ER27-534-000 · 2026-11-16 · DesertLink, LLC

Revisions to TO Tariff to Provide for Large Load Interconnection

DesertLink, LLC files tariff revisions under section 205 on November 16, 2026, in ER27-534-000, answering the CAISO show cause order. It adds a large load interconnection process and a pro forma cost recovery agreement with a 20-year minimum revenue contribution. The letter matches the LS Power Grid California filing in ER27-528, except that DesertLink also revises its Formula Rate Template.

Asks FERC to: Accept the revisions effective January 16, 2027, 61 days after filing, and grant any necessary waivers.

Filed under section 205 to answer the E-10 show cause order. It adds a large load interconnection process and a pro forma cost recovery agreement to a transmission-only owner's tariff, and defers permanent flexible service to CAISO.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62)

Key points

  1. It adds a process for utilities that buy transmission service on behalf of large loads.
    adding a new Section 10A and a new Appendix VI (Large Load Interconnection Procedures (“LLIP”)) to establish an interconnection process for Eligible Customers for Large Load (“ECLLs”) PDF p. 1
  2. The definition is 50 MW of peak load at a single site.
    a Large Load is an End-User located at a single site behind one or more Points of Withdrawal from the CAISO Controlled Grid with a peak load of 50 MW or greater PDF p. 4
  3. The cost recovery agreement sets a 20-year minimum revenue contribution for each upgrade.
    establishes the Eligible Customer’s twenty-year Minimum Transmission Revenue Contribution (“MTRC”) and related payment and security obligations for each Covered Upgrade PDF p. 2
  4. Ending service early costs the customer all remaining revenue responsibility.
    the Eligible Customer owes a lump-sum Termination Fee equal to the Remaining Cumulative Revenue Responsibility PDF p. 7
  5. Direct security can be reduced by security the large load posted under a retail agreement.
    allowing an Eligible Customer to rely on credit support posted by a large load under a retail agreement, direct Operational Security is reduced dollar-for-dollar by Qualifying Retail Security Support PDF p. 7
  6. Interim curtailable service is curtailed ahead of firm service.
    FILI Service is subject to curtailment, including during normal operating conditions, and is curtailed before Firm Interconnection Service PDF p. 4
  7. DesertLink has no retail customers and no retail relationship with a large load.
    DesertLink is a non-load-serving PTO; it neither serves retail load nor has a retail relationship with any customer seeking a Large Load interconnection PDF p. 3
  8. This is the difference from LS Power Grid: DesertLink revises its formula rate template, and says the revised template yields the same revenue requirement absent a covered upgrade.
    the revised Formula Rate Template produces the same revenue requirement as the currently effective Formula Rate Template PDF p. 2

Text extracted from the eLibrary original (SHA-256 a9ba306729926eaf…). Download the original from the official source.

