ER27-559-000 · 2026-11-18 · Southwest Power Pool, Inc.

Enhance Transmission Service for HILLs and Non-Transmission Facilities

PDF page 1

November 18, 2026

The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C.  20426

Re:
Southwest Power Pool, Inc., Docket No. ER27-____-000
Submission of Tariff Revisions to Enhance Transmission Service
Provisions for High Impact Large Loads and Clarify Interconnection
and Market Registration Requirements for Non-Transmission Facilities in Response to Show Cause Order; Related to Docket No. EL26-68-000

Dear Secretary Reese:

Pursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Section 35.13 of the Federal Energy Regulatory Commission’s (“Commission”) Regulations, 18 C.F.R. § 35.13, Southwest Power Pool, Inc. ("SPP"), as authorized by its independent Board of Directors, submits revisions to its Open Access Transmission Tariff (“Tariff”)1 in response to the Commission’s June 18, 2026, order instituting a proceeding under FPA Section 206 in Docket No. EL26-68-000 (“Show Cause Order”).2 The proposed revisions fall into two related sets. The first set (the “HILL Transmission Service Revisions”): (1) requires SPP to evaluate alternative transmission technologies when studying transmission service for High Impact Large Loads (“HILLs”);3 (2) memorializes the ongoing operational requirements applicable

1 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume No. 1.  References in this filing to "Tariff" refer to the version of SPP’s Tariff currently in effect. "Proposed Tariff" refers to a version reflecting the revisions proposed in this filing. All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff.
2 Sw. Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (“Show Cause Order”).
3 Tariff, Part I, Section 1, Definition of High Impact Large Load (“A new commercial or industrial load, or increase in commercial or industrial load, at a single site connected through one or more shared Points of Interconnection (POIs) or delivery points, where such load is either (1) 10 MW or more if connected to the Transmission System at a voltage level less than or equal to 69 kV; or (2) 50 MW or more if connected to the Transmission System at a voltage level greater than 69 kV. An Electric Storage Resource is not considered a HILL. A load may be categorized as a HILL after the initial effective date of Attachment BA of the Tariff.  High Impact Large Loads must register as such in accordance with Attachment AE of the Tariff and follow the processes specified in Attachment BA of the Tariff.”).

PDF page 2

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 2

to HILLs in the pro forma transmission service agreements; and (3) provides transparency regarding the Network Upgrades, and associated costs, needed to serve HILLs. The second set (the “Non-Transmission Facility Revisions”): (1) defines a new term, “Non-Transmission Facility,” that replaces the undefined “non-jurisdictional” terminology; (2) clarifies the interconnection study requirements for generation interconnecting to Non-Transmission Facilities, including Behind-The-Meter Generation and on-site co-located generation; and (3) clarifies which party is responsible for market registration when a Resource fails or refuses to register in the Integrated Marketplace. Together, the HILL Transmission Service Revisions and the Non-Transmission Facility Revisions are referred to as the “Large Load Revisions.” Because both sets address how large loads, and the generation that serves them, connect to and use the Transmission System, SPP submits them in a single filing so the Commission can evaluate them together. As directed by the Show Cause Order, SPP states explicitly that this proposal is submitted under FPA Section 205, and SPP explains below which of the Commission’s Show Cause Order directives this filing addresses, how it resolves them, and, in Sections IV and V, how the proposal avoids disrupting existing commercial arrangements and why the requested effective date is reasonable.4

SPP respectfully requests that the Commission issue an order finding the proposed revisions just and reasonable and not unduly discriminatory or preferential, accepting them effective February 16, 2027, and finding that they resolve the concerns identified in Directive (1)(a), the transparency component of Directive (1)(b), and the clarity, interconnection, and market participation components of Directive (1)(c) of the Show Cause Order.

I. SUMMARY OF FILING
In the Show Cause Order, the Commission commended SPP’s “bold and
proactive steps” to integrate large loads.5 The Commission recognized that SPP’s HILL process already provides an enhanced study framework for Eligible Customers taking transmission service on behalf of large loads.6 Given those enhancements, the Commission stated that it expects SPP will be able to demonstrate that it has resolved several of the concerns the Commission has identified regarding a lack of clarity and consistency in other regions’ tariffs.7 The Commission nonetheless found that the HILL process lacks two components: (1) provisions requiring the evaluation of alternative transmission technologies; and (2) pro forma service agreement provisions

4 Show Cause Order at P 32.
5 Id. at P 2.
6 Id.; see also id. at P 43.
7 Id.

PDF page 3

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 3

memorializing ongoing operational requirements.8 The Commission also preliminarily found that the Tariff does not require centralized, accessible data on the Network Upgrades and associated costs needed to serve large loads,9 and that the Tariff lacks sufficient clarity and consistency regarding the rates, terms, and conditions of service that apply to interconnection customers serving co-located load, including how those customers may use SPP’s generator interconnection processes, the scope of SPP’s study of co-location arrangements, and the responsibilities of the entities involved.10 The Large Load Revisions close each of these gaps, as summarized below:

Show Cause
Order directive
Commission’s concern
Tariff revision
HILL Transmission Service Revisions (RR808)
Directive (1)(a),
first component (PP
44–45)
Evaluation of alternative
transmission technologies
in all instances, without a
customer request, and a
clear demonstration in the
study report if traditional
Network Upgrades are
selected
New provisions in Attachment
BA, Section 2.1.3.4 requiring
every HILL Delivery Point
Study (“HDPS”) to evaluate
grid-enhancing technologies
(“GETs”) and requiring the
HDPS report to explain the
results of that evaluation
Directive (1)(a),
second component
(P 46)
Pro forma transmission
service agreement
provisions memorializing
ongoing HILL operational
requirements
New Section 6.0 of the
Attachment A Firm Point-to-
Point Service Agreement and
new Section 3.0 of the
Attachment F Network
Integration Transmission
Service (“NITS”) Agreement,
which bind the Transmission
Customer or Network Customer
to Attachment BA, Section 2.2.
Both agreements also gain
fields to identify delivery points
that include a HILL
Directive (1)(b),
transparency
component (PP 52–
58) Data in a single location
on SPP’s website,
searchable and filterable,
on Network Upgrades
Attachment O, Section V
requires the SPP Transmission
Expansion Plan (“STEP”) to be
publicly available in a

