Industrial customers ask FERC to clarify or rehear its Large Load registry order
The PJM Industrial Customer Coalition (PJMICC) and Steel Producers ask FERC to clarify, or alternatively rehear, parts of its October 9, 2026 order on PJM's Large Load Registry. They want limits on who sees registry data and on collecting existing customers' contracts and rates.
Asks FERC to: Clarify that registry data is limited to need-to-know users, that retail rates are excluded, and that load serving entities see only their own customers. Alternatively, exclude existing Large Loads or apply the same access limits.
Seeks clarification of FERC's order on PJM's section 205 Large Load Registry in ER26-3515. It does not cite the E-7 show cause order; the Registry and its definition run alongside it.
E-12 NYISO: Define ‘large load’ (P 64, p. 41) E-7 PJM: Application / study process (P 6(a), p. 7)
Key points
- PJMICC and Steel Producers ask for clarification or rehearing on the Registry's application to industrial and manufacturing loads and its confidentiality rules.
PJMICC and Steel Producers respectfully request clarification or, in the alternative, rehearing of portions of the Commission’s October 9, 2026, Order PDF p. 1
- They warn that without limits on who sees the data, the Registry could become a source of competitive intelligence.
Without certain clarifications regarding who may see that information and for what purpose, the Registry risks becoming a source of competitive intelligence rather than a reliability tool. PDF p. 2
- They note that, with IRAS rejected, existing PJMICC and Steel Producers members that meet the Large Load definition will be in the Registry.
Because the Commission rejected IRAS, all retail customers that satisfy the definition of Large Load, including some existing PJMICC and Steel Producers members, will be included in the Registry for “informational purposes” only. PDF p. 3
- They ask FERC to require PJM to limit Registry access on a need-to-know basis.
PJM must segment access to Registry data on a “need-to-know” basis PDF p. 4
- They ask that retail rate and pricing information be excluded from the Registry and redacted from added contracts.
Information on retail customer rates or pricing will be excluded from the Registry and redacted from contracts that are added to the Registry. PDF p. 4
- They say a large manufacturer's load profile and supply contracts are at least as sensitive as a generator's real-time output.
A large manufacturer’s load profile and supply contracts should be viewed as at least as sensitive as a generator’s real-time output. PDF p. 10
- They ask FERC to limit a load serving entity's access to its own customers and bar use of Registry data for marketing.
The Commission should clarify that an LSE’s access to Registry data is limited to its own customers and that Registry data may not be used as a marketing tool. PDF p. 11
- As a rehearing alternative, they ask FERC to exclude existing Large Loads absent record evidence, or to apply the access limits to Registry data.
(1) exclude existing Large Loads from the Registry absent substantial record evidence supporting their inclusion, or (2) direct PJM to apply to Registry data the access limitations and protections described above PDF p. 15
Contents · 12 sections
- I. INTRODUCTION
- II. EXECUTIVE SUMMARY
- III. STATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING
- IV. PROCEDURAL HISTORY
- V. REQUEST FOR CLARIFICATION
- A. The Commission should clarify that PJM must collect and segment access to
- B. The Commission should clarify that confidentiality protections for retail
- C. The Commission should clarify that an LSE may access Registry data only for
- D. The Commission should clarify that retail customers listed in the Registry will
- E. The Commission should clarify that information on rates will be excluded from
- VI. ALTERNATIVE REQUEST FOR REHEARING
- VII. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Registry access · Filing procedure · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
ER26-3515-000 : REQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING OF THE PJM INDUSTRIAL CUSTOMER COALITION AND STEEL PRODUCERS Pursuant to Rule 713 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure,1 the PJM Industrial Customer…Read this passage Filed comments: Registry access
I. INTRODUCTION
printed heading · Topic match: Registry access
Clarification is necessary because OA protections must be applied to retail customers, including to customers who are not signatories to the OA and do not have the privileges of PJM Membership.Read this passage Filed comments: Registry access
II. EXECUTIVE SUMMARY
printed heading · Topic match: Registry access
PJM must segment access to Registry data on a “need-to-know” basis, so that each recipient receives only the data relevant to its own planning and operational responsibilities, consistent with the scope limits in OA section 18.17.7, which provides for Transmission Owners to receive only…Read this passage Filed comments: Registry access
III. STATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING
printed heading · Topic match: Registry access
The October 9 Order errs by approving the Registry despite rejection of the IRAS proposal that the Registry was designed to support, without substantial evidence that the Registry is properly designed for non-IRAS purposes. 5 U.S.C. § 706(2)(A); Vistra Corp. v.Read this passage Filed comments: Registry access
IV. PROCEDURAL HISTORY
printed heading · Topic match: Registry access
PROCEDURAL HISTORY On August 13, 2026, PJM filed, pursuant to section 205 of the Federal Power Act (“FPA”)12, proposed revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement (“RAA”) to establish: (1) a definition of Large Load; (2) a Large Load Registry; (3)…Read this passage Filed comments: Registry access
V. REQUEST FOR CLARIFICATION
printed heading · Topic match: Registry access
REQUEST FOR CLARIFICATION PJMICC and Steel Producers respectfully request clarification regarding five issues: (1) segmentation of Registry data on a “need-to-know” basis; (2) confidentiality protections for retail customer data that are no less restrictive than those for generator data; (3)…Read this passage Filed comments: Registry access
A. The Commission should clarify that PJM must collect and segment access to
printed heading · Topic match: Registry access
The Order accepts PJM’s proposal to make Registry information available to Authorized Commissions, Transmission Owners, Electric Distributors, LSEs, the Independent Market Monitor (“IMM”), the Commission, and other entities, “subject to appropriate confidentiality and data protection safeguards.”21…Read this passage Filed comments: Registry access
B. The Commission should clarify that confidentiality protections for retail
printed heading · Topic match: Registry access
Per the OA, confidential generator data provided to Transmission Owners may be provided “only to transmission function employees,” may be used only for the Transmission Owner’s reliability and transmission functions, and may not be disclosed “to any person, including marketing function employees,”…Read this passage Filed comments: Registry access
C. The Commission should clarify that an LSE may access Registry data only for
printed heading · Topic match: Registry access
The Order confirms that the LSE serving a Large Load is obligated to provide the Registry information for that customer.30 It does not follow that every LSE should have access to the Registry information of every other LSE’s customers.Read this passage Filed comments: Registry access
D. The Commission should clarify that retail customers listed in the Registry will
printed heading · Topic match: Registry access
Additionally, confidentiality protection is needed for retail customers, particularly manufacturers, who must compete globally and for whom information in the Registry could be used as competitive intelligence by competitors. 31 PJMICC Comments at 6. 32 Broad access to customer utility account…Read this passage Filed comments: Registry access
E. The Commission should clarify that information on rates will be excluded from
printed heading · Topic match: Registry access
As mentioned above, many Large Load retail customers must compete globally in their respective industries.Read this passage Filed comments: Registry access
VI. ALTERNATIVE REQUEST FOR REHEARING
printed heading · Topic match: Registry access
First, the October 9 Order does not provide substantial evidence to support the inclusion of existing Large Load, including industrial customers and other energy-intensive customers, in the Registry.33 The Commission recognized that, because IRAS was rejected, industrial customers will be included…Read this passage Filed comments: Registry access
VII. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION PJMICC and Steel Producers respectfully request that the Commission grant the clarifications set forth above, consistent with its holding in the October 9 Order, or, in the alternative, grant rehearing as set forth in Section VI.Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated this 9th day of November, 2026. /s/ Susan E.Read this passage