ER26-3515-002 · 2026-11-09 · PJM

Thirty-Day Compliance Filing on PJM’s Large Load Definition and Large Load Registry

PJM files the tariff and Reliability Assurance Agreement text that keeps the 50 MW Large Load definition and the Large Load Registry FERC accepted on October 9, with the fields tied to its rejected capacity proposal removed.

Asks FERC to: Accept the compliance filing with an October 12, 2026 effective date.

Defines which PJM loads count as large and how PJM learns about them, the threshold question the E-7 order leaves to PJM's show cause response.

E-7 PJM: Application / study process (P 6(a), p. 7) E-12 NYISO: Define ‘large load’ (P 64, p. 41)

Key points

  1. PJM drops the two registry fields tied to its rejected capacity proposal.
    the amount of BYONC brought by a particular Large Load and the allocated RBP UCAP MW quantity PDF p. 2
  2. A Large Load is 50 MW of cumulative peak at one electrical site.
    a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection PDF p. 109
  3. Loads in service before June 1, 2027 must be reported by March 1, 2027.
    prior to June 1, 2027, shall provide the information required by RAA, Schedule 11.B.1 to the Office of the Interconnection by March 1, 2027. PDF p. 124
  4. Later loads must be reported before they enter service.
    before the in-service date of the Large Load. PDF p. 125
Contents · 343 sections
  1. I. DESCRIPTION OF SUBMITTAL p. 2
  2. II. SERVICE p. 3
  3. III. CONCLUSION p. 4
  4. Attachment A p. 6
  5. Definitions – L – M – N p. 8
  6. List of Approved Contractors: p. 9
  7. Load Interest: p. 9
  8. Load Management: p. 10
  9. Load Ratio Share: p. 10
  10. Load Reduction Event: p. 10
  11. “Load Serving Charging Energy” shall mean energy that is purchased from the PJM Interchange Energy Market and stored in an Energy Storage Resource or Open-Loop Hybrid Resource for later resale to end-use load. p. 10
  12. Load Shedding: p. 10
  13. Local Upgrades: p. 10
  14. “Long-lead Project” shall have the same meaning provided in the Operating Agreement. p. 12
  15. Long-Term Firm Point-To-Point Transmission Service: p. 12
  16. Loss Price: p. 12
  17. Attachment K-Appendix, section 2. p. 12
  18. Market Monitoring Unit Advisory Committee or MMU Advisory Committee: p. 13
  19. Market Operations Center: p. 13
  20. Market Participant Energy Injection: p. 14
  21. Market Participant Energy Withdrawal: p. 14
  22. Material Modification: p. 15
  23. Maximum Emergency: p. 15
  24. Maximum Facility Output: p. 15
  25. Maximum Generation Emergency: p. 15
  26. Maximum Generation Emergency Alert: p. 15
  27. Maximum Run Time: p. 16
  28. “Maximum Run Time” shall mean the maximum number of hours a generating unit can run over the course of an Operating Day, as measured by PJM’s State Estimator. p. 16
  29. “Maximum State of Charge” shall mean the maximum State of Charge that should not be exceeded, measured in units of megawatt-hours. p. 16
  30. Maximum Weekly Starts: p. 16
  31. “Maximum Weekly Starts” shall mean the maximum number of times that a generating unit can be started in one week, defined as the 168 hour period starting Monday 0001 hour, under normal operating conditions. p. 16
  32. Merchant A.C. Transmission Facilities: p. 16
  33. Merchant D.C. Transmission Facilities: p. 16
  34. Merchant Network Upgrades: p. 16
  35. Merchant Transmission Facilities: p. 16
  36. Merchant Transmission Provider: p. 17
  37. Metering Equipment: p. 17
  38. Minimum Generation Emergency: p. 18
  39. “Multi-Driver Project” shall have the same meaning provided in the Operating Agreement. p. 19
  40. Native Load Customers: p. 19
  41. Near-Term Transmission Service: p. 19
  42. NERC: p. 19
  43. NERC Interchange Distribution Calculator: p. 20
  44. Network Customer: p. 20
  45. Network Integration Transmission Service: p. 21
  46. Network Load: p. 21
