ER27-578-000 · 2026-11-19 · Southwest Power Pool, Inc.

Revisions to Add Price Adaptive Load Service

PDF page 1

November 19, 2026

The Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C.  20426

Re:
Southwest Power Pool, Inc., Docket No. ER27-____-000
Submission of Tariff Revisions to Add the Price Adaptive Load Service; Related to Docket No. EL26-68-000

Dear Secretary Reese:

Pursuant to Section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Section 35.13 of the Federal Energy Regulatory Commission’s (“Commission”) Regulations, 18 C.F.R. § 35.13, Southwest Power Pool, Inc. ("SPP"), as authorized by its independent Board of Directors, submits revisions to its Open Access Transmission Tariff (“Tariff”)1 to establish Price Adaptive Load Service (“PALS”)2, a non-firm transmission service paired with a new market participation model that enables a Price Adaptive Load (“PAL”)3 to participate as fully dispatchable demand in both the Day- Ahead Market and Real-Time Balancing Market (“RTBM”). SPP submits this filing under Section 205, as the Commission encouraged, in response to the Commission’s June 18, 2026, order instituting a proceeding under FPA Section 206 in Docket No. EL26-68-000 (“Show Cause Order”).4 As explained in Section III.B.10, this filing resolves the Show Cause Order’s directive that SPP explain whether its Tariff remains

1 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume No. 1.  References in this filing to "Tariff" refer to the version of SPP’s Tariff currently in effect. "Proposed Tariff" refers to a version reflecting the revisions proposed in this filing. All capitalized terms not otherwise defined in this filing shall have the definitions assigned by the Tariff. 2 Proposed Tariff, Part I, Section 1, Definition of Price Adaptive Load Service (“A type of transmission service available to serve a Price Adaptive Load at a delivery point, in whole or in part,  as described in Attachment BG and Part VIII of the Tariff.”).
3 Proposed Tariff, Part I, Section 1, Definition of Price Adaptive Load (“A commercial or industrial load, or a portion of a commercial or industrial load, at a delivery point that is eligible to connect to the Transmission System and receive PALS as defined in Attachment BG and Part VIII of the Tariff.”)."
4 Sw. Power Pool, Inc., 195 FERC ¶ 61,213 (2026).

PDF page 2

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 2

just and reasonable without a non-firm contract demand transmission service for Eligible Customers taking service on behalf of flexible large loads and Eligible Load.

SPP requests that the Commission issue an order in this docket as soon as practicable, but not later than February 17, 2027, which is approximately 90 days after submission of this filing. SPP requests an effective date of “12/31/9998”5 for the Tariff Records submitted in this filing to allow SPP staff to develop, test, and implement the necessary software changes. SPP will submit a filing with the Commission specifying a precise effective date prior to implementation. SPP will work as quickly as practicable to technologically implement the Tariff revisions proposed herein. As of the date of this filing, implementation is targeted for the second quarter of 2028.

As discussed in Section VI below, SPP respectfully requests waiver of the 120- day prior-notice limitation in Section 35.3(a)(1) of the Commission’s regulations.6

I. SUMMARY OF FILING
The Show Cause Order commended SPP’s “bold and proactive steps” to
integrate large loads. It recognized that SPP’s High Impact Large Load (“HILL”) process already provides an enhanced study framework for Eligible Customers taking transmission service on behalf of large loads.7 The Commission nonetheless preliminarily found that “SPP’s Tariff appears to be unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking transmission service on behalf of flexible large loads that are willing and able to limit their use of the transmission system under certain conditions.”8  The Commission directed:

SPP should explain whether the Tariff remains just and
reasonable without the transmission services described by the
Commission in the [PJM Interconnection, L.L.C. (“PJM”)] Co-
Location Order[9], with regional variation as appropriate, being
available to Eligible Customers taking transmission service on
behalf of Eligible Load, or propose appropriate Tariff revisions.

5
See, e.g., Implementation Guide for Electronic Filing of Parts 35, 154, 284, 300, and 341 Tariff Filings at 10 (Nov. 14, 2016) (“If the effective date is not known at the time of the filing, such as the effective date is contingent on FERC approval . . . the date of 12/31/9998 must be used.”).

6 18 C.F.R. § 35.3(a)(1).
7 Show Cause Order at P 2.
8 Show Cause Order at P 86. 9 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“PJM Co-Location Order”).

PDF page 3

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 3

Specifically, SPP should explain whether the Tariff remains just
and reasonable without (1) an interim non-firm network
transmission service while Network Upgrades are being
constructed (i.e., interim NITS) and (2) permanent firm and non-
firm contract demand transmission services (transmission
service up to a specified MW quantity, i.e., the contract level, on
a firm or non-firm basis).10

With this filing, SPP is proposing the addition of PALS to the Tariff to address the Commission’s specific concern that the Tariff “does not include transmission services that reflect Eligible Customers taking transmission service on behalf of flexible large loads that are willing and able to limit their use of the transmission system under certain conditions.” PALS is a flexible transmission service that allows Transmission Customers to limit their use of the Transmission System. Under PALS, a PAL’s withdrawals are governed by the price-sensitive PAL Energy Bids11 its Market Participant submits, which are subject to a uniform $25/MWh cap that protects other customers from substantially high energy prices and from utilizing resources for PALS loads that are otherwise intended to serve firm load. PALS is available for renewable terms of one to ten years and is not tied to the construction of Network Upgrades. PALS is SPP’s regional variation on the Non-Firm Contract Demand transmission service described in the PJM Co-Location Order, tailored to SPP’s Integrated Marketplace and SPP’s transmission services. Like the Commission’s Non-Firm Contract Demand transmission service, PALS limits service to a specified MW quantity (the PALS Capacity). It is curtailed before firm service, imposes penalties for unreserved use, carries no resource adequacy obligation, and requires control technologies or protection systems that keep withdrawals within approved levels.

This filing is one part of SPP’s comprehensive response to the Show Cause Order. The collective filings addressing the Show Cause Order’s remaining directives are identified in Section V. Section III.B.11 explains how PALS avoids disrupting existing commercial arrangements, as the Show Cause Order requires.

II. BACKGROUND
A. The HILL Process Filings

The need and ideas that form the basis for SPP’s proposal for PALS grew from SPP’s work to integrate and accommodate new large loads. The present filing is the

10 Show Cause Order at P 83.
11 Proposed Tariff, Attachment AE, Section 1.1, Definition of PAL Energy Bid (“A proposal by a Market Participant associated with a Price Adaptive Load to purchase a price sensitive amount of Energy at a specified location and period of time in the Day- Ahead Market or the Real-Time Balancing Market.”).

PDF page 4

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 4

third major filing as a result of that work. The first filing occurred October 24, 2025, when SPP submitted Tariff revisions to add the HILL study process and a High Impact Large Load Generation Assessment (“HILLGA”).12 The Commission accepted the HILL Filing on January 14, 2026, with an effective date of January 15, 2026.13 The Commission found that “SPP has shown that unprecedented growth in large loads in the SPP region presents significant and unique operational and planning challenges[,]”14 and that the “proposed HILL and HILLGA processes are a just and reasonable and not unduly discriminatory or preferential approach to addressing these challenges, while maintaining the reliable operation of SPP’s transmission system.”15

On February 10, 2026, SPP submitted Tariff revisions to add Conditional High Impact Large Load Service (“CHILLS”).16 CHILLS allows a HILL, or a portion of a HILL, to receive up to seven years of non-firm transmission service when firm service is unavailable because the Transmission Customer lacks sufficient Designated Resources or because Network Upgrades are not yet complete. CHILLS serves as a bridge that allows a HILL to begin operating, when sufficient capacity is available, while it awaits firm service. The Commission accepted the provisions in a series of orders.17

This PALS filing is SPP’s third filing stemming from its initiative to integrate and accommodate new large loads. PALS is a novel approach to non-firm transmission service intended to serve loads that do not seek a bridge to firm service but have a business case for a non-firm transmission product. Unlike CHILLS, PALS is not limited to HILLs and is not tied to the completion of Network Upgrades or the addition of Designated Resources. Instead, PALS is designed for flexible, price-sensitive loads. PALS does not require supporting Resources, will not cause Network Upgrades to be identified or constructed, and uses a rate design based on the rates for hourly Non-Firm Point-To-Point Transmission Service.

12 Submission of Tariff Revisions to Add the High Impact Large Load Processes and High Impact Large Load Generation Assessment of Southwest Power Pool, Inc., Docket No. ER26-247-000 (October 24, 2025) (“HILL Filing”).

13
Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (“HILL/HILLGA Order”). 14

HILL/HILLGA Order at P 60.
15 Id.
16 Submission of Tariff Revisions to Add Conditional High Impact Large Load Service of Southwest Power Pool, Inc., Docket No. ER26-1323-000 (February 10, 2026).
17 Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026); Sw. Power Pool, Inc., Letter Order, Docket No. ER26-1323-002 (Oct. 26, 2026).

PDF page 5

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 5

B. Show Cause Order in Docket No. EL26-68

In the Show Cause Order, the Commission adopted SPP’s HILL definition as its definition of “large load.”18 It then preliminarily found that the Tariff appears unjust and unreasonable in four categories. The Commission directed SPP and the Transmission Owners either to show cause why the Tariff remains just and reasonable or to explain what changes would remedy the identified concerns.19 The Commission strongly encouraged SPP to address these issues through FPA Section 205 filings.20

The Commission also noted that “SPP’s PALS proposal is currently under development in its stakeholder process, and we encourage SPP to consider whether PALS would address our concern….”21  The Commission also explained that Eligible Customers that are willing and able to limit their use of the transmission system should be able to choose a transmission service that aligns their charges with the benefits they receive.22

SPP submitted an informational report on July 20, 2026, describing the status of PALS and SPP's other large load initiatives.23 On August 3, 2026, SPP and certain Transmission Owners moved to hold the Section 206 proceeding in abeyance through November 20, 2026, to allow SPP to complete its stakeholder process, and identified PALS as one of the Section 205 filings SPP would submit in response.24 This filing fulfills that commitment. SPP is concurrently submitting additional FPA Section 205 filings that address the Commission’s remaining concerns, as identified in Section V below.

C. Stakeholder Engagement and Approval

Starting in late 2025, SPP staff began working on the PALS proposal. SPP met with SPP stakeholder groups over thirty separate times to discuss PALS proposal and for the ultimate approval of the proposed Tariff revisions presented herein.

18 Show Cause Order at n.2.
19 Id. at P 3.
20 Id. at P 32. 21 Id. at P 84.
22 Id. at PP 83-84, 86-87.
23 Informational Report of Southwest Power Pool, Inc., Docket No. EL26-68-000 (July 20, 2026).
24 Joint Movants’ Amended Motion to Hold Section 206 Proceeding in Abeyance, Docket No. EL26-68-000 (August 3, 2026).

PDF page 6

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 6

 The proposed Tariff revisions were reviewed and approved through the SPP’s robust stakeholder process, including meetings of the: Market Working Group (“MWG”) on August 18, 2026;25 Operating Reliability Working Group (“ORWG”) on September 2, 2026;26 Supply Adequacy Working Group (“SAWG”) on September 23, 2026;27 Regional Tariff Working Group (“RTWG”) on September 24, 2026;28 and the

25
See MWG Minutes, dated August 18-19, 2026, at Agenda Item 11 posted at: https://www.spp.org/documents/77583/mwg%20minutes%2020260818-19.pdf. The MWG develops and oversees policies and procedures related to the Market Protocols that define SPP’s wholesale markets, including energy and operating reserve, congestion management, congestion hedging, demand response and market power mitigation. The MWG proposes changes to the SPP Tariff and other governing documents to implement suggested market changes.

