ER26-3591-001 · 2026-11-19 · Southwest Power Pool, Inc.

Deficiency Response - Modify the CHILL Policy to Accommodate Planned Outages

Text extracted from the eLibrary original (SHA-256 84c133175b25609d…). Download the original from the official source.

Contents · 3 sections
  1. I. BACKGROUND p. 1
  2. II. RESPONSE TO DEFICIENCY LETTER p. 2
  3. III. CONCLUSION p. 8

Topics in the text: Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Reese Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 RE: Southwest Power Pool, Inc., Docket No.
Read this passage

I. BACKGROUND

printed heading

Electronic Tariff Filings, 130 FERC ¶ 61,047, at PP 3-8 (2010) (stating an amendment filing must include at least one tariff record even though a tariff revision might not otherwise be required). 3 Submission of Tariff Revisions to Modify the Conditional High Impact Large Load Policy to Accommodate…
Read this passage

II. RESPONSE TO DEFICIENCY LETTER

printed heading · Topic match: Reliability and curtailment

For example, in the first row the wind Resource is on Outage, meaning the gas Resource must make at least 80 MW available to serve the CHILL to avoid curtailment of the CHILL.
Read this passage

III. CONCLUSION

printed heading

CONCLUSION For all of the reasons discussed in this instant filing, the Commission should accept the Tariff revisions submitted in this proceeding as just and reasonable.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this 19th day of November, 2026. /s/ Michelle Harris Michelle Harris Southwest Power Pool, Inc. 201 Worthen Drive Little Rock, AR 72223-4936 (501) 614-3200