8 Id. at PP 35, 43.
9 Id. 9 Id. at PP 52, 58.
10 Id. at PP 75–76, 78–79.

PDF page 4

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 4

Show Cause
Order directive
Commission’s concern
Tariff revision
needed to serve large
loads and their costs
searchable and filterable format.
Attachment BA, Section 2.1.3.6
requires the Host Transmission
Owner to provide the Network
Upgrades and costs for HILL
delivery points for inclusion in
the STEP
Non-Transmission Facility Revisions (RR805)
Directive (1)(c),
clarity component
(PP 75–76)
Clear, consistent
terminology identifying
the facilities to which co-
located and Behind-The-
Meter Generation connect
New defined term “Non-
Transmission Facility” in
Attachment V, Section 1,
Attachment AY, Section II, and
Attachment BB, Section 1.
Revised definitions of
“Affected System
Interconnection Customer,”
“Affected System Study,” and
“Transmission System”
Directive (1)(c),
interconnection
component (PP 76,
78–80)
When generation on
facilities outside the
Transmission System is
subject to SPP’s
interconnection study
requirements
Attachment V, Section 9.1 and
Attachment AY, Section V.9.1
point to the study requirements
and criteria in Business Practice
7250, Section 6. Attachment
BB, Section 3.1.3(4) routes
High Impact Large Load
Generation Assessment
(“HILLGA”) requests on Non-
Transmission Facilities to that
same process
Directive (1)(c),
market
participation
component (P 76)
When such generation
must register in the
Integrated Marketplace,
and who is responsible
Attachment AE, Section 2.2(6)
identifies the party under whose
name an unexecuted service
agreement will be filed when a
Resource fails or refuses to
register, including the Market
Participant representing the load
for Behind-The-Meter
Generation

This filing is one part of SPP’s comprehensive response to the Show Cause Order. The other directives are addressed in separate filings, as discussed in Section III.E below.

PDF page 5

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 5

II. BACKGROUND
A. The HILL Process

On January 14, 2026, the Commission accepted SPP's Tariff revisions establishing the HILL study process in Attachment BA and the HILLGA process in Attachment BB.11 Those revisions (1) defined HILLs as a new category of load; (2) established enhanced study requirements for HILLs, including the HDPS, to enable SPP to assess the reliability impacts of a HILL on the Transmission System; and (3) imposed ongoing operational requirements on HILLs to ensure the continued reliable operation of the Transmission System. Those operational requirements, in Attachment BA, Section 2.2, include: compliance with non-conforming load requirements; real- time telemetry; remote disconnect capability; a ramp-rate limitation; phasor measurement unit installation; ride-through requirements; and a prohibition on withdrawals without appropriate transmission service.12 The Commission found the HILL process to be “a just and reasonable approach for integrating transmission customers’ new large loads onto SPP’s transmission system in a reliable manner.”13

B. Generator Interconnections to Facilities Outside the Transmission System

Attachments V and AY of the Tariff govern interconnection to SPP’s
Transmission System.14 Those Attachments also include Affected System Study procedures for proposed interconnections to other transmission systems that may affect SPP’s Transmission System.15 Some generation is Behind-The-Meter Generation, co- located on-site, or connected to distribution or other facilities that are not part of the Transmission System. SPP currently addresses that type of generation through Business Practice 7250, which uses "non-jurisdictional" terminology. The Tariff does not define that term or use it consistently. As a result, the Tariff does not clearly state when such generation will be studied for its impact on the Transmission System, by whom, or through which study process. Nor does it identify the responsible party when such generation fails to register in the Integrated Marketplace and is not subject to an interconnection agreement with the Transmission Provider or a Transmission Owner.

11 Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (“HILL Order”).
12 Tariff, Attachment BA, Section 2.2.
13 HILL Order at P 61.
14 Tariff, Attachments V and AY.
15 Tariff, Attachment V, Section 9; Tariff, Attachment AY, Section V.9.

PDF page 6

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 6

C. The Show Cause Order

For purposes of the Show Cause Order, the Commission adopted SPP’s definition of “large load.”16 The Commission preliminarily found that the Tariff appears unjust and unreasonable in four categories. The Commission directed SPP and the Transmission Owners either to show cause why the Tariff remains just and reasonable or to explain what changes would remedy the identified concerns.17 The Commission strongly encouraged SPP to address these issues through FPA Section 205 filings.18

D. Abeyance

On August 3, 2026, SPP moved to hold Docket No. EL26-68-000 in abeyance through November 20, 2026, so SPP could develop Section 205 filings through its stakeholder process.19 SPP described the anticipated content of those filings in its Abeyance Motion, including the revisions submitted here.20 On August 14, 2026, the Commission granted the Abeyance Motion and set a due date of November 20, 2026, for SPP’s response to the Show Cause Order.21

E. Stakeholder Process and Approval

The HILL Transmission Service Revisions (RR808) were reviewed and approved without opposition through SPP’s robust stakeholder process, including meetings of the Project Cost Working Group (“PCWG”) on September 28, 2026;22

16 Show Cause Order at n.2.
17 Id. at P 3.
18 Id. at P 32.
19 Joint Movants’ Amended Motion to Hold Section 206 Proceeding in Abeyance of Southwest Power Pool, Inc., et al., Docket No. EL26-68-000 (Aug. 3, 2026) (“Abeyance Motion”).
20 Id. at Section IV.
21 Sw. Power Pool, Inc., 196 FERC ¶ 61,128 (2026) (“Abeyance Order”). 22 See PCWG Minutes, dated September 28, 2026, at Agenda Item 2A posted at: https://spp.org/documents/77912/pcwg%20special%20meeting%20minutes%202026 0928.pdf. The PCWG provides stakeholder input, oversight and accountability that allows for a transparent review of transmission project cost variances. The PCWG evaluates projects that exceed allowable variance levels and provides quarterly reports to stakeholders.

PDF page 7

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 7

Transmission Working Group (“TWG”) on September 29, 2026;23 Economic Studies Working Group (“ESWG”) on October 1, 2026;24 Regional Tariff Working Group (“RTWG”) on October 7, 2026;25 Market Working Group (“MWG”) on October 7,

23
See TWG Minutes, dated September 29, 2026, at Agenda Item 5 posted at: https://www.spp.org/documents/77977/twg%20meeting%20minutes%202026 0929.pdf. The TWG develops and oversees regional and interregional transmission planning processes, including generator interconnection and long-term transmission service study processes. The TWG reviews proposed transmission interconnections and coordinates transmission planning activities to develop SPP’s Integrated Transmission Plan and Transmission Expansion Plan.