Contents · 117 sections
  1. I. INTRODUCTION AND SUMMARY OF FILING p. 2
  2. II. BACKGROUND p. 3
  3. A. DesertLink and Its Formula Rate p. 3
  4. B. Show Cause Order and Stakeholder Process p. 3
  5. III. DESCRIPTION OF THE PROPOSED REVISIONS p. 4
  6. A. Large Load Interconnection Framework (Section 10A and Appendix VI) p. 4
  7. B. Pro Forma CRA (Appendix V) p. 5
  8. C. Crediting CRA Amounts Through the TRBAA (Sections 3 and 5.5) p. 8
  9. D. Formula Rate Template Revisions and Rate Treatment of Covered Upgrades p. 9
  10. E. Supporting Testimony and Illustrative Exhibits p. 9
  11. IV. THE PROPOSED REVISIONS ARE JUST AND REASONABLE p. 10
  12. V. REQUESTED EFFECTIVE DATE AND WAIVERS p. 11
  13. VI. CONTENTS OF FILING p. 11
  14. VII. COMMUNICATIONS AND SERVICE p. 12
  15. VIII. CONCLUSION p. 13
  16. I. Col. J computes the total true-up as the sum of Col. G, H and I. p. 72
  17. I. Large Load Interconnection Customer (ECLL) Contact Information p. 203
  18. II. Large Load Customer Information p. 203
  19. III. Point of Interconnection p. 203
  20. IV. Large Load Capacity and Load Ramp Schedule p. 204
  21. V. Proposed Service Commencement Date and Term p. 204
  22. VI. Source of Power p. 204
  23. VII. Site Plan, Site Control, and Permits p. 204
  24. VIII. Co-Located Generation p. 205
  25. IX. Single-Line Diagram and Modeling Information p. 205
  26. X. Required Submittals (LLIP Section 4.2.1) p. 205
  27. XI. Acknowledgment p. 205
  28. I. Col. J computes the total true-up as the sum of Col. G, H and I. p. 266
  29. I. Large Load Interconnection Customer (ECLL) Contact Information p. 398
  30. II. Large Load Customer Information p. 398
  31. III. Point of Interconnection p. 398
  32. IV. Large Load Capacity and Load Ramp Schedule p. 399
  33. V. Proposed Service Commencement Date and Term p. 399
  34. VI. Source of Power p. 399
  35. VII. Site Plan, Site Control, and Permits p. 399
  36. VIII. Co-Located Generation p. 400
  37. IX. Single-Line Diagram and Modeling Information p. 400
  38. X. Required Submittals (LLIP Section 4.2.1) p. 400
  39. XI. Acknowledgment p. 400
  40. I. INTRODUCTION AND EXPERIENCE p. 406
  41. A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310, p. 406
  42. II. PURPOSE AND SCOPE OF TESTIMONY p. 407
  43. A. The purpose of this testimony is to provide relevant context and details regarding p. 407
  44. A. Yes. I am sponsoring the following exhibits: p. 408
  45. III. FERC SHOW CAUSE ORDERS p. 408
  46. A. On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the p. 408
  47. A. Yes, Commissioners Chang and See each issued separate concurrences providing p. 409
  48. IV. CAISO STAKEHOLDER PROCESS p. 411
  49. A. CAISO convened joint coordination meetings with the California Participating p. 411
  50. A. DesertLink coordinated with CAISO and other California PTOs. DesertLink is a non- p. 412
  51. A. DesertLink proposes a large-load interconnection framework under Section 10A and p. 413
  52. V. COST RECOVERY AGREEMENT p. 413
  53. A. The CRA is a pro forma contract between DesertLink, as Transmission Owner, and the p. 413
  54. A. At a high level, the CRA responds directly to the three cost-recovery concerns identified p. 414
  55. A. The core payment mechanism is the Supplemental Minimum Transmission Revenue p. 414
  56. A. The Annual MTRC operates as a revenue floor, not an additive charge. Under Section p. 416
  57. A. The CRA addresses stranded-asset risk through a twenty-year revenue commitment, p. 417
  58. A. Section 7.1 recognizes Construction Security provided under an interconnection or p. 420
  59. A. Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits. In each p. 421
  60. VI. TARIFF REVISIONS p. 421
  61. A. The TO Tariff establishes the Eligible Customer for Large Load ("ECLL") p. 422
  62. A. The principal changes establish definitions for Large Load, Co-Located Large Load, p. 422
  63. A. The proposed framework establishes an ECLL interconnection process under Section p. 423
  64. A. The proposed pro forma CRA is identified as Appendix V to the TO Tariff. TO Tariff p. 424
  65. A. TO Tariff Section 10A.3.7 and LLIP Section 4.6.1.1 require consideration of alternative p. 424
  66. A. Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the p. 426
  67. A. Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into p. 426
  68. A. The Annual Projection workpapers and annual Reconciliation Statement make the p. 427
  69. A. Yes, it does. p. 428
  70. D. ERIC ARZOLA p. 439
  71. D. ERIC ARZOLA p. 442
  72. I. INTRODUCTION AND EXPERIENCE p. 442
  73. A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310, p. 442
  74. A. Yes. I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or p. 442
  75. II. PURPOSE AND SUMMARY OF TESTIMONY p. 443
  76. A. The purpose of my testimony is to explain how DesertLink will recover the cost of p. 443
  77. A. DesertLink proposes to credit the amounts it receives under its CRAs to transmission p. 444
  78. A. No. The cost of service inputs, return, depreciation, taxes, and allocators are unchanged. p. 444
  79. A. Yes. I am sponsoring the following exhibits: p. 445
  80. III. DESERTLINK AND FORMULA RATE BACKGROUND p. 445
  81. A. DesertLink is a transmission-only Participating Transmission Owner in the CAISO that p. 445
  82. A. By October 1, DesertLink posts an Annual Projection of its net revenue requirement for p. 445
  83. A. As provided in Appendix I of the TO Tariff, DesertLink’s Transmission Revenue p. 446
  84. A. In the Show Cause Order, the Commission directed the CAISO and its transmission p. 446
  85. IV. THE LARGE LOAD COST RECOVERY FRAMEWORK p. 447
  86. A. Each Covered Upgrade placed under the CAISO’s Operational Control is included in p. 447
  87. A. The Supplemental MTRC is calculated separately for each Covered Upgrade as the p. 448
  88. A. The Supplemental MTRC follows the same calendar as the Formula Rate. With each p. 448
  89. A. If an Eligible Customer does not pay, DesertLink may draw on the Eligible Customer’s p. 449
  90. A. The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the p. 450
  91. A. Covered Upgrades will be subject to DesertLink’s Commission-accepted Formula Rate p. 450
  92. V. CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA p. 451
  93. A. Through the TRBAA. Each October, DesertLink will include the Forecast TRBAA p. 451
  94. A. There are several reasons. First, the TRBAA already exists to credit customers with p. 452
  95. A. No. DesertLink’s annual TRBAA filing is made under Section 205 of the Federal Power p. 452
  96. A. Section 5.5 of the TO Tariff currently provides for the TRBAA to flow Transmission p. 453
  97. A. DesertLink will add the following lines to the TRBA and TRBAA calculation it files each p. 453
  98. A. Interest applies when DesertLink holds funds that belong to transmission customers, or p. 454
  99. A. Yes. In each annual TRBAA filing, DesertLink will provide the TRBA and TRBAA p. 455
  100. A. No. Appendix I states that DesertLink’s TRR equals its Base TRR plus its TRBAA, and p. 455
  101. VI. DESERTLINK’S PROPOSED FORMULA RATE TEMPLATE CHANGES p. 455
  102. A. The existing Formula Rate Template calculates the revenue requirement of the Harry p. 455
  103. A. Attachment 1a has five sections, each with a line for each project. Additional project lines p. 456
  104. A. Each project line on Attachment 1 now draws its project name, gross plant including p. 456
  105. A. DesertLink proposes a new Line 17a, “Less: Revenue Credits included in the TRBAA,” p. 456
  106. A. Yes. Attachment 1a has been added to the Table of Contents. There are no other changes. p. 457
  107. A. No. The Formula Rate Implementation Protocols already require DesertLink to support p. 457
  108. VII. NATIVE AND ILLUSTRATIVE EXHIBITS p. 457
  109. A. Exhibit No. DLK-203 is the revised Formula Rate Template in native Excel format with p. 457
  110. A. Exhibit No. DLK-204 is the revised Formula Rate Template populated with hypothetical p. 457
  111. A. Exhibit No. DLK-205 illustrates the TRBA and TRBAA calculation for two consecutive p. 459
  112. VIII. CONCLUSION p. 460
  113. A. The revisions implement the Commission’s direction that large load payments be credited p. 460
  114. A. Yes. p. 460
  115. D. Eric Arzola p. 461
  116. I. Col. J computes the total true-up as the sum of Col. G, H and I. p. 474
  117. I. Col. J computes the total true-up as the sum of Col. G, H and I. p. 506

