ER27-577-000 · 2026-11-19 · Southwest Power Pool, Inc.
Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs
PDF page 1
November 19, 2026The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426
Re:
Southwest Power Pool, Inc., Docket No. ER27-____-000
Submission of Tariff Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs; Related to Docket No. EL26-68-000
Dear Secretary Reese:
Pursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Section 35.13 of the Federal Energy Regulatory Commission’s (“Commission”) Regulations, 18 C.F.R. § 35.13, Southwest Power Pool, Inc. ("SPP"), as authorized by its independent Board of Directors, submits revisions to its Open Access Transmission Tariff (“Tariff”)1 in response to the Commission’s June 18, 2026, order instituting a proceeding under FPA Section 206 in Docket No. EL26-68-000 (“Show Cause Order”).2 The proposed revisions establish a new Load Safe Harbor Limit (“LSHL”) for the costs of Network Upgrades identified through the transmission study processes outlined in Attachments AQ, AX, and BA of the Tariff.3 As directed by the Show Cause Order, SPP states explicitly that this proposal is submitted under FPA Section 205, explains which of the Commission’s directives this filing addresses and how it resolves them, explains how the proposal avoids disrupting existing commercial arrangements, and identifies a reasonable effective date.4
The revisions in this filing respond directly to the Commission’s preliminary findings that the Tariff should contain mechanisms or provisions that require minimum
1 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume No. 1. References in this filing to "Tariff" refer to the version of SPP’s Tariff currently in effect. "Proposed Tariff" refers to a version reflecting the revisions proposed in this filing. All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff.2 Sw. Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (“Show Cause Order”).3 The revisions proposed herein are referred to, for purposes of this transmittal letter, as the “Load Safe Harbor Limit Revisions.”4 Show Cause Order at P 32.
PDF page 2
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 2
financial contributions and financial security sufficient to mitigate the risk of cost shifting among transmission customers if a large load does not materialize as planned.5 SPP respectfully requests that the Commission find the proposed revisions just and reasonable and not unduly discriminatory or preferential, accepting them effective February 17, 2027, and finding that they resolve the cost-shifting concerns identified in the Show Cause Order.
I. SUMMARY OF FILING
The Show Cause Order commended SPP’s “bold and proactive steps” to
integrate large loads. It recognized that SPP’s High Impact Large Load (“HILL”) process already provides an enhanced study framework for Eligible Customers taking transmission service on behalf of large loads.6 Notwithstanding this, the Commission preliminarily found “that SPP’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service.”7 The Commission expressed concern that there is no mechanism to help ensure that Eligible Customers taking service on behalf of large loads bear the risk and are ultimately responsible for costs incurred to provide transmission service, including the cost of Network Upgrades.8
To address this concern, SPP proposes the LSHL for Network Upgrades needed to add or modify load delivery points studied under the Tariff. The LSHL mitigates the risk of cost shifting associated with the connection of large loads by requiring the Transmission Customer to pay, and to secure with financial security, all delivery point Network Upgrade costs above a threshold—creating an obligation that correlates directly with the level of cost resulting from the delivery point request and does not depend on whether, when, or at what level the load materializes. The LSHL preserves a defined level of rate support for Network Upgrades approved by SPP (i.e., “Base Plan funding”) for load delivery points while directly assigning costs above that level to the requesting Transmission Customer. Because the LSHL operates through the Tariff and SPP’s existing Commission-accepted cost allocation framework, it applies uniformly to every delivery point request, ties the customer’s obligation to the actual cost of the Network Upgrades identified in SPP’s studies, and preserves SPP’s existing regional
5 Id. at PP 59-65.6 Id. at P 2.7 Id. at P 59.8 Id. at P 62.
PDF page 3
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 3
cost allocation methods, which the Show Cause Order expressly did not intend to disturb.9
This filing, which addresses the Commission’s directive regarding mitigation of the risk of cost shifting, is one part of SPP’s comprehensive response to the Show Cause Order. The filings addressing the Show Cause Order’s remaining directives are identified in Section IV.E.
II. BACKGROUND
A. The HILL Process
On January 14, 2026, the Commission accepted SPP's Tariff revisions establishing the HILL study process in Attachment BA and the High Impact Large Load Generation Assessment ("HILLGA") in Attachment BB. Those revisions: (1) defined HILLs as a new category of load; (2) established enhanced study requirements for HILLs, including the HILL Delivery Point Study ("HDPS"), to enable SPP to assess the reliability impacts of a HILL on the Transmission System; and (3) imposed ongoing operational requirements on HILLs to ensure the continued reliable operation of the Transmission System. The Commission found the HILL process to be “a just and reasonable approach for integrating transmission customers’ new large loads onto SPP’s transmission system in a reliable manner.”10
B. The Show Cause Order
In the Show Cause Order, the Commission adopted SPP’s HILL definition as its definition of “large load.”11 It then preliminarily found that the Tariff appears unjust and unreasonable in four categories. The Commission directed SPP and the Transmission Owners either to show cause why the Tariff remains just and reasonable or to explain what changes would remedy the identified concerns.12 The Commission strongly encouraged SPP to address these issues through FPA Section 205 filings.13
C. Abeyance
On August 3, 2026, SPP and the Transmission Owners jointly moved to hold Docket No. EL26-68-000 in abeyance through November 20, 2026, so SPP could
9 Id. at P 63.10 Sw. Power Pool, Inc., 194 FERC ¶ 61,031 at P 61 (2026) (“HILL Order”).11 Show Cause Order at n.2.12 Id. at P 3.13 Id. at P 32.