24
See ESWG & TWG Joint Meeting Minutes, dated September 30-October 1, 2026, at Agenda Item 10 posted at:

https://www.spp.org/documents/77985/joint%20eswg-
twg%20meeting%20minutes%2020260930-1001.pdf. The ESWG advises and assists SPP staff in determining the appropriate data, planning methods and processes for developing and evaluating economic transmission expansion options for the SPP region.

25
See RTWG Approval, dated October 7, 2026, at RR808 Recommendation Report posted at: https://www.spp.org/spp-documents-filings/?id=21069 (contained in zip file “RR808 (SIR879) Transmission Service to Hill Impact Large Load”). The RTWG develops, implements and oversees SPP’s Open Access Transmission Tariff. The RTWG provides input on regulatory or implementation issues not specifically covered by the tariff and issues where there may be conflicting or differing interpretations of the tariff.

PDF page 8

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 8

2026;26 Operating Reliability Working Group (“ORWG”) on October 8, 2026;27 and the Markets and Operations Policy Committee (“MOPC”) on October 13-14, 2026.28

The Non-Transmission Facility Revisions (RR805) were also reviewed and approved through SPP’s stakeholder process, including meetings of the Generation Interconnection Advisory Group (“GIAG”) on September 16, 2026;29 ESWG on

26
See MWG Approval, dated October 7, 2026, at RR808 Recommendation Report posted at: https://www.spp.org/spp-documents-filings/?id=21069 (contained in zip file “RR808 (SIR879) Transmission Service to Hill Impact Large Load”). The MWG develops and oversees policies and procedures related to the Market Protocols that define SPP’s wholesale markets, including energy and operating reserve, congestion management, congestion hedging, demand response and market power mitigation. The MWG proposes changes to the SPP Tariff and other governing documents to implement suggested market changes.

27
See ORWG Approval, dated October 8, 2026, at RR808 Recommendation Report posted at: https://www.spp.org/spp-documents-filings/?id=21069 (contained in zip file “RR808 (SIR879) Transmission Service to Hill Impact Large Load”). The ORWG develops and oversees policies and procedures related to the reliable and secure operation of the Bulk Electric System within SPP’s Reliability Coordinator, Balancing Authority and Reserve Sharing Group footprints. The ORWG ensures these operating policies are consistent with North American Electric Reliability Corporation and regional reliability standards.

28
See MOPC Meeting Minutes, dated October 13-14, 2026, at Agenda Item 3.c posted at: https://www.spp.org/spp-documents-filings/?id=532303. The MOPC consists of a representative officer or employee from each SPP Member and reports to the SPP Board of Directors. Its responsibilities include recommending modifications to the Tariff. See Southwest Power Pool, Inc., Bylaws, First Revised Volume No. 4 ("Bylaws") at Section 6.1.

29
See GIAG Meeting Minutes, dated September 16, 2026, at Agenda Item 2b posted at: https://spp.org/documents/77873/giag%20meeting%20minutes%2020260916.pdf. The GIAG shares information and gathers feedback related to SPP’s generation interconnection (GI) studies. The GIAG relies on the collective knowledge of interested GI customers and stakeholders to assist in developing recommendations to improve SPP’s GI services.

PDF page 9

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 9

September 21, 2026;30 TWG on September 21, 2026;31 MWG on October 7, 2026;32 the RTWG on October 7, 2026;33 and MOPC on October 13-14, 2026.34

While SPP recognizes that stakeholder approval does not by itself cause a filing to be just and reasonable, SPP requests that the Commission extend appropriate deference to SPP’s stakeholder process, consistent with Commission precedent.35

30
See ESWG & TWG Joint Meeting Minutes, dated September 21, 2026, at Agenda Item 3

posted
at:
https://spp.org/documents/77884/joint%20eswg-
twg%20meeting%20minutes%2020260921.pdf. The ESWG advises and assists SPP staff in determining the appropriate data, planning methods and processes for developing and evaluating economic transmission expansion options for the SPP region. The TWG develops and oversees regional and interregional transmission planning processes, including generator interconnection and long-term transmission service study processes. The TWG reviews proposed transmission interconnections and coordinates transmission planning activities to develop SPP’s Integrated Transmission Plan and Transmission Expansion Plan.

31
Id.
32
See MWG Approval, dated October 7, 2026, at RR805 Recommendation Report posted at: https://www.spp.org/spp-documents-filings/?id=21069 (contained in zip file “RR805 (SIR879) Non-Transmission Facilities”). The MWG develops and oversees policies and procedures related to the Market Protocols that define SPP’s wholesale markets, including energy and operating reserve, congestion management, congestion hedging, demand response and market power mitigation. The MWG proposes changes to the SPP Tariff and other governing documents to implement suggested market changes.

33
See RTWG Approval, dated October 7, 2026, at RR805 Recommendation Report posted at: https://www.spp.org/spp-documents-filings/?id=21069 (contained in zip file “RR805 (SIR879) Non-Transmission Facilities”). The RTWG develops, implements and oversees SPP’s Open Access Transmission Tariff. The RTWG provides input on regulatory or implementation issues not specifically covered by the tariff and issues where there may be conflicting or differing interpretations of the tariff. 34

See MOPC Meeting Minutes, dated October 13-14, 2026, at Agenda Item 3.b posted at: https://www.spp.org/spp-documents-filings/?id=532303. The MOPC consists of a representative officer or employee from each SPP Member and reports to the SPP Board of Directors. Its responsibilities include recommending modifications to the Tariff. See Southwest Power Pool, Inc., Bylaws, First Revised Volume No. 4 ("Bylaws") at Section 6.1.

35 The Commission has previously recognized that provisions approved through regional transmission organization stakeholder processes are due deference. See Sw. Power Pool, Inc., 127 FERC ¶ 61,283, at P 33 (2009) (noting that the Commission “accord[s] an appropriate degree of deference to RTO stakeholder processes”); New Eng. Power Pool, 105 FERC ¶ 61,300, at P 34 (2003) (Commission approval of transmission cost

PDF page 10

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 10

III. DESCRIPTION OF AND JUSTIFICATION FOR THE LARGE LOAD
REVISIONS

The Large Load Revisions respond to the gaps the Commission identified and build on a framework the Commission has already found just and reasonable. They apply uniformly to all similarly situated customers and advance the Commission’s stated objectives of protecting consumers from unnecessary costs, safeguarding reliability, and improving transparency and consistency for customers, Transmission Owners, Market Participants, and federal and state regulators. III.A through III.C describe the HILL Transmission Service Revisions, Section III.D describes the Non- Transmission Facility Revisions, and Section III.E identifies the directives SPP is addressing in separate filings.