Topics in the text: Connecting load and generation · Registry access · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

DesertLink respectfully requests that the Commission accept the proposed tariff revisions to become effective January 16, 2027, sixty-one (61) days after filing, consistent with the Commission’s prior notice requirement,5 and grant any necessary waivers. 1 16 U.S.C. § 824d (2022). 2 18 C.F.R. pt.…
Read this passage

I. INTRODUCTION AND SUMMARY OF FILING

printed heading · Topic match: Cost allocation

The filing responds to the Show Cause Order’s direction that respondents (1) ensure transparency concerning the network upgrade costs to provide transmission service to Eligible Customers on behalf of large loads, (2) establish a pro forma cost recovery agreement to mitigate the risk of cost…
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

A. DesertLink and Its Formula Rate

printed heading

DesertLink and Its Formula Rate DesertLink is a transmission-only PTO in the CAISO that owns the Harry Allen to Eldorado 500 kV Transmission Line Project (“Harry Allen to Eldorado Project”), which CAISO selected DesertLink to develop in 2016 through its Order No. 1000-compliant competitive…
Read this passage

B. Show Cause Order and Stakeholder Process

printed heading · Topic match: Retail and wholesale authority

DesertLink’s proposal does not displace the separate arrangements that an Eligible Customer must enter into with an Affected System Owner for an Affected System Upgrade or with the owner of a regional project share owned by another entity.11
Read this passage

III. DESCRIPTION OF THE PROPOSED REVISIONS

printed heading

III.
Read this passage

A. Large Load Interconnection Framework (Section 10A and Appendix VI)

printed heading · Topic match: Connecting load and generation

Section 10A.2 specifies the contents of an ECLL Interconnection Application, including the load ramp schedule, site plan, Site Control, permits and approvals, electrical configuration, related requests, technical data, and Co-Located Large Load information.
Read this passage

B. Pro Forma CRA (Appendix V)

printed heading · Topic match: Cost allocation

Operational Security must be delivered no later than thirty Calendar Days before the earliest expected in- service date and equals one hundred percent (100%) of the nominal Remaining Cumulative Revenue Responsibility.
Read this passage

C. Crediting CRA Amounts Through the TRBAA (Sections 3 and 5.5)

printed heading

Because the TO Tariff defines Transmission Revenue Credits as amounts received from, or charges imposed by, CAISO, DesertLink proposes to revise the definition of the TRBAA (Section 3.103) and Section 5.5 so that the TRBAA also flows through to transmission customers all amounts that a CRA requires to…
Read this passage

D. Formula Rate Template Revisions and Rate Treatment of Covered Upgrades

printed heading

Formula Rate Template Revisions and Rate Treatment of Covered Upgrades DesertLink’s current Formula Rate Template reports plant values only in total and has no means of identifying facilities built to serve Large Loads.
Read this passage

E. Supporting Testimony and Illustrative Exhibits

printed heading · Topic match: Cost allocation

DLK-100) describes the Show Cause Order, the CAISO stakeholder process, the pro forma CRA, and the associated TO Tariff revisions, and explains how those measures assign cost responsibility for Large Load-Driven Upgrades, mitigate cost shifting 24 See CRA § 6.6; TO Tariff § 5.5. 25 See Ex.
Read this passage

IV. THE PROPOSED REVISIONS ARE JUST AND REASONABLE

printed heading · Topic match: Cost allocation

That design responds to the concern that bilateral revenue contributions “untethered from any assessment of the actual cost of providing transmission service induced by individual large loads” may be insufficient to protect other customers against unjustified cost shifts.27 The proposal also…
Read this passage

V. REQUESTED EFFECTIVE DATE AND WAIVERS

printed heading

REQUESTED EFFECTIVE DATE AND WAIVERS DesertLink requests an effective date of January 16, 2027, sixty-one (61) days after the date of this filing, satisfying the Commission’s sixty-day notice requirement.28 DesertLink requests waiver of the cost-of-service-statement requirements of 18 C.F.R. §…
Read this passage

VI. CONTENTS OF FILING

printed heading

CONTENTS OF FILING DesertLink submits the following materials: • This transmittal letter; • Attachment 1: Clean version of the DesertLink TO Tariff revisions; • Attachment 2: Marked version of the DesertLink TO Tariff revisions; • Attachment 3: Direct testimony of Patrick Hayes (Exhibit No.
Read this passage

VII. COMMUNICATIONS AND SERVICE

printed heading

COMMUNICATIONS AND SERVICE DesertLink requests that all pleadings, correspondence, and other communications concerning this matter be directed to the following persons, and that their names and addresses be placed on the official service list for this proceeding: 29 Josh R.
Read this passage