PDF page 4
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 4
develop Section 205 filings through its stakeholder process.14 SPP described the anticipated content of those filings in its Abeyance Motion, including the revisions submitted here.15 On August 14, 2026, the Commission granted the Abeyance Motion and set a due date of November 20, 2026, for SPP’s response to the Show Cause Order.16
D. Stakeholder Process and Approval
The LSHL revisions were reviewed through SPP’s stakeholder process, including meetings of the Regional Tariff Working Group (“RTWG”) on September 24, 2026;17 Cost Allocation Working Group (“CAWG”) on October 1, 2026;18 Cost Control and Allocation Review and Evaluation Team (“CARE Team”) on October 7,
14 Joint Movants’ Amended Motion to Hold Section 206 Proceeding in Abeyance of Southwest Power Pool, Inc., et al., Docket No. EL26-68-000 (Aug. 3, 2026) (“Abeyance Motion”).15 Id.16 Sw. Power Pool, Inc., 196 FERC ¶ 61,128 (2026) (“Abeyance Order”). 17 The RTWG did not approve the LSHL in its vote dated October 12, 2026. See the votes of the RTWG included in the RR814 Recommendation Report posted at: https://www.spp.org/Documents/77866/rr814%20(6).zip (contained in zip file “RR814 Load Safe Harbor Limit”). The RTWG develops, implements and oversees SPP’s Open Access Transmission Tariff. The RTWG provides input on regulatory or implementation issues not specifically covered by the tariff and issues where there may be conflicting or differing interpretations of the tariff. 18 See CAWG Meeting Minutes, dated October 1, 2026, at Agenda Item 11 posted at: https://www.spp.org/documents/77976/cawg%20minutes%2020261001.pdf. The CAWG reports to the Regional State Committee and assists the RSC in addressing matters for which the RSC has primary responsibility as defined in Section 7.2 of the SPP Bylaws. In addition, the CAWG will assist the RSC in addressing any other issues as requested by the RSC. The CAWG approved a motion which stated “The [CAWG] recommends the Regional State Committee approve RR814 – Load Safe Harbor Limit, which includes a load safe harbor limit of $21,250,000 for load interconnection of 50MW or larger.”. The CAWG approved by a vote of six (6) in favor, four (4) against, and five (5) abstentions.
PDF page 5
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 5
2026;19 Markets and Operations Policy Committee (“MOPC”) on October 13, 2026;20 and Regional State Committee (“RSC”) on November 16, 2026.21
19
See CARE Team Meeting Minutes, dated October 7, 2026, at Agenda Item 7 posted at:
https://www.spp.org/documents/78112/care%20team%20minutes%2020261007.pdf. The CARE Team serves as a cross-functional leadership body to review, evaluate, assess, and recommend refinements or alternatives to the current transmission cost controls and cost allocation methodologies. The CARE Team’s recommendations are intended to increase confidence that SPP’s processes produce efficient cost-effective results and that costs are equitably allocated commensurate with expected benefits received, while maintaining fiscal discipline necessary to support infrastructure investment that meet regional reliability needs. The CARE Team approved the following motion by a vote of fourteen (14) in favor and two (2) abstentions: the CARE Team approves RR814 – Load Safe Harbor Limit, as presented, and with the following changes: Make the Load Safe Harbor Limit applicable only to delivery point additions or modifications that are requested for study on or after the Tariff effective date established by FERC; and limit direct assignment resulting from the Load Safe Harbor Limit to no more than 20 years, with recovery of the revenue requirement subsequently reverting to Base Plan Upgrade cost allocation.”
20
See MOPC Meeting Minutes, dated October 22, 2026, at Agenda Item 3(d) posted
at:
https://www.spp.org/Documents/78127/MOPC%20Mtg%20Minutes%20and
%20Ballots%2020261014.zip. The MOPC is responsible, through its
designated Organizational Groups, for developing and recommending policies and procedures related to the technical operations for the company in accordance with its scope as approved by the Board of Directors. The MOPC failed to pass any motion related to the LSHL.
21
See RSC Meeting Materials, dated November 16, 2026, at Agenda Item 7A posted at: https://spp.org/spp-documents-filings/?id=20623. The meeting minutes will be posted that this location when they become available. The RSC provides collective state regulatory agency input on matters of regional importance related to the development and operation of bulk electric transmission. The SPP RSC is comprised of retail regulatory commissioners from agencies in Arkansas, Arizona, Colorado, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas, Utah and Wyoming. The RSC approved the following motion by a vote of fourteen (14) in favor, one (1) against, and one (1) abstention: “The Regional State Committee approves RR814 - Load Safe Harbor Limit consistent with the CARE Team recommendation, as amended. The RSC further adopts an action item for the Cost Allocation Working Group to review the Load Safe Harbor Limit amounts annually and report to the RSC if the CAWG recommends that a prospective adjustment of the limits be filed with FERC. The period for direct assignment of costs in excess of the Load Safe Harbor Limit shall not exceed forty (40) years.”
PDF page 6
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 6
SPP’s Commission-approved Bylaws expressly recognize state regulatory authority and assign the RSC specific responsibilities within SPP. Section 7.1 of the SPP Bylaws provides that “[n]othing in the formation or operation of SPP as a FERC- recognized regional transmission organization is in any way intended to diminish existing state regulatory jurisdiction and authority.”22 The SPP Bylaws specifically grant the RSC authority over cost allocation proposals in SPP. The Bylaws state, “[t]he RSC has primary responsibility for determining regional proposals and the transition process in the following areas: (a) whether and to what extent participant funding will be used for transmission enhancements… [.]”23 In turn, as the RSC reaches decisions on cost allocation methodologies, SPP will make the requisite filings at the Commission. 24 Because the LSHL determines the extent to which delivery point Network Upgrade costs are directly assigned versus being regionally allocated, it falls squarely within the RSC’s authority.