Under FPA Section 205, SPP must show that its proposal is just and reasonable. It need not show that the proposal is the only reasonable approach or that it is more reasonable than the alternatives.36 As Commissioner LaCerte observed, FPA Section 205 provides a “relatively capacious standard” under which the Commission may accept a broad range of proposals shown to be just and reasonable and not unduly discriminatory or preferential.37 The Large Load Revisions meet that standard. For each concern the Commission identified, SPP:

1. places in the Tariff the binding obligation the Commission found missing;
2. ties that obligation to an existing process the Commission has already accepted (the HDPS, the pro forma service agreements, the STEP, the Affected System Study framework, and the Attachment AE registration requirements) instead of creating a parallel process; and

3. places implementation details, such as technology-specific evaluation methods and size- and impact-based study thresholds, in Business Practices that are developed and revised through SPP's stakeholder process.

allocation proposal based upon an extensive and thorough stakeholder process); Policy Statement Regarding Regional Transmission Groups, 1991-1996 FERC Stats. & Regs., Regs. Preambles ¶ 30,976, at 30,872 (1993) (the Commission will afford the appropriate degree of deference to the stakeholder approval process). The Commission’s deference to RTO stakeholder processes has been upheld by the courts. See Pub. Serv. Comm’n of Wis. v. FERC, 545 F.3d 1058, 1062-63 (D.C. Cir. 2008) (noting that the Commission often gives weight to RTO proposals that reflect the position of the majority of the RTO’s stakeholders) (quoting Am. Elec. Power Serv. Corp. v. Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,083, at P 172 (2008)).

36 See, e.g., Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984); OXY USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995).
37 Show Cause Order (LaCerte, Comm’r, concurring) at P 6.

PDF page 11

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 11

This structure follows the Commission's rule of reason. Under that policy, a tariff must include practices that significantly affect rates, terms, and conditions of service, are realistically susceptible of specification, and are not so generally understood in contractual arrangements that stating them would be superfluous. Implementation details that do not meet that test may be placed in business practices.38 The Large Load Revisions divide the material along that line. The Tariff sets out each binding obligation and references the applicable Business Practices that govern how SPP carries it out. The Business Practices supply the technical and procedural detail needed to carry out obligations the Tariff imposes. The Commission applied this same standard in the Show Cause Order itself, focusing on responsibilities that “may significantly affect rates and are realistically susceptible of specification.”39

A. Evaluation of Alternative Transmission Technologies (Directive
(1)(a), First Component)

1. Commission Concern

The Commission preliminarily found that the Tariff lacks clear and consistent provisions requiring the evaluation of alternative transmission technologies as potential solutions to accommodate a request for transmission service on behalf of a large load.40 The Commission noted three points: (1) these technologies can often add capacity on existing lines within one to three years; (2) large load development timelines frequently outpace traditional Network Upgrades; and (3) when large load driven Network Upgrade costs are rolled into transmission revenue requirements, other transmission customers may bear a portion of those costs.41 The Commission directed SPP to address provisions that would (1) require the evaluation of alternative transmission technologies “in all instances, without the need for a request from the Eligible Customer”; and (2) if traditional Network Upgrades are selected, include in the study report a sufficiently clear demonstration of why those technologies are not feasible or

38 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985); Hecate Energy Greene Cnty., 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir. 2023); Prior Notice & Filing Requirements Under Part II of the Fed. Power Act, 64 FERC ¶ 61,139, at 61,989 (1993); see also Show Cause Order at P 76 & n.150.
39 Show Cause Order at P 76 & n.150.
40 Show Cause Order at P 44; see also id. at P 35.
41 Id.

PDF page 12

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 12

would not result in lower costs or a faster timeline.42 The Commission emphasized that it was “not mandating the use of alternative transmission technologies.”43

2. Proposed Revisions

SPP proposes to add the following to Attachment BA, Section 2.1.3.4:

The HDPS will evaluate the appropriateness of the use
of grid enhancing technologies (“GETs”) as described in
the SPP Business Practices. The Transmission Provider
will determine whether one or more GETs should be
identified as a solution(s) to needs determined in the
HDPS, consistent with Good Utility Practice, Applicable
Reliability Standards, and other Applicable Laws and
Regulations. The HDPS report will include an
explanation of the results of the Transmission Provider’s
evaluation of GETs.44
This revision addresses the Commission’s concerns regarding evaluation of alternative transmission technologies as potential solutions to accommodate a request for transmission service on behalf of a large load. First, Section 2.1.3.4 of Attachment BA of the Proposed Tariff requires evaluation of GETs in all instances.45 Under Attachment BA, SPP performs an HDPS for every requested HILL delivery point change.46 The proposed new language says the HDPS “will evaluate” GETs, making the evaluation mandatory for every HDPS study.47 The evaluation of GETs, therefore, does not depend on a request from the Transmission Customer or Network Customer.48 Because the Commission adopted the HILL definition as its definition of “large load,” the evaluation covers every transmission service request within the scope of the Show Cause Order.49

42 Id. at P 45.
43 Id. 44 Proposed Tariff, Attachment BA, Section 2.1.3.4.
45 Id.
46 Tariff, Attachment BA, Section 2.1.3.4.
47 Proposed Tariff, Attachment BA, Section 2.1.3.4.
48 Id.
49 Show Cause Order at n.2.