VIII. CONCLUSION

printed heading

CONCLUSION For the reasons stated above and in the supporting testimony, DesertLink respectfully requests that the Commission accept the proposed tariff revisions effective January 16, 2027, and grant any necessary waivers.
Read this passage

Table of Contents

printed heading · Topic match: Connecting load and generation

A Large Load Customer receiving FILI Service shall be subject to curtailment prior to any curtailment of customers receiving Firm Interconnection Service.
Read this passage

Table of Contents

printed heading

C Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
Read this passage

I. Col. J computes the total true-up as the sum of Col. G, H and I.

printed heading · Topic match: Credit and exit

After any Large Load-Driven Upgrade reaches its Upgrade In-Service Date or any DesertLink-owned CAISO-Assigned Regional Project reaches its Regional Project In-Service Date specified in Schedule 4, Eligible Customer shall promptly notify DesertLink if Eligible Customer or Large Load Customer…
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.
Read this passage

I. Large Load Interconnection Customer (ECLL) Contact Information

printed heading

Large Load Interconnection Customer (ECLL) Contact Information Company Name Type of ECLL (UDC or MSS) Representative Address Email Phone
Read this passage

II. Large Load Customer Information

printed heading

Large Load Customer Information Large Load Customer Name Large Load Customer Representative and Contact Information Large Load Site Location/Address Type of Large Load Facility (e.g., data center, industrial) Other ECLL interconnection requests submitted for the same Large Load Customer or any of…
Read this passage

III. Point of Interconnection

printed heading

Point of Interconnection Please identify the location and voltage level of the preferred Point of Interconnection in as much detail as possible.
Read this passage

IV. Large Load Capacity and Load Ramp Schedule

printed heading

Large Load Capacity and Load Ramp Schedule Proposed load ramp schedule identifying anticipated load additions over time: Date (MM/DD/YYYY) Incremental Load (MW) Cumulative Load (MW)
Read this passage

V. Proposed Service Commencement Date and Term

printed heading

V.
Read this passage

VI. Source of Power

printed heading

VI.
Read this passage

VII. Site Plan, Site Control, and Permits

printed heading

If the source of the power is not known, a system purchase will be assumed.
Read this passage

VIII. Co-Located Generation

printed heading

Co-Located Generation Will the Large Load be co-located with a generating facility? (Yes/No) Will the generating facility export to the ISO Controlled Grid? (Yes/No) Generating facility queue number or, if executed, identification of its generator interconnection agreement Generating facility…
Read this passage

IX. Single-Line Diagram and Modeling Information

printed heading

Single-Line Diagram and Modeling Information Please attach a single-line diagram of the Large Load and the Large Load Interconnection Customer’s Interconnection Facilities and/or KMZ files to this Interconnection Request.
Read this passage

X. Required Submittals (LLIP Section 4.2.1)

printed heading

Required Submittals (LLIP Section 4.2.1) Item Included (Yes/No) Interconnection Study Deposit of $250,000 Commercial Readiness Deposit equal to two times the Interconnection Study Deposit, in a form permitted by LLIP Section 4.7.1 Demonstration of Site Control Completed technical data form in the…
Read this passage

XI. Acknowledgment

printed heading · Topic match: Registry access

The Large Load Interconnection Customer may designate information in this Interconnection Request, including the identity of the Large Load Customer, as Confidential Information in accordance with LLIP Section 7.1.
Read this passage

Table of Contents

printed heading · Topic match: Connecting load and generation

If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application…
Read this passage

Table of Contents

printed heading

C Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
Read this passage

I. Col. J computes the total true-up as the sum of Col. G, H and I.

printed heading · Topic match: Credit and exit

After any Large Load-Driven Upgrade reaches its Upgrade In-Service Date or any DesertLink-owned CAISO-Assigned Regional Project reaches its Regional Project In-Service Date specified in Schedule 4, Eligible Customer shall promptly notify DesertLink if Eligible Customer or Large Load Customer…
Read this passage

TABLE OF CONTENTS

printed heading · Topic match: Registry access

Participating TO shall assign a Queue Position as follows: the Queue Position shall be assigned based upon the date and time of receipt of all items required pursuant to the provisions of LLIP Section 4.2.1. 3.8.2 Higher Queue Position.
Read this passage

I. Large Load Interconnection Customer (ECLL) Contact Information

printed heading

Large Load Interconnection Customer (ECLL) Contact Information Company Name Type of ECLL (UDC or MSS) Representative Address Email Phone
Read this passage

II. Large Load Customer Information

printed heading

Large Load Customer Information Large Load Customer Name Large Load Customer Representative and Contact Information Large Load Site Location/Address Type of Large Load Facility (e.g., data center, industrial) Other ECLL interconnection requests submitted for the same Large Load Customer or any of…
Read this passage

III. Point of Interconnection

printed heading

Point of Interconnection Please identify the location and voltage level of the preferred Point of Interconnection in as much detail as possible.
Read this passage

IV. Large Load Capacity and Load Ramp Schedule

printed heading

Large Load Capacity and Load Ramp Schedule Proposed load ramp schedule identifying anticipated load additions over time: Date (MM/DD/YYYY) Incremental Load (MW) Cumulative Load (MW)
Read this passage

V. Proposed Service Commencement Date and Term

printed heading

V.
Read this passage

VI. Source of Power

printed heading

VI.
Read this passage

VII. Site Plan, Site Control, and Permits

printed heading

If the source of the power is not known, a system purchase will be assumed.
Read this passage