26
See ORWG Meeting Minutes, dated September 2, 2026, at Agenda Item 7 posted at: https://www.spp.org/documents/77750/orwg%20meeting%20minutes%2020260902. pdf. The ORWG develops and oversees policies and procedures related to the reliable and secure operation of the Bulk Electric System within SPP’s Reliability Coordinator, Balancing Authority and Reserve Sharing Group footprints. The ORWG ensures these operating policies are consistent with North American Electric Reliability Corporation and regional reliability standards.

27
See SAWG Meeting Minutes, dated September 23, 2026, at Agenda Item 4 posted at: https://www.spp.org/documents/78101/sawg%20meeting%20minutes%2020260923- 24.pdf. The SAWG develops and oversees policies and procedures related to reliable supply adequacy within the SPP footprint. This includes ensuring that these policies and procedures meet the compliance obligations of North American Electric Reliability Corporation reliability standards.

28
See  RTWG Minutes, dated September 24, 2026, at Agenda Item 9b posted at: https://www.spp.org/documents/77942/rtwg%20meeting%20minutes%2020260924.p df. The RTWG develops, implements and oversees SPP’s Open Access Transmission Tariff. The RTWG provides input on regulatory or implementation issues not specifically covered by the tariff and issues where there may be conflicting or differing interpretations of the tariff.

PDF page 7

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 7

Transmission Working Group ("TWG")29 and Economic Studies Working Group (“ESWG”)30 on September 30, 2026.31

The proposed revisions were approved by the Markets and Operations Policy Committee (“MOPC”) on October 13, 2026,32 and the SPP Board of Directors on November 17, 2026.33

The Cost Allocation Working Group (“CAWG”) on October 1, 2026, 34 and the RSC on November 16,  2026,35 approved changes to SPP’s Open Access Transmission Tariff  Business Practices, Business Practice 8100, related to these Tariff revisions.

29 The TWG develops and oversees regional and interregional transmission planning processes, including generator interconnection and long-term transmission service study processes. The TWG reviews proposed transmission interconnections and coordinates transmission planning activities to develop SPP’s Integrated Transmission Plan and Transmission Expansion Plan.
30 The ESWG advises and assists SPP staff in determining the appropriate data, planning methods and processes for developing and evaluating economic transmission expansion options for the SPP region. 31 See ESWG & TWG Joint Meeting Minutes, dated September 30, 2026, at Agenda Item 3 posted at: https://www.spp.org/documents/77985/joint%20eswg- twg%20meeting%20minutes%2020260930-1001.pdf. 32 See MOPC Meeting Minutes, dated October 13-14, 2026, at Agenda Item 3.e posted at: https://www.spp.org/spp-documents-filings/?id=532303. The MOPC consists of a representative officer or employee from each SPP Member and reports to the SPP Board of Directors. Its responsibilities include recommending modifications to the Tariff. See Southwest Power Pool, Inc., Bylaws, First Revised Volume No. 4 ("Bylaws") at Section 6.1. 33 See Board of Directors & Members Committee Meeting Materials, dated November 17, 2026, at Agenda Item 3.2.4 and 7.1 posted at: https://www.spp.org/spp- documents-filings/?id=18449. The meeting minutes will be posted that this location when they become available.

34
See CAWG Meeting Minutes, dated October 1, 2026, at Agenda Item 8 posted at: https://www.spp.org/documents/77976/cawg%20minutes%2020261001.pdf. The

CAWG reports to the Regional State Committee (“RSC”) and assists the RSC in addressing matters for which the RSC has primary responsibility as defined in Section 7.2 of the SPP Bylaws. In addition, the CAWG assists the RSC in addressing any other issues as requested by the RSC.

35
See RSC Meeting Materials, dated November 16, 2026, at Agenda Item 6.D posted at: https://www.spp.org/spp-documents-filings/?id=20623. The meeting minutes will be posted at this location when they become available. The RSC provides collective state

PDF page 8

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 8

While SPP recognizes that stakeholder approval does not by itself cause a filing to be just and reasonable, SPP requests that the Commission extend appropriate deference to the wishes of SPP’s stakeholders, consistent with Commission precedent.36

III. DESCRIPTION OF AND JUSTIFICATION FOR PROPOSED TARIFF
REVISIONS

A. Overview

During the development of the CHILLS, there was stakeholder desire for a long-term transmission service product that would provide flexibility in how and when transmission customers could use the SPP Transmission System. CHILLS, although a non-firm, long-term transmission service product, requires the Transmission Customer to obtain and pay for transmission service based on a MW amount of reserved transmission capacity. SPP and its stakeholders developed the PALS to allow loads, not just HILLs, to obtain a long-term, non-firm dispatchable load service and

regulatory agency input on matters of regional importance related to the development and operation of bulk electric transmission. The SPP RSC is comprised of retail regulatory commissioners from agencies in Arkansas, Arizona, Colorado, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas, Utah and Wyoming. The RSC’s approved the following motion: “The Regional State Committee approves the revisions to Business Practice 8100 proposed in RR791 - Price Adaptive Load Service. The Regional State Committee recommends the Board of Directors support policies to reliably maximize utilization of the transmission system and consider the recommendation of the Cost Allocation Working Group relating to RR791 - Price Adaptive Load Service.”

36 The Commission has previously recognized that provisions approved through regional transmission organization stakeholder processes are due deference. See Sw. Power Pool, Inc., 127 FERC ¶ 61,283, at P 33 (2009) (noting that the Commission “accord[s] an appropriate degree of deference to RTO stakeholder processes”); New Eng. Power Pool, 105 FERC ¶ 61,300, at P 34 (2003) (Commission approval of transmission cost allocation proposal based upon an extensive and thorough stakeholder process); Policy Statement Regarding Regional Transmission Groups, 1991-1996 FERC Stats. & Regs., Regs. Preambles ¶ 30,976, at 30,872 (1993) (the Commission will afford the appropriate degree of deference to the stakeholder approval process). The Commission’s deference to RTO stakeholder processes has been upheld by the courts. See Pub. Serv. Comm’n of Wis. v. FERC, 545 F.3d 1058, 1062-63 (D.C. Cir. 2008) (noting that the Commission often gives weight to RTO proposals that reflect the position of the majority of the RTO’s stakeholders) (quoting Am. Elec. Power Serv. Corp. v. Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,083, at P 172 (2008)).

PDF page 9

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 9

withdrawal based on the real-time pricing. PALS will allow Transmission Customers the ability to utilize non-firm transmission service designed for price-sensitive loads to pay for service on a per MW basis based on actual usage and not based on the reserved capacity amount.

To establish the rates, terms, and conditions of PALS, SPP proposes a new Part VIII of the Tariff (Sections 54 through 61), a new Schedule 16, and a new Attachment BG, which contains the study process for PALS, a Sample Request For a Price Adaptive Load Delivery Point Initial Assessment, a pro forma PALS Service Agreement ("PALSA"), and a pro forma PALS Operating Agreement. SPP also proposes revisions to Attachment AE to establish the PAL market participation model, and numerous conforming revisions throughout the Tariff.

SPP proposes new definitions for PAL, PALS, PALS Capacity, PALS
Operating Agreement, PAL Upper Operating Tolerance, PALS Usage, and PALS Usage Limit. Similar to CHILL and CHILLS, PALS is the transmission service, and a PAL is the load that takes the service. The PALS Capacity is the maximum amount of Energy SPP agrees to transmit, the PALS Usage is the amount delivered, and the PALS Usage Limit reflects the four different paths possible for limiting withdrawals by PALs.

PALS is designed to accommodate flexible, price-sensitive loads that are willing to withdraw from the Transmission System only when the transmission capacity is available. PALS is a new transmission service product, similar to CHILLS, that will help expedite the connection of new loads on the Transmission System. As described and justified below, the PALS proposal is just and reasonable and not unduly discriminatory or preferential.

B. Price Adaptive Load Service

1. General Terms and Conditions of PALS37

To provide the rates, terms, and conditions of this new type of long-term non- firm transmission service, SPP proposes a new Part VIII of the Tariff, a new Schedule 16, and a new Attachment BG.38 PALS is the transfer of energy to designated Point(s) of Delivery to serve the PAL of a Transmission Customer or a Network Customer.39 PALS is “as available” transmission service that will be provided by SPP using the transfer capability that is in excess of the capability needed to serve Native Load

37
This section is intended to provide a general overview of the Tariff revisions proposed in this filing. Each requirement or characteristic of PALS discussed in this section is discussed in detail in subsequent sections.

38 Proposed Tariff, Part VIII, Sections 54-61, Schedule 16, and Attachment BG.
39 Proposed Tariff, Part VIII, Preamble.

PDF page 10

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 10

Customers,40 Network Customers, other Transmission Customers taking Long-Term Service and Short-Term Firm Point-To-Point Transmission Service,41 CHILLS, and customers under other transmission tariffs or agreements taking network or Firm Point- to-Point Transmission Service42 from the Transmission Owner(s).43 A Transmission Customer seeking PALS will take conditional transmission service based on the excess capacity available on the current topology of the Transmission System to serve the PAL.

Under Part VIII of the Proposed Tariff, PALS will be available for a minimum term of one (1) year and a maximum term of ten (10) years.44 This term will provide PALS customers with significant flexibility based on their needs, but will also allow SPP to ensure that the changing topology of the SPP Transmission System can reliably accommodate the PALS request after ten (10) years. After the termination of PALS, Transmission Customers cannot withdraw energy from the Transmission System for the PAL without obtaining firm transmission service under other processes in the Tariff or unless a renewed term is granted by SPP under Attachment BG.45 If the PALS customer does not use the PALS for a period of one (1) year, SPP has the ability to terminate the service.46

40 Tariff, Part I, Section 1, Definition of Native Load Customers (“The wholesale and retail power customers of the Transmission Owner(s) on whose behalf the Transmission Owner(s), by statute, franchise, regulatory requirement, or contract, has (have) undertaken an obligation to construct or operate the Transmission Owner's(s') system(s) to meet the reliable electric needs of such customers.  In addition, Native Load Customers also may include the customers of the Federal Government on whose behalf the Government, by policy, statute, regulatory requirement, or contract, delivers Federal capacity and energy to meet all or a portion of the reliable electric needs of such customers.”)
41 Tariff Part I, Section 1, Definition of Short-Term Point-To-Point Transmission Service (“Firm Point-To-Point Transmission Service under Part II of the Tariff with a term of less than one year.”).
42 Tariff, Part I, Section 1, Definition of Firm Point-to-Point Transmission Service (“Transmission Service under this Tariff that is reserved and/or scheduled between specified Points of Receipt and Delivery pursuant to Part II of this Tariff.”).
43 Proposed Tariff, Part VIII, Section 54.2.
44 Proposed Tariff, Part VIII, Section 54.1.
45 Id.
46 Id.