PDF page 13

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 13

Second, the evaluation covers the technologies the Commission identified. In footnote 14, the Show Cause Order lists the alternative transmission technologies the Commission had in mind: static synchronous compensators, static VAR compensators, advanced power flow control devices, transmission switching, synchronous condensers, voltage source converters, advanced conductors, tower lifting, and dynamic line ratings.50 SPP Business Practice 7850, referenced in Attachment BA, evaluates each of these nine technologies and explains how SPP applies them to the types of constraints that large loads typically create.51 Although the Proposed Tariff uses the term “GETs,” Business Practice 7850 applies that term to all nine technologies the Commission identified, including advanced conductors and tower lifting, so the evaluation is not limited to a narrower set of grid-enhancing devices. The Commission likewise noted that it has referred to these technologies as GETs.52 The HDPS evaluation uses models and study tools capable of representing the applicable characteristics of each technology identified in Business Practice 7850, consistent with the Commission's direction that the evaluation use models capable of accurately accounting for advanced transmission technologies.53 Depending on the constraint identified, SPP uses steady-state power flow, short-circuit, RMS/transient stability, and, when necessary, electromagnetic transient ("EMT") analyses. SPP uses PSS®E and TSAT™ for power flow and RMS dynamic studies, and PSCAD™ for detailed EMT studies. Each technology is represented in a way that fits it:

•
Reactive supports including synchronous condenser, static synchronous compensators, and static VAR compensators; advanced power flow control, and VSC-HVDC facilities: power flow, short circuit, and dynamic models;

•
Transmission switching: topology changes
•
Advanced conductors and tower lifting: updated equipment parameters and ratings

•
Dynamic line ratings: condition-dependent thermal ratings

The models and analyses used in a given HDPS depend on the identified constraint, the validated model data and supporting technical information available, and the level of detail needed to determine whether the technology provides reliable mitigation. Where sufficient validated models or supporting data are unavailable, the HDPS report will explain how that limitation affected the evaluation.

50 Id. at n.14.
51 See Business Practice 7850, Section A. 52 Show Cause Order at n.14.
53 Id. at P 45.

PDF page 14

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 14

Third, Section 2.1.3.4 of Attachment BA of the Proposed Tariff requires that the HDPS report include an explanation of the results of SPP’s GETs evaluation.54 Business Practice 7850 requires each HDPS report to explain the results for each identified technology and provides a model format that documents, technology by technology, whether the technology was selected, was less cost-effective than the selected mitigation, could not resolve the identified constraint, or was screened out for a stated technical reason.55 This provides the Eligible Customer the transparency the Commission called for in the Show Cause Order.56 Specifically, where SPP selects traditional Network Upgrades, the HDPS report will explain, technology by technology, whether the alternative technology would not resolve the identified reliability need, would not result in lower costs, or would not provide a faster timeline.

Finally, the revisions respect engineering judgment and do not mandate GETs. As the Commission directed, the revisions require evaluation, not deployment.57 Under the proposed language, SPP selects a GET only when doing so is consistent with Good Utility Practice, Applicable Reliability Standards, and other Applicable Laws and Regulations.58 This protects reliability for existing customers while ensuring cost- effective, faster solutions are not overlooked and is consistent with the Commission’s statement that it is not mandating the use of alternative transmission technologies, as well as the goal, articulated in Commissioner See’s concurrence, of respecting transmission providers’ engineering judgments while protecting against unnecessary upgrade costs.59 By requiring SPP to consider lower-cost and faster-to-deploy alternatives before selecting traditional Network Upgrades, the proposed revision also addresses the Commission’s concern that large load driven Network Upgrade costs rolled into transmission revenue requirements may be borne in part by other transmission customers.

54 Proposed Tariff, Attachment BA, Section 2.1.3.4.
55 Business Practice 7850, Section C.
56 Show Cause Order at P 45.
57 Id.
58 Proposed Tariff, Attachment BA, Section 2.1.3.4.
59 Show Cause Order at P 45.

PDF page 15

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 15

B. Pro Forma Service Agreement Provisions Memorializing Ongoing
Operational Requirements (Directive (1)(a), Second Component)

1. Commission Concern

The Commission found that, although the Tariff includes ongoing operational requirements for HILLs, the HILL process does not include pro forma provisions in a transmission service agreement that memorialize them.60 Without such provisions, the Commission was concerned that SPP “may be unable to enforce ongoing operational requirements.”61

2. Proposed Revisions

SPP proposes the following revisions addressing the Commission’s concerns with respect to operational requirements. Section 6.0 of Attachment A of the Proposed Tariff (Form of Service Agreement for Firm Point-to-Point Transmission Service) provides that, if any portion of the load receiving Firm Point-to-Point Transmission Service under the Service Agreement is a HILL, the Transmission Customer must satisfy the Additional Requirements for High Impact Large Loads in Attachment BA, Section 2.2 for each HILL.62 The Specifications for Long-Term Firm Point-to-Point Transmission Service add a field to identify which Point(s) of Delivery include HILLs.63 Similarly, new Section 3.0 of the Specifications for Network Integration Transmission Service (Attachment 1 to the Network Integration Transmission Service Agreement in Attachment F of the Proposed Tariff), provides that, if any portion of the Network Customer’s Network Load listed in Appendix 3 is a HILL, the Network Customer must satisfy the Additional Requirements for HILLs for each such load as required by Attachment BA, Section 2.2.64 Appendix 3 (Delivery Points) adds a column showing whether each delivery point includes a HILL and, if so, the effective date.65 SPP incorporates the Attachment BA, Section 2.2 requirements by reference rather than restating them. The requirements therefore stay uniform across all customers, and any future Commission-accepted change to Attachment BA, Section 2.2 flows automatically into every service agreement without amending each one.

60 Id. at P 46.
61 Id.
62 Proposed Tariff, Attachment A, Section 6.0. 63 Id. at Specifications for Long-Term Firm Point-To-Point Transmission Service, Section 4.0. 64 Proposed Tariff, Attachment F, Attachment 1 (Specifications for Network Integration Transmission Service), Section 3.0.
65 Id. at Appendix 3.

PDF page 16

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 16

These revisions address the Commission’s concerns by making the Attachment BA, Section 2.2 operational requirements an express contractual obligation of the Transmission Customer or Network Customer in every pro forma transmission service agreement covering a HILL. SPP can therefore enforce those requirements both under the Tariff and under the executed agreement. This directly resolves the Commission’s concern that, without such provisions, SPP “may be unable to enforce ongoing operational requirements,” and preserves the real-time safeguards the Commission relied on when it accepted the HILL process.66 The new delivery point identification fields also make it clear which delivery points carry HILL obligations, and from what date. This removes any ambiguity about the scope of the customer’s obligations and improves SPP’s visibility into where HILLs are on the system.