VIII. Co-Located Generation

printed heading

Co-Located Generation Will the Large Load be co-located with a generating facility? (Yes/No) Will the generating facility export to the ISO Controlled Grid? (Yes/No) Generating facility queue number or, if executed, identification of its generator interconnection agreement Generating facility…
Read this passage

IX. Single-Line Diagram and Modeling Information

printed heading

Single-Line Diagram and Modeling Information Please attach a single-line diagram of the Large Load and the Large Load Interconnection Customer’s Interconnection Facilities and/or KMZ files to this Interconnection Request.
Read this passage

X. Required Submittals (LLIP Section 4.2.1)

printed heading

Required Submittals (LLIP Section 4.2.1) Item Included (Yes/No) Interconnection Study Deposit of $250,000 Commercial Readiness Deposit equal to two times the Interconnection Study Deposit, in a form permitted by LLIP Section 4.7.1 Demonstration of Site Control Completed technical data form in the…
Read this passage

XI. Acknowledgment

printed heading · Topic match: Cost allocation

The Large Load Interconnection Customer may designate information in this Interconnection Request, including the identity of the Large Load Customer, as Confidential Information in accordance with LLIP Section 7.1.
Read this passage

TABLE OF CONTENTS

printed heading

Description DLK-101: DLK-102: DLK-103: Illustrative MTRC Calculation Example Reconciliation Statement Example Invoice Statement Page 1 DIRECT TESTIMONY OF PATRICK HAYES
Read this passage

I. INTRODUCTION AND EXPERIENCE

printed heading

I.
Read this passage

A. My name is Patrick Hayes. My business address is 16150 Main Circle Drive, Suite 310,

printed heading · Topic match: Cost allocation

My responsibilities include Federal Energy Regulatory Commission 10 (“FERC”) policy, regional transmission planning, competitive transmission development, 11 cost allocation and recovery, tariff development, and large-load interconnection. 12 Q.
Read this passage

II. PURPOSE AND SCOPE OF TESTIMONY

printed heading

II.
Read this passage

A. The purpose of this testimony is to provide relevant context and details regarding

printed heading · Topic match: Cost allocation

I describe the proposed Large Load Cost 13 Recovery Agreement (“CRA”) and associated tariff framework, and explain how these 14 measures assign cost responsibility for large-load-driven transmission upgrades, mitigate 15 cost shifting and stranded-asset risk, avoid double recovery, and promote…
Read this passage

A. Yes. I am sponsoring the following exhibits:

printed heading

I am sponsoring the following exhibits: 3 Exhibit No.
Read this passage

III. FERC SHOW CAUSE ORDERS

printed heading

III.
Read this passage

A. On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the

printed heading

On June 18, 2026, the FERC instituted show cause proceedings under section 206 of the 6 Federal Power Act through six show cause orders addressing the integration of large and 7 co-located loads onto the interstate transmission system.
Read this passage

A. Yes, Commissioners Chang and See each issued separate concurrences providing

printed heading · Topic match: Cost allocation

Commissioner Chang supported the Commission's two-part preliminary 15 solution — public posting of information on new large loads, associated network 16 upgrades identified in local transmission planning, and the costs of those upgrades, 17 together with a pro forma cost recovery agreement to help…
Read this passage

IV. CAISO STAKEHOLDER PROCESS

printed heading

PLEASE DESCRIBE THE CAISO PROCESS FOLLOWING THE ISSUANCE OF 7 THE SHOW CAUSE ORDERS. 8
Read this passage

A. CAISO convened joint coordination meetings with the California Participating

printed heading · Topic match: Connecting load and generation

DesertLink participated in the joint coordination process 11 meetings on July 1, July 10, July 23, and July 28; August 4, August 11, August 18, and 12 August 25; September 1, September 8, September 10, September 15, and September 22; 13 and October 23, 2026. 14 The meetings addressed applications…
Read this passage

A. DesertLink coordinated with CAISO and other California PTOs. DesertLink is a non-

printed heading · Topic match: Retail and wholesale authority

DesertLink’s coordination efforts 6 highlighted the need to ensure that an affected PTO has a meaningful role in the process 7 even when the affected PTO does not provide retail service to the requesting load. 8 From July through September 2026, DesertLink participated in additional meetings with 9…
Read this passage

A. DesertLink proposes a large-load interconnection framework under Section 10A and

printed heading

DesertLink proposes a large-load interconnection framework under Section 10A and 8 Appendix VI of DesertLink’s Transmission Owner Tariff ("TO Tariff"), together with the 9 pro forma CRA in Appendix V.
Read this passage

V. COST RECOVERY AGREEMENT

printed heading

V.
Read this passage

A. The CRA is a pro forma contract between DesertLink, as Transmission Owner, and the

printed heading

The CRA is a pro forma contract between DesertLink, as Transmission Owner, and the 16 Eligible Customer taking wholesale transmission service under the CAISO Tariff on 17 behalf of a Large Load Customer.
Read this passage

A. At a high level, the CRA responds directly to the three cost-recovery concerns identified

printed heading · Topic match: Cost allocation

At a high level, the CRA responds directly to the three cost-recovery concerns identified 10 in the Show Cause Order by: (i) establishing a pro forma contract between DesertLink 11 and the Eligible Customer that formalizes cost responsibility for the Covered Upgrades; 12 (ii) establishing payment…
Read this passage