  47. Network Operating Agreement: p. 21
  48. Network Operating Committee: p. 21
  49. Network Resource: p. 21
  50. Network Service User: p. 21
  51. Network Transmission Service: p. 21
  52. Network Upgrades: p. 22
  53. New PJM Zone(s): p. 23
  54. New Service Customers: p. 23
  55. New Service Request: p. 23
  56. New Services Queue: p. 23
  57. No-load Cost: p. 23
  58. Nominal Rated Capability: p. 24
  59. Non-Firm Point-To-Point Transmission Service: p. 24
  60. Non-Firm Sale: p. 25
  61. Non-Firm Transmission Withdrawal Rights: p. 25
  62. Non-Retail Behind The Meter Generation: p. 25
  63. Non-Synchronized Reserve: p. 26
  64. Non-Synchronized Reserve Event: p. 26
  65. “Non-Variable Loads” shall have the meaning specified in Operating Agreement, Schedule 1, section 1.5A.6, and the parallel provisions of Tariff, Attachment K-Appendix, section 1.5A.6. p. 26
  66. Non-Zone Network Load: p. 26
  67. Normal Maximum Generation: p. 26
  68. Normal Minimum Generation: p. 26
  69. III. RESPONSBILITIES OF ELECTRIC DISTRIBUTORS p. 29
  70. II. RESPONSBILITIES OF THE OFFICE OF THE INTERCONNECTION p. 30
  71. ARTICLE 1 – DEFINITIONS p. 32
  72. Agreement: p. 32
  73. “Accredited UCAP” shall mean the quantity of Unforced Capacity, as denominated in Effective UCAP, that an ELCC Resource is capable of providing in a given Delivery Year. p. 32
  74. Accredited UCAP Factor: p. 32
  75. “Accredited UCAP Factor” shall mean, through the 2024/2025 Delivery Year, one minus EFORd, and for 2025/2026 Delivery Year and subsequent Delivery Years, the ratio of the Capacity Resource’s Accredited UCAP to the Capacity Resource’s installed capacity. p. 32
  76. Behind The Meter Generation: p. 33
  77. Black Start Capability: p. 34
  78. Capacity Emergency Transfer Objective (CETO): p. 34
  79. Capacity Emergency Transfer Limit (CETL): p. 34
  80. “Capacity Performance Resource” shall have the same meaning as in Tariff, Attachment DD. p. 36
  81. Capacity Resources: p. 36
  82. Capacity Transfer Right: p. 36
  83. Consolidated Transmission Owners Agreement, PJM Transmission Owners Agreement or Transmission Owners Agreement: p. 37
  84. Control Area: p. 37
  85. Daily Unforced Capacity Obligation: p. 38
  86. Delivery Year: p. 38
  87. Demand Resource (DR): p. 38
  88. Demand Resource Factor or DR Factor: p. 38
  89. Demand Resource Sell Offer Plan: p. 39
  90. Electric Cooperative: p. 41
  91. Electric Distributor: p. 41
  92. Emergency: p. 41
  93. End-Use Customer: p. 41
  94. Energy Efficiency Resource: p. 42
  95. Existing Demand Resource: p. 42
  96. Facilities Study Agreement: p. 43
  97. FERC or Commission: p. 43
  98. Firm Point-To-Point Transmission Service: p. 43
  99. Firm Service Level: p. 43
  100. Firm Transmission Service: p. 44
  101. Fixed Resource Requirement Alternative or FRR Alternative: p. 44
  102. Forecast Pool Requirement: p. 44
  103. FRR Capacity Plan or FRR Plan: p. 44
  104. FRR Entity: p. 44
  105. FRR Service Area: p. 44
  106. Full Requirements Service: p. 45
  107. Generation Capacity Resource: p. 46
  108. Generation Owner: p. 46
  109. Generator Forced Outage: p. 46
  110. Generator Maintenance Outage: p. 47
  111. Generator Planned Outage: p. 47
  112. Good Utility Practice: p. 47
  113. Incremental Auction: p. 48
  114. IOU: p. 48
  115. Load Serving Entity or LSE: p. 49
  116. Locational Reliability Charge: p. 50
  117. Markets and Reliability Committee: p. 50
  118. Maximum Emergency Service Level: p. 50
  119. Member: p. 50
  120. Members Committee: p. 50
  121. NERC: p. 50
  122. Network Transmission Service: p. 51
  123. Nominal PRD Value: p. 51
  124. Nominated Demand Resource Value: p. 51
  125. Non-Retail Behind the Meter Generation: p. 51
  126. Obligation Peak Load: p. 51
  127. Office of the Interconnection: p. 51