PDF page 11

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 11

Through the execution of a PALSA, Transmission Customers accept PALS with full realization that such service is subject to availability and to Curtailment47 or Interruption48 on a non-discriminatory basis in the event the Transmission System is constrained, under any situation that threatens reliability or other unforeseen conditions.49 The Proposed Tariff also requires the Transmission Customer to fully respond to a Load Shedding50 or Curtailment directive for the PAL delivery point limited by the average Setpoint Instruction51 plus the PAL Upper Operating Tolerance52.53 In the event the Transmission System is constrained or under Emergency Conditions, all firm transmission service and CHILLS will have higher priority than any PALS.54 PALS will have equal priority to hourly Non-Firm Point-To-Point Transmission Service.55 The priority of PALS appropriately ranks behind all firm service and CHILLS because PALS  is  non-firm transmission service and PALS is  not a bridge to a long-term firm transmission service like CHILLS. Transmission Customers with firm service are responsible for the costs of any needed Network Upgrades and required to have Resources that support that service, unlike PALS. The equal priority of PALS and hourly Non-Firm Point-To-Point Transmission Service is

47 Tariff, Part I, Section 1, Definition of Curtailment (“A reduction in firm or non-firm transmission service in response to a transmission capacity shortage as a result of system reliability conditions.”).
48 Tariff, Part I, Section 1, Definition of Interruption (“A reduction in non-firm transmission service due to economic reasons pursuant to Section 14.7.”).
49 Proposed Tariff, Part VIII, Section 58.1.
50 Proposed Tariff, Part I, Section 1, Definition of Load Shedding (“The systematic reduction of system demand by temporarily decreasing load in response to Transmission System or area capacity shortages, system instability, or voltage control considerations under Part III, Part VII, or Part VIII of the Tariff.”).
51 Proposed Tariff, Attachment AE, Section 1.1, Definition of Setpoint Instruction (“The Real-Time desired Megawatt output signal calculated for a specific Resource or Price Adaptive Load by SPP’s control system for a specified period.”). 52 Proposed Tariff, Attachment AE, Section 1.1, Definition of PAL Upper Operating Tolerance (“The Megawatt range of a Price Adaptive Load’s withdrawal above its average Setpoint Instruction over the Dispatch Interval within which it will not be subject to charges associated with deviating from its Setpoint Instruction”). 53 Proposed Tariff, Part VIII, Section 58.
54 Proposed Tariff, Part VIII, Section 54.2.
55 Id.

PDF page 12

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 12

appropriate because PALS Usage56 is billed on hourly increments similar to hourly Non-Firm Point-To-Point Transmission Service capacity.

Although Network Upgrades will not be identified for construction to establish a delivery point for the sole purpose of PALS, the Transmission Customer and Host Transmission Owner may still be required to ensure construction of facilities that enable the provision of PALS. The determination of such upgrades will be determined in the PAL Connection Study (“PALCS”) under Attachment BG,57 with the costs for such facilities being directly assigned to the PALS customer.  Further, the Transmission Customer is responsible for constructing, maintaining, and operating facilities on its side of the delivery point for SPP to reliably deliver energy from the Transmission System to the PAL delivery point.58

Transmission Customers will also take PALS under the Tariff with the knowledge that PALS is not available for resale, redirection, reassignment, or transfer of service.59 PALS is provided at the fixed location on the Transmission System that was studied. Therefore, redirection is not appropriate. Furthermore, resale and reassignment apply only to Point-To-Point Transmission Service60 and therefore will not apply to PALS. Lastly, since PALS is available only to entities entitled to serve retail electric load under state regulatory authority, resale, and reassignment are not needed for these types of Transmission Customers.

Section 54.4 of the Proposed Tariff provides that the Transmission Customer must not withdraw energy from the Transmission System at the PAL delivery point in excess of  PALS Usage Limit.61 The Transmission Customer will be billed for its PALS Usage under the terms of Schedules 11 and 16 of the Tariff62 and will be subject to

56 Proposed Tariff, Part I, Section 1, Definition of PALS Usage (“Amount of kilowatts delivered at the PALS delivery point provided pursuant to Part VIII of the Tariff.”).
57 Proposed Tariff, Attachment BG, Section 3.1.
58 Proposed Tariff, Part VIII, Sections 57.4 and 60.1.
59 Proposed Tariff, Part VIII, Section 54.5.
60 Tariff, Part I, Section 1, Definition of Point-To-Point Transmission Service (“The reservation and transmission of capacity and energy on either a firm or non-firm basis from the Point(s) of Receipt to the Point(s) of Delivery under Part II of the Tariff.”).
61 Proposed Tariff, Part I, Section 1, Definition of PALS Usage Limit (“For any five- minute interval within an hour, the lowest of the following: (1) the applicable average Setpoint Instruction plus the PAL Upper Operating Tolerance; (2) the PALS Capacity;
(3) the Curtailment limit; or (4) the Interruption limit.”)
62 Proposed Tariff, Part VIII, Section 54.4.

PDF page 13

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 13

additional unreserved use charges under Schedules 8 and 11 for any period when the additional service exceeds its PALS Usage Limit.63 Schedule 8 is used for this purpose because Schedule 16 applies only hourly and monthly rates, with the latter used solely for the purpose of capping the monthly charge under Section 2 of Schedule 16.  In order for PALS to have as strong a disincentive against unreserved use of the Transmission System as currently applies to Non-Firm Point-To-Point Transmission Service, the Schedule 8 rates are utilized to apply the daily, weekly, and monthly rates of that service schedule. This is appropriate because the hourly rates under Schedule 16 are identical to the hourly rates under Schedule 8. Finally, Transmission Customers taking PALS will be responsible for any real power losses,64 as set forth in Appendix 1 to Attachment M65 of the Tariff, for the PALS Usage amount, which is inclusive of any load exceeding the PALS Usage Limit.66

2. Obtaining PALS67

A Transmission Customer requesting PALS must submit an application,
including all information required pursuant to the SPP Credit Policy set out in Attachment X.68 PALS applications should be submitted by entering the information listed in Section 57.1 of Part VIII of the Proposed Tariff on SPP’s Open Access Same- Time Information System (“OASIS”).69

63 Id.
64 Proposed Tariff, Part VIII, Section 55.3; see also Proposed Tariff, Attachment M, Section VI (Transmission Loss Determination – Price Adaptive Load Service). 65 Tariff, Attachment M. Attachment M describes the loss compensation procedure used to quantify real power losses for which the Transmission Customer or Network Customer is responsible when taking service under the Tariff.  Appendix 1 to Attachment M is a schedule showing the real power loss factors for the provision of transmission service across each Zone on the Transmission System.
66 Proposed Tariff, Part VIII, Section 55.3. 67 See generally, Proposed Tariff, Part VIII; see also Proposed Tariff, Part VIII, Section 56.1 (outlining the conditions required of Transmission Customers taking PALS). 68 Proposed Tariff, Part VIII. Section 57.1.
69 Tariff, Part I, Section 1, Definition of Open Access Same-Time Information System (OASIS) (“The information system and Internet location where the Transmission Provider posts the information required by 18 C.F.R. § 37 of the Commission's regulations, and where the Transmission Provider may also post the information required to be posted on its Internet website by 18 C.F.R. § 358 of the Commission’s regulations.”).

PDF page 14

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 14

When a Transmission Customer applies for PALS, it must specify the amount of PALS Capacity for the term of service (one (1) to ten (10) years).70 To evaluate a request for PALS, SPP requires the Transmission Customer to submit information regarding all of its existing loads and Resources that are currently receiving firm transmission service.71 This information enables SPP to fully assess impacts to the Transmission System associated with granting PALS to an existing Transmission Customer.

A Transmission Customer must also provide timely written notice of material changes in any information provided in its application relating to the PALS, its transmission system, or other aspects of its facilities or operations affecting SPP’s ability to provide reliable service.72 This information will enable SPP to continue planning for safe and reliable transmission service.

The time requirements for submitting and evaluating PALS requests are set out in Attachment P of the Tariff, as for other transmission service.73 SPP will respond to all Completed Applications as soon as practicable and on a non-discriminatory basis, including applications from a Transmission Owner’s own merchant function.74

3. PALS Study Processes

Attachment BG outlines the study processes required for a PAL delivery point to be connected to the Transmission System. To establish or modify a PAL delivery point pursuant to Attachment BG, the Transmission Customer must request, in writing, a PAL Delivery Point Limitations Assessment (“PDPLA”).75 The request must contain the information included in “Sample Request For a Price Adaptive Load Delivery Point Initial Assessment” attached as Addendum 1 to Attachment BG of the Proposed Tariff.76

70 Proposed Tariff, Part VIII, Sections 54.1 and 57.1(vi).
71 Proposed Tariff, Part VIII, Section 57.1.
72 Proposed Tariff, Part VIII, Section 55.2.
73 Proposed Tariff, Part VIII, Section 57.2.
74 Proposed Tariff, Part VIII, Section 57.5.
75 Proposed Tariff, Attachment BG, Section 1.0.
76 Id.

PDF page 15

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 15

Attachment BG makes clear that a Transmission Customer may not make a request for PALS for Critical Loads, as defined in Attachment AE of the Tariff.77 If the PALS delivery point qualifies as a HILL, the delivery point must also satisfy the HILL requirements outlined in Attachment BA of this Tariff.78 CHILLS and PALS cannot be taken at the same delivery point.79

Requirements related to the Host Transmission Owner’s performance of the PALCS are outlined in Section 3.1 of Attachment BG of the Proposed Tariff. The procedures, deposits, and timelines of the PALCS in Attachment BG are consistent with the load connection studies outlined in Attachments AQ, AX, BA, and BC.80

Under the PALCS agreement, the Host Transmission Owner may require an advance deposit equal to the estimated study cost or $10,000, whichever is less.81 Before SPP performs the PDPLA, the Transmission Customer or Network Customer must execute a PDPLA agreement. That agreement commits it to pay a $2,000 non- refundable application fee, adjusted every three years for inflation using the Consumer Price Index for All Urban Consumers, plus the actual cost of the PDPLA.82 A scoping call among the customer, SPP, and the Host Transmission Owner will be held within ten (10) Calendar Days after the executed agreements and any required deposit are received.83 The application fee and inflation adjustment is consistent with other transmission service study processes.

Pursuant to proposed Attachment BG, SPP will perform an assessment of the impact of the requested delivery point configuration change on the Transmission System and, if requested by the Transmission Customer, will provide information detailing the limitations of the Transmission System in supporting any PAL.84 SPP will send a study report to the Transmission Customer and Host Transmission Owner within ninety (90) Calendar Days of all parties (SPP, Host Transmission Owner, and the

77 Id. at Section 2.0.
78 Id.
79 Id.
80 See Tariff, Attachments AQ, AX, BA, and BC.
81 Proposed Tariff, Attachment BG, Section 3.1.
82 Proposed Tariff, Attachment BG, Section 3.2.
83 Id.
84 Proposed Tariff, Attachment BG, Section 3.2.

PDF page 16

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 16

Transmission Customer) agreeing to study assumptions, unless a reason is given by SPP for the delay in providing the study report.85

PDPLA study results are valid for one (1) year after the study report is delivered, or for a shorter period if the Host Transmission Owner’s PALCS agreement requires it. SPP will close the PDPLA billing period within thirty (30) Calendar Days after the last study report is delivered.86 Setting an expiration date ensures that a PALSA is based on a reasonably current assessment of the Transmission System. The Transmission Customer and the Host Transmission Owner must agree in writing on each party’s responsibility for engineering, design, construction, and cost of the facilities identified in the PALCS.87

4. Results of PALS Study Process

After SPP completes the PALS study process outlined in Attachment BG, SPP will determine the PALS Capacity that will be granted for the PALS.88 If SPP determines that there will not be adequate transfer capability to satisfy the full amount of requested PALS Capacity due to considerations on the Transmission System or any third-party systems, SPP will offer the portion of the requested PALS Capacity that can be accommodated without addition of any network facilities.89

SPP and the Transmission Owner will not be responsible for making
arrangements for any necessary engineering, permitting, or construction of transmission or distribution facilities on the system(s) of any other third-party entity or for obtaining any regulatory approval for such facilities.90 Nonetheless, SPP and the affected Transmission Owner(s) will undertake reasonable efforts to assist the Transmission Customer in obtaining such arrangements, including providing required information or data pursuant to Good Utility Practice.91

The costs of constructing, operating, maintaining, or retiring a PALS delivery point, other than any required Network Upgrades, will be recovered under the Tariff,

85 Id.
86 Proposed Tariff, Attachment BG, Section 3.3.
87 Proposed Tariff, Attachment BG, Section 4.0.
88 Proposed Tariff, Part VIII, Section 57.7.
89 Id.
90 Proposed Tariff, Part VIII, Section 59.1.
91 Id.

