Revisions to Add Price Adaptive Load Service
Text extracted from the eLibrary original (SHA-256 fd746390ce38150a…). Download the original from the official source.
Contents · 23 sections
- I. SUMMARY OF FILING
- II. BACKGROUND
- A. The HILL Process Filings
- B. Show Cause Order in Docket No. EL26-68
- C. Stakeholder Engagement and Approval
- III. DESCRIPTION OF AND JUSTIFICATION FOR PROPOSED TARIFF
- A. Overview
- B. Price Adaptive Load Service
- C. SPP Integrated Marketplace Requirement for PALS
- IV. ADDITIONAL TARIFF REVISIONS
- Attachment H
- Attachment L
- Attachment M
- Attachment O
- Attachment T
- V. SHOW CAUSE ORDER DIRECTIVES ADDRESSED IN SEPARATE
- VI. EFFECTIVE DATE AND REQUEST FOR WAIVER
- VII. ADDITIONAL INFORMATION
- A. Documents submitted with this filing:
- B. Service:
- C. Requisite agreements:
- D. Communications
- VIII. CONCLUSION
Topics in the text: Reliability and curtailment · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff. 2 Proposed Tariff, Part I, Section 1, Definition of Price Adaptive Load Service (“A type of transmission service available to serve a Price Adaptive Load at a delivery point, in whole or in…Read this passage
I. SUMMARY OF FILING
printed heading · Topic match: Reliability and curtailment
It is curtailed before firm service, imposes penalties for unreserved use, carries no resource adequacy obligation, and requires control technologies or protection systems that keep withdrawals within approved levels.Read this passage
II. BACKGROUND
printed heading
II.Read this passage
A. The HILL Process Filings
printed heading
The HILL Process Filings The need and ideas that form the basis for SPP’s proposal for PALS grew from SPP’s work to integrate and accommodate new large loads.Read this passage
B. Show Cause Order in Docket No. EL26-68
printed heading · Topic match: Filing procedure
EL26-68 In the Show Cause Order, the Commission adopted SPP’s HILL definition as its definition of “large load.”18 It then preliminarily found that the Tariff appears unjust and unreasonable in four categories.Read this passage
C. Stakeholder Engagement and Approval
printed heading · Topic match: Cost allocation
The MWG proposes changes to the SPP Tariff and other governing documents to implement suggested market changes. 26 See ORWG Meeting Minutes, dated September 2, 2026, at Agenda Item 7 posted at: https://www.spp.org/documents/77750/orwg%20meeting%20minutes%2020260902. pdf.Read this passage
III. DESCRIPTION OF AND JUSTIFICATION FOR PROPOSED TARIFF
printed heading
DESCRIPTION OF AND JUSTIFICATION FOR PROPOSED TARIFF REVISIONSRead this passage
A. Overview
printed heading · Topic match: Cost allocation
To establish the rates, terms, and conditions of PALS, SPP proposes a new Part VIII of the Tariff (Sections 54 through 61), a new Schedule 16, and a new Attachment BG, which contains the study process for PALS, a Sample Request For a Price Adaptive Load Delivery Point Initial Assessment, a pro…Read this passage
B. Price Adaptive Load Service
printed heading · Topic match: Reliability and curtailment
Consistent with other unreserved use charges outlined in the Tariff, the Transmission Customer receiving PALS must purchase losses pursuant to Section 55.3 of the Proposed Tariff for amounts exceeding the PALS Usage Limit.148 These unreserved use charges reflect that the PAL is to use only the PALS…Read this passage
C. SPP Integrated Marketplace Requirement for PALS
printed heading · Topic match: Reliability and curtailment
To reflect the price sensitivity and operational flexibility that distinguish PALs from conventional load, SPP proposes revisions to Attachment AE that allow PALs to submit a different form of Energy Bids and to receive Dispatch Instructions.Read this passage
IV. ADDITIONAL TARIFF REVISIONS
printed heading
SPP proposes the following revisions, not specifically discussed above, to the Tariff to effectuate the addition of the PALS. 1.Read this passage
Attachment H
printed heading
SPP proposes revisions to Attachment H to incorporate references to revenues under new Schedule 16.196 190 “Reliability Registered Demand Response Program” is a newly defined term pending before the Commission in Docket No.Read this passage
Attachment L
printed heading
SPP proposes adding PALS to this section so the PALS revenue under Schedule 16 will be distributed in proportion to the owner-specific Zonal Annual Transmission Revenue Requirements in the Zone where the service is delivered.197 In addition, SPP revises Section III.A of Attachment L to add…Read this passage
Attachment M
printed heading
Attachment M SPP adds Section VI to Attachment M, providing that the Transmission Customer or Network Customer is responsible for real power losses associated with PALS under Schedule 16, and that losses associated with settlement in the Integrated Marketplace are accounted for under Attachment…Read this passage
Attachment O
printed heading
SPP proposes a revision to this section to include a reference to the Attachment BG process as proposed in this filing.200 8.Read this passage
Attachment T
printed heading
Attachment T Attachment T includes the rate sheets for Point-To-Point Transmission Service for all applicable Transmission Owners.201 SPP proposes to add references to Schedule 16 revenues in each of the separate rate sheets.202 These proposed changes are necessary to appropriately adjust the…Read this passage
V. SHOW CAUSE ORDER DIRECTIVES ADDRESSED IN SEPARATE
printed heading · Topic match: Connecting load and generation
SPP respectfully requests that the Commission consider this filing together with the above filings as SPP’s response to the Show Cause Order.Read this passage
VI. EFFECTIVE DATE AND REQUEST FOR WAIVER
printed heading
Therefore, SPP requests waiver of the Commission’s notice requirements.222 Good cause exists for the proposed revisions to be effective in the second quarter of 2028 in accordance with the Commission’s waiver of notice requirement codified in Section 35.11 of the Commission’s regulations223 because…Read this passage
VII. ADDITIONAL INFORMATION
printed heading
VII.Read this passage
A. Documents submitted with this filing:
printed heading
Documents submitted with this filing: In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 1.224Read this passage
B. Service:
printed heading
Service: SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants.Read this passage
C. Requisite agreements:
printed heading
C.Read this passage
D. Communications
printed heading
Communications Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:225 Emon O.Read this passage
VIII. CONCLUSION
printed heading
CONCLUSION For all of the foregoing reasons, SPP respectfully requests that the Commission- issue an order accepting the Tariff revisions proposed herein as soon as practicable but not later than February 17, 2027.Read this passage