ER26-3591-001 · 2026-11-19 · Southwest Power Pool, Inc.
Deficiency Response - Modify the CHILL Policy to Accommodate Planned Outages
PDF page 1
November 19, 2026The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street NE
Washington, DC 20426
RE:
Southwest Power Pool, Inc., Docket No. ER26-3591-____
Submission of Response to Request for Additional Information
Dear Secretary Reese:
Pursuant to the Federal Energy Regulatory Commission’s (“Commission”) letter issued on October 21, 2026,1 in this proceeding, Southwest Power Pool, Inc. (“SPP”) submits additional information2 concerning the filing it submitted on August 24, 2026, in Docket No. ER26-3591-000.3
I. BACKGROUND
In the August Filing, SPP submitted revisions to the SPP Open Access Transmission Tariff 4 to modify the Conditional High Impact Large Load (“CHILL”) policy to accommodate planned Outages.
1
Sw. Power Pool, Inc., Deficiency Letter, Docket No. ER26-3591-000 (Oct. 21, 2026) (“Deficiency Letter”).
2 SPP is attaching one, unmodified tariff record to this filing as required by the Commission. Electronic Tariff Filings, 130 FERC ¶ 61,047, at PP 3-8 (2010) (stating an amendment filing must include at least one tariff record even though a tariff revision might not otherwise be required). 3 Submission of Tariff Revisions to Modify the Conditional High Impact Large Load Policy to Accommodate Planned Outages of Southwest Power Pool, Inc., Docket No. ER26-3591-00 (Aug. 24, 2026) (“August Filing”). 4 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume No. 1. References in this filing to "Tariff" refer to the version of SPP’s Tariff currently in effect. "Proposed Tariff" refers to a version reflecting the revisions proposed in the August Filing. All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff.
PDF page 2
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 2
Several parties filed motions to intervene.5 No parties filed comments or protests.
In the Deficiency Letter, the Commission directed SPP to provide additional information required to process the filing. The Commission required responses be submitted within thirty (30) days of the date of the request for additional information. In this instant filing, SPP submits its responses to the specific questions raised in the Deficiency Letter.
II. RESPONSE TO DEFICIENCY LETTER
Question 1:
SPP explains that, currently, under section 2.22.1(d) of Attachment AE of the Tariff, a CHILL can be curtailed when the sum of the available capacity of its supporting Resources is less than the CHILL.6 SPP proposes to revise its Tariff to provide that a “CHILL will not be curtailed solely due to supporting Resource insufficiency” when its supporting resource takes a Scheduled Resource Outage that is scheduled at least 14 days in advance of the planned start time.7 Please explain whether there are limitations on how long a CHILL can stay online while all or some of its supporting Resources are on a Scheduled Resource Outage or otherwise unavailable to the SPP Integrated Marketplace. Response:
If a CHILL participating under Section 2.22.1(d) of Attachment AE of Attachment AE (“Option 2 CHILL”) of the Tariff has all or some of its supporting Resources on a Scheduled Resource Outage submitted at least 14 Calendar Days in advance, the Option 2 CHILL is limited in its ability to stay online by the duration of the Outage and the results of the system feasibility solve.85 Motions to Intervene were filed by: American Electric Power Service Corporation; Evergy Kansas Central, Inc., Evergy Missouri West, Inc., Evergy Metro, Inc.; Grid Reform; Kansas Electric Power Cooperative, Inc.; Oklahoma Gas and Electric Company; Solar Energy Industries Association; Sunflower Electric Power Cooperative; and Western Farmers Electric Cooperative.6 August Filing at 6.7 Proposed Tariff, Att. AE, § 2.22.2 (Resources Supporting a HILL or CHILL).8 These limitations are specific to the proposed changes to the Resource sufficiency check. The Option 2 CHILL could also be curtailed due to transmission limitations, a Local Reliability Issue, an unfavorable net impact to the Transmission System during system CHILL Curtailments, and Emergency Conditions. See Tariff, Attachment AE, Section 2.22.1(d).
