EL25-49-000 · 2025-04-23 · ENGIE North America Inc.

Comments of ENGIE North America Inc. in response to PJM Interconnection, L.L.C.'s et al. 03/24/2025 filing

Text extracted from the eLibrary original (SHA-256 6a4c24d8d8e8d10f…). Download the original from the official source.

Contents · 9 sections
  1. I. COMMUNICATIONS p. 3
  2. II. INTRODUCTION p. 3
  3. III. COMMENTS p. 4
  4. A. PJM’s filing appropriately acknowledges the acute need for new co-located large p. 4
  5. B. The Commission should provide clear guidance on co-location arrangements. p. 5
  6. C. The Commission must safeguard flexibility in the PJM tariff. p. 5
  7. D. The Commission must ensure that PJM’s participation options capture and p. 6
  8. E. The Commission should address several outstanding issues to ensure p. 8
  9. IV. CONCLUSION p. 9

Read topic-matched comments in EL25-49

Topics in the text: Cost allocation · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. COMMUNICATIONS

printed heading

COMMUNICATIONS All correspondence and communication concerning this filing should be directed to: Sarah Bresolin Silver Vice President, Government and Regulatory Affairs ENGIE North America Inc. 1360 Post Oak Blvd., Suite 400 Houston, TX 77056 sarah.bresolin@engie.com
Read this passage

II. INTRODUCTION

printed heading

INTRODUCTION ENGIE North America is a subsidiary of ENGIE SA, based in Paris, France.
Read this passage

III. COMMENTS

printed heading

III.
Read this passage

A. PJM’s filing appropriately acknowledges the acute need for new co-located large

printed heading

To address the significant increase in requests to interconnect large loads co-located with generation, the Commission, PJM and stakeholders must explore new and innovative market solutions.
Read this passage

B. The Commission should provide clear guidance on co-location arrangements.

printed heading

The Commission should provide clear guidance on co-location arrangements.
Read this passage

C. The Commission must safeguard flexibility in the PJM tariff.

printed heading

The Commission must safeguard flexibility in the PJM tariff.
Read this passage

D. The Commission must ensure that PJM’s participation options capture and

printed heading · Topic match: Cost allocation

The Commission must ensure that PJM’s participation options capture and recognize the system and ratepayer benefits of co-location.
Read this passage Filed comments: Cost allocation

E. The Commission should address several outstanding issues to ensure

printed heading · Topic match: Connecting load and generation

ENGIE also notes the complexity of this type of study including potential mismatching of the time when the load and the generation come online or the lifetime of the load versus the lifetime of the generation or the variances of operational characteristics of co-located load and generation.
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading

CONCLUSION ENGIE commends the Commission for its continued interest and inquiry into co-located arrangements.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Tamarindo, Costa Rica, this 22 day of April 2025. /s/ Sarah Bresolin Silver Sarah Bresolin Silver Vice President, Government and Regulatory ENGIE North America Inc. 1360 Post Oak Blvd.
Read this passage