EL26-68-000 · 2026-07-20 · Southwest Power Pool, Inc.
SPP reports on resource adequacy and large-load proposals
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Southwest Power Pool, Inc.
)
Docket No. EL26-68-000
INFORMATIONAL REPORT OF
SOUTHWEST POWER POOL, INC.
Southwest Power Pool, Inc. (“SPP”) respectfully submits this Informational Report in response to the directive issued by the Federal Energy Regulatory Commission (“Commission”) in its June 18, 2026, Order Instituting Proceeding Under Section 206 of the Federal Power Act in Docket No. EL26-68-0001 (“Show Cause Order”). In the Show Cause Order, the Commission directed SPP to provide, within thirty days, a detailed informational report describing: (1) any proposals under consideration in SPP's stakeholder process to address resource adequacy associated with new large loads, or, to the extent no such proposals are under consideration, information regarding how SPP's existing processes are operating to ensure resource adequacy; and (2) for any new proposals under development, a detailed schedule identifying key stakeholder milestones, including anticipated stakeholder and Board actions and the expected date for any future filing with the Commission.2
I. EXECUTIVE SUMMARY
SPP appreciates the Commission's recognition that unprecedented growth in electric demand from data centers, advanced manufacturing, industrial electrification, and other large load customers presents both opportunities and challenges for the electric
1
Sw. Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (“Show Cause Order”).
2 Show Cause Order at P 91.
PDF page 2
2
industry. SPP likewise recognizes the importance of integrating these new loads in a manner that preserves reliability, maintains resource adequacy, and protects existing customers from unreasonable costs.
As large load requests have increased in both number and size, SPP has worked with stakeholders to develop processes that not only evaluate the transmission impacts associated with these customers but also facilitate the timely addition of new generating resources capable of serving that demand. Rather than relying on a single solution, SPP has developed complementary initiatives that improve planning certainty, accelerate the addition of new resources, enhance operational flexibility, strengthen resource adequacy accountability, and better align transmission and interconnection processes with the unique characteristics of emerging large loads.
As discussed in greater detail below, these efforts include:
•
the Expedited Resource Adequacy Study ("ERAS"), which accelerates evaluation of new generating resources intended to support resource adequacy;3
•
the Provisional Load Process, which allows SPP to study proposed delivery point additions using both existing Designated Resources and identified planned generation that is expected to serve the new load;43 Submission of Tariff Revisions to Implement the Expedited Resource Adequacy Study of Southwest Power Pool, Inc., Docket No. ER25-2296-000 (May 22, 2025) (“ERAS Filing”). Tariff, Attachment AW.4 Submission of Tariff Revisions to Implement a Provisional Load Process of Southwest Power Pool, Inc., Docket No. ER26-2430-000 (June 4, 2025) (“Provisional Load Process Filing”). Tariff, Attachment AX.
PDF page 3
3
•
enhanced study procedures for High Impact Large Loads (“HILLs”) to enable SPP to assess the load’s reliability impacts on the Transmission System;5
•
the High Impact Large Load Generation Assessment ("HILLGA") process, which consists of a new generator interconnection service and related interconnection process to allow the limited connection of supporting generation for HILLs on an expedited basis;6
•
the Conditional High Impact Large Load Service ("CHILLS"), which allows a HILL (or a portion of a HILL) to receive the transfer of energy on a long-term, non- firm basis in instances where transmission service is unavailable due to the lack of existing Designated Resources or completion of Network Upgrades necessary to provide firm transmission service;7
•
the Peak Demand Assessment (“PDA”) and Demand Response reforms, which strengthen resource adequacy through enhanced load forecasting accountability and expanded integration of Demand Response Resources, including the Reliability- Registered Demand Response Program (“RRDRP”);85 Submission of Tariff Revisions to Add the High Impact Large Load Processes and High Impact Large Load Generation Assessment of Southwest Power Pool, Inc., Docket No. ER26-247-000, at 11 (Oct. 24, 2025) (“HILL Filing”). Tariff, Attachment BA, Section 2.6 HILL Filing at 11. Tariff, Attachment BB.7 Submission of Tariff Revisions to Add Conditional High Impact Large Load Service of Southwest Power Pool, Inc., Docket No. ER26-1323-000, at 10 (Feb. 10, 2026) (“CHILLS Filing”). Tariff, Part VII and Attachment BC.8 Submission of Tariff Revisions Regarding the Peak Demand Assessment and Demand Response of Southwest Power Pool, Inc., Docket No. ER26-2249-000 (April 17, 2026) (“PDA Filing”). This proceeding is pending before the Commission with a requested effective date of January 1, 2027.
PDF page 4
4
•
the Consolidated Planning Process (“CPP”), which modernizes SPP's regional transmission planning framework by evaluating transmission needs using coordinated assumptions and integrated studies that better account for significant load growth, including emerging large loads;9 and
•
continued stakeholder development of the Price Adaptive Load (“PAL”) product and Price Adaptive Load Service ("PALS"), intended to address the evolving needs and desire for flexibility of large load customers while preserving system reliability.10
Although several of these initiatives have only recently become effective, they represent significant changes to SPP's transmission service, markets, operations, resource adequacy and interconnection frameworks and provide important tools for ensuring that integration of large loads into the SPP Region is done in a way that facilitates the continued safe and reliable operation of the Transmission System. The Commission has repeatedly recognized SPP's proactive approach to addressing large load growth, emphasizing the innovative and forward-looking nature of these reforms.
