APPENDIX A
Clean Version of the Revised Sections of the Trans Bay Tariff
PDF page 2
Company: Trans Bay Cable LLC
Program: FERC FPA Electric Tariff
Tariff Title: Transmission Owner Tariff
Proposed Effective Date: 2/16/2027
Tariff Record Description: Transmission Owner Tariff Tariff Record Title: Trans Bay Cable LLC
Tariff Record Version: 33.0.0
Option: A
PDF page 3
Trans Bay Cable LLC
Transmission Owner Tariff
PDF page 4
ii
TABLE OF CONTENTS
Section
Page
1. Preamble … 1 1.1.
Transmission Access for Participating TOs … 1 1.2.
Transmission Access for Wheeling Customers … 1
1.3.
Transmission Access for End-Users. E … 1
2. Effective Date … 1 2.1.
Termination … 1
3. TO Definitions … 1 3.1.
Access Charge … 1 3.2.
AGC … 1 3.3.
Ancillary Services … 2 3.4.
Applicable Reliability Criteria … 2 3.5.
Available Transfer Capacity … 2 3.6.
Base Transmission Revenue Requirement … 2 3.7.
Black Start … 2 3.8.
Business Day … 2 3.9.
Completed Application Date … 2 3.10.
Completed Interconnection Application … 2 3.11.
Congestion … 2 3.12.
Congestion Management … 3 3.13.
Converted Rights … 3 3.14.
CPUC … 3 3.15.
Demand … 3 3.16.
Direct Assignment Facilities … 3 3.17.
Dispatch … 3 3.18.
Distribution System … 3 3.19.
Eligible Customer … 3 3.20.
Encumbrance … 3 3.21.
End-Use Customer or End-User … 4 3.22.
Energy … 4 3.23.
Entitlement … 4 3.24.
Existing Contracts … 4 3.25.
Existing Rights … 4 3.26.
Expedited Interconnection Agreement … 4 3.27.
Facilities Study Agreement … 4 3.28.
Facility or Facilities Study … 4 3.29.
FERC … 4 3.30.
Flexible Interim Load Interconnection (“FILI”) Service … 4
3.31.
FPA … 5 3.32.
Generating Unit … 5 3.33.
Generation … 5 3.34.
Good Utility Practice … 5 3.35.
Gross Load … 5 3.36.
High Voltage Access Charge … 6
PDF page 5
iii
3.37.
High Voltage Transmission Facility … 6 3.38.
High Voltage Transmission Revenue Requirement … 6
3.39.
High Voltage Utility-Specific Rate … 6 3.40.
High Voltage Wheeling Access Charge … 6 3.41.
Independent System Operator (“ISO”) … 6 3.42.
Interconnection … 6 3.43.
Interconnection Agreement … 6 3.44.
Interconnection Application … 6 3.45.
Interconnection Facilities … 7 3.46.
Interest … 7 3.47.
ISO ADR Procedures … 7 3.48.
ISO Controlled Grid … 7 3.49.
ISO Protocols … 7 3.50.
ISO Tariff … 7 3.51.
Large Load … 7 3.52.
Load … 7 3.53.
Local Publicly Owned Electric Utility … 7 3.54.
Local Regulatory Authority … 8 3.55.
Local Reliability Criteria … 8 3.56.
Low Voltage Access Charge … 8 3.57.
Low Voltage Transmission Revenue Requirement … 8
3.58.
Low Voltage Wheeling Access Charge … 8 3.59.
Market Participant … 8 3.60.
Metered Subsystem (“MSS”) … 8 3.61.
NERC … 8 3.62.
Network Upgrades … 8 3.63.
New High Voltage Transmission Facility … 8 3.64.
New Participating TO … 9 3.65.
Non-Load-Serving Participating TO … 9 3.66.
Non-Participating TO … 9 3.67.
Non-Spinning Reserve … 9 3.68.
Operational Control … 9 3.69.
Original Participating TO … 9 3.70.
Participating TO (“PTO”) … 9 3.71.
Participation Agreement … 9 3.72.
Physical Scheduling Plant … 9 3.73.
Point of Interconnection … 10 3.74.
Project … 10 3.75.
Project Proponent … 10 3.76.
Project Sponsor … 10 3.77.
Regional Transmission Group (“RTG”) … 10 3.78.
Regulation … 10 3.79.
Regulatory Authority … 11 3.80.
Reliability Criteria … 11 3.81.
Reliability Upgrade … 11 3.82.
Request for Expedited Interconnection Procedures … 11
PDF page 6
iv
3.83.
Scheduling Coordinator … 11 3.84.
Scheduling Point … 11 3.85.
Site Control … 11 3.86.
Spinning Reserve … 12 3.87.
System Impact Study … 12 3.88.
System Impact Study Agreement … 12 3.89.
TO Tariff … 12 3.90.
Trans Bay Cable (“TBC”) … 12 3.91.
Transition Charge … 12 3.92.
Transmission Control Agreement (“TCA”) … 12 3.93.
Transmission Owner (“TO”) … 12 3.94.
Transmission Revenue Balancing Account Adjustment (“TRBAA”) … 12
3.95.
Transmission Revenue Credit … 12 3.96.
Transmission Revenue Requirement (“TRR”) … 13
3.97.
Transmission System Rights (“TSRs”) … 13 3.98.
Uncontrollable Force … 13 3.99.
Utility Distribution Company (“UDC”) … 13 3.100. Voltage Support … 13 3.101. Western Electricity Coordinating Council (“WECC”) … 13 3.102. Wheeling Access Charge … 13 3.103. Wheeling Out … 14 3.104. Wheeling Through … 14 3.105. Wheeling … 14 3.106. Wholesale Customer … 14
4. Eligibility … 14
5. Access Charges and Transmission Rates … 14 5.1.
Low Voltage Access Charge … 14 5.2.
Wheeling Access Charge … 14 5.3.
Transmission Revenue Requirement … 15 5.4.
Transmission System Rights … 15 5.5.
Transmission Revenue Balancing Account Adjustment … 15
6. Ancillary Services – Applicability and Charges … 16
7. Billing and Payment … 16
8. Obligation to Interconnect or Construct Transmission Expansions and Facility
Upgrades … 16 8.1.
Participating TO Obligation to Interconnect … 16 8.2.
Participating TO Obligation to Construct Transmission Expansions or
Facility Upgrades … 19 8.3.
Request for FERC Deference Regarding Need Determination … 19
9. Participating TO Process for Construction or Expansion of Transmission
Facilities … 19 9.1.
Determination of Facilities … 19 9.2.
Obligation to Build … 21 9.3.
Provisions Relating to Transmission Construction on the Systems of
Other TOs … 23
10. Interconnection Process … 23
PDF page 7
v
10.1.
Applicability … 23 10.2.
Voluntary Offer of Unbundled Retail Transmission Service … 23
10.3.
Role of Participating TO; Coordination … 24 10.4.
Applications … 24 10.5.
Interconnection Application … 24 10.6.
Completed Interconnection Application … 25 10.7.
Review of Completed Interconnection Application … 26
10.8.
Notice of Need for System Impact Study … 26 10.9.
System Impact Study Agreement … 26 10.10. Execution of System Impact Study Agreement … 27 10.11. System Impact Study Cost Reimbursement and Agreement … 27
10.12. System Impact Study Procedures … 28 10.13. Procedures Upon Completion of System Impact Study … 29 10.14. Notice of Need for Facilities Study … 30 10.15. Execution of Facilities Study Agreement … 30 10.16. Facilities Study Procedures … 30 10.17. Interconnection Agreement … 31 10.18. Large Load Partial Interim Service and FILI Service Requests … 32
10.19. Expedited Interconnection Procedures … 34 10.20. Transition for Large Loads … 35
11. Uncontrollable Forces and Indemnification … 35 11.1.
Procedures to Follow If Uncontrollable Force Occurs … 35
11.2.
Indemnification … 35
12. Regulatory Filings … 36 12.1.
Open Access … 36
13. Creditworthiness and Financial Security … 36 13.1.
UDCs, MSSs, and Scheduling Coordinators Using the Participating
TO’s Low Voltage Transmission Facilities … 36 13.2.
End-Users … 36
14. Disputes … 37
15. [Reserved] … 37
16. Miscellaneous … 37 16.1.
Notices … 37 16.2.
Waiver … 37 16.3.
Confidentiality … 37 16.4.
TO Tariff Supersedes Existing Tariffs … 38 16.5.
Titles. T … 38 16.6.
Severability … 38 16.7.
Preservation of Obligations … 38 16.8.
Governing Law … 39 16.9.
Appendices Incorporated … 39 16.10. Conflict With ISO Tariff … 39 16.11. Conflicting Operating Instructions … 39 16.12. Reliability Events … 39 APPENDIX I - Transmission Revenue Requirement and TRBAA … 40 APPENDIX II - Notices … 41
PDF page 8
vi
Attachment A - Cost Recovery Agreement
PDF page 9
1
1. Preamble. The Participating TO’s revenue requirements and applicable rates and charges for transmission access over the ISO Controlled Grid and the terms and conditions for transmission expansion and interconnection are set forth in this TO Tariff and the ISO Tariff. For purposes of this TO Tariff and the ISO Tariff, TBC is a Non-Load-Serving Participating TO and does not provide retail electric service to End-Use Customers. 1.1.
Transmission Access for Participating TOs. Participating TOs are able to participate in the ISO and utilize the entire ISO Controlled Grid to serve their End-Use Customers. The applicable High Voltage Access Charges and Transition Charges shall be paid by Participating TOs to the ISO pursuant to the ISO Tariff. If a Participating TO utilizes the Low Voltage Transmission Facilities of another Participating TO, the Participating TO shall also pay the Low Voltage Access Charge of the other Participating TO.
1.2.
Transmission Access for Wheeling Customers. Wheeling allows Scheduling Coordinators to deliver Energy through or out of the ISO Controlled Grid to serve a load located outside the transmission or Distribution System of a Participating TO. Wheeling Access Charges shall be paid by Scheduling Coordinators to the ISO pursuant to the ISO Tariff.
1.3.
Transmission Access for End-Users. End-Users receive transmission service over the ISO Controlled Grid through the Scheduling Coordinator designated by the End-User. Charges to UDCs, MSSs, and, in certain cases, Scheduling Coordinators on behalf of End-Users for access to the ISO Controlled Grid shall be paid to the applicable Participating TO to whose transmission or distribution facilities the End-User is directly connected consistent with the distribution of the Access Charge in Section 26.13 of the ISO Tariff.
2. Effective Date. This TO Tariff is effective on the date on which the Project is placed into service under the Operational Control of the ISO and shall continue to be effective, as amended from time to time, so long as TBC is a party to the Transmission Control Agreement.
2.1.
Termination. This TO Tariff may be terminated by TBC upon such advance notice and with such authorization as FERC may require.
3. TO Definitions. Capitalized terms used in this TO Tariff shall have the meanings set out below unless otherwise stated or the context otherwise requires. Capitalized terms used in this TO Tariff and not defined below shall have the meanings set out in the ISO Tariff as it may be amended from time to time.
3.1.
Access Charge. A charge paid by all UDCs, MSSs, and, in certain cases, Scheduling Coordinators delivering Energy to Gross Load, as set forth in Section 26.1 of the ISO Tariff. The Access Charge includes the High Voltage Access Charge, the Transition Charge, and the Low Voltage Access Charge, as applicable.
3.2.
AGC. Generation equipment that automatically responds to signals from the
PDF page 10
2
ISO’s EMS control in real time to control the power output of electric generators within a prescribed area in response to a change in system frequency, tieline loading, or the relation of these to each other, so as to maintain the target system frequency and/or the established interchange with other areas within the predetermined limits.
3.3.
Ancillary Services. Regulation, Spinning Reserve, Non-Spinning Reserve, Voltage Support and Black Start together with such other interconnected operation services as the ISO may develop in cooperation with Market Participants to support the transmission of Energy from generation resources to Loads while maintaining reliable operation of the ISO Controlled Grid in accordance with WECC standards and Good Utility Practice.
3.4.
Applicable Reliability Criteria. The Reliability Standards and reliability criteria established by NERC and WECC, and Local Reliability Criteria, as amended from time to time, including any requirement of the Nuclear Regulatory Commission.
3.5.
Available Transfer Capacity. The available capacity of a given transmission path, in MW, after subtraction from that path’s Total Transfer Capability of capacity associated with Existing Contracts and Transmission Ownership Rights and any Transmission Reliability Margin, as established consistent with ISO and WECC transmission capacity rating guidelines, as further described in Appendix L to the ISO Tariff.
3.6.
Base Transmission Revenue Requirement. The Transmission Revenue
Requirement which does not reflect amounts for the TRBAA.
3.7.
Black Start. The procedure by which a Generating Unit self-starts without an external source of electricity, thereby restoring power to the ISO Controlled Grid following system or local area blackouts.
3.8.
Business Day. Monday through Friday, excluding federal holidays and the day after Thanksgiving Day.
3.9.
Completed Application Date. The date on which a party submits an Interconnection Application that satisfies the requirements of a Completed Interconnection Application.
3.10. Completed Interconnection Application. An Interconnection Application that satisfies all of the information and other requirements of Section 10.5 of this TO Tariff and, if applicable, the information requirements as specified by the ISO and posted on the ISO Home Page.
3.11. Congestion. A characteristic of the transmission system produced by a binding Constraint to the optimum economic dispatch to meet Demand such that the LMP, exclusive of Marginal Cost of Losses, at different Locations of the transmission system is not equal.
PDF page 11
3
3.12. Congestion Management. The alleviation of Congestion in accordance with applicable ISO Protocols, the ISO Tariff, and Good Utility Practice. 3.13. Converted Rights. Those transmission service rights determined in accordance with Section 4.3.1.6 of the ISO Tariff.
3.14. CPUC. The California Public Utilities Commission, or its successor. 3.15. Demand. The rates at which Energy is delivered to Load and Scheduling Points by Generation, transmission or distribution facilities. It is the product of voltage and the in-phase component of alternating current measured in units of watts or standard multiples therefore, e.g. 1000 W = 1 kW, 1000 kW = 1 MW, etc. 3.16. Direct Assignment Facilities. Facilities or portions of facilities that are owned by the Participating TO necessary to physically and electrically interconnect a particular party requesting interconnection under this TO Tariff to the ISO Controlled Grid at the point of interconnection. Direct Assignment Facilities shall be specified in the Interconnection Agreement that governs Interconnection service to such party and shall be subject to FERC approval.
3.17. Dispatch. The operating control of an integrated electric system to: (i) assign specific Generation Units and other sources of supply to effect the supply to meet the relevant area Demand taken as Load rises or falls; (ii) control operations and maintenance of high voltage lines, substations, and equipment, including administration of safety procedures; (iii) operate Interconnections; (iv) manage Energy transactions with other interconnected Balancing Authority Areas; and (v) curtail Demand.
3.18. Distribution System. The distribution assets of a TO, UDC, or MSS. 3.19. Eligible Customer. (i) Any utility (including any Participating TO, Market Participant or power marketer), Federal power marketing agency, or any person generating Energy for sale or resale; Energy sold or produced by such entity may be Energy produced in the United States, Canada or Mexico; however, such entity is not eligible for transmission service that would be prohibited by FPA Section 212(h)(2); and (ii) any retail customer taking unbundled transmission service pursuant to a state retail access program or pursuant to a voluntary offer of unbundled retail transmissions service by the Participating TO.
3.20. Encumbrance. A legal restriction or covenant binding on the Participating TO that affects the operation of any transmission lines or associated facilities and which the ISO needs to take into account in exercising Operational Control over such transmission lines or associated facilities if the Participating TO is not to risk incurring significant liability. Encumbrances shall include Existing Contracts and may include: (1) other local restrictions or covenants meeting the definition of Encumbrance and arising under other arrangements entered into before the ISO Operations Date, if any; and (2) legal restrictions or covenants meeting the definition of Encumbrance and arising under a contract or other arrangement
PDF page 12
4
entered into after the ISO Operations Date.
3.21. End-Use Customer or End-User. A consumer of electric power that consumes such power to satisfy a Load directly connected to the ISO Controlled Grid or to a Distribution System and who does not resell the power.
3.22. Energy. The electrical energy produced, flowing, or supplied by Generation, transmission, or distribution facilities, being the integral with respect to time of the instantaneous power, measured in units of watt-hours or standard multiples thereof. E.g. 1000 Wh = 1 kW, 1000 kWh = 1 MWh, etc.
3.23. Entitlement. The right of a Participating TO obtained through contract or other means to use another entity’s transmission facilities for the transmission of Energy.
