load-Driven Upgrade is supported by the following study findings and allocation methodology:

Upgrade 1
Customers or Projects Studied
Together
[●]
Allocation Methodology
[●]
Requested Service or Electrical
Impact Used in Allocation
[●]
Incremental Capability Created
by Upgrade, if Quantified
[●] MW or other applicable measure
Capability Initially Assigned to
This Large Load Customer
[●]
Explanation of Any Percentage
Allocated to Other System
Needs or Customers
[●]

PDF page 338

Schedule 1 - 6

Upgrade 2
Customers or Projects Studied
Together
[●]
Allocation Methodology
[●]
Requested Service or Electrical
Impact Used in Allocation
[●]
Incremental Capability Created
by Upgrade, if Quantified
[●] MW or other applicable measure
Capability Initially Assigned to
This Large Load Customer
[●]
Explanation of Any Percentage
Allocated to Other System
Needs or Customers
[●]

Upgrade 3
Customers or Projects Studied
Together
[●]
Allocation Methodology
[●]
Requested Service or Electrical
Impact Used in Allocation
[●]
Incremental Capability Created
by Upgrade, if Quantified
[●] MW or other applicable measure
Capability Initially Assigned to
This Large Load Customer
[●]
Explanation of Any Percentage
Allocated to Other System
Needs or Customers
[●]

The allocation methodology shall account for, as applicable:
(a) Large Load Customers studied individually, jointly, or in a cluster;
(b) the extent to which two or more Large Load Customers caused the need for or share a Large Load-Driven Upgrade;

(c) differing requested service levels, electrical impacts, development phases, and facility configurations;

(d) facilities constructed in phases or placed in service on different dates; and

PDF page 339

Schedule 1 - 7

(e) any portion of a facility determined at the outset to serve other system needs or customers.

6. Initial Cumulative Revenue Responsibility and Security Information Upgrade 1

Initial Projected Cumulative
Revenue Responsibility
$[●]
Construction Security
Attributable to Upgrade
$[●]
Date Operational Security Must
Become Effective
[●]
Initial Projected Incremental
Operational Security
Attributable to Upgrade
$[●]

Upgrade 2
Initial Projected Cumulative
Revenue Responsibility
$[●]
Construction Security
Attributable to Upgrade
$[●]
Date Operational Security Must
Become Effective
[●]
Initial Projected Incremental
Operational Security
Attributable to Upgrade
$[●]
Upgrade 3
Initial Projected Cumulative
Revenue Responsibility
$[●]
Construction Security
Attributable to Upgrade
$[●]
Date Operational Security Must
Become Effective
[●]
Initial Projected Incremental
Operational Security
Attributable to Upgrade
$[●]

PDF page 340

Schedule 1 - 8

The Initial Projected Cumulative Revenue Responsibility stated above represents the initial projection of the Total Required Revenue Commitment for the applicable Large Load-Driven Upgrade, calculated as the Estimated Annual MTRC multiplied by twenty (20) using the MTRC Calculation Template in Schedule 5.

Construction Security shall remain applicable separately to each Large Load-Driven Upgrade until that upgrade reaches its Upgrade In-Service Date and the applicable conditions for release or conversion under Section 7.2 have been satisfied.

Operational Security must be fully effective before the applicable Upgrade In-Service Date. If different Large Load-Driven Upgrades are expected to reach their Upgrade In-Service Dates on different dates, DesertLink shall recalculate the required Operational Security before each subsequent Upgrade In-Service Date in accordance with Article 7.

7. Schedule Qualifications
7.1 Projected Amounts. The capital costs, Estimated Annual MTRC, projected Total Required Revenue Commitment, Cumulative Revenue Responsibility, and Operational Security amounts stated in this Schedule are initial projections provided for planning and administration purposes. They do not constitute fixed amounts, caps, or guarantees.

7.2 Initial and Applicable Allocation Percentages. The Initial Allocation Percentage identified for each Large Load-Driven Upgrade shall remain the initial allocation of that upgrade to the Large Load Customer. The Applicable Allocation Percentage shall equal the Initial Allocation Percentage, as adjusted prospectively by any reassignment effective under Section 6.9 or as otherwise required by a final Commission order or applicable tariff provision. A change in capital costs, the Upgrade In-Service Date, Formula Rate inputs, or the annual revenue requirement shall not, by itself, change the Initial Allocation Percentage or Applicable Allocation Percentage. Cancellation, abandonment, downsizing, curtailment, permanent cessation, or material reduction of service by the Large Load Customer also shall not, by itself, reduce either percentage.

7.3 Allocation Limitation. The aggregate Annual MTRC assigned to all Large Load Customers for a Covered Upgrade shall not exceed one hundred percent (100%) of the Annual MTRC for that Covered Upgrade. DesertLink shall not allocate the same upgrade cost, transmission capability, or annual revenue requirement to more than one Large Load Customer. 7.4 Upgrade In-Service Dates and MTRC Term End Dates. Each Expected Upgrade In- Service Date stated in this Schedule is a planning estimate. DesertLink shall provide written notice to Eligible Customer of a material change to an Expected Upgrade In-Service Date. Within five (5) Business Days after a Covered Upgrade achieves its Upgrade In-Service Date, DesertLink shall provide written notice to Eligible Customer stating the actual Upgrade In- Service Date and the corresponding MTRC Term End Date. DesertLink shall update this Schedule and the applicable Cumulative Revenue Ledger to reflect those dates. The actual Upgrade In-Service Date shall be determined in accordance with the definition of that term in the Agreement. Inclusion of pre-service Construction Work in Progress in rate base does not constitute an Upgrade In-Service Date.

PDF page 341

Schedule 1 - 9

7.5 Annual Updates. Changes in the Estimated Annual MTRC, Final Annual MTRC, Total Required Revenue Commitment, Cumulative Revenue Responsibility, Supplemental MTRC, Qualifying Transmission Revenues, or Operational Security resulting from the MTRC Calculation Template in Schedule 5, the Annual Projection, the Annual Update and Reconciliation Statement, or an effective prospective reassignment under Section 6.9 do not require an amendment to this Schedule.

7.6 Prospective Reassignment. DesertLink shall maintain the customer-, project-, and upgrade-specific ledger required by Sections 6.7 and 6.9. Any prospective reassignment shall be reflected in that ledger and in the applicable Annual Projection and Reconciliation Statement. A prospective reassignment shall adjust the Applicable Allocation Percentage but shall not revise the Initial Allocation Percentage, produce a historical refund, or reopen a prior Rate Year. 7.7 Updated Expected Dates. An update to an expected construction commencement date, Expected Upgrade In-Service Date, or expected Large Load Service Commencement Date may be made by written notice and does not require an amendment to this Schedule unless the update also changes a material rate, term, condition, facility scope, or allocation established by this Agreement.

8. Supporting Materials
The following supporting materials are attached to or incorporated by reference into this Schedule:

1. the applicable final transmission study or studies;
2. the facilities list and cost estimate supporting each Large Load-Driven Upgrade;
3. the study-based allocation methodology and calculations;
4. the initial Annual MTRC and Total Required Revenue Commitment workpapers (per Schedule 5);

5. the initial Cumulative Revenue Responsibility calculation;
6. the Construction Security calculation;
7. the initial projected Operational Security calculation;
8. any applicable project diagrams, metering diagrams, or service-phase schedules; and
9. each applicable Affected System study, Affected System Arrangement, and evidence of required financial security or credit support.

9. Affected System Information
The following information shall be completed for each potential or confirmed Affected System. Eligible Customer shall update the information and provide the documentation required by Section 4.2 if an Affected System or Affected System Upgrade is identified or the status of an Affected System Arrangement changes.

1. Affected System Owner: [●]
2. CAISO Participating TO or External Affected System: [●]
3. Applicable Study and Project Identifier: [●]
4. Identified System Impact: [●]

PDF page 342

Schedule 1 - 10

5. Affected System Upgrade: [●]
6. Estimated Cost: $[●]
7. Affected System Arrangement: [Agreement name, parties, and date]
8. Required Construction Financial Security or Credit Support: $[●]
9. Required Post-In-Service Financial Security or Credit Support: $[●]
10. Commission Filing or Acceptance Required: [Yes/No; docket and status]
11. Deadline for Delivery to DesertLink: [●]
12. Current Status: [Pending/Executed/Effective]
13. If no Affected System or Affected System Upgrade has been identified when this Schedule is executed, insert the following certification:

No Affected System or Affected System Upgrade has been identified as of [date]. This statement does not limit Eligible Customer’s continuing obligations under Section 4.2 if an Affected System or Affected System Upgrade is subsequently identified.

PDF page 343

Schedule 2 - 1

Schedule 2
Qualifying Transmission Revenues Methodology
1. Purpose and Controlling Principles
This Schedule establishes the reproducible methodology for calculating projected and actual Qualifying Transmission Revenues attributable to the Large Load Facility. It is intended to identify wholesale transmission revenues paid by or on behalf of Eligible Customer that are attributable to the Large Load Facility and reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement. Such revenues may include applicable TAC revenues and qualifying Wheeling Access Charges or other wholesale transmission-access, wheeling, or transmission-service charges under the CAISO Tariff or another Commission-accepted arrangement, including charges paid through a non-PTO serving entity. The Supplemental MTRC therefore measures only the remaining shortfall below the applicable Annual MTRC.

Qualifying Transmission Revenues shall be counted once in calculating the Supplemental MTRC and the Cumulative Revenue Responsibility against the combined Annual MTRC for all Covered Upgrades. They shall not also be treated as a TRBAA Credit under Section 6.8 because they reduce transmission revenues otherwise collected from CAISO customers. This Schedule does not modify CAISO settlement rules, establish a retail rate, impose any obligation on CAISO, or alter any cost allocation established under the CAISO Requirements.

2. Project and Settlement Identifiers
The following information shall be completed for each Large Load Facility and updated administratively when a meter, settlement identifier, Eligible Customer, or other listed item changes. An administrative update that does not alter the Commission-accepted methodology does not require an amendment to the Agreement unless a filing is otherwise required by Applicable Laws and Regulations.

Large Load Customer
[●]
Large Load Facility
[●]
Physical location and applicable
CAISO or out-of-state service
area
[●]
Eligible Customer at service
commencement
[●]
Scheduling Coordinator
[●]
Utility Distribution Company,
Metered Subsystem, or non-
PTO serving entity
[●]

PDF page 344

Schedule 2 - 2

CAISO resource, settlement, or
load identifier(s)
[●]
Revenue-quality meter
identifier(s) and location(s)
[●]
Metering point used for this
calculation
[●]
Large Load Service
Commencement Date
[●]
Applicable TAC, Wheeling
Access Charge, or other CAISO
Tariff charge(s)
[●]
Primary source of settlement
and metering data
[●]

3. Data Sources and Responsibilities
(a) DesertLink shall calculate projected and actual Qualifying Transmission Revenues using the best available data from CAISO settlement statements, wheeling, transmission-access, and transmission service invoices, revenue-quality meter data, Eligible Customer and non-PTO serving entity billing records, Scheduling Coordinator records, and other data made available under the CAISO Tariff, another Commission-accepted arrangement, or authorized by Eligible Customer and Large Load Customer.

(b) Eligible Customer shall provide, or cause its Scheduling Coordinator, Utility Distribution Company, Metering Coordinator, or other authorized agent to provide, all information reasonably necessary to identify and verify withdrawals attributable to the Large Load Facility. Eligible Customer shall maintain all authorizations reasonably necessary for release of that information.

(c) The Large Load Customer shall provide the information and authorizations required by its Limited Acknowledgment, including information needed to distinguish the Large Load Facility from other load behind a common meter or within a common settlement identifier.

(d) DesertLink may use CAISO data made available under the CAISO Requirements or through the authorizations provided under this Agreement. Nothing in this Schedule makes CAISO a party to the Agreement or independently requires CAISO to calculate, invoice, collect, or administer the Supplemental MTRC.

(e) If final data are unavailable when a projection, invoice, Annual Update, or Reconciliation Statement is due, DesertLink may use a reasonable estimate based on the most recent available data, the service forecast, applicable TAC rates, and known settlement adjustments. Estimated amounts shall be replaced with actual data in the next practicable reconciliation.

PDF page 345

Schedule 2 - 3

4. Applicable Withdrawals
For each CAISO settlement interval or other reproducible billing interval, Applicable Withdrawals shall equal the metered energy withdrawals attributable to the Large Load Facility at the metering point identified in Section 2 of this Schedule, expressed in MWh and adjusted as follows:

(a) Imports, exports, station service, auxiliary load, behind-the-meter generation, storage charging and discharging, and other injections or withdrawals shall be treated consistently with the manner in which they are recognized for the applicable TAC charge under the CAISO Tariff.

(b) Distribution losses and transmission losses shall be included only to the extent they are included in the billing determinant for the applicable TAC component. The loss factor or method shall be identified in the project-specific table in Section 10 of this Schedule.

(c) If the Large Load Facility shares a meter or settlement identifier with other load, the withdrawals attributable to the Large Load Facility shall be determined from revenue- quality submeters or another objective allocation method identified in Section 10 of this Schedule. An allocation based solely on estimates may be used temporarily but shall be reconciled when reliable data become available.

(d) Withdrawals shall not be counted for a period before the corresponding Annual MTRC is included in the Supplemental MTRC calculation under Section 6.4 of the Agreement, except where necessary to correct a prior-period error or resettlement.

5. Applicable TAC Revenue
Applicable TAC Revenue for an interval shall equal Applicable Withdrawals multiplied by the CAISO transmission rate or rates actually applicable to those withdrawals for that interval. The calculation shall include only transmission charge components that contribute to recovery of the revenue requirement in which DesertLink’s costs are included. It shall exclude retail distribution charges, generation charges, non-transmission surcharges, taxes collected for another governmental entity, and any other charge that does not contribute to recovery of DesertLink’s transmission revenue requirement.

If CAISO uses a monthly, annual, or other non-interval billing determinant, DesertLink shall perform the calculation using that same billing period and determinant. If more than one TAC rate or component applies, each component shall be calculated separately before applying the DesertLink Allocation Factor.

6. DesertLink Allocation Factor
The DesertLink Allocation Factor shall identify the portion of Applicable TAC Revenue allocable to DesertLink for the relevant period. Unless a different Commission-accepted method is stated in Section 10 of this Schedule, the factor shall be calculated from the same revenue requirement, billing determinant, allocation percentage, and other inputs used by CAISO to include DesertLink’s net transmission revenue requirement in the applicable TAC rate. For each applicable rate component and period:

PDF page 346

Schedule 2 - 4

DesertLink Allocation Factor = DesertLink Net Revenue Requirement included in the applicable TAC component ÷ Total Net Revenue Requirement recovered through that TAC component.

If DesertLink’s revenue requirement is recovered through a project-specific, zonal, or other direct allocation rather than a systemwide factor, the corresponding Commission-accepted allocation percentage or rate component shall be used. The supporting workpapers shall identify the source and calculation of each factor.

7. Calculation of Qualifying Transmission Revenues
Projected and actual Qualifying Transmission Revenues shall be calculated as follows for each applicable interval, month, or billing period and then aggregated for the Rate Year or partial Rate Year:

Qualifying Transmission Revenues =  Qualifying TAC Revenue + Qualifying Wheeling and Other Wholesale Transmission Revenues ± Applicable Adjustments.

Qualifying TAC Revenue = Σ [(Applicable Withdrawals × Applicable TAC Rate) × DesertLink Allocation Factor]. Qualifying Wheeling and Other Wholesale Transmission Revenues equal Wheeling Access Charges and other wholesale transmission-access, wheeling, or transmission- service charges actually paid by or on behalf of Eligible Customer to CAISO, a Participating TO, or a non-PTO transmission or load-serving entity for deliveries serving the Large Load Facility, but only to the extent those revenues reduce transmission revenues otherwise collected through TAC or directly credit DesertLink’s Net Revenue Requirement. Applicable Adjustments shall include only amounts attributable to the Large Load Facility, including CAISO resettlements, billing corrections, refunds, charge reversals, balancing-account adjustments, and other adjustments that change the qualifying transmission revenue. Bad debt or uncollectible amounts shall reduce Qualifying Transmission Revenues only to the extent the corresponding revenue is not recovered from another source and is not otherwise included in DesertLink’s Formula Rate recovery.

8. Projections, Actuals, Resettlements, and Customer Changes
(a) The Annual Projection shall use forecast withdrawals, then-effective or forecast TAC rates, the most recent DesertLink Allocation Factor, and known adjustments. The workpapers shall separately identify each material assumption.

(b) The Reconciliation Statement shall replace projected values with actual withdrawals, rates, factors, and adjustments for the applicable period. CAISO resettlements or other corrections received after a Reconciliation Statement becomes final shall be reflected in the next practicable Reconciliation Statement and Annual Update, subject to Section 6.6 of the Agreement, and any dispute concerning them shall be resolved under Article 11 of the Agreement.

(c) A change in Eligible Customer, Scheduling Coordinator, or retail service provider shall not interrupt the calculation or cause the same withdrawals or revenues to be omitted or counted more than once. Qualifying Transmission Revenues shall remain associated with the Large Load Customer and Large Load Facility, regardless of which Eligible Customer is responsible for payment during the applicable period.

PDF page 347

Schedule 2 - 5

(d) If two or more Eligible Customers serve the Large Load Facility during a Rate Year, the Qualifying Transmission Revenues and corresponding Supplemental MTRC shall be assigned between them based on the periods during which each provided service, unless the applicable transition agreement provides another Commission-accepted allocation.

9. Workpapers, Verification, and Records
With each Annual Projection and Reconciliation Statement, DesertLink shall provide workpapers sufficient for Eligible Customer to reproduce the calculation, including applicable meter quantities, TAC rates, DesertLink Allocation Factors, adjustments, source references, and a reconciliation to the corresponding Supplemental MTRC and Cumulative Revenue Ledger. Customer-specific or commercially sensitive information may be provided subject to the confidentiality provisions of Section 16.3 of the TO Tariff, the CAISO Tariff, and any applicable confidentiality agreement.

DesertLink, Eligible Customer, and Large Load Customer shall retain supporting records for the period required by the CAISO Tariff, Commission regulations, and Applicable Laws and Regulations, and in all events until completion of any timely initiated review, audit, or dispute concerning the applicable Rate Year. Any dispute concerning the calculation shall be resolved under Article 11 of the Agreement.

10. Project-Specific Methodology Elections
Applicable Withdrawals
methodology
[●]
Treatment of shared meters or
identifiers
[●]
Treatment of behind-the-meter
generation and storage
[●]
Applicable TAC, Wheeling
Access Charge, or other CAISO
Tariff rate component(s)
[●]
DesertLink Allocation Factor
methodology
[●]
Loss factor or loss methodology
[●]
Treatment of exports and
station service
[●]
Treatment of refunds and
resettlements
[●]
Treatment of bad debt or
uncollectible amounts
[●]

PDF page 348

Schedule 2 - 6

Projection methodology
[●]
Data-delivery process and
timing
[●]
Other Commission-accepted
project-specific provision
[●]

The methodology shall specify the metering point, applicable local and regional TAC components, DesertLink allocation factor, applicable Wheeling Access Charges or other wholesale transmission access, wheeling, or transmission charges, the identity of any non-PTO serving entity collecting the charge, the basis for attributing each charge to the Large Load Facility, and evidence that the charge reduces transmission revenues otherwise collected through TAC or directly credits DesertLink’s Net Revenue Requirement. It also shall specify treatment of losses, refunds, resettlements, bad debt and balancing-account adjustments, treatment of a change in Eligible Customer, the source of billing and meter data, and the calculation and verification of projected and actual revenue. Qualifying Transmission Revenues count toward the annual and cumulative responsibility but are not separately credited against DesertLink’s transmission revenue requirement because they already reduce transmission revenues otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue Requirement.

PDF page 349

Schedule 3 - 1

Schedule 3
Credit and Security Standards
1. Purpose and Application
This Schedule establishes the forms, delivery, maintenance, replacement, draw, application, and release requirements for all Construction Security and Operational Security required under Article 7. Except for the limited reduction of direct Operational Security provided in Section 3, all Security shall be provided directly by Eligible Customer.

2. Permitted Forms of Security
Eligible Customer may provide Security in the form of cash, a Letter of Credit, or any combination thereof. DesertLink may accept another form of Security if it determines, in its sole discretion, that the form is acceptable.

Cash collateral shall be delivered in immediately available funds to an account designated by DesertLink and shall count dollar-for-dollar toward the applicable Required Security Amount while held by DesertLink.

(a) Construction Security
Eligible Customer shall provide and maintain all Construction Security directly in one or more forms permitted under this Section 2. A Retail Security Certification and Qualifying Retail Security Support shall not constitute, reduce, replace, or satisfy Construction Security or any Pre- In-Service Termination Costs.

(b) Operational Security
Except to the extent reduced under Section 3, Eligible Customer shall provide and maintain direct Operational Security in one or more forms permitted under this Section 2 in an amount equal to one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility.

3. Retail Security Certification
A current Retail Security Certification reduces the direct Operational Security requirement dollar-for-dollar by the amount of Qualifying Retail Security Support identified in that certification. It does not reduce Eligible Customer’s underlying obligations, constitute Security posted directly with DesertLink, or apply to Construction Security or Pre-In-Service Termination Costs.

Each Retail Security Certification must be substantially in the form of Exhibit A contained in Schedule 3 of this Agreement. Eligible Customer shall deliver a Retail Security Certification before first relying on Qualifying Retail Security Support to reduce the direct Operational Security requirement. The Retail Security Certification shall remain effective unless and until

PDF page 350

Schedule 3 - 2

superseded, withdrawn, or deemed ineffective under this Agreement. Eligible Customer shall deliver an updated Retail Security Certification within three (3) Business Days after any reduction, draw, expiration, nonrenewal, termination, amendment, loss of enforceable draw or application rights, or other event that could impair the certified support.

With each Reconciliation Statement, DesertLink may identify the amount of Qualifying Retail Security Support then reflected in calculating Required Operational Security. That identification does not require Eligible Customer to deliver a new Retail Security Certification unless an event requiring an update has occurred.

DesertLink may rely on the certification without reviewing the underlying retail security documents in the ordinary course, but may request supporting information after a payment default, Credit Review Event, Material Adverse Credit Event, or reasonable basis to question the certification.

4. Letter of Credit Requirements
If Eligible Customer provides a Letter of Credit as Security, the Letter of Credit must be irrevocable, unconditional, transferable, payable at sight, and permit partial and multiple draws. It must be issued by a major United States commercial bank or United States branch of a major foreign commercial bank rated at least A- by S&P, A3 by Moody’s, or A- by Fitch, in each case by at least two of those three agencies, and otherwise be in form and substance reasonably acceptable to DesertLink.

Each Letter of Credit must have an initial stated term of at least twelve (12) months and provide DesertLink at least ninety (90) Calendar Days’ prior written notice of nonrenewal. Eligible Customer shall provide a conforming extension, replacement Letter of Credit, cash collateral, or other Security accepted by DesertLink no later than sixty (60) Calendar Days before the applicable expiration date following a notice of nonrenewal, and within fifteen (15) Business Days after an issuer rating reduction.

If Eligible Customer fails to timely provide the required replacement or substitute Security, DesertLink may, before the applicable Letter of Credit expires, draw all or any portion of the then-available amount and retain the proceeds as cash collateral, apply the proceeds to secured obligations, or both.

5. Security Notices; Maintenance; and Replenishment
DesertLink may issue a Security Notice whenever it reasonably determines that the Required Security Amount exceeds available Security, including as a result of a draw, application of cash collateral, change in the Required Security Amount, loss of Qualifying Retail Security Support, or other event affecting Security availability.

Eligible Customer shall provide any required increase, restoration, replacement, or other cure within fifteen (15) Business Days after receipt of the Security Notice, or by the applicable in- service date if earlier.

6. Draws; Application; and Release

PDF page 351

Schedule 3 - 3

DesertLink may draw against a Letter of Credit, apply cash collateral, or apply another accepted form of Security as permitted under Article 7. A draw, the holding of proceeds or cash collateral, or replenishment does not by itself satisfy an obligation or reduce Cumulative Revenue Responsibility. Proceeds of Operational Security become Applied Security Proceeds only when applied to an identified secured obligation as provided in Section 7.6; proceeds of Construction Security are treated as provided in Sections 3.3.2 and 3.3.3.

DesertLink shall release excess Security after the applicable Reconciliation Statement becomes final. DesertLink shall release all remaining Security within thirty (30) Calendar Days after final satisfaction of all secured obligations, subject to any specifically identified unresolved dispute.

7. Required Security Amount Not a Limitation
The Required Security Amount is based on then-current estimates and calculations and does not limit Eligible Customer’s total liability or responsibility for its obligations under this Agreement.

PDF page 352

Schedule 3, Exhibit A
Form of Retail Security Certification
Retail Security Certification
To: DesertLink, LLC
Re: Large Load Cost Recovery Agreement dated [●] between DesertLink, LLC and [Eligible Customer] (the “Agreement”)

The undersigned, an authorized officer of [Eligible Customer], certifies on behalf of Eligible Customer, as of the date of this certification, as follows:

1. The retail Large Load Customer is [name], and the Large Load Facility is [identify facility].
2. The retail security arrangement is [identify agreement, security type, provider or issuer, instrument number if applicable, and effective and expiration dates].

3. The amount of retail security currently available to Eligible Customer and available for the wholesale obligations under the Agreement is $[●].

4. Eligible Customer has enforceable draw or application rights, or the benefit of a binding undertaking, that permit it to use the retail-security proceeds to satisfy the corresponding wholesale obligations under the Agreement.

5. The certified amount has not been counted for another inconsistent obligation and has not been reduced, drawn, expired, cancelled, or otherwise impaired except as disclosed here: [●].

6. The retail security arrangement has the following renewal, expiration, and notice terms: [●]. Eligible Customer will deliver an updated Retail Security Certification to DesertLink within three (3) Business Days after any reduction, draw, expiration, nonrenewal, termination, amendment, loss of enforceable draw or application rights, or other event that could impair the certified support.

7. The statements in this certification are true and complete in all material respects as of the date of this certification. Eligible Customer understands that DesertLink is entitled to rely on this continuing certification without reviewing the underlying retail-security documents in the ordinary course, subject to DesertLink’s rights under Article 7 and Schedule 3. No annual renewal or recertification is required unless an updated Retail Security Certification is required under Item 6.

This Retail Security Certification is continuing and shall remain effective unless and until superseded, withdrawn, or deemed ineffective under the Agreement.

ELIGIBLE CUSTOMER
By: ________________________________
Name: ______________________________
Title: _______________________________
Date: _______________________________

PDF page 353

Schedule 4 - 1

Schedule 4
CAISO Regional Project Allocation and Responsibility
This Schedule shall identify each CAISO-Assigned Regional Project associated with the Large Load Facility. If no CAISO-Assigned Regional Project has been identified as of the Effective Date, this Schedule shall state “None identified as of [date]” and shall be updated promptly after CAISO formally assigns a specific project share to the Large Load Facility. The assigned share, ownership, expected and actual Regional Project In-Service Date, any Commission-authorized abandoned-plant incentive and its applicable order, any pre-service payment or security required by the CAISO Tariff or another Commission-accepted arrangement, billing path, applicable operational security, and credits or true-ups shall be documented below. The Schedule shall not be read to impose pre-service Construction Security under this Agreement unless separately required by the applicable tariff or Commission-accepted arrangement.

Required project information
Project-specific entry
CAISO project name and identification number
[to be completed]
Project owner and other responsible entities
[to be completed]
CAISO Tariff provision, order, study, or formal
determination establishing the specific assignment
[to be completed]
Date the assignment is made and its effective date
[to be completed]
Large Load Facility to which the specific share is
assigned
[to be completed]
Assigned share: percentage, dollar amount, or
other CAISO-approved measure
[to be completed]
Allocation basis and calculation, including any
share assigned to other beneficiaries
[to be completed]

PDF page 354

Schedule 4 - 2

Required project information
Project-specific entry
Project ownership and whether costs are included in DesertLink’s Formula Rate

[to be completed]
Expected and actual project in-service date [to be completed]

Estimated Annual MTRC and, once established, Final Annual MTRC for the project share (the Regional Project Allocated ARR), together with the projected Total Required Revenue Commitment, if DesertLink-owned and included in its Formula Rate

[to be completed]
Billing entity, payment method, applicable tariff or project-owner arrangement, and invoicing schedule [to be completed]

Construction and operational security required, security provider, amount, effective date, and deadline [to be completed]

Treatment of TAC revenues, direct payments, credits, refunds, and true-ups to prevent duplicate recovery

[to be completed]
Deadline for Eligible Customer to provide
executed arrangement or compliance evidence [to be completed]

Method and timing for any prospective
assignment change authorized by the CAISO Tariff or Commission-accepted methodology

[to be completed]

PDF page 355

Schedule 4 - 3

Required project information
Project-specific entry
Commission order and status authorizing
abandoned-plant incentive for the project, including
applicable project scope and recovery terms
[to be completed]
Pre-service cancellation or abandonment cost
treatment under the CAISO Tariff, Commission order, or
approved project arrangement; any customer contribution
or security required and applicable credits
[to be completed]
For a CAISO-Assigned Regional Project owned by another entity, this Schedule records the Eligible Customer’s separate obligation under the CAISO Tariff or project-owner arrangement. That obligation is not included in any Annual MTRC, Regional Project Allocated ARR, Total Required Revenue Commitment, Cumulative Revenue Responsibility, or TRBAA Credit unless the costs are included in DesertLink’s Formula Rate and the specific share is expressly identified as DesertLink’s responsibility. Any applicable CAISO Tariff credit or project-owner credit shall be applied to prevent recovery of the same assigned share more than once.

PDF page 356

Schedule 5 - 1

Schedule 5
MTRC Calculation Template and Cumulative Revenue Ledger
This Schedule contains the project-specific calculation of each Estimated Annual MTRC and Final Annual MTRC and the Cumulative Revenue Ledger. DesertLink shall calculate each Annual MTRC solely under this Schedule. The Final Annual MTRC shall equal the applicable final incurred capital cost multiplied by the Project-Specific Levelized Fixed Charge Rate calculated in this Schedule. The calculation shall identify the applicable capital-cost input, present-worth tax-depreciation benefits, Formula Rate inputs, fixed expense allocator, applicable allocation percentage, Annual MTRC, Total Required Revenue Commitment, Remaining Cumulative Revenue Responsibility, and supporting inputs.

For purposes of calculating present-worth federal and state income-tax depreciation benefits, the Schedule applies a levelized-depreciation rate of five percent (5%) of the applicable capital cost input in each year of the twenty (20)-year MTRC Term. This levelized-depreciation schedule is not a separate annual charge. The Schedule is fixed on the Final MTRC Determination Date except to correct an error or fraud, to implement an effective prospective reassignment, to implement a final FERC order applicable to the calculation, to implement a Dispute Determination under Section 11.5, or to reflect, prospectively, a change in (i) DesertLink’s return on equity component of its Formula Rate, resulting from a final FERC order accepting or approving such change, or (ii) applicable federal or state tax rates or tax law enacted after the Final MTRC Determination Date; provided that, the five percent (5%) annual levelized- depreciation schedule shall remain fixed for the MTRC Term unless a final FERC order requires otherwise.

The following project-specific calculation and ledger shall be completed for each Covered Upgrade. DesertLink shall include an updated ledger statement in each Reconciliation Statement served on Eligible Customer under Sections 6.6 and 6.7; this Schedule does not impose a separate FERC filing requirement.

Annual Ledger Service. DesertLink shall update the Cumulative Revenue Ledger at least annually in connection with its Annual Update and shall include the resulting statement and the supporting workpapers in each Reconciliation Statement served on Eligible Customer. The statement is an agreement-administration record and is not required to be filed with FERC unless FERC otherwise requires. Any dispute concerning the statement shall be resolved under Article 11 of the Agreement.

PDF page 357

Schedule 5 - 2

Inputs and Security

PDF page 358

Schedule 5 - 3

Qualifying Revenue and Cumulative Revenue Ledger

PDF page 359

Schedule 5 - 4

Present Worth and Annualization Calculation

PDF page 360

Schedule 5 - 5

Expense and Capital Structure Inputs

PDF page 361

Schedule 5 - 6

Twenty-Year Depreciation Schedule

PDF page 362

Schedule 5 - 7

PDF page 363

i

Appendix VI  LARGE LOAD INTERCONNECTION PROCEDURES

PDF page 364

ii

TABLE OF CONTENTS

 Page No.
Section 1.  Objectives and Applicability … 1

1.1 Objectives……………………………………………………………….1

1.2 Applicability……………………………………………………………. 1

Section 2.
Definitions … 1

Section 3.
General Provisions Applicable to All Interconnection Requests … 6

3.1 Interconnection Requests … 6

3.2 Transmission Interconnection Service … 6

3.2.1
The Product … 6

3.2.2
No Applicability to Transmission Service … 7

3.2.3
Roles and Responsibilities … 7

3.3 Comparability … 7

3.4 Base Case Data … 8

3.5 Coordination with Affected Systems … 8

3.6  Capacity of the Large Load … 8

3.7  Proposed Service Commencement Date … 9

3.7.1
Interconnection Request … 9

3.7.2
After Start of the Large Load Interconnection Study … 9
3.8 Queue Position … 10 3.9 Withdrawal … 10

3.10 Withdrawal Penalty … 11 3.10.1  Calculation of the Withdrawal Penalty … 11 3.11 Standards for Co-located Inverter Based Generating Facilities … 12

Section 4. Large Load Study Process … 12

4.1 Timing for Submitting Interconnection Requests … 12

4.2 Processing of Interconnection Request … 12

4.2.1
Initiating an Interconnection Request … 13

4.2.1.1 Use of Interconnection Study Deposit … 13

4.3 Validation of Interconnection Request … 14

4.3.1
Acknowledgment of Interconnection Request … 14

4.3.2
Deficiencies in Interconnection Request … 14

4.4   Potential Deferral of the Interconnection Studies … 15 4.5 Scoping Meeting … 15

4.6 Interconnection Studies … 16

4.6.1
Large Load Interconnection Study … 17

4.6.1.1  Scope of the Large Load Interconnection Study … 17

4.6.1.2  Timing of the Large Load Interconnection Study Results .18

4.6.1.3   Large Load Interconnection Study Report Meeting … 19

4.6.1.4 Increase in the Commercial Readiness Deposit … 19
4.6.1.5  Restudy … 20 4.6.1.6  Modifications … 20

PDF page 365

iii

4.6.2     Optional Flexible Interim Load Interconnection (FILI) Study and
Agreement … 21 4.6.3     Additional Studies … 23

4.6.4     Financing of Participating TO’s Interconnection Facilities and Large
Load Network Upgrades … 24 4.7 Interconnection Financial Security … 24

4.7.1
Types of Interconnection Financial Security … 24

Section 5.
Large Load Interconnection Agreement … 25

5.1 Tender … 25 5.2   Negotiation … 25

5.3 Execution and Filing … 26 5.4   Commencement of Interconnection Activities … 27

Section 6.
Construction of Participating TO’s Interconnection Facilities

 and Large Load Network Upgrades … 27

6.1 Schedule … 27 6.2 Construction Sequencing … 27

6.2.1
General … 27

6.2.2
Advancing Construction of
Large Load Network Upgrades that are Part of an Expansion Plan of the
Participating TO … 27

6.3 Special Provisions for Affected Systems … 28

Section 7.
Miscellaneous … 28

7.1 Confidentiality … 28

7.1.1
Scope … 28

7.1.2
Release of Confidential Information … 29

7.1.3
Rights … 29

7.1.4
No Warranties … 29

7.1.5
Standard of Care … 30

7.1.6
Order of Disclosure … 30

7.1.7
Remedies … 30

7.1.8
Disclosure to FERC, its Staff, or a State … 30

7.2 Disputes … 31 7.2.1

Submission … 31

Attachment 1 – Interconnection Request Form

PDF page 366

1

 LARGE LOAD INTERCONNECTION PROCEDURES (LLIP)

Section 1.
Objectives and Applicability
1.1 Objectives

The objective of this LLIP is to implement requirements for Large Load interconnections to the Participating TO’s Transmission System pursuant to the TO Tariff.  For purposes of this LLIP, the “Participating TO” is DesertLink, LLC (“DesertLink”), and the “TO Tariff” is the DesertLink, LLC Transmission Owner Tariff.  Because DesertLink is a Non-Load-Serving Participating TO and has no End-Use Customers, a Large Load interconnecting under this LLIP will not be a retail transmission customer of the Participating TO.

1.2 Applicability

The LLIP is applicable to a Large Load Interconnection Customer that is either (1) proposing to interconnect a Large Load to the Participating TO’s Transmission System; (2) seeking to increase the capacity of an existing Large Load processed under the LLIP; or (3) with respect to an existing load interconnected to the Participating TO’s Transmission System that was not processed under the LLIP, seeking an increase of 50 MW or greater.  This LLIP only applies to completed Interconnection Requests submitted after the effective date of this Appendix VI to the TO Tariff.  Consistent with Section 10A of the TO Tariff, all requests for ECLL Interconnection shall be directed to the Participating TO.  An Interconnection Request submitted under this LLIP shall constitute the ECLL Interconnection Application, and the Interconnection Studies and the Large Load Interconnection Agreement under this LLIP shall constitute the study process and the ECLL Interconnection Agreement, respectively, for purposes of Section 10A of the TO Tariff.

Section 2.
Definitions

Terms used in this LLIP with initial capitalization shall have the meanings set forth below.  The singular of any definition shall include the plural and the plural shall include the singular.  If a term with initial capitalization used herein is not defined, such term shall have the meanings ascribed to such term in Section 3 of the TO Tariff.

Affected System shall mean an electric system other than the Participating TO’s Transmission System that may be affected by the proposed interconnection.

Affected System Operator shall mean the entity that owns or operates an Affected System, and includes an Affected System Owner as defined in any Cost Recovery Agreement.

Applicable Laws and Regulations shall mean all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any Governmental Authority.

PDF page 367

2

Base Case shall mean data including, but not limited to, base power flow, short circuit and stability data bases, underlying load, generation, and transmission facility assumptions, contingency lists, including relevant remedial action schemes, and transmission diagrams used to perform the Interconnection Studies.  The Base Case may include Critical Energy Infrastructure Information (as that term is defined by FERC).  The Base Case may include transmission facilities as approved by the Participating TO or ISO, as applicable, Reliability Network Upgrades that are included in a signed interconnection agreement, Large Load Network Upgrades, Large Loads and any co-located generation, and load forecast. The Base Case may also include generation facilities that (i) are directly interconnected to a Distribution System or the ISO Controlled Grid; (ii) are interconnected to Affected Systems and may have an impact on the Interconnection Request; (iii) have a pending request to interconnect to a Distribution System or an Affected System; or (iv) are not interconnected to a Distribution System or the ISO Controlled Grid, but are subject to the terms and conditions of a fully executed interconnection agreement (or its equivalent predecessor agreement) or for which an unexecuted interconnection agreement (or its equivalent predecessor agreement) has been requested to be filed with FERC.

Business Day shall mean Monday through Friday, excluding Federal Holidays.

Calendar Day shall mean any day including Saturday, Sunday or a Federal Holiday.

Commercial Readiness Deposit shall mean a deposit paid as set forth in LLIP Sections 4.2.1 and 4.6.1.4.

Confidential Information shall mean any confidential, proprietary or trade secret information of a plan, specification, pattern, procedure, design, device, list, concept, policy or compilation relating to the present or planned business of a Party, which is designated as confidential by the Party supplying the information, whether conveyed orally, electronically, in writing, through inspection, or otherwise.

Cost Recovery Agreement shall have the meaning set forth in Section 3 of the TO Tariff.

Dispute Resolution shall mean the applicable procedure for resolution of a dispute between the Parties as described in Section 14 of the TO Tariff, including, as applicable, the ISO ADR Procedures.

Flexible Interim Load Interconnection (FILI) Service shall have the meaning set forth in Section 3 of the TO Tariff.

FILI Study shall mean the study performed by the Participating TO pursuant to LLIP Section 4.6.2 to determine the availability of Interim Firm Interconnection Service and FILI Service.

Interconnection Financial Security shall mean any of the financial instruments listed in LLIP Section 4.7.1 provided by the Large Load Interconnection Customer to comply with its obligations under the LLIP or the Large Load Interconnection Agreement.

PDF page 368

3

Interconnection Request shall mean a request, in the form of Attachment 1 to Appendix VI to the TO Tariff, to interconnect a new Large Load, or to increase the capacity of, or make a Material Modification to the operating characteristics of, an existing Large Load that is interconnected with the Participating TO’s Transmission System.

Interconnection Study shall mean any of the following studies: the Large Load Interconnection Study, the FILI Study, restudies, and any additional studies performed pursuant to LLIP Section 4.6.3.

Interconnection Study Deposit shall mean the cash deposit provided to the Participating TO under LLIP Section 4.2.1 as a requirement of a valid Interconnection Request to be used to offset the cost of the Interconnection Studies.

Large Load Capacity shall mean the maximum capacity of the Large Load at the Point of Interconnection.

Large Load Customer shall mean the End-User that owns, operates, or proposes to develop the Large Load and receives, or will receive, retail transmission service from the Large Load Interconnection Customer, and shall be the Large Load Customer for purposes of the TO Tariff and any Cost Recovery Agreement.

Large Load Interconnection Agreement shall mean the interconnection agreement between the Participating TO and the Large Load Interconnection Customer, developed by the Participating TO consistent with the TO Tariff and the results of the Interconnection Studies and negotiated between the Parties pursuant to LLIP Section 5, which sets forth the terms and conditions governing the interconnection of the Large Load to the Participating TO’s Transmission System, including, without limitation, cost responsibility, payment provisions, cost recovery, and financial security for the Participating TO’s Interconnection Facilities and Large Load Network Upgrades, as it may be amended from time to time. The Large Load Interconnection Agreement shall constitute the ECLL Interconnection Agreement for purposes of the TO Tariff, as applicable, and shall be filed with FERC by the Participating TO to the extent required. For purposes of the TO Tariff, the Participating TO’s Interconnection Facilities and Large Load Network Upgrades identified in the Large Load Interconnection Agreement shall together constitute the ECLL Interconnection Facilities.

Large Load Interconnection Customer shall mean an Eligible Customer for Large Load (“ECLL”), as defined in Section 3 of the TO Tariff, that proposes to interconnect its facilities with the Participating TO’s Transmission System for the purpose of providing retail transmission service to a Large Load.

Large Load Interconnection Customer Interconnection Facilities shall mean all facilities and equipment owned, controlled, or operated by the Large Load Interconnection Customer or the Large Load Customer up to the Point of Change of Ownership as identified in the Large Load Interconnection Agreement, including any modifications, additions or upgrades to such facilities and equipment.

PDF page 369

4

Large Load Interconnection Procedures (LLIP) shall mean the interconnection procedures applicable to an Interconnection Request set forth in this Appendix VI to the TO Tariff.

Large Load Interconnection Study shall mean an engineering study conducted by the Participating TO for a Large Load Interconnection Customer under the LLIP that evaluates the impact of the proposed interconnection on the safety and reliability of Participating TO’s Transmission System and, if applicable, an Affected System. The Large Load Interconnection Study will also determine a list of facilities (including Participating TO’s Interconnection Facilities and Large Load Network Upgrades), the cost of those facilities, and the time required to interconnect the Large Load with the Participating TO’s Transmission System. The scope of the study is defined in LLIP Section 4.6.1.1.