In recognition of the RSC authorities under Section 7.2 of the SPP Bylaws, the SPP Board of Directors appropriately approved the filing of these Tariff revisions, as approved by the RSC, to create the LSHL.25
III. CURRENT
COST
ALLOCATION
FOR
DELIVERY
POINT
NETWORK
UPGRADES
AND
EXISTING
SAFE
HARBOR
PROVISIONS
A. SPP Transmission Service Process
As described in Section II.A above, the Commission accepted SPP’s HILL and HILLGA Tariff revisions on January 14, 2026.26 SPP processes all load additions and modifications for long-term firm SPP transmission service, including HILLs, using its existing Attachment AQ and/or Attachment AX study processes.27 However, for
22 See Bylaws at Section 7.1. 23 See Bylaws at Section 7.2. 24 Id.25 See Board of Directors & Members Committee Meeting Materials, dated November 17, 2026, at Agenda Item 3.2.1 posted at: https://www.spp.org/spp-documents- filings/?id=18449. The meeting minutes will be posted that this location when they become available. 26 See HILL Order.27 Through Attachment AQ, any existing customers with a sufficient level of existing Designated Resources may obtain firm transmission service for the modification of an existing delivery point or for the creation of a new delivery point. Under Attachment
PDF page 7
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 7
HILLs, SPP and the applicable Transmission Owner(s) simultaneously conduct additional studies under Attachment BA to ensure that the unique operational characteristics of HILLs are considered when evaluating the addition of a HILL to the Transmission System, and that SPP has mechanisms in place to maintain reliable operation of the Transmission System.28 These ongoing operational requirements under Attachment BA, including the addition of certain equipment, ensure that SPP can continue to manage the Transmission System while accommodating the unique operational demands and characteristics of HILLs.29
Network Upgrades identified as necessary to accommodate load additions or modifications through Attachment AQ are Base Plan Upgrades, meaning that their costs are allocated through rolled-in regional, subregional, and/or zonal rates among SPP Transmission Customers pursuant to the criteria in the Tariff (“Base Plan Funded”).30 Network Upgrades identified in the Attachment AX process are directly assigned to the Transmission Customer until it receives Long-Term Service for the planned generation studied under Attachment AX, at which point the remaining costs are Base Plan Funded.31 Thus, the Commission has already accepted direct assignment as a just and reasonable means to protect other customers from delivery point Network Upgrade costs while load-related uncertainty persists. Currently, there is no limit to the amount of Network Upgrade costs, quantified as either dollars per megawatt (“MW”) or total cost, that can be Base Plan Funded for a delivery point request, regardless of the costs relative to the load requested or whether the load materializes. This is precisely the gap the Show Cause Order identified.
B. Original Safe Harbor Provisions
SPP’s original cost allocation methodology, which the Commission accepted in 2005 (“Base Plan Funding Order”),32 included the Safe Harbor Provisions33 to limit the
AX, existing customers may receive provisional study of a new or modified delivery point using planned generation, instead of existing Designated Resources.
28 Tariff, Attachment BA, Sections 2.1.3.4 and 2.1.3.5. 29 Tariff, Attachment BA, Section 2.2.30 Tariff, Attachment J, Section III.A.31 Tariff, Attachment J, Section V.F; Sw. Power Pool, Inc., 193 FERC ¶ 61,018 (2025).32 See Sw. Power Pool, Inc., 111 FERC ¶ 61,118, order on reh’g, 112 FERC ¶ 61,319 (2005).33 As used herein, the term “Safe Harbor Provisions” refers to the criteria set forth in Tariff Attachment J, Section III.B, which identify the conditions for Network Upgrade costs associated with Designated Resources to be classified as Base Plan Upgrade costs
PDF page 8
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 8
Network Upgrade costs allocated to the SPP Region. Specifically, the Safe Harbor Provisions relate to costs for Network Upgrades associated with designating a generation resource.34 Under the currently applicable set of Safe Harbor Provisions, any Network Upgrades identified as needed because of the designation of a resource are eligible to be Base Plan funded if the following conditions are met: (1) the Transmission Customer’s commitment to the Designated Resource has a duration of at least five years; (2) the new and existing Designated Resources of the Transmission Customer do not exceed the higher of (a) 125% or (b) the sum of 110% and the current Planning Reserve Margin percentage set forth in the SPP Planning Criteria;35 and (3) if the new Designated Resource is a wind generation plant, the sum of the requested capacity for the new wind Designated Resource and the reserved capacity for the Transmission Customer’s existing wind Designated Resources do not exceed 20% of the customer’s projected system peak responsibility (“Wind/Load Condition”).36 If the conditions above are met, or a waiver is requested and received pursuant to Section III.C of Attachment J, aggregate costs for Network Upgrades associated with designating a generation resource that are less than or equal to $180,000 per MW (“Safe Harbor Cost Limit”) are eligible for Base Plan funding (i.e., rolled into generally applicable rates under Schedule 11 of the Tariff). The Safe Harbor Cost Limit was designed to provide a check on the level of investment required to support the transmission service request. This limitation provides an incentive to locate generation closer to load and closer to adequate network transmission infrastructure. In the Base Plan Funding Order, the Commission approved the Safe Harbor Provisions, but the Commission directed SPP to assess average costs of all Network Upgrades as part of its biennial planning process and work with stakeholders and the RSC to evaluate the effectiveness and accuracy of the $180,000 per MW Safe Harbor
eligible for cost allocation. These conditions include the Safe Harbor Cost Limit of $180,000 per MW, which is specified in Section B.1.d.i and Section B.3 of Attachment J.
34 Safe Harbor Provisions are not applicable to transmission upgrades approved for purposes other than resource designation.35 The “higher of (a) 125% or (b) the sum of 110% and the current Planning Reserve Margin percentage set forth in the SPP Planning Criteria” was not part of the original Safe Harbor Provisions accepted by the Commission in the Base Plan Funding Order. The cap originally accepted in 2005 was “125% of the Transmission Customer’s projected system peak responsibility” and the cap was subsequently expanded to its above form by the Commission in 2024. Sw. Power Pool, Inc., 188 FERC ¶ 61,213 (2024).36 This Wind/Load Condition was not included in Safe Harbor Provisions accepted by the Commission in the Base Plan Funding Order. It was subsequently added to the Safe Harbor Provisions and approved by the Commission in 2009. See Sw. Power Pool, Inc., 127 FERC ¶ 61,283 (2009).
PDF page 9
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 9
Cost Limit.37 The Commission directed SPP to file an annual report to include: (1) average costs of new Network Upgrades and the effectiveness of the Safe Harbor Cost Limit threshold; (2) an “unintended consequences” review (now addressed every six years as a consideration in a broad cost allocation review); and (3) SPP’s disposition of requests for waiver of the Base Plan funding eligibility conditions and the Safe Harbor Cost Limit in the Safe Harbor Provisions.38 Since 2006, SPP has complied with this yearly filing requirement.39
The Load Safe Harbor Limit proposed in this filing is modeled after the current Safe Harbor Cost Limit. The Load Safe Harbor Limit, if approved, establishes a direct link to cost causation, with the entity for whom the Network Upgrades were built bearing any excess costs.