This report provides details regarding the evolution of these existing processes, explains how they collectively contribute to resource adequacy, and describes ongoing stakeholder efforts to implement additional enhancements. As with prior large load initiatives, any future Tariff revisions will be developed and approved through SPP's
9 Submission of Revisions to the SPP Open Access Transmission Tariff to Implement the Consolidated Planning Process of Southwest Power Pool, Inc., Docket No. ER26-414- 000 (Nov. 3, 2025) (“CPP Filing”). Tariff, Attachment AY.10 See Price Adaptive Load Service Revision Request posted at: https://www.spp.org/spp- documents-filings/?id=21069 (see zip file “RR791 SIR796 Price Adaptive Load”) (“RR 791”).
PDF page 5
5
established stakeholder process before being submitted to the Commission for review. Consistent with the Commission's directive, this report also provides the anticipated schedule for stakeholder consideration of the PAL/PALS proposal currently under development.
II. BACKGROUND
A. SPP
SPP is a Commission-approved Regional Transmission Organization (“RTO”).11 It is an Arkansas non-profit corporation with its principal place of business in Little Rock, Arkansas. SPP currently has 154 members, including 16 investor-owned utilities, 16 municipal systems, 26 generation and transmission cooperatives, 6 state agencies, 28 independent power producers, 11 power marketers, 18 independent transmission companies, 3 federal agencies, 18 large retail customers, 4 alternative power entities, and 8 public interest entities. As an RTO, SPP: (1) administers, across the facilities of SPP’s Transmission Owners, open access transmission service over approximately 85,000 miles of transmission lines in the Eastern and Western Interconnections covering portions of Arizona, Arkansas, Colorado, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas, Utah, and Wyoming; and (2) administers the Integrated Marketplace, a centralized day-ahead and real-time Energy and Operating Reserve market with locational marginal pricing and market-based congestion management.12 SPP also implements a resource adequacy
11 Sw. Power Pool, Inc., 109 FERC ¶ 61,009 (2004), order on reh’g, 110 FERC ¶ 61,137 (2005).12 Sw. Power Pool, Inc., 146 FERC ¶ 61,130 (2014) (approving the start-up and operation of the Integrated Marketplace).
PDF page 6
6
program under Attachment AA of the Tariff, under which Load Responsible Entities (“LRE”) must demonstrate sufficient accredited resource capacity to satisfy their load and an SPP-established Planning Reserve Margin (“PRM”) for the Summer Season and Winter Season, or else face significant charges for failure to meet their Resource Adequacy Requirement (“RAR”).
B. Role of Stakeholders and States in SPP
SPP operates under a stakeholder-driven governance model in which proposed revisions to the Tariff, Bylaws, Membership Agreement, and business practices are developed through an open, collaborative process involving market participants, transmission owners, state regulators, and other stakeholders before being considered by the SPP Board of Directors (the "Board") and, where applicable, filed with the Commission. This Commission-approved governance framework, established in SPP's Bylaws, Membership Agreement, and organizational governance documents, provides multiple opportunities for stakeholder discussion, refinement, and voting as proposals progress through technical working groups, policy committees, and ultimately to the Board.
This collaborative governance structure has been central to SPP's response to unprecedented large load growth. The stakeholder initiatives discussed throughout this report were each developed through this established process with significant stakeholder participation. Of particular importance are the SPP Regional State Committee ("RSC") and the Resource and Energy Adequacy Leadership Team ("REAL Team"), both of which have played key roles in shaping SPP's evolving resource adequacy framework. Under the SPP Bylaws, the RSC possesses defined authority over regional cost allocation methodology
PDF page 7
7
and resource adequacy matters.13 Complementing that role, the REAL Team was established in January 2023 to evaluate SPP’s long-term resource adequacy construct and to develop recommendations addressing emerging reliability challenges associated with changes in the resource mix, extreme weather events, and rapidly increasing electric demand.14
III. CURRENT STATE OF RESOURCE ADEQUACY
Since adopting Attachment AA of the Tariff in 2018, SPP has continued to strengthen its Resource Adequacy framework to address fundamental changes in the resource mix and unprecedented demand growth across the SPP Region. Historically, the Resource Adequacy program focused primarily on ensuring that each LRE procured sufficient generating capacity to meet its forecasted seasonal peak demand plus an established PRM.15 In recent years, however, accelerating growth in large commercial and industrial loads together with generator retirements and an evolving resource mix have
13 Southwest Power Pool, Inc., Bylaws, First Revised Volume No. 4, Section 7.2. The RSC has primary responsibility for determining regional proposals and the transition process in the following areas: (1) whether and to what extent participant funding will be used for transmission enhancements; (2) whether license plate or postage-stamp rates will be used for the regional access charge; (3) determination of financial transmission rights (“FTRs”) allocations where a locational price methodology is used; and (4) determination of the transition mechanism to be used to assure that existing firm customers receive FTRs equivalent to the customers’ existing firm rights; and (5) determination of the approach for resource adequacy across the entire region.14 Resource and Energy Adequacy Leadership Team, Organizational Group Scope Statement, Southwest Power Pool, Inc. (Jan. 2023) https://spp.org/documents/68934/real_scope_statement%20final.pdf. The REAL Team is composed of members from the RSC, the Board, the Members Committee, the Strategic Planning Committee, the Cost Allocation Working Group (“CAWG”), and the Supply Adequacy Working Group (“SAWG”).15 See Summer Resource Adequacy Report posted at: https://spp.org/documents/76932/2026%20spp%20summer%20resource%20adequacy%2 0report.pdf (“Summer 2026 Resource Adequacy Report”).