Large Load Network Upgrades shall mean the additions, modifications, and upgrades to the ISO Controlled Grid at or beyond the Point of Interconnection necessary to serve one or more Large Loads safely and reliably that are identified through the Large Load Interconnection Study and submitted to the ISO for concurrence pursuant to Section 25.7 of the ISO Tariff. Large Load Network Upgrades do not include Participating TO’s Interconnection Facilities. To the extent a Large Load Network Upgrade is owned or to be constructed by the Participating TO and is identified in Schedule 1 to a Cost Recovery Agreement, such Large Load Network Upgrades shall constitute Large Load-Driven Upgrades, as defined in that Cost Recovery Agreement.

Large Load Study Process Agreement shall mean the agreement, developed and tendered by the Participating TO pursuant to LLIP Section 4.5, entered into by the Large Load Interconnection Customer and the Participating TO which sets forth the Parties’ agreement to perform Interconnection Studies under the LLIP.

Material Modification shall mean those modifications that have a material impact on the cost or timing of any Interconnection Request, or any other valid interconnection request to the Participating TO or the ISO, with an equal or later Queue Position date.

Participating TO’s Interconnection Facilities shall mean all facilities and equipment owned, controlled, or operated by the Participating TO from the Point of Change of Ownership to the Point of Interconnection as identified in the Large Load Interconnection Agreement, including any modifications, additions or upgrades to such facilities and equipment. Participating TO’s Interconnection Facilities are transmission facilities but are not controlled by the ISO.  Participating TO’s Interconnection Facilities are sole use facilities and shall not include Large Load Network Upgrades.

Participating TO’s Transmission System shall mean the facilities owned and operated by the Participating TO and that have been placed under the ISO’s Operational Control, which facilities form part of the ISO Controlled Grid.

Point of Change of Ownership shall mean the point, as set forth in the Large Load Interconnection Agreement, where the Large Load Interconnection Customer's interconnection facilities connect to the Participating TO’s Interconnection Facilities.

PDF page 370

5

Point of Interconnection shall mean the point, as set forth in the Large Load Interconnection Agreement, where the Participating TO’s Interconnection Facilities connect to the Participating TO’s Transmission System.  For purposes of the TO Tariff, the Point of Interconnection shall be the Point of Withdrawal for the Large Load.

Queue Position shall mean the order of a valid Interconnection Request, relative to all other pending valid Interconnection Requests, established pursuant to LLIP Section 3.8.

Reasonable Efforts shall mean, with respect to an action required to be attempted or taken by a Party under the LLIP or the Large Load Interconnection Agreement, efforts that are timely and consistent with Good Utility Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.

Report Meeting shall mean the meeting among the Participating TO, the Large Load Interconnection Customer, and if applicable, the ISO and other Affected System Operators to discuss the results of the Interconnection Studies as set forth in the LLIP.

Scoping Meeting shall mean the meeting between representatives of the Large Load Interconnection Customer and Participating TO, and if applicable, the ISO, conducted for the purpose of discussing alternative interconnection options, to exchange information including any transmission data and earlier study evaluations that would be reasonably expected to impact such interconnection options, to analyze such information, and to determine the potential feasible Points of Interconnection.

Service Commencement Date shall mean the date the Large Load is initially operated in parallel with the Participating TO’s Transmission System and transmission interconnection service is provided to the Large Load Interconnection Customer pursuant to the terms of an executed Large Load Interconnection Agreement. For purposes of any Cost Recovery Agreement, the Service Commencement Date shall be the Large Load Service Commencement Date specified in Schedule 1 to that agreement.

Site Control shall have the meaning set forth in Section 3 of the TO Tariff.

System Protection Facilities shall mean the equipment, including necessary protection signal communications equipment, that protects (1) the Participating TO’s Transmission System, Participating TO’s Interconnection Facilities, ISO Controlled Grid, and Affected Systems from faults or other electrical disturbances occurring at the Large Load and (2) the Large Load from faults or other electrical system disturbances occurring on the ISO Controlled Grid, Participating TO’s Interconnection Facilities, and Affected Systems or on other delivery systems or other generating systems to which the ISO Controlled Grid is directly connected.

Transmission Interconnection Service shall mean the service provided by the Participating TO associated with interconnecting the Large Load to the Participating TO’s Transmission System and enabling the Large Load Interconnection Customer to receive electric energy at the Point of Interconnection, pursuant to the terms of the Large Load Interconnection Agreement and the TO Tariff.

PDF page 371

6

Withdrawal Penalty shall mean the penalty assessed by Participating TO to a Large Load Interconnection Customer that chooses to withdraw or is deemed withdrawn from Participating TO’s interconnection queue or whose Large Load does not otherwise reach its Service Commencement Date. The calculation of the Withdrawal Penalty is set forth in LLIP Section 3.10.1.

Section 3.
General Provisions Applicable to All Interconnection Requests

3.1
Interconnection Requests
A Large Load Interconnection Customer shall submit to Participating TO an Interconnection Request in the form of Attachment 1 to this LLIP for processing under the LLIP.  Consistent with Section 10A.2.1 of the TO Tariff, the Large Load Interconnection Customer shall send a copy of the Interconnection Request to the ISO, and the Interconnection Request and all supporting documentation shall be submitted electronically to the Participating TO in the manner posted on the Participating TO’s public website.

An Interconnection Request for the expansion of capacity of an existing Large Load shall be treated the same as an Interconnection Request for a new Large Load pursuant to this LLIP.

Co-located generation serving a Large Load that will not export to the ISO Controlled Grid shall be interconnected in accordance with the generator interconnection rules of the applicable ECLL, as approved by its Local Regulatory Authority (including, for a UDC subject to the jurisdiction of the CPUC, CPUC Electric Rule 21), consistent with Section 10A.5 of the TO Tariff; provided that, where such co-located generation is included in the Interconnection Request, the Participating TO will evaluate its incremental impacts on the Participating TO’s Transmission System as part of the LLIP study process. Co- located generation that will export to the ISO Controlled Grid is required to submit a generator interconnection request to the ISO in accordance with Section 25.7.6 of the ISO Tariff for evaluation of the proposed generator interconnection and the Large Load will be evaluated pursuant to the LLIP.  For a Large Load co- located with an exporting generating facility, the ISO will be a party to a pro forma agreement that bridges the generator’s Large Generator Interconnection Agreement with the Large Load Interconnection Agreement, or will negotiate a non-conforming Large Generator Interconnection Agreement, consistent with Section 10A.5 of the TO Tariff.

3.2
Transmission Interconnection Service

3.2.1 The Product.  Transmission Interconnection Service allows Large Load Interconnection Customer to connect the Large Load to the Participating TO’s Transmission System and be eligible to receive electric energy and capacity from the ISO Controlled Grid.

PDF page 372

7

3.2.2 No Applicability to Transmission Service.  Nothing in this LLIP shall constitute a request for transmission service or confer upon a Large Load Interconnection Customer any right to receive transmission service.

3.2.3 Roles and Responsibilities.

3.2.3.1 Each Interconnection Request will be subject to the direction and oversight of the Participating TO.  The Participating TO will conduct or cause to be performed the required Interconnection Studies and any additional studies the Participating TO determines to be reasonably necessary.  The analysis of impacts on, and upgrades required to, the Participating TO’s Transmission System will be performed by the Participating TO and will be subject to review and concurrence by the ISO.  The Participating TO will perform all required studies related to the Participating TO’s Transmission System and will coordinate with Affected System Operators in accordance with LLIP Section 3.5.

3.2.3.2 The Participating TO will complete or cause to be completed all studies as required within the timelines provided in this LLIP.

3.2.3.3 Each Large Load Interconnection Customer shall pay the actual costs of all Interconnection Studies, and any additional studies the Participating TO determines to be reasonably necessary in response to the Interconnection Request.  The Participating TO shall reimburse the ISO for the actual cost of any portion of the Interconnection Studies that the ISO performs related to the ISO Controlled Grid, as applicable.

3.2.3.3.1 The Participating TO shall issue invoices for Interconnection Studies that shall include a detailed and itemized accounting of the cost of each Interconnection Study.  Whenever the actual cost of performing the

Interconnection Studies exceeds the Interconnection
Study Deposit, the Large Load Interconnection Customer shall pay the undisputed difference in accordance with the Participating TO issued invoice within thirty (30)

Calendar Days.  The Participating TO shall not be
obligated to continue to have any studies conducted
unless the Large Load Interconnection Customer has paid all undisputed amounts in compliance herewith.

3.3
Comparability
Participating TO shall receive, process and analyze all Interconnection Requests in a timely manner as set forth in this LLIP.  Participating TO will use the same

PDF page 373

8

Reasonable Efforts in processing and analyzing Interconnection Requests from all Large Load Interconnection Customers, whether the Large Load is owned by Participating TO and its Affiliates or by a third party.

3.4
Base Case Data
Participating TO shall provide Base Case data to a Large Load Interconnection Customer upon request subject to confidentiality provisions in LLIP Section 7.1. Participating TO shall provide base power flow, short circuit databases, including all underlying assumptions, and contingency list used in the Large Load Interconnection Customer’s Interconnection Studies.  Participating TO is permitted to require that the Large Load Interconnection Customer sign a confidentiality agreement before the release of commercially sensitive information or Critical Energy Infrastructure Information in the Base Case data. Such Base Cases may include all (i) Large Loads, (ii) generation projects, and (iii) transmission projects, including merchant transmission projects that are proposed for the Participating TO’s Transmission System for which a transmission expansion plan has been submitted and approved by the applicable authority.

3.5
Coordination with Affected Systems
The Participating TO will notify the Affected System Operators that are potentially affected by a Large Load Interconnection Customer’s Interconnection Request.  The Participating TO will coordinate the conduct of any studies required to determine the impact of the Interconnection Request on Affected Systems with Affected System Operators and, if possible, include those results (if available) in its applicable Interconnection Study within the time frame specified in this LLIP.  Participating TO will include such Affected System Operators in all meetings held with Large Load Interconnection Customer as required by this LLIP.  Large Load Interconnection Customer will cooperate with Participating TO in all matters related to the conduct of studies and the determination of modifications to Affected Systems.  If an Affected System Operator, that has been informed its system is an Affected System refuses to cooperate with the Participating TO with whom interconnection has been requested in all matters related to the conduct of studies and the determination of whether modifications to its Affected System are necessary to avoid adverse impacts, it waives any right in any fora that the Participating TO’s provision of service has adversely impacted such Affected System Operator.

3.6
Capacity of the Large Load

The Interconnection Request shall be evaluated using the maximum capacity requested by the Large Load Interconnection Customer.  However, if the maximum capacity that the Large Load is capable of receiving is greater than the maximum capacity requested by the Large Load Interconnection Customer, the Large Load Interconnection Customer will be required to limit the Large Load capacity to no greater than the amount requested (e.g., through use of a control

PDF page 374

9

system, power relay(s), or other similar device settings or adjustments), and the Large Load Interconnection Customer must obtain the Participating TO’s agreement, with such agreement not to be unreasonably withheld, that the manner in which the Large Load Interconnection Customer proposes to implement such a limit will not adversely affect the safety and reliability of the Participating TO’s Transmission System.  If the Participating TO does not so agree, then the Interconnection Request must be withdrawn or revised to specify the maximum capacity that the Large Load is capable of receiving.    Furthermore, nothing in this section shall prevent a Participating TO from considering a capacity higher than the limited capacity, if appropriate, when evaluating system protection impacts.

3.7
Proposed Service Commencement Date
The  proposed Service Commencement Date of the new Large Load or increase in capacity of the existing Large Load shall not exceed seven years from the date the Interconnection Request is received by Participating TO for those Interconnection Requests studied in accordance with the Large Load Interconnection Procedures, unless Large Load Interconnection Customer demonstrates and the Participating TO agrees, such agreement not to be unreasonably withheld, that engineering, permitting and construction of the new Large Load or increase in capacity of the existing Large Load will take longer than the seven-year period.

3.7.1 Interconnection Request.  If the proposed Service Commencement Date in the Interconnection Request is more than seven years from the date the Interconnection Request is received by the Participating TO, the Large Load Interconnection Customer must demonstrate, subject to the Participating TO’s agreement, such agreement not to be unreasonably withheld, that the required engineering, permitting and construction of the Large Load will take longer than the seven-year period.

3.7.2 After Start of the Large Load Interconnection Study.  Any request to extend the Service Commencement Date after commencement of the Large Load Interconnection Study under the LLIP, or following execution of a Large Load Interconnection Agreement, shall be subject to the following:

(i) Requested extension does not exceed seven years from Service Commencement Date in the original Interconnection Request.  A request to extend the Service Commencement Date that does not exceed seven years from the Service Commencement Date in the original

Interconnection Request is subject to the modification assessment process specified in LLIP Section 4.6.1.6.1.

(ii) Requested extension exceeds seven years from Service Commencement Date in the original Interconnection Request.  A request to extend the Service Commencement Date that exceeds seven years from the Service Commencement Date in the original Interconnection Request shall (a) demonstrate, subject to the Participating TO’s agreement, such agreement

PDF page 375

10

not to be unreasonably withheld, that engineering, permitting and construction of the new Large Load or increase in capacity of the existing Large Load will take longer than the seven-year period, and (b) be subject to the modification assessment process specified in LLIP Section 4.6.1.6.1.

Any extension of the Service Commencement Date under this LLIP Section 3.7.2 shall not extend the Outside Date under any applicable Cost Recovery Agreement unless the parties to that agreement agree in writing to such extension.

3.8   Queue Position

           3.8.1 Assignment of Queue Position.
Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1.

3.8.2 Higher Queue Position.
A higher Queue Position assigned to an Interconnection Request is one that has been placed “earlier” in the queue in relation to another Interconnection Request that is assigned a lower Queue Position.

3.9
Withdrawal
Large Load Interconnection Customer may withdraw its Interconnection Request at any time by written notice of such withdrawal to Participating TO, and the Participating TO will notify the ISO and Affected System Operators, if any, within three (3) Business Days of receipt of such a notice.  In addition, after confirmation by the Participating TO of a valid Interconnection Request, if the Large Load Interconnection Customer fails to adhere to all requirements of this LLIP, except as provided in LLIP Section 7.2 (Disputes), Participating TO shall deem the Interconnection Request to be withdrawn and shall provide written notice to Large Load Interconnection Customer of the deemed withdrawal within five (5) Business Days and an explanation of the reasons for such deemed withdrawal.  Upon receipt of such written notice, Large Load Interconnection Customer shall have five (5) Business Days in which to either (i) respond with information or action that cures the deficiency, or (ii) support its position that the deemed withdrawal was erroneous and notify the Participating TO of its intent to pursue Dispute Resolution.

For an Interconnection Request under the LLIP, withdrawal shall result in the removal of the Interconnection Request from the Interconnection Studies.  If a Large Load Interconnection Customer disputes the withdrawal and removal from the Interconnection Studies and has elected to pursue Dispute Resolution, Large Load Interconnection Customer's Interconnection Request will not be considered in any ongoing Interconnection Study during the Dispute Resolution process.

PDF page 376

11

In the event of such withdrawal, Participating TO, subject to the provisions in LLIP Section 7.1, as applicable, shall provide, at Large Load Interconnection Customer's request, all information that Participating TO developed for any completed study conducted up to the date of withdrawal of the Interconnection Request.

3.10
Withdrawal Penalty

A Large Load Interconnection Customer with an Interconnection Request being processed under the LLIP will be subject to a Withdrawal Penalty if it withdraws its Interconnection Request or is deemed withdrawn, or the Large Load does not otherwise achieve its Service Commencement Date, which date may be modified if the necessary Participating TO-owned facilities cannot be constructed on a timeline that meets such date, unless: (1) the withdrawal does not have a material impact on the cost or timing of any equal or later queued interconnection request;

(2) Large Load Interconnection Customer withdraws after receiving Large Load Interconnection Customer’s most recent Interconnection Study report and the Large Load Network Upgrade costs assigned to the Interconnection Request identified in that report have increased by more than twenty-five percent (25%) compared to costs identified in Large Load Interconnection Customer’s preceding Interconnection Study report; or (3) Large Load Interconnection Customer withdraws after receiving an Interconnection Study report issued after completion of the initial Large Load Interconnection Study and the Large Load Network Upgrade costs assigned to the Interconnection Request identified in such Interconnection Study report have increased by more than one hundred percent (100%) compared to costs identified in the initial Large Load Interconnection Study report.

3.10.1 Calculation of the Withdrawal Penalty

If the Large Load Interconnection Customer withdraws its Interconnection Request or is deemed withdrawn prior to the commencement of the Large Load Interconnection Study, Large Load Interconnection Customer will not be subject to a Withdrawal Penalty.  If Large Load Interconnection Customer withdraws, is deemed withdrawn, or otherwise does not achieve its Service Commencement Date at any point after the commencement of the Large Load Interconnection Study, that Large Load Interconnection Customer’s Withdrawal Penalty will be the greater of: (1) the Large Load Interconnection Customer’s Interconnection Study Deposit required under LLIP Section 4.2.1; or (2) as follows in (a)–(c):

(a) If Large Load Interconnection Customer withdraws or is deemed withdrawn during the Large Load Interconnection Study or after receipt of a Large Load Interconnection Study report, Large Load Interconnection Customer will be charged two (2) times the actual cost

PDF page 377

12

of the Large Load Interconnection Study performed for the Large Load Interconnection Customer.

(b) If Large Load Interconnection Customer withdraws or is deemed withdrawn after receipt of the draft Large Load Interconnection Agreement but before Large Load Interconnection Customer has executed a Large Load Interconnection Agreement or has requested that its Large Load Interconnection Agreement be filed unexecuted, Large Load Interconnection Customer will be charged ten percent (10%) of its estimated Large Load Network Upgrade costs as reflected in the most recently completed Interconnection Study.

(c) If Large Load Interconnection Customer has executed a Large Load Interconnection Agreement or has requested that its Large Load Interconnection Agreement be filed unexecuted and subsequently withdraws its Interconnection Request, the Large Load Interconnection Customer’s Withdrawal Penalty will be calculated as set forth in the Large Load Interconnection Agreement.

The Commercial Readiness Deposit shall be retained as financial security for the Withdrawal Penalty (if applicable) and, other than as set forth in the Large Load Interconnection Agreement, any security not applied to the Withdrawal Penalty will be released to the Large Load Interconnection Customer following withdrawal or the Service Commencement Date. Where a Cost Recovery Agreement applies, (i) any Commercial Readiness Deposit or Interconnection Financial Security provided for the same costs shall count toward, and shall not be duplicated by, the Construction Security required under the Cost Recovery Agreement, and (ii) any Withdrawal Penalty paid with respect to a Large Load Network Upgrade shall be credited against the Pre-In-Service Termination Costs payable under the Cost Recovery Agreement for that upgrade, so that the Participating TO does not recover the same costs more than once.

3.11
Standards for Co-located Inverter Based Generating Facilities

Inverters used for the production, and/or later injection from storage, of electricity shall meet the inverter certification standards of UL-1741 and UL-1741 Supplement B.

Section 4.  Large Load Study Process

4.1
Timing For Submitting Interconnection Requests
A Large Load Interconnection Customer may submit an Interconnection Request for processing under the LLIP at any time during the year. The Participating TO, in coordination with the ISO, as applicable, will study the Interconnection Request.

4.2
Processing of Interconnection Request

PDF page 378

13

4.2.1
Initiating an Interconnection Request.  To initiate an
Interconnection Request under the LLIP, Large Load Interconnection Customer must submit all of the following: (i) an Interconnection Study Deposit of $250,000; (ii) a completed Interconnection Request in the form of Attachment 1 to the LLIP, including preferred Point of Interconnection and voltage level, all information required by Section 10A.2.1 of the TO Tariff (other than any election of interim service, which shall be made in accordance with LLIP Section 4.6.2), and all other technical data; (iii) a Commercial Readiness Deposit equal to two times the Interconnection Study Deposit described in this LLIP Section 4.2.1 in the form of an irrevocable letter of credit, cash, a surety bond, or other form of security that is reasonably acceptable to Participating TO, in accordance with LLIP Section 4.7.1. This Commercial Readiness Deposit is refunded to Large Load Interconnection Customer according to LLIP Section 3.10.1; however, the Participating TO shall be entitled to hold the Commercial Readiness Deposit until the Large Load Interconnection Customer’s Large Load achieves its Service Commencement Date; and (iv) demonstration of Site Control.

4.2.1.1 Use of Interconnection Study Deposit.  The Interconnection Study Deposit shall be applied to pay for prudent costs incurred by the Participating TO, the ISO, or third parties at the direction of the Participating TO or ISO, as applicable, to perform and administer the Interconnection Studies.

In the event a Large Load Interconnection Customer withdraws its Interconnection Request prior to the commencement of the Large Load Interconnection Study, Large Load Interconnection Customer must pay Participating TO the actual costs of processing its Interconnection Request. In the event a Large Load

Interconnection Customer withdraws after commencement of the Large Load Interconnection Study, Participating TO shall charge and Large Load Interconnection Customer shall pay the actual costs of the Interconnection Studies.

Any difference between the Interconnection Study Deposit and the actual cost of the Interconnection Studies shall be paid by or refunded to the Large Load Interconnection Customer. Any

invoices for Interconnection Studies shall include a detailed and itemized accounting of the cost of each Interconnection Study. Large Load Interconnection Customers shall pay any such

undisputed costs within thirty (30) Calendar Days of receipt of an invoice. If Large Load Interconnection Customer fails to pay such undisputed costs within the time allotted, its Interconnection Request shall be deemed withdrawn and will be subject to a Withdrawal Penalty pursuant to LLIP Section 3.10.1.

PDF page 379

14

The Participating TO will reimburse the ISO or third parties, as applicable, for all work performed on behalf of the withdrawn Interconnection Request at the Participating TO’s direction. The Large Load Interconnection Customer must pay all monies due before it is allowed to obtain any Interconnection Study data or results.

4.3
Validation of Interconnection Request

4.3.1 Acknowledgment of Interconnection Request.  Participating TO shall notify the Large Load Interconnection Customer within ten (10) Business Days of receipt of the Interconnection Request, which notice shall state whether the Interconnection Request is deemed valid.

4.3.2 Deficiencies in Interconnection Request.  An Interconnection Request will not be considered to be a valid request until all items in LLIP Section 4.2.1 have been received by Participating TO and deemed valid by the Participating TO.  If an Interconnection Request fails to meet the requirements set forth in LLIP Section 4.2.1, Participating TO shall include in its notification to the Large Load Interconnection Customer under LLIP Section 4.3.1 the reasons for such failure and that the Interconnection Request does not constitute a valid request.  Consistent with Section 10A.2.3 of the TO Tariff, the Participating TO will attempt to remedy deficiencies in the Interconnection Request through informal communications with the Large Load Interconnection Customer, and the Large Load Interconnection Customer shall provide Participating TO the additional requested information needed to constitute a valid request. Whenever the additional requested information is provided by the Large Load Interconnection Customer, the Participating TO shall notify the Large Load Interconnection Customer within five (5) Business Days of receipt of the additional requested information whether the Interconnection Request is valid.  If the Interconnection Request continues to fail to meet the requirements set forth in LLIP Section 4.2.1, the Participating TO shall include in its notification to the Large Load Interconnection Customer the reasons for such failure.  If an Interconnection Request has not been deemed valid, the Large Load Interconnection Customer must submit all information necessary to meet the requirements of LLIP Section 4.2.1 no later than twenty (20) Business Days after the date the original Interconnection Request was submitted, or ten (10) Business Days after the Participating TO first provided notice that the Interconnection Request was not valid, whichever is later. Interconnection Requests that have not met the requirements of LLIP Section 4.2.1 within twenty (20) Business Days after the date the original Interconnection Request was submitted or ten (10) Business Days after the Participating TO first provided notice that the Interconnection Request

PDF page 380

15

was not valid, whichever is later, will be deemed invalid, will be returned to the Large Load Interconnection Customer in accordance with Section 10A.2.3 of the TO Tariff, and will not be included in the LLIP.

Interconnection Requests deemed invalid under this LLIP Section 4.3.2 are not subject to LLIP Section 3.9.  Large Load Interconnection Customers with invalid Interconnection Requests under this LLIP Section 4.3.2 may seek relief under LLIP Section 7.2 by so notifying the Participating TO within two (2) Business Days of the notice of invalidity.

4.4     Potential Deferral of the Interconnection Studies

           The Participating TO may defer commencement of the Large Load
Interconnection Study when it determines, using Good Utility Practice and reasonable engineering judgment, that the Interconnection Request cannot be studied meaningfully until other pending study results for higher-queued projects are available.

           Within ten (10) Business Days after deeming an Interconnection Request valid under LLIP Section 4.3.1, the Participating TO will notify the Large Load Interconnection Customer in writing if it is deferring the start of the Interconnection Studies. The notice will include: (i) information regarding the pending studies; and (ii) the estimated start date of the Large Load Interconnection Study.  During the period of deferral, the Participating TO will provide a monthly status update to the Large Load Interconnection Customer.

4.5
Scoping Meeting
Within fifteen (15) Business Days after the Participating TO notifies the Large Load Interconnection Customer that the Interconnection Request has been deemed valid as set forth in LLIP Section 4.3.2, the Participating TO shall establish a date agreeable to the Large Load Interconnection Customer, and the ISO, if applicable, for the Scoping Meeting.

The purpose of the Scoping Meeting shall be to discuss reasonable Service Commencement Dates and alternative interconnection options, to exchange information including any transmission data that would reasonably be expected to impact such interconnection options, to analyze such information and to determine the potential feasible Points of Interconnection and eliminate alternatives given resources and available information. The Scoping Meeting shall also include discussion of a deferral of the Interconnection Studies in accordance with LLIP Section 4.4.

The Participating TO will bring to the meeting, as reasonably necessary to accomplish its purpose, such already available technical data, including, but not limited to, (i) general facility loadings, (ii) general instability issues, (iii) general short circuit issues, (iv) general voltage issues, and (v) general reliability issues.

PDF page 381

16

The Large Load Interconnection Customer will bring to the Scoping Meeting, in addition to the technical data form (Appendix A to Attachment 1) submitted with its Interconnection Request, any system studies previously performed.  The Participating TO, the ISO, if applicable, and the Large Load Interconnection Customer will also bring to the meeting personnel and other resources as may be reasonably required to accomplish the purpose of the meeting in the time allocated for the meeting.  On the basis of the meeting, the Large Load Interconnection Customer shall designate its Point of Interconnection.  The duration of the meeting shall be sufficient to accomplish its purpose.

Within five (5) Business Days after the Scoping Meeting, the Participating TO shall tender to the Large Load Interconnection Customer a Large Load Study Process Agreement developed by the Participating TO consistent with the TO Tariff and this LLIP, which shall contain an outline of the scope of the Large Load Interconnection Study, contain a non-binding good faith estimate of the cost to perform such study, and shall specify that the Large Load Interconnection Customer is responsible for the actual cost of the Interconnection Studies, including reasonable administrative costs.  No later than thirty (30) Calendar Days after the Scoping Meeting, the Large Load Interconnection Customer shall either execute and deliver to the Participating TO  the Large Load Study Process Agreement or request that the Participating TO file it unexecuted with FERC, or the Interconnection Request shall be deemed withdrawn.  If an unexecuted filing is requested, the Interconnection Studies will be paused until the Large Load Study Process Agreement is made effective by FERC.

4.6
Interconnection Studies
The Interconnection Studies shall consist of a Large Load Interconnection Study, any FILI Study requested pursuant to LLIP Section 4.6.2, and any additional studies, including but not limited to those identified in LLIP Section 4.6.3 required for interconnection of the Large Load, and co-located generation not exporting to the ISO Controlled Grid, to the Participating TO’s Transmission System.    The analysis of impacts on, and upgrades required to, the Participating TO’s Transmission System will be performed by the Participating TO and will be subject to the review and concurrence of the ISO in accordance with Section 25.7 of the ISO Tariff. The Interconnection Studies will identify Participating TO’s Interconnection Facilities and required Large Load Network Upgrades necessary to mitigate thermal overloads and voltage violations, and address short circuit, stability, and reliability issues associated with the requested Transmission Interconnection Service.

All cost estimates for Participating TO’s Interconnection Facilities and Large Load Network Upgrades, as applicable, contained in the Interconnection Studies will be set forth in the Interconnection Study report in present dollar costs as well as time-adjusted dollar costs, adjusted to the estimated year of construction of the components being constructed.

PDF page 382

17

The Participating TO will prepare an Interconnection Study report to document the results of the Interconnection Studies.

4.6.1 Large Load Interconnection Study.

4.6.1.1  Scope of the Large Load Interconnection Study.  The Large Load Interconnection Study will consist of a  short circuit analysis, a power flow analysis, an electromagnetic transient (“EMT”) screening, a non-binding good faith estimate of the scope and cost of the Participating TO’s Interconnection Facilities and Large Load Network Upgrades, and any other studies that are deemed necessary. The Large Load Interconnection Study will also identify the need for any additional studies (e.g., stability analysis, EMT study, etc.) to be performed as part of the scope of work set forth in the Large Load Interconnection Agreement pursuant to LLIP Section 4.6.3.  When there is co-located generation not exporting to the ISO Controlled Grid and not subject to electrical short circuit duty dependence, the Large Load Interconnection Study will identify the impacts associated with the Large Load and any incremental impacts of the co-located generation.

The Large Load Interconnection Study will consider the use of alternative transmission technologies including dynamic line ratings, advanced power flow control devices, advanced conductors, and transmission switching, when evaluating transmission solutions to accommodate new Large Loads and their associated transmission system impacts.  If traditional network upgrades are selected instead of alternative transmission technologies, the Participating TO will provide a demonstration of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline for accommodating the interconnection of the Large Load.

The Large Load Interconnection Study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested Transmission Interconnection Service, including an estimate of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the Interconnection.

The Large Load Interconnection Study shall provide a list of Participating TO’s Interconnection Facilities and Large Load Network Upgrades, as applicable, that are required as a result of the Interconnection Request.

PDF page 383

18

4.6.1.2 Timing of the Large Load Interconnection Study Results.  The Participating TO shall use Reasonable Efforts to complete the Large Load Interconnection Study within ninety (90) Calendar Days after the execution of a Large Load Study Process Agreement or, if the Large Load Study Process Agreement is filed unexecuted, after it is made effective by FERC.  The Participating TO will issue a Large Load Interconnection Study report to the Large Load Interconnection Customer. The Participating TO will share study results with the ISO for review and concurrence.

At any time the Participating TO determines that it will not meet the required time frame for completing the Large Load Interconnection  Study, Participating TO shall notify the Large Load Interconnection Customer as to the schedule status of the Large Load Interconnection Study and provide an estimated completion date with an explanation of the reasons why additional time is required.

Upon request, the Participating TO shall provide the Large Load Interconnection Customer all supporting documentation, workpapers and relevant pre-Interconnection Request and post- Interconnection Request power flow and short circuit databases for the Large Load Interconnection Study, subject to confidentiality arrangements consistent with LLIP Section 7.1.

Should the Large Load Interconnection Customer provide written comments on the Large Load Interconnection Study report at least five (5) Business Days before the Report Meeting conducted to discuss the report, the Participating TO will address the written comments in the Large Load Interconnection Study Report Meeting.  Should the Large Load Interconnection Customer provide comments at any later time (up to the time of the Report Meeting), then such comments shall be considered informal inquiries to which the Participating TO will provide informal, informational responses at the Report Meeting, to the extent possible.

The Large Load Interconnection Customer may submit, in writing, additional comments on the final Large Load Interconnection Study report up to three (3) Business Days following the Report Meeting.  Based on any discussion at the Report Meeting and any comments received from the Large Load Interconnection Customer or the ISO, the Participating TO will determine whether it is necessary to follow the Large Load Interconnection Study report with a revised study report.  The Participating TO will issue any such revised report to the Large Load Interconnection Customer no later than fifteen (15) Business Days following the Report

PDF page 384

19

Meeting. If the ISO has not completed its review of the Large Load Interconnection Study report, the Participating TO shall delay its determination of whether a revised study report is required until that review is complete.

4.6.1.3 Large Load Interconnection Study Report Meeting.  A Report Meeting shall be held among the Participating TO, the ISO, if applicable, and the Large Load Interconnection Customer to discuss the results of the Large Load Interconnection Study, including assigned cost responsibility.  Any such Report Meeting will be held within ten (10) Business Days of the date the Large Load Interconnection Study report is provided to the Large Load Interconnection Customer.

4.6.1.4 Commercial Readiness Deposit.  Within thirty (30) Calendar Days after receiving the final Large Load Interconnection Study report, the Large Load Interconnection Customer shall provide an additional Commercial Readiness Deposit sufficient to bring the aggregate Commercial Readiness Deposit to twenty percent (20%) of the Participating TO’s then-current estimated construction cost of the Large Load Network Upgrades identified in that report that are attributable to the Interconnection Request.  If the final Large Load Interconnection Study report is revised following ISO review, the required Commercial Readiness Deposit shall be adjusted to reflect twenty percent (20%) of the corresponding estimated construction cost identified in the revised final report, and any required increase shall be provided within thirty (30) Calendar Days after issuance of that report.

The Commercial Readiness Deposit secures the Withdrawal Penalty and other pre-in-service obligations under this LLIP and the Large Load Interconnection Agreement. It does not establish a direct assignment of the Large Load Network Upgrade costs, constitute a payment toward an Annual MTRC, reduce the Total Required Revenue Commitment, or satisfy Operational Security under a Cost Recovery Agreement.

To the extent a Commercial Readiness Deposit is in a form permitted under Schedule 3 of an applicable Cost Recovery Agreement, DesertLink may elect in writing to credit it dollar-for- dollar toward required Construction Security under that agreement. No amount of Commercial Readiness Deposit may be applied or

PDF page 385

20

credited more than once. Any portion not so credited shall be administered and released under Sections 3.9 and 3.10 of this LLIP and the Large Load Interconnection Agreement.

4.6.1.5 Restudy. If restudy of the Large Load Interconnection Study is required due to a higher queued project dropping out of the queue, or a modification of a higher queued project subject to LLIP Section 4.6.1.6, Participating TO shall notify Large Load Interconnection Customer in writing. Such restudy shall take no longer than forty-five (45) Calendar Days from the date of notice. Any cost of restudy shall be borne by the Large Load Interconnection Customer.

4.6.1.6 Modifications.  At any time during the course of the Interconnection Studies, the Large Load Interconnection Customer, the Participating TO, or the ISO, as applicable, may identify changes to the planned interconnection that may improve the costs and benefits (including reliability) of the interconnection, and the ability of the proposed change to accommodate the Interconnection Request.  To the extent the identified changes are acceptable to the Participating TO, the ISO, as applicable, and Large Load Interconnection Customer, such acceptance not to be unreasonably withheld, Participating TO shall modify the configuration in accordance with such changes without altering the Interconnection Request’s eligibility for participating in Interconnection Studies.

4.6.1.6.1 For any modifications other than those agreed upon under LLIP Section 4.6.1.6, the Large Load Interconnection Customer must first request that Participating TO evaluate whether such modification is a Material Modification.  In response to Large Load Interconnection Customer's

request, Participating TO, in coordination with the ISO, if applicable, shall evaluate the proposed modifications prior to making them and inform Large Load Interconnection Customer in writing of whether the modifications would constitute a Material Modification.  The Participating TO may, at its option, engage the services of the ISO to assist in the assessment of the modification.  Any change to the Point of Interconnection shall constitute a Material Modification.

The Large Load Interconnection Customer shall provide the Participating TO a $30,000 deposit for the modification assessment at the time the request is submitted.  Except as provided below, any modification assessment will be

concluded, and a response provided to the Large Load Interconnection Customer in writing, within forty-five (45)

PDF page 386

21

Calendar Days from the date the Participating TO receives all of the following: 1) the Large Load Interconnection Customer’s written notice to modify the project; 2) a narrative description of the requested modification; 3) technical data required to assess the request, including an updated technical data form (Appendix A to Attachment 1 to this LLIP), if requested by the Participating TO; 4) any additional information requested by Participating TO; and

5) payment of the $30,000 deposit.  If applicable, the Participating TO shall coordinate the modification request with the ISO.  If the modification assessment cannot be completed within that time period, the Participating TO shall notify the Large Load Interconnection Customer and provide an estimated completion date with an explanation of the reasons why additional time is required.  The Large Load Interconnection Customer will be responsible for the actual costs incurred by the Participating TO and, if applicable, the ISO in conducting the modification assessment.  If the actual costs of the modification assessment are less than the deposit provided by the Large Load Interconnection Customer, the Large Load

Interconnection Customer will be refunded the balance within thirty (30) Calendar Days of being invoiced.  If the actual costs of the modification assessment are greater than the deposit provided by the Large Load Interconnection Customer, the Large Load Interconnection Customer shall pay the balance within thirty (30) Calendar Days of being invoiced.

If the proposed modification is determined to be a Material Modification by the Participating TO pursuant to the modification assessment described above, the Large Load Interconnection Customer shall then either:

(i) withdraw the proposed modification, or

(ii) withdraw the proposed modification and submit a new Interconnection Request reflecting such

modification.

4.6.2   Optional Flexible Interim Load Interconnection (FILI) Study and Agreement. If the Large Load Interconnection Study finds that the full amount of the Interconnection Request cannot be accommodated prior to the time that all ECLL Interconnection Facilities are in service, the Large Load Interconnection Customer may request a FILI Study, by written notice to the Participating TO within thirty (30) Calendar Days after receipt of the final Large Load Interconnection Study report, to

PDF page 387

22

determine, consistent with Section 10A.4 of the TO Tariff, whether Interim Firm Interconnection Service and/or FILI Service may be provided.  A Large Load Interconnection Customer may elect to be studied only for Interim Firm Interconnection Service and not FILI Service.  If the Large Load Interconnection Customer elects to proceed with a FILI Study, the Participating TO shall use Reasonable Efforts to complete the FILI Study within sixty (60) Calendar Days after receipt of such request. Large Load Interconnection Customer will be responsible for the actual costs of the FILI Study. The Participating TO will perform the FILI Study. At any time the Participating TO determines that it will not meet the required time frame for completing the FILI Study, Participating TO shall notify the Large Load Interconnection Customer as to the schedule status of the FILI Study and provide an estimated completion date with an explanation of the reasons why additional time is required.

 The FILI Study will determine (i) the maximum amount of Interim Firm Interconnection Service, if any, that can be provided prior to completion of the Participating TO’s Interconnection Facilities and Large Load Network Upgrades; (ii) whether the Large Load Interconnection Customer is eligible to receive FILI Service and the maximum amount of such service; (iii) the conditions and limitations of such service; (iv) the upgrades and the associated cost; and (v) the estimated duration required to provide the interim service. The Participating TO will share study results with the ISO for review and concurrence.  The Participating TO shall update its analysis of the availability of FILI Service at least annually under the terms of the FILI Service Agreement, and the actual amount of FILI Service available during any operating period shall be determined by the Participating TO through operational assessments conducted closer to real-time operating conditions, consistent with Section 10A.4 of the TO Tariff.  If requested by the Large Load Interconnection Customer within ten (10) Business Days of the date of the issuance of the FILI Study report, a Report Meeting shall be scheduled among the Participating TO, the ISO, and the Large Load Interconnection Customer.

The Large Load Interconnection Customer should note the following considerations:

a) Temporary limits may be adjusted if unforeseen conditions arise.
b) Advance notice of non-firm load curtailment may not be possible.
c) Non-firm load may be curtailed during planned or repair outages, which may last longer than 6 months.

d) ISO may have additional operational requirements.
e) Participating TO is not obligated to provide flexibility beyond what it can, in its sole judgment, manage operationally.

PDF page 388

23

f) Participating TO’s Interconnection Facilities costs for interim interconnection service will be directly assigned to the Large Load Interconnection Customer.

g) Large Load Interconnection Customers not adhering to the contractual agreement and conditions may be curtailed indefinitely.

4.6.2.1 FILI Service Agreement. If the Large Load Interconnection Customer has elected FILI Service, as reflected in the Large Load Interconnection Agreement, the Large Load Interconnection

Customer shall ensure that, prior to the Service Commencement Date, the Large Load Customer executes, or requests to be filed unexecuted with FERC, a FILI Service Agreement with the

Participating TO and, as applicable, the ISO, developed by the Participating TO consistent with Section 10A.4 of the TO Tariff and in accordance with ISO Tariff Section 25.7.2. The FILI Service Agreement shall describe the circumstances in which the ISO or Participating TO may temporarily curtail the Large Load receiving FILI Service, and the mechanism the ISO or

Participating TO will use to perform the curtailment. The ISO will post such FILI Service Agreements on the ISO Website.

4.6.3   Additional Studies. The Participating TO may identify the need for additional studies to comply with Applicable Reliability Standards. These additional studies may include, but are not limited to, the following: stability analysis, variable load impact analysis, and EMT analysis.  The associated new scope will be identified in the Large Load Interconnection Study pursuant to LLIP Section 4.6.1.1. The additional studies will be performed by the Participating TO as part of the scope of work set forth in the Large Load Interconnection Agreement. The additional studies may result in the identification of additional facilities scope and cost, and may require a revision to the schedule set forth in the Large Load Interconnection Agreement. The Large Load Interconnection Customer will be responsible for providing the necessary technical information and/or models requested by the Participating TO to conduct the additional studies. The Large Load Interconnection Customer will be responsible for the costs of such studies.

If an additional study results in the need to revise the scope of work of the Large Load Network Upgrades identified in the Large Load

Interconnection Study and the updated assigned costs have increased by more than twenty-five percent (25%) compared to costs identified in the Large Load Interconnection Study report, the Large Load Interconnection Customer shall not be subject to a Withdrawal Penalty under LLIP Section 3.10.1 if the Interconnection Request is withdrawn within thirty (30) Calendar Days of receipt of the additional study report.  If the Large Load Interconnection Customer elects to continue with its Interconnection Request, the Large Load Interconnection Agreement will be amended to

PDF page 389

24

reflect the results of the additional study.

4.6.4   Financing of Participating TO’s Interconnection Facilities and Large Load Network Upgrades.  The responsibility to finance Participating TO’s Interconnection Facilities shall be assigned solely to the Large Load Interconnection Customer. The Participating TO will be responsible for financing Large Load Network Upgrades in accordance with the Large Load Interconnection Agreement and, as to any Large Load Network Upgrades that constitute Large Load-Driven Upgrades, the Cost Recovery Agreement required under LLIP Section 5.3.

4.7
Interconnection Financial Security

4.7.1 Types of Interconnection Financial Security.  The Interconnection Financial Security posted by a Large Load Interconnection Customer may be any combination of the following types of Interconnection Financial Security provided in favor of the Participating TO:

(a) an irrevocable and unconditional letter of credit issued by a bank or financial institution that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s;

(b) an irrevocable and unconditional surety bond issued by an insurance company that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s;

(c) an unconditional and irrevocable guaranty issued by a company that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s;

(d) a cash deposit standing to the credit of the Participating TO and in an interest-bearing escrow account maintained at a bank or financial institution that is reasonably acceptable to the Participating TO;

(e) a certificate of deposit in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s; or

(f) a payment bond certificate in the name of the Participating TO issued by a bank or financial institution that has a credit rating of A or better by Standard and Poor’s or A2 or better by Moody’s.