3.24. Existing Contracts. Those transmission service agreements or other contracts which grant transmission service rights in existence on the ISO Operations Date (including any contracts entered into pursuant to such contracts) as may be amended in accordance with their terms or by agreement between the parties thereto from time to time.
3.25. Existing Rights. Those transmission service rights defined in Section 16.1 of the ISO Tariff.
3.26. Expedited Interconnection Agreement. A contract between a party which has submitted a Request for Expedited Interconnection Procedures and the Participating TO under which the Participating TO agrees to process, on an expedited basis, the Completed Interconnection Application of such party and which sets forth the terms, conditions, and cost responsibilities for such Interconnection.
3.27. Facilities Study Agreement. An agreement between a Participating TO and either a party requesting Interconnection to the ISO Controlled Grid, Market Participants, Project Sponsor, Eligible Customer, or identified principal beneficiaries pursuant to which the party requesting such Interconnection, Market Participant, Project Sponsor, Eligible Customer, or identified principal beneficiaries agrees to reimburse the Participating TO for the cost of performing or reviewing a Facilities Study.
3.28. Facility or Facilities Study. An engineering study conducted to determine required modifications to the Participating TO’s transmission system, including the estimated cost and scheduled completion date for such modifications, that will be required to provide needed services.
3.29. FERC. The Federal Energy Regulatory Commission, or its successor. 3.30. Flexible Interim Load Interconnection (“FILI”) Service. Curtailable, interim interconnection service for a Large Load provided by the ISO and Participating
PDF page 13
5
TO, enabling the Large Load to interconnect prior to the completion of the Large Load’s Network Upgrades or Interconnection Facilities.
3.31. FPA. The Federal Power Act, 16 U.S.C.§ 791a et seq., as it may be amended from time to time.
3.32. Generating Unit. An individual electric generator and its associated plant and apparatus whose electrical output is capable of being separately identified and metered or a Physical Scheduling Plant, that, in either case, is: (a) located within the ISO Balancing Authority Area(which includes a Pseudo-Tie of a generating unit to the ISO Authority Area); (b) connected to the ISO Controlled Grid, either directly or via interconnected transmission or distribution facilities or via a Pseudo-Tie; and (c) that is capable of producing and delivering net Energy (Energy in excess of a generation stations’ internal power requirements). 3.33. Generation. Energy delivered from a Generating Unit.
3.34. Good Utility Practice. Any of the practices, methods, and acts engaged in or approved by a significant portion of the electric utility industry during the relevant time period, or any of the practices, methods, and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety, and expedition. Good Utility Practice is not intended to be limited to any one of a number of the optimum practices, methods, or acts to the exclusion of all others, but rather to be acceptable practice, methods, or acts generally accepted in the region, including those practices required by FPA section 215(a)(4).
3.35. Gross Load. For purposes of calculating the transmission Access Charge, Gross Load is all Energy (adjusted for distribution losses) delivered for the supply of End-Use Customer Loads directly connected to the transmission facilities or directly connected to the Distribution System of a Utility Distribution Company or MSS Operator located in a PTO Service Territory. Gross Load includes Load served by Excess Behind the Meter Production. Gross Load shall exclude (1) Load with respect to which the Wheeling Access Charge is payable, (2) Load that is exempt from the Access Charge pursuant to Section 4.1, Appendix I of the ISO Tariff, and the portion of the load of an individual retail customer of a Utility Distribution Company, Small Utility Distribution Company or MSS Operator that is served by a Generating Unit that: (a) is located on the customer’s site or provides service to the customer’s site through over-the-fence arrangements as authorized by Section 218 of the California Public Utilities Code; (b) is a qualifying small power production facility or qualifying cogeneration facility, as those terms are defined in the FERC’s regulations implementing Section 201 of the Public Utility Regulatory Policies Act of 1978; and (c) secures Standby Service from the Participating TO under terms approved by a Local Regulatory Authority or FERC, as applicable, or can be curtailed concurrently with an Outage of the Generating Unit serving the Load. Gross Load forecasts consistent with
PDF page 14
6
filed Transmission Revenue Requirements will be provided by each Participating TO to the ISO.
3.36. High Voltage Access Charge. A component of the Access Charge determined by the ISO under Section 26.1 of the ISO Tariff.
3.37. High Voltage Transmission Facility. A transmission facility under the Operational Control of the ISO that is owned by the Participating TO or to which the Participating TO has an Entitlement that may be associated with a Converted Right, which operates at a voltage at or above 200 kilovolts, and supporting facilities, and the costs of which are not directly assigned to one or more specific customers.
3.38. High Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s High Voltage Transmission Facilities and Converted Rights associated with High Voltage Transmission Facilities.
3.39. High Voltage Utility-Specific Rate. The Participating TO’s High Voltage Transmission Revenue Requirement divided by the Participating TO’s forecast of its Gross Load.
3.40. High Voltage Wheeling Access Charge. The Wheeling Access Charge assessed by the ISO associated with the recovery of the Participating TO’s High Voltage Transmission Revenue Requirement in accordance with Section 26.1 of the ISO Tariff.
3.41. Independent System Operator (“ISO”). The California Independent System Operator Corporation, a state chartered, nonprofit corporation that controls the transmission facilities of all Participating TOs and dispatches certain Generating Units and Loads.
3.42. Interconnection. Transmission facilities, other than additions or replacements to existing facilities that: (i) connect one system to another system where the facilities emerge from one and only one substation of the two systems and are functionally separate from the ISO Controlled Grid facilities such that the facilities are, or can be, operated and planned as a single facility; (ii) are identified as radial transmission lines pursuant to contract; or (iii) produce Generation at a single point on the ISO Controlled Grid; provided that such interconnection does not include facilities that, if not owned by the Participating TO, would result in a reduction in the ISO’s Operational Control of the Participating TO’s portion of the ISO Controlled Grid.
3.43. Interconnection Agreement. A contract between a party requesting Interconnection and the Participating TO that owns the transmission facility with which the requesting party wishes to interconnect.
3.44. Interconnection Application. An application that requests Interconnection to the
PDF page 15
7
ISO Controlled Grid.
3.45. Interconnection Facilities. Collectively, Interconnection Facilities include all facilities and equipment between the Generating Facility or Large Load and the Point of Interconnection, including any modifications, additions, or upgrades that are necessary to physically and electrically interconnect to the transmission system. Interconnection Facilities are sole use facilities and do not include Distribution Upgrades, Stand Alone Network Upgrades, or Network Upgrades. 3.46. Interest. Interest shall be calculated in accordance with the methodology specified for interest on refunds in the regulations of FERC at 18 C.F.R.§ 35.19(a)(2)(iii). Interest on delinquent amounts shall be calculated from the due date of the bill to the date of payment, except as provided in Section 11.29.13.1 of the ISO Tariff. When payments are made by mail, bills shall be considered as having been paid on the date of receipt.
3.47. ISO ADR Procedures. The procedures for resolution of disputes or differences set out in Section 13 of the ISO Tariff, as amended from time to time. 3.48. ISO Controlled Grid. The system of transmission lines and associated facilities of the Participating TOs that have been placed under the ISO’s Operational Control.
3.49. ISO Protocols. The rules, protocols, procedures and standards promulgated by the ISO (as amended from time to time) to be complied with by the ISO Scheduling Coordinators, Participating TOs and all other Market Participants in relation to the operation of the ISO Controlled Grid and the participation in the markets for Energy and Ancillary Services in accordance with the ISO Tariff. 3.50. ISO Tariff. The California Independent System Operator Agreement and Tariff, dated March 31, 1997, as it may be modified from time to time.
3.51. Large Load. An End-User located at a single site behind one or more Points of Interconnection to the ISO Controlled Grid, and that has a peak load of 50 MW or greater.
3.52. Load. An end-use device of an End-Use Customer that consumes power. Load should not be confused with Demand, which is the measure of power that a Load receives or requires.
3.53. Local Publicly Owned Electric Utility. A municipality or municipal corporation operating as a public utility furnishing electric service, a municipal district furnishing electric services, a public utility district furnishing electric services, an irrigation district furnishing electric services, a state agency or subdivision furnishing electric services, a rural cooperative furnishing electric services, or a joint powers authority that includes one or more of these agencies and that owns Generation or transmission facilities, or furnishes electric services over its own or its members’ electric Distribution System.
PDF page 16
8
3.54. Local Regulatory Authority. The state or local governmental authority responsible for the regulation or oversight of a utility.
3.55. Local Reliability Criteria. Reliability criteria established by the ISO, unique to the transmission systems of each of the Participating TOs, as they may be updated from time to time.
3.56. Low Voltage Access Charge. The Access Charge applicable under Section 26.1 of the ISO Tariff to recover the Low Voltage Transmission Revenue Requirement of the Participating TO.
3.57. Low Voltage Transmission Revenue Requirement. The portion of the Participating TO’s TRR associated with and allocable to the Participating TO’s Low Voltage Transmission Facilities and Converted Rights associated with Low Voltage Transmission Facilities.
3.58. Low Voltage Wheeling Access Charge. The Wheeling Access Charge associated with the recovery of the Participating TO’s Low Voltage Transmission Revenue Requirement in accordance with Section 26.1 of the ISO Tariff.
3.59. Market Participant. An entity, including a Scheduling Coordinator, who participates in the Energy marketplace through the buying, selling, transmission, or distribution of Energy or Ancillary Services into, out of, or through the ISO Controlled Grid.
3.60. Metered Subsystem (“MSS”). A geographically contiguous system, located within a single zone which has been operating as an electric utility for a number of years prior to the ISO Operations Date as a municipal utility, water district, irrigation district, state agency or federal power marketing authority subsumed within the ISO Balancing Authority Area and encompassed by ISO certified revenue quality meters at each interface point with the ISO Controlled Grid and ISO-certified revenue quality meters on all Generating Units or, if aggregated, each individual resource, Participating Load, Reliability Demand Response Resource, and Proxy Demand Response internal to the system, which is operated in accordance with a MSS agreement described in Section 4.9.1 of the ISO Tariff. 3.61. NERC. The North American Electric Reliability Corporation or its successor. 3.62. Network Upgrades. The additions, modifications, and upgrades to the ISO Controlled Grid at or beyond the Point of Interconnection and Distribution System. Network Upgrades do not include Distribution Upgrades or Interconnection Facilities.
3.63. New High Voltage Transmission Facility. A High Voltage Transmission Facility of the Participating TO that enters service on or after the Transition Date described in Section 4 of Appendix F, Schedule 3 of the ISO Tariff, or a capital addition made on or after the Transition Date described in Section 4.1. of Appendix F, Schedule 3 of the ISO Tariff to a High Voltage Transmission Facility
PDF page 17
9
that existed prior to the Transition Date.
3.64. New Participating TO. A Participating TO that is not an Original Participating TO.
3.65. Non-Load-Serving Participating TO. A Participating TO that (1) is not a UDC, MSS Operator or Scheduling Coordinator serving End-Use customers and (2) does not have Gross Load in accordance with ISO Tariff Section 9 of Schedule 3 of Appendix F.
3.66. Non-Participating TO. A TO that is not a party to the TCA or, for the purpose of Section 16.1 of the ISO Tariff, the holder of transmission service rights under an Existing Contract that is not a Participating TO.
3.67. Non-Spinning Reserve. The portion of off-line generating capacity that is capable of being synchronized and ramping to a specified load in ten minutes (or load that is capable of being interrupted in ten minutes) and that is capable of running (or being interrupted) for at least thirty (30) minutes. 3.68. Operational Control. The rights of the ISO under the Transmission Control Agreement and the ISO Tariff to direct Participating TOs how to operate their transmission lines and facilities and other electric plant affecting the reliability of those lines and facilities for the purpose of affording comparable non- discriminatory transmission access and meeting Applicable Reliability Criteria. 3.69. Original Participating TO. A Participating TO that was a Participating TO as of January 1, 2000. The Original Participating TOs are Pacific Gas and Electric Company, Southern California Edison Company, and San Diego Gas & Electric Company.
3.70. Participating TO (“PTO”). A party to the TCA whose application under Section 2.2 of the TCA has been accepted and who has placed its transmission assets and/or Entitlements under the ISO’s Operational Control in accordance with the TCA. A PTO may be an Original Participating TO or a New Participating TO. For the purposes of this Tariff, the Participating TO is TBC.
3.71. Participation Agreement. An agreement between a Participating TO and a Project Sponsor that specifies the terms and conditions under which the Participating TO will construct a transmission addition or upgrade on behalf of the Project Sponsor.
3.72. Physical Scheduling Plant. A group of two or more related Generating Units each of which is individually capable of producing Energy, but which either by physical necessity or operational design must be operated as if they were a single Generating Unit and any Generating Unit or Units containing related multiple generating components which meet one or more of the following criteria: (i) multiple generating components are related by a common flow of fuel which cannot be interrupted without substantial loss of efficiency of the combined
PDF page 18
10
output of all components; (ii) the Energy production from one component necessarily causes Energy production from other components; (iii) the operational arrangement of related multiple generating components determines the overall physical efficiency of the combined output of all components; (iv) the level of coordination required to schedule individual generating components would cause the ISO to incur scheduling costs far in excess of the benefits of having scheduled such individual components separately; or (v) metered output is available only for the combined output of related multiple generation components and separate generating component metering is either impractical or economically inefficient. 3.73. Point of Interconnection. The point, as set forth in the applicable interconnection agreement, where the Interconnection Facilities connect to the ISO Controlled Grid. For Generating Facilities connected to the Distribution System, the Point of Interconnection is the point at which the Generating Facility connects to the ISO Controlled Grid. For a Large Load, the Point of Interconnection is the point at which the Interconnection Facilities connect to the ISO Controlled Grid. 3.74. Project. The approximately fifty-three mile, high voltage, direct current transmission line and associated facilities to establish a dedicated connection between PG&E’s Pittsburg Substation located at a site within the City of Pittsburg, California in Contra Costa County to PG&E’s Potrero Substation within the City of San Francisco. The transmission line will consist of an approximately 7,000 ton bundled cable consisting of a transmission cable, a fiber optic communications cable and a metallic return.
3.75. Project Proponent. A Market Participant or group of Market Participants that (i) advocates a transmission addition or upgrade; (ii) is unwilling to pay the full cost of the proposed transmission addition or upgrade, and thus is not a Project Sponsor; and (iii) initiates proceedings under the ISO ADR Procedures to determine the need for the proposed transmission addition or upgrade. 3.76. Project Sponsor. A Market Participant or group of Market Participants or a Participating TO that proposes the construction of a transmission addition or upgrade in accordance with Section 24 of the ISO Tariff.
3.77. Regional Transmission Group (“RTG”). A voluntary organization approved by FERC and composed of transmission owners, transmission users, and other entities, organized to efficiently coordinate the planning, expansion, and use of transmission on a regional and inter-regional basis.
3.78. Regulation. The service provided either by Generating Units certified by the ISO as equipped and capable of responding to the ISO’s direct digital control (AGC) signals, or by System Resources that have been certified by the ISO as capable of delivering such service to the ISO Balancing Authority Area, in an upward and downward direction to match, on a Real Time basis, Demand and resources, consistent with established NERC and WECC reliability standards, including any requirements of the Nuclear Regulatory Commission. Regulation is used to
PDF page 19
11
control the Power output of electric generators within a prescribed area in response to a change in system frequency, tieline loading, or the relation of these to each other so as to maintain the target system frequency and/or the established interchange with other Balancing Authority Areas within the predetermined Regulation Limits. Regulation includes both the increase of output by a Generating unit or System Resource (Regulation Up) and the decrease in output by a Generating unit or System Resource (Regulation Down). Regulation Up and Regulation Down are distinct capacity products, with separately stated requirements and ASMPs in each Settlement Period.
3.79. Regulatory Authority. In the case of TBC, the FERC.
3.80. Reliability Criteria. Pre-established criteria that are to be followed in order to maintain desired performance of the ISO Controlled Grid under contingency or steady state conditions.
3.81. Reliability Upgrade. The transmission facilities other than Direct Assignment Facilities beyond the first point of Interconnection necessary to interconnect a facility, Large Load, or wholesale Load safely and reliably to the ISO Controlled Grid, which would not have been necessary but for the Interconnection of a facility, Large Load, or wholesale Load, including network upgrades necessary to remedy short circuit or stability problems resulting from the Interconnection of the facility, Large Load, or wholesale Load to the ISO Controlled Grid. Reliability Upgrades also include, consistent with WECC practice, the facilities necessary to mitigate any adverse impact a facility’s, Large Load’s, or wholesale Load’s Interconnection may have on a path’s WECC path rating. Reliability Upgrades shall be specified in the Interconnection Agreement that governs Interconnection service and shall be subject to FERC approval.