C. Transparency Regarding Large Load Driven Network Upgrades
and Costs (Directive (1)(b), Transparency Component)

1. Commission Concern

The Commission preliminarily found that the Tariff “appears to be unjust and unreasonable or unduly discriminatory or preferential because it does not contain provisions requiring the provision of data on SPP’s website in a single location, and in an easily accessible format that is searchable and allows users to filter the data, on transmission service requested by Eligible Customers on behalf of large loads, for Network Upgrades evaluated in the local transmission planning process that are needed to provide transmission service to Eligible Customers on behalf of those large loads, and the costs for those Network Upgrades.”67 The Commission acknowledged that SPP already reports Network Upgrade information generally.68 Its concern was that this reporting is primarily aggregated and not required by the Tariff.69 The Commission directed SPP to explain whether the Tariff remains just and reasonable without provisions that would require SPP and the Transmission Owners to publicly post and regularly update data that details:  (1) the aggregate amounts of proposed large load additions (including by transmission pricing zone), (2) the planned Network Upgrades needed to provide transmission service to Eligible Customers on behalf of large loads,

66 Show Cause Order at P 46; HILL Order at P 63.
67 Show Cause Order at P 52; see also id. at PP 54, 56, & n.126. The Commission emphasized that its concern with transparency regarding Network Upgrades needed to provide transmission service to Eligible Customers on behalf of large loads, as well as the costs of such upgrades, is limited to Network Upgrades planned through the local transmission planning process.
68 Id. at P 55.
69 Id.

PDF page 17

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 17

identified by type of equipment and Network Upgrade (e.g. new substation, reconductoring, a new high-voltage transmission line) for each transmission service request, and (3) cost estimates for those Network Upgrades.70

2. Proposed Revisions

SPP proposes two revisions. First, new language in Section V of Attachment O requires the SPP Transmission Expansion Plan (STEP) to be “publicly available on the Transmission Provider’s website, in a searchable and filterable format, containing non- confidential information.”71 Second, new language in Section 2.1.3.6 of Attachment BA requires the Host Transmission Owner to provide SPP with the Network Upgrades and costs identified in the Load Connection Study Report and the HILL Supplemental Connection Report for each HILL delivery point, for inclusion in the STEP report.72 The STEP already includes Network Upgrades required under the Attachment AQ and Attachment AX study processes, through which HILL delivery points are studied, together with the supplemental HILL studies under Attachment BA.73

These revisions directly respond to the Commission’s concerns. First, the Attachment BA revision addresses the Commission’s transparency concerns regarding Network Upgrades evaluated in the local transmission planning process by requiring the Host Transmission Owner, who identifies these facilities through the HILL Supplemental Connection Report, to report them and their costs to SPP for inclusion in the STEP. This targets exactly the category of upgrades the Commission identified: the Commission limited its transparency concern to Network Upgrades planned through the local transmission planning process, and the Host Transmission Owner is the entity that identifies those facilities.74 Second, the Attachment O revision makes the STEP, a single, Tariff-mandated repository on SPP’s website, searchable and filterable. SPP will document the Network Upgrades reported by Host Transmission Owners under Attachment BA in both the STEP report and the STEP's Appendix 1 spreadsheet, which SPP already posts on its website.75 Together, these revisions give state regulators, transmission customers, and other stakeholders the means to identify which Network Upgrades are driven by large loads and what they cost. The revisions limit public

70 Id. at P 58.
71 Proposed Tariff, Attachment O, Section V.
72 Proposed Tariff, Attachment BA, Section 2.1.3.6.
73 Tariff, Attachment O, Sections I and V.
74 Show Cause Order at P 56 & n.126.
75 See, e.g., SPP, 2026 SPP Transmission Expansion Plan (STEP), posted at: https://spp.org/Documents/76727/2026%20SPP%20Transmission%20Expansion%20 (STEP)%20Plan.zip.

PDF page 18

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 18

posting to non-confidential information, consistent with the Tariff and current practice. This responds to the Commission’s direction that SPP mitigate confidentiality concerns while still providing the necessary transparency.76

D. Co-Location and Behind-The-Meter Generation (Directive (1)(c),
Clarity, Interconnection, and Market Participation Components)

1. Commission Concern

The Commission preliminarily found that the Tariff lacks sufficient clarity and consistency regarding the rates, terms, and conditions of service that apply to interconnection customers serving co-located load,77 including how those customers may use SPP’s generator interconnection processes, the scope of SPP’s study of co- location arrangements, and the responsibilities of the entities involved. The Commission also raised concerns about transmission and ancillary service rates for Eligible Customers taking service on behalf of co-located load and load with Behind- The-Meter Generation.78 This filing provides clarity and addresses the interconnection and market participation components of that concern. SPP addresses the transmission service component, including transmission and ancillary service rates for co-located load, in its response in Docket No. EL26-68-000, as described in Section III.E. The Commission specifically invited SPP to explain how its existing HILLGA process may already clarify some of these requirements or may be modified to provide such clarity. The Non-Transmission Facility Revisions do both.79

2. Proposed Revisions

a. Defining Non-Transmission Facilities

SPP proposes to add the following defined term to Attachment V, Section 1 and Attachment AY, Section II:

Non-Transmission Facility shall mean a facility within
the SPP Region that is not included as part of the

76 Show Cause Order at P 58.
77 The Show Cause Order defines co-located load as a configuration that refers to end- use customer load that is physically connected to the facilities of an existing or planned generating facility on the interconnection customer’s side of the point of interconnection to the RTO/ISO’s transmission system. In the Show Cause Order, the Commission uses the term co-location arrangement when referring to both the co- located load and the associated generating facility. See id. at P 70.
78 Id. at PP 75–80.
79 Id. at P 76.

PDF page 19

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 19

Transmission System or does not meet the criteria for a
transmission facility under Attachment AI.80
Attachment BB, Section 1 incorporates this definition by reference, along with the definitions of “Affected System Interconnection Customer” and “Affected System Study.”81 SPP also proposes to revise the definitions of “Affected System Interconnection Customer” and “Affected System Study” in Attachments V and AY to expressly include interconnection requests for generating facilities “to a Non- Transmission Facility” that may cause the need for Affected System Network Upgrades on, or that have an impact on, SPP’s Transmission System.82 Finally, SPP proposes to revise the definition of “Transmission System” in Attachments V and AY to mean “the facilities used by the Transmission Provider to provide transmission service under Part II, Part III, Part IV, and Part VII of the Tariff.”83