Interconnection Financial Security instruments as listed above shall be in such form as the Participating TO may reasonably require from time to time by notice to Large Load Interconnection Customers, or in such other

PDF page 390

25

form as has been evaluated and approved as reasonably acceptable by the Participating TO.

The Participating TO shall require the use of standardized forms of Interconnection Financial Security to the greatest extent possible.  If at any time the guarantor of the Interconnection Financial Security fails to maintain the credit rating required by this LLIP Section 4.7.1, the Large Load Interconnection Customer shall provide to the Participating TO replacement Interconnection Financial Security meeting the requirements of this LLIP Section 4.7.1 within five (5) Business Days of the change in credit rating.

Interest on a cash deposit standing to the credit of the Participating TO in an interest-bearing escrow account under subpart (d) of this LLIP Section 4.7.1 will accrue to the Large Load Interconnection Customer’s benefit.

Execution and filing of the Large Load Interconnection Agreement at FERC are addressed in LLIP Section 5.

Section 5.
Large Load Interconnection Agreement

5.1
Tender.  Within thirty (30) Calendar Days after the Report Meeting for the final Large Load Interconnection Study report or, if the Large Load Interconnection Customer has timely requested a FILI Study pursuant to LLIP Section 4.6.2, within thirty (30) Calendar Days after issuance of the final FILI Study report (or, if a Report Meeting is requested for the FILI Study, after such Report Meeting), the Participating TO shall tender to the Large Load Interconnection Customer a draft Large Load Interconnection Agreement developed by the Participating TO consistent with the TO Tariff, this LLIP, and the results of the Interconnection Studies.  The draft Large Load Interconnection Agreement shall address, without limitation, the scope, schedule, cost responsibility, payment provisions, cost recovery, and financial security for the Participating TO’s Interconnection Facilities and Large Load Network Upgrades, and any applicable operating requirements.  The Large Load Interconnection Customer shall provide written comments, or notification of no comments, on the draft Large Load Interconnection Agreement within thirty (30) Calendar Days.

5.2
Negotiation.  Notwithstanding LLIP Section 5.1, at the request of Large Load Interconnection Customer, Participating TO shall begin negotiations with Large Load Interconnection Customer concerning the terms and conditions of the Large Load Interconnection Agreement at any time after the Participating TO provides the Large Load Interconnection Customer with the final Large Load Interconnection Study report, or the final FILI Study report, if applicable. Participating TO and Large Load Interconnection Customer shall negotiate in good faith concerning any disputed provisions of the draft Large Load Interconnection Agreement for not more than sixty (60) Calendar Days after the Participating TO provides the Large Load Interconnection Customer with the final

PDF page 391

26

Large Load Interconnection Study report or the final FILI Study report if applicable.  If Large Load Interconnection Customer determines that negotiations are at an impasse, it may request termination of the negotiations at any time after tender of the draft Large Load Interconnection Agreement pursuant to LLIP Section 5.1 and request submission of the unexecuted Large Load Interconnection Agreement with FERC or initiate Dispute Resolution procedures pursuant to LLIP Section 7.2.  If Large Load Interconnection Customer requests termination of the negotiations, but within sixty (60) Calendar Days after issuance of the final Large Load Interconnection Study report, or the final FILI Study report if applicable, fails to request either the filing of the unexecuted Large Load Interconnection Agreement or initiate Dispute Resolution, it shall be deemed to have withdrawn its Interconnection Request.  Unless otherwise agreed by the Parties, if Large Load Interconnection Customer has not executed the Large Load Interconnection Agreement, requested filing of an unexecuted Large Load Interconnection Agreement, or initiated Dispute Resolution procedures pursuant to LLIP Section 7.2 within the time period set forth in LLIP Section 5.3, it shall be deemed to have withdrawn its Interconnection Request.  Participating TO shall provide to Large Load Interconnection Customer a final Large Load Interconnection Agreement within fifteen (15) Business Days after the completion of the negotiation process.

The Participating TO may declare an impasse upon sixty (60) Calendar Days after issuance of the final Large Load Interconnection Study report, or the final FILI Study report if applicable, or at any time following sixty (60) Calendar Days after issuance of the final Large Load Interconnection Study report, or the final FILI Study report if applicable, if the Parties have agreed to extend negotiation of the Large Load Interconnection Agreement.  If the Participating TO declares an impasse, the Participating TO will file the Large Load Interconnection Agreement unexecuted with FERC within twenty-one (21) Calendar Days.

5.3
Execution and Filing
Within thirty (30) Business Days after receipt of the final Large Load Interconnection Agreement, Large Load Interconnection Customer shall either: (i) execute the final Large Load Interconnection Agreement and return it to Participating TO; or (ii) request in writing that Participating TO file with FERC the Large Load Interconnection Agreement in unexecuted form, or its Interconnection Request shall be deemed withdrawn and subject to LLIP Section 3.10.  To the extent FERC filing is required, as soon as practicable, but not later than ten (10) Business Days after receiving either the executed Large Load Interconnection Agreement or the request to file an unexecuted Large Load Interconnection Agreement, Participating TO shall file the Large Load Interconnection Agreement with FERC, together with, in the case of an unexecuted Large Load Interconnection Agreement, its explanation of any matters as to which Large Load Interconnection Customer and Participating TO disagree and support for the costs that Participating TO proposes to charge to Large Load Interconnection Customer under the Large Load Interconnection Agreement.  An unexecuted Large Load Interconnection Agreement should contain terms and conditions deemed appropriate by Participating TO for the Interconnection

PDF page 392

27

Request.  If the Parties agree to proceed with design, procurement, and construction of facilities and upgrades under the agreed-upon terms of the unexecuted Large Load Interconnection Agreement, they may proceed pending FERC action.  As a condition to the Participating TO’s design, procurement, construction, or operation of any Large Load-Driven Upgrades (as defined in the pro forma Large Load Cost Recovery Agreement set forth in Appendix V to the TO Tariff) associated with the Interconnection Request, the Large Load Interconnection Customer shall also, within the same period and subject to the same consequences as the Large Load Interconnection Agreement, execute and maintain a Cost Recovery Agreement substantially in the form set forth in Appendix V to the TO Tariff, or, if the Large Load Interconnection Customer requests that the Cost Recovery Agreement be filed unexecuted with FERC, comply with that agreement as made effective by FERC.  A Cost Recovery Agreement required by this LLIP Section 5.3 is entered into pursuant to the TO Tariff.

5.4
Commencement of Interconnection Activities
If Large Load Interconnection Customer executes the final Large Load Interconnection Agreement, Participating TO and Large Load Interconnection Customer shall perform their respective obligations in accordance with the terms of the Large Load Interconnection Agreement, subject to modification by FERC. Upon submission of an unexecuted Large Load Interconnection Agreement, Large Load Interconnection Customer and Participating TO shall promptly comply with the unexecuted Large Load Interconnection Agreement, if agreed to by the Parties pursuant to LLIP Section 5.3, subject to modification by FERC.

Section 6.
Construction of Participating TO's Interconnection Facilities and Large Load Network Upgrades

6.1
Schedule
Participating TO and Large Load Interconnection Customer shall negotiate in good faith concerning a schedule for the Participating TO’s construction of Participating TO's Interconnection Facilities and the Large Load Network Upgrades.

6.2
Construction Sequencing

6.2.1 General.  In general, the Service Commencement Date will determine the sequence of construction of Large Load Network Upgrades.

6.2.2 Advancing Construction of Large Load Network Upgrades that are Part of an Expansion Plan of the Participating TO.  A Large Load Interconnection Customer with a Large Load Interconnection Agreement, in order to maintain its Service Commencement Date, may request that Participating TO advance to the extent necessary the completion of Large Load Network Upgrades that:  (i) are necessary to support such Service Commencement Date and (ii) would otherwise not be completed, pursuant

PDF page 393

28

to an expansion plan of Participating TO or approved ISO Transmission Plan covering the Participating TO’s facilities, in time to support such Service Commencement Date.  Upon such request, Participating TO will use Reasonable Efforts to advance the construction of such Large Load Network Upgrades to accommodate such request; provided that Large Load Interconnection Customer commits to pay Participating TO any associated expediting costs.

6.3
Special Provisions for Affected Systems
The Large Load Interconnection Customer shall timely enter into and maintain an agreement with each applicable Affected System Operator for each addition, modification, or upgrade to an Affected System identified through the Interconnection Studies or an applicable Affected System study.  The agreement shall specify the terms governing payments to be made by the Large Load Interconnection Customer to the Affected System Operator, including financial security or credit support sufficient to protect the Affected System Operator and its other customers against cost shifting.  Where a Cost Recovery Agreement applies, the Large Load Interconnection Customer shall provide the Participating TO the evidence of such agreements required by, and within the time specified in, the Cost Recovery Agreement, and the Participating TO may decline to commence, or may suspend, construction as provided in the Cost Recovery Agreement.

Section 7.
Miscellaneous

7.1
Confidentiality

For the purposes of this LLIP Section 7.1, “Party” or “Parties” shall mean the Participating TO, Large Load Interconnection Customer, ISO, or any combination of the Participating TO, Large Load Interconnection Customer, or ISO.

Confidential Information shall include, without limitation, all information relating to a Party's technology, research and development, business affairs, and pricing.

Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Party receiving the information that the information is confidential.

If requested by either Party, the other Party shall provide in writing, the basis for asserting that the information referred to in this LLIP Section 7.1 warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority.  Each Party shall be responsible for the costs associated with affording confidential treatment to its information.

7.1.1 Scope.  Confidential Information shall not include information that the receiving Party can demonstrate: (1) is generally available to the public

PDF page 394

29

other than as a result of a disclosure by the receiving Party; (2) was in the lawful possession of the receiving Party on a non-confidential basis before receiving it from the disclosing Party; (3) was supplied to the receiving Party without restriction by a third party, who, to the knowledge of the receiving Party after due inquiry, was under no obligation to the disclosing Party to keep such information confidential; (4) was independently developed by the receiving Party without reference to Confidential Information of the disclosing Party; (5) is, or becomes, publicly known, through no wrongful act or omission of the receiving Party or Breach of the Large Load Interconnection Agreement; or (6) is required, in accordance with LLIP Section 7.1.6, Order of Disclosure, to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena, or is necessary in any legal proceeding establishing rights and obligations under the Large Load Interconnection Agreement. Information designated as Confidential Information will no longer be deemed confidential if the Party that designated the information as confidential notifies the other Party that it no longer is confidential.

7.1.2  Release of Confidential Information.  Neither Party shall release or disclose Confidential Information to any other person, except to its Affiliates (limited by the Standards of Conduct requirements), employees, consultants, Affected System Operators, the Large Load Customer, or to parties who may be providing or considering providing financing to or equity participation with Large Load Interconnection Customer or the Large Load Customer, or to potential purchasers or assignees of Large Load Interconnection Customer or the Large Load Customer, on a need- to-know basis in connection with these procedures, unless such person has first been advised of the confidentiality provisions of this LLIP Section 7.1 and has agreed to comply with such provisions.  Notwithstanding the foregoing, a Party providing Confidential Information to any person shall remain primarily responsible for any release of Confidential Information in contravention of this LLIP Section 7.1.

7.1.3 Rights.  Each Party retains all rights, title, and interest in the Confidential Information that each Party discloses to the other Party.  The disclosure by each Party to the other Party of Confidential Information shall not be deemed a waiver by either Party or any other person or entity of the right to protect the Confidential Information from public disclosure.

7.1.4 No Warranties.  By providing Confidential Information, neither Party makes any warranties or representations as to its accuracy or completeness.  In addition, by supplying Confidential Information, neither Party obligates itself to provide any particular information or Confidential Information to the other Party nor to enter into any further agreements or proceed with any other relationship or joint venture.

PDF page 395

30

7.1.5 Standard of Care.  Each Party shall use at least the same standard of care to protect Confidential Information it receives as it uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination.  Each Party may use Confidential Information solely to fulfill its obligations to the other Party under these procedures or its regulatory requirements.

7.1.6 Order of Disclosure.  If a court or a Governmental Authority or entity with the right, power, and apparent authority to do so requests or requires either Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the other Party with prompt notice of such request(s) or requirement(s) so that the other Party may seek an appropriate protective order or waive compliance with the terms of these confidentiality provisions. Notwithstanding the absence of a protective order or waiver, the Party may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose.  Each Party will use Reasonable Efforts to obtain reliable assurance that confidential treatment will be accorded any Confidential Information so furnished.

7.1.7 Remedies.  The Parties agree that monetary damages would be inadequate to compensate a Party for the other Party's Breach of its obligations under this LLIP Section 7.1.  Each Party accordingly agrees that the other Party shall be entitled to equitable relief, by way of injunction or otherwise, if the first Party Breaches or threatens to Breach its obligations under this LLIP Section 7.1, which equitable relief shall be granted without bond or proof of damages, and the receiving Party shall not plead in defense that there would be an adequate remedy at law.  Such remedy shall not be deemed an exclusive remedy for the Breach of this LLIP Section 7.1, but shall be in addition to all other remedies available at law or in equity.  The Parties further acknowledge and agree that the covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope.  No Party, however, shall be liable for indirect, incidental, or consequential or punitive damages of any nature or kind resulting from or arising in connection with this LLIP Section 7.1.

7.1.8 Disclosure to FERC, its Staff, or a State.  Notwithstanding anything in this LLIP Section 7.1 to the contrary, and pursuant to 18 CFR section 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence pursuant to the LLIP, the Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information.  In providing the information to FERC or its staff, the Party must, consistent with 18 CFR section 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld

PDF page 396

31

from public disclosure.  Parties are prohibited from notifying the other Party prior to the release of the Confidential Information to FERC or its staff.  The Party shall notify the other Party to the Large Load Interconnection Agreement when it is notified by FERC or its staff that a request to release Confidential Information has been received by FERC, at which time either of the Parties may respond before such information would be made public, pursuant to 18 CFR section 388.112.  Requests from a state regulatory body conducting a confidential investigation shall be treated in a similar manner, consistent with applicable state rules and regulations.

7.1.9 Subject to the exception in LLIP Section 7.1.8, any information that a Party claims is competitively sensitive, commercial or financial information ("Confidential Information") shall not be disclosed by the other Party to any person not employed or retained by the other Party, except to the extent disclosure is (i) required by law; (ii) reasonably deemed by the disclosing Party to be required to be disclosed in connection with a dispute between or among the Parties, or the defense of litigation or dispute; (iii) otherwise permitted by consent of the other Party, such consent not to be unreasonably withheld;  or (iv) necessary to fulfill its obligations under this LLIP or as a Participating TO, including disclosing the Confidential Information to the ISO or to a subregional, regional or national reliability organization or planning group.  The Party asserting confidentiality shall notify the other Party in writing of the information it claims is confidential.  Prior to any disclosures of the other Party's Confidential Information under this subparagraph, or if any third party or Governmental Authority makes any request or demand for any of the information described in this subparagraph, the disclosing Party agrees to promptly notify the other Party in writing and agrees to assert confidentiality and cooperate with the other Party in seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order or other reasonable measures.

7.1.10 This provision shall not apply to any information that was or is hereafter in the public domain (except as a result of a Breach of this provision).

7.1.11 Participating TO shall, at Large Load Interconnection Customer's election, destroy, in a confidential manner, or return the Confidential Information provided at the time the Confidential Information is no longer needed.

7.2
Disputes

7.2.1  Submission.  In the event either Party has a dispute, or asserts a claim, that arises out of or in connection with the Large Load Interconnection Agreement, the LLIP, or their performance, such Party (the "disputing Party") shall provide the other Party with written notice of the dispute or claim ("Notice of Dispute").  Such dispute or claim shall be resolved in

PDF page 397

32

accordance with Section 14 of the TO Tariff, including, as applicable, the ISO ADR Procedures; provided, however, that disputes arising under a Cost Recovery Agreement shall be resolved under the dispute resolution provisions of that agreement.

PDF page 398

33

ATTACHMENT 1
TO APPENDIX VI – LARGE LOAD INTERCONNECTION PROCEDURES

INTERCONNECTION REQUEST FORM

This Interconnection Request is submitted to DesertLink, LLC (“Participating TO”) by the Eligible Customer for Large Load (“ECLL”) identified below, acting as the Large Load Interconnection Customer, pursuant to LLIP Section 4.2.1 and Section 10A of the TO Tariff. Consistent with LLIP Section 3.1, the Large Load Interconnection Customer shall send a copy of this Interconnection Request to the ISO.  Capitalized terms not defined herein have the meanings set forth in the LLIP or, if not defined in the LLIP, in Section 3 of the TO Tariff.

I. Large Load Interconnection Customer (ECLL) Contact Information
Company Name

Type of ECLL (UDC or MSS)

Representative

Address

Email

Phone

II. Large Load Customer Information
Large Load Customer Name

Large Load Customer Representative and
Contact Information

Large Load Site Location/Address

Type of Large Load Facility (e.g., data
center, industrial)

Other ECLL interconnection requests
submitted for the same Large Load
Customer or any of its affiliates (see
Section 10A.2.1 of the TO Tariff)

III. Point of Interconnection

Please identify the location and voltage
level of the preferred Point of
Interconnection in as much detail as
possible. If proposing to connect to a
transmission line, provide the approximate
distance from one of the existing line
terminals.  The Point of Interconnection
will serve as the Point of Withdrawal under
the TO Tariff.

PDF page 399

34

IV. Large Load Capacity and Load Ramp Schedule

Proposed load ramp schedule identifying anticipated load additions over time: Date (MM/DD/YYYY)

Incremental Load (MW)
Cumulative Load (MW)

V. Proposed Service Commencement Date and Term

VI. Source of Power

VII. Site Plan, Site Control, and Permits

Please attach: (a) a site plan for the Large Load; (b) documentation demonstrating Site Control, as defined in Section 3 of the TO Tariff; and (c) documentation demonstrating that the Large Maximum Large Load capacity requested

at the Point of Interconnection (MW) (see
LLIP Section 3.6)

Maximum capacity the Large Load is
capable of withdrawing, if greater than the
amount requested, and the proposed means
of limiting withdrawals to the requested
amount

Expected power factor and load factor

Proposed date for energizing the ECLL
Interconnection (MM/DD/YYYY)

Proposed Service Commencement Date
(MM/DD/YYYY) (see LLIP Section 3.7)

Proposed term of service (years)

Please identify the electrical location of the
source of power to be delivered to the
Large Load, if known.  If the source of the
power is not known, a system purchase
will be assumed.  Nothing in this
Interconnection Request constitutes a
request for transmission service (see LLIP
Section 3.2.2).

PDF page 400

35

Load Customer has local permits and regulatory approvals for development of the Large Load, consistent with Section 10A.2.1(f) of the TO Tariff.

VIII. Co-Located Generation

Will the Large Load be co-located with a
generating facility? (Yes/No)

Will the generating facility export to the
ISO Controlled Grid? (Yes/No)

Generating facility queue number or, if
executed, identification of its generator
interconnection agreement

Generating facility nameplate capacity
(MW)

IX. Single-Line Diagram and Modeling Information

Please attach a single-line diagram of the Large Load and the Large Load Interconnection Customer’s Interconnection Facilities and/or KMZ files to this Interconnection Request.  Please provide power flow modeling files (PSS/E or PSLF format preferred) or spreadsheet format containing modeling data such as impedances and ratings of customer-owned equipment. Also provide short-circuit modeling data, dynamic and electromagnetic transient (EMT) models, load characteristics (including ride-through capability, ramp rates, and harmonic characteristics), any other details to be taken into consideration in the Interconnection Studies, and the completed technical data form in the form of Appendix A to this Attachment 1.

X. Required Submittals (LLIP Section 4.2.1)
Item
Included (Yes/No)
Interconnection Study Deposit of $250,000

Commercial Readiness Deposit equal to
two times the Interconnection Study
Deposit, in a form permitted by LLIP
Section 4.7.1

Demonstration of Site Control

Completed technical data form in the form
of Appendix A to this Attachment 1 (TO
Tariff Section 10A.2.1(j))

Copy of this Interconnection Request sent
to the ISO

XI. Acknowledgment

By submission of this Interconnection Request, the Large Load Interconnection Customer acknowledges that additional detail may be required to satisfactorily perform the Interconnection

PDF page 401

36

Studies related to this Interconnection Request and agrees to work with DesertLink, LLC in good faith to provide additional information as necessary.  The Large Load Interconnection Customer may designate information in this Interconnection Request, including the identity of the Large Load Customer, as Confidential Information in accordance with LLIP Section 7.1.

Interconnection Request Submitted By:

Interconnection Request Received By DesertLink, LLC:

Printed Name:

Date:

Printed Name:

Date:

PDF page 402

Attachment 3

Direct Testimony of Patrick Hayes (Exhibit No. DLK-100) and Supporting Exhibits

PDF page 403

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

DesertLink, LLC
California Independent System Operator Corporation )

)
Docket No.
Docket No.
ER27-___-000
EL26-71-___

DIRECT TESTIMONY
OF
PATRICK HAYES

ON BEHALF OF
DESERTLINK, LLC

Large Load Network Upgrade Cost Recovery

November 2026

PDF page 404

DIRECT TESTIMONY OF PATRICK HAYES

TABLE OF CONTENTS

I. INTRODUCTION AND EXPERIENCE … 1
II. PURPOSE AND SCOPE OF TESTIMONY … 2
III. FERC SHOW CAUSE ORDERS … 3
IV. CAISO STAKEHOLDER PROCESS … 6
V. COST RECOVERY AGREEMENT … 8
VI. TARIFF REVISIONS … 16

PDF page 405

EXHIBITS TO
DIRECT TESTIMONY OF PATRICK HAYES

Exhibit No.
Description

DLK-101:
DLK-102:
DLK-103:

Illustrative MTRC Calculation
Example Reconciliation Statement
Example Invoice Statement

PDF page 406

Page 1

DIRECT TESTIMONY OF

PATRICK HAYES

I. INTRODUCTION AND EXPERIENCE
Q.
PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
1
A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310, 2

Chesterfield, Missouri 63017.
3
Q.
BY WHOM ARE YOU EMPLOYED, AND WHAT ARE YOUR
4
RESPONSIBILITIES?
5
A. I am employed by LS Power and serve as Associate Vice President, Transmission 6

Regulatory. I lead regulatory strategy for LS Power’s transmission business across the 7

California Independent System Operator (“CAISO”), Midcontinent Independent System 8

Operator, PJM Interconnection, New York Independent System Operator, and other 9

regional markets. My responsibilities include Federal Energy Regulatory Commission 10

(“FERC”) policy, regional transmission planning, competitive transmission development, 11

cost allocation and recovery, tariff development, and large-load interconnection. 12

Q.
PLEASE SUMMARIZE YOUR PROFESSIONAL EXPERIENCE AND
13
EDUCATION.
14
A. I previously served as LS Power’s Director of Transmission Business Development and 15

Manager of Transmission Policy. Earlier in my career, I held transmission policy, energy 16

trading, and asset optimization positions with Ameren. My experience includes developing 17

strategies for competitive transmission projects and utility partnerships, negotiating 18

commercial and ownership arrangements, evaluating transmission investments, and 19

PDF page 407

Page 2

coordinating multidisciplinary teams. I received a Bachelor of Science in Accounting from 1

the University of Missouri.
2
Q.
ON WHOSE BEHALF ARE YOU SUBMITTING THIS TESTIMONY?
3
A. I am testifying on behalf of DesertLink, LLC (“DesertLink”). DesertLink is a Participating 4

Transmission Owner (“PTO”) selected by the California Independent System Operator 5

Corporation (“CAISO”) in 2016 through its Order No. 1000 compliant Transmission 6

Planning Process to implement DesertLink’s Harry Allen to Eldorado 500 kV Transmission 7

Line Project.1 DesertLink placed the project in service in August 2020. 8

II. PURPOSE AND SCOPE OF TESTIMONY
9
Q.
WHAT IS THE PURPOSE OF YOUR TESTIMONY?
10
A. The purpose of this testimony is to provide relevant context and details regarding 11

DesertLink’s proposed approach to addressing the large-load cost recovery concerns 12

identified in FERC’s show cause orders. I describe the proposed Large Load Cost 13

Recovery Agreement (“CRA”) and associated tariff framework, and explain how these 14

measures assign cost responsibility for large-load-driven transmission upgrades, mitigate 15

cost shifting and stranded-asset risk, avoid double recovery, and promote transparency. 16

The CRA calculates a Minimum Transmission Revenue Contribution ("MTRC") under 17

its Schedule 5, separately from DesertLink’s Formula Rate. DesertLink continues to 18

recover its formula-rate revenue requirement through the Transmission Access Charge 19

("TAC"), with credits under the CRA flowing to transmission customers through the 20

Transmission Revenue Balancing Account Adjustment ("TRBAA").
21

1 See Harry Allen-Eldorado 500 kV Transmission Line Project: Project Sponsor Selection Report (Jan. 11, 2016), available at http://www.caiso.com/Documents/HarryAllentoEldoradoTransmissionLine- ProjectSponsorSelectionReport.pdf.

PDF page 408

Page 3

Q.
ARE YOU SPONSORING ANY EXHIBITS IN SUPPORT OF YOUR
1
TESTIMONY IN THIS CASE?
2
A. Yes. I am sponsoring the following exhibits:
3
Exhibit No.
Description

DLK-101:
DLK-102:
DLK-103:

Illustrative MTRC Calculation
Example Reconciliation Statement
Example Invoice Statement

III. FERC SHOW CAUSE ORDERS
4
Q.
PLEASE DESCRIBE FERC’S SHOW CAUSE ORDERS.
5
A. On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the 6

Federal Power Act through six show cause orders addressing the integration of large and 7

co-located loads onto the interstate transmission system. Each order is directed to an 8

Independent System Operator or Regional Transmission Organization ("ISO/RTO") and, 9

where applicable, its transmission-owning members.2 The orders arise from the 10

Commission's preliminary finding that the existing tariffs on file with the Commission 11

appear to be unjust, unreasonable, or unduly discriminatory or preferential because they 12

lack sufficiently clear and consistent provisions to address the unique challenges posed 13

by the rapid growth of large loads (such as data centers) and co-location arrangements 14

between loads and generating facilities.3
15
Each respondent is directed, within 60 days of the date of the order, to either (1) show 16

cause why its tariff remains just and reasonable and not unduly discriminatory or 17

preferential without the provisions identified by the Commission, or (2) explain what 18

2 Cal. Indep. Sys. Op. Corp., 195 FERC ¶ 61,214 (2026) (relevant CAISO Show Cause Order) (“Show Cause Order”).
3 Show Cause Order at P 38.

PDF page 409

Page 4

tariff changes would remedy the identified concerns if the Commission were to determine 1

that the tariff is unjust and unreasonable and proceeds to establish a replacement tariff.4 2

As relevant here, the show cause order directed to CAISO and its Participating 3

Transmission Owners (the “Show Cause Order”) required respondents to show cause or 4

propose remedial tariff revisions to (1) ensure transparency concerning the network 5

upgrade costs to provide transmission service to Eligible Customers on behalf of large 6

loads, (2) establish a pro forma cost recovery agreement to mitigate the risk of cost 7

shifting among transmission customers, and (3) ensure such payments are appropriately 8

credited toward transmission owners' transmission revenue requirements consistent with 9

the Commission's cost-of-service regulations.5
10
Q.
DID FERC PROVIDE ANY ADDITIONAL GUIDANCE ON HOW THE COST
11
RECOVERY ASPECTS SHOULD BE ADDRESSED BY RESPONDENTS?
12
A. Yes, Commissioners Chang and See each issued separate concurrences providing 13

additional guidance on how cost recovery for large-load-driven transmission costs should 14

be approached. Commissioner Chang supported the Commission's two-part preliminary 15

solution — public posting of information on new large loads, associated network 16

upgrades identified in local transmission planning, and the costs of those upgrades, 17

together with a pro forma cost recovery agreement to help ensure that Eligible Customers 18

serving large loads bear the risk and are ultimately responsible for the costs incurred to 19

provide transmission service — as a necessary step to protect wholesale customers 20

against unjustified cost shifts.6 Commissioner Chang also cautioned that bilateral 21

agreements that simply provide transmission revenue contributions "untethered from any 22

4 Id. at Ordering Para. B.
5 Id. at P 3.
6 Show Cause Order, Comm’n. Chang Concurrence at PP 6-9.

PDF page 410

Page 5

assessment of the actual cost of providing transmission service induced by individual 1

large loads" may be insufficient to protect other customers against unjustified cost shifts.7 2

She urged that the resulting regulatory and rate design not be limited to a pre-defined 3

solution set, encouraging parties to submit comprehensive records outlining various and 4

innovative approaches to customer protection, including but not limited to the Ratepayer 5

Protection Pledge.8
6
Commissioner See likewise described the Commission's findings on cost recovery 7

agreements between transmission owners and Eligible Customers as "an important step in 8

mitigating the risks of stranded assets if large loads prove speculative," and she 9

highlighted the Commission's decision to reduce unnecessary redundancy by allowing an 10

Eligible Customer to satisfy its financial security requirement by relying on credit support 11

or other financial security that a large load customer may have posted under a retail 12

agreement.9 She signaled that, as the Commission gains more experience, further 13

streamlining may be appropriate — suggesting, for example, that a cost recovery 14

agreement between a transmission owner and a large load customer itself could 15

potentially satisfy an Eligible Customer's financial security requirement — and stated that 16

she would be looking to ensure cost recovery agreements contain "fair and transparent 17

measures to ensure the right costs get on the right bills."10 More broadly, Commissioner 18

See reaffirmed the Commission's policy of rolling most network upgrade costs — 19

including those driven by large loads — into the embedded-cost rate paid by transmission 20

customers, but conditioned that approach on a commitment to evaluating alternative 21

7 Id. at P 8.
8  Id. at PP 8-9.
9 Show Cause Order, Comm’n. See Concurrence at P 9.
10 Id.

PDF page 411

Page 6

transmission technologies and other tools (including alternative cost allocation structures, 1

greater clarity in transmission service agreements, accounting for state large-load-specific 2

tariffs, and direct assignment in appropriate cases) that can keep costs at a responsible 3

and accountable level and ensure retail consumers do not bear costs incommensurate with 4

the benefits they receive.11
5
IV. CAISO STAKEHOLDER PROCESS
6
Q.
PLEASE DESCRIBE THE CAISO PROCESS FOLLOWING THE ISSUANCE OF
7
THE SHOW CAUSE ORDERS.
8
A. CAISO convened joint coordination meetings with the California Participating 9

Transmission Owners to address the Show Cause Order and CAISO’s proposed 10

implementation framework. DesertLink participated in the joint coordination process 11

meetings on July 1, July 10, July 23, and July 28; August 4, August 11, August 18, and 12

August 25; September 1, September 8, September 10, September 15, and September 22; 13

and October 23, 2026.
14
The meetings addressed applications and studies, operational requirements, cost-shift 15

prevention, flexible interconnection service options, and co-located resources. The 16

meetings provided an opportunity to examine the respective roles and responsibilities of 17

CAISO and load-serving, non-load-serving, and affected PTOs.
18
DesertLink also participated in CAISO’s public stakeholder meetings on August 19, 19

October 1, and October 19, 2026, and submitted written comments on CAISO’s Straw 20

Proposal, Draft Final Proposal, and Draft Tariff Language. Those comments asked 21

CAISO to recognize non-load-serving and affected PTOs expressly, preserve a 22

11 Id. at P 9.

PDF page 412

Page 7

meaningful role for those PTOs in the interconnection and study process, and address 1

coordination and cost recovery.
2
Q.
WHAT WAS DESERTLINK’S ROLE IN THIS PROCESS?
3
A. DesertLink coordinated with CAISO and other California PTOs. DesertLink is a non- 4

load-serving PTO that neither serves retail load nor has a retail relationship with a 5

customer seeking a large-load interconnection. DesertLink’s coordination efforts 6

highlighted the need to ensure that an affected PTO has a meaningful role in the process 7

even when the affected PTO does not provide retail service to the requesting load. 8

From July through September 2026, DesertLink participated in additional meetings with 9

non-load-serving PTOs and the broader California PTO group. The discussions addressed 10

participation in the application and study process, access to information, technical 11

coordination, timing, and allocation and recovery of costs. The coordination supported 12

the development of positions reflecting the circumstances of non-load-serving PTOs for 13

consideration by the broader PTO group.
14
DesertLink also met with Pacific Gas and Electric Company ("PG&E") in August 2026 15

to discuss notice, information sharing, technical consultation, and coordination when a 16

large-load request affects a non-load-serving PTO’s facilities.
17
DesertLink emphasized the distinct roles of load-serving, non-load-serving, and affected 18

PTOs throughout the process.
19
From October through November 2026, DesertLink participated in joint cost-recovery 20

meetings with load-serving PTOs to examine potential approaches and implementation 21

considerations. DesertLink explained the circumstances of non-load-serving and affected 22

PTOs and discussed potential approaches to large-load interconnection and cost recovery. 23

PDF page 413

Page 8

The coordination provided an opportunity to evaluate different approaches and identify 1

implementation considerations relevant to non-load-serving PTOs. DesertLink’s proposal 2

reflects consideration of those discussions and addresses the interconnection, cost- 3

recovery, and financial-security requirements associated with large loads affecting 4

DesertLink’s facilities.
5
Q.
BASED ON THIS PROCESS, WHAT IS DESERTLINK’S PROPOSED
6
APPROACH?
7
A. DesertLink proposes a large-load interconnection framework under Section 10A and 8

Appendix VI of DesertLink’s Transmission Owner Tariff ("TO Tariff"), together with the 9

pro forma CRA in Appendix V. The interconnection framework addresses applications, 10

studies, interim service, and interconnection agreements. The CRA establishes the 11

Eligible Customer’s minimum revenue contribution and related security obligations for 12

the Covered Upgrades, with credits to transmission customers through the TRBAA. 13

V. COST RECOVERY AGREEMENT
14
Q.
PLEASE DESCRIBE THE CRA.
15
A. The CRA is a pro forma contract between DesertLink, as Transmission Owner, and the 16

Eligible Customer taking wholesale transmission service under the CAISO Tariff on 17

behalf of a Large Load Customer. The Large Load Customer executes a Limited 18

Acknowledgment for the information, authorization, notice, and cooperation purposes 19

stated therein, including cooperation in a transition to a Successor Eligible Customer. The 20

Large Load Customer is not itself a party to the wholesale payment obligations. The CRA 21

establishes the Eligible Customer’s wholesale revenue-support and security obligations 22

associated with the Large Load Facility and the Covered Upgrades, without establishing 23

or prescribing the retail rates, charges, or recovery arrangements between the Eligible 24

PDF page 414

Page 9

Customer and the Large Load Customer. Covered Upgrades include the Large Load- 1

Driven Upgrades and any DesertLink-owned CAISO-Assigned Regional Project share 2

identified in the applicable Schedules for which an Annual MTRC is established. 3

Affected System Upgrades and regional project shares owned by another entity are 4

addressed through separate arrangements under Sections 4.2 and 6.3.6, rather than 5

included in DesertLink’s MTRC absent the authorization and conditions specified in the 6

CRA.
7
Q.
HOW DOES THE CRA ALIGN WITH THE COST RECOVERY PRINCIPLES
8
OUTLINED IN THE SHOW CAUSE ORDER?
9
A. At a high level, the CRA responds directly to the three cost-recovery concerns identified 10

in the Show Cause Order by: (i) establishing a pro forma contract between DesertLink 11

and the Eligible Customer that formalizes cost responsibility for the Covered Upgrades; 12

(ii) establishing payment and security obligations designed to mitigate cost shifting to 13

other transmission customers; and (iii) providing credits to transmission customers 14

through the TRBAA to prevent duplicate recovery. The CRA does not change CAISO 15

cost allocation. TRBAA Credits are passed through the TRBAA, not as Formula Rate 16

revenue credits. The revised Formula Rate Template adds Attachment 1a to identify 17

Covered Upgrade plant and Attachment 12, Line 17a to remove any TRBAA Credits 18

otherwise reported in revenue accounts, preventing those amounts from reducing the 19

Formula Rate revenue requirement and being credited twice.
20
Q.
PLEASE DESCRIBE HOW THE CRA CALCULATES THE ELIGIBLE
21
CUSTOMER'S PAYMENT OBLIGATION.
22
A. The core payment mechanism is the Supplemental Minimum Transmission Revenue 23

Contribution (the "Supplemental MTRC") in Section 6.4 of the CRA. Under Section 6.3 24

and Schedule 5, DesertLink calculates a separate Annual MTRC for each Covered 25

PDF page 415

Page 10

Upgrade over a twenty-year MTRC Term beginning on its applicable in-service date and 1

ending on the day immediately preceding the twentieth anniversary of that date, with 2

partial Rate Years prorated. The Estimated Annual MTRC uses then-current estimated 3

capital cost. Within one year after the Covered Upgrade enters service, when actual 4

capital cost is known and all costs associated with its estimated capital cost have been 5

accounted for, DesertLink establishes the Final Annual MTRC as the final incurred 6

capital cost multiplied by the Project-Specific Levelized Fixed Charge Rate calculated 7

under Schedule 5. Schedule 5 applies a fixed five-percent annual levelized-depreciation 8

schedule over the twenty-year MTRC Term to calculate present-worth federal and state 9

income-tax depreciation benefits; that schedule is not a separate annual MTRC charge. 10

The allocation methodology assigns each Large Load Customer a share of the upgrade 11

costs, taking into account other large loads and any portion serving other transmission 12

system needs or customers. That allocation percentage is applied only once in calculating 13

the customer’s Annual MTRC.
14
DesertLink separately calculates Qualifying Transmission Revenues ("QTR") under 15

Section 6.2 and Schedule 2. QTR consists of qualifying wholesale transmission revenues 16

attributable to service to the Large Load Facility that reduce transmission revenues 17

otherwise collected from CAISO customers or directly credit DesertLink’s Net Revenue 18

Requirement. Qualifying Transmission Revenues include the portion of TAC revenues 19

attributable to the Large Load Facility and allocable to DesertLink, together with 20

qualifying wheeling and other wholesale transmission revenues that reduce the amounts 21

otherwise collected from transmission customers. Each revenue amount is counted only 22

once. The Eligible Customer pays the greater of zero and the applicable Annual MTRC 23

PDF page 416

Page 11

less QTR. Under Section 6.5, DesertLink invoices forecast Supplemental MTRC, 1

including any prior-period true-up adjustment, in monthly installments payable within 2

thirty Calendar Days after receipt. Upon initial finalization, the Final Annual MTRC 3

applies back to the in-service date, with estimated charges reconciled in the next 4

Reconciliation Statement, provided as Ex. DLK-102 to my testimony. QTR attributable 5

to a specific Covered Upgrade is applied to that upgrade; other QTR is allocated among 6

Covered Upgrades then in their MTRC Terms pro rata based on their Annual MTRCs. If 7

an upgrade enters service during a Rate Year without a projected Supplemental MTRC in 8

the Annual Projection, DesertLink promptly forecasts and invoices the prorated amount 9

for the remainder of that year under Section 6.5. The Invoice Statement is provided as Ex. 10

DLK-103 to my testimony.
11
Q.
WHY WAS THE SUPPLEMENTAL MTRC DESIGNED IN THIS WAY?
12
A. The Annual MTRC operates as a revenue floor, not an additive charge. Under Section 13

6.6, DesertLink serves a Reconciliation Statement, provided as Ex. DLK-102 to my 14

testimony, concurrently with each Annual Update using actual QTR and the applicable 15

Annual MTRC. The reconciliation identifies billings, receipts, Applied Security 16

Proceeds, the updated Cumulative Revenue Ledger, Required Operational Security, and 17

the reconciliation of forecast TRBAA credits to amounts recorded in the Transmission 18

Revenue Balancing Account ("TRBA"). It does not annually reopen final capital cost or 19

Formula Rate inputs. The Final Annual MTRC may change only as permitted by Section 20

6.3.1, including correction of error or fraud, effective prospective reassignment, a final 21

FERC order applicable to the calculation, or prospective changes resulting from a final 22

FERC order changing DesertLink’s Formula Rate return on equity or from subsequently 23

enacted tax rates or tax law. Dispute determinations are implemented under Section 11.5. 24

PDF page 417

Page 12

When a permitted recalculation is made under Section 6.3.1, DesertLink updates and 1

serves the MTRC Calculation Template on the Eligible Customer; the replacement 2

template becomes effective on service, subject to the Eligible Customer’s Article 11 3

dispute rights.
4
This design responds to Commissioner Chang’s concern about contributions untethered 5

from the costs induced by individual large loads. The CRA ties the minimum contribution 6

to the allocated capital cost and Schedule 5 inputs for identified Covered Upgrades while 7

establishing a defined twenty-year commitment. Annual reconciliation tests the revenue 8

shortfall against that commitment rather than recalculating an annual Formula Rate-based 9

upgrade revenue requirement.
10
Q.
HOW DOES THE CRA ADDRESS STRANDED-ASSET RISK?
11
A. The CRA addresses stranded-asset risk through a twenty-year revenue commitment, 12

construction and operational security, and termination provisions that preserve the 13

Eligible Customer’s responsibility if the Large Load fails to materialize or departs the 14

system.
15
First, Section 6.7 establishes the Total Required Revenue Commitment for each Covered 16

Upgrade as the Final Annual MTRC multiplied by twenty, subject to the adjustments 17

specified in that section. Before final determination, the projected commitment uses the 18

Estimated Annual MTRC. The Remaining Cumulative Revenue Responsibility equals 19

that commitment less cumulative QTR, Supplemental MTRC Receipts, Applied Security 20

Proceeds, effective prospective reassignment credits, and a Termination Fee received in 21

full, without double counting. DesertLink updates an upgrade-specific Cumulative 22

Revenue Ledger at least annually and includes it with each Reconciliation Statement. 23

When a final Reconciliation Statement determines that the remaining responsibility is 24

PDF page 418

Page 13

zero ("Break-Even"), operational payment and security obligations terminate. Once 1

finally satisfied, the responsibility does not revive because of later changes in Formula 2

Rate inputs, subject to final true-ups and correction of errors or fraud for periods before 3

satisfaction.
4
Second, Sections 3.3.4 and 3.5 provide that cancellation, downsizing, curtailment, or 5

cessation after an applicable in-service date does not itself eliminate payment or security 6

obligations. Upon effective termination of the CRA or permanent cessation of service 7

after that date, the Eligible Customer owes a lump-sum Termination Fee equal to the 8

Remaining Cumulative Revenue Responsibility for the in-service Covered Upgrades, less 9

any Supplemental MTRC billed and unpaid as of the effective termination date, due thirty 10

Calendar Days after DesertLink’s invoice. The excluded unpaid Supplemental MTRC 11

remains separately payable and secured; its later payment, satisfaction through Applied 12

Security Proceeds, or direct recovery reduces the Cumulative Revenue Responsibility. 13

Payment in full discharges only the remaining contractual responsibility included in the 14

fee, and no further Supplemental MTRC accrues for periods after the effective 15

termination or cessation date, subject to final reconciliation for earlier periods. 16

DesertLink holds each Termination Fee, together with any Operational Security proceeds 17

applied to it, in a separate interest-bearing Termination Fee Account. For each Covered 18