3.82. Request for Expedited Interconnection Procedures. A written request by which an applicant for Interconnection can request expedited processing of its interconnection Application.
3.83. Scheduling Coordinator. An entity certified by the ISO for the purpose of undertaking the functions specified in Section 4.5 of the ISO Tariff. 3.84. Scheduling Point. A location at which the ISO Controlled Grid or a transmission facility owned by a Transmission Ownership Right holder is connected, by a group of transmission paths for which a physical, non-simultaneous transmission capacity rating has been established for Congestion Management, to transmission facilities that are outside the ISO’s Operational Control.
3.85. Site Control. The exclusive land right to develop, construct, operate, and maintain the Generating Facility or Large Load over the term of the expected operation of the Generating Facility or Large Load. Site Control may be demonstrated by documentation establishing: (1) ownership of, a leasehold interest in, or a right to develop a site of sufficient size to construct and operate
PDF page 20
12
the Generating Facility or Large Load; (2) an option to purchase or acquire a leasehold site of sufficient size to construct and operate the Generating Facility or Large Load; or (3) any other documentation that clearly demonstrates the right to exclusively occupy a site of sufficient size to construct and operate the Generating Facility or Large Load.
3.86. Spinning Reserve. The portion of unloaded synchronized generating capacity, that is immediately responsive to system frequency and that is capable of being loaded in ten minutes, and that is capable of running for at least thirty (30) minutes.
3.87. System Impact Study. An engineering study conducted to determine whether a request for Interconnection to the ISO Controlled Grid would require new transmission additions, upgrades, or other mitigation measures.
3.88. System Impact Study Agreement. An agreement between a Participating TO and an entity that has requested Interconnection to the Participating TO’s transmission system pursuant to which the entity requesting Interconnection agrees to reimburse the Participating TO for the cost of performing or reviewing a System Impact Study.
3.89. TO Tariff. This Transmission Owner Tariff, as it may be amended or superseded. 3.90. Trans Bay Cable (“TBC”). The Delaware limited liability company that is the Participating TO under this TO Tariff.
3.91. Transition Charge. A component of the Access Charge determined by the ISO and assessed by the Participating TO along with the High Voltage Access Charge in accordance with Section 5.7 of Appendix F, Schedule 3 of the ISO Tariff. 3.92. Transmission Control Agreement (“TCA”). The agreement between the ISO and Participating TOs establishing the terms and conditions under which TOs will become Participating TOs and how the ISO and each Participating TO will discharge its respective duties and responsibilities, as may be modified from time to time.
3.93. Transmission Owner (“TO”). An entity owning transmission facilities or having firm contractual rights to use transmission facilities.
3.94. Transmission Revenue Balancing Account Adjustment (“TRBAA”). A mechanism established by the Participating TO which will ensure that all Transmission Revenue Credits and other credits specified in Sections 6 and 8 of Appendix F, Schedule 3 of the ISO Tariff, flow through to ISO Tariff and TO Tariff transmission customers.
3.95. Transmission Revenue Credit. The proceeds received from the ISO (other than for the recovery of the Participating TO’s High Voltage and Low Voltage Transmission Revenue Requirement through the High Voltage and Low Voltage
PDF page 21
13
Transmission Access Charges) and charges imposed by the ISO that are received and paid by the Participating TO in its role as Participating TO, as defined in the ISO Tariff.
3.96. Transmission Revenue Requirement (“TRR”). The total annual authorized revenue requirement associated with (1) transmission facilities and Entitlements turned over to the Operational Control of the ISO by the Participating TO or (2) transmission facilities that are not yet in operation, but have been approved under Section 24 and assigned to an Approved Project Sponsor. The costs of any transmission facility turned over to the Operational Control of the ISO shall be fully included in the Participating TO’s TRR. The TRR includes the costs of transmission facilities and Entitlements and deducts Transmission Revenue Credits, credits for Standby Transmission Revenue and Cost Recovery Agreement payments, and is shown in Appendix I.
3.97. Transmission System Rights (“TSRs”). TSRs represent Trans Bay Cable’s exclusive transmission entitlement on the Project. Trans Bay Cable, as the holders of the TSRs, is entitled to all associated rights as are available under the ISO Tariff and Protocols. The use of this definition does not limit Trans Bay Cable from seeking any additional revenues or rights that are authorized by FERC due to a beneficial increase in the ISO controlled grid capacity resulting from this Project.
3.98. Uncontrollable Force. Any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm, flood, earthquake, explosion, any curtailment, order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities or any other cause beyond the reasonable control of the ISO or Market Participant, as the case may be, which could not be avoided through the exercise of Good Utility Practice.
3.99. Utility Distribution Company (“UDC”). An entity that owns a Distribution System for the delivery of Energy to and from the ISO Controlled Grid, and/or that provides regulated retail electric service to End-Users, as well as regulated procurement service to those End-Users who are not yet eligible for direct access, or who choose not to arrange service through another retailer.
3.100. Voltage Support. Services provided by Generating Units or other equipment such as shunt capacitors, static var compensators, or synchronous condensers that are required to maintain established grid voltage criteria. This service is required under normal or system emergency conditions.
3.101. Western Electricity Coordinating Council (“WECC”). The Western Electricity Coordinating Council or its successor.
3.102. Wheeling Access Charge. The charge assessed by the ISO that is paid by a Scheduling Coordinator for Wheeling in accordance with Section 26.1.4.1 of the ISO Tariff. Wheeling Access Charges shall not apply for Wheeling under a
PDF page 22
14
bundled non-economy Energy coordination agreement of a Participating TO executed prior to July 9, 1996. The Wheeling Access Charge consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge.
3.103. Wheeling Out. Except for Existing Rights exercised under an Existing Contract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a Generating Unit located within the ISO Controlled Grid to serve a Load located outside the transmission and Distribution System of a Participating TO.
3.104. Wheeling Through. Except for Existing Rights exercised under an Existing Contract in accordance with Section 16.1 of the ISO Tariff, the use of the ISO Controlled Grid for the transmission of Energy from a resource located outside the ISO Controlled Grid to serve a Load located outside the transmission and Distribution System of a Participating TO.
3.105. Wheeling. Wheeling Out or Wheeling Through.
3.106. Wholesale Customer. A person wishing to purchase Energy and Ancillary Services at a Bulk Supply Point or a Scheduling Point for resale.
4. Eligibility. Transmission service over a Participating TO’s system shall be provided only to Eligible Customers.
4.1.
Intentionally Left Blank. Not used.
5. Access Charges and Transmission Rates. The applicable Access Charges are provided in the ISO Tariff.
5.1.
Low Voltage Access Charge. The Low Voltage Access Charge shall be determined in accordance with the ISO Tariff. As TBC is a Non-Load-Serving Participating TO, the ISO shall charge for and collect the Low Voltage Access Charge on TBC’s behalf pursuant to Section 26.1 and Appendix F, Schedule 3, Section 13 of the ISO Tariff from the Participating TO to whose facilities TBC’s Low Voltage Transmission Facilities are directly connected. The rate for TBC’s Low Voltage Access Charge shall be TBC’s Low Voltage Transmission Revenue Requirement divided by the forecasted Gross Load of the Participating TO that is the Low Voltage Access Charge customer. The Low Voltage Access Charge customer shall pay the ISO a Low Voltage Access Charge equal to the product of the TBC’s Low Voltage Access Charge rate and the actual Gross Load of the Participating TO that is the Low Voltage Access Charge customer. Gross Load associated with a Large Load is attributed to the Large Load’s load-serving entity or Scheduling Coordinator under the ISO Tariff and service under Section 10 doesn’t make TBC a UDC, MSS, or Scheduling Coordinator serving End-Use Customers.
5.2.
Wheeling Access Charge. The Wheeling Access Charge shall be determined in
PDF page 23
15
accordance with the ISO Tariff. The Wheeling Access Charge assessed by the ISO consists of a High Voltage Wheeling Access Charge and, if applicable, a Low Voltage Wheeling Access Charge. The High Voltage Wheeling Access Charge is set forth in the ISO Tariff.
5.3.
Transmission Revenue Requirement. As set forth in the ISO Tariff, the Transmission Revenue Requirement for each Participating TO is used to develop the Access Charges set forth in the ISO Tariff and is used by the ISO to calculate the disbursement of Wheeling revenues among Participating TOs. Wheeling revenues are disbursed by the ISO to Participating TOs pursuant to Section 26.1.4.3 of the ISO Tariff. The Transmission Revenue Requirement, High Voltage Transmission Revenue Requirement, and Low Voltage Transmission Revenue Requirement for the Participating TO are set forth in Appendix I. 5.4.
Transmission System Rights. TBC owns the TSRs with respect to the Project. 5.5.
Transmission Revenue Balancing Account Adjustment. The Participating TO shall maintain a Transmission Revenue Balancing Account with an annual Transmission Revenue Balancing Account Adjustment (“TRBAA”) that will ensure that all Transmission Revenue Credits and adjustments for any over- or under-recovery of its annual Transmission Revenue Requirement, if any, specified in Sections 6, 8 and 13 of Appendix F, Schedule 3 of the ISO Tariff, flow through to transmission customers. The TRBAA used to calculate the High Voltage Revenue Requirement shall include other adjustments specified in Appendix F, Schedule 3, Sections 6, 8, and 13 of the ISO Tariff. The TRBAA shall be equal to:
TRBAA = Cr + Cf + I
Where:
Cr = The principal balance in the Transmission Revenue Balancing Account (“TRBA”) recorded in FERC Account No. 254 as of September 30 of the year prior to commencement of the January billing cycle. This balance represents the unamortized balance in the TRBA from the previous period and the difference in the amount of revenues or expenditures from Transmission Revenue Credits and any over- or under-recovery of its annual Transmission Revenue Requirement and the amount of such revenues or expenditures that has been refunded to or collected from customers through operation of the TRBAA;
Cf = The forecast of Transmission Revenue Credits, if any, for the following calendar year;
I = The interest balance for the TRBA, which shall be calculated using the interest rate pursuant to Section 35.19(a) of FERC’s regulations under the Federal Power Act (18 CFR Section 35.19(a)). Interest shall be calculated
PDF page 24
16
based on the average TRBA principal balance each month, compounded quarterly; and
The TBC TRBAA, calculated in accordance with the ISO Tariff and approved by the FERC, is stated in Appendix I.
6. Ancillary Services – Applicability and Charges. Ancillary Services are needed to maintain reliability within the ISO Controlled Grid. If any Ancillary Services are required, TBC will not provide such services directly to the transmission customer and the transmission customer will be required to meet any such requirement in accordance with the ISO Tariff.
7. Billing and Payment.
7.1.
The ISO, in accordance with the ISO Tariff, shall pay the Participating TO, among other things, all applicable Access Charge revenues and Wheeling revenues in connection with the Project.
7.2.
Users of TBC’s High and Low Voltage Transmission Facilities and Entitlements placed under the ISO’s Operational Control shall pay to the ISO all applicable charges in accordance with the ISO Tariff.
8. Obligation to Interconnect or Construct Transmission Expansions and Facility Upgrades
8.1.
Participating TO Obligation to Interconnect. The Participating TO shall, at the request of a third party, interconnect its system to the wholesale generation, Load, or Large Load owned by or served by such third party, or modify an existing Interconnection. Interconnections under this TO Tariff shall be available to entities eligible to request Interconnection consistent with the provisions of Section 210(a) of the FPA and to Eligible Customers. The procedures for Interconnection of wholesale generation to the ISO Controlled Grid shall be governed by the ISO Tariff.
8.1.1. Interconnection to Transmission System. Interconnection must be consistent with Good Utility Practice, in conformance with all Applicable Reliability Criteria, all applicable statutes, regulations, and ISO reliability criteria for the ISO Controlled Grid. The Participating TO will not accommodate the Interconnection if doing so would impair systems reliability, or would otherwise impair the ability of the Participating TO to honor its Encumbrances existing as of the time an entity submits its Interconnection Application. The Participating TO shall identify any such adverse effect on its Encumbrances in the System Impact Study performed pursuant to Section 10.12. To the extent the Participating TO determines that the Interconnection will have an adverse effect on Encumbrances, the party requesting Interconnection shall mitigate such adverse effect. 8.1.2. Costs Associated with Interconnection. Each party requesting
PDF page 25
17
Interconnection shall pay the costs of planning, installing, owning, operating, and maintaining any Direct Assignment Facilities, Interconnection Facilities, and, if applicable, any Reliability Upgrades or Network Upgrades required to provide the requested Interconnection. In addition, such party shall implement all existing operating procedures necessary to safely and reliability interconnect such party’s generation, Large Load, or wholesale load to the facilities of the Participating TO and to ensure the ISO Controlled Grid’s conformance with the ISO Grid Planning Criteria, and shall bear all costs of implementing such operating procedures. Any additional costs associated with accommodating the Interconnection shall be allocated in accordance with the cost responsibility methodology set forth in Attachment A of the TO Tariff and the ISO Tariff for transmission expansions or upgrades.
8.1.3. [Reserved]
8.1.4. Due Diligence to Construct. The Participating TO shall use due diligence to construct, within a reasonable time, any Direct Assignment Facilities and any Reliability Upgrades that it is obligated to construct pursuant to this TO Tariff and Section 24 of the ISO Tariff. The Participating TO’s obligation to build will be subject to: (1) its ability, after making a good faith effort, to obtain any necessary approvals and property rights under applicable federal, state, and local laws; (2) the presence of a cost recovery mechanism with cost responsibility assigned to accordance with the ISO Tariff or applicable FERC precedent; and (3) a signed Interconnection Agreement or a signed Expedited Interconnection Agreement, or, by mutual agreement of the parties, FERC acceptance for filing of an unexecuted Interconnection Agreement.
8.1.5. Energization. The Participating TO shall not be obligated to energize, nor shall the applicant, Large Load, or wholesale load be entitled to have its interconnection to the ISO Controlled Grid energized, unless and until an Interconnection Agreement has been executed, or filed at FERC pursuant to Section 10.17, and become effective and such applicant, Large Load, or wholesale load has demonstrated to the ISO’s reasonable satisfaction that it has complied with all of the requirements of the ISO Tariff and the requirements of this TO Tariff.
8.1.5.1. Large Load Energization. In addition to the requirements of Section 8.1.5, the Participating TO shall not be obligated to energize a Large Load Interconnection until the Eligible Customer has demonstrated to the Participating TO’s reasonable satisfaction that:
(i) the Interconnection Agreement and Cost Recovery
Agreement have been executed, or have been filed with FERC
unexecuted pursuant to Section 10.17 and become effective;
PDF page 26
18
(ii) to the extent the Large Load will withdraw Energy from the ISO Controlled Grid (including for backup, standby, or maintenance service), the Large Load will purchase that Energy from an entity authorized to make such sales by, and in accordance with the requirements of, state law and the applicable Local Regulatory Authority, which may include the Large Load acting as its own Load Serving Entity consistent with Section 25.7.3.1 of the ISO Tariff;
(iii) to the extent the Large Load will withdraw Energy from the ISO Controlled Grid, a Scheduling Coordinator will represent the Large Load in compliance with Section 25.7.3 or Section 25.7.3.1 of the ISO Tariff, as applicable;
(iv) Access Charges will be paid consistent with the ISO Tariff;
(v) the information required by Section 25.7.1 of the ISO Tariff has been provided to the Participating TO;
(vi) the monitoring, disturbance recording, telemetry, communication, control, protection, and disconnection equipment required by the Interconnection Agreement and Section 25.7.1 of the ISO Tariff has been installed, tested, and commissioned;
(vii) if FILI Service has been requested, the FILI Service Agreement has been executed and become effective;
(viii) all financial security required under Section 13.2.1 and the Cost Recovery Agreement has been provided;
(ix) if the Large Load is co-located with, or served by behind- the-meter, generation or storage, the control and system protection technologies have been installed, tested, and validated by the Participating TO, and the Large Load is metered separately from that generation and storage consistent with Sections 25.7.5 and 11.36 of the ISO Tariff; and
(x) the Large Load must meet all frequency ride-through requirements, voltage ride through requirements, post-fault active power recovery requirements, and ramp rate limitations in accordance with ISO Tariff Sections 25.7.1.1, 25.7.1.2, 25.7.1.3, and 25.7.1.4.
8.1.6. Coordination with ISO on Interconnection Requests. The Participating TO shall coordinate with the ISO, pursuant to the provisions of the TCA,
PDF page 27
19
in developing interconnection standards and guidelines for processing interconnection request under this TO Tariff.
8.2.