  128. Operating Agreement of the PJM Interconnection, L.L.C., Operating Agreement or PJM Operating Agreement: p. 52
  129. Operating Reserve: p. 52
  130. Other Supplier: p. 53
  131. Partial Requirements Service: p. 53
  132. Party: p. 53
  133. Percentage Internal Resources Required: p. 54
  134. PJM: p. 54
  135. PJM Board: p. 54
  136. PJM Manuals: p. 54
  137. PJM Region: p. 54
  138. PJM Region Installed Reserve Margin: p. 54
  139. PJM Tariff, Tariff, O.A.T.T., OATT or PJM Open Access Transmission Tariff: p. 55
  140. Planned Demand Resource: p. 55
  141. Planned External Generation Capacity Resource: p. 55
  142. Planned Generation Capacity Resource: p. 56
  143. Planning Period: p. 57
  144. PRD Curve: p. 57
  145. PRD Provider: p. 57
  146. PRD Reservation Price: p. 57
  147. “PRD Reservation Price” shall mean an RPM Auction clearing price identified in a PRD Plan for Price Responsive Demand load below which the PRD Provider desires not to commit the identified load as Price Responsive Demand. p. 57
  148. PRD Substation: p. 57
  149. Price Responsive Demand: p. 58
  150. Price Responsive Demand Credit: p. 58
  151. “Price Responsive Demand Credit” shall mean a credit, based on committed Price Responsive Demand, as determined under Reliability Assurance Agreement, Schedule 6.1. p. 58
  152. Public Power Entity: p. 58
  153. Qualifying Transmission Upgrades: p. 58
  154. Relevant Electric Retail Regulatory Authority: p. 58
  155. “Relevant Electric Retail Regulatory Authority” or “RERRA” shall have the meaning specified in the PJM Operating Agreement. p. 58
  156. Reliability Principles and Standards: p. 59
  157. Required Approvals: p. 59
  158. Self-Supply: p. 59
  159. State Consumer Advocate: p. 59
  160. State Regulatory Structural Change: p. 59
  161. Steam Class: p. 59
  162. “Steam Class” shall mean an ELCC Class consisting of Unlimited Resources of the steam technology type and the primary fuel is not coal or nuclear. p. 60
  163. Supervisory Control: p. 60
  164. Threshold Quantity: p. 60
  165. Transmission Owner: p. 61
  166. Unforced Capacity: p. 61
  167. Winter Peak Load (or WPL): p. 62
  168. Zonal Capacity Price: p. 62
  169. Zone or Zonal: p. 62
  170. Zonal Winter Weather Adjustment Factor (ZWWAF): p. 62
  171. “Zonal Winter Weather Adjustment Factor” or “ZWWAF” shall mean the PJM zonal winter weather normalized coincident peak divided by PJM zonal average of 5 coincident peak loads in December through February. p. 62
  172. SCHEDULE 11 DATA SUBMITTALS p. 63
  173. A. To perform the studies required to determine the Forecast Pool Requirement and Daily p. 63
  174. Attachment B p. 66
  175. Definitions – L – M – N p. 68
  176. List of Approved Contractors: p. 69
  177. Load Interest: p. 69
  178. Load Management: p. 70
  179. Load Ratio Share: p. 70
  180. Load Reduction Event: p. 70
  181. “Load Serving Charging Energy” shall mean energy that is purchased from the PJM Interchange Energy Market and stored in an Energy Storage Resource or Open-Loop Hybrid Resource for later resale to end-use load. p. 70
  182. Load Shedding: p. 70
  183. Local Upgrades: p. 70
  184. “Long-lead Project” shall have the same meaning provided in the Operating Agreement. p. 72
  185. Long-Term Firm Point-To-Point Transmission Service: p. 72
  186. Loss Price: p. 72
  187. Attachment K-Appendix, section 2. p. 72
  188. Market Monitoring Unit Advisory Committee or MMU Advisory Committee: p. 73
  189. Market Operations Center: p. 73
  190. Market Participant Energy Injection: p. 74
  191. Market Participant Energy Withdrawal: p. 74
  192. Material Modification: p. 75
  193. Maximum Emergency: p. 75
  194. Maximum Facility Output: p. 75
  195. Maximum Generation Emergency: p. 75
  196. Maximum Generation Emergency Alert: p. 75
  197. Maximum Run Time: p. 76
  198. “Maximum Run Time” shall mean the maximum number of hours a generating unit can run over the course of an Operating Day, as measured by PJM’s State Estimator. p. 76