PDF page 17

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 17

including Attachment BG, and Commission policy.92 If a design changes because facilities cannot be sited or constructed as proposed, or if new statutory or regulatory requirements or other circumstances beyond SPP’s or the Transmission Owner’s control significantly affect costs, a revised good faith estimate is required.93 These provisions mirror the corresponding provisions for CHILLS in Part VII, Sections 49.2 and 49.3 of the Tariff.

5. PAL Service Agreement

As part of this filing, SPP is proposing a new pro forma service agreement for PALS, which is attached as Addendum 2 of Attachment BG to the Proposed Tariff.94 The PALSA is modeled after the current Non-Firm Point-To-Point Transmission Service Agreement (Attachment B)95 and the Network Integration Transmission Service (“NITS”)96 Agreement (Attachment F).97 The PALSA includes language that is similar to the Attachment B and Attachment F service agreements, such as: (1) the parties’ names; (2) a statement that the Transmission Customer completed an application pursuant to the Tariff requirements; (3) a statement that an authorized agent has requested PALS; (4) a statement that the authorized agent agrees to take PALS subject to the provisions of the Tariff; (5) the delivery points of the PALS and the location of the load; (6) applicable Tariff-authorized transmission and ancillary service charges; and (7) requirements for power losses.98 Unlike other service agreements for firm transmission service, the PALSA provides that the Transmission Customer will receive the delivery of energy subject to availability and to Curtailment, Interruption, or load shed under the terms of the Tariff, including Section 58 of Part VIII and Attachment BG of the Proposed Tariff.99 Section 11.0 of the PALSA also requires the Transmission Customer to have control technologies and/or protection systems, while may include a special protection scheme, to keep withdrawals within the PALS Usage

92 Proposed Tariff, Part VIII, Section 59.2.
93 Proposed Tariff, Part VIII, Section 59.3.
94 Proposed Tariff, Attachment BG, Addendum 2.
95 Tariff, Attachment B.
96 Tariff, Part I, Section 1, Definition of Network Integration Transmission Service (“The transmission service provided under Part III of the Tariff.”).
97 Tariff, Attachment F.
98 Proposed Tariff, Attachment BG, Addendum 2.
99 Proposed Tariff, Attachment BG, Addendum 2, Section 6.0.

PDF page 18

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 18

Limit, Curtailment limit, and Interruption limit.100 This requirement is consistent with the Show Cause Order.101 The PALSA contains an appendix that provides information regarding PAL delivery points and the amount of PALS Capacity studied.102

The PALSA outlines the rights and responsibilities of the parties and specifies which Tariff sections apply to the Transmission Customer for SPP’s provision of energy at the PALS delivery point. Importantly, Section 17.0 of the PALSA requires that each PAL have a separate metered quantity, apart from any firm load served at the same point of delivery, and that any generation located at the same point of delivery will be metered separately from the PAL and separately from any firm load at the same point of delivery. The separately metered quantities are necessary as PALS is neither NITS nor Point-To-Point Transmission Service and must be billed differently and distinctly from other transmission service taken at the same delivery point. Although Transmission Customers are required to take the same type of transmission service at the same point of delivery, providing PALS at potentially the same location as other service is necessary to accommodate the unique needs of large loads for a new type of non-firm, conditional transmission service.

Section 17.0 also describes how Transmission Customers will be charged in instances where both Network Load and PALS load are located at the same point of delivery as Behind-The-Meter Generation. Section 17.0 states:

For instances where both Network Load and PALS load are
located at the same point of delivery with Behind-The-Meter
Generation, as defined in Attachment AE of the Tariff, the
Network Load must be adjusted to (1) add the hourly output
of any Behind-The-Meter Generation that is located on the
Network Load side of the Network Integration Transmission
Service (“NITS”) meter and is not behind a PALS meter, and
(2) subtract the positive (inflow, or PALS load) or negative
(outflow) amount registered on any PALS meter located
behind the NITS meter.103

This provision accounts for Behind-The-Meter Generation so that all generation and load are properly reflected in transmission settlements and no load reported for NITS is netted.  The Network Load amount will be adjusted to add the MW amount of

100 Proposed Tariff, Part VIII, Section 56.1(g); Attachment BG, Addendum 2, Section 11.0.
101 Show Cause Order at PP 83, 87.
102 Proposed Tariff, Attachment BG, Addendum 2, Appendix 1.
103 Proposed Tariff, Attachment BG, Addendum 2, Section 17.0.

PDF page 19

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 19

Behind-The-Meter Generation that is displacing Network Load.104  This treatment is consistent with SPP’s existing practice of no netting Behind-The-Meter Generation in determining NITS charges. It also makes PALS available to Eligible Customers serving load with Behind-The-Meter Generation, a category of Eligible Load identified in the Show Cause Order.105

After SPP provides the PDPLA study report to the Transmission Customer and determines that the customer is eligible to receive PALS, the Transmission Customer may request that SPP update or provide a new PALSA106 for the studied PAL delivery point. After SPP and the Transmission Customer execute the PALSA, SPP will submit the PALSA to the Commission in compliance with applicable Commission regulations.107 Concurrently with the submittal of the PALSA, a transmission service request will be entered into SPP's OASIS to reflect necessary service and the PALS Capacity levels for billing purposes.108

The PALSA also addresses termination. Service ends at the end of the term stated in the agreement, or earlier if the Tariff is terminated, the customer requests termination, or other transmission service is established for the PAL. SPP may terminate the PALSA if PALS is not used for one (1) year. After termination, the customer may not take capacity above the level of any other transmission service it holds at the delivery point.109 The PALSA may not be assigned, resold, or transferred, consistent with Part VIII, Section 54.5 of the Tariff.110 It also requires the customer to take Ancillary Services under Schedules 1, 1-A1, and 2 through 6.111

104 Id.
105 Show Cause Order at n.140. 106 Proposed Tariff, Attachment BG, Addendum 2.
107 Proposed Tariff, Attachment BG, Section 5.0.
108 Id.
109 Proposed Tariff, Attachment BG, Addendum 2, Section 9.0.
110 Id. at Section 14.0. 111 Id. at Section 20.0.

PDF page 20

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 20

6. PALS Operating Agreement

The PALS Operating Agreement,112 in Addendum 3 to Attachment BG, is substantially similar to the pro forma Operating Agreement for CHILLS (“CHILLS Operating Agreement”) in Addendum 2 to Attachment BA of the Tariff).113 Similar to the CHILLS Operating Agreement, the PALS Operating Agreement outlines the terms and conditions under which SPP, the Host Transmission Owner, and the Transmission Customer will coordinate, describes how the Host Transmission Owner and the Transmission Customer will operate their respective systems, and specifies the equipment that will be installed and operated.114 The PALS Operating Agreement is necessary for coordination among SPP, the Transmission Customer, and the Host Transmission Owner to ensure the safe and reliable operation of the Transmission System.

7. Additional Provisions Under Part VIII of the Proposed Tariff

Prior to the SPP providing the PALS Service Commencement Date,115 SPP, the affected Transmission Owner(s), and the Transmission Customer, or a third party, must complete installation of all equipment specified under the PALS Operating Agreement consistent with Good Utility Practice and any additional requirements reasonably and consistently imposed to ensure the reliable operation of the Transmission System.116 SPP and the affected Transmission Owner(s) are required to exercise reasonable efforts, in coordination with the Transmission Customer, to complete such arrangements as soon as practicable, taking into consideration the Service Commencement Date.117

112 Proposed Tariff, Part I, Section 1, Definition of PALS Operating Agreement (“An executed agreement that contains the terms and conditions under which the Transmission Customer or Network Customer will operate its facilities and the technical and operational matters associated with the implementation of PALS under Part VIII of the Tariff.”).
113 Compare Proposed Tariff, Attachment BG, Addendum 3 with Tariff, Attachment BA, Addendum 2.
114 Proposed Tariff, Attachment BG, Addendum 3.
115 Tariff, Part I, Section 1, Definition of Service Commencement Date (“The date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Section 15.3 or Section 29.1 under the Tariff.”).
116 Proposed Tariff, Part VIII, Section 57.3.
117 Id.

PDF page 21

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 21

SPP or its agent must have access to the metering data needed for measurement and billing under the PALSA.118 Unless otherwise agreed, the customer must maintain a power factor within the range SPP specifies in consultation with the Transmission Owners, as set out in the PALS Operating Agreement.119

8. Load Shedding and Curtailments related to PALS

As previously stated, PALS is subject to Curtailment on a non-discriminatory basis in the event the Transmission System is constrained or under Emergency Conditions.120 SPP reserves the right to curtail (or cause to be curtailed), in whole or in part, PALS for any reliability conditions that threaten to impair or degrade the reliability of the Transmission System or the systems directly or indirectly interconnected with the Transmission System.121 Prior to the PALS Service Commencement Date, SPP, in coordination with the affected Transmission Owner(s) and the Transmission Customer, will establish Load Shedding and Curtailment processes pursuant to the PALS Operating Agreement, as described above, with the objective of responding when an Emergency Condition or other unforeseen condition threatens to impair or degrade the reliability of the Transmission System or systems interconnected with the Transmission System.122 The parties, including the affected Transmission Owner(s), will implement Load Shedding and Curtailment processes during any period when SPP determines that such system conditions exist and actions are necessary to alleviate said conditions.123 SPP will notify all affected Transmission Customers and Transmission Owners of any scheduled Curtailment in a timely manner or as soon as practical in instances when it is impractical to provide advance notice.124

Additionally, during any period when SPP determines that a transmission constraint exists on the Transmission System, and such constraint may impair the reliability of the Transmission System, SPP will take whatever actions, consistent with Good Utility Practice and Attachment BG of the Proposed Tariff, that are reasonably necessary to maintain the reliability of the Transmission System.125 To the extent SPP

118 Proposed Tariff, Part VIII, Section 60.2.
119 Proposed Tariff, Part VIII, Section 60.3.
120 Proposed Tariff, Part VIII, Section 54.2.
121 Proposed Tariff, Part VIII, Section 58.1.
122 Id.
123 Id.
124 Id.
125 Proposed Tariff, Part VIII, Section 58.2.

PDF page 22

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 22

determines that the reliability of the Transmission System can be maintained by curtailing a PAL, SPP will initiate procedures consistent with the PALS Operating Agreement to curtail PALS as described in Attachment AE.126

When SPP implements least-cost redispatch to relieve a transmission constraint, all Transmission Customers and Network Customers, including PALS customers, pay their share of redispatch costs through settlement of the Energy and Operating Reserve Markets under Attachment AE.127 If SPP determines that deliveries must be curtailed, the parties will curtail them in accordance with the PALS Operating Agreement.128

To the extent that a system contingency exists on the Transmission System and SPP determines that it is necessary for the affected Transmission Owner(s) and Transmission Customers to shed load, the parties must shed load in accordance with the procedures of the PALS Operating Agreement.129

If the Transmission Customer fails to fully respond to established Load Shedding and Curtailment procedures or to cease or reduce service in response to a directive by SPP, the Transmission Customer will pay any applicable charges and the penalty as described in Section 54.4 of Part VIII of the Proposed Tariff and as discussed in further detail below.130

9. Rates for PALS, Failure to Curtail PALS, and Exceedance of
PALS Capacity

Because PALS charges, while similar to those for hourly Non-Firm Point-To- Point Transmission Service, differ from other transmission charges in the Tariff, SPP proposes a new schedule, Schedule 16, to outline charges related to PALS.131 The Transmission Customer must compensate SPP for the PALS up to the monthly sum of the applicable charges outlined in Schedule 16, in addition to any other applicable charges specified in the Tariff.132 Specifically, the Transmission Customer must pay

126 Id.
127 Proposed Tariff, Part VIII, Section 58.3.
128 Proposed Tariff, Part VIII, Section 58.4.
129 Proposed Tariff, Part VIII, Section 58.5.
130 Proposed Tariff, Part VIII, Section 58.6.
131 Proposed Tariff, Schedule 16.
132 Id.; see also Proposed Tariff, Part VIII, Section 61.