PDF page 8
8
required SPP to modernize both its resource accreditation methodology and its load forecasting processes.16
The most significant recent enhancement is SPP's transition to a planning margin based on accredited capacity (Accredited Capacity Planning Reserve Margin, “Accredited Capacity PRM”) framework beginning with the Summer 2026 Resource Adequacy season.17 Under this framework, resource capability is no longer measured solely by installed or nameplate capability. Instead, SPP utilizes Performance-Based Accreditation (“PBA”) for conventional generation and Effective Load Carrying Capability (“ELCC”) methodologies for wind, solar, and battery Resources to more accurately reflect each resource's expected reliability contribution during periods of system stress.18 For Summer 2026, LREs were required to satisfy their RAR using accredited capacity and a system- wide Accredited Capacity PRM of 7.06 percent.19
The transition to accredited capacity represents a significant advancement in SPP's resource adequacy framework by aligning resource accreditation with actual performance rather than simply relying on installed capability with limited testing to ensure capacity adequacy in SPP. This provides a more accurate assessment of regional reliability while
16 Keeping the Lights On: Examining the State of Regional Grid Reliability (Testimony of Lanny Nickell, Executive Vice President, Chief Operating Officer, Southwest Power Pool, Inc. Before the House Energy & Commerce Subcommittee on Energy), 119th Cong., 3-4 (Mar. 25, 2025), available at:https://www.congress.gov/119/meeting/house/118040/witnesses/HHRG-119-IF03- Wstate-NickellL-20250325.pdf.
17 See Summer 2026 Resource Adequacy Report.18 Id.19 Id.; see also Conventional Resources Class Averages – Summer 2026 posted at: https://spp.org/documents/74895/conventional%20unit%20class%20averages%20- %20summer%202026.pdf.
PDF page 9
9
creating technology-neutral incentives for resource performance during critical system conditions.
A. Current Resource Adequacy Outlook
SPP's most recent Summer 2026 Resource Adequacy Report concludes that the SPP Region is adequately positioned to meet expected Summer 2026 demand while also providing an outlook through the Summer 2031 planning horizon.20 The report evaluates existing accredited Resources, anticipated retirements, planned generation additions, and projected demand growth across the SPP East Balancing Authority Area. For the 2026 Summer Season, all sixty-five LREs satisfied their RAR.21 Based on data submitted in the 2026 Summer Season Workbook, the East BAA maintains a reserve margin of 17.1%, representing approximately 5,752 MW of excess accredited capacity above the total RAR. This is an increase of approximately 2,500 MW of excess capacity compared to the 2025 Summer Season. More than half of all LREs maintain reserve margins exceeding 16%, representing capacity in excess of approximately one-third of LRE forecasted Net Peak Demand.22 The 2026 Summer Season Workbook does not address the West BAA because the West BAA is not required to meet SPP’s resource adequacy processes and procedures until summer 2027.
B. Integration With Recent Large Load Initiatives
While current resource adequacy projections indicate that the East BAA is well positioned to meet near-term demand, SPP recognizes that rapidly increasing load forecasts
20 See Summer 2026 Resource Adequacy Report.21 Id.22 See Summer 2026 Resource Adequacy Report.
PDF page 10
10
represent one of the greatest sources of uncertainty in future resource adequacy planning. Much of this uncertainty stems from unprecedented load interconnection requests associated with data centers and other large commercial and industrial customers, many of which have historically been incorporated into utility load forecasts before development plans were sufficiently mature. Traditional planning processes were designed to accommodate incremental load growth rather than the addition of individual customers with demand measured in hundreds of megawatts. Recognizing that accurate demand forecasts are fundamental to effective resource adequacy planning, SPP also filed Tariff revisions in April 2026 to implement the Peak Demand Assessment,23 establishing a more structured process for validating forecasted peak demand and strengthening accountability by ensuring that all loads (including projected large loads) for the upcoming season are supported by sufficient amounts of Accredited Capacity.
IV. SPP’S EXISTING FRAMEWORK FOR EVALUATING AND SERVING
NEW LARGE LOADS24
SPP has developed a coordinated framework of planning, interconnection, transmission service, and resource adequacy processes to address growing demand and support the reliable integration of new large loads. Rather than addressing large load
23 The PDA Filing is pending before the Commission.
24
While this Informational Report primarily focuses on the evolution of SPP policies directly targeted at large load interconnections, SPP has implemented several complementary initiatives that strengthen resource adequacy. These include annual updates to the Cost of New Entry (“CONE”), which preserve appropriate incentives for LREs to procure sufficient Accredited Capacity; implementation of the Consolidated Planning Process (“CPP”), which integrates long-term transmission planning and generator interconnection into a single, cohesive framework to better accommodate evolving resource and load needs and speed up interconnection processing; and development of the Surplus Plus interconnection reforms, which facilitate more timely additions of incremental generation using existing transmission capability.