  199. “Maximum State of Charge” shall mean the maximum State of Charge that should not be exceeded, measured in units of megawatt-hours. p. 76
  200. Maximum Weekly Starts: p. 76
  201. “Maximum Weekly Starts” shall mean the maximum number of times that a generating unit can be started in one week, defined as the 168 hour period starting Monday 0001 hour, under normal operating conditions. p. 76
  202. Merchant A.C. Transmission Facilities: p. 76
  203. Merchant D.C. Transmission Facilities: p. 76
  204. Merchant Network Upgrades: p. 76
  205. Merchant Transmission Facilities: p. 76
  206. Merchant Transmission Provider: p. 77
  207. Metering Equipment: p. 77
  208. Minimum Generation Emergency: p. 78
  209. “Multi-Driver Project” shall have the same meaning provided in the Operating Agreement. p. 79
  210. Native Load Customers: p. 79
  211. Near-Term Transmission Service: p. 79
  212. NERC: p. 79
  213. NERC Interchange Distribution Calculator: p. 80
  214. Network Customer: p. 80
  215. Network Integration Transmission Service: p. 81
  216. Network Load: p. 81
  217. Network Operating Agreement: p. 81
  218. Network Operating Committee: p. 81
  219. Network Resource: p. 81
  220. Network Service User: p. 81
  221. Network Transmission Service: p. 81
  222. Network Upgrades: p. 82
  223. New PJM Zone(s): p. 83
  224. New Service Customers: p. 83
  225. New Service Request: p. 83
  226. New Services Queue: p. 83
  227. No-load Cost: p. 83
  228. Nominal Rated Capability: p. 84
  229. Non-Firm Point-To-Point Transmission Service: p. 84
  230. Non-Firm Sale: p. 85
  231. Non-Firm Transmission Withdrawal Rights: p. 85
  232. Non-Retail Behind The Meter Generation: p. 85
  233. Non-Synchronized Reserve: p. 86
  234. Non-Synchronized Reserve Event: p. 86
  235. “Non-Variable Loads” shall have the meaning specified in Operating Agreement, Schedule 1, section 1.5A.6, and the parallel provisions of Tariff, Attachment K-Appendix, section 1.5A.6. p. 86
  236. Non-Zone Network Load: p. 86
  237. Normal Maximum Generation: p. 86
  238. Normal Minimum Generation: p. 86
  239. III. RESPONSBILITIES OF ELECTRIC DISTRIBUTORS p. 89
  240. II. RESPONSBILITIES OF THE OFFICE OF THE INTERCONNECTION p. 90
  241. ARTICLE 1 – DEFINITIONS p. 92
  242. Agreement: p. 92
  243. “Accredited UCAP” shall mean the quantity of Unforced Capacity, as denominated in Effective UCAP, that an ELCC Resource is capable of providing in a given Delivery Year. p. 92
  244. Accredited UCAP Factor: p. 92
  245. “Accredited UCAP Factor” shall mean, through the 2024/2025 Delivery Year, one minus EFORd, and for 2025/2026 Delivery Year and subsequent Delivery Years, the ratio of the Capacity Resource’s Accredited UCAP to the Capacity Resource’s installed capacity. p. 92
  246. Behind The Meter Generation: p. 93
  247. Black Start Capability: p. 94
  248. Capacity Emergency Transfer Objective (CETO): p. 94
  249. Capacity Emergency Transfer Limit (CETL): p. 94
  250. “Capacity Performance Resource” shall have the same meaning as in Tariff, Attachment DD. p. 96
  251. Capacity Resources: p. 96
  252. Capacity Transfer Right: p. 96
  253. Consolidated Transmission Owners Agreement, PJM Transmission Owners Agreement or Transmission Owners Agreement: p. 97
  254. Control Area: p. 97
  255. Daily Unforced Capacity Obligation: p. 98
  256. Delivery Year: p. 98
  257. Demand Resource (DR): p. 98
  258. Demand Resource Factor or DR Factor: p. 98
  259. Demand Resource Sell Offer Plan: p. 99
  260. Electric Cooperative: p. 101
  261. Electric Distributor: p. 101
  262. Emergency: p. 101
  263. End-Use Customer: p. 101
  264. Energy Efficiency Resource: p. 102
  265. Existing Demand Resource: p. 102
  266. Facilities Study Agreement: p. 103
  267. FERC or Commission: p. 103