These revisions supply the clear terminology the Commission sought. First, the new defined term replaces the undefined and inconsistently used “non-jurisdictional” terminology with an objective, Tariff-based standard tied to the Transmission System and the transmission facility criteria in Attachment AI. Second, by bringing Non- Transmission Facilities within the Affected System definitions, the revisions make clear that generation interconnecting to those facilities, including Behind-The-Meter Generation and on-site co-located generation, falls within SPP’s existing Affected System Study framework when it may affect the Transmission System. Third, the revised Transmission System definition ties that term to the facilities SPP uses to provide transmission service under the Tariff, so the boundary between the Transmission System and Non-Transmission Facilities is clear. Together, these revisions give Interconnection Customers, Transmission Owners, and Market Participants a consistent vocabulary across the Tariff and SPP’s Business Practices.

b. Interconnection Study Requirements

SPP proposes to revise Attachment V, Section 9.1 and Attachment AY, Section V.9.1 to direct readers to Business Practice 7250 for the study requirements that apply when an Affected System Interconnection Customer seeks to interconnect to a Non- Transmission Facility, or to other facilities not covered by a transmission provider's open access transmission tariff.84 The revised sections also point to the criteria in Business Practice 7250 that SPP uses to decide whether such a request must be studied

80 Proposed Tariff, Attachment V, Section 1; Attachment AY, Section II.
81 Proposed Tariff, Attachment BB, Section 1.
82 Proposed Tariff, Attachment V, Section 1; Attachment AY, Section II.
83 Id.
84 Proposed Tariff, Attachment V, Section 9.1; Attachment AY, Section V.9.1.

PDF page 20

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 20

in the Interconnection Cluster Study under Attachment AY or in the Affected System Study process detailed in Section 9 of Attachment AY.85

SPP also proposes to revise Attachment BB, Section 3.1.3(4). Under the revision, a customer requesting a generator interconnection to a Non-Transmission Facility as part of a HILLGA Request must follow the procedures in Section 6 of Business Practice 7250.86

Business Practice 7250, Section 6, sets out the study framework referenced in the Tariff:87

Notification. When a Transmission Owner becomes aware of an
interconnection request of 5 MW or greater to a Non-Transmission Facility, it must notify SPP. The Transmission Owner must also notify SPP of modifications to existing or planned generation on Non-Transmission Facilities, regardless of size, if they may materially impact the Transmission System.

SPP evaluation. For interconnection requests of 5 MW or more that may impact the Transmission System, SPP will evaluate any identified impacts to ensure continued reliability of the Transmission System. It will do so even though those requests are not subject to Attachments V or AY.

Study pathways. Business Practice 7250 establishes five study pathways based on the size of the request and its injection or impact on the Transmission System.

Pathway
Interconnections to Non-
Transmission Facilities
Study
Naming Convention
1
10 MW or greater with 1 MW
or greater injection/impact
DISIS/ICS
Affected System
Generator
Interconnection (ASGI)
2
10 MW or greater with less
than 1 MW injection/impact
90-Day Affected
System Study
Non-Transmission
Facility Interconnection
(NTF)
3
10 MW or greater with less
than 1 MW injection/impact
under system intact conditions
with proposed load
90-Day High Impact
Large Load Generator
Assessment
Non-Transmission
Facility-High Impact
Large Load Generator
Assessment (NTF-
HILLGA)
4
Less than 10 MW with 1 MW
or greater injection/impact
90-Day Affected
System Study
Non-Transmission
Facility Interconnection
(NTF)
5
Less than 10 MW with less
than 1 MW injection/impact
TO SIS accepted if no
injection/impact, or 90-
Day Affected System
Study
Non-Transmission
Facility Interconnection
(NTF)

85 Id. 86 Proposed Tariff, Attachment BB, Section 3.1.3(4).
87 Business Practice 7250, Section 6.

PDF page 21

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 21

Applicability. Section 6 expressly applies to Behind-The-Meter Generation, on-site co-located generation, and generation connected to Non-Transmission Facilities.

Responsibilities. Section 6 describes the respective study, notification, and agreement responsibilities of the Transmission Owner and SPP. That includes the requirement that Network Upgrades identified on the Transmission System be completed before the Generating Facility operates, unless SPP has approved other mitigations.

These revisions address the Commission’s interconnection concerns. First, the Tariff now expressly states that interconnection requests to Non-Transmission Facilities are evaluated under SPP’s Affected System Study framework. It also identifies where the applicable study criteria are found. Second, Business Practice 7250 gives objective, size- and impact-based thresholds that determine whether a request is studied, which study applies, and who performs it. Generation that is behind the meter or co-located therefore cannot fall outside the Tariff’s study framework merely because the facility it connects to is not part of the Transmission System. Third, the NTF- HILLGA pathway gives interconnection customers a defined route to pair Behind-The- Meter Generation with a HILL. This links SPP’s co-location framework to the HILL process the Commission has already found just and reasonable.88 Finally, the revisions preserve reliability. Generation that could inject onto, or otherwise affect, the Transmission System is identified and studied, and any necessary Network Upgrades are completed before operation. The framework also responds to the Commission’s concern about the scope of the analyses SPP performs to evaluate co-location arrangements. Business Practice 7250 requires Transmission Owner studies to include thermal, voltage, and short-circuit analyses. It adds stability evaluations above specified size thresholds and allows SPP to perform stability analysis for NTF- HILLGA requests within 90 days.89

c. Market Registration Responsibilities

SPP proposes to revise Attachment AE, Section 2.2(6) to provide that a failure or refusal to register a Resource will result in the Transmission Provider filing an unexecuted version of the service agreement specified in Attachment AH with the Commission under the name of the Market Participant or other entity that owns the Resource or, in the case of Behind-The-Meter Generation, under the name of the Market Participant representing the load where the Resource is connected.90

88 HILL Order at PP 61, 64.
89 Show Cause Order at P 78; Business Practice 7250, Section 6.1.
90 Proposed Tariff, Attachment AE, Section 2.2(6).