IV. DESCRIPTION OF AND JUSTIFICATION FOR THE LOAD SAFE
HARBOR LIMIT REVISIONS
A. Show Cause Order Requirements
As noted above, the Show Cause Order preliminarily found “that SPP’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service.”40 The Commission further preliminarily found that the minimum contribution required of Transmission Customers on behalf of large loads “should be based on the level of jurisdictional transmission service (in MW) requested...”41 The Commission also preliminarily found that the cost recovery mechanism should “include a credit support (or other financial security) requirement sufficient to secure the obligations of the Eligible Customer taking transmission service on behalf of a large load to pay the amounts owed…”42
B. Load Safe Harbor Limit Proposal
SPP proposes to establish a LSHL for Network Upgrades needed to add or modify load delivery points studied under Attachment AQ, Attachment AX, or
37 Base Plan Funding Order at P 51.38 Id.39 See Docket No. ER05-652-000.40 Show Cause Order at P 59.41 Id. at P 65. 42 Id.
PDF page 10
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 10
Attachment BA of the Tariff.43 The LSHL will require Transmission Customers to pay for any Network Upgrade costs identified in the SPP transmission service process that exceed the lesser of $25 million or $500,000 per MW of transmission service requested.44 Zonal Reliability Upgrades, which are not Base Plan Upgrades, are excluded. Any cost above the LSHL will be directly assigned to the Transmission Customer that requested the delivery point addition or modification.45 The directly assigned amount will be recovered as a Transmission Owner-calculated revenue requirement, based on the Transmission Owner’s standard revenue requirement methodology, for no more than forty (40) years.46 Thereafter, any remaining revenue requirement will be allocated as a Base Plan Upgrade.47 The LSHL will apply to delivery point addition or modification requests submitted under Attachments AQ, AX, or BA on or after the effective date accepted by the Commission.48
Any Transmission Customer responsible for directly assigned Network
Upgrade costs through application of the LSHL will be required to provide financial security.49 The level of required security will be tied to the amount of direct assignment and will be reduced as the associated Network Upgrade assets depreciate.50 A claim on the financial security will be necessary only if the entity paying the direct assignment defaults.51 The period over which the security will be held is the term of payment for the directly assigned cost.52 Therefore, the financial security arrangements to protect against the risk of cost shifting will have clearly defined parameters for amount, duration, and trigger of any potential claim on the security. This type of financial security arrangement is administered under the Tariff for existing forms of direct assignment, such as charges for Service Upgrades and Sponsored Upgrades.5343 Proposed Tariff, Attachment J, Section V.G.44 Id.45 Id.46 Proposed Tariff, Attachment J, Sections V.F and V.G.47 Id.48 Proposed Tariff, Attachment J, Section V.G.49 Proposed Tariff, Attachment AQ, Section 4.0 and Attachment AX, Section 3.0.50 Id.51 Id.52 Id.53 Tariff, Attachment J, Section V and Attachment Z1, Section III.
PDF page 11
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 11
The Commission’s large load Show Cause Order emphasizes mitigation of the risk of cost shifting, including a specified minimum financial contribution and sufficient financial security to reduce cost shifting risk when forecasted load does not develop as planned. This proposal directly addresses those concerns by retaining a basic level of load interconnection service that is funded by the SPP Region and directly assigning costs exceeding that level, backed by financial security, to the customer whose transmission service request causes the upgrades. This proposal establishes a direct link to cost causation, with the entity for whom the Network Upgrades were built bearing any excess costs.
The proposed limit of $500,000 per MW is informed by two data sets, which are attached to this transmittal letter as Exhibit 1 and Exhibit 2. Exhibit 1 is an affidavit from Natasha Henderson with an attached spreadsheet outlining the upgrade costs resulting from Notifications to Construct (“NTCs”) that have been issued by SPP through its delivery point study processes from 2012 to 2026, which includes for each load request (1) the load amount; (2) the total cost of the Network Upgrades identified;
(3) the cost per MW of load requested; (4) the approximate date when the Network Upgrades are put into service; and (5) the cost per MW percentile compared to the other requests included on Exhibit 1. Exhibit 2 is an affidavit from Don Frerking with an attached spreadsheet that includes transmission gross and net plant values, both in total and on a per-MW basis, for the SPP Region. The transmission plant per-MW values were derived from: (1) gross and net plant values in individual Transmission Owner formula rate template updates (effective as of August 2026); and (2) transmission revenue requirement and zonal load information sourced from the August 2026 Revenue Requirements and Rates (“RRR”) file.54
Historical delivery point studies requiring Network Upgrades showed
approximate costs of $177,000 per MW at the median, $378,000 per MW at the 75th percentile, and $1.018 million per MW at the 95th percentile. The estimated investment in transmission facilities across the entire SPP Region is approximately $422,000 per MW on a net plant basis (reduced for depreciation) and $572,000 per MW on a gross plant basis. The value of the proposed per-MW limit falls between those system-wide investment measures and between the historical 75th and 95th percentiles for delivery point requests. The percentiles from this history of requests that required Network Upgrades suggest that the majority of future delivery point requests requiring such upgrades will remain under the proposed per-MW cost cap, thereby resulting in full Base Plan funding at an average cost level for delivery points which are not HILLs. Also, it should be noted that a large majority of delivery point requests do not require issuance of a Notification to Construct for any Network Upgrade. In addition to protecting the region from bearing excess costs associated with load interconnection requests, the proposed per-MW limit provides an incentive for the requesting Transmission Customer to select cost effective interconnection locations, which is