PDF page 23

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 23

the zonal rate (per kilowatt) based upon the Zone133 where the PAL is located.134 The zonal rate will be the hourly rate applicable to Non-Firm Point-To-Point Transmission Service for the specific on-peak or off-peak hour of the PALS Usage.135 For each hour, the hourly charge will be calculated using kilowatts of the PALS Usage, subject to other provisions in Schedule 16.136

The application of hourly Non-Firm Point-To-Point Transmission Service rates is appropriate because it addresses the expected dynamic use of the Transmission System by the PAL. Charging the rate applicable to the specific on-peak or off-peak hour for the PALS Usage appropriately aligns with the Transmission Customer’s authorization to utilize the Transmission System in each hour. Capping the monthly PALS charge at the monthly Non-Firm Point-To-Point Transmission Service rate multiplied by the maximum hourly PALS Usage in that month further aligns PALS with Non-Firm Point-To-Point Transmission Service.137

PALS customers also pay the Base Plan Zonal Charge, Subregional Charge, and Region-wide Charge under Schedule 11. Each is assessed hourly at the applicable Non-Firm Point-To-Point Transmission Service rate for the specific on-peak or off- peak hour of PALS Usage.138 Each of these charges is capped for the month at the applicable monthly rate multiplied by the maximum hourly PALS Usage in that month, which matches the cap on the Schedule 16 transmission charge.139 Schedule 11 revenues from PALS are credited against Transmission Owners’ annual transmission

133 Tariff, Part I, Section 1, Definition of Zone (“The geographic area of the facilities of a Transmission Owner or a specific combination of Transmission Owners as specified in Schedules 7, 8, and 9.”).
134 Proposed Tariff, Schedule 16, Section 1.
135 Id. 136 Id.
137 Tariff, Part I, Section 1, Definition of Non-Firm Point-To-Point Transmission Service (“Point-To-Point Transmission Service under the Tariff that is reserved and scheduled on an as-available basis and is subject to Curtailment or Interruption as set forth in Section 14.7 under Part II of this Tariff.  Non-Firm Point-To-Point Transmission Service is available on a stand-alone basis for periods ranging from one hour to one month.”).
138 Proposed Tariff, Schedule 11, Section VI; Schedule 16, Section 7.
139 Proposed Tariff, Schedule 16, Section 7.

PDF page 24

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 24

revenue requirements in the same way as Point-To-Point Transmission Service and CHILLS revenues.140

If the Transmission Customer exceeds its PALS Usage Limit at any delivery point, the Transmission Customer must pay, in addition to the charges for all of the PALS Usage, one-hundred percent (100%) of the Non-Firm Point-To-Point Transmission Service charges under Schedules 8 and 11 for the period when the additional service was used, as detailed in Proposed Section 54.4.141 SPP will compensate the Transmission Owners for service and allocate penalty revenues in the manner as described in Section 54.4 of the Proposed Tariff.142 The application of Schedule 8 and Schedule 11 charges is appropriate because unreserved use at a PALS delivery point will be monitored and charged at a time granularity similar to Non-Firm Point-To-Point Transmission Service. An excess of one (1) hour or less will be billed at the charge for weekday deliveries.143 Repeated daily use of unreserved capacity within a seven-day period will increase the duration of the period to a weekly duration and multiple instances of unreserved use during more than one seven-day period during a calendar month will increase the duration of the period to a month.144

Transmission Customers taking PALS will be responsible for any real power losses.145 The delivery loss factors are set forth in Appendix 1 to Attachment M of the Tariff146 and will be applied to the PALS Usage amount, including any load exceeding the PALS Usage Limit.147 This reflects the fact that PALS is served and metered at the delivery point of the load, similar in this regard to Network Load.

The treatment of PALS unreserved use under these Proposed Tariff provisions aligns with the treatment of Non-Firm Point-To-Point Transmission Service unreserved use. Revenues received for unreserved use of the Transmission System will be distributed pursuant to the provisions of Section 54.4 of Part VIII of the Proposed

140 Proposed Tariff, Schedule 11, Section II.A. 141 Proposed Tariff, Part VIII, Section 54.4.
142 Proposed Tariff, Part VIII, Section 58.6.
143 Proposed Tariff, Part VIII, Section 54.4.
144 Proposed Tariff, Part VIII, Section 54.4.
145 Proposed Tariff, Part VIII. Section 55.3; see also Proposed Tariff, Attachment M, Section VI.
146 Tariff, Attachment M, Appendix 1.
147 Proposed Tariff, Part VIII. Section 55.3; see also Proposed Tariff, Attachment M, Section VI.

PDF page 25

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 25

Tariff. Consistent with other unreserved use charges outlined in the Tariff, the Transmission Customer receiving PALS must purchase losses pursuant to Section 55.3 of the Proposed Tariff for amounts exceeding the PALS Usage Limit.148 These unreserved use charges reflect that the PAL is to use only the PALS Capacity that was studied through the transmission service process described in Attachment BG and is to appropriately respond to Curtailment or Load Shedding directives from SPP.

Proposed Schedule 16 also outlines other charges that are applicable to PALS which are consistent with similar charges applicable to other transmission service types, such as Redispatch Costs specified in Attachment K and applicable Wholesale Distribution Service Charges.149

10. PALS Satisfies the Show Cause Order’s Non-Firm Contract
Demand Directive, With Appropriate Regional Variation

The Show Cause Order directed SPP to explain “whether the Tariff remains just and reasonable without (1) an interim non-firm network transmission service while Network Upgrades are being constructed (i.e., interim NITS) and (2) permanent firm and non-firm contract demand transmission services (transmission service up to a specified MW quantity, i.e., the contract level, on a firm or non-firm basis).”150  PALS responds to the non-firm element of the second part of that directive. It establishes a non-firm service that serves the same purpose as the non-firm contract demand (“Non- Firm Contract Demand”) transmission service the Commission required of PJM, with regional variations appropriate to SPP. SPP addresses interim NITS and firm contract demand service in the separate filings identified in Section V.

In the PJM Co-Location Order, the Commission “establish[ed] a new Non-Firm Contract Demand transmission service to be offered to Eligible Customers taking service on behalf of Co-Located Loads.”151 The following are requirements the Commission established for the Non-Firm Contract Demand service:

• “We find that the new Non-Firm Contract Demand transmission service must be available during normal operations and curtailed during emergency operations (i.e., it will be curtailed before existing firm transmission services and the new Firm Contract Demand Transmission Service).”152

148 Proposed Tariff, Part VIII, Sections 54.4 and 55.3.
149 Proposed Tariff, Schedule 16, Sections 3 and 6.
150 Show Cause Order at P 83.
151 PJM Co-Location Order at P 214.
152 Id. at 215.

PDF page 26

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 26

• “Reservations under this service would be available only when there is available transmission capacity, similar to existing non-firm transmission service options in the Tariff.”153

• “Reservations for this service shall be available for terms ranging from one hour to one month, consistent with the terms available for Non-Firm PTPS in the PJM Tariff.”154

• “[S]hould the Eligible Customer taking the Non-Firm Contract Demand transmission service on behalf of the Co-Located Load make unreserved use of the transmission system by withdrawing energy in excess of its transmission service reservation, PJM must apply a penalty rate in such circumstances.”155

• “The new Non-Firm Contract Demand transmission service will not include a charge for generation capacity. Because it is non-firm transmission service, PJM will not have an obligation to serve Eligible Customers taking this new Non-Firm Contract Demand transmission service on behalf of Co-Located Loads; thus, unlike Network Load, Co-Located Loads on whose behalf Eligible Customers are taking Non-Firm Contract Demand transmission service would not be considered for resource adequacy planning purposes.”156

Similar to the Non-Firm Contract Demand, the PALs will be available during normal operation and will be curtailed during emergency operations. Also, PALS will be as-available, similar to hourly Non-Firm Point-to-Point Transmission Service available in the Tariff. PALS customers will also be charged for any unreserved use of the transmission system, including above the PALS capacity or failure to not curtail when directed by SPP. Lastly, PALS will not be required to bring any supported generation to support load and as such the load will not be included in any SPP resource adequacy planning process.

Unlike Non-Firm Contract Demand, PALS is not a reserved capacity
transmission product. PALS is flexible to allow the PALS customer to withdraw from the Transmission System, on an as-available basis, and only pay when it withdraws, instead of paying for the reservation. The PALS is billed only on an hourly basis when the Transmission Customer takes the service, but the PALS charges will be capped at the monthly Point-To-Point Transmission Service price.

The Show Cause Order expressly contemplated “regional variation as
appropriate.” PALS gives Eligible Customers serving flexible loads a non-firm transmission service up to a specified MW quantity (the PALS Capacity). It therefore

153 Id.
154 Id.
155 Id. at 217.
156 PJM Co-Location Order at P 218.

PDF page 27

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 27

supplies the service the Commission found lacking in the Tariff, adapted to SPP’s market design. With PALS in place, the Tariff is just and reasonable with respect to non-firm contract demand service.

As described in SPP’s responsive filing in EL26-68-000, SPP’s Tariff remains just and reasonable without the remaining transmission service products outlined in the PJM Co-Location Order, either because existing or concurrently proposed Tariff provisions provide comparable service or because regional differences warrant a different approach.

11. PALS Will Not Disrupt Existing Commercial Arrangements

The Show Cause Order directs that any Section 205 filing explain how the proposal will avoid disrupting existing commercial arrangements and identify a reasonable effective date that accommodates them.157 PALS satisfies this requirement. PALS is a new, voluntary service option. It does not modify any existing service agreement, transmission service reservation, or pending study request, and it does not alter the terms of existing transmission service processes (i.e. NITS, Point-To-Point Transmission Service, CHILLS, HILLS). No existing customer is required to convert to PALS, and Eligible Customers with agreements nearing completion are free to proceed under existing Tariff process. Because PALS is an as-available service with priority equal to hourly Non-Firm Point-To-Point Transmission Service, it does not reduce the Available Transfer Capability available to firm customers or CHILLS. As discussed in Section VI, PALS will apply prospectively once SPP implements the necessary system changes, currently targeted for the second quarter of 2028.

C. SPP Integrated Marketplace Requirement for PALS

1. PALS Integrated Marketplace Overview

PALS combines a new form of non-firm transmission service with a new framework for dispatchable load participation in SPP’s Integrated Marketplace. To reflect the price sensitivity and operational flexibility that distinguish PALs from conventional load, SPP proposes revisions to Attachment AE that allow PALs to submit a different form of Energy Bids and to receive Dispatch Instructions. The proposed market rules also establish appropriate bidding parameters, operating limits, settlement requirements, and consequences for deviations from SPP’s instructions.