PDF page 22

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 22

Business Practice 7250, Section 6.1 further confirms that, although generation interconnecting to Non-Transmission Facilities is not subject to Attachments V or AY, generating facilities on Non-Transmission Facilities that are 10 MW or greater are subject to the registration requirements in Attachment AE.91

Although the Tariff currently requires registration of Behind-The-Meter Generation that is 10 MW or greater, the existing failure-to-register provision in Attachment AE, Section 2.2(6) contemplates filing an unexecuted service agreement under the name of the generation interconnection customer under an interconnection agreement with the Transmission Provider or the applicable Transmission Owner. That provision does not account for Resources that may not be subject to an interconnection agreement with the Transmission Provider or a Transmission Owner, such as Behind- The-Meter Generation and generation interconnected to Non-Transmission Facilities. These revisions address the Commission's market participation concern by extending the provision to those situations and assigning responsibility to an entity with a Tariff- based relationship to the Resource. During stakeholder review, SPP considered making the Transmission Owner or the Transmission Customer responsible. Either may be an appropriate party in some circumstances, but neither would reliably capture the appropriate party in all of them. In many cases, the entity that owns or controls the Non-Transmission Facility is not a Transmission Customer under the Tariff, and the Transmission Owner may have no control over, or contractual relationship with, the owner of the Non-Transmission Facility or the Resource. Naming the Resource owner or, for Behind-The-Meter Generation, the Market Participant representing the host load places the registration obligation, and the consequences of failing to meet it, on the party best positioned to comply. This gives the Commission clarity about when, and by whom, co-located generation and Behind-The-Meter Generation must be registered in the Integrated Marketplace, consistent with the Commission's emphasis on a common and consistent understanding of entities' responsibilities relevant to co-location arrangements.92

d. Additional Clarifying Revisions

SPP also proposes two related clarifying revisions to the Affected System Study provisions. First, Attachment V, Section 9.1 and Attachment AY, Section V.9.1 now refer generally to any party with which SPP has an effective joint operating agreement or coordination agreement, rather than only MISO or AECI. The terms of that agreement will govern.93 Second, Attachment V, Section 9.8 and Attachment AY, Section V.9.8 replace the mandatory post-study meeting requirement. Instead, within ten Business Days after SPP posts the Affected System Study Report, Affected System Interconnection Customers may submit questions or request a meeting through SPP’s

91 Business Practice 7250, Section 6.1.
92 Show Cause Order at P 76.
93 Proposed Tariff, Attachment V, Section 9.1; Attachment AY, Section V.9.1.

PDF page 23

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 23

Request Management System (“RMS”).94 These revisions are consistent with the revisions described above, which expand on which entities qualify as Affected System Interconnection Customers. They also give those customers a transparent, documented channel for engaging with SPP on study results.

E. Directives Addressed in Separate Filings

This filing does not address the remaining Show Cause Order directives. SPP is addressing them in the following separate filings:

• the Large Load Safe Harbor Revisions;
• the Price Adaptive Load Service (PALS); and
•
SPP’s response to the Show Cause Order in Docket No. EL26-68-000, which addresses, among other things, transmission and ancillary service rates for co-located load.

SPP respectfully requests that the Commission consider this filing together with the above filings as SPP’s response to the Show Cause Order.

IV. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS

The Show Cause Order directs that any Section 205 filing explain how the proposal will avoid disrupting existing commercial arrangements and identify a reasonable effective date.95 The Large Load Revisions are designed to apply prospectively and with minimal disruption. Because the requested effective date is 90 days after this filing, parties to agreements that are nearing completion will have a reasonable period to finalize them before the revisions take effect. The revisions apply as follows:

• GETs evaluation. The new HDPS requirement will apply to HILL delivery point requests submitted on or after the effective date. HDPS for requests submitted before the effective date will finish under the existing scope, so ongoing studies are not delayed or re-performed.

• Service agreement provisions. Transmission Customers taking service on behalf of HILLs are already bound by Attachment BA, Section 2.2 under the Tariff. The new pro forma provisions memorialize existing obligations and do not create new substantive requirements. They will apply to service agreements executed or amended on or after the effective date. Existing service agreements covering HILLs will be conformed at their next amendment.

• Transparency. The searchable, filterable STEP format and the Host Transmission Owner reporting obligation will be implemented beginning with

94 Proposed Tariff, Attachment V, Section 9.8; Attachment AY, Section V.9.8.
95 Show Cause Order at PP 5, 32, 92.

PDF page 24

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 24

the first STEP update following the effective date. Neither imposes new obligations on Eligible Customers or affects pending agreements.

• Definitions. The new “Non-Transmission Facility” definition and conforming revisions replace inconsistent terminology. The revised Transmission System definition is not intended to change which facilities are part of the Transmission System, and these revisions do not alter existing interconnection or transmission service agreements.

• Study requirements. The Business Practice 7250, Section 6 study pathways will apply to interconnection requests to Non-Transmission Facilities for which the Transmission Owner notifies SPP on or after the effective date. Studies already in progress will finish under the existing scope, so ongoing studies are not delayed or re-performed.

• Market Registration. Resources are already required to register under Attachment AE. The revisions identify the party under whose name an unexecuted service agreement will be filed if a Resource fails or refuses to register. They do not affect Resources that are already registered.

• Affected System Study communications. The RMS-based question and meeting process will apply to Affected System Study Reports posted on or after the effective date.

V. EFFECTIVE DATE

For all the reasons discussed in this transmittal letter, SPP requests that the Commission accept the proposed revisions to the Tariff to become effective February 16, 2027, which is not less than 60 days nor more than 120 days after the date of this filing, consistent with Section 35.3(a)(1) of the Commission’s regulations.96

VI. ADDITIONAL INFORMATION

A. Documents submitted with this filing:

In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 1.97

B. Service:

SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants. A complete copy of this filing will be posted on the SPP web site, www.spp.org, and is also being served on all affected state commissions.

96 18 C.F.R. § 35.3(a)(1).

PDF page 25

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 25

C. Requisite agreements:

There are none.

D. Communications
Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:98

Justin A. Hinton
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2468
jhinton@spp.org

Meredith Powell
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2507
mpowell@spp.org

Tessie Kentner
Director & Associate General Counsel
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 688-1782
tkentner@spp.org

98 Pursuant to Commission Rule 101(e), 18 C.F.R. § 385.101(e), SPP requests waiver of Rule 203(b)(3), 18 C.F.R. § 385.203(b)(3), in order to permit more than two persons to be included on the service list.

PDF page 26

The Honorable Debbie-Anne A. Reese
November 18, 2026
Page 26

VII. CONCLUSION

For these reasons, SPP respectfully requests that the Commission accept the Large Load Revisions, effective February 16, 2027. SPP further requests that the Commission find that this filing resolves the concerns identified in Directive (1)(a), the transparency component of Directive (1)(b), and the clarity, interconnection, and market participation components of Directive (1)(c) of the Show Cause Order.

Respectfully submitted,

/s/ Meredith Powell
Justin A. Hinton
Meredith Powell
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR  72223-4936

Attorneys for
Southwest Power Pool, Inc.