54 The SPP RRR files can be found at the following link: https://www.spp.org/spp- documents-filings/?id=18251.
PDF page 12
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 12
consistent with emphasis in the Show Cause Order on cost-effective solutions.55 For load requests that are smaller than the 50 MW threshold for a HILL connecting above 69 kV, these limits will ensure that new load receives Base Plan funding beyond the median level of transmission investment for adding or modifying delivery points, while any costs above the $500,000 per MW level are assigned to the requesting Transmission Customer. For delivery point requests smaller than 50 MW, only those entailing excessive per-MW cost (i.e., above roughly the 85th percentile level) are charged a direct assignment. Although upgrade costs, transmission rates, and transmission rate impacts vary significantly between SPP pricing Zones due to differences among Schedule 9 and Schedule 11 zonal revenue requirements, the proposed limit value of $500,000 per MW is a level that can be supported from an overall system average rate perspective. With this limit in place, Network Upgrades for delivery points can be added without putting a substantial amount of upward pressure on average transmission service rates due to the delivery point changes alone.56 Further, the fact that this proposed limit exceeds the system-wide net transmission plant value of $422,000 per MW provides allowance for some escalation in the system-wide average due to inflation between the date of application of the LSHL in the Attachment AQ or AX study and the actual in-service date of the upgrade(s) when the cost effect will be realized in transmission rates.
The proposed framework of a per-MW limit coupled with an aggregate limit ensures that the focus is on mitigation of cost risk. An aggregate cap is needed because a per-MW limit alone could leave the SPP Region, and its ratepayers, potentially exposed to very large cost burdens. For example, with a $500,000 per MW limit, a 1,000 MW request could qualify for $500 million of Base Plan funding if there were no aggregate cap. Further, a per-MW limit without an aggregate limit could incentivize the submission of inflated delivery point load amounts in some situations. The proposed $25 million aggregate cap for the LSHL is calculated using the 50 MW HILL definition threshold57 for interconnections above 69 kV (i.e., 50 MW multiplied by $500,000) and provides a meaningful, regional funding level. Tying to the Tariff’s HILL definition (and to the Show Cause Order’s adopted large load
55 See generally, Show Cause Order at PP 44-45.56 Although this filing is focused on cost responsibility for Network Upgrades resulting from delivery point changes, it should be noted that long-term incremental costs associated with load growth are broad and are driven through additional planning processes including consolidated planning, generator interconnection, and transmission service. Through the CARE Team, SPP and its stakeholders worked for the past year on development of multiple policy-level proposals to adjust SPP’s cost allocation framework in view of rapid load growth. These proposals will be further refined in coming months through SPP’s stakeholder processes.57 See generally, Show Cause Order at P 16 (the Commission points out its previous approval of the HILL definition).
PDF page 13
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 13
definition) by means of an aggregate cost cap, rather than linking applicability of the limit mechanism strictly to a load threshold (e.g., 50 MW), is a structure that avoids incentivizing Transmission Customers to submit delivery point requests below such a MW threshold regardless of the amount of load actually anticipated.
Table 1 below outlines an example of how the Load Safe Harbor Limit would be applied to Network Upgrades identified under Attachment AX, Attachment AQ, or Attachment BA.
Table 1:
The proposed LSHL results in a division of cost responsibility for the delivery point end of a transmission service path between a portion subject to regional cost allocation and a portion directly assigned to the requesting Transmission Customer. This is generally consistent with the Tariff’s current treatment of the resource end of the transmission service path (i.e., the existing Safe Harbor Provisions), which incorporates a division of cost responsibility between a portion subject to regional cost allocation and a portion assigned to the requesting Transmission Customer by means of the Safe Harbor Cost Limit and other qualifying criteria for regional funding as set forth in Section III.B of Attachment J. This is a means to recognize the benefits that Network Upgrades can provide to other Transmission Customers in the Zone, Subregion, or even across the SPP Region while still applying the cost-causation principle through direct assignment of any cost above the LSHL.
Those Transmission Customers who bear directly assigned costs for delivery point Network Upgrades as a result of the Load Safe Harbor Limit will be eligible for compensation through allocation of Candidate Incremental Long-Term Congestion Rights, as provided under Attachment Z2 of the Tariff.
C. The Load Safe Harbor Limit Resolves the Show Cause Order’s Cost
Recovery Directive
As required by the Show Cause Order, the proposed LSHL specifically
mitigates the cost risks to existing Transmission Customers by requiring a minimum contribution by Transmission Customers taking transmission service on behalf of the large loads that impose costs above the LSHL. The per-MW component of the proposed LSHL is based on the level of SPP transmission service that is requested by the Transmission Customer and the aggregate cap component of the proposed LSHL is based on an amount corresponding to the 50 MW threshold for a HILL. As a result, the
PDF page 14
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 14
amount of potential contribution for large loads varies directly with the cost created by the load request, a cost level which is driven primarily by the MW amount requested.58 The proposed framework also requires Transmission Customers taking transmission service on behalf of large loads to provide a sufficient contribution to ensure that large loads interconnecting to the SPP Transmission System are not unduly burdening other Transmission Customers with costs caused by such interconnection.59 Lastly, the Load Safe Harbor Limit Revisions require the Transmission Customer taking service on behalf of a large load to provide sufficient security to back its obligation to pay the amounts that are owed.60 The directly assigned obligation is a fixed payment that does not depend on whether, when, or at what level the load is energized. Payments begin when the Transmission Owner establishes a revenue requirement for the upgrade, addressing the timing concern in Paragraph 65 of the Show Cause Order; and directly assigned amounts are excluded from the Base Plan Upgrade revenue requirements charged to other customers. This is the kind of “other just and reasonable method[]” the Commission invited.61
Under FPA Section 205, SPP must show that its proposal is just and reasonable. It need not show that the proposal is the only reasonable approach or that it is more reasonable than the alternatives.62 The LSHL meets this burden. As described above, the LSHL provides for a just and reasonable, and not unduly discriminatory, approach for satisfying the Commission’s concern outlined in the Show Cause Order, and the Commission should accept it.
