Comments of the Union of Concerned Scientists in support of the filings dated 03/24/2025 of PJM Interconnection, L.L.C. et al
Text extracted from the eLibrary original (SHA-256 756e71ebc5b9e720…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. INTRODUCTION
printed heading · Topic match: Connecting load and generation
INTRODUCTION These comments support PJM’s conclusion that “all co-located load be served from the PJM Transmission System as PJM Network Load with applicable firm transmission service.”2 UCS also supports the Indicated PJM Transmission Owners view that “consider all the arrangements being…Read this passage Filed comments: Connecting load and generation
II. BACKGROUND
printed heading · Topic match: Connecting load and generation
NOVEC states that the Guidance Document provides that co-located load “benefits from the use of the Transmission System and Ancillary Services.” Exelon argues that a nuclear facility serving co-located load must remain interconnected to the grid.Read this passage Filed comments: Connecting load and generation
III. COMMENTS AND REPLIES TO ORDER
printed heading
COMMENTS AND REPLIES TO ORDER Throughout this inquiry and the preceding dockets, parties make arguments that begin with a presumption regarding the use of the transmission system by the co-located loads.Read this passage
A. Transmission Service reliance
printed heading · Topic match: Connecting load and generation
July 2024), which provides this illustration of connection between transmission, generation and co-located load. power to the co-located load.Read this passage Filed comments: Connecting load and generation
B. Ancillary or other wholesale services reliance
printed heading · Topic match: Connecting load and generation
In the technical conference proceeding, NERC noted the impact of data center energy consumption changing rapidly affecting “thermal overloads, voltage issues, or stability issues.”40 Additional narrative from Dominion Energy41 describes the range of services maintaining reliability, serving…Read this passage Filed comments: Connecting load and generation
C. Transmission Service Requirements
printed heading · Topic match: Connecting load and generation
Interconnection Customer shall, at its expense, design, procure, construct, own and install the ICIF.” factor affecting PJM’s transmission capacity for errors in short-term load forecasting.Read this passage Filed comments: Connecting load and generation
IV. Conclusion
printed heading
“In order for a co-location arrangement (i.e., the generator plus data center) to obtain these services, the grid itself must exist.Read this passage