Comments of Pennsylvania Public Utility Commission
Text extracted from the eLibrary original (SHA-256 5e5f3c82dfe9aa2b…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 COMMONWEALTH OF PENNSYLVANIA PENNSYLVANIA PUBLIC UTILITY COMMISSION COMMONWEALTH KEYSTONE BUILDING 400 NORTH STREET, THIRD FLOOR HARRISBURG, PENNSYLVANIA 17120 April 22, 2025 Via Electronic Filing Honorable Debbie-Anne A.Read this passage
I. Jurisdiction
printed heading · Topic match: Connecting load and generation
Even still, if an entity is confused about whether it is offering public utility service, it can ask the PA PUC for a declaratory order.8 To date, PA PUC has not made any such determination regarding co-located load arrangements, and the determination would be adjudicated under the unique facts of…Read this passage Filed comments: Connecting load and generation
II. Services received in co-located load arrangements.
printed heading · Topic match: Connecting load and generation
Despite the private arrangement of a co-located load and an associated generator not being subject to Pennsylvania Public Utility Commission or FERC jurisdiction9 some services from the grid benefit the co-located load.Read this passage Filed comments: Connecting load and generation
III. PJM’S Tarriff – Wholesale Grid Services
printed heading · Topic match: Connecting load and generation
PJM’s Tariff must be amended to include provisions that ensure that participants in a co-located load arrangement are held financially responsible commensurate with the extent to which they receive benefits from the transmission grid according to the cost-causation and beneficiary pays principles.Read this passage Filed comments: Connecting load and generation
IV. Reliability and Resource Adequacy
printed heading · Topic match: Connecting load and generation
This is particularly true of co-located load arrangements at baseload generation facilities. 7 Accordingly, PA PUC agrees that PJM’s Tariff must be revised to require that PJM conduct long-term scenario analyses on the potential cumulative reliability and cost impacts of behind-the-generator-meter…Read this passage Filed comments: Connecting load and generation
V. Cost Allocation
printed heading · Topic match: Cost allocation
Cost Allocation While the PA PUC appreciates PJM’s thorough breakdown of large load transmission interconnection options, we would observe that PJM assumes in all options except 4 and 5 that transmission upgrades would be the responsibility of either the RTEP 14 PJM Interconnection, L.L.C., Docket…Read this passage Filed comments: Cost allocation
VI. Speed of Interconnection is Driving the Demand for Co-location.
printed heading · Topic match: Connecting load and generation
Although improvements must be made to the transparency and cost sharing in the co-location process, we must also endeavor to increase the speed of traditional grid interconnection.Read this passage Filed comments: Connecting load and generation
VII. Conclusion
printed heading · Topic match: Connecting load and generation
Improvements in transparency must be made to the co-location process.Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Barnes Deputy Chief Counsel Pennsylvania Public Utility Commission 400 North St., 3rd Floor Harrisburg, PA 17120 Tel: (717) 787-5000 Dated: April 22, 2025Read this passage