Upgrade, the Annual Termination Fee Credit for each remaining Rate Year equals the 19

applicable Annual MTRC, prorated for a partial Rate Year, but may not exceed the 20

available Termination Fee Balance. In the final Rate Year of the MTRC Term, the credit 21

includes the entire remaining balance, including earnings, so the account is reduced to 22

zero, subject to release and adjustment if a prospective reassignment occurs. The 23

PDF page 419

Page 14

uncredited balance is separately accounted for as a deferred liability, is not included in 1

rate base, and is not itself a TRBAA Credit. These credits do not reduce rate base. 2

Third, Article 7 requires Construction Security for incurred and irrevocably committed 3

costs and Pre-In-Service Termination Costs, including applicable cancellation, 4

demobilization, and restoration costs and properly accrued allowance for funds used 5

during construction ("AFUDC"). Construction Security continues separately for upgrades 6

not yet in service. Operational Security must be delivered no later than thirty Calendar 7

Days before the earliest expected applicable in-service date and be fully effective before 8

service. Under Section 7.3, it equals one hundred percent of the nominal Remaining 9

Cumulative Revenue Responsibility, reduced only by currently certified Qualifying 10

Retail Security Support.  Security is recalculated at the events specified in Section 7.4, 11

including annual projections and reconciliations, final MTRC determination, permitted 12

recalculations, reassignment, and credit review events. Security does not cap the Eligible 13

Customer’s underlying liability. For a DesertLink-owned CAISO-Assigned Regional 14

Project, the CRA does not independently impose pre-service Construction Security solely 15

because CAISO has assigned a project share; any such requirement must arise under the 16

applicable tariff, interconnection agreement, or other Commission-accepted arrangement. 17

Together, these provisions protect against stranded-asset exposure through an identified 18

revenue commitment and enforceable payment and security obligations. Sections 4.2 and 19

6.3.6 also require separate affected-system and third-party regional-project arrangements 20

and evidence of compliance. These provisions support the Show Cause Order’s objective 21

of mitigating the risk of stranded assets if large loads prove speculative. 22

PDF page 420

Page 15

Q.
HOW DOES THE CRA AVOID REDUNDANT FINANCIAL SECURITY
1
REQUIREMENTS?
2
A. Section 7.1 recognizes Construction Security provided under an interconnection or 3

engineering and procurement agreement for the same costs, avoiding duplication. Under 4

Article 7 and Schedule 3, a currently effective Retail Security Certification reduces direct 5

Operational Security dollar-for-dollar by certified Qualifying Retail Security Support. 6

This does not reduce the underlying wholesale obligation and does not apply to 7

Construction Security or Pre-In-Service Termination Costs. The certification remains 8

effective until superseded, withdrawn, or deemed ineffective; no annual recertification is 9

required unless an update-triggering event occurs. Direct Security may be cash, a 10

qualifying Letter of Credit, or another form accepted by DesertLink in its sole discretion. 11

There is no automatic unsecured allowance for an investment-grade utility. 12

Section 6.10 allows transfer to a Successor Eligible Customer through an assumption 13

agreement and required Security before the prior Eligible Customer is released. Section 14

6.9 permits prospective reassignment to a subsequent large load at another facility only 15

when an objective study demonstrates reliance on identifiable incremental upgrade 16

capability that avoids or reduces otherwise-needed upgrades. The reassignment is 17

bounded by the avoided upgrade cost, capability-supported amount, and remaining 18

allocated net plant. A reduction becomes effective only after the service, agreement, 19

security, and approval conditions are satisfied, and does not reopen prior years. A sale or 20

transfer of the same Large Load Facility is governed by Section 6.10 rather than the 21

reassignment study process.
22

PDF page 421

Page 16

Q.
HOW DOES THE CRA HELP ENSURE THAT PAYMENTS ARE
1
APPROPRIATELY CREDITED TO TRANSMISSION CUSTOMERS?
2
A. Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits. In each 3

annual TRBAA, DesertLink includes as a Forecast TRBAA Credit the projected 4

Supplemental MTRC for the following Rate Year, increased or reduced by any prior- 5

period true-up adjustment, plus any Annual Termination Fee Credit scheduled for that 6

year under Section 3.3.4.  Actual Supplemental MTRC Receipts and Applied Security 7

Proceeds are recorded in the TRBA when received or applied, except that proceeds 8

applied to a Termination Fee are credited through the Termination Fee’s annual crediting 9

schedule. Differences between the forecast credit and the applicable actual amounts flow 10

through a subsequent TRBAA. The TRBA also reflects any adjustments necessary to 11

prevent duplicate recovery of amounts collected under the CRA. Each dollar is counted 12

once; QTR is not credited again, and posting, drawing, or holding Security does not itself 13

produce a credit. DesertLink maintains supporting workpapers and includes sufficient 14

workpapers with each TRBAA filing to permit verification, subject to appropriate 15

confidentiality protections.
16
This mechanism provides transmission customers the benefit of the CRA’s payments 17

without changing the Formula Rate calculation or recovering the same amount twice. 18

Interest on the TRBA balance is governed by Section 5.5 of the TO Tariff. By contrast, 19

Supplemental MTRC invoices, refunds, and prior-period adjustments between 20

DesertLink and the Eligible Customer do not accrue interest under Section 6.6. 21

VI. TARIFF REVISIONS
22
Q.
PLEASE DESCRIBE THE ASSOCIATED TARIFF REVISIONS.
23

PDF page 422

Page 17

A. The TO Tariff establishes the Eligible Customer for Large Load ("ECLL") 1

interconnection framework in Section 10A, identifies the pro forma CRA as Appendix V, 2

and incorporates the Large Load Interconnection Procedures ("LLIP"). The LLIP 3

addresses the physical interconnection and study process; the CRA addresses the 4

wholesale revenue-support obligations. The Formula Rate and Protocols continue to 5

govern DesertLink’s Net Revenue Requirement and rate-base treatment. Schedule 5 of 6

the CRA governs the Annual MTRC, and Section 5.5 of the TO Tariff governs the flow- 7

through of credits through the TRBAA. CRA payments are credited through the TRBAA, 8

not as Formula Rate revenue credits. The revised Formula Rate Template adds 9

Attachment 1a to identify Covered Upgrade plant and Attachment 12, Line 17a to remove 10

any TRBAA Credits otherwise reported in revenue accounts, preventing duplicate 11

crediting.
12
Q.
PLEASE DESCRIBE THE REVISIONS TO THE TO TARIFF.
13
A. The principal changes establish definitions for Large Load, Co-Located Large Load, 14

ECLL, ECLL Interconnection, Firm Interconnection Service, Flexible Interim Load 15

Interconnection ("FILI") Service, Interim Firm Interconnection Service, Point of 16

Withdrawal, Site Control, and CRA. A Large Load is an End-User at a single site behind 17

one or more Points of Withdrawal with peak load of 50 MW or greater. An ECLL is a 18

Utility Distribution Company ("UDC") or Metered Subsystem ("MSS") providing retail 19

transmission and interconnection service to Large Load End-Users in the CAISO 20

Balancing Authority Area. Section 10A addresses ECLL applications, studies, 21

agreements, interim service, and co-located loads, and Section 10A.3 directs that the 22

study and agreement process be conducted under Appendix VI. Section 10 remains the 23

Transmission System Wholesale Load ("TSWL") interconnection process. Related 24

PDF page 423

Page 18

revisions address eligibility, interconnection obligations, creditworthiness, disputes, and 1

TRBAA credits. Section 10A and the LLIP apply when DesertLink is the lead 2

Participating TO; otherwise, the lead Participating TO’s corresponding tariff provisions 3

govern, with notice to DesertLink.
4
Q.
HOW DO THE TO TARIFF REVISIONS ADDRESS THE SHOW CAUSE
5
ORDER'S CONCERN THAT EXISTING TARIFFS LACK CLEAR AND
6
CONSISTENT PROVISIONS FOR LARGE LOADS?
7
A. The proposed framework establishes an ECLL interconnection process under Section 8

10A and the LLIP. The LLIP applies to new Large Loads, capacity increases to Large 9

Loads previously processed under the LLIP, and increases of 50 MW or greater to 10

existing loads not previously processed under the LLIP. It applies to completed 11

Interconnection Requests submitted after Appendix VI becomes effective. Under LLIP 12

Section 1.2, the Interconnection Request, studies, and Large Load Interconnection 13

Agreement serve as the ECLL application, study process, and ECLL Agreement for 14

purposes of Section 10A.
15
Section 10A.2.1 and LLIP Attachment 1 require information concerning the load ramp, 16

site, Site Control, permits and approvals, electrical configuration, related requests, and 17

technical characteristics. LLIP Sections 4.5 and 4.6 provide for a scoping meeting, a 18

Large Load Study Process Agreement, and a Large Load Interconnection Study subject to 19

ISO review and concurrence. LLIP Section 4.6.1.2 establishes a ninety-Calendar-Day 20

reasonable-efforts study period after execution of the study agreement or FERC 21

effectiveness of an unexecuted agreement. LLIP Sections 4.6.2 and 4.6.2.1, together with 22

TO Tariff Section 10A.4, provide an optional study and agreement process for Interim 23

Firm Interconnection Service and FILI Service before completion of required facilities. 24

FILI Service is subject to operating limits and curtailment, including during normal 25

PDF page 424

Page 19

operating conditions, and is curtailed before Firm Interconnection Service. Its maximum 1

studied availability does not guarantee availability under actual operating conditions. 2

Q.
HOW DO THE TO TARIFF REVISIONS IMPLEMENT THE CRA REQUIRED
3
BY THE SHOW CAUSE ORDER?
4
A. The proposed pro forma CRA is identified as Appendix V to the TO Tariff. TO Tariff 5

Sections 10.9, 10A.3.9, and 10A.6  and LLIP Section 5.3 require an applicant, where 6

DesertLink requires a CRA, to execute it or request its filing unexecuted within the 7

applicable interconnection-agreement execution period. The ECLL Agreement will be 8

developed by DesertLink consistent with the TO Tariff. The CRA establishes the Eligible 9

Customer’s payment and security obligations for Covered Upgrades, while the 10

interconnection agreement addresses physical facilities and related responsibilities. Under 11

Article 5 of the CRA, a conforming, executed agreement with populated Schedules 12

generally will not require an individual Section 205 filing once the pro forma is accepted; 13

unexecuted agreements, material deviations, and other agreements required by 14

Commission rule or order must be filed.
15
Q.
HOW DO THE TO TARIFF REVISIONS EVALUATE ALTERNATIVE
16
TRANSMISSION TECHNOLOGIES AND KEEP COSTS AT A RESPONSIBLE
17
AND ACCOUNTABLE LEVEL?
18
A. TO Tariff Section 10A.3.7 and LLIP Section 4.6.1.1 require consideration of alternative 19

transmission technologies. The LLIP identifies dynamic line ratings, advanced power 20

flow control devices, advanced conductors, and transmission switching. If traditional 21

network upgrades are selected, DesertLink must demonstrate why alternative 22

technologies are not feasible or would not lower costs or provide a faster interconnection 23

timeline.
24

PDF page 425

Page 20

The LLIP also establishes financial readiness requirements. Section 4.2.1 requires a 1

$250,000 Interconnection Study Deposit and an initial Commercial Readiness Deposit 2

equal to twice that amount. Section 4.6.1.4 requires an additional Commercial Readiness 3

Deposit sufficient to bring the aggregate deposit to twenty percent of the Participating 4

TO’s then-current estimated construction cost of the Large Load Network Upgrades 5

identified in the final Large Load Interconnection Study report and attributable to the 6

Interconnection Request. The additional deposit is due within thirty Calendar Days after 7

the Large Load Interconnection Customer receives that report. If the final report is 8

revised following ISO review, the deposit is adjusted to reflect twenty percent of the 9

corresponding estimated construction cost in the revised final report, with any required 10

increase due within thirty Calendar Days after issuance of that report.  Study costs are 11

reconciled to actual costs, and Sections 3.10 and 3.10.1 establish withdrawal penalties 12

and exceptions. Under Section 3.10.1, a Commercial Readiness Deposit or 13

Interconnection Financial Security provided for the same costs counts toward, and is not 14

duplicated by, the Construction Security required under the CRA; a Withdrawal Penalty 15

paid for a Large Load Network Upgrade is credited against the Pre-In-Service 16

Termination Costs for that upgrade. Section 4.6.4 assigns financing of the Participating 17

TO’s Interconnection Facilities solely to the Large Load Interconnection Customer and 18

financing of Large Load Network Upgrades to DesertLink under the interconnection 19

agreement and, where required, the CRA. Facilities directly assigned and paid for under 20

an interconnection agreement and excluded from DesertLink’s rate base are excluded 21

from Large Load-Driven Upgrades under the CRA.
22
Q.
HOW DOES THE CRA INTERACT WITH THE FORMULA RATE AND
23
PROTOCOLS?
24

PDF page 426

Page 21

A. Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the 1

calculation, information exchange, and true-up of DesertLink’s Net Revenue 2

Requirement and the rate-base treatment of Covered Upgrades. The CRA preserves 3

DesertLink's recovery of eligible transmission upgrade costs through its Formula Rate 4

and does not require the Eligible Customer to reimburse DesertLink directly for the 5

capital costs of those upgrades. Instead, the CRA establishes a minimum transmission 6

revenue commitment, with Supplemental MTRC payments credited to transmission 7

customers through the TRBAA mechanism.
8
Schedule 5, rather than a new Formula Rate calculation, controls the Estimated Annual 9

MTRC and Final Annual MTRC. The CRA controls Supplemental MTRC, the
10
Cumulative Revenue Responsibility, Operational Security, and prospective reassignment. 11

With each Annual Projection, Section 6.5 requires upgrade-specific workpapers showing 12

the Annual MTRC, forecast QTR, projected Supplemental MTRC, prior-period true-up 13

adjustment, Forecast TRBAA Credit, Total Required Revenue Commitment, and 14

Required Operational Security. With each Annual Update, Sections 6.6 and 6.7 require 15

service of the Reconciliation Statement, updated Cumulative Revenue Ledger, 16

recalculated security, TRBA reconciliation, and supporting workpapers. 17

Section 6.8 governs credits through the TRBAA, and Article 11 governs disputes arising 18

under the CRA. The Annual MTRC and related contractual obligations are administered 19

under the CRA separately from the Formula Rate calculation.
20
Q.
HOW DOES THE CRA ADDRESS ANNUAL TRUE-UPS AND FINALITY?
21
A. Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into 22

billing following the next Annual Projection. If no further Supplemental MTRC will be 23

invoiced, DesertLink separately invoices an under-billed amount, payable within thirty 24

PDF page 427

Page 22

Calendar Days after receipt, or refunds an over-billed amount within thirty Calendar 1

Days after service of the Reconciliation Statement. These adjustments between the 2

Parties bear no interest. The Reconciliation Statement becomes final upon written 3

acceptance or ninety Calendar Days after service, whichever occurs first, unless a timely 4

Notice of Dispute identifies disputed items. Undisputed portions become final on the 5

otherwise applicable date; disputed items become final upon the applicable Dispute 6

Determination.
7
Under Section 11.5, DesertLink implements a final Dispute Determination by updating 8

the affected calculations, Schedules, ledger, reconciliation, and Security, as applicable, 9

and invoicing or refunding amounts between the Parties within thirty Calendar Days, 10

without interest. Any resulting adjustment affecting amounts credited to or recovered 11

from transmission customers is recorded in the TRBA and flows through the TRBAA, 12

with interest on amounts returned to transmission customers as provided in Section 5.5 of 13

the TO Tariff.
14
Q.
HOW DOES THE CRA SUPPORT COST AND BILLING TRANSPARENCY?
15
A. The Annual Projection workpapers and annual Reconciliation Statement make the 16

upgrade-specific minimum contribution, forecast and actual QTR, Supplemental MTRC, 17

cumulative commitment, security, and TRBAA credit calculations available to the 18

Eligible Customer. Schedule 5 records the MTRC calculation and Cumulative Revenue 19

Ledger. Section 6.8 also requires workpapers with each TRBAA filing sufficient for 20

transmission customers to verify the credits, with aggregation or privileged treatment 21

available to protect customer-specific information. LLIP Sections 4.6.1.2 and 4.6.1.3 22

separately provide for study reports, supporting documentation upon request, and a 23

PDF page 428

Page 23
Report Meeting addressing study results and assigned cost responsibility. LLIP Section 1

4.6.2.1 provides for ISO posting of FILI Service Agreements.
2
Section 6.12 provides the Eligible Customer access, upon reasonable request, to the 3

information needed to verify the identification of upgrades and the CRA’s calculations. 4

Article 11 provides informal resolution, alternative dispute resolution, and access to 5

FERC. Consistent with TO Tariff Sections 10.9, 10A.3, 10A.3.9, 10A.6, and 14, disputes 6

arising under a CRA are resolved under that agreement’s dispute resolution provisions. 7

The Large Load Customer and any Successor Eligible Customer may participate to the 8

extent a dispute affects its obligations under the CRA or Limited Acknowledgment. 9

Disputes over CAISO’s regional project designation or assignment are resolved under the 10

applicable CAISO Tariff procedures.
11
The CRA’s confidentiality provisions protect customer-specific information while 12

preserving verification and dispute rights. These contractual records and the TRBAA 13

filing workpapers provide a basis to trace payments and credits and test whether the same 14

obligation has been counted more than once.
15
Q.
DOES THIS CONCLUDE YOUR TESTIMONY?
16
A. Yes, it does.
17

PDF page 429

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

DesertLink, LLC
California Independent System Operator Corporation
)
)
Docket No.
Docket No.
ER27-___-000
EL26-71-___

VERIFICATION

I, Patrick Hayes, verify under penalty of perjury that I have read the testimony, know the contents thereof, and that the facts and representations set forth therein are true to the best of my knowledge, information and belief.

/s/ Patrick Hayes___________________________

Patrick Hayes

Dated: November 16, 2026

PDF page 430

Ex. DLK-101
MTRC Example (Excel)

PDF page 431

Ex. DLK-102

Illustrative Reconciliation Statement

PDF page 432

DesertLink LLC  |  Proposed unpopulated form  |  1 Illustrative Reconciliation Statement

ILLUSTRATIVE FORMAT; THE CRA DOES NOT REQUIRE USE OF THIS EXACT FORM. Serve with the Annual Update. Complete by Covered Upgrade and attach customer totals and workpapers. Amounts are dollars; positive customer adjustments are charges and negative adjustments are credits.

Statement information
Entry
Eligible Customer
[ ]
Large Load Facility
[ ]
CRA identifier
[ ]
Covered Upgrade
[ ]
Rate Year
[ ]
Statement identifier
[ ]
Statement date
[ ]
Statement service date
[ ]

1 Annual obligation and customer true up
Line
Component
Forecast
Actual
1
Applicable Annual MTRC after proration
[ ]
[ ]
2
Qualifying Transmission Revenues
[ ]
[ ]
3
Supplemental MTRC
max(1 − 2, 0)
max(1 − 2, 0)

Line
Component
Amount or calculation
4
Total Supplemental MTRC billed during the Rate Year [ ]

5
Prior-period adjustments included in line 4
[Signed amount as billed]
6
Current-year Supplemental MTRC billed
Line 4 − line 5
7
Customer true-up to carry forward or settle
Line 3 actual − line 6
8
Portion of line 7 already billed or refunded separately [Signed amount; identify transaction]

9
Unimplemented customer adjustment
Line 7 − line 8

Implementation information
Entry
Annual MTRC status
[Estimated / Final / permitted recalculation] Final MTRC Determination Date

[Date or not yet established]
Actual in-service date
[ ]
MTRC Term End Date
[Day before twentieth anniversary of in-service] Schedule 5 calculation reference

[ ]
Adjustment billing Rate Year
[ ]
Next invoice or refund reference
[ ]

PDF page 433

DesertLink LLC  |  Proposed unpopulated form  |  2 2 Collections and cumulative revenue ledger Line

Component
Amount or calculation
10
Opening unpaid Supplemental MTRC billed balance [ ]

11
New Supplemental MTRC billed during the period Line 4

12
Customer payments applied to those billed obligations [Exclude Applied Security Proceeds]

13
Operational Security proceeds applied to those obligations [ ]

14
Other billing adjustments or reversals
[Signed amount; explain]
15
Closing unpaid billed balance
Lines 10 + 11 − 12 − 13 + 14
16
Closing balance per billing records
[ ]
17
Billing balance check
Line 15 − line 16 = 0

3 Remaining cumulative responsibility
Line
Component
Amount or calculation
18
Opening Remaining Cumulative Revenue Responsibility [ ]

19
Permitted commitment changes excluding reassignment [Signed amount; identify authority]

20
Qualifying Transmission Revenues credited this period [Reconcile to line 2 actual and prior-year adjustments] 21

Supplemental MTRC Receipts credited this period [Exclude Applied Security Proceeds and Termination Fee] 22

Applied Security Proceeds credited this period [Count each dollar once]

23
Effective prospective reassignment credit
[ ]
24
Termination Fee recognized upon receipt in full [Exclude amounts already in line 22]

25
Reversals of prior credits or other ledger adjustments [Signed amount; explain]

26
Closing Remaining Cumulative Revenue Responsibility max(18 + 19 − 20 − 21 − 22 − 23 − 24 + 25, 0) 27

Closing responsibility per cumulative ledger [ ]

28
Cumulative ledger check
Line 26 − line 27 = 0

PDF page 434

DesertLink LLC  |  Proposed unpopulated form  |  3 4 Operational security

Line
Component
Amount or calculation
29
Closing nominal remaining responsibility Line 26

30
Currently certified Qualifying Retail Security Support [ ]

31
Required direct Operational Security
max(line 29 − line 30, 0)
32
Eligible direct Operational Security available to DesertLink [Cash and qualifying instruments; exclude retail support] 33

Security deficiency or potential excess
Line 31 − line 32

5 TRBA and TRBAA reconciliation
Line
Component
Amount or calculation
34
Forecast TRBAA Credit for the applicable Rate Year [Include billed prior-period adjustments] 35

Supplemental MTRC Receipts recorded in TRBA [ ]

36
Applied Security Proceeds recorded in TRBA [Exclude amounts counted on another line] 37

Annual Termination Fee Credits recorded in TRBA [Exclude amounts already in line 36]

38
Duplicate-recovery credits recorded in TRBA [§3.3.3(d) / §6.3.5, if applicable]

39
Refunds or reversals reducing recorded credits [ ]

40
Net actual amounts recorded in TRBA
Lines 35 + 36 + 37 + 38 − 39
41
Actual credit less forecast credit
Line 40 − line 34
42
TRBA workpaper difference on the same sign basis [ ]

43
TRBA reconciliation check
Line 41 − line 42 = 0

6 Service and finality
Control
Entry
Prepared by
[ ]
Reviewed by
[ ]
Customer service reference
[ ]
90 Calendar Day dispute deadline from service [ ]

Written acceptance date if earlier
[ ]
Disputed items and Notice of Dispute reference [None or attachment]

Final status
[Pending / partial / final]
Finality date
[ ]

PDF page 435

Ex. DLK-103

Illustrative Invoice Statement

PDF page 436

DesertLink LLC  |  Proposed unpopulated form  |  1 Illustrative Invoice Statement

ILLUSTRATIVE FORMAT; THE CRA DOES NOT REQUIRE USE OF THIS EXACT FORM. DesertLink invoices the Eligible Customer directly. Complete one upgrade calculation and attach supporting workpapers. Amounts are in dollars; positive adjustments are charges and negative adjustments are credits.

Statement information
Entry
Eligible Customer
[ ]
Large Load Facility
[ ]
CRA identifier
[ ]
Covered Upgrade
[ ]
Rate Year
[ ]
Statement identifier
[ ]
Statement date
[ ]
Statement service date
[ ]
Invoice receipt date
[ ]
Payment due date
[30 Calendar Days after receipt; confirm charge provision]

1 Projected Supplemental MTRC
Line
Component
Amount or calculation
1
Applicable projected Annual MTRC after proration [ ]

2
Projected Qualifying Transmission Revenues
[ ]
3
Projected Supplemental MTRC before adjustments
max(line 1 − line 2, 0)
4
Prior-period true-up adjustment allocated to this Rate Year [Signed amount; zero if none]

5
Supplemental MTRC scheduled for this Rate Year
Line 3 + line 4
6
Number of scheduled monthly installments
[12 for full year; actual count for partial year] 7

Scheduled monthly installment
Line 5 ÷ line 6

2 Current invoice
Line
Component
Amount or calculation
8
Current billing period
[Month and year]
9
Supplemental MTRC installment for this period
[From line 7; identify any rounding adjustment]
10
Other incremental charge or credit on page 2
Line 17
11
Payments already applied to lines 9 and 10
[Exclude Applied Security Proceeds]
12
Operational Security proceeds already applied to lines 9 and 10 [ ]

13
Net current invoice amount
Lines 9 + 10 − 11 − 12

PDF page 437

DesertLink LLC  |  Proposed unpopulated form  |  2 3 Other incremental charge or credit

Complete for each additional item and attach a charge detail if more than one item applies. Use only the net amount not already billed or satisfied; carry the aggregate to line 10. Line

Component
Amount or calculation
14
Charge type
[True-up / Termination Fee / other authorized item] 15

Gross amount of this item
[ ]
16a
Less amount of this same item previously billed [ ]

16b
Less previously unbilled amount already paid [ ]

16c
Less previously unbilled amount satisfied by security [Exclude any amount already included in 16b] 17

Net incremental charge or credit
Line 15 − lines 16a − 16b − 16c

Supporting information
Entry
Authorizing CRA provision
[ ]
Source Rate Year
[ ]
Reconciliation Statement identifier
[ ]
Source adjustment amount
[Signed amount]
Portion of adjustment previously billed or refunded [ ]

Supporting calculation reference
[ ]
Termination or cessation date if applicable [ ]

Updated cumulative ledger reference if applicable [ ]

4 Corrections and payment instructions
Control
Entry
Superseded invoice identifier
[Original or prior invoice ID]
Reason for correction
[ ]
Previously invoiced amount
[ ]
Correction to previously billed amount
[Signed amount; identify affected invoices] Payment instructions

[Verified remittance instructions or attachment] DesertLink contact

[Name and contact details]
Prepared by
[ ]
Reviewed by
[ ]
Delivery recipient
[ ]
Delivery reference
[ ]

PDF page 438

Attachment 4

Direct Testimony of D. Eric Arzola (Exhibit No. DLK-200) and Supporting Exhibits

PDF page 439

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

DesertLink, LLC
California Independent System Operator Corporation )

)
Docket No.
Docket No.
ER27-___-000
EL26-71-___

DIRECT TESTIMONY
OF
D. ERIC ARZOLA

ON BEHALF OF
DESERTLINK, LLC

Large Load Network Upgrade Cost Recovery

November 2026

PDF page 440

TABLE OF CONTENTS

I. INTRODUCTION AND EXPERIENCE … 1
II. PURPOSE AND SUMMARY OF TESTIMONY … 2
III. DESERTLINK AND FORMULA RATE BACKGROUND … 4
IV. THE LARGE LOAD COST RECOVERY FRAMEWORK … 6
V. CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA … 10
VI. DESERTLINK’S PROPOSED FORMULA RATE TEMPLATE CHANGES … 14
VII. NATIVE AND ILLUSTRATIVE EXHIBITS … 16
VIII. CONCLUSION … 19

PDF page 441

EXHIBITS TO
DIRECT TESTIMONY OF D. ERIC ARZOLA

Exhibit No.
Description
DLK-201:
Clean Formula Rate Template
DLK-202:
Marked Formula Rate Template
DLK-203:
Clean Formula Rate Template (Excel Format) DLK-204:

Illustrative Formula Rate Template DLK-205:

Illustrative TRBAA Calculation

PDF page 442

DIRECT TESTIMONY OF

D. ERIC ARZOLA

I. INTRODUCTION AND EXPERIENCE
1
Q.
PLEASE STATE YOUR NAME AND BUSINESS ADDRESS.
2
A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310, 3

Chesterfield, Missouri 63017.
4
Q.
WITH WHAT ENTITY ARE YOU EMPLOYED?
5
A. I am employed as the Director of Transmission Rates at LS Power Development, LLC 6

(“LS Power Development”), the general partner and manager of LS Power Associates, 7

L.P. (“LS Power”), which is an affiliate of DesertLink, LLC (“DesertLink” or 8

“Company”).
9
Q.
ON WHOSE BEHALF ARE YOU TESTIFYING IN THIS PROCEEDING?
10
A. I am testifying on behalf of DesertLink.
11
Q.
HAVE YOU PREVIOUSLY FILED TESTIMONY BEFORE A REGULATORY
12
COMMISSION?
13
A. Yes. I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or 14

“Commission”) Docket Nos. ER22-221, ER23-206, ER24-264, ER24-2668, ER25-321, 15

ER25-2025, ER26-69, ER26-140, ER26-315, ER27-165, and ER27-482.
16
Q.
PLEASE DESCRIBE YOUR EDUCATIONAL BACKGROUND AND
17
PROFESSIONAL EXPERIENCE.
18
A. I have a Bachelor of Arts degree in Economics from Rice University in Houston, Texas, 19

and a Graduate Certificate in Energy Policy and Management from Portland State 20

University in Portland, Oregon. I have over 22 years of experience in the energy industry, 21

with over 12 years focused on transmission cost of service rates, regulation, and strategy. 22

PDF page 443

2

I have been employed by LS Power Development since 2020, where I am responsible for 1

overseeing transmission rates for LS Power’s FERC-jurisdictional entities. Prior to 2

joining LS Power, I held positions with similar responsibilities at GridLiance LLC and 3

PacifiCorp.
4
II. PURPOSE AND SUMMARY OF TESTIMONY
5
Q.
WHAT IS THE PURPOSE OF YOUR TESTIMONY?
6
A. The purpose of my testimony is to explain how DesertLink will recover the cost of 7

transmission facilities built to serve large loads and covered by a Large Load Cost 8

Recovery Agreement (“CRA”) (such facilities, “Covered Upgrades”), and how it will 9

credit the amounts Eligible Customers pay under their CRAs to transmission customers. 10

The proposal responds to the Commission’s June 18, 2026, order in Docket No. EL26- 11

71-000 (“Show Cause Order”). Specifically, my testimony (i) describes the large load 12

cost recovery framework; (ii) explains how the amounts DesertLink receives under its 13

CRAs will be credited to customers through DesertLink’s Transmission Revenue 14

Balancing Account Adjustment (“TRBAA”), and the related revisions to DesertLink’s 15

Transmission Owner Tariff (“TO Tariff”); (iii) describes the changes to DesertLink’s 16

Formula Rate Template, including a new Attachment 1a; (iv) explains why no changes 17

are needed to DesertLink’s Formula Rate Implementation Protocols or Appendix I of the 18

TO Tariff; (v) describes the exhibits I sponsor, including two illustrative examples; and 19

(vi) explains why the proposal is just and reasonable. The pro forma CRA, including how 20

each Eligible Customer’s annual Minimum Transmission Revenue Contribution is 21

established, is sponsored by DesertLink witness Mr. Hayes.
22

PDF page 444

3

Q.
PLEASE SUMMARIZE THE PROPOSAL.
1
A. DesertLink proposes to credit the amounts it receives under its CRAs to transmission 2

customers through its TRBAA, the existing mechanism DesertLink uses to pass revenue 3

that it does not receive through the California Independent System Operator Corporation 4

(“CAISO”) Transmission Access Charge (“TAC”) back to customers. To implement this 5

proposal, DesertLink proposes the following:
6
• Revise the definition of the TRBAA and Section 5.5 of the TO Tariff so that the 7

TRBAA also flows through to transmission customers the amounts a CRA 8

requires to be credited through it, including TRBAA Credits that DesertLink 9

receives directly from or on behalf of an Eligible Customer;
10
• Add Attachment 1a – Project Plant Detail to the Formula Rate Template, to report 11

plant and net investment separately for the Harry Allen to Eldorado 500 kV 12

Transmission Project (“Harry Allen to Eldorado Project”) and each Covered 13

Upgrade;
14
• Use the project detail on Attachment 1a to calculate the revenue requirement of 15

each project on Attachment 1 – Project Revenue Requirement Worksheet; and 16

• Add a new Line 17a to Attachment 12 – Revenue Credit Detail, so that TRBAA 17

Credits are not also credited in the Formula Rate.
18
Q.
DO THE REVISIONS CHANGE HOW DESERTLINK’S REVENUE
19
REQUIREMENT IS CALCULATED?
20
A. No. The cost of service inputs, return, depreciation, taxes, and allocators are unchanged. 21

Covered Upgrades are included in DesertLink’s rate base and revenue requirement in the 22

same manner as any other DesertLink transmission plant. The revisions add project-level 23

detail and ensure that TRBAA Credits are credited only once. Absent any Covered 24

PDF page 445

4

Upgrade or CRA, the revised Formula Rate Template produces the same revenue 1

requirement as the currently effective Formula Rate Template. Once these revisions are 2

accepted, entry into a CRA and receipt of amounts under it will not require any further 3

modification of the Formula Rate.
4
Q.
OTHER THAN YOUR TESTIMONY, ARE YOU SPONSORING ANY
5
EXHIBITS?
6
A. Yes. I am sponsoring the following exhibits:
7
Exhibit No.
Description
DLK-201:
Clean Formula Rate Template
DLK-202:
Marked Formula Rate Template
DLK-203:
Clean Formula Rate Template (Excel Format)
DLK-204:
Illustrative Formula Rate Template
DLK-205:
Illustrative TRBAA Calculation
III. DESERTLINK AND FORMULA RATE BACKGROUND
8
Q.
PLEASE PROVIDE AN OVERVIEW OF DESERTLINK AND ITS FORMULA
9
RATE.
10
A. DesertLink is a transmission-only Participating Transmission Owner in the CAISO that 11

owns the Harry Allen to Eldorado Project, which the CAISO selected DesertLink to 12

develop through its competitive solicitation process. DesertLink’s formula rate consists 13

of its Formula Rate Template (Appendix III of the TO Tariff) and its Formula Rate 14

Implementation Protocols (Appendix IV of the TO Tariff) (together, the “Formula 15

Rate”), which were originally accepted by the Commission in Docket No. ER17-135 and 16

most recently revised in Docket No. ER26-3479. DesertLink’s revenue requirement is 17

recovered through the CAISO TAC.
18
Q.
HOW DOES THE FORMULA RATE OPERATE EACH YEAR?
19
A. By October 1, DesertLink posts an Annual Projection of its net revenue requirement for 20

the upcoming Rate Year. By July 1 after each Rate Year, DesertLink posts an Annual 21

PDF page 446

5

Update using actual FERC Form No. 1 or other Company data. The difference between 1

the projected and actual net revenue requirement, with interest, is the True-Up 2

Adjustment, which is included in a later Annual Projection.
3
Q.
HOW IS DESERTLINK’S TRANSMISSION REVENUE REQUIREMENT
4
DETERMINED?
5
A. As provided in Appendix I of the TO Tariff, DesertLink’s Transmission Revenue 6

Requirement (“TRR”) is the sum of its Base Transmission Revenue Requirement (“Base 7

TRR”), determined under the Formula Rate, and its TRBAA. DesertLink files to update 8

its TRBAA each October, effective January 1. Under Section 5.5 of the TO Tariff, the 9

TRBAA equals the principal balance in DesertLink’s Transmission Revenue Balancing 10

Account (“TRBA”) as of September 30 (“Cr”), plus a forecast of Transmission Revenue 11

Credits for the following calendar year (“Cf”), plus the interest balance for the TRBA 12

(“I”). The TRBA compares DesertLink’s Base TRR to the amounts it actually receives, 13

so that DesertLink collects no more and no less than its Base TRR. DesertLink already 14

uses the TRBAA to credit customers with revenue it receives outside the TAC, such as 15

Generator Interconnection Process Forfeited Deposit Allocations.
16
Q.
WHY IS DESERTLINK MAKING THIS FILING?
17
A. In the Show Cause Order, the Commission directed the CAISO and its transmission 18

owners to show cause why their tariffs remain just and reasonable or to propose changes 19

for integrating large loads. Among other things, the Commission called for a mechanism 20

to ensure that large load payments are “credited toward transmission owners’ 21

transmission revenue requirements.” DesertLink’s current Formula Rate Template reports 22

plant values only in total and has no means of identifying the facilities built to serve large 23

loads, and its TO Tariff limits Transmission Revenue Credits to amounts received from 24

PDF page 447

6

the CAISO. The revisions I describe provide the mechanism the Commission called for. 1

IV. THE LARGE LOAD COST RECOVERY FRAMEWORK
2
Q.
WHAT IS A CRA?
3
A. A CRA is an agreement between DesertLink and an Eligible Customer taking 4

transmission service on behalf of a large load. Under its CRA, the Eligible Customer 5

commits to an annual Minimum Transmission Revenue Contribution (“Annual MTRC”) 6

for each Covered Upgrade built to serve the large load, for a fixed twenty-year term 7

beginning on the applicable in-service date, with partial Rate Years prorated as provided 8

in the CRA. The pro forma CRA is set forth in Appendix V of the TO Tariff. The Annual 9

MTRC is calculated solely under the MTRC Calculation Template in Schedule 5 of the 10

CRA and is not an input to, or a calculation made under, the Formula Rate. The terms of 11

the pro forma CRA, including how the Annual MTRC is established, termination, and 12

credit support requirements, are described in the transmittal letter and the testimony of 13

Mr. Hayes.
14
Q.
HOW ARE THE COSTS OF COVERED UPGRADES RECOVERED?
15
A. Each Covered Upgrade placed under the CAISO’s Operational Control is included in 16

DesertLink’s rate base and Base TRR and recovered through the CAISO TAC together 17

with the cost of the Harry Allen to Eldorado Project. The Eligible Customer pays the 18

TAC for the service it takes, like any other transmission customer. The portion of those 19

TAC payments allocable to DesertLink, determined under Schedule 2 of the CRA, counts 20

toward the Eligible Customer’s Annual MTRC as “Qualifying Transmission Revenues.” 21

Under Section 6.2, Qualifying Transmission Revenues also include qualifying wheeling 22

and other wholesale transmission revenues attributable to service to the Large Load 23

Facility, to the extent they reduce transmission revenues otherwise collected from CAISO 24

PDF page 448

7

customers or directly credit DesertLink’s Net Revenue Requirement, without duplicate 1

recognition.
2
Q.
WHAT IS THE SUPPLEMENTAL MTRC?
3
A. The Supplemental MTRC is calculated separately for each Covered Upgrade as the 4

amount, if any, by which the applicable Annual MTRC, prorated for a partial Rate Year, 5

exceeds the Qualifying Transmission Revenues allocated to that upgrade under Section 6

6.4. It ensures that the Eligible Customer pays at least its committed Annual MTRC each 7

year, even if its load develops more slowly than expected. The Supplemental MTRC is 8

never less than zero.
9
Q.
HOW IS THE SUPPLEMENTAL MTRC BILLED AND RECONCILED?
10
A. The Supplemental MTRC follows the same calendar as the Formula Rate. With each 11

Annual Projection, DesertLink forecasts the Eligible Customer’s Qualifying 12

Transmission Revenues and resulting Supplemental MTRC for the Rate Year and 13

invoices that amount, increased or reduced by any prior-period true-up adjustment, to the 14

Eligible Customer in equal monthly installments. In connection with each Annual 15

Update, DesertLink determines the actual Supplemental MTRC using actual Qualifying 16

Transmission Revenues and serves the Eligible Customer a Reconciliation Statement. 17

The difference between the Supplemental MTRC billed for a Rate Year, excluding any 18

prior-period true-up adjustment included in that billing, and the actual Supplemental 19

MTRC for that Rate Year is a prior-period true-up adjustment, which increases or reduces 20

the Supplemental MTRC invoiced following the next Annual Projection. The adjustment 21

is invoiced or refunded separately only if no further Supplemental MTRC will be 22

invoiced. No interest accrues on the Supplemental MTRC or on any prior-period true-up 23

adjustment between DesertLink and the Eligible Customer.
24

PDF page 449

8

Q.
WHAT HAPPENS IF AN ELIGIBLE CUSTOMER DOES NOT PAY OR
1
TERMINATES ITS CRA?
2
A. If an Eligible Customer does not pay, DesertLink may draw on the Eligible Customer’s 3

Operational Security and apply the proceeds to the unpaid amount (“Applied Security 4

Proceeds”). Upon effective termination of the CRA or permanent cessation of service by 5

the Large Load Facility after the applicable in-service date, the Eligible Customer pays a 6

lump-sum Termination Fee equal to the Remaining Cumulative Revenue Responsibility 7

for each in-service Covered Upgrade, less any Supplemental MTRC billed and unpaid as 8

of the effective termination or cessation date. The excluded unpaid amounts remain 9

separately payable and secured; their later payment, satisfaction through Applied Security 10

Proceeds, or direct recovery reduces the Cumulative Revenue Responsibility. Full 11

payment of the Termination Fee discharges only the responsibility included in that fee, as 12

provided in Section 3.3.4. DesertLink will hold the Termination Fee in a separately 13

identified, interest-bearing Termination Fee Account for each Covered Upgrade and 14

credit the balance, including earnings, to transmission customers through the TRBAA in 15

annual amounts equal to the Annual MTRC (“Annual Termination Fee Credits”), for the 16

Rate Years remaining in the applicable MTRC Term, prorated for partial Rate Years, 17

with each year’s credit limited to the available balance and the final year’s credit 18

including any remaining balance, including earnings, so that the account is reduced to 19

zero, subject to the prospective reassignment and release provisions of Section 3.3.4. The 20

uncredited Termination Fee Balance is separately accounted for as a deferred liability and 21

is not itself a TRBAA Credit or Formula Rate input. The Covered Upgrade remains in 22

rate base. The terms governing security and termination are described in the testimony of 23

Mr. Hayes.
24

PDF page 450

9

Q.
WHAT ARE TRBAA CREDITS?
1
A. The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the 2

amounts DesertLink records in the TRBA and credits to transmission customers through 3

the TRBAA: payments of Supplemental MTRC received from or on behalf of the 4

Eligible Customer (“Supplemental MTRC Receipts”), Applied Security Proceeds, Annual 5

Termination Fee Credits, and any credit required to prevent DesertLink from recovering 6

the same cost twice. The projected Supplemental MTRC, increased or reduced by any 7

prior-period true-up adjustment, together with any Annual Termination Fee Credit 8

scheduled for the following year, included in the TRBAA is the “Forecast TRBAA 9

Credit.” Consistent with the CRA, TRBAA Credits are credited solely through the 10

TRBAA and are not inputs to the Formula Rate. Qualifying Transmission Revenues are 11

not TRBAA Credits because they are already reflected in calculating the Supplemental 12

MTRC.
13
Q.
HOW ARE COVERED UPGRADES TREATED FOR PURPOSES OF RETURN
14
ON EQUITY AND COST CONTAINMENT?
15
A. Covered Upgrades will be subject to DesertLink’s Commission-accepted Formula Rate 16

and the return on equity (“ROE”) reflected in the effective Formula Rate. DesertLink’s 17

commitment to limit its ROE to 9.8%, inclusive of incentive ROE adders, was made in 18

connection with the competitive solicitation for the Harry Allen to Eldorado Project. 19