Currently, in the Integrated Marketplace, all load (except for CHILLs) to be served by the market uses the same processes. In the Day-Ahead Market, the Market Participants submit the MW quantity and location of physical load through use of

157 Show Cause Order at P 32.

PDF page 28

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 28

Demand Bids158 and can also submit Virtual Energy Bids.159 These Demand Bids and Virtual Energy Bids may be fixed or price sensitive. After the Day-Ahead Market, SPP uses a load forecast to determine the amount of load to be served for the Reliability Unit Commitment (“RUC”) processes and the RTBM.160 Because SPP uses a forecast for the RUC processes and the RTBM, there is currently not a way for market processes to distinguish between non-firm loads based on price sensitivity, as there is in the Day- Ahead Market. In order for price-sensitive loads to have that price-sensitivity reflected in the RTBM, they must register and participate as Demand Response and must also reserve firm transmission service.

PALs are distinct from Demand Response. Unlike PALs, Demand Response is provided by loads with existing firm service that voluntarily curtail energy withdrawals and relinquish their previously contracted firm right to consume energy. Such participation is contingent upon meeting applicable program requirements, including confirmation of Resource Adequacy where required. PALS, like CHILLS, is not a firm service. PALs will pay different transmission rates, will not have transmission built to serve them, and do not require adequate Resources to serve them on a firm basis. Unlike Demand Response, compensating PALs for reducing withdrawals that they have no firm right to take would pay them for forgoing service they never purchased.

2. PALS Energy Bids

SPP proposes to define the PAL Energy Bid Curve as Megawatt and dollars per Megawatt-hour with up to ten (10) price/quantity pairs.161 These are the same limitations on Energy Offer Curves and Demand Bid Curves used in the Day-Ahead Market.  This allows PALs the ability to economically participate in the market and to reflect their flexibility via the PAL Energy Bid Curve submitted.

For PALS, SPP proposes to allow PALs to enter PAL Energy Bids and have that price sensitivity function in both the Day-Ahead Market and the RTBM. PAL Energy Bids include the following parameters:  (1) PAL Energy Bid Curve, (2)

158 Tariff, Attachment AE, Section 1.1, Definition of Demand Bid (“A proposal by a Market Participant associated with a physical load to purchase a fixed or price sensitive amount of Energy at a specified location and period of time in the Day-Ahead Market.”).
159 Tariff, Attachment AE, Section 1.1, Definition of Virtual Energy Bid (“A proposal by a Market Participant to purchase Energy at a specified price, Settlement Location and period of time in the Day-Ahead Market that is not associated with a physical load.”).
160 Tariff, Attachment AE, Section 3.1.2(1).
161 Proposed Tariff, Attachment AE, Section 1.1.

PDF page 29

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 29

Withdrawal Ramp Rate,162  (3) Maximum Daily Withdrawal,163 (4) Maximum Withdrawal Limit,164 (5) RTBM Maximum Withdrawal Limit165 (RTBM only), and (6) Intra-Interval Maximum Withdrawal Limit166 (RTBM only).167 These inputs in the new Section 4.3.4 of Attachment AE give SPP insight into the behavior and abilities of the PAL in a way that will allow SPP to economically dispatch it.

A bid cap is necessary because PALs differ from other loads served by the Transmission System. PALs do not directly fund Network Upgrades or bring supporting Resources, and the Transmission System is not planned or expanded to serve them. Absent a bid cap, however, the market optimization would treat PAL Energy Bids like any other demand. When PAL withdrawals cause a transmission constraint to bind in a given interval, the optimization could redispatch Resources around that constraint, potentially at significant cost, to keep serving the PAL. The cost of that redispatch shows up as congestion and raises Locational Marginal Prices (“LMP”) for firm loads that are responsible for directly assigned costs related to Network Upgrades needed to establish the transmission service. A bid cap prevents this by limiting PAL withdrawals when LMPs exceed the established cap, so PALs consume energy only when the system can serve them while containing the costs to firm load customers. In this respect, PALS is most comparable to Non-Firm Point-To- Point Transmission Service, which is also as-available, does not directly fund Network Upgrades, and upon which PALS rates are based. Non-Firm Point-To-Point

162 Proposed Tariff, Attachment AE, Section 1.1, Definition of Withdrawal Ramp Rate (“A Bid parameter for PALs consisting of a curve specifying the maximum MW/minute ramp rates used for dispatching the PAL in the direction of increasing withdrawal.”).
163 Proposed Tariff, Attachment AE, Section 1.1, Definition of Maximum Daily Withdrawal (“A daily parameter for PALs specifying the maximum total withdrawal across an Operating Day in Megawatt hours.”).
164 Proposed Tariff, Attachment AE, Section 1.1, Definition of Maximum Withdrawal Limit (“A Bid parameter for Price Adaptive Load specifying the maximum Megawatt quantity a Price Adaptive Load is willing to consume in a specific Operating Hour.”).
165 Proposed Tariff, Attachment AE, Section 1.1, Definition of RTBM Maximum Withdrawal Limit (“A Real-Time Bid parameter for a Price Adaptive Load that establishes the maximum withdrawal dispatch in the RTBM for a specific Dispatch Interval.”).
166 Proposed Tariff, Attachment AE, Section 1.1, Definition of Intra-Interval Maximum Withdrawal Limit (“A continuously updateable Bid for PALS parameter specifying the Real-Time maximum withdrawal MW limit used in the calculation of the Setpoint Instruction.”).
167 Proposed Tariff, Attachment AE, Section 4.3.4.

PDF page 30

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 30

Transmission Service, however, is granted only when SPP determines that transmission capacity is available, which limits its effect on LMPs. Because PALs are instead dispatched economically by the market, the bid cap serves a comparable function, allowing SPP to realize the operational and efficiency benefits of flexible load participation while protecting other loads from the costs of serving load without supporting transmission or generation.

SPP proposes to cap the high end of PAL Energy Bid Curves at $25/MWh.168 As discussed below, SPP selected this level based on simulations of PAL participation under a range of bid caps and on stakeholders' preference for an initially conservative bid cap.

The proposed fixed $25 bid cap is just and reasonable. Because PALs represent a new load participation model in the Integrated Marketplace, no historical operational experience or market data currently exists to support a more dynamic or formula-based approach. Under these circumstances, a fixed bid cap provides transparency, certainty, and administrative simplicity as SPP integrates PALs into market operations and gains experience with their performance and impacts.

To ensure the bid cap remains appropriate over time, SPP will review the bid cap, at minimum, annually.169 As operational experience and market data become available, SPP will evaluate whether modifications to the bid cap are warranted, including the potential adoption of a formula-based methodology in the future.

SPP bases its proposed $25 bid cap on simulation information that balances several different interests. SPP sought to balance protection of load from high LMPs, protect reliability, increase transmission revenues, prevent excessive wear from Resource start-ups, limit utilization of emissions permit constrained or duration limited resources, more fully use available wind generation, reduce make whole payments, and allow PALs to have a load factor that allows them to be viable. Using historical SPP market data, SPP compared a base case with no PALs against scenarios in which PALs participated under fixed bid caps ranging from $20 to $35.170

The simulation results indicate that a $25 bid cap captures the system benefits of PAL participation while limiting the impact on other customers. For example, the

168
Proposed Tariff, Attachment AE, Section 4.3.4.1.
169 See Revision Request 791, Proposed Market Protocols, Section 4.2.3.4.1, available at: https://www.spp.org/spp-documents-filings/?id=21069. 170 The simulations modeled 10 PALs, each 200 MW, at Settlement Locations with historically low LMPs. Each simulation covered seven consecutive days (the 10th through the 16th) of every other month beginning in February 2025, or 42 days in total, to capture seasonal and weekday/weekend dynamics.

PDF page 31

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 31

additional wind generation dispatched in the RTBM relative to the base case increased from the $20 to the $25 scenario but did not increase further at higher bid caps. Gas- fired Resource start-ups also declined relative to the base case, with most of the reduction occurring at or below the $25 bid cap. At the same time, a $25 bid cap allows meaningful PAL participation. Raising the cap from $20 to $25 increased the PAL load factor in the RTBM from 45 percent to 60 percent, the largest increase of any step studied, which supports the viability of PALs as a service. In contrast, price impacts to other customers rose more quickly above $25: the average RTBM LMP increased by $0.20/MWh between the $20 and $25 scenarios, but by $0.80/MWh between the $25 and $30 scenarios. Taken together, these results indicate that a $25 bid cap strikes a just and reasonable balance among the interests described above.

The proposed $25 bid cap is also not unduly discriminatory. It applies uniformly to every PAL, and PALs are not similarly situated to loads that are not subject to it. Firm loads must be supported by accredited capacity and receive firm service; CHILLs must have supporting generation in commercial operation. PALs have no Resource Adequacy obligation and are added without supporting generation. All else equal, adding load without adding supply raises LMPs for existing customers. The cap confines PAL withdrawals to the highly price-elastic portion of SPP's supply curve, where added demand has the least price impact.

PALS represents a different approach to non-firm load than CHILLS and is designed for loads with price-flexibility central to their business case. CHILLS is a bridge to firm service, so the approach to when to reduce service to CHILLs is more reliability centered. The approach to PALS is a capped economically centered approach with additional limits for reliability.

3. Dispatch, Settlement, and Uninstructed Load Deviation

SPP will use the PAL Energy Bids to issue Dispatch Instructions for the PAL. If the LMP at the PAL Settlement Location is above $25, then the PAL will receive Dispatch Instructions for a 0 MW withdrawal. Under other conditions, the PAL may be instructed to withdraw some or all of the MW up to their Maximum Withdrawal Limit, depending on its PAL Energy Bid Curve. In the Integrated Marketplace, PALs that are outside of their Operating Tolerance may be assessed an Uninstructed Load Deviation (“ULD”)171 charge, as well as be assessed RUC make whole payment distribution. ULD charges and RUC make whole payment distribution are market charges, and work within the market. Separately, because PALS is a transmission service, a PAL that withdraws more than its PALS Usage Limit, including during a

171 Proposed Tariff, Attachment AE, Section 1.1, Definition of Uninstructed Load Deviation (“The Megawatt quantity by which a PAL’s Reported Load in a Dispatch Interval deviates from the instruction issued by the local transmission operator or Transmission Provider.”).

PDF page 32

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 32

Curtailment, will be assessed unreserved use charges, as discussed in Section III.B.9 above.

PALs are subject to ULD charges for any Dispatch Interval in which their withdrawal falls outside the PAL Upper Operating Tolerance or PAL Lower Operating Tolerance172.173 The PAL Upper Operating Tolerance is based on the greater of the PAL’s Dispatch Instruction for the current Dispatch Interval and its Dispatch Instruction for the previous Dispatch Interval.174 The PAL Lower Operating Tolerance is based on the PAL’s RTBM Maximum Withdrawal Limit. If the applicable value is fifty (50) MW or less, the tolerance is 10 percent of that value; if it exceeds fifty (50) MW, the tolerance is 5 percent of that value, with a 5 MW floor and a 20 MW ceiling.175 These operating tolerances use the same percentages, MW breakpoints, floor, and ceiling that apply to Resources, applied to values specific to the PAL participation model. As with Resources, the tolerances balance a PAL's ability to precisely follow its Dispatch Instructions against the need to reduce uncertainty in balancing the system. Because the PAL Upper Operating Tolerance is based on the PAL's Dispatch Instructions, a PAL's allowable withdrawal is measured relative to its dispatch, so when SPP dispatches a PAL down, the withdrawal permitted within tolerance decreases accordingly. This ensures the tolerance accommodates limited deviations from dispatch and cannot be used to sustain withdrawals the market has not dispatched.