  268. Firm Point-To-Point Transmission Service: p. 103
  269. Firm Service Level: p. 103
  270. Firm Transmission Service: p. 104
  271. Fixed Resource Requirement Alternative or FRR Alternative: p. 104
  272. Forecast Pool Requirement: p. 104
  273. FRR Capacity Plan or FRR Plan: p. 104
  274. FRR Entity: p. 104
  275. FRR Service Area: p. 104
  276. Full Requirements Service: p. 105
  277. Generation Capacity Resource: p. 106
  278. Generation Owner: p. 106
  279. Generator Forced Outage: p. 106
  280. Generator Maintenance Outage: p. 107
  281. Generator Planned Outage: p. 107
  282. Good Utility Practice: p. 107
  283. Incremental Auction: p. 108
  284. IOU: p. 108
  285. Load Serving Entity or LSE: p. 109
  286. Locational Reliability Charge: p. 110
  287. Markets and Reliability Committee: p. 110
  288. Maximum Emergency Service Level: p. 110
  289. Member: p. 110
  290. Members Committee: p. 110
  291. NERC: p. 110
  292. Network Transmission Service: p. 111
  293. Nominal PRD Value: p. 111
  294. Nominated Demand Resource Value: p. 111
  295. Non-Retail Behind the Meter Generation: p. 111
  296. Obligation Peak Load: p. 111
  297. Office of the Interconnection: p. 111
  298. Operating Agreement of the PJM Interconnection, L.L.C., Operating Agreement or PJM Operating Agreement: p. 112
  299. Operating Reserve: p. 112
  300. Other Supplier: p. 113
  301. Partial Requirements Service: p. 113
  302. Party: p. 113
  303. Percentage Internal Resources Required: p. 114
  304. PJM: p. 114
  305. PJM Board: p. 114
  306. PJM Manuals: p. 114
  307. PJM Region: p. 114
  308. PJM Region Installed Reserve Margin: p. 114
  309. PJM Tariff, Tariff, O.A.T.T., OATT or PJM Open Access Transmission Tariff: p. 115
  310. Planned Demand Resource: p. 115
  311. Planned External Generation Capacity Resource: p. 115
  312. Planned Generation Capacity Resource: p. 116
  313. Planning Period: p. 117
  314. PRD Curve: p. 117
  315. PRD Provider: p. 117
  316. PRD Reservation Price: p. 117
  317. “PRD Reservation Price” shall mean an RPM Auction clearing price identified in a PRD Plan for Price Responsive Demand load below which the PRD Provider desires not to commit the identified load as Price Responsive Demand. p. 117
  318. PRD Substation: p. 117
  319. Price Responsive Demand: p. 118
  320. Price Responsive Demand Credit: p. 118
  321. “Price Responsive Demand Credit” shall mean a credit, based on committed Price Responsive Demand, as determined under Reliability Assurance Agreement, Schedule 6.1. p. 118
  322. Public Power Entity: p. 118
  323. Qualifying Transmission Upgrades: p. 118
  324. Relevant Electric Retail Regulatory Authority: p. 118
  325. “Relevant Electric Retail Regulatory Authority” or “RERRA” shall have the meaning specified in the PJM Operating Agreement. p. 118
  326. Reliability Principles and Standards: p. 119
  327. Required Approvals: p. 119
  328. Self-Supply: p. 119
  329. State Consumer Advocate: p. 119
  330. State Regulatory Structural Change: p. 119
  331. Steam Class: p. 119
  332. “Steam Class” shall mean an ELCC Class consisting of Unlimited Resources of the steam technology type and the primary fuel is not coal or nuclear. p. 120
  333. Supervisory Control: p. 120
  334. Threshold Quantity: p. 120
  335. Transmission Owner: p. 121
  336. Unforced Capacity: p. 121
  337. Winter Peak Load (or WPL): p. 122
  338. Zonal Capacity Price: p. 122
  339. Zone or Zonal: p. 122
  340. Zonal Winter Weather Adjustment Factor (ZWWAF): p. 122
  341. “Zonal Winter Weather Adjustment Factor” or “ZWWAF” shall mean the PJM zonal winter weather normalized coincident peak divided by PJM zonal average of 5 coincident peak loads in December through February. p. 122
  342. SCHEDULE 11 DATA SUBMITTALS p. 123
  343. A. To perform the studies required to determine the Forecast Pool Requirement and Daily p. 123

