EL26-68-000 · 2026-07-20 · Southwest Power Pool, Inc.

SPP reports on resource adequacy and large-load proposals

SPP files its 30-day informational report on resource adequacy for new large loads. It reports a 2026 summer reserve margin of 17.1 percent, describes its ERAS, Provisional Load, HILL, CHILLS and planning reforms, and sets a schedule for the PAL/PALS flexible-load proposal.

Answers the E-9 30-day directive for an informational report on resource adequacy for large loads and gives the stakeholder schedule for the PAL/PALS service the order cites for flexible loads.

E-9 SPP: 30-day report on serving large loads with adequate generation (p. 7) E-9 SPP: New services for flexible loads (Ordering (B)(1)(d), p. 22)

Key points

  1. SPP lists complementary initiatives it says have improved planning, resource addition and large load integration.
    SPP has developed complementary initiatives that improve planning certainty, accelerate the addition of new resources, enhance operational flexibility, strengthen resource adequacy accountability PDF p. 2
  2. SPP's East balancing area shows a 17.1 percent summer 2026 reserve margin, about 5,752 MW above requirements.
    the East BAA maintains a reserve margin of 17.1%, representing approximately 5,752 MW of excess accredited capacity above the total RAR. PDF p. 9
  3. At the ERAS filing SPP predicted a 2-3 GW accredited capacity shortfall by 2030.
    SPP predicted that the SPP Region could face a 2-3 GW accredited capacity shortfall by 2030. PDF p. 11
  4. ERAS has 36 active requests representing about 13.3 GW, with none withdrawn.
    there are 36 active ERAS requests representing approximately 13.3 GW of generating capacity and no requests have withdrawn. PDF p. 12
  5. SPP defines HILLs at 10 MW or more at 69 kV and below, or 50 MW or more above 69 kV.
    50 MW or more if connected to the Transmission System at a voltage level greater than 69 kV PDF p. 16
  6. PALS would be a non-firm service with usage-based billing for fully dispatchable loads subject to curtailment.
    PALS would utilize a usage-based billing structure and require participating loads to be fully dispatchable PDF p. 24
  7. PAL/PALS faces MOPC and RSC votes on October 13 and November 16, with a FERC filing by November 16, 2026.
    final votes by MOPC on October 13, 2026, and the RSC on November 16, 2026. PDF p. 26
Contents · 17 sections
  1. I. EXECUTIVE SUMMARY p. 1
  2. II. BACKGROUND p. 5
  3. B. Role of Stakeholders and States in SPP p. 6
  4. III. CURRENT STATE OF RESOURCE ADEQUACY p. 7
  5. A. Current Resource Adequacy Outlook p. 9
  6. B. Integration With Recent Large Load Initiatives p. 9
  7. IV. SPP’S EXISTING FRAMEWORK FOR EVALUATING AND SERVING p. 10
  8. A. ERAS p. 11
  9. B. Provisional Load Process p. 12
  10. C. HILLs and the HILLGA p. 15
  11. D. CHILLS p. 17
  12. E. PDA and Enhancements to the Participation of Demand Response p. 19
  13. V. PRICE ADAPTIVE LOADS (PALs) AND PRICE ADAPTIVE LOAD p. 23
  14. A. Overview p. 23
  15. B. Stakeholder Schedule and Expected Milestones p. 25
  16. VI. ONGOING WORK OF THE REAL TEAM p. 26
  17. VII. CONCLUSION p. 27

Read topic-matched comments in EL26-68

Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation

What the document says

Interconnection · PDF pp. 9–14

Accelerated supply and provisional load studies

SPP traces its expedited resource process to urgent needs through 2030. A separate provisional process studies load before all supply is named.

a one-time, accelerated pathway for new generating resources to help address urgent reliability needs through 2030 PDF p. 11

Reliability studies · PDF pp. 15–17

Identifying high-impact loads

SPP separates the study of a high-impact load from the agreement for generation assigned to serve it. Operational requirements continue after the initial study.

established enhanced study requirements for HILLs to enable SPP to assess the load’s reliability impacts PDF p. 15

Curtailment · PDF pp. 17–19

Conditional service has an end date

CHILLS allows temporary conditional service with supporting generation and separate metering. Customers must pursue permanent firm transmission service; SPP can curtail in an emergency.

CHILLS are limited to a maximum seven-year term PDF p. 19

Flexible demand · PDF pp. 23–26

A different offer for price-sensitive demand

SPP describes proposed usage-based service for customers willing to follow dispatch instructions and cut demand during constraints. In this July report, the proposal had not been filed.

PAL/PALS remains under active stakeholder development and has not yet been submitted to the Commission PDF p. 24