The penalty for ULD is intended to provide a significant deterrent for failing to operate within the established operating tolerance. Over-withdrawal will be charged at a bounded LMP (floored at $50/MWh and capped at $2,000/MWh) multiplied by a deviation factor that increases from 2.0 to 5.0 as the deviation outside of the operating tolerance grows relative to PALS Capacity; under-withdrawal is charged at the absolute value of the LMP.176 The lower bound is intended to maintain the deterrence factor during low, or even negative, LMPs.177 The upper bound is equal to the hard cap on Energy Offers that can set LMP.178

The value of the deviation factor is calculated as the ULD MW quantity for a Dispatch Interval divided by the PALS Capacity, and that result is then multiplied by

172
Proposed Tariff, Attachment AE, Section 1.1, Definition of PAL Lower Operating Tolerance (“The Megawatt range of a Price Adaptive Load’s withdrawal below its average Setpoint Instruction over the Dispatch Interval within which it will not be subject to charges associated with deviating from its Setpoint Instruction.”). 173

Proposed Tariff, Attachment AE, Sections 6.7.1 and 6.7.3.
174 Proposed Tariff, Attachment AE, Section 6.7.3(1)(a).
175 Proposed Tariff, Attachment AE, Section 6.7.3(1)(b).
176 Proposed Tariff, Attachment AE, Section 8.6.49. 177 Proposed Tariff, Attachment AE, Section 8.6.49(1)(b)(i).
178 Proposed Tariff, Attachment AE, Section 8.6.49(1)(b)(iii).

PDF page 33

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 33

100. If the result of the calculation is: (1) less than or equal to twenty five percent (25%), a deviation factor of 2.0 will apply; or (2) greater than twenty-five 25%, but less than or equal to fifty percent (50%), a deviation factor of 3.0 will apply; or (3) greater than fifty (50%), but less than or equal to seventy-five percent, a deviation factor of 4.0 will apply; or (4) greater than seventy-five (75%), a deviation factor of 5.0 will apply. The result is a range of penalty values from $100/MWh to $10,000 MWh. Using an LMP-based driver ensures that the ULD charge is proportional to the locational value of the energy being withdrawn and reflects underlying market scarcity, with higher LMPs resulting in higher charges.

ULD charges are credited to other Asset Owners on a load ratio share basis, excluding Asset Owners charged ULD.179 It is just and reasonable and not unduly discriminatory to exclude Asset Owners charged ULD as it would dilute the deterrence impact of the charge to give some of the money back to the Asset Owners who are paying the charge. Distribution of ULD charges will help compensate other loads for increased LMPs and these charges give PALs a strong financial incentive to follow dispatch and ensure that other Market Participants do not bear the cost of PAL deviations. Because PALS is a transmission service, failure to curtail when directed may constitute a Tariff violation, which carries additional penalties that incent PALs to follow SPP’s instructions.

SPP also proposes to assign RUC make whole payment distribution for PALs that incur ULD. When Resources are committed after the Day-Ahead Market, they are provided a RUC make whole payment if they do not cover the costs submitted in their Offer through the market. RUC make whole payment distribution funds RUC make whole payments, assigning a proportionate share of the total RUC make whole payments to Asset Owners that drive the need for RUC make whole payments. SPP proposes to assign RUC make whole payment MW in three possible instances for PALs.

First, SPP proposes to assign RUC make whole payment distribution deviation MW to ULD MW if the PAL operated outside of its operating tolerances.180 This provision assigns a share of RUC make whole payment distribution for PALs that are not following their Dispatch Instructions. Doing so is just and reasonable and not unduly discriminatory because a PAL that does not follow its economic dispatch is not operating consistent with the least-cost operation of the market, which increases costs to the market.

179 Proposed Tariff, Attachment AE, Section 8.6.50.
180 Proposed Tariff, Attachment AE, Section 8.6.7(A)(2)(i).

PDF page 34

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 34

Second, SPP proposes to assign RUC make whole payment distribution to the:

positive difference between the PAL Day-Ahead Market cleared
withdrawal quantity and the RTBM Maximum Withdrawal
Limit, provided that: (i) [t]he PAL’s RTBM Maximum
Withdrawal Limit is less than the PAL’s Maximum Withdrawal
Limit used in the Day-Ahead Market by more than the PAL
Lower Operating Tolerance calculated in Section 6.7.3 of []
Attachment AE; (ii) [t]he RTBM Maximum Withdrawal Limit is
less than the Day-Ahead Market cleared withdrawal amount; and
(iii) [t]he  PAL received a Dispatch Instruction greater than or equal to the RTBM Maximum Withdrawal for at least one

Dispatch Interval in the hour.181

Third, SPP proposes to assign RUC make whole payment distribution:

For PALs that cleared withdrawals in the Day-Ahead Market
and that experienced a Setpoint Instruction decrease caused by
the application of their Intra‑Interval Maximum Withdrawal
Limit, the absolute value of the difference between the PAL’s
actual withdrawal and the PAL’s economic operating point.  The
PAL’s economic operating point is the MW withdrawal where
the cost on the PAL’s current Dispatch Interval Energy Bid
curve first exceeds the Real-Time DLMP for that PAL.182

These changes assign RUC make whole payment distribution for MWs where a parameter of the PAL Energy Bid causes the PAL to deviate in Real-Time from the economically optimal point. These changes are just and reasonable and not unduly discriminatory as they assign a share of RUC make whole payments to Asset Owners whose PAL Energy Bids are causing deviations that contribute to differences in Real- Time from the Day-Ahead Market.

SPP’s proposal is a just and reasonable approach that creates a significant financial penalty for non-compliance under similar conditions to those already in the SPP Tariff. When PALs do not follow their dispatch, they can increase LMPs for other participants and negatively impact reliability. SPP anticipates a similar approach to calculating charges for CHILLs that do not follow instructions to reduce load.

181 Proposed Tariff, Attachment AE, Section 8.6.7(A)(2)(j).
182 Proposed Tariff, Attachment AE, Section 8.6.7(A)(2)(k).

PDF page 35

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 35

4. Other Tariff Provisions

In addition, PALs must submit real-time telemetry and five-minute revenue- quality meter data for the PAL.183

To ensure accurate settlement of both transmission and market charges, SPP proposes to require that PALs register at a load Settlement Location that contains only PAL load, and that PAL Meter Data Submittal Locations not be aggregated with those of non-PAL load.184 Because many settlement calculations are performed at the Settlement Location level and PALs are settled differently than other loads, PAL load must be kept separate at that level. In addition, multiple PAL Meter Data Submittal Locations may be aggregated into a single PAL Settlement Location only if the PALs are at the same physical and electrically equivalent point on the Transmission System.185 Because PALs are dispatched and may be subject to penalties for failing to follow Dispatch Instructions, they are more similarly situated to Resources than to other loads. Dispatch and the application of ULD both require location-specific LMPs and metering to be correctly reflected in the market and settled.

SPP's Tariff revisions clarify which requirements govern when a PAL also meets the definition of a HILL. For ramp rates, the PAL requirements supersede the HILL requirements, which removes any ambiguity and avoids applying two sets of ramp limits to the same load.186 PAL is given precedence because it is the more specialized participation model, with its own ramp rate requirements. Similarly, a PAL that is also a HILL is exempt from the Non-Conforming Load forecast requirements.187 Because PALs are dispatched by the market and excluded from SPP's load forecasts, the information SPP needs is already provided through the PAL's bid parameters.

In the execution of the Security Constrained Unit Commitment (“SCUC”) process that is part of the RUC processes, the market clearing engine minimizes commitment cost and not production cost as the Day-Ahead Market SCUC does. Therefore, in the RUC processes, the incremental benefits from meeting PAL Energy Bids are not considered just as the Incremental Energy Offers above minimum for Resources are not considered.188 The effect of this provision is to reduce the ability of PAL Real-Time Energy Bids to drive RUC commitment decisions. This provision does not apply to the Day-Ahead Market or the Security Constrained Economic Dispatch. This provision is consistent with the greater reliability emphasis for RUC processes.

183 Proposed Tariff, Attachment AE, Section 2.26.
184 Proposed Tariff, Attachment AE, Section 2.2(3).
185 Proposed Tariff, Attachment AE, Section 2.2(3).
186 Proposed Tariff, Attachment AE, Sections 2.22(4); 2.26(2)(c).
187 Proposed Tariff, Attachment AE, Section 2.22(1).
188 Proposed Tariff, Attachment AE, Sections 5.2.2(1); 6.1.2(1).

PDF page 36

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 36

Finally, SPP proposes a number of conforming changes to Attachment AE to accommodate the existence of PAL Energy Bids in market processes.  This includes additions to inputs (including limits on PALs consistent with the ability to curtail for any reliability conditions that threaten to impair or degrade the reliability of the Transmission System or the systems directly or indirectly interconnected with the Transmission System), execution, results, and pricing for various market processes. SPP clarifies that PALs are not included in a load deviation charge exemption for Emergency Conditions, as PALs receive Dispatch Instructions and are differently situated from other loads.

These provisions are just and reasonable and not unduly discriminatory as they are needed for SPP to include the right information for PALs in its market processes and to settle PALs correctly.

IV. ADDITIONAL TARIFF REVISIONS

The majority of Proposed Tariff revisions are outlined above. SPP proposes the following revisions, not specifically discussed above, to the Tariff to effectuate the addition of the PALS.

1. Part I, Section 1 (Definitions)

SPP proposes the following changes to the definitions in the main body of the Tariff.189

First, SPP adds the definition for Part VIII of the Tariff to reference Sections 54 through 61 pertaining to PALS in conjunction with the applicable Common Service Provisions of Part I and appropriate Schedules and Attachments.

Second, SPP adds a reference to Part VIII of the Tariff to the following definitions: Load Shedding, Point(s) of Delivery, Point(s) of Receipt, Transmission Customer, and Transmission System.

Third, SPP proposes to add references to Dispatch Instruction and Setpoint Instruction to point to the defined terms within Attachment AE of the Tariff.

189 See generally Tariff, Part I.

PDF page 37

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 37

Fourth, SPP adds the following sentence in the definition of Resource: “A Resource does not include load participating as a Price Adaptive Load, or a Reliability Registered Demand Response Program as defined in Attachment AA of this Tariff190.”

2. Part III (Network Integration Transmission Service)

SPP proposes revisions to Sections 34.1, 34.2, and 34.3 of  Part III of the Tariff describing the Monthly Demand Charge to incorporate references to new Schedule 16 revenue.

3. Schedules

SPP proposes revisions to Schedules 1, 1-A, 11, and 12 of the Tariff to incorporate references to PALS.191 SPP also proposes a revision to Schedule 1-A of the Tariff to specifically state that billing determinants for PALS are as provided in Schedule 16.192 Schedule 2 is modified to specify that Transmission Customers and Network Customers taking PALS will be assessed Schedule 2 charges for each kilowatt of service in a manner consistent with Schedule 16.193 In addition, SPP proposes revisions to Schedule 11 to provide that Transmission and Network Customers taking PALS will be assessed Base Plan Zonal Charges, Subregional Charges, and Region- wide Charges for each kilowatt of service in a manner consistent with Schedule 16.194 SPP also adds a new Section VI to Schedule 11, setting out the Base Plan Zonal Charge, Region-wide Charge, and Subregional Charge for PALS, and revises Section II.A to credit PALS revenue received under Section VI.195

4. Attachment H

Attachment H of the Tariff outlines the Annual Transmission Revenue Requirement for NITS. SPP proposes revisions to Attachment H to incorporate references to revenues under new Schedule 16.196

190
“Reliability Registered Demand Response Program” is a newly defined term pending before the Commission in Docket No. ER26-2249. If the Commission does not accept the filing in Docket No. ER26-2249, SPP will make a clean-up filing with the Commission to appropriately change this definition of “Resource”.

