ER27-559-000 · 2026-11-18 · Southwest Power Pool, Inc.

Enhance Transmission Service for HILLs and Non-Transmission Facilities

Text extracted from the eLibrary original (SHA-256 f098c035ca6677e3…). Download the original from the official source.

Contents · 21 sections
  1. I. SUMMARY OF FILING p. 2
  2. II. BACKGROUND p. 5
  3. A. The HILL Process p. 5
  4. B. Generator Interconnections to Facilities Outside the Transmission p. 5
  5. C. The Show Cause Order p. 6
  6. D. Abeyance p. 6
  7. E. Stakeholder Process and Approval p. 6
  8. III. DESCRIPTION OF AND JUSTIFICATION FOR THE LARGE LOAD p. 10
  9. A. Evaluation of Alternative Transmission Technologies (Directive p. 11
  10. B. Pro Forma Service Agreement Provisions Memorializing Ongoing p. 15
  11. C. Transparency Regarding Large Load Driven Network Upgrades p. 16
  12. D. Co-Location and Behind-The-Meter Generation (Directive (1)(c), p. 18
  13. E. Directives Addressed in Separate Filings p. 23
  14. IV. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS p. 23
  15. V. EFFECTIVE DATE p. 24
  16. VI. ADDITIONAL INFORMATION p. 24
  17. A. Documents submitted with this filing: p. 24
  18. B. Service: p. 24
  19. C. Requisite agreements: p. 25
  20. D. Communications p. 25
  21. VII. CONCLUSION p. 26

Topics in the text: Filing procedure · Connecting load and generation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff. 2 Sw.
Read this passage

I. SUMMARY OF FILING

printed heading · Topic match: Connecting load and generation

Attachment BB, Section 3.1.3(4) routes High Impact Large Load Generation Assessment (“HILLGA”) requests on Non- Transmission Facilities to that same process Directive (1)(c), market participation component (P 76) When such generation must register in the Integrated Marketplace, and who is…
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

A. The HILL Process

printed heading

The HILL Process On January 14, 2026, the Commission accepted SPP's Tariff revisions establishing the HILL study process in Attachment BA and the HILLGA process in Attachment BB.11 Those revisions (1) defined HILLs as a new category of load; (2) established enhanced study requirements for HILLs,…
Read this passage

B. Generator Interconnections to Facilities Outside the Transmission

printed heading

Generator Interconnections to Facilities Outside the Transmission System Attachments V and AY of the Tariff govern interconnection to SPP’s Transmission System.14 Those Attachments also include Affected System Study procedures for proposed interconnections to other transmission systems that may…
Read this passage

C. The Show Cause Order

printed heading

The Show Cause Order For purposes of the Show Cause Order, the Commission adopted SPP’s definition of “large load.”16 The Commission preliminarily found that the Tariff appears unjust and unreasonable in four categories.
Read this passage

D. Abeyance

printed heading · Topic match: Filing procedure

EL26-68-000 in abeyance through November 20, 2026, so SPP could develop Section 205 filings through its stakeholder process.19 SPP described the anticipated content of those filings in its Abeyance Motion, including the revisions submitted here.20 On August 14, 2026, the Commission granted the…
Read this passage

E. Stakeholder Process and Approval

printed heading · Topic match: Filing procedure

The MWG proposes changes to the SPP Tariff and other governing documents to implement suggested market changes. 27 See ORWG Approval, dated October 8, 2026, at RR808 Recommendation Report posted at: https://www.spp.org/spp-documents-filings/?id=21069 (contained in zip file “RR808 (SIR879)…
Read this passage

III. DESCRIPTION OF AND JUSTIFICATION FOR THE LARGE LOAD

printed heading

Under FPA Section 205, SPP must show that its proposal is just and reasonable.
Read this passage

A. Evaluation of Alternative Transmission Technologies (Directive

printed heading · Topic match: Cost allocation

Proposed Revisions SPP proposes to add the following to Attachment BA, Section 2.1.3.4: The HDPS will evaluate the appropriateness of the use of grid enhancing technologies (“GETs”) as described in the SPP Business Practices.
Read this passage

B. Pro Forma Service Agreement Provisions Memorializing Ongoing

printed heading

Proposed Revisions SPP proposes the following revisions addressing the Commission’s concerns with respect to operational requirements.
Read this passage

C. Transparency Regarding Large Load Driven Network Upgrades

printed heading · Topic match: Registry access

Reese November 18, 2026 Page 18 posting to non-confidential information, consistent with the Tariff and current practice.
Read this passage

D. Co-Location and Behind-The-Meter Generation (Directive (1)(c),

printed heading · Topic match: Connecting load and generation

Defining Non-Transmission Facilities SPP proposes to add the following defined term to Attachment V, Section 1 and Attachment AY, Section II: Non-Transmission Facility shall mean a facility within the SPP Region that is not included as part of the 76 Show Cause Order at P 58. 77 The Show Cause…
Read this passage

E. Directives Addressed in Separate Filings

printed heading · Topic match: Connecting load and generation

SPP respectfully requests that the Commission consider this filing together with the above filings as SPP’s response to the Show Cause Order.
Read this passage

IV. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS

printed heading

The new HDPS requirement will apply to HILL delivery point requests submitted on or after the effective date.
Read this passage

V. EFFECTIVE DATE

printed heading

EFFECTIVE DATE For all the reasons discussed in this transmittal letter, SPP requests that the Commission accept the proposed revisions to the Tariff to become effective February 16, 2027, which is not less than 60 days nor more than 120 days after the date of this filing, consistent with Section…
Read this passage

VI. ADDITIONAL INFORMATION

printed heading

VI.
Read this passage

A. Documents submitted with this filing:

printed heading

Documents submitted with this filing: In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 1.97
Read this passage

B. Service:

printed heading

Service: SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants.
Read this passage

C. Requisite agreements:

printed heading

C.
Read this passage

D. Communications

printed heading

Communications Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:98 Justin A.
Read this passage

VII. CONCLUSION

printed heading

CONCLUSION For these reasons, SPP respectfully requests that the Commission accept the Large Load Revisions, effective February 16, 2027.
Read this passage