ER27-577-000 · 2026-11-19 · Southwest Power Pool, Inc.

Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs

Text extracted from the eLibrary original (SHA-256 a9d06721aaa6c185…). Download the original from the official source.

Contents · 31 sections
  1. I. SUMMARY OF FILING p. 2
  2. II. BACKGROUND p. 3
  3. A. The HILL Process p. 3
  4. B. The Show Cause Order p. 3
  5. C. Abeyance p. 3
  6. D. Stakeholder Process and Approval p. 4
  7. III. CURRENT p. 6
  8. A. SPP Transmission Service Process p. 6
  9. B. Original Safe Harbor Provisions p. 7
  10. IV. DESCRIPTION OF AND JUSTIFICATION FOR THE LOAD SAFE p. 9
  11. A. Show Cause Order Requirements p. 9
  12. B. Load Safe Harbor Limit Proposal p. 9
  13. C. The Load Safe Harbor Limit Resolves the Show Cause Order’s Cost p. 13
  14. D. Annual Load Safe Harbor Limit Annual Filing p. 14
  15. E. Directives Addressed in Separate Filings p. 15
  16. V. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS p. 15
  17. VI. PROPOSED TARIFF CHANGES AND JUSTIFICATIONS p. 16
  18. A. Part I, Section 1, Definitions p. 16
  19. B. Part III Section 31.2 p. 18
  20. C. Attachment J p. 18
  21. D. Attachment Y p. 20
  22. E. Attachment AQ p. 20
  23. F. Attachment AX p. 20
  24. G. Attachment BA p. 21
  25. VII. EFFECTIVE DATE p. 22
  26. VIII. ADDITIONAL INFORMATION p. 22
  27. A. Documents submitted with this filing: p. 22
  28. B. Service: p. 22
  29. C. Requisite agreements: p. 22
  30. D. Communications p. 23
  31. IX. CONCLUSION p. 24

Topics in the text: Cost allocation · Filing procedure · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Reese November 19, 2026 Page 2 financial contributions and financial security sufficient to mitigate the risk of cost shifting among transmission customers if a large load does not materialize as planned.5 SPP respectfully requests that the Commission find the proposed revisions just and reasonable…
Read this passage

I. SUMMARY OF FILING

printed heading · Topic match: Cost allocation

The LSHL mitigates the risk of cost shifting associated with the connection of large loads by requiring the Transmission Customer to pay, and to secure with financial security, all delivery point Network Upgrade costs above a threshold—creating an obligation that correlates directly with the level…
Read this passage

II. BACKGROUND

printed heading

II.
Read this passage

A. The HILL Process

printed heading

The HILL Process On January 14, 2026, the Commission accepted SPP's Tariff revisions establishing the HILL study process in Attachment BA and the High Impact Large Load Generation Assessment ("HILLGA") in Attachment BB.
Read this passage

B. The Show Cause Order

printed heading

The Show Cause Order In the Show Cause Order, the Commission adopted SPP’s HILL definition as its definition of “large load.”11 It then preliminarily found that the Tariff appears unjust and unreasonable in four categories.
Read this passage

C. Abeyance

printed heading · Topic match: Filing procedure

Reese November 19, 2026 Page 4 develop Section 205 filings through its stakeholder process.14 SPP described the anticipated content of those filings in its Abeyance Motion, including the revisions submitted here.15 On August 14, 2026, the Commission granted the Abeyance Motion and set a due date of…
Read this passage

D. Stakeholder Process and Approval

printed heading · Topic match: Cost allocation

The period for direct assignment of costs in excess of the Load Safe Harbor Limit shall not exceed forty (40) years.” The Honorable Debbie-Anne A.
Read this passage

III. CURRENT

printed heading

CURRENT COST ALLOCATION FOR DELIVERY POINT NETWORK UPGRADES AND EXISTING SAFE HARBOR PROVISIONS
Read this passage

A. SPP Transmission Service Process

printed heading · Topic match: Cost allocation

Currently, there is no limit to the amount of Network Upgrade costs, quantified as either dollars per megawatt (“MW”) or total cost, that can be Base Plan Funded for a delivery point request, regardless of the costs relative to the load requested or whether the load materializes.
Read this passage

B. Original Safe Harbor Provisions

printed heading · Topic match: Cost allocation

Reese November 19, 2026 Page 9 Cost Limit.37 The Commission directed SPP to file an annual report to include: (1) average costs of new Network Upgrades and the effectiveness of the Safe Harbor Cost Limit threshold; (2) an “unintended consequences” review (now addressed every six years as a…
Read this passage

IV. DESCRIPTION OF AND JUSTIFICATION FOR THE LOAD SAFE

printed heading

DESCRIPTION OF AND JUSTIFICATION FOR THE LOAD SAFE HARBOR LIMIT REVISIONS
Read this passage

A. Show Cause Order Requirements

printed heading · Topic match: Cost allocation

A.
Read this passage

B. Load Safe Harbor Limit Proposal

printed heading · Topic match: Cost allocation

Load Safe Harbor Limit Proposal SPP proposes to establish a LSHL for Network Upgrades needed to add or modify load delivery points studied under Attachment AQ, Attachment AX, or 37 Base Plan Funding Order at P 51. 38 Id. 39 See Docket No.
Read this passage

