EL26-67-000 · 2026-08-13 · FERC

Errata correcting the caption and footnote 13 of 195 FERC ¶ 61,211 (Allegheny Electric Cooperative, Wabash Valley Power Association)

FERC's Secretary corrects the caption and footnote 13 of the E-7 show cause order so Allegheny Electric Cooperative and Wabash Valley Power Association are treated as non-public-utility owners that need not respond.

Corrects which Transmission Owners must respond to the E-7 show cause order in EL26-67, leaving the directive itself unchanged.

E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7)

Key points

  1. The errata removes Allegheny Electric Cooperative and Wabash Valley Power Association from the caption of the EL26-67 order.
    The caption in the order inadvertently included “Allegheny Electric Cooperative, Inc.” and “Wabash Valley Power Association, Inc.” Source text
  2. FERC keeps authority to review non-public-utility formula rates through PJM, which must answer for their Tariff provisions.
    PJM must respond to this order regarding the non-public utilities’ PJM Tariff provisions on file with the Commission. Source text

Read topic-matched comments in EL26-67

What the document says

Unpaginated filing

Errata moves Allegheny Electric and Wabash Valley from the PJM caption to footnote 13.

The caption in the order inadvertently included “Allegheny Electric Cooperative, Inc.” and “Wabash Valley Power Association, Inc.” and footnote 13 inadvertently omitted Source text

Unpaginated filing

Non-public-utility owners need not respond, but FERC can still review their formula rates.

the Commission retains the authority to review each entity’s formula rates as a component of PJM’s Tariff in an order to show cause directed towards PJM Source text

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Document text

document text

Accordingly, the Commission has not included Allegheny Electric Cooperative, Inc.; AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; East Kentucky Power Cooperative, Inc.; Southern Maryland Electric Cooperative, Inc.;…