A. The core payment mechanism is the Supplemental Minimum Transmission Revenue

printed heading

The core payment mechanism is the Supplemental Minimum Transmission Revenue 23 Contribution (the "Supplemental MTRC") in Section 6.4 of the CRA.
Read this passage

A. The Annual MTRC operates as a revenue floor, not an additive charge. Under Section

printed heading

The Annual MTRC operates as a revenue floor, not an additive charge.
Read this passage

A. The CRA addresses stranded-asset risk through a twenty-year revenue commitment,

printed heading · Topic match: Reliability and curtailment

Operational Security must be delivered no later than thirty Calendar 7 Days before the earliest expected applicable in-service date and be fully effective before 8 service.
Read this passage

A. Section 7.1 recognizes Construction Security provided under an interconnection or

printed heading

Section 7.1 recognizes Construction Security provided under an interconnection or 3 engineering and procurement agreement for the same costs, avoiding duplication.
Read this passage

A. Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits. In each

printed heading

Section 6.8 establishes TRBAA Credits rather than Formula Rate revenue credits.
Read this passage

VI. TARIFF REVISIONS

printed heading

PLEASE DESCRIBE THE ASSOCIATED TARIFF REVISIONS. 23 Page 17
Read this passage

A. The TO Tariff establishes the Eligible Customer for Large Load ("ECLL")

printed heading

The TO Tariff establishes the Eligible Customer for Large Load ("ECLL") 1 interconnection framework in Section 10A, identifies the pro forma CRA as Appendix V, 2 and incorporates the Large Load Interconnection Procedures ("LLIP").
Read this passage

A. The principal changes establish definitions for Large Load, Co-Located Large Load,

printed heading · Topic match: Connecting load and generation

The principal changes establish definitions for Large Load, Co-Located Large Load, 14 ECLL, ECLL Interconnection, Firm Interconnection Service, Flexible Interim Load 15 Interconnection ("FILI") Service, Interim Firm Interconnection Service, Point of 16 Withdrawal, Site Control, and CRA.
Read this passage

A. The proposed framework establishes an ECLL interconnection process under Section

printed heading · Topic match: Connecting load and generation

It applies to completed 11 Interconnection Requests submitted after Appendix VI becomes effective.
Read this passage

A. The proposed pro forma CRA is identified as Appendix V to the TO Tariff. TO Tariff

printed heading

Under 11 Article 5 of the CRA, a conforming, executed agreement with populated Schedules 12 generally will not require an individual Section 205 filing once the pro forma is accepted; 13 unexecuted agreements, material deviations, and other agreements required by 14 Commission rule or order must be…
Read this passage

A. TO Tariff Section 10A.3.7 and LLIP Section 4.6.1.1 require consideration of alternative

printed heading

If traditional 21 network upgrades are selected, DesertLink must demonstrate why alternative 22 technologies are not feasible or would not lower costs or provide a faster interconnection 23 timeline. 24 Page 20 The LLIP also establishes financial readiness requirements.
Read this passage

A. Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the

printed heading

Under Sections 6.1 and 12.3, the Formula Rate and Protocols continue to govern the 1 calculation, information exchange, and true-up of DesertLink’s Net Revenue 2 Requirement and the rate-base treatment of Covered Upgrades.
Read this passage

A. Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into

printed heading

Section 6.6 carries an under-billed or over-billed Supplemental MTRC amount into 22 billing following the next Annual Projection.
Read this passage

A. The Annual Projection workpapers and annual Reconciliation Statement make the

printed heading

The Annual Projection workpapers and annual Reconciliation Statement make the 16 upgrade-specific minimum contribution, forecast and actual QTR, Supplemental MTRC, 17 cumulative commitment, security, and TRBAA credit calculations available to the 18 Eligible Customer.
Read this passage

A. Yes, it does.

printed heading

Yes, it does. 17 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION DesertLink, LLC California Independent System Operator Corporation ) ) Docket No.
Read this passage

D. ERIC ARZOLA

printed heading · Topic match: Cost allocation

ERIC ARZOLA ON BEHALF OF DESERTLINK, LLC Large Load Network Upgrade Cost Recovery November 2026
Read this passage

TABLE OF CONTENTS

printed heading

Description DLK-201: Clean Formula Rate Template DLK-202: Marked Formula Rate Template DLK-203: Clean Formula Rate Template (Excel Format) DLK-204: Illustrative Formula Rate Template DLK-205: Illustrative TRBAA Calculation DIRECT TESTIMONY OF
Read this passage

D. ERIC ARZOLA

printed heading

D.
Read this passage

I. INTRODUCTION AND EXPERIENCE

printed heading

I.
Read this passage

A. My name is D. Eric Arzola. My business address is 16150 Main Circle Drive, Suite 310,

printed heading

My business address is 16150 Main Circle Drive, Suite 310, 3 Chesterfield, Missouri 63017. 4 Q.
Read this passage

A. Yes. I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or

printed heading

I have submitted testimony in Federal Energy Regulatory Commission (“FERC” or 14 “Commission”) Docket Nos.
Read this passage

II. PURPOSE AND SUMMARY OF TESTIMONY

printed heading

II.
Read this passage

A. The purpose of my testimony is to explain how DesertLink will recover the cost of

printed heading

The purpose of my testimony is to explain how DesertLink will recover the cost of 7 transmission facilities built to serve large loads and covered by a Large Load Cost 8 Recovery Agreement (“CRA”) (such facilities, “Covered Upgrades”), and how it will 9 credit the amounts Eligible Customers pay…
Read this passage