C. The Load Safe Harbor Limit Resolves the Show Cause Order’s Cost

printed heading

This is the kind of “other just and reasonable method[]” the Commission invited.61 Under FPA Section 205, SPP must show that its proposal is just and reasonable.
Read this passage

D. Annual Load Safe Harbor Limit Annual Filing

printed heading · Topic match: Cost allocation

Annual Load Safe Harbor Limit Annual Filing As described above in Section III.B, the Commission, in the Base Plan Funding Order, directed SPP to assess average costs of all Network Upgrades as part of its biennial planning process and work with stakeholders and the RSC to evaluate the effectiveness…
Read this passage

E. Directives Addressed in Separate Filings

printed heading · Topic match: Connecting load and generation

SPP respectfully requests that the Commission consider this filing together with the above filings as SPP’s response to the Show Cause Order.
Read this passage

V. PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS

printed heading

PROTECTION OF EXISTING COMMERCIAL ARRANGEMENTS The Show Cause Order directs that any Section 205 filing explain how the proposal will avoid disrupting existing commercial arrangements and identify a reasonable effective date.65 The proposed LSHL provisions are designed to apply only to delivery…
Read this passage

VI. PROPOSED TARIFF CHANGES AND JUSTIFICATIONS

printed heading

VI.
Read this passage

A. Part I, Section 1, Definitions

printed heading · Topic match: Cost allocation

Part I, Section 1, Definitions SPP proposes to modify two existing definitions and add a new definition to Part I, Section 1 of the Tariff as follows: i. 1 Definitions B Base Plan Upgrades: Those upgrades included in and constructed pursuant to the SPP Transmission Expansion Plan in order to ensure…
Read this passage

B. Part III Section 31.2

printed heading

Section 31.2c SPP proposes to modify Section 31.2c to include a reference to Attachment AX of the Tariff as a governing attachment for requests for modification of delivery points.69 This edit is simply a clean-up revision necessary to appropriately reference Attachment AX, along with Attachment…
Read this passage

C. Attachment J

printed heading

Section V.F SPP proposes to modify Section V.F of Attachment J to remove language stating that Network Upgrades are to be allocated pursuant to Section III.A of 68 Proposed Tariff, Part I, Section 1 Definitions L. 69 Proposed Tariff, Part III, Section 31.2c. 70 Proposed Tariff, Part III, Section…
Read this passage

D. Attachment Y

printed heading

Attachment Y SPP proposes revisions to Section I.1(a) of Attachment Y to be clear that Network Upgrades identified under Attachment AQ that have no directly assigned costs will be eligible for the specified process under Section III of Attachment Y, subject to meeting the remaining eligibility…
Read this passage

E. Attachment AQ

printed heading · Topic match: Cost allocation

Attachment AQ SPP proposes to add language in Section 4.0 of Attachment AQ to state that responsibility for the costs of facilities required under the Delivery Point Network Study (“DPNS”) shall be as described in proposed Section V.G of Attachment J of the Tariff.
Read this passage

F. Attachment AX

printed heading · Topic match: Cost allocation

Addendum 2 SPP proposes revisions to Addendum 2 of Attachment AX to remove the reference to Schedule 11 and add that the remaining costs of Network Upgrade(s) shall be recovered through allocation in accordance with Section III.A of Attachment J of the Tariff and through direct assignment of any…
Read this passage

G. Attachment BA

printed heading

Attachment BA SPP proposes revisions to Section 2.1.3.6 of Attachment BA to include language specifying that the responsibility for cost of facilities required under the HDPS shall be as described in Sections V.F and V.G of Attachment J of the Tariff.78 This revision is necessary to ensure that…
Read this passage

VII. EFFECTIVE DATE

printed heading

EFFECTIVE DATE For all the reasons discussed in this transmittal letter, SPP requests that the Commission accept the proposed revisions to the Tariff to become effective February 17, 2027, which is not more than 120 days after, and not fewer than 60 days after, the filing date, consistent with the…
Read this passage

VIII. ADDITIONAL INFORMATION

printed heading

VIII.
Read this passage

A. Documents submitted with this filing:

printed heading

Documents submitted with this filing: In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 180; Exhibit No.
Read this passage

B. Service:

printed heading

Service: SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants.
Read this passage

C. Requisite agreements:

printed heading

Requisite agreements: There are none. 79 18 C.F.R. § 35.3(a)(1). 80 Certain tariff records contained in this filing include language in italics indicating revisions pending before the Commission in the following proceedings: ER6-2796-000 and ER27-559-000.
Read this passage

D. Communications

printed heading

Communications Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:81 Justin A.
Read this passage

IX. CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, SPP respectfully requests that the Commission accept the Load Safe Harbor Limit Revisions, effective February 17, 2027.
Read this passage