PDF page 11
11
requests as isolated transmission issues, SPP evaluates them through an integrated framework designed to accommodate significant load growth while preserving the reliable operation of the Transmission System.
A. ERAS
On May 22, 2025, SPP submitted Tariff revisions to add the ERAS process establishing a one-time, accelerated pathway for new generating resources to help address urgent reliability needs through 2030.25 The Commission accepted the ERAS Filing on July 21, 2025, with an effective date of July 22, 2025.26 SPP developed ERAS in collaboration with the RSC, REAL, and other stakeholders in response to the growing need to bring new generation resources online on an accelerated timeline. ERAS enables LREs to identify and secure the generating resources needed to maintain reliability across the SPP footprint, comply with the resource adequacy requirements set forth in Attachment AA of the Tariff, and satisfy their obligation to serve under applicable state or other governing law. To qualify for ERAS, a project was required to address an LRE's projected resource adequacy deficit, commit to achieving commercial operation within five years, and satisfy additional criteria demonstrating that the project was sufficiently developed and reasonably likely to achieve commercial operation in time to address identified resource adequacy needs.27 ERAS operates separately from, but in parallel with, SPP's standard Generator Interconnection Procedures under Attachment V of the Tariff.
25
ERAS Filing at 25. Tariff, Attachment AW. At the time of the ERAS Filing, SPP predicted that the SPP Region could face a 2-3 GW accredited capacity shortfall by 2030. 26
Sw. Power Pool, Inc., 192 FERC ¶ 61,062 (2025) (“ERAS Order”).
27 Tariff, Attachment AW, Section 8.2.
PDF page 12
12
As a one-time study, ERAS accepted requests during a limited application window28 and is no longer accepting new requests as a one-time process. Participation by LREs during the application window was strong. As of the date of this Informational Report, there are 36 active ERAS requests representing approximately 13.3 GW of generating capacity and no requests have withdrawn.29 These requests remain on schedule in the study process. ERAS Generator Interconnection Agreements (GIA) are currently in the negotiation phase and SPP expects to advance to the execution phase in September 2026. The process is on track to achieve its primary objective of accelerating the interconnection of generating resources needed to address near-term resource adequacy concerns. Although ERAS was designed as a one-time initiative, it demonstrated SPP's ability to accelerate the development of reliability-critical generation through a targeted stakeholder-driven process and established an important foundation for subsequent large load and resource adequacy reforms.
B. Provisional Load Process
On June 4, 2025, SPP submitted Tariff revisions to add a Provisional Load Process, documented in Attachment AX of the Tariff.30 The Commission accepted the Provisional Load Process Filing on October 10, 2025, with an effective date of August 4, 2025.31 While
28 Following Commission approval of the ERAS process on July 21, 2025, SPP opened the one-time ERAS application window on September 2, 2025, and closed the window on October 2, 2025.29 See SPP Operations Portal of GI Active Requests posted at: https://opsportal.spp.org/Studies/GIActive and https://app.powerbigov.us/view?r=eyJrIjoiNTFhODQ5MjEtMTQ1My00ZjI5LWFjNWIt ZmQ3NGQxNzM1ZDZiIiwidCI6IjMyMzA5MjZhLTcxYjctNDM3MC1hMTM3LTE5N2 JhZGMwNjZhMiJ9.30 Provision Load Process Filing. Tariff, Attachment AX. 31 Sw. Power Pool, Inc., 193 FERC ¶ 61,018 (2025) (“Provision Load Process Order”).
PDF page 13
13
the HILL process described below is designed for large, high-impact loads, the Provisional Load Process addresses a different challenge: the ability for SPP to study new proposed load additions prior to the Transmission Customers having existing resources online to support the new load. Under Attachment AQ, SPP may only study requests for new or modified delivery points when the Transmission Customer demonstrates that its existing Designated Resources are sufficient to serve both its existing forecasted load and the proposed new load over a ten-year horizon.32 As requests associated with large loads increased significantly, many Transmission Customers were unable to satisfy this prerequisite because the generation intended to serve the load had not yet completed the interconnection process or otherwise become an existing Designated Resource. As a result, SPP was unable to evaluate numerous otherwise viable load requests under its then-existing Tariff provisions.
The Provisional Load Process was developed to address this gap. Using the same study methodologies used for other load connection studies, the Provisional Load Process allows SPP to study proposed delivery point additions using both existing Designated Resources and identified planned generation that is expected to serve the new load.33 Importantly, the Provisional Load Process, alone, does not provide transmission service but instead serves as a planning mechanism that enables Transmission Customers to identify the transmission upgrades necessary to accommodate future load while their planned generation progresses through the applicable interconnection and transmission
32 Tariff, Part II, Section 17.9; Part III, Section 31.2; and Attachment AQ.33 Tariff, Attachment AX.
PDF page 14
14
service processes.34 Because the generation relied upon in the study has not yet completed the interconnection process and may ultimately change or fail to materialize, the revenue requirements for Network Upgrades identified through the Provisional Load Process are treated as Directly Assigned Upgrade Costs and are allocated 100% to the Transmission Customer until the Transmission Customer acquires firm transmission service for the planned generation.35 Once the planned generation obtains Long-Term Service and becomes a Designated Resource, the remaining costs of those Network Upgrades transition to Base Plan funding consistent with Attachment J of the Tariff36 and the Transmission Customer’s Network Integration Transmission Service Agreement or Point-to-Point Transmission Service Agreement is updated to reflect the requested changes.37 This approach protects other loads within SPP from bearing the costs of upgrades associated with speculative or uncertain generation while still allowing transmission planning to move forward in support of anticipated load growth.