PDF page 3
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 3
Outages for Resources supporting CHILL(s) must be reviewed and approved or denied by the Transmission Provider.9 An Outage request must be accompanied by a reason for the Outage in addition to the planned start and end times.10 To help evaluate Outage requests, SPP uses the Generator Assessment Process (GAP), which projects the availability to schedule generating resource maintenance on an hourly basis.11 Consistent with the treatment of other Resources, SPP did not propose a cap on the maximum length of a Scheduled Resource Outage for an Option 2 CHILL supporting Resource, but the potential length of a Scheduled Resource Outage would be limited operationally by the available maintenance margin MW. If the nameplate capacity of the supporting Resource requesting an Outage exceeds the projected available margin in any hour during the requested period, the request would be denied. While the maintenance margin will be used in evaluating Outages for Option 2 CHILLs supporting Resources, SPP will not consider their availability when calculating the maintenance margin.12 Resources supporting CHILLS do not have a net impact on the system because all Resources supporting CHILLs must only submit Resource Offers sufficient to cover the forecasted withdrawals by the CHILL.13 Consistent with reliability needs of the system, SPP may deny an Outage it previously approved.14 Furthermore, the Market Monitoring Unit may request supporting documentation for the Outage.15
Second, when supporting Resources are not on Outage, to avoid curtailment for supporting Resource insufficiency, Option 2 CHILLs must pass a check which compares the Maximum Economic Operating Limits of its supporting Resources to the CHILL.16 In contrast, CHILLs participating under Section 2.22.1(c) of Attachment AE (“Option 1 CHILLs”) of the Tariff do not have designated supporting Resources and instead undergo
9 Tariff, Attachment AE, Section 3.1.5. See also Southwest Power Pool, Inc. Open Access Transmission Tariff Business Practices, Business Practice 10000 Reliability Coordinator Outage Coordination Methodology for the RTO Footprint, Section 1.1 (“Business Practice 10000”), available at: https://www.spp.org/spp-documents- filings/?id=472252.10 Business Practice 10000, Section 3.2.11 Id., Section 3.6.12 See id, Section 3.6.13 Tairff, Attachment AE, Section 2.22.2(2)(b).14 Tariff, Attachment AE, Section 3.1.5.1.15 Tariff, Attachment AG, Sections 4.6.4 and 8.3.16 Tariff, Attachment AE, Section 2.22.1(d)(1).
PDF page 4
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 4
a system feasibility check, where they may be curtailed pro rata if there is insufficient capacity available to serve the CHILL.17 Under the proposed policy, if the supporting Resources of an Option 2 CHILL are all on a Scheduled Resource Outage submitted at least 14 Calendar Days in advance, the CHILL would functionally be treated as an Option 1 CHILL by the market clearing engine and included in the system feasibility solve that is not limited to supporting Resources.
If at least one of the supporting Resources is available (not on a Scheduled Resource Outage submitted at least 14 Calendar Days in advance), the Option 2 CHILL must pass the following sufficiency check:18
𝑆𝑢𝑚(𝐸𝑐𝑜𝑚𝑎𝑥𝑒𝑠 𝑜𝑓 𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑠𝑢𝑝𝑝𝑜𝑟𝑡𝑖𝑛𝑔 𝑅𝑒𝑠𝑜𝑢𝑟𝑐𝑒𝑠) ≥ 𝐶𝐻𝐼𝐿𝐿 − 𝑠𝑢𝑚(𝐴𝑐𝑐𝑟𝑒𝑑𝑖𝑡𝑒𝑑 𝑀𝑊 𝑜𝑓 𝑆𝑢𝑝𝑝𝑜𝑟𝑡𝑖𝑛𝑔 𝑅𝑒𝑠𝑜𝑢𝑟𝑐𝑒𝑠 𝑜𝑛 𝑃𝑙𝑎𝑛𝑛𝑒𝑑 𝑂𝑢𝑡𝑎𝑔𝑒)
If the Option 2 CHILL fails this check, the CHILL will be curtailed.
Below is an example of potential outcomes of the sufficiency check. Assume there is a 100 MW Option 2 CHILL supported by 100 MW of nameplate wind with 20 MW (20%) of accredited value and 100 MW of nameplate gas with 80 MW of accredited value (80%). The examples below illustrate the check outcomes when the CHILL is forecasting 100 MW of consumption while one Resource is on Outage and the other has varying availability. For example, in the first row the wind Resource is on Outage, meaning the gas Resource must make at least 80 MW available to serve the CHILL to avoid curtailment of the CHILL. In this example, the CHILL is curtailed because only 50 MW of the gas Resource were available, which fails the requirement to be greater than or equal to the CHILL less the accredited MW of the supporting wind Resource (100-20=80).