Participating TO Obligation to Construct Transmission Expansions or Facility Upgrades. The Participating TO shall be obligated to: (1) perform System Impact or Facilities Studies where the Project Sponsor or the ISO agrees to pay the study cost and specifies the project objectives to be achieved, and (2) build transmission additions and facility upgrades where the Participating TO is obligated to construct or expand facilities in accordance with and subject to the limitations under Section 24 of the ISO Tariff and this TO Tariff. 8.2.1. Obligation to Construct. A Participating To shall not be obligated to construct or expand transmission facilities or system upgrades unless and until the conditions stated in Section 9.2.1 hereof have been satisfied. 8.3.
Request for FERC Deference Regarding Need Determination. It is intended that FERC grant substantial deference to the factual determinations of the ISO, (including the ISO’s ADR Procedures), the CPUC, WECC, or RTG coordinated planning processes as to the need for or construction of a facility, the need for full cost recovery, and the allocation of costs.
9. Participating TO Process for Construction or Expansion of Transmission Facilities 9.1.
Determination of Facilities. A Participating TO shall perform a Facilities Study in accordance with the Section where (1) the Participating TO is obligated to construct or expand facilities in accordance with Section 24 of the ISO Tariff and this TO Tariff; (2) a Market Participant agrees to pay the costs of the Facilities Study and specifies the project objectives to be achieved in terms of increase capacity or reduce congestion; or (3) the Participating TO is required to perform a Facilities Study pursuant to the ISO Tariff.
9.1.1. Payment of Facilities Study’s Cost.
9.1.1.1. Market Participant to Pay for Facilities Study. Where a Market Participant requests a Facilities Study and the need for the
transmission addition or upgrade has not bet been established in accordance with the procedures established herein and the ISO
Tariff, the Market Participant shall pay the cost of the Facilities Study.
9.1.1.2. Project Sponsor or Project Proponent to Pay for Facilities Study. Where the facilities to be added or upgraded have been
determined to be needed in accordance with the procedures
established herein, the Project Sponsor, Project Proponent, or the ISO requesting the study shall pay in advance the reasonable cost of the Facilities Study. When the Participating TO is the Project Sponsor in accordance with the ISO Tariff, the costs of the
Facilities Study shall be recovered through its Access Charges and
PDF page 28
20
transmission rates.
9.1.1.3. Principal Beneficiaries to Pay for Facilities Study. Where the facilities to be added or upgraded have been determined to be needed and the principal beneficiaries have been identified by the ISO or ISO ADR Procedures in accordance with the ISO Tariff, the Project Sponsor and the identified principal beneficiaries shall pay the reasonable cost of the Facilities Study, in such proportions as may be agreed, or, failing agreement, as determined in
accordance with the ISO ADR Procedures.
9.1.2. Payment Procedure. Where a Facilities Study is being conducted pursuant to this TO Tariff, the Participating TO shall, within thirty days of the receipt of all reasonably required information, tender to the Market Participant, Project Sponsor, Project Proponent, ISO, or identified principal beneficiaries, as the case may be, a Facilities Study Agreement that defines the scope, content, assumptions, and terms of reference for such study, the estimated time required to complete it, and such other provisions as the parties may reasonably require and pursuant to which such Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries agree to reimburse the Participating TO the reasonable cost of performing the required Facilities Study. If the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, agree to the terms of the Facilities Study Agreement, they shall execute the Facilities Study Agreement and return it to the Participating TO within ten Business Days. Alternatively, if the Market Participant, Project Sponsor, Project Proponent, the ISO, or identified principal beneficiaries, as the case may be, request the Participating TO to proceed with the Facilities Study and commit to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures.
9.1.3. Facilities Study Procedures. Upon receipt of an executed Facilities Study Agreement or alternative request to proceed as provided for in Section 9.1.2, a copy of which has been provided to the ISO by the party requesting the Facilities Study, the Participating TO will use due diligence to complete the required Facilities Study within a sixty (60) day period. If the Participating TO is unable to complete the Facilities Study in the allotted time period, the Participating TO shall notify the Market Participant or Eligible Customer and provide an estimate of the time needed to reach a final determination along with an explanation of the reasons that additional time is required to complete the study. If additional time is required, the Participating TO will use best efforts to complete the
PDF page 29
21
study within 10 months, provided adequate information is provided by all the parties.
9.2.
Obligation to Build.
9.2.1. Due Diligence to Construct. Subject to Section 9.3 of this TO Tariff, the Participating TO shall use due diligence to construct, within a reasonable time, additions or upgrades to its transmission system that it is obligated to construct pursuant to the ISO Tariff and this TO Tariff. Alternatively, if a Market Participant or Eligible Customer requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement or alternatively, if a Market Participant or Eligible Customer requests the Participating TO to file an unexecuted Participation Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Participation Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted Participation Agreement, commence construction of the additions or upgrades or incur other costs under the Participation Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Participation Agreement has been issued by the applicable court or regulatory authority. The Participating TO’s obligation to build will be subject to: 1) its ability, after making a good faith effort, to obtain the necessary approvals and property rights under applicable federal, state, and local laws; 2) the presence of a cost recovery mechanism with cost responsibility assigned in accordance with the ISO Tariff; and 3) a signed Participation Agreement. The Participating TO will not construct or expand its existing or planned transmission system, if doing so would impair system reliability as determined through systems analysis based on the Applicable Reliability Criteria.
9.2.2. Delay in Construction or Expansion. If any event occurs that will materially affect the time for completion of new facilities, or the ability to complete them, the Participating TO shall promptly notify: (1) the Project Sponsor with regard to facilities determined to be needed; (2) the Parties to the Participation Agreement with regard to facilities determined to be needed pursuant to the ISO Tariff where principal beneficiaries were
PDF page 30
22
identified; and (3) the ISO. In such circumstances, the Participating TO shall, within thirty days of notifying such Project Sponsor, Parties to the Participation Agreement, and the ISO of such delays, convene a technical meeting with such Project Sponsor, Parties to the Participation Agreement, and the ISO to discuss the circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is circumstances which have arisen and evaluate any options available. The Participating TO also shall make available to such Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be, studies and work papers related to the cause and extent of the delay and the Participating TO’s ability to complete the new facilities, including all information that is in the possession of the Participating TO that is reasonably needed to evaluate the alternatives.
9.2.2.1 Alternatives to the Original Facility Additions. If the review process of Section 9.2.2 determines that one or more alternatives exist to the originally planned construction project, the
Participating TO shall present such alternatives for consideration to the Project Sponsor, Parties to the Participation Agreement, and the ISO, as the case may be. If upon review of any alternatives, such Project Sponsor, the ISO, or Parties to the Participation Agreement wish to evaluate or to proceed with one of the
alternative additions or upgrades, such Project Sponsor, the ISO, or Parties to the Participation Agreement may request that the Participating TO prepare a revised Facilities Study pursuant to Sections 9.1.1, 9.1.2, and 9.1.3 of this TO Tariff. In the event the Participating TO concludes that no reasonable alternative exists to the originally planned addition or upgrade and the Project Sponsor or Parties to the Participation Agreement or the ISO disagree, the dispute shall be resolved pursuant to the ISO ADR Procedure. 9.2.2.2 Refund Obligation for Unfinished Facility Additions. If the Participating TO and the Project Sponsor, the ISO, or Parties to the Participation Agreement, as the case may be, mutually agree that no other reasonable alternatives exist, the obligation to construct the requested additions or upgrades shall terminate and any deposit not yet applied toward the expended project costs shall be returned with interest pursuant to FERC Regulation 35.19(a)(2)(iii). However, the Project Sponsor and any identified principal
beneficiaries, as the case may be, shall be responsible for all costs prudently incurred by the Participating TO through the time the construction was suspended.
PDF page 31
23
9.3.
Provisions Relating to Transmission Construction on the Systems of Other TOs.
9.3.1. Responsibility for Third Party Additions. A Participating TO shall not be responsible for making arrangements for any engineering, permitting, and construction of transmission or distribution facilities on the system(s) of any other entity or for obtaining any regulatory approval for such facilities. The Participating TO will undertake reasonable efforts through the coordinated planning process to assist in making such arrangements, including, without limitation, providing any information or data required by such other electric system pursuant to Good Utility Practice. 9.3.2. Coordination of Third-Party System Additions. Where transmission additions or upgrades being built pursuant to the ISO Tariff require additions or upgrades on other systems, to the extent consistent with Section 9.3 of this TO Tariff, the Participating TO shall coordinate construction on its own system with the construction required by others. The Participating TO, after consultation with the ISO, the Project Sponsor, and Parties to the Participation Agreement, as the case may be, may defer construction if the new transmission facilities on another system cannot be completed in a timely manner. The Participating TO shall notify such Project Sponsor, Parties to the Participation Agreement, and the ISO, in writing of the basis for any decision to defer construction and the specific problems which must be resolved before it will initiate or resume construction of the new facilities. Within forty Business Days of receiving written notification by the Participating TO of its intent to defer construction pursuant to this section, such Project Sponsor, Parties to the Participation Agreement, or the ISO may challenge the decision in accordance with the ISO ADR Procedure.
10. Interconnection Process
10.1. Applicability. All requests for Interconnection directly to the ISO Controlled Grid from Eligible Customers, including entities eligible to request such Interconnection under Section 210(a) of the FPA shall be processed pursuant to the provisions of this Section 10. All requests for Interconnection of wholesale generation directly to the ISO Controlled Grid shall be processed pursuant to the provisions of the ISO Tariff. A Large Load Interconnection must be requested in compliance with this Section 10 in order to connect the facilities of the Participating TO to the facilities of an Eligible Customer and must comply with Section 25.7 of the ISO Tariff.
10.2. Voluntary Offer of Unbundled Retail Transmission Service. Pursuant to clause (ii) of the definition of Eligible Customer, TBC voluntarily offers unbundled retail transmission service to any End-Use Customer whose Point of Interconnection is on facilities owned by TBC. Such service consists solely of Interconnection to TBC’s facilities and associated access to the ISO Controlled
PDF page 32
24
Grid in accordance with the ISO Tariff and where consistent with state law, and does not include the sale of Energy, distribution service, or scheduling or settlement in the ISO Markets. TBC shall provide such service on a non- discriminatory basis in accordance with this TO Tariff.
10.3. Role of Participating TO; Coordination. Participating TO will apprise the ISO of Large Load interconnections to its facilities through its inputs to the Base Case, Interconnection Studies, and Transmission Planning Process. After receiving a Completed Large Load Interconnection Application, Participating TO will notify TOs with transmission facilities potentially affected by the proposed Interconnection. Participating TO will coordinate the conduct of any studies required to determine the impact of the Large Load Interconnection Application with affected TOs, to the extent possible. The Participating TO will coordinate with ISO and affected TOs to identify any upgrades to other TO transmission facilities necessary to accommodate the Interconnection. Prior to energization of any Large Load to the ISO Controlled Grid, Participating TO will provide ISO with the information required by Section 25.7.1 of the ISO Tariff, and the Eligible Customer shall provide Participating TO such ISO Tariff Section 25.7.1 information, and notify it of any material change, within ten (10) Business Days. 10.4. Applications. A party requesting Interconnection shall submit a written Interconnection Application which provides the information required in Section 10.5 to the Participating TO and shall send a copy of the application to the ISO. The Participating TO shall time-stamp the application to establish study priority on a rolling basis.
10.5. Interconnection Application. An Interconnection Application shall provide all the information listed in 18 CFR§2.20, including, but not limited to, the following: (i) the identity, address, telephone number, and email of the entity requesting interconnection; (ii) the Interconnection point(s) to the ISO Controlled Grid contemplated by the applicant; (iii) the resultant (or new) maximum amount of Interconnection capacity contemplated by the applicant; (iv) the proposed date for energizing the Interconnection and the term of the Interconnection service, and
(v) such other information as the Participating TO reasonably required to process the application . In addition to the information specified above, the following information may also be provided in order to properly evaluate system conditions:
(vi) If the applicant is an Eligible Customer requesting Large Load Interconnection or wholesale load, the electrical location of the source of the power (if known) to be transmitted pursuant to applicant’s request for Interconnection. If the source of the power is not known, a system purchase will be assumed. If the location of the load is not known, a system sale will be assumed; and, in addition, if an applicant proposes to perform or cause a third party to perform any required System Impact Study or any required Facilities Study, it shall so indicate in its Interconnection Application. The results of any study or studies performed by an applicant must be approved by both the ISO and the Participating TO. An Interconnection applicant must pay a $5,000 nonrefundable application fee.
PDF page 33
25
10.5.1. Large Load Interconnection Application. In addition to Section 10.5, an Interconnection Application from an Eligible Customer for a Large Load must provide (i) the proposed Large Load’s ramp schedule, identifying load additions over time and the Large Load’s maximum planned load; (ii) a site plan; (iii) documentation demonstrating that the Large Load has local, state, and federal permits and/or regulatory approvals necessary for the development of its Large Load; (iv) documentation demonstrating that the Large Load has Site Control; (v) a single-line electrical diagram; (vi) information regarding any other Interconnection requests in the applicant’s footprint that are made on behalf of the same Large Load or any of its affiliates; (vii) affirmation regarding whether the Large Load intends to request Partial Interim Service or FILI Service; and (viii) if the applicant is submitting an Interconnection Application for a Large Load co-located with a Generating Facility, additional information concerning the Generating Facility sufficient to allow the Participating TO to ensure compliance with the requirements of Sections 25.1.1, 25.7.5, and 25.7.6 of the ISO Tariff. A site subject to a development moratorium or other governmental restriction that prohibits the proposed use shall not satisfy the Site Control requirement unless the restriction has been lifted or the applicant has obtained all necessary approvals, exemptions, or variances permitting the proposed use.
10.6. Completed Interconnection Application. Within ten (10) Business Days after receipt of an Interconnection Application, the Participating TO and the ISO if applicable shall determine whether the application is complete (“Completed Interconnection Application”). Whenever possible, the Participating TO will attempt to remedy deficiencies in the Interconnection Application through informal communications with the applicant. If such efforts are unsuccessful, the Participating TO shall return the Interconnection Application to the applicant. The Participating TO will treat the information in the Interconnection Application, including the applicant’s identity, as confidential at the request of the applicant except to the extent that disclosure of the information is required by this TO Tariff, by regulatory or judicial order, for reliability purposes pursuant to Good Utility Practice, or pursuant to RTG or ISO transmission information sharing agreements. The Participating TO shall treat this information consistent with the standards of conduct contained in Part 37 of FERC’s regulations. 10.6.1. Amendment to Completed Interconnection Application. An applicant shall only be limited to amending its Completed Interconnection Application once. Such amendment shall occur on or before ten (10) Business Days following the date the Participating TO tenders any Facilities Study Agreement. Specifically, an applicant may submit an amendment to its Completed Interconnection Application to reflect a revised configuration for its facility. The amended Completed Interconnection Application shall be treated in accordance with Section 25
PDF page 34
26
of the ISO Tariff and Section 10.6 of this TO Tariff; the applicant’s Completed Interconnection Application shall be deemed withdrawn; and the applicant shall maintain its existing queue position, if (a) the amended Completed Interconnection Application is received by the Participating TO within ten (10) Business Days of the Participating TO’s tender of a Facilities Study Agreement; and (b) the applicant has not submitted a previous amendment to the Completed Interconnection Application. In the event an applicant amends its Completed Interconnection Application, it will be responsible for any additional study costs that result from that amendment, including costs associated with revisions to studies for other applicants holding later queue positions.
10.7. Review of Completed Interconnection Application. After receiving a Completed Interconnection Application, the Participating TO and the ISO, if applicable, will determine on a non-discriminatory basis whether a System Impact Study is required. Whenever the Participating TO, and the ISO, if applicable, determines that a System impact Study is not required and that neither Reliability Upgrades nor changes in existing operating procedures are required, the Participating TO shall notify the applicant within ten (10) Business Days of the Completed Application Date. If the Interconnection can be accommodated without any additions or upgrades, then within thirty (30) Business Days of such notice from the Participating TO, the applicant shall request the Participating TO to tender to the applicant an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provide in Section 10.17.