As described in more detail in the following sections, SPP modified Attachment AX in the HILL and CHILLS Filings to integrate those frameworks into the existing Attachment AX process by requiring additional studies and information for qualifying
34 The Transmission Customer must complete either the Aggregate Transmission Service Study assessing the planned Designated Resource or the expedited process for resource designation as described in Section 30.2.2 of the Tariff before the Transmission Customer’s Network Integration Transmission Service Agreement or Point-to-Point Transmission Service Agreement will be updated to reflect the requested changes. Tariff, Attachment AX, Addenda 2 and 3.35 Tariff at Attachment J, Section V; Tariff at Attachment AX, Addendum 2 at Sections 6.0 and 7.0; Tariff, Attachment AX, Addendum 3 at Sections 6.0 and 7.036 Tariff, Attachment J, Section III.A.37 Tariff, Attachment AX, Addenda 2 and 3.
PDF page 15
15
HILLs and to provide Transmission Customers with additional flexibility when requesting studies for new load additions.
C. HILLs and the HILLGA
On October 24, 2025, SPP submitted Tariff revisions to add a HILL study process and the HILLGA.38 The Commission accepted the HILL Filing on January 14, 2026, with an effective date of January 15, 2026.39 The HILL Filing proposed two new mechanisms:
(1) the HILL study process set forth in Attachment BA; and (2) the HILLGA process set forth in Attachment BB. The HILL Filing revisions (1) defined and created a new category of load, termed a “HILL”; (2) established enhanced study requirements for HILLs to enable SPP to assess the load’s reliability impacts on the Transmission System; and (3) established additional, ongoing operational requirements for HILLs to ensure continued reliability of the Transmission System.40 The HILLGA process consists of a new generator interconnection service and related interconnection process to allow the limited connection of supporting generation for HILLs on an expedited basis.41
The HILL Filing revisions built upon the original Attachment AX framework by preserving Attachment AX as a vehicle through which HILLs may receive provisional transmission service while layering on the HILL-specific study and operational requirements established in Attachment BA. The revisions clarified that requests for new or modified delivery points associated with a HILL remain eligible for study under
38 HILL Filing.
39
Sw. Power Pool, Inc., 194 FERC ¶ 61,031 (2026) (“HILL/HILLGA Order”).
40 HILL Filing at 11-38.41 Tariff, Attachment BB.
PDF page 16
16
Attachment AX but must also satisfy the additional study and operational requirements established in Attachment BA.
The Tariff defines a HILL as:
A new commercial or industrial load, or increase in commercial or industrial load, at a single site connected through one or more shared Points of Interconnection (POIs) or delivery points, where such load is either (1) 10 MW or more if connected to the Transmission System at a voltage level less than or equal to 69 kV; or (2) 50 MW or more if connected to the
Transmission System at a voltage level greater than 69 kV. An Electric Storage Resource is not considered a HILL. A load may be categorized as a HILL after the initial effective date of Attachment BA of the Tariff. High Impact Large Loads must register as such in accordance with Attachment AE of the Tariff and follow the processes specified in Attachment BA of the Tariff.42
SPP processes all load additions and modifications, including HILLs, using its existing Attachment AQ, Attachment AX, and/or Attachment Z1 study processes.43 However, for HILLs, SPP and the applicable Transmission Owner(s) simultaneously conduct additional studies under Attachment BA to ensure that the unique operational characteristics of HILLs are considered when evaluating the addition of a HILL to the Transmission System, and that SPP has mechanisms in place to maintain reliable operation of the Transmission System.44 Attachment BA also imposes ongoing operational requirements, including the addition of certain equipment, to ensure that SPP can continue
42 Tariff, Part I, Section 1, Definition of High Impact Large Load.43 Through Attachment AQ, any existing customers may obtain firm transmission service for the modification of an existing delivery point or for the creation of a new delivery point. Under Attachment AX, existing customers may receive provisional study of a new or modified delivery point using planned generation, instead of existing Designated Resources. Lastly, new customers may receive transmission service for their load and Resources through Attachment Z1.44 Tariff, Attachment BA, Sections 2.1.3.4 and 2.1.3.5.
PDF page 17
17
to manage the Transmission System while accommodating the unique operational demands and characteristics of HILLs.45
The HILLGA process, outlined in Attachment BB, facilitates the prompt
interconnection of generating resources that are specifically identified for and limited to serving a HILL, at the request of the HILLGA Customer.46 SPP studies HILLGA Requests outside of its existing generator interconnection process on a serial basis, but solely for the impact of the Generating Facility47 to serve the identified HILL.48 Unlike traditional interconnection service, HILLGA provides a limited form of interconnection service specifically designed to evaluate generation intended to serve an identified HILL.49
D. CHILLS
On February 10, 2026, SPP submitted Tariff revisions to add a CHILLS, that allows HILLs to be served with non-firm conditional transmission service.50 The Commission
45
Tariff, Attachment BA, Section 2.2.