191 See generally Proposed Tariff, Schedules 1, 1-A, 11, and 12. 192 Proposed Tariff, Schedule 1-A. 193 Proposed Tariff, Schedule 2. 194 Proposed Tariff, Schedule 11.
195 Proposed Tariff, Schedule 11, Sections II.A and VI. 196 Proposed Tariff, Attachment H.

PDF page 38

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 38

5. Attachment L

Attachment L, Section II.C currently outlines the distribution of Point-To-Point Transmission Service revenues associated with the Zonal Annual Transmission Revenue Requirements. SPP proposes adding PALS to this section so the PALS revenue under Schedule 16 will be distributed in proportion to the owner-specific Zonal Annual Transmission Revenue Requirements in the Zone where the service is delivered.197 In addition, SPP revises Section III.A of Attachment L to add references to PALS.198

6. Attachment M

SPP adds Section VI to Attachment M, providing that the Transmission Customer or Network Customer is responsible for real power losses associated with PALS under Schedule 16, and that losses associated with settlement in the Integrated Marketplace are accounted for under Attachment AE.199

7. Attachment O

Attachment O, Section I provides an overview of SPP’s transmission planning process. SPP proposes a revision to this section to include a reference to the Attachment BG process as proposed in this filing.200

8. Attachment T

Attachment T includes the rate sheets for Point-To-Point Transmission Service for all applicable Transmission Owners.201 SPP proposes to add references to Schedule 16 revenues in each of the separate rate sheets.202 These proposed changes are necessary to appropriately adjust the Point-To-Point Transmission Service rates for any revenues received for Schedule 16 charges.

9. Attachment AE

SPP proposes revisions to Section 1.1 of Attachment AE to modify and add definitions:203

197 Proposed Tariff, Attachment L, Section II.C.
198 Proposed Tariff, Attachment L, Section III.A.
199 Proposed Tariff, Attachment M, Section VI.
200 Proposed Tariff, Attachment O, Section I.
201 Tariff, Attachment T.
202 Proposed Tariff, Attachment T.
203 See generally Proposed Tariff, Attachment AE, Section 1.1.

PDF page 39

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 39

a. SPP adds a reference to PAL Energy Bid in the definition of Bid.

b. SPP modifies the Demand Bid defined term to include the sentence: “Demand Bids do not include PAL Energy Bids.”

c. SPP adds a reference to PAL in the definition of Dispatch Instruction.

d. SPP revises the definition of Operating Tolerance to add references to PAL and ULD:

“The Megawatt range of a Resource’s or Price Adaptive Load’s actual output above and below its average Setpoint Instruction over the Dispatch Interval within which it will not be subject to charges associated with Uninstructed Resource Deviation or Uninstructed Load Deviation.”

e. SPP adds new definitions PAL, PALS, and PALS Capacity to refer to the defined term in Part I of the Tariff.

f. SPP adds new defined terms PAL Energy Bid, PAL Energy Bid Curve, PAL Lower Operating Tolerance, and PAL Upper Operating Tolerance, as described in Section III.C above.

g. SPP revises the definition of Setpoint Instruction to include Price Adaptive Loads.

h. SPP adds new defined term Uninstructed Load Deviation Adjusted Real-Time Load Ratio Share: “The Real-Time Load Ratio Share that excludes all withdrawal MWs for each Asset Owner that has a ULD charge.”

SPP proposes the following revisions to various sections of Attachment AE:

a. Section 2.2(2) is revised to add a reference to PAL in several locations.204

b. Section 2.11.1 is revised to specify that Billable Metered Load associated with a PAL will be excluded from the calculation of a Market Participant’s maximum hourly Billable Metered Load.205

204 Proposed Tariff, Attachment AE, Section 2.2(2).
205 Proposed Tariff, Attachment AE, Section 2.11.1(A)(1).

PDF page 40

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 40

c. Section 4.3 is revised to reference PAL Energy Bids. SPP also specifies that PAL Energy Bids may only be submitted at load Settlement Locations where a PAL is registered.206

d. Sections 5.1.1, 5.2.1, 6.1.1, and 6.2.1.1 are revised to add references to PAL Energy Bids and to include Transmission Provider limits on the ability to provide PALS in the list of inputs.207

e. SPP adds references to PAL Energy Bids in Section 5.1.2.208

f. Section 5.1.3 is revised to add cleared PAL Energy Bids to the list of Day-Ahead market results.209

g. SPP adds a reference to PAL’s Maximum Withdrawal Limit in Sections 5.2.2 and 6.1.2.210

h. Sections 6.2.1.2 is revised to add a reference to RTBM Maximum Withdrawal Limits (for PALs only) and to include Transmission Provider limits on the ability to provide PALS in the list of inputs.211

i. SPP removes the word “Resource” in regards to Dispatch Instructions in Section 6.2.2 because PALs will also follow Dispatch Instructions.212 In Section 6.2.3, SPP modifies subsection (1)(a) to state “Dispatch Instructions for Resources and PALs.”213

j. Section 6.3 is revised to add references to PAL, and to specify that for PALs, the RTBM Dispatch Instruction will be replaced with the Intra-Interval Maximum Withdrawal Limit value submitted pursuant to Section 4.3.4(6) of Attachment AE, when

206 Proposed Tariff, Attachment AE, Section 4.3.
207 Proposed Tariff, Attachment AE, Sections 5.1.1; 5.2.1; 6.1.1; 6.2.1.1. 208 Proposed Tariff, Attachment AE, Section 5.1.2.
209 Proposed Tariff, Attachment AE, Section 5.1.3. 210 Proposed Tariff, Attachment AE, Section 5.2.2(3)(b); 6.1.2(3)(b).
211 Proposed Tariff, Attachment AE, Section 6.2.1.2.
212 Proposed Tariff, Attachment AE, Section 6.2.2(2). 213 Proposed Tariff, Attachment AE, Section 6.2.3(1)(a).

PDF page 41

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 41

the Intra-Interval Maximum Withdrawal Limit constrains the
RTBM Dispatch Instruction.214

k. Section 6.4.1.2 is revised to specify that PALs will be excluded from load deviation exemptions.215

l. Sections 8.5.1, 8.5.25, and 8.6.1 are revised to add a reference to cleared PAL Energy Bids.216

m. Section 8.5.10 is revised to add a reference to cleared PAL Energy Bids, and to clarify that Export Interchange Transaction Bids and Virtual Energy Bids are cleared.217

10. Attachment AG

Section 4.2 of Attachment AG of the Tariff specifies the data and information that the Market Monitor will review and analyze. SPP adds PAL curtailments and PAL Energy Bids to the list.218

11. Attachment BA

SPP proposes revisions to Section 1 of Attachment BA of the Tariff to add references to Attachment BC, Attachment BG, and Part VIII of the Tariff.219 SPP also adds references to Attachment BG and Part VIII of the Tariff throughout Section 2 of Attachment BA.220 Finally, SPP specifies that the HILL Delivery Point Study (“HDPS”), if requested by the Transmission Customer or Network Customer, will include information detailing the limitations of the Transmission System in supporting any PAL that may be requested.221

214 Proposed Tariff, Attachment AE, Section 6.3(1)(a).
215 Proposed Tariff, Attachment AE, Section 6.4.1.2.
216 Proposed Tariff, Attachment AE, Section 8.5.1; 8.5.25; 8.6.1.
217 Proposed Tariff, Attachment AE, Section 8.5.10(2).
218 Proposed Tariff, Attachment AG, Section 4.2.
219 Proposed Tariff, Attachment BA, Section 1.
220 Proposed Tariff, Attachment BA, Section 2.
221 Proposed Tariff, Attachment BA, Section 2.1.3.4.

PDF page 42

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 42

V. SHOW CAUSE ORDER DIRECTIVES ADDRESSED IN SEPARATE
FILINGS
This filing does not address the remaining Show Cause Order directives. SPP is addressing them as follows:

• the Large Load Safe Harbor Revisions, filed in Docket No. ER27-577- 000;

• the HILL Transmission Service Revisions and the Non-Transmission Facility Revisions in Docket No. ER27-559-000; and

•
SPP’s response to the Show Cause Order in Docket No. EL26-68-000,
which addresses, among other things, transmission and ancillary service rates for co-located load.

SPP respectfully requests that the Commission consider this filing together with the above filings as SPP’s response to the Show Cause Order.

VI. EFFECTIVE DATE AND REQUEST FOR WAIVER

SPP is requesting an effective date of “12/31/9998” for the Tariff Records included with this filing. The expected effective date of the Tariff revisions included herein is currently in the second quarter of 2028, which is more than 120 days after filing. Therefore, SPP requests waiver of the Commission’s notice requirements.222 Good cause exists for the proposed revisions to be effective in the second quarter of 2028 in accordance with the Commission’s waiver of notice requirement codified in Section 35.11 of the Commission’s regulations223 because SPP will need a number of months to develop, test, and implement the software system changes for the Tariff revisions proposed herein. The length of time needed for the software changes is primarily driven by the markets and settlements changes. SPP requests the Commission issue an order by February 17, 2027, to allow SPP sufficient time to make the necessary software changes prior to implementation. The requested effective date also accommodates existing commercial arrangements, as discussed in Section III.B.11, because PALS applies prospectively and does not alter any existing agreement.

222 18 C.F.R. § 35.3(a)(1).
223 18 C.F.R. § 35.11.

PDF page 43

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 43

VII. ADDITIONAL INFORMATION

A. Documents submitted with this filing:

In addition to this Transmittal Letter, SPP provides with this filing Clean and Redlined Tariff revisions under the Sixth Revised Volume No. 1.224

B. Service:

SPP has electronically served a copy of this filing on all its Members, Transmission Customers and Market Participants. A complete copy of this filing will be posted on the SPP web site, www.spp.org, and is also being served on all affected state commissions.

C. Requisite agreements:

There are none.

D. Communications
Correspondence and communications with respect to this filing should be sent to, and SPP requests the Secretary to include on the official service list, the following:225

Emon O. Mahony
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2506
emahony@spp.org

Christopher M. Nolen
Associate General Counsel
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 614-3200
cnolen@spp.org

224
1 Definitions D, 1 Definitions L, and Attachment BA, Section 2 attached to this filing contain language in italics being included in the Large Load Safe Harbor Revisions and/or the HILL Transmission Service Revisions and the Non-Transmission Facility Revisions. In addition, certain other tariff records contained in this filing include language in italics indicating revisions pending before the Commission in the following proceedings: Docket Nos. ER26-2249, ER26-3720, ER27-313, and ER27- 432. In the event that revisions in any of these proceedings are not accepted by the Commission, SPP commits to submit a clean-up filing to remove the language from the Tariff.

225 Pursuant to Commission Rule 101(e), 18 C.F.R. § 385.101(e), SPP requests waiver of Rule 203(b)(3), 18 C.F.R. § 385.203(b)(3), in order to permit more than two persons to be included on the service list.

PDF page 44

The Honorable Debbie-Anne A. Reese
November 19, 2026
Page 44

Justin A. Hinton
Senior Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
Telephone: (501) 482-2468
jhinton@spp.org

VIII. CONCLUSION

For all of the foregoing reasons, SPP respectfully requests that the Commission- issue an order accepting the Tariff revisions proposed herein as soon as practicable but not later than February 17, 2027. SPP will submit a filing with the Commission specifying a precise effective date when that date is known and not less than seven days before that date.

Respectfully submitted,

/s/ Justin A. Hinton
Justin A. Hinton
Emon O. Mahony
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR  72223-4936

Attorneys for
Southwest Power Pool, Inc.