10.8. Notice of Need for System Impact Study. If the Participating TO, and the ISO, if applicable, determines that a System Impact Study is necessary to accommodate the requested Interconnection, the Participating TO shall so inform the applicant, within ten (10) Business Days of the Completed Application Date. 10.9. System Impact Study Agreement. In such cases, the Participating TO shall within ten (10) Business Days of receipt of a Completed Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO, the estimated time required to complete it, and such other provisions as the parties may reasonably require, and pursuant to which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of performing the required System Impact Study. A description of the Participating TO’s transmission assessment practices for completing a System Impact Study is provided in the Participating TO’s FERC Form 715. Alternatively, if the applicant will perform the System Impact Study, the Participating TO shall within ten (10) Business Days of receipt of a Completed Interconnection Application, tender a System Impact Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete it; and such other provisions as the parties may reasonably require, and pursuant to
PDF page 35
27
which the applicant shall agree to reimburse the Participating TO for the reasonable actual costs of reviewing the required System Impact Study. 10.10. Execution of System Impact Study Agreement. For an Interconnection request to remain a Completed Interconnection Application, the applicant shall execute the System Impact Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated cost of performing the System Impact Study or reviewing the applicant’s System Impact Study. Alternatively, if the applicant request the participating TO to proceed with the System Impact Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the System Impact Study provided that such request is accompanied by payment of the reasonable estimated cost of the System Impact Study, and the parties shall submit the disputed terms for resolution under the ISO’s ADR Procedures. If the applicant elects not to execute a System Impact Study Agreement, and does not request that the Participating TO proceed with the System Impact Study or review thereof, its application shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application.
10.11. System Impact Study Cost Reimbursement and Agreement.
10.11.1. Cost Reimbursement. The System Impact Study Agreement shall clearly specify the charge, based on the Participating TO’s estimate of the cost and time for completion of the System Impact Study. The charge shall not exceed the reasonable actual cost of the study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any modifications to existing planning studies that are reasonably necessary to evaluate the impact on the applicant’s request. The Participating TO must refund any excess study deposit funds to the Eligible Customer, and the Eligible Customer must reimburse the Participating TO for any unpaid study costs in excess of the deposit. 10.11.2. Large Load Interconnection Study Deposit. For Eligible Customer applicants, the Eligible Customer shall remit a study deposit consisting of
(a) $35,000 plus $1,000 per MW for Interconnection less than 80 MW;
(b) $150,000 for Interconnection greater than or equal to 80 MW but less than 200 MW; or (c) $250,000 for Interconnection greater than 200 MW. The Eligible Customer shall remit the study deposit and financial security together with the executed System Impact Study Agreement, or with its request to proceed pursuant to Section 10.10, no later than ten (10) Business Days after the Participating TO tenders the System Impact
PDF page 36
28
Study Agreement. The study deposit shall satisfy the Eligible Customer’s obligation under Section 10.10 to pay the reasonable estimated cost of the System Impact Study. If the Eligible Customer fails to remit the full study deposit and financial security within that period, its Interconnection Application shall cease to be a Completed Interconnection Application and shall be deemed withdrawn.
10.11.3. Multiple Parties. If multiple parties request Interconnection at the same location, the Participating TO may conduct a single System Impact Study. The costs of that study shall be pro-rated among the parties requesting Interconnection.
10.12. System Impact Study Procedures. Upon receipt of an executed System impact Study Agreement or initiation of the ISO ADR Procedures and receipt of payment for estimated study costs and financial security if applicable, the Participating TO shall either (a) complete the required System Impact Study no later than ninety
(90) calendar days after the Completed Application Date or (b) complete its review of an applicant’s System Impact Study within thirty (30) calendar days of its receipt of the completed study. In performing the System Impact Study, the Participating TO shall rely, to the extent reasonably practicable, on existing transmission planning studies. The applicant will not be assessed a charge for such existing studies; however, the applicant will be responsible for the reasonable charges associated with any modifications to existing planning studies that are reasonably necessary to evaluate the impact of the applicant’s request. The System Impact Study will identify whether any Interconnection Facilities, Direct Assignment Facilities, Network Upgrades, or Reliability Upgrades are necessary to deliver a facility’s full output over the ISO Controlled Grid, or any transmission additions or upgrades are necessary to serve a wholesale load or an Eligible Customer. The System Impact Study will also identify any adverse impact on Encumbrances existing as of the applicant’s Completed Application Date. In the event that the Participating TO is unable to complete the required System Impact Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed System Impact Study and related work papers shall be made available to the applicant and the ISO. The Participating TO shall notify the applicant and the ISO immediately upon completion of the System Impact Study. 10.12.1. Large Load System Impact Study Procedures. In addition to Section 10.12, for Large Load, the System Impact Study shall also evaluate the operational characteristics of the Large Load, including its ramp schedule, its performance during system disturbances, and any ability to limit its withdrawals from the ISO Controlled Grid, consistent with Section 25.7.1 of the ISO Tariff. The Participating TO will evaluate impacts to the transmission system using power flow and short circuit analyses, and any other analyses that may be appropriate including
PDF page 37
29
Electromagnetic Transient studies where warranted. The Participating TO will consider alternative transmission technologies in the System Impact Study process. If traditional Network Upgrades are selected instead of alternative transmission technologies, the Participating TO will provide a demonstration of why alternative transmission technologies are not feasible or would not result in lower costs or a faster timeline for accommodating the Large Load Interconnection Application. A
completed System Impact Study for a Large Load Interconnection Application shall include a non-binding good-faith estimate of the cost of Direct Assignment Facilities and Network Upgrades necessary to accommodate the applicant’s request and the time required to construct them, which estimates shall be refined in any Facilities Study. 10.12.2. Applicant Information; Extension of Study Period. The applicant is responsible for the accuracy and completeness of the information in its Completed Interconnection Application and any information provided under this Section. The Participating TO may rely on such information in performing the System Impact Study. If such information is inaccurate or incomplete, the applicant shall bear the reasonable costs of any resulting restudy, including any restudy of later-queued applicants, and any applicable deadlines shall be extended accordingly. The Participating TO may request in writing additional information, data, or models reasonably necessary to perform the System Impact Study, including, for an Eligible Customer, models suitable for Electromagnetic Transient studies where warranted. The applicant shall provide complete responsive information within ten (10) Business Days of the request. The study period in Section 10.12 shall be extended by the number of calendar days from a request until the Participating TO receives complete responsive information. If the applicant does not provide complete responsive information within twenty (20) Business Days of a request, the Participating TO shall notify the applicant in writing, and if the applicant does not cure within five (5) Business Days of that notice, its Interconnection Application shall be deemed withdrawn. The applicant shall reimburse the Participating TO for all costs reasonably incurred, which may include the cost of restudying later-queued applicants, after which any unused study deposit shall be refunded and any financial security released.
10.13. Procedures Upon Completion of System Impact Study. Within fifteen (15) Business Days of completion of the System Impact Study or review and approval of an applicant’s System Impact Study, the Participating TO shall notify the applicant whether the transmission system will be adequate to accommodate all of a request for Interconnection. If no costs are likely to be incurred for any Direct Assignment Facilities, any Reliability Upgrades, or implementing any operating procedures, then within thirty (30) Business Days of receipt of written approval of the applicant’s System Impact Study from the Participating TO and the ISO the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty (30) Business Days of such request. The Participating TO
PDF page 38
30
shall tender to the applicant an Interconnection Agreement as provided in Section 10.17. If costs are likely to be incurred to accommodate a request for Interconnection, the Participating TO shall tender to the applicant a Facilities Study Agreement pursuant to Section 10.8.
10.14. Notice of Need for Facilities Study. If a System Impact Study indicates that additions or upgrades to the ISO Controlled Grid are needed to satisfy an applicant’s request for Interconnection, the Participating TO shall, within fifteen
(15) Business Days of the date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study by the Participating TO, tender to the applicant a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be completed by the Participating TO; the estimated time required to complete the required study; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of performing the required Facilities Study. Alternatively, if the applicant will perform the Facilities Study, the Participating TO shall within fifteen (15) Business Days of the completion date of the System Impact Study or the completion of review and approval of the applicant’s System Impact Study, tender a Facilities Study Agreement that defines the scope, content, assumptions and terms of reference for such study to be reviewed by the Participating TO; the estimated time required to complete the required review; and such other provisions as the parties may reasonably require, and pursuant to which the applicant agrees to reimburse the Participating TO for the reasonable actual costs of reviewing the required Facilities study.
10.15. Execution of Facilities Study Agreement. For an Interconnection request to remain a Completed Interconnection Application, the applicant shall execute the Facilities Study Agreement and return it to the Participating TO within ten (10) Business Days together with payment for the reasonable estimated costs of performing the Facilities Study or reviewing the applicant’s Facilities Study. Alternatively, if the applicant request the Participating TO to proceed with the Facilities Study or review thereof and commits to abide by the terms, conditions, and cost assignments ultimately determined under the ISO ADR Procedures, including any determination by FERC or appeal of a FERC determination in accordance with that process, the Participating TO shall promptly proceed with the Facilities Study provided that such request is accompanied by payment for the reasonable estimated cost of the Facilities Study, and the parties shall submit the disputed terms for resolution under the ISO ADR Procedures. If the applicant elects not to execute a Facilities Study Agreement and does not request that the Participating TO proceed with the Facilities Study or review thereof, its application shall be deemed withdrawn and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by the System Impact Study Agreement, which may include the cost of restudying later-queued applicants, after which any security will be released. 10.16. Facilities Study Procedures. Upon receipt of an executed Facilities Study
PDF page 39
31
Agreement or initiation of the ISO ADR Procedures and receipt of payment for the estimated study costs, the Participating TO will use due diligence to either (a) complete the required Facilities Study within a sixty (60) calendar day period or
(b) complete its review of an applicant’s Facilities Study within thirty (30) calendar days of its receipt of the Completed Study. The Facilities Study shall determine required modifications to the Participating TO’s transmission system, including the estimated cost and scheduled completion date for such modifications that will be required to provide needed services. In the event that the Participating TO is unable to complete the required Facilities Study within such time period, it shall so notify the applicant, in writing, and provide an estimated completion date along with an explanation of the reasons why additional time is required to complete the required studies. A copy of the completed Facilities Study shall be made available to the applicant. 10.16.1. Tender of Interconnection Agreement. Within thirty (30) Business Days of receipt of the completed Facilities Study performed by the Participating TO or receipt of written approval of the applicant’s Facilities Study from the Participating TO, the applicant shall request the Participating TO to tender an Interconnection Agreement within thirty
(30) Business Days of such request. The Participating TO shall tender to the applicant an Interconnection Agreement as provided in Section 10.17. 10.17. Interconnection Agreement. Pursuant to Section 10.7, 10.12.3, or 10.16.1, a party requesting an Interconnection shall request in writing that the Participating TO tender to such party an Interconnection Agreement that will be filed with FERC, or the Local Regulatory Authority, in the case of a Local Publicly Owned Electric Utility. The Interconnection Agreement shall include, without limitation, cost responsibilities, financial security, and payment provisions for any engineering, equipment, construction, ownership, operation and maintenance costs for any Direct Assignment Facilities, Reliability Upgrades, Interconnection Facilities, or Network Upgrades. Large Load Interconnection Agreements shall contain requirements for the Eligible Customer to comply with Section 25.7.1 of the ISO Tariff, including but not limited to the Frequency Ride-Through Requirements, Voltage Ride-Through Requirements, Post-Fault Active Power Recovery Requirements, and Ramp-Rate Limitations. The Large Load Interconnection Agreement shall contain provisions requiring the installation and maintenance of any equipment or facilities necessary for the Participating TO to ensure its ability to disconnect or otherwise isolate the Large Load as required by Section 25.7.1 of the ISO Tariff. The Large Load Interconnection Agreement shall include requirements for the Scheduling Coordinator for each Large Load to provide daily and hourly forecasts, material real-time deviations, outage information, and real-time telemetry consistent with Section 25.7.3 of the ISO Tariff. For an Interconnection request to remain a Completed Interconnection Application, the party requesting the Interconnection shall execute the Interconnection Agreement and return it to the Participating TO within thirty (30) Business Days of receipt.
PDF page 40
32
10.17.1. Filing Unexecuted. Alternatively, if an Eligible Customer requesting the Interconnection requests the Participating TO to file an unexecuted Interconnection Agreement and commits to abide by the terms, conditions, and cost assignments determined to be just and reasonable under the ISO ADR Procedures, including any determination by FERC or on appeal of a FERC determination in accordance with that process, the Participating TO shall promptly file an unexecuted Interconnection Agreement. Provided, however, that if the ISO ADR Procedures concerns whether the requesting entity is an Eligible Customer, the Participating TO shall not be obligated to file an unexecuted interconnection Agreement or commence construction of the Interconnection Facilities or incur other costs under the Interconnection Agreement until a final order determining the just and reasonable rates, terms, and conditions for such Interconnection Agreement has been issued by the applicable court or regulatory authority.
10.17.2. Cost Recovery. The Interconnection Agreement will set forth a payment schedule that enables the Participating TO to recover its costs. For Large Load requesting Interconnection, the Participating TO, Eligible Customer, and ISO at its election shall enter into a Cost Recovery Agreement in the form of Attachment A to this Participating TO Tariff. The Cost Recovery Agreement shall obligate the Eligible Customer for one-hundred (100) percent of the costs incurred to serve the Eligible Customer’s Large Load. The Participating TO may seek an alternative cost recovery structure before FERC by filing a nonconforming Cost Recovery Agreement.
10.17.3. Withdrawn Completed Interconnection Agreement. If the applicant elects not to execute the Interconnection Agreement and does not request the Participating TO to file an unexecuted Interconnection Agreement, its Completed Interconnection Agreement shall be deemed withdrawn, and the applicant shall reimburse to the Participating TO all costs reasonably incurred in processing the application not covered by any System Impact Study Agreement or Facilities Study Agreement, which may include the cost of restudying later-queued applicants. To maintain its queue position, the applicant must timely comply with the Interconnection requirements of Section 25 of the ISO Tariff and Sections 8.1 and 10 of this TO Tariff. If the applicant fails to timely comply with such Interconnection requirements, such applicant shall pay the reasonable costs of revising the System Impact Studies for other applicants that have established a new queue position due to the applicant either withdrawing its Interconnection Application or because its queue position has been modified pursuant to the queuing provisions in Section 25 of the ISO Tariff.
10.18. Large Load Partial Interim Service and FILI Service Requests. If the Eligible Customer has requested Partial Interim Service and/or FILI Service, the
PDF page 41
33
Participating TO shall perform an analysis and report the extent to which each requested interim services can be provided consistent with this TO Tariff and Section 25.7.2 of the ISO Tariff. The maximum amount that may be provided will be based on the anticipated availability of capacity and the information submitted by the Eligible Customer. The Participating TO shall update this analysis annually.
10.18.1. Partial Interim Service. If the Participating TO determines that there will not be adequate transmission capability to satisfy the full amount requested in a Completed Interconnection Application, the Participating TO nonetheless shall be obligated to offer and provide the portion of the requested Interconnection that can be accommodated without any additional Direct Assignments Facilities or Reliability Upgrades. However, the Participating TO shall not be obligated to provide the incremental amount of requested Interconnection that requires such additional facilities or upgrades until such facilities or upgrades have been placed in service.
10.18.2. FILI Service. FILI Service will be available if the Large Load has the ability to reduce the load at a specified Point of Interconnection pursuant to Section 10.18.4, according to the timelines and protocols that will be set forth in an executed and effective FILI Service Agreement attached to the Eligible Customer’s Interconnection Agreement and to be entered into between the Large Load or its authorized agent (which may be the Eligible Customer), the Participating TO, and the ISO. The FILI Service Agreement will specify the Network Upgrades or Interconnection Facilities necessary to conclude FILI Service and provide full Interconnection service. ISO will post the FILI Service Agreement on the ISO Website.
10.18.3. FILI Service Reliability Requirements. The FILI Service Agreement will identify what Large Load Interconnection Facilities must be installed, the necessary protection and control systems and any other equipment necessary to be installed, and operating limitations to allow the Large Load to withdraw energy. FILI Service shall not commence until the Participating TO and Eligible Customer have completed installation and commissioning of all equipment specified under the FILI Service Agreement.
10.18.4. Curtailment of FILI Service. The ISO, Participating TO, and Large Load or its authorized agent (which may be the Eligible Customer), will include in the FILI Service Agreement a description of the circumstances, contingencies, or operating conditions in which the Large Load receiving FILI may be temporarily curtailed and the mechanism used to perform the curtailment. The FILI Service Agreement will further specify the entity responsible for performing the curtailment in each circumstance, contingency, or operating condition; the notification methodology, the
PDF page 42
34
response time(s) required, the duration of curtailment permissible and timeline for restoration, testing and verification requirements, and interim operating limits pending full Interconnection.
10.18.5. Exceedance and Termination of FILI Service. Should the Large Load or Eligible Customer not adhere to the terms of the FILI Service Agreement required by Section 10.18.2, ISO and/or the Participating TO may terminate the FILI Service Agreement and disconnect service to the Large Load in order to preserve reliable operations of the system and maintain Good Utility Practice in carrying out such disconnection and any subsequent reconnection.