46 Tariff, Attachment BB, Section 2.47 Tariff, Attachment BB, Section 1, Definition of Generating Facility (“will mean a HILLGA Customer's device(s) for the production and/or storage for later injection of electricity identified in the HILLGA Request, but will not include HILLGA Customer's Interconnection Facilities and will not include a Storage as Transmission Only Asset as defined in Section 1 of the Tariff. A Generating Facility consists of one or more generating unit(s) and/or storage device(s) which usually can operate independently and be brought online or taken offline individually.”).48 Tariff, Attachment BB, Section 3.1.2.49 Tariff, Attachment BB, Section 3.2. The HILLGA does not grant the Generating Facility traditional generator interconnection service, such as Network Resource Interconnection Service (“NRIS”) or Energy Resource Interconnection Service (“ERIS”); instead, Generating Facilities studied under the HILLGA process receive much more limited “Load Limited Resource Interconnection Service” or “LLRIS,” which only studies the impact of the Generating Facility serving the identified HILL.50 CHILLS Filing.
PDF page 18
18
accepted the CHILLS Filing on June 5, 2026, with an effective date of July 1, 2026.51 CHILLS builds on the HILL and HILLGA processes to help further unlock the interconnection of large loads by facilitating service for HILLs by allowing a HILL (or a portion of a HILL) to receive the transfer of energy on a long-term, non-firm basis. The Attachment AQ and AX processes may delay service to otherwise ready HILLs and postpone the economic benefits associated with those projects. Delays could be related to construction of Network Upgrades or an inability to comply with the need to have sufficient Designated Resources to support the HILL. CHILLS mitigates this challenge by providing Transmission Customers with the ability to receive non-firm transmission service to HILL delivery points before (1) completion of any applicable Network Upgrades and/or (2) meeting the requirements for establishment of Designated Resources.52
The CHILLS Filing further built upon the Attachment AX framework by clarifying which customers may be eligible for the Provisional Load Process. Specifically, a Transmission Customer may request the study of a new load addition pursuant to Attachment AX regardless of whether the Eligible Customer has sufficient Designated Resources to support the study, provided that the Eligible Customer elects not to use its existing Designated Resources for the proposed load addition.53 This framework provides
51
Sw. Power Pool, Inc., 195 FERC ¶ 61,196 (2026) (“CHILLS Order”).
52 Tariff, Part I, Section 1, Definition of Network Resource (“Any designated generating resource owned, purchased or leased by a Network Customer under the Network Integration Transmission Service Tariff. Network Resources do not include any resource, or any portion thereof, that is committed for sale to third parties or otherwise cannot be called upon to meet the Network Customer's Network Load on a non-interruptible basis, except for purposes of fulfilling obligations under a reserve sharing program.”).53 Tariff, Attachment AX, Section 1.
PDF page 19
19
flexibility to Transmission Customers in determining which Designated Resources will be associated with new load additions when studied for firm transmission service under the Tariff.
CHILLS includes numerous reliability protections, including supporting generation requirements, enhanced engineering and operational studies, dedicated operating agreements, separate metering requirements, and SPP's authority to curtail or interrupt service during transmission constraints or Emergency Conditions. CHILLS are limited to a maximum seven-year term and requires customers to pursue permanent firm transmission service through existing Tariff processes, reinforcing that the service is intended as a temporary bridge rather than a substitute for long-term transmission solutions. Although CHILLS only recently became effective, SPP and its stakeholders continue to evaluate potential enhancements to improve its implementation and operation. SPP anticipates filing Tariff changes to clarify the sequencing of Resource commitments and Reliability-Resource Demand Response Program (RRDRP) deployments relative to CHILLs and establish a minimum Curtailment ramp rate for CHILLS.54 SPP also intends to propose Tariff revisions permitting limited outages for Resources supporting certain CHILLs.55 As a first-of-its-kind transmission service, CHILLS will continue to evolve. SPP and its stakeholders will continue refining the service where appropriate to improve its effectiveness while maintaining system reliability.
E. PDA and Enhancements to the Participation of Demand Response
Resources
54 See CHILL Clarification Revision Request posted at: https://www.spp.org/spp- documents-filings/?id=21069 (see zip file “RR767(SIR833) CHILL Clarification). 55 See CHILL Outage Criteria Revision Request posted at: https://www.spp.org/spp- documents-filings/?id=21069 (see zip file “RR768(SIR823) CHILL Outage Criteria).
PDF page 20
20
On April 17, 2026, SPP submitted Tariff revisions to strengthen its Resource Adequacy framework through implementation of a PDA and enhancements to the participation of Demand Response Resources.56 The PDA Filing is pending before the Commission with a requested effective date of January 1, 2027. The filing was developed in response to accelerating load growth, including the emergence of large data center demand, increasing uncertainty in load forecasting, and the continued evolution of the resource mix across the SPP Region, including the anticipated increased reliance on Demand Response Programs by LREs to meet the RAR while dealing with the aforementioned load growth.