A. DesertLink proposes to credit the amounts it receives under its CRAs to transmission

printed heading

DesertLink proposes to credit the amounts it receives under its CRAs to transmission 2 customers through its TRBAA, the existing mechanism DesertLink uses to pass revenue 3 that it does not receive through the California Independent System Operator Corporation 4 (“CAISO”) Transmission Access Charge…
Read this passage

A. No. The cost of service inputs, return, depreciation, taxes, and allocators are unchanged.

printed heading

The cost of service inputs, return, depreciation, taxes, and allocators are unchanged. 21 Covered Upgrades are included in DesertLink’s rate base and revenue requirement in the 22 same manner as any other DesertLink transmission plant.
Read this passage

A. Yes. I am sponsoring the following exhibits:

printed heading

I am sponsoring the following exhibits: 7 Exhibit No.
Read this passage

III. DESERTLINK AND FORMULA RATE BACKGROUND

printed heading

PLEASE PROVIDE AN OVERVIEW OF DESERTLINK AND ITS FORMULA 9 RATE. 10
Read this passage

A. DesertLink is a transmission-only Participating Transmission Owner in the CAISO that

printed heading

DesertLink is a transmission-only Participating Transmission Owner in the CAISO that 11 owns the Harry Allen to Eldorado Project, which the CAISO selected DesertLink to 12 develop through its competitive solicitation process.
Read this passage

A. By October 1, DesertLink posts an Annual Projection of its net revenue requirement for

printed heading

By October 1, DesertLink posts an Annual Projection of its net revenue requirement for 20 the upcoming Rate Year.
Read this passage

A. As provided in Appendix I of the TO Tariff, DesertLink’s Transmission Revenue

printed heading

As provided in Appendix I of the TO Tariff, DesertLink’s Transmission Revenue 6 Requirement (“TRR”) is the sum of its Base Transmission Revenue Requirement (“Base 7 TRR”), determined under the Formula Rate, and its TRBAA.
Read this passage

A. In the Show Cause Order, the Commission directed the CAISO and its transmission

printed heading

In the Show Cause Order, the Commission directed the CAISO and its transmission 18 owners to show cause why their tariffs remain just and reasonable or to propose changes 19 for integrating large loads.
Read this passage

IV. THE LARGE LOAD COST RECOVERY FRAMEWORK

printed heading

A CRA is an agreement between DesertLink and an Eligible Customer taking 4 transmission service on behalf of a large load.
Read this passage

A. Each Covered Upgrade placed under the CAISO’s Operational Control is included in

printed heading

Each Covered Upgrade placed under the CAISO’s Operational Control is included in 16 DesertLink’s rate base and Base TRR and recovered through the CAISO TAC together 17 with the cost of the Harry Allen to Eldorado Project.
Read this passage

A. The Supplemental MTRC is calculated separately for each Covered Upgrade as the

printed heading

The Supplemental MTRC is calculated separately for each Covered Upgrade as the 4 amount, if any, by which the applicable Annual MTRC, prorated for a partial Rate Year, 5 exceeds the Qualifying Transmission Revenues allocated to that upgrade under Section 6 6.4.
Read this passage

A. The Supplemental MTRC follows the same calendar as the Formula Rate. With each

printed heading

The Supplemental MTRC follows the same calendar as the Formula Rate.
Read this passage

A. If an Eligible Customer does not pay, DesertLink may draw on the Eligible Customer’s

printed heading

If an Eligible Customer does not pay, DesertLink may draw on the Eligible Customer’s 3 Operational Security and apply the proceeds to the unpaid amount (“Applied Security 4 Proceeds”).
Read this passage

A. The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the

printed heading

The CRA uses the term “TRBAA Credits” for the Forecast TRBAA Credit and the 2 amounts DesertLink records in the TRBA and credits to transmission customers through 3 the TRBAA: payments of Supplemental MTRC received from or on behalf of the 4 Eligible Customer (“Supplemental MTRC Receipts”), Applied…
Read this passage

A. Covered Upgrades will be subject to DesertLink’s Commission-accepted Formula Rate

printed heading

Covered Upgrades will be subject to DesertLink’s Commission-accepted Formula Rate 16 and the return on equity (“ROE”) reflected in the effective Formula Rate.
Read this passage

V. CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA

printed heading

CREDITING CRA AMOUNTS TO CUSTOMERS THROUGH THE TRBAA 8 Q.
Read this passage

A. Through the TRBAA. Each October, DesertLink will include the Forecast TRBAA

printed heading

Each October, DesertLink will include the Forecast TRBAA 10 Credit for the following calendar year in Cf.
Read this passage

A. There are several reasons. First, the TRBAA already exists to credit customers with

printed heading

First, the TRBAA already exists to credit customers with 3 revenue DesertLink receives outside the TAC, and the Commission and stakeholders 4 review it each year.
Read this passage

A. No. DesertLink’s annual TRBAA filing is made under Section 205 of the Federal Power

printed heading

DesertLink’s annual TRBAA filing is made under Section 205 of the Federal Power 16 Act.
Read this passage

A. Section 5.5 of the TO Tariff currently provides for the TRBAA to flow Transmission

printed heading

Because CRA-related 6 credits include amounts received directly from or on behalf of the Eligible Customer and 7 Annual Termination Fee Credits scheduled under Section 3.3.4, DesertLink proposes to 8 revise the definition of the TRBAA and Section 5.5 so that the TRBAA also flows 9 through to…
Read this passage