10.18.6. Co-Located Large Load. The interconnection processes applicable to a co-located Large Load shall be the same as those that apply to Large Load under this Participating TO Tariff where the co-located Large Load’s Interconnection complies with Section 25.1.1 of the ISO Tariff. For co-located Large Loads that will not inject Energy onto the ISO Controlled Grid in compliance with Section 25.1.1 of the ISO Tariff, the Participating TO will ensure that the co-located Generating Facilities have sufficient control technologies to ensure no material impact on the ISO Controlled Grid, and such requirement will be incorporated into the co-located Large Load’s Interconnection Agreement. The Participating TO shall study all other co-located Large Loads and Generating Facilities together and in accordance with Section 25.7.6 of the ISO Tariff, and shall require specific information regarding the net injection and/or net withdrawal from the combined facility. For any conflict between the ISO Tariff and the Participating TO Tariff pertaining to the interconnection of the Generating Unit, the ISO Tariff will apply. For any conflict between the ISO Tariff and the Participating TO Tariff pertaining to the interconnection of the Large Load, the Participating TO Tariff will apply. 10.19. Expedited Interconnection Procedures. In lieu of the procedures set forth above, the applicant shall have the option to expedite the processing of its Completed Interconnection Application. In order to exercise this option, the applicant shall submit in writing a Request for Expedited Interconnection Procedures to the Participating TO within ten (10) Business Days after receiving a copy of the System Impact Study for the proposed Interconnection. Within ten
(10) Business Days after receiving a Request for Expedited Procedures, the Participating TO shall tender an Expedited Interconnection Agreement that requires the applicant to compensate the Participating TO for all costs reasonably incurred pursuant to the terms of this To Tariff for processing the Completed Interconnection Application and providing the requested Interconnection. While the Participating TO agrees to provide the applicant with its best estimate of the costs of any needed Direct Assignment Facilities and, if applicable, Reliability Upgrades, and such other charges that may be incurred, unless otherwise agreed by the parties, such estimate shall not be binding and the applicant must agree in writing to compensate the Participating TO for all actual Interconnection costs
PDF page 43
35
reasonably incurred pursuant to the provisions of this TO Tariff. The applicant shall execute and return such Expedited Service Agreement within ten (10) Business Days of its receipt or the applicant’s request for Interconnection will cease to be a Completed Interconnection Application and will be deemed terminated and withdrawn. In that event, the applicant shall reimburse the Participating TO for all costs reasonably incurred in processing the application not covered by the terms of the System Impact Study Agreement.
10.20. Transition for Large Loads. Consistent with Section 25.7 of the ISO Tariff, the provisions of this TO Tariff specific to Eligible Customers and Large Loads shall not apply to a Load that is operational or has a Completed Interconnection Application before February 16, 2027, unless and until the Load is modified or increased such that it would be a Large Load, or the Load elects to be treated as a Large Load.
11. Uncontrollable Forces and Indemnification
11.1. Procedures to Follow If Uncontrollable Force Occurs. In the event of the occurrence of an Uncontrollable Force which prevents a Party from performing any of its obligations under this TO Tariff, such Party shall (i) immediately notify the other Parties in writing of the occurrence of such Uncontrollable Force, (ii) not be entitled to suspend performance in any greater or longer duration that is required by the Uncontrollable Force, (iii) use its best efforts to mitigate the effects of such Uncontrollable Force, remedy its inability to perform, and resume full performance hereunder, (iv) keep the other Parties apprised of such efforts on a continual basis and (v) provide written notice of the resumption of performance hereunder. Notwithstanding any of the foregoing, the settlement of any strike, lockout, or labor dispute constituting an Uncontrollable Force shall be within the sole discretion of the Party to this TO Tariff involved in such strike, lockout, or labor dispute, and the requirement that a Party must use its best efforts to remedy the cause of the Uncontrollable Force and mitigate its effects and resume full performance hereunder shall not apply to strikes, lockouts, or labor disputes. No Party will be considered in default as to any obligation under this TO Tariff if prevented from fulfilling the obligation due to the occurrence of an Uncontrollable Force.
11.2. Indemnification. A Market Participant or Eligible Customer shall at all times indemnify, defend, and save the Participating TO harmless from any and all damages, losses, claims, (including claims and actions relating to injury or to death of any person or damage to property), demands, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the Participating TO’s performance of its obligations under this TO Tariff on behalf of a Market Participant or Eligible Customer, except in cases of negligence or intentional wrongdoing by the Participating TO.
PDF page 44
36
12. Regulatory Filings. Nothing contained herein shall be construed as affecting, in any way, the right of any electric utility (as defined by the Federal Power Act) Participating TO furnishing services in accordance with this TO Tariff, or any tariff and rate schedule which results from or incorporates this TO Tariff, unilaterally to make application to FERC as it deems necessary and appropriate to recover its Transmission Revenue Requirements, or for a change in its rates, including changes in rate methodology, or for a change in designation of transmission facilities to be placed under the ISO’s control, in each case under Section 205 of the FPA and pursuant to the FERC’s Rules and Regulations promulgated thereunder. Nothing contained herein shall be construed as affecting in any way the ability of any Eligible Customer receiving services in accordance with this TO Tariff to exercise its rights under the Federal Power Act and pursuant to the FERC’s rules and regulations promulgated thereunder. 12.1. Open Access. For purposes of the Stranded Cost Recovery available under Order Nos. 888 and 888-A, this Tariff, combined with the ISO Tariff and wholesale distribution access tariff, if any, shall be considered an open access tariff under FERC Order Nos. 888 and 888-A.
13. Creditworthiness and Financial Security.
13.1. UDCs, MSSs, and Scheduling Coordinators Using the Participating TO’s Low Voltage Transmission Facilities. For the purpose of determining the ability of a UDC, MSS, and Scheduling Coordinator to meet its obligations related to service using the Participating TO’s Low Voltage Transmission Facilities hereunder where the Participating TO is collecting the Low Voltage Access Charge directly from each UDC, MSS and Scheduling Coordinator, the
Participating TO may require reasonable credit review procedures for the UDC, MSS, or Scheduling Coordinator. This review shall be made in accordance with standard commercial practices. In addition, the Participating TO may require the UDC, MSS, or Scheduling Coordinator to provide and maintain in effect during the term of the service, an unconditional and irrevocable letter of credit as security to meet its responsibilities and obligations under this TO Tariff, or an alternative form of security proposed by the UDC, MSS, or Scheduling Coordinator and acceptable to the Participating TO, and consistent with commercial practices established by the Uniform Commercial Code, that protect the Participating TO against the risk of non-payment.
13.2. End-Users. Creditworthiness rules applicable to End-Users shall be pursuant to the then-current rules of the applicable Local Regulatory Authority, except as provided in Section 13.2.1.
13.2.1. Eligible Customers and Large Load. For the purpose of determining the ability of an Eligible Customer to meet its obligations related to service using the Participating TO’s Transmission Facilities hereunder, the
Participating TO shall require reasonable credit review procedures and financial security for the Eligible Customer. This review shall be made in accordance with standard commercial practices. In addition, the
PDF page 45
37
Participating TO may require the Eligible Customer to provide and
maintain in effect during the term of the service, an unconditional and irrevocable letter of credit as security to meet its responsibilities and obligations under this TO Tariff, or an alternative form of security proposed by the Eligible Customer and acceptable to the Participating TO, and consistent with commercial practices established by the Uniform Commercial Code, that protect the Participating TO against the risk of non-payment. The amount of financial security required will be provided in each applicant’s Cost Recovery Agreement.
14. Disputes. Except as limited below or as otherwise limited by law, the ISO ADR Procedures shall apply to all disputes between parties which arise under this TO Tariff or under or in respect of the proposed terms and conditions of a Facilities Study Agreement, System Impact Study Agreement or Expedited Service Agreement. The ISO ADR Procedures set forth in Section 13 of the ISO Tariff shall not apply to disputes as to whether rates and charges set forth in this TO Tariff (other than charges for studies) are just and reasonable under the FPA.
15. [Reserved]
16. Miscellaneous.
16.1. Notices. Any notice, demand, or request in accordance with this TO Tariff, unless otherwise provided in this TO Tariff, shall be in writing and shall be deemed properly served, given, or made: (i) upon delivery if delivered in person, (ii) five days after deposit in the mail if sent by first class United States mail, postage prepaid, (iii) upon receipt of confirmation by return electronic facsimile if sent by facsimile, or (iv) upon Party at the address set forth in Appendix II. Any Party may at any time, by notice to the other Parties, change the designation or address of the person specified in Appendix II to receive notice on its behalf. Any notice of a routine character in connection with service under this TO Tariff or in connection with operation of facilities shall be given in such a manner as the Parties may determine from time to time, unless otherwise provided in this TO Tariff.
16.2. Waiver. Any waiver at any time by any Party of its rights with respect to any default under this TO Tariff, or with respect to any other matter arising in connection with this TO Tariff, shall not constitute or be deemed a waiver with respect to any subsequent default or other matter arising in connection with this TO Tariff. Any delay short of the statutory period of limitations in asserting or enforcing any right shall not constitute or be deemed a waiver.
16.3. Confidentiality.
16.3.1. Maintaining Confidentiality If Not for Public Disclosure. The Participating TO shall maintain the confidentiality of all of the documents, data, and information provided to it by any other Party that such Party may
PDF page 46
38
designate as confidential, provided, however, that the information will not be held confidential by the receiving Party if (1) the designating Party is required to provide such information for public disclosure pursuant to this TO Tariff or applicable regulatory requirements, or (2) the information becomes available to the public on a non-confidential basis (other than from the receiving Party).
16.3.2. Disclosure of Confidential Information. Notwithstanding anything in this Section 16.3.2 to the contrary, if any Party is required by applicable laws or regulations, or in the course of administrative or judicial proceedings, to disclose information that is otherwise required to be maintained in confidence pursuant to this Section 16.3.2, the Party may disclose such information; provided, however, that as soon as such Party learns of the disclosure requirement and prior to making such disclosure, such Party shall notify the affected Party or Parties of the requirement and the terms thereof. The affected Party or Parties may, at their sole discretion and own costs, direct any challenge to or defense against the disclosure requirement and the disclosing Party shall cooperate with such affected Party or Parties to the maximum extent practicable to minimize the disclosure of the information consistent with applicable law. The disclosing Party shall cooperate with the affected Parties to obtain proprietary or confidential treatment of confidential information by the person to whom such information is disclosed prior to any such disclosure. 16.4. TO Tariff Supersedes Existing Tariffs. This TO Tariff, together with the ISO Tariff and wholesale distribution access tariff, if any, supersedes any pre-existing open access transmission tariff of the Participating TO.
16.5. Titles. The captions and headings in this TO Tariff are inserted solely to facilitate reference and shall have no bearing upon the interpretation of any of the rates, terms, and conditions of this TO Tariff.
16.6. Severability. If any term, covenant, or condition of this TO Tariff or the application or effect of any such term, covenant, or condition is held invalid as to any person, entity, or circumstance, or is determined to be unjust, unreasonable, unlawful, imprudent, or otherwise not in the public interest, by any court or government agency of competent jurisdiction, then such term, covenant, or condition shall remain in force and effect to the maximum extent permitted by law, and all other terms, covenants, and conditions of this TO Tariff and their application shall not be affected thereby but shall remain in force and effect. The Parties shall be relieved of their obligations only to the extent necessary to eliminate such regulatory or other determination, unless a court or governmental agency of competent jurisdiction holds that such provisions are not severable from all other provisions of this TO Tariff.
16.7. Preservation of Obligations. Upon termination of this TO Tariff, all unsatisfied obligations of each Party shall be preserved until satisfied.
PDF page 47
39
16.8. Governing Law. This TO Tariff shall be interpreted, governed by, and construed under the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the State of California. 16.9. Appendices Incorporated. The several appendices (inclusive of any attachments) to this TO Tariff, as may be revised from time to time, are attached to this TO Tariff and are incorporated by reference as if fully set forth herein. 16.10. Conflict With ISO Tariff. If a Market Participant or Eligible Customer identifies a conflict between the TO Tariff and the ISO Tariff, the Participating TO and the Market Participant or Eligible Customer shall make good-faith efforts to resolve the conflict. If the parties are unable to informally resolve that conflict, the Parties may use the ISO ADR Procedures to resolve it as set forth in Section 14 of this Tariff.
16.11. Conflicting Operating Instructions. In the event a Market Participant or Eligible Customer receives conflicting operating instructions from the ISO and one or more Participating TO(s), if human safety would not knowingly be jeopardized nor electric facilities subject to damage while the Market Participant or Eligible Customer seeks to reconcile the conflict with the appropriate ISO and Participating TO employees before acting, the Market Participant or Eligible Customer should attempt a reconciliation. Otherwise, the Market Participant or Eligible Customer shall adhere to ISO Tariff provision 4.2 and follow the ISO’s instructions. In no event shall a Market Participant or Eligible Customer be required to follow operating instructions from the ISO if following those instructions would knowingly jeopardize human safety.
16.12. Reliability Events. After a disturbance or other reliability event involving a Large Load, any associated Eligible Customer, Large Load, Scheduling Coordinator, and Participating TO must comply with any ISO, Regional Entity, or Reliability Coordinator data request related to the event.
PDF page 48
40
APPENDIX I
Transmission Revenue Requirement and TRBAA
1. The Transmission Revenue Requirement shall be $141,661,544 which is composed of a Base Transmission Revenue Requirement of $135,000,000 and a TRBAA of positive $6,661,544
2. The High Voltage Transmission Revenue Requirement shall be $129,741,142 which is composed of a Base Transmission Revenue Requirement for the High Voltage Transmission Facilities of $125,415,000 and a High Voltage TRBAA of positive $4,326,142.
3. The Low Voltage Transmission Revenue Requirement shall be $11,920,403, which is composed of a Base Transmission Revenue Requirement for the Low Voltage Transmission Facilities of $9,585,000 and a Low Voltage TRBAA of positive $2,335,403.
4. The TRBAA will be recalculated annually consistent with the ISO Tariff, approved by the FERC, and provided to the ISO.
PDF page 49
41
APPENDIX II
NOTICES
Designated Representative:
Elizabeth Ramey
Senior Attorney
NextEra Energy, Inc.
801 Pennsylvania Avenue, NW
Suite 220
Washington, DC 20004
Telephone: (202) 909-5696
Elizabeth.Ramey@nexteraenergy.com
<mailto:Elizabeth.Ramey@nexteraenergy.com>
Jaime Hoffmann
President
Trans Bay Cable LLC
700 Universe Blvd.
Juno Beach, FL 33408
Jaime.Hoffmann@nexteraenergy.com
<mailto: Jaime.Hoffmann@nexteraenergy.com>
Trans Bay Cable LLC
700 Universe Boulevard
Juno Beach, Florida 33408
Attention: Business Management MailStop C5B/JBC Email: NEET-Business-Management.SharedMailbox@nexteraenergy.com
With a copy (which shall not constitute notice) to:
NextEra Energy Transmission, LLC
Attn: Legal Department
700 Universe Boulevard
Juno Beach, Florida 33408
Email: NEET-Legal.SharedMailbox@nexteraenergy.com
PDF page 50
ATTACHMENT A
FORM OF COST RECOVERY AGREEMENT
PDF page 51
2
COST RECOVERY AGREEMENT
This Cost Recovery Agreement (“Agreement”) is made and entered into as of __________ (the “Execution Date”) between Trans Bay Cable LLC (“Trans Bay” or “Participating Transmission Owner”) and ________________, a [corporation/limited liability company/other] organized and existing under the laws of the State/Commonwealth of _____________________ (the “Eligible Customer”). The Eligible Customer is requesting Interconnection service to serve a Large Load, as those terms are defined in the Participating Transmission Owner’s tariff. The Participating Transmission Owner and Eligible Customer may be referred to herein individually as a “Party” or collectively as the “Parties.”
RECITALS
WHEREAS, Participating Transmission Owner is a Non-Load-Serving Entity Participating Transmission Owner within the California Independent System Operator, Inc. (“CAISO”) Balancing Authority Area that does not provide retail electric service;
WHEREAS, Participating Transmission Owner owns the [Facility Name], which is under CAISO’s Operational Control and within the CAISO Controlled Grid;
WHEREAS, Participating Transmission Owner’s Transmission Owner Tariff (the “Tariff”) controls the interconnection of load to [Facility Name], subject to compliance with the CAISO tariff;
WHEREAS, Eligible Customer is requesting interconnection to Participating Transmission Owner’s [Facility Name] for the purpose of serving [describe Large Load requesting service, physical location, and MW];
WHEREAS, the Parties have entered into this Agreement to establish the teams and conditions for the Interconnection in order to enable the Eligible Customer to serve the Large Load and for the Participating Transmission Owner to fully recover from the Eligible Customer the costs associated with serving the Large Load.