Just as SPP recently modernized how resource capability is measured through the Accredited Capacity PRM framework, the PDA modernizes how demand is forecasted and measured for resource adequacy purposes. Together, these reforms strengthen both sides of SPP's resource adequacy framework by improving the accuracy of the capacity available to serve load and the forecasted demand against which that capacity is evaluated. The PDA shifts resource adequacy accountability from a solely forecast-based, pre-season evaluation57 to a financially binding post-season assessment based on actual, weather- normalized peak demand.
Under the revised framework, SPP would continue to validate each LRE’s qualified capacity before each season through a new Pre-Season Requirement, while determining compliance with the RAR after the season using verified demand data.58 This approach
56 PDA Filing.57 Tariff, Attachment AA, Section 12 entitled, “Post-Season Analysis.”58 PDA Filing at 6.
PDF page 21
21
addresses a key limitation of the existing framework by establishing accountability for material under-forecasting of load while preserving the operational benefits of pre-season resource qualification. By relying on actual metered data and weather-normalized peak demand, the PDA better aligns resource adequacy obligations with actual system conditions, particularly as large loads introduce greater variability and uncertainty into forecasting.59
The PDA Filing also modernizes SPP's treatment of Demand Response Resources by integrating qualifying Demand Response Resources more fully into the Resource Adequacy framework.60 The revisions permit market-registered Demand Response Resources to serve as capacity Resources, establish a new RRDRP that may receive accredited capacity, implement performance-based accreditation using historical performance, and enhance operational and deployment requirements to ensure dependable performance during system stress and emergency conditions.61 These revisions provide greater operational visibility into available Resources while creating incentives for both accurate load forecasting and reliable Demand Response performance. Additionally, the PDA filing permits LREs to implement non-registered load-modifying Demand Response programs that are not registered in the Integrated Marketplace and do not qualify as RRDRP. This flexibility allows LREs to actively manage their peak demand in real time, supporting compliance with their load forecasts while ensuring their demand remains consistent with the capacity they qualified for under the Pre-Season Requirement.
59 Id.60 Id.61 Id.
PDF page 22
22
Together, the PDA and Demand Response reforms complete a broader set of coordinated transmission planning, interconnection, and resource adequacy reforms. When considered alongside the previously approved Provisional Load Process, the HILL and HILLGA frameworks, the ERAS reforms, and related stakeholder initiatives, these measures illustrate SPP's integrated approach to accommodating significant load growth while preserving reliability and ensuring resource adequacy.
F. CPP
In addition to initiatives specifically focused on large loads and resource adequacy, SPP has undertaken broader reforms to its regional transmission planning processes that will improve the region's ability to identify and address transmission needs associated with evolving load growth, changing resource portfolios, and increasing system complexity. One such initiative is CPP, which streamlines multiple existing transmission planning assessments into a single, coordinated planning framework.
Historically, SPP conducted several planning studies independently, each with distinct objectives, assumptions, and study horizons. While these planning processes provided valuable information, the separate study cycles could result in duplicative analyses, differing assumptions, and limited opportunities to evaluate transmission needs holistically. As the region experiences accelerating load growth—including requests to serve large new loads—along with significant generation interconnection activity and evolving resource adequacy needs, SPP recognized the value of integrating these planning efforts into a unified process.
The CPP establishes a coordinated planning cycle that evaluates reliability, economic, operational, and public policy-driven transmission needs using a common set of
PDF page 23
23
assumptions and coordinated stakeholder input. By consolidating these planning activities, SPP is better positioned to evaluate transmission solutions across multiple planning objectives, improve consistency in forecasting future system conditions, and identify projects that provide broad regional benefits. The process also enhances transparency by providing stakeholders with a single planning framework through which assumptions, study methodologies, and recommended transmission solutions can be reviewed and refined.
Although the CPP is not directed solely at accommodating large loads, it strengthens the planning foundation needed to address significant changes in demand across the SPP footprint. As large industrial facilities, data centers, electrification, and other emerging loads increasingly influence long term transmission needs, the CPP provides a more integrated process for evaluating how those loads interact with generation development, resource adequacy requirements, and regional transmission expansion. This integrated planning approach enables SPP to assess transmission needs using consistent planning assumptions while considering the cumulative impacts of multiple drivers affecting the Transmission System.
The CPP complements SPP's other initiatives discussed in this report, including enhancements to the HILL framework, the HILLGA process, resource adequacy reforms, and other transmission planning improvements. Together, these efforts are intended to improve SPP's ability to plan for and reliably serve substantial new load growth while maintaining an efficient, transparent, and stakeholder-driven regional planning process.
V. PRICE ADAPTIVE LOADS (PALs) AND PRICE ADAPTIVE LOAD
SERVICE (PALS)
A. Overview
PDF page 24
24
The Price Adaptive Load (PAL) and Price Adaptive Load Service (PALS)
framework establishes a new market participation model and transmission service option specifically designed for large, price-responsive loads.62 Unlike the initiatives discussed in Section IV, PAL/PALS remains under active stakeholder development and has not yet been submitted to the Commission. Accordingly, the discussion below summarizes the current proposal and anticipated stakeholder schedule.