D. Annual Load Safe Harbor Limit Annual Filing
As described above in Section III.B, the Commission, in the Base Plan Funding Order, directed SPP to assess average costs of all Network Upgrades as part of its biennial planning process and work with stakeholders and the RSC to evaluate the effectiveness and accuracy of the $180,000 per MW Safe Harbor Cost Limit.63 The Commission directed SPP to file an annual report to include: (1) average costs of new Network Upgrades and the effectiveness of the Safe Harbor Cost Limit threshold; (2) an “unintended consequences” review (now addressed every six years as a consideration in a broad cost allocation review); and (3) SPP’s disposition of requests
58 Id. at P 65.59 Id.60 Id.61 Id.62 See, e.g., Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984); OXY USA, Inc. v. FERC, 64 F.3d 679, 692 (D.C. Cir. 1995).63 Base Plan Funding Order at P 51.
PDF page 15
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 15
for waiver of the Base Plan Funding eligibility conditions and the Safe Harbor Cost Limit in the Safe Harbor Provisions.64
If directed by the Commission to do so here, SPP is willing to annually assess the average costs of all Network Upgrades from SPP’s delivery point studies and average costs from SPP Region transmission plant values and to work with the RSC and stakeholders to evaluate the effectiveness and accuracy of the proposed LSHL. SPP would also be willing to add this updated information regarding average costs of all Network Upgrade from SPP’s delivery point studies and average costs from SPP Region transmission plant values to its annual Safe Harbor Cost Limit filing for informational purposes.
Additionally, as part of the RSC’s approval of the LSHL, the RSC directed the CAWG to review the Load Safe Harbor Limit amounts annually and report to the RSC if the CAWG recommends that a prospective adjustment of the limits be filed with the Commission. This is a similar action item that the CAWG currently has for its annual review of the designated resource Safe Harbor Cost Limit.
E. Directives Addressed in Separate Filings
This filing does not address the remaining Show Cause Order directives. SPP is addressing them in the following separate filings:
• HILL Transmission Service Revisions and Non-Transmission Facility
Revisions (the “Combined Filing”);
• Price Adaptive Load Service (PALS); and
• SPP’s response to the Show Cause Order in Docket No. EL26-68-000,
which addresses, among other things, transmission and ancillary service rates for co-located load.
SPP respectfully requests that the Commission consider this filing together with the above filings as SPP’s response to the Show Cause Order.
V. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS
The Show Cause Order directs that any Section 205 filing explain how the proposal will avoid disrupting existing commercial arrangements and identify a reasonable effective date.65 The proposed LSHL provisions are designed to apply only to delivery point requests submitted for study on or after the effective date accepted by the Commission. This will allow Transmission Customers and their large load customers sufficient time to incorporate and appropriately reference the impacts of the LSHL provisions in their agreements prior to finalization. The LSHL will not affect
64 Id.65 Show Cause Order at PP 5, 32, 92.
PDF page 16
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 16
existing commercial arrangements that are based on currently ongoing or past delivery point studies.
VI. PROPOSED TARIFF CHANGES AND JUSTIFICATIONS
A. Part I, Section 1, Definitions
SPP proposes to modify two existing definitions and add a new definition to Part I, Section 1 of the Tariff as follows:
i. 1 Definitions B
Base Plan Upgrades: Those upgrades included in and constructed pursuant to the SPP Transmission Expansion Plan in order to ensure the reliability of the Transmission System. Base Plan Upgrades shall also include: (i) those Service Upgrades required for new or changed Designated Resources to the extent allowed for in Attachment J to this Tariff, (ii) to the extent allowed in Sections V.F and V.G of Attachment J, Network Upgrades required pursuant to the study results under Attachment AQ to this Tariff or required pursuant to Attachment AX of this Tariff after the planned generation has been included as a Designated Resource in the applicable Transmission Customer’s Network Integration Transmission Service Agreement or Service Agreement for Long-Term Firm Point-To-Point Transmission Service, (iii) ITP Upgrades that are approved for construction by the SPP Board of Directors, (iv) CPP Upgrades that are approved for construction by the SPP Board of Directors or authorized under a CPP GIA and that have a portion of cost allocated pursuant to Section III of Attachment J to this Tariff and recovered under Schedule 11 to this Tariff, (v) high priority upgrades, excluding Balanced Portfolios, that are approved for construction by the SPP Board of Directors, (vi) Network Upgrades due to the retirement of a Resource in accordance with Attachment AB to this Tariff; and
(vii) to the extent allowed in Section III.B of Attachment J, Qualifying NRIS Upgrades. For Zones 1 through 15, all such upgrades shall specifically exclude planned Transmission System facilities identified in the SPP Transmission Expansion Plan that are: (i) placed in service during the 2005 calendar year or
(ii) required to be in service to meet the SPP Criteria and the NERC Reliability Standards for the summer of 2005. For Zones 16, 17, and 18, all such upgrades shall specifically exclude planned Transmission System facilities in those zones identified in the SPP Transmission Expansion Plan Report (2009 – 2018) that are required to be in service to meet the SPP Criteria and the NERC Reliability Standards for the summer of 2008 or which are in operation prior to January 1, 2009, except for those upgrades that are in service prior to January 1, 2009 and are components of Phase 1 of the NPPD 345kV Norfolk to Lincoln (ETR) project or OPPD Sub 1255/3455 Transformer project. Network Upgrades that are components of Phase 1 of the NPPD 345kV Norfolk to Lincoln (ETR) project or OPPD Sub 1255/3455 Transformer project that are in service prior to January 1, 2009 will be Base Plan Upgrades, however, the Zonal component of
PDF page 17
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 17
the costs shall be 100% allocated to the respective host zone. The Base Plan Upgrades in Zones 1 through 18 identified by the Transmission Provider with a need date prior to October 1, 2015 shall not be allocable to Zone 19. The upgrades in Zone 19 identified by the Transmission Provider with a need date prior to October 1, 2015, shall not constitute Base Plan Upgrades. The facilities identified in Schedule 2 to Attachment J are expressly deemed to be Base Plan Upgrades pursuant to Attachment J, Section III.A.2.66
This proposed revision is necessary to reference the portion of any Network Upgrade cost that does not exceed the LSHL, which remains a Base Plan Upgrade cost allocated under Section III.A of Attachment J.