A. DesertLink will add the following lines to the TRBA and TRBAA calculation it files each

printed heading

DesertLink will add the following lines to the TRBA and TRBAA calculation it files each 19 year, as shown in Exhibit No.
Read this passage

A. Interest applies when DesertLink holds funds that belong to transmission customers, or

printed heading

Interest applies when DesertLink holds funds that belong to transmission customers, or 14 when transmission customers hold funds owed to DesertLink.
Read this passage

A. Yes. In each annual TRBAA filing, DesertLink will provide the TRBA and TRBAA

printed heading

In each annual TRBAA filing, DesertLink will provide the TRBA and TRBAA 7 calculation substantially in the form of Exhibit No.
Read this passage

A. No. Appendix I states that DesertLink’s TRR equals its Base TRR plus its TRBAA, and

printed heading

Appendix I states that DesertLink’s TRR equals its Base TRR plus its TRBAA, and 14 that the TRBAA is computed in accordance with Section 5.5 of the TO Tariff and the 15 CAISO Tariff.
Read this passage

VI. DESERTLINK’S PROPOSED FORMULA RATE TEMPLATE CHANGES

printed heading

DESERTLINK’S PROPOSED FORMULA RATE TEMPLATE CHANGES 18 Q.
Read this passage

A. The existing Formula Rate Template calculates the revenue requirement of the Harry

printed heading

To show the revenue 21 requirement of each Covered Upgrade, the Formula Rate Template must report plant for 22 each project separately.
Read this passage

A. Attachment 1a has five sections, each with a line for each project. Additional project lines

printed heading

Attachment 1a has five sections, each with a line for each project.
Read this passage

A. Each project line on Attachment 1 now draws its project name, gross plant including

printed heading

Each project line on Attachment 1 now draws its project name, gross plant including 15 CWIP (Column 3), net plant (Column 6), and depreciation and amortization expense 16 (Column 9) from Attachment 1a.
Read this passage

A. DesertLink proposes a new Line 17a, “Less: Revenue Credits included in the TRBAA,”

printed heading

DesertLink proposes a new Line 17a, “Less: Revenue Credits included in the TRBAA,” 22 and revises Line 18 to subtract it.
Read this passage

A. Yes. Attachment 1a has been added to the Table of Contents. There are no other changes.

printed heading

Attachment 1a has been added to the Table of Contents.
Read this passage

A. No. The Formula Rate Implementation Protocols already require DesertLink to support

printed heading

The Formula Rate Implementation Protocols already require DesertLink to support 8 each input to the Formula Rate Template that is not taken directly from the FERC Form 9 No. 1 and to explain material changes in revenue credits, which will include the amounts 10 on Attachment 12, Line 17a.
Read this passage

VII. NATIVE AND ILLUSTRATIVE EXHIBITS

printed heading

VII.
Read this passage

A. Exhibit No. DLK-203 is the revised Formula Rate Template in native Excel format with

printed heading

DLK-203 is the revised Formula Rate Template in native Excel format with 17 all formulas and links intact, including new Attachment 1a.
Read this passage

A. Exhibit No. DLK-204 is the revised Formula Rate Template populated with hypothetical

printed heading

DLK-204 is the revised Formula Rate Template populated with hypothetical 22 data for the 2030 Rate Year to illustrate the treatment of a Covered Upgrade.
Read this passage

A. Exhibit No. DLK-205 illustrates the TRBA and TRBAA calculation for two consecutive

printed heading

DLK-205 illustrates the TRBA and TRBAA calculation for two consecutive 7 TRBA years ending September 30, 2030 and 2031, using the Supplemental MTRC from 8 Exhibit No.
Read this passage

VIII. CONCLUSION

printed heading

WHY ARE THE PROPOSED REVISIONS JUST AND REASONABLE? 12
Read this passage

A. The revisions implement the Commission’s direction that large load payments be credited

printed heading

The revisions implement the Commission’s direction that large load payments be credited 13 toward transmission owners’ revenue requirements, using DesertLink’s existing TRBAA 14 mechanism.
Read this passage

A. Yes.

printed heading

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION DesertLink, LLC California Independent System Operator Corporation ) ) Docket No.
Read this passage

D. Eric Arzola

printed heading

DLK-201 Formula Rate Template (Clean) Projected ATRR For the 12 months ended 12/31/__ Formula Rate Index DesertLink, LLC
Read this passage

Table of Contents

printed heading

C Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
Read this passage

I. Col. J computes the total true-up as the sum of Col. G, H and I.

printed heading

The Formula Rate shall include a credit to rate base for all unfunded reserves (funds collected from customers that (1) have not been set aside in a trust, escrow or restricted account; (2) whose balance are collected from customers through cost accruals to accounts that are recovered under the…
Read this passage

Table of Contents

printed heading

C Plant In Service, Accumulated Depreciation, and Depreciation Expenses shall exclude Asset Retirement Obligation amounts.
Read this passage

I. Col. J computes the total true-up as the sum of Col. G, H and I.

printed heading

The Formula Rate shall include a credit to rate base for all unfunded reserves (funds collected from customers that (1) have not been set aside in a trust, escrow or restricted account; (2) whose balance are collected from customers through cost accruals to accounts that are recovered under the…
Read this passage

CERTIFICATE OF SERVICE

printed heading

EL26-71-000 and upon each other person entitled to service under the Commission’s regulations.