The PAL/PALS framework is intended to accommodate a new class of commercial and industrial customers—such as certain data centers and advanced manufacturing facilities—that are capable of adjusting or interrupting electricity consumption in response to real-time market conditions while reducing reliance on traditional firm transmission service. Participating PALs would be economically dispatched through SPP's Integrated Marketplace based on submitted price-sensitive bids and would be required to respond to dispatch instructions in both the Day-Ahead Market and Real-Time Balancing Market. To support this market participation model, the proposal also creates Price Adaptive Load Service (PALS), a new non-firm transmission service designed specifically for dispatchable, flexible loads. Unlike traditional transmission service, PALS would utilize a usage-based billing structure and require participating loads to be fully dispatchable, capable of rapidly reducing consumption, and subject to Curtailment during transmission constraints, Emergency Conditions, or local reliability events.
The PAL/PALS framework represents the next evolution of SPP's large load strategy by providing a market-based option for flexible loads that complements SPP's
62 RR 791.
PDF page 25
25
existing planning, transmission service, interconnection, and resource adequacy reforms. Where SPP's previously approved reforms focused primarily on ensuring that sufficient generation, transmission capability, and planning processes exist to support unprecedented load growth, the PAL/PALS proposal recognizes that some emerging large loads possess operational flexibility that can itself become a valuable reliability and market resource. By creating a market participation model and transmission service tailored to those characteristics, PAL/PALS would complement SPP's existing framework while expanding the range of tools available to integrate large flexible loads reliably and efficiently.
B. Stakeholder Schedule and Expected Milestones
The PAL/PALS initiative is the product of extensive stakeholder development that has included technical design, stakeholder education, Tariff drafting, and publication of the associated Revision Request (RR). Development began with an internal team of SPP staff meetings during the first quarter of 2026 to establish the framework and refine the modeling approach. Beginning in April 2026, SPP initiated a broad stakeholder education effort, presenting the concepts to the Cost Allocation Working Group (“CAWG”), Operating Reliability Working Group (“ORWG”), Markets Working Group (“MWG”), Regional Tariff Working Group (“RTWG”), and other stakeholder groups to introduce the proposal and solicit early feedback.
During May and June, the stakeholder process advanced from conceptual
development to preparation of Tariff revisions necessary to implement the PAL/PALS design framework. SPP also hosted question-and-answer sessions and multiple stakeholder forums to discuss the proposal, gather additional feedback, and refine the draft revisions. The PAL/PALS RR was posted for stakeholder review on July 9, 2026.
PDF page 26
26
SPP intends to continue its extensive outreach efforts through additional stakeholder forums and educational presentations across numerous working groups, including the MWG, RTWG, Supply Adequacy Working Group (“SAWG”), Transmission Working Group (“TWG”), Economic Studies Working Group (“ESWG”), ORWG, CAWG, RSC, and the Markets and Operations Policy Committee (“MOPC”). The proposal is expected to advance through the formal stakeholder approval process from August through November 2026, with individual working groups considering the revisions before final votes by MOPC on October 13, 2026, and the RSC on November 16, 2026. Assuming stakeholder approval, SPP intends to file the PAL/PALS proposal with the Commission on or before November 16, 2026. This timeline reflects SPP's collaborative stakeholder process, which is designed to provide multiple opportunities for education, technical discussion, stakeholder input, and formal approval before being filed with the Commission.
VI. ONGOING WORK OF THE REAL TEAM
In 2023, as mentioned above, the SPP Board established the REAL Team to assess SPP’s current resource adequacy construct and anticipated challenges resulting from resource mix changes, extreme weather impacts, increased demand, and evolving consumer behaviors. REAL provides guidance, prioritization, and policy recommendations needed to increase assurance that sufficient energy to meet load requirements can be continuously and cost-effectively provided within the SPP Balancing Authority Areas (“BAA”). The REAL Team consists of a diverse membership from various SPP stakeholder groups, including the SPP Board, transmission owning members, transmission using members, and state commission representatives.
PDF page 27
27
As seen on the REAL Teams work plan,63 the REAL Team will address a number of Resource Adequacy issues in 2027, including Seasonal Resource Adequacy Construct, use of non-firm imports in the development of the planning reserve margin, non-weather related load uncertainty, and the use of coincident peak instead of non-coincident peak in SPP’s resource adequacy requirements. Through this work, SPP is continuing its steadfast commitment to ensuring that SPP continues to have sufficient resource capacity to meet current and projected load growth in both SPP BAAs.
VII. CONCLUSION
SPP continues to work with stakeholders to refine its planning, transmission, market, operations, and resource adequacy frameworks as large load development continues to evolve across the region. The initiatives described in this report reflect SPP's coordinated approach to integrating large loads while preserving reliability, maintaining resource adequacy, and protecting existing customers. SPP respectfully requests the Commission accept this report as responsive to the Commission’s directive to submit an informational report in the Show Cause Order.
Respectfully submitted,
/s/ Meredith Powell
Meredith Powell
Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223
mpowell@spp.org
63 REAL Team meeting materials on the June 17, 2026, item number 5: https://www.spp.org/Documents/76913/REAL%20Meeting%2020260617.zip
PDF page 28
28
Attorney for
Southwest Power Pool, Inc.
July 20, 2026
PDF page 29
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Little Rock, Arkansas, this 20th day of July, 2026.
/s/ Cassie Butler
Cassie Butler
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
(501)