Answer of Allegheny Electric Cooperative, Inc. to the Show Cause Order Issued in Connection with the Treatment of Co-Located Load within PJM…
Text extracted from the eLibrary original (SHA-256 c2516e9e4d01bc42…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Specifically, the Show Cause Order directs PJM and the TOs to either (1) show cause that the PJM Tariff remains just and reasonable and not unduly discriminatory or preferential without rates, terms, and conditions of service specific to Co-Located Load or (2) explain what changes to the Tariff…Read this passage Filed comments: Connecting load and generation
I. PRELIMINARY STATEMENT
printed heading
PRELIMINARY STATEMENT This Answer is submitted pursuant to Rule 213 of the Rules of Practice and Procedure of the Commission and the Commission’s February 20, 2025 Show Cause Order, which established March 24, 2025 as the date by which PJM and the TOs are required to submit answers in this Section…Read this passage
II. DESCRIPTION OF ALLEGHENY
printed heading
DESCRIPTION OF ALLEGHENY Allegheny is a non-profit electric generation and transmission cooperative corporation (“G&T Cooperative”), incorporated under the Electric Cooperative Law of the Commonwealth of Pennsylvania, and it is the exclusive wholesale supplier of its 14 distribution cooperative…Read this passage
III. BACKGROUND
printed heading · Topic match: Connecting load and generation
Specifically, the Exelon Company subsidiaries proposed to revise their transmission rate schedules to clarify that Co-Located Load must be designated as either Network Load or receive Point-to-Point Transmission Service and thus be allocated costs of the transmission grid.Read this passage Filed comments: Connecting load and generation
IV. ANSWER
printed heading · Topic match: Connecting load and generation
This concern was highlighted by the December 9, 2024 warning issued by PJM Board Chair Mark Takahashi that a capacity shortage may affect the PJM system as early as the 2026/2027 Delivery Year.11 Additionally, the lack of generation capacity has a direct impact on transmission prices as well…Read this passage Filed comments: Connecting load and generation
V. RESERVATION OF RIGHTS
printed heading
RESERVATION OF RIGHTS Allegheny reserves the right to posit and address any issues that it or others may identify or raise herein that are developed in any other phase of this proceeding.Read this passage
VI. CONCLUSION
printed heading · Topic match: Connecting load and generation
Allegheny supports the Commission’s efforts to provide certainty on an expedited basis to the questions posed by the growth of Co-Located Load configurations in the PJM region.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Adrian Counsel for Allegheny Electric Cooperative, Inc.Read this passage