CHILL
Withdrawal
Resource on
Outage
Accredited
MW on
Outage
Sufficiency
Threshold
Available
Resource
MW
Outcome
100 MW
Wind
20 MW
100-20 = 80 MW
50 MW
CHILL
curtailed
100 MW
Wind
20 MW
100-20 = 80 MW
80 MW
CHILL
Passes
100 MW
Gas
80 MW
100-80 = 20 MW
0 MW
CHILL
curtailed
100 MW
Gas
80 MW
100-80 = 20 MW
30 MW
CHILL
Passes
17 Tariff, Attachment AE, Section 2.22.1(c)(2) and Market Protocols, Section 4.1.11.18 Proposed Tariff, Attachment AE, Section 2.22.2(1)(c).
PDF page 5
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 5
Question 2:
SPP proposes to incentivize Resources supporting CHILLs to be available during Emergency Conditions by allowing them to receive compensation for deferring Scheduled Resource Outages in certain circumstances.19 Specifically, the proposed revisions state that “Scheduled Resource Outages for supporting Resources for a [CHILL] . . . are solely Qualified [for compensation] if, in addition to the criteria in this Section B, the Outage is rescheduled at the request of the Transmission Provider to make the Resource available in Emergency Conditions . . . and the Resource was made available. . . .”20 SPP contends that this is the same compensation offered to other Resources on approved Scheduled Resource Outages.21
a. Please explain whether and, if so, how SPP will consider whether a Resource is supporting a CHILL in its determination of which approved Scheduled
Resource
Outage
it
will
request
to
be
rescheduled.
b Please describe the circumstances in which SPP will request that “the Resource [be made] available in Emergency Conditions.” For example, please clarify whether a Resource supporting a CHILL would only be eligible for
compensation if it rescheduled its approved Scheduled Resource Outage in Emergency Conditions.
c. Please confirm whether the circumstances in which SPP may offer
compensation to a Resource supporting a CHILL are the same as for other Resources. If not, please describe and support that difference.
Response to 2.a:
Outside of Emergency Conditions, SPP would consider if a Resource is supporting a CHILL. This matters because requesting that an Option 2 CHILL supporting Resource reschedule an Outage has little benefit as the Tariff limits the Resource output to the load forecast value of the corresponding CHILL.22 A Resource supporting a CHILL must only submit a Resource Offer sufficient to cover the forecasted withdrawals of the CHILL.23 An Option 2 CHILL may be curtailed if the supporting Resource Offer is less than the
19 August Filing at 8.20 Proposed Tariff, Att. U, § B (Compensation for Generator Owners).21 August Filing at 8.22 Tariff, Attachment AE, Section 2.22.2(2)(b).23 Tariff, Attachment AE, Section 2.22.2(1)(a).
PDF page 6
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 6
forecasted CHILL withdrawal.24 Furthermore, CHILL supporting Resources are not included in calculating maintenance margin in the Generator Assessment Process, as described above, so requesting that CHILL supporting Resource reschedule an Outage would not help accommodate the Outage of a network Resource.
During Emergency Conditions, SPP would not consider whether a Resource is supporting an Option 2 CHILL in its determination of which Scheduled Resource Outage it will request to be rescheduled during Emergency Conditions. In Emergency Conditions, SPP may allow the Resource to exceed the forecasted CHILL withdrawal, so there is more potential benefit to the reliability for SPP to consider.
Response to 2.b:
A supporting Resource for an Option 2 CHILL is only eligible for compensation if it rescheduled its approved Scheduled Resource Outage in Emergency Conditions. The supporting Resource must make itself available by self-committing or setting its commitment status to market or reliability and meet the other requirements for Qualified Outages in Attachment U, Section B of the Tariff. For example, a Qualified Outage must be submitted at least 60 days prior to the start of the scheduled maintenance.25 This proposal only provides compensation for rescheduled Outages during Emergency Conditions because, as explained above, CHILL supporting resources do not support the capacity for Network Resources to take Outages and provides little system reliability benefit outside of those conditions.
Response to 2.c:
All Resources are subject to the criteria in Attachment U, Section B, including Resources supporting a CHILL. SPP’s proposed Tariff changes specify that the requirements for Resources supporting a CHILL are “in addition to the criteria in this Section B.”26 A Resource that is not supporting a CHILL provides two benefits to the system if it reschedules its Outage: (1) it increases the maintenance margin available for other Resources to retain their Scheduled Resource Outage and (2) it is likely to make additional Energy available beyond what would have been available if it had not rescheduled its Outage. A Resource that is not supporting a CHILL is likely to make additional Energy available because it is subject to must offer requirements and associated
24 Attachment AE, Section 2.22.1(d) (“the CHILL must agree to be curtailable (1) when the sum of the available capacity for the supporting Resources is less than the CHILL. . .”).25 Tariff, Attachment U, Section B. 26 Proposed Tariff, Attachment U, Section B.