ii. 1 Definitions D
Directly Assigned Upgrade Costs: An Eligible Customer’s share of the cost of a Service Upgrade or Network Upgrade, or a Project Sponsor’s share of the cost of a Sponsored Upgrade, determined in accordance with Attachments J, V, Z1, and AX, which includes any Network Upgrade costs that are (i) directly assigned to an Eligible Customer for a Service Upgrade in excess of the normally applicable transmission access charges for the associated transmission service; (ii) directly assigned to an Eligible Customer that are in excess of the Safe Harbor Cost Limit for Service Upgrades associated with new or changed Designated Resource; (iii) directly assigned to a Project Sponsor for a Sponsored Upgrade; (iv) directly assigned to a Generation Interconnection Customer resulting from a request for generation interconnection; or (v) directly assigned to a Transmission Customer for a Network Upgrade when the Transmission Customer has not been granted Long-Term Service for the planned generation that was submitted in accordance with Attachment AX; or
(vi) directly assigned to a Transmission Customer for the Network Upgrade(s) required pursuant to a study conducted under Attachment AQ, Attachment AX, or Attachment BA to add or modify a delivery point when the applicable Network Upgrade costs exceed the Load Safe Harbor Limit specified in Section V.G of Attachment J.67
This proposed revision is necessary to reference the portion of any Network Upgrade cost that exceeds the Load Safe Harbor Limit and is directly assigned to the Transmission Customer.
66
Proposed Tariff, Part I, Section 1 Definitions B.
67
Proposed Tariff, Part I, Section 1 Definitions D.
PDF page 18
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 18
iii. 1 Definitions L
Load Safe Harbor Limit: The maximum amount of Base Plan Upgrade cost eligible for cost allocation, as specified in Section V.G of Attachment J, for each request studied pursuant to Attachment AQ, Attachment AX, or Attachment BA to add or modify a delivery point, which is applicable to the Network Upgrade(s) authorized for construction under such a study other than Zonal Reliability Upgrades.68
This proposed revision is needed to specifically define the LSHL, including the clarification that Zonal Reliability Upgrades, which are not Base Plan Upgrades, are not subject to the cost limitation on rate funding.
B. Part III Section 31.2
i. Section 31.2c
SPP proposes to modify Section 31.2c to include a reference to Attachment AX of the Tariff as a governing attachment for requests for modification of delivery points.69 This edit is simply a clean-up revision necessary to appropriately reference Attachment AX, along with Attachment AQ, as one of the attachments used to modify delivery points.
ii. Section 31.2d
SPP proposes to modify Section 31.2d to remove the reference to Section III of Attachment J and replace it with a reference to Section V.G of Attachment J of the Tariff as the section governing funding for Network Upgrades identified under Attachment AQ.70
This proposed revision is necessary as the appropriate reference should be to the new LSHL section, as that section describes how Network Upgrades identified in the Attachment AQ load addition or modification study processes will be allocated.
C. Attachment J
i. Section V.F
SPP proposes to modify Section V.F of Attachment J to remove language stating that Network Upgrades are to be allocated pursuant to Section III.A of
68 Proposed Tariff, Part I, Section 1 Definitions L.69 Proposed Tariff, Part III, Section 31.2c.70 Proposed Tariff, Part III, Section 31.2d.
PDF page 19
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 19
Attachment J upon the Transmission Customer receiving Long-Term Service for the planned generation that was studied in accordance with Attachment AX. SPP proposes revisions to replace the removed language with language stating that Network Upgrades are to be allocated in accordance with Section III.A of Attachment J for amounts of cost less than or equal to the LSHL and direct assignment for any amount in excess of the LSHL. Under Attachment AX, the full term of directly assigned costs for Network Upgrades, including both the period before Long-Term Service is received and the period after Long-Term Service is received, will not exceed forty (40) years. Subsequent to the termination date of direct assignment payments, the remaining revenue requirements will be allocated in accordance with Section III.A of Attachment J.71
This proposed modification to Section V.F of Attachment J is necessary to describe how Network Upgrades identified in the Provisional Load Process (Attachment AX) will be Base Plan funded or directly assigned using the LSHL.
ii. Section V.G
SPP proposes to add a new subsection V.G of Attachment J for Network Upgrades required by SPP to add or modify a delivery point. SPP proposes revisions to state that cost up to the LSHL will be allocated in accordance with Section III.A of Attachment J for Affected Network Upgrades. “Affected Network Upgrades” are defined as all Network Upgrade(s), other than any Zonal Reliability Upgrade(s), resulting from a request that is studied under Attachment AQ, Attachment AX, or Attachment BA to add or modify a delivery point. For the aggregate cost of Affected Network Upgrades under each study request, the LSHL is defined as the lesser of: a) $500,000 per MW multiplied by the MW amount of requested change in delivery point load, or b) $25,000,000. The LSHL is applicable for load service requests submitted to SPP under Attachment AQ, Attachment AX, or Attachment BA on or after the effective date established by the Commission for these Tariff changes. The aggregate amount of the directly assigned cost for each delivery point request will be apportioned to the Affected Network Upgrade(s) in a manner that will minimize the number of such upgrades for which directly assigned cost will be charged, which is consistent with treatment of Service Upgrades as provided in Section V.c of Tariff Attachment Z1 and reduces long-term administrative cost connected with directly assigned upgrades. The monthly amount of directly assigned costs shall be the monthly revenue requirement of the constructing Transmission Owner(s), with the revenue requirement amount based on the portion of cost of the Affected Network Upgrade that is directly assigned and calculated in a manner consistent with the revenue requirements of Network Upgrade(s) recovered by the Transmission Owner(s) under Schedule 9 or Schedule 11 of this Tariff. The term of each Affected Network Upgrade’s set of direct assignment payments will extend forty (40) years unless the Transmission Owner’s revenue requirement for the Affected Network Upgrade is terminated at an earlier date.
71
Proposed Tariff, Attachment J, Section V.F.