DesertLink is not proposing in this proceeding to extend that project-specific competitive 20

commitment to Covered Upgrades.
21
Covered Upgrade costs will be separately identified on Attachment 1a and reported as 22

“other costs” in the commitment work paper provided under Attachment A to the 23

Formula Rate Implementation Protocols. Those costs will not be subject to the Binding 24

PDF page 451

10

Cost Cap applicable to the Harry Allen to Eldorado Project.
1
DesertLink is not requesting a different ROE or any new incentive ROE adder in this 2

proceeding. DesertLink retains the right, subject to applicable Commission requirements, 3

to seek a different ROE or incentive treatment for Covered Upgrades in a future filing 4

under Section 205 of the Federal Power Act. Unless and until the Commission authorizes 5

different treatment, the ROE and any applicable incentive treatment reflected in the 6

effective Formula Rate will govern.
7
V. CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA
8
Q.
HOW WILL DESERTLINK CREDIT TRBAA CREDITS TO CUSTOMERS?
9
A. Through the TRBAA. Each October, DesertLink will include the Forecast TRBAA 10

Credit for the following calendar year in Cf. Under the CRA, the Forecast TRBAA Credit 11

equals the projected Supplemental MTRC, increased or reduced by any prior-period true- 12

up adjustment, which is the same amount DesertLink will invoice the Eligible Customer, 13

plus any Annual Termination Fee Credit scheduled for that year under Section 3.3.4. The 14

Forecast TRBAA Credit lowers the TRR effective January 1 and, through the TAC, the 15

transmission charges paid by all customers. During the year, the CAISO pays DesertLink 16

the lower TRR, and the Eligible Customer pays the Supplemental MTRC directly to 17

DesertLink. The TRBA records both. For these CRA amounts, a TRBA difference arises 18

when the amounts DesertLink records in the TRBA differ from the corresponding credits 19

reflected in CAISO payments, for example because of late payment or non-payment, the 20

application of security, a termination, or the timing of monthly installments. Any such 21

difference is included in the September 30 TRBA balance and returned to, or recovered 22

from, customers through Cr in the following TRBAA. Amounts later refunded or 23

reversed, and adjustments resulting from the resolution of a dispute under the CRA, are 24

PDF page 452

11

also recorded in the TRBA.
1
Q.
WHY IS THE TRBAA THE APPROPRIATE MECHANISM?
2
A. There are several reasons. First, the TRBAA already exists to credit customers with 3

revenue DesertLink receives outside the TAC, and the Commission and stakeholders 4

review it each year. Second, because the Supplemental MTRC is invoiced on a forecast 5

basis, including the Forecast TRBAA Credit in Cf gives customers the credit in the TRR 6

effective January 1, rather than a year later. Third, the TRBA ensures DesertLink collects 7

no more and no less than its Base TRR, so DesertLink retains none of the TRBAA 8

Credits. Fourth, crediting the revenue through the TRBAA keeps the full cost of each 9

Covered Upgrade in the Base TRR, consistent with the CAISO’s requirement that 10

facilities under its Operational Control be included in the TRR, while the TRBAA shows 11

the credit transparently and separately.
12
Q.
DOES USING THE TRBAA LIMIT THE ABILITY OF CUSTOMERS AND
13
OTHER INTERESTED PARTIES TO REVIEW OR CHALLENGE THESE
14
CREDITS?
15
A. No. DesertLink’s annual TRBAA filing is made under Section 205 of the Federal Power 16

Act. Each filing is noticed by the Commission, is open to intervention, comment, and 17

protest, and is subject to Commission review and acceptance. DesertLink will include in 18

each filing the calculations, work papers, and testimony supporting the TRBAA Credits, 19

so interested parties can review and challenge those amounts in that proceeding. In 20

addition, the inputs to the Formula Rate Template, including the Covered Upgrade plant 21

reported on Attachment 1a and the amounts removed on Attachment 12, Line 17a, are 22

subject to the existing information exchange, review, and challenge procedures of the 23

Formula Rate Implementation Protocols. As a result, every amount affected by the 24

proposal remains subject to review and challenge in one or both of these processes. 25

PDF page 453

12

Q.
WHAT CHANGES TO THE TO TARIFF ARE NEEDED TO IMPLEMENT THIS
1
APPROACH?
2
A. Section 5.5 of the TO Tariff currently provides for the TRBAA to flow Transmission 3

Revenue Credits through to transmission customers. The TO Tariff defines Transmission 4

Revenue Credits as proceeds received from, and charges imposed by, the CAISO, other 5

than proceeds that recover DesertLink’s TRR through the TAC. Because CRA-related 6

credits include amounts received directly from or on behalf of the Eligible Customer and 7

Annual Termination Fee Credits scheduled under Section 3.3.4, DesertLink proposes to 8

revise the definition of the TRBAA and Section 5.5 so that the TRBAA also flows 9

through to transmission customers all amounts a CRA requires to be credited through it. 10

The revisions add amounts recorded in the TRBA under a CRA to Cr, add any forecast 11

credit a CRA requires to Cf, and include amounts recorded in the TRBA under a CRA in 12

the TRBA principal balance used to calculate interest. The revisions also clarify that 13

Section 5.5 does not require the payment of interest between DesertLink and an Eligible 14

Customer, which is governed solely by the CRA. The definition of Transmission 15

Revenue Credits is unchanged.
16
Q.
HOW WILL TRBAA CREDITS BE REFLECTED IN THE ANNUAL TRBAA
17
FILING?
18
A. DesertLink will add the following lines to the TRBA and TRBAA calculation it files each 19

year, as shown in Exhibit No. DLK-205:
20
• Lines 7a through 7d record Supplemental MTRC Receipts, Applied Security 21

Proceeds, Annual Termination Fee Credits, and duplicate-recovery credits and 22

other adjustments, including reversals of amounts later refunded and adjustments 23

resulting from the resolution of disputes under the CRA. Applied Security 24

Proceeds used to pay a Termination Fee are held in the Termination Fee Account 25

PDF page 454

13

and credited through the Annual Termination Fee Credits on Line 7c, rather than 1

on Line 7b. These amounts are included in Net Payment on Line 8; and 2

• Cf on Line 18 is separated into other Transmission Revenue Credits (Line 18a) 3

and the Forecast TRBAA Credit (Line 18b), which equals the projected 4

Supplemental MTRC for the following calendar year, increased or reduced by any 5

prior-period true-up adjustment, plus any Annual Termination Fee Credit 6

scheduled for that year.
7
Because TRBAA Credits are included in Net Payment, any difference between the credit 8

reflected in CAISO payments and the TRBAA Credits recorded becomes part of the 9

TRBA balance and accrues interest in the same manner as other TRBA balances. Absent 10

TRBAA Credits, these lines are zero and the calculation is unchanged. 11

Q.
WHY DO TRBA BALANCES RELATED TO TRBAA CREDITS ACCRUE
12
INTEREST WHILE PRIOR-PERIOD TRUE-UP ADJUSTMENTS DO NOT?
13
A. Interest applies when DesertLink holds funds that belong to transmission customers, or 14

when transmission customers hold funds owed to DesertLink. A TRBA balance created 15

by a late payment, a non-payment before security is applied, or the timing of monthly 16

installments reflects an actual over- or under-recovery by DesertLink, so it accrues 17

interest like any other TRBA balance. A prior-period true-up adjustment is different. 18

When further Supplemental MTRC will be invoiced, the adjustment is added to the 19

Supplemental MTRC invoiced for a later Rate Year and to the Forecast TRBAA Credit 20

for that same Rate Year, so the matched adjustment does not itself create an over- or 21

under-recovery by DesertLink. Differences between the credit reflected in CAISO 22

payments and actual receipts or applied amounts remain subject to TRBA interest. When 23

no further Supplemental MTRC will be invoiced, Section 6.6 instead requires a separate 24

PDF page 455

14

invoice or refund, with the receipt or refund recorded in the TRBA when received or 1

paid. Consistent with Section 6.6 of the CRA and Section 5.5 of the TO Tariff, no interest 2

accrues on a prior-period true-up adjustment between DesertLink and the Eligible 3

Customer; interest on any resulting TRBA balance is calculated separately. 4

Q.
WILL DESERTLINK SUPPORT THESE AMOUNTS IN EACH ANNUAL
5
TRBAA FILING?
6
A. Yes. In each annual TRBAA filing, DesertLink will provide the TRBA and TRBAA 7

calculation substantially in the form of Exhibit No. DLK-205, together with work papers 8

supporting the Forecast TRBAA Credit and the TRBAA Credits recorded during the 9

TRBA year, and its witness will testify to those amounts. As provided in Section 6.8 of 10

the CRA, those work papers may present customer-specific information on an aggregated 11

basis or be submitted with a request for privileged treatment under 18 C.F.R. § 388.112. 12

Q.
ARE ANY CHANGES NEEDED TO APPENDIX I OF THE TO TARIFF?
13
A. No. Appendix I states that DesertLink’s TRR equals its Base TRR plus its TRBAA, and 14

that the TRBAA is computed in accordance with Section 5.5 of the TO Tariff and the 15

CAISO Tariff. TRBAA Credits are included in the TRBAA amount stated in Appendix I 16

each year, so no change to its terms is required.
17
VI. DESERTLINK’S PROPOSED FORMULA RATE TEMPLATE CHANGES
18
Q.
WHY IS ATTACHMENT 1A NEEDED?
19
A. The existing Formula Rate Template calculates the revenue requirement of the Harry 20

Allen to Eldorado Project using total transmission plant. To show the revenue 21

requirement of each Covered Upgrade, the Formula Rate Template must report plant for 22

each project separately. Attachment 1a provides that detail.
23

PDF page 456

15

Q.
PLEASE DESCRIBE ATTACHMENT 1A.
1
A. Attachment 1a has five sections, each with a line for each project. Additional project lines 2

may be added as Covered Upgrades are placed in service.
3
• Section 1 reports monthly transmission gross plant in service and its 13-month 4

average. The total ties to Attachment 4, Line 14, Column (b);
5
• Section 2 reports monthly transmission accumulated depreciation and its 13- 6

month average. The total ties to Attachment 4, Line 14, Column (h);
7
• Sections 3 and 4 report Construction Work in Progress (“CWIP”) and 8

unamortized abandoned plant by project, which tie to Attachment 4; and 9

• Section 5 calculates each project’s net plant (Line 1 – Line 2 + Line 3 + Line 4). 10

The total ties to Appendix III, page 2, Line 14 plus Lines 25 and 27. 11

Because the Attachment 1a totals tie to Attachment 4 and Appendix III, total plant and 12

the total revenue requirement are unchanged.
13
Q.
PLEASE DESCRIBE THE REVISIONS TO ATTACHMENT 1.
14
A. Each project line on Attachment 1 now draws its project name, gross plant including 15

CWIP (Column 3), net plant (Column 6), and depreciation and amortization expense 16

(Column 9) from Attachment 1a. Notes D, E, and F are revised to reference Attachment 17

1a. The allocation factors applied to each project are unchanged, so each project’s 18

revenue requirement reflects its share of total plant, and the project revenue requirements 19

sum to the total revenue requirement on Appendix III.
20
Q.
PLEASE DESCRIBE THE REVISIONS TO ATTACHMENT 12.
21
A. DesertLink proposes a new Line 17a, “Less: Revenue Credits included in the TRBAA,” 22

and revises Line 18 to subtract it. Consistent with Section 6.8 of the CRA, TRBAA 23

Credits are credited solely through the TRBAA and are not Formula Rate revenue credits. 24

PDF page 457

16

Line 17a is a safeguard: to the extent any TRBAA Credits are recorded in the revenue 1

accounts included on Line 15, Line 17a removes them, so they are credited to customers 2

once, through the TRBAA, and not also through the Formula Rate.
3
Q.
ARE THERE OTHER CHANGES TO THE FORMULA RATE TEMPLATE?
4
A. Yes. Attachment 1a has been added to the Table of Contents. There are no other changes. 5

Q.
ARE ANY CHANGES NEEDED TO THE FORMULA RATE
6
IMPLEMENTATION PROTOCOLS?
7
A. No. The Formula Rate Implementation Protocols already require DesertLink to support 8

each input to the Formula Rate Template that is not taken directly from the FERC Form 9

No. 1 and to explain material changes in revenue credits, which will include the amounts 10

on Attachment 12, Line 17a. The existing posting, review, challenge, and true-up 11

procedures apply to Attachment 1a without change. TRBAA Credits are reviewed in 12

DesertLink’s annual TRBAA filing under Section 205 of the Federal Power Act, as I 13

described above.
14
VII. NATIVE AND ILLUSTRATIVE EXHIBITS
15
Q.
PLEASE DESCRIBE EXHIBIT NO. DLK-203.
16
A. Exhibit No. DLK-203 is the revised Formula Rate Template in native Excel format with 17

all formulas and links intact, including new Attachment 1a. It is not populated with 18

DesertLink or customer data. Reviewers can enter values in the input cells and observe 19

the formula mechanics.
20
Q.
PLEASE DESCRIBE EXHIBIT NO. DLK-204.
21
A. Exhibit No. DLK-204 is the revised Formula Rate Template populated with hypothetical 22

data for the 2030 Rate Year to illustrate the treatment of a Covered Upgrade. The 23

example includes the Harry Allen to Eldorado Project and one $60 million Covered 24

PDF page 458

17

Upgrade placed in service January 1, 2030, consistent with the illustrative CRA 1

worksheet sponsored by Mr. Hayes (Exhibit No. DLK-101). In that worksheet, the 2

Covered Upgrade has an Annual MTRC of $7,292,700 and projected Qualifying 3

Transmission Revenues of $3,363,840, for a Supplemental MTRC of $3,928,860. In 4

Exhibit No. DLK-204:
5
• Because the Covered Upgrade is placed in service January 1, 2030, it is not 6

included in the December 2029 plant balance, and its 13-month average gross 7

plant is $55.38 million. The Covered Upgrade’s revenue requirement on 8

Attachment 1 is $7.08 million and the total Base TRR is $23.85 million; 9

• TRBAA Credits of $3,928,860 are assumed to be recorded in a revenue account 10

reported on Attachment 12, Line 14, and are removed on Line 17a, so they do not 11

reduce the Base TRR; without Line 17a, the Base TRR would be $19.92 million 12

and the amounts would be credited twice; and
13
• The Covered Upgrade’s first-year Formula Rate revenue requirement of $7.08 14

million differs from its Annual MTRC of $7.29 million because the two are 15

calculated separately and on different bases. The Annual MTRC is calculated 16

under Schedule 5 of the CRA and, once finalized, is fixed subject to the 17

adjustments expressly permitted by Section 6.3.1. Its levelized calculation uses a 18

twenty-year MTRC Term to recover the allocated capital cost and the return, 19

taxes, and fixed expenses reflected in Schedule 5. The Formula Rate revenue 20

requirement is recalculated each year using 13-month average balances and book 21

depreciation rates, so this January 1 in-service example includes a zero December 22

2029 plant balance in the 13-month average even though the upgrade is in service 23

PDF page 459

18

for all of 2030. All else equal, the capital-related revenue requirement declines as 1

the plant depreciates. The difference does not affect DesertLink’s revenue: the 2

Covered Upgrade is recovered through the Base TRR, and all TRBAA Credits are 3

returned to customers through the TRBAA.
4
The illustrative data are hypothetical and are not DesertLink or customer data. 5

Q.
PLEASE DESCRIBE EXHIBIT NO. DLK-205.
6
A. Exhibit No. DLK-205 illustrates the TRBA and TRBAA calculation for two consecutive 7

TRBA years ending September 30, 2030 and 2031, using the Supplemental MTRC from 8

Exhibit No. DLK-101 and the Base TRR from Exhibit No. DLK-204. For trade months 9

before January 2030, the example uses a Base TRR that excludes the Covered Upgrade; 10

the 2030 Base TRR is then held constant so the TRBA balances shown result only from 11

the TRBAA Credits. Two years are shown because the TRBAA operates on a lag: a 12

credit included in Cf in one filing is compared to actual receipts in the following TRBA 13

year, and any difference is returned in the filing after that.
14
• In the TRBA year ending September 30, 2030, the annual $3,928,860 credit takes 15

effect January 1, 2030, and Supplemental MTRC Receipts replace the reduction 16

in CAISO payments.  Only a small timing difference remains, because the 17

Supplemental MTRC is invoiced in equal monthly installments while CAISO 18

payments reflect the days in each month.  The resulting TRBA balance of $3,883 19

and interest of $202 are returned to customers, and the TRBAA effective January 20

1, 2031 is a credit of $3,932,944.
21
• In the TRBA year ending September 30, 2031, the example assumes two 22

hypothetical events.  First, the 2030 Reconciliation Statement shows that the 23

PDF page 460

19

Eligible Customer was under-billed by $100,000.  Under the CRA, that prior- 1

period true-up adjustment is added to the Supplemental MTRC invoiced for 2032 2

and to the 2032 Forecast TRBAA Credit on Line 18b of $4,028,860, so it does not 3

create a TRBA balance and carries no interest.  Second, the Eligible Customer 4

pays its installment for August 2031 service after September 30.  Together with 5

the remaining timing difference, the late payment produces a TRBA under- 6

collection of $325,636, which is included in Cr with interest of $800 and reverses 7

when the payment is received in the next TRBA year.  The TRBAA effective 8

January 1, 2032 is a credit of $3,702,424.
9
The illustrative data are hypothetical and are not DesertLink or customer data. 10

VIII. CONCLUSION
11
Q.
WHY ARE THE PROPOSED REVISIONS JUST AND REASONABLE?
12
A. The revisions implement the Commission’s direction that large load payments be credited 13

toward transmission owners’ revenue requirements, using DesertLink’s existing TRBAA 14

mechanism. Each Eligible Customer pays at least its committed Annual MTRC for each 15

Covered Upgrade, and TRBAA Credits reduce the TRR paid by all customers through the 16

TAC. DesertLink retains none of the TRBAA Credits, and Attachment 12, Line 17a 17

ensures they are credited only once. The cost of service inputs and methods are 18

unchanged, and Attachment 1a ties to the existing plant totals. The existing Formula Rate 19

review procedures and DesertLink’s annual TRBAA filing provide full transparency for 20

the new calculations.
21
Q.
DOES THIS CONCLUDE YOUR TESTIMONY?
22
A. Yes.

PDF page 461

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

DesertLink, LLC
California Independent System Operator Corporation
)
)
Docket No.
Docket No.
ER27-___-000
EL26-71-___

VERIFICATION

I, D. Eric Arzola, verify under penalty of perjury that I have read the testimony, know the contents thereof, and that the facts and representations set forth therein are true to the best of my knowledge, information, and belief.

/s/ D. Eric Arzola

D. Eric Arzola

Dated: November 16, 2026

PDF page 462

Ex. DLK-201

Formula Rate Template (Clean)

PDF page 463

Projected ATRR
For the 12 months ended
12/31/__
Formula Rate Index
DesertLink, LLC
Table of Contents
Formula Rate Template
Attachments:
Attachment No
Worksheet Name
1
Project Revenue Requirement Worksheet
1a
Project Plant Detail Worksheet
2
Incentive Return
3
Formula Rate True-Up
4
Rate Base Worksheet
5
Return on Rate Base Worksheet
6
Interest on True-Up
6A
True-Up Interest Rate Calculator
7
Weighted Average Federal and State Income Tax Rates
8
Cost of Debt Prior to Issuing Non-Construction Financing
9
True-Up - Construction Financing Cost of Debt
10
Depreciation Rates
11
Prior Period Adjustments
12
Revenue Credit Detail
13
Excess or Deficient Accumulated Deferred Income Taxes - Summary 13.1

Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments 13.2

Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities

PDF page 464

Formula Rate - Non-Levelized
Page 1 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
Projected ATRR
For the 12 months ended
12/31/__
(1) (2)
(3) (4)
(5) Line
Allocated
No.
Source
Amount
1
GROSS REVENUE REQUIREMENT, without incentives (Page 3, Line 49)

 $                               -
REVENUE CREDITS
(Note A)
Total
Allocator (W)
2
Account No. 454
(Page 4, Line 20)
                                                  -
TP
         1.0000
 $                               -
3
Account No. 456.1
(Page 4, Line 21)
                                                  -
TP
         1.0000
 $                               -
4
Revenues from Grandfathered Interzonal Transactions (Note B)

                                                  -
TP
         1.0000
 $                               -
5
Revenues from service provided by the ISO at a discount
                                                  -
TP
         1.0000
 $                               -
6
TOTAL REVENUE CREDITS
(Sum of Lines 2 through 5)
                                                  -
 $                               -
7
Prior Period Adjustments
Attachment 11, Line 18, Col. B
                                                  -
DA
         1.0000
 $                               -
8
True-up Adjustment with Interest
Attachment 3, Line 9, Col. J
                                                  -
DA
         1.0000
 $                               -
9
NET ANNUAL TRANSMISSION REVENUE REQUIREMENT
(Line 1 less Line 6 plus Lines 7 and 8)
 $                               -

PDF page 465

Page 2 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
RATE BASE: (Note R)
Source
Company Total
Allocator (W)
Transmission
GROSS PLANT IN SERVICE
Note C
(Col 3 times Col 4)
1
Production
205.46.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
2
Transmission
Attachment 4, Line 14, Col. (b)
                                                  -
TP
         1.0000
                                  -
3
Distribution
207.75.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
4
General & Intangible
Attachment 4, Line 14, Col. (c)
                                                  -
WS
         1.0000
                                  -
5
TOTAL GROSS PLANT
(Sum of Lines 1 through 4)
                                                  -
GP=
         1.0000
                                  -
6
ACCUMULATED DEPRECIATION
Note C
7
Production
219.20-24.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
8
Transmission
Attachment 4, Line 14, Col. (h)
                                                  -
TP
         1.0000
                                  -
9
Distribution
219.26.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
10
General & Intangible
Attachment 4, Line 14, Col. (i)
                                                  -
WS
         1.0000
                                  -
11
TOTAL ACCUM. DEPRECIATION
(Sum of Lines 7 through 10)
                                                  -
                                  -
12
NET PLANT IN SERVICE
13
Production
(Line 1 - Line 7)
                                              -
                               -
14
Transmission
(Line 2 - Line 8)
                                              -
                               -
15
Distribution
(Line 3 - Line 9)
                                              -
                               -
16
General & Intangible
(Line 4 - Line 10)
                                              -
                               -
17
TOTAL NET PLANT
( Sum of Lines 13 through 16)
                                              -
NP=
         1.0000
                               -
18
ADJUSTMENTS TO RATE BASE
19
Account No. 281 (enter negative)
Attachment 4, Line 28, Col. (d) (Note D)
                                              -
N/A
                 -
                               -
20
Account No. 282 (enter negative)
Attachment 4, Line 28, Col. (e) (Note D)
                                              -
NP
         1.0000
                               -
21
Account No. 283 (enter negative)
Attachment 4, Line 28, Col. (f) (Note D)
                                              -
NP
         1.0000
                               -
22
Account No. 190
Attachment 4, Line 28, Col. (g) (Note D)
                                              -
NP
         1.0000
                               -
22a
Deficient or (Excess) Accumulated Deferred Income Taxes Attachment 13, Line 7 (Note X)

                                                  -
NP
         1.0000
                               -
23
Account No. 255 (enter negative)
Attachment 4, Line 28, Col. (h) (Note D)
                                              -
NP
         1.0000
                               -
24
Unfunded Reserves (enter negative)
Attachment 4, Line 43, Col. (h)
                                              -
DA
         1.0000
                               -
25
CWIP
Attachment 4, Line 14, Col. (d)
                                              -
DA
         1.0000
                               -
26
Unamortized Regulatory Asset
Attachment 4, Line 28, Col. (b) (Note E)
                                              -
DA
         1.0000
                               -
27
Unamortized Abandoned Plant
Attachment 4, Line 28, Col. (c) (Note F)
                                              -
DA
         1.0000
                               -
28
TOTAL ADJUSTMENTS
( Sum of Lines 19 through 27)
                                              -
                                  -
29
LAND HELD FOR FUTURE USE
Attachment 4, Line 14, Col. (e) (Note G)
                                              -
TP
         1.0000
                               -
30
WORKING CAPITAL
Note H
31
Cash Working Capital
1/8*(Page 3, Line 17 minus Page 3, Line 14)
                                              -
                               -
32
Materials & Supplies
Attachment 4, Line 14, Col. (f)
                                              -
TP
         1.0000
                               -
33
Prepayments (Account 165)
Attachment 4, Line 14, Col. (g)
                                              -
GP
         1.0000
                               -
34
TOTAL WORKING CAPITAL
( Sum of Lines 31 through 33)
                                              -
                                  -
35
RATE BASE
( Sum of Lines 17, 28, 29, and 34)
                                              -
                                  -
Formula Rate - Non-Levelized

PDF page 466

Page 3 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
Source
Company Total
Allocator (W)
Transmission
O&M
(Col 3 times Col 4)
1
Transmission
321.112.b
                                                  -
TP
         1.0000
                                  -
2
Less Account 566 (Misc Trans Expense)
321.97.b
                                                  -
TP
         1.0000
                                  -
3
Less Account 565
321.96.b
                                                  -
TP
         1.0000
                                  -
4
A&G
323.197.b
                                                  -
WS
         1.0000
                                  -
5
Less FERC Annual Fees
351.h (Note I)
                                                  -
WS
         1.0000
                                  -
6
Less EPRI Dues
Note J
                                                  -
WS
         1.0000
                                  -
7
Less Reg. Commission Expense Account 928
Note J
                                                  -
WS
         1.0000
                                  -
8
Less: Non-safety Advertising account 930.1
Note J
                                                  -
WS
         1.0000
                                  -
9
10
Plus Transmission Related Reg. Comm. Exp.
Note K
                                                  -
TP
         1.0000
                                  -
11
12
Plus Transmission Lease Payments in Acct 565 Note V

                                                  -
DA
         1.0000
                                  -
13
Account 566
14
Amortization of Regulatory Asset
Note E
                                                  -
DA
         1.0000
                                  -
15
Misc. Transmission Expense (less amort. of regulatory asset) 321.97.b less line 14

                                                  -
TP
         1.0000
                                  -
16
Total Account 566
(Sum of Lines 14 through 15) Ties to 321.97b
                                                  -
                                  -
17
TOTAL O&M
                                                  -
                                  -
18
DEPRECIATION EXPENSE
Note C
19
Transmission
336.7.b&d
                                                  -
TP
         1.0000
                                  -
20
General & Intangible
336.10.b&d, 336.1.b&d
                                                  -
WS
         1.0000
                                  -
21
Amortization of Abandoned Plant
Note F
                                                  -
DA
         1.0000
                                  -
22
TOTAL DEPRECIATION
(Sum of Lines 19 through 21)
                                                  -
                                  -
23
TAXES OTHER THAN INCOME TAXES   (Note M)
24
LABOR RELATED
25
Payroll
263.i
                                                  -
WS
         1.0000
                                  -
26
263.i
                                                  -
WS
         1.0000
                                  -
27
PLANT RELATED
28
Property
263.i
                                                  -
GP
         1.0000
                                  -
29
Gross Receipts
263.i
                                                  -
N/A

                                  -
30
Other
263.i
                                                  -
GP
         1.0000
                                  -
31
Payments in lieu of taxes
263.i
                                                  -
GP
         1.0000
                                  -
32
TOTAL OTHER TAXES
( Sum of Lines 25 through 31)
                                                  -
                                  -
33
INCOME TAXES    (Note N)
Note N
34
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} 0.00%

35
CIT=(T/1-T) * (1-(WCLTD/R)) =
WCLTD = Page 4, Line 15, R = Page 4, Line 18 0.00%

36
FIT & SIT & P
37
38
1 / (1 - T)  = (from line 35)
1 / (1 - T), T from Line 35
                                         1.0000
39
Amortized Investment Tax Credit
266.8f (enter negative) (Note D)
                                                  -
40
Deficient or (Excess) Deferred Income Taxes Attachment 13, Line 12, Col. (d) (Note X)

                                                  -
41
Tax Effect of Permanent Differences
Note O
                                                  -
42
Income Tax Calculation
(Line 35 times Line 48)
                                                  -
N/A
                                  -
43
ITC adjustment
(Line 38 times Line 39)
                                                  -
NP
         1.0000
                                  -
44
Deficient or (Excess) Deferred Income Tax Adjustment Attachment 13, Line 12, Col. (f) (Note X)

                                                  -
NP
         1.0000
                                  -
45
Permanent Differences Tax Adjustment
(Line 38 times Line 41)
                                                  -
NP
         1.0000
                                  -
46
Total Income Taxes
(Sum of Lines 42 through 45)
                                                  -
                                  -
47
RETURN
48
Rate Base times Return
(Page 2, Line 35 times Page 4, Line 18)
                                                  -
N/A
                 -
                                  -
49
GROSS REVENUE REQUIREMENT
( Sum of Lines  17, 22, 32, 46, and 48)
                                                  -
                                  -
(Sum of Lines 1, 4, 10, 12, and 16 less Sum of Lines 2, 3, and 5 through 8)

Highway and vehicle

PDF page 467

Formula Rate - Non-Levelized
Page 4 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
SUPPORTING CALCULATIONS AND NOTES
TRANSMISSION PLANT INCLUDED IN ISO RATES
1
Total Transmission plant
(Page 2, Line 2, Col. 3)
                                  -
2
(Note P)
                                  -
3
(Note S)
                                  -
4
Transmission plant included in ISO rates
(Line 1 minus Lines 2 and 3)
                                  -
5
Percentage of Transmission plant included in ISO Rates (Line 4 divided by Line 1)

TP =                               1.00
6
WAGES & SALARY ALLOCATOR (W&S)
Form 1 Reference
$
TP
Allocation
7
Production
354.20.b
                                                  -
            -                    -
8
Transmission
354.21.b
                                                  -
        1.00                  -
9
Distribution
354.23.b
                                                  -
            -                    -
W&S Allocator
10
Other
354.24,25,26.b
                                                  -
            -                    -
($ / Allocation)
11
Total (W&S Allocator is 1 if lines 7-10 are zero) (Sum of Lines 7 through 10)

                                                  -
                 -
=
                        1.00000  = WS
12
RETURN (R)
13
14
$
%
Cost
Weighted
15
Long Term Debt
Attachment 5, Line 8 (Notes Q & R)
                                                  -
50.0%
0.00%
0.00% = WCLTD
16
Preferred Stock (112.3.c)
Attachment 5, Line 9 (Notes Q & R)
                                                  -
0.0%
0.00%
0.00%
17
Common Stock
Attachment 5, Line 10 (Notes Q, R, and T)
                                                  -
50.0%
9.80%
4.90%
18
Total
( Sum of Lines 15 through 17)
                                                  -
4.90% = R
19
REVENUE CREDITS
$
20
Attachment 12, Line 8, Col. C (Note U)
                                  -
21
ACCOUNT 456.1 (OTHER ELECTRIC REVENUES)
Attachment 12, Line 18, Col. C (Note A)
                                  -
Less Transmission plant excluded from ISO rates Less Transmission plant included in OATT Ancillary Service rates

ACCOUNT 454 (RENT FROM ELECTRIC

PDF page 468

Formula Rate - Non-Levelized
Page 5 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
General Note: References to pages in this formula rate template are indicated as: (Page #, Line #, Col. #)
References to data from FERC Form 1 are indicated as: #.y.x (page, line, column)
Notes
A
B
Company will not have any grandfathered agreements. Therefore, this line shall remain zero.
C
Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
D
E
F
Unamortized Abandoned Plant and Amortization of Abandoned Plant will be zero until the Commission accepts or approves recovery of the cost of Abandoned Plant. Utility must submit a Section 205 filing to recover the cost of abandoned plant. G

Identified in FERC Form 1, or Company records if not so indicated on the FERC Form 1, as being transmission related.
H
I
J
Page 3, Line 6 - Subtract all EPRI Annual Membership Dues listed in Form 1 at 353.f, all Regulatory Commission Expenses in account 928 itemized at 351.h, and non-safety related advertising included in Account 930.1. K

Page 3, Line 8-Add back Regulatory Commission Expenses directly related to transmission service, ISO filings, or transmission siting itemized at 351.h.
M
N
Inputs Required:
FIT =
0.0%
(Weighted Average Federal Income Tax Rate (Attachment 7, line 4, col. (i))
SIT =
0.0%
(Weighted Average State Income Tax Rate (Attachment 7, line 8, col. (i))
p =
0.0%
(Percent of federal income tax deductible for state purposes)
O
P
Removes transmission plant determined by Commission order to be state-jurisdictional according to the seven-factor test (until Form 1 balances are adjusted to reflect application of seven-factor test).
Q
R
S
T
The rate of return on common equity ("ROE") will be supported in the original Section 205 filing and shall, at no time during the life of the Project, be higher than 9.8%, including adders.  No change in ROE may be made absent a filing with FERC. U

Includes only income related to transmission facilities, such as pole attachments, rentals and special use from general ledger.
V
Add back any lease expense of transmission assets used to provide service under this tariff included in account 565. Amount to be obtained from company books and records.
W
DA = Direct Assignment; GP = Gross Plant Allocator (page 2, line 5); N/A = Not Applicable; NP = Net Plant Allocator (page 2, line 17); TP = Transmission Plant Allocator (page 4, line 5); WS = Wage and Salary Allocator (page 4, line 11). X

The revenues credited on page 1, lines 2-6, shall include only the amounts received by DesertLink for service rendered using facilities for which recovery is provided under this tariff. They do not include revenues associated with FERC annual charges, gross receipts taxes, or facilities not included in this template (e.g., direct assignment facilities and GSUs) which are not recovered under this Rate Formula Template.

Accumulated deferred income tax amounts associated with asset or liability accounts excluded from rate base (such as ADIT related to asset retirement obligations and certain tax-related regulatory assets or liabilities) do not affect rate base.  Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income. Account 281 is not allocated to Transmission.

Recovery of Regulatory Asset permitted only for pre-commercial and formation expenses as authorized by the Commission. Recovery of any other regulatory assets requires authorization from the Commission. A carrying charge equal to the AFUDC rate will be applied to the Regulatory Asset prior to the rate year when costs are first recovered.

Cash Working Capital assigned to transmission is one-eighth of O&M allocated to transmission at page 3, line 17, column 5 minus amortization of Regulatory Asset at page 3, line 14, column 5.  Prepayments are the electric related prepayments booked to Account No. 165 and reported on page 111, line 57 in the Form 1.

The FERC's annual charges for the year assessed the Transmission Owner for service under this tariff.  To the extent the charges are separately identified on the FERC Form 1, page 350, column 1, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 350 will be obtained from Company books and records.

Includes only FICA, unemployment, highway, property, gross receipts, and other assessments charged in the current year.  Taxes related to income are excluded.  Enter the line number on page 262-63 upon which each item is identified.  To the extent individual types of taxes are separately identified on the FERC Form 1, page 262, column a, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 262-63 will be obtained from Company books and records.

FIT is the weighted average Federal income tax rate and SIT is the weighted average State income tax rate, both from Attachment 7, and p is the "the percentage of federal income tax deductible for state income taxes". A utility that elected to utilize amortization of tax credits against taxable income, rather than book tax credits to Account No. 255 and reduce rate base, must reduce its income tax expense by the amount of the Amortized Investment Tax Credit (Form 1, 266.8.f) multiplied by (1/1-T) (page 3, line 26). Excess Deferred Income Taxes reduce income tax expense by the amount of the expense multiplied by (1/(1-T)).

The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Tax Effect equals Permanent Differences multiplied by T.

The cost of debt will be determined based on the financing in place during each stage of project development. Before debt is obtained, a proxy interest rate which will be supported in the original Section 205 filing will be used. This rate is provided on Attachment 8 line 36. If construction debt (wherein principal is drawn down over time) is issued, the rate plus an amortization of fees projected to be incurred on the construction debt during the rate year will be the cost of debt. This construction debt rate (inclusive of fees) will be reset and trued-up every year using the method on Attachment 9 for multi-year construction projects. Once non-construction debt is obtained, the actual interest rate and fees on the debt in place at the end of the year such non- construction debt is obtained will become the cost of debt. In the first full year after non-construction debt is obtained, the cost of debt will be the actual cost of debt determined using the method on Attachment 5. A h

h i
l
i l
f 50% E
i
d 50% d b
ill b
d
il h fi
i i
i
l
d i
i
il
h
i
h
i
d b
h C
i i
Af
h f
ili i
l
d i
i
h l
f
50%
i
h
h i
l
Calculate rate base using 13 month average balance, except ADIT.  The calculation of ADIT in the annual true-up calculation will use the beginning-of-year and end-of-year balances, and will be performed in accordance with IRS regulation Section 1.167(l)- 1(h)(6).  The calculation of ADIT in the annual projection will be performed in accordance with IRS Regulation Section 1.167(l)-1(h)(6).

Removes dollar amount of transmission plant to be included in the development of OATT ancillary services rates and generation step-up facilities, which are deemed to be included in OATT ancillary services. For these purposes, generation step-up facilities are those facilities at a generator substation on which there is no through-flow when the generator is shut down.

Upon enactment of changes in tax law, ADIT balances are re-measured and adjusted in the Company’s books of account, resulting in excess or deficient accumulated deferred income tax assets and liabilities.  Excess or deficient ADIT attributable to timing differences between the amounts of expenses or revenues recognized for income tax purposes and amounts of expenses or revenues recognized for ratemaking purposes as well as subsequent recoverable or refundable amortization of such amounts will be based upon Company records and be calculated and recorded in accordance with ASC 740 and any applicable normalization requirements of the taxing jurisdiction.  The Deficient or (Excess) Deferred Income Tax Adjustment (page 3, line 44) is computed by multiplying each component of Deficient or (Excess) Deferred Income Taxes (page 3, line 40) by the applicable tax gross-up factor.  For each re-measurement of ADIT, the amounts entered as the Deficient or (Excess) Accumulated Deferred Income Taxes component of ADJUSTMENTS TO RATE BASE (page 2, line 22a) or as the Deficient or (Excess) Deferred Income Tax Adjustment component of INCOME TAXES (page 3, line 44) will be supported by Attachment 13 (Deficient or Excess Accumulated Deferred Income Taxes) providing the balance for each taxing jurisdiction at the beginning and end of the year, amortization for the year, calculation of the gross-up to the revenue requirement level and any other information required to support compliance with any applicable normalization requirements.

PDF page 469

Page 1 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
To be completed in conjunction with Appendix III. Line

(1) (2)
(3) (4)
No.
Appendix III, Page, Line, Col.
Transmission
Allocator
1
Gross Transmission Plant plus CWIP
Appendix III, p 2, line 2, col 5 plus line 25, col 5 (Note A)
                                                         -
2
Net Transmission Plant plus CWIP and Abandoned Plant Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5 (Note B)

                                                         -
O&M EXPENSE
3
Total O&M Allocated to Transmission
Appendix III, p 3, line 17, col 5
                                                         -
4
Annual Allocation Factor for O&M
(line 3 divided by line 1, col 3)
0.00%
0.00%
GENERAL AND INTANGIBLE (G&I) DEPRECIATION EXPENSE 5

Total G&I Depreciation Expense
Appendix III, p 3, line 20, col 5 (Note C)
                                                         -
6
Annual Allocation Factor for G&I Depreciation Expense (line 5 divided by line 1, col 3)

0.00%
0.00%
TAXES OTHER THAN INCOME TAXES
7
Total Other Taxes
Appendix III, p 3, line 32, col 5
                                                         -
8
Annual Allocation Factor for Other Taxes
(line 7 divided by line 1, col 3)
0.00%
0.00%
9
Less Revenue Credits
Appendix III, p 1, line 6 col 5
                                                         -
10
Annual Allocation Factor for Revenue Credits (line 9 divided by line 1, col 3)

0.00%
0.00%
11
Annual Allocation Factor for Expense
Sum of lines 4, 6, 8, and 10
0.00%
INCOME TAXES
12
Total Income Taxes
Appendix III, p 3, line 46, col 5
                                                         -
13
Annual Allocation Factor for Income Taxes
(line 12 divided by line 2, col 3)
0.00%
0.00%
RETURN
14
Return on Rate Base
Appendix III, p 3, line 48, col 5
                                                         -
15
Annual Allocation Factor for Return on Rate Base (line 14 divided by line 2, col 3)

0.00%
0.00%
16
Annual Allocation Factor for Return
Sum of lines 13 and 15
0.00%

PDF page 470

Page 2 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template.
(1) (2)
(3) (4)
(5) (6)
(7) (8)
Project Name
CAISO Category
Identifier
Project Gross Plant
Project Net Plant
Annual Return Charge
(Note D)
(Page 1, line 11)
(Col. 3 * Col. 4)
(Note E)
(Page 1, line 16)
(Col. 6 * Col. 7)
1a
Project A
AAAA
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
1b
Project B
BBBB
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
2
Total Schedule 12
                                                  -
                       -    $                                                      -
                                        -
3a
Project C
CCCC
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
3b
Project D
DDDD
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
4
Total Zonal
                                                  -
                       -    $                                                      -
                                        -
5
Other
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                        -
6
Annual Totals
                                                  -
                       -    $                                                      -
                                        -
This worksheet is used to compute project specific revenue requirements for any projects for which such calculation is required by CAISO. Other projects which comprise the remaining revenue requirement on Appendix III will not be entered on this schedule.

Line
No.
Annual Allocation
Factor for Expense
Annual
Expense
Charge
Annual
Allocation
Factor for
Return

PDF page 471

Page 3 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
(9) (10)
(11) (12)
(12a) (13)
(14) (15)
(16) Incentive Return
Ceiling Rate
(Note F)
(Sum Col. 5, 8 & 9)
(Note G)
(Sum Col. 10 & 12)
(Note H)
(Sum Col. 10 & 12 Less Col. 13)
(Note I)
(Sum Col. 14 & 15)
1a
                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
1b
                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
2
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                           - 3a

                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
3b
                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
4
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                           - 5

                                         -                             -
                              -                                              -
                             -                          -                                                            -                          -                                           -
6
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                           - Notes

A
Gross Transmission Plant is that identified on page 2 line 2 of Appendix III inclusive of any CWIP or unamortized abandoned plant included in rate base when authorized by FERC order. B

Net Plant is that identified on page 2 line 14 of Appendix III inclusive of any CWIP or unamortized Abandoned Plant included in rate base when authorized by FERC order less any prefunded AFUDC, if applicable. C

D
E
Project Net Plant is the Project Gross Plant Identified in Column 3 less the associated Accumulated Depreciation plus CWIP in rate base if applicable and Unamortized Abandoned Plant.  Refer to Attachment 1a for detail. F

G
Requires approval by FERC of incentive return applicable to the specified project(s).
H
I
True-Up Adjustment is calculated on the Project True-up Schedule for the relevant true-up year.
Line
No.
Project
Depreciation/Amortizatio
n Expense
Annual Revenue
Requirement
Incentive Return in
Basis Points
Competitive
Concession
Total Annual Revenue
Requirement
True-Up
Adjustment
Net Revenue
Requirement
(Attachment 2, Line 28 Incentive
Return * Col. 6 * Col. 11/100)
General and Intangible Depreciation and Amortization Expense includes all expenses (except depreciation and armortization of G&I Asset Retirement Obligations) not directly associated with a project, which is entered on page 3 , column 9.