PDF page 7
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 7
charges if the requirements are not satisfied.27 Therefore, the incentive exists for the Generator Owner to offer the Resource to the market. By contrast, outside of Emergency Conditions, a Resource supporting a CHILL provides neither benefit: it is not included in the maintenance margin calculation and any Energy it produces is offset by the withdrawals from the CHILL.
Accordingly, the proposed revisions include two additional conditions for compensation that apply only to Resources supporting a CHILL. A Resource supporting a CHILL is only eligible for compensation if it has (1) rescheduled its approved Scheduled Resource Outage in Emergency Conditions and (2) made itself available. First, as described above, there is little benefit to the system if a Resource supporting a CHILL reschedules its Outage because the Outage is not included in the maintenance margin calculation. However, a Resource supporting a CHILL does provide a benefit to the system when it injects Energy beyond the needs of the CHILL, which may only occur during Emergency Conditions.
As described above, Resources supporting CHILLs must only submit Resource Offers sufficient to cover the forecasted withdrawals by the CHILL.28 This limitation exists because the supporting Resource interconnected through the High Impact Large Load Generation Assessment (HILLGA) and is subject to a High Impact Large Load Generator Interconnection Agreement (HILLGIA).29 The HILLGIA provides that the Transmission Provider may take whatever actions necessary during Emergency Conditions to
(i) preserve public health and safety, (ii) preserve the reliability of the Transmission System or Transmission Owner’s Interconnection Facilities, (iii) limit or prevent damage, and (iv) expedite restoration of service.30 The CHILL must also agree to be curtailable in the event of Emergency Conditions.31 Due to the limitations of the HILLGIA, SPP may only request that the Resources supporting CHILLS exceed the forecasted withdrawals by the CHILL during Emergency Conditions. Additionally, Resources supporting Option 2 CHILLs may also have Load Limited Resource Interconnection Service, which limits their output to the forecast value of the corresponding CHILL, except when directed by the
27 Tariff, Attachment AF, Section 3.928 Tairff, Attachment AE, Section 2.22.2(2)(b).29 See Submission of Tariff Revisions to Add the High Impact Large Load Processes and High Impact Large Load Generation Assessment of Southwest Power Pool, Inc., Docket No. ER26-247-000 (October 24, 2025) (“HILL Filing”) for a more thorough discussion regarding the HILLGA and HILLGIA.30 Tariff, Attachment BB, Appendix 2, Article 13.5.31 Tariff, Attachment AE, Section 2.22.1(c).
PDF page 8
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 8
Transmission Provider to mitigate Emergency Conditions.32 Because a Resource supporting an Option 2 CHILL with LLRIS is only eligible to produce more than the CHILL’s forecasted withdrawals during Emergency Conditions, the Transmission Provider may only request that the Resource inject Energy onto the Transmission System during Emergency Conditions. Second, because a Resource supporting a CHILL is not subject to must offer requirements that would normally be relied upon to incent a Market Participant to make a Resource available to the market, SPP requires the Resource supporting a CHILL to be made available to receive compensation.
Therefore, compensation under Attachment U of the Tariff is limited to the circumstances in which a Resource supporting a CHILL provides a benefit to the system. Providing compensation under these parameters provides incentives for the Resource supporting a CHILL to remain available during Emergency Conditions to support system reliability while maintaining equitable treatment between Resources supporting CHILLs and Resources that are not supporting CHILLs.
III. CONCLUSION
For all of the reasons discussed in this instant filing, the Commission should accept the Tariff revisions submitted in this proceeding as just and reasonable.
Respectfully submitted,
/s/ Emon Mahony
Emon Mahony
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
(501) 482-2506
emahony@spp.org
Attorney for Southwest Power Pool, Inc.
32 Tariff, Attachment AE, Section 2.22.2(2)(b).
PDF page 9
CERTIFICATE OF SERVICE
I hereby certify that I have on this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated this 19th day of November, 2026.
/s/ Michelle Harris
Michelle Harris
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
(501) 614-3200