NOW, THEREFORE, in exchange for good and valuable consideration of the premises and mutual covenants herein, the Parties agree as follows:
ARTICLE 1: DEFINITIONS
1.1
Definitions
Capitalized terms used in this Agreement that are not otherwise defined herein shall have the meaning provided in the Participating Transmission Owner Tariff, as may be amended from time-
PDF page 52
3
to-time. In the event of a difference in a defined term between this Agreement and the definition in Module A of the Tariff, the defined term in this Agreement shall control.
1.2
Annual Required Revenue Commitment
Annual Required Revenue Commitment means the Eligible Customer’s Total Required Revenue Commitment divided by twenty (20) years.
1.3
Cost Recovery Payment
Cost Recovery Payment means the amount the Eligible Customer must pay in addition to the Large Load Annual Received Revenue to meet its Annual Required Revenue Commitment.
1.4
Large Load Annual Received Revenue
Large Load Annual Received Revenue means revenue that is received by the Participating Transmission Owner from CAISO through the Access Charges during a specific calendar year and that is directly attributable to the Eligible Customer’s Large Load.
1.5
Large Load Network Upgrade
Large Load Network Upgrade shall mean any Network Upgrade attributable to an Eligible Customer interconnecting on behalf of a Large Load. Large Load Network Upgrades shall be specified in the Eligible Customer’s applicable Interconnection Agreement.
1.6
Monthly Cost Recovery Payment
Monthly Cost Recovery Payment means the Cost Recovery Payment divided by twelve (12) months.
1.7
Total Required Revenue Commitment
Total Required Revenue Commitment means the incremental revenue requirement for any Large Load Network Upgrade(s) to serve the Eligible Customer’s Large Load, calculated in accordance with Section 3.2.
ARTICLE 2: EFFECTIVE DATE, TERM AND TERMINATION, FILING
2.1
Effective Date
This Agreement shall be effective as of the date specified herein (“Effective Date”), subject to acceptance by FERC. If FERC accepts this Agreement subject to a different effective date,
PDF page 53
4
including in the event the Agreement is filed unexecuted, this Agreement shall become effective on the date accepted by FERC.
2.2
Term and Termination
Unless terminated earlier by mutual consent of the Parties, the term of this Agreement begins on the Effective Date and shall continue for twenty (20) years after the final Large Load Network Upgrade goes in-service or until, as applicable, the Eligible Customer has satisfied its Total Required Revenue Commitment in full pursuant to Article 3 hereof.
2.3
Filing
The Participating Transmission Owner shall file this Agreement with FERC and/or the appropriate Local Regulatory Authority, if applicable. Either Party may request that this Agreement be filed unexecuted at FERC.
ARTICLE 3: ELIGIBLE CUSTOMER PAYMENT OBLIGATIONS
3.1
Performance Obligations
The Eligible Customer shall be responsible for the Total Required Revenue Commitment as stated in Exhibit A to this Agreement. The Eligible Customer shall be responsible for the timely payment of all applicable invoices assessed herein. This Agreement does not relieve Eligible Customer from paying any charges or amounts assessed by the CAISO or any other governmental or regulatory authority to the Eligible Customer.
3.2
Total Required Revenue Commitment
3.2.1 Calculation of Total Required Revenue Commitment
The Total Required Revenue Commitment shall be calculated consistent with FERC cost of service ratemaking principles and set forth in Exhibit A of this Agreement, and as further set forth in Section 3.2.2, and shall incorporate a full return on the capital cost, depreciation, operations and maintenance, and taxes of the Large Load Network Upgrade(s).
3.2.2 Initial and Adjusted Total Required Revenue Commitment
The initial Total Required Revenue Commitment will be based on the estimated costs of the Large Load Network Upgrade(s) and shall be stated in Exhibit A to this Agreement. The Total Required Revenue Commitment shall be subject to adjustment by the Participating Transmission Owner to reflect the actual costs of the Large Load Network Upgrade(s). Adjustments to the Total Required Revenue Commitment to reflect actual costs shall be initially calculated within one (1) year of the in-service date of the Large Load Network Upgrades and each year thereafter, and shall be reflected
PDF page 54
5
in Exhibit A of this Agreement with a true-up adjustment as a credit or charge and including interest. Interest associated with any true-up adjustment will be determined in accordance with 18 C.F.R § 35.19a.
3.3
Required Cost Recovery Payments
Each calendar year following the Large Load Network Upgrade’s in-service date and continuing throughout the term of this Agreement, the Participating Transmission Owner shall:
(a) determine whether the Large Load Annual Received Revenue for that calendar year meets the Annual Required Revenue Commitment; and, if not,
(b) calculate the Cost Recovery Payment, payable by the Eligible Customer, equal to the difference between (i) the Annual Required Revenue Commitment for the applicable calendar year and (ii) the Large Load Annual Received Revenue for that calendar year, plus any applicable interest calculated in accordance with 18 C.F.R § 35.19a.
3.4
Invoice for Monthly Cost Recovery Payments
Within thirty (30) days of the end of each month of any calendar year in which a Cost Recovery Payment is owed, the Participating Transmission Owner shall invoice the Eligible Customer for the Monthly Cost Recovery Payment as determined under Article 8. The Eligible Customer shall timely pay such invoice in accordance with Article 8.
3.5
Treatment of Cost Recovery Payments
For each calendar year during the Term of this Agreement, the Participating Transmission Owner shall treat any Cost Recovery Payments required to be paid by the Eligible Customer as a credit in the next calculation of the Participating Transmission Owner’s Transmission Revenue Requirement in Appendix I of its Tariff by deducting the Cost Recovery Payments from the Transmission Revenue Requirement, and shall include a workpaper detailing such crediting and rate treatment in the filing at FERC implementing such calculation.
3.6
Payment in Event of Termination, Cancellation, or Withdrawal
Upon termination, disconnection, suspension, or abandonment of the Large Load project, or should the Eligible Customer terminate, cancel, or otherwise withdraw or terminate this Agreement, the Interconnection Agreement, or its Interconnection service for any reason, the Eligible Customer shall remain obligated to pay to the Participating Transmission Owner all costs incurred or committed by the Participating Transmission Owner associated with serving the Large Load, including Network Upgrades, prior to the effective date of any such termination or change. In the event the Eligible Customer fails to make such payment, this Agreement shall not be Terminated until such payment is made and payments shall continue to be due under Article 3. The Participating Transmission Owner may draw upon the Required Security to satisfy the Eligible
PDF page 55
6
Customer’s obligations under this Agreement. This Section 3.6 is without prejudice to any other remedy available to the Participating Transmission Owner.
ARTICLE 4: Security Requirements
4.1
Required Security
The Eligible Customer shall provide and maintain financial security in accordance with this Article 4 (the “Required Security”). The Required Security shall be in an amount equal to the Total Required Revenue Commitment and shall take one of the following forms as reasonably acceptable to the Participating Transmission Owner:
(a) cash;
(b) an irrevocable letter of credit issued by a commercial bank that has (i) an office, branch, or place of business in the United States where claims can be presented, (ii) assets of at least $10 billion, and (iii) a Credit Rating of either “A3” or higher by Moody’s, or (b) “A-” or higher by Standard & Poor’s (“S&P”). If a commercial bank is rated by each of Moody’s and S&P, the lower rating will be the applicable standard;
(c) an irrevocable guaranty, provided that the guarantor maintain a senior unsecured credit rating of BBB- equivalent by Moody’s, S&P, or Fitch. If the guarantor is rated by one or more rating agencies, the lowest rating will be the applicable standard; or
(d) such other form of security as the Eligible Customer may propose and the Participating Transmission Owner, in its sole discretion, determines to be acceptable.
When the amount of Total Required Revenue Commitment is adjusted per Section 3.2.2, the amount of Required Security shall be adjusted accordingly. The amount of Required Security may be further adjusted in accordance with Sections 4.3 and 4.4.
4.2
Timing to Provide Required Security
The Eligible Customer shall provide the Required Security within thirty (30) Calendar Days of the later of (i) the execution of this Agreement by all parties or (ii) acceptance of this Agreement by FERC. Failure to provide the Required Security within such timeframe will result in the Large Load Interconnection Application being deemed withdrawn.
4.3
Annual Reduction of Required Security
The Required Security shall remain with the Participating Transmission Owner for the Term of this Agreement. The Participating Transmission Owner will reduce the Required Security following each Annual Update during the Term of this Agreement to reflect the completed payments made by the Eligible Customer pursuant to Article 3 of this Agreement. Any such reduced Required Security must be provided in a revised form of irrevocable security otherwise meeting the requirements of Section 4.1.
PDF page 56
7
4.4
Use of Required Security by Participating Transmission Owner
In the event Eligible Customer fails to timely pay any invoice or any other payment due under this Agreement, the Participating Transmission Owner shall notify the Eligible Customer in accordance with Section 13.4. If the Eligible Customer fails to timely cure and provide such payment within five (5) Business Days of receiving such notice, the Participating Transmission Owner shall be entitled to draw on the Required Security in the amount of the missed payment, as well as any accrued interest charges based on FERC’s regulations at 18 C.F.R § 35.19a. Within twenty (20) Business Days of such draw on the Required Security occurring, the Eligible Customer shall be required to provide the Participating Transmission Owner with sufficient irrevocable security to maintain sufficient Required Security to meet the obligation under Section 4.1 of this Agreement.
4.5
Term of Required Security
Required Security shall remain in place until the termination of this Agreement. Any Required Security provided by Eligible Customer must be kept active, must continue to meet this Article 4’s requirements, and must be available to the Participating Transmission Owner in the event that Eligible Customer fails to make any payment required under this Agreement. Any fees or costs associated with the provision of the Required Security under this Agreement are the sole responsibility of the Eligible Customer.
ARTICLE 5: [RESERVED]
ARTICLE 6: [RESERVED]
ARTICLE 7: CONFIDENTIALITY
7.1
Confidentiality
During the term of this Agreement and for a period of five (5) years after any termination or expiration of this Agreement, each Party shall hold in confidence and not disclose to any person any Confidential Information received by a Party (“Receiving Party”) from the other party (“Disclosing Party”), and except as Disclosing Party may authorize in writing, a Receiving Party who received Confidential Information shall and shall cause its Representatives to: treat and cause to be treated as confidential all Confidential Information; not disclose any Confidential Information to any third party (other than its Representatives) or make available any reports, recommendations, extracts, summaries, analysis, or conclusions based on the Confidential Information; use or grant access to Confidential Information only in connection with the performance of the respective obligations as provided under this Agreement; or make copies of any tangible embodiment of Confidential Information only as necessary for the performance of respective obligations as provided under this Agreement.
PDF page 57
8
7.2
Scope
Confidential Information shall include, without limitation, all information relating to a Party’s technology, research and development, business affairs, and pricing, and any information supplied by a Party to another Party prior to the execution of this Agreement. Information is Confidential Information only if it is clearly designated or marked in writing as confidential on the face of the document, or, if the information is conveyed orally or by inspection, if the Party providing the information orally informs the Party receiving the information that the information is confidential. The Parties shall maintain as confidential any information that is provided and identified by a Party as Critical Energy/Electric Infrastructure Information (“CEII”), as that term is defined in 18 C.F.R. § 388.113(c). Such confidentiality will be maintained in accordance with this Article 7. If requested by the receiving Party, the disclosing Party shall provide in writing, the basis for asserting that the information referred to in this Article warrants confidential treatment, and the requesting Party may disclose such writing to the appropriate Governmental Authority. Each Party shall be responsible for the costs associated with affording confidential treatment to its information. Confidential Information shall not include information that the receiving Party can demonstrate:
(a) is generally available to the public other than that which is a result of a disclosure by the Receiving Party;
(b) was in the lawful possession of the Receiving Party on a non-confidential basis before receiving it from the Disclosing Party;
(c) was supplied to the Receiving Party without restriction by a third party, who, to the knowledge of the Receiving Party, after due inquiry, was under no obligation to the Disclosing Party to keep such information confidential;
(d) was independently developed by the Receiving Party without reference to Confidential Information of the Disclosing Party;
(e) is, or becomes, publicly known, through no wrongful act or omission of the Receiving Party or breach of this Agreement; or
(f) is required to be disclosed by any Governmental Authority or is otherwise required to be disclosed by law or subpoena or is necessary in any legal proceeding establishing rights and obligations under this Agreement.
Information designated as Confidential Information shall no longer be deemed confidential if the Party that designated the information as confidential notifies the other Party that it no longer is confidential.
PDF page 58
9
7.4
Release of Confidential Information
No Party shall disclose Confidential Information to any other person, except to its Representatives (limited by FERC’s Standards of Conduct requirements) without the prior written consent of the disclosing Party. A receiving Party may disclose Confidential Information to its Representatives provided that such Representatives have first been advised of the confidentiality provisions of this Article 7. Notwithstanding the foregoing, a Party providing Confidential Information to a Representative shall remain primarily responsible for any release of Confidential Information by such Representative in contravention of this Article 7.
7.5
Rights
Each Party retains all rights, title, and interest in the Confidential Information that it discloses to the other Party. A Party’s disclosure to the other Party of Confidential Information shall not be deemed a waiver by such Party or any other person or entity of the right to protect the Confidential Information from public disclosure.
7.6
No Warranties
By providing Confidential Information, neither Party makes any warranties or representations as to its accuracy or completeness.
7.7
Standard of Care
Each Party shall use at least the same standard of care to protect Confidential Information it receives as such Party uses to protect its own Confidential Information from unauthorized disclosure, publication or dissemination. Confidential Information may be used solely to fulfill a Party’s obligations to the other Party under this Agreement or to comply with Applicable Laws, Regulations, and Standards.
7.8
Order of Disclosure
If a Governmental Authority with the right, power, and apparent authority to do so requests or requires a Party, by subpoena, oral deposition, interrogatories, requests for production of documents, administrative order, or otherwise, to disclose Confidential Information, that Party shall provide the Party that provided the Confidential Information with prompt notice of such request(s) or requirement(s) so that the providing Party may seek an appropriate protective order or waive compliance with the terms of this Agreement. Notwithstanding the absence of a protective order or agreement, or waiver, the Party that is subjected to the request or order may disclose such Confidential Information which, in the opinion of its counsel, the Party is legally compelled to disclose. Each Party shall use reasonable efforts to obtain reliable assurance that confidential treatment will be accorded to any Confidential Information so furnished.
PDF page 59
10
7.9
Return or Destruction of Confidential Information
Each Party shall, within ten (10) Business Days of receipt of a written request from the other Party, use reasonable efforts to destroy, erase, or delete (with such destruction, erasure and deletion certified in writing to the requesting Party) or to return to the requesting Party, without retaining copies thereof, any and all written or electronic Confidential Information received from the requesting Party, provided that (i) the non-requesting Party shall not be required to purge any historical backup media, and (ii) if the non-requesting Party elects to delete, destroy or erase all such Confidential Information, it shall certify such deletion, destruction, or erasure to the requesting Party in writing.
7.10
Remedies
Monetary damages would be inadequate to compensate a Party for the other Party’s Breach of its obligations under this Article 7; therefore, a Party shall be entitled to injunctive or other equitable relief, without bond or proof of damages, if the other Party Breaches or threatens to Breach its obligations under this Article 7, and the Party that Breaches or threatens to Breach its obligations under this Article 7 shall not plead in defense that there would be an adequate remedy at law. Injunctive relief shall not be deemed to be an exclusive remedy for the Breach of this Article 7 and shall be in addition to all other remedies available at law or in equity. The covenants contained herein are necessary for the protection of legitimate business interests and are reasonable in scope.
7.11
Disclosure to Federal or State Commissions or their Staff
Notwithstanding anything in this Article 7 to the contrary, and pursuant to 18 C.F.R. § 1b.20, if FERC or its staff, during the course of an investigation or otherwise, requests information from a Party that is otherwise required to be maintained in confidence pursuant to this Agreement, such Party shall provide the requested information to FERC or its staff, within the time provided for in the request for information. In providing the information to FERC or its staff, the Party must, consistent with 18 C.F.R. § 388.112, request that the information be treated as confidential and non-public by FERC and its staff and that the information be withheld from public disclosure. To the extent permitted by law, each Party shall notify the other Party prior to the release of the other Party’s Confidential Information to FERC or its staff. A Party shall promptly notify the other Party when it is notified by FERC or its staff that a request to release the other Party’s Confidential Information has been received by FERC, at which time either of the Parties may respond before such information would be made public, pursuant to 18 C.F.R. § 388.112.