Project Gross Plant is the total capital investment including CWIP for the project calculated from Company books and records in the same method as the gross plant value in line 1.  This value includes subsequent capital investments required to maintain the facilities to their original capabilities.  Refer to Attachment 1a for detail.

Project Depreciation Expense is the actual value booked for the project (excluding General and Intangible depreciation) at Appendix III, page 3, line 19, plus amortization of Abandoned Plant at Appendix III, page 3, line 21.  For each project on Attachment 1a, Depreciation Expense is Attachment 1a, Line 2, Column (15) minus Column (3), and Amortization of Abandoned Plant is the difference between Columns (3) and (15) on Attachment 1a, Line 4. The Competitive Concession is the reduction in revenue, if any, that the company agreed to, for instance, to be selected to build facilities as the result of a competitive process and equals the amount by which the  annual revenue requirement is reduced from the ceiling rate.

PDF page 472

Att 1a - Project Plant Detail
 Page 10
Page 1 of 1
For the twelve months ended 12/31/__
Attachment 1a
Project Plant Detail Worksheet
DesertLink, LLC
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
1a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1

Total Project Transmission Gross Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
2a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2

Total Project Transmission Accumulated Depreciation
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
3a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3

Total Project CWIP
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
4a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4

Total Project Unamortized Abandoned Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
Project Name
5a
Project A
                                                                -
5b
Project B
                                                                -
…
…
 …
5
Total Project Transmission Net Plant
                                                                -   Ties to Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5; Used on Attachment 1, Column (6)
Line
No.
Project
Transmission
Gross Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission Accumulated
Depreciation
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project CWIP
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Unamortized Abandoned Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission
Net Plant
13-month average
(Line 1 - Line 2 + Line 3 + Line 4)

PDF page 473

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 2
Incentive Return
DesertLink, LLC
Line
1
Rate Base
Appendix III, Page 2, Line 35, Col.5
                                                                         -
2
100 Basis Point Incentive Return
$
Cost
$
%
Weighted
3
Long Term Debt
(Notes Q & R from Appendix III)
                            -
50.00%
0.00%
0.00%
4
Preferred Stock
(Notes Q & R from Appendix III)
                            -
0.00%
0.00%
0.00%
5
Common Stock
(Notes Q, R, & T from Appendix III)
                            -
50.00%
10.80%
5.40%
6
Total (sum lines 3-5)
                            -
5.40%
7
100 Basis Point Incentive Return multiplied by Rate Base (line 1 * line 6)
                                                                         -
8
INCOME TAXES
9
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =
0.00%
10
CIT=(T/1-T) * (1-(WCLTD/R)) =
0.00%
11
WCLTD
Line 3
0.00%
12
FIT, SIT & p are as given in Appendix III footnote N.
13
1 / (1 - T)
Line 9
                    1.0000
14
Amortized Investment Tax Credit (266.8f) (enter negative)
Appendix III, Page 3, Line 39
                            -
15
Deficient or (Excess) Deferred Income Taxes
Appendix III, Page 3, Line 40
                            -
16
Tax Effect of Permanent Differences (Note B)
Appendix III, Page 3, Line 41
                            -
17
Income Tax Calculation
Line 7 times Line 10
                        -
18
ITC adjustment
Line 13 times Line 14
                            -
NP             1.00                         -
19
Deficient or (Excess) Deferred Income Tax Adjustment
Appendix III, Page 3, Line 44
                            -
NP             1.00                         -
20
Permanent Differences Tax Adjustment
Line 13 times Line 16
                            -
NP             1.00                         -
21
Total Income Taxes
Sum of Lines 17 through 20
                            -
                        -                                                                            - 22

Return and Income Taxes with 100 basis point increase in ROE
                                                                         -
23
Return
(Appendix III, page 3, line 48, col 5)
                                                                         -
24
Income Tax
(Appendix III, page 3, line 46, col 5)
                                                                         -
25
Return and Income Taxes without 100 basis point increase in ROE Sum of Lines 23 and 24

                                                                         -
26
Incremental Return and Income Taxes for 100 basis point increase in ROE Line 22 less Line 25

                                                                         -
27
Rate Base
Line 1
                                                                         -
28
Incremental Return and Income Taxes for 100 basis point increase in ROE divided by Rate Base Line 26 divided by Line 27 0.00%

Notes
A
B
The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Cost = Appendix III, Page 4, Line 17,

plus 100 bp
The 100 basis point increase in ROE is used only to determine the increase in return and income taxes associated with a 100 basis point increase in ROE and does not reflect what incentives the Commission may approve for a specific transmission project. The overall ROE inclusive of incentives is subject to the limitations noted in Appendix III, Note T.  Any ROE actual incentive must be approved by the Commission.

PDF page 474

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 3
Formula Rate True-Up
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template. Annual True-Up Calculation

Line
1
True-Up Year
2
C
D
                             -
F
G
H
I
J
A
B
E
Project Name
3
Remaining Appendix III
0.0%
                             -
                               -    $                          -
                             -
4a
Project A
AAAA
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
4b
Project B
BBBB
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
5 Total Schedule 12
                             -
                             -                                  -                                  -    $                          -                                -                                -
6a
Project C
CCCC
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
6b
Project D
DDDD
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
7
Total Zonal
                             -
                             -                                  -                                  -    $                          -                                -                                -
8
Other
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
9
                             -
0.0%
                             -                                  -                                  -                                -                                -                                -
10
 $                          -   Total Interest on True-Up - Attachment 6
Prior Period Adjustment
A
B
Source
11
Description of Adjustment
                 -
Notes
1) The revenue received is the total amount of revenue distributed to company in the  year as shown on pages 328-330 of the Form No 1. The Revenue Received is input on line 2, Col. E.
2) From the Attachment 1, lines 1a through 6, col. 16 from the template in which the true-up year revenue requirement was initially projected.
3) From True-Up revenue requirement template Attachment 1, lines 1a through 6, col. 14.
4) 5)
Corrections to true-ups for previous rate years including interest will be computed on Attachment 11 and entered on the appropriate line 3-8 above.
This Attachment 3 is used to calculate the annual formula rate true-up. Any projects for which the RTO requires a true-up on an individual project basis, as shown on Attachment 1, will be computed separately. The remainder of the revenue requirement will also be trued up. The utility will individually enter the projected true-up year revenue requirements in Column C. A percentage of total will be calculated in Column D. Actual revenue received during the true-up year is entered into Column E, line 2 and allocated using the Column D percentage. The utility will prepare this formula rate template with the actual inputs for the true-up year, with the resulting revenue requirement for each line being separately entered in Column F.  In Col. G, Col. F is subtracted from Col. E to calculate the true-up adjustment. Interest on the true-up is computed in Column H. Any adjustments to prior period true-ups are entered in Col.

I.  Col. J computes the total true-up as the sum of Col. G, H and I.
Projected True-Up Year Revenue
Requirement Calculation
True-Up Year
Revenue Received1
Actual True-Up
Year Revenue Req.
CAISO
Identification
Project # Or
Other
Identifier
Net Revenue
Requirement2
% of Total
Revenue
Requirement
Allocation of
Revenue Received

                    (E, Line
2) x (D)
True-Up Net Revenue
Requirement3
Net Under/(Over)
Collection   (F)-(E)
True-Up Interest
Income (Expense)4
(D) x (H, line 10)
Prior Period
Adjustment with
Interest5
Total True-Up
(G) + (H) + (I)
Total Annual Revenue
Requirements
Prior Period Adjustment
(Note 5)
Adjustment
Amount
Attachment
11
Interest due on the true up is calculated for the 24 month period from the start of the true-up year until the end of the year following the true-up year when the true up will be included in rates. Total True up Interest calculate on Attachment 6 and allocated to projects based on the percentage in Column D.

PDF page 475

Page 1 of 2
For the twelve months ended 12/31/__
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Gross Plant in Service
CWIP
LHFFU
Working Capital
Accumulated Depreciation
Month
Transmission
CWIP in Rate Base
Held for Future Use
Materials & Supplies
Prepayments
Transmission
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (Note A)
1
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 2

January
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 3

February
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 4

March
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 5

April
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 6

May
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 7

June
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 8

July
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 9

August
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 10

September
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 11

October
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 12

November
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 13

December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 14

                             -                                -                                  -                                       -                                      -                                      -                                    -                                    - Adjustments to Rate Base

Month
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(Note A)
Note C
Note D
272.8.b & 273.8.k
274.2.b & 275.2.k
276.9.b & 277.9.k
234.8.b & c
15
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 16

January
                   -                                -                                -
                                 -
17
February
                   -                                -                                -
                                 -
18
March
                   -                                -                                -
                                 -
19
April
                   -                                -                                -
                                 -
20
May
                   -                                -                                -
                                 -
21
June
                   -                                -                                -
                                 -
22
July
                   -                                -                                -
                                 -
23
August
                   -                                -                                -
                                 -
24
September
                   -                                -                                -
                                 -
25
October
                   -                                -                                -
                                 -
26
November
                   -                                -                                -
                                 -
27
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 28

                             -                                -                                  -                                       -                                      -                                      -                                    -
Line
No
General &
Intangible
General & Intangible
207.58.g less
207.57.g for end of
year, records for
other months
205.5.g & 207.99.g
less 207.98.g for
end of year, records
for other months
Note B - page 2,
column C
214.47.d for end of
year, records for other
months
227.8.c & 227.16.c for
end of year, records for
other months
111.57.c for end of
year, records for other
months
219.25.c less ARO for
end of year, records
for other months
219.28.c & 200.21.c
less ARO for end of
year, records for other
months
Average of the 13
Monthly Balances
Unamortized
Regulatory Asset
Unamortized
Abandoned Plant
Account No. 281
Accumulated
Deferred Income
Taxes (Note E)
Account No. 282
Accumulated Deferred
Income Taxes (Note E)
Account No. 283
Accumulated Deferred
Income Taxes (Note E)
Account No. 190
Accumulated
Deferred Income
Taxes (Note E)
Account No. 255
Accumulated
Deferred Investment
Credit (Note I)
Consistent with
266.8.b & 267.8.h
Average of the 13
Monthly Balances

PDF page 476

Page 2 of 2
For the twelve months ended 12/31/
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Total CWIP
(a) (b)
(c) = (a) - (b)
Company records
29
December
                   -                                -                                -                                  -
30
January
                   -                                -                                -                                  -
31
February
                   -                                -                                -                                  -
32
March
                   -                                -                                -                                  -
33
April
                   -                                -                                -                                  -
34
May
                   -                                -                                -                                  -
35
June
                   -                                -                                -                                  -
36
July
                   -                                -                                -                                  -
37
August
                   -                                -                                -                                  -
38
September
                   -                                -                                -                                  -
39
October
                   -                                -                                -                                  -
40
November
                   -                                -                                -                                  -
41
December
                   -                                -                                -                                  -
                             -                                -                                  -
Unfunded Reserves   (Notes A and F and G)
(a) (b)
(b.i)
(b.ii)
(c) (d)
(e) (f)
(g) (h)
List of all reserves
Amount
42a
Reserve 1
 -
 -
                               -
 -
 -
 -
                                 -                                    -
42b
Reserve 2
 -
 -
                               -
 -
 -
 -
                                 -                                    -
43
Total
                               -
                                 -
Notes:
A
Calculate using 13 month average balance, except ADIT which is calculated based on the average of the beginning of the year and the end of the year balances
B
C
D
Recovery of abandoned plant is limited to any abandoned plant recovery authorized by FERC.
E
ADIT is computed using the average of the beginning of the year and the end of the year balances. Electric ADIT only, Excludes ARO-related ADIT.
F
G
H
I
Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income.
Reconciliation of CWIP in Rate Base to FERC Form 1 - Note B
Less: CWIP and
AFUDC Excluded
from Rate Base
CWIP allowed in
Rate Base
216.b for end of
year, records for
other months
Average of the 13
Monthly Balances
FERC balance sheet
account where
reserves are
recorded
FERC income
statement account
where expenses are
recorded
Enter 1 if NOT in a
trust or reserved
account, enter zero (0)
if included in a trust or
reserved account
Enter 1 if the accrual
account is included in
the formula rate, enter
(0) if the accrual
account is NOT
included in the formula
rate
Enter the percentage
paid for by customers
less the percent
associated with an
offsetting liability on
the balance sheet (Note
H) Allocation (Plant or
Labor Allocator)
Amount Allocated,
col. c x col. d x col. e
x col. f x col. g
Recovery of CWIP in rate base must be approved by FERC.  Lines 29-41 of page 2 provide a reconciliation of the Company's total CWIP to the CWIP allowed in rate base. The annual report filed pursuant to the Protocols will include for each project under construction (i) the CWIP balance eligible for inclusion in rate base; (ii) the CWIP balance ineligible for inclusion in rate base; and (iii) a demonstration that AFUDC is only applied to the CWIP balance that is not included in rate base The annual report will also describe the reconciliation prepared on this Attachment

Recovery of a Regulatory Asset is permitted only for pre-commercial and formation expenses, and is subject to FERC approval before the amortization of the Regulatory Asset can be included in rates. Recovery of any other regulatory assets requires authorization from the Commission.

The Formula Rate shall include a credit to rate base for all unfunded reserves (funds collected from customers that (1) have not been set aside in a trust, escrow or restricted account; (2) whose balance are collected from customers through cost accruals to accounts that are recovered under the Formula Rate; and (3) exclude the portion of any balance offset by a balance sheet ac count (see Note H)).  Each unfunded reserve will be included on lines 42 above. The allocator in Col. (g) will be the same allocator used in the formula for the cost accruals to the account that is recovered under the Formula Rate.  Since reserves can be created by creating an offsetting balance sheet account, rather than through cost accruals, the amount to be deducted from rate base should exclude the portion offset by another balance sheet account. Not all unfunded reserves are created only from contributions from customers. Many are created by creating an offsetting liability in whole or in part.  Column (f) ensures only the portion of the unfunded reserve contributed by the customer (and not created by an offsetting liability) is a reduction to rate base.

The inputs in Column (f) are the percentage of the unfunded reserve that was created by an offsetting liability. The percentage shown in Column (f) is then equal to the percentage that customers have contributed to the unfunded reserve.

PDF page 477

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 5
Return on Rate Base Worksheet
DesertLink, LLC
RETURN ON RATE BASE ( R )
$
1
Long Term Interest (117, sum of 62.c through 67.c) (Note D)
                                -
2
Preferred Dividends (118.29c) (positive number)
                                -
3
Proprietary Capital (Line 25 (c))
                                -
4
Less Preferred Stock (Line 9)
                                -
5
Less Account 216.1 Undistributed Subsidiary Earnings (Line 25 (d))
                                -
6
Less Account 219 Accum. Other Comprehensive Income (Line 25 (e))
                                -
7
Common Stock
(Sum of Lines 3 through 6)
                                -
$
%
Cost
Weighted
8
Long Term Debt
Line 25 (a), Note A and Appendix III Note Q
                                -
50.00%
0.000%
0.00%
=WCLTD
9
Preferred Stock
Line 25 (b), Note B and Appendix III Note Q
                                -
0.00%
0.00%
0.00%
10
Common Stock
Line 7, Note C  and Appendix III Notes Q and T
                                -
50.00%
9.80%
4.900%
11
Total
(Sum of Lines 8 through 10)
                                -
4.90%
=R
(a) (b)
( c )
(d) ( e )
Monthly Balances for Capital Structure
12
December (Prior Year)
                               -                                 -                             -                                   -                                 - 13

January
                               -                                 -                             -                                   -                                 - 14

February
                               -                                 -                             -                                   -                                 - 15

March
                               -                                 -                             -                                   -                                 - 16

April
                               -                                 -                             -                                   -                                 - 17

May
                               -                                 -                             -                                   -                                 - 18

June
                               -                                 -                             -                                   -                                 - 19

July
                               -                                 -                             -                                   -                                 - 20

August
                               -                                 -                             -                                   -                                 - 21

September
                               -                                 -                             -                                   -                                 - 22

October
                               -                                 -                             -                                   -                                 - 23

November
                               -                                 -                             -                                   -                                 - 24

December
                               -                                 -                             -                                   -                                 - 25

13-Month Average
                               -                                 -                             -                                   -                                 - Notes

A
B
Preferred Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112 line 3.c in the Form No. 1 C

Common Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on Form 1 page 112 line 16.c less lines 3.c , 12.c, and 15.c D

Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies Long Term Debt

(Note A)
Preferred Stock
(112.3.c)
Proprietary
Capital (112.16.c)
Undistributed Sub
Earnings 216.1
(112.12.c)
Accum Other Comp.
Income 219
(112.15.c)
Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, lines 18.c to 21.c, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 478

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6
Interest on True-Up
DesertLink, LLC
Appendix III K23
Line
Rate Year
Rate Year
Projected Revenue Requirement (Note A)
1
                                                                                         -
Less
 $                             -
Equals
 $                        -
Note A - Projected ATRR for the true-up year from Page 1, Line 1 of Projection Appendix III minus Line 6 of Projection Appendix III. Note B - Actual Net ATRR for the true-up year from Page 1, Line 9 of True-Up Appendix III. Interest Rate on Amount of Refunds or Surcharges

Months
Amortization
2
0.000%
An over or under collection will be recovered pro rata over year collected, held for one year and returned pro rata over next year Monthly

3
January
Rate Year
                                -
0.000%
12
                          -
                              -
4
February
Rate Year
                                -
0.000%
11
                          -
                              -
5
March
Rate Year
                                -
0.000%
10
                          -
                              -
6
April
Rate Year
                                -
0.000%
9
                          -
                              -
7
May
Rate Year
                                -
0.000%
8
                          -
                              -
8
June
Rate Year
                                -
0.000%
7
                          -
                              -
9
July
Rate Year
                                -
0.000%
6
                          -
                              -
10
August
Rate Year
                                -
0.000%
5
                          -
                              -
11
September
Rate Year
                                -
0.000%
4
                          -
                              -
12
October
Rate Year
                                -
0.000%
3
                          -
                              -
13
November
Rate Year
                                -
0.000%
2
                          -
                              -
14
December
Rate Year
                                -
0.000%
1
                          -
                              -
15
                          -
                              -
Annual
16
January through December
Rate Yr. + 1                                 -
0.000%
12
                          -
                              -
Over (Under) Recovery Plus Interest Amortized and Recovered Over 12 Months Monthly

17
January
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 18

February
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 19

March
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 20

April
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 21

May
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 22

June
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 23

July
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 24

August
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 25

September
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 26

October
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 27

November
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 28

December
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 29

                          -
30
Total Amount of True-Up Adjustment
 $                           -
31
Less Over (Under) Recovery
 $                        -
32
Total Interest
 $                           -
Actual Net Revenue
Requirement (Note B)
Over (Under)
Recovery
Over (Under)
Recovery Plus
Interest
Monthly Interest
Rate on Attachment
6a
Calculated
Interest
Surcharge (Refund)
Owed
Calculation of Interest

PDF page 479

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6a
True-Up Interest Rate Calculator
DesertLink, LLC
This Attachment is used to compute the interest rate to be applied to each year's revenue requirement true-up.
Applicable FERC Interest Rate (Note A):
1
Rate Year January
0.00%
2
Rate Year February
-
3
Rate Year March
-
4
Rate Year April
-
5
Rate Year May
-
6
Rate Year June
-
7
Rate Year July
-
8
Rate Year August
-
9
Rate Year September
-
10
Rate Year October
-
11
Rate Year November
-
12
Rate Year December
-
13
Rate Year Plus 1  January
-
14
Rate Year Plus 1  February
-
15
Rate Year Plus 1  March
-
16
Rate Year Plus 1  April
-
17
Rate Year Plus 1  May
-
18
Average Rate
0.00%
19
Monthly Average Rate
0.00%
Note A - Lines 1-17 are the FERC interest rates under section 35.19a of the regulations for the period shown. Line 18 is the average of lines 1-17.

PDF page 480

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 7
Weighted Average Federal and State Income Tax Rates
DesertLink, LLC
Subchapter C
Mutual
Pensions, IRAs
UBTI
Non-Taxpaying
Weighted
Line
Description
Source
Corporations
Individuals
Funds
Keogh Plans
Entities
Entities
Average
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) 1
Weighted Marginal Federal Income Tax Rate
Note A
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
2
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
3
Weighted Average
Line 1 x Line 2
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4
Weighted Average Federal Income Tax Rate
Sum of Line 3, Col. (c)-(h)
0.00%
5
Weighted Marginal State Income Tax Rate
Note C
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
6
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
7
Weighted Average
Line 5 x Line 6
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
8
Weighted Average State Income Tax Rate
Sum of Line 7, Col. (c)-(h)
0.00%
A
For each Rate Year, DesertLink will develop a schedule calculating the weighted average federal income tax rate for each category of partners. B

This percentage is developed based on the distributive income allocated to each category of partners rather than their respective ownership percentages. C

For each Rate Year, DesertLink will develop a schedule calculating the weighted average state income tax rate for each category of partners.

PDF page 481

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 8
Cost of Debt Prior to Issuing Non-Construction Financing
DesertLink, LLC
This Attachment 8 is to be utilized to determine the cost of debt prior to issuing non-construction financing.  Once non-construction financing is issued the cost of debt shall be determined using the methodology described in Note Q on Appendix III. If construction debt has not or will not be issued when construction starts, a proxy rate will be used for the cost of debt, which will be supported in the initial section 205 filing. The proxy rate will be entered on line 36 of this attachment. If construction financing is obtained, all rates, fees and monthly debt balances will be subject to true up pursuant to Attachment 9. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template. Line No

1
Interest rate on Construction Debt for Rate Year - Line 19 (g)
0.00%
2
Rate Year Debt Fee expense - Line 35 (e)
0.00%
3
Total Cost of Debt - Sum of Lines 1 and 2
0.0000%
Interest Rate Information
4
Commitment Fee Rate (%)
5
Projected Average Drawn Rate for Rate Year (%) - Note A
Month During Rate Year
Total Loan Amount ($000)
Interest Expense ($000)
(a) (b)
(c) (d)
(e) (f)
(g) 6
December Prior Year
                            -                                         -                                          -                                          - 7

January
                            -                                         -                                          -                                          - 8

February
                            -                                         -                                          -                                          - 9

March
                            -                                         -                                          -                                          - 10

April
                            -                                         -                                          -                                          - 11

May
                            -                                         -                                          -                                          - 12

June
                            -                                         -                                          -                                          - 13

July
                            -                                         -                                          -                                          - 14

August
                            -                                         -                                          -                                          - 15

September
                            -                                         -                                          -                                          - 16

October
                            -                                         -                                          -                                          - 17

November
                            -                                         -                                          -                                          - 18

December
                            -                                         -                                          -                                          - 19

Average of the 13 Monthly Balances
                            -
                                        -                                          -
0.00%
Example Fee Calculation - All amounts represent actual rate year expenses.
(a) (b)
(c) (d)
(e) (f)
(g) Origination Fees
Rate/Fees
Gross Fee Amount ($000)
Year Fee Incurred
20
Underwriting Discount
0.00%
 -
 -
21
Arrangement Fee
0.00%
 -
 -
22
Upfront Fee
0.00%
 -
 -
23
Rating Agency Fee
0.00%
 -
 -
24
Legal Fees
0.00%
 -
 -
25
Other
0.00%
 -
 -
26
   Total Issuance Expense / Origination Fees - Sum of Lines 20-25
 -
 -
 -
 -
27
28
Annual Fees
29
Annual Rating Agency Fee
0.00%
N/A
 -
N/A
N/A
30
Annual Bank Agency Fee
0.00%
N/A                                      -
N/A
N/A
31
Utilization Fee
0.00%
N/A
 -
N/A
N/A
32
Other Fees
0.00%
N/A
 -
N/A
N/A
33
Total Fees
 -
 -
 -
 -
34
13 Month Average Debt balance - Line 19 (c)
                                        -
35
Rate Year cost of fees
0.00%
36
Proxy Debt rate. Used prior to issuance of construction financing and supported in initial section 205 filing. 3.2220%

Notes
A
LIBOR
0.0000%
Spread
2.3500%
Total
2.3500%
If construction financing has been obtained, the cost of debt prior the issuance of non-construction financing shall be based on the terms of the construction financing and determined below. Up-front fees including origination fees will be amortized and included in the cost of debt.

Principal Drawn
($000)
Unutilized Loan
Balance ($000)
Commitment Fee &
Utilization Fee ($000)
Effective Annual
Interest Rate (%)
Fee Amortization Period
(years)
Rate Year Amortized Fee
Amount, col. b / col. d
Prior Years Accumulated
Fee Amortization
Unamortized Balance
- End of Rate Year
Projected rate will be Average LIBOR for rate year + spread. Spread will be supported in initial section 205 filing. LIBOR will be updated based on information in the Wall Street Journal as of the 15th day of the month prior to population of this template.

PDF page 482

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 9
True-Up - Construction Financing Cost of Debt
DesertLink, LLC
One time up-front debt fees, including origination fees will be amortized and included in the cost of debt.
Line No.
$
1
Long Term Interest and Fees (117, sum of 62.c through 67.c) -- Notes A and B
                                    -
2
Line of Credit Fees (68.c) -- Note C
                                    -
3
Total Interest and Fees
                                    -
13 Month Average Long-Term Debt - Notes A and D
Month During Rate Year
Long Term Debt
(a) (d)
4
December Prior Year
                                    -
5
January
                                    -
6
February
                                    -
7
March
                                    -
8
April
                                    -
9
May
                                    -
10
June
                                    -
11
July
                                    -
12
August
                                    -
13
September
                                    -
14
October
                                    -
15
November
                                    -
16
December
                                    -
17
Average of the 13 Monthly Balances
                                    -
18
True-Up Cost of Debt (Line 3 / Line 17)
0.00%
Notes
A
B
Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies.
C
Line of credit fees will include only those related to long-term debt and not for short-term debt.
D
Long-term debt will exclude any short-term debt included in FERC Account 233, Notes Payable to Associated Companies.
This Attachment 9 is to be utilized only in the event construction financing has been obtained to compute the actual cost of debt to be included in the return on rate base calculation for the true-up each year prior to the issuance of non-construction financing. Once non-construction financing has been obtained the cost of debt shall be determined using the methodology described in Note Q on Appendix III. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template.

Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, line 24, columns d and c, respectively, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 483

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 10
Depreciation Rates
DesertLink, LLC
TRANSMISSION AND GENERAL PLANT DEPRECIATION RATES
Annual Depreciation Rates
Line No.
(Note A)
INTANGIBLE PLANT
1
303.1
Contributions in Aid of Construction
Note B
2
303.2
Interconnections
2.27%
3
303.3
Licenses
1.59%
TRANSMISSION PLANT
4
350.2
Land Rights
1.43%
5
351.1
Computer Hardware
20.00%
6
352.0
Structures & Improvements
1.95%
7
353.0
Station Equipment
2.58%
8
354.0
Towers & Fixtures
1.86%
9
355.0
Poles & Fixtures
2.17%
10
356.0
Overhead Conductors & Devices
2.01%
11
392.0
Transportation Equipment
10.00%
12
393.0
Stores Equipment
6.67%
13
394.0
Tools, Shop, and Garage Equipment
12.50%
14
397.2
Computer Software
11.64%
Notes
A
These depreciation rates will not be changed absent a FERC order.
B
GENERAL PLANT
In the event a Contribution in Aid of Construction (CIAC) is made for a transmission facility, the transmission depreciation rates above will be weighted based on the relative amount of underlying plant booked to the accounts shown in lines 4-12 above, and the resultant weighted average depreciation rate will be used to amortize the CIAC.   The CIAC depreciation rate for each facility will be determined at the time the plant is placed into service, and will not change  without FERC approval.

PDF page 484

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 11
Prior Period Adjustments
DesertLink, LLC
(a) (b)
Calendar Year
Line No. Description
Source
Revenue Impact of Correction
Revenue Requirement
1
Filing Name and Date
                                                        -
2
Original Revenue Requirement
                                                              -
3
4
Description of Correction 1
                                                              -
5
Description of Correction 2
                                                              -
6
7
Total Corrections
Line 4 + 5
                                                              -
8
9
Corrected Revenue Requirement
Line 2 + 7
                                                              -
10
11
12
Total Corrections
Line 7
                                                              -
13
14
Average Monthly FERC Refund Rate
Note A
0.00%
15
Number of Months of Interest
Note B
30
16
Interest on Correction
Line 12 x 14 x 15
                                                              -
17
18
Total Annual Amount Due from / (to) Customers
Line 12 + 16
                                                              -
Notes
A
B
The interest rate on corrections will be the average monthly FERC interest rate for the period from the beginning of the year being corrected through the most recent  month available as of the time the correction is computed and included in an annual filing.

The number of months interest due on the correction will be the number of months from the beginning of the year being corrected through June of the year in which the correction will be reflected in rates. In this manner the interest computed will reflect all years prior to when the correction is reflected in rates plus interest on the average unrefunded balance of the correction during the year the correction is reflected in rates.

PDF page 485

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 12
Revenue Credit Detail
DesertLink, LLC
(a) (b)
(c) = (a) - (b)
Line No.
(Note A)
Source
Company Total
Less: Non Transmission
Transmission-related
1
Account 454 - Rent from Electric Property
2
Joint pole attachments - telephone
Company books
                                          -                                                      -                                                                                                                 - 3

Joint pole attachments - cable
Company books
                                          -                                                      -                                                                                                                 - 4

Underground rentals
Company books
                                          -                                                      -                                                                                                                 - 5

Transmission tower wireless rentals
Company books
                                          -                                                      -                                                                                                                 - 6

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 7

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 8

Account 454 Revenue Credit
Form 1 300.19.b
                                          -                                                      -                                                                                                                 - 9

Account 456.1 Other Operating Revenues
10
CAISO NITS
Company books
                                          -                                                      -                                                                                                                 - 11

CAISO Point to Point
Company books
                                          -                                                      -                                                                                                                 - 12

Over/Under recovery deferral
Company books
                                          -                                                      -                                                                                                                 - 13

Other Transmission Service Revenues
Company books
                                          -                                                      -                                                                                                                 - 14

Other
Company books
                                          -                                                      -                                                                                                                 - 15

Total Per Books
Form 1 330.n
                                          -                                                      -                                                                                                                 - 16

Less: revenues received pursuant to this Formula Rate
                                          -                                                      -                                                                                                                 - 17

Less: Over/Under recovery deferral
                                          -                                                      -                                                                                                                 - 17a

Less: Revenue Credits included in the TRBAA
                                          -                                                      -                                                                                                                 - 18

Account 456.1 Revenue Credit
                                          -                                                      -                                                                                                                 - 19

Total Revenue Credits
(Line 8 + line 18)
                                          -                                                      -                                                                                                                 - Note A

All 454 and 456.1 revenues will be detailed from Company books and records or FERC Form 1, and additional rows added if necessary.  Non-transmission-related amounts will be deducted to determine transmission-related amounts. (Line 15 - line 16 - line 17

- line 17a)

PDF page 486

DesertLink, LLC
Attachment 13 - Excess or Deficient Accumulated Deferred Income Taxes - Summary
[Year]
[Projected or Actual]
Line No.
1
2
[List of tax law changes, accounting treatment, and asscociated explanatory notes.]
3
Rate Base Adjustment Mechanism - Summary
4
Account
Amount
References
5
182.3 (debit or <credit>)
                        -
6
254 (debit or <credit>)
                        -
7
Total Deficient or (Excess) ADIT (sum of lines 5-6)
                        -   To Appendix III, Page 2, Line 22a, Col. (3)
8
9
Income Tax Allowance Adjustment Mechanism - Summary
(a) (b)
(c) (d)
(e) (f)
10
11
[Insert rows as necessary]
                        -
                        -
11a
[Insert rows as necessary]
                        -
                        -
11…
[Insert rows as necessary]
                        -
                        -
12
Total
(sum of lines 11_)
                        -
                        -
13
14
[Explanatory statements as needed]
The primary purposes of this worksheet are to:
 - reconcile the amounts of regulatory assets and liabilities comprising the rate base adjustment mechanism on Appendix III, Page 2, Line 22a (ADJUSTMENTS TO RATE BASE > Deficient or (Excess) ADIT) as of the beginning and end of the current test period (summarized beginning at Line 3 below) and

- to support the amount of excess deferred tax expense or benefit recognized due to enacted change(s) in tax rate(s) on Appendix III, Page 3, Line 40 (INCOME TAXES > Deficient or (Excess) Deferred Income Taxes) and the effect of such excess deferred tax expense or benefit on the revenue requirement as reflected in the income tax allowance adjustment mechanism on Appendix III, Page 3, Line 44 (INCOME TAXES > Deficient or (Excess) Deferred Income Tax Adjustment) during the test period (summarized beginning on Line 9 below).

This worksheet supports the computation of the projected revenue requirement or, as appropriate, the actual revenue requirement used to compute the true-up adjustment.
Each tax law change addressed by this worksheet with its associated explanatory note is listed below.  Amounts related to each tax law change are provided and supported throughout this worksheet.  Additional lines and explanatory notes will be added to this worksheet as necessary as tax law changes are enacted without the need for an FPA Section 205 filing.

The amounts summarized above are computed in the Rate Base Adjustment Mechanism-Reconciliation of Beginning and End of Test Period Balances section of the worksheet with proration and averaging of activity during the test period computed in different section of Attachment 13.1 for projected revenue requirement calculations and actual revenue requirement calculations.

 Amortization or
Mitigation of
Deficient or
<Excess> ADIT
 Tax Gross-up
Factor
 Amortization or
Mitigation with
Tax Gross-up
 To Appendix III,
Page 3, Line 40,
Col. (3)
 To Appendix III,
Page 3, Line 44,
Col. (3)

PDF page 487

15
Rate Base Adjustment Mechanism - Reconciliation of Beginning and End of Test Period Balances
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
16
Description (+ = debit, <> = credit)
Amortization period and method
17
[Insert rows as necessary]
                        -                           -                           -                           -                           - 17a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 18

Total for account 182.3
(sum of lines 17_)
                        -                           -                           -                           -                           - 19

 FN1. pg 232
 FN1. pg 232
20
[Insert rows as necessary]
                        -                           -                           -                           -                           - 20a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 21

Total for account 254
(sum of lines 20_)
                        -                           -                           -                           -                           - 22

 FN1. pg 278
 FN1. pg 278
23
24
Income Tax Allowance Adjustment Mechanism
25
26
Amortization of Excess or Deficient ADIT
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
27
Description (+ = debit, <> = credit)
Comments
28
[Insert rows as necessary]
                        -                           -                           -                           -                            - 28a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 29

Total for account 182.3
(sum of lines 28_)
                        -                           -                           -                           -                            - 30

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 31

Total for account 254
(sum of lines 30_)
                        -                           -                           -                           -                            - 32

Total amortization and offsetting entries
(sum of lines 29 & 31)                         -                           -                           -                           -                            - 33

Net income tax expense or benefit
(sum of lines 32(f) & 32(g))
                        -
 To line 11
Balance at
Beginning of
Year
Re-
measurement of
ADIT
Annual
Amortization
(Note 4)
Other
Adjustments
(Note 5)
Balance at End
of Year
(d)+(e)+(f)+
(g) Whether subject
to normalization
rules
(Note 6)
Analysis - Balances of tax-related regulatory assets and liabilities include tax gross-up.  Accordingly, for the regulatory assets and liabilities for deficient or excess deferred taxes included in rate base, the related deferred tax assets and liabilities are also included in rate base.  Remeasurements in column (e) are described in Notes 2 and 3 and are based on the journal entry below and the support on the worksheet for the applicable tax law change.  Averaging or proration of amounts affecting rate base is computed on different sections of Attachment 13.1 for projected revenue requirement and actual revenue requirement. The income tax allowance adjustment mechanism may include amortization of excess or deficient ADIT pertaining to deferred tax expense or benefit reflected in rates at a historical tax rate when the underlying timing difference(s) originated (computed under Amortization of Excess or Deficient ADIT within the Income Tax Allowance Adjustment Mechanism section of this worksheet) as well as an adjustment for tax law changes with prospective effective dates intended to mitigate the over- or under- recovery of deferred income taxes originating prior to the effective date of such tax law changes (computed under Adjustment for Tax Law Changes with Prospective Effective Dates within the Income Tax Allowance Adjustment Mechanism section of this worksheet).

Annual
Amortization
from Table
Above
(Note 4)
Debit or
<Credit> to
Account 410.1
Debit or
<Credit> to
Account 411.1
Debit or
<Credit> to
Account 190
Debit or
<Credit> to
Account 283

PDF page 488

34
Adjustment for Tax Law Changes with Prospective Effective Dates
35
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) 36
37
 (c) x (d)
1 / (1- (d))
 (e) x (f)
 - [(c) x (h)]
 (e) + (i)
 (j) x (f)
38
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
38…
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
39
Note 1 - Summary of re-measurement of ADIT resulting from tax law changes
40
41
Note 1a - Summary of re-measurement of ADIT resulting from
[name of tax law change]
Additional information is provided in Note
42
Re-measurement entry
(a) (b)
(c) 43
Account
Comments or References
44
190
45
281
46
282
47
283
48
182.3 (tax-related, included in rate base - protected)
49
182.3 (tax-related, included in rate base - unprotected)
50
182.3 (tax-related, not in rate base))
51
190 (related to portion of acct. 182.3 not in rate base)
52
254 (tax-related, included in rate base - protected)
53
254 (tax-related, included in rate base - unprotected)
54
254 (tax-related, not in rate base)
55
283 (related to portion of acct. 254 not in rate base)
56
Account 410.1
57
Account 411.1
58
Account 410.2
59
Account 411.2
60
Total
 (sum of lines
                        -
61
[Insert additional analysis.]
In the case of tax law changes with an effective date(s) after the beginning of the test period, the impact of a timing difference on current tax expense or benefit differs from the impact on ADIT.  For example, in the case of a deductible timing difference originating in a tax year with a higher enacted tax rate than will apply when the difference will reverse, the current tax benefit will exceed the deferred tax expense.  In this situation, the adjustment computed below to recoverable income tax expense is made in order to avoid over-recovering income tax expense in the current test period due to the excess of current tax benefit over deferred tax expense (computed based on the estimated amount of the future tax liability) with respect to a given timing difference.  The adjustment to recoverable tax expense during the test period in which a timing difference originates mitigates the need for refund of a regulatory liability for excess deferred taxes in a future period (or, as applicable, the need for recovery of a regulatory asset for deficient deferred taxes in a future period).  Amounts in column (i) are reported in the Income Tax Allowance Adjustment Mechanism - Summary on this worksheet.

 Originating
Taxable or
(Deductible)
Book / Tax
Difference for
Test Year
 Tax Rate for
Test Year
 Current Tax
Expense or
(Benefit) in Test
Year
 Tax Gross-up
Factor for Test
Year
 Revemue
Requirement
Imapct for Test
Year
 Enacted Tax
Rate for the
Reversal Year(s)
 Deferred Tax
Expense or
(Benefit) in Test
Year
 Total Tax
Expense or
(Benefit) in Test
Year
 Adjustment to
Mitigate
Over/under-
recovery of
Deferred Taxes
The purposes of this portion of the worksheet are, for each change in tax law, to explain:
- how any ADIT accounts were re-measured,
- the excess or deficient ADIT contained therein, and
- the accounting for any excess or deficient amounts in Accounts 182.3 (Other Regulatory Assets) and 254 (Other Regulatory Liabilities).
Note 2 describes how ADIT accounts are re-measured upon a change in income tax law.  A separate summary (i.e., Note 1a, Note 1b, etc.) will be added for each tax law change resulting in a re-measurement of ADIT. Debit or

<Credit>

PDF page 489

62
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
63
[Insert additional analysis.]
64
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
65
66
67
68
69
[Continuation of note with respect to particular changes in tax law.]
70
[Insert additional notes as needed.]
Note 2 - Explanation of how ADIT accounts are re-measured upon a change in income tax law
Deferred tax assets and liabilities are adjusted (re-measured) for the effect of the changes in tax law (including tax rates) in the period that the change is enacted.  Adjustments are recorded in the appropriate deferred tax balance sheet accounts (Accounts 190, 281, 282 and 283) based on the nature of the temporary difference and the related classification requirements of the accounts.   If as a result of action or expected action by a regulator, it is probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, a regulatory asset or liability is recognized in Account 182.3 (Other Regulatory Assets), or Account 254 (Other Regulatory Liabilities), as appropriate, for that probable future revenue or reduction in future revenue.  Re-measurements of deferred tax balance sheet accounts may also result in re-measurements of tax-related regulatory assets or liabilities that had been recorded prior to the change in tax law.  If it is not probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, tax expense is recognized in Account 410.2 (Provision for Deferred Income Taxes, Other Income or Deductions) or tax benefit is recognized in Account 411.2 (Provision for Deferred Income Taxes-Credit, Other Income or Deductions), as appropriate.

Note 3 - [Complete to support information above.]
Note 4 - The amortization of the deficient or excess ADIT reducing Account 254 (Other Regulatory Liabilities) is recorded with credits to Account 411.1 (Provision for Deferred Income Taxes – Credit, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance.  The amortization of the deficient or excess ADIT reducing Account 182.3 (Other Regulatory Assets) is recorded with debits to Account 410.1 (Provision for Deferred Income Taxes, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance. This activity is summarized in the table "Income Tax Allowance Mechanism - Projected" or the table "Income Tax Allowance Mechanism - Actual," as appropriate.  The annual amortization in the tables above reflects tax gross-up and is stated at the revenue requirement level.

Note 5 - [Complete to support information above.]
Note 6 -  The worksheet indicates whether each excess or deficient ADIT amounts are protected (i.e., subject to normalization rules of a taxing jurisdiction) or unprotected (i.e., not subject to normalization rules of a taxing jurisdiction).  To the extent that normalization requirements apply to ADIT remeasurements, additional computations (e.g., proration of excess deferred tax activity related to future test periods) may be necessary.

PDF page 490

DesertLink, LLC
Attachment 13.1 - Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments
Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)
[Year]
[Projected or Actual]
Line No.
1
Rate year =
2
Test period days after rates become effective
3
4
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
5
6
Beginning balance  (debit or <credit>)
                        -
7
Less:  Portion not related to transmission
                        -
8
Less:  Portion not reflected in rate base
                        -
9
Subtotal:  Portion reflected in rate base
                        -
10
Less:  Portion subject to proration
                        -
11
Portion subject to averaging  (debit or <credit>)
                        -
12
Ending balance  (debit or <credit>)
                        -
13
Less:  Portion not related to transmission
                        -
14
Less:  Portion not reflected in rate base
                        -
15
Subtotal:  Portion reflected in rate base
                        -
16
Less:  Portion subject to proration (before proration)
                        -
17
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
18
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 36(n)
19
Average balance of portion subject to averaging
                        -
20
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 5
This attachment includes sections that are populated only with actual data and thus, these sections remain blank when the formula rate template is calculating a projected revenue requirement. Columns (i) through (n) below are not used for the projection and are only populated with actual data for the Annual Update.

Note 1 - The computations below apply the proration rules of Treasury Regulation section 1.167(l)-1(h)(6) to the annual activity of the portions of the deficient or excess accumulated deferred income taxes recorded in account 182.3 or 254 that are subject to the normalization requirements.  Activity related to the portions of the account balances reflected in rate base but not subject to the proration requirement is averaged instead of prorated.  The balances below include tax gross-up.  The corresponding portions of the deferred tax asset related to the portions of the regulatory liability and the corresponding portions of the deferred tax liability related to the portions of the regulatory asset are also reflected in rate base and prorated or averaged, as appropriate.  Columns (a) through (h) are used for projected and actual revenue requirements computations.  Columns (i) through (n) are used for actual revenue requirement computations.