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Connecting load and generation · Reliability and curtailment

What the document says

Registry scope · PDF pp. 1–2

Transmittal: what survived the October order

PJM asks for an October 12 effective date for the definition and registry. It strips out the two fields that would have recorded a customer's new capacity and allocated backstop megawatts. The filing does not revive the rejected curtailment service.

the amount of BYONC brought by a particular Large Load and the allocated RBP UCAP MW quantity PDF p. 2
Filed comments: Registry access

Filing record · PDF pp. 2–5

I–III. What PJM submitted and served

PJM submits the same tariff and reliability agreement changes in marked and clean copies. The service section says PJM notified its members and state utility commissions. The conclusion asks for acceptance; it does not establish that FERC accepted this filing.

PJM respectfully requests that the Commission accept this compliance filing PDF p. 4

Registry scope · PDF pp. 6–65

Attachment A: how to read the marked text

The redlines show where PJM placed the surviving definition and reporting rules. Use the clean copy starting on PDF page 66 to read the resulting language; the reproduced definitions surrounding the edits are not all new rules.

all affiliated load facilities within a one-mile radius will be considered a single electrical site PDF p. 49

Registry scope · PDF pp. 66–86

Attachment B: tariff definition

The clean Open Access Transmission Tariff points to the Reliability Assurance Agreement for the definition. Page 109 gives the threshold and the test for grouping affiliated facilities.

“Large Load” shall have the meaning provided in the Reliability Assurance Agreement. PDF p. 68

Registry reporting · PDF pp. 87–90

Attachment DD-4: who keeps the registry

PJM maintains the registry under Schedule 11. Electric distributors coordinate with PJM and supply information they consider appropriate, including applicable retail tariffs and contracts. Section I is reserved.

any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry PDF p. 89
Filed comments: Registry access

Registry scope · PDF pp. 91–122

RAA Article 1: what counts as one site

The threshold is 50 MW of cumulative peak demand at one electrical site, even behind several interconnection points. Affiliated load facilities within a one-mile radius count as one site under the stated configurations.

a cumulative peak load of 50 megawatts or greater at a single electrical site behind one or more points of interconnection PDF p. 109

Registry reporting · PDF pp. 123–124

Schedule 11.B.1(a): what must be reported

Entities bound by the Operating Agreement must submit, or arrange submission of, data about each large load they serve. Fields include location, dates for each load increment, peak MW and ramp schedule, telemetry, and backup generation with fuel and permit limits.

Backup generation (MW), including fuel type and relevant permitting limitations PDF p. 124

Registry access · PDF p. 124

Schedule 11.B.1(b)–(d): validation and access

PJM may check the data with the distributor, transmission owner or customer. The text names regulators, system participants and the market monitor as possible recipients under safeguards. It does not explicitly list state consumer advocate offices.

Information maintained in the Large Load registry may be available to Authorized Commissions PDF p. 124
Filed comments: Registry access

Registry access · PDF p. 124

Schedule 11.B.1(e): what the public can see

PJM would post aggregate data by distributor zone or area where possible. Confidentiality protections still apply; this is not a public list of individual sites and contracts.

aggregated by Electric Distributor zone/area, where possible PDF p. 124

Registry reporting · PDF pp. 124–125

Schedule 11.B.2: deadlines and changes of supplier

For loads in service before June 1, 2027, the serving or contracted entity must report by March 1, 2027. For loads entering service on or after June 1, it must report before startup. It must promptly report later changes, including transfer of the right to serve the load.

before the in-service date of the Large Load PDF p. 125