7.12
General Disclosure
Notwithstanding any other provisions of this Article 7, a Party may disclose the Confidential Information provided by the other Party to the extent disclosure is: (i) reasonably deemed by the disclosing Party to be required in connection with a dispute between the Parties, or the defense of litigation or dispute; (ii) otherwise permitted by written consent of the Party that provided such
PDF page 60
11
Confidential Information; (iii) necessary to fulfill its obligations to an RTO or ISO or to a regional or national reliability organization; or (iv) is required to be disclosed pursuant to any Governmental Authority or is otherwise required to be disclosed by law or subpoena. Prior to any disclosures of another Party’s Confidential Information under this Section 7.12, the Disclosing Party shall promptly notify the other Party in writing and shall assert confidentiality and cooperate with the other Party in seeking to protect the Confidential Information from public disclosure by confidentiality agreement, protective order, or other reasonable measures.
7.13
Audit Rights
Subject to the requirements of confidentiality under Article 7 of this Agreement, (1) the accounts and records related to the adjustment provided for in Section 3.2.2 shall be subject to audit for a period of twenty-four (24) months following the date the adjustment; and (2) the accounts and records related to the determination of whether the Eligible Customer satisfied its Annual Required Revenue Commitment shall be subject to audit for a period of twelve (12) months following each year’s determination in accordance with this Article 7. Eligible Customer at its expense shall have the right, during normal business hours, and upon prior reasonable notice to the other Parties, to audit such accounts and records. Any audit authorized by this Article 7 shall be performed at the offices where such accounts and records are maintained and shall be limited to those portions of such accounts and records that relate to obligations under this Agreement.
ARTICLE 8: INVOICING AND PAYMENT; TAXES
8.1
Purpose of Invoicing
Any invoice that is issued pursuant to this Agreement shall be for the purposes set forth in this Agreement.
8.2
Timeliness of Payment
Unless otherwise agreed upon, any invoices issued pursuant to this Agreement shall be rendered within thirty (30) Calendar Days of the end of the calendar month in which expenses were incurred and shall be due and payable, unless otherwise agreed upon, within thirty (30) Calendar Days of receipt of such invoice. Payment shall be made by electronic transfer or such other means as shall cause such payment to be available for the use of the payee. Interest on unpaid amounts shall be determined based on FERC’s regulations at 18 C.F.R § 35.19a.
8.3
Disputed Invoices
In the event that a Party disputes an invoice, the disputing Party shall pay the invoice in full in accordance with Section 8.2 of this Agreement, subject to the refund of any amounts found to have been incorrectly invoiced plus interest on such amount from the date of payment to the date of the refund at the rate stated in Section 8.2. In the event of a billing dispute, the disputing Party shall
PDF page 61
12
provide written notice of the dispute to the billing Party as set out in Section 13.4. In response to the notice, the billing Party will promptly provide all documentation that is reasonably required in support of its bill and confer with the disputing Party. If these good faith efforts fail to resolve the issue, the matter may, by mutual agreement of the Parties, be settled through the dispute resolution process described in Article 10.
8.4
Invoice Adjustments
Other than as required by law, regulatory action or metering test adjustments, invoice adjustments shall be made within six (6) months of the rendition of the initial invoice.
8.5
Tax Reimbursement
If, as part of any compensation to be paid under this Agreement, any transaction tax, including, but not limited to sales, excise, or similar taxes (other than taxes based on or measured by net income) is levied and/or assessed against either Party by any taxing authority on the power and/or energy manufactured, generated, produced, converted, sold, purchased, transmitted, interchanged, exchanged, exported or imported by the supplying Party to the other Party, then such supplying Party shall be fully compensated by the other Party for such direct taxes.
ARTICLE 9: INDEMNITY
To the extent permitted by law, each Party (the “Indemnifying Party”) shall indemnify, save harmless, and defend the other Party from and against any losses, liabilities, costs, expenses, suits, actions, claims, and all other obligations arising out of injuries or death to persons or damage to property (each a “Loss” and each suffered by or asserted by a third party) arising out of, in connection with, or resulting from the Indemnifying Party’s (or its Contractor’s) performance or non-performance of its obligations under this Agreement; provided, however, that a Party’s obligation to indemnify the other Party shall not apply to any Losses arising from the other Party’s negligence or intentional misconduct. Promptly after receipt by a Party entitled to indemnity (“Indemnified Party”) of any claim or notice of the commencement of any action, administrative or legal proceeding, or investigation as to which the indemnity provided for in this Article 9 may apply, the Indemnified Party shall notify the Indemnifying Party of such fact. Any failure of or delay in such notification shall not affect an Indemnifying Party’s indemnification obligation unless such failure or delay is materially prejudicial to the Indemnifying Party.
The Indemnifying Party shall, at the Indemnified Party’s option and at the Indemnifying Party’s expense, defend the Indemnified Party against any and all suits, actions, or claims arising out of, connected with, or resulting from the performance or non-performance by the Indemnifying Party or any of its Contractors of its obligations under this Agreement. The Indemnifying Party shall not settle or make a plea with respect to any suit, action or claim without the Indemnified Party’s prior written consent.
PDF page 62
13
A Party’s obligations to another Party under this Article 9 shall not be limited in any way by any provision of any workers’ compensation, disability benefits, payroll, or other employee benefits laws; provided, however, that nothing herein shall limit or restrict any defense a Party may be entitled to assert with respect to a Loss, including a defense based on the status of such Party as a statutory employer. EACH PARTY HEREBY SPECIFICALLY AND EXPRESSLY WAIVES
ANY AND ALL DEFENSES IT MAY HAVE TO AN INDEMNIFICATION OBLIGATION TO
THE OTHER PARTY PURSUANT TO THIS AGREEMENT BASED ON ANY IMMUNITY TO
WHICH SUCH PARTY MAY BE ENTITLED UNDER ANY WORKERS’ COMPENSATION,
DISABILITY BENEFITS, PAYROLL, OR EMPLOYEE BENEFITS LAWS.
For the purposes of this Article 9 only, the term “Party” shall include the Party’s Affiliates and the directors, officers, employees, and agents of the Party and its Affiliates.
ARTICLE 10: DISPUTES
10.1
Dispute Resolution
The Parties shall attempt, in good faith, to resolve or cure any dispute, controversy or claim (a “Dispute”) before initiating any formal legal action at law or in equity to resolve the same. If either Party believes that a Dispute has arisen, such Party shall give written notice thereof to the other Party, which notice shall describe in reasonable detail the basis and specifics of the claimed Dispute (the “Dispute Notice”). Within five (5) Business Days after delivery of the Dispute Notice, each Party shall appoint a senior level executive. Each designated executive shall meet (in person or via telephone) to discuss and attempt to resolve or cure such Dispute.
Each senior level executive shall negotiate for a reasonable period of time to settle the Dispute after the Dispute Notice is referred to them; provided that such reasonable period shall not, unless otherwise agreed by the Parties in writing, exceed twenty (20) Business Days from the time of receipt of the Dispute Notice by the senior level executive of each Party, or longer period of time if agreed to by the Parties. Notwithstanding anything to the contrary herein, in no event will the executive officer to whom the matter is referred be a person who is an attorney without the express written permission of the chief legal counsel of the other Party.
If the Dispute has not been resolved pursuant to this Section 10.1 within thirty (30) Business Days from the time of receipt of the Dispute Notice by the applicable individual, either Party may proceed to take any and all actions available to it under this Agreement to resolve such dispute and to obtain any remedies available under this Agreement.
10.2
Not Usable as Evidence
Nothing said or disclosed, nor any document produced, in the course of any negotiations, conferences and discussion in connection with efforts to settle a Dispute that is not otherwise independently discoverable shall be offered or received as evidence or used for impeachment or
PDF page 63
14
for any other purposes in any suit, but shall be considered to have been disclosed for settlement purposes.
ARTICLE 11: BREACH AND DEFAULT
11.1
General
A Party shall be considered in default of this Agreement (“Default”) if it fails to cure a Breach in accordance with the terms of this Section 11.1. A breach (“Breach”) shall mean the failure of a Party to perform or observe any material term or condition of this Agreement; provided that no Breach shall exist where such failure to discharge an obligation (other than the payment of money) is the result of Force Majeure as defined in this Agreement or the result of an act or omission by the other Party. Upon a Breach, the non-breaching Party shall give written notice of such Breach to the breaching Party. The breaching Party shall have thirty (30) Calendar Days from receipt of the Breach notice within which to cure such Breach; provided however, if such Breach is not capable of cure within thirty (30) Calendar Days, the breaching Party shall commence such cure within thirty (30) Calendar Days after notice and continuously and diligently complete such cure within ninety (90) Calendar Days from receipt of the Breach notice; and, if cured within such time, the Breach specified in such notice shall cease to exist.
11.2
Consequence of Default
In the event of Default, Eligible Customer shall promptly pay any remaining Total Required Revenue Commitment owed under this Agreement. In the event that Eligible Customer does not promptly such amount, the Participating Transmission Owner may draw on the Required Security. This payment or draw on the Required Security does not limit any and all rights and remedies available to the non-defaulting Parties allowed by law with respect to such default or collecting all amounts owed under this Agreement. The Defaulting Party shall indemnify non-Defaulting Parties for reasonable costs, attorney fees and/or expenses incurred with respect to a default or collecting all amounts owed, including, as applicable, any tax gross-up obligations under this Agreement.
ARTICLE 12: GOVERNMENTAL AUTHORITIES; AMENDMENT
12.1
Governmental Authorities
This Agreement is made subject to the jurisdiction of FERC and any Local Regulatory Authority having jurisdiction over the rates, terms and conditions, or services provided under this Agreement. Nothing in this Agreement shall limit the rights of the Parties or of FERC under sections 205 and 206 of the Federal Power Act and FERC’s rules and regulations thereunder.
PDF page 64
15
12.2
Amendments to the Agreement
This Agreement may only be modified in a writing signed by the Parties. In the event that the Parties agree to amend this Agreement, the Parties shall, if required by Applicable Laws, Regulations, and Standards, file any such amendment or modification with FERC.
ARTICLE 13: GENERAL
13.1
Force Majeure
No Party shall be in Breach in respect to any obligation hereunder because of Force Majeure. if any Party’s performance under this Agreement is hindered by an event of Force Majeure, it shall make all reasonable efforts to perform its obligations under this Agreement. An event of Force Majeure means any act of God, labor disturbance, act of the public enemy, war, act of terrorism, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, order, regulation or restriction imposed by governmental military or lawfully established civilian authorities, or any other cause beyond a Party’s control. Force Majeure does not include an act of negligence or intentional wrongdoing by the Party claiming Force Majeure or economic hardship or economic conditions rendering a Party’s performance of this Agreement unprofitable or uneconomic. Any Party’s obligation to make payments or maintain the Required Security at all times shall not be suspended by Force Majeure. A Party unable to fulfill any other obligation by reason of Force Majeure shall provide prompt written notice of such Force Majeure event to the other Party and such notice shall include an estimate of the expected duration of such event. The failure of a Party to perform its obligations under this Agreement as a result of Force Majeure shall only be excused for the duration of the Force Majeure and while such Party exercises diligence to remove such disability. As soon as the non-performing Party is able to resume performance of its obligations, such Party shall resume performance and give prompt notice thereof to the other Party.
13.2
Waivers
No failure or delay on the part of either Party in exercising any of its rights under this Agreement, no partial exercise by either Party of any of its rights under this Agreement, and no course of dealing between the Parties shall constitute a waiver of the rights of either Party under this Agreement. Any waiver shall be effective only by a written instrument signed by the Party granting such waiver, and such shall not operate as a waiver of, or continuing waiver with respect to, any subsequent failure to comply therewith.
13.3
Liability
To the fullest extent permitted by law and notwithstanding any provision of this Agreement, in no event shall a Party, its Affiliates, or any of their respective owners, officers, directors, employees, agents, successors or assigns be liable to the other Party, its Affiliates or any of their respective owners, officers, directors, employees, agents, successors or assigns, whether in contract, warranty,
PDF page 65
16
tort, negligence, strict liability, or otherwise, for any special, indirect, incidental, exemplary, consequential (including, without limitation, attorneys’ fees, litigation costs, replacement power costs, lost profits or revenues, loss of good will or lost business opportunities), or punitive damages related to or resulting from performance or nonperformance of this Agreement or any activity associated with or arising out of this Agreement.
13.4
Written Notices
Any notice or other communication required or permitted by this Agreement may be given by personal delivery, by e-mail (with confirmation of receipt), by any courier service which guarantees overnight, receipted delivery, or by U.S. certified or registered mail, return receipt requested, addressed to the Party entitled thereto, at the following addresses. The below listed titles and addresses for a Party may be changed by written notice to all the other Parties. Such change shall not necessitate a filing under Section 205 of the Federal Power Act. Any such notice or communication will be deemed to have been given as of the date received.
If to Trans Bay
Cable LLC:
Trans Bay Cable LLC
700 Universe Boulevard
Juno Beach, Florida 33408
NEET-Business-Management.SharedMailbox@nexteraenergy.com
With a copy (which shall not constitute notice) to:
Trans Bay Cable LLC
Attn: Legal Department
700 Universe Boulevard
Juno Beach, Florida 33408
NEET-Legal.SharedMailbox@nexteraenergy.com
If to [Eligible
Customer]:
[Eligible Customer to insert]
13.5
Governing Law
The validity and meaning of this Agreement shall be governed by and construed in accordance with federal law where applicable and, when not in conflict with or preempted by federal law, the applicable law of the State of California, without application of its conflicts of law provisions.
13.6
Counterparts
This Agreement may be executed in one or more counterparts, each of which shall be deemed an original.
PDF page 66
17
13.7
Entire Agreement; Superseding Effect
This Agreement, including all exhibits, schedules, appendices and other attachments hereto, sets forth the entire understanding and agreement of the Parties as to the subject matter of this Agreement, cost recovery by the Participating Transmission Owner of all costs of Large Load Network Upgrades under the applicable Interconnection Agreement, and supersedes all prior written and oral understandings, offers, agreements, commitments, representations, writings, discussions, or other communications of every kind between the Parties, pertaining to the subject matter hereof.
ARTICLE 14: ASSIGNMENT
14.1
Assignment
This Agreement shall inure to the benefit of and be binding upon the successors and assigns of the Parties. This Agreement shall not be assigned by any Party without the written consent of the other Party, which consent shall not be unreasonably withheld, conditioned, or delayed; provided that the assignee is at least as creditworthy as the assigning Party and the assignee of Eligible Customer shall provide Participating Transmission Owner with valid Security as contemplated herein. No purported assignment of this Agreement shall release or discharge any Party from current or future obligations hereunder unless all such obligations are assumed by the successor or assignee of that Party in writing and in conformity with this provision.
ARTICLE 15: SURVIVAL
15.1
Survival
The termination of this Agreement shall not discharge either Party from any obligation it owes to the other Party under this Agreement by reason of any transaction, loss, cost, damage, expense, or liability that shall occur (or the circumstances, events or basis of which shall occur or arise) prior to such termination, including but not limited to any accrued payment obligations, final cost reconciliation, ownership of the Network Upgrades or Interconnection Facilities, or provisions that expressly or by their nature survive the termination or expiration of this Agreement. It is the intent of the Parties hereby that any such obligation owed (whether the same shall be known or unknown at the termination of this Agreement) shall survive the termination of this Agreement, and that either Party may enforce its rights against the other Party with respect to such obligations in an action at law or in equity to the fullest extent permitted by law.
This Agreement shall continue in effect after termination to the extent necessary: (i) for final billings and payments; (ii) to permit the determination and enforcement of liability and indemnification obligations arising from acts or events that occurred while this Agreement was in effect; and (iii) to permit each Party to have access to the real property, including but not limited
PDF page 67
18
to leased property and easements of the other Party to disconnect, remove or salvage its own facilities and equipment.
[The remainder of this page is intentionally left blank. The next
page of this document is the signature page.]
PDF page 68
19
IN WITNESS WHEREOF, the Parties have caused their authorized representatives to execute this agreement as of the date first above written.
TRANS BAY CABLE LLC
By:
Name:
Title:
[ELIGIBLE CUSTOMER]
By:
Name:
Title:
[ENTITY NAME]
By:
Name:
Title:
PDF page 69
20
EXHIBIT A
Initial Total and Annual Required Revenue Commitment
Estimated costs of the Large Load Network Upgrade(s) stated in the Interconnection Agreement: $
.
Initial Total Required Revenue Commitment: $
.
Initial Annual Required Revenue Commitment: $
.