Amount
debit / <credit>

PDF page 491

21
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
22
Month
Year
23

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
24
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA
 NA                              -
25
January
-
                              -                                 -
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 26

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 27

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 28

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 29

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 30

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 31

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 32

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 33

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 34

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 35

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 36

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 37

Total
                              -
                             -                                -
38
39
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
40
41
Beginning balance  (debit or <credit>)
                        -
42
Less:  Portion not related to transmission
                        -
43
Less:  Portion not reflected in rate base
                        -
44
Subtotal:  Portion reflected in rate base
                        -
45
Less:  Portion subject to proration
                        -
46
Portion subject to averaging  (debit or <credit>)
                        -
47
Ending balance  (debit or <credit>)
                        -
48
Less:  Portion not related to transmission
                        -
49
Less:  Portion not reflected in rate base
                        -
50
Subtotal:  Portion reflected in rate base
                        -
51
Less:  Portion subject to proration (before proration)
                        -
52
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
53
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 70(n)
54
Average balance of portion subject to averaging
                        -
55
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 6
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 2 -
Amount
debit / <credit>

PDF page 492

56
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
57
Month
Year
58

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
58
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA                              -
59
January
-
                              -                                 -
0
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 60

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 61

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 62

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 63

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 64

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 65

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 66

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 67

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 68

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 69

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 70

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 71

Total
                              -
                             -                                -
72
73
74
75
76
77
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 3 -
Note 4  -  Column J is the difference between actual monthly and projected monthly activity (Column I minus Column C).  Specifically, if projected and actual activity are both positive, a negative in Column J represents over-projection (i.e., the amount of projected activity that did not occur) and a positive in Column J represents under-projection (i.e., the excess of actual activity over projected activity). If projected and actual activity are both negative, a negative in Column J represents under-projection (i.e., the excess of actual activity over projected activity) and a positive in Column J represents over-projection (i.e., the amount of projected activity that did not occur).

Note 5  -  Column K preserves the effects of excess ADIT proration from the projected revenue requirement when actual monthly excess ADIT activity and projected monthly excess ADIT activity are either both increases or decreases.  Specifically, if Column J indicates that excess ADIT activity was over-projected, enter Column G x [Column I / Column C].  If Column J indicates that excess ADIT activity was under-projected, enter the amount from Column G and complete Column L).  In other situations, enter zero.

Note 6  -  Column L applies when (1) Column J indicates that excess ADIT activity was under-projected AND (2) actual monthly and projected monthly activity are either both increases or both decreases.  Enter 50 percent of the amount from Column J.  In other situations, enter zero.  The excess ADIT activity in column L is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 7  -  Column M applies when (1) projected monthly activity was an increase while actual monthly activity was a decrease OR (2) projected monthly activity was a decrease while actual monthly activity was an increase.  Enter 50 percent of the amount of actual monthly activity (Column I).  In other situations, enter zero.  The excess ADIT activity in column M is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 8  -  Column N is computed by adding the balance at the end of the prior month to EITHER (1) the sum of prorated monthly excess ADIT activity, if any, from Column K and the portion of monthly excess ADIT activity, if any, from Column L OR (2) the portion of monthly excess ADIT activity in Column M.

PDF page 493

DesertLink, LLC
Attachment 13.2 - Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities Resulting from the Tax Change Identified in Line 1 Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)

[Year]
[Projected or Actual]
Line No.
1
[Identify/describe the tax legislation/change]
2
[Describe the computation.]
3
4
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
5
Balances and rates prior to remeasurement
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
6
Temporary Difference
Account
Account
Account
Account
Account
7
Item
Normalized?
Amount
190
282
283
182.3
283
8
[Insert rows as necessary]
8a
[Insert rows as necessary]
8b
[Insert rows as necessary]
8...
[Insert rows as necessary]
9
Total
                     -                      -                      -                      -                      -
10
Remeasured balances and rates
Other accounts affected by remeasurement
11
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
[1/(1-tax rate [tax rate] /(1-tax rate [tax rate]
12
Temporary Difference
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
13
Item
Normalized?
Amount
190
282
283
182.3
283
410.2
411.2
254
190
182.3
283
14
[Insert rows as necessary]
14a
[Insert rows as necessary]
14b
[Insert rows as necessary]
14...
[Insert rows as necessary]
15
Total
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
16
Remeasurement journal entry:  debt or <credit> (to Attachment 13)
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
17
Summary of Effects on Tax-related Regulatory Assets and Liabilities
18
Account 182.3 - included in rate base, subject to normalization rules
19
Account 182.3 - included in rate base, not subject to normalization rules
20
Account 182.3 - not included in rate base
21
Account 254 - included in rate base, subject to normalization rules
22
Account 254 - included in rate base, not subject to normalization rules
23
Account 254 - not included in rate base
The ratemaking treatment of each item in terms of whether it is subject to the normalization requirements (i.e., P or "protected") or not subject to the normalization requirements (i.e., U or "unprotected") and included in rate base or not (i.e., RB or non-RB) is indicated in column (b).  The balances are measured at the composite tax rate in effect immediately before effective date of the change in tax law and remeasured immediately after the change in tax law.  Each set of balances includes the appropriate income tax rates and tax gross-up factors (as computed in the specific note for this tax law change in Att. 13).  The journal entry to record the remeasurements (Line 16) is based on the differences in balances of accounts recorded prior to the change in law (columns (d)-(h)) and activity in other accounts resulting from the remeasurement (columns (i)-(n)).  The remeasurement entry is also included in Att. 13.  The accounting is further described in Att. 13, Note 2. This worksheet will be included in support of the revenue requirement computation until the excess or deficient ADIT is fully amortized.  A similar worksheet will be used for subsequent changes in tax law resulting in re-measurement of ADIT.

PDF page 494

Ex. DLK-202

Formula Rate Template (Marked)

PDF page 495

Projected ATRR
For the 12 months ended
12/31/__
Formula Rate Index
DesertLink, LLC
Table of Contents
Formula Rate Template
Attachments:
Attachment No
Worksheet Name
1
Project Revenue Requirement Worksheet
1a
Project Plant Detail Worksheet
2
Incentive Return
3
Formula Rate True-Up
4
Rate Base Worksheet
5
Return on Rate Base Worksheet
6
Interest on True-Up
6A
True-Up Interest Rate Calculator
7
Weighted Average Federal and State Income Tax Rates
8
Cost of Debt Prior to Issuing Non-Construction Financing
9
True-Up - Construction Financing Cost of Debt
10
Depreciation Rates
11
Prior Period Adjustments
12
Revenue Credit Detail
13
Excess or Deficient Accumulated Deferred Income Taxes - Summary 13.1

Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments 13.2

Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities

PDF page 496

Formula Rate - Non-Levelized
Page 1 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
Projected ATRR
For the 12 months ended
12/31/__
(1) (2)
(3) (4)
(5) Line
Allocated
No.
Source
Amount
1
GROSS REVENUE REQUIREMENT, without incentives (Page 3, Line 49)

 $                               -
REVENUE CREDITS
(Note A)
Total
Allocator (W)
2
Account No. 454
(Page 4, Line 20)
                                                  -
TP
         1.0000
 $                               -
3
Account No. 456.1
(Page 4, Line 21)
                                                  -
TP
         1.0000
 $                               -
4
Revenues from Grandfathered Interzonal Transactions (Note B)

                                                  -
TP
         1.0000
 $                               -
5
Revenues from service provided by the ISO at a discount
                                                  -
TP
         1.0000
 $                               -
6
TOTAL REVENUE CREDITS
(Sum of Lines 2 through 5)
                                                  -
 $                               -
7
Prior Period Adjustments
Attachment 11, Line 18, Col. B
                                                  -
DA
         1.0000
 $                               -
8
True-up Adjustment with Interest
Attachment 3, Line 9, Col. J
                                                  -
DA
         1.0000
 $                               -
9
NET ANNUAL TRANSMISSION REVENUE REQUIREMENT
(Line 1 less Line 6 plus Lines 7 and 8)
 $                               -

PDF page 497

Page 2 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
RATE BASE: (Note R)
Source
Company Total
Allocator (W)
Transmission
GROSS PLANT IN SERVICE
Note C
(Col 3 times Col 4)
1
Production
205.46.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
2
Transmission
Attachment 4, Line 14, Col. (b)
                                                  -
TP
         1.0000
                                  -
3
Distribution
207.75.g for end of year, records for other months
                                                  -
N/A
                 -
                                  -
4
General & Intangible
Attachment 4, Line 14, Col. (c)
                                                  -
WS
         1.0000
                                  -
5
TOTAL GROSS PLANT
(Sum of Lines 1 through 4)
                                                  -
GP=
         1.0000
                                  -
6
ACCUMULATED DEPRECIATION
Note C
7
Production
219.20-24.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
8
Transmission
Attachment 4, Line 14, Col. (h)
                                                  -
TP
         1.0000
                                  -
9
Distribution
219.26.c for end of year, records for other months
                                                  -
N/A
                 -
                                  -
10
General & Intangible
Attachment 4, Line 14, Col. (i)
                                                  -
WS
         1.0000
                                  -
11
TOTAL ACCUM. DEPRECIATION
(Sum of Lines 7 through 10)
                                                  -
                                  -
12
NET PLANT IN SERVICE
13
Production
(Line 1 - Line 7)
                                              -
                               -
14
Transmission
(Line 2 - Line 8)
                                              -
                               -
15
Distribution
(Line 3 - Line 9)
                                              -
                               -
16
General & Intangible
(Line 4 - Line 10)
                                              -
                               -
17
TOTAL NET PLANT
( Sum of Lines 13 through 16)
                                              -
NP=
         1.0000
                               -
18
ADJUSTMENTS TO RATE BASE
19
Account No. 281 (enter negative)
Attachment 4, Line 28, Col. (d) (Note D)
                                              -
N/A
                 -
                               -
20
Account No. 282 (enter negative)
Attachment 4, Line 28, Col. (e) (Note D)
                                              -
NP
         1.0000
                               -
21
Account No. 283 (enter negative)
Attachment 4, Line 28, Col. (f) (Note D)
                                              -
NP
         1.0000
                               -
22
Account No. 190
Attachment 4, Line 28, Col. (g) (Note D)
                                              -
NP
         1.0000
                               -
22a
Deficient or (Excess) Accumulated Deferred Income Taxes Attachment 13, Line 7 (Note X)

                                                  -
NP
         1.0000
                               -
23
Account No. 255 (enter negative)
Attachment 4, Line 28, Col. (h) (Note D)
                                              -
NP
         1.0000
                               -
24
Unfunded Reserves (enter negative)
Attachment 4, Line 43, Col. (h)
                                              -
DA
         1.0000
                               -
25
CWIP
Attachment 4, Line 14, Col. (d)
                                              -
DA
         1.0000
                               -
26
Unamortized Regulatory Asset
Attachment 4, Line 28, Col. (b) (Note E)
                                              -
DA
         1.0000
                               -
27
Unamortized Abandoned Plant
Attachment 4, Line 28, Col. (c) (Note F)
                                              -
DA
         1.0000
                               -
28
TOTAL ADJUSTMENTS
( Sum of Lines 19 through 27)
                                              -
                                  -
29
LAND HELD FOR FUTURE USE
Attachment 4, Line 14, Col. (e) (Note G)
                                              -
TP
         1.0000
                               -
30
WORKING CAPITAL
Note H
31
Cash Working Capital
1/8*(Page 3, Line 17 minus Page 3, Line 14)
                                              -
                               -
32
Materials & Supplies
Attachment 4, Line 14, Col. (f)
                                              -
TP
         1.0000
                               -
33
Prepayments (Account 165)
Attachment 4, Line 14, Col. (g)
                                              -
GP
         1.0000
                               -
34
TOTAL WORKING CAPITAL
( Sum of Lines 31 through 33)
                                              -
                                  -
35
RATE BASE
( Sum of Lines 17, 28, 29, and 34)
                                              -
                                  -
Formula Rate - Non-Levelized

PDF page 498

Page 3 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
Source
Company Total
Allocator (W)
Transmission
O&M
(Col 3 times Col 4)
1
Transmission
321.112.b
                                                  -
TP
         1.0000
                                  -
2
Less Account 566 (Misc Trans Expense)
321.97.b
                                                  -
TP
         1.0000
                                  -
3
Less Account 565
321.96.b
                                                  -
TP
         1.0000
                                  -
4
A&G
323.197.b
                                                  -
WS
         1.0000
                                  -
5
Less FERC Annual Fees
351.h (Note I)
                                                  -
WS
         1.0000
                                  -
6
Less EPRI Dues
Note J
                                                  -
WS
         1.0000
                                  -
7
Less Reg. Commission Expense Account 928
Note J
                                                  -
WS
         1.0000
                                  -
8
Less: Non-safety Advertising account 930.1
Note J
                                                  -
WS
         1.0000
                                  -
9
10
Plus Transmission Related Reg. Comm. Exp.
Note K
                                                  -
TP
         1.0000
                                  -
11
12
Plus Transmission Lease Payments in Acct 565 Note V

                                                  -
DA
         1.0000
                                  -
13
Account 566
14
Amortization of Regulatory Asset
Note E
                                                  -
DA
         1.0000
                                  -
15
Misc. Transmission Expense (less amort. of regulatory asset) 321.97.b less line 14

                                                  -
TP
         1.0000
                                  -
16
Total Account 566
(Sum of Lines 14 through 15) Ties to 321.97b
                                                  -
                                  -
17
TOTAL O&M
                                                  -
                                  -
18
DEPRECIATION EXPENSE
Note C
19
Transmission
336.7.b&d
                                                  -
TP
         1.0000
                                  -
20
General & Intangible
336.10.b&d, 336.1.b&d
                                                  -
WS
         1.0000
                                  -
21
Amortization of Abandoned Plant
Note F
                                                  -
DA
         1.0000
                                  -
22
TOTAL DEPRECIATION
(Sum of Lines 19 through 21)
                                                  -
                                  -
23
TAXES OTHER THAN INCOME TAXES   (Note M)
24
LABOR RELATED
25
Payroll
263.i
                                                  -
WS
         1.0000
                                  -
26
263.i
                                                  -
WS
         1.0000
                                  -
27
PLANT RELATED
28
Property
263.i
                                                  -
GP
         1.0000
                                  -
29
Gross Receipts
263.i
                                                  -
N/A

                                  -
30
Other
263.i
                                                  -
GP
         1.0000
                                  -
31
Payments in lieu of taxes
263.i
                                                  -
GP
         1.0000
                                  -
32
TOTAL OTHER TAXES
( Sum of Lines 25 through 31)
                                                  -
                                  -
33
INCOME TAXES    (Note N)
Note N
34
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} 0.00%

35
CIT=(T/1-T) * (1-(WCLTD/R)) =
WCLTD = Page 4, Line 15, R = Page 4, Line 18 0.00%

36
FIT & SIT & P
37
38
1 / (1 - T)  = (from line 35)
1 / (1 - T), T from Line 35
                                         1.0000
39
Amortized Investment Tax Credit
266.8f (enter negative) (Note D)
                                                  -
40
Deficient or (Excess) Deferred Income Taxes Attachment 13, Line 12, Col. (d) (Note X)

                                                  -
41
Tax Effect of Permanent Differences
Note O
                                                  -
42
Income Tax Calculation
(Line 35 times Line 48)
                                                  -
N/A
                                  -
43
ITC adjustment
(Line 38 times Line 39)
                                                  -
NP
         1.0000
                                  -
44
Deficient or (Excess) Deferred Income Tax Adjustment Attachment 13, Line 12, Col. (f) (Note X)

                                                  -
NP
         1.0000
                                  -
45
Permanent Differences Tax Adjustment
(Line 38 times Line 41)
                                                  -
NP
         1.0000
                                  -
46
Total Income Taxes
(Sum of Lines 42 through 45)
                                                  -
                                  -
47
RETURN
48
Rate Base times Return
(Page 2, Line 35 times Page 4, Line 18)
                                                  -
N/A
                 -
                                  -
49
GROSS REVENUE REQUIREMENT
( Sum of Lines  17, 22, 32, 46, and 48)
                                                  -
                                  -
(Sum of Lines 1, 4, 10, 12, and 16 less Sum of Lines 2, 3, and 5 through 8)

Highway and vehicle

PDF page 499

Formula Rate - Non-Levelized
Page 4 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
Line
(1) (2)
(3) (4)
(5) No.
SUPPORTING CALCULATIONS AND NOTES
TRANSMISSION PLANT INCLUDED IN ISO RATES
1
Total Transmission plant
(Page 2, Line 2, Col. 3)
                                  -
2
(Note P)
                                  -
3
(Note S)
                                  -
4
Transmission plant included in ISO rates
(Line 1 minus Lines 2 and 3)
                                  -
5
Percentage of Transmission plant included in ISO Rates (Line 4 divided by Line 1)

TP =                               1.00
6
WAGES & SALARY ALLOCATOR (W&S)
Form 1 Reference
$
TP
Allocation
7
Production
354.20.b
                                                  -
            -                    -
8
Transmission
354.21.b
                                                  -
        1.00                  -
9
Distribution
354.23.b
                                                  -
            -                    -
W&S Allocator
10
Other
354.24,25,26.b
                                                  -
            -                    -
($ / Allocation)
11
Total (W&S Allocator is 1 if lines 7-10 are zero) (Sum of Lines 7 through 10)

                                                  -
                 -
=
                        1.00000  = WS
12
RETURN (R)
13
14
$
%
Cost
Weighted
15
Long Term Debt
Attachment 5, Line 8 (Notes Q & R)
                                                  -
50.0%
0.00%
0.00% = WCLTD
16
Preferred Stock (112.3.c)
Attachment 5, Line 9 (Notes Q & R)
                                                  -
0.0%
0.00%
0.00%
17
Common Stock
Attachment 5, Line 10 (Notes Q, R, and T)
                                                  -
50.0%
9.80%
4.90%
18
Total
( Sum of Lines 15 through 17)
                                                  -
4.90% = R
19
REVENUE CREDITS
$
20
Attachment 12, Line 8, Col. C (Note U)
                                  -
21
ACCOUNT 456.1 (OTHER ELECTRIC REVENUES)
Attachment 12, Line 18, Col. C (Note A)
                                  -
Less Transmission plant excluded from ISO rates Less Transmission plant included in OATT Ancillary Service rates

ACCOUNT 454 (RENT FROM ELECTRIC

PDF page 500

Formula Rate - Non-Levelized
Page 5 of 5
Rate Formula Template
Utilizing FERC Form 1 Data
DesertLink, LLC
For the 12 months ended
12/31/__
General Note: References to pages in this formula rate template are indicated as: (Page #, Line #, Col. #)
References to data from FERC Form 1 are indicated as: #.y.x (page, line, column)
Notes
A
B
Company will not have any grandfathered agreements. Therefore, this line shall remain zero.
C
Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
D
E
F
Unamortized Abandoned Plant and Amortization of Abandoned Plant will be zero until the Commission accepts or approves recovery of the cost of Abandoned Plant. Utility must submit a Section 205 filing to recover the cost of abandoned plant. G

Identified in FERC Form 1, or Company records if not so indicated on the FERC Form 1, as being transmission related.
H
I
J
Page 3, Line 6 - Subtract all EPRI Annual Membership Dues listed in Form 1 at 353.f, all Regulatory Commission Expenses in account 928 itemized at 351.h, and non-safety related advertising included in Account 930.1. K

Page 3, Line 8-Add back Regulatory Commission Expenses directly related to transmission service, ISO filings, or transmission siting itemized at 351.h.
M
N
Inputs Required:
FIT =
0.0%
(Weighted Average Federal Income Tax Rate (Attachment 7, line 4, col. (i))
SIT =
0.0%
(Weighted Average State Income Tax Rate (Attachment 7, line 8, col. (i))
p =
0.0%
(Percent of federal income tax deductible for state purposes)
O
P
Removes transmission plant determined by Commission order to be state-jurisdictional according to the seven-factor test (until Form 1 balances are adjusted to reflect application of seven-factor test).
Q
R
S
T
The rate of return on common equity ("ROE") will be supported in the original Section 205 filing and shall, at no time during the life of the Project, be higher than 9.8%, including adders.  No change in ROE may be made absent a filing with FERC. U

Includes only income related to transmission facilities, such as pole attachments, rentals and special use from general ledger.
V
Add back any lease expense of transmission assets used to provide service under this tariff included in account 565. Amount to be obtained from company books and records.
W
DA = Direct Assignment; GP = Gross Plant Allocator (page 2, line 5); N/A = Not Applicable; NP = Net Plant Allocator (page 2, line 17); TP = Transmission Plant Allocator (page 4, line 5); WS = Wage and Salary Allocator (page 4, line 11). X

The revenues credited on page 1, lines 2-6, shall include only the amounts received by DesertLink for service rendered using facilities for which recovery is provided under this tariff. They do not include revenues associated with FERC annual charges, gross receipts taxes, or facilities not included in this template (e.g., direct assignment facilities and GSUs) which are not recovered under this Rate Formula Template.

Accumulated deferred income tax amounts associated with asset or liability accounts excluded from rate base (such as ADIT related to asset retirement obligations and certain tax-related regulatory assets or liabilities) do not affect rate base.  Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income. Account 281 is not allocated to Transmission.

Recovery of Regulatory Asset permitted only for pre-commercial and formation expenses as authorized by the Commission. Recovery of any other regulatory assets requires authorization from the Commission. A carrying charge equal to the AFUDC rate will be applied to the Regulatory Asset prior to the rate year when costs are first recovered.

Cash Working Capital assigned to transmission is one-eighth of O&M allocated to transmission at page 3, line 17, column 5 minus amortization of Regulatory Asset at page 3, line 14, column 5.  Prepayments are the electric related prepayments booked to Account No. 165 and reported on page 111, line 57 in the Form 1.

The FERC's annual charges for the year assessed the Transmission Owner for service under this tariff.  To the extent the charges are separately identified on the FERC Form 1, page 350, column 1, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 350 will be obtained from Company books and records.

Includes only FICA, unemployment, highway, property, gross receipts, and other assessments charged in the current year.  Taxes related to income are excluded.  Enter the line number on page 262-63 upon which each item is identified.  To the extent individual types of taxes are separately identified on the FERC Form 1, page 262, column a, the line number will be added to the source in Column 2 for reference.  Line item references can change from year to year.  Items not specifically identified in the FERC Form 1, page 262-63 will be obtained from Company books and records.

FIT is the weighted average Federal income tax rate and SIT is the weighted average State income tax rate, both from Attachment 7, and p is the "the percentage of federal income tax deductible for state income taxes". A utility that elected to utilize amortization of tax credits against taxable income, rather than book tax credits to Account No. 255 and reduce rate base, must reduce its income tax expense by the amount of the Amortized Investment Tax Credit (Form 1, 266.8.f) multiplied by (1/1-T) (page 3, line 26). Excess Deferred Income Taxes reduce income tax expense by the amount of the expense multiplied by (1/(1-T)).

The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Tax Effect equals Permanent Differences multiplied by T.

The cost of debt will be determined based on the financing in place during each stage of project development. Before debt is obtained, a proxy interest rate which will be supported in the original Section 205 filing will be used. This rate is provided on Attachment 8 line 36. If construction debt (wherein principal is drawn down over time) is issued, the rate plus an amortization of fees projected to be incurred on the construction debt during the rate year will be the cost of debt. This construction debt rate (inclusive of fees) will be reset and trued-up every year using the method on Attachment 9 for multi-year construction projects. Once non-construction debt is obtained, the actual interest rate and fees on the debt in place at the end of the year such non- construction debt is obtained will become the cost of debt. In the first full year after non-construction debt is obtained, the cost of debt will be the actual cost of debt determined using the method on Attachment 5. A h

h i
l
i l
f 50% E
i
d 50% d b
ill b
d
il h fi
i i
i
l
d i
i
il
h
i
h
i
d b
h C
i i
Af
h f
ili i
l
d i
i
h l
f
50%
i
h
h i
l
Calculate rate base using 13 month average balance, except ADIT.  The calculation of ADIT in the annual true-up calculation will use the beginning-of-year and end-of-year balances, and will be performed in accordance with IRS regulation Section 1.167(l)- 1(h)(6).  The calculation of ADIT in the annual projection will be performed in accordance with IRS Regulation Section 1.167(l)-1(h)(6).

Removes dollar amount of transmission plant to be included in the development of OATT ancillary services rates and generation step-up facilities, which are deemed to be included in OATT ancillary services. For these purposes, generation step-up facilities are those facilities at a generator substation on which there is no through-flow when the generator is shut down.

Upon enactment of changes in tax law, ADIT balances are re-measured and adjusted in the Company’s books of account, resulting in excess or deficient accumulated deferred income tax assets and liabilities.  Excess or deficient ADIT attributable to timing differences between the amounts of expenses or revenues recognized for income tax purposes and amounts of expenses or revenues recognized for ratemaking purposes as well as subsequent recoverable or refundable amortization of such amounts will be based upon Company records and be calculated and recorded in accordance with ASC 740 and any applicable normalization requirements of the taxing jurisdiction.  The Deficient or (Excess) Deferred Income Tax Adjustment (page 3, line 44) is computed by multiplying each component of Deficient or (Excess) Deferred Income Taxes (page 3, line 40) by the applicable tax gross-up factor.  For each re-measurement of ADIT, the amounts entered as the Deficient or (Excess) Accumulated Deferred Income Taxes component of ADJUSTMENTS TO RATE BASE (page 2, line 22a) or as the Deficient or (Excess) Deferred Income Tax Adjustment component of INCOME TAXES (page 3, line 44) will be supported by Attachment 13 (Deficient or Excess Accumulated Deferred Income Taxes) providing the balance for each taxing jurisdiction at the beginning and end of the year, amortization for the year, calculation of the gross-up to the revenue requirement level and any other information required to support compliance with any applicable normalization requirements.

PDF page 501

Page 1 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
To be completed in conjunction with Appendix III. Line

(1) (2)
(3) (4)
No.
Appendix III, Page, Line, Col.
Transmission
Allocator
1
Gross Transmission Plant plus CWIP
Appendix III, p 2, line 2, col 5 plus line 25, col 5 (Note A)
                                                         -
2
Net Transmission Plant plus CWIP and Abandoned Plant Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5 (Note B)

                                                         -
O&M EXPENSE
3
Total O&M Allocated to Transmission
Appendix III, p 3, line 17, col 5
                                                         -
4
Annual Allocation Factor for O&M
(line 3 divided by line 1, col 3)
0.00%
0.00%
GENERAL AND INTANGIBLE (G&I) DEPRECIATION EXPENSE 5

Total G&I Depreciation Expense
Appendix III, p 3, line 20, col 5 (Note C)
                                                         -
6
Annual Allocation Factor for G&I Depreciation Expense (line 5 divided by line 1, col 3)

0.00%
0.00%
TAXES OTHER THAN INCOME TAXES
7
Total Other Taxes
Appendix III, p 3, line 32, col 5
                                                         -
8
Annual Allocation Factor for Other Taxes
(line 7 divided by line 1, col 3)
0.00%
0.00%
9
Less Revenue Credits
Appendix III, p 1, line 6 col 5
                                                         -
10
Annual Allocation Factor for Revenue Credits (line 9 divided by line 1, col 3)

0.00%
0.00%
11
Annual Allocation Factor for Expense
Sum of lines 4, 6, 8, and 10
0.00%
INCOME TAXES
12
Total Income Taxes
Appendix III, p 3, line 46, col 5
                                                         -
13
Annual Allocation Factor for Income Taxes
(line 12 divided by line 2, col 3)
0.00%
0.00%
RETURN
14
Return on Rate Base
Appendix III, p 3, line 48, col 5
                                                         -
15
Annual Allocation Factor for Return on Rate Base (line 14 divided by line 2, col 3)

0.00%
0.00%
16
Annual Allocation Factor for Return
Sum of lines 13 and 15
0.00%

PDF page 502

Page 2 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template.
(1) (2)
(3) (4)
(5) (6)
(7) (8)
Project Name
CAISO Category
Identifier
Project Gross Plant
Project Net Plant
Annual Return Charge
(Note D)
(Page 1, line 11)
(Col. 3 * Col. 4)
(Note E)
(Page 1, line 16)
(Col. 6 * Col. 7)
1a
Project A
AAAA
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
1b
Project B
BBBB
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
2
Total Schedule 12
                                                  -
                       -    $                                                      -
                                         -
3a
Project C
CCCC
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
3b
Project D
DDDD
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
4
Total Zonal
                                                  -
                       -    $                                                      -
                                         -
5
Other
                                                  -
0.00%
                       -    $                                                      - 0.00%

                                         -
6
Annual Totals
                                                  -
                       -    $                                                      -
                                         -
This worksheet is used to compute project specific revenue requirements for any projects for which such calculation is required by CAISO. Other projects which comprise the remaining revenue requirement on Appendix III will not be entered on this schedule.

Line
No.
Annual Allocation
Factor for Expense
Annual
Expense
Charge
Annual
Allocation
Factor for
Return

PDF page 503

Page 3 of 3
For the twelve months ended 12/31/__
Attachment 1
Project Revenue Requirement Worksheet
DesertLink, LLC
(9) (10)
(11) (12)
(12a) (13)
(14) (15)
(16) Incentive Return
Ceiling Rate
(Note F)
(Sum Col. 5, 8 & 9)
(Note G)
(Sum Col. 10 & 12)
(Note H)
(Sum Col. 10 & 12 Less Col. 13)
(Note I)
(Sum Col. 14 & 15)
1a
                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
1b
                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
2
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                            - 3a

                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
3b
                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
4
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                            - 5

                                         -                              -
                              -                                               -
                             -                          -                                                            -                          -                                            -
6
                                         -                                 -
                                                  -                                -                          -                                                            -                          -                                            - Notes

A
Gross Transmission Plant is that identified on page 2 line 2 of Appendix III inclusive of any CWIP or unamortized abandoned plant included in rate base when authorized by FERC order. B

Net Plant is that identified on page 2 line 14 of Appendix III inclusive of any CWIP or unamortized Abandoned Plant included in rate base when authorized by FERC order less any prefunded AFUDC, if applicable. C

D
E
F
G
Requires approval by FERC of incentive return applicable to the specified project(s).
H
I
True-Up Adjustment is calculated on the Project True-up Schedule for the relevant true-up year.
Line
No.
Project
Depreciation/Amortizatio
n Expense
Annual Revenue
Requirement
Incentive Return in
Basis Points
Competitive
Concession
Total Annual Revenue
Requirement
True-Up
Adjustment
Net Revenue
Requirement
(Attachment 2, Line 28 Incentive
Return * Col. 6 * Col. 11/100)
General and Intangible Depreciation and Amortization Expense includes all expenses (except depreciation and armortization of G&I Asset Retirement Obligations) not directly associated with a project, which is entered on page 3 , column 9.

Project Gross Plant is the total capital investment including CWIP for the project calculated from Company books and records in the same method as the gross plant value in line 1.  This value includes subsequent capital investments required to maintain the facilities to their original capabilities.  Refer to Attachment 1a for detail.

Project Net Plant is the Project Gross Plant Identified in Column 3 less the associated Accumulated Depreciation plus CWIP in rate base if applicable and Unamortized Abandoned Plant.  Refer to Attachment 1a for detail. Project Depreciation Expense is the actual value booked for the project (excluding General and Intangible depreciation) at Appendix III, page 3, line 19, plus amortization of Abandoned Plant at Appendix III, page 3, line 21.  For each project on Attachment 1a, Depreciation Expense is Attachment 1a, Line 2, Column (15) minus Column (3), and Amortization of Abandoned Plant is the difference between Columns (3) and (15) on Attachment 1a, Line 4. The Competitive Concession is the reduction in revenue, if any, that the company agreed to, for instance, to be selected to build facilities as the result of a competitive process and equals the amount by which the  annual revenue requirement is reduced from the ceiling rate.

PDF page 504

Att 1a - Project Plant Detail
 Page 10
Page 1 of 1
For the twelve months ended 12/31/__
Attachment 1a
Project Plant Detail Worksheet
DesertLink, LLC
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
1a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 1

Total Project Transmission Gross Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
2a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 2

Total Project Transmission Accumulated Depreciation
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
3a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 3

Total Project CWIP
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
(3) (4)
(5) (6)
(7) (8)
(9) (10)
(11) (12)
(13) (14)
(15) Project Name
13-month average
4a
Project A
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4b

Project B
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - …

…
                                                                -                                 -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           - 4

Total Project Unamortized Abandoned Plant
                                                                -                                -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -                           -
(1) (2)
Project Name
5a
Project A
                                                                -
5b
Project B
                                                                -
…
…
 …
5
Total Project Transmission Net Plant
                                                                -   Ties to Appendix III, p 2, line 14, col 5 plus line 25 & 27, col 5; Used on Attachment 1, Column (6)
Line
No.
Project
Transmission
Gross Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission Accumulated
Depreciation
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project CWIP
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Unamortized Abandoned Plant
20__
December
20__
January
20__
February
20__
March
20__
April
20__
May
20__
June
20__
July
20__
August
20__
September
20__
October
20__
November
20__
December
Line
No.
Project
Transmission
Net Plant
13-month average
(Line 1 - Line 2 + Line 3 + Line 4)

PDF page 505

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 2
Incentive Return
DesertLink, LLC
Line
1
Rate Base
Appendix III, Page 2, Line 35, Col.5
                                                                         -
2
100 Basis Point Incentive Return
$
Cost
$
%
Weighted
3
Long Term Debt
(Notes Q & R from Appendix III)
                            -
50.00%
0.00%
0.00%
4
Preferred Stock
(Notes Q & R from Appendix III)
                            -
0.00%
0.00%
0.00%
5
Common Stock
(Notes Q, R, & T from Appendix III)
                            -
50.00%
10.80%
5.40%
6
Total (sum lines 3-5)
                            -
5.40%
7
100 Basis Point Incentive Return multiplied by Rate Base (line 1 * line 6)
                                                                         -
8
INCOME TAXES
9
T=1 - {[(1 - SIT) * (1 - FIT)] / (1 - SIT * FIT * p)} =
0.00%
10
CIT=(T/1-T) * (1-(WCLTD/R)) =
0.00%
11
WCLTD
Line 3
0.00%
12
FIT, SIT & p are as given in Appendix III footnote N.
13
1 / (1 - T)
Line 9
                    1.0000
14
Amortized Investment Tax Credit (266.8f) (enter negative)
Appendix III, Page 3, Line 39
                            -
15
Deficient or (Excess) Deferred Income Taxes
Appendix III, Page 3, Line 40
                            -
16
Tax Effect of Permanent Differences (Note B)
Appendix III, Page 3, Line 41
                            -
17
Income Tax Calculation
Line 7 times Line 10
                        -
18
ITC adjustment
Line 13 times Line 14
                            -
NP             1.00                         -
19
Deficient or (Excess) Deferred Income Tax Adjustment
Appendix III, Page 3, Line 44
                            -
NP             1.00                         -
20
Permanent Differences Tax Adjustment
Line 13 times Line 16
                            -
NP             1.00                         -
21
Total Income Taxes
Sum of Lines 17 through 20
                            -
                        -                                                                            - 22

Return and Income Taxes with 100 basis point increase in ROE
                                                                         -
23
Return
(Appendix III, page 3, line 48, col 5)
                                                                         -
24
Income Tax
(Appendix III, page 3, line 46, col 5)
                                                                         -
25
Return and Income Taxes without 100 basis point increase in ROE Sum of Lines 23 and 24

                                                                         -
26
Incremental Return and Income Taxes for 100 basis point increase in ROE Line 22 less Line 25

                                                                         -
27
Rate Base
Line 1
                                                                         -
28
Incremental Return and Income Taxes for 100 basis point increase in ROE divided by Rate Base Line 26 divided by Line 27 0.00%

Notes
A
B
The Tax Effect of Permanent Differences captures the differences in the income taxes due under the Federal and State calculations and the income taxes calculated in Appendix III that are not the result of a timing difference. Cost = Appendix III, Page 4, Line 17,

plus 100 bp
The 100 basis point increase in ROE is used only to determine the increase in return and income taxes associated with a 100 basis point increase in ROE and does not reflect what incentives the Commission may approve for a specific transmission project. The overall ROE inclusive of incentives is subject to the limitations noted in Appendix III, Note T.  Any ROE actual incentive must be approved by the Commission.

PDF page 506

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 3
Formula Rate True-Up
DesertLink, LLC
Any hypothetical amounts or project names in a filed template will be removed and replaced with actual amounts in the first year actual values are available without the need for a section 205 filing to modify the template. Annual True-Up Calculation

Line
1
True-Up Year
2
C
D
                             -
F
G
H
I
J
A
B
E
Project Name
3
Remaining Appendix III
0.0%
                             -
                               -    $                          -
                             -
4a
Project A
AAAA
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
4b
Project B
BBBB
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
5 Total Schedule 12
                             -
                             -                                  -                                  -    $                          -                                -                                -
6a
Project C
CCCC
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
6b
Project D
DDDD
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
7
Total Zonal
                             -
                             -                                  -                                  -    $                          -                                -                                -
8
Other
                             -
0.0%
                             -                                  -                                  -    $                          -                                -                                -
9
                             -
0.0%
                             -                                  -                                  -                                -                                -                                -
10
 $                          -   Total Interest on True-Up - Attachment 6
Prior Period Adjustment
A
B
Source
11
Description of Adjustment
                 -
Notes
1) The revenue received is the total amount of revenue distributed to company in the  year as shown on pages 328-330 of the Form No 1. The Revenue Received is input on line 2, Col. E.
2) From the Attachment 1, lines 1a through 6, col. 16 from the template in which the true-up year revenue requirement was initially projected.
3) From True-Up revenue requirement template Attachment 1, lines 1a through 6, col. 14.
4) 5)
Corrections to true-ups for previous rate years including interest will be computed on Attachment 11 and entered on the appropriate line 3-8 above.
This Attachment 3 is used to calculate the annual formula rate true-up. Any projects for which the RTO requires a true-up on an individual project basis, as shown on Attachment 1, will be computed separately. The remainder of the revenue requirement will also be trued up. The utility will individually enter the projected true-up year revenue requirements in Column C. A percentage of total will be calculated in Column D. Actual revenue received during the true-up year is entered into Column E, line 2 and allocated using the Column D percentage. The utility will prepare this formula rate template with the actual inputs for the true-up year, with the resulting revenue requirement for each line being separately entered in Column F.  In Col. G, Col. F is subtracted from Col. E to calculate the true-up adjustment. Interest on the true-up is computed in Column H. Any adjustments to prior period true-ups are entered in Col.

I.  Col. J computes the total true-up as the sum of Col. G, H and I.
Projected True-Up Year Revenue
Requirement Calculation
True-Up Year
Revenue Received1
Actual True-Up
Year Revenue Req.
CAISO
Identification
Project # Or
Other
Identifier
Net Revenue
Requirement2
% of Total
Revenue
Requirement
Allocation of
Revenue Received

                    (E, Line
2) x (D)
True-Up Net Revenue
Requirement3
Net Under/(Over)
Collection   (F)-(E)
True-Up Interest
Income (Expense)4
(D) x (H, line 10)
Prior Period
Adjustment with
Interest5
Total True-Up
(G) + (H) + (I)
Total Annual Revenue
Requirements
Prior Period Adjustment
(Note 5)
Adjustment
Amount
Attachment
11
Interest due on the true up is calculated for the 24 month period from the start of the true-up year until the end of the year following the true-up year when the true up will be included in rates. Total True up Interest calculate on Attachment 6 and allocated to projects based on the percentage in Column D.

PDF page 507

Page 1 of 2
For the twelve months ended 12/31/__
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Gross Plant in Service
CWIP
LHFFU
Working Capital
Accumulated Depreciation
Month
Transmission
CWIP in Rate Base
Held for Future Use
Materials & Supplies
Prepayments
Transmission
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (Note A)
1
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 2

January
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 3

February
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 4

March
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 5

April
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 6

May
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 7

June
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 8

July
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 9

August
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 10

September
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 11

October
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 12

November
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 13

December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    -                                    - 14

                             -                                -                                  -                                       -                                      -                                      -                                    -                                    - Adjustments to Rate Base

Month
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(Note A)
Note C
Note D
272.8.b & 273.8.k
274.2.b & 275.2.k
276.9.b & 277.9.k
234.8.b & c
15
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 16

January
                   -                                -                                -
                                 -
17
February
                   -                                -                                -
                                 -
18
March
                   -                                -                                -
                                 -
19
April
                   -                                -                                -
                                 -
20
May
                   -                                -                                -
                                 -
21
June
                   -                                -                                -
                                 -
22
July
                   -                                -                                -
                                 -
23
August
                   -                                -                                -
                                 -
24
September
                   -                                -                                -
                                 -
25
October
                   -                                -                                -
                                 -
26
November
                   -                                -                                -
                                 -
27
December
                   -                                -                                -                                  -                                       -                                      -                                      -                                    - 28

                             -                                -                                  -                                       -                                      -                                      -                                    -
Line
No
General &
Intangible
General & Intangible
207.58.g less
207.57.g for end of
year, records for
other months
205.5.g & 207.99.g
less 207.98.g for
end of year, records
for other months
Note B - page 2,
column C
214.47.d for end of
year, records for other
months
227.8.c & 227.16.c for
end of year, records for
other months
111.57.c for end of
year, records for other
months
219.25.c less ARO for
end of year, records
for other months
219.28.c & 200.21.c
less ARO for end of
year, records for other
months
Average of the 13
Monthly Balances
Unamortized
Regulatory Asset
Unamortized
Abandoned Plant
Account No. 281
Accumulated
Deferred Income
Taxes (Note E)
Account No. 282
Accumulated Deferred
Income Taxes (Note E)
Account No. 283
Accumulated Deferred
Income Taxes (Note E)
Account No. 190
Accumulated
Deferred Income
Taxes (Note E)
Account No. 255
Accumulated
Deferred Investment
Credit (Note I)
Consistent with
266.8.b & 267.8.h
Average of the 13
Monthly Balances

PDF page 508

Page 2 of 2
For the twelve months ended 12/31/
Attachment 4
Rate Base Worksheet
DesertLink, LLC
Total CWIP
(a) (b)
(c) = (a) - (b)
Company records
29
December
                   -                                -                                -                                  -
30
January
                   -                                -                                -                                  -
31
February
                   -                                -                                -                                  -
32
March
                   -                                -                                -                                  -
33
April
                   -                                -                                -                                  -
34
May
                   -                                -                                -                                  -
35
June
                   -                                -                                -                                  -
36
July
                   -                                -                                -                                  -
37
August
                   -                                -                                -                                  -
38
September
                   -                                -                                -                                  -
39
October
                   -                                -                                -                                  -
40
November
                   -                                -                                -                                  -
41
December
                   -                                -                                -                                  -
                             -                                -                                  -
Unfunded Reserves   (Notes A and F and G)
(a) (b)
(b.i)
(b.ii)
(c) (d)
(e) (f)
(g) (h)
List of all reserves
Amount
42a
Reserve 1
 -
 -
                               -
 -
 -
 -
                                 -                                    -
42b
Reserve 2
 -
 -
                               -
 -
 -
 -
                                 -                                    -
43
Total
                               -
                                 -
Notes:
A
Calculate using 13 month average balance, except ADIT which is calculated based on the average of the beginning of the year and the end of the year balances
B
C
D
Recovery of abandoned plant is limited to any abandoned plant recovery authorized by FERC.
E
ADIT is computed using the average of the beginning of the year and the end of the year balances. Electric ADIT only, Excludes ARO-related ADIT.
F
G
H
I
Balance of Account 255 will be reduced by prior flow throughs and excluded if the utility chooses to utilize amortization of tax credits against taxable income.
Reconciliation of CWIP in Rate Base to FERC Form 1 - Note B
Less: CWIP and
AFUDC Excluded
from Rate Base
CWIP allowed in
Rate Base
216.b for end of
year, records for
other months
Average of the 13
Monthly Balances
FERC balance sheet
account where
reserves are
recorded
FERC income
statement account
where expenses are
recorded
Enter 1 if NOT in a
trust or reserved
account, enter zero (0)
if included in a trust or
reserved account
Enter 1 if the accrual
account is included in
the formula rate, enter
(0) if the accrual
account is NOT
included in the formula
rate
Enter the percentage
paid for by customers
less the percent
associated with an
offsetting liability on
the balance sheet (Note
H) Allocation (Plant or
Labor Allocator)
Amount Allocated,
col. c x col. d x col. e
x col. f x col. g
Recovery of CWIP in rate base must be approved by FERC.  Lines 29-41 of page 2 provide a reconciliation of the Company's total CWIP to the CWIP allowed in rate base. The annual report filed pursuant to the Protocols will include for each project under construction (i) the CWIP balance eligible for inclusion in rate base; (ii) the CWIP balance ineligible for inclusion in rate base; and (iii) a demonstration that AFUDC is only applied to the CWIP balance that is not included in rate base The annual report will also describe the reconciliation prepared on this Attachment

Recovery of a Regulatory Asset is permitted only for pre-commercial and formation expenses, and is subject to FERC approval before the amortization of the Regulatory Asset can be included in rates. Recovery of any other regulatory assets requires authorization from the Commission.