PDF page 20
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 20
Subsequent to the termination date of the directly assigned cost, any remaining revenue requirements will be allocated in accordance with Section III.A of Attachment J.72
This proposed new Section V.G of Attachment J is needed to describe how Network Upgrades identified in SPP’s transmission study processes for delivery point additions and modifications will be Base Plan funded or directly assigned using the LSHL.
D. Attachment Y
SPP proposes revisions to Section I.1(a) of Attachment Y to be clear that Network Upgrades identified under Attachment AQ that have no directly assigned costs will be eligible for the specified process under Section III of Attachment Y, subject to meeting the remaining eligibility criteria.73
E. Attachment AQ
SPP proposes to add language in Section 4.0 of Attachment AQ to state that responsibility for the costs of facilities required under the Delivery Point Network Study (“DPNS”) shall be as described in proposed Section V.G of Attachment J of the Tariff. The Transmission Customer will maintain financial security, in an amount corresponding to the engineering and construction costs associated with any direct assignment obligation for Network Upgrades identified for construction under the DPNS. The security requirement may be reduced annually or waived by SPP pursuant to specifications detailed in the proposed revisions.74
These edits are necessary to describe the financial obligations of those Transmission Customers that are directly assigned Network Upgrade costs through the Attachment AQ study process.
F. Attachment AX
i. Section 3.0
SPP proposes to add language in Section 3.0 of Attachment AX to state that responsibility for the costs of facilities required under the Provisional Load Process Study (“PLPS”) shall be as described in proposed Section V.F of Attachment J of the Tariff. The Transmission Customer will maintain financial security, in an amount corresponding to the engineering and construction costs associated with any direct
72
Proposed Tariff, Attachment J, Section V.G.
73 Proposed Tariff, Attachment Y, Section 1.74 Proposed Tariff, Attachment AQ, Section 4.0.
PDF page 21
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 21
assignment obligation for Network Upgrades identified for construction under the PLPS. The security requirement may be reduced annually or waived by SPP pursuant to specifications detailed in the proposed revisions.75
These edits are necessary to describe the financial obligations of those Transmission Customers that are directly assigned Network Upgrade costs through the Attachment AX study process.
ii. Addendum 2
SPP proposes revisions to Addendum 2 of Attachment AX to remove the reference to Schedule 11 and add that the remaining costs of Network Upgrade(s) shall be recovered through allocation in accordance with Section III.A of Attachment J of the Tariff and through direct assignment of any amount in excess of the LSHL, as specified in Sections V.F and V.G of Attachment J.76 This revision is necessary because, under the LSHL, a portion of the remaining Network Upgrade costs may be directly assigned rather than recovered entirely under Schedule 11.
iii. Addendum 3
SPP also proposes revisions to Addendum 3 of Attachment AX to remove the reference to Schedule 11 and add that the remaining costs of Network Upgrade(s) shall be recovered through allocation in accordance with Section III.A of Attachment J of the Tariff and through direct assignment of any amount in excess of the LSHL, as specified in Sections V.F and V.G of Attachment J.77 This revision is necessary because, under the LSHL, a portion of the remaining Network Upgrade costs may be directly assigned rather than recovered entirely under Schedule 11.
G. Attachment BA
SPP proposes revisions to Section 2.1.3.6 of Attachment BA to include language specifying that the responsibility for cost of facilities required under the HDPS shall be as described in Sections V.F and V.G of Attachment J of the Tariff.78 This revision is necessary to ensure that Network Upgrades identified through the HDPS are subject to the same LSHL cost responsibility as those identified under Attachments AQ and AX.
75 Proposed Tariff, Attachment AX, Section 3.0. 76 Proposed Tariff, Attachment AX, Addendum 2, Section 10.0. 77 Proposed Tariff, Attachment AX, Addendum 3, Section 10.0.78 Proposed Tariff, Attachment BA, Section 2.1.3.6.
PDF page 22
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 22
VII. EFFECTIVE DATE
For all the reasons discussed in this transmittal letter, SPP requests that the Commission accept the proposed revisions to the Tariff to become effective February 17, 2027, which is not more than 120 days after, and not fewer than 60 days after, the filing date, consistent with the Commission’s regulations.79 This effective date provides a reasonable implementation period that accommodates existing commercial arrangements, as discussed in Section V.
VIII. ADDITIONAL INFORMATION
A. Documents submitted with this filing:
In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 180; Exhibit No. SPP-0001: Affidavit of Natasha Henderson; and
Exhibit No. SPP-0002: Affidavit of Don Frerking.
B. Service:
SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants. A complete copy of this filing will be posted on the SPP website, www.spp.org, and is also being served on all affected state commissions.
C. Requisite agreements:
There are none.
79 18 C.F.R. § 35.3(a)(1). 80 Certain tariff records contained in this filing include language in italics indicating revisions pending before the Commission in the following proceedings: ER6-2796-000 and ER27-559-000. In the event that revisions in any of these proceedings are not accepted by the Commission, SPP commits to submit a clean-up filing to remove the language from the Tariff.
PDF page 23
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 23
D. Communications
Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:81
Justin A. Hinton
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2468
jhinton@spp.org
Meredith Powell
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2507
mpowell@spp.org
Tessie Kentner
Director & Associate General Counsel
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 688-1782
tkentner@spp.org
81 Pursuant to Commission Rule 101(e), 18 C.F.R. § 385.101(e), SPP requests waiver of Rule 203(b)(3), 18 C.F.R. § 385.203(b)(3), in order to permit more than two persons to be included on the service list.
PDF page 24
The Honorable Debbie-Anne A. ReeseNovember 19, 2026Page 24
IX. CONCLUSION
For the foregoing reasons, SPP respectfully requests that the Commission accept the Load Safe Harbor Limit Revisions, effective February 17, 2027. SPP further requests that the Commission find that the Load Safe Harbor Limit Revisions are just and reasonable and not unduly discriminatory or preferential and resolve the cost recovery directive in Paragraphs 59 through 65 of the Show Cause Order, such that no further action is required in Docket No. EL26-68-000 with respect to that directive.
Respectfully submitted,
/s/ Justin A. Hinton
Justin A. Hinton
Meredith Powell
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
Attorneys for
Southwest Power Pool, Inc.