The Formula Rate shall include a credit to rate base for all unfunded reserves (funds collected from customers that (1) have not been set aside in a trust, escrow or restricted account; (2) whose balance are collected from customers through cost accruals to accounts that are recovered under the Formula Rate; and (3) exclude the portion of any balance offset by a balance sheet ac count (see Note H)).  Each unfunded reserve will be included on lines 42 above. The allocator in Col. (g) will be the same allocator used in the formula for the cost accruals to the account that is recovered under the Formula Rate.  Since reserves can be created by creating an offsetting balance sheet account, rather than through cost accruals, the amount to be deducted from rate base should exclude the portion offset by another balance sheet account. Not all unfunded reserves are created only from contributions from customers. Many are created by creating an offsetting liability in whole or in part.  Column (f) ensures only the portion of the unfunded reserve contributed by the customer (and not created by an offsetting liability) is a reduction to rate base.

The inputs in Column (f) are the percentage of the unfunded reserve that was created by an offsetting liability. The percentage shown in Column (f) is then equal to the percentage that customers have contributed to the unfunded reserve.

PDF page 509

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 5
Return on Rate Base Worksheet
DesertLink, LLC
RETURN ON RATE BASE ( R )
$
1
Long Term Interest (117, sum of 62.c through 67.c) (Note D)
                                -
2
Preferred Dividends (118.29c) (positive number)
                                -
3
Proprietary Capital (Line 25 (c))
                                -
4
Less Preferred Stock (Line 9)
                                -
5
Less Account 216.1 Undistributed Subsidiary Earnings (Line 25 (d))
                                -
6
Less Account 219 Accum. Other Comprehensive Income (Line 25 (e))
                                -
7
Common Stock
(Sum of Lines 3 through 6)
                                -
$
%
Cost
Weighted
8
Long Term Debt
Line 25 (a), Note A and Appendix III Note Q
                                -
50.00%
0.000%
0.00%
=WCLTD
9
Preferred Stock
Line 25 (b), Note B and Appendix III Note Q
                                -
0.00%
0.00%
0.00%
10
Common Stock
Line 7, Note C  and Appendix III Notes Q and T
                                -
50.00%
9.80%
4.900%
11
Total
(Sum of Lines 8 through 10)
                                -
4.90%
=R
(a) (b)
( c )
(d) ( e )
Monthly Balances for Capital Structure
12
December (Prior Year)
                               -                                 -                             -                                   -                                 - 13

January
                               -                                 -                             -                                   -                                 - 14

February
                               -                                 -                             -                                   -                                 - 15

March
                               -                                 -                             -                                   -                                 - 16

April
                               -                                 -                             -                                   -                                 - 17

May
                               -                                 -                             -                                   -                                 - 18

June
                               -                                 -                             -                                   -                                 - 19

July
                               -                                 -                             -                                   -                                 - 20

August
                               -                                 -                             -                                   -                                 - 21

September
                               -                                 -                             -                                   -                                 - 22

October
                               -                                 -                             -                                   -                                 - 23

November
                               -                                 -                             -                                   -                                 - 24

December
                               -                                 -                             -                                   -                                 - 25

13-Month Average
                               -                                 -                             -                                   -                                 - Notes

A
B
Preferred Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112 line 3.c in the Form No. 1 C

Common Stock balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on Form 1 page 112 line 16.c less lines 3.c , 12.c, and 15.c D

Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies Long Term Debt

(Note A)
Preferred Stock
(112.3.c)
Proprietary
Capital (112.16.c)
Undistributed Sub
Earnings 216.1
(112.12.c)
Accum Other Comp.
Income 219
(112.15.c)
Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, lines 18.c to 21.c, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 510

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6
Interest on True-Up
DesertLink, LLC
Appendix III K23
Line
Rate Year
Rate Year
Projected Revenue Requirement (Note A)
1
                                                                                         -
Less
 $                             -
Equals
 $                        -
Note A - Projected ATRR for the true-up year from Page 1, Line 1 of Projection Appendix III minus Line 6 of Projection Appendix III. Note B - Actual Net ATRR for the true-up year from Page 1, Line 9 of True-Up Appendix III. Interest Rate on Amount of Refunds or Surcharges

Months
Amortization
2
0.000%
An over or under collection will be recovered pro rata over year collected, held for one year and returned pro rata over next year Monthly

3
January
Rate Year
                                -
0.000%
12
                          -
                              -
4
February
Rate Year
                                -
0.000%
11
                          -
                              -
5
March
Rate Year
                                -
0.000%
10
                          -
                              -
6
April
Rate Year
                                -
0.000%
9
                          -
                              -
7
May
Rate Year
                                -
0.000%
8
                          -
                              -
8
June
Rate Year
                                -
0.000%
7
                          -
                              -
9
July
Rate Year
                                -
0.000%
6
                          -
                              -
10
August
Rate Year
                                -
0.000%
5
                          -
                              -
11
September
Rate Year
                                -
0.000%
4
                          -
                              -
12
October
Rate Year
                                -
0.000%
3
                          -
                              -
13
November
Rate Year
                                -
0.000%
2
                          -
                              -
14
December
Rate Year
                                -
0.000%
1
                          -
                              -
15
                          -
                              -
Annual
16
January through December
Rate Yr. + 1                                 -
0.000%
12
                          -
                              -
Over (Under) Recovery Plus Interest Amortized and Recovered Over 12 Months Monthly

17
January
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 18

February
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 19

March
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 20

April
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 21

May
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 22

June
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 23

July
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 24

August
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 25

September
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 26

October
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 27

November
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 28

December
Rate Yr. + 2                                 -
0.000%
                          -                                 -                                 - 29

                          -
30
Total Amount of True-Up Adjustment
 $                           -
31
Less Over (Under) Recovery
 $                        -
32
Total Interest
 $                           -
Actual Net Revenue
Requirement (Note B)
Over (Under)
Recovery
Over (Under)
Recovery Plus
Interest
Monthly Interest
Rate on Attachment
6a
Calculated
Interest
Surcharge (Refund)
Owed
Calculation of Interest

PDF page 511

Page 1 of 1
For the twelve months ended 12/31/
Attachment 6a
True-Up Interest Rate Calculator
DesertLink, LLC
This Attachment is used to compute the interest rate to be applied to each year's revenue requirement true-up.
Applicable FERC Interest Rate (Note A):
1
Rate Year January
0.00%
2
Rate Year February
-
3
Rate Year March
-
4
Rate Year April
-
5
Rate Year May
-
6
Rate Year June
-
7
Rate Year July
-
8
Rate Year August
-
9
Rate Year September
-
10
Rate Year October
-
11
Rate Year November
-
12
Rate Year December
-
13
Rate Year Plus 1  January
-
14
Rate Year Plus 1  February
-
15
Rate Year Plus 1  March
-
16
Rate Year Plus 1  April
-
17
Rate Year Plus 1  May
-
18
Average Rate
0.00%
19
Monthly Average Rate
0.00%
Note A - Lines 1-17 are the FERC interest rates under section 35.19a of the regulations for the period shown. Line 18 is the average of lines 1-17.

PDF page 512

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 7
Weighted Average Federal and State Income Tax Rates
DesertLink, LLC
Subchapter C
Mutual
Pensions, IRAs
UBTI
Non-Taxpaying
Weighted
Line
Description
Source
Corporations
Individuals
Funds
Keogh Plans
Entities
Entities
Average
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) 1
Weighted Marginal Federal Income Tax Rate
Note A
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
2
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
3
Weighted Average
Line 1 x Line 2
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4
Weighted Average Federal Income Tax Rate
Sum of Line 3, Col. (c)-(h)
0.00%
5
Weighted Marginal State Income Tax Rate
Note C
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
6
Allocated Income Percentage
Note B
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
7
Weighted Average
Line 5 x Line 6
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
8
Weighted Average State Income Tax Rate
Sum of Line 7, Col. (c)-(h)
0.00%
A
For each Rate Year, DesertLink will develop a schedule calculating the weighted average federal income tax rate for each category of partners. B

This percentage is developed based on the distributive income allocated to each category of partners rather than their respective ownership percentages. C

For each Rate Year, DesertLink will develop a schedule calculating the weighted average state income tax rate for each category of partners.

PDF page 513

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 8
Cost of Debt Prior to Issuing Non-Construction Financing
DesertLink, LLC
This Attachment 8 is to be utilized to determine the cost of debt prior to issuing non-construction financing.  Once non-construction financing is issued the cost of debt shall be determined using the methodology described in Note Q on Appendix III. If construction debt has not or will not be issued when construction starts, a proxy rate will be used for the cost of debt, which will be supported in the initial section 205 filing. The proxy rate will be entered on line 36 of this attachment. If construction financing is obtained, all rates, fees and monthly debt balances will be subject to true up pursuant to Attachment 9. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template. Line No

1
Interest rate on Construction Debt for Rate Year - Line 19 (g)
0.00%
2
Rate Year Debt Fee expense - Line 35 (e)
0.00%
3
Total Cost of Debt - Sum of Lines 1 and 2
0.0000%
Interest Rate Information
4
Commitment Fee Rate (%)
5
Projected Average Drawn Rate for Rate Year (%) - Note A
Month During Rate Year
Total Loan Amount ($000)
Interest Expense ($000)
(a) (b)
(c) (d)
(e) (f)
(g) 6
December Prior Year
                            -                                         -                                          -                                          - 7

January
                            -                                         -                                          -                                          - 8

February
                            -                                         -                                          -                                          - 9

March
                            -                                         -                                          -                                          - 10

April
                            -                                         -                                          -                                          - 11

May
                            -                                         -                                          -                                          - 12

June
                            -                                         -                                          -                                          - 13

July
                            -                                         -                                          -                                          - 14

August
                            -                                         -                                          -                                          - 15

September
                            -                                         -                                          -                                          - 16

October
                            -                                         -                                          -                                          - 17

November
                            -                                         -                                          -                                          - 18

December
                            -                                         -                                          -                                          - 19

Average of the 13 Monthly Balances
                            -
                                        -                                          -
0.00%
Example Fee Calculation - All amounts represent actual rate year expenses.
(a) (b)
(c) (d)
(e) (f)
(g) Origination Fees
Rate/Fees
Gross Fee Amount ($000)
Year Fee Incurred
20
Underwriting Discount
0.00%
 -
 -
21
Arrangement Fee
0.00%
 -
 -
22
Upfront Fee
0.00%
 -
 -
23
Rating Agency Fee
0.00%
 -
 -
24
Legal Fees
0.00%
 -
 -
25
Other
0.00%
 -
 -
26
   Total Issuance Expense / Origination Fees - Sum of Lines 20-25
 -
 -
 -
 -
27
28
Annual Fees
29
Annual Rating Agency Fee
0.00%
N/A
 -
N/A
N/A
30
Annual Bank Agency Fee
0.00%
N/A                                      -
N/A
N/A
31
Utilization Fee
0.00%
N/A
 -
N/A
N/A
32
Other Fees
0.00%
N/A
 -
N/A
N/A
33
Total Fees
 -
 -
 -
 -
34
13 Month Average Debt balance - Line 19 (c)
                                        -
35
Rate Year cost of fees
0.00%
36
Proxy Debt rate. Used prior to issuance of construction financing and supported in initial section 205 filing. 3.2220%

Notes
A
LIBOR
0.0000%
Spread
2.3500%
Total
2.3500%
If construction financing has been obtained, the cost of debt prior the issuance of non-construction financing shall be based on the terms of the construction financing and determined below. Up-front fees including origination fees will be amortized and included in the cost of debt.

Principal Drawn
($000)
Unutilized Loan
Balance ($000)
Commitment Fee &
Utilization Fee ($000)
Effective Annual
Interest Rate (%)
Fee Amortization Period
(years)
Rate Year Amortized Fee
Amount, col. b / col. d
Prior Years Accumulated
Fee Amortization
Unamortized Balance
- End of Rate Year
Projected rate will be Average LIBOR for rate year + spread. Spread will be supported in initial section 205 filing. LIBOR will be updated based on information in the Wall Street Journal as of the 15th day of the month prior to population of this template.

PDF page 514

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 9
True-Up - Construction Financing Cost of Debt
DesertLink, LLC
One time up-front debt fees, including origination fees will be amortized and included in the cost of debt.
Line No.
$
1
Long Term Interest and Fees (117, sum of 62.c through 67.c) -- Notes A and B
                                    -
2
Line of Credit Fees (68.c) -- Note C
                                    -
3
Total Interest and Fees
                                    -
13 Month Average Long-Term Debt - Notes A and D
Month During Rate Year
Long Term Debt
(a) (d)
4
December Prior Year
                                    -
5
January
                                    -
6
February
                                    -
7
March
                                    -
8
April
                                    -
9
May
                                    -
10
June
                                    -
11
July
                                    -
12
August
                                    -
13
September
                                    -
14
October
                                    -
15
November
                                    -
16
December
                                    -
17
Average of the 13 Monthly Balances
                                    -
18
True-Up Cost of Debt (Line 3 / Line 17)
0.00%
Notes
A
B
Long-term interest will exclude any short-term interest included in FERC Account 430, Interest on Debt to Associated Companies.
C
Line of credit fees will include only those related to long-term debt and not for short-term debt.
D
Long-term debt will exclude any short-term debt included in FERC Account 233, Notes Payable to Associated Companies.
This Attachment 9 is to be utilized only in the event construction financing has been obtained to compute the actual cost of debt to be included in the return on rate base calculation for the true-up each year prior to the issuance of non-construction financing. Once non-construction financing has been obtained the cost of debt shall be determined using the methodology described in Note Q on Appendix III. Any hypothetical amounts in a filed template will be removed and replaced with actual amounts in the first year actual construction loans are borrowed or projected to be borrowed without the need for a section 205 filing to modify the template.

Long Term debt balance will reflect the 13 month average of the balances, of which the 1st and 13th are found on page 112, line 24, columns d and c, respectively, in the Form No. 1; the cost is calculated by dividing line 1 by the Long Term Debt balance on line 8.

PDF page 515

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 10
Depreciation Rates
DesertLink, LLC
TRANSMISSION AND GENERAL PLANT DEPRECIATION RATES
Annual Depreciation Rates
Line No.
(Note A)
INTANGIBLE PLANT
1
303.1
Contributions in Aid of Construction
Note B
2
303.2
Interconnections
2.27%
3
303.3
Licenses
1.59%
TRANSMISSION PLANT
4
350.2
Land Rights
1.43%
5
351.1
Computer Hardware
20.00%
6
352.0
Structures & Improvements
1.95%
7
353.0
Station Equipment
2.58%
8
354.0
Towers & Fixtures
1.86%
9
355.0
Poles & Fixtures
2.17%
10
356.0
Overhead Conductors & Devices
2.01%
11
392.0
Transportation Equipment
10.00%
12
393.0
Stores Equipment
6.67%
13
394.0
Tools, Shop, and Garage Equipment
12.50%
14
397.2
Computer Software
11.64%
Notes
A
These depreciation rates will not be changed absent a FERC order.
B
GENERAL PLANT
In the event a Contribution in Aid of Construction (CIAC) is made for a transmission facility, the transmission depreciation rates above will be weighted based on the relative amount of underlying plant booked to the accounts shown in lines 4-12 above, and the resultant weighted average depreciation rate will be used to amortize the CIAC.   The CIAC depreciation rate for each facility will be determined at the time the plant is placed into service, and will not change  without FERC approval.

PDF page 516

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 11
Prior Period Adjustments
DesertLink, LLC
(a) (b)
Calendar Year
Line No. Description
Source
Revenue Impact of Correction
Revenue Requirement
1
Filing Name and Date
                                                        -
2
Original Revenue Requirement
                                                              -
3
4
Description of Correction 1
                                                              -
5
Description of Correction 2
                                                              -
6
7
Total Corrections
Line 4 + 5
                                                              -
8
9
Corrected Revenue Requirement
Line 2 + 7
                                                              -
10
11
12
Total Corrections
Line 7
                                                              -
13
14
Average Monthly FERC Refund Rate
Note A
0.00%
15
Number of Months of Interest
Note B
30
16
Interest on Correction
Line 12 x 14 x 15
                                                              -
17
18
Total Annual Amount Due from / (to) Customers
Line 12 + 16
                                                              -
Notes
A
B
The interest rate on corrections will be the average monthly FERC interest rate for the period from the beginning of the year being corrected through the most recent  month available as of the time the correction is computed and included in an annual filing.

The number of months interest due on the correction will be the number of months from the beginning of the year being corrected through June of the year in which the correction will be reflected in rates. In this manner the interest computed will reflect all years prior to when the correction is reflected in rates plus interest on the average unrefunded balance of the correction during the year the correction is reflected in rates.

PDF page 517

Page 1 of 1
For the twelve months ended 12/31/__
Attachment 12
Revenue Credit Detail
DesertLink, LLC
(a) (b)
(c) = (a) - (b)
Line No.
(Note A)
Source
Company Total
Less: Non Transmission
Transmission-related
1
Account 454 - Rent from Electric Property
2
Joint pole attachments - telephone
Company books
                                          -                                                      -                                                                                                                 - 3

Joint pole attachments - cable
Company books
                                          -                                                      -                                                                                                                 - 4

Underground rentals
Company books
                                          -                                                      -                                                                                                                 - 5

Transmission tower wireless rentals
Company books
                                          -                                                      -                                                                                                                 - 6

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 7

Other rentals
Company books
                                          -                                                      -                                                                                                                 - 8

Account 454 Revenue Credit
Form 1 300.19.b
                                          -                                                      -                                                                                                                 - 9

Account 456.1 Other Operating Revenues
10
CAISO NITS
Company books
                                          -                                                      -                                                                                                                 - 11

CAISO Point to Point
Company books
                                          -                                                      -                                                                                                                 - 12

Over/Under recovery deferral
Company books
                                          -                                                      -                                                                                                                 - 13

Other Transmission Service Revenues
Company books
                                          -                                                      -                                                                                                                 - 14

Other
Company books
                                          -                                                      -                                                                                                                 - 15

Total Per Books
Form 1 330.n
                                          -                                                      -                                                                                                                 - 16

Less: revenues received pursuant to this Formula Rate
                                          -                                                      -                                                                                                                 - 17

Less: Over/Under recovery deferral
                                          -                                                      -                                                                                                                 - 17a

Less: Revenue Credits included in the TRBAA
                                          -                                                      -                                                                                                                 - 18

Account 456.1 Revenue Credit
                                          -                                                      -                                                                                                                 - 19

Total Revenue Credits
(Line 8 + line 18)
                                          -                                                      -                                                                                                                 - Note A

All 454 and 456.1 revenues will be detailed from Company books and records or FERC Form 1, and additional rows added if necessary.  Non-transmission-related amounts will be deducted to determine transmission-related amounts. (Line 15 - line 16 - line 17

- line 17a)

PDF page 518

DesertLink, LLC
Attachment 13 - Excess or Deficient Accumulated Deferred Income Taxes - Summary
[Year]
[Projected or Actual]
Line No.
1
2
[List of tax law changes, accounting treatment, and asscociated explanatory notes.]
3
Rate Base Adjustment Mechanism - Summary
4
Account
Amount
References
5
182.3 (debit or <credit>)
                        -
6
254 (debit or <credit>)
                        -
7
Total Deficient or (Excess) ADIT (sum of lines 5-6)
                        -   To Appendix III, Page 2, Line 22a, Col. (3)
8
9
Income Tax Allowance Adjustment Mechanism - Summary
(a) (b)
(c) (d)
(e) (f)
10
11
[Insert rows as necessary]
                        -
                        -
11a
[Insert rows as necessary]
                        -
                        -
11…
[Insert rows as necessary]
                        -
                        -
12
Total
(sum of lines 11_)
                        -
                        -
13
14
[Explanatory statements as needed]
The primary purposes of this worksheet are to:
 - reconcile the amounts of regulatory assets and liabilities comprising the rate base adjustment mechanism on Appendix III, Page 2, Line 22a (ADJUSTMENTS TO RATE BASE > Deficient or (Excess) ADIT) as of the beginning and end of the current test period (summarized beginning at Line 3 below) and

- to support the amount of excess deferred tax expense or benefit recognized due to enacted change(s) in tax rate(s) on Appendix III, Page 3, Line 40 (INCOME TAXES > Deficient or (Excess) Deferred Income Taxes) and the effect of such excess deferred tax expense or benefit on the revenue requirement as reflected in the income tax allowance adjustment mechanism on Appendix III, Page 3, Line 44 (INCOME TAXES > Deficient or (Excess) Deferred Income Tax Adjustment) during the test period (summarized beginning on Line 9 below).

This worksheet supports the computation of the projected revenue requirement or, as appropriate, the actual revenue requirement used to compute the true-up adjustment.
Each tax law change addressed by this worksheet with its associated explanatory note is listed below.  Amounts related to each tax law change are provided and supported throughout this worksheet.  Additional lines and explanatory notes will be added to this worksheet as necessary as tax law changes are enacted without the need for an FPA Section 205 filing.

The amounts summarized above are computed in the Rate Base Adjustment Mechanism-Reconciliation of Beginning and End of Test Period Balances section of the worksheet with proration and averaging of activity during the test period computed in different section of Attachment 13.1 for projected revenue requirement calculations and actual revenue requirement calculations.

 Amortization or
Mitigation of
Deficient or
<Excess> ADIT
 Tax Gross-up
Factor
 Amortization or
Mitigation with
Tax Gross-up
 To Appendix III,
Page 3, Line 40,
Col. (3)
 To Appendix III,
Page 3, Line 44,
Col. (3)

PDF page 519

15
Rate Base Adjustment Mechanism - Reconciliation of Beginning and End of Test Period Balances
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
16
Description (+ = debit, <> = credit)
Amortization period and method
17
[Insert rows as necessary]
                        -                           -                           -                           -                           - 17a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 17...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 18

Total for account 182.3
(sum of lines 17_)
                        -                           -                           -                           -                           - 19

 FN1. pg 232
 FN1. pg 232
20
[Insert rows as necessary]
                        -                           -                           -                           -                           - 20a

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20b

[Insert rows as necessary]
                        -                           -                           -                           -                           - 20...

[Insert rows as necessary]
                        -                           -                           -                           -                           - 21

Total for account 254
(sum of lines 20_)
                        -                           -                           -                           -                           - 22

 FN1. pg 278
 FN1. pg 278
23
24
Income Tax Allowance Adjustment Mechanism
25
26
Amortization of Excess or Deficient ADIT
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
27
Description (+ = debit, <> = credit)
Comments
28
[Insert rows as necessary]
                        -                           -                           -                           -                            - 28a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 28...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 29

Total for account 182.3
(sum of lines 28_)
                        -                           -                           -                           -                            - 30

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30a

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30b

[Insert rows as necessary]
                        -                           -                           -                           -                            - 30...

[Insert rows as necessary]
                        -                           -                           -                           -                            - 31

Total for account 254
(sum of lines 30_)
                        -                           -                           -                           -                            - 32

Total amortization and offsetting entries
(sum of lines 29 & 31)                         -                           -                           -                           -                            - 33

Net income tax expense or benefit
(sum of lines 32(f) & 32(g))
                        -
 To line 11
Balance at
Beginning of
Year
Re-
measurement of
ADIT
Annual
Amortization
(Note 4)
Other
Adjustments
(Note 5)
Balance at End
of Year
(d)+(e)+(f)+
(g) Whether subject
to normalization
rules
(Note 6)
Analysis - Balances of tax-related regulatory assets and liabilities include tax gross-up.  Accordingly, for the regulatory assets and liabilities for deficient or excess deferred taxes included in rate base, the related deferred tax assets and liabilities are also included in rate base.  Remeasurements in column (e) are described in Notes 2 and 3 and are based on the journal entry below and the support on the worksheet for the applicable tax law change.  Averaging or proration of amounts affecting rate base is computed on different sections of Attachment 13.1 for projected revenue requirement and actual revenue requirement. The income tax allowance adjustment mechanism may include amortization of excess or deficient ADIT pertaining to deferred tax expense or benefit reflected in rates at a historical tax rate when the underlying timing difference(s) originated (computed under Amortization of Excess or Deficient ADIT within the Income Tax Allowance Adjustment Mechanism section of this worksheet) as well as an adjustment for tax law changes with prospective effective dates intended to mitigate the over- or under- recovery of deferred income taxes originating prior to the effective date of such tax law changes (computed under Adjustment for Tax Law Changes with Prospective Effective Dates within the Income Tax Allowance Adjustment Mechanism section of this worksheet).

Annual
Amortization
from Table
Above
(Note 4)
Debit or
<Credit> to
Account 410.1
Debit or
<Credit> to
Account 411.1
Debit or
<Credit> to
Account 190
Debit or
<Credit> to
Account 283

PDF page 520

34
Adjustment for Tax Law Changes with Prospective Effective Dates
35
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) 36
37
 (c) x (d)
1 / (1- (d))
 (e) x (f)
 - [(c) x (h)]
 (e) + (i)
 (j) x (f)
38
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
38…
[Insert rows as necessary]
                        -
                        -
                         -                           -                           -
 To line 11
39
Note 1 - Summary of re-measurement of ADIT resulting from tax law changes
40
41
Note 1a - Summary of re-measurement of ADIT resulting from
[name of tax law change]
Additional information is provided in Note
42
Re-measurement entry
(a) (b)
(c) 43
Account
Comments or References
44
190
45
281
46
282
47
283
48
182.3 (tax-related, included in rate base - protected)
49
182.3 (tax-related, included in rate base - unprotected)
50
182.3 (tax-related, not in rate base))
51
190 (related to portion of acct. 182.3 not in rate base)
52
254 (tax-related, included in rate base - protected)
53
254 (tax-related, included in rate base - unprotected)
54
254 (tax-related, not in rate base)
55
283 (related to portion of acct. 254 not in rate base)
56
Account 410.1
57
Account 411.1
58
Account 410.2
59
Account 411.2
60
Total
 (sum of lines
                        -
61
[Insert additional analysis.]
In the case of tax law changes with an effective date(s) after the beginning of the test period, the impact of a timing difference on current tax expense or benefit differs from the impact on ADIT.  For example, in the case of a deductible timing difference originating in a tax year with a higher enacted tax rate than will apply when the difference will reverse, the current tax benefit will exceed the deferred tax expense.  In this situation, the adjustment computed below to recoverable income tax expense is made in order to avoid over-recovering income tax expense in the current test period due to the excess of current tax benefit over deferred tax expense (computed based on the estimated amount of the future tax liability) with respect to a given timing difference.  The adjustment to recoverable tax expense during the test period in which a timing difference originates mitigates the need for refund of a regulatory liability for excess deferred taxes in a future period (or, as applicable, the need for recovery of a regulatory asset for deficient deferred taxes in a future period).  Amounts in column (i) are reported in the Income Tax Allowance Adjustment Mechanism - Summary on this worksheet.

 Originating
Taxable or
(Deductible)
Book / Tax
Difference for
Test Year
 Tax Rate for
Test Year
 Current Tax
Expense or
(Benefit) in Test
Year
 Tax Gross-up
Factor for Test
Year
 Revemue
Requirement
Imapct for Test
Year
 Enacted Tax
Rate for the
Reversal Year(s)
 Deferred Tax
Expense or
(Benefit) in Test
Year
 Total Tax
Expense or
(Benefit) in Test
Year
 Adjustment to
Mitigate
Over/under-
recovery of
Deferred Taxes
The purposes of this portion of the worksheet are, for each change in tax law, to explain:
- how any ADIT accounts were re-measured,
- the excess or deficient ADIT contained therein, and
- the accounting for any excess or deficient amounts in Accounts 182.3 (Other Regulatory Assets) and 254 (Other Regulatory Liabilities).
Note 2 describes how ADIT accounts are re-measured upon a change in income tax law.  A separate summary (i.e., Note 1a, Note 1b, etc.) will be added for each tax law change resulting in a re-measurement of ADIT. Debit or

<Credit>

PDF page 521

62
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
63
[Insert additional analysis.]
64
Note 1b - Summary of
[name of tax law change]
Additional information is provided in Note
65
66
67
68
69
[Continuation of note with respect to particular changes in tax law.]
70
[Insert additional notes as needed.]
Note 2 - Explanation of how ADIT accounts are re-measured upon a change in income tax law
Deferred tax assets and liabilities are adjusted (re-measured) for the effect of the changes in tax law (including tax rates) in the period that the change is enacted.  Adjustments are recorded in the appropriate deferred tax balance sheet accounts (Accounts 190, 281, 282 and 283) based on the nature of the temporary difference and the related classification requirements of the accounts.   If as a result of action or expected action by a regulator, it is probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, a regulatory asset or liability is recognized in Account 182.3 (Other Regulatory Assets), or Account 254 (Other Regulatory Liabilities), as appropriate, for that probable future revenue or reduction in future revenue.  Re-measurements of deferred tax balance sheet accounts may also result in re-measurements of tax-related regulatory assets or liabilities that had been recorded prior to the change in tax law.  If it is not probable that the future increase or decrease in taxes payable due to the change in tax law or rates will be recovered from or returned to customers through future rates, tax expense is recognized in Account 410.2 (Provision for Deferred Income Taxes, Other Income or Deductions) or tax benefit is recognized in Account 411.2 (Provision for Deferred Income Taxes-Credit, Other Income or Deductions), as appropriate.

Note 3 - [Complete to support information above.]
Note 4 - The amortization of the deficient or excess ADIT reducing Account 254 (Other Regulatory Liabilities) is recorded with credits to Account 411.1 (Provision for Deferred Income Taxes – Credit, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance.  The amortization of the deficient or excess ADIT reducing Account 182.3 (Other Regulatory Assets) is recorded with debits to Account 410.1 (Provision for Deferred Income Taxes, Utility Operating Income) and to Account 190 (Accumulated Deferred Income Taxes) or Account 283 (Accumulated Deferred Income Taxes—Other), as appropriate, in accordance with the Commission’s Accounting for Income Taxes Guidance. This activity is summarized in the table "Income Tax Allowance Mechanism - Projected" or the table "Income Tax Allowance Mechanism - Actual," as appropriate.  The annual amortization in the tables above reflects tax gross-up and is stated at the revenue requirement level.

Note 5 - [Complete to support information above.]
Note 6 -  The worksheet indicates whether each excess or deficient ADIT amounts are protected (i.e., subject to normalization rules of a taxing jurisdiction) or unprotected (i.e., not subject to normalization rules of a taxing jurisdiction).  To the extent that normalization requirements apply to ADIT remeasurements, additional computations (e.g., proration of excess deferred tax activity related to future test periods) may be necessary.

PDF page 522

DesertLink, LLC
Attachment 13.1 - Regulatory Assets/Liabilities for Deficient/Excess ADIT - Averaging and Proration Adjustments
Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)
[Year]
[Projected or Actual]
Line No.
1
Rate year =
2
Test period days after rates become effective
3
4
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
5
6
Beginning balance  (debit or <credit>)
                        -
7
Less:  Portion not related to transmission
                        -
8
Less:  Portion not reflected in rate base
                        -
9
Subtotal:  Portion reflected in rate base
                        -
10
Less:  Portion subject to proration
                        -
11
Portion subject to averaging  (debit or <credit>)
                        -
12
Ending balance  (debit or <credit>)
                        -
13
Less:  Portion not related to transmission
                        -
14
Less:  Portion not reflected in rate base
                        -
15
Subtotal:  Portion reflected in rate base
                        -
16
Less:  Portion subject to proration (before proration)
                        -
17
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
18
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 36(n)
19
Average balance of portion subject to averaging
                        -
20
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 5
This attachment includes sections that are populated only with actual data and thus, these sections remain blank when the formula rate template is calculating a projected revenue requirement. Columns (i) through (n) below are not used for the projection and are only populated with actual data for the Annual Update.

Note 1 - The computations below apply the proration rules of Treasury Regulation section 1.167(l)-1(h)(6) to the annual activity of the portions of the deficient or excess accumulated deferred income taxes recorded in account 182.3 or 254 that are subject to the normalization requirements.  Activity related to the portions of the account balances reflected in rate base but not subject to the proration requirement is averaged instead of prorated.  The balances below include tax gross-up.  The corresponding portions of the deferred tax asset related to the portions of the regulatory liability and the corresponding portions of the deferred tax liability related to the portions of the regulatory asset are also reflected in rate base and prorated or averaged, as appropriate.  Columns (a) through (h) are used for projected and actual revenue requirements computations.  Columns (i) through (n) are used for actual revenue requirement computations.

Amount
debit / <credit>

PDF page 523

21
Account 182.3 - Other Regulatory Assets (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
22
Month
Year
23

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
24
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA
 NA                              -
25
January
-
                              -                                 -
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 26

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 27

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 28

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 29

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 30

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 31

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 32

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 33

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 34

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 35

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 36

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 37

Total
                              -
                             -                                -
38
39
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
40
41
Beginning balance  (debit or <credit>)
                        -
42
Less:  Portion not related to transmission
                        -
43
Less:  Portion not reflected in rate base
                        -
44
Subtotal:  Portion reflected in rate base
                        -
45
Less:  Portion subject to proration
                        -
46
Portion subject to averaging  (debit or <credit>)
                        -
47
Ending balance  (debit or <credit>)
                        -
48
Less:  Portion not related to transmission
                        -
49
Less:  Portion not reflected in rate base
                        -
50
Subtotal:  Portion reflected in rate base
                        -
51
Less:  Portion subject to proration (before proration)
                        -
52
Portion subject to averaging (before averaging)  (debit or <credit>)
                        -
53
Ending balance of portion subject to proration (prorated)  (debit or <credit>)
                        -   From Line 70(n)
54
Average balance of portion subject to averaging
                        -
55
Amount reflected in rate base  (debit or <credit>)
                        -   To Att. 13, Line 6
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 2 -
Amount
debit / <credit>

PDF page 524

56
Account 254 - Other Regulatory Liabilities (portion related to deficient or excess ADIT)
Columns (i) through (n) are not used for the calculation of the projected revenue requirement
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
57
Month
Year
58

prior month (d) + (c)
Line 2
[(c) x (e) / (f)]
prior month (h) + (g)
[Note 5]
[Note 6]
[Note 7]
58
December 31,
-
 NA                               -
NA
0
 NA                               -
 NA
 NA
 NA
 NA                              -
59
January
-
                              -                                 -
0
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 60

February
-
                              -                                 -
307
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 61

March
-
                              -                                 -
276
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 62

April
-
                              -                                 -
246
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 63

May
-
                              -                                 -
215
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 64

June
-
                              -                                 -
185
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 65

July
-
                              -                                 -
154
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 66

August
-
                              -                                 -
123
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 67

September
-
                              -                                 -
93
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 68

October
-
                              -                                 -
62
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 69

November
-
                              -                                 -
32
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 70

December
-
                              -                                 -
1
0
                              -                                 -
                             -                                -                                  -                                  -                                  -                                - 71

Total
                              -
                             -                                -
72
73
74
75
76
77
Forecasted Monthly
Activity
debit / <credit>
Forecasted
Month-end Balance
debit / <credit>
Days until
End of Test
Period
Days in Test
Period
Prorated Forecasted
Monthly Activity
debit / <credit>
Forecasted  Prorated
Month-end Balance
debit / <credit>
Actual Monthly
Activity
Difference between
projected monthly
and actual monthly
activity.
Preserve projected
proration when actual
monthly and projected
monthly activity are
either both increases
or decreases.
Fifty percent of the
difference between
projected and actual
activity when actual
and projected activity
are either both
increases or
decreases.
Fifty percent of actual
monthly activity when
projected activity is
an increase while
actual activity is a
decrease OR projected
activity is a decrease
while actual activity is
an increase.
Balance reflecting
proration or
averaging
(i) - (c)
 [Note 4]
(k) + (l) + (m)
[Note 8]
Note 3 -
Note 4  -  Column J is the difference between actual monthly and projected monthly activity (Column I minus Column C).  Specifically, if projected and actual activity are both positive, a negative in Column J represents over-projection (i.e., the amount of projected activity that did not occur) and a positive in Column J represents under-projection (i.e., the excess of actual activity over projected activity). If projected and actual activity are both negative, a negative in Column J represents under-projection (i.e., the excess of actual activity over projected activity) and a positive in Column J represents over-projection (i.e., the amount of projected activity that did not occur).

Note 5  -  Column K preserves the effects of excess ADIT proration from the projected revenue requirement when actual monthly excess ADIT activity and projected monthly excess ADIT activity are either both increases or decreases.  Specifically, if Column J indicates that excess ADIT activity was over-projected, enter Column G x [Column I / Column C].  If Column J indicates that excess ADIT activity was under-projected, enter the amount from Column G and complete Column L).  In other situations, enter zero.

Note 6  -  Column L applies when (1) Column J indicates that excess ADIT activity was under-projected AND (2) actual monthly and projected monthly activity are either both increases or both decreases.  Enter 50 percent of the amount from Column J.  In other situations, enter zero.  The excess ADIT activity in column L is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 7  -  Column M applies when (1) projected monthly activity was an increase while actual monthly activity was a decrease OR (2) projected monthly activity was a decrease while actual monthly activity was an increase.  Enter 50 percent of the amount of actual monthly activity (Column I).  In other situations, enter zero.  The excess ADIT activity in column M is multiplied by 50 percent to reflect averaging of rate base to the extent that the proration requirement has not been applied to a portion of the monthly excess ADIT activity.

Note 8  -  Column N is computed by adding the balance at the end of the prior month to EITHER (1) the sum of prorated monthly excess ADIT activity, if any, from Column K and the portion of monthly excess ADIT activity, if any, from Column L OR (2) the portion of monthly excess ADIT activity in Column M.

PDF page 525

DesertLink, LLC
Attachment 13.2 - Re-measurement of ADIT and Tax-related Regulatory Assets and Liabilities Resulting from the Tax Change Identified in Line 1 Support for Attachment 13 (Excess or Deficient Accumulated Deferred Income Taxes - Summary)

[Year]
[Projected or Actual]
Line No.
1
[Identify/describe the tax legislation/change]
2
[Describe the computation.]
3
4
(a) (b)
(c) (d)
(e) (f)
(g) (h)
(i) (j)
(k) (l)
(m) (n)
5
Balances and rates prior to remeasurement
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
6
Temporary Difference
Account
Account
Account
Account
Account
7
Item
Normalized?
Amount
190
282
283
182.3
283
8
[Insert rows as necessary]
8a
[Insert rows as necessary]
8b
[Insert rows as necessary]
8...
[Insert rows as necessary]
9
Total
                     -                      -                      -                      -                      -
10
Remeasured balances and rates
Other accounts affected by remeasurement
11
[tax rate]
[tax rate]
[tax rate]
[1/(1-tax rate)]
[tax rate]
[1/(1-tax rate [tax rate] /(1-tax rate [tax rate]
12
Temporary Difference
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
Account
13
Item
Normalized?
Amount
190
282
283
182.3
283
410.2
411.2
254
190
182.3
283
14
[Insert rows as necessary]
14a
[Insert rows as necessary]
14b
[Insert rows as necessary]
14...
[Insert rows as necessary]
15
Total
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
16
Remeasurement journal entry:  debt or <credit> (to Attachment 13)
                     -                      -                      -                      -                      -
              -               -               -               -               -               -
17
Summary of Effects on Tax-related Regulatory Assets and Liabilities
18
Account 182.3 - included in rate base, subject to normalization rules
19
Account 182.3 - included in rate base, not subject to normalization rules
20
Account 182.3 - not included in rate base
21
Account 254 - included in rate base, subject to normalization rules
22
Account 254 - included in rate base, not subject to normalization rules
23
Account 254 - not included in rate base
The ratemaking treatment of each item in terms of whether it is subject to the normalization requirements (i.e., P or "protected") or not subject to the normalization requirements (i.e., U or "unprotected") and included in rate base or not (i.e., RB or non-RB) is indicated in column (b).  The balances are measured at the composite tax rate in effect immediately before effective date of the change in tax law and remeasured immediately after the change in tax law.  Each set of balances includes the appropriate income tax rates and tax gross-up factors (as computed in the specific note for this tax law change in Att. 13).  The journal entry to record the remeasurements (Line 16) is based on the differences in balances of accounts recorded prior to the change in law (columns (d)-(h)) and activity in other accounts resulting from the remeasurement (columns (i)-(n)).  The remeasurement entry is also included in Att. 13.  The accounting is further described in Att. 13, Note 2. This worksheet will be included in support of the revenue requirement computation until the excess or deficient ADIT is fully amortized.  A similar worksheet will be used for subsequent changes in tax law resulting in re-measurement of ADIT.

PDF page 526

Ex. DLK-103

Formula Rate Template (Excel)

PDF page 527

Ex. DLK-204

Illustrative Formula Rate Template (Excel)

PDF page 528

Ex. DLK-205

Illustrative TRBAA Calculation (Excel)

PDF page 529

CERTIFICATE OF SERVICE

Pursuant to Rule 2010 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission, 18 C.F.R. § 385.2010, I hereby certify that I have this day caused a copy of the foregoing filing of DesertLink, LLC to be served electronically upon each person designated on the official service list in Docket No. EL26-71-000 and upon each other person entitled to service under the Commission’s regulations.

Dated at Washington, DC, this 16th day of November 2026.
/s/ Alexandra Zak __ ___
Alexandra Zak